PROPOSED RESIDENTIAL DEVELOPMENT

AT

GAYAZA, WAKISO DISTRICT

BILLS OF QUANTITIES

CLIENT:
MR & MRS

P.O BOX………..., KAMPALA


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

BILL No. 2 : MAIN HOUSE

ELEMENT No. 1

SUBSTRUCTURE

Excavations and Earthworks

Excavate oversite to remove vegetable soil and remove


A materials from site m2 240 2,000 480,000

Excavate surface trenches: not exceeding 1.50 metres deep


B from reduced levels to receive wall foundations m3 98 6,000 588,000

Extra over general excavation for excavation in rock and


C removal of materials from site m3 1 100,000 100,000

D Allow for keeping excavations free from all water Item 250,000

E Allow for supporting sides of excavations Item 250,000

Return, fill and ram selected excavated materials in layers not


F exceeding 200mm thick around foundations m3 48 8,000 384,000

150mm Thick murram compacted and ready to receive


G hardcore (measured separately) m2 160 2,000 320,000

H Remove surplus excavated materials from site m3 50 15,000 750,000

Hardcore filling

200mm bed, consolidated, levelled and blinded with a layer of


I sand m2 160 15,000 2,400,000

Termidor 25 EC' or other equal approved anti-termite


chemical treatment: applied by an approved professional
pest control specialist: strictly in accordance with the
manufacturer's instructions: to

J Hardcore area m2 160 2,000 320,000

K Sides and bottom of foundations m2 358 2,000 716,000

BILL No. 2: MAIN HOUSE 2/1/1 SUBSTRUCTURE


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)
Total carried to collection of element No. 1
(SUBSTRUCTURE) 6,558,000

Plain in-situ concrete grade 15 as described:-

A 200mm Thick in strip foundations m2 98 64,000 6,272,000

Plain in-situ concrete grade 25 as described:-

B 100mm Thick ground floor bed m2 187 42,000 7,854,000

Sawn formwork as described to:-

C Edge of surfaces bed: 75 - 150mm high m 75 3,500 262,500

Solid brickwork in standard approved burnt clay bricks


bedded and pointed in cement mortar (1:4) as described
in:-

D 230mm Thick plinth walling m2 133 68,000 9,044,000

Damp proof membrane

Single layer of 1000 gauge polythene laid on blinded hardcore


E with 150mm minimum side and end laps m2 187 2,000 374,000

Hessian based bituminous felt or other approved damp-


proof course laid on and including 25mm cement and
sand (1:3) mortar as described under walls:-
F 150mm wide m 122 1,500 183,000

Splash apron

100mm Thick precast concrete grade 20 slabs laid to gentle


falls in 2.0 metre bays and jointed with 25mm Thick cement
and sand (1:3) mortar; on and including 100mm Thick
approved hard-core well compacted and blinded with stone
dust; including all necessary excavations and 100mm Thick
locally burnt brick edge kerbing 250mm deep in cement and
sand mortar (1:4) bedded on 100mm thick mass concrete
(class 20) with 25mm Thick cement and sand (1:3) rendering
G to sides m2 45 100,000 4,500,000
Welded fabric mesh reinforcement to BS 4483 as
described

Mesh reinforcement ref. A142 weighing 2.22 kg per square


H metre: in floor slab with 200mm side and end laps m2 187 12,000 2,244,000

BILL No. 2: MAIN HOUSE 2/1/2 SUBSTRUCTURE


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

Total carried to collection of element No. 1


(SUBSTRUCTURE) 30,733,500

Collection of Element No. 1 (SUBSTRUCTURE)

FROM PAGE 2/1/1 6,558,000

FROM PAGE 2/1/3 30,733,500

BILL No. 2: MAIN HOUSE 2/1/3 SUBSTRUCTURE


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

TOTAL ELEMENT No. 1 (SUBSTRUCTURE) CARRIED TO


BILL SUMMARY 37,291,500

BILL No. 2: MAIN HOUSE 2/1/4 SUBSTRUCTURE


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

ELEMENT No. 2

WALLING AND FRAME

Solid brickwork in standard approved burnt clay


bricks bedded and pointed in cement mortar (1:5)
as described in:-
A 230mm Thick external wall m2 137 65,000 8,905,000

B 150mm Thick internal wall m2 138 55,000 7,590,000

Pompey grilles jointed and pointed in cement


sand (1:4) mortar in;
C 200mm Thick external wall m2 20 55,000 1,100,000

Vibrated reinforced concrete grade 25 as


described: in

200 x 150mm lintel reinforced with and including 4No


12mm diameter mild steel bars and 6mm mild steel
D links at 200mm centres m 4 30,000 120,000

E Columns & ring beam m3 11 440,000 4,840,000

F 250mm Thick solid suspended slab m2 16 110,000 1,760,000

Mild steel bars to BS 4461 as specified by the


structural Engineer; including cutting to length,
bending, hoisting and fixing
G Assorted bars Kg 350 4,200 1,470,000

High yield reinforced bars to BS4461 as specified


by the structural Engineer; including cutting to
length, bending, hoisting and fixing and all
necessary tying wire and spacing blocks
H Assorted bars Kg 1,280 4,200 5,376,000

Sawn formwork as described: to


I Sides and soffites: of horizontal lintels m2 3 22,000 66,000

J Sides and soffites: Columns & ring beam m2 120 22,000 2,640,000

K Soffites: of solid slab m2 16 22,000 352,000

L Edges: of solid slab 75 - 150mm wide m 16 3,300 52,800

BILL No. 2: MAIN HOUSE 2/2/1 EXTERNAL WALLS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)
TOTAL ELEMENT No. 2 (WALLING AND FRAME)
TO BILL SUMMARY 34,271,800

BILL No. 2: MAIN HOUSE 2/2/2 EXTERNAL WALLS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

ELEMENT No. 3

ROOF CONSTRUCTION AND COVERING

All timber to be sawn "Cypress" Softwood treated with


pressure impregnated "Celcure" or "Tenalith" solution
as described

(Note: All timber quantities are provisional)

A 75 x 100mm Wall plate m 180 10,000 1,800,000

B 20 x 220mm Fascia board and barge board m 75 15,000 1,125,000

The Following in Timber Trusses

C 50 x 100mm commom rafters m 153 7,500 1,147,500

D 50 x 100mm hip rafters m 44 7,500 330,000

E 50 x 100mm valley rafters m 40 7,500 300,000

F 50 x 100mm tie beams m 142 7,500 1,065,000

G 50 x 100mm tie ridge board m 15 7,500 112,500

H 50 x 100mm struts and ties m 80 7,500 600,000

Roof covering

Single layer of 1000 gauge polythene laid on wire mesh


I (m.s) m2 239 2,000 478,000

J Chicken wire mesh m2 239 2,500 597,500

"Mangalore" clay roofing tiles fixed to and including 50mm


x 50mm softwood battens on 50mm x 50mm softwood
K counter battens at 370mm centres m2 239 60,000 14,340,000

L Clay ridge piece m 15 23,000 345,000

M Gauge 26 steel valley fixed to manufacturers' specifications m 20 25,000 500,000

BILL No. 2: MAIN HOUSE 2/3/1 ROOF


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)
Total Carried to collection of Element No.3 (ROOF
CONSTRUCTION) 22,740,500

Roof drainage

A 150mm diameter pvc gutters with and including connectors m 75 60,000 4,500,000

B 150mm diameter pvc stopped ends No 8 30,000 240,000

150mm Diameter heavy duty pvc fulbora outlet with and


including 200mmx 200mm x 4mm thick galvanised steel
C grating on top No 4 75,000 300,000

D Extra over for swan neck No 4 65,000 260,000

E Extra over for shoe No 4 32,000 128,000

F 100mm down pvc pipe m 8 30,000 240,000

Extra over for dressing around fulbora outlets to make them


G water tight No 4 20,000 80,000

Eaves ceiling

30mm Overall thick ( Pricking and Finishing coat) plastere


on and including expanded metal lathe, 100mm x 50mm
Joists at 1200mm and 150mm x 50mm branderings at
H 600mm centres. m2 45 50,000 2,250,000

I Extra over ceiling for trap door size 600 x 500mm No. 2 30,000 60,000

Painting

Prepare and apply one mist coat and three finishing coats
first grade matt emulsion paint on horizontal Plastered
J eaves ceiling m2 45 9,000 405,000

Prepare and apply three coats of oil based paint on wood


K surfaces 200 - 300mm wide m 75 2,400 180,000

Pergola

Allow a provisional sum of Ushs 1,500,000 (Uganda


Shillings One Million Five Hundred Thousand Only) for
L construction of a pergola, to A rchitect's details Item 1,500,000

BILL No. 2: MAIN HOUSE 2/3/2 ROOF


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

Total Carried to collection of Element No.3 (ROOF


CONSTRUCTION) 10,143,000

Collection of Element No.3 (ROOF CONSTRUCTION)

From page 2/3/1 22,740,500

From page 2/3/2 10,143,000

BILL No. 2: MAIN HOUSE 2/3/3 ROOF


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

TOTAL ELEMENT No. 3 (ROOF CONSTRUCTION AND


COVERING) CARRIED TO BILL SUMMARY 32,883,500

BILL No. 2: MAIN HOUSE 2/3/4 ROOF


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

ELEMENT No. 4
WINDOWS AND EXTERNAL DOORS
WINDOWS

Precast Concrete Grade 25 as described:

300 x 75mm (average) Weathered and throated cill:


bedded and jointed in cement sand mortar (1:4) and
A finished fair on exposed faces m 24 10,000 240,000

Plaster: 9mm first coat of cement/ lime putty/ sand


(1:2:9): 4mm second coat of cement/ lime putty/ sand
(1:1;6): steel trowelled on masonry : to
B Window reveals 200 - 300mm wide m 78 2,500 195,000

ALUMINIUM WINDOWS

Supply, assemble and fix aluminium windows


constructed from standard aluminium sections to BS
1474:1972; with 300mm high louvered aluminium
PVO; dark bronze anodised before delivery to site;
including all necessary ironmongery, to Architect's
details

Sliding window size 3000 x 2100mm high overall:


complete with 5mm Thick clear glass glazed with rubber
C beads (W1) No 2 3,150,000 6,300,000

Side hung window size 2000 x 1500mm high overall: ditto


D (W2) No 3 1,500,000 4,500,000

Top hung window size 600 x 2000mm high overall: ditto


E (W3) No 2 600,000 1,200,000

Top hung window size 1000 x 900mm high overall:


complete with 5mm Thick clear glass glazed with rubber
F beads (W4) No 5 450,000 2,250,000

Side hung window size 2000 x 1400mm high overall: ditto


G (W5) No 1 1,400,000 1,400,000

BILL No. 2: MAIN HOUSE 2/4/1 EXTERNAL DOORS AND WINDOWS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)
Total Carried to collection of Element No.4
(WINDOWS AND EXTERNAL DOORS) 16,085,000

BURGLAR PROOFING WINDOWS

Burglar proofing comprising vertical members size 25


x 25 x 2.5mm Thick SHS welded at 250mm centres to
horizontal members size 25 x 25 x 2.5mm Thick SHS
at 250mm centres with ends bedded in masonry, to
Architect's details

A Size 3000 x 2100mm high No 2 1,100,000 2,200,000

B Size 2000 x 1500mm high No 3 540,000 1,620,000

C Size 600 x 2000mm high No 2 216,000 432,000

D Size 1000 x 900mm high No 5 162,000 810,000

E Size 2000 x 1400mm high No 1 500,000 500,000

Painting

Prepare and spray three coats of approved gloss oil paint


to general surfaces of steel surfaces (measured flat
F overall on both sides) m2 70 8,000 560,000

Prepare and apply one mist coat and three finishing coats
first grade matt emulsion paint on window reveals 200 -
G 300mm wide m 78 3,000 234,000

Prepare and apply three coats of weatherguard paint on


H concrete cill 200 - 300mm girth m 24 3,000 72,000

BILL No. 2: MAIN HOUSE 2/4/2 EXTERNAL DOORS AND WINDOWS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

Total Carried to collection of Element No. 4


(WINDOWS AND EXTERNAL DOORS) 6,428,000

EXTERNAL DOORS

ALUMINIUM DOORS

Supply, assemble and fix aluminium doors


constructed from standard aluminium sections to BS
1474:1972; with 300mm high louvered aluminium
PVO; dark bronze anodised before delivery to site
complete with 6mm Thick clear sheet glass glazed
with rubber beads, including all necessary
ironmongery, to Architect's details

A Swing door size 900 x 2400mm high overall (D3) No 2 1,100,000 2,200,000

B Swing door size 1200 x 2400mm high overall (D4) No 1 1,400,000 1,400,000

Sliding door size 2500 x 2400mm high overall complete


C with sliding gear (D5) No 1 3,300,000 3,300,000

Double sliding door size 4000 x 2400mm high overall


D complete with sliding gear (D6) No 1 5,300,000 5,300,000

TIMBER DOORS

45mm Thick SEMI-SOLID CORE interior quality


FLUSH door shutter comprising plywood veneer fixed
on 150 x 40mm hardwood "MAHOGANY" frame ;

E Single leaf door size 800 x 2100mm high (D2 ) No 1 280,000 280,000

Approved Wrot Joinery Hardwood

F 50 x 225mm Frame: two labours: plugged m 5 40,000 200,000

G 50 x 25 mm Architrave : moulded m 5 10,000 50,000

H 15 x 15mm Quadrant : ditto m 5 7,500 37,500

BILL No. 2: MAIN HOUSE 2/4/3 EXTERNAL DOORS AND WINDOWS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

Total Carried to collection of Element No.4


(WINDOWS AND EXTERNAL DOORS) 12,767,500

Supply and fix the following "UNION" or similar and


approved ironmongery to timber complete with
matching screws

A 2 lever mortice complete lockset No 1 150,000 150,000

B Door stopper No 1 15,000 15,000

C Single acting stainless steel ball bearings hinges Prs 1.5 35,000 52,500

BURGLAR PROOFING DOORS

Burglar proofing comprising vertical members size 25


x 25 x 2.5mm Thick SHS welded at 250mm centres to
horizontal members size 25 x 25 x 2.5mm Thick SHS
at 250mm centres with ends bedded in masonry, to
Architect's details

D Size 900 x 2400mm high No 2 380,000 760,000

E Size 1200 x 2400mm high No 1 500,000 500,000

F Size 2500 x 2400mm high No 1 1,000,000 1,000,000

G Size 4000 x 2400mm high No 1 1,720,000 1,720,000

Painting

Prepare and spray three coats of approved gloss oil paint


to general surfaces of steel surfaces (measured flat
H overall on both sides) m2 46 8,000 368,000

Prepare and apply three coats of polyurethane varnish on


I wood surfaces m² 5 8,000 40,000

J Do. But on wood surfaces 75-150mm girth m 5 1,500 7,500

K Do. But on wood surfaces not exceeding 75mm girth m 5 1,000 5,000

BILL No. 2: MAIN HOUSE 2/4/4 EXTERNAL DOORS AND WINDOWS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

Total Carried to collection of Element No.4


(WINDOWS AND EXTERNAL DOORS) 4,618,000

Collection of Element No. 4 (WINDOWS AND


EXTERNAL DOORS)

FROM PAGE 2/4/1 16,085,000

FROM PAGE 2/4/2 6,428,000

FROM PAGE 2/4/3 12,767,500

FROM PAGE 2/4/4 4,618,000

BILL No. 2: MAIN HOUSE 2/4/5 EXTERNAL DOORS AND WINDOWS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

TOTAL ELEMENT No. 4 (WINDOWS AND EXTERNAL


DOORS) TO SUMMARY 39,898,500

BILL No. 2: MAIN HOUSE 2/4/6 EXTERNAL DOORS AND WINDOWS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

ELEMENT No. 5

INTERNAL DOORS

TIMBER DOORS

45mm Thick SOLID CORE interior quality


PANELLED hardwood "MAHOGANY" door shutter ;

Single leaf door size 900 x 2400mm high overall with


A 300mm high PVO (D1 ) No 3 450,000 1,350,000

45mm Thick SEMI-SOLID CORE interior quality


FLUSH door shutter comprising plywood veneer
fixed on 150 x 40mm hardwood "MAHOGANY" frame
;

B Single leaf door size 800 x 2100mm high (D2 ) No 3 280,000 840,000

ALUMINIUM DOORS

Supply, assemble and fix aluminium doors


constructed from standard aluminium sections to
BS 1474:1972; with 300mm high louvered aluminium
PVO; dark bronze anodised before delivery to site
complete with 6mm Thick clear sheet glass glazed
with rubber beads, including all necessary
ironmongery, to Architect's details

C Swing door size 900 x 2400mm high overall (D3) No 1 1,100,000 1,100,000

Approved Wrot Joinery Hardwood

D 50 x 225mm Frame: two labours: plugged m 15 40,000 600,000

E 50 x 225mm Transome: two labours: plugged m 3 40,000 120,000

F 50 x 175mm Frame: two labours: plugged m 15 35,000 525,000

G 50 x 25 mm Architrave : moulded m 30 10,000 300,000

H 15 x 15mm Quadrant : ditto m 30 7,500 225,000

BILL No. 2: MAIN HOUSE 2/5/1 INTERNAL DOORS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)
Total Carried to collection of Element No. 5
(INTERNAL DOORS) 5,060,000

Supply and fix the following "UNION" or similar and


approved ironmongery to timber complete with
matching screws

A 3 lever mortice complete lockset No 3 180,000 540,000

B 2 lever mortice complete lockset No 3 150,000 450,000

C Door stopper No 6 15,000 90,000

D Single acting stainless steel ball bearings hinges Prs 9 35,000 315,000

Prepare and apply three coats of polyurethane varnish


E on wood surfaces m² 27 8,000 216,000

F Do. But on wood surfaces 225-300mm girth m 15 2,400 36,000

G Do. But on wood surfaces 75-150mm girth m 30 1,500 45,000

H Do. But on wood surfaces not exceeding 75mm girth m 30 1,000 30,000

Total Carried to collection of Element No. 5


(INTERNAL DOORS) 1,722,000

Collection of Element No. 5 (INTERNAL DOORS)

FROM PAGE 2/5/1 5,060,000

FROM PAGE 2/5/2 1,722,000

BILL No. 2: MAIN HOUSE 2/5/2 INTERNAL DOORS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

TOTAL ELEMENT No. 5 (INTERNAL DOORS) TO


BILL SUMMARY 6,782,000

BILL No. 2: MAIN HOUSE 2/5/3 INTERNAL DOORS


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

ELEMENT No. 6

FLOOR FINISHES

Cement and sand (1:3) screed:-

A 25mm Thick floor paving screed: steel floated m2 9 11,000 99,000

25mm Thick floor paving screed: wood float and prepared to


B receive tiles (m.s) m2 150 11,000 1,650,000

25 x 150mm high screed: wood float and prepared to receive


C tiles skirting (m.s) m 115 1,650 189,750

Ceramic Tiles
8mm Thick Ceramic floor tiles laid on prepared surface
(measured separately) with and including tile adhesive
D including pointing to all joints in matching cement grout m2 150 75,000 11,250,000

E Ditto:150mm high skirting m 115 11,250 1,293,750

Waterproofing
4mm Thick "Master seal" or other approved water proofing
F material laid on suspended slab m2 16 65,000 1,040,000

INTERNAL WALL FINISHES

Internal wall finishes Plaster: 9mm first coat of cement/


lime putty/ sand (1:2:9): 4mm second coat of cement/
lime putty/ sand (1:1;6): steel trowelled on masonry or
concrete: to
G Walls m2 270 10,000 2,700,000

Backing: 10mm cement/ sand (1:4): on masonry or


concrete: wood float finished: to

H Walls to receive ceramic tiles (m.s.) m2 60 7,500 450,000

Ceramic glazed wall tiling laid on prepared surface (m.s)


with and including tile adhesive including pointing to all
joints in matching cement grout
I 6mm Thick tiles m2 60 65,000 3,900,000

Prepare and apply one mist coat and three finishing


coats first grade matt emulsion paint : on
J Plastered walls m2 270 9,000 2,430,000

BILL No. 2: MAIN HOUSE 2/6/1 FINISHES


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

Total Carried to collection of Element No. 6 (FINISHES) 25,002,500

EXTERNAL WALL FINISHES

Cement and sand (1:4) rendering

A 25mm Thick cement and sand (1:4) rendering on masonry m2 81 12,000 972,000

Painting

Prepare and apply three coats of first grade weatherguard


B paint : on rendered wall surfaces m2 81 10,000 810,000

CEILING FINISHES

Plasterboard Ceiling
9mm Thick plasterboard fixed to and including 100mm x
50mm Joists at 1200mm centred and 150mm x 50mm
C branderings at 600mm centres; finished ready for painting m2 159 70,000 11,130,000

D Extra over ceiling for trap door size 600 x 500mm No. 2 30,000 60,000

Prepare and apply one mist coat and three finishing


coats first grade matt emulsion paint : on
E Horizontal prepared soffites of ceilings m2 159 9,000 1,431,000

Total Carried to collection of Element No. 6 (FINISHES) 14,403,000

Collection of Element No. 6 (FINISHES)

FROM PAGE 2/6/1 25,002,500

FROM PAGE 2/6/2 14,403,000

BILL No. 2: MAIN HOUSE 2/6/2 FINISHES


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY (USHS) (USHS)

TOTAL ELEMENT No. 6 (FINISHES) CARRIED TO BILL


SUMMARY 39,405,500

BILL No. 2: MAIN HOUSE 2/6/3 FINISHES


ITEM DESCRIPTION AMOUNT (USHS)

BILL No. 2

SUMMARY

MAIN HOUSE

1 SUBSTRUCTURE 37,291,500

2 WALLING AND FRAME 34,271,800

3 ROOF CONSTRUCTION AND COVERING 32,883,500

4 WINDOWS AND EXTERNAL DOORS 39,898,500

5 INTERNAL DOORS 6,782,000

6 FINISHES 39,405,500

7 MECHANICAL INSTALLATIONS 38,747,000

8 ELECTRICAL INSTALLATIONS 48,540,000

ALLOW PROVISIONAL SUMS FOR


9 FURNITURE AND FITTINGS 8,000,000

TOTAL BILL No.2 (MAIN HOUSE) CARRIED TO MAIN


SUMMARY 285,819,800