Professional Documents
Culture Documents
DETAILED ESTIMATE
Grant :
Mandal : Guntur Name of the work
Specification Report to accompany the Detailed Cum Abstract Estimate for the Work:
Construction of CC Drain from Yeminedi Sivannarayana house to in Obulnaidupalem (V), Guntur
Rural (M)
The above work was administratively sanctioned vide Progs Resolution No. dt. . .2020
of the Grampanchayat, Challavaripalem under . Hence the estimate was prepared
with the following provisions.
1
2 Add QC charges @0.50 %
3 Add Supervision charges @ 3%
4 Add NAC @0.10 %
Necessary provisions are made in this estimate for un forseen items and the work will be
executed as per APDSS and the estimate is prepared with SSR 2020-21
1 2 3 4 6 9 8 7 10 11
1 40mm HBG metal Perecherla 14.00 640.00 70.00 160.00 183.60 0.00 1 Cum 1053.60
2 20mm HBG metal Perecherla 14.00 1064.00 70.00 266.00 183.60 0.00 1 Cum 1583.60
3 12mm HBG metal Perecherla 14.00 848.00 70.00 212.00 183.60 0.00 1 Cum 1313.60
2.36mm below metal (Stone Perecherla 14.00 381.00 183.60 0.00 1 Cum 564.60
4 dust)
5 Sand for mortar Amaravathi 40.00 605.00 0.00 0.00 487.10 0.00 1 Cum 1092.10
6 Sand for concrete Amaravathi 40.00 510.00 0.00 0.00 487.10 0.00 1 Cum 997.10
7 Cement Local 0.00 4700.00 0.00 0.00 0.00 1MT 4700.00
8 Gravel Turakapalem 8.00 130.00 117.70 0.00 1cum 247.70
9 Quarry Rubbish Turakapalem 14.00 84.75 0.00 0.00 190.90 0.00 1 Cum 275.65
Certified that the leads mentioned above are nearest and correct to the best of my knowledge
Certified that the village is situated with in the raious of 12 KM from GMC limits. Hence 25% MA allowed
1 2 3 5 6
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
RBR-FNDN-1
material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches
1 with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH
watering and ramming including cost and conveyance of water to work site and all operational,
incidental, labour charges, hire charges of T & P etc., complete for finished item of work. as per
2 drawing and technical specification Clause 305.3.9 MORD & 304 MORTH
a. Material
Cum
0.90
40mm HBG metal 1053.60 Cum 948.24
Cum
0.45
Sand 997.10 Cum 448.70
162.00 Kg Cement 4.70 Kg 761.40
1.20 kl Water 83.00 kl 99.60
b.Machinery
1.00 hr Concrete Mixer 10/7cft(0.28cum) capacity 566.10 Hr 566.10
0.00 hr Water tanker 6 kl capacity 691.00 hr 0.00
C. Labour
0.10 Nos. 1st class mason 550.00 day 55.00
1.39 Nos. Mazdoor 460.00 day 639.40
Add MA on Labour Charges 0.25 694.40 173.60
3692.04
D. Formwork @ 4% on cost of material, labour and machinery (a+b+c) 0.04 0.00
Total per 1 Cum (a+b+c+d) 3692.04
Providing M15 mix using 66% of 20HBG metal and 34% of 12 MM HBG metal including cost
conveyance of all meterials and labour charges etc., including all operational, incidental and
4 labour charges such as mixing, laying, curing concrete for 21 days etc., complete for finished
item of work.
Unit: 1cum
a. Material
275.00 kgs Cement 4.70 kg 1292.50
0.48 cum. 20mm HBG graded metal 1583.60 cum 760.13
0.32 cum 12 mm HBG metal 1313.60 Cum 420.35
0.48 cum. Coarse aggregate Sand 997.10 Cum 478.61
1.20 kl Water (including for curing) 83.00 Kl 99.60
B. LABOUR:
0.1 day 1st Class Mason 550.00 each 55.00
1.39 day Mazdoor (Both Men and Women) 460.00 each 639.40
Add MA on Labour Charges 0.25 173.60
C. MACHINERY
0.40 hour Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity 566.10 Hr 226.44
0.00 hr Water tanker 6 kl capacity 691.00 hr 0.00
Total 4145.63
D. Formwork @ 10% on cost of material, labour and machinery (a+b+c) 0.10 414.56
BASIC COST per 1 cum (A+B+C+D) 4560.19
lead Rate 6