You are on page 1of 7

PROJECT

WEEKLY CONSTRUCTION WORK PLAN Month Week


CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
15-Nov-20
For the Period: November 16 - 21, 2020 Page 1
Contract Details
Owner Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
Site Clearing & Housekeeping Sta. 19+200 (Site Office) FE Grace

Excavation for Waterline System


Sta. 19+200 (Site Office) FE Grace
& Drainage System

Soil Sampling Sta. 05+600 - Sta. 06+400


FE Fajardo & FE
(Excavation of Test Pits) Sta. 13+000 - Sta. 13+620
Estillore
Lay out for Cross-Section Sta. 09+000

Estimated Asphalt or Concrete Requirements


Concrete Unit Asphalt Unit

cu.m. m.t

Procurement Log
List of items needed within seven (7) days

GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s

Environment
Environmental Impact Type of Control Assigned Person/s

Form No. F-CON-001 Rev. No. 2 Issued 11/17/2020 Attach additional sheets if necessary
Distribution Batching, Warehouse, Equipment, HRAD, MTQC, File
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
21-Nov-20
For the Period: November 23 - 28, 2020 Page 1
Contract Details
Owner Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
100(1) Clearing and Grubbing Sta. 05+000 - Sta. 06+000 FE Fajardo & FE
Individual Removal of Trees Sta. 01+380 - Sta. 03+080 Estillore

Soil Sampling/Testing Sta. 01+900 - Sta. 02+940 FE Fajardo


Installation of Electrical Line
Source to Complete the Site CALAX Office FE Corbo & FE Tolentino
Instruction No. 5
Joint Inspection of MPCala &
FE Fajardo & FE
ECDLCC for the location of Sta. 13+000
Estillore
drainage works
Erection of Container Vans Sta. 19+000 (Site 1) FE Grace

Estimated Asphalt or Concrete Requirements


Concrete Unit Asphalt Unit

cu.m. m.t

Procurement Log
List of items needed within seven (7) days

GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s

Environment
Environmental Impact Type of Control Assigned Person/s

Form No. F-CON-001 Rev. No. 2 Issued 11/17/2020 Attach additional sheets if necessary
Distribution Batching, Warehouse, Equipment, HRAD, MTQC, File
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
03-Dec-20
For the Period: December 04 - 17, 2020 Page 1
Contract Details
Owner MPCala Holdings Inc. Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
18+700.00 18+900.00 200.00 m
Stake-Out of Limits Survey Team
19+700.00 20+900.00 1,200.00 m

18+700.00 19+000.00 14,682.00 sq. m


100(1) Clearing and Grubbing
19+700.00 20+900.00 58,728.00 sq. m

18+700.00 19+000.00 FE Camille & FE Shaira 192.00 pcs


100(3)a Individual Removal of Trees
19+700.00 20+900.00 - pcs
Embankment from Roadway
104(1)a 18+700.00 19+000.00 109,234.08 cu. m
Excavation
05+600.00 06+400.00 33,600.00 sq. m
100(1) Clearing and Grubbing
13+000.00 13+620.00 30,342.80 sq. m

Embankment from Roadway 05+600.00 06+400.00 6,720.00 cu. m


104(1)a FE Alfred & FE Adonis
Excavation 13+000.00 13+620.00 6,068.56 cu. m

05+600.00 06+400.00 -
Checking of Lay Out
13+000.00 13+620.00 -

B.1 (b) Contractors Facilities 19+200.00 FE Rex -

Estimated Asphalt or Concrete Requirements


Concrete Unit Asphalt Unit
N/A cu.m. N/A m.t
Procurement Log
List of items needed within seven (7) days

GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
03-Dec-20
For the Period: December 04 - 17, 2020 Page 1
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s
100(1) Clearing and Grubbing Engineer's Certificate Pandemic Face Masks

100(3)a Individual Removal of Trees Engineer's Certificate Face Shield

Grading Goggles

104(1)a
Embankment from Roadway Plasticity NOTE: NO COMPANY NURSE
Excavation Compaction Environment
CBR Environmental Impact Type of Control Assigned Person/s

N/A
Form No. F-CON-001 Rev. No. 2 Issued 11/17/2020 Attach additional sheets if necessary
Distribution Client, Batching, Warehouse, Equipment, HRAD, MTQC, HSE & Engineering HO, File

BATCHING WAREHOUSE EQUIPMENT HRAD MTQC HSE

Field Engineer Field Engineer Field Engineer Field Engineer Field Engineer

ANTONIO P. AGUILAR
Project Manager
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
10-Dec-20
For the Period: December 11 - 23, 2020 Page 1
Contract Details
Owner MPCala Holdings Inc. Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
Survey Team with: 0.00 m

Restoration/Checking of Lay Outs 05+600.00 06+400.00 FE Alfred 800.00 m


& Limits 13+000.00 13+620.00 FE Adonis 620.00 m

01+900.00 02+940.00 FE Alfred/FE Shaira 1,040.00 m

13+000.00 13+620.00 FE Adonis 26,040.00 sq. m


100(1) Clearing and Grubbing
19+700.00 20+900.00 FE Camille 54,145.20 sq. m

01+900.00 02+940.00 FE Alfred/FE Shaira 161.00 pcs

100(3)a Individual Removal of Trees 18+700.00 19+000.00 192.00 pcs


FE Camille
19+700.00 20+900.00 300.00 pcs

18+700.00 19+000.00 FE Camille 2,707.26 cu. m

Embankment from Roadway 05+600.00 06+400.00 FE Alfred 6,720.00 cu. m


104(1)a
Excavation 13+000.00 13+620.00 FE Adonis 5,208.00 cu. m

19+700.00 20+900.00 FE Camille 10,829.04 cu. m

B.1 (b) Contractors Facilities 19+200.00 FE Rex -

Estimated Asphalt or Concrete Requirements


Concrete Unit Asphalt Unit
N/A cu.m. N/A m.t
Procurement Log
List of items needed within seven (7) days

GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s
100(1) Clearing and Grubbing Engineer's Certificate Pandemic Face Masks

100(3)a Individual Removal of Trees Engineer's Certificate Face Shield

Grading Goggles

104(1)a
Embankment from Roadway Plasticity NOTE: NO COMPANY NURSE
Excavation Compaction Environment
CBR Environmental Impact Type of Control Assigned Person/s

N/A
Form No. F-CON-001 Rev. No. 2 Issued 11/17/2020 Attach additional sheets if necessary
Distribution Client, Batching, Warehouse, Equipment, HRAD, MTQC, HSE & Engineering HO, File
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
17-Dec-20
For the Period: December 18 - 23, 2020 Page 1
Contract Details
Owner MPCala Holdings Inc. Project Manager ANTONIO P. AGUILAR
Materials Engineer ELADIO S. LIMOS Quantity Engineer YANIE V. DE VERA
HSE Manager Field Engineer
Work Details
Pay Item No. Description Stations Engineer Manpower Size Target Output Unit
Lay Out and Stake Out for;

a. Abaya 01+900.00 02+940.00


Survey Team
b. Advincula 05+600.00 06+400.00

c. Maralas 13+600.00 13+620.00

Clearing and Grubbing Gov. Drive Interchange


100(1) 23,100.00 sq. m
(Main Ramp) 0+140.00 0+560.00 FE Adonis and FE
Gov. Drive Interchange Camille
100(3)a Individual Removal of Trees 126.00 pcs
18+820.00

Hauling and Dumping of Cleared


loads/dump
& Grubbed and Excavated 18+840.00 10+080.00 FE Shaira 70.00
truck
Materials

Preparation for Installation of


Temporary Board-Up at Amaia 11+600.00 11+800.00
Property
Joint Inspection for Sampling &
FE Alfred
Testing at;
a. Maralas Area 13+000.00 13+620.00

b. Abaya Area 01+900.00 02+940.00


Contractors Facilities
19+200.00 Installation of
B.1 (b) (Septic Tank & Conference FE Rex
Site Office Conference Room
Room)

Estimated Asphalt or Concrete Requirements


Concrete Unit Asphalt Unit
N/A cu.m. N/A m.t
Procurement Log
List of items needed within seven (7) days

GRS No. Item Description Qty GRS No. Item Description Qty
1 6
2 7
3 8
4 9
5 10
Equipment Requirement Summary
Equipment Description Qty Equipment Description Qty
1 6
2 7
3 8
4 9
5 10
Additional Manpower Requirement
Position No. Position No.
1 6
2 7
3 8
4 9
5 10
Quality Test Requirements Health & Safety
Pay Item No. Description Quality Test Required Hazard Description PPE/Device Qty Assigned Person/s
100(1) Clearing and Grubbing Engineer's Certificate Pandemic Face Masks

100(3)a Individual Removal of Trees Engineer's Certificate Face Shield

Goggles
NOTE: NO COMPANY NURSE
Environment
PROJECT
WEEKLY CONSTRUCTION WORK PLAN Month Week
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
17-Dec-20
For the Period: December 18 - 23, 2020 Page 1
Environmental Impact Type of Control Assigned Person/s
N/A