BOQ OF EXTENSION WORK FOR FACTORY SHED-GUJARAT INFRA PIPE PVT LTD

AREA 4136.39325 SQM


PLINTH HEIGHT 0.9 RMT

SR.NO. DESCRIPTION OF ITEMS QTY. RATE UNIT AMOUNT

A UPTO PLINTH LEVEL


1 SURFACE DRESSING / SITE CLEANING
Labour charges for grubbing and clearing Road / land including clearing top soil,
including all plants, vegetations, dirts etc. complete,etc with dumping all the nonuseful
stuff materials into the plot boundary , as per instruction of site engg. for the location 4136.39 smt 0.00
[Max depth @ 150 mm assumed ]

2 EXCAVATION WORK
Earth work in excavation below existing ground level in foundations, trenches, in all class
of soil / murrrum except rock up to a depth of 1.50 mtrs. Including shoring, strutting,
dewatering, and disposing off the un useful soil outside the plot boundary complete as
directed by Engineer IN charge.
a ( upto 1.50 )
Do--- as above in depth 0 mtrs. To 1.50 mtrs. 1284.86 cmt. 0.00
b ( upto 3.00 )
Do--- as above in depth 1.50 mtrs. To 3.00 mtrs. 905.15 cmt. 0.00
c Do--- as above in depth 3.0 mtrs. To 4.50 mtrs. R/O cmt.

3 BACK FILLING WORK


Filling in foundation & in Plinth with selected(Non Expansive) earth spread in layers of
150 to 230 mm thickness to achieve required level and slope / gradient and compacted to
95% of proctor density and leveling finally as per the instruction of Engineer-In-Charge
inclusive cost of soil, transportation and all taxes and royalties .
a Available soil 1662.16 cmt 0.00
b Earth brought from outer side for Plinth filling
Murrum filling 1630.32 cmt 0.00

4 Metalling [ 63-90 mm ]
Providing and laying metal (size 63mm x 90mm) in a layer of 175mm each well
compacted with power roller without damaging foundation filling voids with quarry dust,
watering, ramming, compacting if required for edges and corners use plate compactor 827.28 cmt 0.00
etc. complete as directed by Engineer In charge.

5 PLAIN CEMENT CONCRETE [M10-1:3:6]


Providing and laying cement concrete in foundation and plinth M:10 [Site mix] and curing
complete including cost of formwork as directed by Engineer In charge.
Total Qty. for Metal concrete(PCC) 381.04 cmt 0.00

6 RCC work [ in M25 Grade ]


Providing and laying controlled reinforced Cement Concrete of M25 grade with
20mm down size graded crushed stone aggregate including scaffolding, opening, recesses,
chamfering, finishing top surfaces vibrating, machine mixing tamping, curing (excluding
centering and shuttering) etc. complete as per the specifications, drawings and instruction of
Engineer - in- charge (excluding cost of reinforcement) for all elements of concrete

a Total Qty. for RCC footings 364.74 cmt. 0.00


b Total qty. for RCC columns (Pedestal ) 156.25 cmt. 0.00
c Total Qty. for RCC groundbeams 59.64 cmt. 0.00
d Total Qty. for copping beams 6.32 cmt. 0.00

7 BRICK MASONARY WORK


Providing and constructing Conventional Brick masonry in CM 1:6 (1 Cement and 6
Coarse sand) upto plinth with conventional size bricks having minimum crushing
strength of 35 Kg / Sq. Cm. including scaffolding, racking out joints, curing, watering etc.,
complete as directed by Engineer IN charge.
a Total qty. of brick work upto P.L. (230 mm thick) (1:6) proportion 10.72 cmt. 0.00

PAGE NO:1
8 REINFORCEMENT STEEL FE 500
Providing & Supplying & fixing in position High yield deformed bar Reinforcement
confirming to IS – 1139 or cold Twisted bars, TOR steel / TMT / or Equivalent
Reinforcement bars confirming to IS – 1786 for RCC construction including transporting
(i.e. loading & unloading) the steel from store/issue points to site of works including
unloading from Trucks/Trailers, cleaning, de coiling, cutting, bending to required shape
and lengths as per detailed drawing, binding with 16 SWG black soft annealed binding
wire, placing with proper cover block, support chairs, overlap, spacers, etc. complete in all
respect as directed by Engineer IN charge in foundation and up to Plinth level.

a 8MM DIA 2.00 MT 0.00


b 10MM DIA 1.08 MT 0.00
c 12MM DIA 3.51 MT 0.00
d 16MM DIA 0.21 MT 0.00
e 20MM DIA 0.00 MT 0.00
f 25MM DIA 0.00 MT 0.00

9 SHUTTERING
Providing and erecting in position form work with plate shuttering materials of
approved quality for all type of concrete elements vertical, horizontal or inclined including
scaffolding, stagging, fasteners,locking ,Ties at respective levels necessary nails, wires,
locking pins,Guggus etc keeping in position till concrete is laid and members have 1342.63 sqm 0.00
acquired required strength, removal thereafter, applying shuttering oil etc. complete as
directed by Engineer-in-Charge.

10 RCC Tremix Flooring [M:25] --only concrete pourng work


Providing and laying conventional cement concrete M-25, 200 mm thick in alternate
panels for flooring. Panels shall be formed by MS channel 100 mm depth on all four sides
and bolted adequately to make the panel size as required. Entire concrete mass shall be
vibrated with screed vibrators and levelled etc ,including the cost of form work but 827.28 cmt 0.00
excluding cost of reinforcement, and curing by pounding the surface of concrete,
complete as directed by Engineer IN charge..

11 Outside Double coat Sand faced Plaster OR Mala Plaster


Providing and applying 20 mm th. double coat sandfaced or mala cement plaster on any
surface, consisting of 12 mm thick backing coat in CM 1:3 with water proofing compound
(1:Cement and 3:Coarse sand) & 8 mm thick finishing coat in CM 1:1 with water proofing
compound (Q 200ml /bag as dosage)(1:Cement and 1:Coarse sand) to walls, beams,
column, drain, bends, moulds, making grooves, pattas and all brick and RCC surfaces
164.74 smt. 0.00
including raking joints, scaffolding, curing finishing.The plaster surface shall have rough
finish by using sponge on all types of surfaces in line level and including all scaffolding
and curing & level at all level above plinth and upto ground floor level complete as
directed by Engineer IN charge

12 TRIMIX WORK-Final finisihing work


Extra for using "Tremix system " (vacuum dewatering system and smooth finishing and
after that smooth finish with power trowel) in flooring.etc complete incl.all cost and as per 4136.39 smt 0.00
instruction of Engg Incharge .

13 Groove cutting
Providing and constructing groove cutting of size 5mm x 50mm deep for floor , including
saw cutting of concrete floors / pavement to the required depth, filling the same with 2068.20 rmt 0.00
polysulpide, etc. complete.as per instruction of Engg in charge.

14 Foundation Bolt Fixing


Labour charges for Positioning Foundation Bolts in the pedastals maintaining all the line
& level , confirming from the responsible Engineer etc as per detailed drawing, to keep
the bolts in position as required ,etc. complete as directed by Engineer In Charge. 722.00 nos 0.00

15 GP2 Grouting
Filling the gap between RCC column, base plate and floor with GP2 Grout of M45 I S I
grout to consume shall confirm to company Equavalient of SIKA make / Fair mate / Dr.
fixit etc. as per I S Specification including the all the over head expesnes and the edges 3.24 cmt 0.00
shall be shampered etc completed as directed by Engineer Incharge.

16 Re-bar
Providing, drilling & fixing anchor bars in concrete using Hilti HY-150 chemical grout as
per as per manufacturer's specifications. [ necessary pull out test --if recommended by
consulltant have to be proved , which rate shall not be extra paid etc complete as
directed by engg. incharge .

PAGE NO:2
a 8mm dia #NAME? NOS #NAME?
b 16mm dia 110.00 NOS 0.00

TOTAL AMOUNT FOR CIVIL WORK #NAME?

PAGE NO:3
TIE BEAM
Sr.
Particular
no. L B H

1 GB1 (SIZE IN METER) 6.096 0.230 0.450



Number of beams 24.000

Extra top bars

→ STIRRUPS

2 GB2 7.112 0.230 0.450



Number of beams 18.000
Extra top bars

→ STIRRUPS

3 PB1 6.096 0.230 0.450



Number of beams 24.000

Extra top bars

→ STIRRUPS
BAR BENDING SCHEDULE - GB/PB

Dia of
No. of No. of
Shape of Bar Bar in
bar item
mm

0.250 6.046 0.250 12 3 24

0.250 6.046 0.250 12 3 24

0.250 3.023
12 0 24

0.180
0.075 8 42 24
0.400 0.075 0.400

0.180

0.250 7.062 0.250 12 3 18

0.250 17.655 0.250 12 3 18


0.250 8.828
0 0 18

0.180
0.075 8 48 18
0.400 0.075 0.400

0.180

0.250 6.046 0.250 12 3 24

0.250 6.046 0.250 12 3 24

0.250 3.023
0 2 24

0.180
0.075 8 42 24
0.400 0.075 0.400

0.180
ING SCHEDULE - GB/PB

Weig
Total wt
Spacing in Length in Total length
8mm Total wt 10mm
mtr mtr in mtr
(0.395 (0.617 kg/mt)
kg/mt)

6.546 471.312 - -

6.546 471.312 - -

3.273 0.000 - -

0.150 1.310 1320.480 521.590 -

7.562 408.348 - -

18.155 980.370 - -
9.078 0.000 - -

0.150 1.310 1131.840 447.077 -

6.546 471.312 - -

6.546 471.312 - -

3.273 157.104 - -

0.150 1.310 1320.480 521.590 -

TOTAL 1490.256 0.000


GRAND TOTAL 440
Weight in Kg
Total wt
Total wt Total wt Total wt
12mm
16mm 20mm 25mm (3.85
(0.89
(1.58 kg/mt) (2.47 kg/mt) kg/mt)
kg/mt)

419.468 - - -

419.468 - - -

- - - -

- - - -

363.430 - - -

872.529 - - -
- - - -

- - - -

419.468 - - -

419.468 - - -

- - - -

- - - -

2913.830 0.000 0.000 0.000


4404.086
LINTEL BEAM
Sr.
Particular
no. B

1 FLIGHT 1 WIDTH 1.000 M



Main bar
Number of same flight 1.0

Extra bot bars

Extra top bar

Distribution bars
2 FLIGHT 2 WIDTH 1.000 M

Main bar
Number of same flight 1.0

Extra bot bars

Extra top bar

Distribution bars

3 FLIGHT 3 WIDTH 1.200 M



Main bar
Number of same flight 0.0
.
Extra bot bars

Extra top bar

Distribution bars
BAR BENDING SCHEDULE - STAIR

Dia of
No. of No. of
Shape of Bar Bar in
bar item
mm

1.220 10 11 1

1.220

1.000

10 11 1

1.220
1.000

0.900 10 11 1
1.220

8 53 1
1.000
3.660 10 11 1

4.120

1.220

10 11 1

1.030
1.220

3.660 10 11 1
1.030

8 107 1
1.000

0.500 12 13 0

3.000

0.450
12 13 0

0.750
0.450

0.500 12 13 0
0.750

12 65 0
1.200
NG SCHEDULE - STAIR

Weig
Total wt
Spacing in Length in Total length
8mm Total wt 10mm
mtr mtr in mtr
(0.395 (0.617 kg/mt)
kg/mt)

0.100 3.440 37.840 - 23.347

0.100 2.220 24.420 - 15.067

0.100 2.120 23.320 - 14.388

0.150 1.000 53.000 20.935 -


0.100 9.000 99.000 - 61.083

0.100 2.250 24.750 - 15.271

0.100 4.690 51.590 - 31.831

0.150 1.000 107.000 42.265 -

0.100 3.950 0.000 - -


0.100 1.200 0.000 - -

0.100 1.250 0.000 - -

0.100 1.200 0.000 - -

TOTAL 63.200 160.988


GRAND TOTAL 224
Weight in Kg
Total wt
Total wt Total wt Total wt
12mm
16mm 20mm 25mm (3.85
(0.89
(1.58 kg/mt) (2.47 kg/mt) kg/mt)
kg/mt)

- - - -

- - - -

- - - -

- - - -
- - - -

- - - -

- - - -

- - - -

- - - -
- - - -

- - - -

- - - -

0.000 0.000 0.000 0.000


224.188
SLAB BEAM
Sr.
Particular
no. L B H

1 B1 (SIZE IN METER) 32.280 0.230 0.425



Number of beams 1.000

Extra top bars

→ STIRRUPS

2 BR1 2.100 0.230 0.425



Number of beams 1.000
Extra top bars

→ STIRRUPS

3 B2 21.000 0.230 0.425



Number of beams 1.000

Extra top bars

→ STIRRUPS

4 B3 9.150 0.230 0.575



Number of beams 1.000
Extra top bars

→ STIRRUPS

5 B4 4.600 0.230 0.425



Number of beams 1.000

Extra top bars

→ STIRRUPS
6 B5 7.000 0.230 0.425

Number of beams 1.000

Extra top bars

→ STIRRUPS

7 SB 2.190 0.230 0.115



Number of beams 1.000

Extra top bars

→ STIRRUPS
BAR BENDING SCHEDULE - SLAB BEAM

Dia of
No. of No. of
Shape of Bar Bar in
bar item
mm

0.250 32.230 0.250 12 3 1


0 2 1

0.250 32.230 0.250 12 3 1

0.250 16.115
0 2 1

0.180
0.075 8 216 1
0.375 0.075 0.375

0.180

0.250 2.050 0.250 12 2 1


0 2 1

0.250 5.125 0.250 12 4 1


0.250 2.563
0 2 1

0.180
0.075 8 15 1
0.375 0.075 0.375

0.180

0.250 20.950 0.250 12 4 1

0.250 31.425 0.250 12 2 1

0.250 15.713
12 2 1

0.180
0.075 8 141 1
0.375 0.075 0.375

0.180

0.250 9.100 0.250 16 6 1


12 2 1

0.250 9.100 0.250 16 3 1

0.250 4.550
16 3 1

0.180
0.075 8 62 1
0.525 0.075 0.525

0.180

0.250 4.550 0.250 16 3 1

0.250 4.550 0.250 16 2 1

0.250 2.275
16 1 1

0.180
0.075 8 32 1
0.375 0.075 0.375

0.180
0.250 6.950 0.250 12 2 1

0.250 17.605 0.250 12 2 1

0.250 8.802
0 2 1

0.180
0.075 8 48 1
0.375 0.075 0.375

0.180

0.250 2.140 0.250 12 2 1

0.250 2.140 0.250 12 2 1

0.250 1.070
0 2 1

0.180
0.075 8 16 1
0.065 0.075 0.065

0.180
G SCHEDULE - SLAB BEAM

Weig
Total wt
Spacing in Length in Total length
8mm Total wt 10mm
mtr mtr in mtr
(0.395 (0.617 kg/mt)
kg/mt)

32.730 98.190 - -
32.730 65.460 - -

32.730 98.190 - -

16.365 32.730 - -

0.150 1.260 272.160 107.503 -

2.550 5.100 - -
2.550 5.100 - -

5.625 22.500 - -
2.813 5.625 - -

0.150 1.260 18.900 7.466 -

21.450 85.800 - -

31.925 63.850 - -

15.963 31.925 - -

0.150 1.260 177.660 70.176 -

9.600 57.600 - -
9.600 19.200 - -

9.600 28.800 - -

4.800 14.400 - -

0.150 1.560 96.720 38.204 -

5.050 15.150 - -

5.050 10.100 - -

2.525 2.525 - -

0.150 1.260 40.320 15.926 -


7.450 14.900 - -

18.105 36.210 - -

9.052 18.105 - -

0.150 1.260 60.480 23.890 -

2.640 5.280 - -

2.640 5.280 - -

1.320 2.640 - -

0.150 0.640 10.240 4.045 -


TOTAL 267.210 0.000
GRAND TOTAL 903
Weight in Kg
Total wt
Total wt Total wt Total wt
12mm
16mm 20mm 25mm (3.85
(0.89
(1.58 kg/mt) (2.47 kg/mt) kg/mt)
kg/mt)

87.389 - - -
- - - -

87.389 - - -

- - - -

- - - -

4.539 - - -
- - - -

20.025 - - -
- - - -

- - - -

76.362 - - -

56.827 - - -

28.413 - - -

- - - -

- 91.008 - -
17.088 - - -

- 45.504 - -

- 22.752 - -

- - - -

- 23.937 - -

- 15.958 - -

- 3.989 - -

- - - -
13.261 - - -

32.227 - - -

- - - -

- - - -

4.699 - - -

4.699 - - -

- - - -

- - - -
432.918 203.148 0.000 0.000
903.276
SLAB
Sr.
Particular
no. T

1 S1 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 9.150 m

Bentup bars Length 9.150 m

Extra top bars 2.670 m

Distribuition 1 0.000 m

Distribuition 2 0.000 m

2 S1 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 3.400 m

Bentup bars Length 3.400 m


Extra top bars 1.070 m

Distribuition 1 0.000 m

Distribuition 2 0.000 m

3 S2 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 5.460 m

Bentup bars Length 5.460 m

Extra top bars 4.120 m

Distribuition 1 0.000 m

Distribuition 2 0.000 m

4 S2 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 3.560 m

Bentup bars Length 3.560 m


Extra top bars 2.290 m

Distribuition 1 0.000 m

Distribuition 2 0.000 m

5 S3 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 2.570 m

Bentup bars Length 2.570 m

Extra top bars 0.920 m

Distribuition 1 4.880 m

Distribuition 2 0.000 m

6 S4 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 3.350 m
Bentup bars Length 3.350 m

Extra top bars 0.000 m

Distribuition 1 0.000 m

Distribuition 2 0.000 m

7 S4 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 4.320 m

Bentup bars Length 4.320 m

Extra top bars 1.070 m

Distribuition 1 0.000 m

Distribuition 2 0.000 m

8 S5 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 2.000 m
Bentup bars Length 2.000 m

Extra top bars 0.700 m

Distribuition 1 3.560 m

Distribuition 2 0.000 m

9 S6 Thickness 0.150
→ Number of Slab 1.000
Straight bars Length 3.660 m

Bentup bars Length 3.660 m

Extra top bars 2.290 m

Distribuition 1 2.980 m

Distribuition 2 0.000 m
BAR BENDING SCHEDULE - SLAB

Dia of
No. of No. of
Shape of Bar Bar in
bar item
mm

0.110 9.150 0.110 10 12 1

0.046 9.150 0.046 10 12 1

2.670 10 12 1

0.000 8 91 1

0.000 12 5 1

0.110 3.400 0.110 10 32 1

0.046 3.400 0.046 10 32 1


1.070 10 32 1

0.000 8 23 1

0.000 8 4 1

0.110 5.460 0.110 10 13 1

0.046 5.460 0.046 10 13 1

4.120 10 13 1

0.000 8 14 1

0.000 0 0 1

0.110 3.560 0.110 10 19 1

0.046 3.560 0.046 10 19 1


2.290 10 19 1

0.000 0 0 1

0.000 0 0 1

0.110 2.570 0.110 10 17 1

0.046 2.570 0.046 10 17 1

0.920 10 17 1

4.880 8 18 1

0.000 8 0 1

0.110 3.350 0.110 10 15 1


0.046 3.350 0.046 10 15 1

0.000 10 15 1

0.000 8 13 1

0.000 8 0 1

0.110 4.320 0.110 10 12 1

0.046 4.320 0.046 10 12 1

1.070 10 12 1

0.000 8 21 1

0.000 0 21 1

0.110 2.000 0.110 10 13 1


0.046 2.000 0.046 10 13 1

0.700 10 13 1

3.560 8 14 1

0.000 10 0 1

0.110 3.660 0.110 10 11 1

0.046 3.660 0.046 10 11 1

2.290 10 11 1

2.980 8 26 1

0.000 10 0 1
ING SCHEDULE - SLAB

Weig
Total wt
Number of Length in Total length
8mm Total wt 10mm
bend mtr in mtr
(0.395 (0.617 kg/mt)
kg/mt)

9.370 112.440 - 69.375

4 9.335 112.018 - 69.115

2.670 32.040 - 19.769

0.000 0.000 - -

0.000 0.000 - -

3.620 115.840 - 71.473

2 3.492 111.757 - 68.954


1.070 34.240 - 21.126

0.000 0.000 - -

0.000 0.000 - -

5.680 73.840 - 45.559

2 5.552 72.181 - 44.536

4.120 53.560 - 33.047

0.000 0.000 - -

0.000 0.000 - -

3.780 71.820 - 44.313

2 3.652 69.396 - 42.817


2.290 43.510 - 26.846

0.000 0.000 - -

0.000 0.000 - -

2.790 47.430 - 29.264

2 2.662 45.261 - 27.926

0.920 15.640 - 9.650

4.880 87.840 34.697 -

0.000 0.000 - -

3.570 53.550 - 33.040


2 3.442 51.636 - 31.859

0.000 0.000 - -

0.000 0.000 - -

0.000 0.000 - -

4.540 54.480 - 33.614

2 4.412 52.949 - 32.669

1.070 12.840 - 7.922

0.000 0.000 - -

0.000 0.000 - -

2.220 28.860 - 17.807


2 2.092 27.201 - 16.783

0.700 9.100 - 5.615

3.560 49.840 19.687 -

0.000 0.000 - -

3.880 42.680 - 26.334

2 3.752 41.276 - 25.468

2.290 25.190 - 15.542

2.980 77.480 30.605 -

0.000 0.000 - -
TOTAL 84.988 870.423
GRAND TOTAL 955
Weight in Kg
Total wt
Total wt Total wt Total wt
12mm
16mm 20mm 25mm (3.85
(0.89
(1.58 kg/mt) (2.47 kg/mt) kg/mt)
kg/mt)

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -
- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -
- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -
- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -
- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -

- - - -
0.000 0.000 0.000 0.000
955.411
REINFORCEMENT STEEL CONSUMPTION STATEMENT
REINFORCEMENT STEEL Total Qty
Sr. No. Item Description
8mm 10mm 12mm 16mm 20mm 25mm
1 GB/PB 1,490.256 ----- 2,913.830 ----- ----- ----- 4404.086
2 STAIR 63.200 160.988 ----- ----- ----- ----- 224.188
3 BEAM 267.210 ----- 432.918 203.149 ----- ----- 903.276
4 GF SLAB 84.988 870.423 ----- ----- ----- ----- 955.411

Total in kg :- 1,905.654 1,031.411 3,346.748 203.149 ----- ----- 6,486.961


WASTAGE 5% 95.283 51.571 167.337 10.157 ----- ----- 324.348

Total in MT :- 2.001 1.083 3.514 0.213 ----- ----- 6.811