Professional Documents
Culture Documents
cu.m. m.t
Procurement Log
List of items needed within seven (7) days
GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s
Environment
Environmental Impact Type of Control Assigned Person/s
Form No. F-CON-001 Rev. No. 2 Issued 11/17/2020 Attach additional sheets if necessary
Distribution Batching, Warehouse, Equipment, HRAD, MTQC, File
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
21-Nov-20
For the Period: November 23 - 28, 2020 Page 1
Contract Details
Owner Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
100(1) Clearing and Grubbing Sta. 05+000 - Sta. 06+000 FE Fajardo & FE
Individual Removal of Trees Sta. 01+380 - Sta. 03+080 Estillore
cu.m. m.t
Procurement Log
List of items needed within seven (7) days
GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s
Environment
Environmental Impact Type of Control Assigned Person/s
Form No. F-CON-001 Rev. No. 2 Issued 11/17/2020 Attach additional sheets if necessary
Distribution Batching, Warehouse, Equipment, HRAD, MTQC, File
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
03-Dec-20
For the Period: December 04 - 17, 2020 Page 1
Contract Details
Owner MPCala Holdings Inc. Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
18+700.00 18+900.00 200.00 m
Stake-Out of Limits Survey Team
19+700.00 20+900.00 1,200.00 m
05+600.00 06+400.00 -
Checking of Lay Out
13+000.00 13+620.00 -
GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
03-Dec-20
For the Period: December 04 - 17, 2020 Page 1
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s
100(1) Clearing and Grubbing Engineer's Certificate Pandemic Face Masks
Grading Goggles
104(1)a
Embankment from Roadway Plasticity NOTE: NO COMPANY NURSE
Excavation Compaction Environment
CBR Environmental Impact Type of Control Assigned Person/s
N/A
Form No. F-CON-001 Rev. No. 2 Issued 11/17/2020 Attach additional sheets if necessary
Distribution Client, Batching, Warehouse, Equipment, HRAD, MTQC, HSE & Engineering HO, File
Field Engineer Field Engineer Field Engineer Field Engineer Field Engineer
ANTONIO P. AGUILAR
Project Manager
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
10-Dec-20
For the Period: December 11 - 23, 2020 Page 1
Contract Details
Owner MPCala Holdings Inc. Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
Survey Team with: 0.00 m
GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s
100(1) Clearing and Grubbing Engineer's Certificate Pandemic Face Masks
Grading Goggles
104(1)a
Embankment from Roadway Plasticity NOTE: NO COMPANY NURSE
Excavation Compaction Environment
CBR Environmental Impact Type of Control Assigned Person/s
N/A
Form No. F-CON-001 Rev. No. 2 Issued 11/17/2020 Attach additional sheets if necessary
Distribution Client, Batching, Warehouse, Equipment, HRAD, MTQC, HSE & Engineering HO, File
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
17-Dec-20
For the Period: December 18 - 23, 2020 Page 1
Contract Details
Owner MPCala Holdings Inc. Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
Lay Out and Stake Out for;
GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s
100(1) Clearing and Grubbing Engineer's Certificate Pandemic Face Masks
Goggles
NOTE: NO COMPANY NURSE
Environment
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
17-Dec-20
For the Period: December 18 - 23, 2020 Page 1
Environmental Impact Type of Control Assigned Person/s
N/A