You are on page 1of 11

BILL OF QUANTITY PREPARATION & TOTAL COST E STIMATION

Summary Sheet
DESCRIPTION AMOUNT (BIRR)

A Sub-Structure

1 Earth Work 291,635.35


2 Stone Masonry 47,692.28
3 Concrete Work 1,731,930.60

Sub-Total A 2,071,258.23

B Super-Structure

1 Concrete Work 3,341,791.65


2 Block Work 373,263.143
3 Roofing Work 116,401.95
4 Carpentry & Joinery Works 340,189.56
5 Metal Works 1,820,270.5
6 Finishing Works 2,963,217.2
7 Glazing Work 216,000.00
8 Painting Work 294,756.00
9 Sanitary Installation Work (15%) 1,730,572.20
10 Electrical Installation Work (15%) 1,730,572.20

Sub-Total B 14,998,290.58

Total Summary A + B 17,069,548.58

Page 1
CONTINGENCY 10% 1,706,954.858
Add 15% Vat 2,560,432.30

GRAND SUMMARY 19,629,980.87

Page 2
SPECIFICATION AND BILL OF QUANTITIES FOR (G+6) RESIDENTIAL BUILDING
TOTAL
UNIT
ITEM DESCRIPTION UNIT QUANTITY AMOUNT
PRICE
(Birr)
A. SUB STRUCTURE
1. EARTH WORKS
1.1 Execute site clearing to an average depth of
20cm to remove top organic soil. Price also
m² 765.50 12.38 9476.89
includes grabbing roots and tree stamps where
such are encountered
1.2 Execute deep excavation in ordinary soil for
septic tank to an average depth of not exceeding m³ 63.00 136.00 8568.00
300cm
1.3 Pit excavation in soft rock to a depth not
m3 - -
exceeding 150 cm
1.4 footing excavation in soft rock to a depth greater
m3 810.30 136.00 110,200.80
than 150 cm but not exceeding 200cm
1.5 Trench excavation in ordinary soil for
m3 53.76 80.51 4328.21
construction of stone masonry under grad beams
1.6 Fill around foundation with selected granular
material imported from outside and compact in m3 521.50 133.58 69661.97
layers not exceeding 20 cm thick
1.9 Cart away and spread surplus excavated material
m³ 494.88 45.53 22531.88
to municipality approved fill site

1.10 Supply and pack 25cm thick hard core bedding to


semi basement slab in basaltic stone or
m² 618.00 108.20 66867.60
equivalent, voids and surface filled and blind
with hand crushed and chips of same stone

Total carried to summary


291,635.35

Page 3
UNIT
ITEM DESCRIPTION UNIT QUANTITY
PRICE
2. STONE MASONRY
2.1 Supply and construct stone masonry foundation
wall bedded and joined in 1:4 cement mortar m³ 35.85 995.60 35,692.28
below natural ground level
2.2 Ditto as item 2.1 above natural ground level m³ 10.00 1200.00 12,000.00
Total carried to summary 47,692.28
3. CONCRETE WORKS
3.1 Supply and cast 5cm thick lean concrete in C-5
concrete quality with minimum cement content
of 150Kg/ m3under:
a) Isolated footing m2 344.96 70.00 24,147.20
b) Stone masonry m² 35.85 70.00 2,509.50
c) Ground floor grade beams. m² 35.85 70.00 2,509.50
3.02 Supply and cast according to design reinforced
concrete class C-25, prepared following mix
design based on laboratory test, into form work
and vibrated around steel reinforcement bars
(Steel reinforcement bars and form work
measured separately) for:

a) footing pad m3 275.97 2799.80 772,660.80


b) Foundation column m3 8.45 2799.80 23,658.31
c) Ground floor grade beams. m3 33.10 2799.80 92,673.38
d) Ground floor slab (10cm thick) with C-15 m² 430.92 330.00 142,203.60
3.3 Provide and fix in position steel panel form
work for:
a) Isolated footing m² 394.24 140 55,193.60
b) Foundation column m² 84.48 140 11827.20
c) Ground floor grade beams m² 226.00 140 31,640.00
3.4 Provide and put in place steel reinforcements of
the following type and diameter according to
structural drawings. Price includes tying wire

Page 4
and brushing bars off elements compromising
essential bondage with concrete

a) Dia. 6 mm deformed bar kg 342.89 29.93 10,262.70


b) Dia. 8 mm deformed bar kg 1230.00 29.93 36,813.90
c) Dia. 10 mm deformed bar kg 3250.00 29.93 97,272.50
d) Dia. 12 mm deformed bar kg 3840.00 29.93 114,934.20
e) Dia. 14 mm deformed bar kg 4578.67 29.93 137,039.60
g) Dia. 24 mm deformed bar kg 5900.00 29.93 176,587.00
Total carried to summary 1,731,930.60

TOTAL
UNIT
ITEM DESCRIPTION UNIT QUANTITY AMOUNT
PRICE
(Birr)
B. SUPERSTRUCTURE

1. CONCRETE WORKS
1.1 Supply and cast according to design reinforced
concrete class C-25, prepared following mix
design based on laboratory test, into form work
and vibrated around steel reinforcement bars
(Steel reinforcement bars and form work
measured separately) for:
a) Elevation columns. m³ 128.13 2799.80 358,738.30
b) Intermediate beam m³ 356.01 2799.80 996,765.20
c) 15cm suspended floor slab m² 159.2 2799.80 445,728.20
d) Top tie beam m³ 25.43 2799.80 71,198.9
e) Stair case and landing m³ 40.10 2799.80 112,271.98
f) Ribbed slab toppings m³ 25.76 2799.80 72,122.85
g) Shear walls m³ 18.90 2799.80 52,916.22
1.2 Provide and fix in position steel panel or wooden
form work whichever is appropriate for:

Page 5
a) Elevation columns m² 133.10 140 18634
b) Intermediate beam m² 847.50 140 118,650
c) 15cm suspended floor slab m² 120.00 140 16800
d) Top tie beam m² 226.00 140 31,640
e) Stair case and landing m² 95.70 140 13,398
f) for shear walls m² 235.20 140 32,928
1.3 Provide and put in place steel reinforcements of
the following diameter and type according to
structural drawings. Price includes tying wire
and brushing bars off elements compromising
essential bondage with concrete
a) Dia. 6 mm deformed bar Kg 4890.98 29.93 146,387.03
b) Dia. 8 mm deformed bar Kg 8890.00 29.93 266,077.70
c) Dia. 10 mm deformed bar Kg 12976.00 29.93 388371.68
d) Dia. 12 mm deformed bar Kg 16790.00 29.93 502524.7
e) Dia. 14mm deformed bar Kg 34980.00 29.93 1046951.1
f) Dia. 16 mm deformed bar Kg 22459.00 29.93 672197.87
g) Dia. 20 mm deformed bar Kg 13438.00 29.93 402199.34
h) Dia. 24 mm deformed bar Kg 9809.00 29.93 293583.37
Total Carried to Summary 3,341,791.65

TOTAL
UNIT
ITEM DESCRIPTION UNIT QUANTITY AMOUNT
PRICE
(Birr)
2. BLOCK WORKS AND PARTITION
WALL
2.1 20cm thick class C HCB wall both sides
left for plastering; bedded in cement m² 737.81 301.14 222,184.103
mortar (1:3).Price shall include mortar bed

Page 6
2.2 10cm thick class C HCB wall both sides
left for plastering; bedded in cement m² 599.52 252.00 151,079.04
mortar (1:3).Price shall include mortar bed

Total Carried to Summary 373,263.143


3. ROOFING WORKS
3.1 Supply and fix G-30 EGA sheet roof
cover. Price also includes fixing
accessories. Horizontal projection is taken m2 721.67 147.15 106,193.7
and trusses and purloin measured
separately
3.2 Supply and fix G-30 galvanized flat metal
sheet gutter dev. length 50cm. Price
ml 85.00 82.86 7043.1
includes two coats of anti-rest paint and
three coats of synthetic enamel paint
3.3 Supply and fix G-28 galvanized flat metal
sheet copping dev. Length 50cm. Price
ml 35.00 64.59 2260.65
includes two coats of anti-rest paint and
three coats of synthetic enamel paint
3.4 Supply and fix PVC down pipe with its
ml 25.00 36.18 904.5
Dia. 80 mm
Total Carried to Summary 116,401.95

Page 7
TOTAL
UNIT
ITEM DESCRIPTION UNIT QUANTITY AMOUNT
PRICE
(Birr)
4. CARPENTRY & JOINERY WORKS
4.1 Supply and fix 40mm thick semi solid door, with
KERERO wood double vertical members and
five horizontal frames in the following types and
sizes. Door panels shall be laminated with 4mm
kerero plywood. Price shall also include hinges,
door lock and varnish paint
a) D1: 100x 210cm m2 132.30 2252.33 297983.3
4.2 Supply and fix well finished zigba wood 25x200
mm fascia board ml 85.00 30.47 2589.95

4.3 Supply and fix RHS metal truss as per the detail
drawing. Price shall include all the necessary
accessories
a) 60×60×3 mm upper and lower rafter ml 205.00 30.28 6207.4
b) 60×60×3 mm diagonal & vertical members ml 271.10 30.28 8208.91
c) 50×50×3mm purlin
ml 960.00 26.25 25200

Total Carried to Summary 340,189.56


5. METAL WORKS
5.1 Supply and fix meta1 windows and doors made
of 38mm thick Aluminum profile, all according
to the drawing. Price shall include cylindrical
lock handle hinge rubber stopper and all other
necessary accessories
a) Windows

Page 8
a) W1 size:90x90cm m2 51.03 1334 68074.02
b) W2 size: 90x110cm m2 62.37 1334 83201.58
c) W3 size: 120x160cm m2 120.96 1334 161,360.64
d) W4 size:180x100cm m2 1.80 1334 2401.2
e) W5 size:200x160cm m2 195.20 1334 260,396.8
f) W6 size:200x180cm m2 21.60 1334 28814.4
b) Doors 1334
D1 size: 80x210 cm m2 105.84 1334 141,190.56
D1 size: 90x210cm m2 119.07 1334 158,839.4
D2 size: 120x210 cm m2 158.76 1334 211,785.84
D3 size. 150x210cm m2 3.15 1334 4202.1
Total Carried to Summary 1,820,270.5
6. FINISHING WORKS
6.1 Apply three coats of plastering to the external
and internal HCB wall, to concert ceiling and
staircase soffit and to exposed beam & columns
in cement mortar (1:3). Price shall include pre-
cleaning and preparation of the surface

a) To external wall m2 1200.00 90.00 108000


b) To internal HCB wall m2 6434.24 80.00 514,739.2
c) To concrete ceiling and staircase soffit m 2
2302.00 95.00 218,690
d) To exposed beam and columns m2 424.00 95.00 40,280
6.2 Ditto as item 6.1 but two coats to receive
ceramic wall m2 364.00 62.00 22,568
6.3 20 mm thick Terrazzo floor tile price shall
m2 1890.00 400.00 756,000
include 3 cm thick cement screed

Page 9
6.4 100 mm high ceramic skirting including mortar
backing ml 3384.00 150.00 507600

6.5 Supply and fix 200x300x6mm thick imported


ceramic wall cladding bedded on cement mortar
1:3 mixes. Price shall include white cement m2 364.00 300.00 109,200
pointing
6.6 Supply and fix Italian chip wood ceiling plate as
per the detail drawing. Price shall include all m2 322.00 220.00 70840
necessary fixing accessories
6.7 Supply and fix damp proofing material for the
concrete roof slab and to the basement parking m2 45.00 340.00 15300
floor
Total Carried to Summary 2,963,217.2
7.GLAZING WORK
7.1
Supply and fix 5mm thick tinted glass to
windows and doors. Price shall include m2 480.00 450.00 216000
aluminum gaskets and silicon sealant
Total Carried to Summary 216,000
8. PAINTING
8.1
Apply three coats of plastic emulsion paint to:
a) To external & internal wall m2 10350 22.00 227700
b) To exposed beam and column m 2
424.00 22.00 9328
c) To concrete ceiling and staircase m2 2302.00 22.00 50644
d) To chip wood ceiling m 2
322.00 22.00 7084
Total Carried to Summary 294,756

Page 10
CONCLUSION AND RECOMMENDATION

From the case study it is obtained that the condominium buildings have minor design problems
like insufficient area allocation for rooms, kitchens, corridors etc. The stair case is also not
accessible for disable persons. Beside to this the quality of construction material, sanitary and
electrical fittings and improper installations.
To alleviate this problem special attention is taken in designing process. The proposed typology
is designed considering economy, safety and aesthetic values. Since we used common walls,
common stairs, agro stone partition wall, energy saving lamps such as fluorescent and compacted
lamps the designs are economical and cost efficient.
From this project the lesson we learnt are the following: it improves the knowledge and skill of
structural design, architectural design, electrical installation, sanitary design and computation of
bill of quantity. It helps us to acquire knowledge through discussion, referring different books,
consulting our advisors, familiarizing with EBCS (Ethiopian Building Code Standards). In
addition to this familiarize with different software’s such as Arch cad, AutoCAD, SAP and
ETABs.
The project covers the majority of the courses which are in the curriculum. It helps us to revise
the previous courses and to aqua ire fundamental knowledge. So, the project should continue as
it is.

Page 11

You might also like