This agreement is made on this Saturday of 25/09/2021
(First Party & Owner)
Mr.Salah Jamah Khalifa Juma Al Qazi _
M/s. Alton Contracting LLC (Second Party & Contractor)
Where the client desires to get Construction of Majlis Block, Constructed at: Plot No.3250437 Zabeel First, Dubai,UAE
ALL AS PER FOLLOWING CLAUSES
TERMS & CONDITIONS:
1. Completion period shall be 6 months + 15 days Mobilization (Practical completion) from the date of final approved drawings/building permit approval from DM or site demarcation whichever is later. 2. Total cost of the construction shall be Dhs. 352,000- (Dhs. Three Hundred Fifty Two Thousand only) which shall be paid to the Contractor according to the progress of work certified by the Consultant. 3. An advance payment of 20% of the contract value shall be paid on signing the Contract Agreement against Company Guarantee Cheque. 4. Remaining payment shall be made as per the work progress on site payable within 14 days of submitting the running bill. 7 Days for Consultants approval and 7 Days for Client to release the Payment. 5. Release of First 5% retention on receiving DM BCC and 5% Final retention on receiving DEWA connections against company guarantee Cheque. 6. Building permit fees, Permanent connection charges for Electrical, Plumbing, Drainage, Telephone and Transformers are excluded. 7. Shoring, Dewatering, any kind of temporary support, soil improvement works are excluded from our scope of works 8. Hard, soft landscaping and irrigation works including sweet soil excluded from our scope of works. 9. Transformers, RMUs, HV Cable, main incoming cable to transformer & Rerouting of any existing cables is excluded. 10. Any subcontractor or provisional sum item removed or supplied or added to the contract by the Client shall be charged 10% as builder’s work, Contractor’s over heads and profits. 11. Any type of changes or additional works shall be carried out only on receiving the drawings and written approval of Variation in form of time and cost from the Client and Consultant, no verbal instructions or changes shall be carried out on site during the time of execution. 12. All the instructions either Client or Consultant shall send by mail to the Main Contractor. No site instructions shall be carried out without approval of Client and Consultant. 13. PRICE ESCALATION clause is applicable for all the items described in the Bill of Quantities. 14. Our prices are based on preliminary tender drawings and Specification provided by the Consultant and any changes in DM approved drawings shall be charged extra as variation. 15. 5 % VAT Amount should be paid by Client to the Contractor for every monthly invoice. 16. On non-completion of the work within stipulated period of completion, the contractor would be liable for penalty charges at the rate of Dhs.300 per day for the owner. The maximum limit of penalty will be 5% of contract amount.
Owner Name & Signature
Mr. __________________
Sign :
Contractor Name & Signature
M/s. Alton Contracting LLC Project PROPOSED MAJLIS BLOCK Consultant AL SHAIK MUBARAK Owner SALAH JAMAH KHALIFA JUMA AL QAZI Contractor ALTON CONTRACTING Plot No. 3250437-ZABEEL FIRST Date 25-09-2021
Sr. Description of work Quantity Unit Rate Amount
1 Mobilization Excavation and Backfilling
1.1 Mobilization,Site Office & Services. 1 Ls 12,000 12,000 1.2 Excavation 298 M3 14 4,172 19,172 1.3 Back Filling 214 Ls 14 3,000 2 Sub-Structure (Villa+S.B) 2.1 Pcc (Footing & Tie.Beam) 12 M3 600 7,200 2.2 Rcc for Footings 18 M3 1,050 18,900 2.3 Rcc for Neck Columns 2 M3 1,100 2,200 2.4 Rcc for Tie Beams 9 M3 1,050 9,450 59,005 2.5 Rcc for Flooring (Grade Slab) 15 M3 750 11,250 2.6 Wall Footings 2 M3 750 1,500 2.7 Solid Block 49 M2 95 4,655 2.8 Polythene Sheets + Anti Termite + Sub-Structure Waterproofing 1 Ls 3,850 3,850 3 Super Structure 3.1 Columns (G.F & F.F & R.F) 7 M3 1,100 7,700 3.2 First Floor Slab & Drop Beams Villa + S.Block 38 M3 1,050 40,000 3.3 RCC for Arches & Lintels 1 Ls 1,500 1,500 56,650 3.4 Parapet concrete 3 M3 1,050 3,150 3.5 Parapet block 43 M2 100 4,300 4 Block Works 4.1 External Thermal Block 175 M2 100 17,500 29,660 4.2 Internal Block 152 M2 80 12,160 5 Plaster Works 5.1 External Plaster 282 M2 32 9,024 5.2 Villa Internal Plaster (Walls) 484 M2 26 12,584 21,608 5.3 Villa Internal Plaster (Ceiling) 0 Ls 0 By owner 6 Electrical Works 6.1 Electrical Works 1 Ls 35,000 35,000 35,000 7 Plumbing Works 7.1 All External & Internal Works 1 Ls 23,000 23,000 7.2 Water Tanks & Pumps & Polycon 1 Ls 4,000 4,000 27,000 7.3 Septic Tank & Soakaway 0 Ls 0 By owner 8 Air conditioning Civil Work 8.1 A/C Civil & Plumping Works 1 Ls 1,500 1,500 1,500 9 Water Proofing 9.1 Roof (Combo System) 163 M2 120 19,500 19,500 10 Aluminium and Metal Works 10.1 Windows 1 Ls 29,400 29,400 29,400
Contractor Owner Consultant
Project PROPOSED MAJLIS BLOCK Consultant AL SHAIK MUBARAK Owner SALAH JAMAH KHALIFA JUMA AL QAZI Contractor ALTON CONTRACTING Plot No. 3250437-ZABEEL FIRST Date 25-09-2021
Sr. Description of work Quantity Unit Rate Amount
11 Ceramic, Marble and Granite
11.1 Entrance Marble Platform & Steps (Fixing only) 23 Lm/m2 80 1,840 11.2 Internal Floor Porcelain Tiles G.F + F.F (Fixing only) 121 M2 60 7,260 11.3 All Wet Areas Floor & Wall Tiles (Fixing only) 86 M2 60 5,160 16,360 11.4 All Skirting for Porcelain, Ceramic & Marble (Fixing only) 1 L.s 2,000 2,000 11.5 Marble Thresholds( Fixing only) 1 L.s 100 100 12 Painting & Stone Cladding& False Ceiling 12.1 External Paint Profile Décor , Jotun 282 M2 28 7,896 12.2 Internal Paint (Walls) Fenomastic Emulsion Jotun 415 M2 22 9,130 19,908 12.3 Internal Paint (Ceiling) 131 M2 22 2,882 12.4 False Ceiling Works 0 M2 0 By Owner 13 Joinery Works 13.1 All Inernal Doors (Supply & Fix Price 2000 Dhs) 5 No 2,200 11,000 11,000 14 Provisional Sum 14.1 Sanitary wares(supply by owner) 0 P.S 0 Fixing by cont 14.2 Vanity Marble Counter Top 0 P.S 0 By Owner 14.3 Light Fittings (supply by owner) 0 P.S 0 Fixing by cont 14.4 Wardrobes 0 P.S 0 By Owner 14.5 A/C WORKS & Mechanical Ventilation (Supply & Fix 30000 Dhs) 0 P.S 0 By Owner 4,737 14.6 Individual Water Heater (Supply &fix 3000 Dhs) 1 P.S 3,300 3,300 14.7 Dish Antenna & Intercom System (Supply & Fix) 0 P.S 0 By Owner 14.8 Gypsum Board False Ceiling 0 P.S 0 By Owner 14.9 GRC WORK 0 P.S 0 By Owner 14.10 Opening for compound wall gate (civil work only) 1 ls 1,437 1,437 15 Cleaning and handing over 15.1 Cleaning and handing over 1 ls 1,500 1,500 1,500 Total 352,000 5 % will be added if the Value Added Tax applied / يتم اضافة خمسة بالمائة من قيمة المشرع فى حال تم تطبيق ضريبة القيمة المضافة 352,000 TOTAL "Three Hundred Fifty Two Thousand Dirhams Only "