Gelan Steel Factory Project Fence Work

Item Description Unit Qty Rate Amount


Sub Structure
I. Excavation and Earthwork

1.1 Site clearing to a depth not greater than 200mm m2 75,000.00 15 1,125,000.00

1.2 Bulk excavation to a depth not exceeding 1500mm for levelling of the site
m3 11,250.00 107 1,203,750.00

1.3 Trench excavation around masonary foundation from reduced level & place
excavated soil not distrurb site work activities.
m3 880.00 107.00 94,160.00

1.4
a. Fill around the column footing and other trench excavated parts with
excavated back fill material from the site and well ram in layers of not
exceeding 200mm thick. m3 420.00 135.00 56,700.00

b. if materials are imported from selected site for backfilling. m3 - 285.00

1.5 Cart away surplus excavated material to an appropriate


selected site m3 880.00 80.00 70,400.00

II.Concrete Work
2.1 100mm thick lean concrete in class C-10 With minimum cement content of
150kg/m3

a) Under Masonary and grade beam m2 660.00 250.00 165,000.00


2.2
Fix zigba sawn or metal form work for all columns and grade beams. All
materials are provided by the client m2 795.00 310.00 246,450.00

2.3
Reinforced concrete class C-25 with minimum portland Cement
content of 360kg/m3 well spread leveled. And filled into formwork
and vibrated around steel reinforcement
a) in grade beam m3 66.00 3,100.00 204,600.00
2.4
Steel Reinforcement according to structural drawing, price includes cutting,
bending, placing in position and tying with wires.

dia 8mm Kg 2389.75 32.00 76,472.00


dia 12mm Kg 8311.60 32.00 265,971.20

A. Total carried to Summary 3,508,503.20

Superstructure
I.Concrete Work
1.1
Reinforced concrete class C-25 with minimum portland Cement

content of 360kg/m3 well spread leveled. filled into formwork


and vibrated around steel reinforcement

a) Elevation Column m3 49.50 3,100.00 153,450.00


b) 15cm High Coping ml 1100.00 140.00 154,000.00
1.2 Supply and fix zigba sawn form work m2 363.00 310.00 112,530.00
1.3
Steel Reinforcement according to structural drawing, price includes cutting,
bending, placing in position and tying with wires.

dia 8mm Kg 1194.90 32.00 38,236.80


dia 12mm Kg 3907.50 32.00 125,040.00

II. Block Work


2.1 200mm thick block work both sides left for plastering m2 2035.00 380.00 773,300.00
III. Plastering Work
3.1 Two side plastering of fence wall with 1:3 mortar m2 0.00 0.00

B. Total carried to Summary 1,356,556.80

Total Carried To Summary (A+B) 4,865,060.00

Note: Price shall not include Value added Tax


PROJECT: Gelan Steel Factory Fence Work Project
LOCATION: Gelan

SUMMARY

1.SUBSTRUCTURE WORKS……………. Birr 3,508,503.20


2.SUPERSTRUCTURE WORKS………… Birr 1,356,556.80

TOTAL …………………… Birr 4,865,060.00


SPECIFICATION AND BILL OF QUANTITIES
(WITH ENGINEERS' ESTIMATE)

PROJECT:

Gelan Steel Factory Fence Work

LOCATION:
GELAN
ETHIOPIA

Jun-2016
TITIES
Gelan Steel Factory Project Fence Work Material Schedule

Item Description Unit Qty Rate Amount


Materials List

1.0 Cement Qtl 682.00 0.00


2.0 Sand
m3 112.00 0.00
3.0 Aggregate
m3 156.00 0.00

4.0 Reinforcement Bar

dia 8mm Kg 3764.00 0.00

dia 12mm Kg 12830.06 0.00


5.0
Trachaitic stone for Masonary Work m3 0
6.0
Hollow Section Block for fence masonary wall Pcs 25437.00 0.00

Total Carried To Summary 0.00