Professional Documents
Culture Documents
LEAD STATEMENT
Providing CC Road and Drain approach to RBK Building at Uppalapadu (V) of Rajupalem (M)
There is a necessisty for Providing CC Road and Drain approach to RBK Building at Uppalapadu
(V) of Rajupalem (M) Vide D.O.LR.No : 638/MIN/WRD/CAMP/SAP/2023, dt: 28.10.2023 of the Sri Ambati
Rambabu, Minister for Welfare Resources, Government of Andhra Pradesh. Hence the estimate is prepared for
the following itmes are given below.
The existing surface of the above road is badly damaged and it is very much inconvenience for moving
of vehicles and public. Rain water is stagnated on the road surface during rainy season on the road causing very
much inconvenience. The following provisions are made in the estimate.
1 Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting
out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom and bac kfilling in trenches with excavated suitable material as per
Technical Specification 305 MORD / 304 MORTH charges etc., complete.
2 Construction with Quarry Rubbish, spreading in uniform layers on prepared surface, and compacting with Power
Road Roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause
408 MORD including overheads and contractors profit charges etc., complete.
3 CC (1 4 8) using 40 mm HBG Metal from approved quarry including cost, conveyance of all matirials and all
labour charges etc complete. For bed
4 VCC (1 3 6 ) using 20 mm -12mm HBG Metal chips from approved quarry including all matirials and all labour
charges etc complete.for side walls
5 Cost, supply of filling of HBG stone chips of size 2.36 mm and below and spreading/filling HBG stone chips
including sectioning, watering, consolidation of each deposited layer in not exceeding 15 cms thickness in layers
and compacting by ramming etc complete for finished item of work.
6 Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete
pavement, thickness as per design, over a prepared sub base as per Clause 1501.2.2 M 20 Grade nominal mix
coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.20 cum
capacity laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film,
wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels,
rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation including
provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel
bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs
for 14- days, curing compound (where specified) and water finishing to lines and grade as per drawing and
Technical Specification Clause 1501 MORD.
Rates adopted in the estimate are as per SoR 23-24 and the work will be
executed as per standard specifications of APDSS after obtaining proper aprovals.
LINE ESTIMATE
Administrative Sanction
No. and date
:
Construction with Quarry Rubbish, spreading in uniform layers on prepared surface, and
compacting with Power Road Roller to achieve the desired density complete as per
2 Clause 401.4 as per Technical Specification Clause 408 MORD including overheads and
contractors profit charges etc., complete.
Drain bed
concrete 1 x 2 48.50 0.90 0.15 13.10
VCC (1 3 6 ) using 20 mm -12mm HBG Metal chips from approved quarry including all
4 matirials and all labour charges etc complete.for side walls
Drains
external side 1 x 2 48.50 0.23 0.30 6.69
walls
Drains
external 1 x 2 48.50 0.23 0.13 2.90
Internal walls
9.59 8301.12 Cum 79608.00
5 Cost, supply of filling of HBG stone chips of size 2.36 mm and below and spreading/filling
HBG stone chips including sectioning, watering, consolidation of each deposited layer in
not exceeding 15 cms thickness in layers and compacting by ramming etc complete for
finished item of work.
381768.00
2 MBG +4. PCC (1:4:8) prop nominal mix (cement:FA:CA) using 40 mm size HBG (SS5) metal
from approved quarry (obtained by blasting) including cost and conveyance of all materials as
cement, sand, CA, water etc. to site, including all operational, incidental & labour charges such
as mixing, laying & ramming CC layers in position not exceeding 15 cm, finishing top surface,
curing etc, complete for finished item of work but excluding seigniorage charges for foundations
under column footings (APSSNo.402)
3 MBG +17. VRCC M 25 grade design mix, using 20 mm size HBG (SS5) graded metal from
approved quarry using minimum 340.00 kgs of cement/1cum of concrete including C/C of all
materials as cement, FA, CA, water etc. to site including all operational, centring, scaffolding, lift,
incidental, labour and T & P charges as shuttering, vibrating, machine mix, laying CC, curing CC
etc, complete for finished item of work.(APSS No. 402) but excluding cost of steel & fabrication &
seigniorage charges for staircase slab 150 mm thickness.
4 MBG + 13. VRCC M 25 grade design mix, using 20 mm size HBG (SS5) graded metal from
approved quarry using minimum 340.00 kgs of cement/1cum of concrete including cost and
conveyance of all materials as cement, FA, CA, water etc. to site including all operational,
centring, scaffolding, incidental & labour and T & P charges such as shuttering, vibrating,
machine mix, laying CC, curing CC etc, complete but excluding cost of steel & fabrication &
seigniorage charges etc., complete for finished item of work. (APSS No. 402)
Rcc slab precast cover over opening of septic tank roof slab
1 x 2 0.75 0.60 0.075 0.07
0.07 #REF! 1 Cum #REF!
6 MBG + 45 Providing high yield strength deformed (HYSD) steel TMT bars (Fe 500 grade as per
IS 1786-1985) of 8 mm to 36 mm diameters cutting, bending to required sizes and shapes
placing in position with cover blocks of approved size and binding wire of 20 SWG, forming grills
for reinforcement work as per approved designs and drawings including cost and conveyance of
bars, cover blocks and binding wire from approved sources to site of work with all taxes chains,
overlaps, spacer bars, dowel bars, wastage etc, including all operational, incidental and labour
charges such as cutting, bending, placing in position, tying etc., and other taxes on cost of all
materials complete for finished item of work (APSS No.126)
7 Brick Masonry in CM (1:6) with 2nd class Bricks size 23 x 11 x 7 cms including cost and
conveyance of all materials and labour charges and curing charges etc complete for
finished item of work for superstructure.
Septic tank side walls alround 4 sides
For superstructure of (0.35+0
1 x 1 7.46 1.50 3.25
septic tank .23/2)
Baffle wall above
beam 1 x 1 1.35 0.10 0.90 0.12
Deductions:T-beam
portions 1 X 2 0.23 0.23 -0.10
Sl. Description of the Heigh
Nos Length Width Quantity Rate Per Amount
No item t
Baffle wall portions 1 X 2 0.23 0.23 -0.10
1 X 2 0.10 1.13 -0.23
Scum board portions 1 X 2 0.10 1.20 -0.24
16.21 #REF! 1 Sqm #REF!
9 Plastering with CM (1:5) mix 20 mm thick in single coat including cost and conveyance
of all materials and labour charges and curing charges etc complete for finished item of
work.
Alround 4 sides of septic tank outside
1 x 1 8.14 0.45 3.66
3.66 #REF! 1 Sqm #REF!
#REF!
0 #REF!
#REF! #REF!
LEAD STATEMENT (2023-24 SoR)
Name of Work:- Providing CC Road and Drain approach to RBK Building at Uppalapadu (V) of Rajupalem (M)
Est Cost Rs. 4.00 Lakhs
Machine
Dista Crushing
Sl. Name of the Sl. No./Item Code Blasting Conveyance Loading Unloading
Description of item nce in Unit Initial cost charges @ Total
No. Quarry No. Charges charges charges Charges
Km 25.00 %
Sand for
4 mortor/plastering Amaravathi MAT-00029 57 1 Cum 721.00 806.70 1527.70
(including screening
5 charges
Sand forRs. 116/1
filling Local MAT-00028 5 1 Cum 460.00 99.40 559.40
6 40 mm size HBG metal Perecherla MAT-00220 43 1 Cum 744.00 70.00 186.00 611.70 1611.70
7 20 mm size HBG metal Perecherla MAT-00218 43 1 Cum 1242.00 70.00 310.50 611.70 2234.20
8 12 mm size HBG metal Perecherla MAT-00217 43 1 Cum 989.00 70.00 247.25 611.70 1917.95
9 10 mm size HBG metal Perecherla MAT-00216 43 1 Cum 831.00 70.00 207.75 611.70 1720.45
10 Cement At site 1MT 5400.00 5400.00
11 Steel (Fe-500 Grade) At site Jul-23 1MT 63000.00 63000.00
12 Gravel Local MAT-00177 5 1Cum 155.00 99.40 254.40
13 Quarry Rubbish Local MAT-00473 5 1Cum 96.00 99.40 195.40
1.Certified that the above leads are correct to the best of my knowledge.
2. Certified that the Seigniorage charges are actually payable.
3. Certified that the metal is obtained by blasting.
Machine
Dista Crushing
Sl. Name of the Sl. No./Item Code Blasting Conveyance Loading Unloading
Description of item nce in Unit Initial cost charges @ Total
No. Quarry No. Charges charges charges Charges
Km 25.00 %
Index Code Sl. No. Description of the item Unit Qty Rate Amount
Earth work excavation and depositing on bank with initial lead of 10 meters and initial lift of 2.00
RBR-FNDN- in loamy and clayey soils like B.C. Soils, red earth & Ordinary Gravel (SS 20-B) including
1 shoring, strutting, sheeting, planking including cost of hire charges of T & P, labour charges etc.,
1 (1) (A) (i)
complete for finished item of work for foundations.
Filling in basement with HBG stone chips of 2.36 mm and below from approved quarry/ available
sources including all operational, incidenal, labour charges, sales tax and other taxes, hire
charges of T & P etc., complete (excluding rock) in trenches, sides of foundations and basement
RBR-FNDN-
2 with initial lead in layers not exceeding 15 cm thick, consolidating each deposited layer by
2-2
watering and ramming including cost and cost and conveyance of water to site etc., complete
for finished item of work. (APSS NO. 309 & 310) for finished item of work.
Construction with Quarry Rubbish, spreading in uniform layers on prepared surface, and
compacting with Power Road Roller to achieve the desired density complete as per Clause 401.4
3 as per Technical Specification Clause 408 MORD including overheads and contractors profit
charges etc., complete.
Providing concrete for plain/reinforced concrete in open foundations using 40 mm nominal size
metal 2/3 rd quantity and 20 MM size HBG metal 1/3 rd quantity mechanically mixed, placed in
RBR-FNDN- foundation and compacted by vibration including curing for 14 days complete as per drawings
4
4 I (i) and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100
MORTH.
Note : Water for concrete : A provision for cost of water may be added at 1.2 kl /1 cum (including
curing purpose) keeping the site conditions
Coarse Aggregate : Single grade nominal size can also be used instead of graded metal,
keeping the site conditions in view
P.C.C grade M 10 - Nominal mix (1:3:6) using CC Mixer (MORD)
A Key walls below ground level:
Unit = 1.00 Cum
a Material
Cost of Cement Kgs 220 5.40 1188.00
Cost of Coarse sand cum 0.45 1411.70 635.27
Cost of 40 mm size aggregate cum 0.6 1611.70 967.02
Cost of 20 mm size aggregate cum 0.3 2234.20 670.26
Cost of Water kl 1.2 99.00 118.80
b Labour
LAB-00011 Mason (1st Class) day 0.1 670.00 67.00
LAB-00120 Mazdoor (Unskilled) day 1.39 560.00 778.40
Add Municipal allowance charges 0 845.40 0.00
c Machinery
Mechanical concrete mixer Concrete mixer 0.28
HIR-00018 cum capacity fitted with water measuring device hour 0.4 692.70 277.08
HIR- 00040, and preferably also with load cell.
HIR-
Needle vibrator 40 mm (petrol) hour 0.4 274.40 109.76
00174 and
LAB- 00352
HIR-00076 Water tanker 6 kl capacity hour 0.13 822.00 106.86
4918.45
d Add contractors profit and overhead charges 0 4918.45 0.00
Total cost per 1.00 Cum a+b+c+d 4918.45
Index Code Sl. No. Description of the item Unit Qty Rate Amount
CC (1 4 8) using 40 mm HBG Metal from approved quarry including cost, conveyance of all
6 matirials and all labour charges etc complete. For bed
A) MATERIALS
40 mm HBGMC Metal Cum 0.90 1611.7 1450.53
Cost of sand Cum 0.45 1411.7 635.27
Cement Kgs 162.00 5.4 874.80
Water kl 1.20 99 118.80
B) MACHINARY
Miller charges Cum 1.00 518.2 518.20
C) LABOUR
Ist class mason Nos 0.10 670 67.00
Manmazdoor Nos 1.39 560 778.40
Water charges 1% on labour 845.4 8.45
Cost per 1.00 Cum 4451.45
VCC (1 3 6 ) using 20-12 mm HBG Metal chips from approved quarry including all matirials and
7 all labour charges etc complete.for side walls
A) MATERIALS
D) CENTERING
Centring charges 3073 1 3073.00
Cost per 1.00 Cum 8301.12
Name of the work : Providing CC Road and Drain approach to RBK Building at Uppalapadu (V) of Rajupalem (M)
Or 275.12
Qty Vp no 01 of MB No
1696/B/PRI/2015-16
Footing F2 1 x 1 1.80 1.80 2.10 6.80
Qty Vp no 02 of MB No
1696/B/PRI/2015-16
For F2 type footings 1 x 10 1.80 1.80 2.10 68.04
Qty Vp no 03 of MB No
1696/B/PRI/2015-16
F1 type footings 1 x 6 2.00 2.00 2.10 50.40
F2 type footings 1 x 1 1.80 1.80 2.10 6.80
F3 type footings 1 x 1 1.35 1.35 2.10 3.83
135.87 #REF! #REF!
2 MBG+4.PCC (1:4:8) prop nominal mix (cement:FA:CA) using 40mm
size HBG(SS5) metal from approved quarry (obtained by blasting)
including Cost and Conveyance of all materials as
cement,sand,CA,water etc. to site, including all operational, incidental
& labour charges such as mixing,laying & ramming CC layers in
position not exceeding 15cm,finishing topsurface,curing etc,complete
for finished item of work but excluding seigniorage charges for
foundations under column footings (APSSNo.402)
Qty Vp no 04 of MB No
1696/B/PRI/2015-16
F1 type footings 1 x 6 2.00 2.00 0.15 3.60
F2 type footings 1 x 12 1.80 1.80 0.15 5.83
F3 type footings 1 x 1 1.35 1.35 0.15 0.27
Qty Vp no 12 of MB No
357/B/PRI/2016-17
Bor basement steps at
1 x 1 3.90 1.90 0.10 0.74
Verandah
1 x 1 4.20 1.30 0.10 0.55
10.99 #REF! #REF!
Cum Cum
3 MBG+5.PCC (1:5:10) prop nominal mix (cement: FA: CA) using 40mm
size HBG (SS5) metal from approved quarry including Cost and
Conveyance of all materials like cement, sand, CA, water etc. to site,
including all operational, incidental, and labour charges such as mixing,
laying and ramming CC in layers in position not exceeding 15cm,
finishing top surface, curing concrete, etc., complete for finished item
workbut excluding seigniorage charges for Foundations and Flooring
Bed (APSSNo.402)
For Basement
Alround the building 1 x 1 56.09 0.23 0.60 7.74
Deduction for columns 2 x 7 0.30 0.23 0.60 -0.58
Deduction for columns 1 x 2 0.38 0.23 0.60 -0.10
Wall between A2-D2 1 x 1 7.04 0.23 0.60 0.97
A3-D3/A4-D4 1 x 2 7.28 0.23 0.52 1.74
A5-D5 1 x 1 7.04 0.23 0.60 0.97
C6-D6 1 x 1 7.115 0.23 0.60 0.98
Wall between C5-C6-C7 1 x 1 6.15 0.23 0.60 0.85
B1-B2 1 x 1 3.07 0.23 0.60 0.42
Toilet Cross wall 1 x 1 3.685 0.10 0.60 0.22
Toilet Cross wall 1 x 2 1.025 0.10 0.60 0.12
13.33 #REF! #REF!
Cum Cum
5 Refilling the foundation trenches with excavated soil (excluding rock)
with initial lead in layers not exceeding 15cm thick, consolidating each
deposited layer by watering and ramming including cost and Cost and
Conveyance of water to site and all operational, incidental, labour
charges, , sales and other taxes etc, hire charges of T & P etc.,
complete for finished item of work. (APSS NO. 309 & 310)
Qty Vp no 21 of MB No 1696/B/PRI/2015-16
For F1 type footings 1 x 6 2.00 2.00 1.95 46.80
For F2 type footings 1 x 12 1.80 1.80 1.95 75.82
For F3 type footings 1 x 1 1.35 1.35 1.95 3.55
Deductions F1 type footings 1 x 6 1.85 1.85 0.40 -8.21
Qty Vp no 08 of MB No 1696/B/PRI/2015-16
Pedastal for F1 type Footing 0.86
1 x 4 0.60 0.60 0.60
Qty Vp no 09 of MB No
1696/B/PRI/2015-16
Qty Vp no 19 of MB No
1696/B/PRI/2015-16
Mid landing beam 1 x 1 3.05 0.23 0.30 0.21
Qty Vp no 37 of MB No
1696/B/PRI/2015-16
Beam No 1 A2-A3-A4-A5-
1 x 1 17.10 0.23 0.30 1.18
A6-A7
Deduct columns portions 1 x 6 0.30 0.23 0.30 -0.12
Beam No 2 B1-B2 1 x 1 3.67 0.23 0.30 0.25
Deduct columns portions 1 x 2 0.30 0.23 0.30 -0.04
Beam No 3 C5-C6-C7 1 x 1 7.13 0.23 0.30 0.49
Deduct columns portions 1 x 2 0.30 0.23 0.30 -0.04
Deduct columns portions 1 x 1 0.38 0.23 0.300 -0.03
Beam No 4 D1-D2-D3-D4-
1 x 1 20.40 0.23 0.30 1.41
D5-D6-D7
Deduct columns portions 1 x 7 0.30 0.23 0.30 -0.14
Beam No 6 & 7 A1-B1-D1 &
1 x 2 8.176 0.23 0.30 1.13
A2-B2-D2
Deduct columns portions 2 x 3 0.38 0.23 0.30 -0.16
Portico beams 1 x 2 2.03 0.23 0.375 0.35
Qty Vp no 32 of MB No 357/B/PRI/2016-17
Staircase MLB 1 x 1 3.00 0.23 0.30 0.21
(Qty. VP No. 44)
Qty Vp no 39 of MB No 1696/B/PRI/2015-16
1 x 1 20.93 8.47 177.28
1 x 1 3.60 0.30 1.08
Deduction for staircase
1 x 1 2.878 3.07 -8.84
portion
For Entrance verandah 1 x 1 3.83 2.03 7.77
For Portico 1 x 1 3.83 1.43 5.48
182.77 #REF! #REF!
17 MBG+16.VRCC M20 grade Design mix, using 20mm size HBG(SS5)
metal from approved quarry using minimum 350kg of cement/1cum of
concrete including C/C of all materials like cement,FA,CA,water etc. to
site,including all operational,centring,scaffolding, lift,incidental,labour
and T&P charges such as shuttering,vibrating,machine mix,laying
CC,curing CC etc,complete for finished item of work (APSS No. 402)
but excluding cost of steel & fabrication charges for Roof slab
125mm thick for FF
Qty Vp no 46 of MB No 357/B/PRI/2016-17
Building 1 x 1 13.96 8.78 122.50
Deduction for staircase
1 x 1 3.53 3.79 -13.37
Portion
109.13 #REF! #REF!
Sqm Sqm
.VRCC M20 grade Design mix,using 20mm size HBG(SS5) metal from
approved quarry using minimum 350kg of cement/1cum of concrete
including C/C of all materials as cement,FA,CA,water etc. to
site,including all operational,centring,scaffolding, lift,incidental,labour
and T&P charges as shuttering,vibrating,machine mix,laying CC,curing
CC etc,complete for finished item of work.(APSS No. 402) but
excluding cost of steel & fabrication & seigniorage charges for staircase
Mid landing slab of 150 mm thickness.
Qty Vp no 19 & 40 of MB No
1696/B/PRI/2015-16
1st flight 1 x 1 3.50 1.35 4.73
2nd flight 1 x 1 3.40 1.35 4.59
Mid Landing Slab 1 x 1 3.53 1.22 4.31
13.63 #REF! #REF!
(Qty Vp no 32 of MB No 357/B/PRI/2016-17)
For StairCase Slab 1 x 1 3.20 1.40 4.48
1 x 1 3.40 1.35 4.59
9.07 #REF! #REF!
Sqm Sqm
20 MBG+19.RCC M20 Grade Design mix,using 20mm size HBG(SS5)
machine crushed from approved quarry including C/C of all materials
like cement,FA,CA,water etc. to site including all operational, incidental
& labour charges such as centering,shuttering,scaffolding,lift
charges,machine mix,laying CC,curing CC etc,complete but excluding
cost of steel & its fabrication charges& seigniorage charges for finishd
item of work (APSSNo.402&403) For Lintels GF
(Qty Vp no 8 to 11 of MB No 357/B/PRI/2016-17)
(Qty Vp no 8 to 12 &13 of
MB No 357/B/PRI/2016-17)
(Qty Vp no 6 of MB No 1241/B/PRI/2017-18)
D1 1 x 2 0.00 0.00 0.00 2.00 #REF! #REF!
Nos Each
MBG+39.Supply and fixing of Sal wood door Frame of size 1.20 x 2.1m
with frame scantlings of size 100 x 75mm and bottom reeper of size
75x38mm, Including cost and conveyance of all materials & labour
charges etc.complete(APSSNO.1001&1002).
(Qty Vp no 6 of MB No 1241/B/PRI/2017-18)
Qty Vp no 01 of MB No
1696/B/PRI/2015-16
Qty Vp no 04 of MB No
1696/B/PRI/2015-16
3 MBG+5.PCC (1:5:10) prop nominal mix (cement: FA: CA) using 40mm
size HBG (SS5) metal from approved quarry including Cost and
Conveyance of all materials like cement, sand, CA, water etc. to site,
including all operational, incidental, and labour charges such as mixing,
laying and ramming CC in layers in position not exceeding 15cm,
finishing top surface, curing concrete, etc., complete for finished item
workbut excluding seigniorage charges for Foundations and Flooring
Bed (APSSNo.402)
For Foundations
Flooring bed 1 x 1 20.10 7.65 0.10 15.38
For Steps 1.50
16.88 #REF! #REF!
4 Generic Task .Brick Masonry in CM (1:6) with Bricks traditional size
23 x 11 x 7 cms 2nd Class for Basement
Qty Vp no 41 of MB No
1696/B/PRI/2015-16
For Basement
Alround the building 1 x 1 56.09 0.23 0.60 7.74
Deduction for columns 2 x 7 0.30 0.23 0.60 -0.58
Deduction for columns 1 x 2 0.38 0.23 0.60 -0.10
Wall between A2-D2 1 x 1 7.04 0.23 0.60 0.97
A3-D3/A4-D4 1 x 2 7.28 0.23 0.52 1.74
A5-D5 1 x 1 7.04 0.23 0.60 0.97
C6-D6 1 x 1 7.115 0.23 0.60 0.98
Wall between C5-C6-C7 1 x 1 6.15 0.23 0.60 0.85
B1-B2 1 x 1 3.07 0.23 0.60 0.42
Toilet Cross wall 1 x 1 3.685 0.10 0.60 0.22
Toilet Cross wall 1 x 2 1.025 0.10 0.60 0.12
13.33 #REF! #REF!
5 Refilling the foundation trenches with excavated soil (excluding rock)
with initial lead in layers not exceeding 15cm thick, consolidating each
deposited layer by watering and ramming including cost and Cost and
Conveyance of water to site and all operational, incidental, labour
charges, , sales and other taxes etc, hire charges of T & P etc.,
complete for finished item of work. (APSS NO. 309 & 310)
Qty Vp no 21 of MB No 1696/B/PRI/2015-16
For F1 type footings 1 x 6 2.00 2.00 1.95 46.80
For F2 type footings 1 x 12 1.80 1.80 1.95 75.82
For F3 type footings 1 x 1 1.35 1.35 1.95 3.55
Deductions F1 type footings 1 x 6 1.85 1.85 0.40 -8.21
Qty Vp no 42 of MB No 1696/B/PRI/2015-16
Hall 1 x 1 19.87 7.71 0.80 122.56
Deductions for Plinth & -1.30
1 x 1 7.04 0.23 0.80
Basement wall A2-D2
A3-D3/A4-D4 1 x 2 7.28 0.23 0.80 -2.68
A5-D5 1 x 1 7.04 0.23 0.80 -1.30
A6-D6 1 x 1 7.115 0.23 0.80 -1.31
C5-C6-C7 1 x 1 6.15 0.23 0.80 -1.13
B1-B2 1 x 1 3.07 0.23 0.80 -0.56
Toilet Cross wall 1 x 1 3.685 0.10 0.80 -0.29
Toilet Cross wall 1 x 2 1.025 0.10 0.80 -0.16
113.83 6360.78 724048.00
7 MBG+27.Unskilled labour charges Filling with Sand (excluding rock) in
trenches, sides of foundations and basement with initial lead in layers
not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including cost and Cost and Conveyance of
water to site and all operational, incidental, labour charges, , sales and
other taxes etc, hire charges of T & P etc., complete for finished item
of work. (APSS NO. 309 & 310)
Total 113.83 #REF! #REF!
8 MBG+7.VRCC M20 grade Design mix, using 20mm size HBG(SS5)
metal from approved quarry using minimum 350kg of cement/1cum of
concrete including C/C of all materials as cement,FA,CA,water etc. to
site,including all operational,centring,scaffolding, lift,incidental & labour
and T&P charges such as shuttering,vibrating,machine mix,laying
CC,curing CC etc, complete for finished item of work (APSS No. 402)
but excluding cost of steel &fabrication & seigniorage charges for
column footings
Qty Vp no 08 of MB No
1696/B/PRI/2015-16
Qty Vp no 08 of MB No 1696/B/PRI/2015-16
Pedastal for F1 type Footing 0.86
1 x 4 0.60 0.60 0.60
Qty Vp no 09 of MB No
1696/B/PRI/2015-16
Qty Vp no 19 of MB No
1696/B/PRI/2015-16
Mid landing beam 1 x 1 3.05 0.23 0.30 0.21
Qty Vp no 37 of MB No
1696/B/PRI/2015-16
Beam No 1 A2-A3-A4-A5-
1 x 1 17.10 0.23 0.30 1.18
A6-A7
Deduct columns portions 1 x 6 0.30 0.23 0.30 -0.12
Beam No 2 B1-B2 1 x 1 3.67 0.23 0.30 0.25
Deduct columns portions 1 x 2 0.30 0.23 0.30 -0.04
Beam No 3 C5-C6-C7 1 x 1 7.13 0.23 0.30 0.49
Deduct columns portions 1 x 2 0.30 0.23 0.30 -0.04
Deduct columns portions 1 x 1 0.38 0.23 0.300 -0.03
Beam No 4 D1-D2-D3-D4-
1 x 1 20.40 0.23 0.30 1.41
D5-D6-D7
Deduct columns portions 1 x 7 0.30 0.23 0.30 -0.14
Beam No 6 & 7 A1-B1-D1 &
1 x 2 8.176 0.23 0.30 1.13
A2-B2-D2
Deduct columns portions 2 x 3 0.38 0.23 0.30 -0.16
Portico beams 1 x 2 2.03 0.23 0.375 0.35
Qty Vp no 39 of MB No 1696/B/PRI/2015-16
1 x 1 20.93 8.47 177.28
1 x 1 3.60 0.30 1.08
Deduction for staircase
1 x 1 2.878 3.07 -8.84
portion
For Entrance verandah 1 x 1 3.83 2.03 7.77
For Portico 1 x 1 3.83 1.43 5.48
182.77 #REF! #REF!
17 MBG+16.VRCC M20 grade Design mix, using 20mm size HBG(SS5)
metal from approved quarry using minimum 350kg of cement/1cum of
concrete including C/C of all materials like cement,FA,CA,water etc. to
site,including all operational,centring,scaffolding, lift,incidental,labour
and T&P charges such as shuttering,vibrating,machine mix,laying
CC,curing CC etc,complete for finished item of work (APSS No. 402)
but excluding cost of steel & fabrication charges for Roof slab
125mm thick for FF
Qty Vp no 19 of MB No
1696/B/PRI/2015-16
1st flight 1 x 1 3.50 1.35 4.73
2nd flight 1 x 1 3.40 1.35 4.59
Mid Landing Slab 1 x 1 3.53 1.22 4.31
13.63 #REF! #REF!
19 MBG+18.VRCC M20 grade Design mix,using 20mm size HBG(SS5)
metal from approved quarry using minimum 350kg of cement/1cum of
concrete including C/C of all materials as cement,FA,CA,water etc. to
site,including all operational,centring,scaffolding, lift,incidental,labour
and T&P charges as shuttering,vibrating,machine mix,laying CC,curing
CC etc,complete for finished item of work.(APSS No. 402) but
excluding cost of steel & fabrication & seigniorage charges for
staircase slab 175mm thick for FF
Sand For
S.No. Description of Item Quantity Per Loose Metal Loose Sand Loose Bricks
Filling
BF #REF! #REF! #REF! #REF!
Plastering 20mm thick #REF!
28 C.M.(1:6)/(1:4) Ground Floor #REF! Sqm #REF! 0.021 #REF!
Plastering 20mm thick 0
29 C.M.(1:6)/(1:4) Frist Floor 0.00 Sqm 0.00 0.021 0.00
30 Flooring Shahabad Stones 136.27 Sqm 0.00 0.012 1.64 20.33
Total #REF! #REF! #REF! #REF! #REF!
ABSTRACT Metal
Qty Rate Per Amount 40mm 20mm
Metal #REF! 75.00 Cum #REF! #REF! #REF!
Sand for Mortar & filling #REF! 50.00 Cum #REF!
Bricks 2 nd Class #REF! 38.50 1000No #REF!
TOTAL #REF!
Total Rs #REF!
COMPARETIVE STATEMENT
Name of the work:- #REF!
Grant : MGNREGS
Estimate Cost Rs.32.00 Lakhs
Sl. As Per Original Estimate As Per Working Estimate Remark
Description of Item Excess Less
No Qty. Rate Amount Qty. Rate Amount s
1 2 3 4 5 6 7 8 9 10 11
1 MBG+1.Unskilled labour charges Earth work
excavation and depositing on bank with
initial lead of 10m and initial lift of 2m in
Loamy and Clayey Soils like B.C.
#REF! #REF! #REF! 135.87 116.00 15761.00 #REF! #REF!
2 MBG+4.PCC (1:4:8) prop nominal mix
(cement:FA:CA) using 40mm size
HBG(SS5) metal from approved quarry
(obtained by blasting) including Cost and
#REF! #REF! #REF! 9.70 #REF! #REF! #REF! #REF!
3 MBG+5.PCC (1:5:10) prop nominal mix
(cement: FA: CA) using 40mm size HBG
(SS5) metal from approved quarry including #REF! #REF! #REF! 16.88 #REF! #REF! #REF! #REF!
Cost and Conveyance of all materials
4 Generic Task .Brick Masonry in CM (1:6)
with Bricks traditional size 23 x 11 x 7 cms
2nd Class for Basement
#REF! #REF! #REF! 13.33 #REF! #REF! #REF! #REF!
5 Refilling the foundation trenches with
excavated soil (excluding rock) with initial
lead in layers not exceeding 15cm thick,
consolidating each deposited layer by
As per site
0.00 #REF! #REF! #REF! #REF!
condition.
19 #REF!
20 #REF!
21 #REF!
22 0
23 #REF!
Sun Shade of 0.60 Meters wide #REF! 14.70 #REF! #REF! #REF!
#REF! #REF! #REF!
24 0
25 #REF!
26 #REF!
27 #REF!
28 #REF!
29 #REF!
30 #REF!
31 #REF!
#REF! #REF! #REF! 0.00 #REF! #REF! #REF! #REF!
36 0
ID NO 07704151601109004
Adm. Sanction. Progs Rc. No. 681/2016-17/D, dt. 08.07.2016 of the District Collector, & District Programme
Co-Ordinator, MGNREGS, Guntur
Name of the
Panchayathi Secretary, Dhulipalla. GRANT MGNREGS+ IKP
Contractor :
Voucher : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Last certificate if any : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Month : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Number and month of the last schedule if any : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Mandal. Sattenapalli Amount of Estimate Rs. 32.00 Lakhs Voucher No. . . . . . . . . . . . . . . . . . . . .
Overseer's No. . . . . . . . . . . Authority covering list No.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Schedule No. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
Quantity Executed Amount
Since Since
Remarks
Miles
M3 1 M3
2 PCC (1:4:8) prop nominal mix (cement:FA:CA) using
40mm size HBG(SS5) metal from approved quarry
(obtained by blasting) including Cost and Conveyance
of all materials as cement,sand,CA,water etc. to site,
Qty vide page No. Of MB.
9.70 NO1696/B/2015-16
#REF! #REF!
M3 1 M3
M3 1 No
8 VRCC M20 grade Design mix, using 20mm size HBG(SS5)
metal from approved quarry using minimum 330kg of
cement/1cum of concrete including C/C of all materials as
cement,FA, For GF Staircase Waist slab 175 mm thick
MT 1 MT
Rs #REF!
CERTIFICATES
1 Certified that the work is in progress
2 Certified that there are no further recoveries to be effected in this bill other than now proposed.
3 Certified that there are no liabillities out standing against the contractor.
Certified that all the required materials have been conveyed to site from specified quarry as noted in the
4 lead statement appended.
5 Certified that no Departmental machinary were issed to the work.
6 Certified that the materials issued by the department on the work is here with enclosed.
MGNREGS+ SCSP
Name of the
Panchayat Secretary, Kankanalapalli GP GRANT (C0nvergence)
Contractor :
Voucher : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Last certificate if any : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Month : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Number and month of the last schedule if any : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Mandal.Sattenapalli Amount of Estimate Rs. 10.00 Lakhs Voucher No. . . . . . . . . . . . . . . . .
Overseer's No. . . . . . . . . . . Authority covering list No.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Schedule No. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
Quantity Executed Amount
Sinc
e
Miles
Remarks
last Up to date
date certif certificate
icate
810801.99 507170.87
CERTIFICATES
1 Certified that the work was completed in all respects as per agreement conditions.
2 Certified that there are no further recoveries to be effected in this bill other than now proposed.
3 Certified that there are no liabillities out standing against the contractor.
Certified that all the required materials have been conveyed to site from specified quarry as noted
4 in the lead statement appended.
5 Certified that no Departmental machinary were issed to the work.
6 Certified that the materials issued by the department on the work is here with enclosed.
CONTRACTOR
Rural Development Department
MNREGS-AP
Input Data Sheet for the work
Name of the Work:- Providing CC Road and Drain approach to RBK Building at
Uppalapadu (V) of Rajupalem (M)
Mandal: Rajupalem
1. The estimate should be prepared habitation wise.
4. The detailed estimate, datasheet and lead statement prepared manually outside the computer should be tied to
the computer generated estimate.
A) General Information
ID
DCC (Departmental Computer Center) Name : Narasaraopeta
Name of Mandal Rajupalem
Name of Gram Panchayat Uppalapadu
Name of Habitation Uppalapadu
Abstract estimate
Providing CC Road and Drain approach to RBK Building at
Name of the official filling the details : Uppalapadu (V) of Rajupalem (M)
Estimate Cost Rs. 4.00 Lakhs
Quantites and Rates shall be as per technically sanctioned estimate. Rates shall be worked out as per standard
data basing on rates available in RSSR and CSSR.
Rate Per
Amount
SNo Task Name Unit Task code Qty Unit
(in Rs) (Rs.)
PART-A
1 CW-01. Amount for wage component days 19376 35.99 272.00 9788.00
2 CW-02. Cement bags 19377 276.00 270.00 74520.00
CW-07. 20 mm and 12mm HBG/HBT
3 Metal: Constiting of 20mm metal 66% Cum 19382 34.60 2126.67 73583.00
and 12 mm metal 34%
4 CW-09. 40mm HBG Graded Metal Cum 19384 11.79 1611.70 19002.00
5 CW-19 Sand for concrete Cum 23.21 1411.70 32766.00
6 CW-10. Others : Total Amount 19385 172109.00
381768.00
7 CW-12 QC Charges @ 0.50% 1909.00
8 CW-13 Segniorage Charges 13217.00
9 CW-15 Provision for Unforseen items 3106.00
400000.00
Name of the official filling the details : k Narasimha Rao
Designation of the official filling the details : Assistant Engineer
Signature:
Date: