Professional Documents
Culture Documents
I General Requirements
1. Mobilization
2. Temporary Facilities
2.1 Field offices including conference room/aircon lot
2.2 Temporary Power lot
2.3 Temporary Water lot
2.4 Temporary Fire Extinguisher - 10 lbs. ABC lot
2.5 Temporary T&B / Portalets lot
2.6 Temporary Fence / Board-ups, if required lot
2.7 Temporary Plants, storage, workshops lot
3. Equipment & Accessories lot
4. Site Safety, Protective nets/Deflectors, Security, Sanitation lot
5. Housekeeping & Adequate Protection for completed works lot
6. Daily disposal of construction debris / waste to include other lot
contractors / OSM
7. Preparation of as-built lot
8. Preparation of coordination plans, shop drawings, submittals lot
9. Supervision & Coordination lot
10. Material Testing lot
11. Demobilization lot
12. Contractor's tax lot
13. Others ( Please specify ) lot
- Communication
Total General Requirements
III Siteworks
1. Clearing and Grubbing lot
2. Dewatering lot
3. Dismantling, Demolition, Salvaging Works Needed lot
4. Disposal of Debris lot
5. Provision of temporary ramps including ramp protection lot
6. Fence (G.I. Corrugated sheets #26 painted both face) lm
Incl. Frames braces / supports
7. Others to complete the works ( pls. Specify )
Sub - Total Site Works
Miscellaneous Works
Item Particulars Qty. / Unit Duration Start Finish M1 M2 M3 M4 M5 M6 M7 M8 M9
1. Water Stops lm
2. Dewatering Works lot
3. Construction and Expansion Joints
3.1 Construction Joints lm
3.2 Expansion Joints lm
4. Sealant with Backer Rods on Both sides @ Typical Exterior lm
RC Wall to Beam/ Column Connections
5. Seismic Gap lm
6. Others ( Please Specify )
Wall Finishes
NOTE: PAINTING WORKS ARE EXCLUDED
1. Poured concrete w/ waterproofing m²
2. Poured concrete w/ moisture barrier m²
3. Smooth cement painted finish m²
4. Poured concrete off-form finish w/ 1.2m high m²
5. Smooth cement finish m²
6. Straight to finish m²
7. Smooth Cement Elastomeric Paint Finish m²
8. Other Wall Finishes (Specify)
Plastering to CHB Walls (interior) m²
Plastering to CHB Walls (exterior) m²
Rubbed Concrete Finish for concrete surfaces (interior) m²
Rubbed Concrete Finish for concrete surfaces (exterior) m²
Ceiling Finishes
NOTE: PAINTING WORKS ARE EXCLUDED
1. Poured concrete off-form skim coated finish m²
2. Other Ceiling Finishes (Specify) m²
GUARANTEED QUANTITIES
CEMENT (in bulk)
CEMENT (in bags)
REBARS: Grade 60
REBARS: Grade 40
Submitted by:
Company Name
Authorized Representative
Const Floor Area