1.00 Item No.1:- Excavation in general in soft material comprising of soft soil, soft murum, hard 247.56 cum 244.20 #VALUE! #VALUE!
murum with boulders in wet or dry condition for head works such as percolation well, jack well,
etc. for lift 0 to 1.50 M and lead of 150 M including baricating, guarding, disposing off surplus
excavated stuff within a radius of 0.5 km. as directed by Engineer-in-charge, etc. complete,
excluding refilling. ( for head works on river side ) lift0.00 to 1.50 m
3.00 Item No.2 :- Excavation in general in hard material comprising of soft rock, hard rock, Manjara 76.93 cum 667.70 #VALUE! #VALUE!
rock,etc. by blasting / controlled blasting / chiselling as required in wet or dry condition for head
works such as percolation well, jack well, etc. for lift 0 to 1.50 M and lead of 150 M including
baricating, guarding, disposing off surplus excavated stuff within a radius of 0.5 km. as directed by
Engineer-in-charge, etc. complete, excluding refilling. ( for head works on river side ) lift 1.50 to 3
m
5.00 Item No.3 :- Providing and laying in situ PCC M:150 ( 1:2:4 ) grades of cement concrete of trap / 3.31 cum 4486.90 #VALUE! #VALUE!
granite / quartzite / gneiss metal for foundition and bedding, including dewatering, form-work,
compacting and curing, etc.
6.00 Item No.4 :- Providing and casting in situ Cement concrete of trap / granite / quartzite / gneiss 7.46 cum 6229.30 #VALUE! #VALUE!
metal of approved quality for RCC work as per detailed drawings and designs or as directed by
Engineer-in-charge including normal dewatering, form work, compaction, finishing the formed
surfaces with CM 1:3 of sufficient minimum thickness if special finish is to be provided and curing,
etc. complete. ( excluding reinforcement )A) RCC M-150 for beam at beam& lintel Lift 0.00 to
5.00 M
8.00 Item No.5 :- Providing and fixing in position tor steel bar reinforcement of various dia. For RCC 1.00 M.T 53350.00 #VALUE! #VALUE!
work as per detailed drawings, designs and schedules including cutting, bending, hooking the
bars, binding with wire and supporting as required etc. complete. ( including cost of binding
wire.)
9.00 Item No.7 :- Dewatering including diversion of streams, etc. as may be necessary for foundation 50.00 BHP/Hr 70.40 #VALUE! #VALUE!
and other parts of work during excavation and till its completion in all respects, etc. complete.
10.00 Item No.8 :- Providing and filling around the well,boulder filling of selected variety and size of 118.70 cum 72.60 #VALUE! #VALUE!
boulders including cost of all materials,labour,transportation etc.complete with all leads and lifts.
11.00 Item No.9 :- Providing and fixing on site of work information board of size 1.20 M.x 1.50 1.00 No 3500.00 #VALUE! #VALUE!
M including all labours and material as directed etc. complete.