You are on page 1of 12

Hit Construction Zimbabwe

no 93 Harare Drive Malbrough East


0242787912/0719985697
info@hitconstruction.co.zw
www.hitconstruction.co.zw

CIVIL & STRUCTURES

PROJECT -MAIN HOUSE CONSTRUCTION CLIENT - D TYPE MODEL


PROJECT LOCATION -ARLINGTON ESTATE
DATE PREPARED - 15 MARCH 2023
0 0

Item Description Unit Quantity Rate Amount

BILL NO. 1

PRELIMINERIES AND GENERALS

A. PRELIMINERIES ITEMS(fixed) 850.00

Cost for operation costs including provision of equipment and tools on site
scaffolding, plate compactors, concrete pokers, safety requirements as required,
provision of all necessary secondary equipment i.e dumpy levels to ensure works
are constructed as provided for by the building by laws of Zimbabwe

Total Carried Forward 850.00


Item Description Unit Quantity Rates Amount
BILL NO 2

FOUNDATIONS (PROVISIONAL)

SITE PREPARATION

Site Clearance

A Allow for clearing site including all rubbish, debris and boulders,
cutting down and removing all grass, shrubs and bushes and
trees having a trunk girth e not exceeding 500mm and
grubbing up and removing all roots and filling in with suitable
materials and well consolidating m2 263 0.90 236.70

B Ground floor setting out item 1 100.00 100.00

EXCAVATIONS
C Allow for keeping the excavation free from storm and surface
water by bailing or pumping through out the duration of the contract item R.O 145.00

Excavate in pickable material commencing 200mm below natural


ground level for :-

E Surface trenches not exceeding 1000mm deep m3 64 11.00 704.00

F Extra over all excavations in pickable material for hard pickable m3 R.O 72.56
material including any extra cost of disposal

G Ditto in hard rock ditto (Provisional) m3 R.O 102.00

Planking and Strutting

H Maintain and support sides of all excavations and make good m2 R.O 62.36

Disposal, formation etc.

I Re-dig excavated material fill in around foundation in layers not


exceeding 150mm thick and compact to 98% HCE Density m3 42 9.00 378.00

K Approved inert granular filling levelled under solid floors in one layer
average 150mm thick compacted to 98 % H.C.E m3 17 11.50 200.91

Total Carried Forward 1,619.61


Item Description Unit Quantity Rates Amount

Total brought Forward 1,619.61

Antproofing
L Approved white ant treatment executed by approved specialist
firm on top filling ,the work supplied with a written fifteen
years guarantee against termite infestation m2 117 0.20 23.40

CONCRETING
Concrete (grade 30-20 mm stone) in:

P Strip footing m3 15 30.00 450.00

Q Oversite concrete m3 12 30.00 360.00

Formwork to:

R shutters no. 0 21.59 -

Sundries
S Strike off and cure level top of ground floor slab m2 117 0.10 11.70

Fabric reinforcement

Welded fabric reinforcement of approved manufacture including all


cutting, tying, in position with necessary temporary supports and
minimum 300 mm laps both ways (measured net)

U Metric Mesh Ref. S193 (with a mass of 1.93 kg / square metre)


reinforcement layed to ground floor slab m2 117 0.20 23.40

BRICKWORK (Foundations)
Bricks to foundations shall be load bearing
Foundation depth to be verified by engineer

Load bearing bricks in( 1:4) cement mortar


as described

V One brick wall in Stretcher bond m2 81 13.00 1,056.51

V half brick wall in Stretcher bond m2 17 11.00 187.00

250 micron black plastic sheeting laid with 150mm wide joints on sand and
sealed at all joints and including all cutting and waste

X Under concrete surface beds m2 117 0.20 23.40

Foundations(Provisional) Total Carried to Summary 3,755.02


Item Description Unit Quantity Rates Amount

BILL NO 3 : BRICKWORK

GROUND FLOOR BRICKWORK (SUPERSTRUCTURE)

Brickwork in approved common bricks bedded in


cement mortar (1:4) laid in stretcher bond in:

A One brick wall m2 177 13.00 2,301.00

B Half brick wall m2 37 11.00 407.00

C E.O for facework m2 0 9.00 -

VENTILATION

D Form and leave opening in one brick wall for ventilator


230 x 150mm and bild in air brick pair 24 0.50 12.00

E Set in position and build in steel door frame not exceeding 5


square metres in half brick walls no. 6 10.00 60.00

F Set in position and build in steel Roller shutter doors exceeding 5


square metres in one brick walls no. 0 0.00 -

G Set in position and build in steel window frames


not exceeding 5 square metres to one brick wall no. 0 16.25 -

CONCRETE FORMWORK AND REINFORCEMENT

CONCRETING
Concrete (grade 30-20 mm stone) in:

J Eaves beam m3 3 25.00 75.00

K lintels m3 2 25.00 50.00

Formwork to:

N Eaves beam m2 35 7.50 262.50

O lintels m2 4 7.50 30.00

reinforcement steel
S eaves beams and lintels kgs 600 0.25 150.00

Total Carried to summary gound floor brickwork 3,347.50


MAIN HOUSE LABOUR SUMMARY
SUMMARY

ITEM DESCRIPTION PAGE AMOUNT

1 PRELIMINERIES AND GENERALS $ 850.00

2 FOUNDATIONS (PROVISIONAL) $ 3,755.02

3 SUPERSTRUCTURE - BRICKWORK AND BEAMS $ 3,347.50

SUBTOTAL $ 7,952.52

ADD VALUE ADDED TAX -

TOTAL $ 7,952.52
MAIN HOUSE LABOUR SUMMARY
SUMMARY

ITEM DESCRIPTION PAGE AMOUNT

1 PRELIMINERIES AND GENERALS $ 850.00

2 FOUNDATIONS (PROVISIONAL) $ 3,755.02

3 CONCRETE,FORMWORK AND REINFORCEMENT #REF!

4 BRICKWORK - GROUND FLOOR $ 3,347.50

5 BRICKWORK - FIRST FLOOR #REF!

6 TIMBER ROOF STRUCTURE AND ROOF COVERS #REF!

7 JOINERY AND IRON MONGERY #REF!

8 PLASTERING AND WALL LININGS #REF!

9 PAVINGS, FLOOR COVERINGS AND TILING #REF!

10 PLUMBING (PROVISIONAL) #REF!

11 GLAZING #REF!

12 PAINTING #REF!

13 SPECIALIST WORKS #REF!

SUBTOTAL #REF!

ADD VALUE ADDED TAX #REF!

TOTAL #REF!
Resource Steel and Construction

Item Description Unit Quantity Rates Amount


BILL NO 2

FOUNDATIONS (PROVISIONAL)

SITE PREPARATION

Site Clearance

A Allow for clearing line including all rubbish, debris and boulders,
cutting down and removing all grass, shrubs and bushes and
trees having a trunk girth e not exceeding 500mm and
grubbing up and removing all roots and filling in with suitable
materials and well consolidating m 273 4.29 1,171.17

B Setting out item 1 410.00 410.00

EXCAVATIONS
C Allow for keeping the excavation free from storm and surface
water by bailing or pumping through out the duration of the contract item R.O 145.00

Excavate in pickable material commencing 200mm below natural


ground level for :-

3
D Surface trenches not exceeding 1000mm deep m 194 23.49 4,557.06

3
E Extra over all excavations in pickable material for hard pickable m R.O 72.56
material including any extra cost of disposal

3
F Ditto in hard rock ditto (Provisional) m R.O 102.00

Planking and Strutting

2
G Maintain and support sides of all excavations and make good m R.O 62.36

Disposal, formation etc.

H Re-dig excavated material fill in around foundation in layers not


3
exceeding 150mm thick and compact to 98% HCE Density m 100 21.00 2,100.00

Antproofing
I Approved white ant treatment executed by approved specialist
firm on top filling ,the work supplied with a written fifteen
2
years guarantee against termite infestation m 188 1.20 225.60

Total Carried Forward 8,463.83


Resource Steel and Construction

Item Description Unit Quantity Rates Amount

Total brought Forward 8,463.83

CONCRETING
Concrete (grade 25-20 mm stone) in:

3
J Strip footing m 42 464.85 19,523.70

BRICKWORK
Bricks to boundary wall shall be load bearing

Load bearing bricks in( 1:3) cement mortar


as described

2
K One brick wall in Stretcher bond(Wall height 3800mm) m 885 109.04 96,500.40

L Brick column (Size: 460 x 460 x 3800mm) m³ 50 378.76 18,938.00

Sundries

Welded wire brickwork reinforcement suitable for and building into


walls lapped full width at angles, passing and intersections after every
third course on:

M Ref.C2 in One brick wall m 3650 0.78 2,847.00

N Concrete coping (Size 460 x 460) No. 62 48.50 3,007.00

O Concrete coping (Size 460 x 230) No. 455 24.50 11,147.50

2
P Damp proofing under coping m 92 11.20 1,030.40

FINISHES

2
Q Woodfloat plaster Finish to walls Walls and reveals m 2069 13.78 28,510.82

2
R Paint to Wood float plastered walls m 2069 10.71 22,158.99

METAL WORK

S Metal Slidding door complete with accessories No. 2 16520.00 33,040.00

Total Carried to Summary 245,167.64


Resource Steel and Construction

ITEM DESCRIPTION AMOUNT

1 PRELIMINARIES AND GENERALS 19,613.41

2 MESURED WORKS 245,167.64

SUBTOTAL 264,781.05

ADD VALUE ADDED TAX 15% 39,717.16

TOTAL CARRIED TO FORM OF TENDER 304,498.21


Resource Steel and Construction

PROPOSED SEPTIC TANK AND SOAK AWAY AT ZVIMBA RDC HEAD OFFICES

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

SEPTIC TANK

A Bulk excavations in pickable material to a depth exceeding 2 metres m3 49 18.29 896.21


but not exceeding 4 metres

B Grade 25Mpa reinforced concrete to tank base m3 4 464.85 1,859.40

C S193 Mesh wire m2 21 19.83 416.43

D One brickwall in common bricks m2 43 34.20 1,470.60

E Ditto half brickwall m2 8 21.43 171.44

Backfilling to sides of tank with selected excavated material and


F compact m3 10 9.26 92.60

G Cart away excavated material m3 35 17.96 628.60

20mm Cement sand plaster to walls mixed with impermo as per


H
manufacturer's instructions m2 44 9.08 399.52

I Formwork to roof slab m2 22 61.23 1,347.06

J Grade 25Mpa reinforced concrete to roof slab m3 3 267.00 801.00

K Strike off and cure m3 22 0.98 21.56

L Reinforcement bars (all sizes) Kg 360 2.98 1,072.80

600 x 500mm Heavy duty cast iron manhole cover complete with
M frame placed into position no 2 93.00 186.00

Allow to supply and fix 160mm PVC pipes and accesories as per
N detail item 1 1,200.00 1,200.00

TOTAL CARRIED TO SUMMARY PAGE 10,563.22

Page 10 of 12
Resource Steel and Construction

SOAK AWAY (PROVISIONAL)

Bulk excavations in pickable material to a depth exceeding 2 metres


A m3 48 10.20 489.60
but not exceeding 4 metres

D Fill pit with clean granular rockfill m3 41 32.85 1,346.85

Cover stones with metal sheets from used drums or galvanised iron
E sheet covers m2 22 6.23 137.06

E 250micron black polythene sheet m2 22 4.13 90.86

F Backfill with loose material m3 8 9.26 74.08

G Cart away excavated material to a dump site m3 40 17.96 718.40

TOTAL CARRIED TO SUMMARY PAGE 2,856.85

Page 11 of 12
Resource Steel and Construction

SUMMARY PAGE

AMOUNT (US$)

10,563.22
1 SEPTIC TANK

2 SOAK AWAY 2,856.85

SUBTOTAL 1 13,420.07

ADD PRELIMINARY AND GENERALS


(SUPERVISION,TRANSPORT, TOOLS,FOOD, etc) 2,200.00

SUBTOTAL 2 15,620.07

Add 15% V.A.T 15% 2,343.01

TOTAL AMOUNT 17,963.08

Page 12 of 12