BILL OF QUANTITY

LOCATION: KAFA ZONE /AWURADA CITY

PROJECT: RESIDENTIAL

OWNER: ATO TESHOME TAKELE GEBRE

PREPARED BY: YOHANNES SHAREW


APPROVED BY:------------------------------------------

2014 EC
BILL OF QUALITY AND SPECIFICATION SUMERY

A. SUB-STRUCUTRE AMOUNT
1. Excavation and earth work 50,859.50 Birr
2. Masonry work 144,000.00 birr
SUB TOTAL 190,859.00 Birr

B. SUPER-STRUCUTRE AMOUNT
1. Concrete work 214,560.00 Birr
2. Metal work 187,850.00 Birr
3. Carpentry and Joinery work 207,835.00 Birr
4. Roof work 52,728.00 Birr
5. Finishing work 55,008.00 Birr
6. Painting work 17,460.00 Birr
SUB TOTAL 735,441.00 Birr

TOTAL A + B 926,300.00 Birr


BILL OF QUANTITY OF RESIDENTIAL BUILDING

Item Description Unit Quanti Unit price Sub-total


no ty
A. SUB-STRUCTURE
1. Excavation and earth work
1.1 Clear off site to remove top soil, depth 200m M2 240.00 25.00 6000.00
1.2 Trench excavation in ordinary soil for stone masonry peripheral foundation wall to M3 71.50 85.00 6077.50
depth not exceeding 500mm starting from ground level
1.3 Cart away and spread surplus excavated materials to an appropriate tip for 2km M3 62.50 100.00 6200.00
1.4 Hard basaltic or equivalent stone hard core well rolled consolidated and with M2 71.52 450.00 32,184.00
crushed stone to a finished thickness of 200mm.
Total carried to summary 50,859.50
2. masonry work
2.1 500mm thick roughly dressed stone masonry peripheral foundation wall bedded in
cement sand mortar (1:3)
2.2 Above and below ground level M3 71.52 2,000.00 144,000.00
Total carried to summary 144,000.00

B. SUPER STRUCTURE

1. Concrete work
1.1 Ground floor slab M2 71.52 3000.00 214,560.00
Total carried to summary 214,560.00
2. Metal work
2.1 Doors
2.1.1 Type D1 size (230x240) no 1 36,300.0 36,300.00
0
2.1.2 Type D2 size (230x240) no 1 19,150.0 19,150.00
0
2.1.2 Type D3 size (80x190) no 4 1750,00 7000.00
2.2 Windows
2.2.1 Type w1 size (50 x 60) M2 3 800.00 2400,00
2.2.2 RC steel 12 diameter kg 82 1500.00 123,000.00
3. Total carried to summary 187,850.00
3.1 Carpentry and Joinery work
3.1.1 All structural members shall be well seasoned and free from harmful defects
each truss shall be fixed with dia.6mm plain bar to concrete beam or stones
wall steel
3.1.2 15cm wood wall M2 468.00 350 163.800.00
6cm brick wall
3.1.3 10cm eucalyptus upper and lower members of truss ML 36.10 30.00 1080.00
3.1.4 8cm eucalyptus upper and lower members of truss ML 142.00 25.00 3195
3.1.5 5x5cm zigba purlin ML 80.00 50.00 4000
3.1.6 Supply fix 8mm plastic ceiling fixed to truss which is suspended by ceiling M2 71.52 500.00 35,760.00
buttons.
Total carried to summary 207,835.00
4. Roof work
4.1 Roof cover of G-32 in tile foor to 5x7 cm zigba purlin (roof measured in M2 72.60 120.00 8712.00
horizontal projection.
4.2 G-32 roof cover M2 104.8 420.00 44,016.00
Total carried to summary 52,728.00
5.1 Finishing work
5.1.1 Finishing work shall be include all surfaces per cleaning preparation, chiseling
application of finishing, polishing and cleaning at the end of finishing work.
5.1.1. Wall finishing
1
5.1.1. Apply mud plaster to internal wall surface M2 468.00 35.00 16,380.00
2
Apply gypsum plaster to internal and external wall surface M2 188.21 200.00 37,600.00
5.1.2
5.1.2. Floor finishing
1
Cement screed tile flooring bedded in 3cm thick cement sand screed M2 71.52 150.00 10,728.00
4. Total carried to summary 55,008.00
6.1 Painting work
Apply three coasts of plastic emulsion for internal wall surface M2 388.16 45 17,460.00
Total carried to summary 17,460.00