NABARD RIDF XX
DETAILED ESTIMATE
Name of the District :
SoR 2014-15
1 Necessity :
River :
Existing structures : :
MFL : + 82.505
R.C.L : + 81.58
Foundation strata, SBC and Type of : Individual footings with VRCC M25 is provided
foundations adopted
Sub structure :
Piers: Wall type pipers are proposed in VRCC M25 with skin
reinforcement is proposed.
Abutments Wall type pipers are proposed in VRCC M25 with skin
reinforcement is proposed.
Comon standard schedule of rates for all engineering departments for the year 2014-15 (effective
from 1st June, 2014) approved by the Board of Chief Engineers.
The total amount of work for the above scope of work is working out to Rs.175.00 lakhs.
7. Conclusion :
The work shall be carried out as per approved, designs and drawing, MORTH specifications and
APSS, relevant IRC and IS codes, relevant circulars issued by the department from time to time.
5310
452.876
82.505
2.167
81.58
BRIDGES
Earthwork Earthwork
Total Length Land
S. Sub Land (Above (Above
Proj. Distric Mand Divisio MLA MP length of propose acquisitio
No Tranche Project Name Circle divisio acuisiltio water water
Code t al n Const Const the d for n
. n n cost level ) level )
Bridge loan quantity
quantity cost
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Karimnagar
Karimnagar
Karimnagar
Karimnagar
CONSTRUCTION OF
Siricilla
Siricilla
Siricilla
LOW LEVEL CAUSEWAY
1 RIDF XX 93 93 No 0 1050.14 97495
ON R/F ZP ROAD TO
BHARATHNAGAR
Lean Mix Lean Mix
concrete concrete
Wearing Wearing
Sub under under
Earthwork Earthwork Coat of Coat of
structure wearing Water
(Below (Below Foundatio Sub Approach NVL NVL Bed Bed
Foundatio quantity Approach cost of cost of Deck slab Deck slab
water water n Quantity structure Slab Portion portion Blocks blocks
n Cost (Piers & slab cost NVL NVL Quantity Cost
level ) level ) (Cum) Cost quantity and and quantity Cost
Abutment portion portion
quantity cost Ramps Ramps
s) and and
quantity Cost
ramps ramps
quantity cost
18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
716.12 69807 729.33 3755894 768.97 4845234 47.32 181697 107.53 636592 15.18 95648 271.47 1917154
Others
(i.e., Well
Class
Sinking, No.of
Steel Road (or) Eligible of road Cycle
Steel Aprons, Project villages Popul Market School / Hospita Hand Horse Bullock M.Cycl Tracto
Quantity Approach cost for (VR/ Cycle ricksha Car
Cost Revetmen Cost benifite ation yard College l Cart Veh. Cart e r
(in MT) Road cost loan ODR/ w
t, Weep d
MDR)
holes, B
earings
34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53
40.04 2417964 565240 1198229 17500000 17500000 VR 2 5310 1 2 1 275 0 0 0 75 425 40 155
Pro-
SSR- Span Foundatio Dist.sav Ex.Br Pilgrimag Tourist
Bus Trailor Bridge Spans Super str Ex.brwid EW Qty. EW Cost Remarks
Year length n e in KM length e centre spot
Width
54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69
VRCC VRCC
15 155 2014 7.5 4 10 8 0 0 1766.26 167302.00 0 0
M25 M25
GENERAL ABSTRACT
NABARD RIDF XX
7 Providing and laying reinforced cement concrete M25 grade (Design Mix)
using 20 & 10mm HBG metalmechanically mixed in superstructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5
MORD / Sections 1500, 1600 & 1700 MORTH ,including overhead charges
& Contractors profit ,VAT & Seignarage charges.
8 Backfilling behind abutment, wing wall and return wall complete as per
drawings & technical specification Clause 1204.3.8 MORD / 710.14 of IRC,
78 & 2200 MORTH ,including overhead charges & Contractors profit ,VAT
& Seignarage charges.
14 Supplying and fixing of RCC guard stones including cost of stones, labour
charges, fixing etc., complete
Over bridge portion 46 x 2 92.00
Over approaches ### x 2 400.00
492.00 568.37 Each 279640
Total: 14582725
6 Providing and applying tack coat with Bitumen emulsion (RS-1) using
emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the
prepared granular surfaces treated with primer / (or dry and hungry
bituminous surface) & cleaned with Hydraulic broom as per Technical
Specification Clause 503 MORD,including overhead charges &
Contractors profit but excluding VAT.
1198229
2 E/w for widening (Carted 936.00 Cum Earth 936.00 22.00 20592
earth)
1 GSB (66% gravel & 34% 240.00 Cum Gravel 204.00 22.00 4488
sand)
Sand 103.2 40.00 4128
4 WBM Gr-II 0.00 Cum Metal & stone 0.00 50.00 0
dust
5 WBM Gr-III 0.00 Cum Metal 0.00 50.00 0
5 WMM 240.00 Cum Metal 319.20 50.00 15960
6 OGPC 1500.00 Sqm Metal 40.50 50.00 2025
7 Seal coat 1500.00 Sqm Sand 9.00 40.00 360
2 CC pavement 0.00 Sqm Metal 0.00 50.00 0
Sand 0 40.00 0
9 Shoulders (Selected earth) 225.00 Cum Gravel 225.00 22.00 4950
29664
Deduct Total
Add 25% Seignor
Convey- 14% over Deduct amount
Sl. Lead in Initial Blasting extra for age
Description Quarry ance heads on for excluding Remarks
No. KM Cost charges machine charge
Charges conveyan stocking conveyan
crushing s
ce ce
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
1 60-63 mm IRC HBG Metal 20.00 419.00 273.10 -33.54 70.00 728.56
2 50-55 mm IRC HBG Metal 20.00 456.00 273.10 -33.54 70.00 765.56
3 40-45 mm IRC HBG Metal 20.00 588.00 273.10 -33.54 70.00 897.56
4 25-27 mm IRC HBG Metal 20.00 944.00 273.10 -33.54 70.00 1253.56
5 19-22 mm IRC HBG Metal 20.00 984.00 273.10 -33.54 70.00 1293.56
6 40-45 mm IRC HBG Metal 20.00 588.00 273.10 -33.54 70.00 147.00 1044.56 1267.06 37.5-25
7 25-27 mm IRC HBG Metal 20.00 944.00 273.10 -33.54 70.00 236.00 1489.56 1357.89 WMM
8 19-22 mm IRC HBG Metal 20.00 984.00 273.10 -33.54 70.00 246.00 1539.56 1117.56 WBMM
9 12-14 mm IRC HBG Metal 20.00 780.00 273.10 -33.54 70.00 195.00 1284.56 1207.06 WMM
10 9.5-11.2 mm for Grading 2 20.00 656.00 273.10 -33.54 70.00 164.00 1129.56 1034.56 WMM
11 5-7 mm IRC HBG Metal 20.00 504.00 273.10 -33.54 70.00 126.00 939.56 1117.89 BT
12 5-2.36 mm HBG metal 20.00 308.00 273.10 -33.54 70.00 77.00 694.56 817.06 Gr.II
13 40mm HBG chips-SS5 20.00 620.00 273.10 -33.54 70.00 155.00 1084.56 1034.56 10-5
14 20mm HBG chips-SS5 20.00 1036.00 273.10 -33.54 70.00 259.00 1604.56 921.23 9.5-2.36
15 12mm HBG chips-SS5 20.00 822.00 273.10 -33.54 70.00 205.50 1337.06 637.06 5mm & below
16 10mm HBG chips-SS5 20.00 692.00 273.10 -33.54 70.00 173.00 1174.56 1360.81 25-10
17 2.36mm Below metal 20.00 340.00 273.10 -33.54 579.56 1012.06 12-2.36
18 Stone boulder 300mm (25 20.00 156.00 273.10 -33.54 395.56
kg / 40 Kg minimum)
19 Soling stone 150mm 20.00 95.00 273.10 -33.54 334.56
Deduct Total
Add 25% Seignor
Convey- 14% over Deduct amount
Sl. Lead in Initial Blasting extra for age
Description Quarry ance heads on for excluding Remarks
No. KM Cost charges machine charge
Charges conveyan stocking conveyan
crushing s
ce ce
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
20 Jeddy stone 450-600mm 20.00 188.00 273.10 -33.54 427.56
21 Gravel 10.00 103.00 147.10 -18.06 232.04
22 Selected earth 10.00 40.00 147.10 -18.06 169.04
23 Sand for concrete 15.00 462.00 210.10 -25.80 646.30
24 Sand for Filling 2.00 342.00 44.10 -5.42 380.68
25 Bitumen 60/70 805.00 43090.57 2415.00 2154.53 47660.10
26 Bitumen emulsion (SS-1) 805.00 32254.99 2415.00 1612.75 36282.74
27 Bitumen emulsion (RS-1) 805.00 33719.57 2415.00 1685.98 37820.55
28 Cement 5900.00 5900.00
29 Mild steel 46500.00 46500.00
30 Steel 46500.00 46500.00
31 1000mm dia pipes (Part-I) 55.00 5379 640.50 6019.50
32 700mm dia pipes (Part-I) 55.00 2609 339.00 2948.00
33 600mm dia pipes (Part-I) 55.00 2099 295.50 2394.50
34 1000mm dia collars (Part-I) 55.00 945 945.00
35 700mm dia collars (Part-I) 55.00 510 510.00
36 600mm dia collars (Part-I) 55.00 379 379.00
1) Certified that the leads are provided in the estimate is nearest and correct to the best of my knowledge.
2) The stone quarry is of blasting type. Hence provided blasting charges
4 RBR- Providing concrete for reinforced concrete M 25 grade (Design Mix) in open
FNDN-4
foundations using 20 & 10 mm nominal size Graded hard stone aggregate,
mechanically mixed, placed in foundation and compacted by vibration
including curing for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 &
2100 MORTH ,including overhead charges & Contractors profit ,VAT &
Seignarage charges. -For Footings
R.C.C grade M 25 (Design Mix) using 20 mm Graded
Metal (MORTH) -For Footings
CASE I : Using Concrete Mixer
Unit = cum
(a) Material
Cement t 0.403 5900.00 2377.70
Coarse sand cum 0.45 646.30 290.84
20 mm aggregate cum 0.54 1604.56 866.46
10 mm aggregate cum 0.36 1174.56 422.84
Water kl 0 77.00 0.00
(b) Labour
Mate day -
Mason (1st Class) day 0.1 385.00 38.50
Mazdoor (Unskilled) day 1.39 295.00 410.05
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hr / 0.4 453.00 181.20
cum
Generator 33 KVA hour 0 861.70 0.00
4587.59
(d) Formwork @ 4% on (a+b+c) 4.00% 183.50
S. No. Index Amount
Description of item Unit Qty Rate
Code
f) . 4771.09
Over head charges & Contractors profit @14.00%- 14.00% 667.95
Rate per cum = a+b+c+d+e+f+g Rs 5439.04
5 RBR- Supplying, fitting, and placing HYSD bar reinforcement in foundation
FNDN-4
complete as per drawing and technical specifications Clauses 1002, 1010
and 1202 MORD / 1600 MORTH, for Bars below 36 mm dia including over
laps and wastage, where they are not welded ,including overhead charges
& Contractors profit ,VAT & Seignarage charges.
Unit = t
(a) Material
HYSD bars including 5 per cent for laps and wastage t 1.05 48825.00
46500.00
6 RBR- Providing concrete for plain concrete M15 ( Nominal mix) in open
FNDN-4
foundations using 40,20 & 10mm size Graded hard stone aggregate,
mechanically mixed, placed in foundation and compacted by vibration
including curing for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 &
2100 MORTH ,including overhead charges & Contractors profit ,VAT &
Seignarage charges. for Foundations
Note : Water for concrete : A provision for cost of water may be added at
1.2 kl / 1 cum (including curing purpose) keeping the site conditions
Coarse Aggregate : Single grade nominal size can also be used instead of
graded metal, keeping the site conditions in view
Unit = cum
P.C.C grade M 15 ( Nominal mix ) MORTH ( for
Abutments, Piers, cut-off walls below Bed Level
Unit = cum
(a) Material
Cement t 0.275 5900.00 1622.50
Coarse sand cum 0.480 646.30 310.22
40 mm aggregate cum 0.480 1084.56 520.59
20 mm aggregate cum 0.240 1604.56 385.09
10 mm aggregate cum 0.080 1174.56 93.96
Water kl 1.2 77.00 92.40
(b) Labour
Mason (1st Class) day 0.100 385.00 38.50
Mazdoor (Unskilled) day 1.390 295.00 410.05
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 453.00 181.20
Generator 33 KVA hour 0.000 861.70 0.00
S. No. Index Amount
Description of item Unit Qty Rate
Code
3654.51
(d) Formwork @ 4% on cost of material, labour and 4.00% 146.18
machinery (a+b+c)
e). 3800.69
Over head charges & Contractors profit @14.00%- 14.00% 532.10
Rate per cum = a+b+c+d+e+f Rs 4332.79
7 RBR- Plain cement concrete M15grade (Nominal mix) using 40,20 & 10mm
SBST-5
HBG metal mechanically mixed in substructure complete as per drawings
and technical specification Clauses 802, 804, 805, 806, 807, 1202 and
1204 MORD and 1500, 1700 & 2200 MORTH ,including overhead charges
& Contractors profit ,VAT & Seignarage charges. for Abutments, Piers,
cut-off walls above Bed Level
Note : Water for concrete : A provision for cost of water may be added at
1.2 kl / 1 cum (including curing purpose) keeping the site conditions
Coarse Aggregate : Single grade nominal size can also be used instead of
graded metal, keeping the site conditions in view
For height up to 5 m
Unit = cum
P.C.C grade M15 (Nominal mix) MORTH for
Abutments, Piers, cut-off walls above Bed Level
Unit = cum
(a) Material
Cement t 0.275 5900.00 1622.50
Coarse sand cum 0.480 646.30 310.22
40 mm aggregate cum 0.480 1084.56 520.59
20 mm aggregate cum 0.240 1604.56 385.09
10 mm aggregate cum 0.080 1174.56 93.96
Water kl 1.2 77.00 92.40
(b) Labour
Mason (1st Class) day 0.100 385.00 38.50
Mazdoor (Unskilled) day 1.390 295.00 410.05
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 453.00 181.20
Generator 33 KVA hour 0.000 861.70 0.00
3654.51
(d) Formwork @ 10% on cost of material, labour and 10.00% 365.45
machinery (a+b+c)
e). 4019.96
Over head charges & Contractors profit @14.00%- 14.00% 562.79
Rate per cum = a+b+c+d+e+f Rs 4582.75
8 RBR- Supplying, fitting, and placing HYSD bar reinforcement in sub structure
SBST- 6
complete as per drawing and technical specifications Clauses 1002, 1010
and 1202,1005MORD / 1600 &2200 MORTH, for Bars below 36 mm dia
including over laps and wastage, where they are not welded ,including
overhead charges & Contractors profit ,VAT & Seignarage charges.
Unit = t
(a) Material
HYSD bars including 5 per cent for laps and wastage Fe t 1.05 48825.00
46500.00
415
S. No. Index Amount
Description of item Unit Qty Rate
Code
Binding wire kg 6.00 70.00 420.00
(b) Labour for cutting, bending, tying and placing in
position
Blacksmith/ Rod Binder day 2.00 385.00 770.00
Mazdoor (Unskilled) day 6.84 295.00 2017.80
c). 52032.80
Over head charges & Contractors profit @14.00%- 14.00% 7284.59
Rate per t = a+b+c Rs 59317.39
9 RBR- Providing concrete for reinforced concrete M 25 grade (Design Mix) in Sub
SBST-5
structure using 20 & 10 mm nominal size Graded hard stone aggregate,
mechanically mixed, placed in foundation and compacted by vibration
including curing for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 &
2100 MORTH ,including overhead charges & Contractors profit ,VAT &
Seignarage charges.
R.C.C grade M 25 (Design Mix) using 20 mm Graded Metal (MORTH) -For
abutment, piers
CASE I : Using Concrete Mixer
Unit = cum
(i) Height up to 5m
(a) Material
Cement t 0.403 5900.00 2377.70
Coarse sand cum 0.45 646.30 290.84
20 mm aggregate cum 0.54 1604.56 866.46
10 mm aggregate cum 0.36 1174.56 422.84
Water kl 0 77.00 0.00
(b) Labour
Mate day 0 385.00 0.00
Mason (1st Class) day 0.1 385.00 38.50
Mazdoor (Unskilled) day 1.39 295.00 410.05
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hr / cum 0.4 453.00 181.20
Generator 33 KVA hour 0.4 861.70 344.68
4932.27
(d) Formwork @ 10% on (a+b+c) 10.00% 493.23
e). 5425.50
Over head charges & Contractors profit @14.00%- 14.00% 759.57
Rate per cum = a+b+c+d+e+f Rs 6185.07
(ii) Height 5m to 10 m
(a) Material
Cement t 0.347 5900.00 2047.30
Coarse sand cum 0.45 646.30 290.84
20 mm aggregate cum 0.54 1604.56 866.46
10 mm aggregate cum 0.36 1174.56 422.84
Water kl 1.2 77.00 92.40
(b) Labour
Mate day 0.06 385.00 23.10
Mason (1st Class) day 0.1 385.00 38.50
Mazdoor (Unskilled) day 1.33 295.00 392.35
(c) Machinery
S. No. Index Amount
Description of item Unit Qty Rate
Code
Concrete mixer 0.4/0.28 cum capacity hr / cum 0.4 453.00 181.20
Generator 33 KVA hour 0.4 861.70 344.68
4699.67
(d) Formwork @ 12% on (a+b+c) 12.00% 563.96
(e) Add on cost of material, Labour and machinery 2.00% 93.99
excluding formwork to cater for extra lift
5357.62
Over head charges & Contractors profit @14.00%- 14.00% 750.07
Rate per cum = a+b+c+d+e+f+g Rs 6107.69
12 RBR- Backfilling behind abutment, wing wall and return wall complete as per
SBST-10
drawings & technical specification Clause 1204.3.8 MORD / 710.14 of IRC,
78 & 2200 MORTH ,including overhead charges & Contractors profit ,VAT
& Seignarage charges.
Unit = cum
Taking output = 10 cum
Granular material
(a) Material
Granular material cum 12.000 232.04 2784.48
(b) Labour
Mate day -
Mazdoor (Unskilled) day 7.280 295.00 2147.60
(c) Machinery
Plate compactor / power rammer hour 2.500 0.00
Water Tanker of 6 KL capacity hour 0.050 624.00 31.20
4963.28
Over head charges & Contractors profit @14.00%- 14.00% 694.86
Rate per 10 cum = a+b+c+d 5658.14
Rate per 1 cum = 565.81
Rate per cum = (a+b+c+d+e ) Rs 565.81
S. No. Index Amount
Description of item Unit Qty Rate
Code
14 RBR- Providing and laying reinforced cement concrete M30 grade (Design Mix)
SPST-1
using 20 & 10mm HBG metalmechanically mixed in superstructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5
MORD / Sections 1500, 1600 & 1700 MORTH ,including overhead charges
& Contractors profit ,VAT & Seignarage charges.
Unit = t
(a) Material
HYSD bars including 5 per cent for laps and wastage t 1.05 48825.00
46500.00
(a) Material
Cement t 0.407 5900.00 2401.30
Sand cum 0.45 646.30 290.84
20 mm aggregate cum 0.54 1604.56 866.46
10 mm aggregate cum 0.36 1174.56 422.84
HYSD bar reinforcement including binding wire (Rate as t 0.075 0.00 0.00
per item 13.2) except OH & CP
Water kl 1.2 77.00 92.40
(b) Labour
Mason (1st Class) day 0.10 385.00 38.50
Mazdoor (Unskilled) day 1.39 295.00 410.05
Mazdoor (Unskilled) for cleaning deck slab concrete day 0.15 44.25
295.00
surface
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 453.00 181.20
Generator 33 KVA. hour 0.40 861.70 344.68
5092.52
(d) Formwork @ 3% of cost of concrete 3.00% 152.78
5245.30
Over head charges & Contractors profit @14.00%- 14.00% 734.34
5979.64
Rate per cum = a+b+c+d+e+f Rs 5979.64
17 RBR- Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm
SPST-7
nominal size aggregate, true to line and grade, tolerance of vertical railing
post not to exceed 1 in 500, centre-to-centre spacing between vertical
posts not to exceed 2000 mm as per drawing and technical specifications
Clauses 800, 900 and 1208.3 MORD. ,including overhead charges and
contractors profit ,VAT & Seignarage charges.
Unit = Running m
Taking output = 4x12 m
Span = 48 m
(a) M 25 grade R.C.C.
No. of vertical posts = (6+1) 4 = 28 nos
Cross-sectional area of vertical post = 0.25x0.275 =
0.069 sqm
Concrete in vertical posts = 0.069x28x1.00 = 1.932 cum
106266.89
S. No. Index Amount
Description of item Unit Qty Rate
Code
Over head charges & Contractors profit @14.00%- 14.00% 14877.36
Cost for 48 m = (a+b+c ) 121144.25
Rate per m = (a+b+c )/48 Rs 2523.84
Sub Analysis for Rate of Concrete
(a) Material
Cement t 0.40 5900.00 2360.00
Coarse sand cum 0.45 646.30 290.84
20 mm aggregate cum 0.54 1604.56 866.46
10 mm aggregate cum 0.36 1174.56 422.84
Water kl 1.2 77.00 92.40
(b) Labour
Mate day
Mason (1st Class) day 0.12 385.00 46.20
Mazdoor (Unskilled) day 2.09 295.00 616.55
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 453.00 181.20
4876.49
d). Formwork @ 12% 12.00% 585.18
Total (a+b+c+d) 5461.67
Rate per cum = a+b+c+d+e+f Rs 5461.67
18 RBR- P.C.C. M 15 ordinary grade (1:2.5:5) leveling course below approach slab
SPST-12
complete as per drawing and technical specifications Clauses 800 and
1211 MORD & 2700 MORTH ,including overhead charges and contractors
profit ,VAT & Seignarage charges.
Unit = cum
(a) Material
Cement t 0.275 5900.00 1622.50
Coarse sand cum 0.48 646.30 310.22
40 mm aggregate cum 0.54 1084.56 585.66
20 mm aggregate cum 0.27 1604.56 433.23
10 mm aggregate cum 0.09 1174.56 105.71
Water kl 1.2 77.00 92.40
(b) Labour
Mason (1st Class) day 0.10 385.00 38.50
Mazdoor (Unskilled) day 1.39 295.00 410.05
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 453.00 181.20
Generator 33 KVA. hour 0.40 861.70 344.68
4124.15
Over head charges & Contractors profit @14.00%- 14.00% 577.38
Rate per cum = a+b+c+d+e+f+g Rs 4701.53
19 RBR- Reinforced cement concrete M-30 Grade for approach slab including
SPST-13
reinforcement and formwork complete as per drawing and Technical
specification Clause 800, 1211 MORD / 1500, 1600, 1700 & 2704 MORTH
,including overhead charges and contractors profit ,VAT & Seignarage
charges.
S. No. Index Amount
Description of item Unit Qty Rate
Code
Unit = 1 cum For Approach Slab
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.00 5048.27 5048.27
concrete in item 1(III) by using batching plant, excluding
steel formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP, steel cost,deck slab cleaning )
asper Item no : 16
b). Form Work : Refer relevant item of concrete in item No. cum 2.00% 5048.27 100.97
1(III) except that form work may be added at the rate of
2 per cent of cost against 3.5 per cent provided in the
foundation concrete.
c). HYSD bar reinforcement Rate as per item No:15 t 0.05 0.00 0.00
(Excluding OH&CP)
5149.24
Over head charges & Contractors profit @14.00%- 14.00% 720.89
5870.13
Rate per cum = a+b+c+d+e Rs 5870.13
22 RBR- Providing and laying boulder apron for bed protection with stone boulders
PTWK-1
of minimum size and weight as per Table 1300.1, no fragment weighing
less than 25 / 40 kg laid dry complete as per drawing and technical
specifications Clause 1301 MORD / 2503 MORTH ,including overhead
charges and contractors profit ,VAT & Seignarage charges.
Unit = cum
(a) Material
Stone boulder (25 kg / 40 Kg minimum) cum 1.00 395.56 395.56
Stone spalls cum 0.20 334.56 66.91
(b) Labour
Mate day 0.00 0.00
Mason 1st Class day 0.35 385.00 134.75
Mazdoor (Unskilled) day 0.79 295.00 233.05
830.27
Over head charges & Contractors profit @14.00%- 14.00% 116.24
946.51
Rate per cum = a+b+c+d Rs 946.51
23 RBR- Jeddy Stone Dry Packing for Aprons and Revetments Section 1300 MORD
PTWK-1
,including overhead charges and contractors profit ,VAT & Seignarage
charges.
Unit = cum
(a) Material
Jeddy Stone (Including small stone for wedging) cum 1.20 427.56 513.07
(b) Labour
Mate day 0.00 0.00 0.00
Mason 1st Class day 0.35 385.00 134.75
Mazdoor (Unskilled) day 1.05 295.00 309.75
957.57
Over head charges & Contractors profit @14.00%- 14.00% 134.06
1091.63
Rate per cum = a+b+c+d Rs 1091.63
S. No. Index Amount
Description of item Unit Qty Rate
Code
2. In case of bridges, sufficient length of G.I Pipe shall be provided to ensure that there is no splashing of
water from the drainage spout on the structure.
Add 5 per cent of cost of material for anchorage 5.00% 18383.50 919.18
reinforcement, welding and other incidentals.
19302.68
Over head charges & Contractors profit @14.00%- 14.00% 2702.38
S. No. Index Amount
Description of item Unit Qty Rate
Code
Cost for 12 m = (a+b+c+d) 22005.06
Rate per m = (a+b+c+d)/12 1833.76
S. Index
Description of item Unit Qty Rate Amount
No. Code
By Machanical Means
In area of non Throny Jungle (Light Jungle)
Unit =10 Sqm
Out put = 1 Hectare
a) Labour
Mazdoor (un-skilled) day 4.16 295.00 1227.20
b) Machinery
Dozer D-50 with attachment or suitable machinery for removal of hour 10.00 1570.00 15700.00
trees & stumps
Tractor with trolley 3t hour 1.00 422.00 422.00
Over head charges & Contractors profit @14.00%- 14.00% 17349.20 2428.89
Rate for hectare 19778.09
19778.09
Rate per 10 Sqm = (a+b+c)/10000 1.98
Unit = cum
Taking output = 100 cum
a) Labour
Mazdoor (Unskilled) day 1.04 295.00 306.80
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum per hr hour 1.67 2,848.50 4757.00
Tipper 5.5cum with 10T capacity hour 4.50 922.00 4149.00
Dozer D50 for spreading @ 200 cum per hour hour 0.50 1,570.00 785.00
Tractor with Grader @ 25 cum per hour hour 4.00 422.00 1688.00
Water tanker 6 KL capacity hour 2.00 624.00 1248.00
Vibratory Roller 80-100 KN @100cum per hour hour 1.00 2678.30 2678.30
Over head charges & Contractors profit @14.00%- 14.00% 15612.10 2185.69
17797.79
Rate per cum 177.98
By Manual means
Taking out put = 360 cum
a) Labour
Mazdoor (Skilled) day 12.08 295.00 3563.60
Mazdoor (unskilled) day 250.00 295.00 73750.00
b) Machinery
Vibratory Roller 80-100 KN @60cum per hour hour 6.00 2678.30 16069.80
Water tanker 6kl capacity hour 24.00 624.00 14976.00
c) Material (Total Qty 435.60 Cum)
60-63 mm IRC HBG Metal (50% of 435.60 cum) Cum 217.80 728.56 158680.37
40-45 mm IRC HBG Metal (46% of 435.60 cum) Cum 200.38 897.56 179853.07
19-22 mm IRC HBG Metal (4% of 435.60 cum) Cum 17.42 1539.56 26819.14
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm cum 86.40 817.06 70593.98
Binding Material @ 0.06 cum per 10 sqm for Grading 2 material cum 28.80 579.56 16691.33
Basic rate for 360 Cum 560997.29
Rate per Cum 1558.33
d) Over head charges & Contractors profit @ 14.00% 218.17
Rate per cum 1776.50
S. Index
Description of item Unit Qty Rate Amount
No. Code
By Manual means
Taking out put = 360 cum
a) Labour
Mazdoor (Skilled) day 12.08 295.00 3563.60
Mazdoor (unskilled) day 250.00 295.00 73750.00
b) Machinery
Vibratory Roller 80-100 KN @60cum per hour hour 6.00 2678.30 16069.80
Water tanker 6kl capacity hour 24.00 624.00 14976.00
c) Material (total Qty of Metal 435.60 Cum)
40-45 mm IRC HBG M/c Metal ( 82% of 435.60 Cum) Cum 357.19 1044.56 373106.39
19-22.40 mm IRC HBG M/c Metal ( 18% of 435.60 cum) Cum 78.41 1539.56 120716.90
Stone Screening
Type -B 11.2mm @ 0.18 cum per 10 sqm cum 86.40 579.56 50073.98
(rate of 2.36 mm & below)
Binding Material
Basic rate for 360 Cum 652256.67
Rate per Cum 1811.82
d) Over head charges & Contractors profit @ 14.00% 253.66
Rate per cum 2065.48
Fine aggregate/crushed sand 2.36 mm to 75 mm micron @ 30% cum 39.90 579.56 23124.44
d) Over head charges & Contractors profit @ 14% on (a+b+c) 14.00% 164995.25 23099.34
Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared
surface of granular base including cleaning of road surface and spraying primer at
the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification
Clause 502 MORD (for use on Wet mix macadam & WBM) ,including overhead
charges & Contractors profit but excluding VAT.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mazdoor (Unskilled) day 1.040 295.00 306.80
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.400 357.00 499.80
Air compressor 210 cfm hour 1.400 507.50 710.50
Bitumen emulsion pressure distributor @ 1750 sqm/hour hour 1.000 860.00 860.00
Water tanker 6 kl capacity 1 trip per hour hour 0.500 624.00 312.00
S. Index
Description of item Unit Qty Rate Amount
No. Code
c) Material
Bitumen emulsion (SS-1) @ 0.85 kg per sqm t 1.480 36282.74 53698.46
Water kl 3.000 77.00 0.00
Cost of 1750 sqm = a+b+c 56387.56
(d) Rate per sqm = (a+b+c)/1750 32.22
(e) d,e)Over head charges & contracots profit @ 14.00% on 4.51
(a+b+c+d)
Rate per sqm 36.73
11 RBR- Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion
BASC-2
distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces
treated with primer / (or dry and hungry bituminous surface) & cleaned with Hydraulic
broom as per Technical Specification Clause 503 MORD,including overhead charges
& Contractors profit but excluding VAT.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day 0.000 385.00 0.00
Mazdoor (Unskilled) day 1.040 295.00 306.80
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.400 357.00 499.80
Air compressor 210 cfm hour 1.400 507.50 710.50
Emulsion pressure distributor @1750 sqm per hour hour 1.000 860.00 860.00
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm t 0.480 37820.55 18153.86
Cost of 1750 sqm = (a+b+c) 20530.96
(d) Rate per sqm = a+b+c/1750 11.73
(e) e)Over head charges & contracots profit @ 14.00% on 1.64
(a+b+c+d)
13.37
Providing and laying bituminous liquid Seal coat (Type B - by Manual means)
comprising of a layer of bitumuneous binder followed by a cover of stone chipping of
grading as defined in table 500.16 of MOST Crushed sand defined as passing
through 2.36 mm sieve and retained on 180 micron seive applied @ 0.06 cum per 10
sqm.to be laid simultaneously along with the bitumunous course using 6.80 kgs of
bitumen 60/70 grade for 10 sqm and rolling with power roller including of required
line, level, grade to serve as wearing course on previously prepared surface and
finishing to rquired level and grades including cost and conveyance of all materials
from approved sources and stacking at site to departmental gauge for
premeasurements, labour charges and hire and operational charges of power road
roller 8 to 10 tonnes capacity and all other machinery, tools and plants, providing
barricading for diversion of traffic, erecting red flags other incidental and operational
charges etc., complete for finished item of work as per technical specification clause
510 of MORD.including all over heads , and Contractors profit but excluding VAT &
Seignorage charges.
c) Material
Bitumen (S-65) @ 6.80 kg per 10 sqm t 0.850 47660.10 40511.09
Crushed sand or grit as passing 2.36 mm sieve and retained on cum 7.500 380.68 2855.10
180 micron sieve applied @ 0.06 cum/10 sqm
d&e) Overheads & Contractors Profit 14.00% 53153.69 7441.52
Cost of 1250 sqm = a+b+c+d+e 60595.21
Rate per sqm = (a+b+c+d+e)/1250 48.48
c) Material
(I) Crushed stone coarse aggregates, grading will be as per clause
1501.2.4.1 (Table 1500.1) of specifications @ 0.90 Cum/cum of
concrete
20mm Cum 44.55 1604.56 71483.15
10mm Cum 22.95 1174.56 26956.15
(ii) Sand as per IS:383 and conforming to clause 1500.2.4.2. @ 0.45 cum 33.75 646.30 21812.63
cum of concrete
S. Index
Description of item Unit Qty Rate Amount
No. Code
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
Sub Analysis
RBR-
FNDN-7
24 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per
drawings and technical specifications Clauses 1000 and 1202 MORD & 1100, 1600
MORTH for Bars below 36 mm dia including over laps and wastage, where they are not
welded.
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps and t 1.05 46500.00 48825.00
wastage
Binding wire kg 6.00 70.00 420.00
(b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day -
Blacksmith day 2.00 385.00 770.00
Mazdoor (Unskilled) day 6.40 295.00 1888.00
Over head charges & Contractors profit @14.00%- 14.00% 372.12
RBR- 25 Earthwork in excavation for structures as per drawing and technical specifications Clause
FNDN-1
305.1 including setting out, construction of shoring and bracing, removal of stumps and
other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom
and backfilling in trenches with excavated suitable material as per Technical
Specification 305 MORD / 304 MORTH ,including overhead charges & Contractors
profit ,VAT & Seignarage charges.
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
Note : Water for concrete : A provision for cost of water may be added at 1.2 kl / 1 cum
(including curing purpose) keeping the site conditions
Coarse Aggregate : Single grade nominal size can also be used instead of graded metal,
keeping the site conditions in view
For height upto 5 m
Unit = cum
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement t 0.275 5900.00 1622.50
Coarse sand cum 0.480 646.30 310.22
40 mm aggregate cum 0.480 1084.56 520.59
20 mm aggregate cum 0.240 1604.56 385.09
10 mm aggregate cum 0.080 1174.56 93.96
(b) Labour
Mate day -
Mason (1st Class) day 0.100 385.00 38.50
Mazdoor (Unskilled) day 1.390 295.00 410.05
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 453.00 181.20
(d) Formwork @ 4% on cost of material, labour and 4.00% 142.48
machinery (a+b+c)
3704.59
Over head charges & Contractors profit @14.00%- 14.00% 518.64
RBR- 27 Providing concrete for plain concrete M 10 grade in open foundations using 40 mm
FNDN-4
nominal size Graded hard stone aggregate, mechanically mixed, placed in foundation
and compacted by vibration including curing for 14 days complete as per drawings and
technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100
MORTH ,including overhead charges & Contractors profit ,VAT & Seignarage charges.
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 5900.00 1298.00
Coarse sand cum 0.45 646.30 290.84
40 mm aggregate cum 0.90 1084.56 976.1
Water kl 1.20 77.00 92.40
(b) Labour
Mate day -
Mason (1st Class) day 0.10 385.00 38.50
Mazdoor (Unskilled) day 1.39 295.00 410.05
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity hour 0.40 453.00 181.20
fitted with water measuring device and preferably also
with load cell.
RBR-TSRA
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
Water tanker 6 kl capacity hour 0.13 624.00 81.12
3368.21
Over head charges & Contractors profit @14.00%- 14.00% 471.55
RBR-
TSRA-1
28 Printing New Letters and Figures of any Shade
Printing new letter and figures of any shade with synthetic enamel paint black or any
other approved colour to give an even shade as per drawings and Technical
Specification Clause 1701 MORD / 801 MORTH ,including overhead charges &
Contractors profit ,VAT & Seignarage charges.
(ii) English and Roman
Hyphens, commas and the like not to be measured
and paid
Detail forfor.
100 letters of 160 mm height, i.e. 1600
cm
Unit = per cm height per letter
a) Labour
Mate day -
Painter 1st Class day 1.25 440.00 550.00
Painter Assistant day
Mazdoor (Unskilled) day 0.57 295.00 168.15
b) Material
Paint litre 0.50 240.00 120.00
Over head charges & Contractors profit @14.00%- 14.00% 117.34
RBR-
TSRA-2
29 Traffic Signs
Unit = Each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 107.38 13.53
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.126 4223.24 532.13
RBR-TSRA
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
(iii) Painting two coats including prime coat on
concrete surface with Epoxy Paint as per
specifications
As per item No. 9 of this Chapter sqm 0.46 78.54 36.13
(a) labour (For fixing at site)
Mate day -
Mazdoor (Unskilled) day 0.26 295.00 76.70
b) Material
Support of M.S. Sheet tube
(I) 47 mm x 47 mm x 12 SWG Sheet 3050 mm long kg 12.40 46.50 576.60
(II) Angle iron 50 x 50 x 6 mm for hold fast including kg 1.06 46.50 49.29
5% wastage
Add 3% cost of MS Sheet tube 12 SWG and angle 18.78
irons towards the cost of fabrication, drilling holes,
nuts and bolts etc.
(III) 1.5 mm thick M.S. Sheet duly painted with stove
enameled paint including lettering, signs, border,
message with reflective tape of engineering grade
required size, shade and colour as per Technical
Specifications
(i) 900 mm equilateral triangle sqm 0.35
OR
(ii) 600 mm equilateral triangle sqm 0.156
OR
(iii) 600 mm circular sqm 0.283
OR
(iv) 800 mm x 600 mm rectangular sqm 0.48
OR
(v) 600 mm x 450 mm rectangular sqm 0.27
OR
(0.36 Sqm. X 0.0015X7850 Kg/cum) Kg 4.24 46.50 197.11
(vi) 600 mm x 600 mm square sqm 0.36
OR
(vii) 900 mm side octagon sqm 0.672
(c) Machinery
Tractor with trolley hour 0.08 422.00 33.76
Over head charges & Contractors profit @14.00%- 14.00% 214.76
2. The rate for excavation, cement concrete M-15, and painting may be taken from respective
Chapters.
3. The depth of foundation and quantity of cement in the foundation are indicative. These may
be increased for areas having higher wind velocities like in coastal area. This is applicable to
all road signs and direction boards.
RBR-TSRA
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
RBR-
TSRA-3
30 Direction and Place Identification signs upto 0.9 sqm size board
Unit = each
Take Output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 107.38 13.53
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.126 4223.24 532.13
(iii) Painting on M.S. tube post with primer and two
coat of epoxy paint as per specifications
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
i Painting two coats including primer coat after filling the surface with synthetic enamel
paint in all shades on new, plastered / concrete surfaces as per drawing and Technical
Specification Clause 1701MORD.,including overhead charges & Contractors profit ,VAT
& Seignarage charges.
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day -
Painter (1st Class) day 3.00 440.00 1320.00
Painter Assistant day
Mazdoor (Unskilled) day 2.20 295.00 649.00
#REF! #REF! 492.25
b) Material
Cement Primer as per specifications litre 3.00 134.00 402.00
Paint conforming to requirement of Clause 1701.3.8 litre 6.00 184.00 1104.00
Painting two coats including prime coat with epoxy paint of approved brand on
concrete/steel surfaces after through cleaning of surface to give an even shade as per
drawing and Technical Specification Clause 1701 MORD ,including overhead charges &
Contractors profit ,VAT & Seignarage charges.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day -
Painter (1st Class) day 0.60 440.00 264.00
Mazdoor (Unskilled) day 0.65 295.00 191.75
b) Material
Epoxy primer / Red-oxide litre 0.60 121.00 72.60
Epoxy paint litre 1.25 203.00 253.75
Add @ 1 per cent on cost of material for scaffolding 3.26
wherever required
Over head charges & Contractors profit @14.00%- 14.00%
Cost for 10 sqm = a+b+c+d 785.36
Rate per sqm = (a+b+c+d)/10 78.54
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
Reinforced cement concrete M15 grade kilometre stone/local stone of standard design
as per IRC:8 fixing in position including painting and printing, etc as per drawing and
Technical Specification Clause 1703 MORD / 804 MORTH ,including overhead charges
& Contractors profit ,VAT & Seignarage charges.
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
Mate day -
Mason (1st Class) day 1.00 385.00 385.00
Mazdoor (Unskilled) day 7.32 295.00 2159.40
g) Machinery
50 HP Tractor with trolley hour 6.00 422.00 2532.00
Over head charges & Contractors profit @14.00%- 14.00% 3495.06
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
Providing and fixing of typical informatory sign board with Logo as per MORD
specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle plate duly
welded with MS flat iron 25mm x 5m size on back on edges. The lower plate will be we
welded with MS angle irone frame of 25 mm x 25 mm x 5 mm. The angle iron frame of
the lower most plate and flat iron frame of middle plate will be welded to 2 nos. 75 mm x
75 mm of 12 SWG sheet tubes posts duly embedded in cement concrete M-15 grade
blocks of 450 mm x 450 mm x 600 mm, 600 mm below ground level. The top most
diamond plate will be welded to middle plate by 47 mm x 47mm of 12 SWG sheet tube.
All M.s. will be stove enameled on both sides. Lettering and printing arrows, border etc.,
will be pointed with ready mixed synthetic enamel paint of superior quality in required
shade and colour. All sections of framed posts and steel tube will be painted with primer
and two coats of epoxy paint as per drawing clause 1701 MORD ,including overhead
charges & Contractors profit ,VAT & Seignarage charges.
Unit = Each
Taking out put = one typical board
i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.252 107.38 27.06
(ii) Cement Concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.252 4223.24 1064.26
(iii) Painting on MS Steel tubes with primer and two
coats of epoxy paint
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 9 of Chapter 10 sqm 1.80 78.54 141.37
(iv) Printing new letters and figures of any shade with synthetic
enamel paint black or any other approved colour to give an even
shade.
Index-
code S. No Description Unit Quantity Rate Rs. Amount Rs.
1 2 3 4 5 6
Add 3% cost of MS tube and angle iron towards the 122.52
cost of fabrications, drilling holes, nuts, bolts, etc.
c) Machinery
Tractor with trolley hour 0.24 422.00 101.28
Over head charges & Contractors profit @14.00%- 14.00% 1186.84