You are on page 1of 8

.

Bill of Quantity (BOQ) FOR G+2 Resident

Unit Qty Amount


No .
Description Unit Rate
A. SUB-STRUCTURE
1. EXCAVATION & EARTH WORKS
Excavate for site clearing to a depth of 20 cm to
1.1 remove top soil and vegitables m2 230 10 2300

pit excavation in ordinary soil for isolatig footing to a


1.2 depth of not exceeding 150mm m3 156 25 3900

trench excavation for masonrry foundation in


1.4 ordinarry soil to a depth of 850mm m3 120 25 3000

back fill around footing, masonrry foundation and


under hard-core to maintain the desired level with
1.5 selected borrowed material and compact in layers m3 70 40 2800
25 cm thick basaltic or equivalent stone hardcore ,
consolidated and blinded with crushed stone.
1.6 m3 170 60 10200
Cart away surplus excavated material to a distance
1.7 of appropriate tip. m3 66.5 30 1995
TOTAL CARRIED TO SUMMARY 24195
2. CONCRETE WORK
50 mm thick lean concrete quality C-5, 150 kg of
cement/m3: under
2.1
a.isolated footing m2 33 65 2145
b.massonry foundation around the building m2 52 65 3380

c. under masonry wall suporting staircase beam m2 65 0


d.gread beams m2 32 65 2080
Reinforced concrete quality C-25,minimum cement
content 360 kg of cement/m3 filled in to form work
and vibrated around rod reinforcement (formwork
and reinforcement measured separately)

2.2
a) To footing m3 22 2400 52800
b) To Foundation column m3 6 2400 14400
c) To grade beam m3 15.6 2400 37440
d) Entrance stair m3 8.9 200 1780
e) 10cm thick ground slab m3 27.0825 150 4062.375
2.30 Provide, cut and fix in position sawn zigba wood or
steel formwork which ever appropriate.

a) For Footings. m2 32 120 3840


b) For ground columns. m 2
35 120 4200
c) For grade beams. m 2
65 120 7800
2.40 Mild steel reinforcement according to structural
drawings. Price includes cutting, bending, placing in
position ,tying wire and required spaces.

b) dia 8 mm deformed bar kg 600 34 20400


c) dia 10 mm deformed bar kg 1300 34 44200
e) dia 14 mm deformed bar kg 600 34 20400
f) dia 16 mm deformed bar kg 9354 34 318036
2.5 f)10mm thick styrofoam expansion joint filler board
100mm wide in movement joint between edge of
concrete bed and grade beams ml 95 110 10450
TOTAL CARRIED TO SUMMARY 547413.375
3. MASONRY WORKS
400 mm thick basaltic or equivalent type stone
masonry bedded in cement mortar(1:3) mix below
ground surface. price shall include cement mortar
bed.
3.1 m3 165.6 750 124200
TOTAL CARRIED TO SUMMARY 124200
B. SUPERSTRUCTURE
1. CONCRETE WORK
1.10

Reinforced concrete quality C-25,minimum cement


content 360 kg of cement/m3 filled in to form work
and vibrated around rod reinforcement (formwork
and reinforcement measured separately)
a)To elevation columns m3 23 2400 55200
b) To intermediate beam m3 34 2400 81600
c) To top tie beams m3 21.8 2400 52320
d.cannopy slab supporting beam m3 34.5 200 6900
e.stair case m3 32.6 2400 78240
f. To 150mm thick first floor slab m2 180.8 2400 433920
1.20 Provide, cut and fix in position sawn zigba wood or
steel formwork which ever appropriate.

a) For elevation columns m2 250 160 40000


b) To intermediate beam m2 250 160 40000
c.stair case m2 33.2 160 5312
d. To top tie beams m2 180 160 28800
e.cannopy slab supporting beam m2 33.6 160 5376
f. To 150mm thick first floor slab m2 66.5 160 10640
1.30 Mild steel reinforcement according to structural
drawings. Price includes cutting, bending, placing in
position ,tying wire and required spaces.

b) dia 8 mm deformed bar kg 788.36 34 26804.24


b) dia 10 mm deformed bar kg 3523.2 34 119788.8
d) dia 14 mm deformed bar kg 165.2 34 5616.8
e) dia 12 mm deformed bar kg 350.3 34 11910.2
TOTAL CARRIED TO SUMMARY 1002428.04
2. BLOCK WORK
2.1
Class - C 200mm thick HCB wall which can satisfy the
designed strength , bedded in cement mortar
(1:3).Price shall include mortar bed
m² 560 150 84000
2.4 Ditto, but 150mm thick . m² 56 100 5600
TOTAL CARRIED TO SUMMARY 89600
3. ROOFING .
3.1

Roof cover in percolated or galvanized EGA 400 (t=


0.4mm), fixed to RHS with G-28 flat sheet dev.
Length 310 mm Ridge cap UV resistant washers.
(Purlins measured separately and roof measured in
horizontal projection.
3.3

G-28 Galvanized sheet metal gutter. price includes


two coats of anti-rust and synthetic paint ml 170 65 11050
3.4 dia. 100mm. Pvc down pipe ml 560 70 39200
3.5 ditto to item 3.4 but dia.80mm ml 3.76 70 263.2
3.6
Supply and fix wire mesh ventilation size 60x60mm
(in flat metal frames) under eave with combination
of ribbed sheet size 120x60mm nailed to zigba wood
battens size40x50mm. Price include three coats of
oil paint and all other necessary accessories to
complete the work.
m2 18.8 62.3 1171.24
TOTAL CARRIED TO SUMMARY 52855.68
5. METAL WORK
5.1 Windows with aluminium frame & 6mm thick clear
glass profile all as per the engineers approval and
window door schedule.

WINDOWS
c)W2' Size (670x1000)mm No 12 2000 24000
d)W3 Size (2000x2400)mm No 12 3000 36000
e)W4 size(2000x25000)mm No 9 2500 22500
5.2 door with aluminium frame and full 6mm thick
tinted glass
DOORS
a)WD1 Size 1400X3000mm No 32 2500 80000
b)D3' = size: 3000x3000mm No 17 5000 85000
TOTAL CARRIED TO SUMMARY 247500
7. FINISHING

finishing work can include all surface pre clearing


preparation application of finish, polishing and
clearing of the end finishing work

7.1 apply for two coats of plaster in cement mortar


mix1:3
a)to external walls m² 84.49 80 6759.2
b)ditto but to external beam faces m² 25.97 80 2077.6
c)ditto but to partition walls m² 80.78 80 6462.4
d)ditto but to concret ceiling m² 982.27 110 108049.7
7.2 150x150x7.94mm ceramic wall tile m² 162.54 160 26006.4
7.3 300x300x8mm glazed ceramic tile for locker rooms,
toilets and kitchens. m² 120.25 160 19240
7.4 pvc tile finish for ground floors m² 862.07 140 120689.8
7.5 skirting
a)100mm high ceramic skirting ml 515.65 120 61878
b)100mm terazo skirting for internal corrider ml 5.9 200 1180
c)100mm high pvc skirting ml 329.98 140 46197.2
TOTAL CARRIED TO SUMMARY 398540.3
8. GLAZING
a)supply and properly fix clear glass free from any
defects to aluminium frame windows(6mm thick).
m² 17.3 300 5190
b)ditto but tinted glass for doors WD1 and D3' 4.2 300 1260
c)wooden doors (mahogany)play wood for doors D1,
D2, D3 m2 2.5 300 750
TOTAL CARRIED TO SUMMARY 7200
9. PAINTING
9.1 Apply three coats plastic emulsion paint to
a)internal wall surface. m² 25.3 30 759
b)ditto to exposed columuns m2 21.3 30 639
c)Ditto but to exposed beams m² 90.3 30 2709
d)Ditto but to RC ceiling m² 182.27 28 5103.56
TOTAL CARRIED TO SUMMARY 9210.56
10. Electrical Installation
Surface mounted distribution board,SDB enclosure with
lockable door,and with phase neutral and earth bus-bar of
25A rating and consisting of:-
10.1
1pcs of ACB of 10A/1P Pcs - 140.00 -
Light point fed through pvc insulated conductor of 2x
2.5mm2 in thermoplastic conceits of 13mm under surface
including junction boxes with cover as well flush mounted
switch
No 2.00 300.00 600.00
Flush mounted socket outlets of 10A/1ph fed through pvc
insulated conductor of 3x 2.5mm in thermoplastic conductor
of 3x2.5mm in thermoplastic conduit of f16 under surface
including junction boxes, screw type is isolating caps and
cover
No 2.00 180.00 360.00
Type of light fittings
a.Ceiling mounted crystal lump No 2.00 100.00 200.00
b.Wall mounted crystal lump No - 100.00 -
TOTAL CARRIED TO SUMARY 1,160.00
GRAND TOTAL #REF!
SUMMARY FOR G+2 PROJECT

Item no. A. Sub Sturucture Amount in birr


1 EXCAVATION & EARTH WORK 24195
2 CONCRETE WORK 547413.375
3 MASONRY WORK 124200
SUB TOTAL (A) 695808.375
B. Supper Sturucture
1 CONCRETE WORKS 1002428.04
2 BLOCK WORKS 89600
3 ROOFING 52855.68
5 METAL WORK 247500
7 FINISHING WORKS 398540.3
8 GLASING 7200
9 PAINTING 9210.56
TOTAL (B) 1807334.58
TOTAL (A+B) 2503142.955
15%VAT 375471.44325
GRAND Total 2,878,614.40
OWNER:-x