Professional Documents
Culture Documents
Sebeta City
Administration
Un-Priced BOQ
Nov-21
Summary
Municipal Building Project
Specification and BoQ
For Sebeta City Administration
Total 304,044,717.28
VAT 15% 45,606,707.59
Total After VAT 349,651,424.87
Summary
Summary of Structural Work
Block 1 22,735,643.11
A. SUBSTRUCTURE
1.A.2. CONCRETE WORK 750,351.00
1.A.3. Sundry Work 416,436.30
1.A.4. Masonry Work 78,676.50
1.B. SUPER - STRUCTURE
1.B.1. Concrete Work 21,490,179.31
Block 2 20,354,249.16
1A. SUB STRUCTURE
1.A.2. CONCRETE WORK 782,974.50
1.A.3. Sundry Work 376,806.15
1.A.4. Masonry Work 203,095.20
1.B. SUPER - STRUCTURE
1.B.1. Concrete Work 18,991,373.31
Block 3 11,924,427.78
1.A. SUB - STRUCTURE
1.A.2. CONCRETE WORK(Block 3) 2,653,251.30
1.A.3. Sundry Work 408,672.60
1.A.4. Masonry Work 150,790.50
1.B. SUPER - STRUCTURE
1.B.1. Concrete Work 7,323,593.80
1.B.2 Steel Structure 1,388,119.59
unicipal Building Project
Specification and Bill of Quantities
For Sebeta City Administration
A. SUBSTRUCTURE
1.A.2. CONCRETE WORK
R. Concrete quality in class C-25 in 100mm thick caste to semi-basement
1.A.2.2
floor slab. m2 656.00 621.60 407,769.60
Supply & fix in position steel reinfrocement according to structural
1.A.2.8
drawing; Price includes cutting bending, in position and tying wires.
- -
B) Ø 8M M kg 2,862.00 119.70 342,581.40
C) Ø 10M M kg -
D) Ø 12M M kg -
E) Ø 14M M kg -
F) Ø 16M M kg -
G) Ø 20M M kg -
Total Carried to Summary of concrete work - 750,351.00
1.A.3. Sundry Work -
Construct expanision joints shall be filled with 10mm thick &
1.A.3.1 100mm wide chip wood both sides painted with bitumen
between basement beam and basement slab. ml 512.00 110.25 56,448.00
Expansion joints shall be filled with 10mm thick & 400mm wide
1.A.3.2 chip wood both sides painted with bitumen between floor
beam and beam.
ml 120.00 110.25 13,230.00
Expansion joints shall be filled with 10mm thick & 500mm wide
1.A.3.3 chip wood both sides painted with bitumen between column
and column.
ml 120.00 110.25 13,230.00
Apply chemical resistant POLYSTOP or equivalent material around
beam and slab joint the material standards shall be according to the
1.A.3.4 manufacturer instruction. Price shall include, the edges of the joint are
generally weak, all arr the manufacturer instruction and engineer's
approval. ml 521.00 132.30 68,928.30
Structural Work 4
unicipal Building Project
Specification and Bill of Quantities
For Sebeta City Administration
B.4 4th floor slab m2 608.99 993.30 604,909.77
B.5 5th floor slab m2 553.12 993.30 549,414.10
B.6 Roof floor slab m2 647.83 993.30 643,489.54
C. In Stair Case -
C. 3 From 2nd - 3rd floor m3 6.24 6,207.60 38,735.42
C. 4 From 3rd-4th roof floor m3 6.24 6,207.60 38,735.42
C. 5 From 4th-5th floor m3 6.24 6,207.60 38,735.42
Reinfroced concrete in class C-30, with minimum cement content of
1.B.1.1 4000kg/m3 filled in into formwork and vibrated around steel
reinforcement steel and formwork measured. -
A. In Elevation Column -
A. 4 From 3rd-4th roof floor m3 36.45 7,883.40 287,349.93
A. 5 From 4th-5th floor m3 34.43 7,883.40 271,425.46
A. 6 From 5th-roof floor m3 34.43 7,883.40 271,425.46
Reinforced pre-cast concrete class C-25 shall be east and true and square,
of even color, free from cracks, in suitable size for handling price to
1.B.1.2
include for 4dia. 12mm and dia.8mm c/c 200mm reinforcements. Price to
allow for curing 28 days, from work and renf
-
A. Lintels and front m3 2.00 6,207.60 12,415.20
Provide cut &fix in position sawn zigba wood or equivalent
1.B.1.3
formwork. -
A. For Elevation Column -
A. 4 From 3rd-4th floor m2 260.00 496.65 129,129.00
A. 5 From 4th-5th floor m2 240.00 496.65 119,196.00
A. 6 From 5th-roof floor m3 240.00 496.65 119,196.00
B. For floor beam - -
B.3 3rd floor beam m2 383.52 496.65 190,475.21
B. 4 4th floor beam m2 348.65 496.65 173,157.02
B. 5 5th floor beam m2 338.19 496.65 167,962.06
B. 6 roof floor beam m3 345.16 496.65 171,423.71
C. For 160mm thick solid floor slab - -
C. 3 3rd floor slab m2 567.00 496.65 281,600.55
C. 4 4th floor slab m2 610.00 496.65 302,956.50
C. 5 5th floor slab m2 525.00 496.65 260,741.25
C. 6 Roof floor slab m2 610.00 496.65 302,956.50
D. For stair case - -
D. 3 From 2nd - 3rd floor m3 47.00 496.65 23,342.55
D. 4 From 3rd - 4th roof floor m3 47.00 496.65 23,342.55
D. 5 From 4th - 5th floor m3 47.00 496.65 23,342.55
Structural Work 5
unicipal Building Project
Specification and Bill of Quantities
For Sebeta City Administration
Expansion joints shall be filled with 10mm thick & 500-700mm
1.A.3.3 wide chip wood both sides painted with bitumen between
column and column.
ml 57.00 55.65 3,172.05
Apply chemical resistant POLYSTOP or equivalent material around
beam and slab joint the material standards shall be according to the
1.A.3.6 manufacturer instruction. Price shall include, the edges of the joint are
generally weak, all arr the manufacturer instruction and Engineer's
approval. ml 784.00 220.50 172,872.00
Reinforced pre-cast concrete class C-25 shall be cast and true and square,
of even color, free from cracks, in suitable size for handling price to
1.B.1.2
include for 4dia. 12mm and dia.8mm c/c 200mm reinforcements. Price
to allow for curing 28 days, from work and renf
m3 2.00 6,207.60 12,415.20
1.B.1.3 Provide cut & fix in position sawn zigba wood or equivalent formwork.
-
A. For Elevation Column -
A. 4 From 3rd-4th roof floor m2 330.00 496.65 163,894.50
A. 5 From 4th-roof floor m2 330.00 496.65 163,894.50
Structural Work 6
unicipal Building Project
Specification and Bill of Quantities
For Sebeta City Administration
A. 6 From roof - upper roof floor m2 80.00 496.65 39,732.00
B. For 300mm thick lift shaft wall - - -
B. 4 From 3rd - 4th roof floor m2 116.00 496.65 57,611.40
B. 5 From 4th - roof floor m2 116.00 496.65 57,611.40
B. 6 From roof - upper roof floor m2 120.00 496.65 59,598.00
C. For floor beam - - -
C. 3 3rd floor beam m2 380.00 496.65 188,727.00
C. 4 4th floor beam m2 380.00 496.65 188,727.00
C. 5 Roof floor beam m2 380.00 496.65 188,727.00
C. 6 upper roof floor beam m2 80.00 496.65 39,732.00
D. For 150mm thick solid floor slab - -
D. 3 3rd floor slab m2 690.00 496.65 342,688.50
D. 4 4th floor slab m2 690.00 496.65 342,688.50
D. 5 Roof floor slab m2 845.00 496.65 419,669.25
D. 6 Upper roof floor slab m2 150.00 496.65 74,497.50
E. For stair case - -
E 3 From 2nd - 3rd floor m2 55.00 496.65 27,315.75
E. 4 From 3rd - 4th roof floor m2 55.00 496.65 27,315.75
E. 5 From 4 th-roof floor m2 55.00 496.65 27,315.75
E. 6 From 5th- Upper Roof floor m2 55.00 496.65 27,315.75
f. in disable ramp enterance m2 20.00 496.65 9,933.00
Expansion joints shall be filled with 10mm thick & 400mm wide
1.A.3.2 chip wood both sides painted with bitumen between floor
beam and beam.
ml 50.00 55.65 2,782.50
Expansion joints shall be filled with 10mm thick & 500mm wide
1.A.3.3 chip wood both sides painted with bitumen between column
and column.
ml 50.00 55.65 2,782.50
Structural Work 7
unicipal Building Project
Specification and Bill of Quantities
For Sebeta City Administration
Apply chemical resistant POLYSTOP or equivalent material around
beam and slab joint the material standards shall be according to the
1.A.3.4 manufacturer instruction. Price shall include, the edges of the joint are
generally weak, all arr the manufacturer instruction and Engineer's
approval ml 882.00 276.15 243,564.30
Structural Work 8
unicipal Building Project
Specification and Bill of Quantities
For Sebeta City Administration
Total Carried to Summary of masonry work - 150,790.50
1.B. SUPER - STRUCTURE - -
1.B.1. Concrete Work - -
Reinforced pre- cast concrete class C-25 shall be cast and true and
1.B.1.2 square, of even color, free from cracks, in suitable size for handling price
to include for 4dia. 12mm and dia.8 days, from work and rent
- - -
A. Lintels and front m3 2.00 6,207.60 12,415.20
Provide cut & fix in position sawn zigba wood or equivalent
1.B.1.3
formwork. - - -
A. In Elevation Column - - -
A. 4 From 3rd-4th roof floor m2 180.00 496.65 89,397.00
A. 5 From 4th - roof floor m2 150.00 496.65 74,497.50
B. In floor beam - - -
B. 4 4th floor beam m2 395.00 496.65 196,176.75
B. 5 Roof floor beam m2 215.00 496.65 106,779.75
C. For 150mm thick solid floor slab - - -
C. 4 4th floor slab m2 480.00 496.65 238,392.00
C. Roof floor slab m2 440.00 496.65 218,526.00
E. In Stair case - - -
E. 4 From 3rd - 4th roof floor m3 30.00 496.65 14,899.50
E. 5 From 4 th-roof floor m3 2.00 496.65 993.30
Structural Work 9
unicipal Building Project
Specification and Bill of Quantities
For Sebeta City Administration
1.B.2 Steel Structure - -
- -
1.B.2.1 A) main truss - -
RHS 80 X 80 X 3mm upper and lower member kg 1,931.21 220.50 425,830.83
RHS 50 X 50 X2.5mm vertical and diagonal member kg 543.86 220.50 119,920.32
RHS 30 X 30 X 3mm vertical and diagonal member kg 761.28 220.50 167,862.90
1.B.2.2 b) Latticed Purlin - - -
RHS 40 X 40 X 3mm kg 1,238.27 220.50 273,039.42
RHS 25 X 25 X 2mm kg 365.51 220.50 80,594.51
1.B.2.3 B) Plate - - -
supply and fix base plate size 300 x 300 X 10 in 2pcs No 126.00 1,102.50 138,915.00
1.B.2.4 c) Angle iron - - -
Supply and fix end connection angle ironed size 75 x 30 5mm
Length 100cm
No 252.00 276.15 69,589.80
1.B.2.5 D) Bolt - - -
Supply and fix in position steel bolt. Price shall include all the
necessary accessaries like nut and washer.
No 252.00 165.90 41,806.80
1.B.2.6 Basic Structure sub system - - -
Supply and fix cable bracing at wall & roof price shall include all
necessary accessories eye bolt, brace grip, nut, flat washer, hill side
washer, weld back up plate. Dia. 30mm.
ml 64.00 1,102.50 70,560.00
Total carried to summary 1,388,119.59
Grand total Structural work -
Structural Work 10
Architectural Works(Block 1 + Block Specification
2 + Block 3) and Bill of Quantities
For Sebeta City Administration
Supply and fix Aluminium framed partition walls with 5mm thick clear glass and 2mm dark-
1.B.2.4 grey powder coated Aluminium and with all other necessary accessories as per detail drawing
and Engineer's approval (Price includes all accessaries used for fixing)
m2 1,867.00 10,968.30 20,477,816.10
Supply and fix 90*210 cm Aluminium Framed Glass door for glass partions with 5mm thick
clear glass and 2mm dark-grey powder coated Aluminium with all other necessary
1.B.2.5
accessories as per detail drawing and Engineer's approval (Price includes glazing and all other
accessaries like ASSA-ABLOY or Equivalent lock, hinges and so on)
pcs 94.00 20,730.15 1,948,634.10
1.B.2.6 GLASS DOOR 130*210 pcs 23.00 39,128.25 899,949.75
1.B.2.7 GLASS DOOR 180*210 pcs 10.00 54,176.85 541,768.50
1.B.2.8 FIRE RATED DOOR 130*210 pcs 6.00 60,196.50 361,179.00
Total Carried to Summary 31,006,940.61
1.B.3. Roofing & Cladding -
Supply and fix approved standard pre-painted miniral rock wool sandwiched EGA roof pannel
made of polyurethane core, based on 0.5mm thick (nominial) metal skin with modified
polyster paint and 0.5mm thick (nominial) with modified polyster paint fixed to "Z" girth or
latticed purlin with 5.5mm diameter carbon steel self drlling fasteners. Price shall include all
1.B.3.1
necessary fixing accessories like outside foam closure, self driling fasteners, drip trim, conrner
trim, eave trim, girt trim, girt clip, outside foam closeur and all others necessry fixing
accessories. (purlin measured separately.). All detail and installation shall be in accordance
with the manufacturer's drawing.
m2 450.00 1,565.55 704,497.50
Supply and fix polyester with resistant to whether painted 26 gage galvanized steel flashing, it
shall be supported from roof panels. Price shall include all necessary accessories like corner
1.B.3.2 closure rubber weather seals. All detail and installation shall be
in accordance with the manufacturer's drawings. Dev. Length is
1150mm
ml 69.00 573.30 39,557.70
Concrete gutter as per detail drawing & price shall includes all necessary works like
1.B.3.3
chesseling, plastering and other accessories to complete the work.
ml 110.00 1,929.90 212,289.00
Supply and fix in position approved standard PVC down-pipe. Price shall include all
1.B.3.4 connections like elbow,bends, connectors and all the necessary fixing accessories. All detail
and installation shall be in accordance with the manufacturer's drawings.
ml 900.00 386.40 347,760.00
Water Proofing for Entrance porch canopy - - -
Average 7cm thick light weight concrete spread and leveled over R.C. roof slab, cement
1.B.3.5
pumice and sand mix in the propotion of 1:4:3 with a slope of 2% towards down pipe.
m2 24.00 496.65 11,919.60
3cm thick cement screed a ratio of 1:3 on top of light weight
1.B.3.6
concrete keeping the slope as indicated. m2 24.00 342.30 8,215.20
Supply and install MASTER SEAL 501, SIKA 1 or approved Equivalent, integral water
proofing to be used in light weight screed roofs and terraces as per Engineering instruction .
1.B.3.7 The price including all the assistant civil works. The price including thermal instulation on top
of the water proofing membrsne with all the connection detail and protection layer above the
thermal insulation.
m2 24.00 595.35 14,288.40
Architectural Work 11
Water Proofing for roof slab at 20:25m Specification and Bill of Quantities - -
For Sebeta City Administration
Avarage 7 cm thick light weight concrete spread and leveled over R.C roof slab, cement
1.B.3.8
pumice and sand mix in the proportaion of 1:4:3 with a slope of 2% towards down pipe.
m2 1,947.86 496.65 967,404.67
3cm thick cement screed a ratio of 1:3 on top of light weight
1.B.3.9
concrete keeping the slope as indicated. m2 1,947.86 308.70 601,304.38
Supply and install MASTER SEAL 501, SIKA 1 or approved Equivalent, integral water
proofing to be used in light weight screed roofs and terraces as per Engineering instruction .
1.B.3.10 The price including all the assistant civil works. The price including thermal instulation on top
of the water proofing membrsne with all the connection detail and protection layer above the
thermal insulation.
m2 1,947.86 595.35 1,159,658.45
Water Proofing for roof slab at 25:30cm - - -
Average 7cm thick light weight concrete spread and leveled over R.C. roof slab, cement
1.B.3.11
pumice and sand mix in the propotion of 1:4:3 with a slope of 2% towards down pipe.
m2 1,955.00 496.65 970,950.75
3cm thick cement screed a ratio of 1:3 on top of light weight
1.B.3.12
concrete keeping the slope as indicated. m 2
1,955.00 308.70 603,508.50
Supply and install MASTER SEAL 501, SIKA 1 or approved Equivalent, integral water
proofing to be used in light weight screed roofs and terraces as per Engineering instruction .
1.B.3.13 The price including all the assistant civil works. The price including thermal instulation on top
of the water proofing membrsne with all the connection detail and protection layer above the
thermal insulation.
m2 1,955.00 595.35 1,163,909.25
Water Proofing for Guard house roof slab - - -
Avarage 7 cm thick light weight concrete spread and leveled over R.C roof slab, cement
1.B.3.14
pumice and sand mix in the proportaion of 1:4:3 with a slope of 2% towards down pipe.
m2 19.20 496.65 9,535.68
3cm thick cement screed a ratio of 1:3 on top of light weight
1.B.3.15
concrete keeping the slope as indicated. m 2
19.20 254.10 4,878.72
Supply and install MASTER SEAL 501, SIKA 1 or approved Equivalent, integral water
proofing to be used in light weight screed roofs and terraces as per Engineering instruction .
1.B.3.16 The price including all the assistant civil works. The price including thermal instulation on top
of the water proofing membrsne with all the connection detail and protection layer above the
thermal insulation.
m2 19.20 595.35 11,430.72
Water proofing for stair and lift shaft roof - - -
Average 7cm thick light weight concrete spread and leveled over R.C. roof slab, cement
1.B.3.17
pumice and sand mix in the propotion of 1:4:3 with a slope of 2% towards down pipe.
m2 286.65 496.65 142,364.72
3cm thick cement screed a ratio of 1:3 on top of light weight
1.B.3.18
concrete keeping the slope as indicated. m2 286.65 254.10 72,837.77
Supply and install MASTER SEAL 501, SIKA 1 or approved Equivalent, integral water
proofing to be used in light weight screed roofs and terraces as per Engineering instruction .
1.B.3.19 The price including all the assistant civil works. The price including thermal instulation on top
of the water proofing membrsne with all the connection detail and protection layer above the
thermal insulation.
m2 286.65 595.35 170,657.08
Architectural Work 12
Water Proofing for concrete gutter Specification and Bill of Quantities - -
For Sebeta City Administration
Average 7cm thick light weight concrete spread and leveled over R.C. gutter, cement pumice
1.B.3.20
and sand mix in the proportaion of 1:4:3 with a slope of 2% towards down pipe.
m2 1,018.60 496.65 505,887.69
3cm thick cement screed a ratio of 1:3 on top of light weight
1.B.3.21
concrete keeping the slope as indicated. m2 1,018.60 254.10 258,826.26
Supply and install MASTER SEAL 501, SIKA 1 or approved Equivalent, integral water
proofing to be used in light weight screed roofs and terraces as per Engineering instruction .
1.B.3.22 The price including all the assistant civil works. The price including thermal instulation on top
of the water proofing membrsne with all the connection detail and protection layer above the
thermal insulation.
m2 1,018.60 595.35 606,423.51
Water proofing for 1st floor toilet - -
Supply aand coat XYPEX or equivalent water proofing as per manufactures instruction for all
wet areas, toilet, kitchen, etc as per Engineering instruction. The contructor must consider the
work as complete set provide appropirate measures for the connection b/n pipes and concrete
1.B.3.23
slab. the application of water proofing 30cm above the floor finshing level to the walls within
the wash room. After the completion of the work the contractor should do ponding test using
water at level of 20cm from floor finishig level for atleast 24 hours.
m2 63.50 1,025.85 65,141.48
Water proofing for 2nd floor foilet - -
Supply aand coat XYPEX or equivalent water proofing as per manufactures instruction for all
wet areas, toilet, kitchen, etc as per Engineering instruction. The contructor must consider the
work as complete set provide appropirate measures for the connection b/n pipes and concrete
1.B.3.23
slab. the application of water proofing 30cm above the floor finshing level to the walls within
the wash room. After the completion of the work the contractor should do ponding test using
water at level of 20cm from floor finishig level for atleast 24 hours.
m2 63.50 595.35 37,804.73
Water proofing for 3rd floor toilet - -
Supply aand coat XYPEX or equivalent water proofing as per manufactures instruction for all
wet areas, toilet, kitchen, etc as per Engineering instruction. The contructor must consider the
work as complete set provide appropirate measures for the connection b/n pipes and concrete
1.B.3.24
slab. the application of water proofing 30cm above the floor finshing level to the walls within
the wash room. After the completion of the work the contractor should do ponding test using
water at level of 20cm from floor finishig level for atleast 24 hours.
m2 67.00 595.35 39,888.45
Water Proofing for 4th floor toilet - -
Supply aand coat XYPEX or equivalent water proofing as per manufactures instruction for all
wet areas, toilet, kitchen, etc as per Engineering instruction. The contructor must consider the
work as complete set provide appropirate measures for the connection b/n pipes and concrete
1.B.3.25
slab. the application of water proofing 30cm above the floor finshing level to the walls within
the wash room. After the completion of the work the contractor should do ponding test using
water at level of 20cm from floor finishig level for atleast 24 hours.
m2 57.00 595.35 33,934.95
Architectural Work 13
Water Proofing for 5th floor toilet Specification and Bill of Quantities - -
For Sebeta City Administration
Supply aand coat XYPEX or equivalent water proofing as per manufactures instruction for all
wet areas, toilet, kitchen, etc as per Engineering instruction. The contructor must consider the
work as complete set provide appropirate measures for the connection b/n pipes and concrete
1.B.3.26
slab. the application of water proofing 30cm above the floor finshing level to the walls within
the wash room. After the completion of the work the contractor should do ponding test using
water at level of 20cm from floor finishig level for atleast 24 hours.
m2 22.00 595.35 13,097.70
1.B.3.27 Supply and fix wire dome leaf strainer No 30.00 386.40 11,592.00
Total Carried to Summary - 8,789,564.85
1.B.4. Metal Work - -
Architectural Work 14
WD-xx size 6970x2020mm+2840x1530mm Specification and BillNo
of Quantities 2.00 178,755.15 357,510.30
W01 size 3900 x 600mm For Sebeta City Administration
No 4.00 22,703.10 90,812.40
w02 size 2500 x 600mm No 2.00 14,553.00 29,106.00
W03 size 3880 x 1050mm No 2.00 39,526.20 79,052.40
W05A size 5050 x 4050mm No 1.00 198,431.10 198,431.10
W05C size 3800 x 1975mm No 1.00 72,814.35 72,814.35
W05D size 3800 x 2650mm No 3.00 97,699.35 293,098.05
W06A size 5100 x 1975mm No 1.00 97,723.50 97,723.50
W06B size 5100 x 4050mm No 1.00 200,395.65 200,395.65
W06C size 5100 x 2650mm No 3.00 131,122.95 393,368.85
W4 size 1500 x 2650mm No 72.00 38,565.45 2,776,712.40
W5A size 2500 x 2650mm No 9.00 64,275.75 578,481.75
W5B size 2500x 2650mm No 9.00 64,275.75 578,481.75
W-6A size 4740x 750mm No 3.00 53,264.40 159,793.20
WA5 size 3995x 600mm No 5.00 23,256.45 116,282.25
WA6 size 2860x 600mm No 5.00 16,649.85 83,249.25
WA7 size 1485x 600mm No 5.00 8,645.70 43,228.50
WA8 size 6295x 600mm No 5.00 36,645.00 183,225.00
WA9 size 4300x 600mm No 5.00 25,032.00 125,160.00
WA10 size 4700x 600mm No 7.00 27,359.85 191,518.95
WA11 size 7115x 600mm No 7.00 41,418.30 289,928.10
WA12 size 7550x 600mm No 7.00 43,950.90 307,656.30
WA13 size 6005x 600mm No 7.00 34,956.60 244,696.20
WA14 size 6225x 600mm No 7.00 36,237.60 253,663.20
WA15 size 10270x 600mm No 7.00 59,784.90 418,494.30
WA16 size 9950x 600mm No 7.00 57,921.15 405,448.05
W17 size 3010 x 600mm No 1.00 17,522.40 17,522.40
W18 size 1905x 600mm No 1.00 11,089.05 11,089.05
W19 size 2975 x 600mm No 1.00 17,318.70 17,318.70
W20 size 3420 x 600mm No 1.00 19,909.05 19,909.05
W21 size 2345 x 600mm No 1.00 13,652.10 13,652.10
W22 size 3245 x 600mm No 1.00 18,890.55 18,890.55
W23 size 2435 x 600mm No 1.00 14,175.00 14,175.00
W24 size 3340 x 600mm No 1.00 19,442.85 19,442.85
W25 size 1130 x 600mm No 1.00 6,578.25 6,578.25
W26 size 1700x 600mm No 1.00 9,896.25 9,896.25
W27 size 2975 x 600mm No 1.00 17,318.70 17,318.70
Architectural Work 15
W28 size 3245 x 600mm Specification and BillNo
of Quantities 1.00 18,890.55 18,890.55
W29 size 4535 x 600mm For Sebeta City Administration
No 1.00 26,400.15 26,400.15
W30 size 4780 x 600mm No 1.00 27,825.00 27,825.00
W31 size 1155 x 600mm No 1.00 6,723.15 6,723.15
W32 size 4290 x 600mm No 1.00 24,973.20 24,973.20
W33 size 4131 x 600mm No 1.00 24,048.15 24,048.15
W34 size 3420 x 600mm No 1.00 19,909.05 19,909.05
W35 size 1240 x 600mm No 1.00 7,218.75 7,218.75
W36 size 4500 x 600mm No 1.00 26,195.40 26,195.40
W37 size 5145 x 600mm No 1.00 29,951.25 29,951.25
W38 size 1155 x 600mm No 1.00 6,723.15 6,723.15
W39 size 3700 x 600mm No 1.00 21,538.65 21,538.65
W40 size 4535 x 600mm No 1.00 26,400.15 26,400.15
W41 size 4780 x 600mm No 1.00 27,825.00 27,825.00
W47 4750X600MM No 1.00 27,359.85 27,359.85
WT1 2700X1500MM No 1.00 39,293.10 39,293.10
WT2 6295X1500MM No 1.00 91,611.45 91,611.45
WT3 2700X1500MM No 1.00 39,293.10 39,293.10
DO1 900X3000MM No 1.00 26,195.40 26,195.40
WO2 800X3000MM No 1.00 23,284.80 23,284.80
WO2 800X2100MM No 1.00 16,300.20 16,300.20
WO2 700X2100MM No 1.00 14,262.15 14,262.15
1.B.4.2 Staircase balustrade fixed to wall consisting of:- No - -
Supply and fix flush type of internal wooden doors. 40mm thick
with semi solid ocrd frames and covered quality 4mm walnut veneer, with solid frames
1.B.5.1 according to door schedule. Price includes three coats of varnih, 3pcs approved standard
hinges, cylindrical door lock ASSA or equivalent and all other necessary accessories as per
detail drawing and Engineer's
4,500.00 - -
D01 size 900 x3000mm No 28.00 26,195.40 733,471.20
D02 and D02'size (800 x 3000mm and 800*2100) No 76.00 39,585.00 3,008,460.00
D03 size 700 x 2100mm No 4.00 14,262.15 57,048.60
D04 size 1300 x 2100mm No 22.00 26,487.30 582,720.60
D05 size 1200 x 2100mm No 10.00 24,449.25 244,492.50
D06 size 1670 x 2100mm No 2.00 34,026.30 68,052.60
D07 size 1500 x 2100mm No 2.00 30,561.30 61,122.60
Construct best quality kitchen cabinet made of semi wooden core top and side finish with
walnut veneer with drawer, double bowel kitchen sink. Sheleves and cupboard all as per the
1.B.5.2
architectural detail drawing price shall inhclude the necessary iron monger, And granite top on
sink area. the Contractor shall submit workshop drawing for Architects approval.
ls 1.00 220,500.00 220,500.00
Total Carried to Summary - 4,975,868.10
Architectural Work 16
1.B.6. Finishing Specification and Bill of Quantities - -
For Sebeta City Administration
- -
A) To internal plaster m2 15,930.00 264.60 4,215,078.00
A) To external wall to be plastered m2 2,865.00 264.60 758,079.00
B) To beams and columns m2 7,123.00 264.60 1,884,745.80
C) To slab soffit m2 10,146.00 264.60 2,684,631.60
D) To stair soffit m2 900.00 264.60 238,140.00
E) To exposed concrete retaining wall m2 320.00 264.60 84,672.00
1.B.6.2 Prepare the surface and apply two coats of plastering to receive ceramic wall tiles
m2 1,253.00 264.60 331,543.80
1.B.6.3 Ditto as the above but to receive granite wall tiles. m2 169.00 264.60 44,717.40
supply and fix 40*40*2cm and 60 x 60 x 2cm thick approved granite floor tile bedded on
1.B.6.4 cement sand mortar 1:3. Price include 30mm thick cement mortar backing and white cement
grouting. m2 3,221.00 6,945.75 22,372,260.75
Prepare the surface, supply and fix 30x60x2cm thick polished
juparana granite wall tile with approved quality adhesive. The
1.B.6.5 surface must be clean, dry and free from dust, grease or painting
compound. Price include maxifix or equivalent adhesive. ( colour will be the Engineer's
approval.) Price include maxifix or equivalent adhesive Ditto but 10cm high and 2cm thick
marble skirting m2 169.00 7,386.75 1,248,360.75
1.B.6.6 Ditto but 10cm high and 2cm thick Granite skirting ml 1,254.00 695.10 871,655.40
Ditto but 3 X 25 cm granite threshold for doors and edge
1.B.6.7
of stair case and suspended slab ml 550.00 1,736.70 955,185.00
Supply and fix 3 x 34cm approved quality Granite
1.B.6.8 stair tread bedded on cement mortar 1:3 price include mortar bed. Nosing and chamfering.
(Clour and texture will be approved by an Engineer) ml 758.00 2,362.50 1,790,775.00
1.B.6.9 Granite riser 3 x 15cm ( colour will be the Engineer's approval.) ml 758.00 1,108.80 840,470.40
Supply and fix Supply best quality non-slippery (european standard) 8mm thick 400*400mm
or 600mmx600mm, Non-Skid mat Ceramic stuck down with approved type adhesive on
1.B.6.10 cement sand screed floor finish and joints grouted in approprate color setting coat mortar.
Quality, Color and pattern of tile shall be approved by the Engineers. Price shall include
48mm thick cement sand screed bedding. In cement sand ratio 1:3.
m2 544.00 1,323.00 719,712.00
1.B.6.11 12cm high 8 mm thick chamfered ceramic skirting of matching color to floor tiles.
ml 750.00 276.15 207,112.50
Supply and fix 8mm thick RAK or equivalent ceramic wall cladding, of matching color to
floor, stuck to wall with cement sand mortar 1:3 backing and grouthing with white cement
1.B.6.12
wash, Mortar backing measured separately with two coat plastering. Price shall include rod
anchors to backing. Color and pattern according to architect's drawings.
m2 600.00 1,764.00 1,058,400.00
Architectural Work 17
Specification and Bill of Quantities
Prepare the surface and construct approved S2 2000 heavy duty purpose conductive or anti-
For Sebeta City Administration
static epoxy flooring chermcal,
1.B.6.13 corrasion and impact resistant. Price shall include surface
preparation and necessrery component such as anti cradk loacking. All are as per the
manufactuer instruction and Engineer's approval m2 600.00 1,323.00 793,800.00
Supply and fix best quality RAK or equivalent porcelain stoneware, homogeneous throughout
the body with 8mm thick 600mmx600mm floor tiles bedded in cement sand mortar backing
1.B.6.14
mix (1:3)Quality, Color and pattern of tile shall be approved by the Engineers. Price shall
include 48mm thick cement sand screed bedding.
m2 5,337.00 1,555.05 8,299,301.85
10cm high 1cm thick chamfered porcelain skirting of matching
1.B.6.15
color to floor tiles. ml 4,652.00 551.25 2,564,415.00
Supply and fix 20 x 3cm granite window sill
1.B.6.16
price shall include cement sand mortar bed and cement grouting ml 250.00 1,389.15 347,287.50
Supply and fix 20 x3cm thick Granite balcony sill.Price shall include cement sand mortar bed
1.B.6.17
and cement grouting ml 305.00 1,389.15 423,690.75
Supply and fix best quality purque floor tile with skirting. Quality shall be approved by the
1.B.6.18
Engineers. Price shall include skirting and all other necessary material required for fixing.
m2 900.00 3,307.50 2,976,750.00
Supply and fix suspended armstrong acoustic false ceiling
(Dune Supreme Tegular) size 60 x 60 x 1.5cm for all slab soffit.
1.B.6.19
Price shall include all necessary accessories to fix the ceiling at
needed level Color and pattern is subject ot Architect's approval m2 525.00 2,150.40 1,128,960.00
200cm hight 30*30*2mm chrome plates corner wall protection anchored to wall and finishing
1.B.6.20
fine smooth flush to wall No 150.00 2,040.15 306,022.50
stage: Top wooden particle board thickness 25mm, melamine- coated paper white, silicio,
white oak and walnut finish, ABS edge thickness 1.5mm. Same size finish as the top. They are
alos
available in lacquered finish (see other catalogue references
1.B.6.21 for colors available).
Structure: square steel pipe 50 x 50mm thickness 2mm epoxides powder varnished white
fimsn fitted with leveling feet made of nylon white finish. Steel beams diameter 45mm
thickness 2mm epoxides powder varnished white finish. The connection among less and beam
is made by nylon joints tops are fixed to the structure with nylon brackets.
m2 66.00 3,858.75 254,677.50
Suppy and Fix Best quility Terrazo floor pavement around the building. The patern and colour
1.B.6.22 shall be determined and approved by an Engineer. (Price shall include red-ash and mortar
backing) m2 400.00 793.80 317,520.00
Construct an average size of 300mm half circle concrete ditch around the building over
1.B.6.23 selected material fill. Compact around edges provide a minimum of 0.5% slope towards flow
direction. The surface shall be smooth and edges straight.
m 250.00 1,080.45 270,112.50
Concrete curb stone in C-20 of size 100cmx25cmx10cm having smooth surface and straight
1.B.6.24
edge. Price shall include pointing joints and all related works.
m 250.00 463.05 115,762.50
Total Carried to Summary - 58,103,839.50
1.B.7. Glazing - -
5mm thick clear glass of approved and certified European standard fixed to Aluminium
1.B.7.1
framed window & Window doors with approved quality sealant
m2 1,139.60 2,040.15 2,324,954.94
Supply and fix 8mm thick clear reflective tempered glass for vision and nonvision panel fixed
to cencealed anoidanized special structural T or spider supportiong system aluminum frames
1.B.7.1 as shown on the drawing Price shall include aluminum frames,glazing and all the necessary
fixing system. the contractor shall provide shop drawings for approval by the engineer prior to
placing manufactures order.
5,500.00 - -
Architectural Work 18
CW01 size 2700 x 18800mm Specification and BillNo
of Quantities 1.00 419,721.75 419,721.75
CW02 size 19200 x 20250mm For Sebeta City Administration
No 1.00 3,214,890.00 3,214,890.00
CW03 size 18650 x 3650mm No 1.00 562,875.60 562,875.60
CW04 size 11225 x 16650mm No 1.00 1,545,399.45 1,545,399.45
CW05 size 5400 x 23765mm No 1.00 1,061,138.40 1,061,138.40
CW06 size 10780 x 4050mm No 1.00 361,006.80 361,006.80
CW07 size 20640 x 7000mm No 1.00 1,194,669.00 1,194,669.00
CW07A size 20640 x 3650mm No 1.00 622,934.55 622,934.55
CW07B size 20460 x 2950mm No 1.00 499,077.60 499,077.60
CW08 size 14800 x 7000mm No 1.00 856,642.50 856,642.50
CW09 size 18000 x 7900mm No 1.00 1,175,816.25 1,175,816.25
CW10 size 4100 x 20250mm No 1.00 686,514.15 686,514.15
CW11 size 3050 x 20250mm No 1.00 510,699.00 510,699.00
CW 12A size 18650 x 4050mm No 1.00 624,559.95 624,559.95
CW 12B size 6800 x 4050mm No 1.00 227,721.90 227,721.90
CW 12C size 31600 x 4100mm No 1.00 1,071,299.25 1,071,299.25
CW 12D size 19100 x 4050mm No 1.00 639,630.60 639,630.60
CW 13 size 19100 x 2250mm No 1.00 394,833.60 394,833.60
CW 14 size 2700 x 20250mm No 1.00 452,095.35 452,095.35
CW 15 size 29700 x 3650mm No 1.00 896,374.50 896,374.50
CW 15A size 4850x 3650mm No 1.00 146,378.40 146,378.40
CW 16 size 4250 x 16200mm No 1.00 569,303.70 569,303.70
CW 17 size 3875 x 4050mm No 1.00 129,768.45 129,768.45
CW 18 size 11900 x 20250mm No 1.00 1,992,562.95 1,992,562.95
CW 19 size 1735 x 24300 No 1.00 348,615.75 348,615.75
CW20 size 69350 x 4050mm No 1.00 2,322,423.60 2,322,423.60
CW21 size 2150 x 16200mm No 1.00 288,001.35 288,001.35
CW22 size 7025 x 8100mm No 1.00 470,513.40 470,513.40
CW23 size 20585 x 24300mm No 1.00 4,136,156.85 4,136,156.85
CW24 size 3505 x 7100mm No 1.00 205,772.70 205,772.70
Total Carried to Summary - 29,952,352.29
Architectural Work 19
1.B.8. Painting Specification and Bill of Quantities - -
For Sebeta City Administration
Apply three coats of plastic emulsion paint to all plastered and
1.B.8.1
stucco finished wall surface. m 2
15,931.00 132.30 2,107,671.30
1.B.8.2 Ditto but to plastered beam and columns m2 7,123.00 132.30 942,372.90
1.B.8.3 Ditto but stair case m2 900.00 132.30 119,070.00
1.B.8.4 Ditto slab bottom surface m2 10,078.00 132.30 1,333,319.40
1.B.8.5 Ditto but retaining wall m2 320.00 132.30 42,336.00
Prepare the surface and apply granite paint for external wall surface. The work shall be
1.B.8.6 performed as per the manufacturer instruction, the color and pattern shall be as per the
architect preference. m2 2,865.00 1,080.45 3,095,489.25
Total Carried to Summary - 7,640,258.85
Grand total Architectural work - 155,814,562.65
C Fence Work
- -
C.1 Sub-structure - -
C.1.1 SITE CLEARING M2 250.00 22.05 5,512.50
C.1.2 TRENCH M3 152.00 198.45 30,164.40
C.1.3 LOAD AND CARTEAWAY M3 202.00 176.40 35,632.80
C.1.4 BACKFILL M3 76.00 242.55 18,433.80
5cm thick lean concrete quality in class C-5 with minimum
C.1.5
cement content of 150kg/m3. m2 250.00 210.00 52,500.00
Construct 50cm thick hard trachytic or equivalent stone masonry foundation wall for
C.1.6
perhepherial bedded in cement sand mortar ration 1:3 - -
A. Below Natural Ground Floor Level (BNGL) m3 152.00 2,459.10 373,783.20
B. Ditto but for above natural ground level m3 95.00 3,605.70 342,541.50
Total Carried to Summary - 858,568.20
C.2 Supper structure - -
Supply and install 20cm thick HCB wall which can satisfy the desinged strength, bedded in
C.2.1
cement mortar (1:3), as per the detail drawing m2 360.00 705.60 254,016.00
plastered & painted RCC grade beam and column (column 20cmx20cm with 4 Ø12 rebar ,
stirrup Ø8 c/c 150mm and grade beam dimension 20cm*30cm with 4Ø12, stirrups Ø8 c/c
C.2.2
200mm) as per the detail drawing. Price shall includes formworks. (Reinforcement measured
separately) m3 38.32 7,166.25 274,610.70
Supply & fix in position Ø8,Ø10,Ø10,Ø812 steel reinfrocement according to structural
C.2.3
drawing; Price includes cutting bending, in position and tying wires.
kg 2,730.00 119.70 326,781.00
C.2.4 PLASTERED & POINTED GRADE BEAM m2 200.00 276.15 55,230.00
C.2.4 Plastered & quartiz painted HCB wall m2 650.00 - -
C.2.5 Pointed HCB wall m2 250.00 154.35 38,587.50
C.2.6 40*40mm 2.5mm thick RHS profile m 2,600.00 1,057.35 2,749,110.00
Total Carried to Summary - 3,698,335.20
C.3 Enterance Gate - -
Supply and Fix Main gate door made of 30x30x3mm thick RHS frame,horizontal & vertical
intermediate member shall be 20x20x2mm thick. The Door should be double opening. The
main get door Size shall be 12000mm wide & 2100mm high and two (2)mini gate door size
3500mm*2100mm fixed to concrete column size 40cm*40cm*250cm and grade beam of size
C.3.1 40cm*30cm.The column should constructed to the ground up to 1500mm depth and footing
size 1000*1000 mm size with class C-25 concrete. Approved Hinge should be place at
bottom,middle and top of door. price shall include one coat of antirest, two coats of enamel
paint,door lock and all other necessary accessories for completion of work as per detail
drawing and under the approval of the Engineer.
Ls 1.00 110,250.00 110,250.00
Supply and Fix Main get door made of 30x30x3mm thick RHS frame,horizontal & vertical
intermediate member shall be 20x20x2mm thick. The main get door Size shall be 3500mm
wide & 2100mm high and mini gate door size 1000mm*2100mm fixed to 3(three)concert
column size 40cm*40cm*250cm and grade beam of size 40cm*30cm.The column should
C.3.2
constructed to the ground up to 1000mm depth and footing size 1000*1000 mm size with
class C-25 concrete. Hinge should be place at bottom,meddle and top of door. price shall
include one coat of antirest, two coats of enamel paint,door lock and all other necessary
accessories for completion of work. detail drawing as per engineer approval
- -
Architectural Work 20
Main Gate D-1 Size: 12000x2500mm Specification and BillNo
of Quantities 1.00 110,250.00 110,250.00
Mini Gate GD-2 Size: 3500x2500mm For Sebeta City Administration
No 2.00 49,612.50 99,225.00
Total Carried to Summary - 319,725.00
Grand Total for Fence and Main Gate - 4,876,628.40
D. Guard house
-
D.1 Excavation and Earth works -
D.1.1 Site clearing to an average depth of 20 cm from Natural ground level m2 60.00 22.05 1,323.00
D.1.2 Trench excavation for masonary foundation m3 8.00 198.45 1,587.60
D.1.3 Load and Cart Away surplus excavated material 5 km away from the site m3 20.00 121.80 2,436.00
Backfill with selected material from the quary site at the sides of trench excavated and well
D.1.4 compact in layers of 20 cm thickness m3 8.00 210.00 1,680.00
250 mm thick basaltic or equivalent hardcore well rolled, consolidated and well blinded with
D.1.5 crushed stone m2 60.00 540.75 32,445.00
Construct 50cm thick hard trachytic or equivalent stone masonry fondation wll for
D.1.6
perhepherial bedded in cement sand mortar ration 1:3 m3 10.00 2,944.20 29,442.00
Construct 20cm thick class c hollow concrete block wall
D.1.7
bedded in cement sand mortar (1:3) both sides left for plastering. m2 49.62 705.60 35,011.87
D.1.8 Best quality Terrazo Floor finishing m2 15.60 496.65 7,747.74
D.1.9 Three coat of cement mortar Plastering to internal and external wall and soffit slab m2 99.24 220.50 21,882.42
D.2 Reinforced concrete C- 25 - -
D.2.1 Grade beam and Column m3 1.18 6,207.60 7,324.97
D.2.2 Top tie beam and slab m3 3.60 6,207.60 22,347.36
D.2.3
Mild Steel S400 for column and beam Ø12 c/c 170cm Ø10 for slab c/c 150mm - -
D.2.3.1 i). For Column(20*20cm) - -
D.2.3.2 Ø8mm kg 24.00 128.10 3,074.40
D.2.3.3 Ø12 mm kg 120.00 128.10 15,372.00
D.2.4 For Grade beam (20*20cm) - -
D.2.4.1 Ø8mm kg 34.00 128.10 4,355.40
D.2.4.2 Ø12mm kg 80.00 128.10 10,248.00
D.2.5 For Top tie beam (20*20cm) - -
D.2.5.1 Ø8mm kg 34.00 128.10 4,355.40
D.2.5.2 Ø12 mm kg 53.16 128.10 6,809.80
D.2.5.3 For slab ( 0.15cm thick slab ) Ø10 c/c 120mm kg 228.00 128.10 29,206.80
D.2.6 Gutter (plastered 15 HCB around edge of Rc roof.) lm 18.80 386.40 7,264.32
D.2.7 90 mm PVC down pipe including all necessary accessories lm 13.60 242.55 3,298.68
10cm thick C-20 mass concrete pavement around Guard house bedded on 15cm thick
hard core width of 1m and pavement must have a minimum of 2% slope out ward from
D.2.8 lm
building. Price includes hard core, 50 cm thick selected material fill, expansion joint at
an interval of 1.5m and other necessary works.
22.80 827.40 18,864.72
Architectural Work 21
Specification and Bill of Quantities
Supply and fix RHS framed and Aluminium flashed door and For Sebeta City Administration
D.2.9 Window as per the Architectural drawing. (Price shall includes all Ls
necessary accessaries and Glazing of windows)
4.00 11,025.00 44,100.00
D.2.9.1 D1- 90x210 cm No 6.00 20,730.15 124,380.90
D.2.9.2 w1-90x380 cm No 3.00 37,510.20 112,530.60
50mm Asphaltic surfacing with (penetration grade 60/70 bitumen Asphalt parking and
E.3.3 pavements including prefabricated concrete gutter, aggregate base coarse ,compacted subbase
as per design and detail drawing under the approval of the Engineer.( Price shall includes all
the layers of sub-base and base-course materials and compaction) m2 1,800.00 2,425.50 4,365,900.00
Single unit chiseling stone steps (150mm raiser and 320mm trading ) according to detail
E.3.4
drawing. m2 1,259.30 1,653.75 2,082,567.38
Ditch works including prefabricated concrete gutter, cement screed with min. 2%
slope ,curb stone (side ditch), ditch cover by galvanized iron grill and 5*50mm
E.3.5 galvanized flat iron and max. 50mm spacing, grill shall be framed with 50*50*5 L-
section galvanized iron and indipendent section of max.2.4m length, grills shall be made
easly removable and to clean ditch. lm 367.80 4,983.30 1,832,857.74
E.3.6 Plantation work according to detail drawings. - -
E.3.6.1 dimension 20.4 m*0.5 m No 1.00 11,245.50 11,245.50
E.3.6.2 dimension 6.3m*2.5m No 2.00 17,364.90 34,729.80
E.3.6.3 dimension 3m*3m No 3.00 9,922.50 29,767.50
E.3.9 Preparation of the site and planting selective grasses to make the site Green (Green area)accord m2 794.50 551.25 437,968.13
Architectural Work 22
Specification and Bill of Quantities
For Sebeta City Administration
-
Supply .fix, test & commission hand wash basins made of white Vitreous
China Standard white hand Wash basin with opening of dia. 16mm for faucet
access to acceptable standard with a pair of white painted cast iron screw to
1.1 wall brackets, 32mm slotted basin waste & overflow , chromium plated basin
chain & rubbe plug, complete with
-
a) Hand wash basins
i) Type : Armitage Shanks
Model: Cotage
Approximate size : In the Catalogue
Colur : As per the Architect's Preference Or Equivalent approved by the
engineer
Supply
No 95.00 5,250.00 498,750.00
Supply and fix wash down water closets complete with 10 liter
capacity low flush cistern with press type with half & full option
flushing mechanism; of white Mitereous chinal with overflow drain, plastic
seat , cover galvanised screws and all necessary accessories.
Armitage shanks
Approximate size : IN the Catalogue
1.2 Colour : As per the Architect's Preference
Sanitary Work 23
Specification and Bill of Quantities
For Sebeta City Administration
Supply and fix approved standard stainless steel janitor sink with
opening of dia. 16mm for faucel access with single bowl of type 302 (for
chrome & Nickel content) with Gauge 22 (thickness of 0.8mm) and chromium
plated basin chain & rubber plug, complete with fixing devices. Complete
with chrome plated chain, plug, chrome plated faucet, P-smell trap and with
1.9
all necessary accessories.
Size :- 1000 x 600 mm
Sanitary Work 24
Specification and Bill of Quantities
For Sebeta City Administration
b) dia. 25mm pipe (dia 20mm Equivant GSP) m 270.79 299.25 81,033.91
c) dia. 32mm pipe (dia 25mm Equivant GSP) m 250.00 276.15 69,037.50
Supply, fix, test, and commission European standard (manufactured) service
valves on the water supply pipe before sanitary applices including accessories,
2.2 all as shown on the drawings.
- - -
Dia. 15mm No 182.00 220.50 40,131.00
Ditto item number 2.3 above but approved quality bronze gate
valves on pipe lines above ceiling, internal branch water pipes of
2.3 the following sizes and as where shown on the drawing.
- - -
a) dia. 25mm m 60.00 551.25 33,075.00
b) dia. 32mm m 15.00 661.50 9,922.50
Supply and install 50mm Dia. G.S.P pipes (medium grade) from
municipal water supply to the water tanks as shown on the drawing. Complete
2.4 with all the necessry fittings and accessories.
m 100.00 1,102.50 110,250.00
Sanitary Work 25
Specification and Bill of Quantities
For Sebeta City Administration
Sanitary Work 26
Specification and Bill of Quantities
For Sebeta City Administration
- - -
All Domestic waste pipe lines shall be provided with a minimum
slop of 2% towards the outlet Unless speciffed. All uPVC pipes and
be free from damage during storage, transportatin, construction etc. Unit price
4.1 shall include all the necessary assistance givil works, such as fixing or hanging
to walls beams or slabs, etc., necessary fittings such as bends, Y, T, etc
- - -
a) Dia. 50 mm m 64.00 386.40 24,729.60
b) Dia. 75 mm m 34.00 606.90 20,634.60
c) dia. 110 mm m 170.00 827.40 140,658.00
D) Dia. 160 mm m 60.00 1,102.50 66,150.00
e) Dia. 200mm m - 1,102.50 -
Construct manholes on a sanitary sewer as where shown on the drawing in C-
30 precast concrete round pipes on 100mm thick reinforced concrete bottom
slab in dia. 10 re-bar @200mm C/C both ways and 120mm thick manhole
4.2 cover in dia 10 re-bar @ 150mm c/c both ways. Price shall include all
assistance civil works and handle
- - -
Dia. 600 mm No 16.00 5,512.50 88,200.00
Supply and lay apprved quality storm water uPVC PN6 down pipes
according to where shown on the drawings. Price shall include all
4.3 the necessary connectiong pieces.
m - - -
Dia. 110 mm m 625.00 849.45 530,906.25
4.4 Ditto item no 4.3 above but for storm water - - -
Sanitary Work 27
Specification and Bill of Quantities
For Sebeta City Administration
Sanitary Work 28
Specification and Bill of Quantities
For Sebeta City Administration
Sanitary Work 29
Specification and Bill of Quantities
For Sebeta City Administration
Electrical Installation
1. Internal installation
Power panel
supply, fix and connect flush/surface mounted metal enclosure
1.00 distribution board of slements, legrand, ABB or approved equal with
its circuit breakers.
1.10 SDB-B/A-SemiF
1pc mcb of 25amp/3ph,lcu=6KA
1pc mcb of 20amp/3ph,lcu=6KA
7pc mcb of 16amp/1ph, lcu=6KA
6pc mcb of 10amp/1ph, lcu=6KA No 1.00 35,280.00 35,280.00
1.20 SDB-B/B-SemiF - -
1pc mcb of 25amp/3ph,lcu=6KA - -
1pc mcb of 20amp/3ph,lcu=6KA - -
7pc mcb of 16amp/1ph, lcu=6KA - -
8pc mcb of 10amp/1ph, lcu=6KA No 1.00 35,280.00 35,280.00
- -
1.30 SDB-B/A-GF - -
1pc mcb of 50amp/3ph,lcu=6KA - -
1pc mcb of 25amp/1ph,lcu=6KA - -
1pc mcb of 20amp/1ph,lcu=6KA - -
12pc mcb of 16amp/1ph,lcu=6KA - -
9 pc mcb of 10amp/1ph,lcu=6KS No 1.00 46,305.00 46,305.00
1.40 SDB-B/B-GF - - -
1 pc mcb of 20amp/3ph,lcu=10KA - - -
7pc mcb of 16amp/1ph,lcu=6KA - - -
8 pc mcb of 10amp/1ph,lcu=6KA No 1.00 26,460.00 26,460.00
1.50 SDB-GF-Kitchen - - -
1 pc mcb of 150amp/3ph,lcu=10KA - - -
8 pc mcb of 25amp/3ph,lcu=10KA - - -
4 pc mcb of 25amp/1ph,lcu=10KA - - -
3 pc mcb of 20amp/1ph,lcu=6KA - - -
16 pc mcb of 16amp/1ph,lcu=6KA - - -
8pc mcb of 10amp/1ph,lcu=6KA No 1.00 132,300.00 132,300.00
1.60 SDB-B/A-FF - - -
1 pc mcb of 32amp/3ph,lcu=20KA - - -
1 pc mcb of 32amp/1ph,lcu=10KA - - -
1 pc mcb of 25amp/1ph,lcu= 6KA - - -
1 pc mcb of 20amp/1ph,lcu=6KA - - -
15 pc mcb of 16amp/1ph,lcu=6KA - - -
6 pc mcb of 10amp/1ph,lcu=6KA No 1.00 41,895.00 41,895.00
1.70 SDB-B/B-FF - - -
1pc mcb of 25amp/3ph,lcu=10KA - - -
13pc mcb of 16amp/1ph,lcu=6KA - - -
7pc mcb of 10amp/1ph, =6KA No 1.00 31,421.25 31,421.25
1.80 SDB-B/C-FF - -
1 pc mcb of 25amp/3ph,lcu=10KA - -
1 pc mcb of 20amp/3ph,lcu=10KA - -
1 pc mcb of 20amp/1ph,lcu= 6KA - -
9 pc mcb of 16amp/1ph,lcu=6KA - -
8 pc mcb of 10amp/1ph,lcu=6KA No 1.00 38,587.50 38,587.50
1.90 SDB-B/A-2F - -
1 pc mcb of 32amp/3ph,lcu=10KA - -
15 pc mcb of 16amp/1ph,lcu=6KA - -
7 pc mcb of 10amp/1ph,lcu= 6KA - -
1.10 SDB-B/B-2F No 1.00 33,075.00 33,075.00
1 pc mcb of 25amp/3ph,lcu=10KA - -
13 pc mcb of 16amp/1ph,lcu=6KA - -
6pc mcb of 10amp/1ph,lcu= 6KA - -
1.11 SDB-B/C-2F No 1.00 27,562.50 27,562.50
1 pc mcb of 25amp/3ph,lcu=10KA - -
1 pc mcb of 20amp/1ph,lcu= 6KA - -
12 pc mcb of 16amp/1ph,lcu=6KA - -
10 pc mcb of 10amp/1ph,lcu=6KA No 1.00 35,280.00 35,280.00
Electrical Work 30
Specification and Bill of Quantities
For Sebeta City Administration
1.12 SDB-B/A-3F - - -
1 pc mcb of 25amp/3ph,lcu=10KA - - -
15 pc mcb of 16amp/1ph,lcu=6KA - - -
8 pc mcb of 10amp/1ph,lcu= 6KA No 1.00 30,318.75 30,318.75
1.13 SDB-B/B-3F - -
1 pc mcb of 50amp/3ph,lcu=10KA - -
18 pc mcb of 16amp/1ph,lcu=6KA - -
10 pc mcb of 10amp/1ph,lcu= 6KA No 1.00 42,446.25 42,446.25
1.14 SDB-B/A-4F - -
1 pc mcb of 32amp/3ph,lcu=10KA - -
1 pc mcb of 20amp/1ph,lcu= 6KA - -
13 pc mcb of 16amp/1ph,lcu=6KA - -
7 pc mcb of 10amp/1ph,lcu=6KA No 1.00 27,011.25 27,011.25
1.15 SDB-B/B-4F - -
1 pc mcb of 50amp/3ph,lcu=10KA - -
18pc mcb of 16amp/1ph,lcu=6KA - -
9pc mcb of 10amp/1ph,lcu= 6KA No 1.00 41,895.00 41,895.00
1.16 SDB-5F - -
1 pc mcb of 32amp/3ph,lcu=10KA - -
14pc mcb of 16amp/1ph,lcu=6KA - -
6pc mcb of 10amp/1ph,lcu= 6KA No 1.00 27,011.25 27,011.25
1.17 SDB-LIFT - -
1 pc mcb of 63amp/3ph,lcu=10KA - -
2 pc mcb of 50amp/3ph,lcu=10KA - -
2pc mcb of 32amp/3ph,lcu=10KA - -
2 pc mcb of 16amp/1ph,lcu=6KA - -
2pc mcb of 10amp/1ph,lcu= 10KA No 1.00 57,330.00 57,330.00
- -
1.18 SDB-pump - -
1 pc mcb of 63amp/3ph,lcu=10KA - -
2 pc mcb of 50amp/3ph,lcu=10KA - -
2pc mcb of 32amp/3ph,lcu=10KA - -
2pc mcb of 25amp/1ph,lcu=10KA - -
2pc mcb of 20amp/1ph,lcu=10KA - -
2 pc mcb of 16amp/1ph,lcu=6KA - -
2pc mcb of 10amp/1ph,lcu= 10KA No 1.00 83,569.50 83,569.50
- -
1.19 MDB - -
Voltmeter (0-500V) - -
Ammeter (0-800A) - -
Slector switch - -
1 pc mcb of 800amp/3ph,lcu=10KA - -
1 pc mcb of 150amp/3ph,lcu=10KA - -
1pc mcb of 80amp/3ph,lcu= 10KA - -
5pc mcb of 50amp/3ph,lcu=10KA - -
8pc mcb of 32amp/3ph,lcu=10KA - -
4 pc mcb of 25amp/3ph,lcu=10KA - -
4 pc mcb of 20amp/3ph,lcu=10KA No 1.00 352,800.00 352,800.00
- -
4.1 CAT6a RJ45 8 contact data/tele socket out let points for - -
flush mounting in thermoplastic conduit of 25mm/PVC
duct(specified - -
and measured below)with appropriate type junction box fed by
standard - -
(2x CAT6a UTP cable) for 10G BASE-T - -
of Data socket out lets (1data and 1telephone outlet) No 100.00 1,565.55 156,555.00
- -
4.2.2 Floor Box Data/telephone socket out lets - -
with detachable frames & corresponding - -
box(including all necessary accessories) - -
of Data socket out lets (1data and 1telephone outlet) No 30.00 1,984.50 59,535.00
- -
4.3 Wifi access points - -
Manageable Wi-Fi access points 802.11a & b/g - -
Dual-band and dual-radio - -
Conform with standards 802.11a and 802.11b/g - -
Gross speed: 54 Mbps max. on each frequency - -
14 - -
Electrical Work 31
Specification and Bill of Quantities
For Sebeta City Administration
4.4 Data and Telephone Cables patch pannel with metalic Rack - -
Patch panels (PP- 48ports/2U) CAT6a RJ45 8 contact - -
4 pairs for data and 10pairs tele sub distribution frame in floor
stand - -
supply unit of 6pcs scuko type socket out lets and plug - -
supply unit of 6pcs scuko type socket out lets and plug - -
Electrical Work 32
Specification and Bill of Quantities
For Sebeta City Administration
5.4 Loop powered sounders and fire alarm indicators with the, - -
Electrical Work 33
Specification and Bill of Quantities
For Sebeta City Administration
Electrical Work 34
Specification and Bill of Quantities
For Sebeta City Administration
Electrical Work 35
Specification and Bill of Quantities
For Sebeta City Administration
support ,box for cable junctions for all the necessary acessories - -
14.1 60mmx400mm for voice/data cables+60mmx200mm for power
cables. Refer cable tray detail mt 50.00 2,976.75 148,837.50
14.2 60mm x200mm for voice/data cables+60mmx200mm for power
cables. Refer cable tray detail mt 50.00 2,976.75 148,837.50
- -
CABLE LADDER - -
16.2 Socket outlet in floor box /flush mounted, 16A, 1ph, schuko type in - -
medium duty rigid thermoplastic conduit of - -
diameter 16mm fed by PVC insulated copper - -
cable of 3x2.5mm2. , with all necessary accessories No 50.00 2,205.00 110,250.00
Electrical Work 36
Specification and Bill of Quantities
For Sebeta City Administration
- -
16.3 Socket outlet scame or approve equivalent flush - -
mounted 20A, 1ph with fed by PVC insulated - -
copper cable of 3x4mm2 in medium duty rigid - -
thermoplastic conduit of diameter 25mm.(Stove) No 35.00 2,315.25 81,033.75
- -
16.4 Socket outlet scame or approve equivalent flush - -
mounted 20A, 1ph with fed - -
17.10 10-16A/IP Socket outlet points fed through PVC sheathed cable of
3*2.5mm2 in PVC conduits of 16 mm iametrinclludcing junction
Boxes with covers and insulating screw cap connectors. No 1,300.00 1,929.90 2,508,870.00
17.20 20A/IP Socket outlet points fed through PVC sheathed cable of
3*4mm2 in PVC conduits of 16 mm diameterincludcing junction No 35.00 2,315.25 81,033.75
17.30
Flush MOUNTED socket OUTLET of 10-16A/IP 773720 + 773751 No 1,300.00 606.90 788,970.00
17.40 Flush Mounted twin socket outlet of 10-16A/IP 773727 No 650.00 827.40 537,810.00
17.50 Flush Mounted socket outlet of 20A/IP ,773727 No 35.00 1,047.90 36,676.50
17.60 16 A Flush Mounted socket outlet of in floor box No 50.00 1,124.55 56,227.50
- -
18. Automatic Hand Dryer - -
18.1 Supply and install 220V/50HZ automatic hand dryer with heating
temperature of 40-60 degree Celsius with dynamical balanced
centrifugal fan of multiple metalic vanes, fire retardant, high gloss
finish plastic cover and mounting base, infrared sensors complete
with all the accessories . No 12.00 12,127.50 145,530.00
- -
19. Lightning Arrester System - -
(Eritech or Equivalent) - -
supply and erect steel light pole of height 8m above finished floor
level with 175mm and 60mmdiam., bottom and top diam.
20.10
Respectively, with free fixed door (connection box) 2*2.5sq.mm
from fuse box to lamp.(Double arm Pole)
No 10.00 27,562.50 275,625.00
supply and erect steel light pole of height 8m above finished floor
level with 175mm and 60mmdiam., bottom and top diam.
20.20
Respectively, with free fixed door (connection box) 2*2.5sq.mm
from fuse box to lamp.(Single Arm Pole)
No 18.00 24,255.00 436,590.00
Supply and erect steel light pole with light brackets for holding 3
20.30 light fixtures, of height 3m above finished floor level with 175mm
and 60mm diam,. Bottom and top diam, Respectively with free fixed
door (connection box) , 2*2.5sq.mm from fuse box to lamp. (Post
head Pole) No 12.00 20,396.25 244,755.00
20.40 Pedase 102 with 1xSON-T. 150W lamp No 28.00 12,348.00 345,744.00
20.50 Versailles 1503/01/42 with E27/max 100W lamp. No 12.00 10,473.75 125,685.00
20.60 pole 3000m No 12.00 8,268.75 99,225.00
20.70 pole6000mm,single arm No 18.00 8,268.75 148,837.50
20.80 pole60000mm double arm No 10.00 8,268.75 82,687.50
-
-
-
Electrical Work 37
Specification and Bill of Quantities
For Sebeta City Administration
Electrical Work 38
Specification and Bill of Quantities
For Sebeta City Administration
Passenger Lift - -
Supply and install Passenger Lift as per - -
The specification - -
Technical Specifications - -
Standards - -
ISO 7465:2001,EN-81,BS ,ANSI,JIS,ISO 9001 - -
Electrical Work 39
Specification and Bill of Quantities
For Sebeta City Administration
- -
Shaft information - -
Shall take and consider approprate standards for the shaft, cabin,
cabin doors, machine room size and other parameters before
manufacturing and prepare working drawing referring to the
archtectrural and structural for submission with the technicalo
spsecification
- -
Submit for approval complete upto date lift specification of the
above items including fuide rails, reinforcement bar buffer duty
prewiring, conduiting/ trunking and other required and necessary
specification with working drawing referring to archtectural and
structural from at least 3 lift suppliers having a minimum of 5 years
or equivalent grantee period in lift manufacturing design, installation
and maintenance.
Electrical Work 40
A- Material cost B- Labor Cost C-Tools & Equipment
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
1. EXCAVATION & EARTH WORK
Fuel lit 0.42 24.00 9.98 Carpenter 1.00 0.20 50.00 350.00 0.03 Excavator 350.00 4.11
Daily Labor 6.00 1.00 25.00 350.00 0.43
Site clearing to remove top
soil
14.56 20.00
(Rate=350m2/day/excavat
or) efficiency=100%
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
Excavation foundation Fuel lit 1.24 24.00 29.87 Gang chief 1.00 1.00 43.75 12.50 3.50 Excavator 12.50 115.20
Trench for ordinary soil Daily Labor 15.00 1.00 25.00 12.50 30.00
(Rate=100m3/day/excavat Foreman 1.00 0.25 87.50 12.50 1.75 180.32 250.00
or for Trench)
efficiency=100% 29.87 35.25 115.20
17% 20% 64%
Selected fill
m3 1.25 333.33 416.67 Daily Labor 6.00 1.00 25.00 6.00 25.00 Tools 6.00 0.08
material
Plate
water lit 0.50 0.10 0.05 Gang chief 1.00 0.25 43.75 6.00 1.82 6.00 11.00
compactor
Fill ( sellected borowed)
(Rate=1.0m3/day/dl) Benzine lit 0.14 27.00 3.75 Sm. Operator 1.00 1.00 31.25 6.00 5.21 Loader 6.00 0.00 468.66 640.00
efficiency=80%
Fuel lit 0.13 24.00 3.00 Carpenter 1.00 0.25 50.00 6.00 2.08
Foreman 1.00 0.25 87.50 6.00 3.65
0.10 Plate
water lit 0.50 0.05 Gang chief 1.00 0.25 31.25 5.25 1.49 compactor 5.25 8.33
Fill ( sellected from site)
14.00 (Rate=1.0m3/day/dl) 27.00 134.10 190.00
Benzine lit 0.14 3.75 Sm. Operator 1.00 1.00 31.25 5.25 5.95 Loader 5.25 0.00
efficiency=80%
Fuel lit 0.13 24.00 3.00 Carpenter 1.00 0.25 50.00 5.25 2.38
Foreman 1.00 0.25 72.12 5.25 3.43
Gang chief 1.00 1.00 43.75 400.00 0.11 Dump trucks 800.00 28.88
Fuel lit 0.14 24.00 3.36 Foreman 1.00 0.25 87.50 40.00 0.55
sand m3 0.52 1,125.00 585.00 Ass. Mason 1.00 1.00 35.00 1.25 28.00 Mixer (350lit) 1.25 80.00
Aggregate 02 m3 0.78 750.00 585.00 Mason 1.00 1.00 50.00 1.25 40.00 Tools 1.25 5.60
spacer pcs 3.00 0.16 0.47 Bar bender 1.00 0.50 50.00 1.25 20.00 Pulley lift 1.25 30.00
vibrator
water lt 126.00 0.10 12.60 carpenter 1.00 0.50 50.00 1.25 20.00 1.25 50.00
7.00 C-25 concrete (50mm) 4,167.86 5,630.00
Water stopper ml 0.00 693.00 0.00 Sm. Operator 1.00 1.00 31.25 1.25 25.00
Fuel lit 0.56 24.00 13.50 Foreman 1.00 0.50 87.50 1.25 35.00
Benzine lit 0.06 27.00 1.69
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
87% 8% 5%
cement opc Qtl 4.20 600.00 2,520.00 Daily Labor 25.00 1.00 25.00 1.50 416.67 dumper 1.50 40.00
sand m3 0.60 1,125.00 675.00 Ass. Mason 1.00 1.00 35.00 1.50 23.33 Mixer (350lit) 1.50 66.67
Aggregate 02 m3 0.91 875.00 796.25 Mason 1.00 1.00 50.00 1.50 33.33 Tools 1.50 4.67
spacer pcs 3.00 0.16 0.47 Bar bender 1.00 0.50 50.00 1.50 16.67 Pulley lift 1.50 25.00
vibrator
7.00 C-30 concrete water lt 147.00 0.10 14.70 carpenter 1.00 0.50 50.00 1.50 16.67 1.50 41.67 5,291.22 7,150.00
(50mm)
Water stopper ml 0.77 693.00 534.95 Sm. Operator 1.00 1.00 31.25 1.50 20.83
Fuel lit 0.56 24.00 13.50 Foreman 1.00 0.50 87.50 1.50 29.17
Benzine lit 0.06 27.00 1.69
Type of
mat.
Unit
Qty
Rate
Cost per
unit
A- Material cost
86%
Labor by
trade
No
UF
Indexed Hr
Cost
Hrly out
put
B- Labor Cost
cost per
unit
11%
Type of
Equipment
Cost per
C-Tools & Equipment
3%
unit
Direct
costs A+
B+C
% D.C Vs
C.P.
A- Material cost B- Labor Cost C-Tools & Equipment
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
cement opc Qtl 5.60 600.00 3,360.00 Daily Labor 30.00 1.00 25.00 1.50 500.00 dumper 1.50 40.00
sand m3 0.81 1,125.00 911.25 Ass. Mason 1.00 1.00 35.00 1.50 23.33 Mixer (350lit) 1.50 66.67
Aggregate 02 m3 1.21 875.00 1,058.75 Mason 1.00 1.00 50.00 1.50 33.33 Tools 1.50 4.67
spacer pcs 3.00 0.16 0.47 Bar bender 1.00 0.50 50.00 1.50 16.67 Pulley lift 1.50 25.00
vibrator
water lt 196.00 0.10 19.60 carpenter 1.00 0.50 50.00 1.50 16.67 1.50 41.67
7.00 C-40 concrete (50mm) 6,204.09 8,380.00
Water stopper ml 0.00 693.00 0.00 Sm. Operator 2.00 1.00 31.25 1.50 41.67
Fuel lit 0.56 24.00 13.50 Foreman 1.00 0.50 87.50 1.50 29.17
Benzine lit 0.06 27.00 1.69
cement ppc qtl 0.92 450.00 414.00 Ass. Mason 1.00 1.00 35.00 0.38 93.33 Mixer (350lit) 0.38 13.33
50 cm thick stone masonry Sand m3 0.29 218.75 63.44 Daily Labor 2.00 1.00 25.00 0.38 133.33
14.00 in sub structure 1,646.08 2,230.00
(Rate=1.6m3/day/mason) fuel lit 0.02 24.00 0.46 Sm. Operator 1.00 0.00 31.25 0.38 0.00
water lit 46.00 0.10 4.60 Foreman 1.00 0.25 87.50 0.38 58.33
cement ppc qtl 0.92 450.00 414.00 Ass. Mason 1.00 1.00 35.00 0.19 186.67 Mixer (350lit) 0.19 10.67
50 cm thick stone masonry Sand m3 0.29 218.75 63.44 Daily Labor 3.00 1.00 25.00 0.19 400.00
15.00 above NGL 2,415.99 3,270.00
(Rate=1.6m3/day/mason) fuel lit 0.38 24.00 9.12 Sm. Operator 1.00 0.20 31.25 0.19 33.33
water lit 46.00 0.10 4.60 Foreman 1.00 0.50 87.50 0.19 233.33
Type of
mat.
Unit
Qty
Rate
Cost per
unit
213.88
A- Material cost
#REF!
Labor by
trade
No
UF
Indexed Hr
Cost
Hrly out
put
B- Labor Cost
cost per
unit
23.50
#REF!
Type of
Equipment
Cost per
C-Tools & Equipment
7.89
#REF!
unit
Direct
costs A+
B+C
245.26
% D.C Vs
C.P.
340.00
A- Material cost B- Labor Cost C-Tools & Equipment
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
6. Block work
20cm HCB pcs 13.00 25.00 325.00 Mason 1.00 1.00 50.00 1.25 40.00 Tools 1.25 0.15
cement ppc qtl 0.12 450.00 54.00 Daily Labor 2.00 0.67 25.00 1.25 26.67 Mixer (350lit) 1.25 1.60
20 cm thick Class B HCB
1.00 wall sand m3 0.03 218.75 6.30 Foreman 1.00 0.25 87.50 1.25 17.50 471.70 640.00
(Rate=10m2/day/mason) Water lit 4.80 0.10 0.48
cement ppc qtl 0.12 450.00 54.00 Daily Labor 2.00 0.67 25.00 1.25 26.67 Mixer (350lit) 1.25 1.60
15 cm thick HCB wall
2.00 sand m3 0.03 218.75 6.30 Foreman 1.00 0.25 87.50 1.25 17.50 406.70 550.00
(Rate=10m2/day/mason)
Water lit 4.80 0.10 0.48
cement ppc qtl 0.12 450.00 54.00 Daily Labor 2.00 0.67 12.50 1.25 13.33 Mixer (350lit) 1.25 1.60
10 cm thick HCB wall
6.01 sand m3 0.03 218.75 6.30 Foreman 1.00 0.25 87.50 1.25 17.50 339.36 460.00
(Rate=10m2/day/mason)
Water lit 4.80 0.10 0.48
cement ppc qtl 0.27 450.00 121.50 Daily Labor 2.00 1.00 25.00 0.53 95.24 Mixer (350lit) 0.53 3.81
12 cm thick Brick wall
3.00 sand m3 0.06 218.75 14.18 Foreman 1.00 0.25 87.50 0.53 41.67 2,342.14 3,170.00
(Rate=10m2/day/mason)
Water lit 10.80 0.10 1.08
sand m3 0.35 218.75 75.60 Plasterer 1.00 1.00 43.75 1.13 38.89 Mixer (350lit) 1.13 4.44
Average 10cm thick Light
7.01 wt. concrete (1:2:3). Aggregate 02 m3 0.52 421.88 218.70 daily labor 4.00 1.00 25.00 1.13 88.89 1,525.46 2,060.00
Rate=9.0m2/day/crew Water lit 96.00 0.10 9.60
sand m3 0.06 218.75 13.13 Plasterer 1.00 1.00 43.75 1.50 29.17 Mixer (350lit) 1.50 2.00
3cm thick screed in cement
8.01 mortar (1:4) Water lit 11.11 0.10 1.11 daily labor 2.00 1.00 25.00 1.50 33.33 224.64 310.00
Rate=12m2/day/crew
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
68% 31% 1%
Water proof
Primer water proof kg 0.132 86.00 11.35 0.00 0.20 43.75 3.13 0.00 Tools 3.13 0.00
applier
Apply App memeberenr or proofing membrene m2 1.05 650.00 682.50
9.01 equivalent Water proofing 693.85 940.00
Rate=12m2/day/crew
600mmx600mm
Armstrong ceiling m2 1.05 1,000.00 1050 Foreman 1 0.2 87.50 1.0 17.50
600mmx600mm Armstrong Subcontractor armstrong 1 1 100.00 1.0 100.00
1,167.50 1,580.00
ceiling
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
7x5mm purlin ml 1.20 160.75 192.90 Carpenter 1.00 1.00 50.00 3.75 13.33 Tools 3.75 0.20
Nail kg 0.07 151.00 10.57 Daily Labor 2.00 1.00 25.00 3.75 13.33
8cm dia eucalyptus ml 0.30 22.25 6.68 Foreman 1.00 0.50 87.50 3.75 11.67
1.00 7x5mm Zigba Purlin 38.53 60.00
38.33 0.20
0% 99% 1%
Chipwood 8mm
m2 1.10 92.70 101.97 Carpenter 1.00 1.00 50.00 1.25 40.00 Tools 1.25 0.60
thick
Nail kg 0.10 151.00 15.10 Daily Labor 2.00 1.00 25.00 1.25 40.00
4x5mm purlin ml 3.71 110.75 410.88 Foreman 1.00 0.50 87.50 1.25 35.00
8mm thick chipwood 693.84 940.00
8cm dia eucalyptus ml 2.26 22.25 50.29
86.81
578.24 115.00 0.60
83% 17% 0%
Gypsum board
m2 1.05 255.00 267.75 Carpenter 1.00 1.00 50.00 1.25 40.00 Tools 1.25 0.60
ceiling
Nail kg 0.03 151.00 4.53 Daily Labor 2.00 1.00 25.00 1.25 40.00
4x5mm purlin ml 3.71 110.75 410.88 Foreman 1.00 0.50 87.50 1.25 35.00
Gypsum board ceiling 849.05 1,150.00
8cm dia eucalyptus ml 2.26 22.25 50.29
Subcontractor 500.00
Aluminum windows and Aluminum
works 1 1 1.0 500.00 7,368.75 9,948.00
doors
Subcontractor
Aluminum
Aluminum Partition Wall works 1 1 500.00 1.0 500.00 7,368.75 9,948.00
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
Aluminum WC m2 1.05 7,225.00 7586.25 Foreman 1 0.2 87.50 1.0 17.50
Subcontractor
Aluminum
Aluminum Wall Cladding worksWC 1 1 500.00 1.0 500.00
8,103.75 10,950.00
Panel
Three coats plastering in Sand m3 0.06 218.75 13.13 Daily Labor 2.00 1.00 25.00 0.75 66.67 Mixer (350lit) 0.75 3.33
10.10 cement mortar (1:3) 242.27 330.00
Rate=6m2/day/plasterer Water lit 4.80 0.10 0.48 Chiseler 1.00 0.25 47.50 0.75 15.83
Foreman 1.00 0.25 87.50 0.75 29.17
67.61 170.00 4.67
28% 70% 2%
Cement ppc qtl 0.09 550.00 49.50 plasterer 1.00 1.00 43.75 1.25 35.00 Tools 1.25 0.80
Two coats plastering in Sand m3 0.02 1,125.00 21.87 Daily Labor 2.00 1.00 25.00 1.25 40.00 Mixer (350lit) 1.25 2.00
1.00 cement mortar (1:3) 176.53 240.00
Rate=10m2/day/plasterer Water lit 3.60 0.10 0.36 Chiseler 1.00 0.25 47.50 1.25 9.50
Foreman 1.00 0.25 87.50 1.25 17.50
71.73 102.00 2.80
41% 58% 2%
Cement ppc qtl 0.04 550.00 22.00 plasterer 1.00 1.00 43.75 2.00 21.88 Tools 2.00 0.25
Pointing in cement mortar Sand m3 0.01 1,125.00 9.72 Daily Labor 2.00 1.00 25.00 2.00 25.00 Mixer (350lit) 2.00 1.25
1.00 (1:3) 97.13 140.00
Rate=12m2/day/plasterer Water lit 1.60 0.10 0.16 Chiseler 1.00 0.25 47.50 2.00 5.94
Foreman 1.00 0.25 87.50 2.00 10.94
31.88 63.75 1.50
33% 66% 2%
gypsum qtl 0.06 560.00 35.00 plasterer 1.00 1.00 56.25 2.50 22.50 Tools 2.50 0.20
Sand m3 0.00 1,125.00 0.00 Daily Labor 1.00 1.00 18.75 2.50 7.50 Mixer (350lit) 2.50 0.00
Gypsum(1:3)
1.00 78.95 110.00
Rate=10m2/day/plasterer Water lit 2.50 0.10 0.25 Chiseler 1.00 0.25 47.50 2.50 4.75
Foreman 1.00 0.25 87.50 2.50 8.75
35.25 43.50 0.20
45% 55% 0%
A- Material cost B- Labor Cost C-Tools & Equipment
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
Terrazzo floor tiles m2 1.05 382.61 401.74 Tiler 1.00 1.00 43.75 2.00 21.88 Tools 2.00 0.50
cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 2.00 25.00 Mixer (350lit) 2.00 1.25
Terrazzoe floor tiles
1.00 Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 2.00 23.75 528.43 720.00
(Rate=16m2/day/tile
Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 2.00 10.94
cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 2.00 25.00 Mixer (350lit) 2.00 1.25
Ceramic floor tiles
2.00 Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 2.00 23.75 804.99 1,190.00
(Rate=16m2/day/tile
Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 2.00 10.94
cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 2.00 25.00 Mixer (350lit) 2.00 1.25
Ceramic floor tiles Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 2.00 23.75
3.00 Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 2.00 10.94 646.89 980.00
(Rate=16m2/day/tile
87% 13% 0%
800x800X1Omm
m2 1.02 850.00 867.00 Tiler 1.00 1.00 43.75 1.25 35.00 Tools 1.25 0.80
porcelain floor tiles
800x800x1Omm porcelain cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 1.25 40.00 Mixer (350lit) 1.25 2.00
2.00 floor tiles 1,043.68 1,410.00
Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 1.25 38.00
(Rate=16m2/day/tile
Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 1.25 17.50
cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 2.00 25.00 Mixer (350lit) 2.00 1.25
600x600x10mm porcelain
Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 2.00 23.75
3.00 floor tiles 1,376.19 1,860.00
(Rate=16m2/day/tile Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 2.00 10.94
cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 2.00 25.00 Mixer (350lit) 2.00 1.25
400x400x2Omm White
Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 2.00 23.75
4.00 marble tile 3,696.69 5,000.00
(Rate=16m2/day/tile Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 2.00 10.94
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
Pvc tile glue gal 0.06 1,400.00 87.50 Daily Labor 4.00 1.00 25.00 3.75 26.67
Foreman 1.00 0.25 87.50 3.75 5.83
PVC tile flooring
11.10 562.30 759.00
(Rate=12m2/day/tile)
55% 45% 0%
8mm thick ceramic
m2 1.05 551.00 578.55 Tiler 1.00 1.00 43.75 0.50 87.50 Tools 0.50 1.00
wall tiles
cement ppc qtl 0.07 450.00 33.08 Daily Labor 1.00 1.00 25.00 0.50 50.00 Mixer (350lit) 0.50 0.00
Sand m3 0.01 218.75 2.32 Chiseler 1.00 0.25 47.50 0.50 23.75
Ceramic floor tiles
12.10 Tile spacer pcs 10.00 0.25 2.50 Plasterer 1.00 0.10 43.75 0.50 8.75 831.69 1,200.00
(Rate=10m2/day/tile
White Cement Qtl 0.00 250.00 0.50 Foreman 1.00 0.25 87.50 0.50 43.75
74% 26% 0%
Ceramic skirting m2 1.05 151.00 158.55 Tiler 1.00 1.00 43.75 6.00 7.29 Tools 6.00 0.08
cement ppc qtl 0.01 450.00 4.05 Daily Labor 1.00 1.00 25.00 6.00 4.17 Mixer (350lit) 6.00 0.00
Ceramic skirting Sand m3 0.00 218.75 0.28 Chiseler 1.00 0.25 47.50 6.00 1.98
1.00 180.55 250.00
(Rate=10m2/day/tile Tile spacer pcs 0.00 0.25 0.00 Foreman 1.00 0.25 87.50 6.00 3.65
White Cement Qtl 0.00 250.00 0.50
cement ppc qtl 0.07 450.00 33.08 Daily Labor 1.00 1.00 25.00 0.50 50.00 Mixer (350lit) 0.50 0.00
200x300x8mm glazed
1.00 ceramic wall tile Sand m3 0.01 218.75 2.32 Chiseler 1.00 0.25 47.50 0.50 23.75 778.14 1,100.00
(Rate=10m2/day/tile Tile spacer pcs 10.00 0.25 2.50 Plasterer 1.00 0.10 43.75 0.50 8.75
White Cement Qtl 0.00 250.00 0.50 Foreman 1.00 0.25 87.50 0.50 43.75
cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 1.25 40.00 Mixer (350lit) 1.25 8.00
Granite floor tiles
13.10 Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 1.25 38.00 4,645.18 6,300.00
(Rate=10m2/day/tile
Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 1.25 17.50
cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 1.25 40.00 Mixer (350lit) 1.25 8.00
Granite wall tiles Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 1.25 38.00
2.00 4,907.68 6,700.00
(Rate=10m2/day/tile Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 1.25 17.50
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
300*800 imported
m2 1.05 4,525.00 4,751.25 Tiler 1.00 1.00 43.75 1.25 35.00 Tools 1.25 0.80
marble
cement ppc qtl 0.09 450.00 39.38 Daily Labor 2.00 1.00 25.00 1.25 40.00 Mixer (350lit) 1.25 8.00
Marble floor tiles
2.00 Sand m3 0.01 218.75 2.76 Chiseler 1.00 1.00 47.50 1.25 38.00 4,933.93 6,700.00
(Rate=10m2/day/tile
Tile spacer pcs 5.00 0.25 1.25 Foreman 1.00 0.25 87.50 1.25 17.50
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
Glazing work
5mm thick clear
Gal 1.10 1,200.00 1,320.00 Glazier 1.00 1.00 43.75 1.88 23.33 Tools 1.88 0.27
glass
Putty glass qtl 0.50 15.00 7.50 daily labor 1.00 1.00 25.00 1.88 13.33
41.00 5mm thick glass 1,364.43 1,850.00
97% 3% 0%
wash down water Sanitary
pcs 1.00 12,000.00 12,000.00 1.00 1.00 48.08 0.25 192.31 Tools 0.25 3.00
closet technician
Daily Labor 1.00 1.00 25.00 0.25 100.00
Chiseler 1.00 0.25 47.50 0.25 47.50
43.00 WC Installation 12,386.56 16,730.00
Plasterer 1.00 0.25 43.75 0.25 43.75
A+
Indexed Hr
% D.C Vs
Labor by
45.00 Urinal Installation 10,457.71 14,120.00
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
UF
Hr
costs
10,200.00 255.71 2.00
98% 2% 0%
Sanitary
Shower tray pcs 1.02 5,000.00 5,100.00 1.00 1.00 48.08 0.38 128.21 Tools 0.38 2.00
technician
Daily Labor 1.00 1.00 25.00 0.38 66.67
Chiseler 1.00 0.25 47.50 0.38 31.67
46.00 Shower Tray Installation 5,357.71 7,240.00
Plasterer 1.00 0.25 43.75 0.38 29.17
Framed crystal
glass mirror, back- Sanitary
pcs 1.02 1,000.00 1,020.00 1.00 1.00 48.08 0.63 76.92 Tools 0.63 1.20
silvered, minimum technician
6mm thick
Framed crystal glass
46.00 mirror, back-silvered, Daily Labor 1.00 1.00 25.00 0.63 40.00 1,246.12 1,690.00
minimum 6mm thick Chiseler 1.00 0.50 47.50 0.63 38.00
Plasterer 1.00 0.50 43.75 0.63 35.00
Foreman 1.00 € 0.25 € 87.50 0.63 35.00
Frameless crystal
glass mirror, back- Sanitary
pcs 1.02 800.00 816.00 1.00 1.00 48.08 0.63 76.92 Tools 0.63 1.20
silvered, minimum technician
6mm thick
Frameless crystal glass
46.00 mirror, back-silvered, Daily Labor 1.00 1.00 25.00 0.63 40.00 1,042.12 1,410.00
minimum 6mm thick Chiseler 1.00 0.50 47.50 0.63 38.00
Plasterer 1.00 0.50 43.75 0.63 35.00
Foreman 1.00 € 0.25 € 87.50 0.63 35.00
A+
Indexed Hr
% D.C Vs
Labor by
Hrly out
Cost per
Cost per
cost per
Type of
Type of
Direct
S.N. Description of work
trade
Unit
Cost
mat.
Rate
unit
unit
unit
B+C
Qty
C.P.
put
No
1 uPVCPipe 255.78 350.00
UF
Hr
costs
251.88 3.87 0.03
98% 387% 3%
6mm thick sheet 751.00 welder
metal m2 1.05 788.55 1 1.00 43.75 5.00 8.75 Tools 62.5 0.008
6mm thick steel , side Electro No 0.13 3.50 0.44 Carpenter 2 1.00 50.00 5.00 20.00
gurder, landing, rizer and Cut-dis No 0.05 61.00 3.05 Daily Labor 10 1.00 25.00 5.00 50.00 ding machine 62.5 1.20 875.50 1,190.00
tread steel sheet Foreman 1 0.20 87.50 5.00 3.50
Resource sheet