INDICON LIMITED

GENERAL BUILDING & CIVIL ENGINEERING CONTRACTORS.


P.O Box 28331, KAMAPALA UGANDA
indiconltd27@gmail.com
Contacts : +256 750 992277, +256 755 834847

Serial No. 001

DATE: 19-10-2019

TO: Mr. DENIAL

Ref: QUOTATION FOR WATER CHANNELS.

RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
(UGX) (UGX)
BILL NO.1

WATER CHANNELS;

EELEMENT NO.1

DEMOLITION AND REMOVALS

Demolish existing 200mm thick concerete floor to create a water


A channel, cart away debris from site, thoroughly clear site, and make good LM 21 40,000 840,000
of disturbed surfaces.

Total Element No.1 Carried to Summary 840,000

ELEMENT NO.2

EARTH WORKS AND EXCAVATION;

B Ecavateion for surface trenches; n.e 1.5m deep. CM 11 25,000 287,000

C Excavation for Culvert trenches; n.e 1.5m deep. CM 19 25,000 480,000

Back filling to the trenches using excavated materials and compacting to


D CM 15 30,000 440,400
98% MOD AASHTO.

E Load and cart away surplus excavated materials away from site. CM 5 35,000 158,200

Total Element No.2 Carried to Summary 1,365,600

ELEMENT NO.3

CONCRETE WORKS;

PLAIN CONCRETE GRADE 15 (20mm AGGREGATE);

F 50mm thick blinding to surface trenches CM 2 460,000 745,200

VIBRATED REINFORCED CONCRETE GRADE 25 (20MM


AGGREGATE) IN:

G 200mm thick water Channel Base CM 3 550,000 1,804,000


H 200mm thick Water Channel Walls CM 5 550,000 2,931,500
I Extra Over for joining and haunching around the culverts ; CM 1 550,000 550,000

TOTAL CONCRETE WORKS CARRIED TO COLLECTION 6,030,700


RATE AMOUNT
ITEM DESCRIPTION UNIT QTY
(UGX) (UGX)

ELEMENT NO.3

STEEL REINFORCEMENTS & MS - WATER CHANNEL COVER;

STEEL REINFORCEMENT as described including cutting to length,


bending, hoisting and fixing and including all necessary tying wire
and spacing blocks

MILD STEEL ROUND BARS TO BS 4449

A 10mm Diameter bars KG 460 4,700 2,163,741


500mm wide grating in 2000mm lengths comprising 50 x 50 x 6mm RSA
B anchored into concrete walls using metal lags : 40 x 40 x 6mm RSA LM 21 312,000 6,396,000
frame with 32mm TMT Bar welded on angles at 82mm centers with all
painting and decoration.

Total Element No.3 Carried to Summary 8,559,741

ELEMENT NO.4

FORMWORK;

Shutterinf to;

C Vertical sides of Water Channel Walls SM 44 30,000 1,319,175

Total Element No.4 Carried to Summary 1,319,175

ELEMENT NO.5

PLUMBING WORKS

D 600mm diameter double wall culvert laid on 50mm thick blinded LM 15 380,000 5,700,000

200mm diameter heavy duty PVC pipe connected to existing culvert at


E LM 6 16,250 97,500
every 2.0m

Total Element No.5 Carried to Summary 5,797,500

SUMMARY:
1 DEMOLITION AND REMOVALS 840,000

2 EARTH WORKS AND EXCAVATION; 1,365,600

3 STEEL REINFORCEMENTS & MS - WATER CHANNEL COVER; 8,559,741

4 FORMWORK; 1,319,175

5 PLUMBING WORKS 5,797,500

6 PRELIMINARIES 500,000

SUB - TOTAL 1 18,382,016

ADD: VAT 18% 3,308,763

TOTAL FOR CONTRACT 21,690,779

CLIENT CONTRACTOR
…................................................. …................................................
SIGNATURE SIGNATURE
….................................................. …................................................
DATE: …........................................ DATE: ........................................