Bill Nr.

2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


A ELEMENT NR 1: SUBSTRUCTURE
Site Preparations;
Clearing the site; grubbing up roots bushes, scrub,
undergrowth or the likesmall trees not exceeding 600 551 m2 350.00 192,850.00
mm girth

B Excavation and Earthworks; 551 m2 900.00 495,900.00


Excavate oversite average 150mm deep to remove
top soil, convey average 50 linear meters and deposit
in temporary spoil heaps

C Excavate pit for column base commencing at 68 m3 7,187.50 488,750.00


stripped level and not exceeding 1.50meters deep

D Excavate foundation trench commencing at stripped 73 m3 13,125.00 958,125.00


level and not exceeding 1.50meters deep

E Extra over any kind of excavation for breaking up rock 18 m3 28,750.00 517,500.00
and the like

F Earth backfilling of selected materials around the 46 m3 4,312.50 198,375.00


foundations

G Ditto around columns 66 m3 6,500.00 429,000.00

H Earth filling of imported selected excavated material, 159 m3 6,760.00 1,074,840.00


well rammed and consolidated to make up levels
under floors.

J Load up surplus excavated material and remove 9 m3 11,300.00 101,700.00


away from site

K Disposal of water 1 Item 430,000.00 430,000.00


Allow for keeping all excavations free from water
(except spring or runing water) by pumping,baling or
by other means necessary

L Plaking and strutting 1 Item 220,000.00 220,000.00


Allow for the provision and subsquent removal of
planking and strutting to up hold and maintain
all faces of excavations

To Collection 5,107,040.00

Page 2 / 1
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


Substructure Cont'd

Hardcore
A 150mm Bed levelled and blinded to receive 397 m2 2,137.50 848,587.50
damp proof membrane

B 150mm Ditto, sloping 17 m2 6,500.00 110,500.00

Soil sterilization

C "Gammalin"solution applied at a rate of 7 litres 414 m2 9,500.00 3,933,000.00


per square metre to hardcore beds

CONCRETE WORK

D Plain Concrete grade "10" 45 m2 170,000.00 7,650,000.00


50mm Blinding

E Plain concrete Grade "15" 21 m3 220,000.00 4,620,000.00


Strip Foundations

F 125mm Thick bed 397 m2 28,000.00 11,116,000.00

G 125mm thich Ramps 17 m2 28,000.00 476,000.00

H Reinforced concrete grade '20' including vibrating 11 m3 270,000.00 2,970,000.00


around reinforcement
Column bases

J Columns 2 m3 270,000.00 540,000.00

K Ground beams 9 m3 270,000.00 2,430,000.00

Reinforcement

High yield strength deformed type 2 steel bar


reinforcement to BS 4449:1969

L 8mm Diameter bars 448 kg 3,900.00 1,747,200.00

M 16mm Diameter bars 2256 kg 3,900.00 8,798,400.00

To Collection 45,239,687.50

Page 2 / 2
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


Substructure Cont'd

A Sawn formwork to: 61 m2 35,122.00 2,142,442.00


Vertical sides of columns

B Vertical edge of bed over 150mm but not exceeding 99 m 8,681.25 859,443.75
350mm high

WALLING

Solid concrete blocks to BS2828 type 'A' bedded


and jointed in cement mortar (1:3)

C 230mm Wall 129 m2 33,200.00 4,282,800.00

D Hessian based bitumem damp proof course to BS 743 74 m 15,000.00 1,110,000.00


type 5A 230mm wide laid horizontally on blockwork

E Damp proof membrane; 414 m2 2,500.00 1,035,000.00


500Gauge polythene damp proof membrane laid
over blinded hardcore (measured separately)

Sundries;

F 12mm Cement and sand (1:3) external rendering to 59 m2 4,500.00 265,500.00


concrete blockwall to match existing

G Prepare and apply two coats of black bituminous 59 m2 11,000.00 649,000.00


paint on rendered or concrete surface, externally to
match existing

To collection 10,344,185.75
COLLECTION

Page 2/1 5,107,040.00

Page 2/2 45,239,687.50

Page 2/3 10,344,185.75

ELEMENT NR.1: SUBSTRUCTURE TOTAL CARRIED TO SUMMARY OF BILL NR. 2 60,690,913.25

Page 2 / 3
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


ELEMENT NR. 2: FRAME; CONCRETE WORK
Reinforced conrete grade '20' including vibrating
around reinforcement

A Columns 9 m3 220,000.00 1,980,000.00

B Beams 13 m3 220,000.00 2,860,000.00

Reinforcement;

High yield strength deformed type 2 steel bar


reinforcement to BS4449:1969

C 8mm Diameter bars 174 Kg 3,900.00 678,600.00

D 16mm Ditto 2356 Kg 3,900.00 9,188,400.00

Sawn formwork to:

E Vertical or battering sides of columns 151 m2 35,122.00 5,303,422.00

F Sides and soffits of horizontal beams 173 m2 8,681.25 1,501,856.25

ELEMENT NR.2: FRAME - TOTAL CARRIED TO SUMMARY 21,512,278.25


OF BILL NR. 2

Page 2 / 4
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


AB ELEMENT NR. 3: WALLS Blockwork;

Solid concrete blocks to B.S. 2028 type 'A' bedded and


jointed in cement mortar (1:4)

230mm Wall 716 m2 33,200.00 23,771,200.00

150mm Louvre block Wall 18 m2 22,193.92 399,490.56

ELEMENT NR. 3 - WALLS TOTAL CARRIED TO 24,170,690.56


SUMMARY OF BILL NR. 2

Page 2 / 5
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


ELEMENT NR. 4 - ROOFING ROOF COVERINGS
Troughed roofing sheets IT 5; 28 gauge; colour
coated Coverings; fixing to steel purlinsat
1200mm general spaciengwith Galvlanised steel hook
bolts, nuts, neoprene washers and caps; one and a
half trohgty side laps; 150mm end
laps Slopng not exceeding 45 degrees form horizontal;

A Roof coverings sloping not exceeding 45 degrees from 528 m2 28,373.28 14,981,091.84
horizontal

B Ridge capping, valley, hip 780mm girth 27 m 9,900.00 267,300.00

ROOF STRUCTURE

C Softwood pressure impregnated with 591 m 7,793.37 4,605,881.67


preservative
150 x 50mm Rafters

D 150 x 50mm Tie beams 671 m 7,793.37 5,229,351.27

E 100 x 50mm Struts 844 m 6,450.00 5,443,800.00

F 75 x 50mm Purlins 802 m 5,570.00 4,467,140.00

G 100 x 50mm Wall Plate 79 m 6,450.00 509,550.00

Wrought Hardwood

H 225 x 25mm Thick fascia board 127 m 9,570.00 1,215,390.00

J Mild steel grade 43A 312 Nr 2,500.00 780,000.00


12mm Diameter mild steel anchor bolt, 400mm long
one end cast in concrete and another end threaded

K 230 x 300 x 4mm thick steel plate 78 Nr 9,000.00 702,000.00

L 800 x 150 x 4mm thick mild steel gusset plate 104 Nr 14,300.00 1,487,200.00

M Mild steel black bolts; or the like 832 Nr 4,500.00 3,744,000.00


12mm Ø x 63mm long mild steel bolt

ELEMENT NR. 4 - ROOFING CARRIED TO SUMMARY OF 43,432,704.78


BILL NR. 2

Page 2 / 6
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


ELEMENT NR. 5 - DOORS

Metal Works

Fabricate and fix in position metal grilles slidding gate


to Architect's approved patterns adequately secured
to concrete or block walls overall sizes;

A 2000 x 2700mm high 3 Nr 486,000.00 1,458,000.00

Hardwood doors

B 900 x 2500mm high 4 Nr 350,000.00 1,400,000.00

Wrot Hardwood (approved Mninga)

C 125 x 40mm Frame, plugged 30 m 18,000.00 540,000.00

D 50 x 15mm Architrave 30 m 12,000.00 360,000.00

IRONMONGERY

Supplying and fixing ironmongery; 'Genuine UNION;


ASSA ABLOY'; or other equal and approved to metal,
softwood, hardwood or the like; fixing with matching
screws

E 100mm Brass butt hinges 24 Nr 12,000.00 288,000.00

F Mortice lockset, three lever complete with furniture 4 Nr 85,000.00 340,000.00


and handle

G Ditto, with indicator bolt 4 Nr 5,000.00 20,000.00

ELEMENT NR. 5 - DOORS TOTAL CARRIED TO SUMMARY OF BILL NR. 4,406,000.00


2

Page 2 / 7
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


ELEMENT NR: 6 - WINDOWS

Metal Works;

Anodized aluminium casement window frames


1.5mm thick sections complete with and including
6mm thick clear sheet ordinary quality glass (Refer
windows schedule drawing Nr.)

A 1500 x 1500mm High with two side sliding panels and 6 Nr 300,000.00 1,800,000.00
two fixed top light panels; window type W1

Metal Works

Fabricate and fix in Position metal grilles of


approved patterns comprising of 38 x 38 H.S.S for main
frameworks, infilled with 38 x 38 x 3mm flat bars at
150mm centers, adequately secured to block walls
overall sizes;

B 1500 x 1500mm high 6 Nr 190,000.00 1,140,000.00

ELEMENT NR. 6 - WINDOWS TOTAL SUMMARY OF 2,940,000.00


CARRIED TO BILL NR. 2

Page 2 / 8
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


ELEMENT NR: 7 - FINISHINGS

INTERNAL WORK

Insitu Finishing;
internal plastering in two coats with smooth steel
trowelled; first coat of cement sand12mm cement and
sand (1:4); second coat of cement and lime putty (1:5)
steel trowelled

A Block walls and concrete works 1029 m2 4,500.00 4,630,500.00

B Columns 33 m2 5,500.00 181,500.00

40mm thick cement sand and chipping in 1:1.5:3 mix


applied in one coat generally to;

C Floors 397 m2 11,500.00 4,565,500.00

D Ramp 17 m2 11,500.00 195,500.00

TILES, SLAB AND BLOCK FINISHINGS


Porcelain floor tiles Ex - China or any other equal and
approved type fixed to screeded bed and pointing
joints with grout

E 300 x 300 x 8mm Thick to floors and pavings 71 m2 56,000.00 3,976,000.00

F 100mm High x 6mm thick skirting 68 m 5,500.00 374,000.00

BEDS AND BACKINGS

G 12mm cement and Sand (1:4) bed to receive floor tiles 71 m2 7,500.00 532,500.00

H 12mm cement and Sand (1:4) backings to skirting 68 m 1,500.00 102,000.00

To collection 14,557,500.00

Page 2 / 9
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


A PLAIN SHEET FINISHINGS Suspended ceiling 71 m2 24,826.74 1,762,698.54
12mm Gypsum board ceiling fixed to timber
background (M.S) complete with sealing tape at joints

B 82 x 82mm Doric cornice as per lafarge gypsum board 68 m 6,500.00 442,000.00


type

C 50 x 50mm Treated softwood brandering and the like; 284 m 3,900.00 1,107,600.00

EXTERNAL WORK

Plastering in two coats including preparatory


coat of stucco steel trowelled to a smooth finish

D 15mm Thick render to walls 827 m2 8,500.00 7,029,500.00

To collection 10,341,798.54

COLLECTION

Page 2/9 14,557,500.00

Page 2/10 10,341,798.54

ELEMENT NR. 7 - FINISHINGS TOTAL CARRIED TO SUMMARY OF 24,899,298.54


BILL NR. 2

Page 2 / 10
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Qty Unit Rate Amount (TZS)


ELEMENT NR: 8 - DECORATIONS

INTERNAL WORK

Prepare and apply one thinned coat and two full


coats of Silky emulsion paint on:

A Plastered walls 1029 m2 3,439.80 3,539,554.20

B Gypsum board ceilings and the like 71 m2 3,980.00 282,580.00

Prepare and apply one thinned coat and two full coats
of varnish paint on:

C Wood Surfaces 16 m2 3,500.00 56,000.00

Prepare, Prime and apply one undercoat and two


finishing coats of PVA paint on metal surfaces;

D General metal surfaces 34 m2 4,500.00 153,000.00

EXTERNAL WORK

Prepare and apply one thinned coat and two full


coats of weather guard paint on:

E 15mm Thick render to walls 827 m2 4,100.00 3,390,700.00

ELEMENT NR. 8 - DECORATIONS TOTAL CARRIED TO SUMMARY OF 7,421,834.20


BILL NR. 2

Page 2 / 11
Bill Nr.2 - Measured Works Godowns Admin block

Item Descriptions Amount (TZS)


BILL NR. 2 - MEASURED BUILDING WORKS

WAREHOUSE - SUMMARY

ELEMENT NR 1 - SUBSTRUCTURE 60,690,913.25

ELEMENT NR 2 - FRAME 21,512,278.25

ELEMENT NR 3 - WALLS 24,170,690.56

ELEMENT NR.4 - ROOFING 43,432,704.78

ELEMENT NR 5 - DOORS 4,406,000.00

ELEMENT NR 6 - WINDOWS 2,940,000.00

ELEMENT NR 7 - FINISHINGS 24,899,298.54

ELEMENT NR 8 - PAINTING AND DECORATIONS 7,421,834.20

TOTAL BILL NO. 2 - WAREHOUSE AND ADMIN BLOCKS CARRIED TO 189,473,719.58


GENERAL SUMMARY