RESPONSE 

TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

1 Vol. 4 Viaduct DBR, Cl. 3.7, Pg. 4 Structural steel for steel and composite bridges: IS code for composite RCC is LSM based and as such may not be  Stipulations of Tender document shall prevail.


IS codes may be referred for steel ‐ RCC composite construction accepted by Railway authorities for Railway crossings. Please 
clarify.

2 Vol. 4 Viaduct DBR, Cl. 5.9, Pg. 6 Seismic Load: There are two various viz, RDSO guidelines published in 2015 and  Please refer Addendum No. 1. 


Seismic code for earthquake Resistance Design of Railway  Indian Railway standard published in 2007. Please clarify the code 
bridges shall be followed. to be followed.

3 Vol. 4 Viaduct DBR, Cl. 7.5, Pg. 10 Exposure Condition shall be as per  IRS CBC and will be decided  Please mention/clarify the exposure condition Stipulations of Tender document shall prevail.


by MMRDA

4 Vol. 4 DBR Station, Cl. 1.2, Pg. 4 Scope of Project: Please confirm that Metro live loads are rolling stock loads. Stipulations of Tender document shall prevail.


Structural elements of stations which do not support Metro live 
loads.

5 Vol. 4 DBR Station, Cl. 2.2.4, Pg. 8 Crack width check please mention value of Cmin and clear cover Stipulations of Tender document shall prevail.

6 Vol. 4 Additional DBR Cl. 2.2, Pg. 2 A. General: Please mention the year of Publication. Stipulations of Tender document shall prevail.                                        


IRC code: 22 shall be referred for steel‐RCC composite structure. All Codes shall be of latest Revisions

7 Vol. 4 Additional DBR Cl. 2.14, Pg. 4 Station Transfer Pier arm: Please specify the distance between pier face and joint. The same shall be proposed by the contractor based on Structural 


Construction joints may be required in Station Transverse pier  arrangement for approval of Engineer.
arm (both concourse  & Platform) as per requirement of 
construction. Such joints shall be cast between precast members 
or in‐situ with reinforcement continuity between cast‐in‐situ 
members & precast members. These joints shall be proposed 
away from maximum Bending Moment & Shear Force locations.

8 Vol. 3 Employers requirement Cl. 2.0, Pg.  General: Please clarify that it is not mandatory for successful bidder to  Stipulations of Tender document shall prevail.


13 The earlier Contractor had engaged the Detail Design  deploy earlier DDC.
Consultant, who have done substantial work on this Package. 
Hence, the successful bidder is advised to deploy the same firm 
preferably as DDC to avoid re‐work.

Page 1 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

9 Vol. 3 Employers requirement Cl. 2.1.1.9,  There is an Iconic Bridge being constructed by MMRDA across  Please specify the loads from these bridges. Stipulations of Tender document shall prevail.


Pg. 15 Mithi River through separate Contract as shown in GAD. The  Design and construction of girders, pedestals and bearings for 
same is excluded in this tender. The Pedestal, Bearings and  adjacent spans before the start and after the end of Iconic bridge is 
girder for Superstructure resting on the first/last pier of Iconic  in the scope of this tender.   The Contractor of Package C102 shall 
Bridge is in the Scope of this tender. provide loadings from these adjacent spans  to the Contractor of 
Iconic Bridge.

10 Vol. 5 Part 2 of 4, Structural Drawings,  Station U‐Girder span ‐ 18.5m Lengths Stations are with spans 16.5 and 17. Please provide drawings for  Stipulations of Tender Document shall prevail.


part 3, 11123 these spans.

11 Vol. 5 Part 2 of 4, Architectural Drawings,  Cross section shows Single U‐girder for both tracks. Please provide U‐girder drawings. Stipulations of Tender document shall prevail.                               The 


part 1, MM2B‐PRD‐SGB‐ARC‐CRS‐ U‐girder drawings of Stations to be followed. Please refer drawing 
01438 No. Vol‐5, Part‐2 of 4. 

12 Vol. 5 Part 2 of 4, Architectural Drawings,  Architectural drawings Width of the station is not clear. Please provide more elaborative  Stipulations of Tender document shall prevail.                            


part 1, MM2B‐PRD‐SGB‐ARC‐CRS‐ drawings. Please refer tender drawing Vol. 5, Part1 of 4, No. MM2B‐PRD‐SGB‐
01438 ARC‐PLN‐01410

13 Vol. 1 NIT, Cl. 1.1.2, Pg. 1 Key Details: We request you to kindly consider completion period of 36 months  Stipulations of Tender Document shall prevail.


Completion period instead of 30 months.

14 Vol. 1 10 Material Advance/ Secured Advance We request you to kindly arrange to pay 90% of the invoice value  Stipulations of Tender Document shall prevail.


of material advance/ secured advance (For cement, reinforcement 
steel, HT strand and Structural Steel)

15 Vol. 2 GCC, Cl. 11.2.1, Pg. 45 Mobilisation Advance: We request you to kindly pay interest free mobilization advance  Stipulations of Tender Document shall prevail.


Mobilisation Advance shall be generally 5% of original contract  @10% of the Contract price.
value payable in two equal instalments or as mentioned in the 
Special Conditions of Contract. The first instalment shall be paid 
after mobilisation has started and next instalment shall be paid 
after satisfactory utilization of earlier instalment.

Page 2 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

16 Vol. 2 GCC, Cl. 8.5, Pg. 38 Liquidated damages for delay: We request you to kindly reduce the maximum limit of the  Stipulations of Tender Document shall prevail.


The aforesaid liquidated damages do not, however, include the  liquidated damages upto 5%.
sums payable by the Employer to Designated Contractors on 
account of delay caused by the Contractor to Designated 
Contractors which sums shall be recoverable from the 
Contractor in addition to any liquidated damages payable under 
this clause, the total ceiling limit of which is 15% of the contract 
value including liquidated damages levied under the provision of 
Appendix 1 to the Form of Tender.

17 Vol. 2 SCC, 21 sub‐Clause 11.1.3, Pg. 10 Escalation / Price Variation Tender stipulates that the escalation is payable based on the  Stipulations of Tender Document shall prevail.


indices. And we are aware that the indices do not scatter fully to 
the increase in the prices. Therefore we hereby request you to 
kindly provide the basic rates for major construction material and 
pay us the escalation based on the difference between base rate 
and actual purchase prices.

18 Vol. 1 Volume 1‐ Instruction To Tender  Eligible Tenderer : This is an open competitive‐tender and all  As the Original Clause says this is an open competitive e‐tender,  Stipulations of Tender Document shall prevail.


(lTT) companies corporations, partnership firms , who are involved in  Hence we are requesting you to allow the Joint Venture Firms or 
‐A3  execution of this type of work and those who fulfil the financial  Consortium for this tender.
soundness and work experience criteria and other requirements 
laid down in this document are eligible to participate. No joint 
venture (JV) or Consortium shall be allowed.

Page 3 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

19 Vol. 1 Volume t‐ Notice Inviting Tender  Work Experience: The tenderers will be qualified only if they  And we also request you to accept  the  Work Experience of Lead  Stipulations of Tender Document shall prevail.


(NIT) have completed work(s) during last seven years ending on last  Member in case of JV, who
l.1.3 Qualification Criteria day of month previous to the last date of submission of Tender,  can solely fulfill the Work Experience criteria as mentioned in 
1.1 .3.2 Minimum Eligibilty Criteria as given below: original clause 1.1.3.2.A
A.
(i)Atleast one "similar work" of Value INR 379.62 Crore or 
more.
OR
(ii)Atleast two "similar works" each of Value INR 237.26 Crore 
or more.
OR
iii) Atleast three "similar works" each of Value INR 189.81 Crore 
or more.

The "similar work" for this Contract shall be "Construction of 
Metro Viaduct/underground (including Metro Stations)/ Bridge/ 
ROB/ Flyover (including approaches & embankments) with a pre‐
stressed concrete super structure. For works where approach 
0nd embankment are included, the cost of 
Viaduct/Bridge/ROB/Flyover should be at least 70% of above 
value.
and
( II} The tenderer shall have completed Civil Works for atleast 02 
Metro Stations (elevated/ underground) during last seven years 
ending on last day of previous month of the last date of 
submission of tender.submission of Tender.

20 Vol. 1 NIT Clause 1.1.11 (Pg.No ‐ 11) EMD Payment as mentioned above has to be made through  Submission of EMD has to be made before 5 days of Bid Submission  Stipulations of Tender document shall prevail. 


RTGS / NEFT mode using the System Generated Challan. Bidders  end date. Is it applicable for part amount 1 lakh (or) the whole  It is applicable to part amount of Rs. 1 lakh of the total EMD 
should ensure that the payment of the EMD is made at‐least 5  Amount of EMD. amount.                                                                                        
working days prior to the last date of Bid Preparation and 
Submission of the
Tender Schedule to have seamless submission.

21 Vol. 1 ITT Clause C7.1 & 7.2 (pg.No ‐ 10) 7.1 The Tenderer should note the requirements of warranties  Please provide us with the details of the Previous consultant for  The earlier contractor had appointed M/s Spectrum Techno 


and obligations contained in Clause Detailed Design Consultants as DDC for Viaduct  and M/s AECOM as DDC for Station 
5.2 of GCC. design.
7.2 The design of the Permanent as well as temporary Works as 
per the …..................

Page 4 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

22 Vol. 1 ITT Clause C12.3 (Pg.No ‐11) The key staff for execution of this work shall be having minimum  Why there is a mention about BG while the talks are about the  Please refer  Addendum N0.1


years of total experience as staffs. Please Clarify
mentioned in Annexure‐4 of ITT

23 Vol. 1 ITT Clause C18.1a (Page 12) If the part EMD amount of 1 lakh is on DD. When and where it has  Stipulations of Tender document shall prevail.                                The 


to be  submitted. Can we  upload the Copy of DD 5 days prior and  EMD shall be payable as stipulated in Clause 4 of ITT, Vol.1 of 
send the Original before the end date ? Tender document.                                          

24 Page 28 / Volume‐1/ ITT/  Project Manager ‐ Graduate in Civil Engg Interface Manager ‐  Request to change the clause as follows: Stipulations of Tender Document shall prevail.


Annexure‐4/ Minimum  Graduate in Engineering Planning Manager ‐  Graduate in Civil  Project Manager ‐ Graduate or Diploma in Civil Engg
Organization Structure required Engg. With knowledge in MS Project / Primavera software Interface Manager ‐ Graduate or Diploma in Engineering Planning 
Manager ‐  Graduate or Diploma in Civil Engg. With knowledge in 
MS Project / Primavera software

25 Page 8 of 73 / Volume 2/ Clause  The Contractor will arrange necessary clearances and approvals  We request that Employer to take up and arrange for clearances  Stipulations of Tender Document shall prevail.


1.10, Compliance with Statutes,  before the work is taken up. and approvals. Please confirm.
Regulations and Laws /GCC

26 Page 8 of 73 / Volume 2/ Clause  For any Such delay in handling over of site, Contractors will be  We request to provide Cost Compensation for delay in handing  Stipulations of Tender Document shall prevail.


2.2, Access to and Possession of  entitled to only reasonable extension of time and no monetary  over of site by the Employer.
the Site/GCC claims whatsoever shall be paid or entertained on this account

27 Page 9 of 73 / Volume 2/ Clause  It shall be Contractor's exclusive responsibility to get approval,  We request Employer to take up the responsibility of getting  Stipulations of Tender Document shall prevail.


2.3, Permits, Licenses or  permits or license required for the contract. However, the  approvals, permits or licenses and also we request Cost and Time 
Approvals/ GCC employer may (where he is in a position to do so) provide  Compensation in case of delay caused due to this which is not 
reasonable assistance to Contractor at the request and cost of  attributable to the contractor.
the contractor in getting Permits, License or Approvals required 
during the Contract.

28 Page 9 of 73 / Volume 2/ Clause  The Employer shall be fully entitled without the consent of the  We request to delete this clause. Stipulations of Tender Document shall prevail.


2.4, Assignment by the Employer/  contractor, to assign the benefit of the part thereof and any 
GCC interest therein or thereunder to any third party.

Page 5 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

29 Page 10 of 73 / Volume 2/ Clause  The Contractor acknowledges responsibility for ascertaining and  Please clarify regarding the Design Obligations and location of and  Stipulations of Tender Document shall prevail.


4.1, General Obligations/ GCC securing at his own cost: the authorization required for and the means of diversion of any  In case of any underground services encountered during the 
f) the location of the authorization required for and the means  services and facilities required for the purpose of the works. execution EITHER the utility shall be diverted in consultation with 
of the diversion of any services and facilities required for the  the utility owning agency OR the design shall be modified by the 
purpose of the works. contractor with the approval of Engineer.             

30 Page 13 of 73 / Volume 2/ Clause  Entire Clause. Request to provide time and cost compensation due to reasons not  Stipulations of Tender Document shall prevail.


4.4, Facilities for and coordinations  attributable to the Contractor.
with others/ GCC

31 Page 18 of 73 / Volume 2/ Clause  The Contractor shall bear all cost and charges for special and  We request to provide the Cost and Time Compensation for delay  Stipulations of Tender Document shall prevail.


4.12, Right of Way and Facilities/  temporary rights of way which he may require including those  in giving approval / consent.
GCC for access to the Site. The Contractor shall also obtain, at his risk 
and cost, any additional facility outside the Site which he may 
require for the purpose of the Works.

32 Page 22 of 73 / Volume 2/ Clause  b. for any proper and rea the Contractor may take in absence of  Request to include Cost Compensation Clause. Stipulations of Tender Document shall prevail.


4.23, Unforseeable Physical  specific instructions from the Engineer, as a result of such 
Conditions/ GCC conditions or obstructions being encountered.
The decision of the Engineer  as to the additional cost shall be 
final and binding.

33 Page 23 of 73 / Volume 2/ Clause  Entire Clause. Request to provide suitable Extension of Time and Cost  Stipulations of Tender Document shall prevail.


4.29, Discoveries/ GCC Compensation in case of delay due to any such discoveries at the 
Site.

34 Page 30 of 73 / Volume 2/ Clause  During the Contract Period no extra amount in this regards shall  We request to provide Cost Compensation due to the revision of  Stipulations of Tender Document shall prevail.


6.2, Rates of Wages and  be payable to the contractor, for whatsoever reason including  rates payable in Minimum Wages Act.
Conditions of Labour/ GCC any revisions of rates payable to the labour due to the revisions 
of rates payable in Minimum Wages Act.

35 Page 38 of 73 / Volume 2 / Cl 8.5 /  Entire Clause. We request to release the LD upon achieving the milestone. Stipulations of Tender Document shall prevail.


Liquidated Damages for Delay / 
GCC

Page 6 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

36 Page 45 of 73 / Volume 2 / Cl 8.5 /  Mobilisation Advance shall generally be 5% of the original  Request to release mobilisation advance from 5% to 10% of  Stipulations of Tender Document shall prevail.


Liquidated Damages for Delay /  contract value payable in two equal instalments or as mentioned  Original Contract Value.
GCC in the Special Conditions of Contract.

37 Page 48 of 73 / Volume 2 / Cl 11.6  (a) After preliminary scrutiny and certification by the Engineer,  Requesting Employer to make 80% of certified interim payment  Stipulations of Tender Document shall prevail.


/ Payment‐Interim and FInal / GCC payment of 80% of the certified interim amount shall be made  within 7 days after preliminary scrutiny and certification by the 
by the Employer within 14 Days. Engineer.

38 Page 62 of 73 / Volume 2 / Cl 15.1  Entire Clause. This Contract being part Design Contract the PII shall be taken by  Stipulations of Tender Document shall prevail.                                  


/Professional Indemnity Insurence  Contractor only for the scope of Design that are envisaged under  The clause is self explanatory.
/ GCC this part Design Contract and PII for the Design under the Employer 
scope shall be taken by Employer. Please Confirm.

39 Page 2 of 28 / Volume 2 / Cl 4.9  Any change in Design or Construction Methodology later during  Request to include suitable Time and Cost Compensation if the  Stipulations of Tender Document shall prevail.


/Site Data / SCC the execution on account of change will be born by the  change in design could not be foreseen by an Experienced 
Contractor. Contractor.

40 Page 2 of 28 / Volume 2 / Cl 4.11  If there is any delay or damage or injury, the cost of rectification  The Contractor shall be compensated in both time and cost if the  Stipulations of Tender Document shall prevail.


/Access Route / SCC or reconstruction of highways or bridges shall be born by the  cause of damage is not attributable to the Contractor. Please 
Contractor. The Contractor shall indemnify the Employer in  Confirm.
respect of all claims, demands, proceeding, damages, cost, 
charges and expenses whatsoever arising out of or in relation to 
any such matter.

41 Page 8 of 28 / Volume 2 / Cl 5.3  Entire Clause. Request to provide Cost and Time Compensation for the reasons  Stipulations of Tender Document shall prevail.


/Submission of Documents / SCC bellow:
1. If there are any delay in giving approval / consent by Engineer.
2. If there are any changes after consent/approval is given by the 
Engineer.

42 Page 11 of 28 / Volume 2 / Cl 10.1  The Defect Liability period (DLP) shall be 104 Weeks after the  Kindly reduce the Defect Liability Period (DLP) from 104 weeks to  Stipulations of Tender Document shall prevail.


/Defect Liability Period / SCC date of issue of latest Taking Over Certificate for the whole of  52 weeks.
the works.

43 Vol‐3, (EQR) Felling/Transportation of Trees request to provide present status of environmental clearances for  Please refer Clause 2.1.6 (t) of Employer Requirement Functional.


transplanting/cutting/trimming of trees.

Page 7 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

44 Vol‐3, (EQR), Clause 2.10, Page‐33 Utilities Kindly provide present status of utility diversion (in case of  Interested bidders may contact Mr. Chetan Bendale, EE, MMRDA 


diversion of utility by earlier contractor) along the alignment. for details of utilities diverted by earlier contractor.                              

45 Vol‐3, (EQR), Clause 2.1.10, Page‐ Traffic Management Request to provide time and cost compensation in case of delay in  Stipulations of Tender Document shall prevail.


29 approval of traffic diversion plans.

46 Vol‐3, Employer's Requirement ‐  Please provide the width of ROW for station and viaduct portion  The ROW for construction i.e. permission for barricade erection as 


Construction for metro construction. per construction methodology proposed to be adopted and site 
condition, to be obtained by Contractor from Traffic Police and 
local authority. MMRDA will assist contractor in obtaining the 
permission. General permission for entire alignment from local 
authority and Traffic Police has already been obtained by the 
MMRDA.                                               

47 Vol‐5, Part 3 of 4 C102_GADs AICA/L2B/VIA/PLD/GAD/2020/DW00059 Please clarify whether property (shed) from Ch. 47240 can be  Process for removal of the shed has already been initiated by 


cleared by MMRDA before start of the project. MMRDA. The site at this location would be made available as per 
stipulations of Tender Document (Cl. 2.2, GCC, Vol. 2)

48 Vol‐5, Part 3 of 4 C102_GADs AICA/L2B/VIA/PLD/GAD/2020/DW00059 Please clarify whether property (Hutments and shops along the  Process for removal of the shed has already been initiated by 


alignment) from Ch. 47580 to Ch. 47820 can be cleared by MMRDA  MMRDA. The site at this location would be made available during 
before start of the project. execution phase.

49 Vol‐5, Part 3 of 4 C102_GADs AICA/L2B/VIA/PLD/GAD/2020/DW00060 Request to provide dimensional details of existing flyover at Ch.  The alignment is parallel not crossing to existing flyover, refer GAD  


48+180m to 48+220m crossing bellow proposed viaduct. provided in the Tender Drawings Vol 5 Part 3. For additional details, 
interested bidders may contact Mr. Chetan Bendale, EE, MMRDA 
for obtaining available details of the flyover.

50 Vol‐5, Part 3 of 4 C102_GADs AICA/L2B/VIA/PLD/GAD/2020/DW00061 Kindly specify any restrains due to proposed Bullet Train Corridor at  Please refer Cl.  2.1.1.11 of Employer's Requirements‐ Functional, 


Ch. 48+220m to 48+320m Vol.3 of Tender Document.

51 Vol‐5, Part 3 of 4 C102_GADs AICA/L2B/VIA/PLD/GAD/2020/DW00062 Please confirm that all required railway approvals for construction  Stipulations of Tender Document shall prevail.                              The 


of viaduct span over existing rail track crossing portion will be  design and construction of  Railway crossing including obtaining 
obtained by employer. permissions from concerned Railway authorities is in the scope of 
contract.                        

Page 8 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

52 Vol‐5, Part 3 of 4 C102_GADs AICA/L2B/VIA/PLD/GAD/2020/DW00062 Request to provide span erection sequence and related drawings as  Stipulations of Tender conditions shall prevail. The same to be 


per design at Ch 49+260 to 49+360. developed by the Contractor and seek the approval from Railways 
before execution.

53 Vol‐5, Part 3 of 4 C102_GADs AICA/L2B/VIA/PLD/GAD/2020/DW00062 Request to adopt suitable superstructure type before and after the  Stipulations of Tender Document shall prevail.


ROB span at Ch. 49+260 & 49+360m.

54 Vol‐5, Part 3 of 4 C102_GADs AICA/L2B/VIA/PLD/GAD/2020/DW00065 Request to provide present status regarding approval of property  Process for removal of structures in this stretch has already been 


from Ch. 50+36 to 50+990. Please provide the schedule of land  initiated by MMRDA. The site in this stretch would be made 
hand‐over to contractor in this zone. available during execution phase. Further, please refer reply to 
query No. 46 above.

55 Vol‐5, Part 3 of 4 C102_GADs Please clarify whether permission for traffic block is required over  Stipulations of Tender Document shall prevail.                         The 


Western Expressway. metro alignment not planned on or in the vicinity of Western 
Expressway.                                                             

56 Vol‐5, Part 3 of 4 C102_GADs At majority locations slums were found within the ROW, please  Process for removal of structures/slums in the alignment has 


clarify scope of slum clearance is in employer's scope. already been initiated by MMRDA. The site would be made 
available during execution phase.

57 Vol‐5, Part 3 of 4 C102_GADs Delay in getting traffic blocking and slum clearance will lead delay  Stipulations of Tender Document shall prevail.


in construction, please clarify Employer will provide additional time 
period for construction at this stretch.

58 General Kindly provide the status of the Invoice made by the Employer for  The earlier contract for the metro viaduct and stations work under 


the earlier Contractor. this contract has been terminated and the present tender is invited 
for balance works. 

59 General Construction tools and materials are available along the  Stipulations of Tender Document shall prevail.                                


alignment/ROW. Request to confirm Successful Contractor can use  Only  Row and permanent work done by earlier contractor as 
those tools and material during execution stage at free of cost?  stipulated in the Tender document will be made available to the 
Please clarify. Contractor.

Page 9 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

60 General Construction Plants and Equipment are available along the  Stipulations of Tender Document shall prevail.                              Only 


alignment/ROW. Request to confirm Successful Contractor can use  Row and permanent work done by earlier contractor as stipulated 
those tools and material during execution stage at free of cost?  in the Tender document will be made available to the Contractor.
Please clarify.

61 General In few locations Barrication has been already install along the  Stipulations of Tender Document shall prevail.                 Please refer 


alignment/ROW. Can successful contractor use those Barrication at  Para 2.1.6 (s) of Employer's Requirements‐ functional
free of cost during execution of contract? Please confirm.

62 General Kindly confirm all existing casting yard setup including casting beds,  Please refer Addendum No. 1


substructure and superstructure moulds, gantries site 
establishments/offices will be handed over to the successful bidder 
at free of cost.

63 General Please confirm that Employer shall handover the entire ROW free  Stipulations of Tender Document shall prevail.


of any encumbrance during the start of the project.

64 General Please provide the schedule of land hand‐over to contractor for  Stipulations of Tender Document shall prevail.


entire stretch.

65 General Confirm the flexibility of adopting or changing the type of super  Stipulations of Tender Document shall prevail.             


structure by the contractor

66 General Kindly specify construction joint preparation requirement as  Stipulations of Tender Document shall prevail.


structures are partially completed by earlier contractor.

67 General Kindly confirm design responsibility ownership of earlier completed  Stipulations of Tender Document shall prevail.       


structural work by previous contractor.

Page 10 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

68 General Please specify the maximum tier stacking available for U‐Girder in  Three tier stacking design has been approved by Engineer for 


Casting Yard since its standard design provided by Employer. previous contractor. The contractor shall submit their stacking 
proposal to Engineer for approval.

69 General Please provide proposed traffic diversion plan during construction  Stipulations of Tender Document shall prevail.


of stations, flyover & viaduct at flyover location (if any).

70 1.1.2 Key Details‐ Tender security  INR 4.75 Cr. (1% of work cost) It is requested to make It 0.5% of cost similar to earlier MMRDA  Stipulations of Tender Document shall prevail.


(E.M.O.) works

71 A3 Eligible tenders This is an open competitive e‐tender  and all companies,  For  better competition it is requested to allow the JV, as done  Stipulations of Tender Document shall prevail.


corporations, partnership firms, who are involved in execution of  before.  We are
this type of work and those who fulfil the financial soundness  the working contractor of Metro (JV) & at present executing metro 
and work experience criteria and other requirements laid down  work of BC‐02R of line ‐6 successfully.
in this document are eligible to participate. No joint venture (JV)  OR
or Consortium shall be allowed. Consider the projects of Highway executed by us till date of same 
value.

72 General As the name itself informed that the work is balance work of  Whether the casting yard with gentries, lab. And barricades for  Please refer addendum No. 1


provided  previous contract.                 barricading, shuttering
material etc. which were shown in the photos during bid meeting 
shall be made available to the new awardee, free of cost?
Please confirm.

73 General Please provide status of land acquisition from Kankakla Junction to  Process for removal of structures in this stretch has already been 


Mithi River initiated by MMRDA. The site in this stretch would be made 
available during execution phase.

74 General Please provide details of Mithi river work, if It is inclusive or  Stipulations of Tender Document shall prevail.      Please refer Para 


exclusive In tender cost. If it is iconic structure or include in Viaduct  2.1.1.9 of Employer's Requirement‐ Functional and GAD, Vol. 5 of 
structure. Tender Document. 

Page 11 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

75 General Please provide status of demolition work @ Sable Nagar, MHADA  Process for removal of structures  at Sable Nagar, Nehru Nagar, 


Building near Nehru Nagar Signal, EEH to Nehru Nagar Nallah road  EEH has already been initiated by MMRDA. The site in this stretch 
side shops etc. would be made available during execution phase.

76 General Please provide the details status of NOC for tree  The tree cutting/ transplantation proposals have been submitted to 


cutting/transplantation form site. concerned Authority. The contractor shall follow up with the 
Authority to obtain the permission. Employer will assist the 
contractor in getting the permissions.

77 General Please provide design status of special span, GAD approved by  Stipulations of Tender Document shall prevail.            The design 


Railways. and construction of  special spans is in scope of contractor. Also, 
design and construction of Railway crossing including obtaining 
permissions from concerned Railway authorities is in the scope of 
contractor. The Railway crossing GAD submitted to Railway 
authority would be made available to the successful bidder.

78 General Please provide detailed drawing of Inter connection of EEH Station  Please refer Para 2.1.1.14 of Employer's Requirements‐ Functional. 


and Line‐4. The tentative EEH station drawing showing integration with Line 4 
station has been supplied with tender drawings, Vol. 5 of Tender 
Document.

79 Vol‐6  BoQ Schedule A and Schedule ‐ B Please clarify whether Cost put to tender is inclusive of GST? The cost put to tender is inclusive of GST.

80 Vol‐3 General General The old barricades are not cleaned for long time, which needs  Stipulations of Tender Document shall prevail.      Please refer Para 


vigorous cleaning. Separate payment to be made by the Employer  2.1.6 (s) of Employer's Requirements‐ Functional
for the same.

81 Vol‐3 General General At many locations along viaduct alignment and casting yard, debris  Stipulations of Tender Document shall prevail.       Please refer Para 


are scattered. Please make separate payment for the same after  1.0 of Employer's Requirements‐Functional. The successful bidder 
joint measurements. will be given the work site on as‐is‐where‐is basis and he shall be 
required to carry out further works

Page 12 of 13
RESPONSE TO PREBID QUERIES
CONTRACT NO: MMRDA/MMRP/L2B‐C102
Contract: MMRDA/MMRP/L2B‐C102: Part design and construction of balance works of Package CA‐06, elevated viaduct and 05 elevated stations viz. MTNL, SG Barve Marg, Kurla East, EEH & Chembur [Excluding Architectural Finishing & Pre‐Engineered
Steel Roof Structure of Stations] from chainage 46860.384 m to 52729.312 m of Line 2B [D.N. Nagar to Mandale] of Mumbai Metro Rail Project of MMRDA.

Sr. Reference to Tender Document's 
Volume Provision as per RFP / Clause Bidder's Queries Responses to Queries/Clarifications
No. Clause

82 Vol‐1 ITT General Please allow the Performance BGs to submit for one year and later  Stipulations of Tender Document shall prevail.         


extended. Please refer Clause F 5.1 ( c) of ITT. The Performance Guarantee 
should be valid for a period of 06 (six) months beyond the Defect 
Liability Period

83 Vol‐1 ITT General (Construction Methodolgy) Whether the construction methodology submitted along with the  Stipulations of Tender Document shall prevail.


technical bid shall be considered as approved for execution? The construction methodology submitted by the contractor with 
his technical bid shall not be considered as approved for execution.
The contractor shall have to submit the construction method for 
each item and the same will be approved or asked to modify as per 
tender stipulations and site conditions by the Engineer.

Page 13 of 13