You are on page 1of 10

Name of Work: SLOPE PROTECTION WORKS FOR VADAKARA - MAHE CANAL 3RD REACH

Client:

BILL OF QUANTITIES (OPTION-1A)

Sr. No. DSR Ref. No. Description of Item Unit No. Qty Rate Amount Remarks

A. Slope Protection Works

Shotcreting with designed mix cement concrete M25 as per specifications for thickness as specified in the drawing and as directed by Engineer-in‐Charge in
cutting slopes, including all materials, labour, equipments, etc, required for complete job The work includes cost of production & application of shotcrete
1 MR
by using shotcrete machine, designing the concrete mix, removal of rebound, curing and finishing the exposed surface including any other incidental work
as a complete job.

M25 Grade Shotcreting 1.00 6058.00


Total Quantity cum 6058.00 - -

Supply and placing of 150x150x4.0mm welded wire fabric of Fe500 (steel wire fabric conforming to IS: 1566-1957) as reinforcement in roof and side walls of
2 MR tunnel as per approved drawings and specifications and as directed by Engineer‐in‐Charge. The rate shall include all labour, materials, cost of pins, hooks,
lead, lift, handling, wastage complete with contractor’sown equipment for complete job.

Wiremesh 1.00 60576.00


Total Quantity Sqm 60576.00 - -

Supply, drilling hole, installation and grouting of galvanised SN/SDR Type rockbolts as per approved drawings and specifications and as directed by
3 MR
Engineer-in-Charge. The rate shall include costs of all materials, labour, equipments etc.required for the complete job.

L = 4m 1.00 8402.00
Total Quantity Nos. 8402.00 - -

Providing and installing PVC pipes with all accessories of following diameters in the tunnel as per approved drawings and specifications and as directed by
4 MR
Engineer-in-Charge.

75 mm dia Half Perforated PVC pipe for Tunnel main drainage. 1.00 16134.00
Total Quantity Rmt 16134.00 - -
Total for Schedule-A ----------------------- -
B. Pile Wall Works
I Pilie Works

PADMACHANDRA Consulting Engineers Pvt. Ltd. Page 1 of 10


Sr. No. DSR Ref. No. Description of Item Unit No. Qty Rate Amount Remarks

Boring, providing and installation bored cast-in-situ reinforced cement concrete piles of garde M-25 of specified diameter and length below pile cap, to carry
a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and temporary
DSR
1 casing of appropriate length for setting out and removal of same and the length of the pile to be embedded in the pile cap etc. by Crawler mounted,
20.2A.3
telescopic boom hydraulic pilling Rig all complete, including removal of excavated earth with all its lifts and leads (length of pile for payment shall be
measured up to bottom of pile cap).
1000 mm dia piles 2.00 8040.00
Total Quantity Rmt 8040.00 - -
II Concrete Works
Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using
DSR cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and
1
5.33 reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without
impairing strength and durability as per direction of Engineer-in-charge.
Pile Cap 2.00 720.00
Total Quantity Cum 720.00 - -

Providing, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates,
DSR
2 anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but , excluding cost of reinforcement, with 1:1.5:3 (1
5.12
cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).

RCC Lagging 2.00 1296.00


Total Quantity Cum 1296.00 - -
III Shuttering and Centering for Sub-structures and Super-structures

DSR
1 Centering and shuttering including strutting, propping etc. and removal of form for retaining wall:
5.9

Shuttering Qty for Pile Cap 2.00 2160.00


Total Quantity Sqm 2160.00 - -
IV Steel Reinforcement Works

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level with Thermo-
1 DSR 5.22.6
Mechanically Treated bars of grade Fe-500D or more. as directed by Engineer-incharge.

For Pile 2.00 420.00


For Pile Cap 2.00 36.80
For Lagging 2.00 6.80
Total Quantity MT 463.60 - -
Total for Schedule-B ----------------------- -

PADMACHANDRA Consulting Engineers Pvt. Ltd. Page 2 of 10


Sr. No. DSR Ref. No. Description of Item Unit No. Qty Rate Amount Remarks

SUMMARY OF COST
Sr. No. Schedule No. Amount
1 Schedule - A -
2 Schedule - B -
Total Amount -

PADMACHANDRA Consulting Engineers Pvt. Ltd. Page 3 of 10


QUANTITY
CALCULATION
PILING, LAGGING & PILE CAPS QTY

Length of Pile Wall = 600 m


Pile Dia = 1 m
Pile Spacing = 2 m
Length of pile = 13.4 m
RCC Lagging Width = 0.2 m
RCC Lagging Depth = 0.6 m
RCC Lagging Length = 4 m
RCC Lagging Height = 5.4 m
Pile Cap Width = 1 m
Pile Cap Depth = 0.6 m

Length of Pile Total Length of


Sr. No. Description Nos
(m) Piles

1 Piles 300 13.4 4020

Total Length of Piles (@ One Side) Rmt 4020

Length of Total Qty of


Width Depth Area of Lagging
Sr. No. Description Nos Lagging Lagging
(m) (m) (Sqm)
(m) (Cum)
1 Laggings 9 0.2 0.6 0.12 600 648
Total Qty of Lagging (@ One Side) Cum 648

Total Qty of Pile


Width Depth Area of Pile Cap Length of Pile
Sr. No. Description Nos Cap
(m) (m) (Sqm) Cap (m)
(Cum)
1 Pile Caps 1 1 0.6 0.6 600 360

Total Qty of Pile Cap (@ One Side) Cum 360


SHUTTERING QTY FOR PILE CAP

Length of Pile Wall = 600 m


Pile Dia = 1 m
Pile Spacing = 2 m
Length of pile = 13.4 m
RCC Lagging Width = 0.2 m
RCC Lagging Depth = 0.6 m
RCC Lagging Length = 4 m
RCC Lagging Height = 5.4 m
Pile Cap Width = 1 m
Pile Cap Depth = 0.6 m

Sr. No. Descritption Nos. Length Height Total Area

1 Pile Cap Side 2 600 0.90 1080

Total Shuttering Qty in Sqm 1080


REINFORCEMENT QTY FOR PILE
Length of Pile Wall = 600 m
Pile Dia = 1000 mm
Pile Spacing = 2000 mm
Length of pile = 13400 mm
Clear Cover = 75 mm

BAR EBNDING SCHEDULE


Spacing of Cutting
Bar Dia of Bar No. of Bars Total Length in mm
Specification Bar Length Remarks
Mark
(mm) (mm) (Nos.) (mm) 10 mm 12 mm 16 mm 20 mm 25 mm

01 Vertical Bar 20 - 12 15425.00 - - - 185100 -

02 Outer ring Bar 10 150 91 2906.00 264446 - - - -

Total Length in mm 264446 0 0 185100 0

Total Length in m 264.446 0 0 185.1 0

Unit Weight of Bar (Kg/m) 0.617 0.889 1.58 2.469 3.858

Total Weight in Kg 163.16 0 0 457.01 0

Total Weight of Bars in Kg 620.17

Add 2.0% Wastage 2.0% 12.40

Total Weight of Bars in MT for One Pile 0.70

Total Weight of Bars in MT for One side Piles (300 Nos) 210.00
REINFORCEMENT QTY FOR PILE CAP
Length of Pile Wall = 600000 mm
Pile Dia = 1000 mm
Pile Cap Width = 1000 mm
Pile Cap Height = 600 mm
Clear Cover = 75 mm

BAR EBNDING SCHEDULE


Spacing of Cutting
Bar Dia of Bar No. of Bars Total Length in mm
Specification Bar Length Remarks
Mark
(mm) (mm) (Nos.) (mm) 10 mm 12 mm 16 mm 20 mm 25 mm

01 Bottom Layer 16 250 2401 1650.00 - - 3961650 - -

02 Top Layer 16 250 2401 1650.00 - - 3961650 - -

Bottom
03 12 250 5 600450.00 - 3002250 - - -
Longitudinal bar

Top
03 12 250 5 600450.00 - 3002250 - - -
Longitudinal bar

Total Length in mm 0 6,004,500.00 7,923,300.00 0 0

Total Length in m 0 6004.5 7923.3 0 0

Unit Weight of Bar (Kg/m) 0.617 0.889 1.58 2.469 3.858

Total Weight in Kg 0 5338 12518.81 0 0

Total Weight of Bars in Kg 17856.81

Add 2.5% Wastage 2.5% 446.42

Total Weight of Bars in MT for One side 18.40


REINFORCEMENT QTY FOR LAGGING
Length of Pile Wall = 600000 mm
Lagging Width = 200 mm
Lagging Height = 600 mm
Lagging Length = 4000 mm 150 Nos
Clear Cover = 75 mm

BAR EBNDING SCHEDULE


Spacing of Cutting
Bar Dia of Bar No. of Bars Total Length in mm
Specification Bar Length Remarks
Mark
(mm) (mm) (Nos.) (mm) 10 mm 12 mm 16 mm 20 mm 25 mm

01 Longitudinal Bar 12 200 4 577500.00 - 2310000 - - -

02 Vertical Layer 12 200 21 67500.00 - 1417500 - - -

Total Length in mm 0 3727500 0 0 0

Total Length in m 0 3727.5 0 0 0

Unit Weight of Bar (Kg/m) 0.617 0.889 1.58 2.469 3.858

Total Weight in Kg 0 3313.75 0 0 0

Total Weight of Bars in Kg 3313.75

Add 1.5% Wastage 1.5% 49.71

Total Weight of Bars in MT for One side 3.40


ROCKBOLT, SHOTCRETE & WIREMESH QTY

LHS RHS
Slope, H = 3 3
Slope, V = 7 7
Inclined Length = 7.62 7.62
Open Cut Length ,m = 600 600
Slope Height ,m = 28 28
Berm length (Avg) ,m = 4 4
No. of Berms = 5 5
Rock Bolt Spacing ,m = 2 2
Rock Bolt Length ,m = 4 4
Thk. of Shocrete ,m = 0.1 0.1
Drain Pipe Spacing ,m = 2.5 2.5
Length of Drain Pipe ,m = 3 3

Total
No. of Rock Bolts = 4201 4201 8402 Nos.
Area of Wiremesh, Sqm = 30288 30288 60576 Sqm
Wt. of 150x150x6mm kg/Sqm = 2.96 2.96
Total Weight of Wiremesh, kg = 89652 89652 179304 kg
Shotcrete qty = 3029 3029 6058 Cum

No. of Drain Pipe = 2689 2689


Total Length of Drain Pipe = 8067 8067 16134 m