Flood Protection Program

Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023
Duration
8 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 4
206 17-Sep-22 10-Apr-23 17-Sep-22 10-Apr-23 10-Apr-23, Total
Total
206 17-Sep-22 10-Apr-23 17-Sep-22 10-Apr-23 10-Apr-23, Flood Pro
Flood Protection
Protec Program
Key Milestones
Milestone 206 17-Sep-22 10-Apr-23 17-Sep-22 10-Apr-23 10-Apr-23, Key Miles
A0995 Commencement Date 0 17-Sep-22 17-Sep-22* Commencement Date, 17-Sep-22*
A0996 Trial Trench 10 20-Sep-22 29-Sep-22 20-Sep-22 29-Sep-22 Trial Trench
A1008 Receiving of Documents from Main contractor to submit NOC 21 17-Sep-22 07-Oct-22 17-Sep-22 07-Oct-22 Receiving of Documents from Main contractor to submit NOC
A1009 Construction NOC's 46 08-Oct-22 22-Nov-22 08-Oct-22 22-Nov-22 Construction NOC's
A1010 MOBILIZATION & SAFETY ESTABLISHMENT 10 23-Nov-22 02-Dec-22 23-Nov-22 02-Dec-22 MOBILIZATION & SAFETY ESTABLISHMENT
A1020 Completion of Works - Inside the Plot 0 31-Mar-23 31-Mar-23 Completion of Works - Insid
A1030 Completion of Works - Outside the Plot 0 10-Apr-23 10-Apr-23 Completion of Works

Engineering & Procurement 18 23-Nov-22 10-Dec-22 23-Nov-22 10-Dec-22 10-Dec-22, Engineering & Procurement
A1290 Engineering & Procurement 18 23-Nov-22 10-Dec-22 23-Nov-22 10-Dec-22 Engineering & Procurement
Construction 119 13-Dec-22 10-Apr-23 13-Dec-22 10-Apr-23 10-Apr-23, Construct
Inside the p
plot 109 13-Dec-22 31-Mar-23 13-Dec-22 31-Mar-23 31-Mar-23, Inside the plot
Flood Protection
Pro 48 13-Dec-22 29-Jan-23 13-Dec-22 29-Jan-23 29-Jan-23, Flood Protection
A1470 SETTING OUT FOR THE STORM LINE AND MANHOLES 3 13-Dec-22 15-Dec-22 13-Dec-22 15-Dec-22 SETTING OUT FOR THE STORM LINE AND MANHOLES
A1480 EXCACVATION FOR THE PROPOSED STORM GRP PIPE LINE WITH MANHOLES 6 16-Dec-22 21-Dec-22 16-Dec-22 21-Dec-22 EXCACVATION FOR THE PROPOSED STORM GRP PIPE LINE WITH MANHOLES
A1481 GRP PIPES/FITTINGS DELIVERY BY MAIN CONTRACTOR 0 19-Dec-22 19-Dec-22 GRP PIPES/FITTINGS DELIVERY BY MAIN CONTRACTOR, 19-Dec-22
A1490 BEDDING AND LAYING GRP PIPES 26 19-Dec-22 13-Jan-23 19-Dec-22 13-Jan-23 BEDDING AND LAYING GRP PIPES
A1500 MANHOLE CONSTRUCTION INCLUDING GRP SHORT PCS PIPE AND FITTINGS 15 17-Dec-22 31-Dec-22 17-Dec-22 31-Dec-22 MANHOLE CONSTRUCTION INCLUDING GRP SHORT PCS PIPE AND FITTINGS
A1510 INSPECTION FOR THE ABOVE 7 25-Dec-22 31-Dec-22 25-Dec-22 31-Dec-22 INSPECTION FOR THE ABOVE
A1520 BACKFILLING AND COMPACTION LAYER BY LAYER 33 28-Dec-22 29-Jan-23 28-Dec-22 29-Jan-23 BACKFILLING AND COMPACTION LAYER BY LAYER
Internal R
Road Works 37 23-Feb-23 31-Mar-23 23-Feb-23 31-Mar-23 31-Mar-23, Internal Road W
A1530 LAYING SUB BASE INCLUDING THE COMPACTION (CW) 11 23-Feb-23 05-Mar-23 23-Feb-23 05-Mar-23 LAYING SUB BASE INCLUDING THE COMP
A1540 LAYING ROAD BASE INCLUDING THE COMPACTION (CW) 7 06-Mar-23 12-Mar-23 06-Mar-23 12-Mar-23 LAYING ROAD BASE INCLUDING THE
A1550 FIXING KERSTONE 7 08-Mar-23 14-Mar-23 08-Mar-23 14-Mar-23 FIXING KERSTONE
A1560 SPRAYING PRIME COAT MC70 (CW) 1 15-Mar-23 15-Mar-23 15-Mar-23 15-Mar-23 SPRAYING PRIME COAT MC70 (CW
A1570 LAYING ASPHALT WEARING COURSE 60MM THICK. 2 16-Mar-23 17-Mar-23 16-Mar-23 17-Mar-23 LAYING ASPHALT WEARING COUR
A1580 LAYING SUB BASE INCLUDING THE COMPACTION (FP) 3 18-Mar-23 20-Mar-23 18-Mar-23 20-Mar-23 LAYING SUB BASE INCLUDING T
A1590 FIXING 60MM TILES 8 21-Mar-23 28-Mar-23 21-Mar-23 28-Mar-23 FIXING 60MM TILES
A1600 FIXING TRAFFIC SIGNS 6 26-Mar-23 31-Mar-23 26-Mar-23 31-Mar-23 FIXING TRAFFIC SIGNS
A1610 PRE MARKING AND ROAD MARKING 4 28-Mar-23 31-Mar-23 28-Mar-23 31-Mar-23 PRE MARKING AND ROAD
Outside the plot 109 23-Dec-22 10-Apr-23 23-Dec-22 10-Apr-23 10-Apr-23, Outside t
Flood Protection
Pro 78 23-Dec-22 10-Mar-23 23-Dec-22 10-Mar-23 10-Mar-23, Flood Protection
A1300 REMOVING OF PAVEMENT INFRONT OF THE SHOPS 4 23-Dec-22 26-Dec-22 23-Dec-22* 26-Dec-22 REMOVING OF PAVEMENT INFRONT OF THE SHOPS
A1310 EXCACVATION FOR THE PROPOSED STORM GRP PIPE LINE WITH MANHOLES (EXTERNAL AREA) 31 27-Dec-22 26-Jan-23 27-Dec-22 26-Jan-23 EXCACVATION FOR THE PROPOSED STORM GRP PIPE LINE WIT
A1320 CONNECTION WITH EXISTING CULVERT 15 27-Dec-22 10-Jan-23 27-Dec-22 10-Jan-23 CONNECTION WITH EXISTING CULVERT
A1330 BEDDING AND LAYING GRP PIPES 30 29-Dec-22 27-Jan-23 29-Dec-22 27-Jan-23 BEDDING AND LAYING GRP PIPES
A1340 APPLY FOR ROAD DIVERSION 10 18-Jan-23 27-Jan-23 18-Jan-23 27-Jan-23 APPLY FOR ROAD DIVERSION
A1350 MANHOLE CONSTRUCTION INCLUDING GRP SHORT PCS PIPE AND FITTINGS 13 13-Jan-23 25-Jan-23 13-Jan-23 25-Jan-23 MANHOLE CONSTRUCTION INCLUDING GRP SHORT PCS PIPE AN
A1360 BACKFILLING AND COMPACTION LAYER BY LAYER 16 28-Jan-23 12-Feb-23 28-Jan-23 12-Feb-23 BACKFILLING AND COMPACTION LAYER BY LAYER
A1370 INSPECTION FOR THE ABOVE 7 13-Feb-23 19-Feb-23 13-Feb-23 19-Feb-23 INSPECTION FOR THE ABOVE
A1380 RE-INSTATEMENT OF DEMOLISHED AND REMOVED AREAS 8 20-Feb-23 27-Feb-23 20-Feb-23 27-Feb-23 RE-INSTATEMENT OF DEMOLISHED AND REM
A1390 TESTING, COMMISSIONING AND HANDING OVER 10 01-Mar-23 10-Mar-23 01-Mar-23 10-Mar-23 TESTING, COMMISSIONING AND HAND
External Access Road 42 28-Feb-23 10-Apr-23 28-Feb-23 10-Apr-23 10-Apr-23, External A
A1400 LAYING OF STORM WATER NETWORK 6 28-Feb-23 05-Mar-23 28-Feb-23 05-Mar-23 LAYING OF STORM WATER NETWORK
A1410 FIXING STREET LIGHT FOUNDATION AND LIGHTING COLUMNS 4 02-Mar-23 05-Mar-23 02-Mar-23 05-Mar-23 FIXING STREET LIGHT FOUNDATION AND
A1420 FIXING TRAFFIC SIGNS 3 03-Mar-23 05-Mar-23 03-Mar-23 05-Mar-23 FIXING TRAFFIC SIGNS
A1430 EARTHWORKS & KERBSTONE LAYING AND PAVEMENT 20 06-Mar-23 25-Mar-23 06-Mar-23 25-Mar-23 EARTHWORKS & KERBSTON
A1440 ASPHALTLAYERS LAYING 9 26-Mar-23 03-Apr-23 26-Mar-23 03-Apr-23 ASPHALTLAYERS LAYIN
A1450 RTA INSPECTION FOR ASPHALT 3 04-Apr-23 06-Apr-23 04-Apr-23 06-Apr-23 RTA INSPECTION FOR
A1460 CONSULTANT /CLIENT/RTA INSPECTION FOR ROAD PAVEMENT,ROAD MARKING , TRAFFIC SIGNS & UTIL 4 07-Apr-23 10-Apr-23 07-Apr-23 10-Apr-23 CONSULTANT /CLIE

Actual Level of Effort Actual Work Page 1 of 1 Date Revision Checked Approved
15-Dec-22
Primary Baseline Remaining Work