Professional Documents
Culture Documents
Ref:https://railsystem.net/drill-and-blast-method/
Zheng, Y.L., Zhang, Q.B., Zhao, J, 2016. Challenges and opportunities of using tunnel boring machines in mining
Tunnelling and Underground Space Technology 57, 287–299
• Excavation rate:
D&B 2-6 m per day, depending on tunnel cross section and the ground
TBM 10-30 m per day, depending on the ground type
By Nuh Bilgin
Ref: Macias, F.J.Bruland, A., 2014. D&B versus TBM: Review of the parameters for a right choice of the
excavation method, Rock Engineering, and Rock Mechanics: Structures in and on Rock Masses – Alejano,
Perucho, Olalla & Jiménez (Eds), Taylor & Francis Group, London, 978-1-138-00149-7
By Nuh Bilgin
TBM could or should have been used only on the better investigated
portion of such projects.
The following example is given of the Kargı HEPP project where the
excavation started from the Eastern portal by a 10 m diameter double
shield TBM.
Due to the unexpected geology, at the beginning, the progress rate was
slow due to face collapses, and TBM squeezing. To reach the scheduled
project termination, it also decided to excavate the tunnel from the
Western portal. This gave the opportunity to compare drill and blast and
TBM tunnelling.
By Nuh Bilgin
An additional 7th bypass tunnel was required to free the trapped TBM shields
due to squeezing ground
Bypass tunnels dangerous hand tunnels were all completed safely and in a
timely manner.
By Nuh Bilgin
By Nuh Bilgin
Au 2
Ap 2
Ap 3
Se 2
O 2
D 2
Ja 2
M 3
M 2
N 2
M 3
12
Fe 3
Ju 2
3
-1
-1
l-1
-1
-1
1
-1
-1
1
r-1
-1
r-1
1
407.7 m/month
b-
n-
n-
g-
p-
ar
ar
ay
ay
ct
ov
ec
Ju
M
4
M 4
N 3
13
13
14
Se 3
13
D 3
Ja 3
4
M 4
Ju 4
l- 1
l- 1
r-1
-1
1
-1
-1
-1
1
-1
n-
n-
n-
g-
p-
b-
ct
ov
ec
ar
ay
Ju
Ju
Ap
Ju
Fe
O
By Nuh Bilgin
By Nuh Bilgin
100 102
100
57.5
50
17
0
M 3
3
M 4
4
Fe 3
13
14
3
4
Au 2
Au 3
N 2
M 3
N 3
M 4
Se 2
12
D 2
2
Se 3
13
D 3
3
l-1
l-1
1
-1
-1
-1
-1
1
-1
-1
1
-1
-1
-1
r-1
-1
r-1
n-
n-
n-
g-
p-
g-
p-
b-
b-
ov
ec
ov
ec
ct
ct
ar
ar
ay
ay
Ju
Ju
Ap
Ap
Fe
Ja
Ju
Ja
O
O
By Nuh Bilgin
TBM
Boring length: 7.8 km
Months to complete: 28
Average advance: 271.4 m per month
D&B
Boring length: 4 km
Months to complete: 23
Average advance: 173.8 m per month
By Nuh Bilgin
By Nuh Bilgin
The choise between drill and blast tunnelling and TBM tunnelling
mainly depends on:
1.The length of tunnel
2.Time schedule of the project
3.Are we ready on high initial investment?
3. How we are confident on the geology baseline report
4. Environmental restrictions
By Nuh Bilgin
March 2022