INDICON LIMITED

GENERAL BUILDING & CIVIL ENGINEERING CONTRACTORS.


P.O Box 28331, KAMAPALA UGANDA
indiconltd27@gmail.com
Contacts : +256 750 992277, +256 755 834847

DATE: 19.08-2021

TO: BRITANIA

Ref: WORK SCHEDULE FOR BOUNDARY WALL

STATING ENDING
Sir. NO DESCRIPTION OF WORK DAYS Remark
DATE DATE

1 Fixing Site hoarding 23.08.2021 23.08.2021 1


2 Removals and Demolitions; 25.08.2021 27.08.2021 3
3 Shapoting Exiting fence 25.08.2021 25.08.2021 1
4 Exawation foundation 26.08.2021 27.09.2021 2
200mm Thick concrete casting for strip
5 28.08.2021 28.08.2021 1
foundations
6 Building Hardcore wall 400mm thick 30.08.2021 02.09.2021 3
7 Steel fixing & formwork for beam 03.09.2021 05.09.2021 3
8 Building block wall 06.09.2021 08.09.2021 3
9 Formwork for Column 09.09.2021 10.09.2021 2
10 Column casting 10.09.2021 11.09.2021 2
11 Plaster work 11.09.2021 14.09.2021 4
12 Rafcating 14.09.2021 14.09.2021 1
13 Copping 15.09.2021 16.09.2021 2
14 Painting work 17.09.2021 18.09.2021 2

Yours Faithfully,

Kishor Kerai
Managing Director
Indicon Ltd

CLIENT CONFIRMATION

I confirm the above mentioned quotation and terms

Client's name & signature: ….................................................................

Date: ….....................
INDICON LIMITED
GENERAL BUILDING & CIVIL ENGINEERING CONTRACTORS.
P.O Box 28331, KAMAPALA UGANDA
indiconltd27@gmail.com
Contacts : +256 750 992277, +256 755 834847
Serial No. 003

DATE: 11.08-2021

TO: BRITANIA

Ref: QUOTATION FOR HARDCORE WALL

RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
(UGX) (UGX)

BILL NO.1
1 QUOTATION:

Removals and Demolitions;

Demolish careful existing Boundary wall and remove debris from site and make good of disturbed
A SM 59 15,000 877,500
surfaces.

TOTAL CARRIED TO SUMMARY 877,500

2 BILL NO.2

Excavation

A Excavation foundation trench 0.6m LM 3.9 15,000 58,500

B Extra over for excavation of existing rocks NO 1 25,000 25,000

Load from spoil heaps, spread and level surplus excavated materials where directed on site including
compacting in layers not exceeding 150mm thick using 15 ton vibrating roller to 95% MDD to Engineer's CM 6 35,000 210,000
C approval

D 200mm Thick concrete blinding layer under strip foundations LM 13 66,000 858,000

Hardcore wall 400mm thick with column & beam SM 59 115,000 6,727,500

TOTAL CARPENTRY CARRIED TO SUMMARY 7,879,000


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
(UGX) (UGX)

SUMMARY
1 Demolitions and Removals 877,500

2 Civil Works 7,879,000

SUB - TOTAL 1 8,756,500

ADD: VAT 18% 1,576,170

TOTAL FOR CONTRACT (WITHOUT VAT) 10,332,670

1 VALIDITY
The above quotation is only valid for 15 day

2 PAYMENT TERMS
Signed quotation/ contract/ local purchase order (LPO)
50%Advance payment of contract value on confirmation
30% Payment on 50% completion of the work
15% Payment on 100% completion of the work
5 % Payment after the 3 month completion of the work

3 INSTALLATION AT SITE
Water, storage, security shall be provided by client
Approved permission letter for the work shall be provided by client
If any recqurd KCCA document provided by the client

we thanks you once again for the opportunity to provide you with a quotation for the above mentioned project.
we hope that the above mentioned criterias and terms meet with your approval and we look forward to get further
instructions from you to work in this project and others in future.

Yours Faithfully,

Kishor Kerai
Managing Director
Indicon Ltd

CLIENT CONFIRMATION

I confirm the above mentioned quotation and terms

Client's name & signature: ….................................................................

Date: ….....................