EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT

ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01A-C CIVIL WORKS

AIRSIDE EXISTING PQC PANEL REPAIR, REPLACEMENT WORKS, PROPOSED APRON


EXPANSION WORK INCLUDING REMOTE APRON & AIRSIDE SERVICE ROAD / OTHER
CIVIL WORKS

A complete condition survey shall be jointly carried


out prior to execution of works by the Employer,
Engineer and Contractor to the identify the extent
of distress and to finalize procedure, sequence &
methodology of repair / rectification works.
Contractor shall be fully responsible for the safety
and stability of existing works during dismantling
removing, cleaning, reconstruction / repair works.

DISMANTLING
Ref.Spec. No.0200

01A-1C Isolation of Pavement Quality Concrete (PQC)


panels to be demolished from surrounding panels,
its dismantling, cutting of dowels, stacking of
salvaged material (i.e., dowels etc. and its handing
over to Employer) including disposal of demolished
material with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.
Cum 2,295

Unit Rate in words …………………………………..

01A-2C Dismantling / cutting and removal of existing


Cement Treated Base Course including disposal of
demolished material with loading, unloading &
transporting to designated places up to any lead
etc., as directed by the Engineer, complete in all
respect. Cum 850

Unit Rate in words …………………………………..

01A-3C Dismantling and removal of existing granular sub-


base courses including disposal or storage of
demolished materials with loading, unloading &
transporting to an area exclusively designated for
this material up to any lead etc., as directed by the
Engineer, complete in all respect. Cum 1,045

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01A-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01A-4C Isolation of damaged portion of PQC panels from


adjacent concrete and surrounding panels, cutting /
dismantling / chiseling / and removal of loose /
deteriorated / dismantled concrete, cutting of
dowels, stacking of salvaged material (i.e., dowels
etc. and its handing over to Employer) including
disposal of demolished material with loading,
unloading & transportation to designated places up
to any lead etc., as directed by the Engineer,
complete in all respect. Cum 1,180

Unit Rate in words …………………………………..

01A-5C Dismantling and removal of bituminous wearing


and binder course including disposal of demolished
materials with loading, unloading & transportation
to designated places up to any lead etc., as
directed by the Engineer, complete in all respect.
Cum 500

Unit Rate in words …………………………………..

01A-6C Dismantling and removal of existing granular sub-


base / base courses including disposal or storage
of demolished materials with loading, unloading &
transporting to an area exclusively designated for
this material up to any lead etc., as directed by the
Engineer, complete in all respect. Cum 2,970

Unit Rate in words …………………………………..

01A-7C Dismantling and removal of existing footh path,


stacking of re-useable material (incl. pavers, edge
/ kerb stones, etc.) and its handing over to
Employer, disposal of surplus material with
loading, unloading & transportation to designated
places up to any lead etc., as directed by the
Engineer, complete in all respect. Sqm 360

Unit Rate in words …………………………………..

01A-8C Removal of existing marking and symbols with


sandblasting etc complete in all respect as shown
on the drawings Sqm 50

Unit Rate in words …………………………………..

01A-9C Removal and handing over of existing fence at


airside to Employer comprising fence fabric,
barbed / concertina wire, post, bracing beams, etc
complete in all respect as shown on the drawings, Rm 365

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01A-C-2 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

STRIPPING OF TOP SOIL


Ref. Sec.No. 0160

01A-10C Stripping of top soil having thickness of 150mm to


300mm as specified or as directed by the Engineer
Cum 11,155

Unit Rate in words …………………………………..

EARTH WORKS
Ref. Sec.No. 1100

01A-11C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 60,125

Unit Rate in words …………………………………..

01A-12C Common embankment complete in all respect as


shown on the drawings Cum 4,151

Unit Rate in words …………………………………..

01A-13C Select embankment (20% sand blended with


existing soil) including watering, compaction etc;
complete in all respect as shown on the drawing
and specification as per belnding procedure
approved by the Engineer. Cum 12,800

Unit Rate in words …………………………………..

01A-14C Sand filling including watering, compaction etc;


complete in all respect as shown on the drawing
and specification. Cum 200

Unit Rate in words …………………………………..

GRANULAR SUB-BASE COURSE & CRUSHED


AGGREGATE BASE COURSE
Ref. Sec.No. 7410

01A-15C Laying of 200mm compacted crushed aggregate


base course and compaction upto required
maximum dry density as specified or as directed by
the Engineer. Cum 8,730

Unit Rate in words …………………………………..


Expansion of Terminal Building & Allied
Facilities at AIIAP, Lahore 01A-C-3 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01A-16C Laying of 300mm compacted granular sub-base


course including compaction upto required
maximum dry density as specified or as directed by
the Engineer. Cum 4,045

Unit Rate in words …………………………………..

01A-17C Laying of 250mm compacted crushed aggregate


base course including compaction upto required
maximum dry density as specified or as directed by
the Engineer. Cum 3,370

Unit Rate in words …………………………………..

BITUMINOUS SURFACE COURSES


Ref. Sec.No. 7420

01A-18C Providing and laying Bituminous Binder Course of


following compacted thickness including prime coat
etc; complete in all respect as shown on the
drawing or as directed by the Engineer

a) 60 mm thick Cum 650

Unit Rate in words …………………………………..

01A-19C Providing and laying Bituminous Wearing Course


of following compacted thickness including tack
coat etc; complete in all respect as shown on the
drawing or as directed by the Engineer

a) 40 mm thick Cum 435

Unit Rate in words …………………………………..

01A-20C 80mm thick compacted overlay to be laid in two


consecutive layers of 40mm wearing and 40mm
binder course on existing service road including
prime and tack coat, where applicable etc;
complete in all respect as shown on the drawing
and as directed by the Engineer Cum 5,570

Unit Rate in words …………………………………..

PLAIN & REINFORCED CONCRETE


Ref. Sec. 2300, 2100

01A-21C Laying of lean concrete over specified surface


complete in all respect as shown on the drawing or
as directed by the Engineer Cum 8,730

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01A-C-4 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01A-22C Pavement Quality Concrete (PQC) having flexural


strength of 4.5Mpa (650psi) including Dowel
Anchorage, Reinforcement for odd shaped panels,
Bond Braker, Geotextile Fabric conforming to
ASTM M-288 class-1, all type of pavement joints
etc., complete in all respect as specified, shown on
the drawing or as directed by the Engineer
Cum 25,615

Unit Rate in words …………………………………..

01A-23C Sealing of existing major & minor cracks using hot


jet fuel resistant sealant along with debonding tape
for concrete pavements conforming to ASTM
D7116 , including joint formation / routing /
beveling, disposal of debris / demolished materials,
its loading, unloading and transportation to
designated places, up to any lead, etc. complete in
all respect as shown on the drawings and as
specified or as directed by the Engineer.
Rm 1,400

Unit Rate in words …………………………………..

TAXIWAY & APRON PAVEMENT MARKING


Ref. Sec. 7385

01A-24C Airside pavement marking and symbols using


reflective acrylic paint of the following colors, with
glass beads etc; complete in all respect as
specified or as shown in drawing and as directed
by the Engineer.

a) Yellow Sqm 560

Unit Rate in words …………………………………..

b) Red Sqm 525

Unit Rate in words …………………………………..

01A-25C Pavement marking and symbols using reflective


thermoplastic paint of the following colors etc;
complete in all respect as specified or as shown in
drawing and as directed by the Engineer.

a) Yellow Sqm 150

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01A-C-5 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

MISCELLANEOUS ROAD WORK


Ref. Sec. 7190

01A-26C Precast fairfaced edge stone of Class B concrete


(100mmx250mm) including earthwork, cement
sand mortar, fixing with Class D plain cement
concrete etc complete in all respect as shown on
the drawings and as directed by the Engineer Rm 1,355

Unit Rate in words …………………………………..

01A-27C Precast fairfaced curbstone concrete of Class B


concrete (150mmx300mm) including earthwork,
cement sand mortar, fixing with Class D plain
cement concrete etc complete in all respect as
shown on the drawing and as directed by the
Engineer Rm 665

Unit Rate in words …………………………………..

PAVEMENT MARKING
Ref. Sec. 7385

01A-28C Pavement marking and symbols using reflective


thermoplastic paint of the following colors etc;
complete in all respect as specified as shown in
drawings and as directed by the Engineer.

a) Yellow Sqm 595

Unit Rate in words …………………………………..

PRECAST CONCRETE PAVING BLOCK/TILES


Ref. Sec. 7510

01A-29C 60mm thick precast fairfaced pavers including


50mm sand cushion etc. complete in all respect as
shown on the drawings Sqm 225

Unit Rate in words …………………………………..

01A-30C 80mm thick precast fairfaced pavers including


50mm sand cusion etc. complete in all respect as
shown on the drawings Sqm 100

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01A-C-6 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

THRUST BORING
Ref.Sec. 5820

01A-31C Thrust boring below roads for providing 200mm


diameter steel pipes sleeves for pipe crossings
etc. complete in all respect as shown on the
drawings: Rm 75

Unit Rate in words …………………………………..

CAST IRON COVER WITH FRAME & LADDER RUNGS


Ref.Spec. No. 5233, 3100

01A-32C CI / DI manhole cover & frame type B-125 of


following sizes with frame including embedment in
concrete, embedding parts / fixing and fixing
accessories etc. complete in all respect as shown
on the drawing and specification.

a) 600mm x 600mm No 10

Unit Rate in words …………………………………..

b) Dia 600mm No 10

Unit Rate in words …………………………………..

01A-33C CI / DI manhole cover & frame type C-250 of


following sizes with frame including embedment in
concrete, embedding parts / fixing and fixing
accessories etc. complete in all respect as shown
on the drawing and specification.

a) 600mm x 600mm No 10

Unit Rate in words …………………………………..

b) Dia 600mm No 10

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01A-C-7 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01A-34C CI / DI manhole cover & frame type A-15 of


following sizes with frame including embedment in
concrete, embedding parts / fixing and fixing
accessories etc. complete in all respect as shown
on the drawing and specification.

a) 600mm x 600mm No 10

Unit Rate in words …………………………………..

b) Dia 600mm No 10

Unit Rate in words …………………………………..

01A-35C CI / DI gratting & frame type B-125 of following


sizes with frame including embedment in concrete,
embedding parts / fixing and fixing accessories etc.
complete in all respect as shown on the drawing
and specification.

a) 600mm x 600mm No 20

Unit Rate in words …………………………………..

01A-36C Galvanized MS ladder rungs of 20mm dia including


embedding etc; complete in all respect as shown
on the drawings and specifications. No. 220

Unit Rate in words …………………………………..

FENCING
Ref. Sec. No. 0200, 1100, 2100, 2200, 2300, 2450, 3100, 6411

01A-37C Precast fairfaced Class 'B' reinforced concrete line


post & bracing post with reinforcement using
ordinary Portland cement including RCC
foundation, bitumen coating etc. complete in all
respect as shown on the drawings, specifications
and as directed by the Engineer. Cum 25

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01A-C-8 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01A-38C Chain link fence PVC coated including chain link


fabric, tension wire, strecher bar, cleat, RCC line
posts, RCC bracing post etc. comprising
earthwork, plain & RCC concrete, bitumen coating
including fixing and all fixing accessories etc.
complete in all respect and as shown on the
drawings or as specified and as directed by the
Engineer. Rm 370

Unit Rate in words …………………………………..

Total Cost of Code 01A (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01A-C-9 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01B-C CIVIL WORKS

EXTERNAL STORM WATER DRAINAGE

STORM WATER DRAINAGE WORKS AIRSIDE, LAND SIDE AND CULVERT

DISMANTLING
Ref.Spec. No.0200

01B-1C Removing / dismantling of following types of


existing structures at any depth, stacking of
salvage material and its handing over to Employer
and disposal of surplus materials, with loading,
unloading & transportation to designated places up
to any lead etc., as directed by the Engineer,
complete in all respect. Contractor is fully
responsible for the safety and stability of existing
structure during dismantling works.

a) Brick Masonary with plaster Cum 335

Unit Rate in words …………………………………..

b) Plain cement concrete in coping, base slab,


lean concrete etc. Cum 235

Unit Rate in words …………………………………..

01B-2C Dismantling of existing Manholes at any depth,


stacking of salvage material (cover, frame etc.)
and its handing over to Employer and disposal of
surplus materials, with loading, unloading &
transportation to designated places up to any lead
etc., as directed by the Engineer, complete in all
respect. Contractor is fully responsible for the
safety and stability of existing structure during
dismantling works
No 16

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01B-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01B-3C Dismantling & careful removal of existing RCC


Pipe 750mm to 900mm dia at any depth, stacking
of salvage material and its handing over to
Employer and disposal of surplus materials, with
loading, unloading & transportation to designated
places up to any lead etc., as directed by the
Engineer, complete in all respect. Contractor is
fully responsible for the safety and stability of
existing structure during dismantling works and
reinstatement of trench and surrounding area.
Rm 380

Unit Rate in words …………………………………..

EARTH WORKS
Ref. Sec.No. 1100

01B-4C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 3,085

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 673

Unit Rate in words …………………………………..

01B-5C Fill and backfill with selected material obatined


from required excavation in layers including
watering, compaction & etc, complete in all respect
as shown on the drawing and specification.
Cum 1,555

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

01B-6C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and specification. tonne 137

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01B-C-2 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)
Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

01B-7C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer Cum 174

Unit Rate in words …………………………………..

01B-8C Class 'C' plain concrete for pipe encasement


complete in all respect as shown on the drawing or
as directed by the Engineer Cum 240

Unit Rate in words …………………………………..

01B-9C Class 'B' reinforced concrete, using specified


cement in following structural members of
rectangular drain etc., complete in all respect as
shown on the drawing and specification.

a) Bed Cum 475

Unit Rate in words …………………………………..

b) Wall Cum 294

Unit Rate in words …………………………………..

c) Head walls Cum 34

Unit Rate in words …………………………………..

c) Top Slab Cum 122

Unit Rate in words …………………………………..

01B-10C Class 'A' reinforced cement concrete manhole of


size (internal dimension 1250mm dia, depth from
1.0 to 3.0m) including earthwork, stone soling,
PCC / RCC, steel reinforcement, bitumen coating,
ladder rungs, bitumen coating, DI/CI manhole
cover & farme type D-400 with locking
arrangement complete in all respect as specifed
and shown in drawing and approved by the
Engineer. No 11

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01B-C-3 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)
Unit Rate in words …………………………………..

01B-11C Class 'A' reinforced cement concrete inlet


chamber of size 600x600x1000mm including
earthwork, stone soling, PCC / RCC, steel
reinforcement, bitumen coating, ladder rungs,
bitumen coating, DI/CI grating type D-400 with
locking arrangement complete in all respect as
specifed and shown in drawing and approved by
the Engineer. No 22

Unit Rate in words …………………………………..

CONCRETE PIPES & PIPES FITTINGS


Ref. Sec.No. 5311

01B-12C RCC Pipe and fittings of following diameter


conforming to ASTM C76, class-IV, wall B
including rubber O ring / jute caulking etc complete
in all respect as specified or as shown on the
drawings and approved by the Engineer.

a) 900 mm dia R.m 900

Unit Rate in words …………………………………..

b) 225 mm dia R.m 60

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

01B-13C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth. Sqm 2,107

Unit Rate in words …………………………………..

Total Cost of Code 01B (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01B-C-4 August-2022
EXPANSION OF PASSENGER TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)

01C-C CIVIL WORKS

WATER SUPPLY SYSTEM

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

01C-1C Class 'B' reinforced cement concrete Gate Valve


Chambers in "Non trafic area" of specified size
including earthwork, stone soling, PCC / RCC,
steel reinforcement, ladder rungs, bitumen
coating, CI/DI cover type A15 with frame and
locking arrngement etc. complete in all respect as
specfied or as shown on the drawing and
approved by the Engineer. No 9

Unit Rate in words …………………………………..

01C-2C Class 'B' reinforced cement concrete Air Release


Valve Chambers in "Non trafic area" of specified
size including earthwork, PCC / RCC, steel
reinforcement, ladder rungs, bitumen coating,
CI/DI cover type A15 with frame & locking
arrnagement etc. complete in all respect as
specfied or as shown on the drawing and
approved by the Engineer. No 2

Unit Rate in words …………………………………..

01C-3C Class 'B' reinforced cement concrete Washout


Valve Chambers in "Non trafic area" of specified
size including earthwork, PCC/ RCC, steel
reinforcement, ladder rungs, bitumen coating,
CI/DI cover type A15 with frame & locking
arrangement etc. complete in all respect as
specfied or as shown on the drawing and
approved by the Engineer. No 1

Total Cost of Code 01C (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01C-C-1 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)

01D-C CIVIL WORKS

FIRE FIGHTING SYSTEM

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100,2200, 2300

01D-1C Class 'B' reinforced cement concrete Gate Valve


chamber in "Non Trafic area" of specified size
including earthwork, PCC/ RCC, steel
reinforcement, ladder rungs, bitumen coating,
DI/CI cover type A15 with frame & locking
arrangement etc complete in all respect as
specfied or as shown on the drawing and
approved by the Engineer. No 7

Unit Rate in words …………………………………..

01D-2C Class 'A' reinforced cement concrete below


ground Fire Hydrant Chamber in "Air-side Apron
Area" of specified size including earthwork, stone
soling, PCC/ RCC, steel reinforcement bars,
ladder rungs, bitumen coating, DI/CI cover type
F900 with frame & locking arrangement etc.
complete in all respect as specfied or as shown on
the drawing and approved by the Engineer. No 2

Unit Rate in words …………………………………..

01D-3C Class 'B' reinforced cement concrete below


ground Fire Hydrant Chamber of specified size
including earthwork, PCC/ RCC, steel
reinforcement bars, ladder rungs, bitumen coating,
DI/CI cover type A15 with frame & locking
arrangement etc. complete in all respect as
specfied or as shown on the drawing and No 2

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01D-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Item Rate Amount
Description Unit Qty
No. (Rs.) (Rs.)

01D-4C Class 'B' reinforced cement concrete Air Release


Valve Chamber in "Non Traffic area" of specified
size including earthwork, PCC/ RCC, steel
reinforcement, ladder rungs, bitumen coating,
DI/CI cover with frame type A15 & locking
arrangement etc. complete in all respect as
specfied or as shown on the drawing and
approved by the Engineer. No 1

Unit Rate in words …………………………………..

Total Cost of Code 01D (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01D-C-2 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01E-C CIVIL WORKS

SEWERAGE SYSTEM INCLUDING SEWERAGE LIFT STATION LS-01 & LS-02

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

01E-1C Class 'A' reinforced cement concrete manhole at


Airside in "Traffic area" of size (internal dimension
1200mm dia, depth upto 3.5m) including
earthwork, PCC/ RCC, steel reinforcement, ladder
rungs, bitumen coating, CI/DI manhole cover Type
D400 with frame & locking arrangement etc.
complete in all respect as specfied, as shown on
the drawing and approved by the Engineer.
No 10

Unit Rate in words …………………………………..

01E-2C Class 'B' reinforced cement concrete manhole in


"Non Traffic area" of size (internal dimension
1200mm dia, depth upto 3.5m) including
earthwork, PCC/ RCC, steel reinforcement bars,
ladder rungs, bitumen coating, RCC manhole
cover with frame etc. complete in all respect as
specfied, as shown on the drawing and approved
by the Engineer. No 14

Unit Rate in words …………………………………..

01E-3C Class 'B' reinforced cement concrete manhole in


"Non traffic area" of size (internal dimension
1500mm dia, depth upto 4.5m) including
earthwork, PCC/ RCC, steel reinforcement bars,
ladder rungs, bitumen coating, RCC manhole
cover with frame etc. complete in all respect as
specfied, as shown on the drawing and approved
by the Engineer. No 22

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01E-4C Class 'A' reinforced cement concrete manhole in


"Traffic area" of size (internal dimension 1500mm
dia, depth upto 4.5m) including earthwork, stone
soling, PCC/ RCC, steel reinforcement bars,
ladder rungs, bitumen coating, RCC manhole
cover with frame etc. complete in all respect as
specfied or as shown on the drawing and
approved by the Engineer. No 2

Unit Rate in words …………………………………..

01E-4C Class 'B' reinforced cement concrete Gate Valve


Chamber of specified size including earthwork,
PCC/ RCC, steel reinforcement bars, ladder
rungs, bitumen coating, A15 CI/DI cover with
frame & locking arrngement etc. complete in all
respect as specfied, as shown on the drawing and
approved by the Engineer. No 4

Unit Rate in words …………………………………..

01E-5C Class 'B' reinforced cement concrete Washout


Valve Chamber of specified size including
earthwork, PCC/ RCC, steel reinforcement bars,
ladder rungs, bitumen coating, CI/DI cover Type
A15 with frame & locking arrngement etc.
complete in all respect as specfied, as shown on
the drawing and approved by the Engineer.
No 2

Unit Rate in words …………………………………..

01E-6C Class 'B' reinforced cement concrete Release


Valve Chamber of specified size including
earthwork, PCC/ RCC, steel reinforcement bars,
ladder rugs, bitumen coating, CI/DI cover Type
A15 with frame & locking arrngement etc.
complete in all respect as specfied, as shown on
the drawing and approved by the Engineer. No 1

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-2 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

EARTH WORKS
Ref. Sec.No. 1100

01E-7C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 434

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 425

Unit Rate in words …………………………………..

c) From 4 to 6 meter Cum 305

Unit Rate in words …………………………………..

d) From 6 to 8 meter Cum 81

Unit Rate in words …………………………………..

01E-8C Fill and backfill with selected material obatined


from required exavation including watering,
compaction, & etc, complete in all respect as
shown on the drawing and as per specification. Cum 239

Unit Rate in words …………………………………..

TERMITE CONTROL TREATMENT


Ref. Sec.No. 1600

01E-9C Termite Control Treatment complete in all respect


as specified, as shown on drawings and approved
by the Engineer. Sqm 90

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-3 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

REINFORCEMENT
Ref. Sec.No. 2200

01E-10C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and as per specification. tonne 69

Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

01E-11C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer Cu.m 23

Unit Rate in words …………………………………..

01E-12C Class 'D' plain concrete in steps using specified


cement complete in all respect as shown on the
drawing, as per specification and as directed by
the Engineer Cum 4

Unit Rate in words …………………………………..

01E-13C Class 'C' second stage concrete using specified


cement as shown on the drawing or as specified
and as directed by the Engineer Cum 1

Unit Rate in words …………………………………..

01E-14C Class 'B' reinforced concrete, using specified


cement in following sub-structural memebers,
complete in all respect, as shown on the drawing
and as per specification.

a) Raft/Footing/Foundations Cum 84

Unit Rate in words …………………………………..

b) Walls
including water proofing admixture BETOCRETE-
C16 product of Schomburg Germany or approved
equivalent Cum 157

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-4 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

c) Stair Cum 6

Unit Rate in words …………………………………..

d) Pad Cum 3

Unit Rate in words …………………………………..

e) Slab
including water proofing admixture BETOCRETE-
C16 product of Schomburg Germany or approved
equivalent Cum 32

Unit Rate in words …………………………………..

01E-15C Class 'B' reinforced concrete, using specified


cement in following super-structural members etc,
complete in all respect as shown on the drawing
and as per specification.

a) Columns Cum 8

Unit Rate in words …………………………………..

b) Beams & lintels Cum 8

Unit Rate in words …………………………………..

c) Slab & Projection Cum 16

Unit Rate in words …………………………………..

d) Purdi Cum 2

Unit Rate in words …………………………………..

01E-16C Class 'A' reinforced concrete, using specified


cement in following structural members including
water proofing admixture BETOCRETE- C16
product of Schomburg Germany or approved
equivalent etc, complete in all respect as shown
on the drawing and as per specification.

a) Base Cum 14

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-5 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Walls Cum 24

Unit Rate in words …………………………………..

01E-17C Precast fair faced Class 'B' concrete using


specified cement in following structural members,
laid/ fixed in specified cement sand mortar
including fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and as per specification.

a) Sills & Coping


(pigmented) Cum 1

Unit Rate in words …………………………………..

b) Water Spout Cum 1

Unit Rate in words …………………………………..

c) Type-4: Saddle/ Threshold


with metal flashing, 30x30 galvanized steel angle,
steel dowels, weather stripping & water proofing
membrane. Cum 1

Unit Rate in words …………………………………..

MISCELLENEOUS STEEL
Ref. Sec.No. 3100,6700

01E-18C Door Type: 44mm thick MS Tubular frame Metal


Door, fully sand trap louvered with 16 gauge MS
sheet louvers, finish in PU painted with compatible
hardware set (as per schedule) including fixing
and fixing accessories etc of the following design
types, complete in all respect as shown on the
drawing, as per specification and as approved by
the Engineer.

a) Type-SD1 Sqm 5

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-6 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01E-19C Louver fully sand trap MS louver with 16 gauge


MS sheet fixed screen / window, finish in PU
painted with MS louvers frame and compatible
hardware set (as per schedule), including exhaust
fan provision (where required), fixing and fixing
accessories etc of the following design types;
complete in all respect as shown on the drawing,
as per specification and as approved by the
Engineer.

a) Type-L1 Sqm 10

Unit Rate in words …………………………………..

b) Type-L2 Sqm 4

Unit Rate in words …………………………………..

01E-20C Railing: Providing, fabrication and installation of


epoxy painted Floor mounted MS Railing including
embedding, embedding parts, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing and as per specification and as
approved by the Engineer. Rm 26

Unit Rate in words …………………………………..

01E-21C GI Pipe Post with Railing: Providing, fabrication


and installation of GI pipe post with railing
including embedding, embedding parts, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing and as per specification and
as approved by the Engineer. Rm 16

Unit Rate in words …………………………………..

CAST IRON COVER WITH FRAME & LADDER RUNGS


Ref.Spec. No. 5233, 3100

01E-22C CI/DI cover (900mm x 750mm) Class A15 with


frame & locking arrngement including embedding
parts, fixing and fixing accessories complete in all
respect as shown on the drawing and as per
specification. No 2

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-7 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01E-23C CI/DI cover (750mm x 750mm) Class A15 with


frame & locking arrangement including embedding
parts, fixing and fixing accessories complete in all
respect as shown on the drawing and as per
specification. No 2

Unit Rate in words …………………………………..

01E-24C CI/DI cover (600mm x 600mm) Class A15 with


frame & locking arrngement including embedding
parts, fixing and fixing accessories complete in all
respect as shown on the drawing and as per
specification. No 1

Unit Rate in words …………………………………..

01E-25C Galvanized MS ladder rungs 20mm diameter


including embedding etc; complete in all respect
as shown on the drawing and specification. No. 59

Unit Rate in words …………………………………..

BRICK MASONRY WORKS


Ref.Spec. No. 4200

01E-26C Reinforced facing brick masonry outer wall 225mm


thick, set in specified cement mortar including MS
anchor Bars etc; complete in all respect as shown
on the drawing and as per specification. Cum 25

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

01E-27C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth as specified. Sqm 515

Unit Rate in words …………………………………..

01E-28C Water proofing and built-up roofing of the following


types over roof slab etc. complete in all respect as
shown on the drawing and as per specification.

a) Type-II Sqm 78

Unit Rate in words …………………………………..


Expansion of Terminal Building & Allied
Facilities at AIIAP, Lahore 01E-C-8 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

CEMENT PLASTER
Ref. Sec.No. 6521

01E-29C 13mm thick 1:6 cement sand plaster to specified


interior surfaces etc, complete in all respect as
shown on the drawing and as per specification. Sqm 398

Unit Rate in words …………………………………..

01E-30C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove / plain in plaster as
specified etc, complete in all respect as shown on
the drawing and as per specification. Sqm 466

Unit Rate in words …………………………………..

FLOOR AND WALL FINISHES


Ref. Sec.No. 6531, 6600

01E-31C Floor type F01: 80mm thick cement concrete


floor; comprising top surface floor with 1mm thick
epoxy coating over heavy duty smooth cemented
screed floor etc; complete in all respect as shown
on the drawing, as per specification and as
approved by the Engineer. Sqm 94

Unit Rate in words …………………………………..

01E-32C Skirting type SK01: 100mm high epoxy coating


over 13mm thick cemented skirting in approved
size/ panels, color/ shade and texture including
rough base plaster etc. complete in all respect as
shown on the drawing, as per specification and as
approved by the Engineer. Sqm 10

Unit Rate in words …………………………………..

PAINTING
Ref. Sec.No. 6700

01E-33C Plastic emulsion paint to specified interior surfaces


in approved color / shade etc; complete in all
respect as shown on the drawings, as per
specifications and as approved by the Engineer. Sqm 398

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-9 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01E-34C Weather resistant paint to specified exterior


surfaces in approved color / shade etc; complete
in all respect as shown on the drawings, as per
specifications and as approved by the Engineer. Sqm 76

Unit Rate in words …………………………………..

Total Cost of Code 01E (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01E-C-10 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO. 01 : EXTERNAL DEVELOPMENT WORKS


Unit Rate Amount
Foreign Local Foreign
Local Currency Total Amount in
Item Currency Currency Currency
Description Unit Qty. Component equivalent Pak. Rs.
No. Component Component Component
Pak Rs. 7+8 x Exchange Rate
US $ Pak Rs. US $
1 2 3 4 5 6 7 8 9

F. CIVIL WORKS

01F - SEWAGE TREATMENT PLANT


REF. SPEC. NO. 5540

Design, Supply, provision, installation, testing and Job 1


commissioning, of Sewage Treatment Plant (STP)
700,000 gallons per day (about 2,650 cum/day).
Construction of all civil works related to the plant and its
allied ancillary facilities including but not limited to:
connection with manholes, bypass arrangements within
treatment units/plant, treated effluent storage tank and
filtered water storage tank each having capacity of
100,000 gallons, along with pump rooms/stations,
disposal of suplus treated effluent to near by drain,
toilets, boundary wall, blower room, control panel room,
safety railings, staircases, and other infrastructure to
support the facility including road network within the
treatment plant, guidance signs and other facilities as
required (complete in all respect). The scope of work
01F-1C also includes the design, construction, supply,
installation, testing, commissioning of dedicated
11/0.415kV Substation including all electrical equipment
(MV Switchboard, transformer, LV Switchboard). The
scope of work also includes the transportation of all
materials and items (local / imported) of the STP
including equipment / instrument supplies and personnel
to the site and making all the necessary arrangements
Expansion forofsatisfactory completion
Terminal Building & Alliedand performance of the STP
Facilities as
at AIIAP, Lahore
specified and directed by the Engineer. Confirmation 01F-C1 August 2022
of treated wastewater level as mentioned in these
filtered water storage tank each having capacity of
100,000 gallons, along with pump rooms/stations,
disposal of suplus treated effluent to near by drain, BILL OF QUANTITIES
toilets, boundary wall, blower room, control panel room,
CODE NO.safety railings, staircases,
01 : EXTERNAL DEVELOPMENTand other infrastructure to
WORKS
support the facility including road network within the
Unit Rate Amount
treatment plant, guidance signs and other facilities as
required (complete in all respect). The scope of work Foreign Local Foreign
Local Currency Total Amount in
Item
01F-1C also includes the Description
design, construction, supply, Currency Currency Currency
Unit Qty. Component equivalent Pak. Rs.
No. installation, testing, commissioning of dedicated Component Component Component
Pak Rs. 7+8 x Exchange Rate
11/0.415kV Substation including all electrical equipment US $ Pak Rs. US $
1 (MV Switchboard, transformer, 2 LV Switchboard). The 3 4 5 6 7 8 9
scope of work also includes the transportation of all
materials and items (local / imported) of the STP
including equipment / instrument supplies and personnel
to the site and making all the necessary arrangements
for satisfactory completion and performance of the STP
as specified and directed by the Engineer. Confirmation
of treated wastewater level as mentioned in these
specifications and / or as directed by the Engineer shall
be deemed to be included in the scope of works.

a Civil Works Job 1 xxxx xxxx

Unit Rate in Words………...……………………

b MEP Works Job 1 xxxx xxxx

Unit Rate in Words………...……………………

c STP Equipment and Allied Works Job 1

Unit Rate in Words………...……………………

Total Amount of Code 01F (C)


Carried over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01F-C2 August 2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01G-C CIVIL WORKS

BLUE WATER DISPOSAL FACILITY

CONTROL ROOM & TRITURATOR CHAMBER

EARTHWORKS
Ref. Sec.No. 1100

01G-1C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 44

Unit Rate in words …………………………………..

01G-2C Fill and backfill with selected material obtained


from required excavation including watering,
compaction & etc, complete in all respect as
shown on the drawing and specification. Cum 20

Unit Rate in words …………………………………..

STONE SOLING
Ref. Sec.No. 1330

01G-3C 150mm thick crushed stone soling including


blinding material and compaction, complete in all
respect as shown on the drawing and as per
specification. Cum 6

Unit Rate in words …………………………………..

TERMITE CONTROL TREATMENT


Ref.Spec. No.1600

01G-4C Termite Control Treatment complete in all respect


as specified, as shown on drawings and approved
by the Engineer. Sqm 6

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01G-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

REINFORCEMENT
Ref. Sec.No. 2200

01G-5C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield strength
not less than 414 MPa (60,000 Psi) etc complete in
all respect as shown on the drawing and
specification. tonne 5

Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

01G-6C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing and directed by
the Engineer Cum 3

Unit Rate in words …………………………………..

01G-7C Class 'D' plain concrete in situ using specified


cement complete in all respect as shown on the
drawing, as per specification and as directed by
the Engineer Cum 2

Unit Rate in words …………………………………..

01G-8C Class 'D' plain concrete in steps using specified


cement complete in all respect as shown on the
drawing, as per specification and as directed by
the Engineer Cum 1

Unit Rate in words …………………………………..

01G-9C Class 'C' concrete using specified cement in plinth


protection including bitumen seal with rubberized
material etc; complete in all respect as shown on
the drawing and as per specification and as
approved by the Engineer. Cum 1

Unit Rate in words …………………………………..

01G-10C Class 'B' reinforced concrete, using specified


cement in following sub-structural memebers etc,
complete in all respect as shown on the drawing
and specification.

a) Raft/Footing/Foundations Cum 9

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01G-C-2 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Walls Cum 10

Unit Rate in words …………………………………..

c) Columns upto plinth Cum 2

Unit Rate in words …………………………………..

d) Plinth beams Cum 4

Unit Rate in words …………………………………..

01G-11C Class 'B' reinforced concrete, using specified


cement in following super-structural members etc,
complete in all respect as shown on the drawing
and as per specification and as approved by the
Engineer.

a) Columns Cum 1

Unit Rate in words …………………………………..

b) Beams & lintels Cum 2

Unit Rate in words …………………………………..

c) Slab & Projection Cum 3

Unit Rate in words …………………………………..

d) Purdi Cum 1

Unit Rate in words …………………………………..

01G-12C Precast fair faced Class 'B' concrete using


specified cement in following structural memebers,
laid / fixed in specified cement sand mortar
including fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and as per specification and as approved by the
Engineer.

a) Sills & Coping Cum 1

Unit Rate in words …………………………………..

b) Water Spout Cum 1

Unit Rate in words …………………………………..


Expansion of Terminal Building & Allied
Facilities at AIIAP, Lahore 01G-C-3 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

c) Type-1: Saddle/ Threshold


with 9x50mm aluminum strip Cum 1

Unit Rate in words …………………………………..

MISCELLENEOUS STEEL
Ref. Sec.No. 3100,5233,6700

01G-13C Angle Plate: Providing, fabrication and installation


MS angles 100x100x10mm thick welded with PL
10x25 @ 300mm c/c anchors 150mm long,
including embedding, embedding parts, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing and specification.
No 140

Unit Rate in words …………………………………..

01G-14C Grating: Providing, fabrication and installation of


heavy duty galvanized MS grating cover any thick
or diemension including embedding, embedding
parts, fixing and fixing accessories etc; complete
in all respect as shown on the drawing and
specification. Kg 450

Unit Rate in words …………………………………..

01G-15C Galvanized MS ladder rungs 20mm diameter


including embedding etc; complete in all respect as
shown on the drawing and specification. No. 6

Unit Rate in words …………………………………..

01G-16C Door Type: 44mm thick Hollow Metal Door 16


gauge MS sheet on both sides seamless door,
polyurethane paint top coat (internal and external
faces) filled with Rockwool, with compatible
hardware set (as per schedule), including fixing
and fixing accessories etc of the following design
types; complete in all respect as shown on the
drawing and as per specification and as approved
by the Engineer.

a) Type-SD1
including door grill Sqm 2

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01G-C-4 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

BRICK MASONRY
Ref.Spec. No. 4200

01G-17C Reinforced facing brick masonry outer wall 225mm


thick, set in specified cement mortar including MS
anchor Bars etc; complete in all respect as shown
on the drawing and as per specification.
Cum 2

Unit Rate in words …………………………………..

ALUMINIUM WORKS
Ref. Sec.No. 6220, 6250

01G-18C Window Type: 8mm thick tinted tempered glass


window of the following types on powder coated
aluminum frame (Deluxe Type) with compatible
hardware set (as per schedule) including fixing and
fixing accessories etc of the following design types;
complete in all respect as shown on the drawing
and as per specification and as approved by the
Engineer.

a) Type-W1
Tinted tempered glass openable window Sqm 3

Unit Rate in words …………………………………..

b) Type-W2
Tinted tempered glass fixed window Sqm 2

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

01G-19C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth. Sqm 21

Unit Rate in words …………………………………..

01G-20C Crystalline Cementitious water proofing coating


(Aquafin-IC or approved equivalent) on specified
surfaces etc; complete in all respect as shown on
the drawings and as per specification. Sqm 78

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01G-C-5 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01G-21C Water proofing and built-up roofing of the following


types over roof slab complete in all respect as
shown on the drawing and as per specification and
as approved by the Engineer.

a) Type-II Sqm 9

Unit Rate in words …………………………………..

CEMENT PLASTER
Ref. Sec.No. 6521

01G-22C 13mm thick 1:6 cement sand plaster to specified


interior surfaces etc; complete in all respect as
shown on the drawing and specification. Sqm 27

Unit Rate in words …………………………………..

01G-23C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove/ plain in plaster as
specified etc; complete in all respect as shown on
the drawing and specification. Sqm 35

Unit Rate in words …………………………………..

FLOOR AND WALL FINISHES


Ref. Sec.No. 6531, 6600

01G-24C Floor type F01: 80mm thick cement concrete


screed (Full Body) with hardener steel troweled
finish, laid in panels not more than 2400x2400mm,
of specified ratio and separated by glass/ pvc
divider strip etc; complete in all respect as shown
on the drawing and as per specification and as
approved by the Engineer. Sqm 6

Unit Rate in words …………………………………..

01G-25C Skirting type SK01: 150mm high cemented


skirting in approved size/ panels, color/ shade and
texture including rough base plaster etc; complete
in all respect as shown on the drawing and as per
specification and as approved by the Engineer. Sqm 2

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01G-C-6 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01G-26C 100mm thick Class 'D' cement concrete sub-floor


complete in all respect as shown on the drawing
and as per specification and as approved by the
Engineer. Cum 6

Unit Rate in words …………………………………..

PAINTING
Ref. Sec.No. 6700

01G-27C Plastic emulsion paint to specified interior surfaces


in approved color / shade etc; complete in all
respect as shown on the drawings, as per
specifications and as approved by the Engineer. Sqm 28

Unit Rate in words …………………………………..

01G-28C Weather resistant paint to specified exterior


surfaces in approved color / shade etc; complete in
all respect as shown on the drawings, as per
specifications and as approved by the Engineer. Sqm 35

Unit Rate in words …………………………………..

Total Cost of Code 01G (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01G-C-7 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01H-C CIVIL WORKS

HYDRANT REFUELING SYSTEM

EARTH WORKS
Ref. Sec.No. 1100

01H-1C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 583

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 583

Unit Rate in words …………………………………..

c) From 4 to 6 meter Cum 215

Unit Rate in words …………………………………..

01H-2C Fill and backfill with selected material obtained


from required excavation including watering,
compaction etc, complete in all respect as shown
on the drawing and specification. Cum 487

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

01H-3C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and specification. tonne 101

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01H-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

01H-4C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer Cum 30

Unit Rate in words …………………………………..

01H-5C Class 'B' plain concrete using specified cement


complete in all respect as shown on the drawing or
as directed by the Engineer Cum 8

Unit Rate in words …………………………………..

01H-6C Class 'B' reinforced concrete, using specified


cement in following sub-structural members etc,
complete in all respect as shown on the drawing
and specification.

a) Raft/Footing/Foundations Cum 156

Unit Rate in words …………………………………..

b) Walls Cum 209

Unit Rate in words …………………………………..

c) Beam Cum 11

Unit Rate in words …………………………………..

d) Slab Cum 107

Unit Rate in words …………………………………..

01H-7C Class 'B' reinforced concrete, using specified


cement in Pipe Encasement etc, complete in all
respect as shown on the drawing and
specification. Cum 75

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01H-C-2 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

MISCELLENEOUS STEEL
Ref. Sec.No. 3100,6700

01H-8C Ladder: Providing, fabrication and installation of


epoxy painted MS Monkey ladder/ MS stair with
cage, including embedding, embedding parts,
fixing and fixing accessories etc; complete in all
respect as shown on the drawing, as per
specification and as approved by the Engineer. Kg 500

Unit Rate in words …………………………………..

CAST IRON COVER WITH FRAME & LADDER RUNGS


Ref.Spec. No. 5233, 3100

01H-9C CI cover Class 'F' (2000mm x 1000mm) with frame


including embedding, embedding parts/ fixing and
fixing accessories etc. complete in all respect as
shown on the drawing and specification.
No 4

Unit Rate in words …………………………………..

01H-10C CI cover Class 'F' (1000mm x 1000mm) with frame


including embedding, embedding parts/ fixing and
fixing accessories etc. complete in all respect as
shown on the drawing and specification.
No 1

Unit Rate in words …………………………………..

01H-11C CI cover Class 'F' (610mm x 610mm) with frame


including embedding, embedding parts/ fixing and
fixing accessories etc. complete in all respect as
shown on the drawing and specification. No 4

Unit Rate in words …………………………………..

01H-12C Galvanized MS ladder rungs 20mm diameter


including embedding etc; complete in all respect
as shown on the drawing and specification. No. 65

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01H-C-3 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

BRICK MASONRY
Ref.Spec. No. 4200

01H-13C Reinforced brick masonry wall 113mm thick


around fuel pit, set in specified cement mortar
including MS anchor bars etc; complete in all
respect as shown on the drawing and
specification. Cum 30

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

01H-14C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth. Sqm 301

Unit Rate in words …………………………………..

01H-15C 20x20mm Polysulfide sealent with 18swg


aluminum flashing on specified surfaces including
fixing and fixing accessories etc; complete in all
respect as shown on the drawing and
specification.
Rm 55

Unit Rate in words …………………………………..

01H-16C Self adhesive membrane Hy-Grip (P2000-SBS or


equivalent) with Hy-Grip primer (or equivalent)
applied as per manufacturer specification on
specified surfaces including fixing and fixing
accessories etc; complete in all respect as shown
on the drawing and specification. Sqm 365

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01H-C-4 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

CEMENT PLASTER
Ref. Sec.No. 6521

01H-17C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove/ plain in plaster as
specified etc; complete in all respect as shown on
the drawing and specification. Sqm 301

Unit Rate in words …………………………………..

Total Cost of Code 01H (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01H-C-5 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01M-C CIVIL WORKS

CHILLED WATER PIPE TRENCHES

EARTH WORKS
Ref. Sec.No. 1100

01M-1C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 164

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 60

Unit Rate in words …………………………………..

01M-2C Fill and backfill with selected material obtained


from required excavation including watering,
compaction etc, complete in all respect as shown
on the drawing and as per specification. Cum 38

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

01M-3C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and specification. tonne 15

Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

01M-4C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer Cum 10

Unit Rate in words …………………………………..

01M-5C Class 'B' plain concrete using specified cement


complete in all respect as shown on the drawing or
as directed by the Engineer Cum 15

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01M-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01M-6C Class 'B' reinforced concrete, using specified


cement in following structural members of
trenches etc, complete in all respect as shown on
the drawing and specification.

a) Bed/ Base Cum 33

Unit Rate in words …………………………………..

b) Walls Cum 35

Unit Rate in words …………………………………..

c) Top Slab Cum 11

Unit Rate in words …………………………………..

01M-7C Precast fair faced Class 'B' concrete using


specified cement in following structural memebers,
including fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and specification.

a) Planks with 20mm dia MS galvanized lifting


hooks Cum 6

Unit Rate in words …………………………………..

MISCELLENEOUS STEEL
Ref. Sec.No. 3100,6700

01M-8C Angle Plate : Providing, fabrication and


installation angles of size 100x100x10mm thick
MS plate welded with PL 10x25 @ 300mm c/c
anchors 150mm long, including embedding,
embedding parts, fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and as per specification. No 110

Unit Rate in words …………………………………..

BRICK MASONRY WORKS


Ref.Spec. No. 4200

01M-9C 113mm thick reinforced brick masonry wall set in


cement sand mortar including stiffener columns,
beams, steel reinforcement, water repellant
coating, weep holes, S-shape anchors, fillet,
pointing etc complete in all respect as shown on
the drawing & as per specification.
Cum 25

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01M-C-2 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01M-10C 228mm thick reinforced brick masonry wall set in


cement sand mortar including stiffener columns,
beams, steel reinforcement, water barrier etc
complete in all respect as shown on the drawing &
specification. Cum 45

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

01M-11C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth. Sqm 158

Unit Rate in words …………………………………..

CEMENT PLASTER
Ref. Sec.No. 6521

01M-12C 13mm thick 1:6 cement sand plaster to specified


interior surfaces etc; complete in all respect as
shown on the drawing and specification. Sqm 217

Unit Rate in words …………………………………..

01M-13C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove/ plain in plaster as
specified etc; complete in all respect as shown on
the drawing and specification. Sqm 158

Unit Rate in words …………………………………..

BITUMINOUS CONCRETE
Ref. Sec. 7140

01M-14C 60mm thick asphalt binder course over concrete


slab of HVAC Trench complete in all respect as
shown on the drawings and as per specifications Sqm 34

Unit Rate in words …………………………………..

01M-15C 40mm thick asphalt wearing course over HVAC


Trench complete in all respect as shown on the
drawings and as per specifications Sqm 34

Unit Rate in words …………………………………..

Total Cost of Code 01M (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01M-C-3 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01N - LANDSCAPING

DEMOLITION, DISMANTLING, REMOVAL AND


RELOCATION WORKS
Ref.Spec. No.0200

01N-1C Dismantling of following type existing structure at


any depth, stacking of salvaged material and its
handing over to Employer and disposal of surplus
materials, with loading, unloading & transportation
to designated places up to any lead etc., as
directed by the Engineer, complete in all respect.
Contractor is fully responsible for the safety and
stability of existing structure during dismantling
works

a) Brick Masonry Cum 75

Unit Rate in words …………………………………..

b) Plain cement concrete Cum 165

Unit Rate in words …………………………………..

c) Reinforced cement concrete Cum 155

Unit Rate in words …………………………………..

d) Doors of any size No 8

Unit Rate in words …………………………………..

e) Window / Ventilator ofany size No 12

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01N-2C Dismantling of existing Manholes at any depth,


stacking of salvage material (cover, frame etc.)
and its handing over to Employer and disposal of
surplus materials, with loading, unloading &
transportation to designated places up to any lead
etc., as directed by the Engineer, complete in all
respect. Contractor is fully responsible for the
safety and stability of existing structure during
dismantling works No 10

Unit Rate in words …………………………………..

01N-3C Dismantling & careful removal of existing RCC


Pipe at any depth, stacking of salvage material
and its handing over to Employer and disposal of
surplus materials, with loading, unloading &
transportation to designated places up to any lead
etc., as directed by the Engineer, complete in all
respect. Contractor is fully responsible for the
safety and stability of existing structure during
dismantling works and reinstatement of trench and
surrounding area. Rm 135

Unit Rate in words …………………………………..

01N-4C Demolition of existing concrete paving block


stacking of salvage material and its handing over
to Employer and disposal of surplus materials, with
loading, unloading & transportation to designated
places up to any lead etc., as directed by the
Engineer, complete in all respect. Sqm 215

Unit Rate in words …………………………………..

01N-5C Dismantling of existing concrete Kerb stone / Edge


stone, including stacking of salvage material and
its handing over to Employer and disposal of
surplus materials, with loading, unloading &
transportation to designated places up to any lead
etc., as directed by the Engineer, complete in all
respect. Rm 225

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-2 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01N-6C Dismantling and removal of bituminous wearing


and binder course including disposal of
demolished materials with loading, unloading &
transportation to designated places up to any lead
etc., as directed by the Engineer, complete in all
respect. Cum 150

Unit Rate in words …………………………………..

01N-7C Dismantling and removal of existing granular sub-


base / base courses including disposal or storage
of demolished materials with loading, unloading &
transporting to an area exclusively designated for
this material up to any lead etc., as directed by the
Engineer, complete in all respect. Cum 325

Unit Rate in words …………………………………..

01N-8C Dismantling of existing land scape/soft scape


including disposal or storage of demolished
materials with loading, unloading & transporting to
an area exclusively designated for this material up
to any lead etc., as directed by the Engineer,
complete in all respect. Cum 415

Unit Rate in words …………………………………..

01N-9C Dismantling of following existing structures


including stacking of salvage material and its
handing over to Employer and disposal of surplus
materials, with loading, unloading & transportation
to designated places up to any lead etc., as
directed by the Engineer, complete in all respect.

a) Shed Job 1

Unit Rate in words …………………………………..

b) Check posts Job 1

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-3 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

EARTHWORKS
Ref. Sec.No. 1100

01N-10C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 6,370

Unit Rate in words …………………………………..

01N-11C Fill and backfill with selected material including


watering, compaction & etc, complete in all respect
as shown on the drawings and specifications.

a) Obtained from required excavation. Cum 3,505

Unit Rate in words …………………………………..

STONE SOLING
Ref. Sec.No. 1330

01N-12C 300mm thick crushed stone soling including


blinding material and compaction. Cum 2,300

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

01N-13C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and specification. tonne 325

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-4 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

PLAIN & REINFORCED CONCRETE


Ref. Sec. 2100, 2300

01N-14C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer Cum 565

Unit Rate in words …………………………………..

01N-15C Class 'D' plain concrete using specified cement in


following structures complete in all respect as
shown on the drawing or as directed by the
Engineer

a) Steps/ Ramp Cum 655

Unit Rate in words …………………………………..

b) Pad Cum 2

Unit Rate in words …………………………………..

01N-16C Class 'B' reinforced concrete, using specified


cement in following structural members etc,
complete in all respect as shown on the drawing
and specification.

a) Foundations Cum 1,814

Unit Rate in words …………………………………..

b) Column & Water Jet Cum 8

Unit Rate in words …………………………………..

c) Walls Cum 1,010

Unit Rate in words …………………………………..

d) Beam with water channel Cum 21

Unit Rate in words …………………………………..

e) Planks Cum 30

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-5 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

STRUCTURAL STEEL
Ref. Sec.No. 3000,3100

01N-17C Providing, fabrication and installation of PU


painted MS railing including embedding,
embedding parts, fixing and fixing accessories etc;
complete in all respect as shown on the drawing,
as per specification and as approved by the
Engineer.

a) Floor mounted Rm 1,575

Unit Rate in words …………………………………..

01N-18C Providing, fabrication and installation of 25mm


thick wrought iron grill (as describe & shown on
drawing) including embedding, embedding parts,
fixing and fixing accessories etc; complete in all
respect as shown on the drawing, as per
specification and as approved by the Engineer. Sqm 60

Unit Rate in words …………………………………..

01N-19C Providing, fabrication and installation of 25mm


thick wrought iron trellis & 25mm thick metal
strings (as describe & shown on drawing)
including embedding, embedding parts, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing, as per specification and as
approved by the Engineer. No 6

Unit Rate in words …………………………………..

CARPENTARY & JOINERY


Ref.Sec.No. 4600, 6700

01N-20C Bench of specified size comprising WPC, epoxy


painted 40x40mm GI L-shaped frame, 20x8mm GI
frame, 40x40mm GI tubular frame & GI Sapcer
including embedding, embedding parts, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing, as per specification and as
approved by the Engineer. No 12

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-6 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

WATER PROOFING AND BUILT-UP ROOFING


Ref. Sec. 6411

01N-21C Two coats of hot bitumen grade 10/20 applied @


1 Kg./sq.m. per coat to all structural concrete
surfaces in contact with earth. Sqm 10,415

Unit Rate in words …………………………………..

01N-22C Cementitious Flexible Waterproofing Coating over


specified surfaces etc; complete in all respect as
shown on the drawing and specification. Sqm 2,020

Unit Rate in words …………………………………..

01N-23C Geotextile membrane over perforated drain with


backfilling etc; complete in all respect as shown on
the drawing and as per specification. Sqm 240

Unit Rate in words …………………………………..

CEMENT PLASTER
Ref. Sec.No. 6521

01N-24C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove / plain in plaster as
specified etc; complete in all respect as shown on
the drawing and as per specification.
Sqm 1,680

Unit Rate in words …………………………………..

FLOOR AND WALL FINISHES


Ref. Sec.No. 6531, 6600

01N-25C 150x150mm glazed ceramic tile in approved


thickness, color/shade and texture laid in specified
pattern filled with matching grout, set in specified
cement sand mortar including rough base plaster
etc; complete in all respect as shown on the
drawing, as per specification and as approved by
the Engineer. Sqm 2,020

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-7 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01N-26C Texture coating over cc plaster on specified


surfaces etc; complete in all respect as shown on
the drawing, as per specification and as approved
by the Engineer. Sqm 1,680

Unit Rate in words …………………………………..

MARBLE & GRANITE WORKS


Ref. Sec.No. 6531, 6532

01N-27C 50mm thick prepolished granite top / coping / sill


of specified size, color and quality including
bullnozing (where required), c.c base, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing, as per specification and as
approved by the Engineer. Sqm 170

Unit Rate in words …………………………………..

01N-28C 20mm thick Granite tile cladding chemically


polished in approved size, color, shade and
texture, laid in specified pattern filled with matching
grout, set in specified cement sand mortar
including base plaster etc; complete in all respect
as shown on the drawing, as per specification and
as approved by the Engineer.
Sqm 620

Unit Rate in words …………………………………..

01N-29C 12mm thick Marble tile chemically polished in


approved size, color, shade and texture, laid in
specified pattern filled with matching grout, set in
specified cement sand mortar including base
plaster etc; complete in all respect as shown on
the drawing, as per specification and as approved
by the Engineer. Sqm 325

Unit Rate in words …………………………………..

01N-30C Mosaic tile in approved size, color, shade and


texture, pattern etc, laid in specified pattern filled
with matching grout, set in specified cement sand
mortar including base plaster etc; complete in all
respect as shown on the drawing, as per
specification and as approved by the Engineer. Sqm 185

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-8 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

MISCELLANEOUS ROAD WORK


Ref. Sec. 7190

01N-31C Precast fairfaced Class 'B' cement concrete Curb


stone of size 150x300x450mm including
earthwork, plain cement concrete & cement sand
mortar etc complete in all respect as shown on Rm 340
th d i
Unit Rate in words …………………………………..

01N-32C Layoing of 150mm thick aggregate base course


including blinding material & compaction of
existing ground complete in all respect as shown
on the drawing, as per specification and as
approved by the Engineer. Cum 19,165

Unit Rate in words …………………………………..

PRECAST CNCRETE PAVING BLOCK/TILES


Ref. Sec. 7510

01N-33C Precast fairfaced pavers/tiles of following sizes &


color, including 75mm thick Class 'C' concrete &
50mm thick sand cusion etc; complete in all
respect as shown on the drawing & specification.

a) 200x100x50mm thick Paver White color Sqm 3,835

Unit Rate in words …………………………………..

b) 200x100x50mm thick Paver Red color Sqm 15,330

Unit Rate in words …………………………………..

c) 150x300x45mm thick Paver (mover) Sqm 350

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-9 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

LANDSCAPING
Ref.Spec. No.0500

01N-34C Relocation / shifting of existing plants with name


plates from Orchid Garden to a specified place
within airport boundary as directed by the Engineer
including excavation and disposal of surplus with
loading, unloading & transportation to designated
places up to any lead etc., as directed by the
Engineer, safe removal of plants, temporary
storage before re-plantation and removal of old
roots from exiting orchid garden etc. Preparation of
ground / new site for Orchid Garden at specified
location incluidng laying of sweet earth ,dry
fertiizer, organic backfill etc. as per requirements
specfied for proper nurishment of plant.
(Contractor is fully responsible to ensure proper
care during and after the process of shifting and
relocation with regular maintenance as per routine
maintenece program approved by the Engineer)
No 132

Unit Rate in words …………………………………..

01N-35C Relocation / shifting of existing plants to a


specified place within airport boundary as directed
by the Engineer including excavation and disposal
of surplus with loading, unloading & transportation
to designated places up to any lead etc., as
directed by the Engineer, safe removal of plants,
temporary storage before re-plantation and
removal of old roots from exiting plantation area
etc. Preparation of ground / new site at specified
location incluidng laying of sweet earth ,dry
fertiizer, organic backfill etc. as per requirements
specfied for proper nurishment of plant.
(Contractor is fully responsible to ensure proper
care during and after the process of shifting and
relocation with regular maintenance as per routine
maintenece program approved by the Engineer)
No 84

Unit Rate in words …………………………………..

01N-36C Filling with sweet earth for Grassy Area with dry
fertilizer. Cum 4,505

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-10 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01N-37C Filling of organic backfill (60% sand, 20% Organic


manure & 20% silt) as shown on the drawings and
specification. Cum 13,610

Unit Rate in words …………………………………..

01N-38C Providing and planting of Trees as per size and


location as shown on the Drawings or as directed
by the Engineer.

a) Providing & Planting plant "Alistonia Tree" (AL)


of specified plant height & stem size (as describe
and shown on the drawing), planted in bed filled
with sweat earth, watering till proper handing over
as per satisfaction of the Engineer. No 6

Unit Rate in words …………………………………..

b) Providing & Planting plant "Bauhinia Variegata/


Kachnar Tree" (BAU) of specified plant height &
stem size (as describe and shown on the drawing),
planted in bed filled with sweat earth, watering till
proper handing over as per satisfaction of the
Engineer. No 13

Unit Rate in words …………………………………..

c) Providing & Planting plant "Cupressus/ Saroo


Tree" (CU) of specified plant height & stem size
(as describe and shown on the drawing), planted
in bed filled with sweat earth, watering till proper
handing over as per satisfaction of the Engineer. No 13

Unit Rate in words …………………………………..

d) Providing & Planting plant "Jacaranda Tree"


(JA) of specified plant height & stem size (as
describe and shown on the drawing), planted in
bed filled with sweat earth, watering till proper
handing over as per satisfaction of the Engineer. No 4

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-11 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

e) Providing & Planting plant "Mangnolia


Grandiflora/ Champa Tree" (MG) of specified
plant, height & stem size (as describe and shown
on the drawing), planted in bed filled with sweat
earth, watering till proper handing over as per
satisfaction of the Engineer. No 5

Unit Rate in words …………………………………..

f) Providing & Planting plant "Pongamia Glabra/


Sukh Chain" (PG) of specified plant height & stem
size (as describe and shown on the drawing),
planted in bed filled with sweat earth, watering till
proper handing over as per satisfaction of the
Engineer. No 21

Unit Rate in words …………………………………..

g)Providing & Planting plant "Poinciana Regia/


Gul Mohar Tree" (POI) of specified plant, height &
stem size (as describe and shown on the drawing),
planted in bed filled with sweat earth, watering till
proper handing over as per satisfaction of the
Engineer. No 21

Unit Rate in words …………………………………..

h) Providing & Planting plant "Cassia Nodosa/


Pink Cassia" (CN) of specified plant, height & stem
size (as describe and shown on the drawing),
planted in bed filled with sweat earth, watering till
proper handing over as per satisfaction of the No 3

Unit Rate in words …………………………………..

01N-39C Providing and planting of Decorative Shrub as


per size and location as shown on the Drawings or
as directed by the Engineer.

a) Providing & Planting plant "Bougain Villea"


(BV) of specified plant, height & stem size (as
describe and shown on the drawing), planted in
bed filled with sweat earth, watering till proper
handing over as per satisfaction of the Engineer. No 21

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-12 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Providing & Planting plant "Tecoma Stans/


Peela Tecoma" (TS) of specified plant, height &
stem size (as describe and shown on the drawing),
planted in bed filled with sweat earth, watering till
proper handing over as per satisfaction of the
Engineer. No 7

Unit Rate in words …………………………………..

c) Providing & Planting plant "Hamelia Patins/


Surk Bunday" (HP) of specified plant, height &
stem size (as describe and shown on the drawing),
planted in bed filled with sweat earth, watering till
proper handing over as per satisfaction of the No 3

Unit Rate in words …………………………………..

d) Providing & Planting plant "Clerodendrum


(CL) of specified plant, height & stem size (as
describe and shown on the drawing), planted in
bed filled with sweat earth, watering till proper
handing over as per satisfaction of the Engineer. No 21

Unit Rate in words …………………………………..

e) Providing & Planting plant "Jatropha Curcas"


(JC) of specified plant, height & stem size (as
describe and shown on the drawing), planted in
bed filled with sweat earth, watering till proper
handing over as per satisfaction of the Engineer. No 5

Unit Rate in words …………………………………..

f) Providing & Planting plant "Decorative Palm"


(DP) of specified plant, height & stem size (as
describe and shown on the drawing), planted in
bed filled with sweat earth, watering till proper
handing over as per satisfaction of the Engineer. No 20

Unit Rate in words …………………………………..

01N-40C Providing and planting of Herbs/ Flowers as per


size and location as shown on the Drawings or as
directed by the Engineer.

a) Providing & Planting plant "Azalea" (AZ) of


specified plant, height & stem size (as describe
and shown on the drawing), planted in bed filled
with sweat earth, watering till proper handing over
as per satisfaction of the Engineer. No 6,200

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-13 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Providing & Planting plant "Francisia" (FR) of


specified plant, height & stem size (as describe
and shown on the drawing), planted in bed filled
with sweat earth, watering till proper handing over
as per satisfaction of the Engineer. No 4,710

Unit Rate in words …………………………………..

c) Providing & Planting plant "Hibiscus" (HIB) of


specified plant, height & stem size (as describe
and shown on the drawing), planted in bed filled
with sweat earth, watering till proper handing over
as per satisfaction of the Engineer. No 11,235

Unit Rate in words …………………………………..

d) Providing & Planting plant "Hmargold/ Genda"


(MG) of specified plant, height & stem size (as
describe and shown on the drawing), planted in
bed filled with sweat earth, watering till proper
handing over as per satisfaction of the Engineer. No 2,810

Unit Rate in words …………………………………..

e) Providing & Planting plant "Petunia" (PT) of


specified plant, height & stem size (as describe
and shown on the drawing), planted in bed filled
with sweat earth, watering till proper handing over
as per satisfaction of the Engineer. No 2,810

Unit Rate in words …………………………………..

f) Providing & Planting plant "Raat Ke Rani" (RR)


of specified plant, height & stem size (as describe
and shown on the drawing), planted in bed filled
with sweat earth, watering till proper handing over
as per satisfaction of the Engineer. No 2,810

Unit Rate in words …………………………………..

g) Providing & Planting plant "Venca Floweri" (VF)


of specified plant, height & stem size (as describe
and shown on the drawing), planted in bed filled
with sweat earth, watering till proper handing over
as per satisfaction of the Engineer. No 2,810

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-14 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

h) Providing & Planting plant "Sardo tree" (ST) of


specified plant, height & stem size (as describe
and shown on the drawing), planted in bed filled
with sweat earth, watering till proper handing over
as per satisfaction of the Engineer. No 10

Unit Rate in words …………………………………..

01N-41C Providing and planting of Ground Spread as per


size and location mentioned at architectrual,
including rigid support as shown on the Drawings
and as per the instruction of the Engineer. Sqm 100

Unit Rate in words …………………………………..

01N-42C Providing and plugging of Korean Grass (KG) on


appropriate distance as per location mentioned at
architectural drawings and and as per the
instruction of the Engineer. Sqm 7,510

Unit Rate in words …………………………………..

01N-43C Providing and laying of pabbles of specified size &


color in layers around Ground spread planters as
per drawing. Cum 2,365

Unit Rate in words …………………………………..

01N-44C Providing and laying of gravel mulch in layers


around Ground spread planters as per drawing. Cum 4

Unit Rate in words …………………………………..

01N-45C Providing and laying of boulders of specified size


in layers around Ground as per drawing. Cum 11

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-15 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

OPERATION & MAINTENANCE


Ref. Sec. 0501

01N-46C Operation & Maintenance of Landscaping area


incluidng Orchid Garden including moving,
blowing, edging, trimming, pruning, fertilizer /
manure for Plants and Bed including watering
chemical application, weed illumination and
cleaning of Plants bed or Tree wells, edging of all
side walks curbs as shown on the Drawings & as
per Specifications. Month 12

Unit Rate in words …………………………………..

Total Cost of Code 01N (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01N-C-16 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O- ACCESS ROAD WORKS FOR CAR PARK

ACCESS ROAD WORKS, ROAD BLOCKER,


TYRE KILLER, CONTROL ROOM-ASF, ASF SHED & GANTRY

01O-1C Classified Traffic Movement Count (Video


recording method) for 24 continuous hours for 7
consecutive days of the week at 16 locations as
per methodology / program to be provided by the
Engineer and submission of report with
recommendations. Job 1

Unit Rate in words …………………………………..

DISMANTLING
Ref.Spec. No.0200

01O-2C Dismantling and removal of bituminous wearing


and binder course including disposal of demolished
materials with loading, unloading & transportation
to designated places up to any lead etc., as
directed by the Engineer, complete in all respect.
Cum 180

Unit Rate in words …………………………………..

01O-3C Dismantling and removal of existing granular sub-


base / base courses including disposal or storage
of demolished materials with loading, unloading &
transporting to an area exclusively designated for
this material up to any lead etc., as directed by the
Engineer, complete in all respect. Cum 978

Unit Rate in words …………………………………..

01O-4C Dismantling and removal of existing footh path,


stacking of re-useable material (incl. pavers, edge
/ kerb stones, etc.) and its handing over to
Employer, disposal of surplus material with
loading, unloading & transportation to designated
places up to any lead etc., as directed by the
Engineer, complete in all respect.
Sqm 565

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-1 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O-5C Dismantling / cutting and removal of existing ASF


shed with supporting system, related E&M Works,
stacking of salvaged material and its handing over
to Employer & disposal of surplus material
including material with loading, unloading &
transportation to designated places up to any lead
etc., as directed by the Engineer, complete in all
respect. Job 1

Unit Rate in words …………………………………..

EARTH WORKS
Ref. Sec.No. 1100

01O-6C Earthen shoulder using common fill etc complete in


all respect as shown on the drawings and as per
specifications Cum 525

Unit Rate in words …………………………………..

01O-7C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 4,729

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 175

Unit Rate in words …………………………………..

01O-8C Fill and backfill with selected material including


watering, compaction & etc, complete in all respect
as shown on the drawings and specifications.

a) Obtained from required excavation. Cum 1,097

Unit Rate in words …………………………………..

b) Obtained from outside source Cum 75

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-2 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

STONE SOLING
Ref. Sec.No. 1330

01O-9C 150mm thick crushed stone soling including


blinding material and compaction, complete in all
respect as shown on the drawing and as per
specification. Sqm 30

Unit Rate in words …………………………………..

TERMITE CONTROL TREATMENT


Ref.Spec. No.1600

01O-10C Termite Control Treatment complete in all respect


as specified, as shown on drawings and approved
by the Engineer. Sqm 30

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

01O-11C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield strength
not less than 414 MPa (60,000 Psi) etc complete in
all respect as shown on the drawing and
specification. tonne 118

Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2300, 2100

01O-12C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer Cum 76

Unit Rate in words …………………………………..

01O-13C Class 'D' plain concrete in steps/ situ using


specified cement complete in all respect as shown
on the drawing, as per specification and as
directed by the Engineer Cum 16

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-3 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O-14C Class 'C' concrete using specified cement in plinth


protection including bitumen seal with rubberized
material etc; complete in all respect as shown on
the drawing and specification. Cum 15

Unit Rate in words …………………………………..

01O-15C Class 'B' reinforced concrete, using specified


cement in following sub-structural members etc,
complete in all respect as shown on the drawing
and specification.

a) Raft/Footing/Foundations/Base Cum 545

Unit Rate in words …………………………………..

b) Walls Cum 128

Unit Rate in words …………………………………..

c) Columns upto plinth Cum 25

Unit Rate in words …………………………………..

d) Plinth beams Cum 5

Unit Rate in words …………………………………..

01O-16C Class 'B' reinforced concrete, using specified


cement in following super-structural members etc,
complete in all respect as shown on the drawing
and specification.

a) Columns Cum 60

Unit Rate in words …………………………………..

b) Beams & lintels Cum 4

Unit Rate in words …………………………………..

c) Slab & Projection Cum 12

Unit Rate in words …………………………………..

d) Purdi Cum 4

Unit Rate in words …………………………………..


Expansion of Terminal Building & Allied
Facilities at AIIAP, Lahore 01O-C-4 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

e) Pad for Fiber OHWT Cum 2

Unit Rate in words …………………………………..

01O-17C Class 'A' reinforced concrete, using specified


cement in following structural members etc,
complete in all respect as shown on the drawings
and specifications.

a) Base/ Foundation Cum 45

Unit Rate in words …………………………………..

b) Pedestal Column Cum 6

Unit Rate in words …………………………………..

01O-18C Precast fair faced Class 'B' concrete using


specified cement in following structures member,
laid/ fixed in specified cement sand mortar
including fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and specification.

a) Sills & Coping (pigmented) Cum 2

Unit Rate in words …………………………………..

b) Water Spout Cum 1

Unit Rate in words …………………………………..

c) Removable New Jersy Barrier Rm 32

Unit Rate in words …………………………………..

d) Pad bottom of column Cum 2

Unit Rate in words …………………………………..

e) Block top of column Cum 2

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-5 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

MISCELLENEOUS STEEL
Ref. Sec.No. 3100, 6255, 6700

01O-19C Ladder Type: Providing, fabrication and


installation of PU painted MS Monkey ladder/ MS
stair with cage, including embedding, embedding
parts, fixing and fixing accessories etc; complete
in all respect as shown on the drawing and as per
specification and as approved by the Engineer. Kg 500

Unit Rate in words …………………………………..

01O-20C Fiber Glass Water Tank: Providing and


installation of fiber glass water tank of specified
size at control room including fixing and fixing
accessories etc; complete in all respect as shown
on the drawing and as per specification and as
approved by the Engineer. No 1

Unit Rate in words …………………………………..

01O-21C Providing, fabrication and installation of ASF shed


comprising of MS pipe frame structure, MS pipe
truss structure, metal sheeting,I girder, metal strip
ceiling with light fixture, base plate welded, J-bolt
with washer & double nut, MS structure etc.
complete system as per design drawings following
by manufacturer / fabricator recommondation
including painting, embedding, embedding parts,
fixing and fixing accessories etc; complete in all
respect as shown on the drawing, as per
specification and as approved by the Engineer.
tonne 45

Unit Rate in words …………………………………..

01O-22C Providing, fabrication and installation of Teflon


Fabric Shed (mehler Type-II 900 gm/sq.m) or
approved equivalent with fixing and fixing
accessories etc; complete in all respect as shown
on the drawing, as per specification and as
approved by the Engineer. sqm 1,125

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-6 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O-23C Parking Ticket Booth: Providing, fabrication and


installation of floor mounted parking ticket booth
with MS frame structure, external metal sheeting
with rock wool insulation, internal gypsum board
false ceiling, heavy duty PVC floor and tinted
tempered glass in aniodized aluminum frame,
corean top & sill, foundation/pad, foot path / island,
Airconditioning [Supply, installation, testing and
commissioning of High Ambient Series / Model (T-
3) Split inverter type AC units (indoor + outdoor),
Reversible (Heat pump), Nominal cooling capacity
3.52 kW (1.0 TR) Four Way or Round Ceiling
Cassette / Wall Mounted (or of the type as per site
requirements), complete with supports, refrigerant
charge, thermostat, drain pumps (other than wall
mouunted) of make LG, Thailand / Korea, Daikin,
Malaysia / Thailand, General Thailand / Japan,
Samsung, Thailand / Korea or approved equivalent
from same origin, controls, mounting brackets and
accessories as per actual site requirements.
Refrigerant copper piping (Mueller, USA or
approved equivalent) for Split type AC units
complete with refrigerant charge, pipe insulation,
canvas cloth covering with adhesive, supports,
hangers, etc. complete in all respect. All refrigerant
piping shall be provided with Dura Duct conduiting.
Electrical works including all power and control
cabling / wiring, components, hangers, supports,
conduiting, fixing and other accessories as per site
requirements, complete in all respect. Condensate
drain uPVC piping including pipe insulation,
insulation protection, canvas cloth covering with
adhesive, fittings, supports, hangers, conduiting,
fixing and other accessories as per site, etc.
complete in all respects. Painting, tagging &
Identification of Services. Supply of manufacturer
recommended essential spare parts to ensure
smooth and seamless operation of AC units with
proper packing & tagging. AC units shall be with
three (03) years compressor warranty and one (01)
year parts warranty] and other related electrical
and HVAC fittings / fixtures including lights,
sockets etc., painting, embedding, embedding
parts, fixing and fixing accessories etc; complete in
all respect as shown on the drawings, as per
specifications and as approved by the Engineer.

No 4

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-7 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O-24C Providing, fabrication and installation of PU painted


gantry structure comprising MS farme cap plate,
nuts tack, tie plate, anchor bolt, base plate, rib
plate, flange plate, sign plate, MS pipe, steel pipe
dia etc. including embedding, painting, fixing and
fixing accessories, lettering & signs, reflectorized
sheet etc; complete in all respect as shown on the
drawings, as per specifications and as approved by
the Engineer.
tonne 1

Unit Rate in words …………………………………..

01O-25C Fabrication and installation of MS Bollard 1.1m


high comprising dia 150mm, 7mm thick schedule
40 pipe filled with class-C concrete & coated with
fluorescent epoxy paint in alternative yellow &
black strip of appropriate width and covered with
10mm thick ms plate cap welded all around
including civil work for foundation and anchorage
etc; complete in all respect as specified or as
directed by the Engineer.
No 230

Unit Rate in words …………………………………..

BRICK MASONRY
Ref.Spec. No. 4200

01O-26C Reinforced facing brick masonry outer wall 225mm


thick, set in specified cement mortar including MS
anchor Bars etc; complete in all respect as shown
on the drawing and as per specification.
Cum 8

Unit Rate in words …………………………………..

01O-27C Reinforced facing brick masonry wall 114mm thick,


set in specified cement mortar including MS anchor
bars etc; complete in all respect as shown on the
drawing and specification. Cum 3

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-8 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

CARPENTARY & JOINERY


Ref.Sec.No. 4600,6700

01O-28C Door Type: 38mm thick wooden hollow core flush


door filled with rough wood both side laminated
and hardwood lipping all around in teak wood
frame in lacquer finish with hardware set (as per
schedule), including fixing and fixing accessories
etc of the following design types; complete in all
respect as shown on the drawing and as per
specification and as approved by the Engineer.

a) Type-A1
including splash plate Sqm 2

Unit Rate in words …………………………………..

ALUMINIUM WORKS
Ref. Sec.No. 6220, 6250

01O-29C Door Type: 8mm thick tinted/ clear tempered


glass pivoted door on anodized heavy duty
aluminum frame with hardware set (as per
schedule) including fixing and fixing accessories
etc. of the following design types; complete in all
respect as shown on the drawing and specification.

a) Type-GD1
tinted tempered glass Sqm 3

Unit Rate in words …………………………………..

01O-30C Window Type: 8mm thick tinted/ clear tempered


glass fixed/ openable screen/ window/ ventilator on
anodized heavy duty aluminum frame with
compatible hardware set (as per schedule)
including fixing and fixing accessories etc of the
following design types; complete in all respect as
shown on the drawing and as per specification and
as approved by the Engineer.

a) Type-W01
tinted tempered glass screen Sqm 5

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-9 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Type-W02
tinted tempered glass screen Sqm 9

Unit Rate in words …………………………………..

c) Type-W03
tinted tempered glass screen Sqm 3

Unit Rate in words …………………………………..

d) Type-W04
tinted tempered glass ventilator Sqm 1

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

01O-31C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth. Sqm 1,930

Unit Rate in words …………………………………..

01O-32C Water proofing and built-up roofing of the following


types over roof slab etc; complete in all respect as
shown on the drawing and specification.

a) Type-I Sqm 30

Unit Rate in words …………………………………..

CEMENT PLASTER
Ref. Sec.No. 6521

01O-33C 13mm thick 1:6 cement sand plaster to specified


interior surfaces etc; complete in all respect as
shown on the drawing and specification. Sqm 80

Unit Rate in words …………………………………..

01O-34C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove/ plain in plaster as
specified etc; complete in all respect as shown on
the drawing and specification. Sqm 240

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-10 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

FLOOR AND WALL FINISHES


Ref. Sec.No. 6531, 6600

01O-35C Floor type F01: 600x600x8mm thick fully vitrified


glazed Porcelain tiles in approved color/shade and
texture conforming to ISO 13006 Bla requirements,
laid in specified pattern with matching grout, set in
specified cement sand mortar including 50mm
thick Class 'C' concrete screed, cement mortar
with approved adhesive, 16mm thick 1:3 dry
cement mortar binding course and dry cement
spread & splash of water etc; complete in all
respect as shown on the drawing and as per
specification and as approved by the Engineer.
Sqm 23

Unit Rate in words …………………………………..

01O-36C Floor type F02: 300x300x8mm thick fully vitrified


semi glazed Porcelain tiles in approved
color/shade and texture conforming to ISO 13006
Bla requirements, filled with matching grout, set in
specified cement sand mortar including water
barrier course of approved liquid proofing
(application as per manufacturer
recommendation), 45mm thick Class 'C' concrete
screed base, cement mortar with approved
adhesive, 20mm thick 1:3 dry cement mortar
binding course and dry cement spread & splash of
water etc; complete in all respect as shown on the
drawing and as per specification and as approved
by the Engineer. Sqm 5

Unit Rate in words …………………………………………………………………………

01O-37C Floor type F03: 75mm thick Class 'C' cement


concrete screed (pigmented) floor in steel trowel
finish laid in panels of specified sizes and
separated by glass/ pvc divider strip as per design
etc; complete in all respect as shown on the
drawing and as per specification and as approved
by the Engineer. Sqm 2

Unit Rate in words …………………………………..

01O-38C 100mm thick Class 'D' cement concrete sub-floor


complete in all respect as shown on the drawing
and as per specification and as approved by the
Engineer. Sqm 35

Unit Rate in words …………………………………..


Expansion of Terminal Building & Allied
Facilities at AIIAP, Lahore 01O-C-11 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O-39C Wall type W02: 300x300x8mm thick fully vitrified


glazed Porcelain tile cladding upto 2100mm height
in approved color/ shade and texture conforming to
ISO 13006 Bla requirements, laid in specified
pattern with matching grout, set in specified
cement sand mortar including rough base plaster
etc; complete in all respect as shown on the
drawing and as per specification and as approved
by the Engineer. Sqm 19

Unit Rate in words …………………………………..

01O-40C Clading: Red brick clading over specified surfaces


in approved size, color/shade and texture, laid in
specified pattern etc; complete in all respect as
shown on the drawing & specification.
Sqm 35

Unit Rate in words …………………………………..

01O-40C Skirting type SK01: 150mm high Porcelain tile


skirting same as floor tile in approved size,
color/shade and texture, conforming to ISO 13006
Bla requirements, set in specified cement sand
mortar including rough base plaster etc; complete
in all respect as shown on the drawing and as per
specification and as approved by the Engineer. Sqm 4

Unit Rate in words …………………………………..

FALSE CEILING
Ref. Sec.No. 6560

01O-41C Ceiling Type C02: 600x600x12mm mineral fiber


ceiling (premium quality) with T-Grid & threaded
rod system with provision light fixtures and other
fixture with sound insulation on top etc; complete in
all respect as shown on the drawing and as per
specification and as approved by the Engineer. Sqm 28

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-12 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

MARBLE & GRANITE WORKS


Ref. Sec.No. 6531, 6532

01O-42C Saddle/ Threshold Type: Prepolished granite


threshold of following types, including bullnozing &
water proofing membrane (where required as per
drawing & design), c.c base, fixing and fixing
accessories etc. of the following types; complete in
all respect as shown on the drawing and as per
specification and as approved by the Engineer.

a) Type-1: Saddle/ Threshold


with 9x50mm Aluminum Strip Sqm 2

Unit Rate in words …………………………………..

b) Type-2: Saddle/ Threshold


with water proofing membrane Sqm 1

Unit Rate in words …………………………………..

01O-43C Stair/Step Type # 1: Prepolished granite for the


following structures of specified size, color and
quality, laid in approved pattern set in cement
concrete base with abrasive inserts & sstl
dowel/anchor including fixing and fixing
accessories etc; complete in all respect as shown
on the drawing and as per specification and as
approved by the Engineer.

a) Trade 20mm thick Sqm 2

Unit Rate in words …………………………………..

b) Riser 10mm thick Sqm 1

Unit Rate in words …………………………………..

PAINTING
Ref. Sec.No. 6700

01O-44C Plastic emulsion paint to specified interior surfaces


in approved color / shade etc; complete in all
respect as shown on the drawings, as per
specifications and as approved by the Engineer.
Sqm 100

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-13 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O-45C Weather resistant paint to specified exterior


surfaces in approved color / shade etc; complete in
all respect as shown on the drawings, as per
specifications and as approved by the Engineer.
Sqm 63

Unit Rate in words …………………………………..

ILLUMINATED / NEON SIGNS


Ref. Sec.No. 6720

01O-46C Providing and fixing / installation of Illuminated


Neon signs (LED) Acrylic sign with back housing
MS sheet, 19SWG Powder coated with gas
welding, Pure acrylic sheet 4mm as per the
approved color scheme, LED injected Modules
with weather proof power supply and appropriate
size copper internal wiring etc, including fixing and
fixing accessories etc complete in all respect as
shown on the drawings and specification or as
directed by the Engineer Sqm 32

Unit Rate in words …………………………………..

GRANULAR SUB-BASE COURSE &


AGGREGATE BASE COURSE
Ref. Sec.No. 7410

01O-47C Laying of 200 mm compacted granular sub-base


course including compaction upto required
maximum dry density as specified or as directed by
the Engineer. Cum 1,195

Unit Rate in words …………………………………..

01O-48C Laying of 200 mm compacted crushed aggregate


base course including compaction upto required
maximum dry density as specified or as directed by
the Engineer. Cum 1,195

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-14 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

BITUMINOUS SURFACE COURSES


Ref. Sec.No. 7420

01O-49C Providing and laying Asphalt binder course of


following compacted thickness in two layers
including prime & tack coats etc; complete in all
respect as shown on the drawing or as directed by
the Engineer

a) 100 mm thick Sqm 5,680

Unit Rate in words …………………………………..

01O-50C Providing and laying asphalt wearing course of


following compacted thickness including tack coat
etc; complete in all respect as shown on the
drawing or as directed by the Engineer

a) 50 mm thick Sqm 5,680

Unit Rate in words …………………………………..

MISCELLANEOUS ROAD WORK


Ref. Sec. 7190

01O-51C Precast fairfaced edge stone (100 x 250 mm)


including earthwork, cement sand mortar, plain
cement concrete etc complete in all respect as
shown on the drawings Rm 2,100

Unit Rate in words …………………………………..

01O-52C Precast fairfaced Kerbstone (150 x 300 mm)


including earthwork, cement sand mortar, plain
cement concrete etc complete in all respect as
shown on the drawings Rm 855

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-15 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

ROAD PAVEMENT MARKING & ROAD STUDS


Ref. Sec. 7385, 7370

01O-53C Pavement markings and symbols with


thermoplastic paint etc including cleaning of dust
& dirt by mechanical means etc. of the following
colors; complete in all respect as shown on the
drawings and as per specifications.

a) White Sqm 300

Unit Rate in words …………………………………..

b) Yellow Sqm 600

Unit Rate in words …………………………………..

01O-54C Reflectorized road studs (heavy duty) including


fixing and fixing accesories etc. of the following
colors; complete in all respect as shown on the
drawings and as per specifications.

a) White/Red No 170

Unit Rate in words …………………………………..

b) Yellow/Red No 170

Unit Rate in words …………………………………..

01O-55C Providing, fixing & installation of Fiber Bollard


(heavy duty) including fixing and fixing accesories
etc. of the following colors; complete in all respect
as shown on the drawings, as per specifications
and as approved by the Engineer.

a) White/Red No 230

Unit Rate in words …………………………………..

PRECAST CONCRETE PAVING BLOCK/TILES


Ref. Sec. 7510

01O-56C 60mm thick precast fairfaced pavers including


earthwork, sand cushion & plain cement concrete
etc. complete in all respect as shown on the
drawings and as per specfications Sqm 2,480

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-16 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O-57C 80mm thick precast fairfaced pavers including


earthwork, sand cusion & plain cement concrete
etc. complete in all respect as shown on the
drawings and as per specfications Sqm 2,480

Unit Rate in words …………………………………..

TRAFFIC SIGNS
Ref. Sec.No. 7380

01O-58C Providing & fixing traffic sign boards of following


types comprising pipe post, stiffeners plates,
anchor bolts wth nut washer, fillet welding,
excavation, reinforced cement concrete in
foundations, steel reinforcement, paint,
retroreflective sheet, lettering & signs etc.
complete in all respect as shown on the drawings
and as per specifications.

a) Circular Nos

Unit Rate in words …………………………………..

b) Triangular Nos

Unit Rate in words …………………………………..

c) Rectangular Nos

Unit Rate in words …………………………………..

FENCING
Ref. Sec. No. 0200, 1100,2100,2200,2300,2450,3100,6412

01O-59C Removal, shifting & re-reinstallation of existing


fence including fence fabric, posts, bracing posts,
barbed / concertina wire, strecher bar, cleat etc.
earthwork including exavation and backfill,
Structure including new RCC foundation & tie
beam, steel reinforcement, etc complete in all
respect as shown on the drawing, as per
specification and as directed by the Engineer.
Rm 265

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-17 August-2022
BILL OF QUANTITIES

CODE NO.01 - EXTERNAL DEVELOPMENT WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

01O-60C PVC Coated Chain link including fence fabric,


barbed / concertina wire, strecher bar, cleat, PU
painted frame with 2-25x3mm flat bar, 30x3mm flat
bar bracing, 100x100x3m gusset plate,
125x125x6mm HSS for line posts and bracing
posts etc. compatable with existing fence
completet in all respect, including exavation and
backfill, new RCC foundation & tie beam etc
complete in all respect as shown on the drawing,
as per specification and as directed by the
Engineer. Rm 825

Unit Rate in words …………………………………..

01O-61C PVC Coated Chain link Gate of following width with


framing assembly, fence fabric, barbed /
concertina wire, strecher bar, cleat, PU painted
frame with 2-25x3mm flat bar, 30x3mm flat bar
bracing, 100x100x3m gusset plate, 125x125x6mm
HSS for line posts and bracing posts etc.
compatable with existing fence completet in all
respect, including exavation and backfill, new RCC
foundation & tie beam etc complete in all respect
as shown on the drawing, as per specification and
as directed by the Engineer.

a) 8.5 m wide No 1

Unit Rate in words …………………………………..

b) 5.5 m wide No 1

Unit Rate in words …………………………………..

Total Cost of Code 01O (Civil Works) Carried


Over to Summary of Bid Price - A

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 01O-C-18 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

C. CIVIL WORKS

02-PASSENGER TERMINAL BUILDING

DEMOUNTABLE PARTITIONS
Ref.Spec. No. 6625

Methodology for dismantling/ repouring/ remedial


works as mentioned in General Notes drawing
shall be strictly followed and as approved by the
Engineer.

02-1C Providing, fixing/ erecting and removing


demountable temporary partitions with M.S.
supporting system, both sides painted fiber
cement board, insulated polycarbonate sheet,
lockable metal door etc. comprising propping,
bracing and shoring of existing RCC structures till
completion of works. (The Contractor shall submit
methodology and design of temporary partitions/
supporting system to the Engineer for approval
prior to start the works.) Sqm 4,000

Unit Rate in words …………………………………..


.
DISMANTLING
Ref.Spec. No.0200

02-2C Dismantling/ Cutting/ chiseling of existing


reinforced cement concrete works (as describe/
shown in drawing) at any depth & level, stacking of
useable material shall be handed over to Employer
and disposal of debris/ unused/ demolished/
removed materials, including loading, unloading
and transporting complete in all respect to
designated places and up to any lead or as
directed by the Engineer and specification
(Contractor is fully responsible for the safety and
stability of existing structure during removing/
dismantling works)

a) Remote access ramp Cum 215

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-1 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Boarding Bridge including stairs Cum 205

Unit Rate in words …………………………………..

c) Waffle Slab 600mm thick Sqm 1,600

Unit Rate in words …………………………………..

d) Columns, Beams, Slabs, Purdi, Walls etc. Cum 2,100

Unit Rate in words …………………………………..

e) Trench Cum 200

Unit Rate in words …………………………………..

02-3C Dismantling/ Cutting/ chiseling and removal of


existing plain cement concrete works (as
describe/ shown in drawing) at any depth & level
including loading, unloading and transporting
complete in all respect to designated places and
up to any lead or as directed by the Engineer and
specification (Contractor is fully responsible for the
safety and stability of existing structure during
removing/ dismantling works) Cum 50

Unit Rate in words …………………………………..

02-4C Dismantling/ removal of existing brick masonry


walls of any thickness (as describe/ shown in
drawing) at any depth & level, stacking of useable
material, shall be handed over to Employer and
disposal of debris/ unused/ demolished/ removed
materials, including loading, unloading and
transporting complete in all respect to designated
places and up to any lead or as directed by the
Engineer and specification (Contractor is fully
responsible for the safety and stability of existing
structure during removing/ dismantling works)
Cum 585

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-2 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-5C Dismantling/ removal of existing floor and


skirting of any kinds with base/ sub-floor (as
describe/ shown in drawing) at any depth & level,
stacking of useable material shall be handed over
to Employer and disposal of debris/ unused/
demolished/ removed materials, including loading,
unloading and transporting complete in all respect
to designated places and up to any lead or as
directed by the Engineer and specification
(Contractor is fully responsible for the safety and
stability of existing structure during removing/
dismantling works) Sqm 4,390

Unit Rate in words …………………………………..

02-6C Removal and reinstallation of existing marble/


granite cladding (as describe/ shown on drawing)
without damaging panels, tiles, trims, moulding &
motifs at any level, safely removing, handling,
safe storage/ stacking, shifting including repairing
if required, reinstallation/ refixing and refixing
accessories etc; and disposal of debris/ unused/
demolished/ removed materials, including loading,
unloading and transporting complete in all respect
to designated places and up to any lead or as
directed by the Engineer and specification
(Contractor is fully responsible for the safety and
stability of existing structure during removing/
dismantling works) Sqm 1,650

Unit Rate in words …………………………………..

02-7C Removal of existing brick cladding from walls (as


describe/ shown in drawing) at any level, safely
removing, handling, safe storage/ stacking,
shifting including repairing if required,
reinstallation/ refixing and refixing accessories
etc; and disposal of debris/ unused/ demolished/
removed materials, including loading, unloading
and transporting complete in all respect to
designated places and up to any lead or as
directed by the Engineer and specification
(Contractor is fully responsible for the safety and
stability of existing structure during removing/
dismantling works) Sqm 9,655

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-3 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-8C Dismantling/ removal of existing precast fairfaced


concrete sill, coping, moulding and concrete
blocks (as describe/ shown in drawing) at any
level, safely removing, handling, safe storage/
stacking, shifting including repairing if required,
reinstallation/ refixing and refixing accessories
etc; and disposal of debris/ unused/ demolished/
removed materials, including loading, unloading
and transporting complete in all respect to
designated places and up to any lead or as
directed by the Engineer and specification
(Contractor is fully responsible for the safety and
stability of existing structure during removing/
dismantling works)

a) Sill Rm 75

Unit Rate in words …………………………………..

b) Coping Rm 165

Unit Rate in words …………………………………..

c) Block Rm 165

Unit Rate in words …………………………………..

d) Moulding Rm 165

Unit Rate in words …………………………………..

02-9C Removal and reinstallation of existing Fixtures


such as door/ window/ ventilator/ screen/
curtain wall etc with supporting system (as
describe/ shown in drawing) at any level, safely
removing, handling, safe storage/ stacking,
shifting including repairing if required,
reinstallation/ refixing and refixing accessories
etc; and disposal of debris/ unused/ demolished/
removed materials, including loading, unloading
and transporting complete in all respect to
designated places and up to any lead or as
directed by the Engineer and specification
(Contractor is fully responsible for the safety and
stability of existing structure during removing/
dismantling works) Sqm 480

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-4 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-10C Removal and reinstalling/ refixing of existing False


Ceiling Type C03 and fixtures (as describe/
shown in drawing) at any level, safely removing,
handling, safe storage/ stacking, shifting including
repairing if required, fixing and fixing accessories
etc complete in all respect as shown on the
drawings. (Contractor is fully responsible for the
safety and stability of existing structure during
removing/ dismantling works) Sqm 6,705

Unit Rate in words …………………………………..

02-11C Removal and reinstallation of existing glazed


partition and other existing operations
Fixtures/ furniture such as check-in/ immigration/
other counters, scanners, signage & etc (as
describe/ shown in drawing) at any level, safely
removing, handling, safe storage/ stacking,
shifting including repairing if required, to remain till
substantial completion of project area/ as advised
by the Engineer (Contractor is fully responsible for
the safety during removing works) Job 1

Unit Rate in words …………………………………..

EARTH WORKS
Ref. Sec.No. 1100

02-12C Excavation in all kinds of sub-surface material up


to following depth including dewatering and
disposal of surplus/ rejected all the required
excavated material to designated places and up to
any lead, complete in all respect as shown on the
drawing and specification and as directed by the
Engineer.

a) From 0 to 2 meter Cum 34,120

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 19,005

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-5 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-13C Fill and backfill with selected material including


watering, compaction & etc, complete in all respect
as shown on the drawing and specification.

a) Obtained from required excavation. Cum 17,714

Unit Rate in words …………………………………..

b) Obtained from outside sources. Cum 13,110

Unit Rate in words …………………………………..

02-14C Selected fill material including watering,


compaction & etc, complete in all respect as
shown on the drawing and specification. Cum 16,926

Unit Rate in words …………………………………..

STONE SOLING
Ref. Sec.No. 1330

02-15C Crushed stone soling of any thickness including


blinding material and compaction etc. complete in
all respect as directed by the Engineer and as
shown on the drawing and specification. Cum 25

Unit Rate in words …………………………………..

TERMITE CONTROL TREATMENT


Ref. Sec.No. 1600

02-16C Termite Control Treatment complete in all respect


as shown on the drawing and specification. Sqm 17,095

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

02-17C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and specification. tonne 5,900

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-6 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-18C Dowels anchorage with epoxy chemical adhesive


Fisher Adhesive FIS-EM Plus or HILTI HIT-RE 500
or approved equivalent including drilling of holes in
existing structures, fixing and fixing acessories
etc., complete in all respects as per
manufacturer's recommendations and as shown
on the drawings and specifications.

i) #8 dia No 640

Unit Rate in words …………………………………..

ii) #6 dia No 740

Unit Rate in words …………………………………..

iii) #5 dia No 70

Unit Rate in words …………………………………..

iv) #4 dia No 4,600

Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

02-19C Class 'E' plain concrete using specified cement


complete in all respect as shown on the drawings
and specifications. Cum 2,917

Unit Rate in words …………………………………..

02-20C Class 'D' plain concrete in situ using specified


cement complete in all respect as shown on the
drawings and specifications. Cum 1,743

Unit Rate in words …………………………………..

02-21C Class 'C' concrete using specified cement in plinth


protection including bitumen seal with rubberized
material etc; complete in all respect as shown on
the drawings and specifications. Cum 125

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-7 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-22C Class 'B' reinforced concrete using specified


cement in following sub-structures including
providing and applying approved cementitious
bonding agent between existing and new concrete
surfaces etc complete in all respect as shown on
the drawing & specification.

a) Raft/ Footing/ Foundations Cum 12,463

Unit Rate in words …………………………………..

b) Wall Cum 113

Unit Rate in words …………………………………..

c) Plinth beams/ walls Cum 1,193

Unit Rate in words …………………………………..

e) Grade Slab
including expansion joint (Polysulphide sealant,
Bitumen impregnated soft board, Backer Rod)
etc.complete in all respect as shown on the
drawing and specification. Cum 3,265

Unit Rate in words …………………………………..

e) Trenches Cum 51

Unit Rate in words …………………………………..

02-23C Class 'B' reinforced concrete using specified


cement in following superstructures including
providing and applying approved cementitious
bonding agent between existing and new concrete
surfaces etc complete in all respect as shown on
the drawing & specification.

a) Beams & lintels Cum 3,033

Unit Rate in words …………………………………..

b) Slab & projections Cum 2,575

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-8 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

c) Waffle Slab Sqm 28,347

Unit Rate in words …………………………………..

d) Ribbed slab including ribs Cum 365

Unit Rate in words …………………………………..

e) Curve slab including ribs Cum 125

Unit Rate in words …………………………………..

f) Staircase Cum 62

Unit Rate in words …………………………………..

g) Walls Cum 55

Unit Rate in words …………………………………..

h) Parapet/Purdi Cum 708

Unit Rate in words …………………………………..

i) Decorative Arches as per design Cum 55

Unit Rate in words …………………………………..

02-24C Class 'A' reinforced concrete using specified


cement in sub-structure columns etc complete in
all respect as shown on the drawing &
specification. Cum 458

Unit Rate in words …………………………………..

02-25C Class 'A' reinforced concrete using specified


cement in superstructure columns etc complete in
all respect as shown on the drawing &
specification. Cum 2,622

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-9 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-26C RETROFITTING
Jacketing around existing column in Class 'A'
concrete including application of SBR (MASTER
EMACO SBR2 or approved equivalant) etc.
complete in all respects as per manufacturer's
recommendations and as shown on the drawing &
specification. Cum 80

Unit Rate in words …………………………………..

02-27C Precast fairfaced Class 'B' reinforced concrete


using ordinary Portland cement in moulding, block,
window sills, water spouts, planks and coping (as
describe/ shown on the drawing) etc. as per
design laid in specified cement sand mortar
including fixing etc complete in all respect as
shown on the drawing & specification. Cum 175

Unit Rate in words …………………………………..

02-28C Class 'B' reinforced concrete slab using specified


cement including providing and applying approved
cementitious bonding agent between existing and
new concrete surfaces etc complete in all respect
as shown on the drawing & specification.

a) Slab Repour/ Recast Sqm 550

Unit Rate in words …………………………………..

b) Waffle 600mm thick slab Repour/ Recast Sqm 750

Unit Rate in words …………………………………..

SADDLE TYPE

02-29C Precast fair faced Class 'B' concrete using


specified cement in following structures, laid/ fixed
in specified cement sand mortar including fixing
and fixing accessories etc; complete in all respect
as shown on the drawing & specification.

a) Type-02: Saddle/ Threshold


with 9x50mm aluminum strip Cum 5

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-10 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Type-07: Saddle/ Threshold


with 30x30 galvanized steel angle, metal flashing,
steel dowels, weather stripping & water proofing
membrane. Cum 2

Unit Rate in words …………………………………..

STRUCTURAL STEEL WORKS


Ref. Sec.No. 3000

02-30C Providing, fabrication and installation of structural


steel comprising MS framing, HSS, pipes, angles,
plates, channel, nuts, bolts, metal flashing etc.
including embedding, welding, painting, fixing and
fixing accessories etc.; complete in all respects as
shown on the drawing & specification.
tonne 15

Unit Rate in words …………………………………..

MISCELLANEOUS STEEL WORKS


Ref. Sec.No. 3100

02-31C Providing, fabrication and installation of MS


Monkey ladder/ MS stair with cage/ without cage,
platform, chemical anchor bolt including
embedding, welding, painting, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing & specification. Kg 1000

Unit Rate in words …………………………………..

02-32C Providing, fabrication and installation of PU


painted MS ramp railing (as describe & shown on
the drawing) including embedding and embedding
parts etc; complete in all respect as shown on the
drawing and specification. Rm 430

Unit Rate in words …………………………………..

02-33C Providing, fabrication and installation of galvanized


MS grating cover including fixing and fixing
accessories etc; complete in all respects as shown
on the drawing and specification. Sqm 4

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-11 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-34C Providing, fabrication and installation of 6mm thick


MS chequred plate, including fixing and fixing
accessories etc; complete in all respects as shown
on the drawing and specifications. Sqm 180

Unit Rate in words …………………………………………………………………………

02-35C Providing, fabrication and installation of MS


powder coated Trolley Guard / Bumper Rail
including powder coated MS moulded face sheet
plate, MS plate, expansion bolts, fixing
accessories etc; complete in all respects as shown
on the drawing and specifications.

i) Floor mounted Rm. 1,980

Unit Rate in words …………………………………..

ii) Wall mounted Rm. 1,320

Unit Rate in words …………………………………..

02-36C Providing, fabrication and installation of galvanized


angle iron corner guard at column's edge including
expansion bolts, strips of yellow & black paint,
fixing accessories etc; complete in all respects as
shown on the drawing and specifications. Rm. 1,290

Unit Rate in words …………………………………..

02-37C Cover Sheet: UV resistant PVC insulated cover in


MS framing including fixing and fixing accessories
etc, complete in all respect as shown on the
drawing, as per specifications and as per
manufacturer's recommendations. Sqm 5

Unit Rate in words …………………………………..

02-38C Roof Hatch: Steel cover & liner as per MFTR


Standard with insulation, rubber gasket, spring
latch with handles, automatic hold open arm, pad
lock, lifting mechanism, steel curbs including fixing
and fixing accessories etc, complete in all respect
as shown on the drawing, as per specifications
and as per manufacturer's recommendations. No 1

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-12 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-39C Shaft Covering: PVC roof covering including


fixing and fixing accessories etc, complete in all
respect as shown on the drawing, as per
specifications and as directed by the Engineer.
(excluding the cost of structural steel) Sqm 10

Unit Rate in words …………………………………..

02-40C Window Type: Fully sand trap louvered with 16


guage MS blades with 2mm thick MS frame in
epoxy paint finish with compatible hardware set
(as per schedule) including fixing and fixing
accessories etc of the following design types;
complete in all respect as shown on the drawing
and specification.

a) Type-xLS1 9

Unit Rate in words …………………………………..

b) Type-xLS2 78

Unit Rate in words …………………………………..

c) Type-xLS3
23
Unit Rate in words …………………………………..

d) Type-xLS4 12

Unit Rate in words …………………………………..

02-41C Staircase Type 5 (Stair N8, N9, N10)


Providing, fabrication and installation of floor
mounted PU painted MS railing with galvanized
steel handrail, PVC coated cap, MS bracket
including embedding, embedding parts, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing and specification. Rm 75

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-13 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-42C Staircase Type 5 (Stair N8, N9, N10)


Providing, fabrication and installation of wall
mounted PU painted MS pipe rail with MS wall
bracket including embedding, embedding parts,
fixing and fixing accessories etc; complete in all
respect as shown on the drawing and Rm 75

Unit Rate in words …………………………………..

02-43C Staircase Type 6 (Stair N7)


Providing, fabrication and installation of floor
mounted epoxy painted MS railing with MS pipe
(upper rail, baluster & mid rail) including
embedding, embedding parts, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing and specification. Rm 14

Unit Rate in words …………………………………..

02-44C Staircase Type 6 (Stair N7)


Providing, fabrication and installation of wall
mounted epoxy painted MS pipe rail with MS wall
bracket including embedding, embedding parts,
fixing and fixing accessories etc; complete in all
respect as shown on the drawing and Rm 14

Unit Rate in words …………………………………..

02-45C Door Type: 44mm thick Hollow Metal door 1.5mm


(16gauge) thick seamless MS facing sheets,
epoxy painted, filled with mineral fiber wool and
compatible hardware set (as per schedule)
including fixing and fixing accessories etc. of the
following design types; complete in all respect as
shown on the drawing & specification.

a) Type-SD1
fire rated Sqm 25

Unit Rate in words …………………………………..

b) Type-SD2
including vision panel in 12mm thick (6+6)
laminated glass & aluminum door grill (powder
coated), fire rated Sqm 30

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-14 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

c) Type-SD3
including 12mm thick (6+6) laminated glass (Fan
light & kick plate, fire rated Sqm 3

Unit Rate in words …………………………………..

d) Type-SD4
including aluminum door grill (powder coated)
fire rated Sqm 8

Unit Rate in words …………………………………..

e) Type-SD5
including aluminum door grill (powder coated)
fire rated Sqm 135

Unit Rate in words …………………………………..

f) Type-SD6
fire rated Sqm 20

Unit Rate in words …………………………………..

g) Type-SD9
fire rated Sqm 15

Unit Rate in words …………………………………..

h) Type-SD10
fire rated Sqm 18

Unit Rate in words …………………………………..

i) Type-SD11
including vision panel in 12mm thick (6+6)
laminated glass, fire rated Sqm 5

Unit Rate in words …………………………………..

j) Type-SD12
fire rated Sqm 5

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-15 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-46C Door Type: Fully sand trap MS louvered door with


1.5mm (16 gauge) MS blades louvers in 2mm
thick MS frame in epoxy paint finish with
compatible hardware set (as per schedule)
including fixing and fixing accessories etc. of the
following design types; complete in all respect as
shown on the drawing & specification.

a) Type-SD7
fire rated Sqm 10

Unit Rate in words …………………………………..

b) Type-SD8
fire rated Sqm 55

Unit Rate in words …………………………………..

02-47C Door Type SD13: Motorized operated weather


seal insulated galvanized steel, epoxy painted fire
rated rolling shutter (provide chain hoist for
emergency operation/manual option) with
compatible hardware set (as per schedule)
including fixing and fixing accessories etc. of the
following design types; complete in all respect as
shown on the drawing & specification. Sqm 5

Unit Rate in words …………………………………..

02-48C Providing, fabrication and installation of metal


threshold of specified size including grout, base,
fixing and fixing accessories etc. of the following
types; complete in all respect as shown on the
drawing & specification.

a) Type-01: Metal Saddle/ Threshold


with drip edge & weather stripping Sqm 15

Unit Rate in words …………………………………..

b) Type-04: Metal Saddle/ Threshold Sqm 8

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-16 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-49C Providing, fabrication and installation of continuous


galvanized steel angle threshold of specified size
including base, fixing and fixing accessories etc. of
the following types; complete in all respect as
shown on the drawing & specification.

a) Type-08: Saddle/ Threshold


continuous galvanized steel angle Sqm 5

Unit Rate in words …………………………………..

b) Type-09: Saddle/ Threshold


continuous galvanized steel angle Sqm 1

Unit Rate in words …………………………………..

STAINLESS STEEL MATERIAL & FINISHES


Ref. Sec.No. 3010

02-50C Stainless steel trolley guard as per design & detail


including fixing and fixing accessories etc
complete in all respect as shown on the drawing
and specification. Rm 1,570

Unit Rate in words …………………………………..

02-51C Wall type W12: Providing, fabrication and


installation of stainless steel cladding over
specified surfaces including embedding,
embedding parts, fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and specification. Sqm 350

Unit Rate in words …………………………………..

02-52C Skirting type SK07: 200mm high stainless steel


skirting in approved size including all fixing
accessories etc.; complete in all respects as
shown on the drawing & specification. Sqm 6

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-17 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-53C Staircase Type 4 (Stair N5, N6)


Providing, fabrication and installation of floor
mounted chrome finished stainless steel pipe
railing with top rail, mid rail, balusters including
embedding, embedding parts, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing and specification. Rm 25

Unit Rate in words …………………………………..

02-54C Staircase Type 2 (Stair N1, N4)


Staircase Type 4 (Stair N5, N6)
Providing, fabrication and installation of chrome
finished stainless steel pipe rail with stainless steel
wall bracket including embedding, embedding
parts, fixing and fixing accessories etc; complete in
all respect as shown on the drawing and
specification. Rm 85

Unit Rate in words …………………………………..

02-55C Providing, fabrication and installation of stainless


steel barrier of following lengths with 60mm dia
stainless steel tube & cap including embedding,
embedding parts, fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and specification:

a) 715mm No. 25

Unit Rate in words …………………………………..

b) 1000mm No. 25

Unit Rate in words …………………………………..

c) 1050mm No. 25

Unit Rate in words …………………………………..

d) 1150mm No. 25

Unit Rate in words …………………………………..

e) 1350mm No. 25

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-18 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

f) 1750mm No. 80

Unit Rate in words …………………………………..

BRICK MASONRY WORKS


Ref.Spec. No. 4200

02-56C 113mm thick reinforced brick masonry wall set in


cement sand mortar including damp proof course,
stiffener columns, beams, steel reinforcement,
weep holes, S-shape anchors, fillet, pointing, steel
plate, SS anchor, expansion bolt, fiberglass fire
stopping filler & sealant wherever required etc.
complete in all respects as shown on the drawing
& specification. Cum 725

Unit Rate in words …………………………………..

02-57C 228mm thick reinforced brick masonry wall set in


cement sand mortar including damp proof course,
stiffener columns, beams, steel reinforcement,
water barrier, weep holes, S-shape anchors, fillet,
pointing, steel plate, SS anchor, expansion bolt,
fiberglass fire stopping filler & sealant wherever
required etc. complete in all respects as shown on
the drawing & specification. Cum 2,585

Unit Rate in words …………………………………..

02-58C Brick Cladding/ Brick facing (to be match with


existing brick facing work) set in cement sand
mortar including steel dowels, 6mm dia stainless
steel wall ties, weep holes, vapour barrier coating,
breathing holes, fixing accessories etc. complete
in all respects as shown on the drawing &
specification. Sqm 11380

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-19 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

CARPENTARY & JOINERY


Ref.Sec.No. 4600,6700

02-59C Door Type: 35mm thick wooden single leaf, single


swing, hollow core, both sides plastic laminated
with teakwood lipping finished, all around wooden
flush door in lacquered finish with hardware set
(as per schedule), including fixing and fixing
accessories etc; of the following design types;
complete in all respect as shown on the drawing
and specification.

a) Type-D2
fire rated Sqm 65

Unit Rate in words …………………………………..

b) Type-D16
including aluminum door grill (powder coated)
& kick plate, fire rated Sqm 5

Unit Rate in words …………………………………..

02-60C Door Type: 45mm thick single leaf, single swing,


solid core door filled with rough wood, both sides
plastic laminated with teakwood lipping finished, all
around wooden flush door in lacquered finish with
hardware set (as per schedule), including fixing
and fixing accessories etc; complete in all respect
as shown on the drawing and specification.

a) Type-D3
including aluminum door grill (powder coated)
& kick plate, fire rated Sqm 60

Unit Rate in words …………………………………..

b) Type-D4
including aluminum door grill (powder coated)
& kick plate, fire rated Sqm 15

Unit Rate in words …………………………………..

c) Type-D5
including vision panel (where required)
& kick plate, fire rated Sqm 30

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-20 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

d) Type-D6
including aluminum door grill (powder coated)
& kick plate, fire rated Sqm 100

Unit Rate in words …………………………………..

e) Type-D7
including 12mm thick (6+6) laminated glass
Fan light, aluminum door grill (powder coated)
& kick plate, fire rated Sqm 52

Unit Rate in words …………………………………..

f) Type-D9
including vision panel 12mm thick (6+6) laminated
glass, aluminum door grill (powder coated) & kick
plate, fire rated Sqm 53

Unit Rate in words …………………………………..

g) Type-D10
including vision panel 12mm thick (6+6) laminated
glass, aluminum door grill (powder coated) & kick
plate, fire rated Sqm 42

Unit Rate in words …………………………………..

h) Type-D11
including 12mm thick (6+6) laminated glass
Fan light, fire rated Sqm 3

Unit Rate in words …………………………………..

i) Type-D12
including 12mm thick (6+6) laminated glass
Fan light, aluminum door grill (powder coated)
& kick plate, fire rated Sqm 45

Unit Rate in words …………………………………..

j) Type-D13
including 12mm thick (6+6) laminated glass
Fan light, aluminum door grill (powder coated)
& kick plate, fire rated Sqm 3

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-21 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

k) Type-D15
including 12mm thick (6+6) laminated glass
Fan light, fire rated Sqm 10

Unit Rate in words …………………………………..

02-61C Door Type: 45mm thick single leaf, single swing,


mineral core door both side plastic laminated with
teakwood lipping finished, all around wooden flush
door in lacquered finish with hardware set (as per
schedule), including fixing and fixing accessories
etc; of the following design types; complete in all
respect as shown on the drawing and
specification.

a) Type-D8
including 12mm thick (6+6) laminated glass
Fan light, aluminum door grill (powder coated)
& kick plate, fire rated Sqm 90

Unit Rate in words …………………………………..

b) Type-D14
including aluminum door grill (powder coated)
& kick plate, fire rated Sqm 5

Unit Rate in words …………………………………..

02-62C Door Type D17: 45mm thick single leaf, single


swing, solid core door (fire rated) filled with rough
wood, both side plastic laminated with teakwood
lipping all around, wooden panel door including
wooden louver panel in lacquered finish, kick plate
with hardware set (as per schedule), including
fixing and fixing accessories etc; of the following
design types; complete in all respect as shown on
the drawing and specification. Sqm 40

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-22 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-63C Wooden Cabinets (Floor Mounted) in Kitchen/


Pantry: Providing and fixing kitchen wooden
cabinets of approved design comprising wooden
framing and laminated sheet shutter and provision
of light fixture (where required) with compatible
hardware set (as per schedule) including 18mm
thick marble top with bull nose edge, concrete
slabs, plaster, deodar wood lipping, terrazzo floor
finish and specified finishes on wooden surfaces/
panels and fittings/ all accessories etc; complete
in all respect as shown on the drawing and
specification and as directed by the Engineer.
Rm 70

Unit Rate in words …………………………………..

02-64C Wooden Cabinets (Wall Mounted) in Kitchen/


Pantry: Providing and fixing kitchen wooden
cabinets of approved design comprising wooden
framing and laminated sheet and provision of light
fixture (where required) with compatible hardware
set (as per schedule) including deodar wood
frame, deodar wood lipping and specified finishes
on wooden surfaces/ panels and fittings/ all
accessories etc; complete in all respect as shown
on the drawing and specification and as directed
by the Engineer. Rm 70

Unit Rate in words …………………………………..

02-65C Wooden pelmet of first class teak wood as per


design in white oil paint finish etc. complete in all
respects, as approved by the Engineer and as
shown on the drawing and specification. Rm 85

Unit Rate in words …………………………………..

02-66C Providing, fabrication and installation of floor


mounted hardwood handrail with teakwood top
hand rail in lacquer finish, hard wood caping,
middle panel are in 15mm thick tempered glass,
wooden balustrades, steel channel painted black
(matt finish), rubber packing including embedding,
embedding parts, fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and specification. Rm 250

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-23 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-67C Wall type W08: 75mm thick Partition Wall for


offices comprising of wooden framing, cladding
with 12mm thick high density fiber board, both
sides plastic laminated with machine press and
teak wood lipping all around, 150mm high skirting
& 75x75mm cladding corner studs of teak wood as
per detail complete with doors and hardwares etc;
complete in all respect as shown on the drawing &
specification. Sqm 750

Unit Rate in words …………………………………..

02-68C Wall Type W11 & Door Type D1: Cubical Wall &
Door in 12mm thick CDF-Compact density fiber
board with (density 1000Kg/m3) both sides
melamine laminated coating, scratch resistance,
splash water resistance and flame retardancy (fire
resistant) for cubical complete with compatible
hardware set of (SS 304 grade) etc; complete in all
respect as shown on the drawing & specification
and as directed by the Engineer. Sqm 1,230

Unit Rate in words …………………………………..

02-69C Wall type W15: Wooden cladding of 20mm thick


MDF board plastic laminated sheet machine
pressed with teak wood veneer / lipping all around
in lacquered finish etc; complete in all respect as
shown on the drawing & specification. Sqm 385

Unit Rate in words …………………………………..

02-70C Providing and fixing of wooden Bumper Rail with


teakwood in lacquered finish as per design
including fixing accessories etc; complete in all
respects as shown on the drawing and
specifications. Rm 110

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-24 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-71C Staircase Type 1 (Stair N2)


Staircase Type 2 (Stair N4)
Staircase Type 3 (Stair N3)
Providing, fabrication and installation of floor
mounted hardwood handrail with teakwood top
hand rail in lacquer finish, middle panel are in
15mm thick tempered glass, stainless steel tube
balusters, aluminum channel, rubber packing
including embedding, embedding parts, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing and specification. Rm 136

Unit Rate in words …………………………………..

02-72C Staircase Type 1 (Stair N2)


Providing, fabrication and installation of floor
mounted hardwood handrail with teakwood top
hand rail in lacquer finish, middle panel are in
teakwood panels (lacquered polish), stainless
steel bar balusters & cap, plywood backing
including embedding, embedding parts, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing and specification. Rm 25

Unit Rate in words …………………………………..

02-73C Staircase Type 1 (Stair N2)


Providing, fabrication and installation of wall
mounted hardwood handrail with teakwood hand
rail in lacquer finish, stainless steel wall bracket,
including embedding, embedding parts, fixing and
fixing accessories etc; complete in all respect as
shown on the drawing and specification. Rm 20

Unit Rate in words …………………………………..

02-74C Wooden decorative gola in teakwood with


lacquered finish in appropriate size & detail as per
design etc; complete in all respect as shown on
the drawing and specification. Rm 100

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-25 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

ALUMINIUM WORKS
Ref. Sec.No. 6220, 6250

02-75C Door Type: 12mm thick (6+6mm) laminated


tinted/ clear glass, sliding/ double pivoted door on
powder coated heavy duty aluminum frame with
compatible hardware set (as per schedule)
including fixing and fixing accessories etc. of the
following design types; complete in all respect as
shown on the drawing and specification:

a) Type-GD1
lockable from inside Sqm 65

Unit Rate in words …………………………………..

b) Type-GD2
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 5

Unit Rate in words …………………………………..

c) Type-GD3
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 10

Unit Rate in words …………………………………..

d) Type-GD4
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 53

Unit Rate in words …………………………………..

e) Type-GD5
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 20

Unit Rate in words …………………………………..

f) Type-GD7
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 14

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-26 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

g) Type-GD8
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 85

Unit Rate in words …………………………………..

h) Type-GD9
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 82

Unit Rate in words …………………………………..

i) Type-GD10
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 3

Unit Rate in words …………………………………..

j) Type-GD11
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 22

Unit Rate in words …………………………………..

k) Type-GD12
lockable from inside
including 200mm wide push plate inside, door
handle outside & door closer Sqm 19

Unit Rate in words …………………………………..

02-76C Door Type: 30mm double glazed insulated curtain


wall door in 12mm thick (6+6mm) inner clear
laminated glass + 12mm air gap + 6mm anti sun
glass (tinted) pivoted door on powder coated
heavy duty aluminum frame with compatible
hardware set (as per schedule) including fixing
and fixing accessories etc. of the following design
types; complete in all respect as shown on the
drawing and specification:

a) Type-GD6
including 200mm wide push plate inside, door
handle outside & door closer Sqm 13

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-27 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Type-GD13
including 200mm wide push plate inside, door
handle outside & door closer Sqm 5

Unit Rate in words …………………………………..

02-77C Door Type: Fully louver door, double leaf, single


swing on powder coated heavy duty aluminum
frame, lockable from outside with flush bolt, door
handle out side & compatible hardware set (as per
schedule) including fixing and fixing accessories
etc. of the following design types; complete in all
respect as shown on the drawing and
specification:

a) Type-ALD1
fire rated Sqm 6

Unit Rate in words …………………………………..

b) Type-ALD2
fire rated Sqm 8

Unit Rate in words …………………………………..

c) Type-ALD3
fire rated Sqm 9

Unit Rate in words …………………………………..

02-78C Window Type: 12mm thick (6+6mm) laminated


tinted/ clear glass on powder coated heavy duty
aluminum frame set in epoxy painted MS support
structure with compatible hardware set (as per
schedule) including fixing and fixing accessories
etc. of the following design types; complete in all
respect as shown on the drawing and
specification:

a) Type-xALS1
including teakwood lattice screen in polish finish Sqm 81

Unit Rate in words …………………………………..

b) Type-xALS2 Sqm 44

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-28 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

c) Type-xALS3 Sqm 14

Unit Rate in words …………………………………..

d) Type-xALS4
including teakwood lattice screen in polish finish Sqm 175

Unit Rate in words …………………………………..

e) Type-xALS5 Sqm 22

Unit Rate in words …………………………………..

f) Type-xALS6
including teakwood lattice screen in polish finish Sqm 22

Unit Rate in words …………………………………..

g) Type-xALS7
including teakwood lattice screen in polish finish Sqm 100

Unit Rate in words …………………………………..

h) Type-xALS8 Sqm 88

Unit Rate in words …………………………………..

i) Type-xALS9 Sqm 20

Unit Rate in words …………………………………..

j) Typex-ALS10 Sqm 86

Unit Rate in words …………………………………..

k) Type-xALS11 Sqm 15

Unit Rate in words …………………………………..

l) Type-xALS12
including teakwood lattice screen in polish finish Sqm 87

Unit Rate in words …………………………………..

m) Type-xALS13
including teakwood lattice screen in polish finish Sqm 66

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-29 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

n) Type-xALS14 Sqm 116

Unit Rate in words …………………………………..

o) Type-xALS15 Sqm 83

Unit Rate in words …………………………………..

p) Type-xALS16 Sqm 76

Unit Rate in words …………………………………..

q) Type-xALS17 Sqm 187

Unit Rate in words …………………………………..

r) Type-xALS18
including teakwood lattice screen in polish finish Sqm 26

Unit Rate in words …………………………………..

s) Type-xALS19
including teakwood lattice screen in polish finish Sqm 50

Unit Rate in words …………………………………..

t) Type-xALS20
including teakwood lattice screen in polish finish Sqm 12

Unit Rate in words …………………………………..

u) Type-xALS21
including teakwood lattice screen in polish finish Sqm 91

Unit Rate in words …………………………………..

v) Type-xALS22
including teakwood lattice screen in polish finish Sqm 17

Unit Rate in words …………………………………..

w) Type-xALS23 Sqm 33

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-30 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

x) Type-xALS24 Sqm 16

Unit Rate in words …………………………………..

y) Type-xALS25
including teakwood lattice screen in polish finish Sqm 55

Unit Rate in words …………………………………..

z) Type-xALS26 Sqm 40

Unit Rate in words …………………………………..

a1) Type-xALS27 Sqm 8

Unit Rate in words …………………………………..

b1) Type-xALS28 Sqm 53

Unit Rate in words …………………………………..

c1) Type-xALS29 Sqm 30

Unit Rate in words …………………………………..

d1) Type-xALS30 Sqm 7

Unit Rate in words …………………………………..

e1) Type-xALS31
including teakwood lattice screen in polish finish Sqm 26

Unit Rate in words …………………………………..

f1) Type-xALS32
including teakwood lattice screen in polish finish Sqm 38

Unit Rate in words …………………………………..

g1) Type-xALS33
including teakwood lattice screen in polish finish Sqm 50

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-31 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

h1) Type-xALS34 Sqm 10

Unit Rate in words …………………………………..

i1) Type-xALS35
including teakwood lattice screen in polish finish Sqm 48

Unit Rate in words …………………………………..

j1) Type-xALS36
including PVC coated/ aluminum rolling shutter
screen as per manufacturer's recommendation &
counter glass optionally cut/slice as per
commercial requirement Sqm 200

Unit Rate in words …………………………………..

k1) Type-xALS37
including PVC coated/ aluminum rolling shutter
screen as per manufacturer's recommendation &
counter glass optionally cut/slice as per
commercial requirement Sqm 6

Unit Rate in words …………………………………..

l1) Type-xALS38
including teakwood lattice screen in polish finish Sqm 170

Unit Rate in words …………………………………..

m1) Type-xALS39 Sqm 9

Unit Rate in words …………………………………..

n1) Type-xALS40
including teakwood lattice screen in polish finish Sqm 98

Unit Rate in words …………………………………..

o1) Type-xALS41
including teakwood lattice screen in polish finish Sqm 48

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-32 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

p1) Type-xALS42
including PVC coated/ aluminum rolling shutter
screen as per manufacturer's recommendation Sqm 20

Unit Rate in words …………………………………..

q1) Type-xALS43
including PVC coated/ aluminum rolling shutter
screen as per manufacturer's recommendation Sqm 22

Unit Rate in words …………………………………..

r1) Type-xALS44
including teakwood lattice screen in polish finish Sqm 28

Unit Rate in words …………………………………..

s1) Type-xALS45 Sqm 73

Unit Rate in words …………………………………..

t1) Type-xALS46
including teakwood lattice screen in polish finish Sqm 64

Unit Rate in words …………………………………..

u1) Type-xALS47
including teakwood lattice screen in polish finish Sqm 13

Unit Rate in words …………………………………..

v1) Type-xALS48 Sqm 31

Unit Rate in words …………………………………..

w1) Type-xALS49 Sqm 38

Unit Rate in words …………………………………..

x1) Type-xALS50 Sqm 140

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-33 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

y1) Type-xALS51 Sqm 10

Unit Rate in words …………………………………..

z1) Type-xALS52
including teakwood lattice screen in polish finish Sqm 175

Unit Rate in words …………………………………..

a2) Type-xALS53 Sqm 40

Unit Rate in words …………………………………..

b2) Type-xALS54 Sqm 45

Unit Rate in words …………………………………..

c2) Type-xALS55 Sqm 33

Unit Rate in words …………………………………..

c2) Type-xALS56 Sqm 20

Unit Rate in words …………………………………..

d2) Type-xALS57 Sqm 6

Unit Rate in words …………………………………..

e2) Type-xALS58 Sqm 25

Unit Rate in words …………………………………..

f2) Type-xALS59 Sqm 146

Unit Rate in words …………………………………..

g2) Type-xALS60 Sqm 82

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-34 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

h2) Type-xALS61 Sqm 42

Unit Rate in words …………………………………..

i2) Type-xALS62 Sqm 31

Unit Rate in words …………………………………..

j2) Type-xALS63 Sqm 14

Unit Rate in words …………………………………..

k2) Type-xALS64 Sqm 17

Unit Rate in words …………………………………..

02-79C Window Type xALW1: 30mm thick double glazed


insulated sliding window with 12mm thick (6+6mm)
inner clear laminated glass +12mm air gap, +6mm
anti sun glass tinted on powder coated heavy duty
aluminum framing & support system (as required
by design/calculations with compatible hardware
set (as per schedule) including fixing and fixing
accessories etc. complete in all respect as shown
on the drawing and specification.
Sqm 8

Unit Rate in words …………………………………..

02-80C Window Type: 30mm thick double glazed


insulated curtain wall with 12mm thick (6+6mm)
inner clear laminated glass +12mm air gap, +6mm
anti sun glass tinted on powder coated heavy duty
aluminum framing & support system as required
by design/calculations with compatible hardware
set (as per schedule) including fixing and fixing
accessories etc. of the following design types;
complete in all respect as shown on the drawing
and specification.

a) Type-xCW2 Sqm 34

Unit Rate in words …………………………………..

b) Type-xCW3 Sqm 29

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-35 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

c) Type-xCW4 Sqm 62

Unit Rate in words …………………………………..

d) Type-xCW5 Sqm 73

Unit Rate in words …………………………………..

e) Type-xCW6 Sqm 57

Unit Rate in words …………………………………..

f) Type-xCW7
with smoke outlet Sqm 191

Unit Rate in words …………………………………..

g) Type-xCW8
with smoke outlet Sqm 64

Unit Rate in words …………………………………..

h) Type-xCW9
with smoke outlet Sqm 12

Unit Rate in words …………………………………..

i) Type-xCW10 Sqm 4

Unit Rate in words …………………………………..

j) Type-xCW11 Sqm 4

Unit Rate in words …………………………………..

k) Type-xCW12 Sqm 2

Unit Rate in words …………………………………..

l) Type-xCW13 Sqm 4

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-36 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

m) Type-xCW14 Sqm 28

Unit Rate in words …………………………………..

n) Type-xCW15 Sqm 30

Unit Rate in words …………………………………..

o) Type-xCW16 Sqm 45

Unit Rate in words …………………………………..

p) Type-xCW17 Sqm 25

Unit Rate in words …………………………………..

02-81C Window Type xALG1: 12mm thick (6+6mm) clear


laminated glass on powder coated heavy duty
aluminum frame with compatible hardware set (as
per schedule) including 10mm thick MS square
bar grill, fixing and fixing accessories etc. of the
following design types; complete in all respect as
shown on the drawing and specification.
Sqm 3

Unit Rate in words …………………………………..

02-82C Window Type: 30mm thick double glazed


insulated window with 12mm thick (6+6mm) inner
clear laminated glass +12mm air gap, +6mm anti
sun glass tinted on powder coated heavy duty
aluminum framing & support system as required
by design/calculations with compatible hardware
set (as per schedule) including fixing and fixing
accessories etc. of the following design types;
complete in all respect as shown on the drawing
and specification.

a) Type-xALF1 Sqm 9

Unit Rate in words …………………………………..

b) Type-xALF2 Sqm 5

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-37 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-83C Wall type W10: Powder coated heavy duty


aluminum frame with glazing/screen/partition
including all accessories etc complete in all
respect as shown on the drawing and
specification. Sqm 250

Unit Rate in words …………………………………..

ALUMINUM COMPOSITE PANELS


Ref. Sec.No. 6230

02-84C Aluminum Composite Panels Cladding with


mounting system including anchorage, shims,
fasteners, gaskets, sealants, fixing and fixing
accessories etc. complete in all respects as per
manufacturer's recommendations and as shown
on the drawing and specification. Sqm 100

Unit Rate in words …………………………………..

02-85C Composite Aluminum Jali Panels in approved


colour/ texture/ finish with mounting system as per
design including fixing and fixing accessories etc.
complete in all respects as per manufacturer's
recommendations and as shown on the drawing
and specification. Sqm 10

Unit Rate in words …………………………………..

POLYCARBONATE SHEET
Ref. Sec.No. 6240

02-86C 8mm thick Poly-Carbonate EGG crate sheet


covering as per design including fixing and fixing
accessories etc. complete in all respects as per
manufacturer's recommendations and as shown
on the drawing and specification. (Excluding steel
structure) Sqm 370

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-38 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

WATER PROOFING AND BUILT-UP ROOFING


Ref. Sec.No. 6411

02-87C Two coats of hot bitumen grade 10/20 applied @


1 Kg./sq.m. per coat to all structural concrete
surfaces in contact with earth etc complete in all
respect as shown on the drawings. Sqm 29,550

Unit Rate in words …………………………………..

02-88C Water proofing and built-up roofing of the following


types over roof slab etc; complete in all respect as
shown on the drawing and specification:

a) Type-R1 Sqm 12,035

Unit Rate in words …………………………………..

b) Type-R2 Sqm 4,015

Unit Rate in words …………………………………..

CEMENT PLASTER
Ref. Sec.No. 6521

02-89C 12mm thick cement sand plaster to specified


interior surfaces etc complete in all respect as
shown on the drawings. Sqm 75,000

Unit Rate in words …………………………………..

02-90C 20mm thick cement sand plaster to specified


exterior surfaces etc complete in all respect as
shown on the drawings. Sqm 7,500

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-39 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

FLOOR AND WALL FINISHES


Ref. Sec.No. 6600

02-91C Floor type F02: 600x600x8mm thick fully vitrified


glazed porcelain tile flooring in approved
color/shade and texture conforming to ISO 13006
Bla requirements etc, laid in combination of
rectilinear/ diagonal pattern filled with matching
grout, provide thermal expansion 8mm thick PVC
divider strip in 6mm gap at a distance of 6000mm
from c/c in both directions, set in specified cement
sand mortar including 50mm thick Class 'C'
concrete screed, cement mortar with approved
adhesive admixture, 20mm thick 1:3 dry cement
mortar binding course and dry cement spread &
splash of water etc.; complete in all respects as
shown on the drawing & specification. Sqm 5,990

Unit Rate in words …………………………………..

02-92C Floor type F03: 300x300x8mm fully vitrified semi


glazed porcelain tile flooring in approved
color/shade and texture conforming to ISO 13006
Bla requirements, laid in specified pattern filled
with water tight matching grout; set in specified
cement sand mortar including water barrier course
of approved liquid proofing (application as per
manufacturer's recommendation), 45mm thick
Class 'C' concrete screed, cement mortar with
approved adhesive admixture, 20mm thick 1:3 dry
cement mortar binding course, dry cement spread
& splash of water etc.; complete in all respects as
shown on the drawing & specification. Sqm 1,638

Unit Rate in words …………………………………..

02-93C Floor type F04: 450x450x10mm heavy duty acid


resistant ceramic tile flooring in approved
color/shade and texture, laid in specified pattern
filled with acid resistant grout; set in specified
cement sand mortar including thermal expansion
joint, 50mm thick Class 'C' concrete screed,
cement mortar with approved adhesive admixture,
20mm thick 1:3 dry cement mortar binding course
and dry cement spread & splash of water etc.;
complete in all respects as shown on the drawing
& specification. Sqm 653

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-40 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-94C Floor type F05: Wall to wall broadloom carpet


flooring in approved color/ shade & texture, laid on
finished floor forming row (suff) for prayers
including carpet tacking device etc.; complete in all
respects as shown on the drawing & specification.
Sqm 141

Unit Rate in words …………………………………..

02-95C Floor type F06: 600x190x12mm interlocking


laminated wooden strips flooring in approved color
shade, texture in specified pattern; including 6mm
foam pad, water barrier course of approved liquid
proofing (application as per manufacturer's
recommendations), Class 'C' concrete screed,
1mm thick plastic barrier etc.; complete in all
respects as shown on the drawing & specification.
Sqm 53

Unit Rate in words …………………………………..

02-96C Floor type F07: 80mm thick heavy duty smooth


cemented screed floor comprising top surface
floor 2mm thick self leveling, solvent free, epoxy
overlay topping of approved quality laid as per
specification & manufacturer's recommendations
etc.; including cement mortar with approved
adhesive admixture,Class 'C' concrete screed with
10mm dia 200x200 wire mesh, cement mortar with
approved adhesive, joints etc; complete in all
respect as shown on the drawing & specification.
Sqm 3,015

Unit Rate in words …………………………………………………………………………

02-97C Floor type F08: 80mm thick Class 'C' cement


concrete screed (Full Body) with hardener
compound laid in panels not more than
2400x2400mm in steel troweled finish and
separated by glass divider strip etc; complete in all
respect as shown on the drawing & specification.
Sqm 1,240

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-41 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-98C Floor type F09: 80mm thick Class 'C' cement


concrete screed (Full Body) laid in panels not
more than 2400x2400mm in steel troweled finish
and separated by glass divider strip etc.; complete
in all respects as shown on the drawing &
specification. Sqm 62

Unit Rate in words …………………………………..

02-99C Floor type F10: 2mm thick PVC flooring with


rubberized underlay & 4mm thick pvc lining strip,
laid in specified pattern etc.; including cement
mortar with approved adhesive admixture, Class
'C' concrete screed etc.; complete in all respects
as shown on the drawing & specification. Sqm 246

Unit Rate in words …………………………………..

02-100C Floor type F11: 2mm thick anti-static heavy duty


PVC tile flooring with rubberized underlay laid in
specified pattern gaps filled with grout as per
manufacturer's recommendations including
cement mortar with approved adhesive admixture,
Class 'C' concrete screed etc.; complete in all
respects as shown on the drawing & specification.
Sqm 280

Unit Rate in words …………………………………..

02-101C Floor type F12: 600x600x10mm Heavy duty


carpet tile flooring in approved color shade, texture
and design with rubberized under lay over
cemented floor, gaps filled with grout as per
manufacturer's recommendations including Class
'C' concrete screed, cement mortar with approved
adhesive admixture, 20mm thick 1:3 dry cement
mortar binding course and dry cement spread &
splash of water and carpet tacking device etc.;
complete in all respects as shown on the drawing
& specification. Sqm 82

Unit Rate in words …………………………………..

02-102C 100mm thick Class 'D' cement concrete sub-floor/


bed etc.; complete in all respects as shown on the
drawing & specification. Sqm 17,227

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-42 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-103C 100mm thick Class 'C' cement concrete sub-


floor/ bed etc.; complete in all respects as shown
on the drawing & specification. Sqm 653

Unit Rate in words …………………………………..

02-104C Skirting type SK02: 8mm thick porcelain tile


skirting same as floor tiles in approved size,
color/shade and texture, confirming to ISO 13006
Bla requirements set in specified cement sand
mortar including rough base plaster etc.; complete
in all respects as shown on the drawing &
specification. Sqm 600

Unit Rate in words …………………………………..

02-105C Skirting type SK03: 10mm thick acid proof


ceramic tile skirting in approved size, color/shade
and texture set in specified cement sand mortar
including rough base plaster etc.; complete in all
respects as shown on the drawing & specification. Sqm 65

Unit Rate in words …………………………………..

02-106C Skirting type SK04: 20mm thick teakwood


skirting in lacquered polished finish in approved
size, color/shade and texture etc.; complete in all
respects as shown on the drawing & specification. Sqm 600

Unit Rate in words …………………………………..

02-107C Skirting type SK05: 13mm thick cemented


skirting in approved size/ panels, color/ shade and
texture including rough base plaster etc.; complete
in all respects as shown on the drawing & Sqm 305

Unit Rate in words …………………………………..

02-108C Skirting type SK06: 100mm high PVC tile skirting


in approved size/ panels, color/ shade and texture
including wooden base etc.; complete in all
respects as shown on the drawing & specification. Sqm 30

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-43 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-109C Skirting type SK08: Epoxy skirting including


epoxy coating, 13mm thick cemented skirting in
approved size/ panels, color/ shade and texture &
base plaster etc.; complete in all respects as
shown on the drawing & specification. Sqm 300

Unit Rate in words …………………………………..

02-110C Staircase Type 5 (Stair N8, N9, N10) &


Staircase Type 6 (Stair N7)
50mm thick fairfaced precast pigmented concrete
steps including c.c mortar in tread & riser etc.;
complete in all respects as shown on the drawing
and specification. Sqm 118

Unit Rate in words …………………………………..

02-111C Wall type W03: 300x300x8mm fully vitrified


glazed porcelain tile on wall in approved color/
shade and texture, confirming to ISO 13006 Bla
requirements laid in specified pattern filled with
impervious grout, set in specified cement sand
mortar including base plaster etc; complete in all
respect as shown on the drawing & specification. Sqm 2,500

Unit Rate in words …………………………………..

02-112C Wall type W04: 300x600x8mm fully vitrified


glazed porcelain tile on wall in approved color/
shade and texture, confirming to ISO 13006 Bla
requirements laid in specified pattern filled with
impervious grout, set in specified cement sand
mortar including base plaster etc; complete in all
respect as shown on the drawing & specification. Sqm 3,275

Unit Rate in words …………………………………..

02-113C Wall type W05: 150x600x8mm fully vitrified


glazed porcelain tile on wall in approved color/
shade and texture, confirming to ISO 13006 Bla
requirements laid in specified pattern filled with
impervious grout, set in specified cement sand
mortar including base plaster etc; complete in all
respect as shown on the drawing & specification. Sqm 2,100

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-44 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-114C Wall type W06: Combination of pattern consisting


of :
Main Wall: 300x300x8mm thick fully vitrified
glazed porcelain tiles on wall in approved
color/shade and texture conforming to ISO 13006
Bla requirements etc, laid in specified pattern
filled with water tight grout;
Wall Border: 150x150x8mm thick fully vitrified
glazed porcelain tiles on wall in approved
color/shade and texture conforming to ISO 13006
Bla requirements etc, laid in specified pattern
filled with water tight grout;
set in specified cement sand mortar including base
plaster etc; complete in all respect as shown on
the drawing & specification. Sqm 400

Unit Rate in words …………………………………..

02-115C Wall type W13: 450x450mm acid resistant heavy


duty ceramic tile on wall in approved color/ shade
and texture laid in specified pattern filled with acid
resistant grout, set in specified cement sand
mortar including base plaster etc; complete in all
respect as shown on the drawing & specification.
Sqm 250

Unit Rate in words …………………………………..

02-116C Wall type W14: Precast pigmented Terrazzo


panel over specified surfaces on wall in approved
size, color/ shade and texture laid in specified
pattern including stainless steel anchor & counter
sunk expansion bolts, base plaster & fixing
accessories etc; complete in all respect as shown
on the drawing & specification. Sqm 1,250

Unit Rate in words …………………………………..

02-117C Ramp Finishes: Anti slip broom texture finish cc


floor on ramp with grooves etc; complete in all
respect as shown on the drawing & specification. Sqm 265

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-45 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-118C Precast pigmented Terrazzo moulding panel over


specified surfaces in approved size, color/ shade
and texture laid in specified pattern including base
plaster & fixing accessories etc; complete in all
respect as shown on the drawing & specification. Rm 175

Unit Rate in words …………………………………..

02-119C Glazed ceramic tiles on wall in approved color/


shade and texture laid in specified pattern filled
with matching grout, set in specified cement sand
mortar including base plaster etc; complete in all
respect as shown on the drawing & specification. Sqm 350

Unit Rate in words …………………………………..

MARBLE WORKS
Ref. Sec.No. 6531

02-120C 20mm thick prepolished marble sill of specified


size, colour and quality laid in approved pattern
filled with grouting compound, set in specified
cement sand mortar including cement concrete
screed etc. complete in all respects as shown on
the drawing & specifications. Sqm 20

Unit Rate in words …………………………………..

02-121C Marble moulding over specified surfaces in


approved size, color/ shade and texture, laid in
specified pattern filled with matching grout, set in
specified cement sand mortar including base
plaster etc; complete in all respect as shown on
the drawing & specification.

a) Moulding of size 65x50mm Rm 575

Unit Rate in words …………………………………..

b) Moulding of size 200x100mm Rm 385

Unit Rate in words …………………………………..

c) Moulding of size 50x50mm Rm 225

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-46 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

d) Moulding of size 100x80mm Rm 350

Unit Rate in words …………………………………..

e) Moulding 30mm thick Rm 25

Unit Rate in words …………………………………..

f) Moulding of size 100x110mm Rm 20

Unit Rate in words …………………………………..

02-122C Marble trim over specified surfaces in approved


size, color/ shade and texture laid in specified
pattern including base plaster etc; complete in all
respect as shown on the drawing & specification. Rm 625

Unit Rate in words …………………………………..

02-123C Wall type W02: 30mm thick marble tile cladding


chemically polished in approved color/ shade and
texture, laid in specified pattern filled with matching
grout, set in specified cement sand mortar
including base plaster and metal clamping system
to wall etc.; complete in all respects as shown on
the drawing & specification. Sqm 4,355

Unit Rate in words …………………………………..

02-124C 15mm thick marble tile cladding chemically


polished fixed with marble panel in approved color/
shade and texture, laid in specified pattern filled
with matching grout, set in specified cement sand
mortar including base plaster and metal clamping
system to wall etc.; complete in all respects as
shown on the drawing & specification.
Sqm 50

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-47 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-125C Staircase Type 2 (Stair N1)


30mm thick stair balustrade marble caping,
chemically polished in approved size, color/shade
and texture, set in specified cement sand mortar
including 15x15mm chamfering, 20x5mm groove
& cement concrete screed etc.; complete in all
respects as shown on the drawing & specification.
Sqm 60

Unit Rate in words …………………………………..

02-126C Prepolished marble/ stone threshold of specified


size, color and quality including bullnozing (where
required), c.c base, fixing and fixing accessories
etc. of the following types; complete in all respect
as shown on the drawing and specification.

a) Type-03: Marble Saddle/ Threshold


with 9x50mm aluminum strip Sqm 10

Unit Rate in words …………………………………..

b) Type-05: Stone Saddle/ Threshold


with 50x10mm SSTL divider Sqm 35

Unit Rate in words …………………………………..

c) Type-06: Marble Saddle/ Threshold


with waterproofing membrane Sqm 25

Unit Rate in words …………………………………..

d) Type-10: Marble Saddle/ Threshold


with 9x50mm aluminum strip Sqm 15

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-48 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

GRANITE WORKS
Ref. Sec.No. 6532

02-127C Floor type F01: 20mm thick granite tile flooring,


chemical polished in approved color/ shade and
texture, laid in rectilinear and diagonal pattern
arrangement in one or more basic color, with linear
band/ borders in different color pieces cut to
different shapes, 6mm brass/ stainless steel or
8mm thick PVC divider strip including construction
joints as detailed, filled with grouting compound,
set in specified cement sand mortar including
40mm thick Class 'C' concrete screed, 200x200
wire mesh, cement mortar with approved adhesive
admixture, 20mm thick 1:3 dry cement mortar
binding course and dry cement spread & splash of
water etc.; complete in all respects as shown on
the drawing & specification.
Sqm 23,110

Unit Rate in words …………………………………..

02-128C Skirting type SK01: 10mm thick granite skirting,


chemical polished in approved size, color/shade
and texture, set in specified cement sand mortar
including 20mm thick c.c base mortar etc.;
complete in all respects as shown on the drawing
& specification. Sqm 2,315

Unit Rate in words …………………………………..

02-129C Wall type W01: 30mm thick granite tile cladding


chemically polished in approved color/ shade and
texture, laid in specified pattern filled with matching
grout, fixed with specified cement sand mortar and
metal clamping system to wall including base
plaster etc.; complete in all respects as shown on
the drawing & specification.
Sqm 5,435

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-49 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-130C 20mm thick granite tile cladding/ fascia chemically


polished in approved color/ shade and texture,
laid in specified pattern filled with matching grout,
fixed with specified cement sand mortar and metal
clamping system to wall including base plaster
etc.; complete in all respects as shown on the
drawing & specification.
Sqm 50

Unit Rate in words …………………………………..

02-131C Prepolished Granite vanity top to specified


surfaces comprising 30mm thick granite top slab,
20mm thick apron and back splash of approved
size, color and quality including fixing and fixing
accessories etc; complete in all respect as shown
on the drawing and specification and as directed
by the Engineer. Rm 155

Unit Rate in words …………………………………..

02-132C Staircase Type 1 (Stair N2)


Staircase Type 2 (Stair N1, N4)
Staircase Type 3 (Stair N3)
Staircase Type 4 (Stair N5, N6)
20mm thick granite skirting, chemical polished in
approved size, color/shade and texture, set in
specified cement sand mortar including rough
base plaster etc.; complete in all respects as
shown on the drawing & specification. Sqm 50

Unit Rate in words …………………………………..

02-133C Staircase Type 1 (Stair N2)


Staircase Type 2 (Stair N1, N4)
Staircase Type 3 (Stair N3)
Staircase Type 4 (Stair N5, N6)
20mm thick prepolished granite on treads, risers
and landing of specified size, colour and quality
laid in approved pattern filled with grouting
compound, set in specified cement sand mortar
including cement concrete screed etc. complete in
all respects as shown on the drawing &
specifications. Sqm 417

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-50 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-134C Staircase Type 1 (Stair N2)


Staircase Type 2 (Stair N4)
Staircase Type 3 (Stair N3)
20mm thick prepolished granite sill of specified
size, colour and quality laid in approved pattern
filled with grouting compound, set in specified
cement sand mortar including cement concrete
screed etc. complete in all respects as shown on
the drawing & specifications. Sqm 50

Unit Rate in words …………………………………..

TEXTURED / GRAFFITO WALL COATING


Ref. Sec.No. 6701

02-135C Wall type W07: Texture coating over cc plaster/


cement fiber board over specified surfaces etc;
complete in all respect as shown on the drawing &
specification. Sqm 8,150

Unit Rate in words …………………………………..

FALSE CEILING
Ref. Sec.No. 6560

02-136C False Ceiling Type C01: Perforated linear


aluminum strip ceiling placed at 55/155/255mm
wide c/c, but jointed backed enamel painted
suspended by 6mm dia. rigid threaded rods &
compatible suspension system with provision of
light fixtures, HVAC grills & other fixtures with
sound insulation on top etc; complete in all respect
as shown on the drawing and specification.
Sqm 9,100

Unit Rate in words …………………………………..

02-137C False Ceiling Type C02: 300mm wide perforated


linear aluminum strip ceiling @ 300mm wide c/c,
butt jointed, backed enamel painted suspended by
6mm dia. rigid threaded rods & compatible
suspension system with provision of light fixtures,
HVAC grills & other fixtures with sound insulation
on top etc; complete in all respect as shown on the
drawing and specification. Sqm 5,660

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-51 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-138C False Ceiling Type C03: Aluminum Baffle ceiling


including acoustic membrane, mineral wool
insulation, baffle perforation, extruded aluminum
intersection joints, clamps, plastic cover cap, clip
twist, hanger, hanger rod and all fixing accessories
etc.; complete in all respect as shown on the
drawing and specification. Sqm 2,890

Unit Rate in words …………………………………..

02-139C False Ceiling Type C04: 100mm wide linear non-


perforated aluminum strip ceiling @ 100mm c/c,
butt jointed, backed enamel painted suspended by
6mm dia. rigid threaded rods & compatible
suspension system with provision of light fixtures,
HVAC grills & other fixtures with sound insulation
on top etc; complete in all respect as shown on the
drawing and specification. Sqm 1,506

Unit Rate in words …………………………………..

02-140C False Ceiling Type C05: 600x600mm flat


aluminum tiles ceiling (1-hour fire-rated), with
closed groove joints, backed enamel painted
suspended by 6mm dia. rigid threaded rods &
compatible suspension system with provision of
light fixtures, HVAC grills & other fixtures with
sound insulation on top etc; complete in all respect
as shown on the drawing and specification.
Sqm 4,108

Unit Rate in words …………………………………..

02-141C False Ceiling Type C06: 200mm wide perforated


aluminum strip ceiling @ 200mm c/c, butt jointed,
backed enamel painted suspended by 6mm dia.
rigid threaded rods & compatible suspension
system with provision of light fixtures, HVAC grills
& other fixtures with sound insulation on top and
300x600mm aluminum tiles laid as border at
corridor wall etc; complete in all respect as shown
on the drawing and specification. Sqm 1,255

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-52 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-142C False Ceiling Type C07: 200mm wide non-


perforated aluminum strip ceiling @ 200mm c/c,
butt jointed, backed enamel painted suspended by
6mm dia. rigid threaded rods & compatible
suspension system with provision of light fixtures,
HVAC grills & other fixtures with sound insulation
on top and 300x600mm aluminum tiles laid as
border at corridor wall etc; complete in all respect
as shown on the drawing and specification. Sqm 520

Unit Rate in words …………………………………..

02-143C False Ceiling Type C09: Plastic emulsion painted


cement board ceiling as per design, band/border
bulkhead with polished wooden/metal edge trim
with compatible suspension support system and
provision of light fixtures & other fixtures etc;
complete in all respect as shown on the drawing
and specification. Sqm 4,625

Unit Rate in words …………………………………..

02-144C False Ceiling Type C11: Combination


Border: Painted cement board band/border with
polished wooden edge trim
Ceiling Deck: 50x150mm polished wooden rafter
with provision of LED lights (decorative) &
600x600x12mm thick gypsum board tile ceiling
(DFB manufacturer or equivalent), texture paint
finish on concealed T-grid profile & metal
suspension system including access panel, trims,
edge trims, shadow trims, expansion joints (where
required) etc; complete in all respect as shown on
the drawing and specification. Sqm 795

Unit Rate in words …………………………………..

02-145C False Ceiling Type C12: Suspended ceiling


having decorative geometric pattern in hardwood
polished, with 15mm thick gypsum board ceiling
panel (DFB manufacturer or equivalent),in paint/
texture paint finish on to concealed rigid metal
suspension system including access panel, trims,
edge trims, shadow trims, expansion joints (where
required) etc; complete in all respect as shown on
the drawing and specification. Sqm 50

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-53 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

02-146C False Ceiling Type C13: 4mm aluminum


composite panel (FR) ceiling/bulkhead on to
framing with compatible suspension system etc;
complete in all respect as shown on the drawing
and specification. Sqm 90

Unit Rate in words …………………………………..

GYPSUM BOARD
Ref. Sec.No. 6605

02-147C Providing and installation of decorative panel in


moulded gypsum board, paint (texture coating
match with existing parapet) of specified size on
GI frame including fixing and fixing accessories
etc. complete in all respect as shown on the
drawing & specification.
Sqm 850

Unit Rate in words …………………………………..

PAINTING
Ref. Sec.No. 6700

02-148C Plastic emulsion paint to specified surfaces


including wall sealer primer etc complete in all
respect as shown on the drawings. Sqm 68,705

Unit Rate in words …………………………………..

02-149C Weather resistant paint to specified exterior


surfaces etc complete in all respect as shown on
the drawings. Sqm 13,570

Unit Rate in words …………………………………..

02-150C Water repellent coating to specified exterior


surfaces etc. complete in all respect as shown on
the drawings. Sqm 1,255

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-54 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

SIGNOLOGY
NON ILLUMINATED SIGNS
Ref. Sec.No. 4960

02-151C Provide and installed typical door plates sign with


appropriate message as per design and drawing
including fixing and fixing accessories etc. of the
following design types; complete in all respect as
shown on the drawing and specification.

a) Type-T1 No 8

Unit Rate in words …………………………………..

b) Type-T2 No 11

Unit Rate in words …………………………………..

c) Type-T3 No 11

Unit Rate in words …………………………………..

d) Type-T4 No 10

Unit Rate in words …………………………………..

e) Type-T5 No 11

Unit Rate in words …………………………………..

f) Type-T6 No 10

Unit Rate in words …………………………………..

g) Type-T7 No 8

Unit Rate in words …………………………………..

h) Type-T8 No 9

Unit Rate in words …………………………………..

i) Type-T9 No 6

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-55 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

j) Type-T10 No 12

Unit Rate in words …………………………………..

k) Type-T1 No 9

Unit Rate in words …………………………………..

l) Type-T12 No 6

Unit Rate in words …………………………………..

m) Type-E No 4

Unit Rate in words …………………………………..

ILLUMINATED SIGNS
Ref. Sec.No. 4970

02-152C Provide and installed Illuminated signs as per


design and drawing with appropriate message
including fixing and fixing accessories etc. of the
following design types; complete in all respect as
shown on the drawings and specification. Sqm 385

Unit Rate in words …………………………………..

FURNITURE & COUNTERS


Ref. Sec.No. 4290

02-153C Following types of the furniture as per design and


as approved by the Engineer etc. complete in all
respects as shown on the drawings and
specifications:

a) Sitting arrangement with side tables.

I) Sofa Set with Centre Table

i) Single seater No. 74

Unit Rate in words …………………………………..

ii) Two seater No. 118

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-56 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

iii) Centre tables with sofa set No. 50

Unit Rate in words …………………………………..

II) Air Port Waiting Chairs with Side Tables

i) single seater with side Tables No. 5

Unit Rate in words …………………………………..

ii) Two seater with side Tables No. 21

Unit Rate in words …………………………………..

iii) Three seater with side Tables No. 20

Unit Rate in words …………………………………..

iv) Four seater with side Tables No. 149

Unit Rate in words …………………………………..

v) Five seater with side Tables No. 30

Unit Rate in words …………………………………..

vi) Six seater with side Tables No. 47

Unit Rate in words …………………………………..

vii) Two seater without side Tables No. 31

Unit Rate in words …………………………………..

viii) Three seater without side Tables No. 37

Unit Rate in words …………………………………..

ix) Four seater without side Tables No. 21

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-57 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

x) Seven seater with side Tables No. 17

Unit Rate in words …………………………………..

b) Stainless Steel Planter Boxes of following sizes:

(i) 450mm dia & 400-500mm high No. 96

Unit Rate in words …………………………………..

(ii) 600mm dia & 400-500mm high No. 164

Unit Rate in words …………………………………..

(iii) 1200mm dia & 600-900mm high No. 41

Unit Rate in words …………………………………..

c) Heavy duty Stainless Waste Disposal Bins with


sorting/ segregation arrangement and clean out
bucket. No. 50

Unit Rate in words …………………………………..

d) Heavy duty Stainless Steel Ash tray No. 57

Unit Rate in words …………………………………..

e) Counters with high adjustable chairs of


following types:

i) Check-in Counters No. 80

Unit Rate in words …………………………………..

ii) Passport Control Counter No. 35

Unit Rate in words …………………………………..

(iii) Immigration Counter No. 40

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-58 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

iv) Custom Counter No. 10

Unit Rate in words …………………………………..

v) Mishandled Baggage Counter No. 10

Unit Rate in words …………………………………..

vi) Information/ Facilitation Desk Counter No. 20

Unit Rate in words …………………………………..

vii) Operation Desk Counter No. 15

Unit Rate in words …………………………………..

viii) Gate Counter No. 10

Unit Rate in words …………………………………..

ix) CAA Facilitation Counter No. 5

Unit Rate in words …………………………………..

x) Search Booth Counter No. 10

Unit Rate in words …………………………………..

f) 4 seater Dining Table No. 75

Unit Rate in words …………………………………..

g) Mobile Phone Charging KIOSK No. 7

Unit Rate in words …………………………………..

h) Wall Mounted Telephone Hoods No. 7

Unit Rate in words …………………………………..

i) Stationary Recliner Chairs No. 25

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-59 August-2022
BILL OF QUANTITIES

CODE NO.02 - PASSENGER TERMINAL BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

j) Internet KIOSK No. 1

Unit Rate in words …………………………………..

k) Table lamp No. 45

Unit Rate in words …………………………………..

KEY CUTTING / DUPLICATING MACHINE

02-154C Supply, installation, testing, commissioning,


training of Employer's Staff and maintenance
during defect liability period of brand new imported
Key Cutting / Duplicating Machine of Western
Europe origin, complete in all respect as per
following specifications and requirements:

- Electronic Type Key Cutting / Duplicating


Machine with Microprocessor Control
- User Interface LCD (industrial color touch screen
type)
- For processing of edge and double edge cut keys

- Automatic Key Decoding and Cutting


- Illuminated Cutting Area
- Power Supply 220V 50Hz
- Provide multiple Jaws, Clamps, Cutters and other
accessories required to process the supplied key
types
- Provide key Blanks including 30 blanks for each
key type
- Provide Spare Cutters, decoder tracer,
consumables and other manufacturer's
recommended spare parts for two (2) years
operation
- Machine Model NINJA, manufactured by M/s
KEYLINE S.p.A, Italy or approved equivalent No. 1

Unit Rate in words …………………………………..

Total Cost of Code 02 (Civil Works) Carried


Over to Summary of Bid Price - C

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 02C-60 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

C. CIVIL WORKS

03-HVAC PLANT & SUB-STATION

EARTHWORKS
Ref. Sec.No. 1100

03-1C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 1,895

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 42

Unit Rate in words …………………………………..

03-2C Fill and backfill with selected material including


watering, compaction etc, complete in all respect
as shown on the drawing and specification.

a) Obtained from required excavation. Cum 1,555

Unit Rate in words …………………………………..

b) Obtained from outside source Cum 200

Unit Rate in words …………………………………..

STONE SOLING
Ref. Sec.No. 1330

03-3C 150mm thick crushed stone soling including


blinding material and compaction. Cum 1,308

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-1 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

TERMITE CONTROL TREATMENT


Ref.Spec. No.1600

03-4C Termite Control Treatment complete in all respect


as specified, as shown on drawings and approved
by the Engineer. Sqm 1,518

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

03-5C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and specification. tonne 241

Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

03-6C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer Cum 168

Unit Rate in words …………………………………..

03-7C Class 'D' plain concrete in situ using specified


cement complete in all respect as shown on the
drawing or as directed by the Engineer Cum 74

Unit Rate in words …………………………………..

03-8C Class 'C' concrete using specified cement in plinth


protection including bitumen seal with rubberized
material etc; complete in all respect as shown on
the drawing and specification. Cum 18

Unit Rate in words …………………………………..

03-9C Class 'B' reinforced concrete, using specified


cement in following sub-structural memebers etc,
complete in all respect as shown on the drawing
and specification.

a) Raft/Footing/Foundations Cum 275

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-2 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Columns upto plinth Cum 56

Unit Rate in words …………………………………..

d) Plinth beams Cum 124

Unit Rate in words …………………………………..

e) Bottom slab & Walls


OP - Oil Pit Cum 10

Unit Rate in words …………………………………..

f) Grade Slab
including expansion joint (Polyurethane sealant,
Bitumen impregnated soft board, Backer Rod)
etc.complete in all respect as shown on the
drawing and specification. Cum 195

Unit Rate in words …………………………………..

03-10C Class 'B' reinforced concrete, using specified


cement in following super-structural members etc,
complete in all respect as shown on the drawing
and as per specification.

a) Columns Cum 86

Unit Rate in words …………………………………..

b) Beams & lintels Cum 216

Unit Rate in words …………………………………..

c) Slab & Projection Cum 361

Unit Rate in words …………………………………..

d) Purdi Cum 33

Unit Rate in words …………………………………..

e) Stair Cum 6

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-3 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

f) Pad Cum 111

Unit Rate in words …………………………………..

03-11C Class 'B' reinforced concrete, using specified


cement in following structual memebers of
trenches etc, complete in all respect as shown on
the drawing and specification.

a) Bed/ Base Cum 54

Unit Rate in words …………………………………..

b) Walls Cum 77

Unit Rate in words …………………………………..

03-12C Class 'B' reinforced concrete, using specified


cement in following structures of rectangular floor
drain channel etc, complete in all respect as
shown on the drawing and specification.

a) Bed/ Base Cum 5

Unit Rate in words …………………………………..

b) Walls Cum 4

Unit Rate in words …………………………………..

03-13C Precast fair faced Class 'B' concrete using


specified cement in following structures, laid/ fixed
in specified cement sand mortar including fixing
and fixing accessories etc; complete in all respect
as shown on the drawing and specification.

a) Sills & Coping (pigmented) Cum 6

Unit Rate in words …………………………………..

b) Water Spout Cum 2

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-4 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

c) Planks with 20mm dia MS galvanized lifting Cum 3

Unit Rate in words …………………………………..

d) Type-1: Saddle/ Threshold


with 9x50mm aluminum strip Cum 2

Unit Rate in words …………………………………..

e) Type-4: Saddle/ Threshold


with metal flashing, 30x30 galvanized steel angle,
steel dowels, weather stripping & water proofing
membrane. Cum 1

Unit Rate in words …………………………………..

STRUCTURAL STEEL WORKS


Ref.Spec. No. 3000

03-14C Cable Tray Bridge: Providing, fabrication and


installation of PU painted Cable Tray Bridge
comprising MS pipe bluster & upper/mid rail, MS
tubular beam/framing, MS chequered plates (with
perforated holes including embedding, embedding
parts, fixing and fixing accessories etc; complete
in all respect as shown on the drawing and
specification. tonne 3.15

Unit Rate in words …………………………………..

MISCELLENEOUS STEEL
Ref. Sec.No. 3100,6700

03-15C Ladder: Providing, fabrication and installation of


epoxy painted MS Monkey ladder/ MS stair with
cage, including embedding, embedding parts,
fixing and fixing accessories etc; complete in all
respect as shown on the drawing and
specification. Kg 1,000

Unit Rate in words …………………………………..

03-16C Chequered Plates: Providing, fabrication and


installation of MS chequered including embedding
parts, fixing and fixing accessories etc; complete in
all respect as shown on the drawing, as per
specfications and as directed by the Engineer. tonne 8.10

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-5 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

03-17C Providing, fabrication and installation of MS Frame


etc. including metal flashing, nuts, bolts, washers,
painting, erection/ embedding, embedded parts,
fixing and fixing accessories etc, complete in all
respect as shown on the drawing, as per
specifications and as directed by the Engineer. Kg 80

Unit Rate in words …………………………………..

03-18C PVC roof covering including fixing and fixing


accessories etc, complete in all respect as shown
on the drawing, as per specifications and as
directed by the Engineer.
(excluding the cost of structural steel) Sqm 10

Unit Rate in words …………………………………..

03-19C Door Type: 44mm thick MS Tubular frame Metal


Door; fully sand louvered with 16 gauge MS sheet
louvers, finish in PU painted with compatible
hardware set (as per schedule) including fixing
and fixing accessories etc of the following design
types; complete in all respect as shown on the
drawing, as per specification and as approved by
the Engineer.

a) Type-SD1 Sqm 31

Unit Rate in words …………………………………..

b) Type-SD2 Sqm 76

Unit Rate in words …………………………………..

03-20C Door: 44mm thick Hollow Metal Door; 16 gauge


GI sheet on both sides seamless door,
polyurethane top coat (internal and external faces)
filled with Rockwool, with compatible hardware set
(as per schedule), including fixing and fixing
accessories etc of the following design types;
complete in all respect as shown on the drawing,
as per specfications and as directed by the
Engineer.(45 min fire rated)

a) Type-SD3 Sqm 4

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-6 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

03-21C Louver: fully sand trap MS louver with 16 gauge


MS sheet fixed screen/ window, finish in PU
painted with MS louvers frame and compatible
hardware set (as per schedule), including exhaust
fan provision (where required), fixing and fixing
accessories etc of the following design types;
complete in all respect as shown on the drawing,
as per specification and as approved by the
Engineer.

a) Type-L1 Sqm 12

Unit Rate in words …………………………………..

b) Type-L2 Sqm 91

Unit Rate in words …………………………………..

d) Type-L3 Sqm 5

Unit Rate in words …………………………………..

03-22C Railing: Providing, fabrication and installation of


epoxy painted Floor mounted MS Railing including
embedding, embedding parts, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing, as per specification and as
approved by the Engineer. Rm 11

Unit Rate in words …………………………………..

03-23C Grating: Providing, fabrication and installation of


heavy duty galvanized MS grating cover including
embedding, embedding parts, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing, as per specification and as
approved by the Engineer. Kg 850

Unit Rate in words …………………………………..

BRICK MASONRY
Ref.Spec. No. 4200

03-24C Reinforced facing brick masonry outer wall 225mm


thick, set in specified cement mortar including MS
anchor Bars etc; complete in all respect as shown
on the drawing and as per specification.
Cum 378

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-7 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

CARPENTARY & JOINERY


Ref.Sec.No. 4600,6700

03-25C Door: 55mm thick wooden solid core flush door in


teak wood frame in lacquer finish with hardware
set (as per schedule), including fixing and fixing
accessories complete in all respect as shown on
the drawing, as per specification and as approved
by the Engineer.
(60 min fire rated)

a) Type-WD1
including SS kick plate Sqm 3

Unit Rate in words …………………………………..

b) Type-WD2
including ss kick plate, powder coated aluminum
grill & 8mm thick tempered glass Sqm 5

Unit Rate in words …………………………………..

c) Type-WD5 Sqm 6

Unit Rate in words …………………………………..

03-26C Door: 35mm thick wooden hollow core flush door


in teak wood frame both side plastic laminated in
lacquer finish with hardware set (as per
schedule), including fixing and fixing accessories
etc of the following design types; complete in all
respect as shown on the drawing, as per
specification and as approved by the Engineer.

a) Type-WD3 Sqm 2

Unit Rate in words …………………………………..

b) Type-WD4
including powder coated aluminum grill Sqm 4

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-8 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

ALUMINIUM WORKS
Ref. Sec.No. 6220, 6250

03-27C Door: 8mm thick tinted / clear tempered glass


pivoted door on powder coated aluminum frame
with hardware set (as per schedule) including
fixing and fixing accessories etc. of the following
design types; complete in all respect as shown on
the drawing, as per specification and as approved
by the Engineer.

a) Type-ALD1
tinted tempered glass Sqm 8

Unit Rate in words …………………………………..

b) Type-ALD2
clear tempered glass Sqm 3

Unit Rate in words …………………………………..

c) Type-ALD3
tinted tempered glass Sqm 3

Unit Rate in words …………………………………..

03-28C Window : 8mm thick tinted / clear tempered glass


fixed / openable window / ventilator on powder
coated aluminum frame (Deluxe Type) with
compatible hardware set (as per schedule)
including fixing and fixing accessories etc of the
following design types; complete in all respect as
shown on the drawing, as per specification and as
approved by the Engineer.

a) Type-ALS1
tinted tempered glass fixed window Sqm 4

Unit Rate in words …………………………………..

b) Type-ALS2
clear tempered glass fixed window Sqm 7

Unit Rate in words …………………………………..

c) Type-ALS3
tinted tempered glass fixed window Sqm 4

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-9 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

03-29C Window Type: 8mm thick tinted/ clear tempered


glass fixed / openable window / ventilator on
powder coated aluminum frame (Deluxe Type)
with compatible hardware set (as per schedule)
including fixing and fixing accessories etc of the
following design types; complete in all respect as
shown on the drawing, as per specification and as
approved by the Engineer.

a) Type-W1
Tinted tempered glass fixed window Sqm 7

Unit Rate in words …………………………………..

b) Type-W2
Tinted tempered glass openable window Sqm 1

Unit Rate in words …………………………………..

c) Type-V1
Tinted tempered glass openable ventilator Sqm 1

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

03-30C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth. Sqm 2,106

Unit Rate in words …………………………………..

03-31C Water proofing and built-up roofing of the following


types over roof slab etc; complete in all respect as
shown on the drawing, as per specification and as
approved by the Engineer.

a) Type-I Sqm 1,530

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-10 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

CEMENT PLASTER
Ref. Sec.No. 6521

03-32C 13mm thick 1:6 cement sand plaster to specified


interior surfaces etc; complete in all respect as
shown on the drawing and specification. Sqm 3,774

Unit Rate in words …………………………………..

03-33C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove / plain in plaster as
specified etc; complete in all respect as shown on
the drawing and specification. Sqm 655

Unit Rate in words …………………………………..

FLOOR AND WALL FINISHES


Ref. Sec.No. 6531, 6600

03-34C Floor type F01: 600x600x8mm thick fully vitrified


glazed Porcelain tiles in approved color/shade
and texture conforming to ISO 13006 Bla
requirements, laid in combination of rectilinear /
diagonal pattern, providing thermal expansion
8mm thick PVC strip in 6mm at approx. 6000mm
c/c in both directions filled with matching grout, set
in specified cement sand mortar including water
barrier course of approved liquid proofing
(application as per manufacturer
recommendation), 50mm thick Class 'C' concrete
screed, cement mortar with approved adhesive,
20mm thick 1:3 dry cement mortar binding course
and dry cement spread & splash of water etc;
complete in all respect as shown on the drawing,
as per specification and as approved by the
Engineer.
Sqm 32

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-11 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

03-35C Floor type F02: 300x300x8mm thick fully vitrified


semi glazed Porcelain tiles in approved
color/shade and texture conforming to ISO 13006
Bla requirements, filled with water tight matching
grout, set in specified cement sand mortar
including water barrier course of approved liquid
proofing (application as per manufacturer
recommendation), 50mm thick Class 'C' concrete
screed base, cement mortar with approved
adhesive, 20mm thick 1:3 dry cement mortar
binding course and dry cement spread & splash of
water etc; complete in all respect as shown on the
drawing, as per specification and as approved by
the Engineer.
Sqm 9

Unit Rate in words …………………………………..

03-36C Floor type F03: 450x450x8mm thick Acid


resistant tile with matching grout, set in specified
cement sand mortar including 50mm thick Class
'C' concrete screed base, cement mortar with
approved adhesive etc; complete in all respect as
shown on the drawing, as per specfications and as
directed by the Engineer. Sqm 69

Unit Rate in words …………………………………..

03-37C Floor type F04: 80mm thick cement concrete


floor; comprising top surface floor with 1mm thick
epoxy coating over heavy duty smooth cemented
screed floor etc; complete in all respect as shown
on the drawing & specification. Sqm 878

Unit Rate in words …………………………………..

03-38C Floor type F05: 80mm thick cement concrete


screed (Full Body) with hardener steel troweled
finish laid in panels not more than 2400x2400mm
of specified ratio and separated by glass/ pvc
divider strip etc; complete in all respect as shown
on the drawing, as per specfications and as
directed by the Engineer. Sqm 455

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-12 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

03-39C Floor type F06: 80mm thick Class 'C' cement


concrete screed, Full Body laid in panels not more
than 2400x2400mm in steel troweled finish and
separated by glass/ pvc divider strip etc; complete
in all respect as shown on the drawing, as per
specification and as approved by the Engineer.
Sqm 49

Unit Rate in words …………………………………..

03-40C Wall type W03: 300x300x8mm thick fully vitrified


glazed Porcelain tiles in approved color/ shade
and texture conforming to ISO 13006 Bla
requirements, laid along project grid with
impervious grout, set in specified cement sand
mortar including rough base plaster etc; complete
in all respect as shown on the drawing, as per
specification and as approved by the Engineer. Sqm 51

Unit Rate in words …………………………………..

03-41C Wall type W05: 450x450x8mm thick Acid resistant


tile with matching grout, set in specified cement
sand mortar including rough base plaster etc;
complete in all respect as shown on the drawing,
as per specfications and as directed by the
Engineer. Sqm 91

Unit Rate in words …………………………………..

03-42C Skirting type SK01: 100mm high Porcelain tile


skirting same as floor tile in approved size,
color/shade and texture, conforming to ISO 13006
Bla requirements, set in specified cement sand
mortar including rough base plaster etc; complete
in all respect as shown on the drawing, as per
specification and as approved by the Engineer. Sqm 5

Unit Rate in words …………………………………..

03-43C Skirting type SK02: 100mm high cemented


skirting in approved size/ panels, color/ shade and
texture including rough base plaster etc; complete
in all respect as shown on the drawing, as per
specification and as approved by the Engineer. Sqm 44

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-13 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

03-44C Skirting type SK03: 100mm high epoxy coating


over 13mm thick cemented skirting in approved
size/ panels, color/ shade and texture including
rough base plaster etc; complete in all respect as
shown on the drawing & specification. Sqm 19

Unit Rate in words …………………………………..

03-45C Stair case type: Tread & riser with base skirting
are in pigmented concrete in plank formation using
specified cement in trowel finish including
40x40x3mm thick GI corner edge etc; complete in
all respect as shown on the drawing, as per
specification and as approved by the Engineer. Sqm 33

Unit Rate in words …………………………………..

03-46C 150mm thick Class 'D' cement concrete


sub-floor in ramp complete in all respect as
shown on the drawing, as per specification and as
approved by the Engineer. Sqm 168

Unit Rate in words …………………………………..

03-47C 50mm thick Class 'C' cement concrete floor in


ramp complete in all respect as shown on the
drawing, as per specification and as approved by
the Engineer. Sqm 168

Unit Rate in words …………………………………..

FALSE CEILING
Ref. Sec.No. 6560

03-48C Ceiling Type C01: 100mm wide linear non


perforated aluminum strip ceiling @ 100mm c/c,
butt jointed, baked enamel painted suspended by
6mm dia rigid threaded rods and compatible
suspension system with provision light fixtures,
HVAC grills and other fixture with sound insulation
on top etc.; complete in all respect as shown on
the drawing, as per specification and as approved
by the Engineer. Sqm 15

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-14 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

03-49C Ceiling Type C02: 600x600 Flat aluminum tiles


ceiling, with closed grove joints, baked enamel
painted suspended by 6mm dia rigid threaded rods
and compatible suspension system with provision
light fixtures, HVAC grills and other fixture with
sound insulation on top etc; complete in all respect
as shown on the drawing, as per specification and
as approved by the Engineer.
(1 hour fire rated) Sqm 20

Unit Rate in words …………………………………..

GRANITE WORKS
Ref. Sec.No. 6532

03-50C Saddle/ Threshold Type: Prepolished granite


threshold of following types, including bullnozing &
water proofing membrane (where required as per
drawing & design), c.c base, fixing and fixing
accessories etc. of the following types; complete in
all respect as shown on the drawing, as per
specification and as approved by the Engineer.

a) Type-2: Saddle/ Threshold 20mm thick Sqm 2

Unit Rate in words …………………………………..

b) Type-3: Saddle/ Threshold 30mm thick Sqm 1

Unit Rate in words …………………………………..

PAINTING
Ref. Sec.No. 6700

03-51C Plastic emulsion paint to specified interior surfaces


in approved color / shade etc; complete in all
respect as shown on the drawings, as per
specifications and as approved by the Engineer. Sqm 3,774

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-15 August-2022
BILL OF QUANTITIES

CODE NO.03 - UTILITY BUILDING


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

03-52C Weather resistant paint to specified exterior


surfaces in approved color / shade etc; complete
in all respect as shown on the drawings, as per
specifications and as approved by the Engineer.
Sqm 450

Unit Rate in words …………………………………..

Total Cost of Code 03 (Civil Works) Carried


Over to Summary of Bid Price - C

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 03C-16 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

C. CIVIL WORKS

04.1-TUBE WELL

EARTHWORKS
Ref. Sec.No. 1100

04.1-1C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 74

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 4

Unit Rate in words …………………………………..

04.1-2C Fill and backfill with selected material including


watering, compaction & etc, complete in all respect
as shown on the drawing and specification.

a) Obtained from required excavation. Cum 20

Unit Rate in words …………………………………..

b) Obtained from outside source Cum 12

Unit Rate in words …………………………………..

STONE SOLING
Ref. Sec.No. 1330

04.1-3C 150mm thick crushed stone soling including


blinding material and compaction. Cum 8

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.1 C-1 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

TERMITE CONTROL TREATMENT


Ref.Spec. No.1600

04.1-4C Termite Control Treatment complete in all respect


as specified, as shown on drawings and approved
by the Engineer. Sqm 8

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

04.1-5C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and specification. tonne 8

Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

04.1-6C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer
Cum 6

Unit Rate in words …………………………………..

04.1-7C Class 'D' plain concrete in situ using specified


cement complete in all respect as shown on the
drawing or as directed by the Engineer Cum 4

Unit Rate in words …………………………………..

04.1-8C Class 'C' concrete using specified cement in plinth


protection including bitumen seal with rubberized
material etc; complete in all respect as shown on
the drawing and specification. Cum 56

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.1 C-2 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

04.1-9C Class 'B' reinforced concrete, using specified


cement in following sub-structural memebers etc,
complete in all respect as shown on the drawing
and specification.

a) Raft/Footing/Foundations Cum 14

Unit Rate in words …………………………………..

b) Columns upto plinth Cum 6

Unit Rate in words …………………………………..

c) Plinth Beam Cum 4

Unit Rate in words …………………………………..

04.1-10C Class 'B' reinforced concrete, using specified


cement in following super-structural memebers
etc, complete in all respect as shown on the
drawing and specification.

a) Columns Cum 6

Unit Rate in words …………………………………..

b) Beams & Lintels Cum 8

Unit Rate in words …………………………………..

c) Slab & Projection Cum 12

Unit Rate in words …………………………………..

d) Purdi Cum 4

Unit Rate in words …………………………………..

e) Footing/Foundations/Bottom & Walls


UG Sump - Underground Sump Cum 2

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.1 C-3 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

04.1-11C Precast fair faced Class 'B' concrete using


specified cement in following structural memebers,
laid / fixed in specified cement sand mortar
including fixing and fixing accessories etc;
complete in all respect as shown on the drawing
and specification.

a) Sills & Coping Cum 2

Unit Rate in words …………………………………..

b) Water Spout Cum 2

Unit Rate in words …………………………………..

c) Type-1: Saddle/ Threshold


with 9x50mm aluminum strip Cum 2

Unit Rate in words …………………………………..

MISCELLENEOUS STEEL
Ref. Sec.No. 3100,6700

04.1-12C Door Type: 44mm thick MS Tubular frame Metal


Door; fully sand louvered with 16 gauge MS sheet
louvers, finish in PU painted with compatible
hardware set (as per schedule) including fixing
and fixing accessories etc of the following design
types; complete in all respect as shown on the
drawing, as per specfications and as directed by
the Engineer.

a) Type-SD1 Sqm 8

Unit Rate in words …………………………………..

04.1-13C Louver Type: fully sand trap MS louver with 16


gauge MS sheet fixed screen/ window, finish in PU
painted with MS louvers frame and compatible
hardware set (as per schedule), including exhaust
fan provision (where required), fixing and fixing
accessories etc of the following design types;
complete in all respect as shown on the drawing,
as per specfications and as directed by the
Engineer.

a) Type-L1 Sqm 6

Unit Rate in words …………………………………..


Expansion of Terminal Building & Allied
Facilities at AIIAP, Lahore 04.1 C-4 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

04.1-14C Providing & fabrication of MS skylight of


900x900mm size, finish in PU paint, including
fixing and fixing accessories etc; complete in all
respect as shown on the drawing, as per
specfications and as directed by the Engineer. Sqm 2

Unit Rate in words …………………………………..

BRICK MASONRY
Ref.Spec. No. 4200

04.1-15C Reinforced facing brick masonry outer wall 225mm


thick, set in specified cement mortar including MS
anchor Bars etc; complete in all respect as shown
on the drawing and as per specification.
Cum 20

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

04.1-16C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth. Sqm 170

Unit Rate in words …………………………………..

04.1-17C Water proofing and built-up roofing of the following


types over roof slab etc; complete in all respect as
shown on the drawing, as per specfications and as
directed by the Engineer.

a) Type-II Sqm 64

Unit Rate in words …………………………………..

CEMENT PLASTER
Ref. Sec.No. 6521

04.1-18C 13mm thick 1:6 cement sand plaster to specified


interior surfaces etc; complete in all respect as
shown on the drawing, as per specfications and as
directed by the Engineer. Sqm 180

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.1 C-5 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

04.1-19C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove/ plain in plaster as
specified etc; complete in all respect as shown on
the drawing, as per specfications and as directed
by the Engineer. Sqm 152

Unit Rate in words …………………………………..

FLOOR AND WALL FINISHES


Ref. Sec.No. 6531, 6600

04.1-20C Floor type F01: 80mm thick cement concrete


floor; comprising top surface floor with 1mm thick
epoxy coating over heavy duty smooth cemented
screed floor etc; complete in all respect as shown
on the drawing, as per specfications and as
directed by the Engineer. Sqm 42

Unit Rate in words …………………………………..

04.1-21C Skirting type SK01: 100mm high epoxy coating


over 13mm thick cemented skirting in approved
size/ panels, color/ shade and texture including
rough base plaster etc; complete in all respect as
shown on the drawing, as per specfications and as
directed by the Engineer. Sqm 4

Unit Rate in words …………………………………..

04.1-22C 150mm thick Class 'D' cement concrete sub-floor


in ramp complete in all respect as shown on the
drawing, as per specfications and as directed by
the Engineer. Sqm 10

Unit Rate in words …………………………………..

04.1-23C 50mm thick Class 'C' cement concrete floor in


ramp complete in all respect as shown on the
drawing, as per specfications and as directed by
the Engineer. Sqm 10

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.1 C-6 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

PAINTING
Ref. Sec.No. 6700

04.1-24C Plastic emulsion paint to specified interior surfaces


in approved color / shade etc; complete in all
respect as shown on the drawings, as per
specifications and as approved by the Engineer.
Sqm 138

Unit Rate in words …………………………………..

04.1-25C Weather resistant paint to specified exterior


surfaces in approved color / shade etc; complete
in all respect as shown on the drawings, as per
specifications and as approved by the Engineer.
Sqm 152

Unit Rate in words …………………………………..

Total Cost of Code 04.1 (Civil Works) Carried


Over to Summary of Bid Price - D

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.1 C-7 August-2022
EXPANSION OF TERMINAL BUILDING AND ALLIED FACILITIES AT
ALLAMA IQBAL INTERNATIONAL AIRPORT PROJECT (AIIAP), LAHORE

BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

C. CIVIL WORKS

04.2-UNDERGROUND WATER TANK & PUMP ROOM

DISMANTLING
Ref.Spec. No.0200

04.2-1C Removal and handing over of existing fence to


Employer comprising fence fabric, barbed /
concertina wire, post, bracing beams, etc complete
in all respect as shown on the drawings,
specifications and as directed by the Engineer.
Rm 65

Unit Rate in words …………………………………..

EARTHWORKS
Ref. Sec.No. 1100

04.2-2C Excavation in all kinds of sub-surface material


upto specified depth including dewatering and
disposal of surplus / rejected excavated material
with loading, unloading & transportation to
designated places up to any lead etc., as directed
by the Engineer, complete in all respect.

a) From 0 to 2 meter Cum 1,151

Unit Rate in words …………………………………..

b) From 2 to 4 meter Cum 1,151

Unit Rate in words …………………………………..

c) From 4 to 6 meter Cum 958

Unit Rate in words …………………………………..

04.2-3C Fill and backfill with selected material including


watering, compaction & etc, complete in all respect
as shown on the drawing and specification.

a) Obtained from required excavation. Cum 595

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-1 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

b) Obtained from outside source Cum 200

Unit Rate in words …………………………………..

STONE SOLING
Ref. Sec.No. 1330

04.2-4C 150mm thick crushed stone soling including


blinding material and compaction. Cum 50

Unit Rate in words …………………………………..

TERMITE CONTROL TREATMENT


Ref.Spec. No.1600

04.2-5C Termite Control Treatment complete in all respect


as specified, as shown on drawings and approved
by the Engineer. Sqm 50

Unit Rate in words …………………………………..

REINFORCEMENT
Ref. Sec.No. 2200

04.2-6C Hot rolled deformed billet steel bars conforming to


ASTM A615, Grade 60 with specified yield
strength not less than 414 MPa (60,000 Psi) etc
complete in all respect as shown on the drawing
and specification. tonne 146

Unit Rate in words …………………………………..

PLAIN AND REINFORCED CONCRETE


Ref. Sec.No. 2100, 2300

04.2-7C Laying of Class 'E' plain concrete complete in all


respect as shown on the drawing or as directed by
the Engineer
Cum 58

Unit Rate in words …………………………………..

04.2-8C Class 'D' plain concrete in situ using specified


cement complete in all respect as shown on the
drawing or as directed by the Engineer Cum 2

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-2 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

04.2-9C Class 'C' concrete using specified cement in plinth


protection including bitumen seal with rubberized
material etc; complete in all respect as shown on
the drawing and specification. Cum 10

Unit Rate in words …………………………………..

04.2-10C Class 'A' reinforced concrete, using specified


cement in following sub-structural members etc,
complete in all respect as shown on the drawing
and specification.

a) Raft/Footing/Foundations Cum 30

Unit Rate in words …………………………………..

b) Columns upto plinth Cum 1

Unit Rate in words …………………………………..

c) Walls Cum 57

Unit Rate in words …………………………………..

d) Slab Cum 8

Unit Rate in words …………………………………..

d) Pad Cum 1

Unit Rate in words …………………………………..

04.2-11C Class 'A' reinforced concrete, using specified


cement in following super-structural members etc,
complete in all respect as shown on the drawing
and specification.

a) Columns Cum 7

Unit Rate in words …………………………………..

b) Beams & lintels Cum 18

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-3 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

c) Slab & Projection Cum 10

Unit Rate in words …………………………………..

d) Purdi Cum 2

Unit Rate in words …………………………………..

e) Stair Cum 3

Unit Rate in words …………………………………..

04.2-12C Class 'A' reinforced concrete, using specified


cement including integral water proofing admixture
BETOCRETE C16 (product of Schomburg
Germany) or approved equivalent in following
structures of under ground water tank UGWT etc,
complete in all respect as shown on the drawing
and as per specification.

a) Raft/Footing/Foundations Cum 258

Unit Rate in words …………………………………..

b) Columns upto plinth Cum 11

Unit Rate in words …………………………………..

c) Walls 253

Unit Rate in words …………………………………..

d) Beam Cum 40

Unit Rate in words …………………………………..

e) Slab Cum 122

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-4 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

04.2-13C Precast fair faced Class 'B' concrete using


specified cement in following structures, laid/ fixed
in specified cement sand mortar including fixing
and fixing accessories etc; complete in all respect
as shown on the drawing and specification.

a) Sills & Coping Cum 1

Unit Rate in words …………………………………..

b) Water Spout Cum 1

Unit Rate in words …………………………………..

c) Type-4: Saddle/ Threshold


with metal flashing, 30x30 galvanized steel angle,
steel dowels, weather stripping & water proofing
membrane. Cum 1

Unit Rate in words …………………………………..

MISCELLENEOUS STEEL
Ref. Sec.No. 3100,6700

04.2-14C Door Type: 44mm thick MS Tubular frame Metal


Door; fully sand louvered with 16 gauge MS sheet
louvers, finish in PU painted with compatible
hardware set (as per schedule) including fixing
and fixing accessories etc of the following design
types; complete in all respect as shown on the
drawing, as per specfications and as directed by
the Engineer.

a) Type-SD1 Sqm 5

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-5 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

04.2-15C Louver Type: fully sand trap MS louver with 16


gauge MS sheet fixed screen/ window, finish in PU
painted with MS louvered frame and compatible
hardware set (as per schedule), including exhaust
fan provision (where required), fixing and fixing
accessories etc of the following design types;
complete in all respect as shown on the drawing,
as per specfications and as directed by the
Engineer.

a) Type-L1 Sqm 6

Unit Rate in words …………………………………..

b) Type-L2 Sqm 3

Unit Rate in words …………………………………..

c) Type-L3 Sqm 4

Unit Rate in words …………………………………..

04.2-16C Railing: Providing, fabrication and installation of


epoxy painted Floor mounted MS Railing including
embedding, embedding parts, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing, as per specfications and as
directed by the Engineer. Rm 24

Unit Rate in words …………………………………..

04.2-17C Railing: Providing, fabrication and installation of


epoxy painted Wall mounted MS Railing including
embedding, embedding parts, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing, as per specfications and as
directed by the Engineer.
Rm 24

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-6 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

CAST IRON COVER WITH FRAME & LADDER RUNGS


Ref.Spec. No. 5233, 3100

04.2-18C C.I/D.I cover (600mm x 600mm) Class A15 with


frame including embedding parts, fixing and fixing
accessories etc; complete in all respect as shown
on the drawing, as per specfications and as
directed by the Engineer. No 9

Unit Rate in words …………………………………..

04.2-19C Galvanized MS ladder rungs 20mm diameter


including embedding etc; complete in all respect
as shown on the drawing, as per specfications and
as directed by the Engineer.
No. 108

Unit Rate in words …………………………………..

BRICK MASONRY
Ref.Spec. No. 4200

04.2-20C Reinforced brick masonry wall of the 100mm thick


wall around UGWT, set in specified cement mortar
including MS anchor bars etc; complete in all
respect as shown on the drawing, as per
specfications and as directed by the Engineer.
Cum 57

Unit Rate in words …………………………………..

04.2-21C Reinforced facing brick masonry outer wall 225mm


thick, set in specified cement mortar including MS
anchor Bars etc; complete in all respect as shown
on the drawing and as per specification. Cum 10

Unit Rate in words …………………………………..

WATER PROOFING & BUILT UP ROOFING


Ref. Sec.No. 6411

04.2-22C Two coats of hot bitumen grade 10/20 applied @ 1


Kg./Sqm per coat to all structural concrete
surfaces in contact with earth. Sqm 620

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-7 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

04.2-23C Water proofing and built-up roofing of the following


types over roof slab etc; complete in all respect as
shown on the drawing, as per specfications and as
directed by the Engineer.

a) Type-II Sqm 57

Unit Rate in words …………………………………..

04.2-24C Crystalline Cementitious water proofing coating


(Aquafin-IC or approved equivalent) on specified
surfaces etc; complete in all respect as shown on
the drawing, as per specfications and as directed
by the Engineer. Sqm 677

Unit Rate in words …………………………………..

04.2-25C 25X10mm Polyurethane sealant on specified


surfaces etc; complete in all respect as shown on
the drawing, as per specfications and as directed
by the Engineer. Sqm 6

Unit Rate in words …………………………………..

04.2-26C Bitumen impregnated wood fiber board laid/fixed


on specified surfaces including fixing and fixing
accessories etc; complete in all respect as shown
on the drawing, as per specfications and as
directed by the Engineer. Sqm 6

Unit Rate in words …………………………………..

CEMENT PLASTER
Ref. Sec.No. 6521

04.2-27C 13mm thick 1:6 cement sand plaster to specified


interior surfaces etc; complete in all respect as
shown on the drawing and specification. Sqm 178

Unit Rate in words …………………………………..

04.2-28C 20mm thick 1:4 cement sand plaster to specified


exterior surfaces, groove/ plain in plaster as
specified etc; complete in all respect as shown on
the drawing and specification. Sqm 97

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-8 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

FLOOR AND WALL FINISHES


Ref. Sec.No. 6531, 6600

04.2-29C Floor type F01: 80mm thick cement concrete


floor; comprising top surface floor with 1mm thick
epoxy coating over heavy duty smooth cemented
screed floor etc; complete in all respect as shown
on the drawing, as per specfications and as
directed by the Engineer. Sqm 48

Unit Rate in words …………………………………..

04.2-30C Skirting type SK01: 100mm high epoxy coating


over 13mm thick cemented skirting in approved
size/ panels, color/ shade and texture including
rough base plaster etc; complete in all respect as
shown on the drawing, as per specfications and as
directed by the Engineer.
Sqm 5

Unit Rate in words …………………………………..

04.2-31C Stair case type: Tread & riser with base skirting
are in pigmented concrete in plank formation using
specified cement in trowel finish including
40x40x3mm thick GI corner edge etc; complete in
all respect as shown on the drawing, as per
specfications and as directed by the Engineer.
Sqm 15

Unit Rate in words …………………………………..

04.2-32C 150mm thick Class 'D' cement concrete sub-floor


in ramp complete in all respect as shown on the
drawing, as per specfications and as directed by
the Engineer. Sqm 14

Unit Rate in words …………………………………..

04.2-33C 50mm thick Class 'C' cement concrete floor in


ramp complete in all respect as shown on the
drawing, as per specfications and as directed by
the Engineer. Sqm 14

Unit Rate in words …………………………………..

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-9 August-2022
BILL OF QUANTITIES

CODE NO.04 - WATER WORKS


Rate Amount
Item No. Description Unit Qty
(Rs.) (Rs.)

PAINTING
Ref. Sec.No. 6700

04.2-34C Plastic emulsion paint to specified interior surfaces


in approved color / shade etc; complete in all
respect as shown on the drawings, as per
specifications and as approved by the Engineer. Sqm 178

Unit Rate in words …………………………………..

04.2-35C Weather resistant paint to specified exterior


surfaces in approved color / shade etc; complete
in all respect as shown on the drawings, as per
specifications and as approved by the Engineer. Sqm 97

Unit Rate in words …………………………………..

FENCING
Ref. Sec. No. 0200, 1100, 2100, 2200, 2300, 2450, 3100, 6411

04.2-36C Chain link fence PVC coated including chain link


fabric, tension wire, strecher bar, cleat, RCC line
posts, RCC bracing post etc. comprising
earthwork, plain & RCC concrete, bitumen coating
including fixing and all fixing accessories etc.
complete in all respect and as shown on the
drawings or as specified and as directed by the
Engineer. Rm 65

Unit Rate in words …………………………………..

Total Cost of Code 04.2 (Civil Works) Carried


Over to Summary of Bid Price - E

Expansion of Terminal Building & Allied


Facilities at AIIAP, Lahore 04.2 C-10 August-2022