PROJECT: RESIDENTIAL
2014 EC
BILL OF QUALITY AND SPECIFICATION SUMERY
A. SUB-STRUCUTRE AMOUNT
1. Excavation and earth work 50,859.50 Birr
2. Masonry work 144,000.00 birr
SUB TOTAL 190,859.00 Birr
B. SUPER-STRUCUTRE AMOUNT
1. Concrete work 214,560.00 Birr
2. Metal work 187,850.00 Birr
3. Carpentry and Joinery work 207,835.00 Birr
4. Roof work 52,728.00 Birr
5. Finishing work 55,008.00 Birr
6. Painting work 17,460.00 Birr
SUB TOTAL 735,441.00 Birr
B. SUPER STRUCTURE
1. Concrete work
1.1 Ground floor slab M2 71.52 3000.00 214,560.00
Total carried to summary 214,560.00
2. Metal work
2.1 Doors
2.1.1 Type D1 size (230x240) no 1 36,300.0 36,300.00
0
2.1.2 Type D2 size (230x240) no 1 19,150.0 19,150.00
0
2.1.2 Type D3 size (80x190) no 4 1750,00 7000.00
2.2 Windows
2.2.1 Type w1 size (50 x 60) M2 3 800.00 2400,00
2.2.2 RC steel 12 diameter kg 82 1500.00 123,000.00
3. Total carried to summary 187,850.00
3.1 Carpentry and Joinery work
3.1.1 All structural members shall be well seasoned and free from harmful defects
each truss shall be fixed with dia.6mm plain bar to concrete beam or stones
wall steel
3.1.2 15cm wood wall M2 468.00 350 163.800.00
6cm brick wall
3.1.3 10cm eucalyptus upper and lower members of truss ML 36.10 30.00 1080.00
3.1.4 8cm eucalyptus upper and lower members of truss ML 142.00 25.00 3195
3.1.5 5x5cm zigba purlin ML 80.00 50.00 4000
3.1.6 Supply fix 8mm plastic ceiling fixed to truss which is suspended by ceiling M2 71.52 500.00 35,760.00
buttons.
Total carried to summary 207,835.00
4. Roof work
4.1 Roof cover of G-32 in tile foor to 5x7 cm zigba purlin (roof measured in M2 72.60 120.00 8712.00
horizontal projection.
4.2 G-32 roof cover M2 104.8 420.00 44,016.00
Total carried to summary 52,728.00
5.1 Finishing work
5.1.1 Finishing work shall be include all surfaces per cleaning preparation, chiseling
application of finishing, polishing and cleaning at the end of finishing work.
5.1.1. Wall finishing
1
5.1.1. Apply mud plaster to internal wall surface M2 468.00 35.00 16,380.00
2
Apply gypsum plaster to internal and external wall surface M2 188.21 200.00 37,600.00
5.1.2
5.1.2. Floor finishing
1
Cement screed tile flooring bedded in 3cm thick cement sand screed M2 71.52 150.00 10,728.00
4. Total carried to summary 55,008.00
6.1 Painting work
Apply three coasts of plastic emulsion for internal wall surface M2 388.16 45 17,460.00
Total carried to summary 17,460.00