You are on page 1of 3

Dire Dawa University Construction Project Office

Specifications & Bill of Quantities


for Fence Work (Bill no.3)

Item
Description Unit Qty Rate Amount
No.

A. SUB-STRUCTURE

1. EXCAVATION & EARTH WORK

Clearing of the site to remove top soil and other


rubbish materials to an average depth of 30cm and
1.1
cutting trees as per the Engineer's Instruction, work
shall includes demolishing of existing fence structures
2
other materials that obstruct the work. m 1008.00

1.2 Bulk excavation in ordinary soil, depth not exceeding


3
2.0m. m 144.90

1.3 Bulk excavation in weathered rock, depth not


exceeding 2.0m. m3 724.50

1.4 Bulk excavation in hard rock, depth not exceeding


2.0m. m3 96.60

Backfill around built structures with selected soil


materials. Compacted and well rammed in 20cm thick
1.5 layers until it attains a minimum of 95% proctor dry
density and optimum moisture content. The degree of
compaction and the selected materials should be
approved by the Engineer. m3 386.40

1.6 Cart away excavated material as per engineer's


instruction . m3 0.00

Sub-Total (1)

2. CONCRETE WORK
Lean Concrete (C-5) 50mm thick, under strip footing
2
2.1 pads and/or masonry walls. m 378.00

Reinforced Concrete Class C-25, minimum of 360 kg


cement per meter cube of concrete. Filled into
formwork and vibrated around reinforcement
(formwork and reinforcement bar are measured
2.2 separately). In:

a) Strip Footing Pads m3 75.60

b) Grade Beams m3 32.00

2.3 Provide, Cut & Fix in position Formwork to:-

a) Strip Footing Pads m2 89.04

b) Grade Beams m2 129.40

7
Specifications and Bill of Quantities
Dire Dawa University Construction Project Office

Item
Description Unit Qty Rate Amount
No.

2.4 Mild Steel Reinforcement Bars (S-300), work includes


cutting, bending & placing in position according to the
drawings. Price includes tying wires.

a) Diameter 8mm deformed bar Kg 838.03

b) Diameter 12mm deformed bar Kg 4784.10

Supply & Install Reinforced Concrete Drain Pipes as


per the detail drawing and engineer's instruction ,
2.5
Price includes bedding, jointing and all other
necessary works.The pipe shall be laid with the
bottom portion on Class C-25 concrete.

a) Diameter of 250mm ml 42.00

Sub-Total (2)

3. MASONRY WORK

Stone Masonry of Class "B" for retaining walls below &


above N.G.L. Masonry made from the stones shall
consist of shaped, dressed, and laid broken-coursed in
3.1 cement mortar of 1:3 ratio. m3 577.50

Sub-Total (3)
B. SUPER-STRUCTURE

4. CONCRETE WORK
Reinforced Concrete Class in C-25, minimum of 360
kg cement per meter cube of concrete. Filled into
4.1 formwork and vibrated around reinforcement
(formwork and reinforcement bar are measured
separately) In:

a) Columns m3 9.65
3
b) Copping m 9.60

4.2 Provide, cut and fix in position sawn structural wood


or steel formwork which ever is appropriate, to:-

a) Columns m2 192.96

b) Copping m2 96.00

4.3 Mild Steel Reinforcement Bars (S-300),work includes


cutting, bending & placing in position according to the
drawings. Price includes tying wires.

a) Diameter 8mm deformed bar Kg 370.51

b) Diameter 12mm deformed bar Kg 1213.72

Sub-Total (4)
8
Specifications and Bill of Quantities
Dire Dawa University Construction Project Office

Item
Description Unit Qty Rate Amount
No.

5. BLOCK WORK

Solid Concrete Block (SCB) Wall of "Class B'' quality


and size of 20X20X40cm bedded in cement sand
5.1 mortar 1:3. m2 444.16

Solid Concrete Block (SCB) Wall of "Class B'' quality


and size of 15X20X40cm bedded in cement sand
5.2 mortar1:3. m2 34.56

Sub-Total (5)

6. PLASTERING & POINTING WORK


Apply 3 coats of Plaster in cement mortar 1:3 mix
6.1 ratio to all SCB Wall surfaces. m2 973.76

Ditto Item 6.1 but to Grade Beam, Column & Copping


6.2 exposed surfaces. m2 464.24

Pointing to Masonary Wall Foundation above N.G.L


6.3 with 1:3 cement mortar ratio. m2 630.00
Grooved mortar finish on surface of solid concrete
block as per the given drawing with cement sand
6.4 mortar mix 1:3 m2 92.16

Sub-Total (6)

3. Fence Work Summary of Measurement


A. SUB-STRUCTURE

1. EXCAVATION & EARTH WORK

2. CONCRETE WORK

3. MASONRY WORK

Sub-Total (A)

B. SUPER-STRUCTURE

4. CONCRETE WORK

5. BLOCK WORK

6. PLASTERING & POINTING WORK

Sub-Total (B)

Total Sum of Bill no. 3 =

9