You are on page 1of 17

GOVERNMENT OF KARNATAKA

PW, P & IWT DEPARTMENT

DETAILED & ABSTRACT


ESTIMATE FOR

Construction of CD works at Koppar village in Deodurga

In DeodurgaTaluka
Raichur District.

Under: H.K.R.D.B for the year 2018-19 (MACRO)

AMOUNT OF ESTIMATE
Rs 40.00 Lakhs

OFFICE OF THE
ASSISTANT EXECUTIVE ENGINEER
PUBLIC WORKS, PORTS AND INLAND WATER TRANSPORT DEPARTMENT.
SUB-DIVISION, DEODURGA
FORM PWG-62. QM/ F 62
(Paragraph 130(a) of the Karnataka Public Works Departmental Code)

ESTIMATE FACE SHEET

Division : PW, P & IWTD. Division, Raichur. .

Sanctioned Estimate No. : ____________________________________of 2018-19

Fund Head : _

Major Head : _

Minor Head : _

Service Head : _

Department Head : _

Estimate framed in the Office of the Assistant Executive Engineer P. W. D. Sub-Division,


Deodurga.

Division of the probable expenses that will be incurred in


Construction of CD works at Koppar village in Deodurga In DeodurgaTaluka
Raichur District. Under: H.K.R.D.B for the year 2018-19 (MACRO)

Rs. 40.00 Lakhs

Administratively approved under .

No: _____________________________________ Dated: ___________________________

Technically sanctioned under .

No: _____________________________________ Dated: ___________________________

Estimate prepared by: Sri. BASAVARAJ, J. E. .

And Checked by: Sri. B.B. PATIL, A. E. E. .


(Call or Authority).
Section Assistant Executive Engineer
officer PW, P & IWTD. Sub-Division, Deodurga.
er
REPORT
Name of work: -
Construction of CD works at Koppar village in Deodurga In DeodurgaTaluka
Raichur District. Under: H.K.R.D.B for the year 2018-19 (MACRO)

* * *

Work is proposed Under: H.K.R.D.B (MACRO) for the year 2018-19 to an amount of
Rs.40.00 Lakhs,. Accordingly an estimate is prepared as per the CSR of PW, P & IWTD
Bellary Circle Bellary for the year 2018-19 with area weightage of 5%

The estimate for CDs, Box drain and Side drain is prepared based on site observations
noted. There is a necessity of constructing culverts and box drain as per the site
conditions as the water from up stream side overflows on road surface which is causing
damages to the road surface and erosions. Therefore the underline structures have been
proposed in this estimate with the following provisions.

1 KSRRB M300-14. Excavation for roadwork in all types of soil by mechanical


2 KSRB 2.8 : Providing and Filling in foundation with granite / trap broken metal
3 KSRB 4-1.3 : Providing and laying in position plain cement concrete of Mix 1:4:8
4 Providing and laying plain/reinforced cement concrete for side drains using M20
5 KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including
6 Providing and laying reinforced cement concrete pipe NP3 for culverts including
7 KSRRB M300-55 : Construction of sub grade and Earthen shoulders.
8 Construction of granular sub-base Grading-V as Sub-base and drainage layer by
9 KSRRB M400-17. Providing, laying, spreading and compacting cushed stone
10 Constructing un-reinforced, plain cement concrete for pavements using
11 Add GST rate @ 12 % of the total cost
12 Add for thirty party charges 1%

Early approval to the estimate is solicited.

Section Assistant Executive Engineer


officer PW, P & IWTD. Sub-Division, Deodurga.
Page 1

General Description
PWG 62 (a)
(Paragraph 130 (a) of the Karnataka Public Works Departmental Code)

Construction of CD works at Koppar village in Deodurga In DeodurgaTaluka Raichur District. Under: H.K.R.D.B
for the year 2018-19 (MACRO)

Estimate
Abstract Sheet
QM / F - 62 (a)
Sl.
Quantity Unit Description of work Rate Per Amount
No.
1 2 3 4 5 6 7
1 406.69 /Cum KSRRB M300-14. Excavation for roadwork in all types of soil by 43.05 /Cum 17508.00
mechanical means including cutting and loading to tippers,
trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transportation with a lead of 1.00 km and complete as per
specifications. MORTH Specification No.301
2 40.11 /Cum KSRB 2.8 : Providing and Filling in foundation with granite / trap 2396.10 /Cum 96108.00
broken metal 100mm. and down size & with approved sand
including hand packing, ramming, watering, including cost of all
materials and labour with all lead and lift. complete as per
specifications. specification. No. KBS 2.10.2
3 49.38 /Cum KSRB 4-1.3 : Providing and laying in position plain cement 5199.60 /Cum 256756.00
concrete of Mix 1:4:8 with OPC @ 180kgs, with 40mm and down
size graded granite metal coarse aggregates @0.85cum and fine
aggregates @ 0.57cum machine mixed, machine mixed,
concrete laid in layers not exceeding 15 cms. thick, well
compacted, in foundation, including cost of all materials, labour,
HOM curing complete as per specifications. Specification No.
KBS 4.1, 4.2

4 152.19 /Cum Providing and laying plain/reinforced cement concrete for side 7061.25 /Cum 1074616.00
drains using M20 nominal mix concrete with OPC at 300 kgs.
with 20mm and down size granite metal coarse aggregates at
0.69 cum and fine aggregates at 0.43 cum machine mixed, well
compacted for walls and bottom including centering, shuttering,
cost of materials, HOM of machinery, curing etc., complete
excluding cost of steel as per MORTH specification No. 1500,
1700, 2200. including cost of materials, labour, HOM complete
as per specifications.

5 9.11 / KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work 74505.90 /Tonne 678823.00
including straightening, cutting, bending, hooking, placing in
position, lapping and / or welding wherever required, tying with
binding wire and anchoring to the adjoining members wherever
necessary complete as per design (laps, hooks and wastage
shall not be measured and paid) cost of materials, labour, HOM
complete as per specifications. Specification No. KBS 4.6.3
Tonne
6 22.50 /M Providing and laying reinforced cement concrete pipe NP3 for 5776.05 /M 129961.00
culverts including pointing ends, and fixing collars with cement
mortar 1:2 including cost of all materials, labour, curing,
including cost of materials, labour, HOM complete as per
specifications. Specifications. No. KSRB 1000, 2300 MOST
Specification No.1000 / 2300 900mm dia
7 1275.74 /Cum KSRRB M300-55 : Construction of sub grade and Earthen 617.40 /Cum 787639.00
shoulders. Construction of sub grade and Earthen shoulders with
approved material Gravel / Murrum with all lifts and leads,
transporting to site, spreading grading to required slope and
compacted to meet requirement of Table No. 300-2 complete as
per specifications (including cost of earth, water charges and
compaction by vibratory roller) MORTH Specification No. 305
Page 2

Sl.
Quantity Unit Description of work Rate Per Amount
No.
1 2 3 4 5 6 7
8 38.50 /Cum Construction of granular sub-base Grading-V as Sub-base and 2033.85 /Cum 78303.00
drainage layer by providing coarse graded crushed stone
aggregates of granite/ trap/basalt material, mixing in a
mechanical mix plant at OMC, Carriage of mixed material to
work site, spreading in uniform layers with motor grader on
prepared surface and compacting with vibratory power roller to
achieve the 98 % proctor density, complete as per specifications.

Clause 401 of MORTH V Revision.

9 38.50 /Cum KSRRB M400-17. Providing, laying, spreading and compacting 1970.85 /Cum 75878.00
cushed stone aggregates of granite / trap / basalt to wet mix
macadam specifications including pre mixing the material with
water at OMC in mechanical mix plant carriage of mixed
materials by tipper to site, laying in uniform layers with paver in
sub-base/base course on well prepared surface and compacting
with vibratory roller to achieve the desired density complete as
per specifications. MORTH Specification No. 406

10 69.80 /Cum Constructing un-reinforced, plain cement concrete for 4914.00 /Cum 342997.00
pavements using Grade concrete M30 over a prepared base
with OPC coarse aggregate at 0.69 cum, fine aggregates at 0.46
cum,Coarse and fine aggregate conforming to IS:383-2016,
with Superplastizer at 3 lts conforming to IS 9103-2008.
mixed in a concrete mixer of not less than 0.6 cum capacity
and appropriate weigh batcher as per approved mix design, laid
in approved fixed side form work (steel channel, laying and
fixing of 125 micron thick polythene film, wedges, steel
plates including levelling the form work as per drawing). &
Spreading the concrete with shovels, rackers compacted
using needle, screed and plate vibrator and finished with
floaters in a continuous operation including provision of
contraction, expansion, construction and longitudinal
joints,including groove cutting charges, joint filler, separation
membrane of impermiable plastic sheet of 125 micron, sealant
primer, joint sealant, admixtures as approved, curing compound,
finishing to lines and grades, textured with texturing machine,
and curing including cost of all materials, labour,hire charges of
machineries,all lead & lift charges etc., complete as per
specifications.
-do- with OPC at 360 kg/cum and coarse aggregate 0.69cum,
fine aggregate 0.46cum. TOTAL Rs: - 3538589.00
11 Add GST rate @ 12 % of the total cost 424,631.00
12 Add for thirty party charges 1% 35,386.00
13 1,394.00
Grand Total Rs 4,000,000.00

Section Assistant Executive Engineer EXECUTIVE ENGINEER


officer PW, P & IWTD. Sub-Division, Deodurga PW, P & IWTD. Division, Raichur.
Page 1

PWG 62 (b)
Paragraphs 130 (a) of the Karnataka Public Works Departmental Code

Construction of CD works at Koppar village in Deodurga In DeodurgaTaluka Raichur District. Under: H.K.R.D.B
for the year 2018-19 (MACRO)

Estimate
MEASUREMENT Sheet
QM / F - 62 (b)
Sl. Description of work No Measurements Contents Total
No. L B D
1 2 3 4 5 6 7 8
1 KSRRB M300-14. Excavation for roadwork in all types of soil by
mechanical means including cutting and loading to tippers, trimming
bottom and side slopes, in accordance with requirements of lines,
grades and cross sections, and transportation with a lead of 1.00 km
and complete as per specifications. MORTH Specification No.301

For CDs
Near Laxminarayana temple
Head wall 2 3.00 1.20 2.10 15.12
Pipe portion 1 6.00 1.00 1.65 9.90
Koppur cross to Laxminarayana temple road
Head wall 2 3.00 1.20 2.10 15.12
Pipe portion 1 3.50 1.00 1.65 5.78
At MDR deodurga-koppur road (Ch:11.800)
Head wall 2 3.00 1.20 2.10 15.12
Pipe portion 1 6.00 1.00 1.65 9.90
For Deck Slab at Eshwar chowk
Head Wall & Vent portion 1 3.80 12.00 1.55 70.68
For Deck Slab 10.00m at Km11.60 MDR Deodruga- Koppur road
Head Wall & Vent portion 1 3.80 10.00 1.55 58.90
For Deck Slab near temple cross road
Head Wall & Vent portion 1 3.80 7.50 1.55 44.18
Head Wall & Vent portion
1 150.00 1.20 0.90 162.00
406.69 406.69
2 KSRB 2.8 : Providing and Filling in foundation with granite / trap
broken metal 100mm. and down size & with approved sand including
hand packing, ramming, watering, including cost of all materials and
labour with all lead and lift. complete as per specifications.
specification. No. KBS 2.10.2
For CDs
Near Laxminarayana temple
Head wall 2 3.00 1.20 0.30 2.16
Koppur cross to Laxminarayana temple road
Head wall 2 3.00 1.20 0.30 2.16
At MDR deodurga-koppur road (Ch:11.800)
Head wall 2 3.00 1.20 0.30 2.16
For Deck Slab at Eshwar chowk
Head Wall & Vent portion 1 3.80 12.00 0.30 13.68
For Deck Slab 10.00m at Km11.60 MDR Deodruga- Koppur road
Head Wall & Vent portion 1 3.80 10.00 0.30 11.40
For Deck Slab near temple cross road
Head Wall & Vent portion 1 3.80 7.50 0.30 8.55
40.11 40.11
3 KSRB 4-1.3 : Providing and laying in position plain cement concrete of
Mix 1:4:8 with OPC @ 180kgs, with 40mm and down size graded
granite metal coarse aggregates @0.85cum and fine aggregates @
0.57cum machine mixed, machine mixed, concrete laid in layers not
exceeding 15 cms. thick, well compacted, in foundation, including cost
of all materials, labour, HOM curing complete as per specifications.
Specification No. KBS 4.1, 4.2

For CDs
Page 2

Sl. Description of work No Measurements Contents Total


No. L B D
1 2 3 4 5 6 7 8
Near Laxminarayana temple
Head wall 2 3.00 1.20 0.15 1.08
Pipe portion 1 6.00 1.00 0.15 0.90
Koppur cross to Laxminarayana temple road
Head wall 2 3.00 1.20 0.15 1.08
Pipe portion 1 3.50 1.00 0.15 0.53
At MDR deodurga-koppur road (Ch:11.800)
Head wall 2 3.00 1.20 0.15 1.08
Pipe portion 1 6.00 1.00 0.15 0.90
For Deck Slab at Eshwar chowk
Head Wall & Vent portion 1 3.80 12.00 0.15 6.84
For Deck Slab 10.00m at Km11.60 MDR Deodruga- Koppur road
Head Wall & Vent portion 1 3.80 10.00 0.15 5.70
For Deck Slab near temple cross road
Head Wall & Vent portion 1 3.80 7.50 0.15 4.28
For CC Drain
1 150.00 1.20 0.15 27.00
49.38 49.38
4 Providing and laying plain/reinforced cement concrete for side drains
using M20 nominal mix concrete with OPC at 300 kgs. with 20mm and
down size granite metal coarse aggregates at 0.69 cum and fine
aggregates at 0.43 cum machine mixed, well compacted for walls and
bottom including centering, shuttering, cost of materials, HOM of
machinery, curing etc., complete excluding cost of steel as per
MORTH specification No. 1500, 1700, 2200. including cost of
materials, labour, HOM complete as per specifications.

Near Laxminarayana temple


Head wall Raft 2 3.00 0.90 0.15 0.81
Head wall 2 3.00 0.675 1.50 6.08
Parapet wall 2 3.00 0.45 0.60 1.62
Koppur cross to Laxminarayana temple road
Head wall Raft 2 3.00 0.90 0.15 0.81
Head wall 2 3.00 0.675 1.90 7.70
Parapet wall 2 3.00 0.45 0.600 1.62
At MDR deodurga-koppur road (Ch:11.800)
Head wall Raft 2 3.00 0.90 0.15 0.81
Head wall 2 3.00 0.675 1.50 6.08
Parapet wall 2 3.00 0.45 0.60 1.62
Deduction for pipe vents 3x2 3.14 0.675 0.200 -2.54
For Deck Slab at Eshwar chowk
Head wall Raft 2 12.00 0.900 0.15 3.24
Wall 2 12.00 0.675 1.00 16.20
Deck slab 1 12.00 2.000 0.30 7.20
For Deck Slab 10.00m at Km11.60 MDR Deodruga- Koppur road
Head wall Raft 2 10.00 0.90 0.15 2.70
Wall 2 10.00 0.68 1.00 13.50
Deck slab 1 10.00 2.000 0.30 6.00
For Deck Slab near temple cross road
Head wall Raft 2 7.50 0.90 0.15 2.03
Wall 2 7.50 0.68 1.00 10.13
Deck slab 1 7.50 2.000 0.30 4.50
Raft 1 150.00 0.90 0.10 13.50
Wall 2 150.00 0.10 0.90 27.00
Drain cover slab 30 4.00 1.20 0.15 21.60
Guard stone
152.19 152.19
Page 3

Sl. Description of work No Measurements Contents Total


No. L B D
1 2 3 4 5 6 7 8
5 KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work
including straightening, cutting, bending, hooking, placing in position,
lapping and / or welding wherever required, tying with binding wire and
anchoring to the adjoining members wherever necessary complete as
per design (laps, hooks and wastage shall not be measured and paid)
cost of materials, labour, HOM complete as per specifications.
Specification No. KBS 4.6.3

Near Laxminarayana temple


Main bars 12mm dia @ 150mm C/C 2 21 4.00 0.890 149.52
Distbn. Bars 10mm dia @ 150mm C/C 2 22 3.00 0.620 81.84
Koppur cross to Laxminarayana temple road
Main bars 12mm dia @ 150mm C/C 2 21 4.00 0.890 149.52
Distbn. Bars 10mm dia @ 150mm C/C 2 22 3.00 0.620 81.84
At MDR deodurga-koppur road (Ch:11.800)
Main bars 12mm dia @ 150mm C/C 2 21 4.00 0.890 149.52
Distbn. Bars 10mm dia @ 150mm C/C 2 22 3.00 0.620 81.84
For Deck Slab at Eshwar chowk
Main Bars 12mm dia @200mm C/C 2 81 3.10 0.89 446.96
Distbn. Bars 10mm dia @ 150mm C/C 2 20 12.00 0.62 297.60
For Deck Slab 10.00m at Km11.60 MDR Deodruga- Koppur road
Main Bars 12mm dia @200mm C/C 2 67 3.10 0.89 369.71
Distbn. Bars 10mm dia @ 150mm C/C 2 20 10.00 0.62 248.00
For Deck Slab near temple cross road
Main Bars 12mm dia @200mm C/C 2 51 3.10 0.89 281.42
Distbn. Bars 10mm dia @ 150mm C/C 2 20 7.50 0.62 186.00
For Deck slab ( Double Matt) 12.00m length
Main Bars 12mm dia @150mm C/C 1x2 81 2.00 0.89 288.36
Distbn. Bars 10mm dia @ 150mm C/C 1x2 14 12.00 0.62 208.32
For Deck slab ( Double Matt) 10.00m length
Main Bars 12mm dia @150mm C/C 1x2 67 2.00 0.89 238.52
Distbn. Bars 10mm dia @ 150mm C/C 1x2 14 10.00 0.62 173.6
For Deck slab ( Double Matt) 10.00m length
Main Bars 16mm dia @150mm C/C 1x2 51 2.00 1.58 322.32
Distbn. Bars 12mm dia @ 150mm C/C 1x2 14 7.50 0.89 186.9
Guard stones 5x3x2 4 0.75 0.62 55.8
Guard stones Stirrups 5x3x2 4 0.92 0.39 43.056
For CC Drain
Main bar 10mm dia 1 1001 2.70 0.62 1675.67
Distbn. Bar 10mm dia 1 20 150.00 0.62 1860.00
Drain cover slab
Main bars12mm dia 30 27 1.20 0.89 865.08
Distbn. Bars10mm dia 30 9 4.00 0.62 669.60
Kg 9110.99
Say in Tonne 9.11
6 Providing and laying reinforced cement concrete pipe NP3 for
culverts including pointing ends, and fixing collars with cement mortar
1:2 including cost of all materials, labour, curing, including cost of
materials, labour, HOM complete as per specifications. Specifications.
No. KSRB 1000, 2300 MOST Specification No.1000 / 2300 900mm
dia
3 Nos of CD's work at Chainage 3x3 2.50 22.50 22.50
7 KSRRB M300-55 : Construction of sub grade and Earthen shoulders.
Construction of sub grade and Earthen shoulders with approved
material Gravel / Murrum with all lifts and leads, transporting to site,
spreading grading to required slope and compacted to meet
requirement of Table No. 300-2 complete as per specifications
(including cost of earth, water charges and compaction by vibratory
roller) MORTH Specification No. 305

For pipe cusions at CDs 3 6.00 1.00 0.650 11.70


For approach slab 3 5.00 6.00 0.300 27.00
For approach slab at 12.00m deck slab 2 5.00 12.00 0.300 36.00
For approach slab at 10.00m deck slab 2 5.00 10.00 0.300 30.00
Page 4

Sl. Description of work No Measurements Contents Total


No. L B D
1 2 3 4 5 6 7 8
For approach slab at 7.50m deck slab 2 5.00 7.50 0.300 22.50
Approaches 2x3 20.00 6.00 0.200 144.00
Backfilling at CDs 2x3 3.00 0.45 1.350 10.94
Murrum spreading (Selected reaches) 1 276.00 4.00 0.150 993.60

1275.74 1275.74
8 Construction of granular sub-base Grading-V as Sub-base and
drainage layer by providing coarse graded crushed stone aggregates
of granite/ trap/basalt material, mixing in a mechanical mix plant at
OMC, Carriage of mixed material to work site, spreading in uniform
layers with motor grader on prepared surface and compacting with
vibratory power roller to achieve the 98 % proctor density, complete as
per specifications.
Clause 401 of MORTH V Revision.

For approach slab 3 5.00 6.00 0.100 9.00


For approach slab at 12.00m deck slab 2 5.00 12.00 0.100 12.00
For approach slab at 10.00m deck slab 2 5.00 10.00 0.100 10.00
For approach slab at 7.50m deck slab 2 5.00 7.50 0.100 7.50
38.50 38.50

9 KSRRB M400-17. Providing, laying, spreading and compacting


cushed stone aggregates of granite / trap / basalt to wet mix macadam
specifications including pre mixing the material with water at OMC in
mechanical mix plant carriage of mixed materials by tipper to site,
laying in uniform layers with paver in sub-base/base course on well
prepared surface and compacting with vibratory roller to achieve the
desired density complete as per specifications. MORTH Specification
No. 406

For approach slab 3 5.00 6.00 0.100 9.00


For approach slab at 12.00m deck slab 2 5.00 12.00 0.100 12.00
For approach slab at 10.00m deck slab 2 5.00 10.00 0.100 10.00
For approach slab at 7.50m deck slab 2 5.00 7.50 0.100 7.50
38.50 38.50
10 Constructing un-reinforced, plain cement concrete for pavements
using Grade concrete M30 over a prepared base with OPC coarse
aggregate at 0.69 cum, fine aggregates at 0.46 cum,Coarse and fine
aggregate conforming to IS:383-2016, with Superplastizer at 3 lts
conforming to IS 9103-2008. mixed in a concrete mixer of not
less than 0.6 cum capacity and appropriate weigh batcher as per
approved mix design, laid in approved fixed side form work (steel
channel, laying and fixing of 125 micron thick polythene film,
wedges, steel plates including levelling the form work as per drawing).
& Spreading the concrete with shovels, rackers compacted using
needle, screed and plate vibrator and finished with floaters in a
continuous operation including provision of contraction, expansion,
construction and longitudinal joints,including groove cutting charges,
joint filler, separation membrane of impermiable plastic sheet of 125
micron, sealant primer, joint sealant, admixtures as approved, curing
compound, finishing to lines and grades, textured with texturing
machine, and curing including cost of all materials, labour,hire charges
of machineries,all lead & lift charges etc., complete as per
specifications.
-do- with OPC at 360 kg/cum and coarse aggregate 0.69cum, fine
For approach slab 3 3.00 6.00 0.200 10.80
For approach slab at 12.00m deck slab 2 5.00 12.00 0.200 24.00
For approach slab at 10.00m deck slab 2 5.00 10.00 0.200 20.00
For approach slab at 7.50m deck slab 2 5.00 7.50 0.200 15.00
69.80 69.80

Section Assistant Executive Engineer


officer PW, P & IWTD. Sub-Division, Deodurga.
Page 1

General Description
PWG 62 (c)
(Paragraph 130 (a) of the Karnataka Public Works Departmental Code)

Construction of CD works at Koppar village in Deodurga In DeodurgaTaluka Raichur District. Under: H.K.R.D.B for the year 2018-19
(MACRO)

RATE ANALYSIS QM / F - 62 (c)


Sl. Description of work Rate
No.
1 2 3

1 KSRRB M300-14. Excavation for roadwork in all types of soil by mechanical means including cutting and
loading to tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross
sections, and transportation with a lead of 1.00 km and complete as per specifications. MORTH Specification
No.301
PWD DSR I. No.19.14 P.No. 143 for 2018-19
Basic Rate 41.00
Add Area Weightage for MICA 5% 2.05
43.05

2 KSRB 2.8 : Providing and Filling in foundation with granite / trap broken metal 100mm. and down size & with
approved sand including hand packing, ramming, watering, including cost of all materials and labour with all
lead and lift. complete as per specifications. specification. No. KBS 2.10.2
PWD DSR I. No.2.15 P.No. 7 for 2018-19
Basic Rate 2282.00
Add 5% for Area Weightage 114.10
@ Rs. 2396.10
3 KSRB 4-1.3 : Providing and laying in position plain cement concrete of Mix 1:4:8 with OPC @ 180kgs, with
40mm and down size graded granite metal coarse aggregates @0.85cum and fine aggregates @ 0.57cum
machine mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in
foundation, including cost of all materials, labour, HOM curing complete as per specifications. Specification No.
KBS 4.1, 4.2
PWD DSR I. No.4.3 P.No.13 for 2018-19
Basic Rate 5114.00
Previllage cement rate (0.90x180=162.00) -162.00
4952.00
Add Area Weightage for MICA 5% 247.60
5199.60
4 Providing and laying plain/reinforced cement concrete for side drains using M20 nominal mix concrete with
OPC at 300 kgs. with 20mm and down size granite metal coarse aggregates at 0.69 cum and fine aggregates
at 0.43 cum machine mixed, well compacted for walls and bottom including centering, shuttering, cost of
materials, HOM of machinery, curing etc., complete excluding cost of steel as per MORTH specification No.
1500, 1700, 2200. including cost of materials, labour, HOM complete as per specifications.
PWD DSR I. No.37.59.2 P.No.271 for 2018-19
Basic Rate 6995.00
Previllage cement rate (0.90x300=270.00) -270.00
6725.00
Add Area Weightage for MICA 5% 336.25
7061.25
5 KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting, bending,
hooking, placing in position, lapping and / or welding wherever required, tying with binding wire and anchoring
to the adjoining members wherever necessary complete as per design (laps, hooks and wastage shall not be
measured and paid) cost of materials, labour, HOM complete as per specifications. Specification No. KBS
4.6.3
PWD DSR I. No.4.46.3 P.No.18 for 2018-19
Basic Rate 70958.00
Add 5% for Area Weightage 3547.90
@ Rs. 74505.90
Page 2

Sl. Description of work Rate


No.
1 2 3
6 Providing and laying reinforced cement concrete pipe NP3 for culverts including pointing ends, and fixing
collars with cement mortar 1:2 including cost of all materials, labour, curing, including cost of materials, labour,
HOM complete as per specifications. Specifications. No. KSRB 1000, 2300 MOST Specification No.1000 /
2300 900mm dia
PWD DSR I. No.34.6.5 P.No.254 for 2018-19
Basic Rate 5501.00
Add 5% for Area Weightage 275.05
@ Rs. 5776.05

7 KSRRB M300-55 : Construction of sub grade and Earthen shoulders. Construction of sub grade and Earthen
shoulders with approved material Gravel / Murrum with all lifts and leads, transporting to site, spreading grading
to required slope and compacted to meet requirement of Table No. 300-2 complete as per specifications
(including cost of earth, water charges and compaction by vibratory roller) MORTH Specification No. 305
PWD/SR/2018-19/ P.No. 147/ I.No.19.62
Basic Rate 588.00
Add Area Weightage for MICA 5% 29.40
617.40

8 Construction of granular sub-base Grading-V as Sub-base and drainage layer by providing coarse graded
crushed stone aggregates of granite/ trap/basalt material, mixing in a mechanical mix plant at OMC, Carriage of
mixed material to work site, spreading in uniform layers with motor grader on prepared surface and compacting
with vibratory power roller to achieve the 98 % proctor density, complete as per specifications.
Clause 401 of MORTH V Revision.
PWD DSR I. No.20.4 P.No. 153 for 2018-19
Basic Rate 1937.00
Add 5% for Area Weightage 96.85
@ Rs. 2033.85

9 KSRRB M400-17. Providing, laying, spreading and compacting cushed stone aggregates of granite / trap /
basalt to wet mix macadam specifications including pre mixing the material with water at OMC in mechanical
mix plant carriage of mixed materials by tipper to site, laying in uniform layers with paver in sub-base/base
course on well prepared surface and compacting with vibratory roller to achieve the desired density complete
as per specifications. MORTH Specification No. 406
PWD/SR/2018-19/ P.No. 155/ I.No.20.18
Basic Rate 1877.00
Add 5% for Area Weightage 93.85
@ Rs. 1970.85

10 Constructing un-reinforced, plain cement concrete for pavements using Grade concrete M30 over a
prepared base with OPC coarse aggregate at 0.69 cum, fine aggregates at 0.46 cum,Coarse and fine
aggregate conforming to IS:383-2016, with Superplastizer at 3 lts conforming to IS 9103-2008. mixed in
a concrete mixer of not less than 0.6 cum capacity and appropriate weigh batcher as per approved mix
design, laid in approved fixed side form work (steel channel, laying and fixing of 125 micron thick
polythene film, wedges, steel plates including levelling the form work as per drawing). & Spreading the
concrete with shovels, rackers compacted using needle, screed and plate vibrator and finished with
floaters in a continuous operation including provision of contraction, expansion, construction and
longitudinal joints,including groove cutting charges, joint filler, separation membrane of impermiable plastic
sheet of 125 micron, sealant primer, joint sealant, admixtures as approved, curing compound, finishing to lines
and grades, textured with texturing machine, and curing including cost of all materials, labour,hire charges of
machineries,all lead & lift charges etc., complete as per specifications.
-do- with OPC at 360 kg/cum and coarse aggregate 0.69cum, fine aggregate 0.46cum.
PWD/SR/2018-19/ P.No. 176/ I.No.22.6.1
Basic Rate 5004.00
Previllage cement rate (0.90x360=324.00) -324.00
4680.00
Add Area Weightage for MICA 5% 234.00
4914.00
Page 3

Sl. Description of work Rate


No.
1 2 3

Section Assistant Executive Engineer


officer PW, P & IWTD. Sub-Division, Deodurga.
Page 4

year 2018-19

Rate

/Cum

/Cum

/Cum

/Cum

/Tonne
Page 5

Rate

/M

/Cum

/Cum

/Cum

/Cum
CERTIFICATE
Name of work Construction of CD works at Koppar village in Deodurga In
DeodurgaTaluka Raichur District. Under: H.K.R.D.B for the
year 2018-19 (MACRO)

***

Certified that, I have personally visited the spot


prepared the estimates, using the sanctioned schedule rates and
providing for the most economical and safe way of executing
the work

Certify that the Deodurga taluka is covered under major


irrigation commend area of KBJNL project . There fore an
additional 5% Area Weightage is considered over DSR rates of
2016-17

Section officer Assistant Executive Engineer


PW, P & IWTD. Sub-Division, Deodurga