85

Name of work:-S.R. to road from crossing No.2 to crossing No.3 on sui side at port Navlakhi.
CHAPTER NO.6
:: S C H E D U L E - B ::
It. Item of Work Quantity Unit. Tender rate Total amount
No. estimated but according to
In Figures In Words
may be more estimated
or less quantities.
1 2 3 4 5 6 7
1 Dismantling tiled or stone floors laid in mortar including stacking of seviceable sqm 16.80 Rupees Sixteen & 57120.00
materials and disposal of unserviceable materials with all lead and lift. Ps. Eighty.

2 Supplying, spreading and consolidation the quarry spell material in layers not cum 898.45 Rupees Eight 122189.20
exceeding 200 mm thickness including watering ,dressing and leveling with all hunderd ninty eight
equipments, labours etc.complete. & Ps. Fourty five.

3 Construction of dry lean cement concrete sub-base over a prepared sub-grade cum 1853.20 Rupees One 661592.40
with coarse and fine aggregate conforming to IS:383, the size of coarse thousand eight
aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, hundred Fifty three
aggregate gradation after ble & Ps. Twenty.

4 Providing and laying separation membrane of impermeable plastic sheeting 125 sqm 32.30 Rupees Thirty two 109820.00
micron thick laid flat without creases including cleaning the sub-base using air and ps. Thirty.
compressor etc. complete.

5 Providing & laying cement concrete pavement of specified thickness over a cum 3786.80 Rupees Three 3540658.00
prepared sub-base with concrete of grade M40 using OPC 43 grade cement thousand seven
minimum @ 405 kg/cum and graded stone agregate 25 mm nominal size laid to hundred eighty six
required slope and camber in panels and Ps. Eighty.

6 Supplying, bending, hooking and binding thermomechanically treated (TMT) Kg 45.20 Rupees Fourty five 430756.00
corrosion resistant Fe-415 grade bar reinforcement including placing in position and Ps. Twenty.
etc. complete upto floor two level.
86
7 Providing MS reinforcement for RCC work including bending, binding and placing 1,252.00 Kg Rupees Fourty and 50580.80
in position complete upto floor two level. Ps. Fourty.
Rupees Fourty nine lacs seventy two thousand seven hundred sixteen Total Rs. : 4972716.40
& Ps. Fourty

Signature of Contractor Executive Engineer (C)


Construction Division,
MORBI

I/We am/are willing to carry out the work at % above / below percent (should be written in figures and words)
of the the estimate mentioned rates mentioned above.

Amount of My / our tender work out as under :

*Estimated amount put to tender *Estimated amount put to tender

(*Please strike out whichever is not applicable)