Professional Documents
Culture Documents
Abstract estimate
Sl. Data Reference Quantity Units Description of items Rate per Amount
No. Code
1 2 3 4 5 6
Excavation in ordinary rock (including HDR) without
blasting including boulders above 0.30 m upto 0.6 m
dia. for canals, seating of embankment, filter drain /
catch water drains etc., including dressing of bed and
IRR-CAW-1-3
Excavation in ordinary rock (including HDR) without blasting including boulders above
IRR-CAW-1-3
0.30 m upto 0.6 m dia. For canals, seating of embankment, filter drain / catch water drains etc.,
1 including dressing of bed and sides to required level and profile, cost of all materials,
machinery, labour, placing the excavated soft rock neatly in dump area or for formation
of service road as directed etc., complete with lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 872.70 6981.60
2 Tippers 5 cum capacity 5 Nos Hour 40.00 446.70 17868.00
Fuel / Energy charges Hour 40.00 299.90 11996.00
Total hire charges of Machinery Rs: 50498.40
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 236.60 1892.80
2 Crew for Tipper Hour 40.00 177.50 7100.00
3 work inspector Day 1.00 450.00 450.00
4 Crowbarman Day 11.00 400.00 4400.00
5 mazdoor Day 22.00 350.00 7700.00
Total cost of Labour Rs: 21542.80
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 50498.40
C. Cost of Labour Rs: 21542.80
Total Rs: 72041.20
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 9808.41
Total cost for 630.00 cum Rs: 81849.61
Rate per cum (A+B+C+D)/630 Rs. 129.90
Or say Rs. 129.90
Providing hearting / casing embankment with homogeneous soil from approved borrow
IRR-CAW-2-7
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Angle dozer 90 hp Hour 6.06 1715.50 10395.93
Fuel / Energy charges Hour 6.06 610.50 3699.63
2 Shovel 0.5 cum Hour 8.00 1003.10 8024.80
Fuel / Energy charges Hour 8.00 476.00 3808.00
SSR 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Dozer Hour 6.06 236.60 1433.80
2 Crew for Shovel Hour 8.00 236.60 1892.80
3 Crew for Tipper Hour 48.00 177.50 8520.00
4 Crew for Pump Hour 3.00 111.10 333.30
5 Crew for Water tanker Hour 6.00 177.50 1065.00
6 Crew for Roller Hour 6.16 263.60 1623.78
7 work inspector Day 2.00 450.00 900.00
8 mazdoor Day 4.00 350.00 1400.00
Total cost of Labour Rs: 17168.67
ABSTRACT:
A. Cost of Materials Rs: 69759.84
B. Hire charges of Machinery Rs: 81019.44
C. Cost of Labour Rs: 17168.67
Total Rs: 167947.95
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 22866.11
Total cost for 677.28 cum Rs: 190814.06
Rate per cum (A+B+C+D)/677.28 Rs. 281.74
Add for Lead charges:
Lead Charges for gravel for 5 Kms 1.00 84.00 Rs. 84.00
Rate per sqm Rs. 365.74
Or say Rs. 365.70
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
IRR-CCDW-2-10
15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
3 machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
3 Water tanker 8000 ltr Hour 1.00 402.50 402.50
SSR 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Vibrator Hour 8.00 158.20 1265.60
5 Mason Class-I Day 1.00 445.00 445.00
6 work inspector Day 1.00 450.00 450.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 4.00 350.00 1400.00
for conveying concrete Day 15.71 350.00 5498.50
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 31.42 88.50 2780.67
Labour cost for scaffolding @ 25% 695.17
Total cost of Labour Rs: 20125.59
ABSTRACT:
A. Cost of Materials Rs: 53095.46
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 20125.59
Total Rs: 75241.80
D. Add for contractor's profit and overheads on (A 13.615% Rs: 10244.17
Total cost for 15.71 cum Rs: 85485.97
Rate per cum (A+B+C+D)/15.71 Rs. 5441.50
Add for Lead charges:
Lead Charges for FA for 34 Kms 0.45 441.00 198.45
Lead Charges for CA for 25 Kms 0.80 336.00 Rs. 268.80
Rate per cum Rs. 5908.75
Or say Rs. 5908.80
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
IRR-CCDW-2-3
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
4
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
with initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of super
plasticiser(0.4% by wt. of cement), CA : 0.90cum, Blending Ratio of CA--50:30:20,
FA : 0.40 cum)
Data RATE ANALYSIS UNIT : 15.38 cum
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Cement for mix kg 3998.80 6.40 25592.32
Cement for incidentals @ 3 kg / cum kg 46.14 6.40 295.30
2 Coarse aggregate 40-20 mm cum 6.92 1175.00 8132.18
Coarse aggregate 20-10 mm cum 4.15 1225.00 5086.94
Coarse aggregate 10 mm below cum 2.77 900.00 2491.56
3 Fine aggregate (Un-Screened) cum 6.15 95.00 584.44
4 Super Plasticizer kg 16.00 55.00 879.74
5 Use rate of shuttering for 40 uses sqm 15.38 224.57 3453.85
Scaffolding @ of shuttering 10% 345.38
6 Sundries LS 0.50 30.00 15.00
Total cost of Materials Rs: 46876.70
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 79.30 634.40
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 79.30 39.65
SSR 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 219.70 1757.60
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.50
4 Crew for Needle vibrator Hour 8.00 158.20 1265.60
5 work inspector Day 1.00 450.00 450.00
6 Mason Class-I Day 1.00 445.00 445.00
7 mazdoor
for batching materials Day 11.00 350.00 3850.00
for loading mortar pans Day 4.00 350.00 1400.00
for laying Day 3.00 350.00 1050.00
for conveying concrete Day 15.38 350.00 5383.00
for cleaning/ washing/ curing Day 1.00 350.00 350.00
8 Labour cost for shuttering sqm 15.38 88.50 1361.13
Labour cost for scaffolding @ 10% 136.11
Total cost of Labour Rs: 17681.49
ABSTRACT:
A. Cost of Materials Rs: 46876.70
B. Hire charges of Machinery Rs: 2020.75
C. Cost of Labour Rs: 17681.49
Total Rs: 66578.94
D. Add for contractor's profit and overheads on
(A+B+C) 13.615% Rs: 9064.72
Total cost for 15.38 cum Rs: 75643.66
Rate per cum (A+B+C+D)/15.38 Rs. 4918.31
Add for Lead charges:
Lead Charges for FA for 34 Kms 0.40 441.00 Rs. 176.40
Lead Charges for CA for 25 Kms 0.90 336.00 Rs. 302.40
Rate per cum Rs. 5397.11
Or say Rs. 5397.10
Providing and fixing 25 mm diameter steel rock bolts with resin bond cement capsule
IRR-TAW-3-2
anchorage including drilling 35 mm dia holes, inserting grout capsule, driving bolt,fixing 10 mm
5 thick plate washers and nuts and tightening the same by torque wrench after hardening of
cement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and other
ancillary operations etc., complete with lead upto 1 km and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Air compressor 15 cmm ( ele ) Hour 1.50 138.80 208.20
Fuel / Energy charges Hour 1.50 700.50 1050.75
2 Pump 10 hp ( ele ) Hour 1.00 6.70 6.70
Fuel / Energy charges Hour 1.00 56.00 56.00
3 Jack hammer Hour 6.00 19.80 118.80
SSR 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Air compressor Hour 1.50 175.80 263.70
2 Crew for pump Hour 1.00 83.30 83.30
3 Crew for Jack hammer Hour 6.00 329.60 1977.60
4 Crew for Drilling jumbo Hour 4.00 175.80 703.20
5 Fitter Day 0.50 400.00 200.00
6 Gas cutter Day 1.00 445.00 445.00
7 Turner Day 1.00 510.00 510.00
8 Khalasi ( 2 x 0.5 ) Day 1.00 445.00 445.00
9 Hammerman Day 0.50 400.00 200.00
10 mazdoor Day 2.00 350.00 700.00
Total cost of Labour Rs: 5527.80
ABSTRACT:
A. Cost of Materials Rs: 7041.61
B. Hire charges of Machinery Rs: 3251.45
C. Cost of Labour Rs: 5527.80
Total Rs: 15820.86
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 2154.01
Shortcreting in two layers (each layer+38 mm thickness) for slabs duly fixing chain weld
as per IRR-
TAW-2-3
wire mesh 100 x 100x5 mm in between the two layers including cost and conveyance of
6
all materials, labour charges laying concrete with shortcrete machine etc, all heads, lifts,
centering, scaffolding, machine mixing, . complete as per specification and as
directed by Engineer-in-Charge
Note: in IRR TAW 2-3 Super palsticizer @ 1 % of wt.of cement & Accelerator @ 5% of wt.of cement is
added as per CE CDO drawings
Data RATE ANALYSIS UNIT : 36.00 sqm
A. MATERIALS:
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs.
1 Cement kg 1548.00 6.40 9907.20
2 Sand (Screened) cum 2.41 165.00 397.65
3 Coarse aggregate 10-4.75 mm size cum 1.03 900.00 927.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Guniting equipment Hour 8.00 110.10 880.80
SSR 2016-17
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Guniting equipment Hour 8.00 219.70 1757.60
2 Crew for Air compressor Hour 8.00 164.80 1318.40
3 Crew for pump Hour 1.00 83.30 83.30
4 Crew for Drilling jumbo Hour 4.00 175.80 703.20
5 Mason Cl I Day 1.00 445.00 445.00
6 mazdoor Day 6.00 350.00 2100.00
Total cost of Labour Rs: 6407.50
ABSTRACT:
A. Cost of Materials Rs: 35480.62
B. Hire charges of Machinery Rs: 6536.30
C. Cost of Labour Rs: 6407.50
Total Rs: 48424.42
D.Add for contractor's profit and overheads on
(A+B+C+other percentages) 13.615% Rs: 6592.98
Total cost for 36.00 sqm Rs: 55017.40
Rate per sqm (A+B+C+D)/36.0 Rs: 1528.26
Add for Lead charges:
Lead Charges for FA for 34 Kms 0.0669 441.00 29.50
Lead Charges for CA for 25 Kms 0.0286 336.00 Rs. 9.61
Rate per sqm Rs. 1567.37
Or say Rs. 1567.40
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
IRR-CAW-7-15
aggregates for bed and side lining of canal(100 mm thick) including finishing the junction of
bed and sides to required curveture, cost of all materials, machinery, labour, formwork including
7
supports,cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 300 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 16.00 219.70 3515.2
2 Crew for Pump Hour 0.50 111.10 55.55
3 Crew for Water tanker Hour 1.00 177.50 177.5
4 Crew for Vibrator Hour 16.00 158.20 2531.2
5 Mason Class-I Day 2.00 445.00 890
6 work inspector Day 1.00 450.00 450
7 Fitter Day 1.00 475.00 475
8 mazdoor
for batching materials Day 22.00 350.00 7700
for loading mortar pans Day 8.00 350.00 2800
for laying and moving paver Day 6.00 350.00 2100
for conveying concrete Day 23.10 350.00 8085
for cleaning/ washing/ curing Day 2.00 350.00 700
Total cost of Labour Rs: 29479.45
ABSTRACT:
A. Cost of Materials Rs: 74578.60
B. Hire charges of Machinery Rs: 5191.95
C. Cost of Labour Rs: 29479.45
Total Rs: 109250.00
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 14874.39
Total cost for 23.10 cum Rs: 124124.39
Rate per cum (A+B+C+D)/23.10 Rs. 5373.35
Add for Lead charges:
Lead Charges for FA for 34 Kms 0.45 441.00 198.45
Lead Charges for CA for 25 Kms 0.80 336.00 Rs. 268.80
Rate per cum Rs. 5840.60
Or say Rs. 5840.60
8 for concrete lining by mastic filler including cost of all materials, labour etc., complete with
36
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Nill 0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Mason Cl- II Day 0.50 400.00 200.00
2 mazdoor Day 1.00 350.00 350.00
Total cost of Labour Rs: 550.00
ABSTRACT:
A. Cost of Materials Rs: 1616.60
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 550.00
SSR 2016-17
Seignorage Charges calculations ( G.O MS No.100 Dt: 31-10-2015 Industries & Commerce Department)
Sl.No. Description Total Qty Seignorage Charges per Cu.m amount
1 Sand 2054.00 50 102700
Coarse
2 Aggregate 1973.00 75 147975
3 Gravel 0.00 30 0
Total Seignorage charges = Rs. 250675 /-
DATA SSR 2016-17
Laying and fixing of 160 mm Dia 300 mm long precast porus CC plugs in bed and sides
as per IRR-
CAW-5-7
using 20 mm HG metal and placing in local filters of size 600x600x750 mm in size
34
including Excavation of drains and Cost of procuring of all materials including 50 m lead
and for all lifts.
in IRR CAW 5-7 laying & fixing 100 mm dia 300 mm long is available . But as per CE CDO drawing size of
Note: porous plug is 160 mm dia 300 mm long hence data is worked out accordingly.
DATA:
EWE in all soils= 1x0.60x0.75x0.60 = 0.27 cum
Volume of plug=3.14/4*0.16*0.16= 0.006
Quantity of metal 20-40 mm= 0.32*0.32*0.375-vol.of plug 0.032
Quantity of metal 05 to 20 mm=0.48*0.48*0.45-0.32*0.32*0.375 0.065
Quantity of Sand = 0.525*0.6*0.6-0.48*0.48*0.45 0.085
Plug
metal Qty = 3.14/4*0.16*0.16*0.375*80% 0.006
Qty of Metal ( 0.032+0.065+0.006) 0.103
A. MATERIALS:
Unit
Sl.No Particulars Qty Rate in Rs Amount in Rs.
1 Coarse aggregate 40 mm Cum 0.032 1175.00 37.60
2 Coarse aggregate 20 mm Cum 0.071 1225.00 86.98
3 Sand (Un-Screened ) cum 0.117 95.00 11.12
4 Cement Kg 3.15 5.00 15.75
Total cost of Materials Rs. 151.44
B. MACHINERY
Sl.No Description Unit Quantity Rate in Rs. Amount in Rs.
C. LABOUR
Unit
Sl.No Particulars Qty Rate in Rs Amount in Rs.
1 Mazdoor Day 0.30 350.00 105.00
Total cost of Labour Rs. 105.00
ABSTRACT
A. Cost of Materials Rs. 151.44
B. Hire charges of Machinery Rs. 12.27
C. Cost of Labour Rs. 105.00
Total Rs: 268.71
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 36.58
Total cost for 1.00 Plug Rs: 305.29
Rate per each plug (A+B+C+D)/1.0 Rs. 305.29
Add for Lead charges:
Lead Charges for FA for 34 Kms 0.117 441.00 Rs. 51.60
DATA SSR 2016-17