BETON TAPAK
1.20 1.00 0.50 0.60 45.00 27.00 8
0.50 0.50 1.20 0.30 45.00 13.50 4
40.50 32
besi tapak
2.60 6.00 2.00 31.20 45 1,404.00
Luas penampang Ø16 = 1/4 (n) d2 = 1/4(3.14)(0.016)2 =
volume Ø16 = luas penampang x panjang batang =
berat besi Ø16 = Volume x 7850 kg/m3 =
Bekisting
1.20 45.00 54.00
kolom pedistral
0.5 0.5 1.3 0.33 45.00 14.63
bekisting
1.5 1.5 1 2.25 45 101.25
besi beton uk 16 mm
1.5 12 1 18.00 45 810.00
Luas penampang Ø16 = 1/4 (n) d2 = 1/4(3.14)(0.016)2 =
volume Ø16 = luas penampang x panjang batang =
berat besi Ø16 = Volume x 7850 kg/m3 =
total 1,469.47
sloof beton
0.3 0.3 48 4.32 6 25.92
0.3 0.4 24 2.88 12 34.56
total 60.48
bekisting
0.6 48 1 28.80 6 172.80
0.6 24 1 14.40 12 172.80
345.60
besi beton sloof 12 mm memanjang
8 48 1 384.00 6 2,304.00
cincin dia 8 mm
1.2 320 1 384.00 6 2,304.00
besi beton sloof 12 mm melintang
8 24 1 192.00 12 2,304.00
cincin dia 8 mm
1.2 160 1 192.00 12 2,304.00
pekerjaan lantai
beton lantai
48 24 0.15 172.80 1 172.80
bekisting
0.15 48 2 14.40 1 14.40
0.15 24 2 7.20 1 7.20
total 21.60
besi beton lantai uk. 10 mm
120 40 2 9,600.00 1 9,600.00
240 24 2 11,520.00 1 11,520.00
total 21,120.00
Luas penampang Ø10 = 1/4 (n) d2 = 1/4(3.14)(0.010)2 =
volume Ø16 = luas penampang x panjang batang =
berat besi Ø16 = Volume x 7850 kg/m3 =
BETON K.225
0.4 0.4 2.3 0.37 21 7.73
BEKISTING
1.4 2.3 1 3.22 21 67.62
BESI BETON
DIA 12 MM 2.3 9 1 20.70 21 434.70
DIA 8 MM 15.33333 1.30 1 19.93 21 418.60
0.00020096 m2
0.00020096 m2 x 810.00 m = 0.1627776 m3
0.1627776 m3 x 7,850 kg/m3 = 1,277.80 kg
0.00005024
0.00005024 m3 x 486.00 m = 0.02441664 m3
0.02441664 m3 x 7,850 kg/m3 = 191.67 kg
12
0.00011304 m2
0.00011304 m2 x 4,608.00 m = 0.52088832 m3
0.52088832 m3 x 7,850 kg/m3 = 4,088.97 kg
0.00005024
0.00005024 m2 x 4,608.00 m = 0.23150592 m3
0.23150592 m3 x 7,850 kg/m3 = 1,817.32 kg
total 5,906.29
0.00007850 m2
0.00007850 m2 x 21,120.00 m = 1.65792 m3
1.65792 m3 x 7,850 kg/m3 = 13,014.67 kg
0.00007850 m2
0.00007850 m2 x 3,925.33 m = 0.3081386667 m3
0.30813866667 m3 x 7,850 kg/m3 = 2,418.89 kg
0.00005024
0.00005024 0x 3,925.33 m = 0.1972087467 m3
0.19720874667 m3 x 7,850 kg/m3 = 1,548.09 kg
total 3,966.98
92
0.00011304 m2
0.00011304 m2 x 434.70 m = 0.049138488 m3
0.049138488 m3 x 7,850 kg/m3 = 385.74 kg
0.00005024
0.00005024 0x 418.60 m = 0.021030464 m3
0.021030464 m3 x 7,850 kg/m3 = 165.09 kg
TOTAL 550.83
0.00020096 m2
0.00020096 m2 x 3,456.00 m = 0.69451776 m3
0.69451776 m3 x 7,850 kg/m3 = 5,451.96 kg
0.00005024
0.00005024 m2 x 3,456.00 m = 0.17362944 m3
0.17362944 m3 x 7,850 kg/m3 = 1,362.99 kg
total 6,814.96
0.00007850 m2
0.00007850 m2 x 21,120.00 m = 1.65792 m3
1.65792 m3 x 7,850 kg/m3 = 13,014.67 kg
galian tanah
pondasi tapak
beton pondasi tapak 0.80 0.80 0.30 0.19 12.00
beton kolom struktur 0.30 0.40 4.00 0.48 12.00
pondasi sloof
beton sloof uk 20 x 25 0.30 0.50 8.00 1.20 4.00
0.30 0.50 12.00 1.80 3.00
lantai beton
beton lantai 12.00 8.00 0.15 14.40 1.00
atap beton 13.20 9.20 0.15 18.22 1.00
Lisplank 44.80 0.90 0.10 44.80 4.03 1.00
PEK. DINDING
PASANG DINDING BATA HABEL 40.00 4.00 1.00 160.00 1.00
LANTAI KERAMIK 8.00 12.00 1.00 96.00 1.00
Keramik Dinding 20.00 4.00 1.00 80.00 1.00
pengecatan 40.00 4.00 1.00 160.00 2.00
115.20
13.31
3.84
1.08
133.43
2.30
5.76
4.80
5.40
10.20
14.40
18.22
4.03
160.00
96.00
80.00
320.00
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN RESEVOIR, RUMAH POMPA DAN PEMASANGAN MEKANIKAL ELEKTRIKAL SERTA
SISTEM BOOSTER PUMP INVENTER
LOKASI : PT . FREETREEN CIREBON
TAHUN ANGGARAN : 2020
l PEMBANGUNAN RESERVOIR
l UNIT PEKERJAAN : PERSIAPAN
1 Pembuatan Direksi Keet & Gudang Bahan 24.00 UNIT 935,000.00 22,440,000.00
2 Dokumentasi dan Pelaporan 1.00 LS 2,200,000.00 2,200,000.00
3 Pembuatan As Built Drawing 1.00 UIT 3,300,000.00 3,300,000.00
4 Biaya Tranportasi dan Mobilisasi 1.00 LS 5,500,000.00 5,500,000.00
SUB TOTAL. 1 33,440,000.00
ll PEKERJAAN GALIAN TANAH
1 Galian tanah biasa 1,926.10 m3 159,500.00 307,212,950.00
2 Buangan Tanah 1,926.10 m3 71,500.00 137,716,150.00
SUB TOTAL. II 444,929,100.00
lll PEKERJAAN STRUKTUR
1 Pekerjaan Pondasi Tapak
a Besi Beton Uk 16 mm 2,214.86 kg 19,250.00 42,636,065.47
b Bekisting 54.00 m2 192,500.00 10,395,000.00
c Beton K.225 40.50 m3 1,595,000.00 64,597,500.00
2 Pekerjaan Kolom Struktur pedistral
a Besi Beton Uk 12 mm 1,469.47 kg 19,250.00 28,287,389.59
b Bekisting 101.25 m2 192,500.00 19,490,625.00
c Beton K.225 14.63 m3 1,595,000.00 23,326,875.00
3 Pekerjaan Sloof uk 20 cm x 25 cm
a Besi Beton Uk 12 mm 5,906.29 kg 19,250.00 113,696,174.59
b Bekisting 345.60 m2 192,500.00 66,528,000.00
c Beton K.225 60.48 m3 1,595,000.00 96,465,600.00
4 Pekerjaan Lantai
a Urugan Pasir Pasang 115.20 m3 379,500.00 43,718,400.00
b Lantai kerja mutu beton k.125 57.60 m3 951,500.00 54,806,400.00
c Besi Beton Uk 10 mm 13,014.67 kg 19,250.00 250,532,436.00
d Bekisting 21.60 m2 192,500.00 4,158,000.00
e Beton K.225 172.80 m3 1,595,000.00 275,616,000.00
5 Pekerjaan Dinding Beton
a Besi Beton Uk 12 mm 3,966.98 kg 19,250.00 76,364,311.00
b Bekisting 736.00 m2 192,500.00 141,680,000.00
c Beton K.225 58.88 m3 1,595,000.00 93,913,600.00
2 Pekerjaan Kolom Struktur uk. 30 x30
a Besi Beton Uk 12 mm 550.83 kg 19,250.00 10,603,405.76
b Bekisting 67.62 m2 192,500.00 13,016,850.00
c Beton K.225 34.56 m3 1,595,000.00 55,123,200.00
6 Pekerjaan Balok uk. 20 x 30
a Besi Beton Uk 16 mm 6,814.96 kg 19,250.00 131,187,893.76
b Bekisting 288.00 m2 192,500.00 55,440,000.00
c Beton K.225 63.36 m3 1,595,000.00 101,059,200.00
7 Pekerjaan Atap Beton
a Besi Beton Uk 10 mm 21,120.00 kg 19,250.00 406,560,000.00
HARGA SATUAN HARGA PEKERJAAN
NO URAIAN QUANTITY (Rp) (Rp)
m2 t x vol x juml
m2 x 395.20 m = 0.079419 m3 3.80 8 13
m3 x 7,850 kg/m3 = 623.44 kg 1.24 18 13
total besi beton
m2 t x vol x juml
m2 x 110.00 m = 0.012434 m3 2.75 8 5
m3 x 7,850 kg/m3 = 97.61 kg 1.04 14 5
x ttl panjang = Total Sat
120.00 kg besi beton dia 10 mm
65.40 kg besi beton dia 10 mm
185.40 114.25 kg besi beton dia 10 mm