6.1.2 408 Providing Vibrated Cement Concrete (1:3:6) mix using 40 mm 8 Cu.m. 3999.00 8 31992
size HBG crushed stone aggregate (Coarse aggregate conforming
to table 1000-1 and fine aggregate conforming to table 1000-2 of
MoRT&H) including cost, conveyance of all materials to site and
labour charges, centering, machine mixing , laying, vibrating,
curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per MoRT&H
(5th Revision) Specification Section Nos 1500, 1700 & 2100 and
as directed by the Engineer-in-Charge for Levelling Course
6.1.3 1500, Vibrated cement concrete M-15 Grade using 40 mm, 20 mm and 126 Cu.m. 4097.00 126 516222
1700 & 10 mm size HBG crushed stone aggregate (Coarse aggregate
2100 conforming to table 1000-1 and fine aggregate conforming to table
1000-2 of MoRT&H) including cost and conveyance of all materials
to site and all labour charges, mixing using Concrete Batching
Plant, laying in position, compacting, Vibrating and curing including
all other incidental and all other operational charges of T&P
required etc., complete as per MoRT&H (5th Revision) Section Nos
1500, 1700, 2200 for Body Walls of HP Culverts
6.1.4 2900 Providing first class bedding with Granular material below the 20 Cu.m. 791.00 20 15820
pipes of Hume pipe culverts suitably compacted / rammed
including cost and conveyance of materials to site etc., complete
as per drawing and MoRT&H (5th Revision) Specification Section
No. 2900 and as directed by the Engineer-in-Charge .
6.1.5 710.1.4. Filling in between body walls with Gravel including cost, 295 Cu.m. 791.00 295 233345
of conveyance of all materials to site etc., complete as per Clause
IRC:78 710.1.4 of IRC:78 and as per MoRT&H (5th Revision) Specification
& 2200 Section Nos. 2200 & 2907 and as per Drawing and technical
specifications for finished item of work .
6.1.7 2504 Providing and laying filter material with gravel underneath 5 Cu.m. 1057.00 5 5285
pitching in slopes including cost and conveyance of materials to
site including labour charges etc., complete for finished item of
work as per MoRT&H (5th Revision) Specification Clause No. 2504
6.1.8 2900 and as directed
Providing, layingbyReinforced
the Engineer-in-Charge
cement concrete Hume pipes of 45 RM 8766.00 45 394470
1000 mm diametre NP-4 class for pipe culverts including cost and
conveyance of Pipes etc., complete and labour charges for laying,
jointing of 1000 mm diametre RCC hume pipes in position
including lifting, aligning, lowering and hoisting etc., as per drawing
and as per MoRT&H (5th Revision) Specification Section Nos
2900, 2905 & 2906 and IRC Special Publication No: 13 and as
directed by the Engineer-in-Charge for finished item of work.
Total: 12,34,672