You are on page 1of 4

Providing and fixing crash barriers on Various chainages of 2/L distributary of RBMC of

Name of work:-
PHLC Project.

Schedule B
Item Estimated Rate
Qty. Description of Item Unit
No. In Figure In Words
1 2 3 4 5 6
Excavation for foundation trenches in all sorts
of soil sand clay, hard clay, soft murrum Three
including shoring, strutting and depositing the Hundred
excavated stuff, refilling the remaining Eleven
1 5.85 excavated trenches upto G.L. as and where 311.90 Cu.M
Rupees and
directed within a lead of 50 m. etc. complete as Ninety Paisa
directed. (For Special situation up to 10 cum) only
(a) lift up to 1.5 m
Providing & Laying in position "NOMINAL
MIX" cement concrete using cement, sand and
crushed aggregate by mass and machine mix for
Three
C.C./R.C.C work incl. necessary formworks
Thousand
centering, scaffolding, compaction by vibrator,
Three
2 2.66 curing as directed with all lead & lift etc 3346.00 Cu.M
Hundred
complete Without Dewatering and excluding
Fourty-Six
cost of steel reinforcement.
Rupees only
a) C.C.Nominal Mix, M-10 and MSA-40 mm

Providing & erecting a "W" metal beam crash


barrier comprising of 3mm thick corrugated
sheet meatal beam rail, 70 cm above road/
ground level, fixed onISMC series channel
vertical posts, 150 75 x 5 mm spaced 2m centre Three
to centre, 1.8 m high, 1.1 m below ground/road Thousand
level, all steel parts and fitments to be Two Hundred
3 118.00 galvanised by hot dip process, all fittings to 3321.00 Rmt
Sixty-
conform to IS:1367 and IS:1364, metal beam TwoRupees
rail to be fixed on the vertical post with a spacer only
of channel section 150 x 75 x 5 mm, 330 mm
long complete as per clause 810 (Type - A, "W"
: Metal Beam Crash Barrier)

Total…..
Say…….

Deputy Executive Engineer


Panam High Level Canal Sub Dn. No.3
Godhra
I/We am/are willing to carry out the work at ………………………………………………………....% above/below
(percent should be written in figures and words) of the estimated rates mention above.
Amount of my / our tender worksout as under :
Estimated amount * Estimated amount
put to tenderRs. …………… put to tender
deduct ……% below Rs………………. Add …….%above
Net Rs ……………. Net
In words ……………………………….. In words ………………………………..

(Please strike out whichever is not applicable)

Note 1 : All work shall be carried out as per Public Works Department Handbook and other specifications of
Division or directed.
Note 2 : All the columns in schedule should be filled in ink and the total of the entries in the last coulmn
should be struck by the contractor under his signature.
Note 3 : Rates quoted include clearance of site (prior commencement of work and at its close) in all respects
and hold good for work under all conditions, site, moisture, weather etc.
Note 4 : To be continued on additional sheets, if found necessary.

Executive Engineer
Panam Project Division
Godhra
distributary of RBMC of

Amount
7

1824.62

8900.36

391878.00

402602.98
402603.00

al Sub Dn. No.3


…....% above/below

Rs. …………
Rs. …………
Rs. …………
……………………………..

specifications of

se) in all respects

Executive Engineer
nam Project Division
Godhra

You might also like