1.1 Site clearing to a depth not greater than 200mm m2 75,000.00 15 1,125,000.00
1.2 Bulk excavation to a depth not exceeding 1500mm for levelling of the site
m3 11,250.00 107 1,203,750.00
1.3 Trench excavation around masonary foundation from reduced level & place
excavated soil not distrurb site work activities.
m3 880.00 107.00 94,160.00
1.4
a. Fill around the column footing and other trench excavated parts with
excavated back fill material from the site and well ram in layers of not
exceeding 200mm thick. m3 420.00 135.00 56,700.00
II.Concrete Work
2.1 100mm thick lean concrete in class C-10 With minimum cement content of
150kg/m3
2.3
Reinforced concrete class C-25 with minimum portland Cement
content of 360kg/m3 well spread leveled. And filled into formwork
and vibrated around steel reinforcement
a) in grade beam m3 66.00 3,100.00 204,600.00
2.4
Steel Reinforcement according to structural drawing, price includes cutting,
bending, placing in position and tying with wires.
Superstructure
I.Concrete Work
1.1
Reinforced concrete class C-25 with minimum portland Cement
SUMMARY
PROJECT:
LOCATION:
GELAN
ETHIOPIA
Jun-2016
TITIES
Gelan Steel Factory Project Fence Work Material Schedule