Professional Documents
Culture Documents
Cellar Dewatering & Earth Dressing Sft 1 81,806 81,806.00 17.00 1,390,702.00
1 CONCRETE WORKS - -
1.1 PCC 1:4:8/ M-10 FOR BELOW RCC FOOTINGS/FLOORING - -
Providing & laying 100mm thick PCC 1:4:8 using 40mm and
downsize graded granite aggregates for below foundation of
column footings, stone masonry walls, plinth beams/ under
flooring / plinth including the cost of form work with proper - -
compaction, vibration, curing, tools and tackles etc., complete as
per the direction of Engineer-in-charge.
(RMC or Materials supply by Clients)
a Foundation PCC Cum 1.00 347.20 347.20 650 225,680.00
b Grade Slab PCC Cum 1.00 482.79 482.79 650 313,813.50
c Floor PCC Cum 1.00 781.00 781.00 700 546,700.00
d Retaining Wall Footings Cum 1.00 95.09 95.09 650 61,808.50
- -
1.20 REINFORCED CEMENT CONCRETE WORKS - -
1.2.1 Substructure
- -
a Footings Cum 1.00 1,613.16 1,613.16 750 1,209,870.00
b Retaining Wall Footing Cum 1.00 294.37 294.37 750 220,777.50
c RCC Retaining Wall Cum 1.00 433.44 433.44 850 368,424.00
d St.Case [Villa ] Cum 26.00 2.82 73.32 750 54,990.00
e St.Case [Podium] Cum 1.00 5.13 5.13 750 3,847.50
f Ramp Cum 1.00 31.51 31.51 750 23,632.50
g Columns - Foundation to Plinth Top Cum 1.00 43.53 43.53 750 32,647.50
h Lift Retainer Cum 1.00 30.63 30.63 750 22,972.50
i Grade Slab Cum 1.00 678.09 678.09 650 440,758.50
- -
Note: Unless otherwise specified the following will apply for all
items of plain and reinforced cement concrete formwork. Rates
quoted shall be inclusive of cost of the following to the RCC item at
various levels / height as indicated in the dwgs. No extra cost to be - -
entertained due to height / levels variation of floors / roof / beams
/ columns etc., hence, the additional staging, bracing if required to
meet the height / levels to be accounted in the respective item of
work. (Shuttering/MS Sheets by Contractor scope)
a) Adequate protection to edges and corners from damage during
construction.
- -
b) Work either straight, curved, sloping, plain or tapered. - -
c) Building in and placing in position any inserts supplied. - -
d) Deshuttering and cleaning. - -
e) Cost of all supports, struts, braces, ties, wedges, PVC strips, M.S.
props or other suitable - -
arrangements to support the form work.
f) Cost of all formwork including vertical supports of M.S. props,
M.S. spans, M.S. shuttering - -
sheets, runners plywood, battens, bolts etc.,
g) Cost of providing, making and erecting formwork, scaffolding,
staging, deshuttering, etc.,
- -
h) Cost of approved shuttering oil and labour and consumables like
wires, nails, ropes, clamps, - -
bolts or other items to hold the form work together.
i) Providing cut outs wherever necessary as indicated in the
drawings.
- -
j) Working scaffolds, gangways, ladders & similar items. - -
k) Filleting to form stop - chamfered edge or splayed external
angle, not exceeding 25 mm - -
wide to beams, columns & the like.
2.1.1 Substructure
- -
a Footings Sqm 1.00 1,694.47 1,694.47 550 931,958.50
b Retaining Wall Footing Sqm 1.00 267.80 267.80 550 147,290.00
c Retaining Wall (Ply wood Shuttering with tie rods) Sqm 1.00 3,467.51 3,467.51 915 3,172,771.65
d St.Case Villa Sqm 26.00 23.29 605.54 630 381,490.20
e St.Case Podium Sqm 1.00 44.74 44.74 630 28,186.20
f Ramp Sqm 1.00 210.08 210.08 650 136,552.00
g Columns - Foundation to Plinth Top Sqm 1.00 487.97 487.97 650 317,180.50
h Lift Retainer Sqm 1.00 266.32 266.32 650 173,108.00
- -
The rate quoted for bar bending works shall include of Pins, cranks,
Hooks, Chairs, bends etc. Only Lap length will be calculated as extra - -
for the calculation of total tonnage of steel
The rate quoted for Bar bending Works shall include works at all
heights, levels, works inside - -
trenches, scaffolding etc. with all necessary lead and lifts.
The rate quoted for bar bending works shall include necessary
labour, lead & lifts, machinery, tools & plants for supplying & fixing - -
of Cover Blocks for concrete related items.
The rate quoted for Reinforcement works shall include works at all
levels with all shapes as - -
shown in drawing.
The rate quoted for reinforcement works shall include all necessary
labour, material, tools, plants etc. required for provision of Dowels - -
at all the levels as directed by Engineer In Charge
- -
3.10 REINFORCEMENT STEEL WORKS - -
3.1.1 Substructure
- -
a Footings MT 1.00 92.00 92.00 10500 966,000.00
b Retaining Wall Footing MT 1.00 20.61 20.61 10500 216,405.00
c Retaining Wall MT 1.00 43.34 43.34 10500 455,070.00
d St.Case - Villa MT 26.00 0.25 6.50 10500 68,250.00
e St.Case - Podium MT 1.00 0.46 0.46 10500 4,830.00
f Ramp MT 1.00 3.15 3.15 10500 33,075.00
g Grade Slab MT 1.00 47.47 47.47 10500 498,435.00
h Lift Retainer MT 1.00 2.14 2.14 10500 22,470.00
- -
3.1.2 Columns
- -
a Columns Upto Podium Lvl MT 1.00 58.04 58.04 10500 609,420.00
b Columns Ground Floor MT 26.00 0.91 23.66 10500 248,430.00
c Columns First Floor MT 26.00 0.91 23.66 10500 248,430.00
d Columns Above Terrace MT 26.00 0.49 12.74 10500 133,770.00
- -
Internal Plastering- As per GFC drawings Sqm 1.00 22830.00 22,830.00 350 7,990,500.00
External Plastering 20mm thick in two coats using screened sand
with base coat of 16mm thick in CM(1:6) and top coat of 4mm
thick in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site,
including sales & other taxes on all materials, and all operational,
incidental charges on materials and including cost of all labour
6 charges for mixing mortar, finishing, scaffolding, elevations, lift -
charges, curing, including cutting grooves as directed by Engineer
etc., and overheads & contractors profit complete for finished item
of work. (Sand & Cement Supply by client scope)
(Cement & Sand Supply by Client's scope)
External Plastering - - As per GFC drawings Sqm 1.00 6040.00 6,040.00 450 2,718,000.00
TOTAL AMOUNT 59,456,901.05
SLAB AREA 142,301.00
PER SFT RATE 417.82