Removals and Demolitions;

Demolish careful existing Boundary wall and remove debris from site and make good of
A SM 94 15,000 1,410,000
disturbed surfaces.

B Site hoarding to the site SM 24 75,000 1,762,500

Shapoting exiting fance angle SUM 1 250,000 250,000

TOTAL CARRIED TO SUMMARY 3,422,500

BILL NO.2

Excavation

A Excavation foundation trench 1.1m deep from reduced level n.e 1.5m deep CM 25.85 12,000 310,200

D Extra over for excavation of existing rocks CM 2 25,000 50,000

Load from spoil heaps, spread and level surplus excavated materials where directed on site including
compacting in layers not exceeding 150mm thick using 15 ton vibrating roller to 95% MDD to Engineer's CM 6 35,000 210,000
F approval

G 200mm Thick concrete blinding layer under strip foundations CM 2.82 600,000 1,692,000

Hardcore wall 400mm thick up to ground level SM 18.8 95,000 1,786,000

Ground beam 200mm x 300mm concrete class 25 CM 1.88 600,000 1,128,000

T10mm TMT steel bar 4 pcs with T8 mm rings 200mm c/c KG 101.9 5,500 560,450

Formwork for beam SM 18.8 30,000 564,000

Block Work

2
Solid concrete block work 2.8n/mm with 25mm wide strip of 2mm thick hoop iron into
alternate horizontal joints in the wall centre; bedded and jointed in cement and sand
(1:4) mortar in;

I 200mm Thick walls solid blocks SM 64.5 85,000 5,482,500

J 400 X 400 solid block columan NO 6 180,000 1,080,000

Plastering; -

E Scap-off worn-out plaster and apply new plaster in cement sand 1:3 to walls SM 150.6 23000 3,463,800

I Plaster copping to the top of the boundary wall LM 32 35,000 1,120,000

Re-fixing exitng fence on boundary wall SUM 1 450,000 450,000

TOTAL CARPENTRY CARRIED TO SUMMARY 17,896,950


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
(UGX) (UGX)

SUMMARY
1 Demolitions and Removals 3,422,500

2 Civil Works 17,896,950

SUB - TOTAL 1 21,319,450

ADD: VAT 18% 3,837,501

TOTAL FOR CONTRACT (WITHOUT VAT) 25,156,951

1 VALIDITY
The above quotation is only valid for 15 day

2 PAYMENT TERMS
Signed quotation/ contract/ local purchase order (LPO)
50%Advance payment of contract value on confirmation
30% Payment on 50% completion of the work
15% Payment on 100% completion of the work
5 % Payment affter the 3 month completion of the work

3 INSTALLATION AT SITE
Water, storage, security shall be provided by client
Aproved parmison letter for the work shall be provided by client
If any recqurd KCCA document provaided by the clint

we thanks you once again for the opportunity to provide you with a quotation for the above mentioned project.
we hope that the above mentioned criterias and terms meet with your approval and we look froward to get further
instrutions from you to work in this project and others in future.

Yours Faithfully,

Kishor Kerai
Managing Director
Indicon Ltd

CLIENT CONFIRMATION

I confirm the above mentioned quotation and terms

Client's name & signature: ….................................................................

Date: ….....................

You might also like