Professional Documents
Culture Documents
Construction of G+2 Block of Classroom for Canadian Citizens Oct-16-23 Jan-05-24 Jan-05-24, Construction of G+2 Block
General Oct-16-23 Nov-02-23 Nov-02-23, General
Project Milestone Oct-16-23 Oct-16-23 Oct-16-23, Project Milestone
PCG02 Project Close Oct-16-23 Project Close
PCG01 Project Start Oct-16-23 Project Start
Key Dates Oct-16-23 Oct-16-23 Oct-16-23, Key Dates
PCD05 Building Permit Oct-16-23 Building Permit
PCD04 Issue IFC Drawings Oct-16-23 Issue IFC Drawings
PCD03 Site Handover Oct-16-23 Site Handover
Preliminary Oct-16-23 Nov-02-23 Nov-02-23, Preliminary
PC2P-02 Geotechnical Investigation & Topography suirvey Oct-16-23 Nov-02-23 Nov-02-23
PC2P-01 Site Hoarding & Site Of ice Oct-16-23 Oct-24-23 Oct-24-23
Engineering Oct-16-23 Nov-02-23 Nov-02-23, Engineering
Subcontractor Prequalification Oct-16-23 Oct-20-23 Oct-20-23, Subcontractor Prequali ication
PC2SP-02 Plumbing & Drainage Subcontractor Oct-16-23 Oct-20-23 Oct-20-23
PC2SP-01 Electrical Works Subcontractor Pre.process Oct-16-23 Oct-20-23 Oct-20-23
Submission & Approvals of Metthod Statements Oct-16-23 Nov-02-23 Nov-02-23, Submission & Approvals of Metthod Statements
PC2MS-04 Method Statement for Reinforcement & Forrmworks Oct-16-23 Nov-02-23 Nov-02-23
PC2MS-02 Method Statement for Concrete Works Oct-16-23 Nov-02-23 Nov-02-23
PC2MS-01 Method Statement for Site Clearance & Excavation Oct-16-23 Nov-02-23 Nov-02-23
Submission of Shop Drawings Oct-16-23 Nov-02-23 Nov-02-23, Submission of Shop Drawings
Preparation & Submission Oct-16-23 Nov-02-23 Nov-02-23, Preparation & Submission
PC2SD-01 Site Location & Site Layout Shop Drawing Submittals Oct-16-23 Nov-02-23 Nov-02-23
Review & Approval
Procurement Oct-16-23 Jan-05-24 Jan-05-24, Procurement
Local Materials Oct-16-23 Nov-02-23 Nov-02-23, Local Materials
PC2PM-02 Electrical Material Order & Delivery Oct-16-23 Nov-02-23 Nov-02-23
PC2PM-01 Structural Material Order & Delivery Oct-16-23 Nov-02-23 Nov-02-23
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 1 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
hod Statements
urement
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 2 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Lead Items
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 4 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 6 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 8 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
PC2FV-27 Reinforcement for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
Blockwork Oct-16-23 Oct-20-23 Oct-20-23, Blockwork
PC2FB-34 Masonry Works at Ground Floor Oct-16-23 Oct-20-23 Oct-20-23
PC2FB-33 Plastering Work for Ground Floor Oct-16-23 Oct-20-23 Oct-20-23
MEP Works Oct-16-23 Oct-20-23 Oct-20-23, MEP Works
Electrical Works Oct-16-23 Oct-20-23 Oct-20-23, Electrical Works
PC2FE-03 Electrical Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FE-02 Electrical Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FE-01 Electrical First Fix Oct-16-23 Oct-20-23 Oct-20-23
Mechanical Works Oct-16-23 Oct-20-23 Oct-20-23, Mechanical Works
PC2FM-06 Mechanical Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FM-05 Mechanical Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FM-04 Mechanical First Fix Oct-16-23 Oct-20-23 Oct-20-23
Plumbing & Drainage Oct-16-23 Oct-20-23 Oct-20-23, Plumbing & Drainage
PC2FPD-09 Plumbing & Drainage Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FPD-08 Plumbing & Drainage Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FPD-07 Plumbing & Drainage First Fix Oct-16-23 Oct-20-23 Oct-20-23
Finishes Oct-16-23 Oct-20-23 Oct-20-23, Finishes
Ceiling Finishes Oct-16-23 Oct-20-23 Oct-20-23, Ceiling Finishes
PC2FCF-02 Final Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
PC2FCF-01 First Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
Walll Finishes Oct-16-23 Oct-20-23 Oct-20-23, Walll Finishes
PC2FWF-03 Wet Area Wall Tiling Oct-16-23 Oct-20-23 Oct-20-23
PC2FWF-02 Final Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
PC2FWF-01 First Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
Floor Finishes Oct-16-23 Oct-20-23 Oct-20-23, Floor Finishes
PC2FFF-01 Waterproof for Wet Area Oct-16-23 Oct-20-23 Oct-20-23
PC2F-57 Floor Tiling Works Oct-16-23 Oct-20-23 Oct-20-23
Second Floor Oct-16-23 Oct-20-23 Oct-20-23, Second Floor
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 9 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 10 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 12 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 14 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
Landscape
Hard Landscape
Soft Landscape
Handing Over
Authority Approval
Project Handover
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 15 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens
2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 16 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone