Contract Quantity

Contract Pcs
Item No. Description Unit Contract amount
Qty Rate/UoM
A. Substructure
1 Excavation and Earth work
1.01 Trench excavation in ordinary soil to a depth not exceding 100cm from m3
reduce ground level. 2.48 400.00 992.00
1.02 25cm thick hardcore well consolidated and blind with crushed stone m2 7.04 300.00 2,112.00
TOTAL CARRIED TO SUMMARY 3,104.00
2. Masonary Work
40cm thick basaltic equivalent stone masonary foundation well bedded and
2.01 jointed in cement mortar of 1:3 mix ratio below NG level to depth not m3
exceeding 150cm. 7.44 400.00 2,976.00
2.02 Ditto but well dressed stone masonary to an average height of 100cm above m3
RGL. Price shall include pointing and all necessary finishing works. 4.96 400.00 1,984.00
TOTAL CARRIED TO SUMMARY 4,960.00
3.CONCRETE WORKS
3.01 5 cm lean concrete with minimum cement content of 150 kg/m3
a under masonary foundation m2 5.00 250.00 1,250.00
Reinforced concrete class C-25,360kg of cement/m3 of concrete filled into
3.02 formwork and vibrated around reinforcement bars. Formwork and
reinforcement bars are to be measured
a In 10cm thick RC ground slab, Concrete quality C-20,320kg of cement/m3 of m2
concrete evenly spread 12.00 250.00 3,000.00
Construct 25*30 (w*d) cm rectangular semi dressed stone rain water ditch of
masonry work arround the building bedded and jointed in cement mortar 1:4.
d The ditch work includes plastering the internal faces of the ditch with smooth
finish, hard core on the water way of the ditch and conctere above the hard core
and on the top of the masonry work of the ditch. Ml 26 150 3900.00
TOTAL CARRIED TO SUMMARY 8,150.00
B. SUPER STRUCTURE
1. ROOFING WORKS
Fix G-30 corrugated Iron sheet for roof cover and Roof Ridge. Roof cover and
1.01 Roof Ridge measured in horizontal projection. Purlins measured separately m2
and roof measured in horizontal projection. 20.00 120.00 2,400.00
TOTAL CARRIED TO SUMMARY 2,400.00
2. CARPENTARY & JOINERY WORKS
Fix Diameter 8-10 mm eucl. Upper, lower, Verical and Diagonal truss members
for roofing. All structural members shall be well seasoned and free of harmful
2.01 defects. Each truss shall be painted anti- termite solution and firmly fixed to
R.C beams with Dia 6mm plain bars. Price shall include fixing Purlin for roof
work. m2 20.00 150.00 3,000.00
Supply and fix G-32 corrugated Iron sheet wall cover above the hard mesh
2.02 cover. Price shall include fixing Purlin for roof work.Price shall include fixing
Purlin for wall work. m2 40.00 120.00 4,800.00
Hard Mesh wire for insect netting and Ventilation. Price shall include cutting
2.03
and mounting in position with 80cm height. Ml 12.00 150.00 1,800.00
TOTAL CARRIED TO SUMMARY 9,600.00
3. Wood works
Supply and fix Tid or Equavalent wooden frame lockable doors made of G-32
G.I. sheets. All supply and fix wooden frame doors shall be fabricated from
3
locally tree. Unit cost includes fixing hinges,door locks of approve quality and
grill. /material quality approved by the Supervisor/
3.01 Doors
D=0.9X2.95m Pcs 1.00 200.00 200.00
3.02 Window
W=1.50*1.50m Pcs 2.00 200.00 400.00
TOTAL CARRIED TO SUMMARY 600.00
4. Finishing

Finishing work shall include all surface pre-cleaning, preparation, application


4.01
of the finish, polishing & cleaning at the end of the finishing work.

a) cement screed for floor finish m2 12.00 300 3,600.00


TOTAL CARRIED TO SUMMARY 3,600.00
5. Painting
5.01 Apply three coats of approved quality Metallic Anti-Rust plastic paint price
shall include pre-cleaning
a To internal/extenal wall surface m2 42.00 50.00 2,100.00
TOTAL CARRIED TO SUMMARY 2,100.00