A EARTHWORK 48,180.00
B P C C WORKS 1,03,076.10
C R C C WORKS 13,11,937.75
E MASONRY 12,96,958.75
G PLASTERING 14,96,288.15
H FLOORING 9,53,023.80
I DADOING 2,57,977.50
J PAINTING 5,75,378.66
Q MISCELLLANEOUS 18,000.00
TOTAL 92,26,310.30
General earth work excavation in all kind of soft rock/hard rock from 0'-
0" to 5'-0" depth for foundation trenches / column footings, stacking the
1b excavated material.
a) Depth up to 5'0" Cft 2520.00 9.00 22,680.00
b) Beyond 5'0" depth Cft RO
Earth filling for foundation with available surplus earth at site or with
2a approved earth bought from outsite to attain desired level, filling not 1000.00
more than 6" in layers including watering and tamping and
consolidating etc., complete Cft 7.00 7,000.00
Supply good quality murum from external sources and refill the same in
6" successive layers including watering and compaction with Manual 1500.00
2b hand rammer Cft 9.00 13,500.00
Total 48,180.00
Providing and laying 4" thick PCC 1:4:8 with 40mm and down sized
graded granite stone aggregates including machine mixing, tamping,
1 curing, shuttering wherever necessary etc. for below foundation, Cft 168.00 85.00 14,280.00
column footings, etc.
Providing and laying 4" thick PCC 1:4:8 with 40mm and down sized
graded granite stone aggregates including machine mixing, tamping,
2 Cft 534.00 85.00 45,390.00
curing, shuttering wherever necessary etc.
For below ground floor
Same as above but PCC 1:3:6 below toilet flooring as levelling course,
3 before laying the finish flooring.
For Toilets and Balconys
a) First floor Cft 94.05 85.00 7,994.25
b) Second floor Cft 96.03 85.00 8,162.55
b)Third floor Cft 94.05 85.00 7,994.25
b)Fourth floor Cft 96.03 85.00 8,162.55
Providing and laying PCC 1:3:6 in Damp Proof Course below plinth
4 beams and for any other such works of 4" thick, with 20mm and down Cft 130.50 85.00 11,092.50
size graded granite stone aggregates
Total 1,03,076.10
Total 13,11,937.75
E MASONRY :
Total 12,96,958.75
F WATER PROOFING :
a) Ground floor
Toilet Sft 33.17 45.00 1,492.79
b) First floor
Toilet Sft 105.50 45.00 4,747.50
Balcony and utility Sft 127.23 45.00 5,725.35
b) Second floor
Toilet Sft 105.50 45.00 4,747.50
Balcony and utility Sft 146.85 45.00 6,608.25
b) Third floor
Toilet Sft 105.50 45.00 4,747.50
Balcony and utility Sft 127.23 45.00 5,725.35
b) Fourth floor
Toilet Sft 105.50 45.00 4,747.50
Balcony and utility Sft 146.85 45.00 6,608.25
c)Terrace Sft 1035.34 45.00 46,590.30
d)Above Head room Sft 165.00 45.00 7,425.00
Total 1,76,778.09
G PLASTERING:
Note: Rate quoted should include for
necessary hacking the RCC surface,
scaffolding curing, fixing necessary
chicken wire mesh at junction of brick and RCC
works) Make of Cement - Blended ACC/Birla.
Total 14,96,288.15
H FLOORING:
I DADOING
Total 2,57,977.50
Total 5,75,378.66
D1 - (Bedroom doors - 3' 0" x 7' 0") sft 294.00 850.00 2,49,900.00
14 NOS
2 Providing & fixing of door with WPVC shutter and frame as per detailed
drawing.
D2 - Toilet doors (2' 6" x 7' 0") sft 227.50 550.00 1,25,125.00
13 NOS
4 Providing & fixing UPVC WINDOWS as per specifications
with 3 track (Glass + Mesh shutter) all as per
design.
W1 - ( 6' 6" x 7' 0") sft 104.00 450.00 46,800.00
4 Nos
13,90,249.50
Total 3,60,000.00
2b hole cutting to fix the sink and faucet. Nos. 5.00 800.00 4,000.00
3a hole cutting to fix the sink and faucet. Nos. 13.00 800.00 10,400.00
Total 96,262.00
N ANTITERMITE TREATMENT
Total 16,000.00
Total 1,70,000.00
Total 48,000.00
Q MISCELLANEOUS
Total 18,000.00
R COMPOUND WALL
S ELEVATION TREATMENT
Total 4,38,825.00