Professional Documents
Culture Documents
School ID : 28215000406
ESTIMATE COST : 6.50 lakhs
The Working estimate for the work "CONSTRUCTION OF COMPOUND WALL KGBV SCHOOL AT
TUGGALI VILLAGE" the Estimate is prepared with the following provision. For favor of according Administrative
Sanction
1 Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy & Clayey Soils like BC Soils, Red
Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour charges such as shoring, strutting, sheeting,
planking and dewatering including cost of hire charges of T & P, labour charges etc., complete for finished item of work including
seignerage charges excluding dewatering charges etc., complete for Foundation of Building.(APSS No. 308)
2 Plain Cement Concrete corresponding to M15 grade as per IS 456 equivalent to (1:5:10) proportion nominal mix (cement: fine
aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved quarry including cost and
conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including seigniorage charges, sales & other taxes
on all materials, all operational, incidental, and labour charges such as mixing, laying and ramming concrete in layers in position not
exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished item of work for Foundations and Flooring Bed
(APSS No. 402)
3 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blasted granite machine
crushed graded metal (Coarse aggregate) from approved quarry, including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage charges on all materials including centering using Steel
scaffolding pipes, jack props, wallers, foot plates, brackets, steel centering plates, etc., shuttering , machine mixing, laying concrete,
vibrating,lift charges, curing etc., complete but excluding cost of steel and it’s fabrication charges for finished item of work for
foundation, plinth , pedastals(below plinth)(APSS No. 402 & 403) : Columns Footings
4 Random Rubble stone masonry, in CM (1:6) prop: (Cement: Sand) using Hard blasted Granite stones from approved quarry including
cost and conveyance of all materials like Granite stones, cement, sand, water, etc., to site including seigniorage charges, sales & other
taxes on all materials, all operational, incidental, and labour charges such as cutting stones to required size and shape, mixing of
cement mortar, constructing masonry, curing etc., complete for finished item of work for foundation and basement (APSS No. 601 &
615)
5 Brick Masonry in CM (1:6) with Fly ash cement/lime solid blocks with compressive strength of 75 kg/sq.cm - IS:12894-1990 - CLASS -
7.5 - 290 x 225 x 140 mm
6 plastering with CM(1:8) Prop: 12mm thick in single coat including cost and conveyance of all materials like cement, sand, water etc., to
site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental charges and labour charges such as
mixing mortar, finishing, curing, etc., complete for finished item of work. (APSS 901,906)
7 Painting, 2 Coats with Acrylic Paint Exterior Grade with silicon adhesives having VOC (Volatile Organic Compound) content less than
50 grams / liter.
8 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specifications for Bars
below 36 mm dia including over laps and wastage, where they are not welded
The Estimate is prepared with current SSR 2019-20 and Seignorage charges the work will be executed as
per the Detailed Standard Specifications of APDSS
5 CW05 : Grade - II Metal Consisting of 63mm to Cum 19380 0.00 0.00 0.00
45mm IRC HBG/HBT metal 96% and 19mm to
22mm IRC HBG metal 4%
6 CW06 : Grade - III Metal Consisting of 53mm Cum 19381 0.00 0.00 0.00
to 22.4mm IRC HBG/HBT metal 95% and
20mm to 10mm IRC HBG metal 5%
7 CW07 : 20mm to 12mm HBG/HBT graded Cum 19382 0.00 0.00 0.00
metal consisting of 20mm metal 60% and
12mm metal 40%
8 CW08 : Graded metal consisting of 60% of Cum 19383 0.00 0.00 0.00
40mm and 40% of 20mm to 10mm graded
HBG/HBT metal
9 CW09 : 40mm Nominal HBG/HBT Graded Cum 19384 1.80 1026.10 1845.00
Metal
10 CW10 : Cost towords engaging skilled labour, Rs 19385 1.00 537052.75 537053.00
Semi skilled labour, Other materials and
equipment charges including all other material
not covered above
11 CW11 : VAT added in Lead Rs 19386 1.00 0.00 0.00
14 CW14 : Cost of NP, Other Pipes and Precast Rs 19389 1.00 0.00 0.00
chambers etc.,
15 CW15 : LS amount for unforseen items Rs 19390 1.00 130.00 130.00
650000.00
Name of the official filling the details : A Venkateswarlu
Designation of the official filling the details : Mandal Engineer
Signature :
LEAD STATEMENT
NAME OF THE WORK: CONSTRUCTION OF COMPOUND WALL TO KGBV SCHOOL AT TUGGALI VILLAGE
Conveyance
Initial cost
Charges Machine
Lead in Excluding excluding Blasting
S.No Description of materials Source of supply 13.615% crushing GST GST % Unit Net Rate
Kms Seigniorage Charges
contractor charges
profit charges
1 2 3 5 6 7 8 9 10 11 4 14
1 Sand for Concrete Gudikambali 103 1044.00 510.00 25.50 5% Cum 1579.50
2 Sand for filling Gudikambali 103 1044.00 375.00 18.75 5% Cum 1437.75
3 Sand for Mortar Gudikambali 103 1044.00 590.00 29.50 5% Cum 1663.50
4 R.R.Stone for masonry Ratana 9 120.50 250.00 70.00 12.50 5% Cum 453.00
7 40mm HBG Metal Pattikonda 13 165.70 608.00 70.00 152.00 30.40 5% Cum 1026.10
8 20mm machine crushed metal Pattikonda 13 165.70 1016.00 70.00 254.00 50.80 5% Cum 1556.50
9 Steel(HYSD) At Site 36500.00 6570.00 18% 1 MT 43070.00
11 2 nd class bricks 23 x 11 x7cm G.Erragudi 18 359.80 6000.00 300.00 5% 1000 nos 6659.80
12 Fly ash cement/lime solid blocks with G.Erragudi 18 359.80 2750.00 137.50 5% 110 Nos 3247.30
compressive strength
of 75 kg/sq.cm - IS:12894-1990 -
CLASS - 7.5 - 290 x 225 x
140 mm
Certified that the leads provided above are true and nearest to the best of my knowledge
b Pedastals
Column Footings 1 x 37 0.45 0.45 0.60 4.50
4.50 7219.35 Cum
e Plinth beams
Around Compound 1 x 1 110.00 0.30 0.30 9.90
Wall
9.90 8798.345 Cum
c Columns
Columns 1 x 37 0.30 0.30 1.50 5.00
5.00 8943.35 Cum
5 Brick Masonry in CM (1:6) with Fly ash cement/lime solid blocks with
compressive strength of 75 kg/sq.cm - IS:12894-1990 - CLASS - 7.5 -
290 x 225 x 140 mm
Amount
12
3264.00
6176.00
Amount
12
62479.00
32455.00
87104.00
44672.00
172180.00
Amount
12
41193.00
35558.00
91134.00
45000.00
20000.00
641215.00
0.00
5449.00
3206.00
130.00
650000.00
Unit = 1cum
A. MATERIALS:
Cement kg 129.60 4.80 622.08
Coarse aggregate 40 mm cum 0.90 1026.10 923.49
Fine aggregate (Sand) cum 0.45 1579.50 710.78
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 0.61 394.40 200.80
capacity
C. LABOUR:
Mason 1st class day 0.10 500.00 50.00
Mazdoor (unskilled) day 1.39 420.00 583.80
Grand Total 3090.95
R.C.C. M-20 Nominal Mix
RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) corresponding to Table 9 of
IS 456 using 20mm size graded machine crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including sales & other taxes on all materials
including all operational, incidental and labour charges such as machine mixing, laying concrete,
curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of
work, but excluding centering, shuttering.
S
Description Unit Quantity Rate Rs. Amount Rs.
No
A FOUNDATIONS, PLINTH, PEDESTALS
(Below Plinth)
A. MATERIALS:
20mm HBG M/c metal cum 0.900 1556.50 1400.85
Sand cum 0.450 1579.50 710.78
Cement Kgs 330.000 4.80 1584.00
B. LABOUR: 0.00
1st Class Mason day 0.133 500.00 66.50
2nd Class Mason day 0.267 460.00 122.82
Mazdoor (Both Men and Women) day 3.600 420.00 1512.00
B. MACHINERY 0.00
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.000 394.40 394.40
capacity
Cost of Diesel for Miller Liters 0.133 0.00 0.00
Cost of Petrol for Vibrator Liters 0.667 0.00 0.00
Water (including for curing) kl 1.200 80.00 96.00
BASIC COST per 1 cum 5887.35
4 Footings
BASIC COST per 1 cum 5887.35
centering charges 919.00
6806.35
5 Pedastals
BASIC COST per 1 cum 5887.35
centering charges 1332.00
7219.35
6 Plinth beams
BASIC COST per 1 cum 5887.35
centering charges 2911.00
8798.35
7 Columns 6320.35
centering charges 2623.00
BASIC COST per 1 cum 8943.35
8 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings
and technical specifications for Bars below 36 mm dia including over laps and wastage, where
they are not welded
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps t 1.05 43070.00 45223.50
and wastage
Binding wire kg 6.00 60.00 360.00
(b) Labour for cutting, bending, shifting to 0.00
site, tying and placing in position
Blacksmith / Bar bender day 2.00 495.00 990.00
Mazdoor (Unskilled) day 6.40 420.00 2688.00
Sundries on Material
Rate per t = a+b+c+d 49261.50
9 Brick Masonry in CM (1:6) with Fly ash cement/lime solid blocks with compressive strength of 75
kg/sq.cm - IS:12894-1990 - CLASS - 7.5 - 290 x 225 x 140 mm
Unit = 1cum
A. MATERIALS:
Cement kg 48.00 4.80 230.40
Fly ash cement/lime solid blocks with Nos 110.00 29.52 3247.30
compressive strength of 75 kg/sq.cm -
IS:12894-1990 - CLASS - 7.5 - 290 x 225 x 140
mm
10 RR Masonry in CM (1:6)
Unit = 1cum
A. MATERIALS:
Cement kg 79.20 4.80 380.16
S
Description Unit Quantity Rate Rs. Amount Rs.
No
CR Stone cum 0.44 453.00 199.32
Rough Stone cum 0.50 453.00 226.50
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = cum 0.16 2203.00 352.48
0.16cum
Fine aggregate (Sand) cum 0.33 1579.50 521.24
Seigniorage charges for F.A cum 0.33 0.00 0.00
Seigniorage charges for Stone cum 1.10 0.00 0.00
B. LABOUR: 0.00
Mason 1st class day 1.20 500.00 600.00
Mazdoor (unskilled) day 2.00 420.00 840.00
Grand Total 3119.69
PLASTERING
11 Plastering with CM (1:8), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.15 2527.50 379.13
Seigniorage charges for F.A cum 0.15 0.00 0.00
B. LABOUR: 0.00
Mason 1st class day 0.60 500.00 300.00
Mazdoor (unskilled) day 0.96 420.00 403.20
Rate per 10 sqm 1082.33
12 Painting, 2 Coats with Acrylic Paint Exterior Grade with silicon adhesives having VOC (Volatile
Organic Compound) content less than 50 grams / liter.
Unit: 10 sqm
A. MATERIALS :
Acrylic Emulsion Paint Kg 1.70 194.00 329.80
B. LABOUR
SCHOOL BUILDING
HOSTEL
95 m
3.0 m
Name of the Work: CONSTRUCTION OF COMPOUND WALL TO KGBV SCHOOL AT TUGGALI VILLAGE
Caluculation of Quantities for Simplified tasks
CW09 : 40mm
Rs.205/- day
Cum in data
Cum in data
Cum in data
Cum in data
Amount
Days @
Rate
Qty
Qty
Qty
1 3 4 7 8 9 10 11 12 13 14 19
1 Earth work excavation for 26.27 3264.00 205.00 3264.00 15.922
2 Plain Cement Concrete of (1:5:10) 2.00 6176.00 2.00 5.18 2.00 0.90 2.00
7 Brick Masonary in superstructure with CM (1:8) 32.05 172180.00 32.05 30.77 32.05 6.41
11 Gate 1 No 45000.00
Amount
Qty
20 21 22
4886.87 21968.91
6465.81 64011.51
6610.77 33020.79
2190.58 43871.38
4809.05 154132.36
49261.62 91134.00
70.32 26763.50
35558.00
45000.00
20000.00
0.00
1.80 537052.75