Sl. Data
Reference Quantity Unit Description of work Rate Per Amount
No. Code
1 2 3 4 5 6 7 8
Earth work in excavation in all kinds of soils of
foundation of structures as per drawing and
IRR-CCDW-1-2
Sl. Data
Reference Quantity Unit Description of work Rate Per Amount
No. Code
1 2 3 4 5 6 7 8
Providing and laying insitu vibrated M-20 ( 28
days cube compressive strength not less than 20 N
/ sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded
IRR-CCDW-2-19
Sl. Data
Reference Quantity Unit Description of work Rate Per Amount
No. Code
1 2 3 4 5 6 7 8
Providing and laying insitu vibrated M-15 ( 28
days cube compressive strength not less than 15 N
/sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded
aggregates for bed and side lining(of thickness 100
IRR-CAW-7-15
Sl.No 33 of
21(P.No.
Booklet
18 Data 12 Nos as per MORTH Specification 2705 and as per 1586.80 Nos 19042
11
(4.7+5.20)/
Slab 1 x 3 7.26 0.60 64.69
2
(0.475+0.4
Kerb 2 x 3 7.26 0.23 4.41
25)/2
Parapet walls 2 x 3 7.26 0.20 1.00 8.71
ornamental pillars 2 x 2 0.50 0.5 1.200 1.20
U/s & D/s side slopes of the structure 2 x 4 3.68 0.30 0.20 1.76
Bottom lug 2 x 4 0.30 0.30 0.20 0.14
Top lug 2 x 4 0.30 0.30 0.20 0.14
Total Quantity in cum 2.05
Or Say 2.00
QUANTITY ESTIMATE OF SLB @ 25.100 KM OF CBR RIGHT CANAL (LINGALA)
as per statement
10.62
Total Quantity in MT 10.62
Supply and fixing of 12.7mm thick Mastic pads including
21(P.No.
MBS-W-
(4.25+3.05)
return walls 1 x 2 3.03 /2 1.98 43.80
2 x 2 3.8 0.3 1.98 9.03
piers 2 x 1 6.26 (3.3-1.2) 1.425 37.47
Total quantity in Cum 90.29
Or Say 90.00
RBR-SPST-
Coarse
2 Aggregate 356.00 75 26700
Laying and fixing of 160 mm Dia 300 mm long precast porus CC plugs in bed and sides
as per IRR-
CAW-5-7
using 20 mm HG metal and placing in local filters of size 600x600x750 mm in size
34
including Excavation of drains and Cost of procuring of all materials including 50 m lead
and for all lifts.
in IRR CAW 5-7 laying & fixing 100 mm dia 300 mm long is available . But as per CE CDO drawing size of
Note: porous plug is 160 mm dia 300 mm long hence data is worked out accordingly.
DATA:
EWE in all soils= 1x0.60x0.75x0.60 = 0.27 cum
Volume of plug=3.14/4*0.16*0.16= 0.006
Quantity of metal 20-40 mm= 0.32*0.32*0.375-vol.of plug 0.032
Quantity of metal 05 to 20 mm=0.48*0.48*0.45-0.32*0.32*0.375 0.065
Quantity of Sand = 0.525*0.6*0.6-0.48*0.48*0.45 0.085
Plug
metal Qty = 3.14/4*0.16*0.16*0.375*80% 0.006
Qty of Metal ( 0.032+0.065+0.006) 0.103
A. MATERIALS:
Unit
Sl.No Particulars Qty Rate in Rs Amount in Rs.
1 Coarse aggregate 40 mm Cum 0.032 1175.00 37.60
2 Coarse aggregate 20 mm Cum 0.071 1225.00 86.98
3 Sand (Un-Screened ) cum 0.117 95.00 11.12
4 Cement Kg 3.15 5.00 15.75
Total cost of Materials Rs. 151.44
B. MACHINERY
Sl.No Description Unit Quantity Rate in Rs. Amount in Rs.
C. LABOUR
Unit
Sl.No Particulars Qty Rate in Rs Amount in Rs.
1 Mazdoor Day 0.30 350.00 105.00
Total cost of Labour Rs. 105.00
ABSTRACT
A. Cost of Materials Rs. 151.44
B. Hire charges of Machinery Rs. 12.27
C. Cost of Labour Rs. 105.00
Total Rs: 268.71
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 36.58
Total cost for 1.00 Plug Rs: 305.29
Rate per each plug (A+B+C+D)/1.0 Rs. 305.29
Add for Lead charges:
Lead Charges for FA for 34 Kms 0.117 441.00 Rs. 51.60
Lead Charges for CA for 25 Kms 0.103 336.00 Rs. 34.61
DATA SSR 2016-17
IRR-CAW-
using 1.181 Kgs of cement per each using 20 mm HG metal and placing in local filters of size
5-7
35
600x600x750 mm in size including Excavation of drains and Cost of procuring of all materials
including 50 m lead and for all lifts.
DATA:
EWE in all soils= 1x0.60x0.75x100 = 0.27 cum
Qty of Metal = 1X0.30X 0.45 x100 = 0.081 cum
6 mm to 40 mm cum
Deduct Qty of Plug = 11/4x0.1x0.1x0.325 -0.003 cum
0.078 cum
Add metal for plug
11/4x0.1x0.1x0.4x80% 0.0024 cum
0.0804 cum
Qty of Sand =0.60x0.6x0.75=0.27-0.081= 0.189 cum
Add 1/3 metal qty =0.078/3 = 0.026 cum
0.215 cum
Deduct Qty of Plug 11/4x0.1x0.1x0.15= -0.012 cum
0.203 cum
Qty of Porus plug =11/4x0.1x0.1x0.4= 0.003 cum
Cement Required for 0.003 = 0.003x50/0.127= 1.181 Kgs
A. MATERIALS:
B. MACHINERY
Sl.No Description Unit Quantity Rate in Rs. Amount in Rs.
C. LABOUR
ABSTRACT
A. Cost of Materials Rs. 123.68
B. Hire charges of Machinery Rs. 10.51
C. Cost of Labour Rs. 105.00
D. Add for contractor's profit and overheads on Total Rs: 239.19
(A+B+C) 13.615% Rs: 32.57
Total cost for 1.00 Plug Rs: 271.76
Rate per each plug (A+B+C+D)/1.0 Rs. 271.76
Add for Lead charges:
Lead Charges for FA for 34 Kms 0.203 441.00 89.52
Lead Charges for CA for 25 Kms 0.08 336.00 Rs. 26.88
Rate per each plug Rs. 388.16
Or say Rs. 388.20