NURSERY & KINDERGARTEN SCHOOL

Bid Proposal

Prepared by: ALOOL CONSTRUCTION COMPANY

Signature: ____________________________

Date: 25/01/2023

Bid for: NURSERY & KINDERGARTEN SCHOOL


PROJECT SCOPE

Project Summary
Construction of new activity hall, new offices, 4 bathroom, demolition of partition walls, enlarging door
& window openings and closing old opening, painting the whole building, ceiling interior design, office
interior design, installing new glass doors and windows , installing an electric wires and appliances,
installing plumbing appliances and accessories, construction of playing ground.
PROJECT COSTS

Required Materials and labor cost

BOQ & COST ESTIMATION FOR CONSTRUCTION MAIN BUILDING


Unit
Item Quantit Item Sub- Item Total Amount
Item Description Unit Pric
No. y Total US$ US$
e
CONSTRUCTION WORKS

1.00 DEMARCATION - EXCAVATIONS - BACKFILL


$1,800.00
Excavation trench foundation for stone walls size 40cm
1.10 x 50cm and 30cm average depth for earth material of M3 12.00 30.00 360.00
moderate soil

Backfill with 200 mm thick stony hard core gravel & well
1.20 back before river mixed course sand below concrete M3 80.00 12.00 960.00
floor slab
Backfill river sand 200 mm thick & compact well below
1.30 M3 80.00 6.00 480.00
concrete floor slab place

2.00 FOUNDATIONS AND FLOORS


$11,585.00
Apply 5cm thick of mass blinding concrete for under
2.10 wall foundation & column basements which having M3 2.00 160.0 320.00
proportions equivalent of mixture 1:3:6

Construct RC concrete class 20 for columns basement


Average size 90cmx 90cm x 40cm depth using of 3,400.0
2.20 M3 10.00 340.0
Y14mm main reinforcement bars both direction (28 0
units) rate should including curing 7 days
Construct plain Concrete floor slab 100 mm thick 1,650.0
2.30 M3 22.00 75.0
(Mixture equivalent to 1:2:4) including curing 4 days 0
Apply 30mm thick rich cement sand mortar with
1,540.0
2.40 containing course sand for screed mortar on floor slab M2 220.00 7.00
0
finishing with 1:3 mix ratio
Apply Floor ground slab finishing ceramic tiles 60x60 4,515.0
2.50 M2 215.00 21.00
having skidding resistance 0
Construct masonry ground Floor external stepped stair
2.60 Lm 8.00 20.00 160.00
with its finishing
3.00 MASONRY WORKS- SURFACE FINISH
Construct 10cm thick hollow concrete block Masonry
wall from ground floor to top roof ring beam aver. High 7,600.0
3.10 M2 380.00 20.0
3.3 m with 1:4 cement sand mortar including curing 3 0 $14,530.00
days including Scaffolding cost for work

Apply cement sand plaster mortar 1:3 mix on all


5,250.0
3.20 surfaces of block walls internal & external to be two M2 750.00 7.00
0
layers 15mm thick each
1,680.0
3.30 Apply painting on all underside of hall metal roof sheet M2 240.00 7.00
0

$9,840.00
4.00 ROOFING
4.10 provide and install metal roof truss M2 240.00 18.00
2
4.20 provide and install metal roof sheet M 240.00 23.00

5.00 DOORS & WINDOWS


$7,200.00
Provide & fix sliding glass door and wood frame size 2.1
2,580.0
5.10 x 2.5m with its frames including needed fitting for No 12.00 215.00
0
entrance
Provide & fix Aluminum glass Windows size 2 x1.5M 4,620.0
5.20 No 22.00 210.00
with its frames including needed fitting 0

6.00 REHABILITATION
$9,380.00
doors and windows enlargement; no lintel beam
6.10 unit 16.00 160.00
installation
6.20 demolition of partition walls unit 16.00 130.00
6.30 painting the whole building M2 790.00 6.00
7.00 SANITARY INSTALLATIONS $2,348.00
3
7.10 septic distribution tanks M 2.00 30.00 60.00
7.20 provide septic tank pipe line lm 5.00 20.00
7.30 15cm thick RCC slab for cover septic tanks 1:2:4 M3 1.6 60.00 96.00
7.40 provide and install bathroom accessories set Lm 4 41.00
7.50 provide and install bathroom shower and taps Lm 4 80.00
7.60 provide and install bathroom seat Lm 4 60.00
7.70 Provide and fix sanitary equipment WC with its fitting unit 4.00 60.00 240.00
7.80 provide washing basin and fix on place with its fittings Unit 4.00 35.00 140.00
Manhole 500 x500x500 mm (with brick or concrete
7.90 Unit 4.00 18.00 72.00
blocks, cover in or fabricated RC slab)
Drainage pipes and ventilation (100 mm (4") diameter
8.00 Lm 2.00 8.00 16.00
for drainage pipe, 50 mm (2") for ventilation.
Apply white ceramic tiles (15cm*15cm) interior surface
8.10 M2 60.00 15.00 900.00
toilet walls up to 1.5m high with rich cement sand mortar
9.00 ELECTRICAL INSTALLATIONS $1,200.00
9.10 electricity work Lm 1.00 900.00 900.00
Contingency fund 0% 0
GRAND TOTAL CONSTRUCTION COST $ 57,883.00
PAYMENT TERMS

Payment shall be made incrementally according to the schedule laid out below.

PAYMENT AMOUNT TO BE PAID


Initial Payment 25% of the project cost Construction starting day
Payment #2 20% of the project cost End of month 1
Payment #3 20% of the project cost End of month 2
Final Payment 20% of the project cost End of month 3
Final Payment 15% of the project cost After completion

Permits & Easements


Owners will be responsible for obtaining all required construction-related permits prior to the project start
date and assumes legal responsibility for any permit- or approval-related delays.

WORK SCHEDULE

DEADLINE DATE
Project Start Issued date
Project Completion 120 days after issued date

LIMITED LIABILITY: Contractor will not be held liable for delays to work schedule caused by project
o ner, permi appro al , poor ea her condi ion , and/or an circ m ance be ond he con rac or
control.

Total: _________________________________________________DOLLARS: $ 57,883

Signa e .. Da e: 25/01/2023