Professional Documents
Culture Documents
RESIDENTIAL
APARTMENTS
FOR
ON
BILLS OF
QUANTITIES
December 2016
INDEX PAGE
PRELIMINARIES
Item Description
ELEMENT….i
PRELIMINARIES
A Sufficiency of Bid
The Contractor shall be deemed to have satisfied
himself before bidding as to the correctness and
sufficiency of his Bid for the Works and of the rates
and prices stated in the bills of Quantities which rates
and prices shall cover all his obligations under the
Contract and all matters and things necessary for the
proper completion and maintenance of the works
B Definition of Terms and Abbreviations
The Terms and Abbreviations used in this Bills of
Quantities Shall be interpreted as follows:-
The current British Standard of
shall
Specification published by the
“ B.S.” mean
British Standard Institution, Park
Street, London, W.1 England
shall
“ NO.” mean Number
shall
"L.M. mean Linear Meter
shall
"M" mean Linear Meter
shall
"SM" mean Square Meter
shall
"CM" mean Cubic Meter
The whole of the preceding
description except as qualified in
shall the section in which it occurs.
"Ditto" mean Where it occurs in brackets, it shall
mean the whole of the preceding
description which is contained
within the appropriate.
shall
"MS" mean Measured separately
shall
"BSM" mean Both sides measured
shall
"P.C" mean Prime cost
Exceeding 75mm but not exceeding
shall
150mm in girth, and all items
"75mm tomean
described in this manner shall be
similarly construed.
TOTAL CARRIED TO SUMMARY
PRELIMINARIES
Item Description
A Access to site and temporary roads
Means of access to the Site shall be agreed with the
Project Manager prior to the commencement of the
Works and the Contractor must allow for building any
temporary access roads for the transport of materials,
plant and workmen as may be required for the
complete execution of the Works including the
provision of temporary culverts, crossings, bridges or
any other means of gaining access.
Upon the completion of the Works, the Contractor
shall remove such temporary roads, culverts, bridges,
etc., and make good and reinstate all Works and 1,850,000
services disturbed to the satisfaction of the Project
Manager.
B Area to be occupied by the Contractor
The area of the Site which may be occupied by the
Contractor for use as storage and for the purpose of
erecting workshops, etc., shall be defined on the Site
by the Project Manager.
C Setting out
The Contractor shall set out the Works in accordance
with the dimension and levels shown on the Drawings
and shall be responsible for the correctness of all
dimensions and levels so set out by him and will be
required to amend all errors arising from inaccurate
setting out at his own cost and expense. In the event 5,000,000
of any error or discrepancy in the dimensions or
levels marked on the Drawings being discovered,
such errors or discrepancies shall be reported by the
Contractor to the Project Manager for his immediate
No Work shall be commenced by the Contractor until
attention.
he has received written instruction from the Project
Manager to adjust such discrepancies which may be
proved. Upon receipt of such instructions, the
Contractor shall thereupon be responsible for
accurate setting out of the Works, giving effect to the
adjustments necessary to comply with such
instructions, and no claim for extra expense or relief
based on any discrepancy or error in the dimensions
or levels shown on the Drawings may be made
Before any Work is commenced by the Sub-
thereafter.
Contractors or Specialised Firms, dimensions must be
checked on the Site and / or buildings and agreed
with the Contractor, irrespective of the comparative
dimensions shown on the Drawings. The Contractor
shall be responsible for the accuracy of such
dimensions.
TOTAL CARRIED TO SUMMARY 6,850,000
PRELIMINARIES
Item Description
A Existing services
Prior to the commencement of any Work, the
Contractor is to ascertain from the relevant
Authorities the exact position, depth and levels of all
existing electric cables, water pipes or other services
in the area and he shall make whatever provisions
may be required by the Authorities concerned for the 2,000,000
support and protection of such services. Any damage
or disturbance caused to any service shall be reported
immediately to the Project Manager and the relevant
Authority and shall be made good to their satisfaction
at the Contractors expense.
B Transport to and from the site
The Contractor shall include in his prices for the
transport of materials, workmen, etc., to and from the
Site of the proposed Works, at such hours and such
routes as are permitted by the Authorities
C Public and private roads, pavements
The Contractor will be required to make good, at his
own expense, any damage he may cause to the
present road surfaces and pavements during the
period of the Works. In particular all the existing
lawns, gardens, stormwater channels, hedges, fences
etc., which may be destroyed or damaged during the
progress of the Works are to be made good by the
Contractor to the approval of the Project Manager.
D Security of the works
The Contractor shall be entirely responsible for the
security of all the Works, stores, materials, plant,
personnel, etc., both of his own and Sub-Contractors’,
12,000,000
and shall provide all necessary watching, lighting and
other precautions as necessary as to ensure the
security and the protection of the public.
E Water for the works
The Contractor shall allow for providing all temporary
water supplies required for the works, including Sub-
Contract Works, together with all necessary storage
tanks and distribution systems for the same and must
allow for bearing all expenses incurred and paying for 18,000,000
all water consumed without charge to any Sub-
Contractor. Expenses in connection with Nominated
Sub-Contractors should be allowed for in the
attendance items under the relevant P.C. Sums.
No guarantee or warranty is given as to the
availability or suitability of water at the site.
TOTAL CARRIED TO SUMMARY 30,000,000
PRELIMINARIES
Item Description
A Electric light and power
The Contractor shall allow for providing all temporary
lighting and power supplies required for the works,
including Sub-Contract works, together with all
necessary distribution systems for the same and must
allow for bearing all expenses incurred and paying for 18,000,000
all current consumed without charge to any Sub-
Contractor. Expenses in connection with Nominated
Sub-Contractors should be allowed for in the
attendance
No guarantee itemsor
under the relevant
warranty P.C. Sums.
is given as to the
availability or suitability of power at the site.
B Telephone
The Contractor shall arrange for, provide and
maintain a telephone on the Site from the
2,800,000
commencement to the completion of the Contract and
shall pay all charges in connection therewith.
C Temporary Buildings for use by the Contractor
The Contractor shall at his own cost, supply and
erect all temporary buildings, sheds, mess rooms and
stores with floors at least 150mm above ground level.
No office, stores or other temporary buildings shall be
erected on Site without first obtaining the consent
from the Project Manager as to the type of temporary
building to be supplied and the position in which they
are to be erected.
D Sheds for storage of Materials
The Contractor shall provide and maintain on the
Site, ample weatherproof sheds for storage of cement
and other perishable materials and shall clear the 4,600,000
same away on completion and make good any
disturbed surfaces.
E Offices for the Project Manager
The Contractor shall provide, erect and maintain
where directed on Site approved weatherproof
lockup office for the sole use of the Project
Manager with a floor area not less than 30 square
metres. The office shall be constructed with
concrete or wooden floor and the walls and ceiling
internally are to be lined with fibreboard. Glazed
windows shall be provided of not less than 1
metre square area and the door shall have a
(i) strong lock or fastening. The office shall be
provided with artificial lighting and electric
power. The office is to be furnished with a table of
sufficient size to carry the drawings, complete
with drawers, and also stools and chairs. The
table should be adequate to sit at least 20
(Twenty) people. The Contractor shall also provide
Two (2 No) working desks and furniture for the
Project Manager. The contractor shall allow for
regular cleaning of the office.
BILL No 1
PRELIMINARIES
SUMMARY
SUBSTRUCTURE
Item Description Unit Qty
ELEMENT…ii
SUBSTRUCTURE
ALL PROVISIONAL
The work in this element
includes all works up to and
including the ground floor
slab
EARTHWORKS
Allow for maintaining and
upholding sides of excavation:
A ITEM 1 800,000 800,000
clear off all fallen material,
rubbish
Allow for keeping the whole of
B the excavation free from general ITEM 1 800,000 800,000
water
Excavate oversite average
C 150mm deep to remove vegetable SM 508 8,500 4,318,000
top soil; remove from site
Mass excavation atleast 0.3m
D CM 146 26,000 3,796,000
deep to reduce levels.
Excavate column bases not
E exceeding 1.5 meters deep from CM 125 29,500 3,687,500
reduced level.
Excavate for plinth wall
G foundations not exceeding 1.5 CM 500 31,000 15,500,000
meters deep from reduced level.
Extra over excavations for
H CM 10 35,000 350,000
excavating in rock.
Return fill and ram selected
I excavated material around CM 286 8,500 2,431,000
foundations.
Load from spoil heaps, spread
and level surplus excavated
J materials around the building CM 0
including compacting in layers
not exceeding 150mm thick
Load and cart away surplus
K CM 143 29,500 4,218,500
excavated material from site.
200mm Thick bed of hand packed
L stone base, well rolled and SM 263 36,000 9,468,000
compacted.
50mm thick stone dust blinding
M SM 263 16,000 4,208,000
over surfaces of hardcore
Insecticide treatment to surfaces
of hardcore, top of foundation
N SM 263 8,000 2,104,000
walling, bottom and sides of
excavation.
0
TOTAL CARRIED TO
###
COLLECTION
TOTAL CARRIED TO
###
COLLECTION
COLLECTION
Total brought forward from Page
51,681,000
3/1/1
Total brought forward from Page
###
3/1/2
Total brought forward from Page
45,302,000
3/1/3
Subtotal ###
Add Vat 18% ###
WALLING AND
FRAME
Rate
Item Description Unit Qty
(UGX)
ELEMENT …iii
WALLING AND FRAME
SUB ELEMENT ...1
GROUND FLOOR TO FIRST FLOOR
SLAB
R.C. FRAME
CONCRETE WORK
VIBRATED REINFORCED
CONCRETE CLASS 25; 20mm
AGGREGATE : in
A (230 x 230mm) Columns CM 6 550,000 3,300,000
B (230 x 500mm) Beams CM 76 550,000 ###
Moulded concrete copping (400mm
C LM 34,550
girth)
D Do to (230mm girth) LM 24,550
150mm Thick horizontal solid
E SM 46 82,500 3,795,000
suspended slab
HOLLOW BLOCK SUSPENDED
FLOOR comprised of 100mm wide
Ribs, 50mm thick topping
0
concrete class 25: hollow maxpans
blocks 380 x 300 x 150 mm high
at 480 mm centre:
F 200mm thick suspended slab SM 217 154,550 ###
STEEL REINFORCEMENT as
described including cutting to
length, bending, hoisting and
fixing and including all necessary
tying wire and spacing blocks
MILD STEEL ROUND BARS TO BS
4449
8mm - 10mm Diameter bars in
G KG 2,280 5,000 ###
columns and beams
HIGH TENSILE RIBBED BARS TO
BS 4449
12 - 25mm Diameter bars in columns,
H KG 9,576 5,000 ###
beams and slab
STEEL FABRIC REINFORCEMENT
TO BS 4483 as described
No. A142 Fabric Mesh reinforcement
I weighing 2.22 kg. per square meter SM 414 10,500 4,347,000
fixed in slab
FORMWORK TO:
J Horizontal soffit's of suspended slab SM 263 25,000 6,575,000
K Sides and soffit's of beams SM 769 18,500 ###
L Vertical sides of columns SM 105 18,500 1,942,500
Vertical Edges of slabs 175-225mm
M LM 43 10,500 451,500
high
Moulded concrete copping (400mm
N LM 9,500
girth)
O Do to (230mm girth) LM 6,500
TOTAL CARRIED TO SUB
###
COLLECTION
Rate
Item Description Unit Qty
(UGX)
STAIRCASE
CONCRETE WORK
VIBRATED REINFORCED
CONCRETE CLASS 25; 20mm
AGGREGATE : in
A Staircases CM 8 550,000 4,400,000
180mm Thick horizontal suspended
B SM 8 96,250 770,000
landings
STEEL REINFORCEMENT as
described including cutting to
length, bending, hoisting and
fixing and including all necessary
tying wire and spacing blocks
MILD STEEL ROUND BARS TO BS
4449
C 8mm Diameter bars KG 0 5,000
HIGH YIELD SQUARE TWISTED
BARS TO BS 4449
D 10 - 16mm Diameter bars KG 454 5,000 2,270,000
FORMWORK to:-
E Soffit's of suspended landing SM 8 18,500 148,000
F Sloping soffit's of staircase SM 14 19,500 273,000
G Risers of steps 75-150mm high LM 49 5,500 269,500
H Edges of landing 150 - 225mm high LM 11 5,500 60,500
Open string edge of staircase 225-
I 300mm (extreme) including cutting to LM 14 8,500 119,000
profile of treads and risers.
TOTAL CARRIED TO COLLECTION ###
Rate
Item Description Unit Qty
(UGX)
WALLING
PRECAST CONCRETE CLASS 20;
20mm AGGREGATE : finished fair
on all exposed surfaces including
bedding and jointing in cement
sand (1:3) mortar
A 200 x 200mm Lintols LM 0 25,900
B 150 x 200mm Lintols LM 0 19,500
BLOCK WORK
Solid Concrete blockwork jointed
and pointed in cement sand (1:3)
mortar with and including hoop
iron wall ties every alternative
course : in
C 230mm Thick walls SM 1,933 54,600 ###
D 150mm thick SM 39,000
DAMP PROOF COURSE OF
BITUMEN FELT TO B.S 743 Type A
with 150mm laps including cement
and sand (1:3) leveling bed
E 230mm Wide LM 660 2,500 1,650,000
F 150mm wide LM 2,000
COLLECTION
Total carried forward from Page 3/1/1
###
- R.C. FRAME
Total carried forward from Page 3/1/2
8,310,000
-STAIRCASE
Total carried forward from Page 3/1/3
###
-WALLING
TOTAL CARRIED TO
###
COLLECTION
TOTAL CARRIED TO
###
COLLECTION
COLLECTION
Total carried forward from Page
###
3/2/1 -R.C. FRAME
Total carried forward from Page
8,986,000
3/2/2 -STAIRCASE
Total carried forward from Page
###
3/2/3 -WALLING
TOTAL CARRIED TO ELEMENT …
###
iii SUMMARY
Item Description Unit Qty
ELEMENT …iii
WALLING AND FRAME
SUB ELEMENT …4
THIRD FLOOR TO ROOF LEVEL
R.C. FRAME
CONCRETE WORK
VIBRATED REINFORCED
CONCRETE CLASS 25; 20mm
AGGREGATE : in
A (230 x 230mm) Columns CM 6 550,000 3,300,000
B (230 x 500mm) concrete gutter CM 10 550,000 5,500,000
Moulded concrete copping (400mm
C LM 0
girth)
D Do to (230mm girth) LM 0
150mm Thick horizontal solid
E SM 34 86,000 2,924,000
suspended slab
F (230 X 300mm) Ring Beams CM 76
MOULDED CONCRETE GUTTER
as described;
Water gutter (internal size 600 x
G 150mm high) moulded on exposed LM 154,550
surfaces (200mm girth)
STEEL REINFORCEMENT as
described including cutting to
length, bending, hoisting and
fixing and including all necessary
tying wire and spacing blocks
MILD STEEL ROUND BARS TO
BS 4449
H 8 - 10mm Diameter bars KG 2,280 5,000 ###
HIGH TENSILE RIBBED BARS TO
0
BS 4449
I 12 - 25mm Diameter bars KG 7,855 5,000 ###
STEEL FABRIC
REINFORCEMENT TO BS 4483 as
described
No. A142 Fabric Mesh reinforcement
J weighing 2.22 kg. per square meter SM 10,500
fixed in slab
FORMWORK TO:
K Horizontal soffit's of suspended slab SM 34 25,000 850,000
L Sides and soffit's of beams SM 815 18,500 ###
M Vertical sides of columns SM 105 18,500 1,942,500
N Vertical Edges of slabs 600mm high LM 20 10,500 210,000
O Moulded concrete gutter LM
P Do to (230mm girth) LM
TOTAL CARRIED TO SUB
###
COLLECTION
TOTAL CARRIED TO
###
COLLECTION
COLLECTION
Total carried forward from Page
###
3/4/1 -R.C. FRAME
Total carried forward from Page
0
3/4/2 -STAIRCASE
Total carried forward from Page
###
3/4/3 -WALLING
TOTAL CARRIED TO ELEMENT …
###
iii SUMMARY
PAGE AMOUNT
SUB-ELEMENT DESCRIPTION
NO (UGX)
ELEMENT…iii
SUMMARY
SUBTOTAL 759,023,100
ADD VAT 18% 136,624,158
TOTAL ELEMENT…iii CARRIED
895,647,258
TO BILL A -SUMMARY
ELEMENT...iv
ROOF
Item Description Unit Qty
ELEMENT…iv
ROOF CONSTRUCTION, COVERING
AND RAINWATER DISPOSAL
Pressure impregnated treated sawn
pine timber
A 75 x 100mm Wall plate LM 172 6,500 1,118,000
B 50 x 50mm Batterns LM - 0
C 50 x 150mm Principal Rafters LM 320 4,500 1,440,000
D 50 x 150mm common Rafters LM - 0
E 50 x 100mm Struts and Tensioners LM 470 5,500 2,585,000
F 50 x 150mm Tie beams LM 305 6,000 1,830,000
G 50 x 150mm Under purlins LM 270 6,000 1,620,000
H 50 x 150mm Ridge pieces LM 140 6,000 840,000
I 50 x 150mm Valley pieces LM 65 6,000 390,000
ROOF COVERING 0
J Gauge 28 Vrsatile roofing sheeets SM 360 46,000 ###
K Ditto but ridge cappings LM 90 18,000 1,620,000
Pre-painted Galvernised iron sheet
L LM 56 18,500 1,036,000
valley pieces gauge 28
RAIN WATER DISPOSAL
WATERPROOFING
WATER PROOF CEMENT SAND
SCREED (1:4) finished to receive
waterproofing membrane
M 25mm Thick to flat roofs; laid to falls SM
20mm Thick around gutters to receive
N SM 0
zinc alum flat sheets
WATER PROOF CEMENT SAND
SCREED (1:4) finished to receive
tiles
O 25mm Thick to flat roofs; laid to falls SM
TOTAL CARRIED TO COLLECTION ###
COLLECTION
Total carried forward from Page 5 / 1 ###
Total carried forward from Page 5 / 2 3,346,000
SUBTOTAL ###
ADD VAT 18% 5,829,300
TOTAL CARRIED TO ELEMENT
###
SUMMARY
ELEMENT…v
FINISHES
Item Description Unit Qty
ELEMENT…v
FINISHES
SUB-ELEMENT-1
INTERNAL FINISHES
WALL FINISHES
CEMENT AND SAND (1:4)
PLASTER finished to receive
wall tiles
20mm Thick wall plaster to receive
A SM 5,175 13,000 67,275,000
matt tiles
ELEMENT…v
FINISHES
SUB-ELEMENT- 2
FLOOR FINISHES
25MM THICK CEMENT AND
SAND (1:4) SCREEDS finished to
receive floor finishes;
A General floor surfaces SM 789 15,000 11,835,000
ELEMENT…v
FINISHES
SUB-ELEMENT - 3
CEILING
INTERNAL LIME PLASTER,
FIRST COAT of cement lime
and sand (1:2:9) second coat
of cement, lime putty and sand
(1:1:6) steel trowelled as
described
20mm Two coat work to soffit's of
A SM 789 13,000 10,257,000
suspended slabs
B Do. But Cornice 200mm girth LM 1,235 4,500 5,557,500
12MM THICK GYPSUM
BOARDS nailed on (50 x
100mm) treated timber joists
and branderings at 600mm
centers both ways including
the necessary molded gypsum
cornice
C Suspended ceilings SM 0
D Ditto but gypsum cornice LM 0
PREPARE AND APPLY THREE
COATS first matt emulsion
paint
E Steel trowelled plastered soffit's. SM 789 1,300 1,025,700
F Gypsum ceiling SM 0 0
G Do. But Cornice 200mm girth LM 1,235 4,500 5,557,500
TOTAL CARRIED TO
22,397,700
SUMMARY
Item Description Unit Qty
ELEMENT…v
FINISHES
SUB-ELEMENT - 4
STAIRCASE FINISHES
CEMENT AND SAND (1:4)
SCREEDS finished to;
A Risers LM 94 4,500 423,000
B Treads LM 92 4,500 414,000
C Landings SM 15 1,300 19,500
D Hall way SM 0
E Sides of landings and open strings LM 20 4,500 90,000
100 x 10mm sloping skirting; cut
F to profile LM 20 4,500 90,000
G 100 x 10mm TERRAZO:
POLISHED horizontal skirting
FIRST LM 0
COAT OF 25MM THICK
WATERPROOFED CEMENT
AND SAND (1:3) SCREED,
second coat of 25mm thick
coloured cement and approved
marble aggregates (1:2;5),
including 25 x 3mm pvc
dividing strips at 1200mm
centres : in
H Risers LM 94 23,000 2,162,000
I Treads LM 92 23,000 2,116,000
J Landings SM 15 105,000 1,575,000
K Hall way SM 0 0
L Sides of landings and open strings LM 20 23,000 460,000
100 x 10mm sloping skirting; cut
M to profile LM 20 23,000 460,000
N 100 x 10mm skirting LM 0
INTERNAL LIME PLASTER,
FIRST COAT of cement lime
and sand (1:2:9) second coat of
cement, lime putty and sand
(1:1:6) steel trowelled as
described
O Slopping soffits of stairs SM 29 13,000 377,000
P Soffits
PREPARE of landing
AND APPLY THREE SM 15 13,000 195,000
COATS first matt emulsion
paint 0
Q Slopping soffits of stairs SM 29 12,000 348,000
R Soffits of landing SM 15 12,000 180,000
TOTAL CARRIED TO
COLLECTION 7,873,000
TOTAL CARRIED TO
COLLECTION 3,990,000
COLLECTION
Total carried forward from Page
6/4 7,873,000
Total carried forward from Page
6/5 3,990,000
TOTAL CARRIED TO SUMMARY 11,863,000
Item Description Unit Qty
ELEMENT…v
FINISHES
SUB-ELEMENT -.4
EXTERNAL FINISHES
CEMENT AND WASHED SAND
(1:3) RENDER trowelled
smooth
20mm Thick wall plaster to
A SM 887 15,000 13,305,000
external walls
Ditto but to Plinth walls SM 51 15,000 765,000
B Ditto but to Parapet walls SM 68 15,000 1,020,000
BALUSTRADING
1000mm high comprising of:
75mm diameter x 6mm thick mild
steel hollow section railing;
welded to 6mm thick mild steel
bearer balustrade cut to shape
cast into concrete at 450mm
E LM 100 86,000 8,600,000
centers; 25mm diameter CHS
metal intermediate rails; 12mm
diameter steel solid section
vertical post at 115mm centres all
painting and decorations: to
Architect's detailed drawings No.
TOTAL CARRIED TO SUMMARY
38,077,000
AMOUNT
SUB-ELEMENT DESCRIPTION PAGE NO
(UGX)
SUMMARY
DOORS AND
WINDOWS
6/1
Amount
Item Description Unit Qty
(UGX)
ELEMENT…vi
DOORS AND WINDOWS
SUB-ELEMENT - 1
DOORS
ALUMINIUM DOORS
PURPOSE MADE DOORS,
NATURAL ANODISED ALUMINIUM
SECTION; aluminium door frame;
6.5mm thick laminated clear plate
glass and glazing; iron mongery
and accessories as per Architect's
detailed drawing No. WSC/01
Door size 4000 x 2500mm high overall
comprising of 300mm high fixed
A louvered vent,double glazed sliding NO 6 2,800,000 ###
pannel, l with and including
ironmongery
Door size 2800 x 2800mm high overall
comprising of 300mm high fixed
B louvered vent,double glazed sliding NO 12 2,100,000 ###
pannel, l with and including
ironmongery
45mm THICK HARDWOOD DOORS
COMPLETE WITH WROT
MAHOGANY FRAMES AND
LININGS selected, treated and
kept clean; INCLUDING LOCKS
AND FURNITURE WHERE
APPLICABLE "UNION"
MANUFACTURE; all to Architect's
detailed drawings
Door D1 Size 2400 x 2350mm high
overall, patially glazed panelled with
C NO 1 1,800,000 1,800,000
and including 300mm high fixed
louvred vent,
TEEL BURGLARS
PURPOSE MADE DOOR
BURGLARS; mild steel as per
Architect's detailed drawing No.
WSC/01
Door D1 Size 4000 x 2500mm high
D NO 6 850,000 5,100,000
overall
E Door size 2800 x 2800mm high overall NO 12 730,000 8,760,000
TOTAL CARRIED TO COLLECTION ###
6/2
Amount
Item Description Unit Qty
(UGX)
45mm THICK SOLID CORE FLUSH
DOORS COMPLETE WITH WROT
MAHOGANY FRAMES AND
LININGS selected, treated and
kept clean; INCLUDING LOCKS
AND FURNITURE WHERE
APPLICABLE "UNION"
MANUFACTURE; all to Architect's
detailed drawings
Door D05 Size 1200 x 2500mm high
F overall comprising of 300mm high NO 6 860,000 5,160,000
fixed louvered vent
G Ditto size 900 x2700mm high overall NO 36 750,000 ###
H Ditto size 800 x 2200mm high overall NO 12 750,000 9,000,000
COLLECTION
SUMMARY
1 DOORS 6/ 1 / 1 98,820,000
2 WINDOWS 6/ 2 / 1 64,440,000
JOINERY &
FITTINGS
7/1
Rate Amount
Item Description Unit Qty (UGX) (UGX)
ELEMENT…vii
JOINERY & FITTINGS
SUB-ELEMENT -1
BUILT IN WARDROBES
complete with partitions
shelves and shurtters all
made in 12mm thick MDF
boards with and including
all the necessary
ironmongery as described;
Overall size 1150 x 2100mm
A high
Overall size 900 x 2100mm NO 6 1,060,000 6,360,000
B high
Overall size 1300 x 2100mm NO 6 950,000 5,700,000
C high NO 24 1,300,000 31,200,000
TOTAL CARRIED TO
SUMMARY ###
7/2
Amount
Item Description Unit Qty (UGX)
KITCHEN UNITS comprised
of granite worktop, 12mm
thick MDF boards
partitions, shelves and
shutters complete with all
the necessary ironmongery
as described;
Overall size 9400 x 1000mm
A high NO 6 1,800,000 10,800,000
SUMMARY
ELECTRICAL
INSTALLATION
8/0
Rate Amount
Item Description Unit Qty
(UGX) (UGX)
Electrical Drawings E01 -E19 ` SPL CONSULTING ENGINEERS
ALL SPECIFIED MATERIALS -
GENERAL NOTES
8/1
Rate Amount
Item Description Unit Qty
(UGX) (UGX)
vii) All lighting fittings shall be as per
Specifications and Drawings with control
gear compartible with 240V/50Hz. All
lighting fittings are to be approved by the
Electrical Engineer prior to installation.
8/4
Rate Amount
Item Description Unit Qty
(UGX) (UGX)
LIGHTING FITTINGS
8/6
Rate Amount
Item Description Unit Qty
(UGX) (UGX)
WIRING ACCESSORIES:
A Lighting points:
All wiring of lighting points are to be
connected complete and ready from 16A SP
miniature circuit breakers, using 3x1.5mm
sq. PVC-Insulated single core copper cables
drawn in uPVC flush installed
conduits/trunking, through switches, and as
per drawings.
No. 16 100,000 1,600,000
B Power points:
All wiring of all power points are to be
connected complete and ready from 32A SP
miniature circuit breakers, using 3x2.5mm
sq. PVC-Insulated single core copper cables
in ring circuit, drawn in trunking/conduits,
as per drawings.
No. 16 0
Main Collection
MECHANICAL
INSTALLATION
9/0
Rate Amount
Item Description Unit Qty
(UGX) (UGX)
MECHANICAL INSTALLATION-BILLS OF QUANTITES SPL CONSULTING ENGIN
TYPICAL APARTMENT
INTERNAL WATER SUPPLY AND DISTRIBUTION
All Cold and Hot Water piping shall be
PPR pipe PN25 complete with elbows,
sockets, tees, adapters and all associated
fixing accessories.
D Isolating Valves
40mm No 4 76,000 304,000
A WC Suite
Close couple WC suite as Roca or equal No 3 800,000 2,400,000
and approved, in white colour, vitreous
china to BS3402 with horizontal outlet,
6Litre Cistern with dual flashing
Mechanism, complete with seat and seat
cover and all associated fitings
C SHOWER
Shower mixer mixer with Headshower No 3 600,000 1,800,000
modern Spray 150mm diameter rose,
450mm long Shower arm (only the
mixer)
E KITCHEN SINK
Stainless steel kitchen sink, single bowl, No 1 800,000 800,000
single drain 900 x 500 complete with
40mm Bottlle trap, 15mm Kitchen Sink
Mixer Tap as logics Kitchen monoblock
mixer and all fixing accessories.
D Gate Valves
40mm No 1 74,100 74,100
LIFT SHAFT
ELEMENT…xi
EXTERNAL WORKS
10/1
Rate Amount
Item Description Unit Qty
(Ush) (Ush)
ELEMENT…x
EXTERNAL WORKS
SUB-ELEMENT -1
ACCESS DRIVE WAYS /
PARKING
EARTH WORKS as described;
Shape to level and Compact
A formation to 95% modified AASHO SM 700 33,000 ###
to receive sub-base course
Imported gravel filling to make up
levels and to form sub base
B deposited in 300 mm thick layers CM 105 28,000 2,940,000
and compacted with a 10 - tone
roller to 95% MDD (Provisional)
Base course layer of imported
gravel on formation stabilised
C with 6% lime compacted with a CM 41 78,000 3,198,000
10-tonne roller to falls and
cambers.
PRECAST CONCRETE
"CABROWORKS" heavy duty
paving blocks or any other
equal and approved : quad
block pattern.
80 mm Thick heavy duty concrete
block size 205 x 110 mm laid on
falls and including 50 mm thick
D SM 700 86,000 ###
sand bed, allow for compaction,
rolling and vibration, spread and
brush into joints and compact.
PRECAST CONCRETE Class
"20" as described finished fair
on all exposed surfaces
including bedding, jointing and
pointing in cement and sand
(1:3) mortar
250 x 125 mm Splayed kerb to BS
340 including 125 x 100 mm
channel on and including 100mm
E thick concrete Class 20 mass LM 130 15,500 2,015,000
concrete bed and haunching,
including all necessary excavation,
formwork and disposal.
ROAD MARKING
Prepare surfaces and apply
three coats of approved road
marking
Surfaces ofpaint: to
road kerbs 200 -
F LM 130 8,500 1,105,000
300mm girth
Roads and parking 75 to 150mm
G LM 24 5,500 132,000
girth
TOTAL CARRIED TO ELEMENT
###
…x SUMMARY
10/2
Rate Amount
Item Description Unit Qty
(Ush) (Ush)
EXTERNAL WORKS
SUB-ELEMENT -2
BOUNDARY WALL AND GATES
BOUNDARY WALL
Allow for labour and material for
construction of boundary walling
2200mm high overall above
existing ground level comprising;
200mm Thick solid Rock face (both
sides) concrete block walls
(1000mm above ground) with 250
x 100mm thick weathered and
throated coping, 400 x 400mm
concrete columns 2200mm high
above ground at 3200mm centres;
1200 mm high painted metal grille
to a pattern comprising
25x25x3mm thick SHS vertical
A LM 150 145,000 21,750,000
members spiked at the top at
200mm centres, welded to 2no. 50
x 50 x 3mm Angle bars cast into
concrete columns; including razor
wire; sub walling - 1000mm high
below ground level in 200mm thick
solid concrete blocks; with and
including 600 x 200mm reinforced
concrete class 20 strip footing :
600 x 600 x 200mm thick
reinforced concrete column bases;
300 x 300 x 100mm weathered and
throated coping to columns; to
Architect detail drawing
GATE
Mild steel welded grill / sliding
gate to parking (overall size 8000
B x 3500mm high) complete with No. 1 3,800,000 3,800,000
sliding mechanism, hinges and all
the necessary locking system
TOTAL CARRIED TO
###
ELEMENT…x SUMMARY
10/3
Rate Amount
Item Description Unit Qty
(Ush) (Ush)
EXTERNAL WORKS
SUB-ELEMENT -3
LANDSCAPING
A PROVISIIONAL SUM
Allow a PROVISIONAL SUM OF
UGX.10,000,000 (UGANDA
SHILLINGS TEN MILLIONS ) for
the necessary LAND SCAPING
WORKS INCLUDING ;Digging out
to breaking existing ground and all
weeds and roots, supply, spread
B ITEM 1 ### ###
and level 300mm black imported
soil and mix with manure and
general fertilizer including
planting approved grass tufts at
100mm centres in each direction
and trees / thrubs , water the until
established.
TOTAL CARRIED TO SUMMARY ###
PAGE
ELEMENT DESCRIPTION AMOUNT (UGX)
NO
EXTERNAL WORKS
SUMMARY
1 DRIVE WAYS & PARKING 10 / 1 92,690,000
2 BOUNDARY WALL 10/2 25,550,000
3 LANDSCAPING 10 /3 10,000,000