CONSTRUCTION COST BREAKDOWN SHEET FOR


A 2 STOREY BUILDING WITH
SIX UNITS OF 2 BEDROOMS FLAT

MATERIAL / LABOUR COSTS

Unit Quantity
No Description/Items Total
price
FROM SECOND FLOOR DECK TO WALL PLATE LEVEL
( Without Concrete Fascia )
1 9'' Block 320 2,600 pcs. 832,000.00
2 6'' Block 260 500 pcs. 130,000.00
3 Cement 4,700 120 bags 564,000.00
3 "
4 / stone (chippings)
4 360,000 25 tons 360,000.00
5 Sharp Sand 40,000 4 trips 160,000.00
6 16mm iron rod (deformed) 7,650 60 lengths 459,000.00
7 12mm iron rod (deformed) 4,450 70 lengths 311,500.00
8 8mm iron rod (deformed) 2,300 70 lengths 161,000.00
9 Binding wire 850 40 kg 34,000.00
10 1 x 1 x 12 board (mid west) 1,750 ??? ???
11 2 x 2 x 12 h/w puline 270 ??? ???
12 2 x 4 x 16 h/w rafter 900 20 pcs. 18,000.00
13 2" nail 14,000 1 bag 14,000.00
14 3" nail 14,000 1 bag 14,000.00

Total N3,057,500

Labor costs N 850,000,00

T0TAL SUM N3,907,500

this stage comprised from Second floor to wallplate level only.


NOTE : without (Concrete Fascia)