KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

PART -A CIVL WORKS

01-SITE CLEARANCE & EARTH WORK


Clearing and grubbing road land including uprooting rank vegetation,
grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of
stumps of trees cut earlier and disposal of unserviceable materials and
stacking of serviceable material to be used or auctioned, with all leads
200-01 201 Hec 21.70
including removal and disposal of top organic soil not exceeding 150 mm in
thickness -In area of light jungle as per MoRTH specification Clause 201
including conveyance labour charges etc complete as per Drawing &
Technical Specifications

Dismantling of existing structures like culverts, bridges, retaining walls and


other structure comprising of masonry cement concrete, including T&P and
scaffolding wherever necessary, sorting the dismantled material, disposal of
200-02 202 unserviceable material and stacking the serviceable material with all lifts cum 73.00
and leads of cement concrete Grade M-15 & M-20 by mechanical means
including conveyance labour charges etc complete as per Drawing &
Technical Specifications

Dismantling Stone Masonry -Rubble stone masonry in cement mortar,


including T&P and scaffolding wherever necessary, sorting the dismantled
200-03 202 material, disposal of unserviceable material and stacking the serviceable cum 50.00
material with all lifts and lead of 1000 metres including conveyance labour
charges etc complete as per Drawing & Technical Specifications
Removing all type of Hume Pipes and Stacking within a lead of 1000 metres
including Earthwork and Dismantling of Masonry Works.( Above 600 mm
200-04 202 Rm 45.00
to 900 mm dia) including conveyance labour charges etc complete as per
Drawing & Technical Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 3

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Dismantling of flexible pavements and disposal of dismantled materials
with all leads, stacking serviceable and unserviceable materials separately
200-05 202 cum 696.00
including conveyance labour charges etc complete as per Drawing &
Technical Specifications

Dismantling of granular courses and disposal of dismantled materials with


all leads, stacking serviceable and unserviceable materials separately
200-06 202 cum 1453.00
including conveyance labour charges etc complete as per Drawing &
Technical Specifications
Scarifying the existing bituminous road surface to a depth of 50 mm and

500-01 501 disposal of scarified material with all leads including conveyance labour sqm 10670.00

charges etc complete as per Drawing & Technical Specifications

Loosening of the ground upto a level of 500 mm below the sub-grade level,
watered, graded and compacted in layers to meet requirement of table 300-2
300-01 301 cum 1729.00
for sub-grade construction. including conveyance labour charges etc
complete as per Drawing & Technical Specifications

Creating cofferdam by fixing ISMB250 and inserting steel sheets in between


the ISMB to the bed level. Laying sand filled bags inside the sheet pile.
300-02 305 cum 360.00
including conveyance labour charges etc complete as per Drawing &
Technical Specifications

Earth work in excavation of foundation of structures as per drawing and


technical specification, including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides
300-03 301
and bottom, backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work. including conveyance
labour charges etc complete as per Drawing & Technical Specifications
300-03(a) Ordinary soil cum 21384.40

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 4

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

300-03(b) Hard Rock ( requiring blasting ) cum 2.00

Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in tippers, trimming bottom and side
slopes, in accordance with requirements of lines, grades and cross sections,
300-04 304 cum 6291.80
and transporting to the embankment location with all leads. including
conveyance labour charges etc complete as per Drawing & Technical
Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 5

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

02-SUB BASE,BASE,HARD (NON-BITUMINOUS) SHOULDERS

Construction of embankment with approved material obtained from borrow


pits with all lifts and leads, transportating to site, spreading, grading to
300-05 305 required slope and compacting to meet requirement including cost of cum 1729.00
materials conveyance labour charges etc complete as per Drawing &
Technical Specifications of table 300-2

Construction of sub-grade and earthen shoulders with approved material


obtained from borrow pits with all lifts & leads, transporting to site,
spreading, grading to required slope and compacted to meet requirement
300-06 305 cum 9968.00
including cost of materials conveyance labour charges etc complete as per
Drawing & Technical Specifications of table No. 300-2 as per MoRTH
specification 305

Back filling behind abutment, wing wall and return wall with selected
granular material of approved quality including cost of materials
300-07 304 cum 65.00
conveyance labour charges etc complete as per Drawing & Technical
Specifications

Sand Filling in Foundation Trenches using contractors own sand including


compaction cost of materials conveyance labour charges etc complete
300-08 304 cum 510.00
including cost of materials conveyance labour charges etc complete as per
Drawing & Technical Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 6

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Providing and laying of Filter media with granular materials/stone crushed
aggregates satisfying the requirements laid down in clause 2504.2.2. of
MoRTH specifications to a thickness of not less than 600 mm with smaller
2500-01 2504 size towards the soil and bigger size towards the wall and provided over the cum 96.00
entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition including cost of materials conveyance
labour charges etc complete as per Drawing & Technical Specifications

Providing and laying Filter material underneath stone boulders pitching in


2500-02 2504 slopes complete including cost of materials conveyance labour charges etc cum 13.00
complete as per Drawing & Technical Specifications ( MORTH 15-5-2504 )

Providing and laying stone boulder Pitching on slopes complete including

2500-03 2504 cost of materials conveyance labour charges etc complete as per Drawing & cum 26.00

Technical Specifications ( MORTH 15-4-2504 )

Flexible Apron :Construction of flexible apron 1 m thick comprising of loose


stone boulders weighing not less than 40 kg beyond curtain wall.including
2500-04 2507 cum 153.00
cost of materials conveyance labour charges etc complete as per Drawing &
Technical Specifications

Floor apron 150 mm thick stone flooring for protection works in box culverts
embedded in cement concrete M15 grade (Cost of concrete excluded)
2500-05 2505 cum 19.00
including cost of materials conveyance labour charges etc complete as per
Drawing & Technical Specifications

Dry Rubble masonry construction of dry rubble packing for cross drainage
2500-06 2506 works including cost of materials conveyance labour charges etc complete cum 392.00
as per Drawing & Technical Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 7

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

Construction of granular sub-base by providing close graded material,


spreading in uniform layers with motor grader on prepared surface, mixing
by mix in place method with rotavator at OMC, and compacting with
400-01 401 cum 1888.00
vibratory roller to achieve the desired density, including cost of materials
conveyance labour charges etc complete as per Drawing & Technical
Specifications complete as per clause 401

Providing, laying, spreading and compacting graded stone aggregate to wet


mix macadam specification including premixing the Material with water at
OMC in mechanical mix plant carriage of mixed Material by tipper to site,
400-02 406 laying in uniform layers with paver in sub- base / base course on well cum 3517.00
prepared surface and compacting with vibratory roller to achieve the
desired density. including cost of materials conveyance labour charges etc
complete as per Drawing & Technical Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 8

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

03-CORRECTION OF DEFECTS & CLEANING/REPAIR WORKS


Removal & cleaning of silt deposit, including grubbing of grass,
vegetations etc for the side drain, cleaning area at the inlet, outlet and
inside the barrel of the CD work and conveying the silt deposit and dirty
materials and biological waste away from the site and deposit available
3006 departmental land etc. including all labour charges 5 km conveyance
300-09
&312 charges ,removing the existing covering slab carefully stacking and
replacing over the side drain after clearing the drainetc. complete as per
direction of departmental officers at site..as per technical specifications
clause 3006 & 312 and as directed by the engineer including conveyance
labour charges etc complete as per Drawing & Technical Specifications

300-09(a) For drains having no covering slabs RM 39922.00

300-09(b) For drains having covering slabs 10 to 12 cm thick slab RM 46774.00

300-09(c) For drains having covering slabs 15 to 18 cm thick slab RM 2704.00

300-09(d) For culverts RM 2790.32

Providing and applying low viscosity bitumen emulsion for sealing cracks
less than 3 mm wide or incipient fretting or disintegration in an existing
500-02 513 bituminous surfacing. Including blinding the fog spray including cost of sqm 3003.00
materials conveyance labour charges etc complete as per Drawing &
Technical Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 9

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Providing and laying slurry seal consisting of a mixture of fine aggregates,
portland cement filler, bituminous emulsion and water on a road surface
including cleaning of surface, mixing of slurry seal in a suitable mobile
500-03 512 sqm 9713.00
plant, laying and compacting to provide even riding surface including cost
of materials conveyance labour charges etc complete as per Drawing &
Technical Specifications

Providing and laying seal coat sealing the voids in a bituminous surface laid
to the specified levels, grade and cross fall using Type A and B seal coats
500-04 511 sqm 572.00
including cost of materials conveyance labour charges etc complete as per
Drawing & Technical Specifications

Removal of all failed material, trimming of completed excavation to provide


firm vertical faces, cleaning of surface, painting of tack coat on the sides and
base of excavation as per clause 503, back filling the pot holes with hot
3000-01 3004 bituminous material as per clause 504, compacting, trimming and finishing sqm 173.00
the surface to form a smooth continuous surface,including cost of materials
conveyance labour charges etc complete as per Drawing & Technical
Specifications all as per clause 3004.2

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 10

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

04-BASE&SURFACE COURSES(BITUMINOUS)
Providing and applying primer coat with bitumen emulsion on prepared
surface of granular Base including clearing of road surface and spraying
500-05 502 primer at the rate of 0.60 kg/sqm using mechanical means.including cost of sqm 12619.00
materials conveyance labour charges etc complete as per Drawing &
Technical Specifications

Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
500-06 503 bituminous/granular surface cleaned with mechanical broom including sqm 859375.00
cost of materials, conveyance labour charges etc complete as per Drawing &
Technical Specifications
Providing and laying dense graded bituminous macadam with 100-120 TPH
batch type HMP producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder
@ 4.0 to 4.5 per cent by weight of total mix and filler, transporting the hot
mix to work site, laying with a hydrostatic paver finisher with sensor control
500-07 505 cum 9524.00
to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per
MoRTH specification clause No. 507 complete in all respects.including cost
of materials conveyance labour charges etc complete as per Drawing &
Technical Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 11

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Providing and laying bituminous concrete with 100-120 TPH batch type hot
mix plant producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 5.4 to
5.6 per cent of mix and filler, transporting the hot mix to work site, laying
500-08 507 with a hydrostatic paver finisher with sensor control to the required grade, cum 39396.00
level and alignment, rolling with smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as per MORTH specification clause
No. 509 complete in all respects including cost of materials conveyance
labour charges etc complete as per Drawing & Technical Specifications

Pointing with cement mortar (1:3 ) on rubble work in substructure including


1400-01 1406 cost of materials conveyance labour charges etc complete as per Drawing & sqm 800.00
Technical Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 12

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

05- MASONRY & CONCRETE WORKS


Random Rubble Masonry in CM 1:6 for side protection wall including all
cost of earth work, pointing , including all cost and conveyance of materials
1400-02 1400 cum 72.00
labour charges etc complete as per Drawing and Technical
Specifications.(MORTH 12.7.1405-3B)
72.00
Reinforced Cement Concrete (RCC Grade M15 ) in Open Foundation
2100-01 2100 complete including cost of materials conveyance labour charges etc cum 72.00
complete as per Drawing and Technical Specifications.
72.00
RCC M 20 for side wall of drain with and 20 mm and 10 mm nominal size
309, crushed stone aggregates mechanically mixed placed in forms and
1500,
1700-01 compacted by vibrator including including cost of materials conveyance cum 72.00
1700,
1900 labour charges etc complete curing for 14 days etc. complete excluding
reinforcement as per Drawing and Technical Specifications
72.00
Reinforced Cement Concrete M 25 in super structure etc including centering
1500,
1700, and shuttering all complete excluding reinforcement but including cost of
1700-02 cum 72.00
1900, materials conveyance labour charges etc completeas as per Drawing and
2300
Technical Specifications. ( MORTH 12-8- E-1500,1700,2100 )
72.00
Reinforced Cement Concrete M 35 in super structure etc including centering
1500, and shuttering all complete excluding reinforcement but including cost of
1700-03 1700, cum 72.00
1900 materials conveyance labour charges etc completeas as per Drawing and
Technical Specifications. ( MORTH 12-8- H-1500,1700,2100 )
72.00
72.00
Plastering with cement mortar (1:3 ) in sub-structure including all cost and
1300-01 1300 conveyance of materials labour charges etc complete as per technical sqm 72.00
specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 13

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
72.00
Supplying, fitting and placing HYSD bar reinforcement including all cost
1600-01 1600 and conveyance of materials labour charges etc complete as per technical MT 72.00
specifications
72.00
Casting and paving Solid concrete interlocking blocks of size 200mm
x150mmx100mm in PCC M45 grade(IS 2185 Part I of 1979) Minimum
strength 45 N/mm2 for external use of best quality over 50mm thick 6 mm
chips (for filling) cussion spread on the ground to line and level including
1700-04 1700 sqm 72.00
compacting the original ground to density and compacting concrete block
with plate vibrators including the other equipment used for compacting the
ground etc complete including all cost of materials, labour charges, etc
complete (PWD 413)
72.00
Replacement of Expansion Joints including Removal of old expansion joint
including breaking of concrete, cutting of lugs and shifting of broken
2600,
2800-01 material ,Epoxy for bonding new concrete to old concrete and M30 concrete RM 72.00
2800
etc complete including all cost and conveyance of materials labour charges
etc complete as per technical specifications
72.00
Providing weep holes in Brick masonry/Plain/Reinforced concrete
abutment, wing wall/ return wall with 100 mm dia pvc pipe, extending
2700-01 2706 through the full width of the structure with slope of 1V :20H towards RM 72.00
drawing foce. including all cost and conveyance of materials labour charges
etc complete as per technical specifications
72.00
Providing and maintaining of hard top passenger car or hard top jeep
8000-01 8000 including cost of driver, fuel charges , repair charges, and all other expenses Months 72.00
as per Technical Specifications Clause .

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 14

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

06- REHABILITATION OF BRIDGES


Under water inspection for piles including hire charges for vedio
transmisson , charges for oxygen cylinder and accessories , charges for
4000-01 4000 Hr 10.00
safety equipments , labour charges and all conveyance etc complete as per
technical specifications

De- watering all around the well structures with required capacity pump
4000-02 4001 including all charges of pump set , labour charges conveyance etc complete Hr 100.00
as per technical specifications.
Cleaning the fouls and chipping out the spalled concrete including hire for
Pneumatic chipping machine,compressor as directed by the Engineer-in-
2800-02 2800 sqm 503.00
charge including all cost and conveyance of materials labour charges etc
complete as per technical specifications

M & L for TMT bars 16mm dia, 8mm dia and 10mm dia over cut to length
bend to shape required including cranking, bending MS (anneald) wire not
1600-02 1600 less than 0.9mm to existing reinforcement in beam all as directed by the MT 2.00
Engineer-in-charge including all cost and conveyance of materials labour
charges etc complete as per technical specifications

Providing and inserting nipples with approved compound after drilling


holes for grouting as per Technical spesifications including subsequent
cutting/removal and sealing of hole of nipples necessary after completion
2800-03 2800 nos 1006.00
of grouting with Cement/Epoxy as directed by the Engineer-in-charge
including all cost and conveyance of materials labour & fixing charges etc
complete as per technical specifications .

Sealing of crack / porous concrete with Epoxy Grout by injection using


Grouting pump not less than a pressure of 40 PSI through nipples etc
2806,
2800-04 complete as directed by the Engineer-in-charge including all cost and kg 503.00
2803
conveyance of materials labour & fixing charges etc complete as per
technical specifications .

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 15

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Supply and erection of steel shutters with appropriate struts, bolts, and
plates to encase the damaged pile surfaces including all cost and
4000-03 4002 sqm 503.00
conveyance of materials labour & fixing charges as directed by the Engineer-
in-charge etc complete as per technical specifications.
Providing under water grade micro concrete: CERA MICRO CONCRETE can be
used for repairing larger section by mixing with 5-12 mm aggregate in the proportion
4000-04 4003 of 50 to 100% by weight of micro concrete as directed by the Engineer-in-charge cum 21.00
including all cost and conveyance of materials labour & fixing charges etc complete
as per technical specifications .

Applying protective coating to the existing structure using CERA


4000-05 4004 INFRAGAURD-S. including all cost and conveyance of materials labour & sqm 2223.00
fixing charges etc complete as per technical specifications.

Providing and laying of a strip seal expansion joint catering to maximum


horizontal movement upto 70 mm, complete as per approved drawings and
2607, standard specifications to be installed by the manufacturer/supplier or their
2800-05 RM 96.00
2800 authorised representative ensuring compliance to the manufacturer's
instructions for installation including all cost and conveyance of materials
labour & fixing charges etc complete as per technical specifications.

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 16

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

07-DAY WORK
Hire charges of lorry/ tipper 5.5 Tonnes capacity for conveyance of the
evicted materials includimg all running and operational charges from spot
5000-01 5001 Hr 200.00
to office including all hire and conveyance charges labour charges etc
complete as per technical specifications

Heavy load mazdoor for loading and unloading materials into the lorry
5000-02 5002 and unloading stacking the same at the stacking yard , including all labour Each 100.00
charges etc complete as per technical specifications
Engaging man mazdoor for assisting heavy load mazdoor and for
5000-03 5003 demolishing and removing temporary and masonry structures. including all Each 100.00
labour charges etc complete as per technical specifications
Engaging carpenters for detaching the lean to roof, dismantling pettikada etc
5000-04 5004 Each 20.00
including all labour charges etc complete as per technical specifications
Engaging Blacksmith for cutting iron materials, unlocking the locked shops
5000-05 5005 Each 25.00
etc. including all labour charges etc complete as per technical specifications
Engaging wood cutter including all labour charges etc complete as per
5000-06 5006 Each 50.00
technical specifications
Engaging Electricians for cutting electric connection and dismantling
5000-07 5007 electric fittings including all labour charges etc complete as per technical Each 20.00
specifications.
Engaging Welder including all labour charges etc complete as per
5000-08 5008 Each 10.00
technical specifications
Engaging Concrete cutting machine including all accessories including all
5000-09 5009 Day 20.00
labour charges etc complete as per technical specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 17

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Engaging metal cutting machine including including all hire and
5000-10 5010 conveyance charges labour charges etc complete as per technical Day 20.00
specifications
Engaging Hydraulic Excavator / JCB of capacity 1 cum bucket for
5000-11 5011 dismantling the concrete structures including all hire and conveyance Day 50.00
charges labour charges etc complete as per technical specifications
Supplying gas cutter with operator including conveying the same from
place to place as directed by departmental officers including all cost of gas
5000-12 5012 (oxyacetylene) labour, hire charges of pickup van etc complete including all Day 50.00
hire and conveyance charges labour charges etc complete as per technical
specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 18

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)

PART -B ROAD SAFETY WORKS

01- ROAD SAFETY


RCC M20 for concrete slabs with and 20 mm and 10 mmnominal size
crushed stone aggregates mechanically mixed placed in forms and
1500,
compacted by vibrator with grip tile type design and colour on top f slab
1700-05 1700, cum 7087.00
including cost of materials conveyance labour charges etc complete curing
1900
for 14 days etc. complete excluding reinforcement. as per Drawing and
Technical Specifications
Road Marking ( lines, dashes, arrows etc on roads) by Providing and laying
of hot applied thermoplastic compound 2.5 mm thick including
reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm on
Bituminous Surface is exclusive of surface applied glass beads as per IRC:35
800-01 803 sqm 81726.00
2015 .The finished surface to be level, uniform and free from streaks and
holes including all cost & conveyance of materials ,all labour charges
charges etc. complete as per Drawing and Technical Specifications.
(MORTH 8.13.803)

Providing Road Studs (raised pavement markers) of moulded poly


carbonate body with twin shanks and retro reflective cornercube
microprismatic lense elements of not less than 10 sq.cm and the type "H"
studs conforming to ASTM D 4280 standard for luminous intensity,
800-02 804 compressive strength and abrasion including fixing on to the pavement Each 56437.00
surface using epoxy specified by the manufacturer, as directed by the
departmental officers including all cost & conveyance of materials ,all
labour & fixing charges etc. complete as per Drawing and Technical
Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 19

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Providing and erecting retro- reflectorised Warning/cautionary signs as
per IRC :67-2012 made of Type XI of ASTM D-4956-09 reflective sheeting ,
mounted over hard and corrosion resistant aluminium sheet , 2mm thick
conforming to IS: 736 and clause 1.2.5 of the approved specification
supported by frames made of mild steel angle iron of designed size and
supported on GI pipe leg 50 mm dia conforming to IS 1239, firmly fixed to
800-03 801
the ground by means of foundation with M 25 grade cement concrete 45 cm
x 45 cm x 60cm, 60 cm below ground level as per approved drawings and
painting with two coats epoxy paint to steel and GI members and red lead
paint to post below ground level including all cost & conveyance of
materials ,all labour & fixing charges charges etc. complete as per Drawing
and Technical Specifications

800-03(a) 801 InformatorySigns - 45 x 60 cm rectangular Each 84.00

800-03(b) 801 Chevron Signs Double sided - 60 x 80 cm Each 4400.00

800-03(c) 801 OHM - 30 x 90 cm size, Each 2304.00

800-03(d) 801 Warning/Regulatory Signs - 90 cm equilateral triangle Each 1317.00


Circular/Octagonal 90 cm
800-03(e) 801 Each 1768.00

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 20

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Providing and erecting direction and place identification retro-reflectorised
sign asas per IRC :67-2012 made of Type XI of ASTM D-4956-09 reflective
sheeting , mounted over hard and corrosion resistant aluminium alloy sheet
, 2mm thick conforming to IS: 736 and clause 1.2.5 of the approved
specification supported by frames made of mild steel angle iron of designed
size and supported on GI pipe leg 50 mm dia conforming to IS 1239 & 35X
800-04 801 35 x 4 mm alround ,firmly fixed to the ground by means of properly Sqm 3.00
designed foundation with M 25 grade cement concrete 45 x 45 x 60 cm, 60
cm below ground level as per approved drawing and painting with two
coats epoxy paint to steel and GI members and red lead paint to post below
ground leve including all cost & conveyance of materials ,all labour &
fixing charges charges etc. complete as per Drawing and Technical
Specifications (lupto 0.9m2 size)
Providing and erecting retro- reflectorised Direction and place identification
signs as per IRC :67-2012 made of Type XI of ASTM D-4956-09 reflective
sheeting , mounted over hard and corrosion resistant aluminium alloy sheet
, 2mm thick conforming to IS: 736 and clause 1.2.5 of the approved
specification supported by frames made of mild steel angle iron of designed
size and supported on post 2 nos with GI pipe leg 75 mm dia conforming
to IS 1239 & 35X 35 x 4 mm alround, firmly fixed to the ground by means of
800-05 801 Sqm 658.00
foundation with M 25grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing and painting with two coats
epoxy paint to steel and GI members and red lead paint to post below
ground level including all cost & conveyance of materials ,all labour &
fixing charges charges etc. complete as per Drawing and Technical
Specifications(Direction and Place Identification Signs with size more than
0.9 sqm size Board - two legged)

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 21

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Providing and erecting a "W" metal beam crash barrier as per IRC 73 2015
comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above
road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5
mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level,
all steel parts and fitments to be galvanised by hot dip process, all fittings to
conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical
800-06 811 post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long Rm 15015.00
complete as per clause 810 ( size of foundation 0.40 m x 0.40 m x 1.1 m
foundation concrete M15grade ,anchoring end to the ground with M25
concrete ,providing reflecting sticker on metal stip perpendicular attached to
metal beam including all cost & conveyance of materials ,all labour &
fixing charges charges etc. complete as per Drawing and Technical
Specifications
Supplying Post Delineators made out of Cold Rolled MS 100x50,14 gauge
tubular section 120 cm in length,top capped with MS plate and provided
with micro prismatic retro reflectors 8x12 cm size on 16 G aluminium
substrate riveted on to the post on both sides using aluminium rivets and the
805,
800-07 post installed in CC M15 of size 30x30x40 cm embedding 30 cm into the each 340.00
806
concrete,bottom anchored with MS base plate,all joints and corners made
smooth and finished with electrostatic powder coating including all cost &
conveyance of materials ,all labour & fixing charges charges etc. complete as
per Drawing and Technical Specifications ,

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 22

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Providing rust free Rigid Post Delineator having wide angle cube corner
micro prismatic non metallic reflective sheeting confirming to Type XI of
ASTM D4956 -09 on both the sides with White Colour on one side and Red
Colour on other side and having minimum of retro reflective exposed area
of 130 Sq cm and with no edges exposed for tampering, tubular delineator
having a core and shell construction, made of tough shell, high impact
resistant, injection-molded, thermoplastic outer body & the inner core of
powder coated mild steel 1mm thick.&post of height not less than 800 mm
above the ground and width not less than 80 mm, the metallic core of the
6000-01 6001 delineator extending 300mm beyond the shell length from bottom for each 100.00
installing in the ground .The engineering thermoplastic used for making the
delineator body shall have minimum initial mechanical properties of 600J/m
tested in accordance with ASTM D256 and shall retain at least 70% of these
minimum initial values when subjected to accelerated weathering for
1000hrs as per ASTM G155 or UL 746C and as per IRC 79 specifications and
including fixing the unit in M15 Grade Cement Concrete of Size 30x30x40 cm
including earth work exacvation for pit. including all cost & conveyance of
materials ,all labour & fixing charges charges etc. complete as per Drawing
and Technical Specifications

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 23

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Hazard Marking on the surface of Trees, Concrete, Mansonry etc using
Aluminum-backed flexible prismatic (‘AFP’) sheeting consisting of Yellow
colored flexible prismatic sheeting non-metallic prismatic lens as retro
reflective elements and conforming to ASTM D 4956-09 Type VI
specification values for reboundable sheeting with printed arrow/slant line
pattern in black colour. AFP sheeting laminated at the back with a 50
micron thick Aluminum (Al) foil with pressure sensitive adhesive and liner
6000-02 6002 each 50.00
and shall not crack when tested for flexibility as per section S2.2.2 of ASTM
D 4956-09 including application on any surface with a neoprene contact
adhesive with Polychloroprene as base and ceiling the edges all around with
epoxy based structural adhesive to resist any peel-off and shall confirm to
IRC Accreditation No. IRC 24(12)/2010 ACC-70 dt 14.07.2010 , including all
cost & conveyance of materials ,all labour & fixing charges charges etc.
complete as per Drawing and Technical Specifications
Providing and fixing hand rails with 50mm GI class B pipe at 1.5m C/c to a
height of 1.25m above footpath and 0.35m below footpath fixed with PCC
M15 grade 20cmx20cmx35cm fixing hooks with 12mm square rod at bottom
of vertical pipe for anchoring in to the concrete 1 No horizontal top and
6000-03 6003 1no. bottom with 50mm class B GI pipe , framing the pipes with welded Rm 21400.00
joint including fixing the hand rails as per lines and levels and plump.
painting two coats with synthetic enamel paint etc including all cost &
conveyance of materials ,all labour & fixing charges charges etc. complete as
per Drawing and Technical Specifications
Plain Cement Concrete M15 Grade for kerb foundation width 215mm
(50mm projection from kerb) and 150mm thick including curing all cost &
1700-06 1700 Rm 21400.00
conveyance of materials ,all labour charges etc. complete as per Drawing
and Technical Specifications (12-8-1500,1700,2100 )

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 24

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Cement Concrete M 20 grade cast in situ kerb with top and bottom width
115 and 165 mm respectively, 250 mm including drain spout starting from
1700, gratings leading pvc pipe upto drain whereever necessary including
1700-07 Rm 211052.00
409 curing all cost & conveyance of materials ,all labour & fixing charges charges
etc. complete as per Drawing and Technical Specifications , all complete as
per clause 409 (12-8-1500,1700,2100 )
Cement Concrete M 20 grade precast kerb with top and bottom width 115
and 165 mm respectively, 100 mm including drain spout starting from
1700, gratings leading pvc pipe upto drain whereever necessary including
1700-08 Rm 42211.00
409 curing all cost & conveyance of materials ,all labour & fixing charges charges
etc. complete as per Drawing and Technical Specifications , all complete as
per clause 409 (12-8-1500,1700,2100 )
Construction of median and Island above road level with approved material
brought from borrow pits, spread, sloped and compacted as per clause 408
400-03 408 including watering all cost & conveyance of materials ,all labour & fixing cum 1000.00
charges charges etc. complete as per drawings and technical specifications.
(MORTH 4.14.407)

Turfing lawns with fine grassing including ploughing, dressing including


breaking of clods, removal of rubbish, dressing and supplying doobs grass
roots at 10 cm apart, including supplying and spreading of farm yard
300-10 307 sqm 2500.00
manure at rate of0.6 cum per 100 sqm including watering all cost &
conveyance of materials ,all labour & fixing charges charges etc. complete as
per drawings and technical specifications. (MORTH 11.5.307)

Maintenance of lawns with fine grassing for the first year including watering
all cost & conveyance of materials ,all labour & fixing charges charges etc.
300-11 307 sqm 2500.00
complete as per drawings and technical specifications. etc (MORTH
11.6.307)

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 25

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Supplying and paving and levelling antifungal designer tiles precast
chequered cement tiles 0.30 X 0.30 m size 22 mm thick medium shade using
50% white cement 50% ordinary cement for external use of best quality over
409,
400-04 cement mortar 1:3 12mm thick with neat pointing with joint filler etc sqm 23610.00
410
complete including all cost & conveyance of materials ,all labour & fixing
charges charges etc. complete as per drawings and technical specifications.
(PWD 413)
Reinforced cement concrete M15 grade kilometre stone of standard design as
804, per IRC:8-1980, fixing in position including painting , printing , all cost &
1700-09 Each 10.00
1700 conveyance of materials ,all labour & fixing charges charges etc. complete as
per drawings and technical specifications.
Printing new letter and figures of any shade with synthetic enamel paint
black or any other approved colour to give an even shade, including all cost
800-08 803 Each 2370.00
& conveyance of materials , all labour charges etc. complete as per technical
specifications.
Providing and applying two coats of ready mix paint of approved brand on
1900-01 1906 steel surface after through cleaning of surface to give an even shade , sqm 1080.00
including all cost & conveyance of materials , all labour charges etc.
complete as per technical specifications.
Painting two coats after filling the surface with synthetic enamel paint in all
800-09 803 shades on new plastered concrete surfaces, including all cost & conveyance sqm 54085.00
of materials , all labour charges etc. complete as per technical specifications.

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 26

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Supplying design, installation and commissioning of 10m height GI
octagonal Mini Mast general purpose flood lighting High power LED
Luminaire with system efficacy greater than 95lm/W with a lumen output
minimum of 10700lm and power consumption maximum of 105W. B50L70
lifetime,Ta= -20 degree to +35 degree at outdoor with IP 65 housing,Class 1.
Optical beam choice : symmetrical, painted non corrosive die cast
Aluminium housing and painted steel bracket.Lens made of PMMA with
7000-01 7001 Each 30.00
5mm thermal harden flat glass.Reflective layer made of MCPET and Gasket
made of heat resistant silicon rubber. Univarsal "U" shaped mounting
bracket. Power requiirement 22040VAC,50/60Hz, Cool white(6500K) color
temperature with CRI 75. Integrated electronic gear.Certifications :
CB/EMC. Dimension 490mmx366mmx74mm with a weight of 10.5kg.
including all cost & conveyance of materials , all labour & fitting charges
etc. complete as per drawings and technical specifications.
Supply, Design,Installation and Commissioning of 78W LED Standalone
Solar Street Light mounted on Octagonal Galvanized Pole 7m height above
7000-02 7002 ground with seprate pole for installing solar panel and battery including all Each 2000.00
cost & conveyance of materials , all labour & fitting charges etc. complete as
per drawings and technical specifications.

Providing Median markers made of Heavy density PVC with Retro-


reflective Delinators (Both side) including all cost & conveyance of materials
7000-03 7003 nos 2080.00
, all labour & fitting charges etc. complete as per drawings and technical
specifications.

Supplying design, installation and providing Bus shelter including all cost
7000-04 7004 & conveyance of materials and all labour & fitting charges charges etc. nos 14.00
complete as per drawings and technical specifications.

Providing traffic signal system at Juntions as per drawings and technical


800-10 812 Each 1
specifications.

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 27

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
Provision of an Reinforced cement concrete crash barrier at the edges of the
road, approaches to bridge structures and medians, constructed with M-20
grade concrete with HYSD reinforcement conforming to IRC:21 and dowel
1500, bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded
1700-10 1700, RM 350
1900 asphalt filler board, keyed to the structure on which it is built and installed
as per design given in the enclosure to MOST circular No. RW/NH -
33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified

02- WORK ZONE


100-01 112 Setting up work zone for drain works as per IRC SP055( fig 10.23) by

providing traffic safety equipments and sign boards including all cost &
nos 126
conveyance of materials, labour chargesetc complete as per technical

specification and drawings of work zone

100-02 112 Setting up work zone for cross drain works as per IRC SP055( fig 10.10) by
providing traffic safety equipments and sign boards including all cost &
nos 24
conveyance of materials, labour chargesetc complete as per technical
specification and drawings of work zone

100-03 112 Setting up work zone for overlay works as per IRC SP 055( fig 10.9) by
providing traffic safety equipments and sign boards including all cost &
nos 536
conveyance of materials, labour chargesetc complete as per technical
specification and drawings of work zone

STP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY AND ROAD SAFETY WORKS FROM KAZHAKOOTAM TO ADOOR
Page 28

KSTP -2 MC ROAD - SAFE CORRIDOR DEMONSTRATION PROJECT - BC- OVERLAY & ROAD SAFETY
WORKS FROM KAZHAKOOTAM TO ADOOR (0/000 to 12/600 (Bye pass) and from 25/000 to 93/000)
ABSTRACT OF COST
Rate (Rs)
Pay Item Estimated
Spec Description of items Unit Amount
No. Quantity Figures Words
(Rs.)
100-04 112 Setting up work zone for road markings and road stud fixing works as per
IRC SP055( fig 7.7) by providing traffic safety equipments and sign boards
nos 804
including all cost & conveyance of materials, labour chargesetc complete as
per technical specification and drawings of work zone

100-05 112 Setting up work zone for foot path as per IRC SP055( fig 6.4) by providing
traffic safety equipments and sign boards including all cost & conveyance of
nos 804
materials, labour chargesetc complete as per technical specification and
drawings of work zone

MISCELLANEOUS ITEMS
Shifting of electric posts and trasformers which is identified as road side
200-07 202 Each 100
hazards from Kazahkootam to Adoor

GRAND TOTAL