GROUTING AND TUNNEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION

OF TUNNEL IN NEELUM JHELUM HYDRO POWER PROJECT

By

Ameer Hamza Sundal


Awais Iqbal
Umair Javaid

Supervisor Mr. Saqib Mehmood

Department of Earth and Environmental Sciences

Bahria University Islamabad


2018
EVOLUTION OF THE PRECAMBRIAN CRUST EXPOSED IN SARGODHA AREA, PUNJAB, PAKISTAN
BS Thesis Defence
CONTENTS

 Introduction
 Stratigraphy
 Tectonics
 Objectives
 Methodology
 Conclusions

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide2
INTRODUCTION

(Norconsult, 1996)

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 3
TECTONICS

(Masrour, 2017)

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 4
TECTONICS

(Masrour, 2017)

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 5
STRATIGRAPHY

Foramtion Age

Quaternary alluvium Recent


Unconformity
Mirpur Formation Pleistocene
Unconformity
Soan Formation Pliocene
Dhok Pathan Formation Late Miocene
Nagri Formation Late Miocene
Chinji Formation Middle to Late Miocene
Kamlial Formation Early to middle Miocene
Murree Formation Early Miocene
Kuldana Formation Middle to Late Eocene
Chorgali Formation Early Eocene
Margalla Hill Limestone Early Eocene
Patala Formation Late Paleocene
Lockhart Limestone Early Paleocene
Hangu Formation Early Paleocene
Unconformity
Muzaffarabad Formation Cambrian
Unconformity
Dogra Formation Precambrian
Unconformity
Precambrian Basement rocks (IJSRP, Vol. 7, Issue. 7, 2017)
GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 6
STRATIGRAPHY OF STUDY AREA

Formation Age Lithology

Silt, gravel and unconsolidated


Alluvium Recent
deposits of clay

Mostly clays, shales and


sandstone and mudstone.
Sandstone is red to purple red
Murree Formation Miocene
in colour and is fine to medium
grained while shales are
reddish maroon

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 7
OBJECTIVES

Assess Q value of the rock units exposed in the study area

To evaluate the excavation method for tunnelling

To design support used during excavation process

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 8
METHODOLOGY

Tunnel Support
Analysis

Q-Value Excavation Technique Support

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 9
Q-Value

Q-Value

Inter-block
Block Size Active Stress
Shear Strength

Rock Quality Joint set Joint roughness Joint Alteration Joint water Stress Reduction
Designation numbers Number Number reduction factor Factor

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 10
Q-Value Formula

Q =( RQD / Jn) × (Jr / Ja) ×( Jw / SRF)

(Barton et al 1974)

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 11
Q-Value

Q1 Q2 Q3 Q4 Q5

Exceptionally Extremely Exceptionally


Very Good Good Fair Poor Very Poor Extremely Poor
Good Good Poor

a b c -- -- a b a b

400<Q<1000 100<Q<400 40<Q<100 10<Q<40 4<Q<10 1<Q<4 0.1<Q<1 0.01<Q<0.1 0.001<Q<0.01

Subdivisions of Q-Values

(Barton et al 1974)

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 12
Calculations

Lithology RQD Jn Jr Ja Jw SRF Q value Rock Quality

Mudstone 95 6 1.5 3 1 1 7.9166667 Q3

Sandstone 30 12 1.5 6 1 2.5 0.25 Q4b

Mudstone 10 20 1 8 1 5 0.0125 Q5a

Sandstone 25 6 1.5 4 1 5 0.3125 Q4b

Mudstone 60 6 1.5 4 1 2.5 1.5 Q4a

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 13
Road Header

Figure. Road Header

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 14
TUNNEL BORING MACHINE

Figure.TBM used for tunnel excavation in NJHPP

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 15
Initial Support

Supports

Reinforced Grout (if Lattice Umbrella


Shotcrete Ribs of Rock Bolts
needed) Girder Arches
Shotcrete

Single Double Project Pipe


Swellex Self Drilling Spiling
Layer Layer Specific Canopy

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 16
Sprayed Concrete (Shotcrete)

Figure. Shotcrete sprayed (arrow) by workers (oval) at C2 Majohi Figure. Shotcrete spray (random)

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 17
Grouted Rock bolts

Figure. Grouted Rock Bolt (blue oval) A4, Majohi Figure. Swellex Rock Bolt

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 18
Grouted Rock Bolts

Figure. Water flowing from bore hole (red circle) A4, Majohi Figure. Rock Bolt installation C2 Majohi

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 19
Reinforced Ribs of Shotcrete (RRS)

Figure. Single Layer RRS (with swellex), C2 Majohi Figure. Project specific RRS, C2 Majohi

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 20
Lattice Girders

Figure. Lattice Girders at portal of Addits(A2,A3,A4&A4a) & Tunnel (T3L)

Figure. Shotcrete sprayed on Lattice Girder

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 21
Umbrella Arches

Figure. Spiling

Figure. Pipe Canopy installation with new system

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 22
Challenges

Serial
Tunnel Section Type of Failure
No.

1 TL Roof collapse-Chimney type failure

2 TR Chimney type failure of roof & Exceptionally high water inflow

3 TL Major water flow from invert

4 TR Shotcrete failure & Major water inflow

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 23
Roof Collapse

Figure. Deposit of muck material on top of collapse debris C2, Majohi

Figure. Shotcrete wall

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 24
Roof Collapse Rehabilitation

Figure. Concrete backfilling of roof

Figure. Chemical (PU) grouting


GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 25
Collapse & Water Ingress Rehabilitation

Figure. Buttressing Tunnel Face with muck and sand bags Figure. Water Flowing through drain holes (red circles)

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 26
Collapse & Water Ingress Rehabilitation

Figure. Tunnel Plug (temporary)

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 27
Major Water Inflow (invert)

Figure. Flooded Invert Figure. Water diversion through channelling

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 28
Major Water Inflow (invert) Rehabilitation

Figure. Concrete Slab Installation

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 29
Shotcrete failure & Major water ingress

Figure. Shotcrete blowout & water ingress (white arrows) Figure. Damaged side wall

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 30
Shotcrete failure & Major water ingress

Figure. Shotcrete wire mesh

Figure. Drain holes

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 31
Conclusions

The rock quality was highly heterogeneous so the Q value assessed are between Q1 to Q5.
Slow progress of Drill and Blast technique led to a change in excavation method so TBM was selected
as the best choice for excavation due to its fast pacing and automated functionality.
Due to high water content some support systems were customized like Reinforced Shotcrete Rib,
Lattice Girders, Rock bolts & Pipe canopy System for project specific installation. To overcome
challenges in the tunnel tunnel plug, concrete plug, buttressing and remediation grouting was used.

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 32
Q-Value parameters

RO CK Q UAL IT Y DE S IGNAT IO N JO INT S E T NUMB E R VAL UE J O I NT WAT E R RE DUCT I O N


FACTOR
RQD Jn
Jw
120 25
100 20 1.2
15 1
0.8

Jn
80

Jw
10 0.6
RQD

60 5 0.4
0.2
40 0 0
20
0
VERY POOR POOR FAIR GOOD EXCELLENT
Class No. Of Joint Sets Inflow

JO I NT RO UGH NE S S NUMB E R JO INT ALT E RAT IO N NUMB E R S T RE S S RE DUCT I O N FACTO R


Jr Ja SRF
5 15 15
4
3 10 10

SRF
Jr

Ja

2 5
1 5
0 0
0

Roughness Alteration Stress Zones

GROUTING AND TUNEEL SUPPORT SYSTEM FOR THE SAFE EXCAVATION OF TUNNEL IN NJHPP Slide 33