Construction of G+2 Block of Classroom for Canadian Citizens

Activity ID Activity Name Start Finish 2023 2024


Oct Nov Dec Jan Feb

Construction of G+2 Block of Classroom for Canadian Citizens Oct-16-23 Jan-05-24 Jan-05-24, Construction of G+2 Block
General Oct-16-23 Nov-02-23 Nov-02-23, General
Project Milestone Oct-16-23 Oct-16-23 Oct-16-23, Project Milestone
PCG02 Project Close Oct-16-23 Project Close
PCG01 Project Start Oct-16-23 Project Start
Key Dates Oct-16-23 Oct-16-23 Oct-16-23, Key Dates
PCD05 Building Permit Oct-16-23 Building Permit
PCD04 Issue IFC Drawings Oct-16-23 Issue IFC Drawings
PCD03 Site Handover Oct-16-23 Site Handover
Preliminary Oct-16-23 Nov-02-23 Nov-02-23, Preliminary
PC2P-02 Geotechnical Investigation & Topography suirvey Oct-16-23 Nov-02-23 Nov-02-23
PC2P-01 Site Hoarding & Site Of ice Oct-16-23 Oct-24-23 Oct-24-23
Engineering Oct-16-23 Nov-02-23 Nov-02-23, Engineering
Subcontractor Prequalification Oct-16-23 Oct-20-23 Oct-20-23, Subcontractor Prequali ication
PC2SP-02 Plumbing & Drainage Subcontractor Oct-16-23 Oct-20-23 Oct-20-23
PC2SP-01 Electrical Works Subcontractor Pre.process Oct-16-23 Oct-20-23 Oct-20-23
Submission & Approvals of Metthod Statements Oct-16-23 Nov-02-23 Nov-02-23, Submission & Approvals of Metthod Statements
PC2MS-04 Method Statement for Reinforcement & Forrmworks Oct-16-23 Nov-02-23 Nov-02-23
PC2MS-02 Method Statement for Concrete Works Oct-16-23 Nov-02-23 Nov-02-23
PC2MS-01 Method Statement for Site Clearance & Excavation Oct-16-23 Nov-02-23 Nov-02-23
Submission of Shop Drawings Oct-16-23 Nov-02-23 Nov-02-23, Submission of Shop Drawings
Preparation & Submission Oct-16-23 Nov-02-23 Nov-02-23, Preparation & Submission
PC2SD-01 Site Location & Site Layout Shop Drawing Submittals Oct-16-23 Nov-02-23 Nov-02-23
Review & Approval
Procurement Oct-16-23 Jan-05-24 Jan-05-24, Procurement
Local Materials Oct-16-23 Nov-02-23 Nov-02-23, Local Materials
PC2PM-02 Electrical Material Order & Delivery Oct-16-23 Nov-02-23 Nov-02-23
PC2PM-01 Structural Material Order & Delivery Oct-16-23 Nov-02-23 Nov-02-23

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 1 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

ruction of G+2 Block of Classroom for Canadian Citizens

hod Statements

urement

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 2 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

Activity ID Activity Name Start Finish 2023 2024


Oct Nov Dec Jan Feb

Long Lead Items Oct-16-23 Jan-05-24 Jan-05-24, Long Lead Items


PC2LM-02 Adiovisual Teaching Aid order & Delivery Oct-16-23 Dec-15-23 Dec-15-23
PC2LM-01 Laboratory Equipment Order & Delivery Oct-16-23 Jan-05-24 Jan-05-24
Construction Oct-16-23 Oct-20-23 Oct-20-23, Construction
Classroom Building Oct-16-23 Oct-20-23 Oct-20-23, Classroom Building
Substructure Oct-16-23 Oct-20-23 Oct-20-23, Substructure
Foundation Works Oct-16-23 Oct-20-23 Oct-20-23, Foundation Works
PC2CF-09 Curing for Footing, Retaining & Shear Wall Concrete Oct-16-23 Oct-20-23 Oct-20-23
PC2CF-08 Removal of Formwork Oct-16-23 Oct-20-23 Oct-20-23
PC2CF-07 Concrete for Footings, Retaining Wall & Shear Wall Oct-16-23 Oct-20-23 Oct-20-23
PC2CF-06 Formworks for Footings, Retaining Wall & Shear Wall Oct-16-23 Oct-20-23 Oct-20-23
PC2CF-05 Reinforcement for footing, Shear wall & Retaining wall base Oct-16-23 Oct-20-23 Oct-20-23
PC2CF-04 Screeding & Waterproo ing Oct-16-23 Oct-20-23 Oct-20-23
PC2CF-03 Blinding Works Oct-16-23 Oct-20-23 Oct-20-23
PC2CF-02 Excavation Works Oct-16-23 Oct-20-23 Oct-20-23
PC2CF-01 Site Clearance and Setting Out Oct-16-23 Oct-20-23 Oct-20-23
Retaining Walls Oct-16-23 Oct-20-23 Oct-20-23, Retaining Walls
PC2R-05 Curing for Retaining Wall Oct-16-23 Oct-20-23 Oct-20-23
PC2R-04 Removalof Formwork for Retaining Wall Oct-16-23 Oct-20-23 Oct-20-23
PC2R-03 Concrete for Retaining Wall Oct-16-23 Oct-20-23 Oct-20-23
PC2R-02 Formwork for Retaining Wall Oct-16-23 Oct-20-23 Oct-20-23
PC2R-01 Reinforcement ForRetaining Wall Oct-16-23 Oct-20-23 Oct-20-23
Basement Oct-16-23 Oct-20-23 Oct-20-23, Basement
PC2B-06 Curing for r Basement Columns & shear wall Oct-16-23 Oct-20-23 Oct-20-23
PC2B-05 Removal of Formwor forr Basement Columns & shear wall Oct-16-23 Oct-20-23 Oct-20-23
PC2B-04 Concrete for r Basement Columns & shear wall Oct-16-23 Oct-20-23 Oct-20-23
PC2B-03 MEP Interface for r Basement Columns & shear wall Oct-16-23 Oct-20-23 Oct-20-23
PC2B-02 Formwork for r Basement Columns & shear wall Oct-16-23 Oct-20-23 Oct-20-23
PC2B-01 Reinforcement for Basement Columns & shear wall Oct-16-23 Oct-20-23 Oct-20-23
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 3 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Lead Items

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 4 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

Activity ID Activity Name Start Finish 2023 2024


Oct Nov Dec Jan Feb

Ground Floor Oct-16-23 Oct-20-23 Oct-20-23, Ground Floor


Structural Work Oct-16-23 Oct-20-23 Oct-20-23, Structural Work
Horizontal Element Oct-16-23 Oct-20-23 Oct-20-23, Horizontal Element
PC2G-06 Removalof Formwork for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-05 Curing for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-04 Concrete for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-03 MEP Interface for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-02 Reinforcement for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-01 Formworm for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
Vertical Element Oct-16-23 Oct-20-23 Oct-20-23, Vertical Element
PC2G-12 Curing for for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2G-11 Removal of Formwork for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2G-10 Concrete for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2G-09 Formwork for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2G-08 MEP Interface for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2G-07 Reinforcement for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
Blockwork Oct-16-23 Oct-20-23 Oct-20-23, Blockwork
PC2G-14 Plastering Work for Ground Floor Oct-16-23 Oct-20-23 Oct-20-23
PC2G-13 Masonry Works at Ground Floor Oct-16-23 Oct-20-23 Oct-20-23
MEP Works Oct-16-23 Oct-20-23 Oct-20-23, MEP Works
Electrical Works Oct-16-23 Oct-20-23 Oct-20-23, Electrical Works
PC2E-03 Electrical Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2E-02 Electrical Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2E-01 Electrical First Fix Oct-16-23 Oct-20-23 Oct-20-23
Mechanical Works Oct-16-23 Oct-20-23 Oct-20-23, Mechanical Works
PC2M-03 Mechanical Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2M-02 Mechanical Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2M-01 Mechanical First Fix Oct-16-23 Oct-20-23 Oct-20-23
Plumbing & Drainage Oct-16-23 Oct-20-23 Oct-20-23, Plumbing & Drainage
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 5 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 6 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

Activity ID Activity Name Start Finish 2023 2024


Oct Nov Dec Jan Feb

PC2PD-03 Plumbing & Drainage Fnal Fix Oct-16-23 Oct-20-23 Oct-20-23


PC2PD-02 Plumbing & Drainage Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2PD-01 Plumbing & Drainage First Fix Oct-16-23 Oct-20-23 Oct-20-23
Finishes Oct-16-23 Oct-20-23 Oct-20-23, Finishes
Ceiling Finishes Oct-16-23 Oct-20-23 Oct-20-23, Ceiling Finishes
PC2F-02 Final Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
PC2F-01 First Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
Walll Finishes Oct-16-23 Oct-20-23 Oct-20-23, Walll Finishes
PC2F-05 Wet Area Wall Tiling Oct-16-23 Oct-20-23 Oct-20-23
PC2F-04 Final Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
PC2F-03 First Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
Floor Finishes Oct-16-23 Oct-20-23 Oct-20-23, Floor Finishes
PC2F-07 Floor Tiling Works Oct-16-23 Oct-20-23 Oct-20-23
PC2F-06 Waterproof for Wet Area Oct-16-23 Oct-20-23 Oct-20-23
First Floor Oct-16-23 Oct-20-23 Oct-20-23, First Floor
Structural Work Oct-16-23 Oct-20-23 Oct-20-23, Structural Work
Horizontal Element Oct-16-23 Oct-20-23 Oct-20-23, Horizontal Element
PC2G-26 Removalof Formwork for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-25 Curing for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-24 Concrete for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-23 MEP Interface for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-22 Reinforcement for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2G-21 Formworm for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
Vertical Element Oct-16-23 Oct-20-23 Oct-20-23, Vertical Element
PC2FV-32 Curing for for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2FV-31 Removal of Formwork for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2FV-30 Concrete for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2FV-29 Formwork for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2FV-28 MEP Interface for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 7 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 8 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

Activity ID Activity Name Start Finish 2023 2024


Oct Nov Dec Jan Feb

PC2FV-27 Reinforcement for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
Blockwork Oct-16-23 Oct-20-23 Oct-20-23, Blockwork
PC2FB-34 Masonry Works at Ground Floor Oct-16-23 Oct-20-23 Oct-20-23
PC2FB-33 Plastering Work for Ground Floor Oct-16-23 Oct-20-23 Oct-20-23
MEP Works Oct-16-23 Oct-20-23 Oct-20-23, MEP Works
Electrical Works Oct-16-23 Oct-20-23 Oct-20-23, Electrical Works
PC2FE-03 Electrical Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FE-02 Electrical Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FE-01 Electrical First Fix Oct-16-23 Oct-20-23 Oct-20-23
Mechanical Works Oct-16-23 Oct-20-23 Oct-20-23, Mechanical Works
PC2FM-06 Mechanical Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FM-05 Mechanical Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FM-04 Mechanical First Fix Oct-16-23 Oct-20-23 Oct-20-23
Plumbing & Drainage Oct-16-23 Oct-20-23 Oct-20-23, Plumbing & Drainage
PC2FPD-09 Plumbing & Drainage Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FPD-08 Plumbing & Drainage Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2FPD-07 Plumbing & Drainage First Fix Oct-16-23 Oct-20-23 Oct-20-23
Finishes Oct-16-23 Oct-20-23 Oct-20-23, Finishes
Ceiling Finishes Oct-16-23 Oct-20-23 Oct-20-23, Ceiling Finishes
PC2FCF-02 Final Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
PC2FCF-01 First Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
Walll Finishes Oct-16-23 Oct-20-23 Oct-20-23, Walll Finishes
PC2FWF-03 Wet Area Wall Tiling Oct-16-23 Oct-20-23 Oct-20-23
PC2FWF-02 Final Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
PC2FWF-01 First Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
Floor Finishes Oct-16-23 Oct-20-23 Oct-20-23, Floor Finishes
PC2FFF-01 Waterproof for Wet Area Oct-16-23 Oct-20-23 Oct-20-23
PC2F-57 Floor Tiling Works Oct-16-23 Oct-20-23 Oct-20-23
Second Floor Oct-16-23 Oct-20-23 Oct-20-23, Second Floor
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 9 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 10 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

Activity ID Activity Name Start Finish 2023 2024


Oct Nov Dec Jan Feb

Structural Work Oct-16-23 Oct-20-23 Oct-20-23, Structural Work


PC2SSW-12 Curing for for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-11 Removal of Formwork for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-10 Concrete for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-09 Formwork for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-08 MEP Interface for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-07 Reinforcement for Columns & Shear walls Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-06 Removalof Formwork for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-05 Curing for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-04 Concrete for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-03 MEP Interface for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-02 Reinforcement for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
PC2SSW-01 Formworm for Tie Beam & Ground Slab Oct-16-23 Oct-20-23 Oct-20-23
Blockwork Oct-16-23 Oct-20-23 Oct-20-23, Blockwork
PC2SB-02 Plastering Work for Ground Floor Oct-16-23 Oct-20-23 Oct-20-23
PC2SB-01 Masonry Works at Ground Floor Oct-16-23 Oct-20-23 Oct-20-23
MEP Works Oct-16-23 Oct-20-23 Oct-20-23, MEP Works
Electrical Works Oct-16-23 Oct-20-23 Oct-20-23, Electrical Works
PC2SE-03 Electrical Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2SE-02 Electrical Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2SE-01 Electrical First Fix Oct-16-23 Oct-20-23 Oct-20-23
Mechanical Works Oct-16-23 Oct-20-23 Oct-20-23, Mechanical Works
PC2SM-03 Mechanical Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2SM-02 Mechanical Second Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2SM-01 Mechanical First Fix Oct-16-23 Oct-20-23 Oct-20-23
Plumbing & Drainage Oct-16-23 Oct-20-23 Oct-20-23, Plumbing & Drainage
PC2SPD-03 Plumbing & Drainage Final Fix Oct-16-23 Oct-20-23 Oct-20-23
PC2SPD-02 Plumbing & Drainage First Fix Oct-16-23 Oct-20-23 Oct-20-23
PC22PD-01 Plumbing & Drainage Second Fix Oct-16-23 Oct-20-23 Oct-20-23
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 11 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 12 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

Activity ID Activity Name Start Finish 2023 2024


Oct Nov Dec Jan Feb

Finishes Oct-16-23 Oct-20-23 Oct-20-23, Finishes


Ceiling Finishes Oct-16-23 Oct-20-23 Oct-20-23, Ceiling Finishes
PC2SCF-02 Final Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
PC2SCF-01 First Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
Walll Finishes Oct-16-23 Oct-20-23 Oct-20-23, Walll Finishes
PC2SWF-03 Wet Area Wall Tiling Oct-16-23 Oct-20-23 Oct-20-23
PC2SWF-02 Final Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
PC2SWF-01 First Coat Painting Oct-16-23 Oct-20-23 Oct-20-23
Floor Finishes Oct-16-23 Oct-20-23 Oct-20-23, Floor Finishes
PC2SFF-02 Floor Tiling Works Oct-16-23 Oct-20-23 Oct-20-23
PC2SFF-01 Waterproof for Wet Area Oct-16-23 Oct-20-23 Oct-20-23
Roof Oct-16-23 Oct-20-23 Oct-20-23, Roof
PC2RW-04 Covering of Roof Oct-16-23 Oct-20-23 Oct-20-23
PC2RW-03 Underlayment of Roof Oct-16-23 Oct-20-23 Oct-20-23
PC2RW-02 Sheeting of Roof Oct-16-23 Oct-20-23 Oct-20-23
PC2RW-01 Framing of Roof Oct-16-23 Oct-20-23 Oct-20-23
External Works Oct-16-23 Oct-20-23 Oct-20-23, External Works
Boundary Wall Oct-16-23 Oct-20-23 Oct-20-23, Boundary Wall
PC2RBW-11 Paint Application on Boundary Wall Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-10 Installing of Boundary Wall Drainage & Electrical Accessories and Fittings
Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-09 Errection of Blockwork for Boundary Wall Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-08 Casting of Concrete for Bounday Wall Column Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-07 Forwork for Boundary Wall Column Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-06 Curing of Concrete for Boundary Wall & Column Wall Foundation Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-05 Concrete Casting for Boundary Wall & Column Wall Foundation Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-04 Reinforcement for Boundary Wall Column Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-03 Surface Compaction & Laying of Waterproof Polyethylne Material on Oct-16-23
Excavated Trench Foundation Oct-20-23
Oct-20-23
PC2RBW-02 Excavation for Boundary Column Foundation Oct-16-23 Oct-20-23 Oct-20-23
PC2RBW-01 Excavation for Boundary wall Foundation Oct-16-23 Oct-20-23 Oct-20-23
Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 13 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 14 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

Activity ID Activity Name Start Finish 2023 2024


Oct Nov Dec Jan Feb

Landscape
Hard Landscape
Soft Landscape
Handing Over
Authority Approval
Project Handover

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 15 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone
Construction of G+2 Block of Classroom for Canadian Citizens

2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Remaining Level of Effort Remaining Work Summary Date Revision Checked Approved
Page 16 of 16
Actual Level of Effort Critical Remaining Work
Actual Work Milestone