Activity ID Activity Name Start Finish Original Total Float

Duration

Landscape Construction of Neighborhoods Olaisaha And Middle Al 18-Jul-23 14-Dec-24


Uraija Project 02 Crushing 425 0

Construction 18-Jul-23 14-Dec-24 425 0

Sector 1 18-Jul-23 22-Oct-24 381 27


Zone 08 18-Jul-23 29-Sep-24 360 48
Future Neighborhood Park FNP-22 18-Jul-23 15-Jun-24 275 121
Site Preparation 18-Jul-23 16-Aug-23 26 370
GR-CON-Z08-1000 Demolition (Asphalt.Paving,etc.....) 18-Jul-23 23-Jul-23 5 1
GR-CON-Z08-1001 Excavation And Disposal 24-Jul-23 31-Jul-23 7 253
GR-CON-Z08-1002 Prepretion And Compaction 01-Aug-23 06-Aug-23 5 370
GR-CON-Z08-1003 Backfilling 07-Aug-23 16-Aug-23 9 370
Curbstone and Paving 01-Aug-23 12-Oct-23 62 322
GR-CON-Z08-1004 Excavation Curbstone 01-Aug-23 08-Aug-23 7 307
GR-CON-Z08-1005 Plain Concrete 09-Aug-23 19-Aug-23 9 322
GR-CON-Z08-1006 Installation Curbstone 20-Aug-23 02-Sep-23 12 322
GR-CON-Z08-1007 Casting Concrete (Mortar haunch) 03-Sep-23 07-Sep-23 5 322
GR-CON-Z08-1008 Backfilling (sand / Sub base) 09-Sep-23 21-Sep-23 12 322
GR-CON-Z08-1009 Installation of Paving 24-Sep-23 12-Oct-23 17 322
Landscape Works 09-Aug-23 15-Jun-24 256 121
GR-CON-Z08-1010 Excavation (Tree Pit ) 09-Aug-23 16-Aug-23 7 307
GR-CON-Z08-1011 Aggregate Drainage layer 17-Aug-23 27-Aug-23 9 307
GR-CON-Z08-1012 Installation Geotextile 28-Aug-23 02-Sep-23 5 307
GR-CON-Z08-1013 Backfilling (Soil max for tree) 03-Sep-23 12-Sep-23 9 307
GR-CON-Z08-1014 Installation of Trees 30-Apr-24 01-May-24 2 121
GR-CON-Z08-1986 Installation of Shrubs 02-May-24 04-May-24 2 121
GR-CON-Z08-1996 Installation of Succulents 05-May-24 06-May-24 2 121
GR-CON-Z08-2006 Installation of Ground Covers 07-May-24 08-May-24 2 121
GR-CON-Z08-2016 Installation of Climbers 09-May-24 11-May-24 2 121
GR-CON-Z08-2026 Installation of Grass 12-May-24 13-May-24 2 121
GR-CON-Z08-2036 Installation of Lawns 14-May-24 15-May-24 2 121
GR-CON-Z08-1015 Backfilling (Mulch) 16-May-24 20-May-24 4 121
GR-CON-Z08-1016 Natural Boulders Installation 21-May-24 26-May-24 5 121
GR-CON-Z08-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
27-May-24 15-Jun-24 17 121
Irrigation Works 01-Aug-23 15-Jun-24 263 121
GR-CON-Z08-1018 Excavation Pipe Irrigation 01-Aug-23 08-Aug-23 7 253
GR-CON-Z08-1019 Sand Bedding 09-Aug-23 13-Aug-23 4 253
GR-CON-Z08-1020 HDPE Pipe Installations and fittings and conduit for cable 28-Aug-23 20-Sep-23 20 240
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1022 Test pressure 20-Sep-23 30-Sep-23 7 240


GR-CON-Z08-1021 Installation of Valves and Accessories 30-Sep-23 05-Oct-23 5 240
GR-CON-Z08-1023 Back filling (sand / Subbase ) 05-Oct-23 16-Oct-23 9 240
GR-CON-Z08-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Oct-23 26-Oct-23 9 300
GR-CON-Z08-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
04-Jun-24
system 15-Jun-24 10 121
Pump Room - 01 24-Jul-23 29-Sep-24 355 36
Site Preparation 24-Jul-23 02-Sep-23 35 36
GR-CON-Z08-1317 Excavation And Disposal 24-Jul-23 03-Aug-23 10 36
GR-CON-Z08-1318 Blinding concrete 05-Aug-23 02-Sep-23 25 36
Civil Works 03-Sep-23 02-Apr-24 177 36
Reinforcement steel bars / Formwork / Concrete 25-Sep-23 20-Feb-24 128 36
GR-CON-Z08-1319 Raft 25-Sep-23 15-Oct-23 18 36
GR-CON-Z08-1321 Wall 21-Oct-23 18-Nov-23 25 36
GR-CON-Z08-1322 Stairs 19-Nov-23 23-Nov-23 5 36
GR-CON-Z08-1323 Slabs and Beams 25-Nov-23 14-Dec-23 18 36
GR-CON-Z08-1320 Columns 16-Dec-23 01-Jan-24 15 36
GR-CON-Z08-1325 Stairs (pump room) 02-Jan-24 07-Jan-24 5 36
GR-CON-Z08-1326 Slabs and Beams Ground floor (pump room) 08-Jan-24 05-Feb-24 25 36
GR-CON-Z08-1324 Columns (pump room) 06-Feb-24 20-Feb-24 13 36
Waterproofing 03-Sep-23 02-Apr-24 177 36
GR-CON-Z08-1329 Waterproofing to structures, / tank) horizontal and vertical 03-Sep-23 24-Sep-23 18 36
GR-CON-Z08-1327 Water stop 16-Oct-23 19-Oct-23 4 36
GR-CON-Z08-1328 Surface preparation 21-Feb-24 06-Mar-24 13 36
GR-CON-Z08-1330 Roof waterproofing 07-Mar-24 02-Apr-24 18 36
Architectural Works 02-Apr-24 25-May-24 39 36
GR-CON-Z08-1331 Blockwork 02-Apr-24 22-Apr-24 11 36
GR-CON-Z08-1332 Floor finish 22-Apr-24 02-May-24 9 36
GR-CON-Z08-1333 Wall finish 02-May-24 13-May-24 9 36
GR-CON-Z08-1334 Door installation 13-May-24 18-May-24 4 36
GR-CON-Z08-1336 Celling finish 18-May-24 25-May-24 6 36
Mechanical Works 16-Oct-23 12-Sep-24 271 36
Piping Works 16-Oct-23 15-Feb-24 106 157
GR-CON-Z08-1337 Excavation of Pipe Irrigation 16-Oct-23 11-Nov-23 23 157
GR-CON-Z08-1338 Sand Bedding 12-Nov-23 21-Nov-23 9 157
GR-CON-Z08-1339 HDPE Pipe Installations and fittings 22-Nov-23 24-Dec-23 28 157
GR-CON-Z08-1340 Thrust Blocks 25-Dec-23 04-Jan-24 10 157
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1341 Test pressure 06-Jan-24 20-Jan-24 13 157


GR-CON-Z08-1355 Back filling (sand / Subbase ) 21-Jan-24 15-Feb-24 23 157
Pipe Works Specialties 25-May-24 28-Jul-24 51 36
GR-CON-Z08-1342 Excavation chamber 25-May-24 04-Jun-24 9 36
GR-CON-Z08-1343 Installation chamber 04-Jun-24 08-Jul-24 25 36
GR-CON-Z08-1344 Installation valve (Gate /Air / Washout / …..) 08-Jul-24 23-Jul-24 13 36
GR-CON-Z08-1345 Tie-in Point 23-Jul-24 28-Jul-24 4 36
Pump Works 28-Jul-24 12-Sep-24 40 36
GR-CON-Z08-1346 Irrigation pump 28-Jul-24 01-Aug-24 4 36
GR-CON-Z08-1347 Piping system ( valves and connection to main network ) 01-Aug-24 01-Sep-24 26 36
GR-CON-Z08-1348 Vent crowl 01-Sep-24 07-Sep-24 5 36
GR-CON-Z08-1349 Sensor With Alarm (Low level / High level ) 07-Sep-24 12-Sep-24 5 36
Electrical Works 22-Apr-24 29-Sep-24 132 36
GR-CON-Z08-1350 Conduits Installation 22-Apr-24 02-May-24 9 36
GR-CON-Z08-1351 Install of power cables 10-Jun-24 16-Jun-24 5 98
GR-CON-Z08-1352 Earthing and lightning protection system 10-Jun-24 16-Jun-24 5 98
GR-CON-Z08-1353 Installation of wiring devices and lighting fixtures 16-Jun-24 01-Jul-24 9 98
GR-CON-Z08-1354 Connecting to Main Network 12-Sep-24 29-Sep-24 13 36
Future Neighborhood Park FNP-02 24-Jul-23 08-Jun-24 264 139
Site Preparation 24-Jul-23 15-Aug-23 20 371
GR-CON-Z08-1026 Demolition (Asphalt.Paving,etc.....) 24-Jul-23 27-Jul-23 4 140
GR-CON-Z08-1027 Excavation And Disposal 29-Jul-23 03-Aug-23 6 264
GR-CON-Z08-1028 Prepretion And Compaction 05-Aug-23 08-Aug-23 4 371
GR-CON-Z08-1029 Backfilling 09-Aug-23 15-Aug-23 6 371
Curbstone and Paving 05-Aug-23 27-Sep-23 46 335
GR-CON-Z08-1030 Excavation Curbstone 05-Aug-23 09-Aug-23 5 321
GR-CON-Z08-1031 Plain Concrete 10-Aug-23 16-Aug-23 6 323
GR-CON-Z08-1032 Installation Curbstone 17-Aug-23 27-Aug-23 9 323
GR-CON-Z08-1033 Casting Concrete (Mortar haunch) 28-Aug-23 31-Aug-23 4 323
GR-CON-Z08-1034 Backfilling (sand / Sub base) 02-Sep-23 11-Sep-23 9 335
GR-CON-Z08-1035 Installation of Paving 12-Sep-23 27-Sep-23 13 335
Landscape Works 10-Aug-23 08-Jun-24 249 127
GR-CON-Z08-1036 Excavation (Tree Pit ) 10-Aug-23 15-Aug-23 5 321
GR-CON-Z08-1037 Aggregate Drainage layer 16-Aug-23 22-Aug-23 6 321
GR-CON-Z08-1038 Installation Geotextile 23-Aug-23 27-Aug-23 4 321
GR-CON-Z08-1039 Backfilling (Soil max for tree) 28-Aug-23 03-Sep-23 6 321
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1040 Installation of Trees 30-Apr-24 01-May-24 2 127


GR-CON-Z08-1926 Installation of Shrubs 02-May-24 04-May-24 2 127
GR-CON-Z08-1936 Installation of Succulents 05-May-24 06-May-24 2 127
GR-CON-Z08-1946 Installation of Ground Covers 07-May-24 08-May-24 2 127
GR-CON-Z08-1956 Installation of Climbers 09-May-24 11-May-24 2 127
GR-CON-Z08-1966 Installation of Grass 12-May-24 13-May-24 2 127
GR-CON-Z08-1976 Installation of Lawns 14-May-24 15-May-24 2 127
GR-CON-Z08-1041 Backfilling (Mulch) 16-May-24 19-May-24 3 127
GR-CON-Z08-1042 Natural Boulders Installation 20-May-24 23-May-24 4 127
GR-CON-Z08-1043 Retaining walls . Steps, forming risers, treads and edges with finishes
25-May-24 08-Jun-24 13 127
Irrigation Works 05-Aug-23 08-Jun-24 254 139
GR-CON-Z08-1044 Excavation Pipe Irrigation 05-Aug-23 09-Aug-23 5 264
GR-CON-Z08-1045 Sand Bedding 10-Aug-23 13-Aug-23 3 264
GR-CON-Z08-1046 HDPE Pipe Installations and fittings and conduit for cable 28-Aug-23 14-Sep-23 15 251
GR-CON-Z08-1048 Test pressure 14-Sep-23 20-Sep-23 5 251
GR-CON-Z08-1047 Installation of Valves and Accessories 20-Sep-23 26-Sep-23 4 251
GR-CON-Z08-1049 Back filling (sand / Subbase ) 26-Sep-23 03-Oct-23 6 251
GR-CON-Z08-1050 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Oct-23 10-Oct-23 6 328
GR-CON-Z08-1051 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
30-May-24
system 08-Jun-24 8 139
Mosque M-38 29-Jul-23 16-Jul-24 289 98
Site Preparation 29-Jul-23 19-Aug-23 19 346
GR-CON-Z08-1052 Demolition (Asphalt.Paving,etc.....) 29-Jul-23 01-Aug-23 4 140
GR-CON-Z08-1053 Excavation And Disposal 02-Aug-23 07-Aug-23 5 261
GR-CON-Z08-1054 Prepretion And Compaction 08-Aug-23 12-Aug-23 4 346
GR-CON-Z08-1055 Backfilling 13-Aug-23 19-Aug-23 6 346
Curbstone and Paving 20-Aug-23 13-Sep-23 22 346
GR-CON-Z08-1060 Backfilling (sand / Sub base) 20-Aug-23 29-Aug-23 9 346
GR-CON-Z08-1061 Installation of Paving 30-Aug-23 13-Sep-23 13 346
Landscape Works 08-Aug-23 16-Jul-24 280 98
GR-CON-Z08-1062 Excavation (Tree Pit ) 08-Aug-23 13-Aug-23 5 294
GR-CON-Z08-1063 Aggregate Drainage layer 14-Aug-23 20-Aug-23 6 294
GR-CON-Z08-1064 Installation Geotextile 21-Aug-23 26-Aug-23 5 294
GR-CON-Z08-1065 Backfilling (Soil max for tree) 27-Aug-23 31-Aug-23 5 294
GR-CON-Z08-1066 Installation of Trees 30-Apr-24 04-May-24 4 98
GR-CON-Z08-3786 Installation of Climbers 05-May-24 08-May-24 4 98
GR-CON-Z08-3796 Installation of Shrubs 09-May-24 13-May-24 4 98
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-3806 Installation of Succulents 14-May-24 18-May-24 4 98


GR-CON-Z08-3816 Installation of Ground Covers 19-May-24 22-May-24 4 98
GR-CON-Z08-1067 Backfilling (Mulch) 23-May-24 09-Jun-24 15 98
GR-CON-Z08-1068 Natural Boulders Installation 10-Jun-24 29-Jun-24 13 98
GR-CON-Z08-1069 Retaining walls . Steps, forming risers, treads and edges with finishes
30-Jun-24 16-Jul-24 15 98
Irrigation Works 08-Aug-23 16-Jul-24 280 98
GR-CON-Z08-1070 Excavation Pipe Irrigation 08-Aug-23 13-Aug-23 5 261
GR-CON-Z08-1071 Sand Bedding 14-Aug-23 16-Aug-23 3 261
GR-CON-Z08-1072 HDPE Pipe Installations and fittings and conduit for cable 28-Aug-23 14-Sep-23 15 251
GR-CON-Z08-1074 Test pressure 14-Sep-23 20-Sep-23 5 251
GR-CON-Z08-1073 Installation of Valves and Accessories 20-Sep-23 26-Sep-23 4 251
GR-CON-Z08-1075 Back filling (sand / Subbase ) 26-Sep-23 03-Oct-23 6 251
GR-CON-Z08-1076 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Oct-23 10-Oct-23 6 318
GR-CON-Z08-1077 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Jul-24
system 16-Jul-24 6 98
Mosque M-04 02-Aug-23 16-Jul-24 285 98
Site Preparation 02-Aug-23 23-Aug-23 19 342
GR-CON-Z08-1078 Demolition (Asphalt.Paving,etc.....) 02-Aug-23 06-Aug-23 4 140
GR-CON-Z08-1079 Excavation And Disposal 07-Aug-23 12-Aug-23 5 257
GR-CON-Z08-1080 Prepretion And Compaction 13-Aug-23 16-Aug-23 4 342
GR-CON-Z08-1081 Backfilling 17-Aug-23 23-Aug-23 6 342
Curbstone and Paving 24-Aug-23 18-Sep-23 22 342
GR-CON-Z08-1086 Backfilling (sand / Sub base) 24-Aug-23 03-Sep-23 9 342
GR-CON-Z08-1087 Installation of Paving 04-Sep-23 18-Sep-23 13 342
Landscape Works 13-Aug-23 16-Jul-24 276 98
GR-CON-Z08-1088 Excavation (Tree Pit ) 13-Aug-23 17-Aug-23 5 290
GR-CON-Z08-1089 Aggregate Drainage layer 19-Aug-23 24-Aug-23 6 290
GR-CON-Z08-1090 Installation Geotextile 26-Aug-23 30-Aug-23 5 290
GR-CON-Z08-1091 Backfilling (Soil max for tree) 31-Aug-23 05-Sep-23 5 290
GR-CON-Z08-1092 Installation of Trees 30-Apr-24 04-May-24 4 98
GR-CON-Z08-3826 Installation of Climbers 05-May-24 08-May-24 4 98
GR-CON-Z08-3836 Installation of Shrubs 09-May-24 13-May-24 4 98
GR-CON-Z08-3846 Installation of Succulents 14-May-24 18-May-24 4 98
GR-CON-Z08-3856 Installation of Ground Covers 19-May-24 22-May-24 4 98
GR-CON-Z08-1093 Backfilling (Mulch) 23-May-24 09-Jun-24 15 98
GR-CON-Z08-1094 Natural Boulders Installation 10-Jun-24 29-Jun-24 13 98
GR-CON-Z08-1095 Retaining walls . Steps, forming risers, treads and edges with finishes
30-Jun-24 16-Jul-24 15 98
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 13-Aug-23 16-Jul-24 276 98


GR-CON-Z08-1096 Excavation Pipe Irrigation 13-Aug-23 17-Aug-23 5 257
GR-CON-Z08-1097 Sand Bedding 19-Aug-23 21-Aug-23 3 257
GR-CON-Z08-1098 HDPE Pipe Installations and fittings and conduit for cable 28-Aug-23 14-Sep-23 15 251
GR-CON-Z08-1100 Test pressure 14-Sep-23 20-Sep-23 5 251
GR-CON-Z08-1099 Installation of Valves and Accessories 20-Sep-23 26-Sep-23 4 251
GR-CON-Z08-1101 Back filling (sand / Subbase ) 26-Sep-23 03-Oct-23 6 251
GR-CON-Z08-1102 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Oct-23 10-Oct-23 6 318
GR-CON-Z08-1103 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Jul-24
system 16-Jul-24 6 98
Parking P-48 05-Aug-23 01-Jun-24 248 133
Site Preparation 05-Aug-23 10-Aug-23 6 362
GR-CON-Z08-1107 Backfilling 05-Aug-23 10-Aug-23 6 362
GR-CON-Z08-1105 Excavation And Disposal 06-Aug-23 10-Aug-23 5 258
GR-CON-Z08-1104 Demolition (Asphalt.Paving,etc.....) 07-Aug-23 10-Aug-23 4 140
GR-CON-Z08-1106 Prepretion And Compaction 07-Aug-23 10-Aug-23 4 362
Curbstone and Paving 12-Aug-23 04-Oct-23 46 329
GR-CON-Z08-1108 Excavation Curbstone 12-Aug-23 16-Aug-23 5 321
GR-CON-Z08-1109 Plain Concrete 17-Aug-23 23-Aug-23 6 329
GR-CON-Z08-1110 Installation Curbstone 24-Aug-23 03-Sep-23 9 329
GR-CON-Z08-1111 Casting Concrete (Mortar haunch) 04-Sep-23 07-Sep-23 4 329
GR-CON-Z08-1112 Backfilling (sand / Sub base) 09-Sep-23 18-Sep-23 9 329
GR-CON-Z08-1113 Installation of Paving 19-Sep-23 04-Oct-23 13 329
Landscape Works 17-Aug-23 20-May-24 227 133
GR-CON-Z08-1114 Excavation (Tree Pit ) 17-Aug-23 22-Aug-23 5 321
GR-CON-Z08-1115 Aggregate Drainage layer 23-Aug-23 29-Aug-23 6 321
GR-CON-Z08-1116 Installation Geotextile 30-Aug-23 03-Sep-23 4 321
GR-CON-Z08-1117 Backfilling (Soil max for tree) 04-Sep-23 10-Sep-23 6 321
GR-CON-Z08-1118 Installation of Trees 30-Apr-24 02-May-24 3 133
GR-CON-Z08-7256 Installation of Shrubs 04-May-24 06-May-24 3 133
GR-CON-Z08-7266 Installation of Ground Covers 07-May-24 09-May-24 3 133
GR-CON-Z08-7276 Installation of Succulents 11-May-24 13-May-24 3 133
GR-CON-Z08-7286 Installation of Grass 14-May-24 16-May-24 3 133
GR-CON-Z08-1119 Backfilling (Mulch) 18-May-24 20-May-24 3 133
Site Furnishing 21-May-24 01-Jun-24 10 133
GR-CON-Z08-1130 Tree Grate 21-May-24 26-May-24 5 133
GR-CON-Z08-1131 Wheel stoppers 27-May-24 01-Jun-24 5 133
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 12-Aug-23 01-Jun-24 242 133


GR-CON-Z08-1122 Excavation Pipe Irrigation 12-Aug-23 16-Aug-23 5 258
GR-CON-Z08-1123 Sand Bedding 17-Aug-23 20-Aug-23 3 258
GR-CON-Z08-1124 HDPE Pipe Installations and fittings and conduit for cable 28-Aug-23 14-Sep-23 15 251
GR-CON-Z08-1126 Test pressure 14-Sep-23 20-Sep-23 5 251
GR-CON-Z08-1125 Installation of Valves and Accessories 20-Sep-23 26-Sep-23 4 251
GR-CON-Z08-1127 Back filling (sand / Subbase ) 26-Sep-23 03-Oct-23 6 251
GR-CON-Z08-1128 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Oct-23 10-Oct-23 6 316
GR-CON-Z08-1129 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-May-24
system 01-Jun-24 8 133
Street SS-113 22-Aug-23 07-Jul-24 259 106
Site Preparation 22-Aug-23 16-Sep-23 21 344
GR-CON-Z08-1132 Demolition (Asphalt.Paving,etc.....) 22-Aug-23 27-Aug-23 4 130
GR-CON-Z08-1133 Excavation And Disposal 27-Aug-23 02-Sep-23 5 238
GR-CON-Z08-1134 Prepretion And Compaction 02-Sep-23 09-Sep-23 6 344
GR-CON-Z08-1135 Backfilling 09-Sep-23 16-Sep-23 6 344
Curbstone and Paving 02-Sep-23 26-Oct-23 46 310
GR-CON-Z08-1136 Excavation Curbstone 02-Sep-23 07-Sep-23 5 275
GR-CON-Z08-1137 Plain Concrete 07-Sep-23 14-Sep-23 6 310
GR-CON-Z08-1138 Installation Curbstone 14-Sep-23 26-Sep-23 9 310
GR-CON-Z08-1139 Casting Concrete (Mortar haunch) 26-Sep-23 01-Oct-23 4 310
GR-CON-Z08-1140 Backfilling (sand / Sub base) 01-Oct-23 11-Oct-23 9 310
GR-CON-Z08-1141 Installation of Paving 11-Oct-23 26-Oct-23 13 310
Landscape Works 07-Sep-23 09-Jun-24 225 106
GR-CON-Z08-1142 Excavation (Tree Pit ) 07-Sep-23 13-Sep-23 5 275
GR-CON-Z08-1143 Aggregate Drainage layer 13-Sep-23 20-Sep-23 6 275
GR-CON-Z08-1144 Installation Geotextile 20-Sep-23 26-Sep-23 4 275
GR-CON-Z08-1145 Backfilling (Soil max for tree) 26-Sep-23 03-Oct-23 6 275
GR-CON-Z08-1146 Installation of Trees 30-Apr-24 02-May-24 3 106
GR-CON-Z08-10816 Installation of Shrubs 04-May-24 06-May-24 3 106
GR-CON-Z08-10826 Installation of Succulents 07-May-24 09-May-24 3 106
GR-CON-Z08-10836 Installation of Ground Covers 11-May-24 13-May-24 3 106
GR-CON-Z08-10846 Installation of Grass 14-May-24 16-May-24 3 106
GR-CON-Z08-1147 Backfilling (Mulch) 18-May-24 20-May-24 3 106
GR-CON-Z08-1148 Natural Boulders Installation 21-May-24 25-May-24 4 106
GR-CON-Z08-1149 Retaining walls . Steps, forming risers, treads and edges with finishes
26-May-24 09-Jun-24 13 106
Site Furnishing 10-Jun-24 07-Jul-24 20 106
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1158 Garden planter box 10-Jun-24 15-Jun-24 5 106


GR-CON-Z08-1159 Wheel stoppers 16-Jun-24 25-Jun-24 5 106
GR-CON-Z08-1160 Steel Lattice 26-Jun-24 01-Jul-24 5 106
GR-CON-Z08-1161 Handrail 02-Jul-24 07-Jul-24 5 106
Storm Piping Works 01-Jul-24 07-Jul-24 6 106
GR-CON-Z08-1162 Installation of DI grating covers 01-Jul-24 07-Jul-24 6 106
Irrigation Works 02-Sep-23 04-Nov-23 53 297
GR-CON-Z08-1150 Excavation Pipe Irrigation 02-Sep-23 07-Sep-23 5 238
GR-CON-Z08-1151 Sand Bedding 07-Sep-23 12-Sep-23 4 238
GR-CON-Z08-1152 HDPE Pipe Installations and fittings and conduit for cable 12-Sep-23 01-Oct-23 15 238
GR-CON-Z08-1154 Test pressure 01-Oct-23 07-Oct-23 5 238
GR-CON-Z08-1153 Installation of Valves and Accessories 07-Oct-23 11-Oct-23 4 238
GR-CON-Z08-1155 Back filling (sand / Subbase ) 11-Oct-23 18-Oct-23 6 238
GR-CON-Z08-1156 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Oct-23 25-Oct-23 6 297
GR-CON-Z08-1157 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Oct-23
system 04-Nov-23 8 297
Electrical Works 07-Sep-23 07-Jul-24 245 106
GR-CON-Z08-1163 Excavation And Disposal 07-Sep-23 13-Sep-23 5 324
GR-CON-Z08-1164 Sand Bedding 13-Sep-23 18-Sep-23 4 324
GR-CON-Z08-1165 laying cables 18-Sep-23 24-Sep-23 4 324
GR-CON-Z08-1166 Backfilling (sand / Sub base) 24-Sep-23 30-Sep-23 5 324
GR-CON-Z08-1167 Control Panel / Distribution Panel Installation 30-Sep-23 04-Oct-23 4 324
GR-CON-Z08-1168 Road Crossing Ducts 02-Jul-24 07-Jul-24 5 106
Street SS-02 19-Sep-23 04-Aug-24 259 82
Site Preparation 19-Sep-23 28-Oct-23 32 309
GR-CON-Z08-1169 Demolition (Asphalt.Paving,etc.....) 19-Sep-23 27-Sep-23 6 110
GR-CON-Z08-1170 Excavation And Disposal 27-Sep-23 07-Oct-23 8 188
GR-CON-Z08-1171 Prepretion And Compaction 07-Oct-23 17-Oct-23 9 309
GR-CON-Z08-1172 Backfilling 17-Oct-23 28-Oct-23 9 309
Curbstone and Paving 07-Oct-23 28-Dec-23 71 256
GR-CON-Z08-1173 Excavation Curbstone 07-Oct-23 16-Oct-23 8 208
GR-CON-Z08-1174 Plain Concrete 16-Oct-23 26-Oct-23 9 256
GR-CON-Z08-1175 Installation Curbstone 26-Oct-23 12-Nov-23 14 256
GR-CON-Z08-1176 Casting Concrete (Mortar haunch) 12-Nov-23 19-Nov-23 6 256
GR-CON-Z08-1177 Backfilling (sand / Sub base) 19-Nov-23 05-Dec-23 14 256
GR-CON-Z08-1178 Installation of Paving 05-Dec-23 28-Dec-23 20 256
Landscape Works 16-Oct-23 27-Jun-24 205 82
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1179 Excavation (Tree Pit ) 16-Oct-23 25-Oct-23 8 208


GR-CON-Z08-1180 Aggregate Drainage layer 25-Oct-23 05-Nov-23 9 208
GR-CON-Z08-1181 Installation Geotextile 05-Nov-23 12-Nov-23 6 208
GR-CON-Z08-1182 Backfilling (Soil max for tree) 12-Nov-23 22-Nov-23 9 208
GR-CON-Z08-1183 Installation of Trees 30-Apr-24 04-May-24 4 82
GR-CON-Z08-10856 Installation of Shrubs 05-May-24 07-May-24 3 82
GR-CON-Z08-10866 Installation of Succulents 08-May-24 11-May-24 3 82
GR-CON-Z08-10876 Installation of Ground Covers 12-May-24 14-May-24 3 82
GR-CON-Z08-10886 Installation of Grass 15-May-24 18-May-24 3 82
GR-CON-Z08-1184 Backfilling (Mulch) 19-May-24 23-May-24 5 82
GR-CON-Z08-1185 Natural Boulders Installation 25-May-24 30-May-24 6 82
GR-CON-Z08-1186 Retaining walls . Steps, forming risers, treads and edges with finishes
01-Jun-24 27-Jun-24 20 82
Site Furnishing 29-Jun-24 04-Aug-24 32 82
GR-CON-Z08-1195 Garden planter box 29-Jun-24 07-Jul-24 8 82
GR-CON-Z08-1196 Wheel stoppers 08-Jul-24 16-Jul-24 8 82
GR-CON-Z08-1197 Steel Lattice 17-Jul-24 25-Jul-24 8 82
GR-CON-Z08-1198 Handrail 27-Jul-24 04-Aug-24 8 82
Storm Piping Works 25-Jul-24 04-Aug-24 9 82
GR-CON-Z08-1199 Installation of DI grating covers 25-Jul-24 04-Aug-24 9 82
Irrigation Works 07-Oct-23 09-Jan-24 81 237
GR-CON-Z08-1187 Excavation Pipe Irrigation 07-Oct-23 16-Oct-23 8 188
GR-CON-Z08-1188 Sand Bedding 16-Oct-23 23-Oct-23 6 188
GR-CON-Z08-1189 HDPE Pipe Installations and fittings and conduit for cable 23-Oct-23 19-Nov-23 23 188
GR-CON-Z08-1191 Test pressure 19-Nov-23 28-Nov-23 8 188
GR-CON-Z08-1190 Installation of Valves and Accessories 28-Nov-23 05-Dec-23 6 188
GR-CON-Z08-1192 Back filling (sand / Subbase ) 05-Dec-23 16-Dec-23 9 188
GR-CON-Z08-1193 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Dec-23 26-Dec-23 9 237
GR-CON-Z08-1194 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-Dec-23
system 09-Jan-24 12 237
Electrical Works 16-Oct-23 04-Aug-24 237 82
GR-CON-Z08-1200 Excavation And Disposal 16-Oct-23 25-Oct-23 8 277
GR-CON-Z08-1201 Sand Bedding 25-Oct-23 01-Nov-23 6 277
GR-CON-Z08-1202 laying cables 01-Nov-23 08-Nov-23 6 277
GR-CON-Z08-1203 Backfilling (sand / Sub base) 08-Nov-23 18-Nov-23 8 277
GR-CON-Z08-1204 Control Panel / Distribution Panel Installation 18-Nov-23 25-Nov-23 6 277
GR-CON-Z08-1205 Road Crossing Ducts 27-Jul-24 04-Aug-24 8 82
Street SS-85 01-Oct-23 07-Jul-24 226 106
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 01-Oct-23 25-Oct-23 21 311


GR-CON-Z08-1206 Demolition (Asphalt.Paving,etc.....) 01-Oct-23 05-Oct-23 4 107
GR-CON-Z08-1207 Excavation And Disposal 05-Oct-23 11-Oct-23 5 205
GR-CON-Z08-1208 Prepretion And Compaction 11-Oct-23 18-Oct-23 6 311
GR-CON-Z08-1209 Backfilling 18-Oct-23 25-Oct-23 6 311
Curbstone and Paving 11-Oct-23 04-Dec-23 46 277
GR-CON-Z08-1210 Excavation Curbstone 11-Oct-23 17-Oct-23 5 242
GR-CON-Z08-1211 Plain Concrete 17-Oct-23 24-Oct-23 6 277
GR-CON-Z08-1212 Installation Curbstone 24-Oct-23 04-Nov-23 9 277
GR-CON-Z08-1213 Casting Concrete (Mortar haunch) 04-Nov-23 08-Nov-23 4 277
GR-CON-Z08-1214 Backfilling (sand / Sub base) 08-Nov-23 19-Nov-23 9 277
GR-CON-Z08-1215 Installation of Paving 19-Nov-23 04-Dec-23 13 277
Landscape Works 17-Oct-23 09-Jun-24 192 106
GR-CON-Z08-1216 Excavation (Tree Pit ) 17-Oct-23 23-Oct-23 5 242
GR-CON-Z08-1217 Aggregate Drainage layer 23-Oct-23 30-Oct-23 6 242
GR-CON-Z08-1218 Installation Geotextile 30-Oct-23 04-Nov-23 4 242
GR-CON-Z08-1219 Backfilling (Soil max for tree) 04-Nov-23 11-Nov-23 6 242
GR-CON-Z08-1220 Installation of Trees 30-Apr-24 02-May-24 3 106
GR-CON-Z08-10896 Installation of Shrubs 04-May-24 06-May-24 3 106
GR-CON-Z08-10906 Installation of Succulents 07-May-24 09-May-24 3 106
GR-CON-Z08-10916 Installation of Ground Covers 11-May-24 13-May-24 3 106
GR-CON-Z08-10926 Installation of Grass 14-May-24 16-May-24 3 106
GR-CON-Z08-1221 Backfilling (Mulch) 18-May-24 20-May-24 3 106
GR-CON-Z08-1222 Natural Boulders Installation 21-May-24 25-May-24 4 106
GR-CON-Z08-1223 Retaining walls . Steps, forming risers, treads and edges with finishes
26-May-24 09-Jun-24 13 106
Site Furnishing 10-Jun-24 07-Jul-24 20 106
GR-CON-Z08-1232 Garden planter box 10-Jun-24 15-Jun-24 5 106
GR-CON-Z08-1233 Wheel stoppers 16-Jun-24 25-Jun-24 5 106
GR-CON-Z08-1234 Steel Lattice 26-Jun-24 01-Jul-24 5 106
GR-CON-Z08-1235 Handrail 02-Jul-24 07-Jul-24 5 106
Storm Piping Works 01-Jul-24 07-Jul-24 6 106
GR-CON-Z08-1236 Installation of DI grating covers 01-Jul-24 07-Jul-24 6 106
Irrigation Works 11-Oct-23 12-Dec-23 53 264
GR-CON-Z08-1224 Excavation Pipe Irrigation 11-Oct-23 17-Oct-23 5 205
GR-CON-Z08-1225 Sand Bedding 17-Oct-23 22-Oct-23 4 205
GR-CON-Z08-1226 HDPE Pipe Installations and fittings and conduit for cable 22-Oct-23 08-Nov-23 15 205
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1228 Test pressure 08-Nov-23 14-Nov-23 5 205


GR-CON-Z08-1227 Installation of Valves and Accessories 14-Nov-23 19-Nov-23 4 205
GR-CON-Z08-1229 Back filling (sand / Subbase ) 19-Nov-23 26-Nov-23 6 205
GR-CON-Z08-1230 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 26-Nov-23 03-Dec-23 6 264
GR-CON-Z08-1231 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Dec-23
system 12-Dec-23 8 264
Electrical Works 17-Oct-23 07-Jul-24 212 106
GR-CON-Z08-1237 Excavation And Disposal 17-Oct-23 23-Oct-23 5 291
GR-CON-Z08-1238 Sand Bedding 23-Oct-23 28-Oct-23 4 291
GR-CON-Z08-1239 laying cables 28-Oct-23 01-Nov-23 4 291
GR-CON-Z08-1240 Backfilling (sand / Sub base) 01-Nov-23 07-Nov-23 5 291
GR-CON-Z08-1241 Control Panel / Distribution Panel Installation 07-Nov-23 12-Nov-23 4 291
GR-CON-Z08-1242 Road Crossing Ducts 02-Jul-24 07-Jul-24 5 106
Street SS-86 11-Oct-23 07-Jul-24 217 106
Site Preparation 11-Oct-23 05-Nov-23 21 302
GR-CON-Z08-1243 Demolition (Asphalt.Paving,etc.....) 11-Oct-23 16-Oct-23 4 102
GR-CON-Z08-1244 Excavation And Disposal 16-Oct-23 22-Oct-23 5 196
GR-CON-Z08-1245 Prepretion And Compaction 22-Oct-23 29-Oct-23 6 302
GR-CON-Z08-1246 Backfilling 29-Oct-23 05-Nov-23 6 302
Curbstone and Paving 22-Oct-23 14-Dec-23 46 268
GR-CON-Z08-1247 Excavation Curbstone 22-Oct-23 28-Oct-23 5 233
GR-CON-Z08-1248 Plain Concrete 28-Oct-23 04-Nov-23 6 268
GR-CON-Z08-1249 Installation Curbstone 04-Nov-23 14-Nov-23 9 268
GR-CON-Z08-1250 Casting Concrete (Mortar haunch) 14-Nov-23 19-Nov-23 4 268
GR-CON-Z08-1251 Backfilling (sand / Sub base) 19-Nov-23 29-Nov-23 9 268
GR-CON-Z08-1252 Installation of Paving 29-Nov-23 14-Dec-23 13 268
Landscape Works 28-Oct-23 09-Jun-24 183 106
GR-CON-Z08-1253 Excavation (Tree Pit ) 28-Oct-23 02-Nov-23 5 233
GR-CON-Z08-1254 Aggregate Drainage layer 02-Nov-23 09-Nov-23 6 233
GR-CON-Z08-1255 Installation Geotextile 09-Nov-23 14-Nov-23 4 233
GR-CON-Z08-1256 Backfilling (Soil max for tree) 14-Nov-23 21-Nov-23 6 233
GR-CON-Z08-1257 Installation of Trees 30-Apr-24 02-May-24 3 106
GR-CON-Z08-10936 Installation of Shrubs 04-May-24 06-May-24 3 106
GR-CON-Z08-10946 Installation of Succulents 07-May-24 09-May-24 3 106
GR-CON-Z08-10956 Installation of Ground Covers 11-May-24 13-May-24 3 106
GR-CON-Z08-10966 Installation of Grass 14-May-24 16-May-24 3 106
GR-CON-Z08-1258 Backfilling (Mulch) 18-May-24 20-May-24 3 106
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1259 Natural Boulders Installation 21-May-24 25-May-24 4 106


GR-CON-Z08-1260 Retaining walls . Steps, forming risers, treads and edges with finishes
26-May-24 09-Jun-24 13 106
Site Furnishing 10-Jun-24 07-Jul-24 20 106
GR-CON-Z08-1269 Garden planter box 10-Jun-24 15-Jun-24 5 106
GR-CON-Z08-1270 Wheel stoppers 16-Jun-24 25-Jun-24 5 106
GR-CON-Z08-1271 Steel Lattice 26-Jun-24 01-Jul-24 5 106
GR-CON-Z08-1272 Handrail 02-Jul-24 07-Jul-24 5 106
Storm Piping Works 01-Jul-24 07-Jul-24 6 106
GR-CON-Z08-1273 Installation of DI grating covers 01-Jul-24 07-Jul-24 6 106
Irrigation Works 22-Oct-23 23-Dec-23 53 255
GR-CON-Z08-1261 Excavation Pipe Irrigation 22-Oct-23 28-Oct-23 5 196
GR-CON-Z08-1262 Sand Bedding 28-Oct-23 01-Nov-23 4 196
GR-CON-Z08-1263 HDPE Pipe Installations and fittings and conduit for cable 01-Nov-23 19-Nov-23 15 196
GR-CON-Z08-1265 Test pressure 19-Nov-23 25-Nov-23 5 196
GR-CON-Z08-1264 Installation of Valves and Accessories 25-Nov-23 29-Nov-23 4 196
GR-CON-Z08-1266 Back filling (sand / Subbase ) 29-Nov-23 06-Dec-23 6 196
GR-CON-Z08-1267 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Dec-23 13-Dec-23 6 255
GR-CON-Z08-1268 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Dec-23
system 23-Dec-23 8 255
Electrical Works 28-Oct-23 07-Jul-24 203 106
GR-CON-Z08-1274 Excavation And Disposal 28-Oct-23 02-Nov-23 5 282
GR-CON-Z08-1275 Sand Bedding 02-Nov-23 07-Nov-23 4 282
GR-CON-Z08-1276 laying cables 07-Nov-23 12-Nov-23 4 282
GR-CON-Z08-1277 Backfilling (sand / Sub base) 12-Nov-23 18-Nov-23 5 282
GR-CON-Z08-1278 Control Panel / Distribution Panel Installation 18-Nov-23 22-Nov-23 4 282
GR-CON-Z08-1279 Road Crossing Ducts 02-Jul-24 07-Jul-24 5 106
Street SS-96 08-Nov-23 07-Jul-24 193 106
Site Preparation 08-Nov-23 03-Dec-23 21 278
GR-CON-Z08-1280 Demolition (Asphalt.Paving,etc.....) 08-Nov-23 13-Nov-23 4 82
GR-CON-Z08-1281 Excavation And Disposal 13-Nov-23 19-Nov-23 5 82
GR-CON-Z08-1282 Prepretion And Compaction 19-Nov-23 26-Nov-23 6 278
GR-CON-Z08-1283 Backfilling 26-Nov-23 03-Dec-23 6 278
Curbstone and Paving 19-Nov-23 11-Jan-24 46 244
GR-CON-Z08-1284 Excavation Curbstone 19-Nov-23 25-Nov-23 5 209
GR-CON-Z08-1285 Plain Concrete 25-Nov-23 02-Dec-23 6 244
GR-CON-Z08-1286 Installation Curbstone 02-Dec-23 12-Dec-23 9 244
GR-CON-Z08-1287 Casting Concrete (Mortar haunch) 12-Dec-23 17-Dec-23 4 244
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1288 Backfilling (sand / Sub base) 17-Dec-23 27-Dec-23 9 244


GR-CON-Z08-1289 Installation of Paving 27-Dec-23 11-Jan-24 13 244
Landscape Works 25-Nov-23 09-Jun-24 159 106
GR-CON-Z08-1290 Excavation (Tree Pit ) 25-Nov-23 30-Nov-23 5 209
GR-CON-Z08-1291 Aggregate Drainage layer 30-Nov-23 07-Dec-23 6 209
GR-CON-Z08-1292 Installation Geotextile 07-Dec-23 12-Dec-23 4 209
GR-CON-Z08-1293 Backfilling (Soil max for tree) 12-Dec-23 19-Dec-23 6 209
GR-CON-Z08-1294 Installation of Trees 30-Apr-24 02-May-24 3 106
GR-CON-Z08-10976 Installation of Shrubs 04-May-24 06-May-24 3 106
GR-CON-Z08-10986 Installation of Succulents 07-May-24 09-May-24 3 106
GR-CON-Z08-10996 Installation of Ground Covers 11-May-24 13-May-24 3 106
GR-CON-Z08-11006 Installation of Grass 14-May-24 16-May-24 3 106
GR-CON-Z08-1295 Backfilling (Mulch) 18-May-24 20-May-24 3 106
GR-CON-Z08-1296 Natural Boulders Installation 21-May-24 25-May-24 4 106
GR-CON-Z08-1297 Retaining walls . Steps, forming risers, treads and edges with finishes
26-May-24 09-Jun-24 13 106
Site Furnishing 10-Jun-24 07-Jul-24 20 106
GR-CON-Z08-1306 Garden planter box 10-Jun-24 15-Jun-24 5 106
GR-CON-Z08-1307 Wheel stoppers 16-Jun-24 25-Jun-24 5 106
GR-CON-Z08-1308 Steel Lattice 26-Jun-24 01-Jul-24 5 106
GR-CON-Z08-1309 Handrail 02-Jul-24 07-Jul-24 5 106
Storm Piping Works 01-Jul-24 07-Jul-24 6 106
GR-CON-Z08-1310 Installation of DI grating covers 01-Jul-24 07-Jul-24 6 106
Irrigation Works 19-Nov-23 20-Jan-24 53 231
GR-CON-Z08-1298 Excavation Pipe Irrigation 19-Nov-23 25-Nov-23 5 82
GR-CON-Z08-1299 Sand Bedding 25-Nov-23 29-Nov-23 4 82
GR-CON-Z08-1300 HDPE Pipe Installations and fittings and conduit for cable 29-Nov-23 17-Dec-23 15 82
GR-CON-Z08-1302 Test pressure 17-Dec-23 23-Dec-23 5 82
GR-CON-Z08-1301 Installation of Valves and Accessories 23-Dec-23 27-Dec-23 4 82
GR-CON-Z08-1303 Back filling (sand / Subbase ) 27-Dec-23 03-Jan-24 6 82
GR-CON-Z08-1304 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Jan-24 10-Jan-24 6 231
GR-CON-Z08-1305 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Jan-24
system 20-Jan-24 8 231
Electrical Works 25-Nov-23 07-Jul-24 179 106
GR-CON-Z08-1311 Excavation And Disposal 25-Nov-23 30-Nov-23 5 258
GR-CON-Z08-1312 Sand Bedding 30-Nov-23 05-Dec-23 4 258
GR-CON-Z08-1313 laying cables 05-Dec-23 10-Dec-23 4 258
GR-CON-Z08-1314 Backfilling (sand / Sub base) 10-Dec-23 16-Dec-23 5 258
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z08-1315 Control Panel / Distribution Panel Installation 16-Dec-23 20-Dec-23 4 258


GR-CON-Z08-1316 Road Crossing Ducts 02-Jul-24 07-Jul-24 5 106
Zone 04 10-Aug-23 05-Oct-24 345 19
Future Neighborhood Park FNP-06 10-Aug-23 01-Jun-24 242 122
Site Preparation 10-Aug-23 02-Sep-23 20 344
GR-CON-Z04-1034 Demolition (Asphalt.Paving,etc.....) 10-Aug-23 14-Aug-23 4 1
GR-CON-Z04-1035 Excavation And Disposal 15-Aug-23 21-Aug-23 6 237
GR-CON-Z04-1036 Prepretion And Compaction 22-Aug-23 26-Aug-23 4 344
GR-CON-Z04-1037 Backfilling 27-Aug-23 02-Sep-23 6 344
Curbstone and Paving 22-Aug-23 15-Oct-23 46 308
GR-CON-Z04-1038 Excavation Curbstone 22-Aug-23 27-Aug-23 5 267
GR-CON-Z04-1039 Plain Concrete 28-Aug-23 03-Sep-23 6 297
GR-CON-Z04-1040 Installation Curbstone 04-Sep-23 13-Sep-23 9 297
GR-CON-Z04-1041 Casting Concrete (Mortar haunch) 14-Sep-23 18-Sep-23 4 297
GR-CON-Z04-1042 Backfilling (sand / Sub base) 19-Sep-23 30-Sep-23 9 297
GR-CON-Z04-1043 Installation of Paving 01-Oct-23 15-Oct-23 13 308
Landscape Works 28-Aug-23 01-Jun-24 227 122
GR-CON-Z04-1044 Excavation (Tree Pit ) 28-Aug-23 02-Sep-23 5 267
GR-CON-Z04-1045 Aggregate Drainage layer 03-Sep-23 09-Sep-23 6 294
GR-CON-Z04-1046 Installation Geotextile 10-Sep-23 13-Sep-23 4 294
GR-CON-Z04-1047 Backfilling (Soil max for tree) 14-Sep-23 20-Sep-23 6 294
GR-CON-Z04-1048 Installation of Trees 22-Apr-24 24-Apr-24 2 122
GR-CON-Z04-1626 Installation of Shrubs 24-Apr-24 27-Apr-24 2 122
GR-CON-Z04-1636 Installation of Succulents 27-Apr-24 29-Apr-24 2 122
GR-CON-Z04-1646 Installation of Ground Covers 29-Apr-24 01-May-24 2 122
GR-CON-Z04-1656 Installation of Climbers 01-May-24 04-May-24 2 122
GR-CON-Z04-1666 Installation of Grass 04-May-24 06-May-24 2 122
GR-CON-Z04-1676 Installation of Lawns 06-May-24 08-May-24 2 122
GR-CON-Z04-1049 Backfilling (Mulch) 08-May-24 12-May-24 3 122
GR-CON-Z04-1050 Natural Boulders Installation 12-May-24 16-May-24 4 122
GR-CON-Z04-1051 Retaining walls . Steps, forming risers, treads and edges with finishes
16-May-24 01-Jun-24 13 122
MUGA 03-Sep-23 01-Jun-24 222 122
GR-CON-Z04-1052 Excavation And Disposal 03-Sep-23 07-Sep-23 5 267
GR-CON-Z04-1053 Prepretion And Compaction 09-Sep-23 14-Sep-23 6 267
GR-CON-Z04-1054 polyethylene under footings ( fence and gates) 16-Sep-23 20-Sep-23 5 267
GR-CON-Z04-1055 Blinding concrete (flooring) 21-Sep-23 27-Sep-23 5 267
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1056 Concrete Footings ( fence and gates) 28-Sep-23 12-Oct-23 13 267


GR-CON-Z04-1057 Tools Play Installation ( basketball / football ..) 02-Jan-24 20-Jan-24 15 197
GR-CON-Z04-1058 PaintAcrylic Play Surface 20-Jan-24 04-Feb-24 13 197
GR-CON-Z04-1059 Fence (high / low) / gates Installation 14-May-24 01-Jun-24 15 122
Irrigation Works 22-Aug-23 01-Jun-24 232 122
GR-CON-Z04-1060 Excavation Pipe Irrigation 22-Aug-23 27-Aug-23 5 237
GR-CON-Z04-1061 Sand Bedding 28-Aug-23 30-Aug-23 3 237
GR-CON-Z04-1062 HDPE Pipe Installations and fittings and conduit for cable 10-Sep-23 28-Sep-23 15 228
GR-CON-Z04-1064 Test pressure 28-Sep-23 04-Oct-23 5 228
GR-CON-Z04-1063 Installation of Valves and Accessories 04-Oct-23 09-Oct-23 4 228
GR-CON-Z04-1065 Back filling (sand / Subbase ) 09-Oct-23 16-Oct-23 6 228
GR-CON-Z04-1066 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Oct-23 23-Oct-23 6 293
GR-CON-Z04-1067 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-May-24
system 01-Jun-24 8 122
Future Neighborhood Park FNP-07 19-Aug-23 03-Jun-24 237 120
Site Preparation 19-Aug-23 13-Sep-23 23 334
GR-CON-Z04-1000 Demolition (Asphalt.Paving,etc.....) 19-Aug-23 23-Aug-23 5 19
GR-CON-Z04-1001 Excavation And Disposal 24-Aug-23 30-Aug-23 6 223
GR-CON-Z04-1002 Prepretion And Compaction 31-Aug-23 05-Sep-23 5 334
GR-CON-Z04-1003 Backfilling 06-Sep-23 13-Sep-23 7 334
Curbstone and Paving 31-Aug-23 31-Oct-23 52 294
GR-CON-Z04-1004 Excavation Curbstone 31-Aug-23 06-Sep-23 6 247
GR-CON-Z04-1005 Plain Concrete 07-Sep-23 14-Sep-23 7 294
GR-CON-Z04-1006 Installation Curbstone 16-Sep-23 27-Sep-23 10 294
GR-CON-Z04-1007 Casting Concrete (Mortar haunch) 28-Sep-23 03-Oct-23 5 294
GR-CON-Z04-1008 Backfilling (sand / Sub base) 04-Oct-23 15-Oct-23 10 294
GR-CON-Z04-1009 Installation of Paving 16-Oct-23 31-Oct-23 14 294
Landscape Works 07-Sep-23 03-Jun-24 220 120
GR-CON-Z04-1010 Excavation (Tree Pit ) 07-Sep-23 13-Sep-23 6 247
GR-CON-Z04-1011 Aggregate Drainage layer 14-Sep-23 21-Sep-23 7 279
GR-CON-Z04-1012 Installation Geotextile 24-Sep-23 28-Sep-23 5 279
GR-CON-Z04-1013 Backfilling (Soil max for tree) 30-Sep-23 07-Oct-23 7 279
GR-CON-Z04-1014 Installation of Trees 22-Apr-24 24-Apr-24 2 120
GR-CON-Z04-1686 Installation of Shrubs 24-Apr-24 27-Apr-24 2 120
GR-CON-Z04-1696 Installation of Succulents 27-Apr-24 29-Apr-24 2 120
GR-CON-Z04-1706 Installation of Ground Covers 29-Apr-24 01-May-24 2 120
GR-CON-Z04-1716 Installation of Climbers 01-May-24 04-May-24 2 120
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1726 Installation of Grass 04-May-24 06-May-24 2 120


GR-CON-Z04-1736 Installation of Lawns 06-May-24 08-May-24 2 120
GR-CON-Z04-1015 Backfilling (Mulch) 08-May-24 12-May-24 3 120
GR-CON-Z04-1016 Natural Boulders Installation 12-May-24 18-May-24 5 120
GR-CON-Z04-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
18-May-24 03-Jun-24 14 120
MUGA 14-Sep-23 03-Jun-24 214 120
GR-CON-Z04-1018 Excavation And Disposal 14-Sep-23 20-Sep-23 6 247
GR-CON-Z04-1019 Prepretion And Compaction 21-Sep-23 30-Sep-23 7 247
GR-CON-Z04-1020 polyethylene under footings ( fence and gates) 01-Oct-23 07-Oct-23 6 247
GR-CON-Z04-1021 Blinding concrete (flooring) 08-Oct-23 14-Oct-23 6 247
GR-CON-Z04-1022 Concrete Footings ( fence and gates) 15-Oct-23 30-Oct-23 14 247
GR-CON-Z04-1023 Tools Play Installation ( basketball / football ..) 02-Jan-24 22-Jan-24 17 192
GR-CON-Z04-1024 PaintAcrylic Play Surface 22-Jan-24 07-Feb-24 14 192
GR-CON-Z04-1025 Fence (high / low) / gates Installation 14-May-24 03-Jun-24 17 120
Irrigation Works 31-Aug-23 03-Jun-24 226 120
GR-CON-Z04-1026 Excavation Pipe Irrigation 31-Aug-23 06-Sep-23 6 223
GR-CON-Z04-1027 Sand Bedding 07-Sep-23 10-Sep-23 3 223
GR-CON-Z04-1028 HDPE Pipe Installations and fittings and conduit for cable 11-Sep-23 01-Oct-23 17 223
GR-CON-Z04-1030 Test pressure 02-Oct-23 08-Oct-23 6 223
GR-CON-Z04-1029 Installation of Valves and Accessories 09-Oct-23 14-Oct-23 5 223
GR-CON-Z04-1031 Back filling (sand / Subbase ) 15-Oct-23 22-Oct-23 7 223
GR-CON-Z04-1032 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-Oct-23 30-Oct-23 7 286
GR-CON-Z04-1033 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-May-24
system 03-Jun-24 9 120
Mosque M-11 28-Aug-23 09-Jul-24 256 93
Site Preparation 28-Aug-23 18-Sep-23 19 308
GR-CON-Z04-1068 Demolition (Asphalt.Paving,etc.....) 28-Aug-23 31-Aug-23 4 19
GR-CON-Z04-1069 Excavation And Disposal 02-Sep-23 06-Sep-23 5 223
GR-CON-Z04-1070 Prepretion And Compaction 07-Sep-23 11-Sep-23 4 308
GR-CON-Z04-1071 Backfilling 12-Sep-23 18-Sep-23 6 308
Curbstone and Paving 19-Sep-23 15-Oct-23 22 308
GR-CON-Z04-1076 Backfilling (sand / Sub base) 19-Sep-23 30-Sep-23 9 308
GR-CON-Z04-1077 Installation of Paving 01-Oct-23 15-Oct-23 13 308
Landscape Works 07-Sep-23 09-Jul-24 247 93
GR-CON-Z04-1078 Excavation (Tree Pit ) 07-Sep-23 12-Sep-23 5 256
GR-CON-Z04-1079 Aggregate Drainage layer 13-Sep-23 19-Sep-23 6 256
GR-CON-Z04-1080 Installation Geotextile 20-Sep-23 26-Sep-23 5 256
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1081 Backfilling (Soil max for tree) 27-Sep-23 02-Oct-23 5 256


GR-CON-Z04-1082 Installation of Trees 22-Apr-24 27-Apr-24 4 93
GR-CON-Z04-3466 Installation of Climbers 27-Apr-24 01-May-24 4 93
GR-CON-Z04-3476 Installation of Shrubs 01-May-24 06-May-24 4 93
GR-CON-Z04-3486 Installation of Succulents 06-May-24 11-May-24 4 93
GR-CON-Z04-3496 Installation of Ground Covers 11-May-24 15-May-24 4 93
GR-CON-Z04-1083 Backfilling (Mulch) 15-May-24 02-Jun-24 15 93
GR-CON-Z04-1084 Natural Boulders Installation 02-Jun-24 17-Jun-24 13 93
GR-CON-Z04-1085 Retaining walls . Steps, forming risers, treads and edges with finishes
17-Jun-24 09-Jul-24 15 93
Irrigation Works 07-Sep-23 09-Jul-24 247 93
GR-CON-Z04-1086 Excavation Pipe Irrigation 07-Sep-23 12-Sep-23 5 223
GR-CON-Z04-1087 Sand Bedding 13-Sep-23 16-Sep-23 3 223
GR-CON-Z04-1088 HDPE Pipe Installations and fittings and conduit for cable 17-Sep-23 04-Oct-23 15 223
GR-CON-Z04-1090 Test pressure 05-Oct-23 10-Oct-23 5 223
GR-CON-Z04-1089 Installation of Valves and Accessories 11-Oct-23 15-Oct-23 4 223
GR-CON-Z04-1091 Back filling (sand / Subbase ) 16-Oct-23 22-Oct-23 6 223
GR-CON-Z04-1092 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-Oct-23 29-Oct-23 6 290
GR-CON-Z04-1093 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Jul-24
system 09-Jul-24 6 93
Mosque M-12 05-Sep-23 09-Jul-24 249 93
Site Preparation 05-Sep-23 27-Sep-23 19 301
GR-CON-Z04-1094 Demolition (Asphalt.Paving,etc.....) 05-Sep-23 09-Sep-23 4 19
GR-CON-Z04-1095 Excavation And Disposal 10-Sep-23 14-Sep-23 5 216
GR-CON-Z04-1096 Prepretion And Compaction 16-Sep-23 19-Sep-23 4 301
GR-CON-Z04-1097 Backfilling 20-Sep-23 27-Sep-23 6 301
Curbstone and Paving 28-Sep-23 23-Oct-23 22 301
GR-CON-Z04-1102 Backfilling (sand / Sub base) 28-Sep-23 08-Oct-23 9 301
GR-CON-Z04-1103 Installation of Paving 09-Oct-23 23-Oct-23 13 301
Landscape Works 16-Sep-23 09-Jul-24 240 93
GR-CON-Z04-1104 Excavation (Tree Pit ) 16-Sep-23 20-Sep-23 5 249
GR-CON-Z04-1105 Aggregate Drainage layer 21-Sep-23 28-Sep-23 6 249
GR-CON-Z04-1106 Installation Geotextile 30-Sep-23 04-Oct-23 5 249
GR-CON-Z04-1107 Backfilling (Soil max for tree) 05-Oct-23 10-Oct-23 5 249
GR-CON-Z04-1108 Installation of Trees 22-Apr-24 27-Apr-24 4 93
GR-CON-Z04-3506 Installation of Climbers 27-Apr-24 01-May-24 4 93
GR-CON-Z04-3516 Installation of Shrubs 01-May-24 06-May-24 4 93
GR-CON-Z04-3526 Installation of Succulents 06-May-24 11-May-24 4 93
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-3536 Installation of Ground Covers 11-May-24 15-May-24 4 93


GR-CON-Z04-1109 Backfilling (Mulch) 15-May-24 02-Jun-24 15 93
GR-CON-Z04-1110 Natural Boulders Installation 02-Jun-24 17-Jun-24 13 93
GR-CON-Z04-1111 Retaining walls . Steps, forming risers, treads and edges with finishes
17-Jun-24 09-Jul-24 15 93
Irrigation Works 16-Sep-23 09-Jul-24 240 93
GR-CON-Z04-1112 Excavation Pipe Irrigation 16-Sep-23 20-Sep-23 5 216
GR-CON-Z04-1113 Sand Bedding 21-Sep-23 25-Sep-23 3 216
GR-CON-Z04-1114 HDPE Pipe Installations and fittings and conduit for cable 26-Sep-23 12-Oct-23 15 216
GR-CON-Z04-1116 Test pressure 14-Oct-23 18-Oct-23 5 216
GR-CON-Z04-1115 Installation of Valves and Accessories 19-Oct-23 23-Oct-23 4 216
GR-CON-Z04-1117 Back filling (sand / Subbase ) 24-Oct-23 30-Oct-23 6 216
GR-CON-Z04-1118 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 31-Oct-23 06-Nov-23 6 283
GR-CON-Z04-1119 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Jul-24
system 09-Jul-24 6 93
Parking P-28 07-Sep-23 25-May-24 212 128
Site Preparation 07-Sep-23 13-Sep-23 6 321
GR-CON-Z04-1123 Backfilling 07-Sep-23 13-Sep-23 6 321
GR-CON-Z04-1121 Excavation And Disposal 09-Sep-23 13-Sep-23 5 217
GR-CON-Z04-1120 Demolition (Asphalt.Paving,etc.....) 10-Sep-23 13-Sep-23 4 19
GR-CON-Z04-1122 Prepretion And Compaction 10-Sep-23 13-Sep-23 4 321
Curbstone and Paving 14-Sep-23 07-Nov-23 46 288
GR-CON-Z04-1124 Excavation Curbstone 14-Sep-23 19-Sep-23 5 280
GR-CON-Z04-1125 Plain Concrete 20-Sep-23 27-Sep-23 6 288
GR-CON-Z04-1126 Installation Curbstone 28-Sep-23 08-Oct-23 9 288
GR-CON-Z04-1127 Casting Concrete (Mortar haunch) 09-Oct-23 12-Oct-23 4 288
GR-CON-Z04-1128 Backfilling (sand / Sub base) 14-Oct-23 23-Oct-23 9 288
GR-CON-Z04-1129 Installation of Paving 24-Oct-23 07-Nov-23 13 288
Landscape Works 20-Sep-23 13-May-24 191 128
GR-CON-Z04-1130 Excavation (Tree Pit ) 20-Sep-23 26-Sep-23 5 280
GR-CON-Z04-1131 Aggregate Drainage layer 27-Sep-23 03-Oct-23 6 280
GR-CON-Z04-1132 Installation Geotextile 04-Oct-23 08-Oct-23 4 280
GR-CON-Z04-1133 Backfilling (Soil max for tree) 09-Oct-23 15-Oct-23 6 280
GR-CON-Z04-1134 Installation of Trees 22-Apr-24 25-Apr-24 3 128
GR-CON-Z04-7016 Installation of Shrubs 25-Apr-24 29-Apr-24 3 128
GR-CON-Z04-7026 Installation of Ground Covers 29-Apr-24 02-May-24 3 128
GR-CON-Z04-7036 Installation of Succulents 02-May-24 06-May-24 3 128
GR-CON-Z04-7046 Installation of Grass 06-May-24 09-May-24 3 128
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1135 Backfilling (Mulch) 09-May-24 13-May-24 3 128


Site Furnishing 13-May-24 25-May-24 10 128
GR-CON-Z04-1146 Tree Grate 13-May-24 19-May-24 5 128
GR-CON-Z04-1147 Wheel stoppers 19-May-24 25-May-24 5 128
Irrigation Works 14-Sep-23 25-May-24 206 128
GR-CON-Z04-1138 Excavation Pipe Irrigation 14-Sep-23 19-Sep-23 5 217
GR-CON-Z04-1139 Sand Bedding 20-Sep-23 24-Sep-23 3 217
GR-CON-Z04-1140 HDPE Pipe Installations and fittings and conduit for cable 25-Sep-23 11-Oct-23 15 217
GR-CON-Z04-1142 Test pressure 12-Oct-23 17-Oct-23 5 217
GR-CON-Z04-1141 Installation of Valves and Accessories 18-Oct-23 22-Oct-23 4 217
GR-CON-Z04-1143 Back filling (sand / Subbase ) 23-Oct-23 29-Oct-23 6 217
GR-CON-Z04-1144 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Oct-23 05-Nov-23 6 282
GR-CON-Z04-1145 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
15-May-24
system 25-May-24 8 128
Parking P-29 12-Sep-23 25-May-24 208 128
Site Preparation 12-Sep-23 18-Sep-23 6 317
GR-CON-Z04-1151 Backfilling 12-Sep-23 18-Sep-23 6 317
GR-CON-Z04-1149 Excavation And Disposal 13-Sep-23 18-Sep-23 5 213
GR-CON-Z04-1148 Demolition (Asphalt.Paving,etc.....) 14-Sep-23 18-Sep-23 4 19
GR-CON-Z04-1150 Prepretion And Compaction 14-Sep-23 18-Sep-23 4 317
Curbstone and Paving 19-Sep-23 12-Nov-23 46 284
GR-CON-Z04-1152 Excavation Curbstone 19-Sep-23 25-Sep-23 5 276
GR-CON-Z04-1153 Plain Concrete 26-Sep-23 02-Oct-23 6 284
GR-CON-Z04-1154 Installation Curbstone 03-Oct-23 12-Oct-23 9 284
GR-CON-Z04-1155 Casting Concrete (Mortar haunch) 14-Oct-23 17-Oct-23 4 284
GR-CON-Z04-1156 Backfilling (sand / Sub base) 18-Oct-23 28-Oct-23 9 284
GR-CON-Z04-1157 Installation of Paving 29-Oct-23 12-Nov-23 13 284
Landscape Works 26-Sep-23 13-May-24 187 128
GR-CON-Z04-1158 Excavation (Tree Pit ) 26-Sep-23 01-Oct-23 5 276
GR-CON-Z04-1159 Aggregate Drainage layer 02-Oct-23 08-Oct-23 6 276
GR-CON-Z04-1160 Installation Geotextile 09-Oct-23 12-Oct-23 4 276
GR-CON-Z04-1161 Backfilling (Soil max for tree) 14-Oct-23 19-Oct-23 6 276
GR-CON-Z04-1162 Installation of Trees 22-Apr-24 25-Apr-24 3 128
GR-CON-Z04-7056 Installation of Shrubs 25-Apr-24 29-Apr-24 3 128
GR-CON-Z04-7066 Installation of Ground Covers 29-Apr-24 02-May-24 3 128
GR-CON-Z04-7076 Installation of Succulents 02-May-24 06-May-24 3 128
GR-CON-Z04-7086 Installation of Grass 06-May-24 09-May-24 3 128
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1163 Backfilling (Mulch) 09-May-24 13-May-24 3 128


Site Furnishing 13-May-24 25-May-24 10 128
GR-CON-Z04-1174 Tree Grate 13-May-24 19-May-24 5 128
GR-CON-Z04-1175 Wheel stoppers 19-May-24 25-May-24 5 128
Irrigation Works 19-Sep-23 25-May-24 202 128
GR-CON-Z04-1166 Excavation Pipe Irrigation 19-Sep-23 25-Sep-23 5 213
GR-CON-Z04-1167 Sand Bedding 26-Sep-23 28-Sep-23 3 213
GR-CON-Z04-1168 HDPE Pipe Installations and fittings and conduit for cable 30-Sep-23 16-Oct-23 15 213
GR-CON-Z04-1170 Test pressure 17-Oct-23 22-Oct-23 5 213
GR-CON-Z04-1169 Installation of Valves and Accessories 23-Oct-23 26-Oct-23 4 213
GR-CON-Z04-1171 Back filling (sand / Subbase ) 28-Oct-23 02-Nov-23 6 213
GR-CON-Z04-1172 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Nov-23 09-Nov-23 6 278
GR-CON-Z04-1173 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
15-May-24
system 25-May-24 8 128
Parking P-30 17-Sep-23 25-May-24 204 128
Site Preparation 17-Sep-23 24-Sep-23 6 313
GR-CON-Z04-1179 Backfilling 17-Sep-23 24-Sep-23 6 313
GR-CON-Z04-1177 Excavation And Disposal 18-Sep-23 24-Sep-23 5 209
GR-CON-Z04-1176 Demolition (Asphalt.Paving,etc.....) 19-Sep-23 24-Sep-23 4 19
GR-CON-Z04-1178 Prepretion And Compaction 19-Sep-23 24-Sep-23 4 313
Curbstone and Paving 25-Sep-23 16-Nov-23 46 280
GR-CON-Z04-1180 Excavation Curbstone 25-Sep-23 30-Sep-23 5 272
GR-CON-Z04-1181 Plain Concrete 01-Oct-23 07-Oct-23 6 280
GR-CON-Z04-1182 Installation Curbstone 08-Oct-23 17-Oct-23 9 280
GR-CON-Z04-1183 Casting Concrete (Mortar haunch) 18-Oct-23 22-Oct-23 4 280
GR-CON-Z04-1184 Backfilling (sand / Sub base) 23-Oct-23 01-Nov-23 9 280
GR-CON-Z04-1185 Installation of Paving 02-Nov-23 16-Nov-23 13 280
Landscape Works 01-Oct-23 13-May-24 183 128
GR-CON-Z04-1186 Excavation (Tree Pit ) 01-Oct-23 05-Oct-23 5 272
GR-CON-Z04-1187 Aggregate Drainage layer 07-Oct-23 12-Oct-23 6 272
GR-CON-Z04-1188 Installation Geotextile 14-Oct-23 17-Oct-23 4 272
GR-CON-Z04-1189 Backfilling (Soil max for tree) 18-Oct-23 24-Oct-23 6 272
GR-CON-Z04-1190 Installation of Trees 22-Apr-24 25-Apr-24 3 128
GR-CON-Z04-7096 Installation of Shrubs 25-Apr-24 29-Apr-24 3 128
GR-CON-Z04-7106 Installation of Ground Covers 29-Apr-24 02-May-24 3 128
GR-CON-Z04-7116 Installation of Succulents 02-May-24 06-May-24 3 128
GR-CON-Z04-7126 Installation of Grass 06-May-24 09-May-24 3 128
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1191 Backfilling (Mulch) 09-May-24 13-May-24 3 128


Site Furnishing 13-May-24 25-May-24 10 128
GR-CON-Z04-1202 Tree Grate 13-May-24 19-May-24 5 128
GR-CON-Z04-1203 Wheel stoppers 19-May-24 25-May-24 5 128
Irrigation Works 25-Sep-23 25-May-24 198 128
GR-CON-Z04-1194 Excavation Pipe Irrigation 25-Sep-23 30-Sep-23 5 209
GR-CON-Z04-1195 Sand Bedding 01-Oct-23 03-Oct-23 3 209
GR-CON-Z04-1196 HDPE Pipe Installations and fittings and conduit for cable 04-Oct-23 21-Oct-23 15 209
GR-CON-Z04-1198 Test pressure 22-Oct-23 26-Oct-23 5 209
GR-CON-Z04-1197 Installation of Valves and Accessories 28-Oct-23 31-Oct-23 4 209
GR-CON-Z04-1199 Back filling (sand / Subbase ) 01-Nov-23 07-Nov-23 6 209
GR-CON-Z04-1200 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-Nov-23 14-Nov-23 6 274
GR-CON-Z04-1201 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
15-May-24
system 25-May-24 8 128
Street SS-102 25-Sep-23 30-Jun-24 225 101
Site Preparation 25-Sep-23 18-Oct-23 21 305
GR-CON-Z04-1204 Demolition (Asphalt.Paving,etc.....) 25-Sep-23 28-Sep-23 4 19
GR-CON-Z04-1205 Excavation And Disposal 30-Sep-23 04-Oct-23 5 199
GR-CON-Z04-1206 Prepretion And Compaction 05-Oct-23 11-Oct-23 6 305
GR-CON-Z04-1207 Backfilling 12-Oct-23 18-Oct-23 6 305
Curbstone and Paving 05-Oct-23 27-Nov-23 46 271
GR-CON-Z04-1208 Excavation Curbstone 05-Oct-23 10-Oct-23 5 236
GR-CON-Z04-1209 Plain Concrete 11-Oct-23 17-Oct-23 6 271
GR-CON-Z04-1210 Installation Curbstone 18-Oct-23 28-Oct-23 9 271
GR-CON-Z04-1211 Casting Concrete (Mortar haunch) 29-Oct-23 01-Nov-23 4 271
GR-CON-Z04-1212 Backfilling (sand / Sub base) 02-Nov-23 12-Nov-23 9 271
GR-CON-Z04-1213 Installation of Paving 13-Nov-23 27-Nov-23 13 271
Landscape Works 11-Oct-23 02-Jun-24 191 101
GR-CON-Z04-1214 Excavation (Tree Pit ) 11-Oct-23 16-Oct-23 5 236
GR-CON-Z04-1215 Aggregate Drainage layer 17-Oct-23 23-Oct-23 6 236
GR-CON-Z04-1216 Installation Geotextile 24-Oct-23 28-Oct-23 4 236
GR-CON-Z04-1217 Backfilling (Soil max for tree) 29-Oct-23 04-Nov-23 6 236
GR-CON-Z04-1218 Installation of Trees 22-Apr-24 25-Apr-24 3 101
GR-CON-Z04-9656 Installation of Shrubs 25-Apr-24 29-Apr-24 3 101
GR-CON-Z04-9666 Installation of Succulents 29-Apr-24 02-May-24 3 101
GR-CON-Z04-9676 Installation of Ground Covers 02-May-24 06-May-24 3 101
GR-CON-Z04-9686 Installation of Grass 06-May-24 09-May-24 3 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1219 Backfilling (Mulch) 09-May-24 13-May-24 3 101


GR-CON-Z04-1220 Natural Boulders Installation 13-May-24 18-May-24 4 101
GR-CON-Z04-1221 Retaining walls . Steps, forming risers, treads and edges with finishes
18-May-24 02-Jun-24 13 101
Site Furnishing 02-Jun-24 30-Jun-24 20 101
GR-CON-Z04-1230 Garden planter box 02-Jun-24 08-Jun-24 5 101
GR-CON-Z04-1231 Wheel stoppers 08-Jun-24 13-Jun-24 5 101
GR-CON-Z04-1232 Steel Lattice 13-Jun-24 24-Jun-24 5 101
GR-CON-Z04-1233 Handrail 24-Jun-24 30-Jun-24 5 101
Storm Piping Works 18-Jun-24 30-Jun-24 6 101
GR-CON-Z04-1234 Installation of DI grating covers 18-Jun-24 30-Jun-24 6 101
Irrigation Works 05-Oct-23 05-Dec-23 53 258
GR-CON-Z04-1222 Excavation Pipe Irrigation 05-Oct-23 10-Oct-23 5 199
GR-CON-Z04-1223 Sand Bedding 11-Oct-23 15-Oct-23 4 199
GR-CON-Z04-1224 HDPE Pipe Installations and fittings and conduit for cable 16-Oct-23 01-Nov-23 15 199
GR-CON-Z04-1226 Test pressure 02-Nov-23 07-Nov-23 5 199
GR-CON-Z04-1225 Installation of Valves and Accessories 08-Nov-23 12-Nov-23 4 199
GR-CON-Z04-1227 Back filling (sand / Subbase ) 13-Nov-23 19-Nov-23 6 199
GR-CON-Z04-1228 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Nov-23 26-Nov-23 6 258
GR-CON-Z04-1229 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
27-Nov-23
system 05-Dec-23 8 258
Electrical Works 11-Oct-23 30-Jun-24 211 101
GR-CON-Z04-1235 Excavation And Disposal 11-Oct-23 16-Oct-23 5 285
GR-CON-Z04-1236 Sand Bedding 17-Oct-23 21-Oct-23 4 285
GR-CON-Z04-1237 laying cables 22-Oct-23 25-Oct-23 4 285
GR-CON-Z04-1238 Backfilling (sand / Sub base) 26-Oct-23 31-Oct-23 5 285
GR-CON-Z04-1239 Control Panel / Distribution Panel Installation 01-Nov-23 05-Nov-23 4 285
GR-CON-Z04-1240 Road Crossing Ducts 24-Jun-24 30-Jun-24 5 101
Street SS-104 30-Sep-23 30-Jun-24 221 101
Site Preparation 30-Sep-23 23-Oct-23 21 301
GR-CON-Z04-1241 Demolition (Asphalt.Paving,etc.....) 30-Sep-23 03-Oct-23 4 19
GR-CON-Z04-1242 Excavation And Disposal 04-Oct-23 09-Oct-23 5 195
GR-CON-Z04-1243 Prepretion And Compaction 10-Oct-23 16-Oct-23 6 301
GR-CON-Z04-1244 Backfilling 17-Oct-23 23-Oct-23 6 301
Curbstone and Paving 10-Oct-23 02-Dec-23 46 267
GR-CON-Z04-1245 Excavation Curbstone 10-Oct-23 15-Oct-23 5 232
GR-CON-Z04-1246 Plain Concrete 16-Oct-23 22-Oct-23 6 267
GR-CON-Z04-1247 Installation Curbstone 23-Oct-23 01-Nov-23 9 267
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1248 Casting Concrete (Mortar haunch) 02-Nov-23 06-Nov-23 4 267


GR-CON-Z04-1249 Backfilling (sand / Sub base) 07-Nov-23 16-Nov-23 9 267
GR-CON-Z04-1250 Installation of Paving 18-Nov-23 02-Dec-23 13 267
Landscape Works 16-Oct-23 02-Jun-24 187 101
GR-CON-Z04-1251 Excavation (Tree Pit ) 16-Oct-23 21-Oct-23 5 232
GR-CON-Z04-1252 Aggregate Drainage layer 22-Oct-23 28-Oct-23 6 232
GR-CON-Z04-1253 Installation Geotextile 29-Oct-23 01-Nov-23 4 232
GR-CON-Z04-1254 Backfilling (Soil max for tree) 02-Nov-23 08-Nov-23 6 232
GR-CON-Z04-1255 Installation of Trees 22-Apr-24 25-Apr-24 3 101
GR-CON-Z04-9696 Installation of Shrubs 25-Apr-24 29-Apr-24 3 101
GR-CON-Z04-9706 Installation of Succulents 29-Apr-24 02-May-24 3 101
GR-CON-Z04-9716 Installation of Ground Covers 02-May-24 06-May-24 3 101
GR-CON-Z04-9726 Installation of Grass 06-May-24 09-May-24 3 101
GR-CON-Z04-1256 Backfilling (Mulch) 09-May-24 13-May-24 3 101
GR-CON-Z04-1257 Natural Boulders Installation 13-May-24 18-May-24 4 101
GR-CON-Z04-1258 Retaining walls . Steps, forming risers, treads and edges with finishes
18-May-24 02-Jun-24 13 101
Site Furnishing 02-Jun-24 30-Jun-24 20 101
GR-CON-Z04-1267 Garden planter box 02-Jun-24 08-Jun-24 5 101
GR-CON-Z04-1268 Wheel stoppers 08-Jun-24 13-Jun-24 5 101
GR-CON-Z04-1269 Steel Lattice 13-Jun-24 24-Jun-24 5 101
GR-CON-Z04-1270 Handrail 24-Jun-24 30-Jun-24 5 101
Storm Piping Works 18-Jun-24 30-Jun-24 6 101
GR-CON-Z04-1271 Installation of DI grating covers 18-Jun-24 30-Jun-24 6 101
Irrigation Works 10-Oct-23 10-Dec-23 53 254
GR-CON-Z04-1259 Excavation Pipe Irrigation 10-Oct-23 15-Oct-23 5 195
GR-CON-Z04-1260 Sand Bedding 16-Oct-23 19-Oct-23 4 195
GR-CON-Z04-1261 HDPE Pipe Installations and fittings and conduit for cable 21-Oct-23 06-Nov-23 15 195
GR-CON-Z04-1263 Test pressure 07-Nov-23 12-Nov-23 5 195
GR-CON-Z04-1262 Installation of Valves and Accessories 13-Nov-23 16-Nov-23 4 195
GR-CON-Z04-1264 Back filling (sand / Subbase ) 18-Nov-23 23-Nov-23 6 195
GR-CON-Z04-1265 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-Nov-23 30-Nov-23 6 254
GR-CON-Z04-1266 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Dec-23
system 10-Dec-23 8 254
Electrical Works 16-Oct-23 30-Jun-24 207 101
GR-CON-Z04-1272 Excavation And Disposal 16-Oct-23 21-Oct-23 5 281
GR-CON-Z04-1273 Sand Bedding 22-Oct-23 25-Oct-23 4 281
GR-CON-Z04-1274 laying cables 26-Oct-23 30-Oct-23 4 281
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1275 Backfilling (sand / Sub base) 31-Oct-23 05-Nov-23 5 281


GR-CON-Z04-1276 Control Panel / Distribution Panel Installation 06-Nov-23 09-Nov-23 4 281
GR-CON-Z04-1277 Road Crossing Ducts 24-Jun-24 30-Jun-24 5 101
Street SS-12 04-Oct-23 28-Jul-24 241 77
Site Preparation 04-Oct-23 09-Nov-23 32 286
GR-CON-Z04-1278 Demolition (Asphalt.Paving,etc.....) 04-Oct-23 10-Oct-23 6 19
GR-CON-Z04-1279 Excavation And Disposal 11-Oct-23 19-Oct-23 8 165
GR-CON-Z04-1280 Prepretion And Compaction 21-Oct-23 30-Oct-23 9 286
GR-CON-Z04-1281 Backfilling 31-Oct-23 09-Nov-23 9 286
Curbstone and Paving 21-Oct-23 10-Jan-24 71 233
GR-CON-Z04-1282 Excavation Curbstone 21-Oct-23 29-Oct-23 8 185
GR-CON-Z04-1283 Plain Concrete 30-Oct-23 08-Nov-23 9 233
GR-CON-Z04-1284 Installation Curbstone 09-Nov-23 25-Nov-23 14 233
GR-CON-Z04-1285 Casting Concrete (Mortar haunch) 26-Nov-23 02-Dec-23 6 233
GR-CON-Z04-1286 Backfilling (sand / Sub base) 03-Dec-23 18-Dec-23 14 233
GR-CON-Z04-1287 Installation of Paving 19-Dec-23 10-Jan-24 20 233
Landscape Works 30-Oct-23 16-Jun-24 187 77
GR-CON-Z04-1288 Excavation (Tree Pit ) 30-Oct-23 07-Nov-23 8 185
GR-CON-Z04-1289 Aggregate Drainage layer 08-Nov-23 18-Nov-23 9 185
GR-CON-Z04-1290 Installation Geotextile 19-Nov-23 25-Nov-23 6 185
GR-CON-Z04-1291 Backfilling (Soil max for tree) 26-Nov-23 05-Dec-23 9 185
GR-CON-Z04-1292 Installation of Trees 22-Apr-24 27-Apr-24 4 77
GR-CON-Z04-9736 Installation of Shrubs 27-Apr-24 30-Apr-24 3 77
GR-CON-Z04-9746 Installation of Succulents 30-Apr-24 04-May-24 3 77
GR-CON-Z04-9756 Installation of Ground Covers 04-May-24 07-May-24 3 77
GR-CON-Z04-9766 Installation of Grass 07-May-24 11-May-24 3 77
GR-CON-Z04-1293 Backfilling (Mulch) 11-May-24 16-May-24 5 77
GR-CON-Z04-1294 Natural Boulders Installation 16-May-24 23-May-24 6 77
GR-CON-Z04-1295 Retaining walls . Steps, forming risers, treads and edges with finishes
23-May-24 16-Jun-24 20 77
Site Furnishing 16-Jun-24 28-Jul-24 32 77
GR-CON-Z04-1304 Garden planter box 16-Jun-24 30-Jun-24 8 77
GR-CON-Z04-1305 Wheel stoppers 30-Jun-24 09-Jul-24 8 77
GR-CON-Z04-1306 Steel Lattice 09-Jul-24 18-Jul-24 8 77
GR-CON-Z04-1307 Handrail 18-Jul-24 28-Jul-24 8 77
Storm Piping Works 17-Jul-24 28-Jul-24 9 77
GR-CON-Z04-1308 Installation of DI grating covers 17-Jul-24 28-Jul-24 9 77
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 21-Oct-23 22-Jan-24 81 214


GR-CON-Z04-1296 Excavation Pipe Irrigation 21-Oct-23 29-Oct-23 8 165
GR-CON-Z04-1297 Sand Bedding 30-Oct-23 05-Nov-23 6 165
GR-CON-Z04-1298 HDPE Pipe Installations and fittings and conduit for cable 06-Nov-23 02-Dec-23 23 165
GR-CON-Z04-1300 Test pressure 03-Dec-23 11-Dec-23 8 165
GR-CON-Z04-1299 Installation of Valves and Accessories 12-Dec-23 18-Dec-23 6 165
GR-CON-Z04-1301 Back filling (sand / Subbase ) 19-Dec-23 28-Dec-23 9 165
GR-CON-Z04-1302 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Dec-23 08-Jan-24 9 214
GR-CON-Z04-1303 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
09-Jan-24
system 22-Jan-24 12 214
Electrical Works 30-Oct-23 28-Jul-24 219 77
GR-CON-Z04-1309 Excavation And Disposal 30-Oct-23 07-Nov-23 8 254
GR-CON-Z04-1310 Sand Bedding 08-Nov-23 14-Nov-23 6 254
GR-CON-Z04-1311 laying cables 15-Nov-23 21-Nov-23 6 254
GR-CON-Z04-1312 Backfilling (sand / Sub base) 22-Nov-23 30-Nov-23 8 254
GR-CON-Z04-1313 Control Panel / Distribution Panel Installation 02-Dec-23 07-Dec-23 6 254
GR-CON-Z04-1314 Road Crossing Ducts 18-Jul-24 28-Jul-24 8 77
Street SS-44 11-Oct-23 30-Jun-24 211 101
Site Preparation 11-Oct-23 04-Nov-23 21 291
GR-CON-Z04-1315 Demolition (Asphalt.Paving,etc.....) 11-Oct-23 15-Oct-23 4 19
GR-CON-Z04-1316 Excavation And Disposal 16-Oct-23 21-Oct-23 5 185
GR-CON-Z04-1317 Prepretion And Compaction 22-Oct-23 28-Oct-23 6 291
GR-CON-Z04-1318 Backfilling 29-Oct-23 04-Nov-23 6 291
Curbstone and Paving 22-Oct-23 13-Dec-23 46 257
GR-CON-Z04-1319 Excavation Curbstone 22-Oct-23 26-Oct-23 5 222
GR-CON-Z04-1320 Plain Concrete 28-Oct-23 02-Nov-23 6 257
GR-CON-Z04-1321 Installation Curbstone 04-Nov-23 13-Nov-23 9 257
GR-CON-Z04-1322 Casting Concrete (Mortar haunch) 14-Nov-23 18-Nov-23 4 257
GR-CON-Z04-1323 Backfilling (sand / Sub base) 19-Nov-23 28-Nov-23 9 257
GR-CON-Z04-1324 Installation of Paving 29-Nov-23 13-Dec-23 13 257
Landscape Works 28-Oct-23 02-Jun-24 177 101
GR-CON-Z04-1325 Excavation (Tree Pit ) 28-Oct-23 01-Nov-23 5 222
GR-CON-Z04-1326 Aggregate Drainage layer 02-Nov-23 08-Nov-23 6 222
GR-CON-Z04-1327 Installation Geotextile 09-Nov-23 13-Nov-23 4 222
GR-CON-Z04-1328 Backfilling (Soil max for tree) 14-Nov-23 20-Nov-23 6 222
GR-CON-Z04-1329 Installation of Trees 22-Apr-24 25-Apr-24 3 101
GR-CON-Z04-9776 Installation of Shrubs 25-Apr-24 29-Apr-24 3 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-9786 Installation of Succulents 29-Apr-24 02-May-24 3 101


GR-CON-Z04-9796 Installation of Ground Covers 02-May-24 06-May-24 3 101
GR-CON-Z04-9806 Installation of Grass 06-May-24 09-May-24 3 101
GR-CON-Z04-1330 Backfilling (Mulch) 09-May-24 13-May-24 3 101
GR-CON-Z04-1331 Natural Boulders Installation 13-May-24 18-May-24 4 101
GR-CON-Z04-1332 Retaining walls . Steps, forming risers, treads and edges with finishes
18-May-24 02-Jun-24 13 101
Site Furnishing 02-Jun-24 30-Jun-24 20 101
GR-CON-Z04-1341 Garden planter box 02-Jun-24 08-Jun-24 5 101
GR-CON-Z04-1342 Wheel stoppers 08-Jun-24 13-Jun-24 5 101
GR-CON-Z04-1343 Steel Lattice 13-Jun-24 24-Jun-24 5 101
GR-CON-Z04-1344 Handrail 24-Jun-24 30-Jun-24 5 101
Storm Piping Works 18-Jun-24 30-Jun-24 6 101
GR-CON-Z04-1345 Installation of DI grating covers 18-Jun-24 30-Jun-24 6 101
Irrigation Works 22-Oct-23 21-Dec-23 53 244
GR-CON-Z04-1333 Excavation Pipe Irrigation 22-Oct-23 26-Oct-23 5 185
GR-CON-Z04-1334 Sand Bedding 28-Oct-23 31-Oct-23 4 185
GR-CON-Z04-1335 HDPE Pipe Installations and fittings and conduit for cable 01-Nov-23 18-Nov-23 15 185
GR-CON-Z04-1337 Test pressure 19-Nov-23 23-Nov-23 5 185
GR-CON-Z04-1336 Installation of Valves and Accessories 25-Nov-23 28-Nov-23 4 185
GR-CON-Z04-1338 Back filling (sand / Subbase ) 29-Nov-23 05-Dec-23 6 185
GR-CON-Z04-1339 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Dec-23 12-Dec-23 6 244
GR-CON-Z04-1340 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Dec-23
system 21-Dec-23 8 244
Electrical Works 28-Oct-23 30-Jun-24 197 101
GR-CON-Z04-1346 Excavation And Disposal 28-Oct-23 01-Nov-23 5 271
GR-CON-Z04-1347 Sand Bedding 02-Nov-23 06-Nov-23 4 271
GR-CON-Z04-1348 laying cables 07-Nov-23 11-Nov-23 4 271
GR-CON-Z04-1349 Backfilling (sand / Sub base) 12-Nov-23 16-Nov-23 5 271
GR-CON-Z04-1350 Control Panel / Distribution Panel Installation 18-Nov-23 21-Nov-23 4 271
GR-CON-Z04-1351 Road Crossing Ducts 24-Jun-24 30-Jun-24 5 101
Street SS-46 16-Oct-23 30-Jun-24 207 101
Site Preparation 16-Oct-23 08-Nov-23 21 287
GR-CON-Z04-1352 Demolition (Asphalt.Paving,etc.....) 16-Oct-23 19-Oct-23 4 19
GR-CON-Z04-1353 Excavation And Disposal 21-Oct-23 25-Oct-23 5 181
GR-CON-Z04-1354 Prepretion And Compaction 26-Oct-23 01-Nov-23 6 287
GR-CON-Z04-1355 Backfilling 02-Nov-23 08-Nov-23 6 287
Curbstone and Paving 26-Oct-23 18-Dec-23 46 253
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1356 Excavation Curbstone 26-Oct-23 31-Oct-23 5 218


GR-CON-Z04-1357 Plain Concrete 01-Nov-23 07-Nov-23 6 253
GR-CON-Z04-1358 Installation Curbstone 08-Nov-23 18-Nov-23 9 253
GR-CON-Z04-1359 Casting Concrete (Mortar haunch) 19-Nov-23 22-Nov-23 4 253
GR-CON-Z04-1360 Backfilling (sand / Sub base) 23-Nov-23 03-Dec-23 9 253
GR-CON-Z04-1361 Installation of Paving 04-Dec-23 18-Dec-23 13 253
Landscape Works 01-Nov-23 02-Jun-24 173 101
GR-CON-Z04-1362 Excavation (Tree Pit ) 01-Nov-23 06-Nov-23 5 218
GR-CON-Z04-1363 Aggregate Drainage layer 07-Nov-23 13-Nov-23 6 218
GR-CON-Z04-1364 Installation Geotextile 14-Nov-23 18-Nov-23 4 218
GR-CON-Z04-1365 Backfilling (Soil max for tree) 19-Nov-23 25-Nov-23 6 218
GR-CON-Z04-1366 Installation of Trees 22-Apr-24 25-Apr-24 3 101
GR-CON-Z04-9816 Installation of Shrubs 25-Apr-24 29-Apr-24 3 101
GR-CON-Z04-9826 Installation of Succulents 29-Apr-24 02-May-24 3 101
GR-CON-Z04-9836 Installation of Ground Covers 02-May-24 06-May-24 3 101
GR-CON-Z04-9846 Installation of Grass 06-May-24 09-May-24 3 101
GR-CON-Z04-1367 Backfilling (Mulch) 09-May-24 13-May-24 3 101
GR-CON-Z04-1368 Natural Boulders Installation 13-May-24 18-May-24 4 101
GR-CON-Z04-1369 Retaining walls . Steps, forming risers, treads and edges with finishes
18-May-24 02-Jun-24 13 101
Site Furnishing 02-Jun-24 30-Jun-24 20 101
GR-CON-Z04-1378 Garden planter box 02-Jun-24 08-Jun-24 5 101
GR-CON-Z04-1379 Wheel stoppers 08-Jun-24 13-Jun-24 5 101
GR-CON-Z04-1380 Steel Lattice 13-Jun-24 24-Jun-24 5 101
GR-CON-Z04-1381 Handrail 24-Jun-24 30-Jun-24 5 101
Storm Piping Works 18-Jun-24 30-Jun-24 6 101
GR-CON-Z04-1382 Installation of DI grating covers 18-Jun-24 30-Jun-24 6 101
Irrigation Works 26-Oct-23 26-Dec-23 53 240
GR-CON-Z04-1370 Excavation Pipe Irrigation 26-Oct-23 31-Oct-23 5 181
GR-CON-Z04-1371 Sand Bedding 01-Nov-23 05-Nov-23 4 181
GR-CON-Z04-1372 HDPE Pipe Installations and fittings and conduit for cable 06-Nov-23 22-Nov-23 15 181
GR-CON-Z04-1374 Test pressure 23-Nov-23 28-Nov-23 5 181
GR-CON-Z04-1373 Installation of Valves and Accessories 29-Nov-23 03-Dec-23 4 181
GR-CON-Z04-1375 Back filling (sand / Subbase ) 04-Dec-23 10-Dec-23 6 181
GR-CON-Z04-1376 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Dec-23 17-Dec-23 6 240
GR-CON-Z04-1377 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Dec-23
system 26-Dec-23 8 240
Electrical Works 01-Nov-23 30-Jun-24 193 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1383 Excavation And Disposal 01-Nov-23 06-Nov-23 5 267


GR-CON-Z04-1384 Sand Bedding 07-Nov-23 11-Nov-23 4 267
GR-CON-Z04-1385 laying cables 12-Nov-23 15-Nov-23 4 267
GR-CON-Z04-1386 Backfilling (sand / Sub base) 16-Nov-23 21-Nov-23 5 267
GR-CON-Z04-1387 Control Panel / Distribution Panel Installation 22-Nov-23 26-Nov-23 4 267
GR-CON-Z04-1388 Road Crossing Ducts 24-Jun-24 30-Jun-24 5 101
Street SS-49 21-Oct-23 30-Jun-24 203 101
Site Preparation 21-Oct-23 13-Nov-23 21 283
GR-CON-Z04-1389 Demolition (Asphalt.Paving,etc.....) 21-Oct-23 24-Oct-23 4 19
GR-CON-Z04-1390 Excavation And Disposal 25-Oct-23 30-Oct-23 5 177
GR-CON-Z04-1391 Prepretion And Compaction 31-Oct-23 06-Nov-23 6 283
GR-CON-Z04-1392 Backfilling 07-Nov-23 13-Nov-23 6 283
Curbstone and Paving 31-Oct-23 23-Dec-23 46 249
GR-CON-Z04-1393 Excavation Curbstone 31-Oct-23 05-Nov-23 5 214
GR-CON-Z04-1394 Plain Concrete 06-Nov-23 12-Nov-23 6 249
GR-CON-Z04-1395 Installation Curbstone 13-Nov-23 22-Nov-23 9 249
GR-CON-Z04-1396 Casting Concrete (Mortar haunch) 23-Nov-23 27-Nov-23 4 249
GR-CON-Z04-1397 Backfilling (sand / Sub base) 28-Nov-23 07-Dec-23 9 249
GR-CON-Z04-1398 Installation of Paving 09-Dec-23 23-Dec-23 13 249
Landscape Works 06-Nov-23 02-Jun-24 169 101
GR-CON-Z04-1399 Excavation (Tree Pit ) 06-Nov-23 11-Nov-23 5 214
GR-CON-Z04-1400 Aggregate Drainage layer 12-Nov-23 18-Nov-23 6 214
GR-CON-Z04-1401 Installation Geotextile 19-Nov-23 22-Nov-23 4 214
GR-CON-Z04-1402 Backfilling (Soil max for tree) 23-Nov-23 29-Nov-23 6 214
GR-CON-Z04-1403 Installation of Trees 22-Apr-24 25-Apr-24 3 101
GR-CON-Z04-9856 Installation of Shrubs 25-Apr-24 29-Apr-24 3 101
GR-CON-Z04-9866 Installation of Succulents 29-Apr-24 02-May-24 3 101
GR-CON-Z04-9876 Installation of Ground Covers 02-May-24 06-May-24 3 101
GR-CON-Z04-9886 Installation of Grass 06-May-24 09-May-24 3 101
GR-CON-Z04-1404 Backfilling (Mulch) 09-May-24 13-May-24 3 101
GR-CON-Z04-1405 Natural Boulders Installation 13-May-24 18-May-24 4 101
GR-CON-Z04-1406 Retaining walls . Steps, forming risers, treads and edges with finishes
18-May-24 02-Jun-24 13 101
Site Furnishing 02-Jun-24 30-Jun-24 20 101
GR-CON-Z04-1415 Garden planter box 02-Jun-24 08-Jun-24 5 101
GR-CON-Z04-1416 Wheel stoppers 08-Jun-24 13-Jun-24 5 101
GR-CON-Z04-1417 Steel Lattice 13-Jun-24 24-Jun-24 5 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1418 Handrail 24-Jun-24 30-Jun-24 5 101


Storm Piping Works 18-Jun-24 30-Jun-24 6 101
GR-CON-Z04-1419 Installation of DI grating covers 18-Jun-24 30-Jun-24 6 101
Irrigation Works 31-Oct-23 31-Dec-23 53 236
GR-CON-Z04-1407 Excavation Pipe Irrigation 31-Oct-23 05-Nov-23 5 177
GR-CON-Z04-1408 Sand Bedding 06-Nov-23 09-Nov-23 4 177
GR-CON-Z04-1409 HDPE Pipe Installations and fittings and conduit for cable 11-Nov-23 27-Nov-23 15 177
GR-CON-Z04-1411 Test pressure 28-Nov-23 03-Dec-23 5 177
GR-CON-Z04-1410 Installation of Valves and Accessories 04-Dec-23 07-Dec-23 4 177
GR-CON-Z04-1412 Back filling (sand / Subbase ) 09-Dec-23 14-Dec-23 6 177
GR-CON-Z04-1413 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Dec-23 21-Dec-23 6 236
GR-CON-Z04-1414 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-Dec-23
system 31-Dec-23 8 236
Electrical Works 06-Nov-23 30-Jun-24 189 101
GR-CON-Z04-1420 Excavation And Disposal 06-Nov-23 11-Nov-23 5 263
GR-CON-Z04-1421 Sand Bedding 12-Nov-23 15-Nov-23 4 263
GR-CON-Z04-1422 laying cables 16-Nov-23 20-Nov-23 4 263
GR-CON-Z04-1423 Backfilling (sand / Sub base) 21-Nov-23 26-Nov-23 5 263
GR-CON-Z04-1424 Control Panel / Distribution Panel Installation 27-Nov-23 30-Nov-23 4 263
GR-CON-Z04-1425 Road Crossing Ducts 24-Jun-24 30-Jun-24 5 101
Street SS-05.1 25-Oct-23 28-Jul-24 223 77
Site Preparation 25-Oct-23 30-Nov-23 32 268
GR-CON-Z04-1426 Demolition (Asphalt.Paving,etc.....) 25-Oct-23 31-Oct-23 6 19
GR-CON-Z04-1427 Excavation And Disposal 01-Nov-23 09-Nov-23 8 77
GR-CON-Z04-1428 Prepretion And Compaction 11-Nov-23 20-Nov-23 9 268
GR-CON-Z04-1429 Backfilling 21-Nov-23 30-Nov-23 9 268
Curbstone and Paving 11-Nov-23 31-Jan-24 71 215
GR-CON-Z04-1430 Excavation Curbstone 11-Nov-23 19-Nov-23 8 167
GR-CON-Z04-1431 Plain Concrete 20-Nov-23 29-Nov-23 9 215
GR-CON-Z04-1432 Installation Curbstone 30-Nov-23 16-Dec-23 14 215
GR-CON-Z04-1433 Casting Concrete (Mortar haunch) 17-Dec-23 23-Dec-23 6 215
GR-CON-Z04-1434 Backfilling (sand / Sub base) 24-Dec-23 08-Jan-24 14 215
GR-CON-Z04-1435 Installation of Paving 09-Jan-24 31-Jan-24 20 215
Landscape Works 20-Nov-23 16-Jun-24 169 77
GR-CON-Z04-1436 Excavation (Tree Pit ) 20-Nov-23 28-Nov-23 8 167
GR-CON-Z04-1437 Aggregate Drainage layer 29-Nov-23 09-Dec-23 9 167
GR-CON-Z04-1438 Installation Geotextile 10-Dec-23 16-Dec-23 6 167
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1439 Backfilling (Soil max for tree) 17-Dec-23 26-Dec-23 9 167


GR-CON-Z04-1440 Installation of Trees 22-Apr-24 27-Apr-24 4 77
GR-CON-Z04-9896 Installation of Shrubs 27-Apr-24 30-Apr-24 3 77
GR-CON-Z04-9906 Installation of Succulents 30-Apr-24 04-May-24 3 77
GR-CON-Z04-9916 Installation of Ground Covers 04-May-24 07-May-24 3 77
GR-CON-Z04-9926 Installation of Grass 07-May-24 11-May-24 3 77
GR-CON-Z04-1441 Backfilling (Mulch) 11-May-24 16-May-24 5 77
GR-CON-Z04-1442 Natural Boulders Installation 16-May-24 23-May-24 6 77
GR-CON-Z04-1443 Retaining walls . Steps, forming risers, treads and edges with finishes
23-May-24 16-Jun-24 20 77
Site Furnishing 16-Jun-24 28-Jul-24 32 77
GR-CON-Z04-1452 Garden planter box 16-Jun-24 30-Jun-24 8 77
GR-CON-Z04-1453 Wheel stoppers 30-Jun-24 09-Jul-24 8 77
GR-CON-Z04-1454 Steel Lattice 09-Jul-24 18-Jul-24 8 77
GR-CON-Z04-1455 Handrail 18-Jul-24 28-Jul-24 8 77
Storm Piping Works 17-Jul-24 28-Jul-24 9 77
GR-CON-Z04-1456 Installation of DI grating covers 17-Jul-24 28-Jul-24 9 77
Irrigation Works 11-Nov-23 12-Feb-24 81 196
GR-CON-Z04-1444 Excavation Pipe Irrigation 11-Nov-23 19-Nov-23 8 77
GR-CON-Z04-1445 Sand Bedding 20-Nov-23 26-Nov-23 6 77
GR-CON-Z04-1446 HDPE Pipe Installations and fittings and conduit for cable 27-Nov-23 23-Dec-23 23 77
GR-CON-Z04-1448 Test pressure 24-Dec-23 01-Jan-24 8 77
GR-CON-Z04-1447 Installation of Valves and Accessories 02-Jan-24 08-Jan-24 6 77
GR-CON-Z04-1449 Back filling (sand / Subbase ) 09-Jan-24 18-Jan-24 9 77
GR-CON-Z04-1450 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Jan-24 29-Jan-24 9 196
GR-CON-Z04-1451 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
30-Jan-24
system 12-Feb-24 12 196
Electrical Works 20-Nov-23 28-Jul-24 201 77
GR-CON-Z04-1457 Excavation And Disposal 20-Nov-23 28-Nov-23 8 236
GR-CON-Z04-1458 Sand Bedding 29-Nov-23 05-Dec-23 6 236
GR-CON-Z04-1459 laying cables 06-Dec-23 12-Dec-23 6 236
GR-CON-Z04-1460 Backfilling (sand / Sub base) 13-Dec-23 21-Dec-23 8 236
GR-CON-Z04-1461 Control Panel / Distribution Panel Installation 23-Dec-23 28-Dec-23 6 236
GR-CON-Z04-1462 Road Crossing Ducts 18-Jul-24 28-Jul-24 8 77
Street SS-90 01-Nov-23 30-Jun-24 193 101
Site Preparation 01-Nov-23 25-Nov-23 21 273
GR-CON-Z04-1463 Demolition (Asphalt.Paving,etc.....) 01-Nov-23 05-Nov-23 4 19
GR-CON-Z04-1464 Excavation And Disposal 06-Nov-23 11-Nov-23 5 167
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1465 Prepretion And Compaction 12-Nov-23 18-Nov-23 6 273


GR-CON-Z04-1466 Backfilling 19-Nov-23 25-Nov-23 6 273
Curbstone and Paving 12-Nov-23 03-Jan-24 46 239
GR-CON-Z04-1467 Excavation Curbstone 12-Nov-23 16-Nov-23 5 204
GR-CON-Z04-1468 Plain Concrete 18-Nov-23 23-Nov-23 6 239
GR-CON-Z04-1469 Installation Curbstone 25-Nov-23 04-Dec-23 9 239
GR-CON-Z04-1470 Casting Concrete (Mortar haunch) 05-Dec-23 09-Dec-23 4 239
GR-CON-Z04-1471 Backfilling (sand / Sub base) 10-Dec-23 19-Dec-23 9 239
GR-CON-Z04-1472 Installation of Paving 20-Dec-23 03-Jan-24 13 239
Landscape Works 18-Nov-23 02-Jun-24 159 101
GR-CON-Z04-1473 Excavation (Tree Pit ) 18-Nov-23 22-Nov-23 5 204
GR-CON-Z04-1474 Aggregate Drainage layer 23-Nov-23 29-Nov-23 6 204
GR-CON-Z04-1475 Installation Geotextile 30-Nov-23 04-Dec-23 4 204
GR-CON-Z04-1476 Backfilling (Soil max for tree) 05-Dec-23 11-Dec-23 6 204
GR-CON-Z04-1477 Installation of Trees 22-Apr-24 25-Apr-24 3 101
GR-CON-Z04-9936 Installation of Shrubs 25-Apr-24 29-Apr-24 3 101
GR-CON-Z04-9946 Installation of Succulents 29-Apr-24 02-May-24 3 101
GR-CON-Z04-9956 Installation of Ground Covers 02-May-24 06-May-24 3 101
GR-CON-Z04-9966 Installation of Grass 06-May-24 09-May-24 3 101
GR-CON-Z04-1478 Backfilling (Mulch) 09-May-24 13-May-24 3 101
GR-CON-Z04-1479 Natural Boulders Installation 13-May-24 18-May-24 4 101
GR-CON-Z04-1480 Retaining walls . Steps, forming risers, treads and edges with finishes
18-May-24 02-Jun-24 13 101
Site Furnishing 02-Jun-24 30-Jun-24 20 101
GR-CON-Z04-1489 Garden planter box 02-Jun-24 08-Jun-24 5 101
GR-CON-Z04-1490 Wheel stoppers 08-Jun-24 13-Jun-24 5 101
GR-CON-Z04-1491 Steel Lattice 13-Jun-24 24-Jun-24 5 101
GR-CON-Z04-1492 Handrail 24-Jun-24 30-Jun-24 5 101
Storm Piping Works 18-Jun-24 30-Jun-24 6 101
GR-CON-Z04-1493 Installation of DI grating covers 18-Jun-24 30-Jun-24 6 101
Irrigation Works 12-Nov-23 11-Jan-24 53 226
GR-CON-Z04-1481 Excavation Pipe Irrigation 12-Nov-23 16-Nov-23 5 167
GR-CON-Z04-1482 Sand Bedding 18-Nov-23 21-Nov-23 4 167
GR-CON-Z04-1483 HDPE Pipe Installations and fittings and conduit for cable 22-Nov-23 09-Dec-23 15 167
GR-CON-Z04-1485 Test pressure 10-Dec-23 14-Dec-23 5 167
GR-CON-Z04-1484 Installation of Valves and Accessories 16-Dec-23 19-Dec-23 4 167
GR-CON-Z04-1486 Back filling (sand / Subbase ) 20-Dec-23 26-Dec-23 6 167
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1487 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-Dec-23 02-Jan-24 6 226
GR-CON-Z04-1488 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jan-24
system 11-Jan-24 8 226
Electrical Works 18-Nov-23 30-Jun-24 179 101
GR-CON-Z04-1494 Excavation And Disposal 18-Nov-23 22-Nov-23 5 253
GR-CON-Z04-1495 Sand Bedding 23-Nov-23 27-Nov-23 4 253
GR-CON-Z04-1496 laying cables 28-Nov-23 02-Dec-23 4 253
GR-CON-Z04-1497 Backfilling (sand / Sub base) 03-Dec-23 07-Dec-23 5 253
GR-CON-Z04-1498 Control Panel / Distribution Panel Installation 09-Dec-23 12-Dec-23 4 253
GR-CON-Z04-1499 Road Crossing Ducts 24-Jun-24 30-Jun-24 5 101
Toilet - 03 06-Nov-23 05-Oct-24 271 19
Site Preparation 06-Nov-23 16-Nov-23 10 19
GR-CON-Z04-1500 Excavation And Disposal 06-Nov-23 11-Nov-23 5 19
GR-CON-Z04-1501 Backfilling (one layer) 12-Nov-23 16-Nov-23 5 19
Civil Works 18-Nov-23 11-May-24 140 19
GR-CON-Z04-1502 Polyethylene Under Footings, Grade Slab and Beams 18-Nov-23 20-Nov-23 3 19
GR-CON-Z04-1503 Blinding concrete 21-Nov-23 26-Nov-23 5 19
GR-CON-Z04-1504 Footings 27-Nov-23 05-Dec-23 8 19
GR-CON-Z04-1505 Waterproofing Under Footing 06-Dec-23 11-Dec-23 5 19
GR-CON-Z04-1506 Column Necks 12-Dec-23 18-Dec-23 6 19
GR-CON-Z04-1507 Waterproofing (Toilet) 25-Dec-23 03-Jan-24 9 19
GR-CON-Z04-1508 Backfilling 04-Jan-24 10-Jan-24 6 19
GR-CON-Z04-1509 Ground beams 11-Jan-24 25-Jan-24 13 19
GR-CON-Z04-1510 Slab on grade 27-Jan-24 15-Feb-24 18 19
GR-CON-Z04-1511 Columns 17-Feb-24 02-Mar-24 13 19
GR-CON-Z04-1512 Concrete, slabs Ground floor 03-Mar-24 31-Mar-24 21 19
GR-CON-Z04-1513 Roof Thermal And Moisture Protection Work 30-Apr-24 11-May-24 9 19
Architectural Works 11-May-24 05-Oct-24 121 19
GR-CON-Z04-1514 Blockwork 11-May-24 02-Jun-24 19 19
GR-CON-Z04-1515 Waterproofing 11-Jun-24 26-Jun-24 9 19
GR-CON-Z04-1516 Back Filling (sand) 26-Jun-24 02-Jul-24 5 19
GR-CON-Z04-1517 Floor finish 02-Jul-24 17-Jul-24 13 19
GR-CON-Z04-1518 Wall Finish 17-Jul-24 15-Aug-24 25 19
GR-CON-Z04-1519 Door Installation 15-Aug-24 20-Aug-24 4 19
GR-CON-Z04-1521 Celling finish 20-Aug-24 26-Aug-24 5 19
GR-CON-Z04-1522 ToiletAccessories 26-Aug-24 31-Aug-24 4 19
GR-CON-Z04-1523 Facade Finishing Works 31-Aug-24 11-Sep-24 10 19
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z04-1524 Metal Work 31-Aug-24 11-Sep-24 10 19


GR-CON-Z04-1525 Wood Work 11-Sep-24 05-Oct-24 19 19
Mechanical Works 02-Jun-24 05-Oct-24 102 19
GR-CON-Z04-1526 Pipework Installations and fittings 02-Jun-24 11-Jun-24 8 19
GR-CON-Z04-1527 Installation of refrigerant supply/return pipework 02-Jun-24 06-Jun-24 4 79
GR-CON-Z04-1529 Water Meter With Meter Cabinet 02-Jun-24 05-Jun-24 3 108
GR-CON-Z04-1528 Installation of Sanitary Fixtures 17-Jul-24 27-Jul-24 8 40
GR-CON-Z04-1530 Installation of Exhaust Equipmets and Air outlets 22-Sep-24 05-Oct-24 10 19
Electrical Works 02-Jun-24 05-Oct-24 102 19
GR-CON-Z04-1531 Conduits Installation 02-Jun-24 08-Jun-24 5 49
GR-CON-Z04-1533 Earthing and lightning protection system 10-Jun-24 15-Jun-24 4 84
GR-CON-Z04-1532 Install of power cables 15-Aug-24 19-Aug-24 3 20
GR-CON-Z04-1534 Installation of wiring devices and lighting fixtures 15-Aug-24 21-Aug-24 5 36
GR-CON-Z04-1535 Installation of Alarm with park BMS system 21-Aug-24 27-Aug-24 5 36
GR-CON-Z04-1536 Installation of Fire Detection System 27-Aug-24 05-Sep-24 8 36
GR-CON-Z04-1537 Installation of Panel Board 05-Sep-24 10-Sep-24 4 36
GR-CON-Z04-1538 Connecting to nearest feeder pillar 01-Oct-24 05-Oct-24 3 19
Zone 07 14-Aug-23 20-Oct-24 355 17
Future Neighborhood Park FNP-01a 15-Aug-23 27-Apr-24 209 163
Site Preparation 15-Aug-23 06-Sep-23 20 1
GR-CON-Z07-1039 Demolition (Asphalt.Paving,etc.....) 15-Aug-23 19-Aug-23 4 1
GR-CON-Z07-1040 Excavation And Disposal 20-Aug-23 26-Aug-23 6 1
GR-CON-Z07-1041 Prepretion And Compaction 27-Aug-23 30-Aug-23 4 1
GR-CON-Z07-1042 Backfilling 31-Aug-23 06-Sep-23 6 1
Curbstone and Paving 27-Aug-23 19-Oct-23 46 316
GR-CON-Z07-1043 Excavation Curbstone 27-Aug-23 31-Aug-23 5 275
GR-CON-Z07-1044 Plain Concrete 02-Sep-23 07-Sep-23 6 316
GR-CON-Z07-1045 Installation Curbstone 09-Sep-23 18-Sep-23 9 316
GR-CON-Z07-1046 Casting Concrete (Mortar haunch) 19-Sep-23 24-Sep-23 4 316
GR-CON-Z07-1047 Backfilling (sand / Sub base) 25-Sep-23 04-Oct-23 9 316
GR-CON-Z07-1048 Installation of Paving 05-Oct-23 19-Oct-23 13 316
Landscape Works 02-Sep-23 27-Apr-24 194 163
GR-CON-Z07-1049 Excavation (Tree Pit ) 02-Sep-23 06-Sep-23 5 275
GR-CON-Z07-1050 Aggregate Drainage layer 07-Sep-23 13-Sep-23 6 302
GR-CON-Z07-1051 Installation Geotextile 14-Sep-23 18-Sep-23 4 302
GR-CON-Z07-1052 Backfilling (Soil max for tree) 19-Sep-23 26-Sep-23 6 302
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1053 Installation of Trees 06-Mar-24 09-Mar-24 2 163


GR-CON-Z07-1866 Installation of Shrubs 09-Mar-24 11-Mar-24 2 163
GR-CON-Z07-1876 Installation of Succulents 11-Mar-24 13-Mar-24 2 163
GR-CON-Z07-1886 Installation of Ground Covers 13-Mar-24 17-Mar-24 2 163
GR-CON-Z07-1896 Installation of Climbers 17-Mar-24 19-Mar-24 2 163
GR-CON-Z07-1906 Installation of Grass 20-Mar-24 23-Mar-24 2 163
GR-CON-Z07-1916 Installation of Lawns 23-Mar-24 26-Mar-24 2 163
GR-CON-Z07-1054 Backfilling (Mulch) 26-Mar-24 31-Mar-24 3 163
GR-CON-Z07-1055 Natural Boulders Installation 31-Mar-24 06-Apr-24 4 163
GR-CON-Z07-1056 Retaining walls . Steps, forming risers, treads and edges with finishes
06-Apr-24 27-Apr-24 13 163
MUGA 07-Sep-23 27-Apr-24 189 163
GR-CON-Z07-1057 Excavation And Disposal 07-Sep-23 12-Sep-23 5 275
GR-CON-Z07-1058 Prepretion And Compaction 13-Sep-23 19-Sep-23 6 275
GR-CON-Z07-1059 polyethylene under footings ( fence and gates) 20-Sep-23 26-Sep-23 5 275
GR-CON-Z07-1060 Blinding concrete (flooring) 27-Sep-23 02-Oct-23 5 275
GR-CON-Z07-1061 Concrete Footings ( fence and gates) 03-Oct-23 17-Oct-23 13 275
GR-CON-Z07-1062 Tools Play Installation ( basketball / football ..) 02-Jan-24 20-Jan-24 15 209
GR-CON-Z07-1063 PaintAcrylic Play Surface 20-Jan-24 04-Feb-24 13 209
GR-CON-Z07-1064 Fence (high / low) / gates Installation 03-Apr-24 27-Apr-24 15 163
Irrigation Works 27-Aug-23 27-Apr-24 199 163
GR-CON-Z07-1065 Excavation Pipe Irrigation 27-Aug-23 31-Aug-23 5 245
GR-CON-Z07-1066 Sand Bedding 02-Sep-23 04-Sep-23 3 245
GR-CON-Z07-1067 HDPE Pipe Installations and fittings and conduit for cable 14-Sep-23 03-Oct-23 15 236
GR-CON-Z07-1069 Test pressure 03-Oct-23 09-Oct-23 5 236
GR-CON-Z07-1068 Installation of Valves and Accessories 09-Oct-23 14-Oct-23 4 236
GR-CON-Z07-1070 Back filling (sand / Subbase ) 14-Oct-23 21-Oct-23 6 236
GR-CON-Z07-1071 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Oct-23 28-Oct-23 6 301
GR-CON-Z07-1072 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Apr-24
system 27-Apr-24 8 163
Mosque M-01a 20-Aug-23 30-May-24 234 134
Site Preparation 20-Aug-23 10-Sep-23 19 327
GR-CON-Z07-1073 Demolition (Asphalt.Paving,etc.....) 20-Aug-23 23-Aug-23 4 191
GR-CON-Z07-1074 Excavation And Disposal 24-Aug-23 29-Aug-23 5 242
GR-CON-Z07-1075 Prepretion And Compaction 30-Aug-23 03-Sep-23 4 327
GR-CON-Z07-1076 Backfilling 04-Sep-23 10-Sep-23 6 327
Curbstone and Paving 11-Sep-23 07-Oct-23 22 327
GR-CON-Z07-1081 Backfilling (sand / Sub base) 11-Sep-23 20-Sep-23 9 327
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1082 Installation of Paving 21-Sep-23 07-Oct-23 13 327


Landscape Works 30-Aug-23 30-May-24 225 134
GR-CON-Z07-1083 Excavation (Tree Pit ) 30-Aug-23 04-Sep-23 5 275
GR-CON-Z07-1084 Aggregate Drainage layer 05-Sep-23 11-Sep-23 6 275
GR-CON-Z07-1085 Installation Geotextile 12-Sep-23 17-Sep-23 5 275
GR-CON-Z07-1086 Backfilling (Soil max for tree) 18-Sep-23 24-Sep-23 5 275
GR-CON-Z07-1087 Installation of Trees 06-Mar-24 11-Mar-24 4 134
GR-CON-Z07-3666 Installation of Climbers 11-Mar-24 17-Mar-24 4 134
GR-CON-Z07-3676 Installation of Shrubs 17-Mar-24 23-Mar-24 4 134
GR-CON-Z07-3686 Installation of Succulents 23-Mar-24 28-Mar-24 4 134
GR-CON-Z07-3696 Installation of Ground Covers 30-Mar-24 04-Apr-24 4 134
GR-CON-Z07-1088 Backfilling (Mulch) 04-Apr-24 28-Apr-24 15 134
GR-CON-Z07-1089 Natural Boulders Installation 29-Apr-24 13-May-24 13 134
GR-CON-Z07-1090 Retaining walls . Steps, forming risers, treads and edges with finishes
14-May-24 30-May-24 15 134
Irrigation Works 30-Aug-23 30-May-24 225 134
GR-CON-Z07-1091 Excavation Pipe Irrigation 30-Aug-23 04-Sep-23 5 242
GR-CON-Z07-1092 Sand Bedding 05-Sep-23 07-Sep-23 3 242
GR-CON-Z07-1093 HDPE Pipe Installations and fittings and conduit for cable 14-Sep-23 03-Oct-23 15 236
GR-CON-Z07-1095 Test pressure 03-Oct-23 09-Oct-23 5 236
GR-CON-Z07-1094 Installation of Valves and Accessories 09-Oct-23 14-Oct-23 4 236
GR-CON-Z07-1096 Back filling (sand / Subbase ) 14-Oct-23 21-Oct-23 6 236
GR-CON-Z07-1097 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Oct-23 28-Oct-23 6 303
GR-CON-Z07-1098 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-May-24
system 30-May-24 6 134
Mosque M-02a 24-Aug-23 30-May-24 230 134
Site Preparation 24-Aug-23 14-Sep-23 19 323
GR-CON-Z07-1099 Demolition (Asphalt.Paving,etc.....) 24-Aug-23 28-Aug-23 4 191
GR-CON-Z07-1100 Excavation And Disposal 29-Aug-23 03-Sep-23 5 238
GR-CON-Z07-1101 Prepretion And Compaction 04-Sep-23 07-Sep-23 4 323
GR-CON-Z07-1102 Backfilling 09-Sep-23 14-Sep-23 6 323
Curbstone and Paving 16-Sep-23 11-Oct-23 22 323
GR-CON-Z07-1107 Backfilling (sand / Sub base) 16-Sep-23 26-Sep-23 9 323
GR-CON-Z07-1108 Installation of Paving 27-Sep-23 11-Oct-23 13 323
Landscape Works 04-Sep-23 30-May-24 221 134
GR-CON-Z07-1109 Excavation (Tree Pit ) 04-Sep-23 09-Sep-23 5 271
GR-CON-Z07-1110 Aggregate Drainage layer 10-Sep-23 16-Sep-23 6 271
GR-CON-Z07-1111 Installation Geotextile 17-Sep-23 21-Sep-23 5 271
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1112 Backfilling (Soil max for tree) 24-Sep-23 28-Sep-23 5 271


GR-CON-Z07-1113 Installation of Trees 06-Mar-24 11-Mar-24 4 134
GR-CON-Z07-3706 Installation of Climbers 11-Mar-24 17-Mar-24 4 134
GR-CON-Z07-3716 Installation of Shrubs 17-Mar-24 23-Mar-24 4 134
GR-CON-Z07-3726 Installation of Succulents 23-Mar-24 28-Mar-24 4 134
GR-CON-Z07-3736 Installation of Ground Covers 30-Mar-24 04-Apr-24 4 134
GR-CON-Z07-1114 Backfilling (Mulch) 04-Apr-24 28-Apr-24 15 134
GR-CON-Z07-1115 Natural Boulders Installation 29-Apr-24 13-May-24 13 134
GR-CON-Z07-1116 Retaining walls . Steps, forming risers, treads and edges with finishes
14-May-24 30-May-24 15 134
Irrigation Works 04-Sep-23 30-May-24 221 134
GR-CON-Z07-1117 Excavation Pipe Irrigation 04-Sep-23 09-Sep-23 5 238
GR-CON-Z07-1118 Sand Bedding 10-Sep-23 12-Sep-23 3 238
GR-CON-Z07-1119 HDPE Pipe Installations and fittings and conduit for cable 14-Sep-23 03-Oct-23 15 236
GR-CON-Z07-1121 Test pressure 03-Oct-23 09-Oct-23 5 236
GR-CON-Z07-1120 Installation of Valves and Accessories 09-Oct-23 14-Oct-23 4 236
GR-CON-Z07-1122 Back filling (sand / Subbase ) 14-Oct-23 21-Oct-23 6 236
GR-CON-Z07-1123 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Oct-23 28-Oct-23 6 303
GR-CON-Z07-1124 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-May-24
system 30-May-24 6 134
Mosque M-03 29-Aug-23 30-May-24 226 134
Site Preparation 29-Aug-23 19-Sep-23 19 319
GR-CON-Z07-1125 Demolition (Asphalt.Paving,etc.....) 29-Aug-23 02-Sep-23 4 191
GR-CON-Z07-1126 Excavation And Disposal 03-Sep-23 07-Sep-23 5 234
GR-CON-Z07-1127 Prepretion And Compaction 09-Sep-23 12-Sep-23 4 319
GR-CON-Z07-1128 Backfilling 13-Sep-23 19-Sep-23 6 319
Curbstone and Paving 20-Sep-23 16-Oct-23 22 319
GR-CON-Z07-1133 Backfilling (sand / Sub base) 20-Sep-23 01-Oct-23 9 319
GR-CON-Z07-1134 Installation of Paving 02-Oct-23 16-Oct-23 13 319
Landscape Works 09-Sep-23 30-May-24 217 134
GR-CON-Z07-1135 Excavation (Tree Pit ) 09-Sep-23 13-Sep-23 5 267
GR-CON-Z07-1136 Aggregate Drainage layer 14-Sep-23 20-Sep-23 6 267
GR-CON-Z07-1137 Installation Geotextile 21-Sep-23 27-Sep-23 5 267
GR-CON-Z07-1138 Backfilling (Soil max for tree) 28-Sep-23 03-Oct-23 5 267
GR-CON-Z07-1139 Installation of Trees 06-Mar-24 11-Mar-24 4 134
GR-CON-Z07-3746 Installation of Climbers 11-Mar-24 17-Mar-24 4 134
GR-CON-Z07-3756 Installation of Shrubs 17-Mar-24 23-Mar-24 4 134
GR-CON-Z07-3766 Installation of Succulents 23-Mar-24 28-Mar-24 4 134
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-3776 Installation of Ground Covers 30-Mar-24 04-Apr-24 4 134


GR-CON-Z07-1140 Backfilling (Mulch) 04-Apr-24 28-Apr-24 15 134
GR-CON-Z07-1141 Natural Boulders Installation 29-Apr-24 13-May-24 13 134
GR-CON-Z07-1142 Retaining walls . Steps, forming risers, treads and edges with finishes
14-May-24 30-May-24 15 134
Irrigation Works 09-Sep-23 30-May-24 217 134
GR-CON-Z07-1143 Excavation Pipe Irrigation 09-Sep-23 13-Sep-23 5 234
GR-CON-Z07-1144 Sand Bedding 14-Sep-23 17-Sep-23 3 234
GR-CON-Z07-1145 HDPE Pipe Installations and fittings and conduit for cable 18-Sep-23 05-Oct-23 15 234
GR-CON-Z07-1147 Test pressure 07-Oct-23 11-Oct-23 5 234
GR-CON-Z07-1146 Installation of Valves and Accessories 12-Oct-23 16-Oct-23 4 234
GR-CON-Z07-1148 Back filling (sand / Subbase ) 17-Oct-23 23-Oct-23 6 234
GR-CON-Z07-1149 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Oct-23 30-Oct-23 6 301
GR-CON-Z07-1150 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-May-24
system 30-May-24 6 134
Parking P-15 03-Sep-23 20-Apr-24 187 169
Site Preparation 03-Sep-23 25-Sep-23 19 324
GR-CON-Z07-1151 Demolition (Asphalt.Paving,etc.....) 03-Sep-23 06-Sep-23 4 191
GR-CON-Z07-1152 Excavation And Disposal 07-Sep-23 12-Sep-23 5 230
GR-CON-Z07-1153 Prepretion And Compaction 13-Sep-23 17-Sep-23 4 324
GR-CON-Z07-1154 Backfilling 18-Sep-23 25-Sep-23 6 324
Curbstone and Paving 13-Sep-23 06-Nov-23 46 301
GR-CON-Z07-1155 Excavation Curbstone 13-Sep-23 18-Sep-23 5 293
GR-CON-Z07-1156 Plain Concrete 19-Sep-23 26-Sep-23 6 301
GR-CON-Z07-1157 Installation Curbstone 27-Sep-23 07-Oct-23 9 301
GR-CON-Z07-1158 Casting Concrete (Mortar haunch) 08-Oct-23 11-Oct-23 4 301
GR-CON-Z07-1159 Backfilling (sand / Sub base) 12-Oct-23 22-Oct-23 9 301
GR-CON-Z07-1160 Installation of Paving 23-Oct-23 06-Nov-23 13 301
Landscape Works 19-Sep-23 01-Apr-24 163 169
GR-CON-Z07-1161 Excavation (Tree Pit ) 19-Sep-23 25-Sep-23 5 293
GR-CON-Z07-1162 Aggregate Drainage layer 26-Sep-23 02-Oct-23 6 293
GR-CON-Z07-1163 Installation Geotextile 03-Oct-23 07-Oct-23 4 293
GR-CON-Z07-1164 Backfilling (Soil max for tree) 08-Oct-23 14-Oct-23 6 293
GR-CON-Z07-1165 Installation of Trees 06-Mar-24 10-Mar-24 3 169
GR-CON-Z07-7216 Installation of Shrubs 10-Mar-24 13-Mar-24 3 169
GR-CON-Z07-7226 Installation of Ground Covers 13-Mar-24 18-Mar-24 3 169
GR-CON-Z07-7236 Installation of Succulents 18-Mar-24 23-Mar-24 3 169
GR-CON-Z07-7246 Installation of Grass 23-Mar-24 27-Mar-24 3 169
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1166 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 169


Site Furnishing 01-Apr-24 20-Apr-24 10 169
GR-CON-Z07-1177 Tree Grate 01-Apr-24 09-Apr-24 5 169
GR-CON-Z07-1178 Wheel stoppers 09-Apr-24 20-Apr-24 5 169
Irrigation Works 13-Sep-23 20-Apr-24 178 169
GR-CON-Z07-1169 Excavation Pipe Irrigation 13-Sep-23 18-Sep-23 5 230
GR-CON-Z07-1170 Sand Bedding 19-Sep-23 21-Sep-23 3 230
GR-CON-Z07-1171 HDPE Pipe Installations and fittings and conduit for cable 24-Sep-23 10-Oct-23 15 230
GR-CON-Z07-1173 Test pressure 11-Oct-23 16-Oct-23 5 230
GR-CON-Z07-1172 Installation of Valves and Accessories 17-Oct-23 21-Oct-23 4 230
GR-CON-Z07-1174 Back filling (sand / Subbase ) 22-Oct-23 28-Oct-23 6 230
GR-CON-Z07-1175 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Oct-23 04-Nov-23 6 295
GR-CON-Z07-1176 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
04-Apr-24
system 20-Apr-24 8 169
Street SS-01 07-Sep-23 21-May-24 210 142
Site Preparation 07-Sep-23 02-Oct-23 21 331
GR-CON-Z07-1207 Demolition (Asphalt.Paving,etc.....) 07-Sep-23 11-Sep-23 4 191
GR-CON-Z07-1208 Excavation And Disposal 12-Sep-23 17-Sep-23 5 225
GR-CON-Z07-1209 Prepretion And Compaction 18-Sep-23 25-Sep-23 6 331
GR-CON-Z07-1210 Backfilling 26-Sep-23 02-Oct-23 6 331
Curbstone and Paving 18-Sep-23 11-Nov-23 46 297
GR-CON-Z07-1211 Excavation Curbstone 18-Sep-23 24-Sep-23 5 262
GR-CON-Z07-1212 Plain Concrete 25-Sep-23 01-Oct-23 6 297
GR-CON-Z07-1213 Installation Curbstone 02-Oct-23 11-Oct-23 9 297
GR-CON-Z07-1214 Casting Concrete (Mortar haunch) 12-Oct-23 16-Oct-23 4 297
GR-CON-Z07-1215 Backfilling (sand / Sub base) 17-Oct-23 26-Oct-23 9 297
GR-CON-Z07-1216 Installation of Paving 28-Oct-23 11-Nov-23 13 297
Landscape Works 25-Sep-23 28-Apr-24 176 142
GR-CON-Z07-1217 Excavation (Tree Pit ) 25-Sep-23 30-Sep-23 5 262
GR-CON-Z07-1218 Aggregate Drainage layer 01-Oct-23 07-Oct-23 6 262
GR-CON-Z07-1219 Installation Geotextile 08-Oct-23 11-Oct-23 4 262
GR-CON-Z07-1220 Backfilling (Soil max for tree) 12-Oct-23 18-Oct-23 6 262
GR-CON-Z07-1221 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10336 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10346 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10356 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10366 Installation of Grass 23-Mar-24 27-Mar-24 3 142
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1222 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142


GR-CON-Z07-1223 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1224 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1233 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1234 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1235 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1236 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1237 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 18-Sep-23 19-Nov-23 53 284
GR-CON-Z07-1225 Excavation Pipe Irrigation 18-Sep-23 24-Sep-23 5 225
GR-CON-Z07-1226 Sand Bedding 25-Sep-23 28-Sep-23 4 225
GR-CON-Z07-1227 HDPE Pipe Installations and fittings and conduit for cable 30-Sep-23 16-Oct-23 15 225
GR-CON-Z07-1229 Test pressure 17-Oct-23 22-Oct-23 5 225
GR-CON-Z07-1228 Installation of Valves and Accessories 23-Oct-23 26-Oct-23 4 225
GR-CON-Z07-1230 Back filling (sand / Subbase ) 28-Oct-23 02-Nov-23 6 225
GR-CON-Z07-1231 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Nov-23 09-Nov-23 6 284
GR-CON-Z07-1232 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
11-Nov-23
system 19-Nov-23 8 284
Electrical Works 25-Sep-23 21-May-24 196 142
GR-CON-Z07-1238 Excavation And Disposal 25-Sep-23 30-Sep-23 5 311
GR-CON-Z07-1239 Sand Bedding 01-Oct-23 04-Oct-23 4 311
GR-CON-Z07-1240 laying cables 05-Oct-23 09-Oct-23 4 311
GR-CON-Z07-1241 Backfilling (sand / Sub base) 10-Oct-23 15-Oct-23 5 311
GR-CON-Z07-1242 Control Panel / Distribution Panel Installation 16-Oct-23 19-Oct-23 4 311
GR-CON-Z07-1243 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-39 12-Sep-23 21-May-24 206 142
Site Preparation 12-Sep-23 07-Oct-23 21 327
GR-CON-Z07-1244 Demolition (Asphalt.Paving,etc.....) 12-Sep-23 16-Sep-23 4 191
GR-CON-Z07-1245 Excavation And Disposal 17-Sep-23 21-Sep-23 5 221
GR-CON-Z07-1246 Prepretion And Compaction 24-Sep-23 30-Sep-23 6 327
GR-CON-Z07-1247 Backfilling 01-Oct-23 07-Oct-23 6 327
Curbstone and Paving 24-Sep-23 15-Nov-23 46 293
GR-CON-Z07-1248 Excavation Curbstone 24-Sep-23 28-Sep-23 5 258
GR-CON-Z07-1249 Plain Concrete 30-Sep-23 05-Oct-23 6 293
GR-CON-Z07-1250 Installation Curbstone 07-Oct-23 16-Oct-23 9 293
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1251 Casting Concrete (Mortar haunch) 17-Oct-23 21-Oct-23 4 293


GR-CON-Z07-1252 Backfilling (sand / Sub base) 22-Oct-23 31-Oct-23 9 293
GR-CON-Z07-1253 Installation of Paving 01-Nov-23 15-Nov-23 13 293
Landscape Works 30-Sep-23 28-Apr-24 172 142
GR-CON-Z07-1254 Excavation (Tree Pit ) 30-Sep-23 04-Oct-23 5 258
GR-CON-Z07-1255 Aggregate Drainage layer 05-Oct-23 11-Oct-23 6 258
GR-CON-Z07-1256 Installation Geotextile 12-Oct-23 16-Oct-23 4 258
GR-CON-Z07-1257 Backfilling (Soil max for tree) 17-Oct-23 23-Oct-23 6 258
GR-CON-Z07-1258 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10376 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10386 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10396 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10406 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1259 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1260 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1261 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1270 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1271 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1272 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1273 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1274 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 24-Sep-23 23-Nov-23 53 280
GR-CON-Z07-1262 Excavation Pipe Irrigation 24-Sep-23 28-Sep-23 5 221
GR-CON-Z07-1263 Sand Bedding 30-Sep-23 03-Oct-23 4 221
GR-CON-Z07-1264 HDPE Pipe Installations and fittings and conduit for cable 04-Oct-23 21-Oct-23 15 221
GR-CON-Z07-1266 Test pressure 22-Oct-23 26-Oct-23 5 221
GR-CON-Z07-1265 Installation of Valves and Accessories 28-Oct-23 31-Oct-23 4 221
GR-CON-Z07-1267 Back filling (sand / Subbase ) 01-Nov-23 07-Nov-23 6 221
GR-CON-Z07-1268 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-Nov-23 14-Nov-23 6 280
GR-CON-Z07-1269 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
15-Nov-23
system 23-Nov-23 8 280
Electrical Works 30-Sep-23 21-May-24 192 142
GR-CON-Z07-1275 Excavation And Disposal 30-Sep-23 04-Oct-23 5 307
GR-CON-Z07-1276 Sand Bedding 05-Oct-23 09-Oct-23 4 307
GR-CON-Z07-1277 laying cables 10-Oct-23 14-Oct-23 4 307
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1278 Backfilling (sand / Sub base) 15-Oct-23 19-Oct-23 5 307


GR-CON-Z07-1279 Control Panel / Distribution Panel Installation 21-Oct-23 24-Oct-23 4 307
GR-CON-Z07-1280 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-04 17-Sep-23 18-Jun-24 226 118
Site Preparation 17-Sep-23 24-Oct-23 32 312
GR-CON-Z07-1281 Demolition (Asphalt.Paving,etc.....) 17-Sep-23 24-Sep-23 6 191
GR-CON-Z07-1282 Excavation And Disposal 25-Sep-23 03-Oct-23 8 191
GR-CON-Z07-1283 Prepretion And Compaction 04-Oct-23 14-Oct-23 9 312
GR-CON-Z07-1284 Backfilling 15-Oct-23 24-Oct-23 9 312
Curbstone and Paving 04-Oct-23 25-Dec-23 71 259
GR-CON-Z07-1285 Excavation Curbstone 04-Oct-23 12-Oct-23 8 211
GR-CON-Z07-1286 Plain Concrete 14-Oct-23 23-Oct-23 9 259
GR-CON-Z07-1287 Installation Curbstone 24-Oct-23 08-Nov-23 14 259
GR-CON-Z07-1288 Casting Concrete (Mortar haunch) 09-Nov-23 15-Nov-23 6 259
GR-CON-Z07-1289 Backfilling (sand / Sub base) 16-Nov-23 02-Dec-23 14 259
GR-CON-Z07-1290 Installation of Paving 03-Dec-23 25-Dec-23 20 259
Landscape Works 14-Oct-23 12-May-24 172 118
GR-CON-Z07-1291 Excavation (Tree Pit ) 14-Oct-23 22-Oct-23 8 211
GR-CON-Z07-1292 Aggregate Drainage layer 23-Oct-23 01-Nov-23 9 211
GR-CON-Z07-1293 Installation Geotextile 02-Nov-23 08-Nov-23 6 211
GR-CON-Z07-1294 Backfilling (Soil max for tree) 09-Nov-23 19-Nov-23 9 211
GR-CON-Z07-1295 Installation of Trees 06-Mar-24 11-Mar-24 4 118
GR-CON-Z07-10416 Installation of Shrubs 11-Mar-24 14-Mar-24 3 118
GR-CON-Z07-10426 Installation of Succulents 16-Mar-24 19-Mar-24 3 118
GR-CON-Z07-10436 Installation of Ground Covers 20-Mar-24 24-Mar-24 3 118
GR-CON-Z07-10446 Installation of Grass 25-Mar-24 28-Mar-24 3 118
GR-CON-Z07-1296 Backfilling (Mulch) 30-Mar-24 06-Apr-24 5 118
GR-CON-Z07-1297 Natural Boulders Installation 06-Apr-24 18-Apr-24 6 118
GR-CON-Z07-1298 Retaining walls . Steps, forming risers, treads and edges with finishes
20-Apr-24 12-May-24 20 118
Site Furnishing 13-May-24 18-Jun-24 32 118
GR-CON-Z07-1307 Garden planter box 13-May-24 21-May-24 8 118
GR-CON-Z07-1308 Wheel stoppers 22-May-24 30-May-24 8 118
GR-CON-Z07-1309 Steel Lattice 01-Jun-24 09-Jun-24 8 118
GR-CON-Z07-1310 Handrail 10-Jun-24 18-Jun-24 8 118
Storm Piping Works 09-Jun-24 18-Jun-24 9 118
GR-CON-Z07-1311 Installation of DI grating covers 09-Jun-24 18-Jun-24 9 118
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 04-Oct-23 06-Jan-24 81 240


GR-CON-Z07-1299 Excavation Pipe Irrigation 04-Oct-23 12-Oct-23 8 191
GR-CON-Z07-1300 Sand Bedding 14-Oct-23 19-Oct-23 6 191
GR-CON-Z07-1301 HDPE Pipe Installations and fittings and conduit for cable 21-Oct-23 15-Nov-23 23 191
GR-CON-Z07-1303 Test pressure 16-Nov-23 25-Nov-23 8 191
GR-CON-Z07-1302 Installation of Valves and Accessories 26-Nov-23 02-Dec-23 6 191
GR-CON-Z07-1304 Back filling (sand / Subbase ) 03-Dec-23 12-Dec-23 9 191
GR-CON-Z07-1305 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Dec-23 23-Dec-23 9 240
GR-CON-Z07-1306 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Dec-23
system 06-Jan-24 12 240
Electrical Works 14-Oct-23 18-Jun-24 204 118
GR-CON-Z07-1312 Excavation And Disposal 14-Oct-23 22-Oct-23 8 280
GR-CON-Z07-1313 Sand Bedding 23-Oct-23 29-Oct-23 6 280
GR-CON-Z07-1314 laying cables 30-Oct-23 05-Nov-23 6 280
GR-CON-Z07-1315 Backfilling (sand / Sub base) 06-Nov-23 14-Nov-23 8 280
GR-CON-Z07-1316 Control Panel / Distribution Panel Installation 15-Nov-23 21-Nov-23 6 280
GR-CON-Z07-1317 Road Crossing Ducts 10-Jun-24 18-Jun-24 8 118
Street SS-40 25-Sep-23 21-May-24 196 142
Site Preparation 25-Sep-23 18-Oct-23 21 317
GR-CON-Z07-1318 Demolition (Asphalt.Paving,etc.....) 25-Sep-23 28-Sep-23 4 211
GR-CON-Z07-1319 Excavation And Disposal 30-Sep-23 04-Oct-23 5 211
GR-CON-Z07-1320 Prepretion And Compaction 05-Oct-23 11-Oct-23 6 317
GR-CON-Z07-1321 Backfilling 12-Oct-23 18-Oct-23 6 317
Curbstone and Paving 05-Oct-23 27-Nov-23 46 283
GR-CON-Z07-1322 Excavation Curbstone 05-Oct-23 10-Oct-23 5 248
GR-CON-Z07-1323 Plain Concrete 11-Oct-23 17-Oct-23 6 283
GR-CON-Z07-1324 Installation Curbstone 18-Oct-23 28-Oct-23 9 283
GR-CON-Z07-1325 Casting Concrete (Mortar haunch) 29-Oct-23 01-Nov-23 4 283
GR-CON-Z07-1326 Backfilling (sand / Sub base) 02-Nov-23 12-Nov-23 9 283
GR-CON-Z07-1327 Installation of Paving 13-Nov-23 27-Nov-23 13 283
Landscape Works 11-Oct-23 28-Apr-24 162 142
GR-CON-Z07-1328 Excavation (Tree Pit ) 11-Oct-23 16-Oct-23 5 248
GR-CON-Z07-1329 Aggregate Drainage layer 17-Oct-23 23-Oct-23 6 248
GR-CON-Z07-1330 Installation Geotextile 24-Oct-23 28-Oct-23 4 248
GR-CON-Z07-1331 Backfilling (Soil max for tree) 29-Oct-23 04-Nov-23 6 248
GR-CON-Z07-1332 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10456 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-10466 Installation of Succulents 13-Mar-24 18-Mar-24 3 142


GR-CON-Z07-10476 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10486 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1333 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1334 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1335 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1344 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1345 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1346 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1347 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1348 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 05-Oct-23 05-Dec-23 53 270
GR-CON-Z07-1336 Excavation Pipe Irrigation 05-Oct-23 10-Oct-23 5 211
GR-CON-Z07-1337 Sand Bedding 11-Oct-23 15-Oct-23 4 211
GR-CON-Z07-1338 HDPE Pipe Installations and fittings and conduit for cable 16-Oct-23 01-Nov-23 15 211
GR-CON-Z07-1340 Test pressure 02-Nov-23 07-Nov-23 5 211
GR-CON-Z07-1339 Installation of Valves and Accessories 08-Nov-23 12-Nov-23 4 211
GR-CON-Z07-1341 Back filling (sand / Subbase ) 13-Nov-23 19-Nov-23 6 211
GR-CON-Z07-1342 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Nov-23 26-Nov-23 6 270
GR-CON-Z07-1343 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
27-Nov-23
system 05-Dec-23 8 270
Electrical Works 11-Oct-23 21-May-24 182 142
GR-CON-Z07-1349 Excavation And Disposal 11-Oct-23 16-Oct-23 5 297
GR-CON-Z07-1350 Sand Bedding 17-Oct-23 21-Oct-23 4 297
GR-CON-Z07-1351 laying cables 22-Oct-23 25-Oct-23 4 297
GR-CON-Z07-1352 Backfilling (sand / Sub base) 26-Oct-23 31-Oct-23 5 297
GR-CON-Z07-1353 Control Panel / Distribution Panel Installation 01-Nov-23 05-Nov-23 4 297
GR-CON-Z07-1354 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-42 14-Aug-23 21-May-24 230 142
Site Preparation 14-Aug-23 07-Sep-23 21 351
GR-CON-Z07-1355 Demolition (Asphalt.Paving,etc.....) 14-Aug-23 19-Aug-23 4 245
GR-CON-Z07-1356 Excavation And Disposal 19-Aug-23 24-Aug-23 5 245
GR-CON-Z07-1357 Prepretion And Compaction 24-Aug-23 31-Aug-23 6 351
GR-CON-Z07-1358 Backfilling 31-Aug-23 07-Sep-23 6 351
Curbstone and Paving 24-Aug-23 18-Oct-23 46 317
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1359 Excavation Curbstone 24-Aug-23 30-Aug-23 5 282


GR-CON-Z07-1360 Plain Concrete 30-Aug-23 06-Sep-23 6 317
GR-CON-Z07-1361 Installation Curbstone 06-Sep-23 17-Sep-23 9 317
GR-CON-Z07-1362 Casting Concrete (Mortar haunch) 17-Sep-23 21-Sep-23 4 317
GR-CON-Z07-1363 Backfilling (sand / Sub base) 21-Sep-23 03-Oct-23 9 317
GR-CON-Z07-1364 Installation of Paving 03-Oct-23 18-Oct-23 13 317
Landscape Works 30-Aug-23 28-Apr-24 196 142
GR-CON-Z07-1365 Excavation (Tree Pit ) 30-Aug-23 05-Sep-23 5 282
GR-CON-Z07-1366 Aggregate Drainage layer 05-Sep-23 12-Sep-23 6 282
GR-CON-Z07-1367 Installation Geotextile 12-Sep-23 17-Sep-23 4 282
GR-CON-Z07-1368 Backfilling (Soil max for tree) 17-Sep-23 25-Sep-23 6 282
GR-CON-Z07-1369 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10496 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10506 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10516 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10526 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1370 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1371 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1372 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1381 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1382 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1383 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1384 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1385 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 24-Aug-23 06-Nov-23 62 295
GR-CON-Z07-1373 Excavation Pipe Irrigation 24-Aug-23 30-Aug-23 5 245
GR-CON-Z07-1374 Sand Bedding 30-Aug-23 04-Sep-23 4 245
GR-CON-Z07-1375 HDPE Pipe Installations and fittings and conduit for cable 14-Sep-23 03-Oct-23 15 236
GR-CON-Z07-1377 Test pressure 03-Oct-23 09-Oct-23 5 236
GR-CON-Z07-1376 Installation of Valves and Accessories 09-Oct-23 14-Oct-23 4 236
GR-CON-Z07-1378 Back filling (sand / Subbase ) 14-Oct-23 21-Oct-23 6 236
GR-CON-Z07-1379 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Oct-23 28-Oct-23 6 295
GR-CON-Z07-1380 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
28-Oct-23
system 06-Nov-23 8 295
Electrical Works 30-Aug-23 21-May-24 216 142
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1386 Excavation And Disposal 30-Aug-23 05-Sep-23 5 331


GR-CON-Z07-1387 Sand Bedding 05-Sep-23 10-Sep-23 4 331
GR-CON-Z07-1388 laying cables 10-Sep-23 14-Sep-23 4 331
GR-CON-Z07-1389 Backfilling (sand / Sub base) 14-Sep-23 20-Sep-23 5 331
GR-CON-Z07-1390 Control Panel / Distribution Panel Installation 20-Sep-23 26-Sep-23 4 331
GR-CON-Z07-1391 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-05 24-Aug-23 18-Jun-24 245 118
Site Preparation 24-Aug-23 02-Oct-23 32 331
GR-CON-Z07-1429 Demolition (Asphalt.Paving,etc.....) 24-Aug-23 31-Aug-23 6 210
GR-CON-Z07-1430 Excavation And Disposal 31-Aug-23 10-Sep-23 8 210
GR-CON-Z07-1431 Prepretion And Compaction 10-Sep-23 20-Sep-23 9 331
GR-CON-Z07-1432 Backfilling 20-Sep-23 02-Oct-23 9 331
Curbstone and Paving 10-Sep-23 03-Dec-23 71 278
GR-CON-Z07-1433 Excavation Curbstone 10-Sep-23 19-Sep-23 8 230
GR-CON-Z07-1434 Plain Concrete 19-Sep-23 01-Oct-23 9 278
GR-CON-Z07-1435 Installation Curbstone 01-Oct-23 17-Oct-23 14 278
GR-CON-Z07-1436 Casting Concrete (Mortar haunch) 17-Oct-23 24-Oct-23 6 278
GR-CON-Z07-1437 Backfilling (sand / Sub base) 24-Oct-23 09-Nov-23 14 278
GR-CON-Z07-1438 Installation of Paving 09-Nov-23 03-Dec-23 20 278
Landscape Works 19-Sep-23 12-May-24 191 118
GR-CON-Z07-1439 Excavation (Tree Pit ) 19-Sep-23 30-Sep-23 8 230
GR-CON-Z07-1440 Aggregate Drainage layer 30-Sep-23 10-Oct-23 9 230
GR-CON-Z07-1441 Installation Geotextile 10-Oct-23 17-Oct-23 6 230
GR-CON-Z07-1442 Backfilling (Soil max for tree) 17-Oct-23 28-Oct-23 9 230
GR-CON-Z07-1443 Installation of Trees 06-Mar-24 11-Mar-24 4 118
GR-CON-Z07-10536 Installation of Shrubs 11-Mar-24 14-Mar-24 3 118
GR-CON-Z07-10546 Installation of Succulents 16-Mar-24 19-Mar-24 3 118
GR-CON-Z07-10556 Installation of Ground Covers 20-Mar-24 24-Mar-24 3 118
GR-CON-Z07-10566 Installation of Grass 25-Mar-24 28-Mar-24 3 118
GR-CON-Z07-1444 Backfilling (Mulch) 30-Mar-24 06-Apr-24 5 118
GR-CON-Z07-1445 Natural Boulders Installation 06-Apr-24 18-Apr-24 6 118
GR-CON-Z07-1446 Retaining walls . Steps, forming risers, treads and edges with finishes
20-Apr-24 12-May-24 20 118
Site Furnishing 13-May-24 18-Jun-24 32 118
GR-CON-Z07-1455 Garden planter box 13-May-24 21-May-24 8 118
GR-CON-Z07-1456 Wheel stoppers 22-May-24 30-May-24 8 118
GR-CON-Z07-1457 Steel Lattice 01-Jun-24 09-Jun-24 8 118
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1458 Handrail 10-Jun-24 18-Jun-24 8 118


Storm Piping Works 09-Jun-24 18-Jun-24 9 118
GR-CON-Z07-1459 Installation of DI grating covers 09-Jun-24 18-Jun-24 9 118
Irrigation Works 10-Sep-23 14-Dec-23 81 259
GR-CON-Z07-1447 Excavation Pipe Irrigation 10-Sep-23 19-Sep-23 8 210
GR-CON-Z07-1448 Sand Bedding 19-Sep-23 27-Sep-23 6 210
GR-CON-Z07-1449 HDPE Pipe Installations and fittings and conduit for cable 27-Sep-23 24-Oct-23 23 210
GR-CON-Z07-1451 Test pressure 24-Oct-23 02-Nov-23 8 210
GR-CON-Z07-1450 Installation of Valves and Accessories 02-Nov-23 09-Nov-23 6 210
GR-CON-Z07-1452 Back filling (sand / Subbase ) 09-Nov-23 20-Nov-23 9 210
GR-CON-Z07-1453 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Nov-23 30-Nov-23 9 259
GR-CON-Z07-1454 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
30-Nov-23
system 14-Dec-23 12 259
Electrical Works 19-Sep-23 18-Jun-24 223 118
GR-CON-Z07-1460 Excavation And Disposal 19-Sep-23 30-Sep-23 8 299
GR-CON-Z07-1461 Sand Bedding 30-Sep-23 07-Oct-23 6 299
GR-CON-Z07-1462 laying cables 07-Oct-23 14-Oct-23 6 299
GR-CON-Z07-1463 Backfilling (sand / Sub base) 14-Oct-23 23-Oct-23 8 299
GR-CON-Z07-1464 Control Panel / Distribution Panel Installation 23-Oct-23 30-Oct-23 6 299
GR-CON-Z07-1465 Road Crossing Ducts 10-Jun-24 18-Jun-24 8 118
Street SS-78 04-Sep-23 21-May-24 212 142
Site Preparation 04-Sep-23 30-Sep-23 21 333
GR-CON-Z07-1392 Demolition (Asphalt.Paving,etc.....) 04-Sep-23 09-Sep-23 4 227
GR-CON-Z07-1393 Excavation And Disposal 09-Sep-23 14-Sep-23 5 227
GR-CON-Z07-1394 Prepretion And Compaction 14-Sep-23 21-Sep-23 6 333
GR-CON-Z07-1395 Backfilling 21-Sep-23 30-Sep-23 6 333
Curbstone and Paving 14-Sep-23 08-Nov-23 46 299
GR-CON-Z07-1396 Excavation Curbstone 14-Sep-23 20-Sep-23 5 264
GR-CON-Z07-1397 Plain Concrete 20-Sep-23 28-Sep-23 6 299
GR-CON-Z07-1398 Installation Curbstone 28-Sep-23 09-Oct-23 9 299
GR-CON-Z07-1399 Casting Concrete (Mortar haunch) 09-Oct-23 14-Oct-23 4 299
GR-CON-Z07-1400 Backfilling (sand / Sub base) 14-Oct-23 24-Oct-23 9 299
GR-CON-Z07-1401 Installation of Paving 24-Oct-23 08-Nov-23 13 299
Landscape Works 20-Sep-23 28-Apr-24 178 142
GR-CON-Z07-1402 Excavation (Tree Pit ) 20-Sep-23 27-Sep-23 5 264
GR-CON-Z07-1403 Aggregate Drainage layer 27-Sep-23 04-Oct-23 6 264
GR-CON-Z07-1404 Installation Geotextile 04-Oct-23 09-Oct-23 4 264
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1405 Backfilling (Soil max for tree) 09-Oct-23 16-Oct-23 6 264


GR-CON-Z07-1406 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10576 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10586 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10596 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10606 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1407 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1408 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1409 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1418 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1419 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1420 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1421 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1422 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 14-Sep-23 16-Nov-23 53 286
GR-CON-Z07-1410 Excavation Pipe Irrigation 14-Sep-23 20-Sep-23 5 227
GR-CON-Z07-1411 Sand Bedding 20-Sep-23 26-Sep-23 4 227
GR-CON-Z07-1412 HDPE Pipe Installations and fittings and conduit for cable 26-Sep-23 14-Oct-23 15 227
GR-CON-Z07-1414 Test pressure 14-Oct-23 19-Oct-23 5 227
GR-CON-Z07-1413 Installation of Valves and Accessories 19-Oct-23 24-Oct-23 4 227
GR-CON-Z07-1415 Back filling (sand / Subbase ) 24-Oct-23 31-Oct-23 6 227
GR-CON-Z07-1416 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 31-Oct-23 07-Nov-23 6 286
GR-CON-Z07-1417 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-Nov-23
system 16-Nov-23 8 286
Electrical Works 20-Sep-23 21-May-24 198 142
GR-CON-Z07-1423 Excavation And Disposal 20-Sep-23 27-Sep-23 5 313
GR-CON-Z07-1424 Sand Bedding 27-Sep-23 02-Oct-23 4 313
GR-CON-Z07-1425 laying cables 02-Oct-23 07-Oct-23 4 313
GR-CON-Z07-1426 Backfilling (sand / Sub base) 07-Oct-23 12-Oct-23 5 313
GR-CON-Z07-1427 Control Panel / Distribution Panel Installation 12-Oct-23 17-Oct-23 4 313
GR-CON-Z07-1428 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-79 14-Sep-23 21-May-24 203 142
Site Preparation 14-Sep-23 10-Oct-23 21 324
GR-CON-Z07-1466 Demolition (Asphalt.Paving,etc.....) 14-Sep-23 19-Sep-23 4 218
GR-CON-Z07-1467 Excavation And Disposal 19-Sep-23 26-Sep-23 5 218
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1468 Prepretion And Compaction 26-Sep-23 03-Oct-23 6 324


GR-CON-Z07-1469 Backfilling 03-Oct-23 10-Oct-23 6 324
Curbstone and Paving 26-Sep-23 19-Nov-23 46 290
GR-CON-Z07-1470 Excavation Curbstone 26-Sep-23 02-Oct-23 5 255
GR-CON-Z07-1471 Plain Concrete 02-Oct-23 09-Oct-23 6 290
GR-CON-Z07-1472 Installation Curbstone 09-Oct-23 19-Oct-23 9 290
GR-CON-Z07-1473 Casting Concrete (Mortar haunch) 19-Oct-23 24-Oct-23 4 290
GR-CON-Z07-1474 Backfilling (sand / Sub base) 24-Oct-23 04-Nov-23 9 290
GR-CON-Z07-1475 Installation of Paving 04-Nov-23 19-Nov-23 13 290
Landscape Works 02-Oct-23 28-Apr-24 169 142
GR-CON-Z07-1476 Excavation (Tree Pit ) 02-Oct-23 08-Oct-23 5 255
GR-CON-Z07-1477 Aggregate Drainage layer 08-Oct-23 15-Oct-23 6 255
GR-CON-Z07-1478 Installation Geotextile 15-Oct-23 19-Oct-23 4 255
GR-CON-Z07-1479 Backfilling (Soil max for tree) 19-Oct-23 26-Oct-23 6 255
GR-CON-Z07-1480 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10616 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10626 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10636 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10646 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1481 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1482 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1483 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1492 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1493 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1494 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1495 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1496 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 26-Sep-23 27-Nov-23 53 277
GR-CON-Z07-1484 Excavation Pipe Irrigation 26-Sep-23 02-Oct-23 5 218
GR-CON-Z07-1485 Sand Bedding 02-Oct-23 07-Oct-23 4 218
GR-CON-Z07-1486 HDPE Pipe Installations and fittings and conduit for cable 07-Oct-23 24-Oct-23 15 218
GR-CON-Z07-1488 Test pressure 24-Oct-23 30-Oct-23 5 218
GR-CON-Z07-1487 Installation of Valves and Accessories 30-Oct-23 04-Nov-23 4 218
GR-CON-Z07-1489 Back filling (sand / Subbase ) 04-Nov-23 11-Nov-23 6 218
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1490 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Nov-23 18-Nov-23 6 277
GR-CON-Z07-1491 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Nov-23
system 27-Nov-23 8 277
Electrical Works 02-Oct-23 21-May-24 189 142
GR-CON-Z07-1497 Excavation And Disposal 02-Oct-23 08-Oct-23 5 304
GR-CON-Z07-1498 Sand Bedding 08-Oct-23 12-Oct-23 4 304
GR-CON-Z07-1499 laying cables 12-Oct-23 17-Oct-23 4 304
GR-CON-Z07-1500 Backfilling (sand / Sub base) 17-Oct-23 23-Oct-23 5 304
GR-CON-Z07-1501 Control Panel / Distribution Panel Installation 23-Oct-23 28-Oct-23 4 304
GR-CON-Z07-1502 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-81 27-Sep-23 21-May-24 193 142
Site Preparation 27-Sep-23 22-Oct-23 21 314
GR-CON-Z07-1503 Demolition (Asphalt.Paving,etc.....) 27-Sep-23 02-Oct-23 4 208
GR-CON-Z07-1504 Excavation And Disposal 02-Oct-23 08-Oct-23 5 208
GR-CON-Z07-1505 Prepretion And Compaction 08-Oct-23 15-Oct-23 6 314
GR-CON-Z07-1506 Backfilling 15-Oct-23 22-Oct-23 6 314
Curbstone and Paving 08-Oct-23 30-Nov-23 46 280
GR-CON-Z07-1507 Excavation Curbstone 08-Oct-23 14-Oct-23 5 245
GR-CON-Z07-1508 Plain Concrete 14-Oct-23 21-Oct-23 6 280
GR-CON-Z07-1509 Installation Curbstone 21-Oct-23 31-Oct-23 9 280
GR-CON-Z07-1510 Casting Concrete (Mortar haunch) 31-Oct-23 05-Nov-23 4 280
GR-CON-Z07-1511 Backfilling (sand / Sub base) 05-Nov-23 15-Nov-23 9 280
GR-CON-Z07-1512 Installation of Paving 15-Nov-23 30-Nov-23 13 280
Landscape Works 14-Oct-23 28-Apr-24 159 142
GR-CON-Z07-1513 Excavation (Tree Pit ) 14-Oct-23 19-Oct-23 5 245
GR-CON-Z07-1514 Aggregate Drainage layer 19-Oct-23 26-Oct-23 6 245
GR-CON-Z07-1515 Installation Geotextile 26-Oct-23 31-Oct-23 4 245
GR-CON-Z07-1516 Backfilling (Soil max for tree) 31-Oct-23 07-Nov-23 6 245
GR-CON-Z07-1517 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10656 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10666 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10676 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10686 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1518 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1519 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1520 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1529 Garden planter box 29-Apr-24 04-May-24 5 142


GR-CON-Z07-1530 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1531 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1532 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1533 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 08-Oct-23 09-Dec-23 53 267
GR-CON-Z07-1521 Excavation Pipe Irrigation 08-Oct-23 14-Oct-23 5 208
GR-CON-Z07-1522 Sand Bedding 14-Oct-23 18-Oct-23 4 208
GR-CON-Z07-1523 HDPE Pipe Installations and fittings and conduit for cable 18-Oct-23 05-Nov-23 15 208
GR-CON-Z07-1525 Test pressure 05-Nov-23 11-Nov-23 5 208
GR-CON-Z07-1524 Installation of Valves and Accessories 11-Nov-23 15-Nov-23 4 208
GR-CON-Z07-1526 Back filling (sand / Subbase ) 15-Nov-23 22-Nov-23 6 208
GR-CON-Z07-1527 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 22-Nov-23 29-Nov-23 6 267
GR-CON-Z07-1528 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
29-Nov-23
system 09-Dec-23 8 267
Electrical Works 14-Oct-23 21-May-24 179 142
GR-CON-Z07-1534 Excavation And Disposal 14-Oct-23 19-Oct-23 5 294
GR-CON-Z07-1535 Sand Bedding 19-Oct-23 24-Oct-23 4 294
GR-CON-Z07-1536 laying cables 24-Oct-23 29-Oct-23 4 294
GR-CON-Z07-1537 Backfilling (sand / Sub base) 29-Oct-23 04-Nov-23 5 294
GR-CON-Z07-1538 Control Panel / Distribution Panel Installation 04-Nov-23 08-Nov-23 4 294
GR-CON-Z07-1539 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-82 09-Oct-23 21-May-24 183 142
Site Preparation 09-Oct-23 02-Nov-23 21 304
GR-CON-Z07-1540 Demolition (Asphalt.Paving,etc.....) 09-Oct-23 14-Oct-23 4 198
GR-CON-Z07-1541 Excavation And Disposal 14-Oct-23 19-Oct-23 5 198
GR-CON-Z07-1542 Prepretion And Compaction 19-Oct-23 26-Oct-23 6 304
GR-CON-Z07-1543 Backfilling 26-Oct-23 02-Nov-23 6 304
Curbstone and Paving 19-Oct-23 12-Dec-23 46 270
GR-CON-Z07-1544 Excavation Curbstone 19-Oct-23 25-Oct-23 5 235
GR-CON-Z07-1545 Plain Concrete 25-Oct-23 01-Nov-23 6 270
GR-CON-Z07-1546 Installation Curbstone 01-Nov-23 12-Nov-23 9 270
GR-CON-Z07-1547 Casting Concrete (Mortar haunch) 12-Nov-23 16-Nov-23 4 270
GR-CON-Z07-1548 Backfilling (sand / Sub base) 16-Nov-23 27-Nov-23 9 270
GR-CON-Z07-1549 Installation of Paving 27-Nov-23 12-Dec-23 13 270
Landscape Works 25-Oct-23 28-Apr-24 149 142
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1550 Excavation (Tree Pit ) 25-Oct-23 31-Oct-23 5 235


GR-CON-Z07-1551 Aggregate Drainage layer 31-Oct-23 07-Nov-23 6 235
GR-CON-Z07-1552 Installation Geotextile 07-Nov-23 12-Nov-23 4 235
GR-CON-Z07-1553 Backfilling (Soil max for tree) 12-Nov-23 19-Nov-23 6 235
GR-CON-Z07-1554 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10696 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10706 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10716 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10726 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1555 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1556 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1557 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1566 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1567 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1568 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1569 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1570 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 19-Oct-23 20-Dec-23 53 257
GR-CON-Z07-1558 Excavation Pipe Irrigation 19-Oct-23 25-Oct-23 5 198
GR-CON-Z07-1559 Sand Bedding 25-Oct-23 30-Oct-23 4 198
GR-CON-Z07-1560 HDPE Pipe Installations and fittings and conduit for cable 30-Oct-23 16-Nov-23 15 198
GR-CON-Z07-1562 Test pressure 16-Nov-23 22-Nov-23 5 198
GR-CON-Z07-1561 Installation of Valves and Accessories 22-Nov-23 27-Nov-23 4 198
GR-CON-Z07-1563 Back filling (sand / Subbase ) 27-Nov-23 04-Dec-23 6 198
GR-CON-Z07-1564 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Dec-23 11-Dec-23 6 257
GR-CON-Z07-1565 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
11-Dec-23
system 20-Dec-23 8 257
Electrical Works 25-Oct-23 21-May-24 169 142
GR-CON-Z07-1571 Excavation And Disposal 25-Oct-23 31-Oct-23 5 284
GR-CON-Z07-1572 Sand Bedding 31-Oct-23 05-Nov-23 4 284
GR-CON-Z07-1573 laying cables 05-Nov-23 09-Nov-23 4 284
GR-CON-Z07-1574 Backfilling (sand / Sub base) 09-Nov-23 15-Nov-23 5 284
GR-CON-Z07-1575 Control Panel / Distribution Panel Installation 15-Nov-23 20-Nov-23 4 284
GR-CON-Z07-1576 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-83 15-Oct-23 21-May-24 178 142
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 15-Oct-23 08-Nov-23 21 299


GR-CON-Z07-1577 Demolition (Asphalt.Paving,etc.....) 15-Oct-23 19-Oct-23 4 193
GR-CON-Z07-1578 Excavation And Disposal 19-Oct-23 25-Oct-23 5 193
GR-CON-Z07-1579 Prepretion And Compaction 25-Oct-23 01-Nov-23 6 299
GR-CON-Z07-1580 Backfilling 01-Nov-23 08-Nov-23 6 299
Curbstone and Paving 25-Oct-23 18-Dec-23 46 265
GR-CON-Z07-1581 Excavation Curbstone 25-Oct-23 31-Oct-23 5 230
GR-CON-Z07-1582 Plain Concrete 31-Oct-23 07-Nov-23 6 265
GR-CON-Z07-1583 Installation Curbstone 07-Nov-23 18-Nov-23 9 265
GR-CON-Z07-1584 Casting Concrete (Mortar haunch) 18-Nov-23 22-Nov-23 4 265
GR-CON-Z07-1585 Backfilling (sand / Sub base) 22-Nov-23 03-Dec-23 9 265
GR-CON-Z07-1586 Installation of Paving 03-Dec-23 18-Dec-23 13 265
Landscape Works 31-Oct-23 28-Apr-24 144 142
GR-CON-Z07-1587 Excavation (Tree Pit ) 31-Oct-23 06-Nov-23 5 230
GR-CON-Z07-1588 Aggregate Drainage layer 06-Nov-23 13-Nov-23 6 230
GR-CON-Z07-1589 Installation Geotextile 13-Nov-23 18-Nov-23 4 230
GR-CON-Z07-1590 Backfilling (Soil max for tree) 18-Nov-23 25-Nov-23 6 230
GR-CON-Z07-1591 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10736 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10746 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10756 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10766 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1592 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
GR-CON-Z07-1593 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142
GR-CON-Z07-1594 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1603 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1604 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1605 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1606 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1607 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 25-Oct-23 26-Dec-23 53 252
GR-CON-Z07-1595 Excavation Pipe Irrigation 25-Oct-23 31-Oct-23 5 193
GR-CON-Z07-1596 Sand Bedding 31-Oct-23 05-Nov-23 4 193
GR-CON-Z07-1597 HDPE Pipe Installations and fittings and conduit for cable 05-Nov-23 22-Nov-23 15 193
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1599 Test pressure 22-Nov-23 28-Nov-23 5 193


GR-CON-Z07-1598 Installation of Valves and Accessories 28-Nov-23 03-Dec-23 4 193
GR-CON-Z07-1600 Back filling (sand / Subbase ) 03-Dec-23 10-Dec-23 6 193
GR-CON-Z07-1601 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Dec-23 17-Dec-23 6 252
GR-CON-Z07-1602 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Dec-23
system 26-Dec-23 8 252
Electrical Works 31-Oct-23 21-May-24 164 142
GR-CON-Z07-1608 Excavation And Disposal 31-Oct-23 06-Nov-23 5 279
GR-CON-Z07-1609 Sand Bedding 06-Nov-23 11-Nov-23 4 279
GR-CON-Z07-1610 laying cables 11-Nov-23 15-Nov-23 4 279
GR-CON-Z07-1611 Backfilling (sand / Sub base) 15-Nov-23 21-Nov-23 5 279
GR-CON-Z07-1612 Control Panel / Distribution Panel Installation 21-Nov-23 26-Nov-23 4 279
GR-CON-Z07-1613 Road Crossing Ducts 16-May-24 21-May-24 5 142
Street SS-84 21-Oct-23 21-May-24 173 142
Site Preparation 21-Oct-23 14-Nov-23 21 294
GR-CON-Z07-1614 Demolition (Asphalt.Paving,etc.....) 21-Oct-23 25-Oct-23 4 18
GR-CON-Z07-1615 Excavation And Disposal 25-Oct-23 31-Oct-23 5 118
GR-CON-Z07-1616 Prepretion And Compaction 31-Oct-23 07-Nov-23 6 294
GR-CON-Z07-1617 Backfilling 07-Nov-23 14-Nov-23 6 294
Curbstone and Paving 31-Oct-23 24-Dec-23 46 260
GR-CON-Z07-1618 Excavation Curbstone 31-Oct-23 06-Nov-23 5 225
GR-CON-Z07-1619 Plain Concrete 06-Nov-23 13-Nov-23 6 260
GR-CON-Z07-1620 Installation Curbstone 13-Nov-23 23-Nov-23 9 260
GR-CON-Z07-1621 Casting Concrete (Mortar haunch) 23-Nov-23 28-Nov-23 4 260
GR-CON-Z07-1622 Backfilling (sand / Sub base) 28-Nov-23 09-Dec-23 9 260
GR-CON-Z07-1623 Installation of Paving 09-Dec-23 24-Dec-23 13 260
Landscape Works 06-Nov-23 28-Apr-24 139 142
GR-CON-Z07-1624 Excavation (Tree Pit ) 06-Nov-23 12-Nov-23 5 225
GR-CON-Z07-1625 Aggregate Drainage layer 12-Nov-23 19-Nov-23 6 225
GR-CON-Z07-1626 Installation Geotextile 19-Nov-23 23-Nov-23 4 225
GR-CON-Z07-1627 Backfilling (Soil max for tree) 23-Nov-23 30-Nov-23 6 225
GR-CON-Z07-1628 Installation of Trees 06-Mar-24 10-Mar-24 3 142
GR-CON-Z07-10776 Installation of Shrubs 10-Mar-24 13-Mar-24 3 142
GR-CON-Z07-10786 Installation of Succulents 13-Mar-24 18-Mar-24 3 142
GR-CON-Z07-10796 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 142
GR-CON-Z07-10806 Installation of Grass 23-Mar-24 27-Mar-24 3 142
GR-CON-Z07-1629 Backfilling (Mulch) 27-Mar-24 01-Apr-24 3 142
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1630 Natural Boulders Installation 01-Apr-24 07-Apr-24 4 142


GR-CON-Z07-1631 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Apr-24 28-Apr-24 13 142
Site Furnishing 29-Apr-24 21-May-24 20 142
GR-CON-Z07-1640 Garden planter box 29-Apr-24 04-May-24 5 142
GR-CON-Z07-1641 Wheel stoppers 05-May-24 09-May-24 5 142
GR-CON-Z07-1642 Steel Lattice 11-May-24 15-May-24 5 142
GR-CON-Z07-1643 Handrail 16-May-24 21-May-24 5 142
Storm Piping Works 15-May-24 21-May-24 6 142
GR-CON-Z07-1644 Installation of DI grating covers 15-May-24 21-May-24 6 142
Irrigation Works 31-Oct-23 01-Jan-24 53 247
GR-CON-Z07-1632 Excavation Pipe Irrigation 31-Oct-23 06-Nov-23 5 118
GR-CON-Z07-1633 Sand Bedding 06-Nov-23 11-Nov-23 4 118
GR-CON-Z07-1634 HDPE Pipe Installations and fittings and conduit for cable 11-Nov-23 28-Nov-23 15 118
GR-CON-Z07-1636 Test pressure 28-Nov-23 04-Dec-23 5 118
GR-CON-Z07-1635 Installation of Valves and Accessories 04-Dec-23 09-Dec-23 4 118
GR-CON-Z07-1637 Back filling (sand / Subbase ) 09-Dec-23 16-Dec-23 6 118
GR-CON-Z07-1638 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Dec-23 23-Dec-23 6 247
GR-CON-Z07-1639 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-Dec-23
system 01-Jan-24 8 247
Electrical Works 06-Nov-23 21-May-24 159 142
GR-CON-Z07-1645 Excavation And Disposal 06-Nov-23 12-Nov-23 5 274
GR-CON-Z07-1646 Sand Bedding 12-Nov-23 16-Nov-23 4 274
GR-CON-Z07-1647 laying cables 16-Nov-23 21-Nov-23 4 274
GR-CON-Z07-1648 Backfilling (sand / Sub base) 21-Nov-23 27-Nov-23 5 274
GR-CON-Z07-1649 Control Panel / Distribution Panel Installation 27-Nov-23 02-Dec-23 4 274
GR-CON-Z07-1650 Road Crossing Ducts 16-May-24 21-May-24 5 142
School S-01a 26-Oct-23 16-May-24 164 146
Site Preparation 26-Oct-23 06-Nov-23 9 301
GR-CON-Z07-1180 Excavation And Disposal 26-Oct-23 01-Nov-23 5 17
GR-CON-Z07-1181 Prepretion And Compaction 01-Nov-23 06-Nov-23 4 301
Curbstone and Paving 01-Nov-23 25-Dec-23 46 259
GR-CON-Z07-1183 Excavation Curbstone 01-Nov-23 07-Nov-23 5 228
GR-CON-Z07-1184 Plain Concrete 07-Nov-23 14-Nov-23 6 259
GR-CON-Z07-1185 Installation Curbstone 14-Nov-23 25-Nov-23 9 259
GR-CON-Z07-1186 Casting Concrete (Mortar haunch) 25-Nov-23 29-Nov-23 4 259
GR-CON-Z07-1187 Backfilling (sand / Sub base) 29-Nov-23 10-Dec-23 9 259
GR-CON-Z07-1188 Installation of Paving 10-Dec-23 25-Dec-23 13 259
Activity ID Activity Name Start Finish Original Total Float
Duration

Landscape Works 07-Nov-23 05-May-24 144 146


GR-CON-Z07-1189 Excavation (Tree Pit ) 07-Nov-23 13-Nov-23 5 228
GR-CON-Z07-1190 Aggregate Drainage layer 13-Nov-23 20-Nov-23 6 228
GR-CON-Z07-1191 Installation Geotextile 20-Nov-23 25-Nov-23 4 228
GR-CON-Z07-1192 Backfilling (Soil max for tree) 25-Nov-23 02-Dec-23 6 228
GR-CON-Z07-1193 Installation of Trees 06-Mar-24 10-Mar-24 3 146
GR-CON-Z07-5476 Installation of Shrubs 10-Mar-24 13-Mar-24 3 146
GR-CON-Z07-5486 Installation of Succulents 13-Mar-24 18-Mar-24 3 146
GR-CON-Z07-5496 Installation of Ground Covers 18-Mar-24 23-Mar-24 3 146
GR-CON-Z07-5506 Installation of Climbers 23-Mar-24 27-Mar-24 3 146
GR-CON-Z07-5516 Installation of Grass 27-Mar-24 01-Apr-24 3 146
GR-CON-Z07-5526 Installation of Lawns 01-Apr-24 06-Apr-24 3 146
GR-CON-Z07-1194 Backfilling (Mulch) 06-Apr-24 10-Apr-24 3 146
GR-CON-Z07-1195 Natural Boulders Installation 10-Apr-24 20-Apr-24 4 146
GR-CON-Z07-1196 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Apr-24 05-May-24 13 146
Site Furnishing 06-May-24 16-May-24 10 146
GR-CON-Z07-1205 Garden planter box 06-May-24 11-May-24 5 146
GR-CON-Z07-1206 Wheel stoppers 12-May-24 16-May-24 5 146
Irrigation Works 01-Nov-23 16-May-24 159 146
GR-CON-Z07-1197 Excavation Pipe Irrigation 01-Nov-23 07-Nov-23 5 188
GR-CON-Z07-1198 Sand Bedding 07-Nov-23 11-Nov-23 3 188
GR-CON-Z07-1199 HDPE Pipe Installations and fittings and conduit for cable 11-Nov-23 28-Nov-23 15 188
GR-CON-Z07-1201 Test pressure 28-Nov-23 04-Dec-23 5 188
GR-CON-Z07-1200 Installation of Valves and Accessories 04-Dec-23 09-Dec-23 4 188
GR-CON-Z07-1202 Back filling (sand / Subbase ) 09-Dec-23 16-Dec-23 6 188
GR-CON-Z07-1203 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Dec-23 23-Dec-23 6 253
GR-CON-Z07-1204 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-May-24
system 16-May-24 8 146
Toilet - 01 01-Nov-23 20-Oct-24 288 17
Site Preparation 01-Nov-23 13-Nov-23 10 17
GR-CON-Z07-1000 Excavation And Disposal 01-Nov-23 07-Nov-23 5 17
GR-CON-Z07-1001 Backfilling (one layer) 07-Nov-23 13-Nov-23 5 17
Civil Works 13-Nov-23 06-May-24 140 17
GR-CON-Z07-1002 Polyethylene Under Footings, Grade Slab and Beams 13-Nov-23 16-Nov-23 3 17
GR-CON-Z07-1003 Blinding concrete 16-Nov-23 22-Nov-23 5 17
GR-CON-Z07-1004 Footings 22-Nov-23 02-Dec-23 8 17
GR-CON-Z07-1005 Waterproofing Under Footing 02-Dec-23 07-Dec-23 5 17
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z07-1006 Column Necks 07-Dec-23 14-Dec-23 6 17


GR-CON-Z07-1007 Waterproofing (Toilet) 20-Dec-23 31-Dec-23 9 17
GR-CON-Z07-1008 Backfilling 31-Dec-23 07-Jan-24 6 17
GR-CON-Z07-1009 Ground beams 07-Jan-24 22-Jan-24 13 17
GR-CON-Z07-1010 Slab on grade 22-Jan-24 12-Feb-24 18 17
GR-CON-Z07-1011 Columns 12-Feb-24 27-Feb-24 13 17
GR-CON-Z07-1012 Concrete, slabs Ground floor 27-Feb-24 26-Mar-24 21 17
GR-CON-Z07-1013 Roof Thermal And Moisture Protection Work 27-Apr-24 06-May-24 9 17
Architectural Works 07-May-24 20-Oct-24 138 17
GR-CON-Z07-1014 Blockwork 07-May-24 28-May-24 19 17
GR-CON-Z07-1015 Waterproofing 08-Jun-24 17-Jun-24 9 17
GR-CON-Z07-1016 Back Filling (sand) 18-Jun-24 27-Jun-24 5 17
GR-CON-Z07-1017 Floor finish 29-Jun-24 13-Jul-24 13 17
GR-CON-Z07-1018 Wall Finish 14-Jul-24 11-Aug-24 25 17
GR-CON-Z07-1019 Door Installation 12-Aug-24 15-Aug-24 4 17
GR-CON-Z07-1021 Celling finish 17-Aug-24 31-Aug-24 13 17
GR-CON-Z07-1022 ToiletAccessories 01-Sep-24 04-Sep-24 4 17
GR-CON-Z07-1023 Facade Finishing Works 05-Sep-24 28-Sep-24 19 17
GR-CON-Z07-1024 Metal Work 05-Sep-24 28-Sep-24 19 17
GR-CON-Z07-1025 Wood Work 29-Sep-24 20-Oct-24 19 17
Mechanical Works 29-May-24 20-Oct-24 119 17
GR-CON-Z07-1026 Pipework Installations and fittings 29-May-24 06-Jun-24 8 17
GR-CON-Z07-1027 Installation of refrigerant supply/return pipework 29-May-24 02-Jun-24 4 77
GR-CON-Z07-1029 Water Meter With Meter Cabinet 29-May-24 01-Jun-24 3 123
GR-CON-Z07-1028 Installation of Sanitary Fixtures 14-Jul-24 22-Jul-24 8 38
GR-CON-Z07-1031 Installation of Exhaust Equipmets and Air outlets 09-Oct-24 20-Oct-24 10 17
Electrical Works 29-May-24 20-Oct-24 119 17
GR-CON-Z07-1032 Conduits Installation 29-May-24 03-Jun-24 5 47
GR-CON-Z07-1034 Earthing and lightning protection system 29-May-24 02-Jun-24 4 107
GR-CON-Z07-1033 Install of power cables 12-Aug-24 14-Aug-24 3 18
GR-CON-Z07-1035 Installation of wiring devices and lighting fixtures 12-Aug-24 17-Aug-24 5 51
GR-CON-Z07-1036 Installation of Alarm with park BMS system 18-Aug-24 22-Aug-24 5 51
GR-CON-Z07-1030 Installation of Fire Detection System 24-Aug-24 01-Sep-24 8 51
GR-CON-Z07-1037 Installation of Panel Board 02-Sep-24 05-Sep-24 4 51
GR-CON-Z07-1038 Connecting to nearest feeder pillar 17-Oct-24 20-Oct-24 3 17
Zone 01 12-Sep-23 05-Oct-24 318 0
Activity ID Activity Name Start Finish Original Total Float
Duration

Future Neighborhood Park FNP-01 12-Sep-23 15-Jul-24 249 69


Site Preparation 12-Sep-23 30-Sep-23 15 303
GR-CON-Z01-1332 Demolition (Asphalt.Paving,etc.....) 12-Sep-23 14-Sep-23 3 17
GR-CON-Z01-1333 Excavation And Disposal 16-Sep-23 19-Sep-23 4 183
GR-CON-Z01-1334 Prepretion And Compaction 20-Sep-23 24-Sep-23 3 303
GR-CON-Z01-1335 Backfilling 25-Sep-23 30-Sep-23 5 303
Curbstone and Paving 20-Sep-23 01-Nov-23 36 275
GR-CON-Z01-1336 Excavation Curbstone 20-Sep-23 25-Sep-23 4 261
GR-CON-Z01-1337 Plain Concrete 26-Sep-23 01-Oct-23 5 275
GR-CON-Z01-1338 Installation Curbstone 02-Oct-23 09-Oct-23 7 275
GR-CON-Z01-1339 Casting Concrete (Mortar haunch) 10-Oct-23 12-Oct-23 3 275
GR-CON-Z01-1340 Backfilling (sand / Sub base) 14-Oct-23 21-Oct-23 7 275
GR-CON-Z01-1341 Installation of Paving 22-Oct-23 01-Nov-23 10 275
Landscape Works 26-Sep-23 15-Jul-24 238 69
GR-CON-Z01-1342 Excavation (Tree Pit ) 26-Sep-23 30-Sep-23 4 261
GR-CON-Z01-1343 Aggregate Drainage layer 01-Oct-23 05-Oct-23 5 261
GR-CON-Z01-1344 Installation Geotextile 07-Oct-23 09-Oct-23 3 261
GR-CON-Z01-1345 Backfilling (Soil max for tree) 10-Oct-23 15-Oct-23 5 261
GR-CON-Z01-1346 Installation of Trees 08-Jun-24 09-Jun-24 2 69
GR-CON-Z01-1486 Installation of Shrubs 10-Jun-24 11-Jun-24 2 69
GR-CON-Z01-1496 Installation of Succulents 12-Jun-24 13-Jun-24 2 69
GR-CON-Z01-1506 Installation of Ground Covers 15-Jun-24 16-Jun-24 2 69
GR-CON-Z01-1516 Installation of Climbers 17-Jun-24 18-Jun-24 2 69
GR-CON-Z01-1526 Installation of Grass 24-Jun-24 25-Jun-24 2 69
GR-CON-Z01-1536 Installation of Lawns 26-Jun-24 27-Jun-24 2 69
GR-CON-Z01-1347 Backfilling (Mulch) 29-Jun-24 30-Jun-24 2 69
GR-CON-Z01-1348 Natural Boulders Installation 01-Jul-24 03-Jul-24 3 69
GR-CON-Z01-1349 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jul-24 15-Jul-24 10 69
Irrigation Works 20-Sep-23 15-Jul-24 242 69
GR-CON-Z01-1350 Excavation Pipe Irrigation 20-Sep-23 25-Sep-23 4 183
GR-CON-Z01-1351 Sand Bedding 26-Sep-23 27-Sep-23 2 183
GR-CON-Z01-1352 HDPE Pipe Installations and fittings and conduit for cable 05-Oct-23 19-Oct-23 12 176
GR-CON-Z01-1354 Test pressure 19-Oct-23 24-Oct-23 4 176
GR-CON-Z01-1353 Installation of Valves and Accessories 24-Oct-23 28-Oct-23 3 176
GR-CON-Z01-1355 Back filling (sand / Subbase ) 28-Oct-23 02-Nov-23 5 176
GR-CON-Z01-1356 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 02-Nov-23 08-Nov-23 5 263
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1357 Pull box , Decoders , Connecting to plots /Connection to infra irrigation


09-Jul-24
system 15-Jul-24 6 69
Mosque M-01 16-Sep-23 10-Jul-24 242 73
Site Preparation 16-Sep-23 03-Oct-23 15 283
GR-CON-Z01-1358 Demolition (Asphalt.Paving,etc.....) 16-Sep-23 18-Sep-23 3 17
GR-CON-Z01-1359 Excavation And Disposal 19-Sep-23 24-Sep-23 4 180
GR-CON-Z01-1360 Prepretion And Compaction 25-Sep-23 27-Sep-23 3 283
GR-CON-Z01-1361 Backfilling 28-Sep-23 03-Oct-23 5 283
Curbstone and Paving 04-Oct-23 23-Oct-23 17 283
GR-CON-Z01-1366 Backfilling (sand / Sub base) 04-Oct-23 11-Oct-23 7 283
GR-CON-Z01-1367 Installation of Paving 12-Oct-23 23-Oct-23 10 283
Landscape Works 25-Sep-23 10-Jul-24 235 73
GR-CON-Z01-1368 Excavation (Tree Pit ) 25-Sep-23 28-Sep-23 4 266
GR-CON-Z01-1369 Aggregate Drainage layer 30-Sep-23 04-Oct-23 5 266
GR-CON-Z01-1370 Installation Geotextile 05-Oct-23 08-Oct-23 3 266
GR-CON-Z01-1371 Backfilling (Soil max for tree) 09-Oct-23 14-Oct-23 5 266
GR-CON-Z01-1372 Installation of Trees 08-Jun-24 09-Jun-24 2 73
GR-CON-Z01-1482 Installation of Climbers 10-Jun-24 11-Jun-24 2 73
GR-CON-Z01-1492 Installation of Shrubs 12-Jun-24 13-Jun-24 2 73
GR-CON-Z01-1502 Installation of Succulents 15-Jun-24 16-Jun-24 2 73
GR-CON-Z01-1512 Installation of Ground Covers 17-Jun-24 18-Jun-24 2 73
GR-CON-Z01-1373 Backfilling (Mulch) 24-Jun-24 25-Jun-24 2 73
GR-CON-Z01-1374 Natural Boulders Installation 26-Jun-24 29-Jun-24 3 73
GR-CON-Z01-1375 Retaining walls . Steps, forming risers, treads and edges with finishes
30-Jun-24 10-Jul-24 10 73
Irrigation Works 25-Sep-23 10-Jul-24 235 73
GR-CON-Z01-1376 Excavation Pipe Irrigation 25-Sep-23 28-Sep-23 4 180
GR-CON-Z01-1377 Sand Bedding 30-Sep-23 01-Oct-23 2 180
GR-CON-Z01-1378 HDPE Pipe Installations and fittings and conduit for cable 02-Oct-23 15-Oct-23 12 180
GR-CON-Z01-1380 Test pressure 16-Oct-23 19-Oct-23 4 180
GR-CON-Z01-1379 Installation of Valves and Accessories 21-Oct-23 23-Oct-23 3 180
GR-CON-Z01-1381 Back filling (sand / Subbase ) 24-Oct-23 29-Oct-23 5 180
GR-CON-Z01-1382 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Oct-23 04-Nov-23 5 267
GR-CON-Z01-1383 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
04-Jul-24
system 10-Jul-24 6 73
Mosque M-02 19-Sep-23 24-Aug-24 277 35
Site Preparation 19-Sep-23 11-Oct-23 19 271
GR-CON-Z01-1000 Demolition (Asphalt.Paving,etc.....) 19-Sep-23 24-Sep-23 4 17
GR-CON-Z01-1001 Excavation And Disposal 25-Sep-23 30-Sep-23 5 167
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1002 Prepretion And Compaction 01-Oct-23 04-Oct-23 4 271


GR-CON-Z01-1003 Backfilling 05-Oct-23 11-Oct-23 6 271
Curbstone and Paving 12-Oct-23 06-Nov-23 22 271
GR-CON-Z01-1008 Backfilling (sand / Sub base) 12-Oct-23 22-Oct-23 9 271
GR-CON-Z01-1009 Installation of Paving 23-Oct-23 06-Nov-23 13 271
Landscape Works 01-Oct-23 24-Aug-24 268 35
GR-CON-Z01-1010 Excavation (Tree Pit ) 01-Oct-23 05-Oct-23 5 219
GR-CON-Z01-1011 Aggregate Drainage layer 07-Oct-23 12-Oct-23 6 219
GR-CON-Z01-1012 Installation Geotextile 14-Oct-23 18-Oct-23 5 219
GR-CON-Z01-1013 Backfilling (Soil max for tree) 19-Oct-23 24-Oct-23 5 219
GR-CON-Z01-1014 Installation of Trees 08-Jun-24 11-Jun-24 4 35
GR-CON-Z01-3306 Installation of Climbers 12-Jun-24 16-Jun-24 4 35
GR-CON-Z01-3316 Installation of Shrubs 17-Jun-24 25-Jun-24 4 35
GR-CON-Z01-3326 Installation of Succulents 26-Jun-24 30-Jun-24 4 35
GR-CON-Z01-3336 Installation of Ground Covers 01-Jul-24 04-Jul-24 4 35
GR-CON-Z01-1015 Backfilling (Mulch) 06-Jul-24 22-Jul-24 15 35
GR-CON-Z01-1016 Natural Boulders Installation 23-Jul-24 06-Aug-24 13 35
GR-CON-Z01-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Aug-24 24-Aug-24 15 35
Irrigation Works 01-Oct-23 24-Aug-24 268 35
GR-CON-Z01-1018 Excavation Pipe Irrigation 01-Oct-23 05-Oct-23 5 167
GR-CON-Z01-1019 Sand Bedding 07-Oct-23 09-Oct-23 3 167
GR-CON-Z01-1020 HDPE Pipe Installations and fittings and conduit for cable 10-Oct-23 26-Oct-23 15 167
GR-CON-Z01-1022 Test pressure 28-Oct-23 01-Nov-23 5 167
GR-CON-Z01-1021 Installation of Valves and Accessories 02-Nov-23 06-Nov-23 4 167
GR-CON-Z01-1023 Back filling (sand / Subbase ) 07-Nov-23 13-Nov-23 6 167
GR-CON-Z01-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Nov-23 20-Nov-23 6 253
GR-CON-Z01-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Aug-24
system 24-Aug-24 6 35
Parking P-01 25-Sep-23 14-Jul-24 238 70
Site Preparation 25-Sep-23 11-Oct-23 15 280
GR-CON-Z01-1412 Demolition (Asphalt.Paving,etc.....) 25-Sep-23 28-Sep-23 4 17
GR-CON-Z01-1413 Excavation And Disposal 30-Sep-23 04-Oct-23 5 163
GR-CON-Z01-1414 Prepretion And Compaction 01-Oct-23 04-Oct-23 4 280
GR-CON-Z01-1415 Backfilling 05-Oct-23 11-Oct-23 6 280
Curbstone and Paving 05-Oct-23 27-Nov-23 46 253
GR-CON-Z01-1416 Excavation Curbstone 05-Oct-23 10-Oct-23 5 245
GR-CON-Z01-1417 Plain Concrete 11-Oct-23 17-Oct-23 6 253
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1418 Installation Curbstone 18-Oct-23 28-Oct-23 9 253


GR-CON-Z01-1419 Casting Concrete (Mortar haunch) 29-Oct-23 01-Nov-23 4 253
GR-CON-Z01-1420 Backfilling (sand / Sub base) 02-Nov-23 12-Nov-23 9 253
GR-CON-Z01-1421 Installation of Paving 13-Nov-23 27-Nov-23 13 253
Landscape Works 11-Oct-23 02-Jul-24 214 70
GR-CON-Z01-1422 Excavation (Tree Pit ) 11-Oct-23 16-Oct-23 5 245
GR-CON-Z01-1423 Aggregate Drainage layer 17-Oct-23 23-Oct-23 6 245
GR-CON-Z01-1424 Installation Geotextile 24-Oct-23 28-Oct-23 4 245
GR-CON-Z01-1425 Backfilling (Soil max for tree) 29-Oct-23 04-Nov-23 6 245
GR-CON-Z01-1426 Installation of Trees 08-Jun-24 10-Jun-24 3 70
GR-CON-Z01-6136 Installation of Shrubs 11-Jun-24 13-Jun-24 3 70
GR-CON-Z01-6156 Installation of Ground Covers 15-Jun-24 17-Jun-24 3 70
GR-CON-Z01-6166 Installation of Succulents 18-Jun-24 25-Jun-24 3 70
GR-CON-Z01-6176 Installation of Grass 26-Jun-24 29-Jun-24 3 70
GR-CON-Z01-1427 Backfilling (Mulch) 30-Jun-24 02-Jul-24 3 70
Site Furnishing 03-Jul-24 14-Jul-24 10 70
GR-CON-Z01-1438 Tree Grate 03-Jul-24 08-Jul-24 5 70
GR-CON-Z01-1439 Wheel stoppers 09-Jul-24 14-Jul-24 5 70
Irrigation Works 05-Oct-23 14-Jul-24 229 70
GR-CON-Z01-1430 Excavation Pipe Irrigation 05-Oct-23 10-Oct-23 5 163
GR-CON-Z01-1431 Sand Bedding 11-Oct-23 14-Oct-23 3 163
GR-CON-Z01-1432 HDPE Pipe Installations and fittings and conduit for cable 15-Oct-23 31-Oct-23 15 163
GR-CON-Z01-1434 Test pressure 01-Nov-23 06-Nov-23 5 163
GR-CON-Z01-1433 Installation of Valves and Accessories 07-Nov-23 11-Nov-23 4 163
GR-CON-Z01-1435 Back filling (sand / Subbase ) 12-Nov-23 18-Nov-23 6 163
GR-CON-Z01-1436 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-Nov-23 25-Nov-23 6 247
GR-CON-Z01-1437 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Jul-24
system 14-Jul-24 8 70
Parking P-11 27-Sep-23 14-Jul-24 236 70
Site Preparation 27-Sep-23 03-Oct-23 6 287
GR-CON-Z01-1029 Backfilling 27-Sep-23 03-Oct-23 6 287
GR-CON-Z01-1027 Excavation And Disposal 28-Sep-23 03-Oct-23 5 164
GR-CON-Z01-1026 Demolition (Asphalt.Paving,etc.....) 30-Sep-23 03-Oct-23 4 17
GR-CON-Z01-1028 Prepretion And Compaction 30-Sep-23 03-Oct-23 4 287
Curbstone and Paving 04-Oct-23 26-Nov-23 46 254
GR-CON-Z01-1030 Excavation Curbstone 04-Oct-23 09-Oct-23 5 246
GR-CON-Z01-1031 Plain Concrete 10-Oct-23 16-Oct-23 6 254
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1032 Installation Curbstone 17-Oct-23 26-Oct-23 9 254


GR-CON-Z01-1033 Casting Concrete (Mortar haunch) 28-Oct-23 31-Oct-23 4 254
GR-CON-Z01-1034 Backfilling (sand / Sub base) 01-Nov-23 11-Nov-23 9 254
GR-CON-Z01-1035 Installation of Paving 12-Nov-23 26-Nov-23 13 254
Landscape Works 10-Oct-23 02-Jul-24 215 70
GR-CON-Z01-1036 Excavation (Tree Pit ) 10-Oct-23 15-Oct-23 5 246
GR-CON-Z01-1037 Aggregate Drainage layer 16-Oct-23 22-Oct-23 6 246
GR-CON-Z01-1038 Installation Geotextile 23-Oct-23 26-Oct-23 4 246
GR-CON-Z01-1039 Backfilling (Soil max for tree) 28-Oct-23 02-Nov-23 6 246
GR-CON-Z01-1040 Installation of Trees 08-Jun-24 10-Jun-24 3 70
GR-CON-Z01-6616 Installation of Shrubs 11-Jun-24 13-Jun-24 3 70
GR-CON-Z01-6626 Installation of Ground Covers 15-Jun-24 17-Jun-24 3 70
GR-CON-Z01-6636 Installation of Succulents 18-Jun-24 25-Jun-24 3 70
GR-CON-Z01-6646 Installation of Grass 26-Jun-24 29-Jun-24 3 70
GR-CON-Z01-1041 Backfilling (Mulch) 30-Jun-24 02-Jul-24 3 70
Site Furnishing 03-Jul-24 14-Jul-24 10 70
GR-CON-Z01-1052 Tree Grate 03-Jul-24 08-Jul-24 5 70
GR-CON-Z01-1053 Wheel stoppers 09-Jul-24 14-Jul-24 5 70
Irrigation Works 04-Oct-23 14-Jul-24 230 70
GR-CON-Z01-1044 Excavation Pipe Irrigation 04-Oct-23 09-Oct-23 5 164
GR-CON-Z01-1045 Sand Bedding 10-Oct-23 12-Oct-23 3 164
GR-CON-Z01-1046 HDPE Pipe Installations and fittings and conduit for cable 14-Oct-23 30-Oct-23 15 164
GR-CON-Z01-1048 Test pressure 31-Oct-23 05-Nov-23 5 164
GR-CON-Z01-1047 Installation of Valves and Accessories 06-Nov-23 09-Nov-23 4 164
GR-CON-Z01-1049 Back filling (sand / Subbase ) 11-Nov-23 16-Nov-23 6 164
GR-CON-Z01-1050 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Nov-23 23-Nov-23 6 248
GR-CON-Z01-1051 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Jul-24
system 14-Jul-24 8 70
Parking P-12 02-Oct-23 14-Jul-24 232 70
Site Preparation 02-Oct-23 08-Oct-23 6 283
GR-CON-Z01-1085 Backfilling 02-Oct-23 08-Oct-23 6 283
GR-CON-Z01-1083 Excavation And Disposal 03-Oct-23 08-Oct-23 5 160
GR-CON-Z01-1082 Demolition (Asphalt.Paving,etc.....) 04-Oct-23 08-Oct-23 4 17
GR-CON-Z01-1084 Prepretion And Compaction 04-Oct-23 08-Oct-23 4 283
Curbstone and Paving 09-Oct-23 30-Nov-23 46 250
GR-CON-Z01-1086 Excavation Curbstone 09-Oct-23 14-Oct-23 5 242
GR-CON-Z01-1087 Plain Concrete 15-Oct-23 21-Oct-23 6 250
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1088 Installation Curbstone 22-Oct-23 31-Oct-23 9 250


GR-CON-Z01-1089 Casting Concrete (Mortar haunch) 01-Nov-23 05-Nov-23 4 250
GR-CON-Z01-1090 Backfilling (sand / Sub base) 06-Nov-23 15-Nov-23 9 250
GR-CON-Z01-1091 Installation of Paving 16-Nov-23 30-Nov-23 13 250
Landscape Works 15-Oct-23 02-Jul-24 211 70
GR-CON-Z01-1092 Excavation (Tree Pit ) 15-Oct-23 19-Oct-23 5 242
GR-CON-Z01-1093 Aggregate Drainage layer 21-Oct-23 26-Oct-23 6 242
GR-CON-Z01-1094 Installation Geotextile 28-Oct-23 31-Oct-23 4 242
GR-CON-Z01-1095 Backfilling (Soil max for tree) 01-Nov-23 07-Nov-23 6 242
GR-CON-Z01-1096 Installation of Trees 08-Jun-24 10-Jun-24 3 70
GR-CON-Z01-6656 Installation of Shrubs 11-Jun-24 13-Jun-24 3 70
GR-CON-Z01-6666 Installation of Ground Covers 15-Jun-24 17-Jun-24 3 70
GR-CON-Z01-6676 Installation of Succulents 18-Jun-24 25-Jun-24 3 70
GR-CON-Z01-6686 Installation of Grass 26-Jun-24 29-Jun-24 3 70
GR-CON-Z01-1097 Backfilling (Mulch) 30-Jun-24 02-Jul-24 3 70
Site Furnishing 03-Jul-24 14-Jul-24 10 70
GR-CON-Z01-1108 Tree Grate 03-Jul-24 08-Jul-24 5 70
GR-CON-Z01-1109 Wheel stoppers 09-Jul-24 14-Jul-24 5 70
Irrigation Works 09-Oct-23 14-Jul-24 226 70
GR-CON-Z01-1100 Excavation Pipe Irrigation 09-Oct-23 14-Oct-23 5 160
GR-CON-Z01-1101 Sand Bedding 15-Oct-23 17-Oct-23 3 160
GR-CON-Z01-1102 HDPE Pipe Installations and fittings and conduit for cable 18-Oct-23 04-Nov-23 15 160
GR-CON-Z01-1104 Test pressure 05-Nov-23 09-Nov-23 5 160
GR-CON-Z01-1103 Installation of Valves and Accessories 11-Nov-23 14-Nov-23 4 160
GR-CON-Z01-1105 Back filling (sand / Subbase ) 15-Nov-23 21-Nov-23 6 160
GR-CON-Z01-1106 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 22-Nov-23 28-Nov-23 6 244
GR-CON-Z01-1107 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Jul-24
system 14-Jul-24 8 70
Parking P-02 07-Oct-23 14-Jul-24 228 70
Site Preparation 07-Oct-23 12-Oct-23 6 279
GR-CON-Z01-1057 Backfilling 07-Oct-23 12-Oct-23 6 279
GR-CON-Z01-1055 Excavation And Disposal 08-Oct-23 12-Oct-23 5 156
GR-CON-Z01-1054 Demolition (Asphalt.Paving,etc.....) 09-Oct-23 12-Oct-23 4 17
GR-CON-Z01-1056 Prepretion And Compaction 09-Oct-23 12-Oct-23 4 279
Curbstone and Paving 14-Oct-23 05-Dec-23 46 246
GR-CON-Z01-1058 Excavation Curbstone 14-Oct-23 18-Oct-23 5 238
GR-CON-Z01-1059 Plain Concrete 19-Oct-23 25-Oct-23 6 246
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1060 Installation Curbstone 26-Oct-23 05-Nov-23 9 246


GR-CON-Z01-1061 Casting Concrete (Mortar haunch) 06-Nov-23 09-Nov-23 4 246
GR-CON-Z01-1062 Backfilling (sand / Sub base) 11-Nov-23 20-Nov-23 9 246
GR-CON-Z01-1063 Installation of Paving 21-Nov-23 05-Dec-23 13 246
Landscape Works 19-Oct-23 02-Jul-24 207 70
GR-CON-Z01-1064 Excavation (Tree Pit ) 19-Oct-23 24-Oct-23 5 238
GR-CON-Z01-1065 Aggregate Drainage layer 25-Oct-23 31-Oct-23 6 238
GR-CON-Z01-1066 Installation Geotextile 01-Nov-23 05-Nov-23 4 238
GR-CON-Z01-1067 Backfilling (Soil max for tree) 06-Nov-23 12-Nov-23 6 238
GR-CON-Z01-1068 Installation of Trees 08-Jun-24 10-Jun-24 3 70
GR-CON-Z01-6696 Installation of Shrubs 11-Jun-24 13-Jun-24 3 70
GR-CON-Z01-6706 Installation of Ground Covers 15-Jun-24 17-Jun-24 3 70
GR-CON-Z01-6716 Installation of Succulents 18-Jun-24 25-Jun-24 3 70
GR-CON-Z01-6726 Installation of Grass 26-Jun-24 29-Jun-24 3 70
GR-CON-Z01-1069 Backfilling (Mulch) 30-Jun-24 02-Jul-24 3 70
Site Furnishing 03-Jul-24 14-Jul-24 10 70
GR-CON-Z01-1080 Tree Grate 03-Jul-24 08-Jul-24 5 70
GR-CON-Z01-1081 Wheel stoppers 09-Jul-24 14-Jul-24 5 70
Irrigation Works 14-Oct-23 14-Jul-24 222 70
GR-CON-Z01-1072 Excavation Pipe Irrigation 14-Oct-23 18-Oct-23 5 156
GR-CON-Z01-1073 Sand Bedding 19-Oct-23 22-Oct-23 3 156
GR-CON-Z01-1074 HDPE Pipe Installations and fittings and conduit for cable 23-Oct-23 08-Nov-23 15 156
GR-CON-Z01-1076 Test pressure 09-Nov-23 14-Nov-23 5 156
GR-CON-Z01-1075 Installation of Valves and Accessories 15-Nov-23 19-Nov-23 4 156
GR-CON-Z01-1077 Back filling (sand / Subbase ) 20-Nov-23 26-Nov-23 6 156
GR-CON-Z01-1078 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-Nov-23 03-Dec-23 6 240
GR-CON-Z01-1079 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Jul-24
system 14-Jul-24 8 70
Street SS-02 14-Oct-23 10-Sep-24 272 20
Site Preparation 14-Oct-23 19-Nov-23 32 242
GR-CON-Z01-1440 Demolition (Asphalt.Paving,etc.....) 14-Oct-23 19-Oct-23 6 17
GR-CON-Z01-1441 Excavation And Disposal 21-Oct-23 29-Oct-23 8 120
GR-CON-Z01-1442 Prepretion And Compaction 30-Oct-23 08-Nov-23 9 242
GR-CON-Z01-1443 Backfilling 09-Nov-23 19-Nov-23 9 242
Curbstone and Paving 30-Oct-23 20-Jan-24 71 207
GR-CON-Z01-1444 Excavation Curbstone 30-Oct-23 07-Nov-23 8 160
GR-CON-Z01-1445 Plain Concrete 08-Nov-23 18-Nov-23 9 207
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1446 Installation Curbstone 19-Nov-23 04-Dec-23 14 207


GR-CON-Z01-1447 Casting Concrete (Mortar haunch) 05-Dec-23 11-Dec-23 6 207
GR-CON-Z01-1448 Backfilling (sand / Sub base) 12-Dec-23 27-Dec-23 14 207
GR-CON-Z01-1449 Installation of Paving 28-Dec-23 20-Jan-24 20 207
Landscape Works 08-Nov-23 04-Aug-24 218 20
GR-CON-Z01-1450 Excavation (Tree Pit ) 08-Nov-23 16-Nov-23 8 160
GR-CON-Z01-1451 Aggregate Drainage layer 18-Nov-23 27-Nov-23 9 160
GR-CON-Z01-1452 Installation Geotextile 28-Nov-23 04-Dec-23 6 160
GR-CON-Z01-1453 Backfilling (Soil max for tree) 05-Dec-23 14-Dec-23 9 160
GR-CON-Z01-1454 Installation of Trees 08-Jun-24 10-Jun-24 3 20
GR-CON-Z01-6256 Installation of Shrubs 11-Jun-24 13-Jun-24 3 20
GR-CON-Z01-6266 Installation of Succulents 15-Jun-24 17-Jun-24 3 20
GR-CON-Z01-6276 Installation of Ground Covers 18-Jun-24 25-Jun-24 3 20
GR-CON-Z01-6296 Installation of Grass 26-Jun-24 29-Jun-24 3 20
GR-CON-Z01-1455 Backfilling (Mulch) 30-Jun-24 04-Jul-24 5 20
GR-CON-Z01-1456 Natural Boulders Installation 06-Jul-24 11-Jul-24 6 20
GR-CON-Z01-1457 Retaining walls . Steps, forming risers, treads and edges with finishes
13-Jul-24 04-Aug-24 20 20
Site Furnishing 05-Aug-24 10-Sep-24 32 20
GR-CON-Z01-1466 Garden planter box 05-Aug-24 13-Aug-24 8 20
GR-CON-Z01-1467 Wheel stoppers 14-Aug-24 22-Aug-24 8 20
GR-CON-Z01-1468 Steel Lattice 24-Aug-24 01-Sep-24 8 20
GR-CON-Z01-1469 Handrail 02-Sep-24 10-Sep-24 8 20
Storm Piping Works 01-Sep-24 10-Sep-24 9 20
GR-CON-Z01-1470 Installation of DI grating covers 01-Sep-24 10-Sep-24 9 20
Irrigation Works 30-Oct-23 31-Jan-24 81 188
GR-CON-Z01-1458 Excavation Pipe Irrigation 30-Oct-23 07-Nov-23 8 120
GR-CON-Z01-1459 Sand Bedding 08-Nov-23 14-Nov-23 6 120
GR-CON-Z01-1460 HDPE Pipe Installations and fittings and conduit for cable 15-Nov-23 11-Dec-23 23 120
GR-CON-Z01-1462 Test pressure 12-Dec-23 20-Dec-23 8 120
GR-CON-Z01-1461 Installation of Valves and Accessories 21-Dec-23 27-Dec-23 6 120
GR-CON-Z01-1463 Back filling (sand / Subbase ) 28-Dec-23 07-Jan-24 9 120
GR-CON-Z01-1464 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-Jan-24 17-Jan-24 9 188
GR-CON-Z01-1465 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Jan-24
system 31-Jan-24 12 188
Electrical Works 08-Nov-23 10-Sep-24 250 20
GR-CON-Z01-1471 Excavation And Disposal 08-Nov-23 16-Nov-23 8 228
GR-CON-Z01-1472 Sand Bedding 18-Nov-23 23-Nov-23 6 228
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1473 laying cables 25-Nov-23 30-Nov-23 6 228


GR-CON-Z01-1474 Backfilling (sand / Sub base) 02-Dec-23 10-Dec-23 8 228
GR-CON-Z01-1475 Control Panel / Distribution Panel Installation 11-Dec-23 17-Dec-23 6 228
GR-CON-Z01-1476 Road Crossing Ducts 02-Sep-24 10-Sep-24 8 20
Street SS-27 21-Oct-23 05-Oct-24 286 0
Site Preparation 21-Oct-23 07-Dec-23 42 238
GR-CON-Z01-1110 Demolition (Asphalt.Paving,etc.....) 21-Oct-23 29-Oct-23 8 17
GR-CON-Z01-1111 Excavation And Disposal 30-Oct-23 09-Nov-23 10 76
GR-CON-Z01-1112 Prepretion And Compaction 11-Nov-23 23-Nov-23 12 238
GR-CON-Z01-1113 Backfilling 25-Nov-23 07-Dec-23 12 238
Curbstone and Paving 11-Nov-23 22-Feb-24 90 178
GR-CON-Z01-1114 Excavation Curbstone 11-Nov-23 21-Nov-23 10 76
GR-CON-Z01-1115 Plain Concrete 22-Nov-23 05-Dec-23 12 178
GR-CON-Z01-1116 Installation Curbstone 06-Dec-23 26-Dec-23 18 178
GR-CON-Z01-1117 Casting Concrete (Mortar haunch) 27-Dec-23 04-Jan-24 8 178
GR-CON-Z01-1118 Backfilling (sand / Sub base) 06-Jan-24 25-Jan-24 18 178
GR-CON-Z01-1119 Installation of Paving 27-Jan-24 22-Feb-24 24 178
Landscape Works 22-Nov-23 18-Aug-24 218 0
GR-CON-Z01-1120 Excavation (Tree Pit ) 22-Nov-23 03-Dec-23 10 76
GR-CON-Z01-1121 Aggregate Drainage layer 04-Dec-23 17-Dec-23 12 76
GR-CON-Z01-1122 Installation Geotextile 18-Dec-23 26-Dec-23 8 76
GR-CON-Z01-1123 Backfilling (Soil max for tree) 27-Dec-23 09-Jan-24 12 118
GR-CON-Z01-1124 Installation of Trees 08-Jun-24 11-Jun-24 4 0
GR-CON-Z01-9176 Installation of Shrubs 12-Jun-24 16-Jun-24 4 0
GR-CON-Z01-9186 Installation of Succulents 17-Jun-24 25-Jun-24 4 0
GR-CON-Z01-9196 Installation of Ground Covers 26-Jun-24 30-Jun-24 4 0
GR-CON-Z01-9206 Installation of Grass 01-Jul-24 04-Jul-24 4 0
GR-CON-Z01-1125 Backfilling (Mulch) 06-Jul-24 11-Jul-24 6 0
GR-CON-Z01-1126 Natural Boulders Installation 13-Jul-24 21-Jul-24 8 0
GR-CON-Z01-1127 Retaining walls . Steps, forming risers, treads and edges with finishes
22-Jul-24 18-Aug-24 24 0
Site Furnishing 19-Aug-24 05-Oct-24 40 0
GR-CON-Z01-1136 Garden planter box 19-Aug-24 29-Aug-24 10 0
GR-CON-Z01-1137 Wheel stoppers 31-Aug-24 10-Sep-24 10 0
GR-CON-Z01-1138 Steel Lattice 11-Sep-24 22-Sep-24 10 0
GR-CON-Z01-1139 Handrail 24-Sep-24 05-Oct-24 10 0
Storm Piping Works 21-Sep-24 05-Oct-24 12 0
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1140 Installation of DI grating covers 21-Sep-24 05-Oct-24 12 0


Irrigation Works 11-Nov-23 07-Apr-24 122 134
GR-CON-Z01-1128 Excavation Pipe Irrigation 11-Nov-23 21-Nov-23 10 98
GR-CON-Z01-1129 Sand Bedding 22-Nov-23 30-Nov-23 8 98
GR-CON-Z01-1130 HDPE Pipe Installations and fittings and conduit for cable 27-Dec-23 23-Jan-24 24 76
GR-CON-Z01-1132 Test pressure 24-Jan-24 04-Feb-24 10 76
GR-CON-Z01-1131 Installation of Valves and Accessories 05-Feb-24 13-Feb-24 8 76
GR-CON-Z01-1133 Back filling (sand / Subbase ) 14-Feb-24 27-Feb-24 12 76
GR-CON-Z01-1134 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-Feb-24 12-Mar-24 12 134
GR-CON-Z01-1135 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Mar-24
system 07-Apr-24 16 134
Electrical Works 22-Nov-23 05-Oct-24 258 0
GR-CON-Z01-1141 Excavation And Disposal 22-Nov-23 03-Dec-23 10 209
GR-CON-Z01-1142 Sand Bedding 04-Dec-23 12-Dec-23 8 209
GR-CON-Z01-1143 laying cables 13-Dec-23 21-Dec-23 8 209
GR-CON-Z01-1144 Backfilling (sand / Sub base) 23-Dec-23 02-Jan-24 10 209
GR-CON-Z01-1145 Control Panel / Distribution Panel Installation 03-Jan-24 11-Jan-24 8 209
GR-CON-Z01-1146 Road Crossing Ducts 30-Sep-24 05-Oct-24 5 0
Street SS-71 30-Oct-23 29-Aug-24 248 30
Site Preparation 30-Oct-23 14-Dec-23 40 238
GR-CON-Z01-1147 Demolition (Asphalt.Paving,etc.....) 30-Oct-23 02-Nov-23 4 17
GR-CON-Z01-1148 Excavation And Disposal 04-Nov-23 08-Nov-23 5 132
GR-CON-Z01-1149 Prepretion And Compaction 09-Nov-23 15-Nov-23 6 257
GR-CON-Z01-1150 Backfilling 09-Dec-23 14-Dec-23 6 238
Curbstone and Paving 09-Nov-23 08-Feb-24 79 190
GR-CON-Z01-1151 Excavation Curbstone 09-Nov-23 14-Nov-23 5 179
GR-CON-Z01-1152 Plain Concrete 06-Dec-23 17-Dec-23 10 190
GR-CON-Z01-1153 Installation Curbstone 18-Dec-23 09-Jan-24 20 190
GR-CON-Z01-1154 Casting Concrete (Mortar haunch) 10-Jan-24 14-Jan-24 4 190
GR-CON-Z01-1155 Backfilling (sand / Sub base) 15-Jan-24 24-Jan-24 9 190
GR-CON-Z01-1156 Installation of Paving 25-Jan-24 08-Feb-24 13 190
Landscape Works 04-Dec-23 07-Aug-24 199 30
GR-CON-Z01-1157 Excavation (Tree Pit ) 04-Dec-23 09-Dec-23 5 163
GR-CON-Z01-1158 Aggregate Drainage layer 10-Dec-23 16-Dec-23 6 163
GR-CON-Z01-1159 Installation Geotextile 17-Dec-23 20-Dec-23 4 163
GR-CON-Z01-1160 Backfilling (Soil max for tree) 21-Dec-23 27-Dec-23 6 163
GR-CON-Z01-1161 Installation of Trees 12-Jun-24 17-Jun-24 5 30
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-9136 Installation of Shrubs 18-Jun-24 27-Jun-24 5 30


GR-CON-Z01-9146 Installation of Succulents 29-Jun-24 03-Jul-24 5 30
GR-CON-Z01-9156 Installation of Ground Covers 04-Jul-24 09-Jul-24 5 30
GR-CON-Z01-9166 Installation of Grass 10-Jul-24 15-Jul-24 5 30
GR-CON-Z01-1162 Backfilling (Mulch) 16-Jul-24 18-Jul-24 3 30
GR-CON-Z01-1163 Natural Boulders Installation 20-Jul-24 23-Jul-24 4 30
GR-CON-Z01-1164 Retaining walls . Steps, forming risers, treads and edges with finishes
24-Jul-24 07-Aug-24 13 30
Site Furnishing 08-Aug-24 29-Aug-24 19 30
GR-CON-Z01-1173 Garden planter box 08-Aug-24 13-Aug-24 5 30
GR-CON-Z01-1174 Wheel stoppers 14-Aug-24 19-Aug-24 5 30
GR-CON-Z01-1175 Steel Lattice 20-Aug-24 25-Aug-24 5 30
GR-CON-Z01-1176 Handrail 26-Aug-24 29-Aug-24 4 30
Storm Piping Works 24-Aug-24 29-Aug-24 6 30
GR-CON-Z01-1177 Installation of DI grating covers 24-Aug-24 29-Aug-24 6 30
Irrigation Works 09-Nov-23 25-Jan-24 67 196
GR-CON-Z01-1165 Excavation Pipe Irrigation 09-Nov-23 14-Nov-23 5 132
GR-CON-Z01-1166 Sand Bedding 02-Dec-23 05-Dec-23 4 118
GR-CON-Z01-1167 HDPE Pipe Installations and fittings and conduit for cable 06-Dec-23 23-Dec-23 15 118
GR-CON-Z01-1169 Test pressure 24-Dec-23 28-Dec-23 5 118
GR-CON-Z01-1168 Installation of Valves and Accessories 30-Dec-23 02-Jan-24 4 118
GR-CON-Z01-1170 Back filling (sand / Subbase ) 03-Jan-24 09-Jan-24 6 118
GR-CON-Z01-1171 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Jan-24 16-Jan-24 6 196
GR-CON-Z01-1172 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Jan-24
system 25-Jan-24 8 196
Electrical Works 04-Dec-23 29-Aug-24 218 30
GR-CON-Z01-1178 Excavation And Disposal 04-Dec-23 09-Dec-23 5 221
GR-CON-Z01-1179 Sand Bedding 10-Dec-23 13-Dec-23 4 221
GR-CON-Z01-1180 laying cables 14-Dec-23 18-Dec-23 4 221
GR-CON-Z01-1181 Backfilling (sand / Sub base) 19-Dec-23 24-Dec-23 5 221
GR-CON-Z01-1182 Control Panel / Distribution Panel Installation 25-Dec-23 28-Dec-23 4 221
GR-CON-Z01-1183 Road Crossing Ducts 25-Aug-24 29-Aug-24 5 30
Street SS-90 04-Nov-23 14-Aug-24 231 43
Site Preparation 04-Nov-23 27-Nov-23 21 253
GR-CON-Z01-1184 Demolition (Asphalt.Paving,etc.....) 04-Nov-23 07-Nov-23 4 17
GR-CON-Z01-1185 Excavation And Disposal 08-Nov-23 13-Nov-23 5 128
GR-CON-Z01-1186 Prepretion And Compaction 14-Nov-23 20-Nov-23 6 253
GR-CON-Z01-1187 Backfilling 21-Nov-23 27-Nov-23 6 253
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 14-Nov-23 06-Jan-24 46 219


GR-CON-Z01-1188 Excavation Curbstone 14-Nov-23 19-Nov-23 5 184
GR-CON-Z01-1189 Plain Concrete 20-Nov-23 26-Nov-23 6 219
GR-CON-Z01-1190 Installation Curbstone 27-Nov-23 06-Dec-23 9 219
GR-CON-Z01-1191 Casting Concrete (Mortar haunch) 07-Dec-23 11-Dec-23 4 219
GR-CON-Z01-1192 Backfilling (sand / Sub base) 12-Dec-23 21-Dec-23 9 219
GR-CON-Z01-1193 Installation of Paving 23-Dec-23 06-Jan-24 13 219
Landscape Works 20-Nov-23 22-Jul-24 197 43
GR-CON-Z01-1194 Excavation (Tree Pit ) 20-Nov-23 25-Nov-23 5 184
GR-CON-Z01-1195 Aggregate Drainage layer 26-Nov-23 02-Dec-23 6 184
GR-CON-Z01-1196 Installation Geotextile 03-Dec-23 06-Dec-23 4 184
GR-CON-Z01-1197 Backfilling (Soil max for tree) 07-Dec-23 13-Dec-23 6 184
GR-CON-Z01-1198 Installation of Trees 08-Jun-24 10-Jun-24 3 43
GR-CON-Z01-9216 Installation of Shrubs 11-Jun-24 13-Jun-24 3 43
GR-CON-Z01-9226 Installation of Succulents 15-Jun-24 17-Jun-24 3 43
GR-CON-Z01-9236 Installation of Ground Covers 18-Jun-24 25-Jun-24 3 43
GR-CON-Z01-9246 Installation of Grass 26-Jun-24 29-Jun-24 3 43
GR-CON-Z01-1199 Backfilling (Mulch) 30-Jun-24 02-Jul-24 3 43
GR-CON-Z01-1200 Natural Boulders Installation 03-Jul-24 07-Jul-24 4 43
GR-CON-Z01-1201 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Jul-24 22-Jul-24 13 43
Site Furnishing 23-Jul-24 14-Aug-24 20 43
GR-CON-Z01-1210 Garden planter box 23-Jul-24 28-Jul-24 5 43
GR-CON-Z01-1211 Wheel stoppers 29-Jul-24 03-Aug-24 5 43
GR-CON-Z01-1212 Steel Lattice 04-Aug-24 08-Aug-24 5 43
GR-CON-Z01-1213 Handrail 10-Aug-24 14-Aug-24 5 43
Storm Piping Works 08-Aug-24 14-Aug-24 6 43
GR-CON-Z01-1214 Installation of DI grating covers 08-Aug-24 14-Aug-24 6 43
Irrigation Works 14-Nov-23 14-Jan-24 53 206
GR-CON-Z01-1202 Excavation Pipe Irrigation 14-Nov-23 19-Nov-23 5 128
GR-CON-Z01-1203 Sand Bedding 20-Nov-23 23-Nov-23 4 128
GR-CON-Z01-1204 HDPE Pipe Installations and fittings and conduit for cable 25-Nov-23 11-Dec-23 15 128
GR-CON-Z01-1206 Test pressure 12-Dec-23 17-Dec-23 5 128
GR-CON-Z01-1205 Installation of Valves and Accessories 18-Dec-23 21-Dec-23 4 128
GR-CON-Z01-1207 Back filling (sand / Subbase ) 23-Dec-23 28-Dec-23 6 128
GR-CON-Z01-1208 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Dec-23 04-Jan-24 6 206
GR-CON-Z01-1209 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Jan-24
system 14-Jan-24 8 206
Activity ID Activity Name Start Finish Original Total Float
Duration

Electrical Works 20-Nov-23 14-Aug-24 217 43


GR-CON-Z01-1215 Excavation And Disposal 20-Nov-23 25-Nov-23 5 233
GR-CON-Z01-1216 Sand Bedding 26-Nov-23 29-Nov-23 4 233
GR-CON-Z01-1217 laying cables 30-Nov-23 04-Dec-23 4 233
GR-CON-Z01-1218 Backfilling (sand / Sub base) 05-Dec-23 10-Dec-23 5 233
GR-CON-Z01-1219 Control Panel / Distribution Panel Installation 11-Dec-23 14-Dec-23 4 233
GR-CON-Z01-1220 Road Crossing Ducts 10-Aug-24 14-Aug-24 5 43
Street SS-92 08-Nov-23 14-Aug-24 227 43
Site Preparation 08-Nov-23 02-Dec-23 21 249
GR-CON-Z01-1221 Demolition (Asphalt.Paving,etc.....) 08-Nov-23 12-Nov-23 4 17
GR-CON-Z01-1222 Excavation And Disposal 13-Nov-23 18-Nov-23 5 124
GR-CON-Z01-1223 Prepretion And Compaction 19-Nov-23 25-Nov-23 6 249
GR-CON-Z01-1224 Backfilling 26-Nov-23 02-Dec-23 6 249
Curbstone and Paving 19-Nov-23 10-Jan-24 46 215
GR-CON-Z01-1225 Excavation Curbstone 19-Nov-23 23-Nov-23 5 180
GR-CON-Z01-1226 Plain Concrete 25-Nov-23 30-Nov-23 6 215
GR-CON-Z01-1227 Installation Curbstone 02-Dec-23 11-Dec-23 9 215
GR-CON-Z01-1228 Casting Concrete (Mortar haunch) 12-Dec-23 16-Dec-23 4 215
GR-CON-Z01-1229 Backfilling (sand / Sub base) 17-Dec-23 26-Dec-23 9 215
GR-CON-Z01-1230 Installation of Paving 27-Dec-23 10-Jan-24 13 215
Landscape Works 25-Nov-23 22-Jul-24 193 43
GR-CON-Z01-1231 Excavation (Tree Pit ) 25-Nov-23 29-Nov-23 5 180
GR-CON-Z01-1232 Aggregate Drainage layer 30-Nov-23 06-Dec-23 6 180
GR-CON-Z01-1233 Installation Geotextile 07-Dec-23 11-Dec-23 4 180
GR-CON-Z01-1234 Backfilling (Soil max for tree) 12-Dec-23 18-Dec-23 6 180
GR-CON-Z01-1235 Installation of Trees 08-Jun-24 10-Jun-24 3 43
GR-CON-Z01-9256 Installation of Shrubs 11-Jun-24 13-Jun-24 3 43
GR-CON-Z01-9266 Installation of Succulents 15-Jun-24 17-Jun-24 3 43
GR-CON-Z01-9276 Installation of Ground Covers 18-Jun-24 25-Jun-24 3 43
GR-CON-Z01-9286 Installation of Grass 26-Jun-24 29-Jun-24 3 43
GR-CON-Z01-1236 Backfilling (Mulch) 30-Jun-24 02-Jul-24 3 43
GR-CON-Z01-1237 Natural Boulders Installation 03-Jul-24 07-Jul-24 4 43
GR-CON-Z01-1238 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Jul-24 22-Jul-24 13 43
Site Furnishing 23-Jul-24 14-Aug-24 20 43
GR-CON-Z01-1247 Garden planter box 23-Jul-24 28-Jul-24 5 43
GR-CON-Z01-1248 Wheel stoppers 29-Jul-24 03-Aug-24 5 43
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1249 Steel Lattice 04-Aug-24 08-Aug-24 5 43


GR-CON-Z01-1250 Handrail 10-Aug-24 14-Aug-24 5 43
Storm Piping Works 08-Aug-24 14-Aug-24 6 43
GR-CON-Z01-1251 Installation of DI grating covers 08-Aug-24 14-Aug-24 6 43
Irrigation Works 19-Nov-23 18-Jan-24 53 202
GR-CON-Z01-1239 Excavation Pipe Irrigation 19-Nov-23 23-Nov-23 5 124
GR-CON-Z01-1240 Sand Bedding 25-Nov-23 28-Nov-23 4 124
GR-CON-Z01-1241 HDPE Pipe Installations and fittings and conduit for cable 29-Nov-23 16-Dec-23 15 124
GR-CON-Z01-1243 Test pressure 17-Dec-23 21-Dec-23 5 124
GR-CON-Z01-1242 Installation of Valves and Accessories 23-Dec-23 26-Dec-23 4 124
GR-CON-Z01-1244 Back filling (sand / Subbase ) 27-Dec-23 02-Jan-24 6 124
GR-CON-Z01-1245 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Jan-24 09-Jan-24 6 202
GR-CON-Z01-1246 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Jan-24
system 18-Jan-24 8 202
Electrical Works 25-Nov-23 14-Aug-24 213 43
GR-CON-Z01-1252 Excavation And Disposal 25-Nov-23 29-Nov-23 5 229
GR-CON-Z01-1253 Sand Bedding 30-Nov-23 04-Dec-23 4 229
GR-CON-Z01-1254 laying cables 05-Dec-23 09-Dec-23 4 229
GR-CON-Z01-1255 Backfilling (sand / Sub base) 10-Dec-23 14-Dec-23 5 229
GR-CON-Z01-1256 Control Panel / Distribution Panel Installation 16-Dec-23 19-Dec-23 4 229
GR-CON-Z01-1257 Road Crossing Ducts 10-Aug-24 14-Aug-24 5 43
Street SS-93 13-Nov-23 14-Aug-24 223 43
Site Preparation 13-Nov-23 06-Dec-23 21 245
GR-CON-Z01-1258 Demolition (Asphalt.Paving,etc.....) 13-Nov-23 16-Nov-23 4 17
GR-CON-Z01-1259 Excavation And Disposal 18-Nov-23 22-Nov-23 5 120
GR-CON-Z01-1260 Prepretion And Compaction 23-Nov-23 29-Nov-23 6 245
GR-CON-Z01-1261 Backfilling 30-Nov-23 06-Dec-23 6 245
Curbstone and Paving 23-Nov-23 15-Jan-24 46 211
GR-CON-Z01-1262 Excavation Curbstone 23-Nov-23 28-Nov-23 5 176
GR-CON-Z01-1263 Plain Concrete 29-Nov-23 05-Dec-23 6 211
GR-CON-Z01-1264 Installation Curbstone 06-Dec-23 16-Dec-23 9 211
GR-CON-Z01-1265 Casting Concrete (Mortar haunch) 17-Dec-23 20-Dec-23 4 211
GR-CON-Z01-1266 Backfilling (sand / Sub base) 21-Dec-23 31-Dec-23 9 211
GR-CON-Z01-1267 Installation of Paving 01-Jan-24 15-Jan-24 13 211
Landscape Works 29-Nov-23 22-Jul-24 189 43
GR-CON-Z01-1268 Excavation (Tree Pit ) 29-Nov-23 04-Dec-23 5 176
GR-CON-Z01-1269 Aggregate Drainage layer 05-Dec-23 11-Dec-23 6 176
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1270 Installation Geotextile 12-Dec-23 16-Dec-23 4 176


GR-CON-Z01-1271 Backfilling (Soil max for tree) 17-Dec-23 23-Dec-23 6 176
GR-CON-Z01-1272 Installation of Trees 08-Jun-24 10-Jun-24 3 43
GR-CON-Z01-9296 Installation of Shrubs 11-Jun-24 13-Jun-24 3 43
GR-CON-Z01-9306 Installation of Succulents 15-Jun-24 17-Jun-24 3 43
GR-CON-Z01-9316 Installation of Ground Covers 18-Jun-24 25-Jun-24 3 43
GR-CON-Z01-9326 Installation of Grass 26-Jun-24 29-Jun-24 3 43
GR-CON-Z01-1273 Backfilling (Mulch) 30-Jun-24 02-Jul-24 3 43
GR-CON-Z01-1274 Natural Boulders Installation 03-Jul-24 07-Jul-24 4 43
GR-CON-Z01-1275 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Jul-24 22-Jul-24 13 43
Site Furnishing 23-Jul-24 14-Aug-24 20 43
GR-CON-Z01-1284 Garden planter box 23-Jul-24 28-Jul-24 5 43
GR-CON-Z01-1285 Wheel stoppers 29-Jul-24 03-Aug-24 5 43
GR-CON-Z01-1286 Steel Lattice 04-Aug-24 08-Aug-24 5 43
GR-CON-Z01-1287 Handrail 10-Aug-24 14-Aug-24 5 43
Storm Piping Works 08-Aug-24 14-Aug-24 6 43
GR-CON-Z01-1288 Installation of DI grating covers 08-Aug-24 14-Aug-24 6 43
Irrigation Works 23-Nov-23 23-Jan-24 53 198
GR-CON-Z01-1276 Excavation Pipe Irrigation 23-Nov-23 28-Nov-23 5 120
GR-CON-Z01-1277 Sand Bedding 29-Nov-23 03-Dec-23 4 120
GR-CON-Z01-1278 HDPE Pipe Installations and fittings and conduit for cable 04-Dec-23 20-Dec-23 15 120
GR-CON-Z01-1280 Test pressure 21-Dec-23 26-Dec-23 5 120
GR-CON-Z01-1279 Installation of Valves and Accessories 27-Dec-23 31-Dec-23 4 120
GR-CON-Z01-1281 Back filling (sand / Subbase ) 01-Jan-24 07-Jan-24 6 120
GR-CON-Z01-1282 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-Jan-24 14-Jan-24 6 198
GR-CON-Z01-1283 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
15-Jan-24
system 23-Jan-24 8 198
Electrical Works 29-Nov-23 14-Aug-24 209 43
GR-CON-Z01-1289 Excavation And Disposal 29-Nov-23 04-Dec-23 5 225
GR-CON-Z01-1290 Sand Bedding 05-Dec-23 09-Dec-23 4 225
GR-CON-Z01-1291 laying cables 10-Dec-23 13-Dec-23 4 225
GR-CON-Z01-1292 Backfilling (sand / Sub base) 14-Dec-23 19-Dec-23 5 225
GR-CON-Z01-1293 Control Panel / Distribution Panel Installation 20-Dec-23 24-Dec-23 4 225
GR-CON-Z01-1294 Road Crossing Ducts 10-Aug-24 14-Aug-24 5 43
Street SS-94 18-Nov-23 14-Aug-24 219 43
Site Preparation 18-Nov-23 11-Dec-23 21 241
GR-CON-Z01-1295 Demolition (Asphalt.Paving,etc.....) 18-Nov-23 21-Nov-23 4 17
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1296 Excavation And Disposal 22-Nov-23 27-Nov-23 5 116


GR-CON-Z01-1297 Prepretion And Compaction 28-Nov-23 04-Dec-23 6 241
GR-CON-Z01-1298 Backfilling 05-Dec-23 11-Dec-23 6 241
Curbstone and Paving 28-Nov-23 20-Jan-24 46 207
GR-CON-Z01-1299 Excavation Curbstone 28-Nov-23 03-Dec-23 5 172
GR-CON-Z01-1300 Plain Concrete 04-Dec-23 10-Dec-23 6 207
GR-CON-Z01-1301 Installation Curbstone 11-Dec-23 20-Dec-23 9 207
GR-CON-Z01-1302 Casting Concrete (Mortar haunch) 21-Dec-23 25-Dec-23 4 207
GR-CON-Z01-1303 Backfilling (sand / Sub base) 26-Dec-23 04-Jan-24 9 207
GR-CON-Z01-1304 Installation of Paving 06-Jan-24 20-Jan-24 13 207
Landscape Works 04-Dec-23 22-Jul-24 185 43
GR-CON-Z01-1305 Excavation (Tree Pit ) 04-Dec-23 09-Dec-23 5 172
GR-CON-Z01-1306 Aggregate Drainage layer 10-Dec-23 16-Dec-23 6 172
GR-CON-Z01-1307 Installation Geotextile 17-Dec-23 20-Dec-23 4 172
GR-CON-Z01-1308 Backfilling (Soil max for tree) 21-Dec-23 27-Dec-23 6 172
GR-CON-Z01-1309 Installation of Trees 08-Jun-24 10-Jun-24 3 43
GR-CON-Z01-9336 Installation of Shrubs 11-Jun-24 13-Jun-24 3 43
GR-CON-Z01-9346 Installation of Succulents 15-Jun-24 17-Jun-24 3 43
GR-CON-Z01-9356 Installation of Ground Covers 18-Jun-24 25-Jun-24 3 43
GR-CON-Z01-9366 Installation of Grass 26-Jun-24 29-Jun-24 3 43
GR-CON-Z01-1310 Backfilling (Mulch) 30-Jun-24 02-Jul-24 3 43
GR-CON-Z01-1311 Natural Boulders Installation 03-Jul-24 07-Jul-24 4 43
GR-CON-Z01-1312 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Jul-24 22-Jul-24 13 43
Site Furnishing 23-Jul-24 14-Aug-24 20 43
GR-CON-Z01-1321 Garden planter box 23-Jul-24 28-Jul-24 5 43
GR-CON-Z01-1322 Wheel stoppers 29-Jul-24 03-Aug-24 5 43
GR-CON-Z01-1323 Steel Lattice 04-Aug-24 08-Aug-24 5 43
GR-CON-Z01-1324 Handrail 10-Aug-24 14-Aug-24 5 43
Storm Piping Works 08-Aug-24 14-Aug-24 6 43
GR-CON-Z01-1325 Installation of DI grating covers 08-Aug-24 14-Aug-24 6 43
Irrigation Works 28-Nov-23 28-Jan-24 53 194
GR-CON-Z01-1313 Excavation Pipe Irrigation 28-Nov-23 03-Dec-23 5 116
GR-CON-Z01-1314 Sand Bedding 04-Dec-23 07-Dec-23 4 116
GR-CON-Z01-1315 HDPE Pipe Installations and fittings and conduit for cable 09-Dec-23 25-Dec-23 15 116
GR-CON-Z01-1317 Test pressure 26-Dec-23 31-Dec-23 5 116
GR-CON-Z01-1316 Installation of Valves and Accessories 01-Jan-24 04-Jan-24 4 116
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z01-1318 Back filling (sand / Subbase ) 06-Jan-24 11-Jan-24 6 116


GR-CON-Z01-1319 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Jan-24 18-Jan-24 6 194
GR-CON-Z01-1320 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
20-Jan-24
system 28-Jan-24 8 194
Electrical Works 04-Dec-23 14-Aug-24 205 43
GR-CON-Z01-1326 Excavation And Disposal 04-Dec-23 09-Dec-23 5 221
GR-CON-Z01-1327 Sand Bedding 10-Dec-23 13-Dec-23 4 221
GR-CON-Z01-1328 laying cables 14-Dec-23 18-Dec-23 4 221
GR-CON-Z01-1329 Backfilling (sand / Sub base) 19-Dec-23 24-Dec-23 5 221
GR-CON-Z01-1330 Control Panel / Distribution Panel Installation 25-Dec-23 28-Dec-23 4 221
GR-CON-Z01-1331 Road Crossing Ducts 10-Aug-24 14-Aug-24 5 43
School S-01 11-Dec-23 10-Aug-24 194 47
Site Preparation 11-Dec-23 21-Dec-23 9 232
GR-CON-Z01-1385 Excavation And Disposal 11-Dec-23 17-Dec-23 5 0
GR-CON-Z01-1386 Prepretion And Compaction 17-Dec-23 21-Dec-23 4 232
Curbstone and Paving 17-Dec-23 08-Feb-24 46 190
GR-CON-Z01-1388 Excavation Curbstone 17-Dec-23 23-Dec-23 5 159
GR-CON-Z01-1389 Plain Concrete 23-Dec-23 30-Dec-23 6 190
GR-CON-Z01-1390 Installation Curbstone 30-Dec-23 09-Jan-24 9 190
GR-CON-Z01-1391 Casting Concrete (Mortar haunch) 09-Jan-24 14-Jan-24 4 190
GR-CON-Z01-1392 Backfilling (sand / Sub base) 14-Jan-24 24-Jan-24 9 190
GR-CON-Z01-1393 Installation of Paving 24-Jan-24 08-Feb-24 13 190
Landscape Works 23-Dec-23 29-Jul-24 174 47
GR-CON-Z01-1394 Excavation (Tree Pit ) 23-Dec-23 28-Dec-23 5 159
GR-CON-Z01-1395 Aggregate Drainage layer 28-Dec-23 04-Jan-24 6 159
GR-CON-Z01-1396 Installation Geotextile 04-Jan-24 09-Jan-24 4 159
GR-CON-Z01-1397 Backfilling (Soil max for tree) 09-Jan-24 16-Jan-24 6 159
GR-CON-Z01-1398 Installation of Trees 08-Jun-24 10-Jun-24 3 47
GR-CON-Z01-1488 Installation of Shrubs 11-Jun-24 13-Jun-24 3 47
GR-CON-Z01-1498 Installation of Succulents 15-Jun-24 17-Jun-24 3 47
GR-CON-Z01-1428 Installation of Ground Covers 18-Jun-24 25-Jun-24 3 47
GR-CON-Z01-1478 Installation of Climbers 26-Jun-24 29-Jun-24 3 47
GR-CON-Z01-1508 Installation of Grass 30-Jun-24 02-Jul-24 3 47
GR-CON-Z01-5106 Installation of Lawns 03-Jul-24 06-Jul-24 3 47
GR-CON-Z01-1399 Backfilling (Mulch) 07-Jul-24 09-Jul-24 3 47
GR-CON-Z01-1400 Natural Boulders Installation 10-Jul-24 14-Jul-24 4 47
GR-CON-Z01-1401 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Jul-24 29-Jul-24 13 47
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Furnishing 30-Jul-24 10-Aug-24 10 47


GR-CON-Z01-1410 Garden planter box 30-Jul-24 04-Aug-24 5 47
GR-CON-Z01-1411 Wheel stoppers 05-Aug-24 10-Aug-24 5 47
Irrigation Works 17-Dec-23 10-Aug-24 189 47
GR-CON-Z01-1402 Excavation Pipe Irrigation 17-Dec-23 23-Dec-23 5 0
GR-CON-Z01-1403 Sand Bedding 23-Dec-23 26-Dec-23 3 0
GR-CON-Z01-1404 HDPE Pipe Installations and fittings and conduit for cable 26-Dec-23 13-Jan-24 15 0
GR-CON-Z01-1406 Test pressure 13-Jan-24 18-Jan-24 5 0
GR-CON-Z01-1405 Installation of Valves and Accessories 18-Jan-24 23-Jan-24 4 0
GR-CON-Z01-1407 Back filling (sand / Subbase ) 23-Jan-24 30-Jan-24 6 0
GR-CON-Z01-1408 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Jan-24 06-Feb-24 6 184
GR-CON-Z01-1409 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
01-Aug-24
system 10-Aug-24 8 47
Zone 05 16-Sep-23 20-Jul-24 250 89
Future Neighborhood Park FNP-08 16-Sep-23 31-Mar-24 165 174
Site Preparation 16-Sep-23 09-Oct-23 20 319
GR-CON-Z05-1000 Demolition (Asphalt.Paving,etc.....) 16-Sep-23 19-Sep-23 4 22
GR-CON-Z05-1001 Excavation And Disposal 20-Sep-23 27-Sep-23 6 172
GR-CON-Z05-1002 Prepretion And Compaction 28-Sep-23 02-Oct-23 4 319
GR-CON-Z05-1003 Backfilling 03-Oct-23 09-Oct-23 6 319
Curbstone and Paving 28-Sep-23 20-Nov-23 46 283
GR-CON-Z05-1004 Excavation Curbstone 28-Sep-23 03-Oct-23 5 242
GR-CON-Z05-1005 Plain Concrete 04-Oct-23 10-Oct-23 6 283
GR-CON-Z05-1006 Installation Curbstone 11-Oct-23 21-Oct-23 9 283
GR-CON-Z05-1007 Casting Concrete (Mortar haunch) 22-Oct-23 25-Oct-23 4 283
GR-CON-Z05-1008 Backfilling (sand / Sub base) 26-Oct-23 05-Nov-23 9 283
GR-CON-Z05-1009 Installation of Paving 06-Nov-23 20-Nov-23 13 283
Landscape Works 04-Oct-23 31-Mar-24 150 174
GR-CON-Z05-1010 Excavation (Tree Pit ) 04-Oct-23 09-Oct-23 5 242
GR-CON-Z05-1011 Aggregate Drainage layer 10-Oct-23 16-Oct-23 6 269
GR-CON-Z05-1012 Installation Geotextile 17-Oct-23 21-Oct-23 4 269
GR-CON-Z05-1013 Backfilling (Soil max for tree) 22-Oct-23 28-Oct-23 6 269
GR-CON-Z05-1014 Installation of Trees 15-Feb-24 18-Feb-24 2 174
GR-CON-Z05-1746 Installation of Shrubs 18-Feb-24 20-Feb-24 2 174
GR-CON-Z05-1756 Installation of Succulents 20-Feb-24 22-Feb-24 2 174
GR-CON-Z05-1766 Installation of Ground Covers 22-Feb-24 25-Feb-24 2 174
GR-CON-Z05-1776 Installation of Climbers 25-Feb-24 27-Feb-24 2 174
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z05-1786 Installation of Grass 27-Feb-24 29-Feb-24 2 174


GR-CON-Z05-1796 Installation of Lawns 29-Feb-24 03-Mar-24 2 174
GR-CON-Z05-1015 Backfilling (Mulch) 03-Mar-24 06-Mar-24 3 174
GR-CON-Z05-1016 Natural Boulders Installation 06-Mar-24 11-Mar-24 4 174
GR-CON-Z05-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
11-Mar-24 31-Mar-24 13 174
MUGA 10-Oct-23 31-Mar-24 145 174
GR-CON-Z05-1018 Excavation And Disposal 10-Oct-23 15-Oct-23 5 242
GR-CON-Z05-1019 Prepretion And Compaction 16-Oct-23 22-Oct-23 6 242
GR-CON-Z05-1020 polyethylene under footings ( fence and gates) 23-Oct-23 28-Oct-23 5 242
GR-CON-Z05-1021 Blinding concrete (flooring) 29-Oct-23 02-Nov-23 5 242
GR-CON-Z05-1022 Concrete Footings ( fence and gates) 04-Nov-23 18-Nov-23 13 242
GR-CON-Z05-1023 Tools Play Installation ( basketball / football ..) 02-Jan-24 20-Jan-24 15 203
GR-CON-Z05-1024 PaintAcrylic Play Surface 20-Jan-24 04-Feb-24 13 203
GR-CON-Z05-1025 Fence (high / low) / gates Installation 09-Mar-24 31-Mar-24 15 174
Irrigation Works 28-Sep-23 31-Mar-24 155 174
GR-CON-Z05-1026 Excavation Pipe Irrigation 28-Sep-23 03-Oct-23 5 172
GR-CON-Z05-1027 Sand Bedding 04-Oct-23 07-Oct-23 3 172
GR-CON-Z05-1028 HDPE Pipe Installations and fittings and conduit for cable 08-Oct-23 24-Oct-23 15 172
GR-CON-Z05-1030 Test pressure 25-Oct-23 30-Oct-23 5 172
GR-CON-Z05-1029 Installation of Valves and Accessories 31-Oct-23 04-Nov-23 4 172
GR-CON-Z05-1031 Back filling (sand / Subbase ) 05-Nov-23 11-Nov-23 6 172
GR-CON-Z05-1032 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 12-Nov-23 18-Nov-23 6 277
GR-CON-Z05-1033 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Mar-24
system 31-Mar-24 8 174
Mosque M-13 20-Sep-23 11-May-24 190 145
Site Preparation 20-Sep-23 12-Oct-23 19 294
GR-CON-Z05-1034 Demolition (Asphalt.Paving,etc.....) 20-Sep-23 25-Sep-23 4 122
GR-CON-Z05-1035 Excavation And Disposal 26-Sep-23 01-Oct-23 5 169
GR-CON-Z05-1036 Prepretion And Compaction 02-Oct-23 05-Oct-23 4 294
GR-CON-Z05-1037 Backfilling 07-Oct-23 12-Oct-23 6 294
Curbstone and Paving 14-Oct-23 07-Nov-23 22 294
GR-CON-Z05-1042 Backfilling (sand / Sub base) 14-Oct-23 23-Oct-23 9 294
GR-CON-Z05-1043 Installation of Paving 24-Oct-23 07-Nov-23 13 294
Landscape Works 02-Oct-23 11-May-24 181 145
GR-CON-Z05-1044 Excavation (Tree Pit ) 02-Oct-23 07-Oct-23 5 242
GR-CON-Z05-1045 Aggregate Drainage layer 08-Oct-23 14-Oct-23 6 242
GR-CON-Z05-1046 Installation Geotextile 15-Oct-23 19-Oct-23 5 242
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z05-1047 Backfilling (Soil max for tree) 21-Oct-23 25-Oct-23 5 242


GR-CON-Z05-1048 Installation of Trees 15-Feb-24 20-Feb-24 4 145
GR-CON-Z05-3546 Installation of Climbers 20-Feb-24 25-Feb-24 4 145
GR-CON-Z05-3556 Installation of Shrubs 25-Feb-24 29-Feb-24 4 145
GR-CON-Z05-3566 Installation of Succulents 29-Feb-24 05-Mar-24 4 145
GR-CON-Z05-3576 Installation of Ground Covers 05-Mar-24 10-Mar-24 4 145
GR-CON-Z05-1049 Backfilling (Mulch) 10-Mar-24 01-Apr-24 15 145
GR-CON-Z05-1050 Natural Boulders Installation 01-Apr-24 23-Apr-24 13 145
GR-CON-Z05-1051 Retaining walls . Steps, forming risers, treads and edges with finishes
24-Apr-24 11-May-24 15 145
Irrigation Works 02-Oct-23 11-May-24 181 145
GR-CON-Z05-1052 Excavation Pipe Irrigation 02-Oct-23 07-Oct-23 5 169
GR-CON-Z05-1053 Sand Bedding 08-Oct-23 10-Oct-23 3 169
GR-CON-Z05-1054 HDPE Pipe Installations and fittings and conduit for cable 11-Oct-23 28-Oct-23 15 169
GR-CON-Z05-1056 Test pressure 29-Oct-23 02-Nov-23 5 169
GR-CON-Z05-1055 Installation of Valves and Accessories 04-Nov-23 07-Nov-23 4 169
GR-CON-Z05-1057 Back filling (sand / Subbase ) 08-Nov-23 14-Nov-23 6 169
GR-CON-Z05-1058 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Nov-23 21-Nov-23 6 276
GR-CON-Z05-1059 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
05-May-24
system 11-May-24 6 145
Street SS-12.1 26-Sep-23 01-May-24 178 153
Site Preparation 26-Sep-23 19-Oct-23 21 310
GR-CON-Z05-1116 Demolition (Asphalt.Paving,etc.....) 26-Sep-23 30-Sep-23 4 122
GR-CON-Z05-1117 Excavation And Disposal 01-Oct-23 05-Oct-23 5 164
GR-CON-Z05-1118 Prepretion And Compaction 07-Oct-23 12-Oct-23 6 310
GR-CON-Z05-1119 Backfilling 14-Oct-23 19-Oct-23 6 310
Curbstone and Paving 07-Oct-23 28-Nov-23 46 276
GR-CON-Z05-1120 Excavation Curbstone 07-Oct-23 11-Oct-23 5 241
GR-CON-Z05-1121 Plain Concrete 12-Oct-23 18-Oct-23 6 276
GR-CON-Z05-1122 Installation Curbstone 19-Oct-23 29-Oct-23 9 276
GR-CON-Z05-1123 Casting Concrete (Mortar haunch) 30-Oct-23 02-Nov-23 4 276
GR-CON-Z05-1124 Backfilling (sand / Sub base) 04-Nov-23 13-Nov-23 9 276
GR-CON-Z05-1125 Installation of Paving 14-Nov-23 28-Nov-23 13 276
Landscape Works 12-Oct-23 01-Apr-24 144 153
GR-CON-Z05-1126 Excavation (Tree Pit ) 12-Oct-23 17-Oct-23 5 241
GR-CON-Z05-1127 Aggregate Drainage layer 18-Oct-23 24-Oct-23 6 241
GR-CON-Z05-1128 Installation Geotextile 25-Oct-23 29-Oct-23 4 241
GR-CON-Z05-1129 Backfilling (Soil max for tree) 30-Oct-23 05-Nov-23 6 241
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z05-1130 Installation of Trees 15-Feb-24 19-Feb-24 3 153


GR-CON-Z05-9976 Installation of Shrubs 19-Feb-24 22-Feb-24 3 153
GR-CON-Z05-9986 Installation of Succulents 22-Feb-24 26-Feb-24 3 153
GR-CON-Z05-9996 Installation of Ground Covers 26-Feb-24 29-Feb-24 3 153
GR-CON-Z05-10006 Installation of Grass 29-Feb-24 04-Mar-24 3 153
GR-CON-Z05-1131 Backfilling (Mulch) 04-Mar-24 07-Mar-24 3 153
GR-CON-Z05-1132 Natural Boulders Installation 07-Mar-24 12-Mar-24 4 153
GR-CON-Z05-1133 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Mar-24 01-Apr-24 13 153
Site Furnishing 01-Apr-24 01-May-24 20 153
GR-CON-Z05-1142 Garden planter box 01-Apr-24 09-Apr-24 5 153
GR-CON-Z05-1143 Wheel stoppers 09-Apr-24 20-Apr-24 5 153
GR-CON-Z05-1144 Steel Lattice 21-Apr-24 25-Apr-24 5 153
GR-CON-Z05-1145 Handrail 27-Apr-24 01-May-24 5 153
Storm Piping Works 25-Apr-24 01-May-24 6 153
GR-CON-Z05-1146 Installation of DI grating covers 25-Apr-24 01-May-24 6 153
Irrigation Works 07-Oct-23 06-Dec-23 53 263
GR-CON-Z05-1134 Excavation Pipe Irrigation 07-Oct-23 11-Oct-23 5 164
GR-CON-Z05-1135 Sand Bedding 12-Oct-23 16-Oct-23 4 164
GR-CON-Z05-1136 HDPE Pipe Installations and fittings and conduit for cable 17-Oct-23 02-Nov-23 15 164
GR-CON-Z05-1138 Test pressure 04-Nov-23 08-Nov-23 5 164
GR-CON-Z05-1137 Installation of Valves and Accessories 09-Nov-23 13-Nov-23 4 164
GR-CON-Z05-1139 Back filling (sand / Subbase ) 14-Nov-23 20-Nov-23 6 164
GR-CON-Z05-1140 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Nov-23 27-Nov-23 6 263
GR-CON-Z05-1141 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
28-Nov-23
system 06-Dec-23 8 263
Electrical Works 12-Oct-23 01-May-24 164 153
GR-CON-Z05-1147 Excavation And Disposal 12-Oct-23 17-Oct-23 5 290
GR-CON-Z05-1148 Sand Bedding 18-Oct-23 22-Oct-23 4 290
GR-CON-Z05-1149 laying cables 23-Oct-23 26-Oct-23 4 290
GR-CON-Z05-1150 Backfilling (sand / Sub base) 28-Oct-23 01-Nov-23 5 290
GR-CON-Z05-1151 Control Panel / Distribution Panel Installation 02-Nov-23 06-Nov-23 4 290
GR-CON-Z05-1152 Road Crossing Ducts 27-Apr-24 01-May-24 5 153
Street SS-14 01-Oct-23 01-May-24 174 153
Site Preparation 01-Oct-23 24-Oct-23 21 306
GR-CON-Z05-1153 Demolition (Asphalt.Paving,etc.....) 01-Oct-23 04-Oct-23 4 122
GR-CON-Z05-1154 Excavation And Disposal 05-Oct-23 10-Oct-23 5 160
GR-CON-Z05-1155 Prepretion And Compaction 11-Oct-23 17-Oct-23 6 306
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z05-1156 Backfilling 18-Oct-23 24-Oct-23 6 306


Curbstone and Paving 11-Oct-23 03-Dec-23 46 272
GR-CON-Z05-1157 Excavation Curbstone 11-Oct-23 16-Oct-23 5 237
GR-CON-Z05-1158 Plain Concrete 17-Oct-23 23-Oct-23 6 272
GR-CON-Z05-1159 Installation Curbstone 24-Oct-23 02-Nov-23 9 272
GR-CON-Z05-1160 Casting Concrete (Mortar haunch) 04-Nov-23 07-Nov-23 4 272
GR-CON-Z05-1161 Backfilling (sand / Sub base) 08-Nov-23 18-Nov-23 9 272
GR-CON-Z05-1162 Installation of Paving 19-Nov-23 03-Dec-23 13 272
Landscape Works 17-Oct-23 01-Apr-24 140 153
GR-CON-Z05-1163 Excavation (Tree Pit ) 17-Oct-23 22-Oct-23 5 237
GR-CON-Z05-1164 Aggregate Drainage layer 23-Oct-23 29-Oct-23 6 237
GR-CON-Z05-1165 Installation Geotextile 30-Oct-23 02-Nov-23 4 237
GR-CON-Z05-1166 Backfilling (Soil max for tree) 04-Nov-23 09-Nov-23 6 237
GR-CON-Z05-1167 Installation of Trees 15-Feb-24 19-Feb-24 3 153
GR-CON-Z05-10016 Installation of Shrubs 19-Feb-24 22-Feb-24 3 153
GR-CON-Z05-10026 Installation of Succulents 22-Feb-24 26-Feb-24 3 153
GR-CON-Z05-10036 Installation of Ground Covers 26-Feb-24 29-Feb-24 3 153
GR-CON-Z05-10046 Installation of Grass 29-Feb-24 04-Mar-24 3 153
GR-CON-Z05-1168 Backfilling (Mulch) 04-Mar-24 07-Mar-24 3 153
GR-CON-Z05-1169 Natural Boulders Installation 07-Mar-24 12-Mar-24 4 153
GR-CON-Z05-1170 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Mar-24 01-Apr-24 13 153
Site Furnishing 01-Apr-24 01-May-24 20 153
GR-CON-Z05-1179 Garden planter box 01-Apr-24 09-Apr-24 5 153
GR-CON-Z05-1180 Wheel stoppers 09-Apr-24 20-Apr-24 5 153
GR-CON-Z05-1181 Steel Lattice 21-Apr-24 25-Apr-24 5 153
GR-CON-Z05-1182 Handrail 27-Apr-24 01-May-24 5 153
Storm Piping Works 25-Apr-24 01-May-24 6 153
GR-CON-Z05-1183 Installation of DI grating covers 25-Apr-24 01-May-24 6 153
Irrigation Works 11-Oct-23 11-Dec-23 53 259
GR-CON-Z05-1171 Excavation Pipe Irrigation 11-Oct-23 16-Oct-23 5 160
GR-CON-Z05-1172 Sand Bedding 17-Oct-23 21-Oct-23 4 160
GR-CON-Z05-1173 HDPE Pipe Installations and fittings and conduit for cable 22-Oct-23 07-Nov-23 15 160
GR-CON-Z05-1175 Test pressure 08-Nov-23 13-Nov-23 5 160
GR-CON-Z05-1174 Installation of Valves and Accessories 14-Nov-23 18-Nov-23 4 160
GR-CON-Z05-1176 Back filling (sand / Subbase ) 19-Nov-23 25-Nov-23 6 160
GR-CON-Z05-1177 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 26-Nov-23 02-Dec-23 6 259
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z05-1178 Pull box , Decoders , Connecting to plots /Connection to infra irrigation


03-Dec-23
system 11-Dec-23 8 259
Electrical Works 17-Oct-23 01-May-24 160 153
GR-CON-Z05-1184 Excavation And Disposal 17-Oct-23 22-Oct-23 5 286
GR-CON-Z05-1185 Sand Bedding 23-Oct-23 26-Oct-23 4 286
GR-CON-Z05-1186 laying cables 28-Oct-23 31-Oct-23 4 286
GR-CON-Z05-1187 Backfilling (sand / Sub base) 01-Nov-23 06-Nov-23 5 286
GR-CON-Z05-1188 Control Panel / Distribution Panel Installation 07-Nov-23 11-Nov-23 4 286
GR-CON-Z05-1189 Road Crossing Ducts 27-Apr-24 01-May-24 5 153
Street SS-15 05-Oct-23 20-Jul-24 234 89
Site Preparation 05-Oct-23 11-Nov-23 32 291
GR-CON-Z05-1190 Demolition (Asphalt.Paving,etc.....) 05-Oct-23 11-Oct-23 6 122
GR-CON-Z05-1191 Excavation And Disposal 12-Oct-23 21-Oct-23 8 122
GR-CON-Z05-1192 Prepretion And Compaction 22-Oct-23 31-Oct-23 9 291
GR-CON-Z05-1193 Backfilling 01-Nov-23 11-Nov-23 9 291
Curbstone and Paving 22-Oct-23 14-Jan-24 73 236
GR-CON-Z05-1194 Excavation Curbstone 22-Oct-23 30-Oct-23 8 147
GR-CON-Z05-1195 Plain Concrete 31-Oct-23 09-Nov-23 9 236
GR-CON-Z05-1196 Installation Curbstone 11-Nov-23 10-Dec-23 26 236
GR-CON-Z05-1197 Casting Concrete (Mortar haunch) 11-Dec-23 17-Dec-23 6 236
GR-CON-Z05-1199 Installation of Paving 16-Dec-23 14-Jan-24 26 236
GR-CON-Z05-1198 Backfilling (sand / Sub base) 18-Dec-23 02-Jan-24 14 236
Landscape Works 31-Oct-23 08-Jun-24 180 89
GR-CON-Z05-1200 Excavation (Tree Pit ) 31-Oct-23 08-Nov-23 8 147
GR-CON-Z05-1201 Aggregate Drainage layer 09-Nov-23 20-Nov-23 10 147
GR-CON-Z05-1202 Installation Geotextile 21-Nov-23 28-Nov-23 7 147
GR-CON-Z05-1203 Backfilling (Soil max for tree) 29-Nov-23 10-Dec-23 10 147
GR-CON-Z05-1204 Installation of Trees 15-Feb-24 25-Feb-24 8 89
GR-CON-Z05-10056 Installation of Shrubs 25-Feb-24 05-Mar-24 8 89
GR-CON-Z05-10066 Installation of Succulents 05-Mar-24 14-Mar-24 8 89
GR-CON-Z05-10076 Installation of Ground Covers 16-Mar-24 27-Mar-24 8 89
GR-CON-Z05-10086 Installation of Grass 27-Mar-24 09-Apr-24 8 89
GR-CON-Z05-1205 Backfilling (Mulch) 09-Apr-24 01-May-24 15 89
GR-CON-Z05-1206 Natural Boulders Installation 02-May-24 15-May-24 12 89
GR-CON-Z05-1207 Retaining walls . Steps, forming risers, treads and edges with finishes
16-May-24 08-Jun-24 20 89
Site Furnishing 09-Jun-24 20-Jul-24 32 89
GR-CON-Z05-1216 Garden planter box 09-Jun-24 17-Jun-24 8 89
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z05-1217 Wheel stoppers 18-Jun-24 01-Jul-24 8 89


GR-CON-Z05-1218 Steel Lattice 02-Jul-24 10-Jul-24 8 89
GR-CON-Z05-1219 Handrail 11-Jul-24 20-Jul-24 8 89
Storm Piping Works 10-Jul-24 20-Jul-24 9 89
GR-CON-Z05-1220 Installation of DI grating covers 10-Jul-24 20-Jul-24 9 89
Irrigation Works 22-Oct-23 25-Jan-24 83 217
GR-CON-Z05-1208 Excavation Pipe Irrigation 22-Oct-23 30-Oct-23 8 122
GR-CON-Z05-1209 Sand Bedding 31-Oct-23 06-Nov-23 6 122
GR-CON-Z05-1210 HDPE Pipe Installations and fittings and conduit for cable 07-Nov-23 06-Dec-23 26 122
GR-CON-Z05-1212 Test pressure 07-Dec-23 16-Dec-23 8 122
GR-CON-Z05-1211 Installation of Valves and Accessories 17-Dec-23 23-Dec-23 6 122
GR-CON-Z05-1213 Back filling (sand / Subbase ) 24-Dec-23 02-Jan-24 9 122
GR-CON-Z05-1214 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Jan-24 13-Jan-24 9 217
GR-CON-Z05-1215 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
14-Jan-24
system 25-Jan-24 11 217
Electrical Works 31-Oct-23 20-Jul-24 212 89
GR-CON-Z05-1221 Excavation And Disposal 31-Oct-23 08-Nov-23 8 259
GR-CON-Z05-1222 Sand Bedding 09-Nov-23 15-Nov-23 6 259
GR-CON-Z05-1223 laying cables 16-Nov-23 22-Nov-23 6 259
GR-CON-Z05-1224 Backfilling (sand / Sub base) 23-Nov-23 02-Dec-23 8 259
GR-CON-Z05-1225 Control Panel / Distribution Panel Installation 03-Dec-23 09-Dec-23 6 259
GR-CON-Z05-1226 Road Crossing Ducts 11-Jul-24 20-Jul-24 8 89
School S-04 21-Dec-23 27-Apr-24 99 157
Site Preparation 21-Dec-23 01-Jan-24 9 247
GR-CON-Z05-1061 Excavation And Disposal 21-Dec-23 27-Dec-23 5 89
GR-CON-Z05-1062 Prepretion And Compaction 27-Dec-23 01-Jan-24 4 247
Curbstone and Paving 27-Dec-23 19-Feb-24 46 205
GR-CON-Z05-1064 Excavation Curbstone 27-Dec-23 02-Jan-24 5 174
GR-CON-Z05-1065 Plain Concrete 02-Jan-24 09-Jan-24 6 205
GR-CON-Z05-1066 Installation Curbstone 09-Jan-24 20-Jan-24 9 205
GR-CON-Z05-1067 Casting Concrete (Mortar haunch) 20-Jan-24 24-Jan-24 4 205
GR-CON-Z05-1068 Backfilling (sand / Sub base) 24-Jan-24 04-Feb-24 9 205
GR-CON-Z05-1069 Installation of Paving 04-Feb-24 19-Feb-24 13 205
Landscape Works 02-Jan-24 10-Apr-24 79 157
GR-CON-Z05-1070 Excavation (Tree Pit ) 02-Jan-24 08-Jan-24 5 174
GR-CON-Z05-1071 Aggregate Drainage layer 08-Jan-24 15-Jan-24 6 174
GR-CON-Z05-1072 Installation Geotextile 15-Jan-24 20-Jan-24 4 174
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z05-1073 Backfilling (Soil max for tree) 20-Jan-24 27-Jan-24 6 174


GR-CON-Z05-1074 Installation of Trees 15-Feb-24 19-Feb-24 3 157
GR-CON-Z05-5296 Installation of Shrubs 19-Feb-24 22-Feb-24 3 157
GR-CON-Z05-5306 Installation of Succulents 22-Feb-24 26-Feb-24 3 157
GR-CON-Z05-5316 Installation of Ground Covers 26-Feb-24 29-Feb-24 3 157
GR-CON-Z05-5326 Installation of Climbers 29-Feb-24 04-Mar-24 3 157
GR-CON-Z05-5336 Installation of Grass 04-Mar-24 07-Mar-24 3 157
GR-CON-Z05-5346 Installation of Lawns 07-Mar-24 11-Mar-24 3 157
GR-CON-Z05-1075 Backfilling (Mulch) 11-Mar-24 14-Mar-24 3 157
GR-CON-Z05-1076 Natural Boulders Installation 16-Mar-24 21-Mar-24 4 157
GR-CON-Z05-1077 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Mar-24 10-Apr-24 13 157
Site Furnishing 10-Apr-24 27-Apr-24 10 157
GR-CON-Z05-1086 Garden planter box 10-Apr-24 21-Apr-24 5 157
GR-CON-Z05-1087 Wheel stoppers 22-Apr-24 27-Apr-24 5 157
Irrigation Works 27-Dec-23 27-Apr-24 94 157
GR-CON-Z05-1078 Excavation Pipe Irrigation 27-Dec-23 02-Jan-24 5 94
GR-CON-Z05-1079 Sand Bedding 02-Jan-24 06-Jan-24 3 94
GR-CON-Z05-1080 HDPE Pipe Installations and fittings and conduit for cable 06-Jan-24 23-Jan-24 15 94
GR-CON-Z05-1082 Test pressure 23-Jan-24 29-Jan-24 5 94
GR-CON-Z05-1081 Installation of Valves and Accessories 29-Jan-24 03-Feb-24 4 94
GR-CON-Z05-1083 Back filling (sand / Subbase ) 03-Feb-24 10-Feb-24 6 94
GR-CON-Z05-1084 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Feb-24 17-Feb-24 6 199
GR-CON-Z05-1085 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Apr-24
system 27-Apr-24 8 157
School S-05 27-Dec-23 27-Apr-24 94 157
Site Preparation 27-Dec-23 07-Jan-24 9 242
GR-CON-Z05-1089 Excavation And Disposal 27-Dec-23 02-Jan-24 5 89
GR-CON-Z05-1090 Prepretion And Compaction 02-Jan-24 07-Jan-24 4 242
Curbstone and Paving 02-Jan-24 25-Feb-24 46 200
GR-CON-Z05-1092 Excavation Curbstone 02-Jan-24 08-Jan-24 5 169
GR-CON-Z05-1093 Plain Concrete 08-Jan-24 15-Jan-24 6 200
GR-CON-Z05-1094 Installation Curbstone 15-Jan-24 25-Jan-24 9 200
GR-CON-Z05-1095 Casting Concrete (Mortar haunch) 25-Jan-24 30-Jan-24 4 200
GR-CON-Z05-1096 Backfilling (sand / Sub base) 30-Jan-24 10-Feb-24 9 200
GR-CON-Z05-1097 Installation of Paving 10-Feb-24 25-Feb-24 13 200
Landscape Works 08-Jan-24 10-Apr-24 74 157
GR-CON-Z05-1098 Excavation (Tree Pit ) 08-Jan-24 14-Jan-24 5 169
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z05-1099 Aggregate Drainage layer 14-Jan-24 21-Jan-24 6 169


GR-CON-Z05-1100 Installation Geotextile 21-Jan-24 25-Jan-24 4 169
GR-CON-Z05-1101 Backfilling (Soil max for tree) 25-Jan-24 01-Feb-24 6 169
GR-CON-Z05-1102 Installation of Trees 15-Feb-24 19-Feb-24 3 157
GR-CON-Z05-5356 Installation of Shrubs 19-Feb-24 22-Feb-24 3 157
GR-CON-Z05-5366 Installation of Succulents 22-Feb-24 26-Feb-24 3 157
GR-CON-Z05-5376 Installation of Ground Covers 26-Feb-24 29-Feb-24 3 157
GR-CON-Z05-5386 Installation of Climbers 29-Feb-24 04-Mar-24 3 157
GR-CON-Z05-5396 Installation of Grass 04-Mar-24 07-Mar-24 3 157
GR-CON-Z05-5406 Installation of Lawns 07-Mar-24 11-Mar-24 3 157
GR-CON-Z05-1103 Backfilling (Mulch) 11-Mar-24 14-Mar-24 3 157
GR-CON-Z05-1104 Natural Boulders Installation 16-Mar-24 21-Mar-24 4 157
GR-CON-Z05-1105 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Mar-24 10-Apr-24 13 157
Site Furnishing 10-Apr-24 27-Apr-24 10 157
GR-CON-Z05-1114 Garden planter box 10-Apr-24 21-Apr-24 5 157
GR-CON-Z05-1115 Wheel stoppers 22-Apr-24 27-Apr-24 5 157
Irrigation Works 02-Jan-24 27-Apr-24 89 157
GR-CON-Z05-1106 Excavation Pipe Irrigation 02-Jan-24 08-Jan-24 5 89
GR-CON-Z05-1107 Sand Bedding 08-Jan-24 11-Jan-24 3 89
GR-CON-Z05-1108 HDPE Pipe Installations and fittings and conduit for cable 11-Jan-24 29-Jan-24 15 89
GR-CON-Z05-1110 Test pressure 29-Jan-24 04-Feb-24 5 89
GR-CON-Z05-1109 Installation of Valves and Accessories 04-Feb-24 08-Feb-24 4 89
GR-CON-Z05-1111 Back filling (sand / Subbase ) 08-Feb-24 15-Feb-24 6 89
GR-CON-Z05-1112 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Feb-24 22-Feb-24 6 194
GR-CON-Z05-1113 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Apr-24
system 27-Apr-24 8 157
Zone 03 20-Sep-23 25-Aug-24 276 47
Future Neighborhood Park FNP-34 20-Sep-23 06-Jun-24 212 111
Site Preparation 20-Sep-23 14-Oct-23 20 303
GR-CON-Z03-1000 Demolition (Asphalt.Paving,etc.....) 20-Sep-23 25-Sep-23 4 22
GR-CON-Z03-1001 Excavation And Disposal 26-Sep-23 02-Oct-23 6 177
GR-CON-Z03-1002 Prepretion And Compaction 03-Oct-23 07-Oct-23 4 303
GR-CON-Z03-1003 Backfilling 08-Oct-23 14-Oct-23 6 303
Curbstone and Paving 03-Oct-23 25-Nov-23 46 267
GR-CON-Z03-1004 Excavation Curbstone 03-Oct-23 08-Oct-23 5 253
GR-CON-Z03-1005 Plain Concrete 09-Oct-23 15-Oct-23 6 267
GR-CON-Z03-1006 Installation Curbstone 16-Oct-23 25-Oct-23 9 267
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-1007 Casting Concrete (Mortar haunch) 26-Oct-23 30-Oct-23 4 267


GR-CON-Z03-1008 Backfilling (sand / Sub base) 31-Oct-23 09-Nov-23 9 267
GR-CON-Z03-1009 Installation of Paving 11-Nov-23 25-Nov-23 13 267
Landscape Works 09-Oct-23 06-Jun-24 197 111
GR-CON-Z03-1010 Excavation (Tree Pit ) 09-Oct-23 14-Oct-23 5 253
GR-CON-Z03-1011 Aggregate Drainage layer 15-Oct-23 21-Oct-23 6 253
GR-CON-Z03-1012 Installation Geotextile 22-Oct-23 25-Oct-23 4 253
GR-CON-Z03-1013 Backfilling (Soil max for tree) 26-Oct-23 01-Nov-23 6 253
GR-CON-Z03-1014 Installation of Trees 28-Apr-24 30-Apr-24 2 111
GR-CON-Z03-1556 Installation of Shrubs 30-Apr-24 02-May-24 2 111
GR-CON-Z03-1566 Installation of Succulents 02-May-24 05-May-24 2 111
GR-CON-Z03-1576 Installation of Ground Covers 05-May-24 07-May-24 2 111
GR-CON-Z03-1586 Installation of Climbers 07-May-24 09-May-24 2 111
GR-CON-Z03-1596 Installation of Grass 09-May-24 12-May-24 2 111
GR-CON-Z03-1606 Installation of Lawns 12-May-24 14-May-24 2 111
GR-CON-Z03-1015 Backfilling (Mulch) 14-May-24 18-May-24 3 111
GR-CON-Z03-1016 Natural Boulders Installation 18-May-24 22-May-24 4 111
GR-CON-Z03-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
22-May-24 06-Jun-24 13 111
Irrigation Works 03-Oct-23 06-Jun-24 202 111
GR-CON-Z03-1018 Excavation Pipe Irrigation 03-Oct-23 08-Oct-23 5 177
GR-CON-Z03-1019 Sand Bedding 09-Oct-23 11-Oct-23 3 177
GR-CON-Z03-1020 HDPE Pipe Installations and fittings and conduit for cable 12-Oct-23 29-Oct-23 15 177
GR-CON-Z03-1022 Test pressure 30-Oct-23 04-Nov-23 5 177
GR-CON-Z03-1021 Installation of Valves and Accessories 05-Nov-23 08-Nov-23 4 177
GR-CON-Z03-1023 Back filling (sand / Subbase ) 09-Nov-23 15-Nov-23 6 177
GR-CON-Z03-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Nov-23 22-Nov-23 6 261
GR-CON-Z03-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
28-May-24
system 06-Jun-24 8 111
Mosque M-04 26-Sep-23 15-Jul-24 237 82
Site Preparation 26-Sep-23 17-Oct-23 19 278
GR-CON-Z03-1026 Demolition (Asphalt.Paving,etc.....) 26-Sep-23 30-Sep-23 4 47
GR-CON-Z03-1027 Excavation And Disposal 01-Oct-23 05-Oct-23 5 174
GR-CON-Z03-1028 Prepretion And Compaction 07-Oct-23 10-Oct-23 4 278
GR-CON-Z03-1029 Backfilling 11-Oct-23 17-Oct-23 6 278
Curbstone and Paving 18-Oct-23 12-Nov-23 22 278
GR-CON-Z03-1034 Backfilling (sand / Sub base) 18-Oct-23 28-Oct-23 9 278
GR-CON-Z03-1035 Installation of Paving 29-Oct-23 12-Nov-23 13 278
Activity ID Activity Name Start Finish Original Total Float
Duration

Landscape Works 07-Oct-23 15-Jul-24 228 82


GR-CON-Z03-1036 Excavation (Tree Pit ) 07-Oct-23 11-Oct-23 5 226
GR-CON-Z03-1037 Aggregate Drainage layer 12-Oct-23 18-Oct-23 6 226
GR-CON-Z03-1038 Installation Geotextile 19-Oct-23 24-Oct-23 5 226
GR-CON-Z03-1039 Backfilling (Soil max for tree) 25-Oct-23 30-Oct-23 5 226
GR-CON-Z03-1040 Installation of Trees 28-Apr-24 02-May-24 4 82
GR-CON-Z03-3386 Installation of Climbers 02-May-24 07-May-24 4 82
GR-CON-Z03-3396 Installation of Shrubs 07-May-24 12-May-24 4 82
GR-CON-Z03-3406 Installation of Succulents 12-May-24 16-May-24 4 82
GR-CON-Z03-3416 Installation of Ground Covers 16-May-24 21-May-24 4 82
GR-CON-Z03-1041 Backfilling (Mulch) 21-May-24 08-Jun-24 15 82
GR-CON-Z03-1042 Natural Boulders Installation 08-Jun-24 27-Jun-24 13 82
GR-CON-Z03-1043 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 15-Jul-24 15 82
Irrigation Works 07-Oct-23 15-Jul-24 228 82
GR-CON-Z03-1044 Excavation Pipe Irrigation 07-Oct-23 11-Oct-23 5 174
GR-CON-Z03-1045 Sand Bedding 12-Oct-23 15-Oct-23 3 174
GR-CON-Z03-1046 HDPE Pipe Installations and fittings and conduit for cable 16-Oct-23 01-Nov-23 15 174
GR-CON-Z03-1048 Test pressure 02-Nov-23 07-Nov-23 5 174
GR-CON-Z03-1047 Installation of Valves and Accessories 08-Nov-23 12-Nov-23 4 174
GR-CON-Z03-1049 Back filling (sand / Subbase ) 13-Nov-23 19-Nov-23 6 174
GR-CON-Z03-1050 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Nov-23 26-Nov-23 6 260
GR-CON-Z03-1051 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Jul-24
system 15-Jul-24 6 82
Mosque M-05 01-Oct-23 15-Jul-24 233 82
Site Preparation 01-Oct-23 22-Oct-23 19 274
GR-CON-Z03-1052 Demolition (Asphalt.Paving,etc.....) 01-Oct-23 04-Oct-23 4 47
GR-CON-Z03-1053 Excavation And Disposal 05-Oct-23 10-Oct-23 5 170
GR-CON-Z03-1054 Prepretion And Compaction 11-Oct-23 15-Oct-23 4 274
GR-CON-Z03-1055 Backfilling 16-Oct-23 22-Oct-23 6 274
Curbstone and Paving 23-Oct-23 16-Nov-23 22 274
GR-CON-Z03-1060 Backfilling (sand / Sub base) 23-Oct-23 01-Nov-23 9 274
GR-CON-Z03-1061 Installation of Paving 02-Nov-23 16-Nov-23 13 274
Landscape Works 11-Oct-23 15-Jul-24 224 82
GR-CON-Z03-1062 Excavation (Tree Pit ) 11-Oct-23 16-Oct-23 5 222
GR-CON-Z03-1063 Aggregate Drainage layer 17-Oct-23 23-Oct-23 6 222
GR-CON-Z03-1064 Installation Geotextile 24-Oct-23 29-Oct-23 5 222
GR-CON-Z03-1065 Backfilling (Soil max for tree) 30-Oct-23 04-Nov-23 5 222
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-1066 Installation of Trees 28-Apr-24 02-May-24 4 82


GR-CON-Z03-3426 Installation of Climbers 02-May-24 07-May-24 4 82
GR-CON-Z03-3436 Installation of Shrubs 07-May-24 12-May-24 4 82
GR-CON-Z03-3446 Installation of Succulents 12-May-24 16-May-24 4 82
GR-CON-Z03-3456 Installation of Ground Covers 16-May-24 21-May-24 4 82
GR-CON-Z03-1067 Backfilling (Mulch) 21-May-24 08-Jun-24 15 82
GR-CON-Z03-1068 Natural Boulders Installation 08-Jun-24 27-Jun-24 13 82
GR-CON-Z03-1069 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 15-Jul-24 15 82
Irrigation Works 11-Oct-23 15-Jul-24 224 82
GR-CON-Z03-1070 Excavation Pipe Irrigation 11-Oct-23 16-Oct-23 5 170
GR-CON-Z03-1071 Sand Bedding 17-Oct-23 19-Oct-23 3 170
GR-CON-Z03-1072 HDPE Pipe Installations and fittings and conduit for cable 21-Oct-23 06-Nov-23 15 170
GR-CON-Z03-1074 Test pressure 07-Nov-23 12-Nov-23 5 170
GR-CON-Z03-1073 Installation of Valves and Accessories 13-Nov-23 16-Nov-23 4 170
GR-CON-Z03-1075 Back filling (sand / Subbase ) 18-Nov-23 23-Nov-23 6 170
GR-CON-Z03-1076 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-Nov-23 30-Nov-23 6 256
GR-CON-Z03-1077 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Jul-24
system 15-Jul-24 6 82
Parking P-28 05-Oct-23 30-May-24 194 117
Site Preparation 05-Oct-23 26-Oct-23 19 279
GR-CON-Z03-1078 Demolition (Asphalt.Paving,etc.....) 05-Oct-23 09-Oct-23 4 47
GR-CON-Z03-1079 Excavation And Disposal 10-Oct-23 15-Oct-23 5 166
GR-CON-Z03-1080 Prepretion And Compaction 16-Oct-23 19-Oct-23 4 279
GR-CON-Z03-1081 Backfilling 21-Oct-23 26-Oct-23 6 279
Curbstone and Paving 16-Oct-23 07-Dec-23 46 256
GR-CON-Z03-1082 Excavation Curbstone 16-Oct-23 21-Oct-23 5 248
GR-CON-Z03-1083 Plain Concrete 22-Oct-23 28-Oct-23 6 256
GR-CON-Z03-1084 Installation Curbstone 29-Oct-23 07-Nov-23 9 256
GR-CON-Z03-1085 Casting Concrete (Mortar haunch) 08-Nov-23 12-Nov-23 4 256
GR-CON-Z03-1086 Backfilling (sand / Sub base) 13-Nov-23 22-Nov-23 9 256
GR-CON-Z03-1087 Installation of Paving 23-Nov-23 07-Dec-23 13 256
Landscape Works 22-Oct-23 19-May-24 170 117
GR-CON-Z03-1088 Excavation (Tree Pit ) 22-Oct-23 26-Oct-23 5 248
GR-CON-Z03-1089 Aggregate Drainage layer 28-Oct-23 02-Nov-23 6 248
GR-CON-Z03-1090 Installation Geotextile 04-Nov-23 07-Nov-23 4 248
GR-CON-Z03-1091 Backfilling (Soil max for tree) 08-Nov-23 14-Nov-23 6 248
GR-CON-Z03-1092 Installation of Trees 28-Apr-24 01-May-24 3 117
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-6856 Installation of Shrubs 01-May-24 05-May-24 3 117


GR-CON-Z03-6866 Installation of Ground Covers 05-May-24 08-May-24 3 117
GR-CON-Z03-6876 Installation of Succulents 08-May-24 12-May-24 3 117
GR-CON-Z03-6886 Installation of Grass 12-May-24 15-May-24 3 117
GR-CON-Z03-1093 Backfilling (Mulch) 15-May-24 19-May-24 3 117
Site Furnishing 19-May-24 30-May-24 10 117
GR-CON-Z03-1104 Tree Grate 19-May-24 25-May-24 5 117
GR-CON-Z03-1105 Wheel stoppers 25-May-24 30-May-24 5 117
Irrigation Works 16-Oct-23 30-May-24 185 117
GR-CON-Z03-1096 Excavation Pipe Irrigation 16-Oct-23 21-Oct-23 5 166
GR-CON-Z03-1097 Sand Bedding 22-Oct-23 24-Oct-23 3 166
GR-CON-Z03-1098 HDPE Pipe Installations and fittings and conduit for cable 25-Oct-23 11-Nov-23 15 166
GR-CON-Z03-1100 Test pressure 12-Nov-23 16-Nov-23 5 166
GR-CON-Z03-1099 Installation of Valves and Accessories 18-Nov-23 21-Nov-23 4 166
GR-CON-Z03-1101 Back filling (sand / Subbase ) 22-Nov-23 28-Nov-23 6 166
GR-CON-Z03-1102 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Nov-23 05-Dec-23 6 250
GR-CON-Z03-1103 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-May-24
system 30-May-24 8 117
Parking P-03 10-Oct-23 30-May-24 190 117
Site Preparation 10-Oct-23 31-Oct-23 19 275
GR-CON-Z03-1106 Demolition (Asphalt.Paving,etc.....) 10-Oct-23 14-Oct-23 4 47
GR-CON-Z03-1107 Excavation And Disposal 15-Oct-23 19-Oct-23 5 162
GR-CON-Z03-1108 Prepretion And Compaction 21-Oct-23 24-Oct-23 4 275
GR-CON-Z03-1109 Backfilling 25-Oct-23 31-Oct-23 6 275
Curbstone and Paving 21-Oct-23 12-Dec-23 46 252
GR-CON-Z03-1110 Excavation Curbstone 21-Oct-23 25-Oct-23 5 244
GR-CON-Z03-1111 Plain Concrete 26-Oct-23 01-Nov-23 6 252
GR-CON-Z03-1112 Installation Curbstone 02-Nov-23 12-Nov-23 9 252
GR-CON-Z03-1113 Casting Concrete (Mortar haunch) 13-Nov-23 16-Nov-23 4 252
GR-CON-Z03-1114 Backfilling (sand / Sub base) 18-Nov-23 27-Nov-23 9 252
GR-CON-Z03-1115 Installation of Paving 28-Nov-23 12-Dec-23 13 252
Landscape Works 26-Oct-23 19-May-24 166 117
GR-CON-Z03-1116 Excavation (Tree Pit ) 26-Oct-23 31-Oct-23 5 244
GR-CON-Z03-1117 Aggregate Drainage layer 01-Nov-23 07-Nov-23 6 244
GR-CON-Z03-1118 Installation Geotextile 08-Nov-23 12-Nov-23 4 244
GR-CON-Z03-1119 Backfilling (Soil max for tree) 13-Nov-23 19-Nov-23 6 244
GR-CON-Z03-1120 Installation of Trees 28-Apr-24 01-May-24 3 117
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-6896 Installation of Shrubs 01-May-24 05-May-24 3 117


GR-CON-Z03-6906 Installation of Ground Covers 05-May-24 08-May-24 3 117
GR-CON-Z03-6916 Installation of Succulents 08-May-24 12-May-24 3 117
GR-CON-Z03-6926 Installation of Grass 12-May-24 15-May-24 3 117
GR-CON-Z03-1121 Backfilling (Mulch) 15-May-24 19-May-24 3 117
Site Furnishing 19-May-24 30-May-24 10 117
GR-CON-Z03-1132 Tree Grate 19-May-24 25-May-24 5 117
GR-CON-Z03-1133 Wheel stoppers 25-May-24 30-May-24 5 117
Irrigation Works 21-Oct-23 30-May-24 181 117
GR-CON-Z03-1124 Excavation Pipe Irrigation 21-Oct-23 25-Oct-23 5 162
GR-CON-Z03-1125 Sand Bedding 26-Oct-23 29-Oct-23 3 162
GR-CON-Z03-1126 HDPE Pipe Installations and fittings and conduit for cable 30-Oct-23 15-Nov-23 15 162
GR-CON-Z03-1128 Test pressure 16-Nov-23 21-Nov-23 5 162
GR-CON-Z03-1127 Installation of Valves and Accessories 22-Nov-23 26-Nov-23 4 162
GR-CON-Z03-1129 Back filling (sand / Subbase ) 27-Nov-23 03-Dec-23 6 162
GR-CON-Z03-1130 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Dec-23 10-Dec-23 6 246
GR-CON-Z03-1131 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-May-24
system 30-May-24 8 117
Parking P-05 15-Oct-23 30-May-24 186 117
Site Preparation 15-Oct-23 05-Nov-23 19 271
GR-CON-Z03-1134 Demolition (Asphalt.Paving,etc.....) 15-Oct-23 18-Oct-23 4 47
GR-CON-Z03-1135 Excavation And Disposal 19-Oct-23 24-Oct-23 5 158
GR-CON-Z03-1136 Prepretion And Compaction 25-Oct-23 29-Oct-23 4 271
GR-CON-Z03-1137 Backfilling 30-Oct-23 05-Nov-23 6 271
Curbstone and Paving 25-Oct-23 17-Dec-23 46 248
GR-CON-Z03-1138 Excavation Curbstone 25-Oct-23 30-Oct-23 5 240
GR-CON-Z03-1139 Plain Concrete 31-Oct-23 06-Nov-23 6 248
GR-CON-Z03-1140 Installation Curbstone 07-Nov-23 16-Nov-23 9 248
GR-CON-Z03-1141 Casting Concrete (Mortar haunch) 18-Nov-23 21-Nov-23 4 248
GR-CON-Z03-1142 Backfilling (sand / Sub base) 22-Nov-23 02-Dec-23 9 248
GR-CON-Z03-1143 Installation of Paving 03-Dec-23 17-Dec-23 13 248
Landscape Works 31-Oct-23 19-May-24 162 117
GR-CON-Z03-1144 Excavation (Tree Pit ) 31-Oct-23 05-Nov-23 5 240
GR-CON-Z03-1145 Aggregate Drainage layer 06-Nov-23 12-Nov-23 6 240
GR-CON-Z03-1146 Installation Geotextile 13-Nov-23 16-Nov-23 4 240
GR-CON-Z03-1147 Backfilling (Soil max for tree) 18-Nov-23 23-Nov-23 6 240
GR-CON-Z03-1148 Installation of Trees 28-Apr-24 01-May-24 3 117
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-6936 Installation of Shrubs 01-May-24 05-May-24 3 117


GR-CON-Z03-6946 Installation of Ground Covers 05-May-24 08-May-24 3 117
GR-CON-Z03-6956 Installation of Succulents 08-May-24 12-May-24 3 117
GR-CON-Z03-6966 Installation of Grass 12-May-24 15-May-24 3 117
GR-CON-Z03-1149 Backfilling (Mulch) 15-May-24 19-May-24 3 117
Site Furnishing 19-May-24 30-May-24 10 117
GR-CON-Z03-1160 Tree Grate 19-May-24 25-May-24 5 117
GR-CON-Z03-1161 Wheel stoppers 25-May-24 30-May-24 5 117
Irrigation Works 25-Oct-23 30-May-24 177 117
GR-CON-Z03-1152 Excavation Pipe Irrigation 25-Oct-23 30-Oct-23 5 158
GR-CON-Z03-1153 Sand Bedding 31-Oct-23 02-Nov-23 3 158
GR-CON-Z03-1154 HDPE Pipe Installations and fittings and conduit for cable 04-Nov-23 20-Nov-23 15 158
GR-CON-Z03-1156 Test pressure 21-Nov-23 26-Nov-23 5 158
GR-CON-Z03-1155 Installation of Valves and Accessories 27-Nov-23 30-Nov-23 4 158
GR-CON-Z03-1157 Back filling (sand / Subbase ) 02-Dec-23 07-Dec-23 6 158
GR-CON-Z03-1158 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Dec-23 14-Dec-23 6 242
GR-CON-Z03-1159 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-May-24
system 30-May-24 8 117
Parking P-06 19-Oct-23 30-May-24 182 117
Site Preparation 19-Oct-23 09-Nov-23 19 267
GR-CON-Z03-1162 Demolition (Asphalt.Paving,etc.....) 19-Oct-23 23-Oct-23 4 47
GR-CON-Z03-1163 Excavation And Disposal 24-Oct-23 29-Oct-23 5 154
GR-CON-Z03-1164 Prepretion And Compaction 30-Oct-23 02-Nov-23 4 267
GR-CON-Z03-1165 Backfilling 04-Nov-23 09-Nov-23 6 267
Curbstone and Paving 30-Oct-23 21-Dec-23 46 244
GR-CON-Z03-1166 Excavation Curbstone 30-Oct-23 04-Nov-23 5 236
GR-CON-Z03-1167 Plain Concrete 05-Nov-23 11-Nov-23 6 244
GR-CON-Z03-1168 Installation Curbstone 12-Nov-23 21-Nov-23 9 244
GR-CON-Z03-1169 Casting Concrete (Mortar haunch) 22-Nov-23 26-Nov-23 4 244
GR-CON-Z03-1170 Backfilling (sand / Sub base) 27-Nov-23 06-Dec-23 9 244
GR-CON-Z03-1171 Installation of Paving 07-Dec-23 21-Dec-23 13 244
Landscape Works 05-Nov-23 19-May-24 158 117
GR-CON-Z03-1172 Excavation (Tree Pit ) 05-Nov-23 09-Nov-23 5 236
GR-CON-Z03-1173 Aggregate Drainage layer 11-Nov-23 16-Nov-23 6 236
GR-CON-Z03-1174 Installation Geotextile 18-Nov-23 21-Nov-23 4 236
GR-CON-Z03-1175 Backfilling (Soil max for tree) 22-Nov-23 28-Nov-23 6 236
GR-CON-Z03-1176 Installation of Trees 28-Apr-24 01-May-24 3 117
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-6976 Installation of Shrubs 01-May-24 05-May-24 3 117


GR-CON-Z03-6986 Installation of Ground Covers 05-May-24 08-May-24 3 117
GR-CON-Z03-6996 Installation of Succulents 08-May-24 12-May-24 3 117
GR-CON-Z03-7006 Installation of Grass 12-May-24 15-May-24 3 117
GR-CON-Z03-1177 Backfilling (Mulch) 15-May-24 19-May-24 3 117
Site Furnishing 19-May-24 30-May-24 10 117
GR-CON-Z03-1188 Tree Grate 19-May-24 25-May-24 5 117
GR-CON-Z03-1189 Wheel stoppers 25-May-24 30-May-24 5 117
Irrigation Works 30-Oct-23 30-May-24 173 117
GR-CON-Z03-1180 Excavation Pipe Irrigation 30-Oct-23 04-Nov-23 5 154
GR-CON-Z03-1181 Sand Bedding 05-Nov-23 07-Nov-23 3 154
GR-CON-Z03-1182 HDPE Pipe Installations and fittings and conduit for cable 08-Nov-23 25-Nov-23 15 154
GR-CON-Z03-1184 Test pressure 26-Nov-23 30-Nov-23 5 154
GR-CON-Z03-1183 Installation of Valves and Accessories 02-Dec-23 05-Dec-23 4 154
GR-CON-Z03-1185 Back filling (sand / Subbase ) 06-Dec-23 12-Dec-23 6 154
GR-CON-Z03-1186 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Dec-23 19-Dec-23 6 238
GR-CON-Z03-1187 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-May-24
system 30-May-24 8 117
Street SS-25 24-Oct-23 25-Aug-24 248 47
Site Preparation 24-Oct-23 11-Dec-23 42 253
GR-CON-Z03-1218 Demolition (Asphalt.Paving,etc.....) 24-Oct-23 01-Nov-23 8 47
GR-CON-Z03-1219 Excavation And Disposal 02-Nov-23 13-Nov-23 10 47
GR-CON-Z03-1220 Prepretion And Compaction 14-Nov-23 27-Nov-23 12 253
GR-CON-Z03-1221 Backfilling 28-Nov-23 11-Dec-23 12 253
Curbstone and Paving 14-Nov-23 26-Feb-24 90 187
GR-CON-Z03-1222 Excavation Curbstone 14-Nov-23 25-Nov-23 10 127
GR-CON-Z03-1223 Plain Concrete 26-Nov-23 09-Dec-23 12 187
GR-CON-Z03-1224 Installation Curbstone 10-Dec-23 30-Dec-23 18 187
GR-CON-Z03-1225 Casting Concrete (Mortar haunch) 31-Dec-23 08-Jan-24 8 187
GR-CON-Z03-1226 Backfilling (sand / Sub base) 09-Jan-24 29-Jan-24 18 187
GR-CON-Z03-1227 Installation of Paving 30-Jan-24 26-Feb-24 24 187
Landscape Works 26-Nov-23 09-Jul-24 180 47
GR-CON-Z03-1228 Excavation (Tree Pit ) 26-Nov-23 06-Dec-23 10 127
GR-CON-Z03-1229 Aggregate Drainage layer 07-Dec-23 20-Dec-23 12 127
GR-CON-Z03-1230 Installation Geotextile 21-Dec-23 30-Dec-23 8 127
GR-CON-Z03-1231 Backfilling (Soil max for tree) 31-Dec-23 13-Jan-24 12 127
GR-CON-Z03-1232 Installation of Trees 28-Apr-24 02-May-24 4 47
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-9456 Installation of Shrubs 02-May-24 07-May-24 4 47


GR-CON-Z03-9466 Installation of Succulents 07-May-24 12-May-24 4 47
GR-CON-Z03-9476 Installation of Ground Covers 12-May-24 16-May-24 4 47
GR-CON-Z03-9486 Installation of Grass 16-May-24 21-May-24 4 47
GR-CON-Z03-1233 Backfilling (Mulch) 21-May-24 28-May-24 6 47
GR-CON-Z03-1234 Natural Boulders Installation 28-May-24 06-Jun-24 8 47
GR-CON-Z03-1235 Retaining walls . Steps, forming risers, treads and edges with finishes
06-Jun-24 09-Jul-24 24 47
Site Furnishing 09-Jul-24 25-Aug-24 40 47
GR-CON-Z03-1244 Garden planter box 09-Jul-24 21-Jul-24 10 47
GR-CON-Z03-1245 Wheel stoppers 21-Jul-24 01-Aug-24 10 47
GR-CON-Z03-1246 Steel Lattice 01-Aug-24 13-Aug-24 10 47
GR-CON-Z03-1247 Handrail 13-Aug-24 25-Aug-24 10 47
Storm Piping Works 11-Aug-24 25-Aug-24 12 47
GR-CON-Z03-1248 Installation of DI grating covers 11-Aug-24 25-Aug-24 12 47
Irrigation Works 14-Nov-23 09-Mar-24 100 165
GR-CON-Z03-1236 Excavation Pipe Irrigation 14-Nov-23 25-Nov-23 10 47
GR-CON-Z03-1237 Sand Bedding 26-Nov-23 04-Dec-23 8 47
GR-CON-Z03-1238 HDPE Pipe Installations and fittings and conduit for cable 05-Dec-23 01-Jan-24 24 47
GR-CON-Z03-1240 Test pressure 02-Jan-24 13-Jan-24 10 47
GR-CON-Z03-1239 Installation of Valves and Accessories 14-Jan-24 22-Jan-24 8 47
GR-CON-Z03-1241 Back filling (sand / Subbase ) 23-Jan-24 05-Feb-24 12 47
GR-CON-Z03-1242 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Feb-24 19-Feb-24 12 165
GR-CON-Z03-1243 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
20-Feb-24
system 09-Mar-24 16 165
Electrical Works 26-Nov-23 25-Aug-24 220 47
GR-CON-Z03-1249 Excavation And Disposal 26-Nov-23 06-Dec-23 10 213
GR-CON-Z03-1250 Sand Bedding 07-Dec-23 16-Dec-23 8 213
GR-CON-Z03-1251 laying cables 17-Dec-23 25-Dec-23 8 213
GR-CON-Z03-1252 Backfilling (sand / Sub base) 26-Dec-23 06-Jan-24 10 213
GR-CON-Z03-1253 Control Panel / Distribution Panel Installation 07-Jan-24 15-Jan-24 8 213
GR-CON-Z03-1254 Road Crossing Ducts 13-Aug-24 25-Aug-24 10 47
Street SS-33 02-Nov-23 06-Jul-24 197 90
Site Preparation 02-Nov-23 26-Nov-23 21 266
GR-CON-Z03-1255 Demolition (Asphalt.Paving,etc.....) 02-Nov-23 06-Nov-23 4 101
GR-CON-Z03-1256 Excavation And Disposal 07-Nov-23 12-Nov-23 5 141
GR-CON-Z03-1257 Prepretion And Compaction 13-Nov-23 19-Nov-23 6 266
GR-CON-Z03-1258 Backfilling 20-Nov-23 26-Nov-23 6 266
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 13-Nov-23 04-Jan-24 46 232


GR-CON-Z03-1259 Excavation Curbstone 13-Nov-23 18-Nov-23 5 197
GR-CON-Z03-1260 Plain Concrete 19-Nov-23 25-Nov-23 6 232
GR-CON-Z03-1261 Installation Curbstone 26-Nov-23 05-Dec-23 9 232
GR-CON-Z03-1262 Casting Concrete (Mortar haunch) 06-Dec-23 10-Dec-23 4 232
GR-CON-Z03-1263 Backfilling (sand / Sub base) 11-Dec-23 20-Dec-23 9 232
GR-CON-Z03-1264 Installation of Paving 21-Dec-23 04-Jan-24 13 232
Landscape Works 19-Nov-23 08-Jun-24 163 90
GR-CON-Z03-1265 Excavation (Tree Pit ) 19-Nov-23 23-Nov-23 5 197
GR-CON-Z03-1266 Aggregate Drainage layer 25-Nov-23 30-Nov-23 6 197
GR-CON-Z03-1267 Installation Geotextile 02-Dec-23 05-Dec-23 4 197
GR-CON-Z03-1268 Backfilling (Soil max for tree) 06-Dec-23 12-Dec-23 6 197
GR-CON-Z03-1269 Installation of Trees 28-Apr-24 01-May-24 3 90
GR-CON-Z03-9496 Installation of Shrubs 01-May-24 05-May-24 3 90
GR-CON-Z03-9506 Installation of Succulents 05-May-24 08-May-24 3 90
GR-CON-Z03-9516 Installation of Ground Covers 08-May-24 12-May-24 3 90
GR-CON-Z03-9526 Installation of Grass 12-May-24 15-May-24 3 90
GR-CON-Z03-1270 Backfilling (Mulch) 15-May-24 19-May-24 3 90
GR-CON-Z03-1271 Natural Boulders Installation 19-May-24 23-May-24 4 90
GR-CON-Z03-1272 Retaining walls . Steps, forming risers, treads and edges with finishes
23-May-24 08-Jun-24 13 90
Site Furnishing 08-Jun-24 06-Jul-24 20 90
GR-CON-Z03-1281 Garden planter box 08-Jun-24 13-Jun-24 5 90
GR-CON-Z03-1282 Wheel stoppers 13-Jun-24 24-Jun-24 5 90
GR-CON-Z03-1283 Steel Lattice 24-Jun-24 30-Jun-24 5 90
GR-CON-Z03-1284 Handrail 30-Jun-24 06-Jul-24 5 90
Storm Piping Works 29-Jun-24 06-Jul-24 6 90
GR-CON-Z03-1285 Installation of DI grating covers 29-Jun-24 06-Jul-24 6 90
Irrigation Works 13-Nov-23 13-Jan-24 53 219
GR-CON-Z03-1273 Excavation Pipe Irrigation 13-Nov-23 18-Nov-23 5 141
GR-CON-Z03-1274 Sand Bedding 19-Nov-23 22-Nov-23 4 141
GR-CON-Z03-1275 HDPE Pipe Installations and fittings and conduit for cable 23-Nov-23 10-Dec-23 15 141
GR-CON-Z03-1277 Test pressure 11-Dec-23 16-Dec-23 5 141
GR-CON-Z03-1276 Installation of Valves and Accessories 17-Dec-23 20-Dec-23 4 141
GR-CON-Z03-1278 Back filling (sand / Subbase ) 21-Dec-23 27-Dec-23 6 141
GR-CON-Z03-1279 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-Dec-23 03-Jan-24 6 219
GR-CON-Z03-1280 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
04-Jan-24
system 13-Jan-24 8 219
Activity ID Activity Name Start Finish Original Total Float
Duration

Electrical Works 19-Nov-23 06-Jul-24 183 90


GR-CON-Z03-1286 Excavation And Disposal 19-Nov-23 23-Nov-23 5 246
GR-CON-Z03-1287 Sand Bedding 25-Nov-23 28-Nov-23 4 246
GR-CON-Z03-1288 laying cables 29-Nov-23 03-Dec-23 4 246
GR-CON-Z03-1289 Backfilling (sand / Sub base) 04-Dec-23 09-Dec-23 5 246
GR-CON-Z03-1290 Control Panel / Distribution Panel Installation 10-Dec-23 13-Dec-23 4 246
GR-CON-Z03-1291 Road Crossing Ducts 30-Jun-24 06-Jul-24 5 90
Street SS-34 07-Nov-23 06-Jul-24 193 90
Site Preparation 07-Nov-23 30-Nov-23 21 262
GR-CON-Z03-1292 Demolition (Asphalt.Paving,etc.....) 07-Nov-23 11-Nov-23 4 101
GR-CON-Z03-1293 Excavation And Disposal 12-Nov-23 16-Nov-23 5 137
GR-CON-Z03-1294 Prepretion And Compaction 18-Nov-23 23-Nov-23 6 262
GR-CON-Z03-1295 Backfilling 25-Nov-23 30-Nov-23 6 262
Curbstone and Paving 18-Nov-23 09-Jan-24 46 228
GR-CON-Z03-1296 Excavation Curbstone 18-Nov-23 22-Nov-23 5 193
GR-CON-Z03-1297 Plain Concrete 23-Nov-23 29-Nov-23 6 228
GR-CON-Z03-1298 Installation Curbstone 30-Nov-23 10-Dec-23 9 228
GR-CON-Z03-1299 Casting Concrete (Mortar haunch) 11-Dec-23 14-Dec-23 4 228
GR-CON-Z03-1300 Backfilling (sand / Sub base) 16-Dec-23 25-Dec-23 9 228
GR-CON-Z03-1301 Installation of Paving 26-Dec-23 09-Jan-24 13 228
Landscape Works 23-Nov-23 08-Jun-24 159 90
GR-CON-Z03-1302 Excavation (Tree Pit ) 23-Nov-23 28-Nov-23 5 193
GR-CON-Z03-1303 Aggregate Drainage layer 29-Nov-23 05-Dec-23 6 193
GR-CON-Z03-1304 Installation Geotextile 06-Dec-23 10-Dec-23 4 193
GR-CON-Z03-1305 Backfilling (Soil max for tree) 11-Dec-23 17-Dec-23 6 193
GR-CON-Z03-1306 Installation of Trees 28-Apr-24 01-May-24 3 90
GR-CON-Z03-9536 Installation of Shrubs 01-May-24 05-May-24 3 90
GR-CON-Z03-9546 Installation of Succulents 05-May-24 08-May-24 3 90
GR-CON-Z03-9556 Installation of Ground Covers 08-May-24 12-May-24 3 90
GR-CON-Z03-9566 Installation of Grass 12-May-24 15-May-24 3 90
GR-CON-Z03-1307 Backfilling (Mulch) 15-May-24 19-May-24 3 90
GR-CON-Z03-1308 Natural Boulders Installation 19-May-24 23-May-24 4 90
GR-CON-Z03-1309 Retaining walls . Steps, forming risers, treads and edges with finishes
23-May-24 08-Jun-24 13 90
Site Furnishing 08-Jun-24 06-Jul-24 20 90
GR-CON-Z03-1318 Garden planter box 08-Jun-24 13-Jun-24 5 90
GR-CON-Z03-1319 Wheel stoppers 13-Jun-24 24-Jun-24 5 90
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-1320 Steel Lattice 24-Jun-24 30-Jun-24 5 90


GR-CON-Z03-1321 Handrail 30-Jun-24 06-Jul-24 5 90
Storm Piping Works 29-Jun-24 06-Jul-24 6 90
GR-CON-Z03-1322 Installation of DI grating covers 29-Jun-24 06-Jul-24 6 90
Irrigation Works 18-Nov-23 17-Jan-24 53 215
GR-CON-Z03-1310 Excavation Pipe Irrigation 18-Nov-23 22-Nov-23 5 137
GR-CON-Z03-1311 Sand Bedding 23-Nov-23 27-Nov-23 4 137
GR-CON-Z03-1312 HDPE Pipe Installations and fittings and conduit for cable 28-Nov-23 14-Dec-23 15 137
GR-CON-Z03-1314 Test pressure 16-Dec-23 20-Dec-23 5 137
GR-CON-Z03-1313 Installation of Valves and Accessories 21-Dec-23 25-Dec-23 4 137
GR-CON-Z03-1315 Back filling (sand / Subbase ) 26-Dec-23 01-Jan-24 6 137
GR-CON-Z03-1316 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 02-Jan-24 08-Jan-24 6 215
GR-CON-Z03-1317 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
09-Jan-24
system 17-Jan-24 8 215
Electrical Works 23-Nov-23 06-Jul-24 179 90
GR-CON-Z03-1323 Excavation And Disposal 23-Nov-23 28-Nov-23 5 242
GR-CON-Z03-1324 Sand Bedding 29-Nov-23 03-Dec-23 4 242
GR-CON-Z03-1325 laying cables 04-Dec-23 07-Dec-23 4 242
GR-CON-Z03-1326 Backfilling (sand / Sub base) 09-Dec-23 13-Dec-23 5 242
GR-CON-Z03-1327 Control Panel / Distribution Panel Installation 14-Dec-23 18-Dec-23 4 242
GR-CON-Z03-1328 Road Crossing Ducts 30-Jun-24 06-Jul-24 5 90
Street SS-04 12-Nov-23 03-Aug-24 213 66
Site Preparation 12-Nov-23 18-Dec-23 32 247
GR-CON-Z03-1329 Demolition (Asphalt.Paving,etc.....) 12-Nov-23 18-Nov-23 6 101
GR-CON-Z03-1330 Excavation And Disposal 19-Nov-23 27-Nov-23 8 107
GR-CON-Z03-1331 Prepretion And Compaction 28-Nov-23 07-Dec-23 9 247
GR-CON-Z03-1332 Backfilling 09-Dec-23 18-Dec-23 9 247
Curbstone and Paving 28-Nov-23 04-Feb-24 59 206
GR-CON-Z03-1333 Excavation Curbstone 28-Nov-23 06-Dec-23 8 146
GR-CON-Z03-1334 Plain Concrete 07-Dec-23 17-Dec-23 9 206
GR-CON-Z03-1335 Installation Curbstone 18-Dec-23 02-Jan-24 14 206
GR-CON-Z03-1336 Casting Concrete (Mortar haunch) 03-Jan-24 09-Jan-24 6 206
GR-CON-Z03-1337 Backfilling (sand / Sub base) 10-Jan-24 25-Jan-24 14 206
GR-CON-Z03-1338 Installation of Paving 13-Jan-24 04-Feb-24 20 206
Landscape Works 07-Dec-23 26-Jun-24 159 66
GR-CON-Z03-1339 Excavation (Tree Pit ) 07-Dec-23 16-Dec-23 8 146
GR-CON-Z03-1340 Aggregate Drainage layer 17-Dec-23 26-Dec-23 9 146
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-1341 Installation Geotextile 27-Dec-23 02-Jan-24 6 146


GR-CON-Z03-1342 Backfilling (Soil max for tree) 03-Jan-24 13-Jan-24 9 146
GR-CON-Z03-1343 Installation of Trees 28-Apr-24 02-May-24 4 66
GR-CON-Z03-9576 Installation of Shrubs 02-May-24 06-May-24 3 66
GR-CON-Z03-9586 Installation of Succulents 06-May-24 09-May-24 3 66
GR-CON-Z03-9596 Installation of Ground Covers 09-May-24 13-May-24 3 66
GR-CON-Z03-9606 Installation of Grass 13-May-24 16-May-24 3 66
GR-CON-Z03-1344 Backfilling (Mulch) 16-May-24 22-May-24 5 66
GR-CON-Z03-1345 Natural Boulders Installation 22-May-24 29-May-24 6 66
GR-CON-Z03-1346 Retaining walls . Steps, forming risers, treads and edges with finishes
29-May-24 26-Jun-24 20 66
Site Furnishing 26-Jun-24 03-Aug-24 32 66
GR-CON-Z03-1355 Garden planter box 26-Jun-24 06-Jul-24 8 66
GR-CON-Z03-1356 Wheel stoppers 06-Jul-24 15-Jul-24 8 66
GR-CON-Z03-1357 Steel Lattice 15-Jul-24 24-Jul-24 8 66
GR-CON-Z03-1358 Handrail 24-Jul-24 03-Aug-24 8 66
Storm Piping Works 23-Jul-24 03-Aug-24 9 66
GR-CON-Z03-1359 Installation of DI grating covers 23-Jul-24 03-Aug-24 9 66
Irrigation Works 28-Nov-23 29-Feb-24 81 175
GR-CON-Z03-1347 Excavation Pipe Irrigation 28-Nov-23 06-Dec-23 8 107
GR-CON-Z03-1348 Sand Bedding 07-Dec-23 13-Dec-23 6 107
GR-CON-Z03-1349 HDPE Pipe Installations and fittings and conduit for cable 14-Dec-23 09-Jan-24 23 107
GR-CON-Z03-1351 Test pressure 10-Jan-24 18-Jan-24 8 107
GR-CON-Z03-1350 Installation of Valves and Accessories 20-Jan-24 25-Jan-24 6 107
GR-CON-Z03-1352 Back filling (sand / Subbase ) 27-Jan-24 05-Feb-24 9 107
GR-CON-Z03-1353 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Feb-24 15-Feb-24 9 175
GR-CON-Z03-1354 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Feb-24
system 29-Feb-24 12 175
Electrical Works 07-Dec-23 03-Aug-24 191 66
GR-CON-Z03-1360 Excavation And Disposal 07-Dec-23 16-Dec-23 8 215
GR-CON-Z03-1361 Sand Bedding 17-Dec-23 23-Dec-23 6 215
GR-CON-Z03-1362 laying cables 24-Dec-23 30-Dec-23 6 215
GR-CON-Z03-1363 Backfilling (sand / Sub base) 31-Dec-23 08-Jan-24 8 215
GR-CON-Z03-1364 Control Panel / Distribution Panel Installation 09-Jan-24 15-Jan-24 6 215
GR-CON-Z03-1365 Road Crossing Ducts 24-Jul-24 03-Aug-24 8 66
Street SS-05 19-Nov-23 03-Aug-24 207 66
Site Preparation 19-Nov-23 25-Dec-23 32 241
GR-CON-Z03-1366 Demolition (Asphalt.Paving,etc.....) 19-Nov-23 25-Nov-23 6 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-1367 Excavation And Disposal 26-Nov-23 04-Dec-23 8 101


GR-CON-Z03-1368 Prepretion And Compaction 05-Dec-23 14-Dec-23 9 241
GR-CON-Z03-1369 Backfilling 16-Dec-23 25-Dec-23 9 241
Curbstone and Paving 05-Dec-23 25-Feb-24 71 188
GR-CON-Z03-1370 Excavation Curbstone 05-Dec-23 13-Dec-23 8 140
GR-CON-Z03-1371 Plain Concrete 14-Dec-23 24-Dec-23 9 188
GR-CON-Z03-1372 Installation Curbstone 25-Dec-23 09-Jan-24 14 188
GR-CON-Z03-1373 Casting Concrete (Mortar haunch) 10-Jan-24 16-Jan-24 6 188
GR-CON-Z03-1374 Backfilling (sand / Sub base) 17-Jan-24 01-Feb-24 14 188
GR-CON-Z03-1375 Installation of Paving 03-Feb-24 25-Feb-24 20 188
Landscape Works 14-Dec-23 26-Jun-24 153 66
GR-CON-Z03-1376 Excavation (Tree Pit ) 14-Dec-23 23-Dec-23 8 140
GR-CON-Z03-1377 Aggregate Drainage layer 24-Dec-23 02-Jan-24 9 140
GR-CON-Z03-1378 Installation Geotextile 03-Jan-24 09-Jan-24 6 140
GR-CON-Z03-1379 Backfilling (Soil max for tree) 10-Jan-24 20-Jan-24 9 140
GR-CON-Z03-1380 Installation of Trees 28-Apr-24 02-May-24 4 66
GR-CON-Z03-9616 Installation of Shrubs 02-May-24 06-May-24 3 66
GR-CON-Z03-9626 Installation of Succulents 06-May-24 09-May-24 3 66
GR-CON-Z03-9636 Installation of Ground Covers 09-May-24 13-May-24 3 66
GR-CON-Z03-9646 Installation of Grass 13-May-24 16-May-24 3 66
GR-CON-Z03-1381 Backfilling (Mulch) 16-May-24 22-May-24 5 66
GR-CON-Z03-1382 Natural Boulders Installation 22-May-24 29-May-24 6 66
GR-CON-Z03-1383 Retaining walls . Steps, forming risers, treads and edges with finishes
29-May-24 26-Jun-24 20 66
Site Furnishing 26-Jun-24 03-Aug-24 32 66
GR-CON-Z03-1392 Garden planter box 26-Jun-24 06-Jul-24 8 66
GR-CON-Z03-1393 Wheel stoppers 06-Jul-24 15-Jul-24 8 66
GR-CON-Z03-1394 Steel Lattice 15-Jul-24 24-Jul-24 8 66
GR-CON-Z03-1395 Handrail 24-Jul-24 03-Aug-24 8 66
Storm Piping Works 23-Jul-24 03-Aug-24 9 66
GR-CON-Z03-1396 Installation of DI grating covers 23-Jul-24 03-Aug-24 9 66
Irrigation Works 05-Dec-23 07-Mar-24 81 169
GR-CON-Z03-1384 Excavation Pipe Irrigation 05-Dec-23 13-Dec-23 8 101
GR-CON-Z03-1385 Sand Bedding 14-Dec-23 20-Dec-23 6 101
GR-CON-Z03-1386 HDPE Pipe Installations and fittings and conduit for cable 21-Dec-23 16-Jan-24 23 101
GR-CON-Z03-1388 Test pressure 17-Jan-24 25-Jan-24 8 101
GR-CON-Z03-1387 Installation of Valves and Accessories 27-Jan-24 01-Feb-24 6 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z03-1389 Back filling (sand / Subbase ) 03-Feb-24 12-Feb-24 9 101


GR-CON-Z03-1390 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Feb-24 22-Feb-24 9 169
GR-CON-Z03-1391 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Feb-24
system 07-Mar-24 12 169
Electrical Works 14-Dec-23 03-Aug-24 185 66
GR-CON-Z03-1397 Excavation And Disposal 14-Dec-23 23-Dec-23 8 209
GR-CON-Z03-1398 Sand Bedding 24-Dec-23 30-Dec-23 6 209
GR-CON-Z03-1399 laying cables 31-Dec-23 06-Jan-24 6 209
GR-CON-Z03-1400 Backfilling (sand / Sub base) 07-Jan-24 15-Jan-24 8 209
GR-CON-Z03-1401 Control Panel / Distribution Panel Installation 16-Jan-24 22-Jan-24 6 209
GR-CON-Z03-1402 Road Crossing Ducts 24-Jul-24 03-Aug-24 8 66
School S-04 26-Nov-23 01-Jul-24 173 94
Site Preparation 26-Nov-23 05-Dec-23 9 258
GR-CON-Z03-1191 Excavation And Disposal 26-Nov-23 30-Nov-23 5 126
GR-CON-Z03-1192 Prepretion And Compaction 02-Dec-23 05-Dec-23 4 258
Curbstone and Paving 02-Dec-23 23-Jan-24 46 216
GR-CON-Z03-1194 Excavation Curbstone 02-Dec-23 06-Dec-23 5 185
GR-CON-Z03-1195 Plain Concrete 07-Dec-23 13-Dec-23 6 216
GR-CON-Z03-1196 Installation Curbstone 14-Dec-23 24-Dec-23 9 216
GR-CON-Z03-1197 Casting Concrete (Mortar haunch) 25-Dec-23 28-Dec-23 4 216
GR-CON-Z03-1198 Backfilling (sand / Sub base) 30-Dec-23 08-Jan-24 9 216
GR-CON-Z03-1199 Installation of Paving 09-Jan-24 23-Jan-24 13 216
Landscape Works 07-Dec-23 15-Jun-24 153 94
GR-CON-Z03-1200 Excavation (Tree Pit ) 07-Dec-23 12-Dec-23 5 185
GR-CON-Z03-1201 Aggregate Drainage layer 13-Dec-23 19-Dec-23 6 185
GR-CON-Z03-1202 Installation Geotextile 20-Dec-23 24-Dec-23 4 185
GR-CON-Z03-1203 Backfilling (Soil max for tree) 25-Dec-23 31-Dec-23 6 185
GR-CON-Z03-1204 Installation of Trees 28-Apr-24 01-May-24 3 94
GR-CON-Z03-5236 Installation of Shrubs 01-May-24 05-May-24 3 94
GR-CON-Z03-5246 Installation of Succulents 05-May-24 08-May-24 3 94
GR-CON-Z03-5256 Installation of Ground Covers 08-May-24 12-May-24 3 94
GR-CON-Z03-5266 Installation of Climbers 12-May-24 15-May-24 3 94
GR-CON-Z03-5276 Installation of Grass 15-May-24 19-May-24 3 94
GR-CON-Z03-5286 Installation of Lawns 19-May-24 22-May-24 3 94
GR-CON-Z03-1205 Backfilling (Mulch) 22-May-24 26-May-24 3 94
GR-CON-Z03-1206 Natural Boulders Installation 26-May-24 30-May-24 4 94
GR-CON-Z03-1207 Retaining walls . Steps, forming risers, treads and edges with finishes
30-May-24 15-Jun-24 13 94
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Furnishing 15-Jun-24 01-Jul-24 10 94


GR-CON-Z03-1216 Garden planter box 15-Jun-24 25-Jun-24 5 94
GR-CON-Z03-1217 Wheel stoppers 25-Jun-24 01-Jul-24 5 94
Irrigation Works 02-Dec-23 01-Jul-24 168 94
GR-CON-Z03-1208 Excavation Pipe Irrigation 02-Dec-23 06-Dec-23 5 126
GR-CON-Z03-1209 Sand Bedding 07-Dec-23 10-Dec-23 3 126
GR-CON-Z03-1210 HDPE Pipe Installations and fittings and conduit for cable 11-Dec-23 27-Dec-23 15 126
GR-CON-Z03-1212 Test pressure 28-Dec-23 02-Jan-24 5 126
GR-CON-Z03-1211 Installation of Valves and Accessories 03-Jan-24 07-Jan-24 4 126
GR-CON-Z03-1213 Back filling (sand / Subbase ) 08-Jan-24 14-Jan-24 6 126
GR-CON-Z03-1214 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Jan-24 21-Jan-24 6 210
GR-CON-Z03-1215 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Jun-24
system 01-Jul-24 8 94
Zone 06 26-Sep-23 22-Oct-24 322 15
Future Neighborhood Park FNP-09 26-Sep-23 01-Aug-24 253 84
Site Preparation 26-Sep-23 18-Oct-23 20 22
GR-CON-Z06-1018 Demolition (Asphalt.Paving,etc.....) 26-Sep-23 30-Sep-23 4 22
GR-CON-Z06-1019 Excavation And Disposal 01-Oct-23 07-Oct-23 6 22
GR-CON-Z06-1020 Prepretion And Compaction 08-Oct-23 11-Oct-23 4 22
GR-CON-Z06-1021 Backfilling 12-Oct-23 18-Oct-23 6 22
Curbstone and Paving 08-Oct-23 29-Nov-23 46 281
GR-CON-Z06-1022 Excavation Curbstone 08-Oct-23 12-Oct-23 5 267
GR-CON-Z06-1023 Plain Concrete 14-Oct-23 19-Oct-23 6 281
GR-CON-Z06-1024 Installation Curbstone 21-Oct-23 30-Oct-23 9 281
GR-CON-Z06-1025 Casting Concrete (Mortar haunch) 31-Oct-23 04-Nov-23 4 281
GR-CON-Z06-1026 Backfilling (sand / Sub base) 05-Nov-23 14-Nov-23 9 281
GR-CON-Z06-1027 Installation of Paving 15-Nov-23 29-Nov-23 13 281
Landscape Works 14-Oct-23 01-Aug-24 238 84
GR-CON-Z06-1028 Excavation (Tree Pit ) 14-Oct-23 18-Oct-23 5 267
GR-CON-Z06-1029 Aggregate Drainage layer 19-Oct-23 25-Oct-23 6 267
GR-CON-Z06-1030 Installation Geotextile 26-Oct-23 30-Oct-23 4 267
GR-CON-Z06-1031 Backfilling (Soil max for tree) 31-Oct-23 06-Nov-23 6 267
GR-CON-Z06-1032 Installation of Trees 24-Jun-24 25-Jun-24 2 84
GR-CON-Z06-1806 Installation of Shrubs 26-Jun-24 27-Jun-24 2 84
GR-CON-Z06-1816 Installation of Succulents 29-Jun-24 30-Jun-24 2 84
GR-CON-Z06-1826 Installation of Ground Covers 01-Jul-24 02-Jul-24 2 84
GR-CON-Z06-1836 Installation of Climbers 03-Jul-24 04-Jul-24 2 84
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1846 Installation of Grass 06-Jul-24 07-Jul-24 2 84


GR-CON-Z06-1856 Installation of Lawns 08-Jul-24 09-Jul-24 2 84
GR-CON-Z06-1033 Backfilling (Mulch) 10-Jul-24 13-Jul-24 3 84
GR-CON-Z06-1034 Natural Boulders Installation 14-Jul-24 17-Jul-24 4 84
GR-CON-Z06-1035 Retaining walls . Steps, forming risers, treads and edges with finishes
18-Jul-24 01-Aug-24 13 84
Irrigation Works 08-Oct-23 01-Aug-24 243 84
GR-CON-Z06-1036 Excavation Pipe Irrigation 08-Oct-23 12-Oct-23 5 186
GR-CON-Z06-1037 Sand Bedding 14-Oct-23 16-Oct-23 3 186
GR-CON-Z06-1038 HDPE Pipe Installations and fittings and conduit for cable 17-Oct-23 02-Nov-23 15 186
GR-CON-Z06-1040 Test pressure 04-Nov-23 08-Nov-23 5 186
GR-CON-Z06-1039 Installation of Valves and Accessories 09-Nov-23 13-Nov-23 4 186
GR-CON-Z06-1041 Back filling (sand / Subbase ) 14-Nov-23 20-Nov-23 6 186
GR-CON-Z06-1042 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Nov-23 27-Nov-23 6 275
GR-CON-Z06-1043 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Jul-24
system 01-Aug-24 8 84
Mosque M-14 01-Oct-23 04-Sep-24 278 55
Site Preparation 01-Oct-23 22-Oct-23 19 292
GR-CON-Z06-1044 Demolition (Asphalt.Paving,etc.....) 01-Oct-23 04-Oct-23 4 78
GR-CON-Z06-1045 Excavation And Disposal 05-Oct-23 10-Oct-23 5 183
GR-CON-Z06-1046 Prepretion And Compaction 11-Oct-23 15-Oct-23 4 292
GR-CON-Z06-1047 Backfilling 16-Oct-23 22-Oct-23 6 292
Curbstone and Paving 23-Oct-23 16-Nov-23 22 292
GR-CON-Z06-1052 Backfilling (sand / Sub base) 23-Oct-23 01-Nov-23 9 292
GR-CON-Z06-1053 Installation of Paving 02-Nov-23 16-Nov-23 13 292
Landscape Works 11-Oct-23 04-Sep-24 269 55
GR-CON-Z06-1054 Excavation (Tree Pit ) 11-Oct-23 16-Oct-23 5 240
GR-CON-Z06-1055 Aggregate Drainage layer 17-Oct-23 23-Oct-23 6 240
GR-CON-Z06-1056 Installation Geotextile 24-Oct-23 29-Oct-23 5 240
GR-CON-Z06-1057 Backfilling (Soil max for tree) 30-Oct-23 04-Nov-23 5 240
GR-CON-Z06-1058 Installation of Trees 24-Jun-24 27-Jun-24 4 55
GR-CON-Z06-3586 Installation of Climbers 29-Jun-24 02-Jul-24 4 55
GR-CON-Z06-3596 Installation of Shrubs 03-Jul-24 07-Jul-24 4 55
GR-CON-Z06-3606 Installation of Succulents 08-Jul-24 11-Jul-24 4 55
GR-CON-Z06-3616 Installation of Ground Covers 13-Jul-24 16-Jul-24 4 55
GR-CON-Z06-1059 Backfilling (Mulch) 17-Jul-24 03-Aug-24 15 55
GR-CON-Z06-1060 Natural Boulders Installation 04-Aug-24 18-Aug-24 13 55
GR-CON-Z06-1061 Retaining walls . Steps, forming risers, treads and edges with finishes
19-Aug-24 04-Sep-24 15 55
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 11-Oct-23 04-Sep-24 269 55


GR-CON-Z06-1062 Excavation Pipe Irrigation 11-Oct-23 16-Oct-23 5 183
GR-CON-Z06-1063 Sand Bedding 17-Oct-23 19-Oct-23 3 183
GR-CON-Z06-1064 HDPE Pipe Installations and fittings and conduit for cable 21-Oct-23 06-Nov-23 15 183
GR-CON-Z06-1066 Test pressure 07-Nov-23 12-Nov-23 5 183
GR-CON-Z06-1065 Installation of Valves and Accessories 13-Nov-23 16-Nov-23 4 183
GR-CON-Z06-1067 Back filling (sand / Subbase ) 18-Nov-23 23-Nov-23 6 183
GR-CON-Z06-1068 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-Nov-23 30-Nov-23 6 274
GR-CON-Z06-1069 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
29-Aug-24
system 04-Sep-24 6 55
Mosque M-15 05-Oct-23 04-Sep-24 274 55
Site Preparation 05-Oct-23 26-Oct-23 19 288
GR-CON-Z06-1070 Demolition (Asphalt.Paving,etc.....) 05-Oct-23 09-Oct-23 4 78
GR-CON-Z06-1071 Excavation And Disposal 10-Oct-23 15-Oct-23 5 179
GR-CON-Z06-1072 Prepretion And Compaction 16-Oct-23 19-Oct-23 4 288
GR-CON-Z06-1073 Backfilling 21-Oct-23 26-Oct-23 6 288
Curbstone and Paving 28-Oct-23 21-Nov-23 22 288
GR-CON-Z06-1078 Backfilling (sand / Sub base) 28-Oct-23 06-Nov-23 9 288
GR-CON-Z06-1079 Installation of Paving 07-Nov-23 21-Nov-23 13 288
Landscape Works 16-Oct-23 04-Sep-24 265 55
GR-CON-Z06-1080 Excavation (Tree Pit ) 16-Oct-23 21-Oct-23 5 236
GR-CON-Z06-1081 Aggregate Drainage layer 22-Oct-23 28-Oct-23 6 236
GR-CON-Z06-1082 Installation Geotextile 29-Oct-23 02-Nov-23 5 236
GR-CON-Z06-1083 Backfilling (Soil max for tree) 04-Nov-23 08-Nov-23 5 236
GR-CON-Z06-1084 Installation of Trees 24-Jun-24 27-Jun-24 4 55
GR-CON-Z06-3626 Installation of Climbers 29-Jun-24 02-Jul-24 4 55
GR-CON-Z06-3636 Installation of Shrubs 03-Jul-24 07-Jul-24 4 55
GR-CON-Z06-3646 Installation of Succulents 08-Jul-24 11-Jul-24 4 55
GR-CON-Z06-3656 Installation of Ground Covers 13-Jul-24 16-Jul-24 4 55
GR-CON-Z06-1085 Backfilling (Mulch) 17-Jul-24 03-Aug-24 15 55
GR-CON-Z06-1086 Natural Boulders Installation 04-Aug-24 18-Aug-24 13 55
GR-CON-Z06-1087 Retaining walls . Steps, forming risers, treads and edges with finishes
19-Aug-24 04-Sep-24 15 55
Irrigation Works 16-Oct-23 04-Sep-24 265 55
GR-CON-Z06-1088 Excavation Pipe Irrigation 16-Oct-23 21-Oct-23 5 179
GR-CON-Z06-1089 Sand Bedding 22-Oct-23 24-Oct-23 3 179
GR-CON-Z06-1090 HDPE Pipe Installations and fittings and conduit for cable 25-Oct-23 11-Nov-23 15 179
GR-CON-Z06-1092 Test pressure 12-Nov-23 16-Nov-23 5 179
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1091 Installation of Valves and Accessories 18-Nov-23 21-Nov-23 4 179


GR-CON-Z06-1093 Back filling (sand / Subbase ) 22-Nov-23 28-Nov-23 6 179
GR-CON-Z06-1094 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Nov-23 05-Dec-23 6 270
GR-CON-Z06-1095 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
29-Aug-24
system 04-Sep-24 6 55
Parking P-18 10-Oct-23 25-Jul-24 235 90
Site Preparation 10-Oct-23 31-Oct-23 19 293
GR-CON-Z06-1096 Demolition (Asphalt.Paving,etc.....) 10-Oct-23 14-Oct-23 4 78
GR-CON-Z06-1097 Excavation And Disposal 15-Oct-23 19-Oct-23 5 175
GR-CON-Z06-1098 Prepretion And Compaction 21-Oct-23 24-Oct-23 4 293
GR-CON-Z06-1099 Backfilling 25-Oct-23 31-Oct-23 6 293
Curbstone and Paving 21-Oct-23 12-Dec-23 46 270
GR-CON-Z06-1100 Excavation Curbstone 21-Oct-23 25-Oct-23 5 262
GR-CON-Z06-1101 Plain Concrete 26-Oct-23 01-Nov-23 6 270
GR-CON-Z06-1102 Installation Curbstone 02-Nov-23 12-Nov-23 9 270
GR-CON-Z06-1103 Casting Concrete (Mortar haunch) 13-Nov-23 16-Nov-23 4 270
GR-CON-Z06-1104 Backfilling (sand / Sub base) 18-Nov-23 27-Nov-23 9 270
GR-CON-Z06-1105 Installation of Paving 28-Nov-23 12-Dec-23 13 270
Landscape Works 26-Oct-23 14-Jul-24 211 90
GR-CON-Z06-1106 Excavation (Tree Pit ) 26-Oct-23 31-Oct-23 5 262
GR-CON-Z06-1107 Aggregate Drainage layer 01-Nov-23 07-Nov-23 6 262
GR-CON-Z06-1108 Installation Geotextile 08-Nov-23 12-Nov-23 4 262
GR-CON-Z06-1109 Backfilling (Soil max for tree) 13-Nov-23 19-Nov-23 6 262
GR-CON-Z06-1110 Installation of Trees 24-Jun-24 26-Jun-24 3 90
GR-CON-Z06-7136 Installation of Shrubs 27-Jun-24 30-Jun-24 3 90
GR-CON-Z06-7146 Installation of Ground Covers 01-Jul-24 03-Jul-24 3 90
GR-CON-Z06-7156 Installation of Succulents 04-Jul-24 07-Jul-24 3 90
GR-CON-Z06-7166 Installation of Grass 08-Jul-24 10-Jul-24 3 90
GR-CON-Z06-1111 Backfilling (Mulch) 11-Jul-24 14-Jul-24 3 90
Site Furnishing 15-Jul-24 25-Jul-24 10 90
GR-CON-Z06-1122 Tree Grate 15-Jul-24 20-Jul-24 5 90
GR-CON-Z06-1123 Wheel stoppers 21-Jul-24 25-Jul-24 5 90
Irrigation Works 21-Oct-23 25-Jul-24 226 90
GR-CON-Z06-1114 Excavation Pipe Irrigation 21-Oct-23 25-Oct-23 5 175
GR-CON-Z06-1115 Sand Bedding 26-Oct-23 29-Oct-23 3 175
GR-CON-Z06-1116 HDPE Pipe Installations and fittings and conduit for cable 30-Oct-23 15-Nov-23 15 175
GR-CON-Z06-1118 Test pressure 16-Nov-23 21-Nov-23 5 175
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1117 Installation of Valves and Accessories 22-Nov-23 26-Nov-23 4 175


GR-CON-Z06-1119 Back filling (sand / Subbase ) 27-Nov-23 03-Dec-23 6 175
GR-CON-Z06-1120 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Dec-23 10-Dec-23 6 264
GR-CON-Z06-1121 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Jul-24
system 25-Jul-24 8 90
Parking P-34 15-Oct-23 25-Jul-24 231 90
Site Preparation 15-Oct-23 05-Nov-23 19 289
GR-CON-Z06-1124 Demolition (Asphalt.Paving,etc.....) 15-Oct-23 18-Oct-23 4 78
GR-CON-Z06-1125 Excavation And Disposal 19-Oct-23 24-Oct-23 5 171
GR-CON-Z06-1126 Prepretion And Compaction 25-Oct-23 29-Oct-23 4 289
GR-CON-Z06-1127 Backfilling 30-Oct-23 05-Nov-23 6 289
Curbstone and Paving 25-Oct-23 17-Dec-23 46 266
GR-CON-Z06-1128 Excavation Curbstone 25-Oct-23 30-Oct-23 5 258
GR-CON-Z06-1129 Plain Concrete 31-Oct-23 06-Nov-23 6 266
GR-CON-Z06-1130 Installation Curbstone 07-Nov-23 16-Nov-23 9 266
GR-CON-Z06-1131 Casting Concrete (Mortar haunch) 18-Nov-23 21-Nov-23 4 266
GR-CON-Z06-1132 Backfilling (sand / Sub base) 22-Nov-23 02-Dec-23 9 266
GR-CON-Z06-1133 Installation of Paving 03-Dec-23 17-Dec-23 13 266
Landscape Works 31-Oct-23 14-Jul-24 207 90
GR-CON-Z06-1134 Excavation (Tree Pit ) 31-Oct-23 05-Nov-23 5 258
GR-CON-Z06-1135 Aggregate Drainage layer 06-Nov-23 12-Nov-23 6 258
GR-CON-Z06-1136 Installation Geotextile 13-Nov-23 16-Nov-23 4 258
GR-CON-Z06-1137 Backfilling (Soil max for tree) 18-Nov-23 23-Nov-23 6 258
GR-CON-Z06-1138 Installation of Trees 24-Jun-24 26-Jun-24 3 90
GR-CON-Z06-7176 Installation of Shrubs 27-Jun-24 30-Jun-24 3 90
GR-CON-Z06-7186 Installation of Ground Covers 01-Jul-24 03-Jul-24 3 90
GR-CON-Z06-7196 Installation of Succulents 04-Jul-24 07-Jul-24 3 90
GR-CON-Z06-7206 Installation of Grass 08-Jul-24 10-Jul-24 3 90
GR-CON-Z06-1139 Backfilling (Mulch) 11-Jul-24 14-Jul-24 3 90
Site Furnishing 15-Jul-24 25-Jul-24 10 90
GR-CON-Z06-1150 Tree Grate 15-Jul-24 20-Jul-24 5 90
GR-CON-Z06-1151 Wheel stoppers 21-Jul-24 25-Jul-24 5 90
Irrigation Works 25-Oct-23 25-Jul-24 222 90
GR-CON-Z06-1142 Excavation Pipe Irrigation 25-Oct-23 30-Oct-23 5 171
GR-CON-Z06-1143 Sand Bedding 31-Oct-23 02-Nov-23 3 171
GR-CON-Z06-1144 HDPE Pipe Installations and fittings and conduit for cable 04-Nov-23 20-Nov-23 15 171
GR-CON-Z06-1146 Test pressure 21-Nov-23 26-Nov-23 5 171
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1145 Installation of Valves and Accessories 27-Nov-23 30-Nov-23 4 171


GR-CON-Z06-1147 Back filling (sand / Subbase ) 02-Dec-23 07-Dec-23 6 171
GR-CON-Z06-1148 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Dec-23 14-Dec-23 6 260
GR-CON-Z06-1149 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Jul-24
system 25-Jul-24 8 90
Street SS-109 19-Oct-23 26-Aug-24 254 63
Site Preparation 19-Oct-23 12-Nov-23 21 296
GR-CON-Z06-1180 Demolition (Asphalt.Paving,etc.....) 19-Oct-23 23-Oct-23 4 78
GR-CON-Z06-1181 Excavation And Disposal 24-Oct-23 29-Oct-23 5 166
GR-CON-Z06-1182 Prepretion And Compaction 30-Oct-23 05-Nov-23 6 296
GR-CON-Z06-1183 Backfilling 06-Nov-23 12-Nov-23 6 296
Curbstone and Paving 30-Oct-23 21-Dec-23 46 262
GR-CON-Z06-1184 Excavation Curbstone 30-Oct-23 04-Nov-23 5 227
GR-CON-Z06-1185 Plain Concrete 05-Nov-23 11-Nov-23 6 262
GR-CON-Z06-1186 Installation Curbstone 12-Nov-23 21-Nov-23 9 262
GR-CON-Z06-1187 Casting Concrete (Mortar haunch) 22-Nov-23 26-Nov-23 4 262
GR-CON-Z06-1188 Backfilling (sand / Sub base) 27-Nov-23 06-Dec-23 9 262
GR-CON-Z06-1189 Installation of Paving 07-Dec-23 21-Dec-23 13 262
Landscape Works 05-Nov-23 03-Aug-24 220 63
GR-CON-Z06-1190 Excavation (Tree Pit ) 05-Nov-23 09-Nov-23 5 227
GR-CON-Z06-1191 Aggregate Drainage layer 11-Nov-23 16-Nov-23 6 227
GR-CON-Z06-1192 Installation Geotextile 18-Nov-23 21-Nov-23 4 227
GR-CON-Z06-1193 Backfilling (Soil max for tree) 22-Nov-23 28-Nov-23 6 227
GR-CON-Z06-1194 Installation of Trees 24-Jun-24 26-Jun-24 3 63
GR-CON-Z06-10096 Installation of Shrubs 27-Jun-24 30-Jun-24 3 63
GR-CON-Z06-10106 Installation of Succulents 01-Jul-24 03-Jul-24 3 63
GR-CON-Z06-10116 Installation of Ground Covers 04-Jul-24 07-Jul-24 3 63
GR-CON-Z06-10126 Installation of Grass 08-Jul-24 10-Jul-24 3 63
GR-CON-Z06-1195 Backfilling (Mulch) 11-Jul-24 14-Jul-24 3 63
GR-CON-Z06-1196 Natural Boulders Installation 15-Jul-24 18-Jul-24 4 63
GR-CON-Z06-1197 Retaining walls . Steps, forming risers, treads and edges with finishes
20-Jul-24 03-Aug-24 13 63
Site Furnishing 04-Aug-24 26-Aug-24 20 63
GR-CON-Z06-1206 Garden planter box 04-Aug-24 08-Aug-24 5 63
GR-CON-Z06-1207 Wheel stoppers 10-Aug-24 14-Aug-24 5 63
GR-CON-Z06-1208 Steel Lattice 15-Aug-24 20-Aug-24 5 63
GR-CON-Z06-1209 Handrail 21-Aug-24 26-Aug-24 5 63
Storm Piping Works 20-Aug-24 26-Aug-24 6 63
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1210 Installation of DI grating covers 20-Aug-24 26-Aug-24 6 63


Irrigation Works 30-Oct-23 30-Dec-23 53 249
GR-CON-Z06-1198 Excavation Pipe Irrigation 30-Oct-23 04-Nov-23 5 166
GR-CON-Z06-1199 Sand Bedding 05-Nov-23 08-Nov-23 4 166
GR-CON-Z06-1200 HDPE Pipe Installations and fittings and conduit for cable 09-Nov-23 26-Nov-23 15 166
GR-CON-Z06-1202 Test pressure 27-Nov-23 02-Dec-23 5 166
GR-CON-Z06-1201 Installation of Valves and Accessories 03-Dec-23 06-Dec-23 4 166
GR-CON-Z06-1203 Back filling (sand / Subbase ) 07-Dec-23 13-Dec-23 6 166
GR-CON-Z06-1204 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Dec-23 20-Dec-23 6 249
GR-CON-Z06-1205 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-Dec-23
system 30-Dec-23 8 249
Electrical Works 05-Nov-23 26-Aug-24 240 63
GR-CON-Z06-1211 Excavation And Disposal 05-Nov-23 09-Nov-23 5 276
GR-CON-Z06-1212 Sand Bedding 11-Nov-23 14-Nov-23 4 276
GR-CON-Z06-1213 laying cables 15-Nov-23 19-Nov-23 4 276
GR-CON-Z06-1214 Backfilling (sand / Sub base) 20-Nov-23 25-Nov-23 5 276
GR-CON-Z06-1215 Control Panel / Distribution Panel Installation 26-Nov-23 29-Nov-23 4 276
GR-CON-Z06-1216 Road Crossing Ducts 21-Aug-24 26-Aug-24 5 63
Street SS-110 29-Oct-23 26-Aug-24 245 63
Site Preparation 29-Oct-23 22-Nov-23 21 287
GR-CON-Z06-1217 Demolition (Asphalt.Paving,etc.....) 29-Oct-23 02-Nov-23 4 73
GR-CON-Z06-1218 Excavation And Disposal 02-Nov-23 08-Nov-23 5 157
GR-CON-Z06-1219 Prepretion And Compaction 08-Nov-23 15-Nov-23 6 287
GR-CON-Z06-1220 Backfilling 15-Nov-23 22-Nov-23 6 287
Curbstone and Paving 08-Nov-23 01-Jan-24 46 253
GR-CON-Z06-1221 Excavation Curbstone 08-Nov-23 14-Nov-23 5 218
GR-CON-Z06-1222 Plain Concrete 14-Nov-23 21-Nov-23 6 253
GR-CON-Z06-1223 Installation Curbstone 21-Nov-23 02-Dec-23 9 253
GR-CON-Z06-1224 Casting Concrete (Mortar haunch) 02-Dec-23 06-Dec-23 4 253
GR-CON-Z06-1225 Backfilling (sand / Sub base) 06-Dec-23 17-Dec-23 9 253
GR-CON-Z06-1226 Installation of Paving 17-Dec-23 01-Jan-24 13 253
Landscape Works 14-Nov-23 03-Aug-24 211 63
GR-CON-Z06-1227 Excavation (Tree Pit ) 14-Nov-23 20-Nov-23 5 218
GR-CON-Z06-1228 Aggregate Drainage layer 20-Nov-23 27-Nov-23 6 218
GR-CON-Z06-1229 Installation Geotextile 27-Nov-23 02-Dec-23 4 218
GR-CON-Z06-1230 Backfilling (Soil max for tree) 02-Dec-23 09-Dec-23 6 218
GR-CON-Z06-1231 Installation of Trees 24-Jun-24 26-Jun-24 3 63
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-10136 Installation of Shrubs 27-Jun-24 30-Jun-24 3 63


GR-CON-Z06-10146 Installation of Succulents 01-Jul-24 03-Jul-24 3 63
GR-CON-Z06-10156 Installation of Ground Covers 04-Jul-24 07-Jul-24 3 63
GR-CON-Z06-10166 Installation of Grass 08-Jul-24 10-Jul-24 3 63
GR-CON-Z06-1232 Backfilling (Mulch) 11-Jul-24 14-Jul-24 3 63
GR-CON-Z06-1233 Natural Boulders Installation 15-Jul-24 18-Jul-24 4 63
GR-CON-Z06-1234 Retaining walls . Steps, forming risers, treads and edges with finishes
20-Jul-24 03-Aug-24 13 63
Site Furnishing 04-Aug-24 26-Aug-24 20 63
GR-CON-Z06-1243 Garden planter box 04-Aug-24 08-Aug-24 5 63
GR-CON-Z06-1244 Wheel stoppers 10-Aug-24 14-Aug-24 5 63
GR-CON-Z06-1245 Steel Lattice 15-Aug-24 20-Aug-24 5 63
GR-CON-Z06-1246 Handrail 21-Aug-24 26-Aug-24 5 63
Storm Piping Works 20-Aug-24 26-Aug-24 6 63
GR-CON-Z06-1247 Installation of DI grating covers 20-Aug-24 26-Aug-24 6 63
Irrigation Works 08-Nov-23 09-Jan-24 53 240
GR-CON-Z06-1235 Excavation Pipe Irrigation 08-Nov-23 14-Nov-23 5 157
GR-CON-Z06-1236 Sand Bedding 14-Nov-23 19-Nov-23 4 157
GR-CON-Z06-1237 HDPE Pipe Installations and fittings and conduit for cable 19-Nov-23 06-Dec-23 15 157
GR-CON-Z06-1239 Test pressure 06-Dec-23 12-Dec-23 5 157
GR-CON-Z06-1238 Installation of Valves and Accessories 12-Dec-23 17-Dec-23 4 157
GR-CON-Z06-1240 Back filling (sand / Subbase ) 17-Dec-23 24-Dec-23 6 157
GR-CON-Z06-1241 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Dec-23 31-Dec-23 6 240
GR-CON-Z06-1242 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
31-Dec-23
system 09-Jan-24 8 240
Electrical Works 14-Nov-23 26-Aug-24 231 63
GR-CON-Z06-1248 Excavation And Disposal 14-Nov-23 20-Nov-23 5 267
GR-CON-Z06-1249 Sand Bedding 20-Nov-23 25-Nov-23 4 267
GR-CON-Z06-1250 laying cables 25-Nov-23 29-Nov-23 4 267
GR-CON-Z06-1251 Backfilling (sand / Sub base) 29-Nov-23 05-Dec-23 5 267
GR-CON-Z06-1252 Control Panel / Distribution Panel Installation 05-Dec-23 10-Dec-23 4 267
GR-CON-Z06-1253 Road Crossing Ducts 21-Aug-24 26-Aug-24 5 63
Street SS-111 08-Nov-23 26-Aug-24 236 63
Site Preparation 08-Nov-23 03-Dec-23 21 278
GR-CON-Z06-1254 Demolition (Asphalt.Paving,etc.....) 08-Nov-23 13-Nov-23 4 68
GR-CON-Z06-1255 Excavation And Disposal 13-Nov-23 19-Nov-23 5 148
GR-CON-Z06-1256 Prepretion And Compaction 19-Nov-23 26-Nov-23 6 278
GR-CON-Z06-1257 Backfilling 26-Nov-23 03-Dec-23 6 278
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 19-Nov-23 11-Jan-24 46 244


GR-CON-Z06-1258 Excavation Curbstone 19-Nov-23 25-Nov-23 5 209
GR-CON-Z06-1259 Plain Concrete 25-Nov-23 02-Dec-23 6 244
GR-CON-Z06-1260 Installation Curbstone 02-Dec-23 12-Dec-23 9 244
GR-CON-Z06-1261 Casting Concrete (Mortar haunch) 12-Dec-23 17-Dec-23 4 244
GR-CON-Z06-1262 Backfilling (sand / Sub base) 17-Dec-23 27-Dec-23 9 244
GR-CON-Z06-1263 Installation of Paving 27-Dec-23 11-Jan-24 13 244
Landscape Works 25-Nov-23 03-Aug-24 202 63
GR-CON-Z06-1264 Excavation (Tree Pit ) 25-Nov-23 30-Nov-23 5 209
GR-CON-Z06-1265 Aggregate Drainage layer 30-Nov-23 07-Dec-23 6 209
GR-CON-Z06-1266 Installation Geotextile 07-Dec-23 12-Dec-23 4 209
GR-CON-Z06-1267 Backfilling (Soil max for tree) 12-Dec-23 19-Dec-23 6 209
GR-CON-Z06-1268 Installation of Trees 24-Jun-24 26-Jun-24 3 63
GR-CON-Z06-10176 Installation of Shrubs 27-Jun-24 30-Jun-24 3 63
GR-CON-Z06-10186 Installation of Succulents 01-Jul-24 03-Jul-24 3 63
GR-CON-Z06-10196 Installation of Ground Covers 04-Jul-24 07-Jul-24 3 63
GR-CON-Z06-10206 Installation of Grass 08-Jul-24 10-Jul-24 3 63
GR-CON-Z06-1269 Backfilling (Mulch) 11-Jul-24 14-Jul-24 3 63
GR-CON-Z06-1270 Natural Boulders Installation 15-Jul-24 18-Jul-24 4 63
GR-CON-Z06-1271 Retaining walls . Steps, forming risers, treads and edges with finishes
20-Jul-24 03-Aug-24 13 63
Site Furnishing 04-Aug-24 26-Aug-24 20 63
GR-CON-Z06-1280 Garden planter box 04-Aug-24 08-Aug-24 5 63
GR-CON-Z06-1281 Wheel stoppers 10-Aug-24 14-Aug-24 5 63
GR-CON-Z06-1282 Steel Lattice 15-Aug-24 20-Aug-24 5 63
GR-CON-Z06-1283 Handrail 21-Aug-24 26-Aug-24 5 63
Storm Piping Works 20-Aug-24 26-Aug-24 6 63
GR-CON-Z06-1284 Installation of DI grating covers 20-Aug-24 26-Aug-24 6 63
Irrigation Works 19-Nov-23 20-Jan-24 53 231
GR-CON-Z06-1272 Excavation Pipe Irrigation 19-Nov-23 25-Nov-23 5 148
GR-CON-Z06-1273 Sand Bedding 25-Nov-23 29-Nov-23 4 148
GR-CON-Z06-1274 HDPE Pipe Installations and fittings and conduit for cable 29-Nov-23 17-Dec-23 15 148
GR-CON-Z06-1276 Test pressure 17-Dec-23 23-Dec-23 5 148
GR-CON-Z06-1275 Installation of Valves and Accessories 23-Dec-23 27-Dec-23 4 148
GR-CON-Z06-1277 Back filling (sand / Subbase ) 27-Dec-23 03-Jan-24 6 148
GR-CON-Z06-1278 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Jan-24 10-Jan-24 6 231
GR-CON-Z06-1279 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Jan-24
system 20-Jan-24 8 231
Activity ID Activity Name Start Finish Original Total Float
Duration

Electrical Works 25-Nov-23 26-Aug-24 222 63


GR-CON-Z06-1285 Excavation And Disposal 25-Nov-23 30-Nov-23 5 258
GR-CON-Z06-1286 Sand Bedding 30-Nov-23 05-Dec-23 4 258
GR-CON-Z06-1287 laying cables 05-Dec-23 10-Dec-23 4 258
GR-CON-Z06-1288 Backfilling (sand / Sub base) 10-Dec-23 16-Dec-23 5 258
GR-CON-Z06-1289 Control Panel / Distribution Panel Installation 16-Dec-23 20-Dec-23 4 258
GR-CON-Z06-1290 Road Crossing Ducts 21-Aug-24 26-Aug-24 5 63
Street SS-14.1 19-Nov-23 26-Aug-24 227 63
Site Preparation 19-Nov-23 13-Dec-23 21 269
GR-CON-Z06-1291 Demolition (Asphalt.Paving,etc.....) 19-Nov-23 23-Nov-23 4 63
GR-CON-Z06-1292 Excavation And Disposal 23-Nov-23 29-Nov-23 5 139
GR-CON-Z06-1293 Prepretion And Compaction 29-Nov-23 06-Dec-23 6 269
GR-CON-Z06-1294 Backfilling 06-Dec-23 13-Dec-23 6 269
Curbstone and Paving 29-Nov-23 22-Jan-24 46 235
GR-CON-Z06-1295 Excavation Curbstone 29-Nov-23 05-Dec-23 5 200
GR-CON-Z06-1296 Plain Concrete 05-Dec-23 12-Dec-23 6 235
GR-CON-Z06-1297 Installation Curbstone 12-Dec-23 23-Dec-23 9 235
GR-CON-Z06-1298 Casting Concrete (Mortar haunch) 23-Dec-23 27-Dec-23 4 235
GR-CON-Z06-1299 Backfilling (sand / Sub base) 27-Dec-23 07-Jan-24 9 235
GR-CON-Z06-1300 Installation of Paving 07-Jan-24 22-Jan-24 13 235
Landscape Works 05-Dec-23 03-Aug-24 193 63
GR-CON-Z06-1301 Excavation (Tree Pit ) 05-Dec-23 11-Dec-23 5 200
GR-CON-Z06-1302 Aggregate Drainage layer 11-Dec-23 18-Dec-23 6 200
GR-CON-Z06-1303 Installation Geotextile 18-Dec-23 23-Dec-23 4 200
GR-CON-Z06-1304 Backfilling (Soil max for tree) 23-Dec-23 30-Dec-23 6 200
GR-CON-Z06-1305 Installation of Trees 24-Jun-24 26-Jun-24 3 63
GR-CON-Z06-10216 Installation of Shrubs 27-Jun-24 30-Jun-24 3 63
GR-CON-Z06-10226 Installation of Succulents 01-Jul-24 03-Jul-24 3 63
GR-CON-Z06-10236 Installation of Ground Covers 04-Jul-24 07-Jul-24 3 63
GR-CON-Z06-10246 Installation of Grass 08-Jul-24 10-Jul-24 3 63
GR-CON-Z06-1306 Backfilling (Mulch) 11-Jul-24 14-Jul-24 3 63
GR-CON-Z06-1307 Natural Boulders Installation 15-Jul-24 18-Jul-24 4 63
GR-CON-Z06-1308 Retaining walls . Steps, forming risers, treads and edges with finishes
20-Jul-24 03-Aug-24 13 63
Site Furnishing 04-Aug-24 26-Aug-24 20 63
GR-CON-Z06-1317 Garden planter box 04-Aug-24 08-Aug-24 5 63
GR-CON-Z06-1318 Wheel stoppers 10-Aug-24 14-Aug-24 5 63
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1319 Steel Lattice 15-Aug-24 20-Aug-24 5 63


GR-CON-Z06-1320 Handrail 21-Aug-24 26-Aug-24 5 63
Storm Piping Works 20-Aug-24 26-Aug-24 6 63
GR-CON-Z06-1321 Installation of DI grating covers 20-Aug-24 26-Aug-24 6 63
Irrigation Works 29-Nov-23 30-Jan-24 53 222
GR-CON-Z06-1309 Excavation Pipe Irrigation 29-Nov-23 05-Dec-23 5 139
GR-CON-Z06-1310 Sand Bedding 05-Dec-23 10-Dec-23 4 139
GR-CON-Z06-1311 HDPE Pipe Installations and fittings and conduit for cable 10-Dec-23 27-Dec-23 15 139
GR-CON-Z06-1313 Test pressure 27-Dec-23 02-Jan-24 5 139
GR-CON-Z06-1312 Installation of Valves and Accessories 02-Jan-24 07-Jan-24 4 139
GR-CON-Z06-1314 Back filling (sand / Subbase ) 07-Jan-24 14-Jan-24 6 139
GR-CON-Z06-1315 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Jan-24 21-Jan-24 6 222
GR-CON-Z06-1316 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-Jan-24
system 30-Jan-24 8 222
Electrical Works 05-Dec-23 26-Aug-24 213 63
GR-CON-Z06-1322 Excavation And Disposal 05-Dec-23 11-Dec-23 5 249
GR-CON-Z06-1323 Sand Bedding 11-Dec-23 16-Dec-23 4 249
GR-CON-Z06-1324 laying cables 16-Dec-23 20-Dec-23 4 249
GR-CON-Z06-1325 Backfilling (sand / Sub base) 20-Dec-23 26-Dec-23 5 249
GR-CON-Z06-1326 Control Panel / Distribution Panel Installation 26-Dec-23 31-Dec-23 4 249
GR-CON-Z06-1327 Road Crossing Ducts 21-Aug-24 26-Aug-24 5 63
Street SS-25 06-Dec-23 22-Oct-24 260 15
Site Preparation 06-Dec-23 24-Jan-24 42 233
GR-CON-Z06-1328 Demolition (Asphalt.Paving,etc.....) 06-Dec-23 16-Dec-23 8 52
GR-CON-Z06-1329 Excavation And Disposal 16-Dec-23 27-Dec-23 10 52
GR-CON-Z06-1330 Prepretion And Compaction 27-Dec-23 10-Jan-24 12 233
GR-CON-Z06-1331 Backfilling 10-Jan-24 24-Jan-24 12 233
Curbstone and Paving 27-Dec-23 28-Mar-24 76 181
GR-CON-Z06-1332 Excavation Curbstone 27-Dec-23 08-Jan-24 10 102
GR-CON-Z06-1333 Plain Concrete 08-Jan-24 22-Jan-24 12 181
GR-CON-Z06-1334 Installation Curbstone 22-Jan-24 12-Feb-24 18 181
GR-CON-Z06-1335 Casting Concrete (Mortar haunch) 12-Feb-24 21-Feb-24 8 181
GR-CON-Z06-1336 Backfilling (sand / Sub base) 21-Feb-24 13-Mar-24 18 181
GR-CON-Z06-1337 Installation of Paving 26-Feb-24 28-Mar-24 24 181
Landscape Works 08-Jan-24 04-Sep-24 192 15
GR-CON-Z06-1338 Excavation (Tree Pit ) 08-Jan-24 20-Jan-24 10 102
GR-CON-Z06-1339 Aggregate Drainage layer 20-Jan-24 03-Feb-24 12 102
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1340 Installation Geotextile 03-Feb-24 12-Feb-24 8 102


GR-CON-Z06-1341 Backfilling (Soil max for tree) 12-Feb-24 26-Feb-24 12 102
GR-CON-Z06-1342 Installation of Trees 24-Jun-24 29-Jun-24 5 15
GR-CON-Z06-10256 Installation of Shrubs 30-Jun-24 04-Jul-24 5 15
GR-CON-Z06-10266 Installation of Succulents 06-Jul-24 10-Jul-24 5 15
GR-CON-Z06-10276 Installation of Ground Covers 11-Jul-24 16-Jul-24 5 15
GR-CON-Z06-10286 Installation of Grass 17-Jul-24 22-Jul-24 5 15
GR-CON-Z06-1343 Backfilling (Mulch) 23-Jul-24 29-Jul-24 6 15
GR-CON-Z06-1344 Natural Boulders Installation 30-Jul-24 07-Aug-24 8 15
GR-CON-Z06-1345 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Aug-24 04-Sep-24 24 15
Site Furnishing 05-Sep-24 22-Oct-24 40 15
GR-CON-Z06-1354 Garden planter box 05-Sep-24 16-Sep-24 10 15
GR-CON-Z06-1355 Wheel stoppers 17-Sep-24 29-Sep-24 10 15
GR-CON-Z06-1356 Steel Lattice 30-Sep-24 10-Oct-24 10 15
GR-CON-Z06-1357 Handrail 12-Oct-24 22-Oct-24 10 15
Storm Piping Works 09-Oct-24 22-Oct-24 12 15
GR-CON-Z06-1358 Installation of DI grating covers 09-Oct-24 22-Oct-24 12 15
Irrigation Works 27-Dec-23 04-May-24 100 145
GR-CON-Z06-1346 Excavation Pipe Irrigation 27-Dec-23 08-Jan-24 10 52
GR-CON-Z06-1347 Sand Bedding 08-Jan-24 17-Jan-24 8 52
GR-CON-Z06-1348 HDPE Pipe Installations and fittings and conduit for cable 17-Jan-24 14-Feb-24 24 52
GR-CON-Z06-1350 Test pressure 14-Feb-24 26-Feb-24 10 52
GR-CON-Z06-1349 Installation of Valves and Accessories 26-Feb-24 06-Mar-24 8 52
GR-CON-Z06-1351 Back filling (sand / Subbase ) 06-Mar-24 23-Mar-24 12 52
GR-CON-Z06-1352 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-Mar-24 10-Apr-24 12 145
GR-CON-Z06-1353 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Apr-24
system 04-May-24 16 145
Electrical Works 08-Jan-24 22-Oct-24 232 15
GR-CON-Z06-1359 Excavation And Disposal 08-Jan-24 20-Jan-24 10 193
GR-CON-Z06-1360 Sand Bedding 20-Jan-24 29-Jan-24 8 193
GR-CON-Z06-1361 laying cables 29-Jan-24 07-Feb-24 8 193
GR-CON-Z06-1362 Backfilling (sand / Sub base) 07-Feb-24 19-Feb-24 10 193
GR-CON-Z06-1363 Control Panel / Distribution Panel Installation 19-Feb-24 28-Feb-24 8 193
GR-CON-Z06-1364 Road Crossing Ducts 12-Oct-24 22-Oct-24 10 15
Street SS-54 17-Dec-23 26-Aug-24 203 63
Site Preparation 17-Dec-23 10-Jan-24 21 245
GR-CON-Z06-1365 Demolition (Asphalt.Paving,etc.....) 17-Dec-23 21-Dec-23 4 54
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1366 Excavation And Disposal 21-Dec-23 27-Dec-23 5 115


GR-CON-Z06-1367 Prepretion And Compaction 27-Dec-23 03-Jan-24 6 245
GR-CON-Z06-1368 Backfilling 03-Jan-24 10-Jan-24 6 245
Curbstone and Paving 27-Dec-23 19-Feb-24 46 211
GR-CON-Z06-1369 Excavation Curbstone 27-Dec-23 02-Jan-24 5 176
GR-CON-Z06-1370 Plain Concrete 02-Jan-24 09-Jan-24 6 211
GR-CON-Z06-1371 Installation Curbstone 09-Jan-24 20-Jan-24 9 211
GR-CON-Z06-1372 Casting Concrete (Mortar haunch) 20-Jan-24 24-Jan-24 4 211
GR-CON-Z06-1373 Backfilling (sand / Sub base) 24-Jan-24 04-Feb-24 9 211
GR-CON-Z06-1374 Installation of Paving 04-Feb-24 19-Feb-24 13 211
Landscape Works 02-Jan-24 03-Aug-24 169 63
GR-CON-Z06-1375 Excavation (Tree Pit ) 02-Jan-24 08-Jan-24 5 176
GR-CON-Z06-1376 Aggregate Drainage layer 08-Jan-24 15-Jan-24 6 176
GR-CON-Z06-1377 Installation Geotextile 15-Jan-24 20-Jan-24 4 176
GR-CON-Z06-1378 Backfilling (Soil max for tree) 20-Jan-24 27-Jan-24 6 176
GR-CON-Z06-1379 Installation of Trees 24-Jun-24 26-Jun-24 3 63
GR-CON-Z06-10296 Installation of Shrubs 27-Jun-24 30-Jun-24 3 63
GR-CON-Z06-10306 Installation of Succulents 01-Jul-24 03-Jul-24 3 63
GR-CON-Z06-10316 Installation of Ground Covers 04-Jul-24 07-Jul-24 3 63
GR-CON-Z06-10326 Installation of Grass 08-Jul-24 10-Jul-24 3 63
GR-CON-Z06-1380 Backfilling (Mulch) 11-Jul-24 14-Jul-24 3 63
GR-CON-Z06-1381 Natural Boulders Installation 15-Jul-24 18-Jul-24 4 63
GR-CON-Z06-1382 Retaining walls . Steps, forming risers, treads and edges with finishes
20-Jul-24 03-Aug-24 13 63
Site Furnishing 04-Aug-24 26-Aug-24 20 63
GR-CON-Z06-1391 Garden planter box 04-Aug-24 08-Aug-24 5 63
GR-CON-Z06-1392 Wheel stoppers 10-Aug-24 14-Aug-24 5 63
GR-CON-Z06-1393 Steel Lattice 15-Aug-24 20-Aug-24 5 63
GR-CON-Z06-1394 Handrail 21-Aug-24 26-Aug-24 5 63
Storm Piping Works 20-Aug-24 26-Aug-24 6 63
GR-CON-Z06-1395 Installation of DI grating covers 20-Aug-24 26-Aug-24 6 63
Irrigation Works 27-Dec-23 27-Feb-24 53 198
GR-CON-Z06-1383 Excavation Pipe Irrigation 27-Dec-23 02-Jan-24 5 115
GR-CON-Z06-1384 Sand Bedding 02-Jan-24 07-Jan-24 4 115
GR-CON-Z06-1385 HDPE Pipe Installations and fittings and conduit for cable 07-Jan-24 24-Jan-24 15 115
GR-CON-Z06-1387 Test pressure 24-Jan-24 30-Jan-24 5 115
GR-CON-Z06-1386 Installation of Valves and Accessories 30-Jan-24 04-Feb-24 4 115
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1388 Back filling (sand / Subbase ) 04-Feb-24 11-Feb-24 6 115


GR-CON-Z06-1389 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Feb-24 18-Feb-24 6 198
GR-CON-Z06-1390 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Feb-24
system 27-Feb-24 8 198
Electrical Works 02-Jan-24 26-Aug-24 189 63
GR-CON-Z06-1396 Excavation And Disposal 02-Jan-24 08-Jan-24 5 225
GR-CON-Z06-1397 Sand Bedding 08-Jan-24 13-Jan-24 4 225
GR-CON-Z06-1398 laying cables 13-Jan-24 17-Jan-24 4 225
GR-CON-Z06-1399 Backfilling (sand / Sub base) 17-Jan-24 23-Jan-24 5 225
GR-CON-Z06-1400 Control Panel / Distribution Panel Installation 23-Jan-24 28-Jan-24 4 225
GR-CON-Z06-1401 Road Crossing Ducts 21-Aug-24 26-Aug-24 5 63
School S-06 14-Jan-24 21-Aug-24 175 67
Site Preparation 14-Jan-24 24-Jan-24 9 233
GR-CON-Z06-1153 Excavation And Disposal 14-Jan-24 20-Jan-24 5 34
GR-CON-Z06-1154 Prepretion And Compaction 20-Jan-24 24-Jan-24 4 233
Curbstone and Paving 20-Jan-24 13-Mar-24 46 191
GR-CON-Z06-1156 Excavation Curbstone 20-Jan-24 25-Jan-24 5 160
GR-CON-Z06-1157 Plain Concrete 25-Jan-24 01-Feb-24 6 191
GR-CON-Z06-1158 Installation Curbstone 01-Feb-24 12-Feb-24 9 191
GR-CON-Z06-1159 Casting Concrete (Mortar haunch) 12-Feb-24 17-Feb-24 4 191
GR-CON-Z06-1160 Backfilling (sand / Sub base) 17-Feb-24 27-Feb-24 9 191
GR-CON-Z06-1161 Installation of Paving 27-Feb-24 13-Mar-24 13 191
Landscape Works 25-Jan-24 10-Aug-24 155 67
GR-CON-Z06-1162 Excavation (Tree Pit ) 25-Jan-24 31-Jan-24 5 160
GR-CON-Z06-1163 Aggregate Drainage layer 31-Jan-24 07-Feb-24 6 160
GR-CON-Z06-1164 Installation Geotextile 07-Feb-24 12-Feb-24 4 160
GR-CON-Z06-1165 Backfilling (Soil max for tree) 12-Feb-24 19-Feb-24 6 160
GR-CON-Z06-1166 Installation of Trees 24-Jun-24 26-Jun-24 3 67
GR-CON-Z06-5416 Installation of Shrubs 27-Jun-24 30-Jun-24 3 67
GR-CON-Z06-5426 Installation of Succulents 01-Jul-24 03-Jul-24 3 67
GR-CON-Z06-5436 Installation of Ground Covers 04-Jul-24 07-Jul-24 3 67
GR-CON-Z06-5446 Installation of Climbers 08-Jul-24 10-Jul-24 3 67
GR-CON-Z06-5456 Installation of Grass 11-Jul-24 14-Jul-24 3 67
GR-CON-Z06-5466 Installation of Lawns 15-Jul-24 17-Jul-24 3 67
GR-CON-Z06-1167 Backfilling (Mulch) 18-Jul-24 21-Jul-24 3 67
GR-CON-Z06-1168 Natural Boulders Installation 22-Jul-24 25-Jul-24 4 67
GR-CON-Z06-1169 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jul-24 10-Aug-24 13 67
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Furnishing 11-Aug-24 21-Aug-24 10 67


GR-CON-Z06-1178 Garden planter box 11-Aug-24 15-Aug-24 5 67
GR-CON-Z06-1179 Wheel stoppers 17-Aug-24 21-Aug-24 5 67
Irrigation Works 20-Jan-24 21-Aug-24 170 67
GR-CON-Z06-1170 Excavation Pipe Irrigation 20-Jan-24 25-Jan-24 5 96
GR-CON-Z06-1171 Sand Bedding 25-Jan-24 29-Jan-24 3 96
GR-CON-Z06-1172 HDPE Pipe Installations and fittings and conduit for cable 29-Jan-24 15-Feb-24 15 96
GR-CON-Z06-1174 Test pressure 15-Feb-24 21-Feb-24 5 96
GR-CON-Z06-1173 Installation of Valves and Accessories 21-Feb-24 26-Feb-24 4 96
GR-CON-Z06-1175 Back filling (sand / Subbase ) 26-Feb-24 04-Mar-24 6 96
GR-CON-Z06-1176 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Mar-24 11-Mar-24 6 185
GR-CON-Z06-1177 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Aug-24
system 21-Aug-24 8 67
Existing Neighborhood Park ENP-07 11-Feb-24 10-Aug-24 141 77
Site Preparation 11-Feb-24 10-Apr-24 45 173
GR-CON-Z06-1000 Demolition (Asphalt.Paving,etc.....) 11-Feb-24 21-Feb-24 9 15
GR-CON-Z06-1001 Excavation And Disposal 21-Feb-24 06-Mar-24 12 15
GR-CON-Z06-1002 Prepretion And Compaction 06-Mar-24 18-Mar-24 9 173
GR-CON-Z06-1003 Backfilling 18-Mar-24 10-Apr-24 15 173
Landscape Works 06-Mar-24 10-Aug-24 120 77
GR-CON-Z06-1004 Excavation (Tree Pit ) 06-Mar-24 23-Mar-24 12 105
GR-CON-Z06-1005 Aggregate Drainage layer 23-Mar-24 18-Apr-24 15 105
GR-CON-Z06-1006 Installation Geotextile 20-Apr-24 29-Apr-24 9 105
GR-CON-Z06-1007 Backfilling (Soil max for tree) 30-Apr-24 16-May-24 15 105
GR-CON-Z06-1008 Installation of Trees 24-Jun-24 29-Jun-24 5 77
GR-CON-Z06-1048 Installation of Climbers 30-Jun-24 04-Jul-24 5 77
GR-CON-Z06-14096 Installation of Succulents 06-Jul-24 10-Jul-24 5 77
GR-CON-Z06-14106 Installation of Ground Covers 11-Jul-24 16-Jul-24 5 77
GR-CON-Z06-1408 Installation of Shrubs 17-Jul-24 22-Jul-24 5 77
GR-CON-Z06-1418 Installation of Grass 23-Jul-24 28-Jul-24 5 77
GR-CON-Z06-1428 Installation of Lawns 29-Jul-24 03-Aug-24 5 77
GR-CON-Z06-1009 Backfilling (Mulch) 04-Aug-24 10-Aug-24 6 77
Irrigation Works 06-Mar-24 10-Aug-24 120 77
GR-CON-Z06-1010 Excavation Pipe Irrigation 06-Mar-24 23-Mar-24 12 15
GR-CON-Z06-1011 Sand Bedding 23-Mar-24 01-Apr-24 6 15
GR-CON-Z06-1012 HDPE Pipe Installations and fittings and conduit for cable 01-Apr-24 07-May-24 25 15
GR-CON-Z06-1014 Test pressure 08-May-24 21-May-24 12 15
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z06-1013 Installation of Valves and Accessories 22-May-24 01-Jun-24 9 15


GR-CON-Z06-1015 Back filling (sand / Subbase ) 02-Jun-24 18-Jun-24 15 15
GR-CON-Z06-1016 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Jun-24 10-Jul-24 15 85
GR-CON-Z06-1017 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-Jul-24
system 10-Aug-24 18 77
Zone 02 19-Oct-23 04-Jul-24 208 85
Mosque M-03 19-Oct-23 12-Jun-24 193 100
Site Preparation 19-Oct-23 09-Nov-23 19 252
GR-CON-Z02-1000 Demolition (Asphalt.Paving,etc.....) 19-Oct-23 23-Oct-23 4 22
GR-CON-Z02-1001 Excavation And Disposal 24-Oct-23 29-Oct-23 5 168
GR-CON-Z02-1002 Prepretion And Compaction 30-Oct-23 02-Nov-23 4 252
GR-CON-Z02-1003 Backfilling 04-Nov-23 09-Nov-23 6 252
Curbstone and Paving 11-Nov-23 05-Dec-23 22 252
GR-CON-Z02-1008 Backfilling (sand / Sub base) 11-Nov-23 20-Nov-23 9 252
GR-CON-Z02-1009 Installation of Paving 21-Nov-23 05-Dec-23 13 252
Landscape Works 30-Oct-23 12-Jun-24 184 100
GR-CON-Z02-1010 Excavation (Tree Pit ) 30-Oct-23 04-Nov-23 5 200
GR-CON-Z02-1011 Aggregate Drainage layer 05-Nov-23 11-Nov-23 6 200
GR-CON-Z02-1012 Installation Geotextile 12-Nov-23 16-Nov-23 5 200
GR-CON-Z02-1013 Backfilling (Soil max for tree) 18-Nov-23 22-Nov-23 5 200
GR-CON-Z02-1014 Installation of Trees 20-Mar-24 26-Mar-24 4 100
GR-CON-Z02-3346 Installation of Climbers 27-Mar-24 02-Apr-24 4 100
GR-CON-Z02-3356 Installation of Shrubs 02-Apr-24 08-Apr-24 4 100
GR-CON-Z02-3366 Installation of Succulents 08-Apr-24 18-Apr-24 4 100
GR-CON-Z02-3376 Installation of Ground Covers 18-Apr-24 23-Apr-24 4 100
GR-CON-Z02-1015 Backfilling (Mulch) 23-Apr-24 11-May-24 15 100
GR-CON-Z02-1016 Natural Boulders Installation 11-May-24 26-May-24 13 100
GR-CON-Z02-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
26-May-24 12-Jun-24 15 100
Irrigation Works 30-Oct-23 12-Jun-24 184 100
GR-CON-Z02-1018 Excavation Pipe Irrigation 30-Oct-23 04-Nov-23 5 168
GR-CON-Z02-1019 Sand Bedding 05-Nov-23 07-Nov-23 3 168
GR-CON-Z02-1020 HDPE Pipe Installations and fittings and conduit for cable 08-Nov-23 25-Nov-23 15 168
GR-CON-Z02-1022 Test pressure 26-Nov-23 30-Nov-23 5 168
GR-CON-Z02-1021 Installation of Valves and Accessories 02-Dec-23 05-Dec-23 4 168
GR-CON-Z02-1023 Back filling (sand / Subbase ) 06-Dec-23 12-Dec-23 6 168
GR-CON-Z02-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Dec-23 19-Dec-23 6 234
GR-CON-Z02-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
05-Jun-24
system 12-Jun-24 6 100
Activity ID Activity Name Start Finish Original Total Float
Duration

Parking P-25 22-Oct-23 02-May-24 156 135


Site Preparation 22-Oct-23 28-Oct-23 6 272
GR-CON-Z02-1029 Backfilling 22-Oct-23 28-Oct-23 6 272
GR-CON-Z02-1027 Excavation And Disposal 23-Oct-23 28-Oct-23 5 169
GR-CON-Z02-1026 Demolition (Asphalt.Paving,etc.....) 24-Oct-23 28-Oct-23 4 85
GR-CON-Z02-1028 Prepretion And Compaction 24-Oct-23 28-Oct-23 4 272
Curbstone and Paving 29-Oct-23 20-Dec-23 46 239
GR-CON-Z02-1030 Excavation Curbstone 29-Oct-23 02-Nov-23 5 231
GR-CON-Z02-1031 Plain Concrete 04-Nov-23 09-Nov-23 6 239
GR-CON-Z02-1032 Installation Curbstone 11-Nov-23 20-Nov-23 9 239
GR-CON-Z02-1033 Casting Concrete (Mortar haunch) 21-Nov-23 25-Nov-23 4 239
GR-CON-Z02-1034 Backfilling (sand / Sub base) 26-Nov-23 05-Dec-23 9 239
GR-CON-Z02-1035 Installation of Paving 06-Dec-23 20-Dec-23 13 239
Landscape Works 04-Nov-23 21-Apr-24 135 135
GR-CON-Z02-1036 Excavation (Tree Pit ) 04-Nov-23 08-Nov-23 5 231
GR-CON-Z02-1037 Aggregate Drainage layer 09-Nov-23 15-Nov-23 6 231
GR-CON-Z02-1038 Installation Geotextile 16-Nov-23 20-Nov-23 4 231
GR-CON-Z02-1039 Backfilling (Soil max for tree) 21-Nov-23 27-Nov-23 6 231
GR-CON-Z02-1040 Installation of Trees 20-Mar-24 25-Mar-24 3 135
GR-CON-Z02-6736 Installation of Shrubs 25-Mar-24 30-Mar-24 3 135
GR-CON-Z02-6746 Installation of Ground Covers 30-Mar-24 03-Apr-24 3 135
GR-CON-Z02-6756 Installation of Succulents 03-Apr-24 08-Apr-24 3 135
GR-CON-Z02-6766 Installation of Grass 08-Apr-24 17-Apr-24 3 135
GR-CON-Z02-1041 Backfilling (Mulch) 17-Apr-24 21-Apr-24 3 135
Site Furnishing 21-Apr-24 02-May-24 10 135
GR-CON-Z02-1052 Tree Grate 21-Apr-24 27-Apr-24 5 135
GR-CON-Z02-1053 Wheel stoppers 27-Apr-24 02-May-24 5 135
Irrigation Works 29-Oct-23 02-May-24 150 135
GR-CON-Z02-1044 Excavation Pipe Irrigation 29-Oct-23 02-Nov-23 5 169
GR-CON-Z02-1045 Sand Bedding 04-Nov-23 06-Nov-23 3 169
GR-CON-Z02-1046 HDPE Pipe Installations and fittings and conduit for cable 07-Nov-23 23-Nov-23 15 169
GR-CON-Z02-1048 Test pressure 25-Nov-23 29-Nov-23 5 169
GR-CON-Z02-1047 Installation of Valves and Accessories 30-Nov-23 04-Dec-23 4 169
GR-CON-Z02-1049 Back filling (sand / Subbase ) 05-Dec-23 11-Dec-23 6 169
GR-CON-Z02-1050 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 12-Dec-23 18-Dec-23 6 233
GR-CON-Z02-1051 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-Apr-24
system 02-May-24 8 135
Activity ID Activity Name Start Finish Original Total Float
Duration

Parking P-26 26-Oct-23 02-May-24 152 135


Site Preparation 26-Oct-23 01-Nov-23 6 268
GR-CON-Z02-1057 Backfilling 26-Oct-23 01-Nov-23 6 268
GR-CON-Z02-1055 Excavation And Disposal 28-Oct-23 01-Nov-23 5 165
GR-CON-Z02-1054 Demolition (Asphalt.Paving,etc.....) 29-Oct-23 01-Nov-23 4 85
GR-CON-Z02-1056 Prepretion And Compaction 29-Oct-23 01-Nov-23 4 268
Curbstone and Paving 02-Nov-23 25-Dec-23 46 235
GR-CON-Z02-1058 Excavation Curbstone 02-Nov-23 07-Nov-23 5 227
GR-CON-Z02-1059 Plain Concrete 08-Nov-23 14-Nov-23 6 235
GR-CON-Z02-1060 Installation Curbstone 15-Nov-23 25-Nov-23 9 235
GR-CON-Z02-1061 Casting Concrete (Mortar haunch) 26-Nov-23 29-Nov-23 4 235
GR-CON-Z02-1062 Backfilling (sand / Sub base) 30-Nov-23 10-Dec-23 9 235
GR-CON-Z02-1063 Installation of Paving 11-Dec-23 25-Dec-23 13 235
Landscape Works 08-Nov-23 21-Apr-24 131 135
GR-CON-Z02-1064 Excavation (Tree Pit ) 08-Nov-23 13-Nov-23 5 227
GR-CON-Z02-1065 Aggregate Drainage layer 14-Nov-23 20-Nov-23 6 227
GR-CON-Z02-1066 Installation Geotextile 21-Nov-23 25-Nov-23 4 227
GR-CON-Z02-1067 Backfilling (Soil max for tree) 26-Nov-23 02-Dec-23 6 227
GR-CON-Z02-1068 Installation of Trees 20-Mar-24 25-Mar-24 3 135
GR-CON-Z02-6776 Installation of Shrubs 25-Mar-24 30-Mar-24 3 135
GR-CON-Z02-6786 Installation of Ground Covers 30-Mar-24 03-Apr-24 3 135
GR-CON-Z02-6796 Installation of Succulents 03-Apr-24 08-Apr-24 3 135
GR-CON-Z02-6806 Installation of Grass 08-Apr-24 17-Apr-24 3 135
GR-CON-Z02-1069 Backfilling (Mulch) 17-Apr-24 21-Apr-24 3 135
Site Furnishing 21-Apr-24 02-May-24 10 135
GR-CON-Z02-1080 Tree Grate 21-Apr-24 27-Apr-24 5 135
GR-CON-Z02-1081 Wheel stoppers 27-Apr-24 02-May-24 5 135
Irrigation Works 02-Nov-23 02-May-24 146 135
GR-CON-Z02-1072 Excavation Pipe Irrigation 02-Nov-23 07-Nov-23 5 165
GR-CON-Z02-1073 Sand Bedding 08-Nov-23 11-Nov-23 3 165
GR-CON-Z02-1074 HDPE Pipe Installations and fittings and conduit for cable 12-Nov-23 28-Nov-23 15 165
GR-CON-Z02-1076 Test pressure 29-Nov-23 04-Dec-23 5 165
GR-CON-Z02-1075 Installation of Valves and Accessories 05-Dec-23 09-Dec-23 4 165
GR-CON-Z02-1077 Back filling (sand / Subbase ) 10-Dec-23 16-Dec-23 6 165
GR-CON-Z02-1078 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 17-Dec-23 23-Dec-23 6 229
GR-CON-Z02-1079 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-Apr-24
system 02-May-24 8 135
Activity ID Activity Name Start Finish Original Total Float
Duration

Parking P-27 31-Oct-23 02-May-24 148 135


Site Preparation 31-Oct-23 06-Nov-23 6 264
GR-CON-Z02-1085 Backfilling 31-Oct-23 06-Nov-23 6 264
GR-CON-Z02-1083 Excavation And Disposal 01-Nov-23 06-Nov-23 5 161
GR-CON-Z02-1082 Demolition (Asphalt.Paving,etc.....) 02-Nov-23 06-Nov-23 4 85
GR-CON-Z02-1084 Prepretion And Compaction 02-Nov-23 06-Nov-23 4 264
Curbstone and Paving 07-Nov-23 30-Dec-23 46 231
GR-CON-Z02-1086 Excavation Curbstone 07-Nov-23 12-Nov-23 5 223
GR-CON-Z02-1087 Plain Concrete 13-Nov-23 19-Nov-23 6 231
GR-CON-Z02-1088 Installation Curbstone 20-Nov-23 29-Nov-23 9 231
GR-CON-Z02-1089 Casting Concrete (Mortar haunch) 30-Nov-23 04-Dec-23 4 231
GR-CON-Z02-1090 Backfilling (sand / Sub base) 05-Dec-23 14-Dec-23 9 231
GR-CON-Z02-1091 Installation of Paving 16-Dec-23 30-Dec-23 13 231
Landscape Works 13-Nov-23 21-Apr-24 127 135
GR-CON-Z02-1092 Excavation (Tree Pit ) 13-Nov-23 18-Nov-23 5 223
GR-CON-Z02-1093 Aggregate Drainage layer 19-Nov-23 25-Nov-23 6 223
GR-CON-Z02-1094 Installation Geotextile 26-Nov-23 29-Nov-23 4 223
GR-CON-Z02-1095 Backfilling (Soil max for tree) 30-Nov-23 06-Dec-23 6 223
GR-CON-Z02-1096 Installation of Trees 20-Mar-24 25-Mar-24 3 135
GR-CON-Z02-6816 Installation of Shrubs 25-Mar-24 30-Mar-24 3 135
GR-CON-Z02-6826 Installation of Ground Covers 30-Mar-24 03-Apr-24 3 135
GR-CON-Z02-6836 Installation of Succulents 03-Apr-24 08-Apr-24 3 135
GR-CON-Z02-6846 Installation of Grass 08-Apr-24 17-Apr-24 3 135
GR-CON-Z02-1097 Backfilling (Mulch) 17-Apr-24 21-Apr-24 3 135
Site Furnishing 21-Apr-24 02-May-24 10 135
GR-CON-Z02-1108 Tree Grate 21-Apr-24 27-Apr-24 5 135
GR-CON-Z02-1109 Wheel stoppers 27-Apr-24 02-May-24 5 135
Irrigation Works 07-Nov-23 02-May-24 142 135
GR-CON-Z02-1100 Excavation Pipe Irrigation 07-Nov-23 12-Nov-23 5 161
GR-CON-Z02-1101 Sand Bedding 13-Nov-23 15-Nov-23 3 161
GR-CON-Z02-1102 HDPE Pipe Installations and fittings and conduit for cable 16-Nov-23 03-Dec-23 15 161
GR-CON-Z02-1104 Test pressure 04-Dec-23 09-Dec-23 5 161
GR-CON-Z02-1103 Installation of Valves and Accessories 10-Dec-23 13-Dec-23 4 161
GR-CON-Z02-1105 Back filling (sand / Subbase ) 14-Dec-23 20-Dec-23 6 161
GR-CON-Z02-1106 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Dec-23 27-Dec-23 6 225
GR-CON-Z02-1107 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-Apr-24
system 02-May-24 8 135
Activity ID Activity Name Start Finish Original Total Float
Duration

Street SS-03 07-Nov-23 04-Jul-24 192 85


Site Preparation 07-Nov-23 13-Dec-23 32 245
GR-CON-Z02-1166 Demolition (Asphalt.Paving,etc.....) 07-Nov-23 13-Nov-23 6 85
GR-CON-Z02-1167 Excavation And Disposal 14-Nov-23 22-Nov-23 8 85
GR-CON-Z02-1168 Prepretion And Compaction 23-Nov-23 03-Dec-23 9 245
GR-CON-Z02-1169 Backfilling 04-Dec-23 13-Dec-23 9 245
Curbstone and Paving 23-Nov-23 13-Feb-24 71 192
GR-CON-Z02-1170 Excavation Curbstone 23-Nov-23 02-Dec-23 8 145
GR-CON-Z02-1171 Plain Concrete 03-Dec-23 12-Dec-23 9 192
GR-CON-Z02-1172 Installation Curbstone 13-Dec-23 28-Dec-23 14 192
GR-CON-Z02-1173 Casting Concrete (Mortar haunch) 30-Dec-23 04-Jan-24 6 192
GR-CON-Z02-1174 Backfilling (sand / Sub base) 06-Jan-24 21-Jan-24 14 192
GR-CON-Z02-1175 Installation of Paving 22-Jan-24 13-Feb-24 20 192
Landscape Works 03-Dec-23 23-May-24 138 85
GR-CON-Z02-1176 Excavation (Tree Pit ) 03-Dec-23 11-Dec-23 8 145
GR-CON-Z02-1177 Aggregate Drainage layer 12-Dec-23 21-Dec-23 9 145
GR-CON-Z02-1178 Installation Geotextile 23-Dec-23 28-Dec-23 6 145
GR-CON-Z02-1179 Backfilling (Soil max for tree) 30-Dec-23 08-Jan-24 9 145
GR-CON-Z02-1180 Installation of Trees 20-Mar-24 25-Mar-24 3 85
GR-CON-Z02-9376 Installation of Shrubs 25-Mar-24 30-Mar-24 3 85
GR-CON-Z02-9386 Installation of Succulents 30-Mar-24 03-Apr-24 3 85
GR-CON-Z02-9396 Installation of Ground Covers 03-Apr-24 08-Apr-24 3 85
GR-CON-Z02-9406 Installation of Grass 08-Apr-24 17-Apr-24 3 85
GR-CON-Z02-1181 Backfilling (Mulch) 17-Apr-24 23-Apr-24 5 85
GR-CON-Z02-1182 Natural Boulders Installation 23-Apr-24 30-Apr-24 6 85
GR-CON-Z02-1183 Retaining walls . Steps, forming risers, treads and edges with finishes
30-Apr-24 23-May-24 20 85
Site Furnishing 23-May-24 04-Jul-24 32 85
GR-CON-Z02-1192 Garden planter box 23-May-24 02-Jun-24 8 85
GR-CON-Z02-1193 Wheel stoppers 02-Jun-24 11-Jun-24 8 85
GR-CON-Z02-1194 Steel Lattice 11-Jun-24 25-Jun-24 8 85
GR-CON-Z02-1195 Handrail 25-Jun-24 04-Jul-24 8 85
Storm Piping Works 24-Jun-24 04-Jul-24 9 85
GR-CON-Z02-1196 Installation of DI grating covers 24-Jun-24 04-Jul-24 9 85
Irrigation Works 23-Nov-23 25-Feb-24 81 173
GR-CON-Z02-1184 Excavation Pipe Irrigation 23-Nov-23 02-Dec-23 8 85
GR-CON-Z02-1185 Sand Bedding 03-Dec-23 09-Dec-23 6 85
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z02-1186 HDPE Pipe Installations and fittings and conduit for cable 10-Dec-23 04-Jan-24 23 85
GR-CON-Z02-1188 Test pressure 06-Jan-24 14-Jan-24 8 85
GR-CON-Z02-1187 Installation of Valves and Accessories 15-Jan-24 21-Jan-24 6 85
GR-CON-Z02-1189 Back filling (sand / Subbase ) 22-Jan-24 31-Jan-24 9 85
GR-CON-Z02-1190 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Feb-24 11-Feb-24 9 173
GR-CON-Z02-1191 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-Feb-24
system 25-Feb-24 12 173
Electrical Works 03-Dec-23 04-Jul-24 170 85
GR-CON-Z02-1197 Excavation And Disposal 03-Dec-23 11-Dec-23 8 213
GR-CON-Z02-1198 Sand Bedding 12-Dec-23 18-Dec-23 6 213
GR-CON-Z02-1199 laying cables 19-Dec-23 25-Dec-23 6 213
GR-CON-Z02-1200 Backfilling (sand / Sub base) 26-Dec-23 03-Jan-24 8 213
GR-CON-Z02-1201 Control Panel / Distribution Panel Installation 04-Jan-24 10-Jan-24 6 213
GR-CON-Z02-1202 Road Crossing Ducts 25-Jun-24 04-Jul-24 8 85
Street SS-30.1 14-Nov-23 03-Jun-24 163 108
Site Preparation 14-Nov-23 07-Dec-23 21 250
GR-CON-Z02-1203 Demolition (Asphalt.Paving,etc.....) 14-Nov-23 18-Nov-23 4 141
GR-CON-Z02-1204 Excavation And Disposal 19-Nov-23 23-Nov-23 5 145
GR-CON-Z02-1205 Prepretion And Compaction 25-Nov-23 30-Nov-23 6 250
GR-CON-Z02-1206 Backfilling 02-Dec-23 07-Dec-23 6 250
Curbstone and Paving 25-Nov-23 16-Jan-24 46 216
GR-CON-Z02-1207 Excavation Curbstone 25-Nov-23 29-Nov-23 5 181
GR-CON-Z02-1208 Plain Concrete 30-Nov-23 06-Dec-23 6 216
GR-CON-Z02-1209 Installation Curbstone 07-Dec-23 17-Dec-23 9 216
GR-CON-Z02-1210 Casting Concrete (Mortar haunch) 18-Dec-23 21-Dec-23 4 216
GR-CON-Z02-1211 Backfilling (sand / Sub base) 23-Dec-23 01-Jan-24 9 216
GR-CON-Z02-1212 Installation of Paving 02-Jan-24 16-Jan-24 13 216
Landscape Works 30-Nov-23 11-May-24 129 108
GR-CON-Z02-1213 Excavation (Tree Pit ) 30-Nov-23 05-Dec-23 5 181
GR-CON-Z02-1214 Aggregate Drainage layer 06-Dec-23 12-Dec-23 6 181
GR-CON-Z02-1215 Installation Geotextile 13-Dec-23 17-Dec-23 4 181
GR-CON-Z02-1216 Backfilling (Soil max for tree) 18-Dec-23 24-Dec-23 6 181
GR-CON-Z02-1217 Installation of Trees 20-Mar-24 25-Mar-24 3 108
GR-CON-Z02-9416 Installation of Shrubs 25-Mar-24 30-Mar-24 3 108
GR-CON-Z02-9426 Installation of Succulents 30-Mar-24 03-Apr-24 3 108
GR-CON-Z02-9436 Installation of Ground Covers 03-Apr-24 08-Apr-24 3 108
GR-CON-Z02-9446 Installation of Grass 08-Apr-24 17-Apr-24 3 108
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z02-1218 Backfilling (Mulch) 17-Apr-24 21-Apr-24 3 108


GR-CON-Z02-1219 Natural Boulders Installation 21-Apr-24 25-Apr-24 4 108
GR-CON-Z02-1220 Retaining walls . Steps, forming risers, treads and edges with finishes
25-Apr-24 11-May-24 13 108
Site Furnishing 11-May-24 03-Jun-24 20 108
GR-CON-Z02-1229 Garden planter box 11-May-24 16-May-24 5 108
GR-CON-Z02-1230 Wheel stoppers 16-May-24 22-May-24 5 108
GR-CON-Z02-1231 Steel Lattice 22-May-24 28-May-24 5 108
GR-CON-Z02-1232 Handrail 28-May-24 03-Jun-24 5 108
Storm Piping Works 27-May-24 03-Jun-24 6 108
GR-CON-Z02-1233 Installation of DI grating covers 27-May-24 03-Jun-24 6 108
Irrigation Works 25-Nov-23 24-Jan-24 53 203
GR-CON-Z02-1221 Excavation Pipe Irrigation 25-Nov-23 29-Nov-23 5 145
GR-CON-Z02-1222 Sand Bedding 30-Nov-23 04-Dec-23 4 145
GR-CON-Z02-1223 HDPE Pipe Installations and fittings and conduit for cable 05-Dec-23 21-Dec-23 15 145
GR-CON-Z02-1225 Test pressure 23-Dec-23 27-Dec-23 5 145
GR-CON-Z02-1224 Installation of Valves and Accessories 28-Dec-23 01-Jan-24 4 145
GR-CON-Z02-1226 Back filling (sand / Subbase ) 02-Jan-24 08-Jan-24 6 145
GR-CON-Z02-1227 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Jan-24 15-Jan-24 6 203
GR-CON-Z02-1228 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
16-Jan-24
system 24-Jan-24 8 203
Electrical Works 30-Nov-23 03-Jun-24 149 108
GR-CON-Z02-1234 Excavation And Disposal 30-Nov-23 05-Dec-23 5 230
GR-CON-Z02-1235 Sand Bedding 06-Dec-23 10-Dec-23 4 230
GR-CON-Z02-1236 laying cables 11-Dec-23 14-Dec-23 4 230
GR-CON-Z02-1237 Backfilling (sand / Sub base) 16-Dec-23 20-Dec-23 5 230
GR-CON-Z02-1238 Control Panel / Distribution Panel Installation 21-Dec-23 25-Dec-23 4 230
GR-CON-Z02-1239 Road Crossing Ducts 28-May-24 03-Jun-24 5 108
School S-02 21-Dec-23 29-May-24 127 112
Site Preparation 21-Dec-23 01-Jan-24 9 229
GR-CON-Z02-1111 Excavation And Disposal 21-Dec-23 27-Dec-23 5 112
GR-CON-Z02-1112 Prepretion And Compaction 27-Dec-23 01-Jan-24 4 229
Curbstone and Paving 27-Dec-23 19-Feb-24 46 187
GR-CON-Z02-1114 Excavation Curbstone 27-Dec-23 02-Jan-24 5 156
GR-CON-Z02-1115 Plain Concrete 02-Jan-24 09-Jan-24 6 187
GR-CON-Z02-1116 Installation Curbstone 09-Jan-24 20-Jan-24 9 187
GR-CON-Z02-1117 Casting Concrete (Mortar haunch) 20-Jan-24 24-Jan-24 4 187
GR-CON-Z02-1118 Backfilling (sand / Sub base) 24-Jan-24 04-Feb-24 9 187
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z02-1119 Installation of Paving 04-Feb-24 19-Feb-24 13 187


Landscape Works 02-Jan-24 18-May-24 107 112
GR-CON-Z02-1120 Excavation (Tree Pit ) 02-Jan-24 08-Jan-24 5 156
GR-CON-Z02-1121 Aggregate Drainage layer 08-Jan-24 15-Jan-24 6 156
GR-CON-Z02-1122 Installation Geotextile 15-Jan-24 20-Jan-24 4 156
GR-CON-Z02-1123 Backfilling (Soil max for tree) 20-Jan-24 27-Jan-24 6 156
GR-CON-Z02-1124 Installation of Trees 20-Mar-24 25-Mar-24 3 112
GR-CON-Z02-5116 Installation of Shrubs 25-Mar-24 30-Mar-24 3 112
GR-CON-Z02-5126 Installation of Succulents 30-Mar-24 03-Apr-24 3 112
GR-CON-Z02-5136 Installation of Ground Covers 03-Apr-24 08-Apr-24 3 112
GR-CON-Z02-5146 Installation of Climbers 08-Apr-24 17-Apr-24 3 112
GR-CON-Z02-5156 Installation of Grass 17-Apr-24 21-Apr-24 3 112
GR-CON-Z02-5166 Installation of Lawns 21-Apr-24 24-Apr-24 3 112
GR-CON-Z02-1125 Backfilling (Mulch) 24-Apr-24 28-Apr-24 3 112
GR-CON-Z02-1126 Natural Boulders Installation 28-Apr-24 02-May-24 4 112
GR-CON-Z02-1127 Retaining walls . Steps, forming risers, treads and edges with finishes
02-May-24 18-May-24 13 112
Site Furnishing 18-May-24 29-May-24 10 112
GR-CON-Z02-1128 Garden planter box 18-May-24 23-May-24 5 112
GR-CON-Z02-1129 Wheel stoppers 23-May-24 29-May-24 5 112
Irrigation Works 27-Dec-23 29-May-24 122 112
GR-CON-Z02-1130 Excavation Pipe Irrigation 27-Dec-23 02-Jan-24 5 117
GR-CON-Z02-1131 Sand Bedding 02-Jan-24 06-Jan-24 3 117
GR-CON-Z02-1132 HDPE Pipe Installations and fittings and conduit for cable 06-Jan-24 23-Jan-24 15 117
GR-CON-Z02-1134 Test pressure 23-Jan-24 29-Jan-24 5 117
GR-CON-Z02-1133 Installation of Valves and Accessories 29-Jan-24 03-Feb-24 4 117
GR-CON-Z02-1135 Back filling (sand / Subbase ) 03-Feb-24 10-Feb-24 6 117
GR-CON-Z02-1136 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Feb-24 17-Feb-24 6 181
GR-CON-Z02-1137 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
20-May-24
system 29-May-24 8 112
School S-03 27-Dec-23 29-May-24 122 112
Site Preparation 27-Dec-23 07-Jan-24 9 224
GR-CON-Z02-1139 Excavation And Disposal 27-Dec-23 02-Jan-24 5 112
GR-CON-Z02-1140 Prepretion And Compaction 02-Jan-24 07-Jan-24 4 224
Curbstone and Paving 02-Jan-24 25-Feb-24 46 182
GR-CON-Z02-1142 Excavation Curbstone 02-Jan-24 08-Jan-24 5 151
GR-CON-Z02-1143 Plain Concrete 08-Jan-24 15-Jan-24 6 182
GR-CON-Z02-1144 Installation Curbstone 15-Jan-24 25-Jan-24 9 182
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z02-1145 Casting Concrete (Mortar haunch) 25-Jan-24 30-Jan-24 4 182


GR-CON-Z02-1146 Backfilling (sand / Sub base) 30-Jan-24 10-Feb-24 9 182
GR-CON-Z02-1147 Installation of Paving 10-Feb-24 25-Feb-24 13 182
Landscape Works 08-Jan-24 18-May-24 102 112
GR-CON-Z02-1148 Excavation (Tree Pit ) 08-Jan-24 14-Jan-24 5 151
GR-CON-Z02-1149 Aggregate Drainage layer 14-Jan-24 21-Jan-24 6 151
GR-CON-Z02-1150 Installation Geotextile 21-Jan-24 25-Jan-24 4 151
GR-CON-Z02-1151 Backfilling (Soil max for tree) 25-Jan-24 01-Feb-24 6 151
GR-CON-Z02-1152 Installation of Trees 20-Mar-24 25-Mar-24 3 112
GR-CON-Z02-5176 Installation of Shrubs 25-Mar-24 30-Mar-24 3 112
GR-CON-Z02-5186 Installation of Succulents 30-Mar-24 03-Apr-24 3 112
GR-CON-Z02-5196 Installation of Ground Covers 03-Apr-24 08-Apr-24 3 112
GR-CON-Z02-5206 Installation of Climbers 08-Apr-24 17-Apr-24 3 112
GR-CON-Z02-5216 Installation of Grass 17-Apr-24 21-Apr-24 3 112
GR-CON-Z02-5226 Installation of Lawns 21-Apr-24 24-Apr-24 3 112
GR-CON-Z02-1153 Backfilling (Mulch) 24-Apr-24 28-Apr-24 3 112
GR-CON-Z02-1154 Natural Boulders Installation 28-Apr-24 02-May-24 4 112
GR-CON-Z02-1155 Retaining walls . Steps, forming risers, treads and edges with finishes
02-May-24 18-May-24 13 112
Site Furnishing 18-May-24 29-May-24 10 112
GR-CON-Z02-1164 Garden planter box 18-May-24 23-May-24 5 112
GR-CON-Z02-1165 Wheel stoppers 23-May-24 29-May-24 5 112
Irrigation Works 02-Jan-24 29-May-24 117 112
GR-CON-Z02-1156 Excavation Pipe Irrigation 02-Jan-24 08-Jan-24 5 112
GR-CON-Z02-1157 Sand Bedding 08-Jan-24 11-Jan-24 3 112
GR-CON-Z02-1158 HDPE Pipe Installations and fittings and conduit for cable 11-Jan-24 29-Jan-24 15 112
GR-CON-Z02-1160 Test pressure 29-Jan-24 04-Feb-24 5 112
GR-CON-Z02-1159 Installation of Valves and Accessories 04-Feb-24 08-Feb-24 4 112
GR-CON-Z02-1161 Back filling (sand / Subbase ) 08-Feb-24 15-Feb-24 6 112
GR-CON-Z02-1162 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Feb-24 22-Feb-24 6 176
GR-CON-Z02-1163 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
20-May-24
system 29-May-24 8 112
Sector 2 24-Jul-23 14-Dec-24 420 0
Zone 10 24-Jul-23 14-Dec-24 420 0
Future Neighborhood Park FNP-05 24-Jul-23 21-Oct-24 374 46
Site Preparation 24-Jul-23 15-Aug-23 20 400
GR-CON-Z10-1083 Demolition (Asphalt.Paving,etc.....) 24-Jul-23 27-Jul-23 4 1
GR-CON-Z10-1084 Excavation And Disposal 29-Jul-23 03-Aug-23 6 293
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1085 Prepretion And Compaction 05-Aug-23 08-Aug-23 4 400


GR-CON-Z10-1086 Backfilling 09-Aug-23 15-Aug-23 6 400
Curbstone and Paving 05-Aug-23 14-Sep-23 36 374
GR-CON-Z10-1087 Excavation Curbstone 05-Aug-23 09-Aug-23 5 351
GR-CON-Z10-1088 Plain Concrete 10-Aug-23 15-Aug-23 5 374
GR-CON-Z10-1089 Installation Curbstone 16-Aug-23 24-Aug-23 8 374
GR-CON-Z10-1090 Casting Concrete (Mortar haunch) 26-Aug-23 29-Aug-23 4 374
GR-CON-Z10-1091 Backfilling (sand / Sub base) 30-Aug-23 04-Sep-23 5 374
GR-CON-Z10-1092 Installation of Paving 31-Aug-23 14-Sep-23 13 374
Landscape Works 10-Aug-23 21-Oct-24 359 46
GR-CON-Z10-1093 Excavation (Tree Pit ) 10-Aug-23 15-Aug-23 5 351
GR-CON-Z10-1094 Aggregate Drainage layer 16-Aug-23 22-Aug-23 6 351
GR-CON-Z10-1095 Installation Geotextile 23-Aug-23 27-Aug-23 4 351
GR-CON-Z10-1096 Backfilling (Soil max for tree) 28-Aug-23 03-Sep-23 6 351
GR-CON-Z10-1097 Installation of Trees 11-Sep-24 14-Sep-24 2 46
GR-CON-Z10-2226 Installation of Shrubs 14-Sep-24 16-Sep-24 2 46
GR-CON-Z10-2236 Installation of Succulents 16-Sep-24 18-Sep-24 2 46
GR-CON-Z10-2246 Installation of Ground Covers 18-Sep-24 21-Sep-24 2 46
GR-CON-Z10-2256 Installation of Climbers 21-Sep-24 24-Sep-24 2 46
GR-CON-Z10-2266 Installation of Grass 24-Sep-24 26-Sep-24 2 46
GR-CON-Z10-2276 Installation of Lawns 26-Sep-24 29-Sep-24 2 46
GR-CON-Z10-1098 Backfilling (Mulch) 29-Sep-24 02-Oct-24 3 46
GR-CON-Z10-1099 Natural Boulders Installation 02-Oct-24 06-Oct-24 3 46
GR-CON-Z10-1100 Retaining walls . Steps, forming risers, treads and edges with finishes
06-Oct-24 21-Oct-24 13 46
Irrigation Works 05-Aug-23 21-Oct-24 364 46
GR-CON-Z10-1101 Excavation Pipe Irrigation 05-Aug-23 09-Aug-23 5 293
GR-CON-Z10-1102 Sand Bedding 10-Aug-23 13-Aug-23 3 293
GR-CON-Z10-1103 HDPE Pipe Installations and fittings and conduit for cable 30-Aug-23 17-Sep-23 15 279
GR-CON-Z10-1105 Test pressure 17-Sep-23 24-Sep-23 5 279
GR-CON-Z10-1104 Installation of Valves and Accessories 24-Sep-23 28-Sep-23 4 279
GR-CON-Z10-1106 Back filling (sand / Subbase ) 28-Sep-23 05-Oct-23 6 279
GR-CON-Z10-1107 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-Oct-23 12-Oct-23 6 344
GR-CON-Z10-1108 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-Oct-24
system 21-Oct-24 8 46
Pump Room - 02 29-Jul-23 17-Aug-24 315 101
Site Preparation 29-Jul-23 30-Aug-23 29 101
GR-CON-Z10-1000 Excavation And Disposal 29-Jul-23 08-Aug-23 10 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1001 Blinding concrete 09-Aug-23 30-Aug-23 19 101


Civil Works 31-Aug-23 31-Mar-24 178 101
Reinforcement steel bars / Formwork / Concrete 21-Sep-23 19-Feb-24 129 101
GR-CON-Z10-1002 Raft 21-Sep-23 12-Oct-23 18 101
GR-CON-Z10-1004 Wall 19-Oct-23 16-Nov-23 25 101
GR-CON-Z10-1005 Stairs 18-Nov-23 22-Nov-23 5 101
GR-CON-Z10-1006 Slabs and Beams 23-Nov-23 13-Dec-23 18 101
GR-CON-Z10-1003 Columns 14-Dec-23 31-Dec-23 15 101
GR-CON-Z10-1008 Stairs (pump room) 01-Jan-24 06-Jan-24 5 101
GR-CON-Z10-1009 Slabs and Beams Ground floor (pump room) 07-Jan-24 04-Feb-24 25 101
GR-CON-Z10-1007 Columns (pump room) 05-Feb-24 19-Feb-24 13 101
Waterproofing 31-Aug-23 31-Mar-24 178 101
GR-CON-Z10-1012 Waterproofing to structures, / tank) horizontal and vertical 31-Aug-23 20-Sep-23 18 101
GR-CON-Z10-1010 Water stop 14-Oct-23 18-Oct-23 5 101
GR-CON-Z10-1011 Surface preparation 20-Feb-24 05-Mar-24 13 101
GR-CON-Z10-1013 Roof waterproofing 06-Mar-24 31-Mar-24 18 101
Architectural Works 01-Apr-24 23-May-24 39 101
GR-CON-Z10-1014 Blockwork 01-Apr-24 21-Apr-24 11 101
GR-CON-Z10-1015 Floor finish 21-Apr-24 01-May-24 9 101
GR-CON-Z10-1016 Wall finish 01-May-24 12-May-24 9 101
GR-CON-Z10-1017 Door installation 12-May-24 16-May-24 4 101
GR-CON-Z10-1019 Celling finish 16-May-24 23-May-24 6 101
Mechanical Works 12-Nov-23 05-Aug-24 215 101
Piping Works 12-Nov-23 12-Mar-24 105 179
GR-CON-Z10-1020 Excavation of Pipe Irrigation 12-Nov-23 06-Dec-23 22 179
GR-CON-Z10-1021 Sand Bedding 07-Dec-23 17-Dec-23 9 179
GR-CON-Z10-1022 HDPE Pipe Installations and fittings 18-Dec-23 18-Jan-24 28 179
GR-CON-Z10-1023 Thrust Blocks 20-Jan-24 30-Jan-24 10 179
GR-CON-Z10-1024 Test pressure 31-Jan-24 14-Feb-24 13 179
GR-CON-Z10-1038 Back filling (sand / Subbase ) 15-Feb-24 12-Mar-24 23 179
Pipe Works Specialties 23-May-24 08-Jul-24 35 101
GR-CON-Z10-1025 Excavation chamber 23-May-24 28-May-24 4 101
GR-CON-Z10-1026 Installation chamber 28-May-24 09-Jun-24 10 101
GR-CON-Z10-1027 Installation valve (Gate /Air / Washout / …..) 09-Jun-24 29-Jun-24 13 101
GR-CON-Z10-1028 Tie-in Point 29-Jun-24 08-Jul-24 8 101
Pump Works 08-Jul-24 05-Aug-24 24 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1029 Irrigation pump 08-Jul-24 13-Jul-24 4 101


GR-CON-Z10-1030 Piping system ( valves and connection to main network ) 13-Jul-24 24-Jul-24 10 101
GR-CON-Z10-1031 Vent crowl 24-Jul-24 30-Jul-24 5 101
GR-CON-Z10-1032 Sensor With Alarm (Low level / High level ) 30-Jul-24 05-Aug-24 5 101
Electrical Works 21-Apr-24 17-Aug-24 97 101
GR-CON-Z10-1033 Conduits Installation 21-Apr-24 01-May-24 9 101
GR-CON-Z10-1034 Install of power cables 21-Apr-24 27-Apr-24 5 174
GR-CON-Z10-1035 Earthing and lightning protection system 21-Apr-24 27-Apr-24 5 174
GR-CON-Z10-1036 Installation of wiring devices and lighting fixtures 12-May-24 22-May-24 9 161
GR-CON-Z10-1037 Connecting to Main Network 05-Aug-24 17-Aug-24 10 101
Future Neighborhood Park FNP-33 29-Jul-23 22-Oct-24 371 45
Site Preparation 29-Jul-23 20-Aug-23 20 396
GR-CON-Z10-1109 Demolition (Asphalt.Paving,etc.....) 29-Jul-23 01-Aug-23 4 156
GR-CON-Z10-1110 Excavation And Disposal 02-Aug-23 08-Aug-23 6 289
GR-CON-Z10-1111 Prepretion And Compaction 09-Aug-23 13-Aug-23 4 396
GR-CON-Z10-1112 Backfilling 14-Aug-23 20-Aug-23 6 396
Curbstone and Paving 09-Aug-23 02-Oct-23 46 360
GR-CON-Z10-1113 Excavation Curbstone 09-Aug-23 14-Aug-23 5 346
GR-CON-Z10-1114 Plain Concrete 15-Aug-23 21-Aug-23 6 360
GR-CON-Z10-1115 Installation Curbstone 22-Aug-23 31-Aug-23 9 360
GR-CON-Z10-1116 Casting Concrete (Mortar haunch) 02-Sep-23 05-Sep-23 4 360
GR-CON-Z10-1117 Backfilling (sand / Sub base) 06-Sep-23 16-Sep-23 9 360
GR-CON-Z10-1118 Installation of Paving 17-Sep-23 02-Oct-23 13 360
Landscape Works 15-Aug-23 22-Oct-24 356 45
GR-CON-Z10-1119 Excavation (Tree Pit ) 15-Aug-23 20-Aug-23 5 346
GR-CON-Z10-1120 Aggregate Drainage layer 21-Aug-23 27-Aug-23 6 346
GR-CON-Z10-1121 Installation Geotextile 28-Aug-23 31-Aug-23 4 346
GR-CON-Z10-1122 Backfilling (Soil max for tree) 02-Sep-23 07-Sep-23 6 346
GR-CON-Z10-1123 Installation of Trees 11-Sep-24 14-Sep-24 2 45
GR-CON-Z10-2286 Installation of Shrubs 14-Sep-24 16-Sep-24 2 45
GR-CON-Z10-2296 Installation of Succulents 16-Sep-24 18-Sep-24 2 45
GR-CON-Z10-2306 Installation of Ground Covers 18-Sep-24 21-Sep-24 2 45
GR-CON-Z10-2316 Installation of Climbers 21-Sep-24 24-Sep-24 2 45
GR-CON-Z10-2326 Installation of Grass 24-Sep-24 26-Sep-24 2 45
GR-CON-Z10-2336 Installation of Lawns 26-Sep-24 29-Sep-24 2 45
GR-CON-Z10-1124 Backfilling (Mulch) 29-Sep-24 02-Oct-24 3 45
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1125 Natural Boulders Installation 02-Oct-24 07-Oct-24 4 45


GR-CON-Z10-1126 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 22-Oct-24 13 45
Irrigation Works 09-Aug-23 22-Oct-24 361 45
GR-CON-Z10-1127 Excavation Pipe Irrigation 09-Aug-23 14-Aug-23 5 289
GR-CON-Z10-1128 Sand Bedding 15-Aug-23 17-Aug-23 3 289
GR-CON-Z10-1129 HDPE Pipe Installations and fittings and conduit for cable 30-Aug-23 17-Sep-23 15 279
GR-CON-Z10-1131 Test pressure 17-Sep-23 24-Sep-23 5 279
GR-CON-Z10-1130 Installation of Valves and Accessories 24-Sep-23 28-Sep-23 4 279
GR-CON-Z10-1132 Back filling (sand / Subbase ) 28-Sep-23 05-Oct-23 6 279
GR-CON-Z10-1133 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-Oct-23 12-Oct-23 6 344
GR-CON-Z10-1134 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Oct-24
system 22-Oct-24 8 45
Future Neighborhood Park FNP-22 02-Aug-23 29-Oct-24 373 39
Site Preparation 02-Aug-23 31-Aug-23 26 386
GR-CON-Z10-1057 Demolition (Asphalt.Paving,etc.....) 02-Aug-23 07-Aug-23 5 156
GR-CON-Z10-1058 Excavation And Disposal 08-Aug-23 15-Aug-23 7 269
GR-CON-Z10-1059 Prepretion And Compaction 16-Aug-23 21-Aug-23 5 386
GR-CON-Z10-1060 Backfilling 22-Aug-23 31-Aug-23 9 386
Curbstone and Paving 16-Aug-23 31-Oct-23 65 335
GR-CON-Z10-1061 Excavation Curbstone 16-Aug-23 23-Aug-23 7 323
GR-CON-Z10-1062 Plain Concrete 24-Aug-23 03-Sep-23 9 335
GR-CON-Z10-1063 Installation Curbstone 04-Sep-23 17-Sep-23 12 335
GR-CON-Z10-1064 Casting Concrete (Mortar haunch) 18-Sep-23 27-Sep-23 8 335
GR-CON-Z10-1065 Backfilling (sand / Sub base) 28-Sep-23 11-Oct-23 12 335
GR-CON-Z10-1066 Installation of Paving 12-Oct-23 31-Oct-23 17 335
Landscape Works 24-Aug-23 29-Oct-24 354 39
GR-CON-Z10-1067 Excavation (Tree Pit ) 24-Aug-23 31-Aug-23 7 323
GR-CON-Z10-1068 Aggregate Drainage layer 02-Sep-23 11-Sep-23 9 323
GR-CON-Z10-1069 Installation Geotextile 12-Sep-23 17-Sep-23 5 323
GR-CON-Z10-1070 Backfilling (Soil max for tree) 18-Sep-23 28-Sep-23 9 323
GR-CON-Z10-1071 Installation of Trees 11-Sep-24 14-Sep-24 2 39
GR-CON-Z10-2166 Installation of Shrubs 14-Sep-24 16-Sep-24 2 39
GR-CON-Z10-2176 Installation of Succulents 16-Sep-24 18-Sep-24 2 39
GR-CON-Z10-2186 Installation of Ground Covers 18-Sep-24 21-Sep-24 2 39
GR-CON-Z10-2196 Installation of Climbers 21-Sep-24 24-Sep-24 2 39
GR-CON-Z10-2206 Installation of Grass 24-Sep-24 26-Sep-24 2 39
GR-CON-Z10-2216 Installation of Lawns 26-Sep-24 29-Sep-24 2 39
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1072 Backfilling (Mulch) 29-Sep-24 03-Oct-24 4 39


GR-CON-Z10-1073 Natural Boulders Installation 03-Oct-24 09-Oct-24 5 39
GR-CON-Z10-1074 Retaining walls . Steps, forming risers, treads and edges with finishes
09-Oct-24 29-Oct-24 17 39
Irrigation Works 16-Aug-23 29-Oct-24 361 39
GR-CON-Z10-1075 Excavation Pipe Irrigation 16-Aug-23 23-Aug-23 7 269
GR-CON-Z10-1076 Sand Bedding 24-Aug-23 28-Aug-23 4 269
GR-CON-Z10-1077 HDPE Pipe Installations and fittings and conduit for cable 30-Aug-23 24-Sep-23 20 268
GR-CON-Z10-1079 Test pressure 24-Sep-23 02-Oct-23 7 268
GR-CON-Z10-1078 Installation of Valves and Accessories 02-Oct-23 08-Oct-23 5 268
GR-CON-Z10-1080 Back filling (sand / Subbase ) 08-Oct-23 18-Oct-23 9 268
GR-CON-Z10-1081 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Oct-23 29-Oct-23 9 328
GR-CON-Z10-1082 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Oct-24
system 29-Oct-24 10 39
Mosque M-10 11-Oct-23 25-Nov-24 337 16
Site Preparation 11-Oct-23 02-Nov-23 19 312
GR-CON-Z10-1135 Demolition (Asphalt.Paving,etc.....) 11-Oct-23 16-Oct-23 4 101
GR-CON-Z10-1136 Excavation And Disposal 16-Oct-23 22-Oct-23 5 227
GR-CON-Z10-1137 Prepretion And Compaction 22-Oct-23 26-Oct-23 4 312
GR-CON-Z10-1138 Backfilling 26-Oct-23 02-Nov-23 6 312
Curbstone and Paving 02-Nov-23 28-Nov-23 22 312
GR-CON-Z10-1143 Backfilling (sand / Sub base) 02-Nov-23 13-Nov-23 9 312
GR-CON-Z10-1144 Installation of Paving 13-Nov-23 28-Nov-23 13 312
Landscape Works 22-Oct-23 25-Nov-24 328 16
GR-CON-Z10-1145 Excavation (Tree Pit ) 22-Oct-23 28-Oct-23 5 260
GR-CON-Z10-1146 Aggregate Drainage layer 28-Oct-23 04-Nov-23 6 260
GR-CON-Z10-1147 Installation Geotextile 04-Nov-23 09-Nov-23 5 260
GR-CON-Z10-1148 Backfilling (Soil max for tree) 09-Nov-23 15-Nov-23 5 260
GR-CON-Z10-1149 Installation of Trees 11-Sep-24 16-Sep-24 4 16
GR-CON-Z10-3946 Installation of Climbers 16-Sep-24 21-Sep-24 4 16
GR-CON-Z10-3956 Installation of Shrubs 21-Sep-24 26-Sep-24 4 16
GR-CON-Z10-3966 Installation of Succulents 26-Sep-24 01-Oct-24 4 16
GR-CON-Z10-3976 Installation of Ground Covers 01-Oct-24 06-Oct-24 4 16
GR-CON-Z10-1150 Backfilling (Mulch) 06-Oct-24 23-Oct-24 15 16
GR-CON-Z10-1151 Natural Boulders Installation 23-Oct-24 07-Nov-24 13 16
GR-CON-Z10-1152 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Nov-24 25-Nov-24 15 16
Irrigation Works 22-Oct-23 25-Nov-24 328 16
GR-CON-Z10-1153 Excavation Pipe Irrigation 22-Oct-23 28-Oct-23 5 227
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1154 Sand Bedding 28-Oct-23 31-Oct-23 3 227


GR-CON-Z10-1155 HDPE Pipe Installations and fittings and conduit for cable 31-Oct-23 18-Nov-23 15 227
GR-CON-Z10-1157 Test pressure 18-Nov-23 23-Nov-23 5 227
GR-CON-Z10-1156 Installation of Valves and Accessories 23-Nov-23 28-Nov-23 4 227
GR-CON-Z10-1158 Back filling (sand / Subbase ) 28-Nov-23 05-Dec-23 6 227
GR-CON-Z10-1159 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-Dec-23 12-Dec-23 6 294
GR-CON-Z10-1160 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Nov-24
system 25-Nov-24 6 16
Mosque M-12 23-Nov-23 25-Nov-24 300 16
Site Preparation 23-Nov-23 16-Dec-23 19 275
GR-CON-Z10-1161 Demolition (Asphalt.Paving,etc.....) 23-Nov-23 28-Nov-23 4 68
GR-CON-Z10-1162 Excavation And Disposal 28-Nov-23 04-Dec-23 5 190
GR-CON-Z10-1163 Prepretion And Compaction 04-Dec-23 09-Dec-23 4 275
GR-CON-Z10-1164 Backfilling 09-Dec-23 16-Dec-23 6 275
Curbstone and Paving 16-Dec-23 10-Jan-24 22 275
GR-CON-Z10-1169 Backfilling (sand / Sub base) 16-Dec-23 26-Dec-23 9 275
GR-CON-Z10-1170 Installation of Paving 26-Dec-23 10-Jan-24 13 275
Landscape Works 04-Dec-23 25-Nov-24 291 16
GR-CON-Z10-1171 Excavation (Tree Pit ) 04-Dec-23 10-Dec-23 5 223
GR-CON-Z10-1172 Aggregate Drainage layer 10-Dec-23 17-Dec-23 6 223
GR-CON-Z10-1173 Installation Geotextile 17-Dec-23 23-Dec-23 5 223
GR-CON-Z10-1174 Backfilling (Soil max for tree) 23-Dec-23 28-Dec-23 5 223
GR-CON-Z10-1175 Installation of Trees 11-Sep-24 16-Sep-24 4 16
GR-CON-Z10-3986 Installation of Climbers 16-Sep-24 21-Sep-24 4 16
GR-CON-Z10-3996 Installation of Shrubs 21-Sep-24 26-Sep-24 4 16
GR-CON-Z10-4006 Installation of Succulents 26-Sep-24 01-Oct-24 4 16
GR-CON-Z10-4016 Installation of Ground Covers 01-Oct-24 06-Oct-24 4 16
GR-CON-Z10-1176 Backfilling (Mulch) 06-Oct-24 23-Oct-24 15 16
GR-CON-Z10-1177 Natural Boulders Installation 23-Oct-24 07-Nov-24 13 16
GR-CON-Z10-1178 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Nov-24 25-Nov-24 15 16
Irrigation Works 04-Dec-23 25-Nov-24 291 16
GR-CON-Z10-1179 Excavation Pipe Irrigation 04-Dec-23 10-Dec-23 5 190
GR-CON-Z10-1180 Sand Bedding 10-Dec-23 13-Dec-23 3 190
GR-CON-Z10-1181 HDPE Pipe Installations and fittings and conduit for cable 13-Dec-23 31-Dec-23 15 190
GR-CON-Z10-1183 Test pressure 31-Dec-23 06-Jan-24 5 190
GR-CON-Z10-1182 Installation of Valves and Accessories 06-Jan-24 10-Jan-24 4 190
GR-CON-Z10-1184 Back filling (sand / Subbase ) 10-Jan-24 17-Jan-24 6 190
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1185 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 17-Jan-24 24-Jan-24 6 257
GR-CON-Z10-1186 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Nov-24
system 25-Nov-24 6 16
Mosque M-06 29-Nov-23 25-Nov-24 295 16
Site Preparation 29-Nov-23 21-Dec-23 19 270
GR-CON-Z10-1187 Demolition (Asphalt.Paving,etc.....) 29-Nov-23 04-Dec-23 4 67
GR-CON-Z10-1188 Excavation And Disposal 04-Dec-23 10-Dec-23 5 185
GR-CON-Z10-1189 Prepretion And Compaction 10-Dec-23 14-Dec-23 4 270
GR-CON-Z10-1190 Backfilling 14-Dec-23 21-Dec-23 6 270
Curbstone and Paving 21-Dec-23 16-Jan-24 22 270
GR-CON-Z10-1195 Backfilling (sand / Sub base) 21-Dec-23 01-Jan-24 9 270
GR-CON-Z10-1196 Installation of Paving 01-Jan-24 16-Jan-24 13 270
Landscape Works 10-Dec-23 25-Nov-24 286 16
GR-CON-Z10-1197 Excavation (Tree Pit ) 10-Dec-23 16-Dec-23 5 218
GR-CON-Z10-1198 Aggregate Drainage layer 16-Dec-23 23-Dec-23 6 218
GR-CON-Z10-1199 Installation Geotextile 23-Dec-23 28-Dec-23 5 218
GR-CON-Z10-1200 Backfilling (Soil max for tree) 28-Dec-23 03-Jan-24 5 218
GR-CON-Z10-1201 Installation of Trees 11-Sep-24 16-Sep-24 4 16
GR-CON-Z10-4026 Installation of Climbers 16-Sep-24 21-Sep-24 4 16
GR-CON-Z10-4036 Installation of Shrubs 21-Sep-24 26-Sep-24 4 16
GR-CON-Z10-4046 Installation of Succulents 26-Sep-24 01-Oct-24 4 16
GR-CON-Z10-4056 Installation of Ground Covers 01-Oct-24 06-Oct-24 4 16
GR-CON-Z10-1202 Backfilling (Mulch) 06-Oct-24 23-Oct-24 15 16
GR-CON-Z10-1203 Natural Boulders Installation 23-Oct-24 07-Nov-24 13 16
GR-CON-Z10-1204 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Nov-24 25-Nov-24 15 16
Irrigation Works 10-Dec-23 25-Nov-24 286 16
GR-CON-Z10-1205 Excavation Pipe Irrigation 10-Dec-23 16-Dec-23 5 185
GR-CON-Z10-1206 Sand Bedding 16-Dec-23 19-Dec-23 3 185
GR-CON-Z10-1207 HDPE Pipe Installations and fittings and conduit for cable 19-Dec-23 06-Jan-24 15 185
GR-CON-Z10-1209 Test pressure 06-Jan-24 11-Jan-24 5 185
GR-CON-Z10-1208 Installation of Valves and Accessories 11-Jan-24 16-Jan-24 4 185
GR-CON-Z10-1210 Back filling (sand / Subbase ) 16-Jan-24 23-Jan-24 6 185
GR-CON-Z10-1211 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-Jan-24 30-Jan-24 6 252
GR-CON-Z10-1212 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Nov-24
system 25-Nov-24 6 16
Parking P-18 22-Jan-24 15-Oct-24 214 51
Site Preparation 22-Jan-24 29-Jan-24 6 246
GR-CON-Z10-1244 Backfilling 22-Jan-24 29-Jan-24 6 246
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1242 Excavation And Disposal 23-Jan-24 29-Jan-24 5 142


GR-CON-Z10-1241 Demolition (Asphalt.Paving,etc.....) 24-Jan-24 29-Jan-24 4 23
GR-CON-Z10-1243 Prepretion And Compaction 24-Jan-24 29-Jan-24 4 246
Curbstone and Paving 29-Jan-24 25-Mar-24 46 213
GR-CON-Z10-1245 Excavation Curbstone 29-Jan-24 04-Feb-24 5 205
GR-CON-Z10-1246 Plain Concrete 04-Feb-24 11-Feb-24 6 213
GR-CON-Z10-1247 Installation Curbstone 11-Feb-24 21-Feb-24 9 213
GR-CON-Z10-1248 Casting Concrete (Mortar haunch) 21-Feb-24 26-Feb-24 4 213
GR-CON-Z10-1249 Backfilling (sand / Sub base) 26-Feb-24 07-Mar-24 9 213
GR-CON-Z10-1250 Installation of Paving 07-Mar-24 25-Mar-24 13 213
Landscape Works 04-Feb-24 03-Oct-24 193 51
GR-CON-Z10-1251 Excavation (Tree Pit ) 04-Feb-24 10-Feb-24 5 205
GR-CON-Z10-1252 Aggregate Drainage layer 10-Feb-24 17-Feb-24 6 205
GR-CON-Z10-1253 Installation Geotextile 17-Feb-24 21-Feb-24 4 205
GR-CON-Z10-1254 Backfilling (Soil max for tree) 21-Feb-24 28-Feb-24 6 205
GR-CON-Z10-1255 Installation of Trees 11-Sep-24 15-Sep-24 3 51
GR-CON-Z10-7456 Installation of Shrubs 15-Sep-24 18-Sep-24 3 51
GR-CON-Z10-7466 Installation of Ground Covers 18-Sep-24 22-Sep-24 3 51
GR-CON-Z10-7476 Installation of Succulents 22-Sep-24 26-Sep-24 3 51
GR-CON-Z10-7486 Installation of Grass 26-Sep-24 30-Sep-24 3 51
GR-CON-Z10-1256 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 51
Site Furnishing 03-Oct-24 15-Oct-24 10 51
GR-CON-Z10-1267 Tree Grate 03-Oct-24 09-Oct-24 5 51
GR-CON-Z10-1268 Wheel stoppers 09-Oct-24 15-Oct-24 5 51
Irrigation Works 29-Jan-24 15-Oct-24 208 51
GR-CON-Z10-1259 Excavation Pipe Irrigation 29-Jan-24 04-Feb-24 5 142
GR-CON-Z10-1260 Sand Bedding 04-Feb-24 07-Feb-24 3 142
GR-CON-Z10-1261 HDPE Pipe Installations and fittings and conduit for cable 07-Feb-24 25-Feb-24 15 142
GR-CON-Z10-1263 Test pressure 25-Feb-24 02-Mar-24 5 142
GR-CON-Z10-1262 Installation of Valves and Accessories 02-Mar-24 06-Mar-24 4 142
GR-CON-Z10-1264 Back filling (sand / Subbase ) 06-Mar-24 13-Mar-24 6 142
GR-CON-Z10-1265 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Mar-24 23-Mar-24 6 207
GR-CON-Z10-1266 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Oct-24
system 15-Oct-24 8 51
Parking P-31 27-Jan-24 15-Oct-24 210 51
Site Preparation 27-Jan-24 03-Feb-24 6 242
GR-CON-Z10-1328 Backfilling 27-Jan-24 03-Feb-24 6 242
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1326 Excavation And Disposal 28-Jan-24 03-Feb-24 5 138


GR-CON-Z10-1325 Demolition (Asphalt.Paving,etc.....) 29-Jan-24 03-Feb-24 4 23
GR-CON-Z10-1327 Prepretion And Compaction 29-Jan-24 03-Feb-24 4 242
Curbstone and Paving 03-Feb-24 01-Apr-24 46 209
GR-CON-Z10-1329 Excavation Curbstone 03-Feb-24 08-Feb-24 5 201
GR-CON-Z10-1330 Plain Concrete 08-Feb-24 15-Feb-24 6 209
GR-CON-Z10-1331 Installation Curbstone 15-Feb-24 26-Feb-24 9 209
GR-CON-Z10-1332 Casting Concrete (Mortar haunch) 26-Feb-24 02-Mar-24 4 209
GR-CON-Z10-1333 Backfilling (sand / Sub base) 02-Mar-24 12-Mar-24 9 209
GR-CON-Z10-1334 Installation of Paving 12-Mar-24 01-Apr-24 13 209
Landscape Works 08-Feb-24 03-Oct-24 189 51
GR-CON-Z10-1335 Excavation (Tree Pit ) 08-Feb-24 14-Feb-24 5 201
GR-CON-Z10-1336 Aggregate Drainage layer 14-Feb-24 21-Feb-24 6 201
GR-CON-Z10-1337 Installation Geotextile 21-Feb-24 26-Feb-24 4 201
GR-CON-Z10-1338 Backfilling (Soil max for tree) 26-Feb-24 04-Mar-24 6 201
GR-CON-Z10-1339 Installation of Trees 11-Sep-24 15-Sep-24 3 51
GR-CON-Z10-7576 Installation of Shrubs 15-Sep-24 18-Sep-24 3 51
GR-CON-Z10-7586 Installation of Ground Covers 18-Sep-24 22-Sep-24 3 51
GR-CON-Z10-7596 Installation of Succulents 22-Sep-24 26-Sep-24 3 51
GR-CON-Z10-7606 Installation of Grass 26-Sep-24 30-Sep-24 3 51
GR-CON-Z10-1340 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 51
Site Furnishing 03-Oct-24 15-Oct-24 10 51
GR-CON-Z10-1351 Tree Grate 03-Oct-24 09-Oct-24 5 51
GR-CON-Z10-1352 Wheel stoppers 09-Oct-24 15-Oct-24 5 51
Irrigation Works 03-Feb-24 15-Oct-24 204 51
GR-CON-Z10-1343 Excavation Pipe Irrigation 03-Feb-24 08-Feb-24 5 138
GR-CON-Z10-1344 Sand Bedding 08-Feb-24 12-Feb-24 3 138
GR-CON-Z10-1345 HDPE Pipe Installations and fittings and conduit for cable 12-Feb-24 29-Feb-24 15 138
GR-CON-Z10-1347 Test pressure 29-Feb-24 06-Mar-24 5 138
GR-CON-Z10-1346 Installation of Valves and Accessories 06-Mar-24 11-Mar-24 4 138
GR-CON-Z10-1348 Back filling (sand / Subbase ) 11-Mar-24 19-Mar-24 6 138
GR-CON-Z10-1349 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-Mar-24 28-Mar-24 6 203
GR-CON-Z10-1350 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Oct-24
system 15-Oct-24 8 51
Parking P-14 18-Feb-24 15-Oct-24 191 51
Site Preparation 18-Feb-24 25-Feb-24 6 223
GR-CON-Z10-1216 Backfilling 18-Feb-24 25-Feb-24 6 223
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1214 Excavation And Disposal 19-Feb-24 25-Feb-24 5 119


GR-CON-Z10-1213 Demolition (Asphalt.Paving,etc.....) 20-Feb-24 25-Feb-24 4 8
GR-CON-Z10-1215 Prepretion And Compaction 20-Feb-24 25-Feb-24 4 223
Curbstone and Paving 25-Feb-24 30-Apr-24 46 190
GR-CON-Z10-1217 Excavation Curbstone 25-Feb-24 02-Mar-24 5 182
GR-CON-Z10-1218 Plain Concrete 02-Mar-24 09-Mar-24 6 190
GR-CON-Z10-1219 Installation Curbstone 09-Mar-24 21-Mar-24 9 190
GR-CON-Z10-1220 Casting Concrete (Mortar haunch) 21-Mar-24 27-Mar-24 4 190
GR-CON-Z10-1221 Backfilling (sand / Sub base) 27-Mar-24 10-Apr-24 9 190
GR-CON-Z10-1222 Installation of Paving 10-Apr-24 30-Apr-24 13 190
Landscape Works 02-Mar-24 03-Oct-24 170 51
GR-CON-Z10-1223 Excavation (Tree Pit ) 02-Mar-24 07-Mar-24 5 182
GR-CON-Z10-1224 Aggregate Drainage layer 07-Mar-24 14-Mar-24 6 182
GR-CON-Z10-1225 Installation Geotextile 16-Mar-24 21-Mar-24 4 182
GR-CON-Z10-1226 Backfilling (Soil max for tree) 21-Mar-24 31-Mar-24 6 182
GR-CON-Z10-1227 Installation of Trees 11-Sep-24 15-Sep-24 3 51
GR-CON-Z10-7416 Installation of Shrubs 15-Sep-24 18-Sep-24 3 51
GR-CON-Z10-7426 Installation of Ground Covers 18-Sep-24 22-Sep-24 3 51
GR-CON-Z10-7436 Installation of Succulents 22-Sep-24 26-Sep-24 3 51
GR-CON-Z10-7446 Installation of Grass 26-Sep-24 30-Sep-24 3 51
GR-CON-Z10-1228 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 51
Site Furnishing 03-Oct-24 15-Oct-24 10 51
GR-CON-Z10-1239 Tree Grate 03-Oct-24 09-Oct-24 5 51
GR-CON-Z10-1240 Wheel stoppers 09-Oct-24 15-Oct-24 5 51
Irrigation Works 25-Feb-24 15-Oct-24 185 51
GR-CON-Z10-1231 Excavation Pipe Irrigation 25-Feb-24 02-Mar-24 5 119
GR-CON-Z10-1232 Sand Bedding 02-Mar-24 05-Mar-24 3 119
GR-CON-Z10-1233 HDPE Pipe Installations and fittings and conduit for cable 05-Mar-24 26-Mar-24 15 119
GR-CON-Z10-1235 Test pressure 26-Mar-24 02-Apr-24 5 119
GR-CON-Z10-1234 Installation of Valves and Accessories 03-Apr-24 09-Apr-24 4 119
GR-CON-Z10-1236 Back filling (sand / Subbase ) 09-Apr-24 21-Apr-24 6 119
GR-CON-Z10-1237 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 22-Apr-24 28-Apr-24 6 184
GR-CON-Z10-1238 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Oct-24
system 15-Oct-24 8 51
Parking P-22 22-Feb-24 15-Oct-24 187 51
Site Preparation 22-Feb-24 29-Feb-24 6 219
GR-CON-Z10-1272 Backfilling 22-Feb-24 29-Feb-24 6 219
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1270 Excavation And Disposal 24-Feb-24 29-Feb-24 5 115


GR-CON-Z10-1269 Demolition (Asphalt.Paving,etc.....) 25-Feb-24 29-Feb-24 4 8
GR-CON-Z10-1271 Prepretion And Compaction 25-Feb-24 29-Feb-24 4 219
Curbstone and Paving 29-Feb-24 05-May-24 46 186
GR-CON-Z10-1273 Excavation Curbstone 29-Feb-24 06-Mar-24 5 178
GR-CON-Z10-1274 Plain Concrete 06-Mar-24 13-Mar-24 6 186
GR-CON-Z10-1275 Installation Curbstone 13-Mar-24 27-Mar-24 9 186
GR-CON-Z10-1276 Casting Concrete (Mortar haunch) 27-Mar-24 02-Apr-24 4 186
GR-CON-Z10-1277 Backfilling (sand / Sub base) 03-Apr-24 20-Apr-24 9 186
GR-CON-Z10-1278 Installation of Paving 21-Apr-24 05-May-24 13 186
Landscape Works 06-Mar-24 03-Oct-24 166 51
GR-CON-Z10-1279 Excavation (Tree Pit ) 06-Mar-24 12-Mar-24 5 178
GR-CON-Z10-1280 Aggregate Drainage layer 12-Mar-24 21-Mar-24 6 178
GR-CON-Z10-1281 Installation Geotextile 21-Mar-24 27-Mar-24 4 178
GR-CON-Z10-1282 Backfilling (Soil max for tree) 27-Mar-24 06-Apr-24 6 178
GR-CON-Z10-1283 Installation of Trees 11-Sep-24 15-Sep-24 3 51
GR-CON-Z10-7496 Installation of Shrubs 15-Sep-24 18-Sep-24 3 51
GR-CON-Z10-7506 Installation of Ground Covers 18-Sep-24 22-Sep-24 3 51
GR-CON-Z10-7516 Installation of Succulents 22-Sep-24 26-Sep-24 3 51
GR-CON-Z10-7526 Installation of Grass 26-Sep-24 30-Sep-24 3 51
GR-CON-Z10-1284 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 51
Site Furnishing 03-Oct-24 15-Oct-24 10 51
GR-CON-Z10-1295 Tree Grate 03-Oct-24 09-Oct-24 5 51
GR-CON-Z10-1296 Wheel stoppers 09-Oct-24 15-Oct-24 5 51
Irrigation Works 29-Feb-24 15-Oct-24 181 51
GR-CON-Z10-1287 Excavation Pipe Irrigation 29-Feb-24 06-Mar-24 5 115
GR-CON-Z10-1288 Sand Bedding 06-Mar-24 10-Mar-24 3 115
GR-CON-Z10-1289 HDPE Pipe Installations and fittings and conduit for cable 10-Mar-24 01-Apr-24 15 115
GR-CON-Z10-1291 Test pressure 01-Apr-24 09-Apr-24 5 115
GR-CON-Z10-1290 Installation of Valves and Accessories 09-Apr-24 18-Apr-24 4 115
GR-CON-Z10-1292 Back filling (sand / Subbase ) 20-Apr-24 25-Apr-24 6 115
GR-CON-Z10-1293 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-Apr-24 02-May-24 6 180
GR-CON-Z10-1294 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Oct-24
system 15-Oct-24 8 51
Parking P-24 29-Feb-24 15-Oct-24 181 51
Site Preparation 29-Feb-24 26-Mar-24 19 200
GR-CON-Z10-1297 Demolition (Asphalt.Paving,etc.....) 29-Feb-24 05-Mar-24 4 8
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1298 Excavation And Disposal 05-Mar-24 11-Mar-24 5 106


GR-CON-Z10-1299 Prepretion And Compaction 11-Mar-24 17-Mar-24 4 200
GR-CON-Z10-1300 Backfilling 17-Mar-24 26-Mar-24 6 200
Curbstone and Paving 11-Mar-24 15-May-24 46 177
GR-CON-Z10-1301 Excavation Curbstone 11-Mar-24 18-Mar-24 5 169
GR-CON-Z10-1302 Plain Concrete 18-Mar-24 27-Mar-24 6 177
GR-CON-Z10-1303 Installation Curbstone 27-Mar-24 10-Apr-24 9 177
GR-CON-Z10-1304 Casting Concrete (Mortar haunch) 10-Apr-24 20-Apr-24 4 177
GR-CON-Z10-1305 Backfilling (sand / Sub base) 21-Apr-24 30-Apr-24 9 177
GR-CON-Z10-1306 Installation of Paving 01-May-24 15-May-24 13 177
Landscape Works 18-Mar-24 03-Oct-24 157 51
GR-CON-Z10-1307 Excavation (Tree Pit ) 18-Mar-24 26-Mar-24 5 169
GR-CON-Z10-1308 Aggregate Drainage layer 26-Mar-24 04-Apr-24 6 169
GR-CON-Z10-1309 Installation Geotextile 04-Apr-24 10-Apr-24 4 169
GR-CON-Z10-1310 Backfilling (Soil max for tree) 10-Apr-24 22-Apr-24 6 169
GR-CON-Z10-1311 Installation of Trees 11-Sep-24 15-Sep-24 3 51
GR-CON-Z10-7536 Installation of Shrubs 15-Sep-24 18-Sep-24 3 51
GR-CON-Z10-7546 Installation of Ground Covers 18-Sep-24 22-Sep-24 3 51
GR-CON-Z10-7556 Installation of Succulents 22-Sep-24 26-Sep-24 3 51
GR-CON-Z10-7566 Installation of Grass 26-Sep-24 30-Sep-24 3 51
GR-CON-Z10-1312 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 51
Site Furnishing 03-Oct-24 15-Oct-24 10 51
GR-CON-Z10-1323 Tree Grate 03-Oct-24 09-Oct-24 5 51
GR-CON-Z10-1324 Wheel stoppers 09-Oct-24 15-Oct-24 5 51
Irrigation Works 11-Mar-24 15-Oct-24 172 51
GR-CON-Z10-1315 Excavation Pipe Irrigation 11-Mar-24 18-Mar-24 5 106
GR-CON-Z10-1316 Sand Bedding 18-Mar-24 23-Mar-24 3 106
GR-CON-Z10-1317 HDPE Pipe Installations and fittings and conduit for cable 23-Mar-24 18-Apr-24 15 106
GR-CON-Z10-1319 Test pressure 20-Apr-24 24-Apr-24 5 106
GR-CON-Z10-1318 Installation of Valves and Accessories 25-Apr-24 29-Apr-24 4 106
GR-CON-Z10-1320 Back filling (sand / Subbase ) 30-Apr-24 06-May-24 6 106
GR-CON-Z10-1321 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 07-May-24 13-May-24 6 171
GR-CON-Z10-1322 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Oct-24
system 15-Oct-24 8 51
Street SS-09 03-Mar-24 14-Dec-24 230 0
Site Preparation 03-Mar-24 21-Apr-24 32 198
GR-CON-Z10-1649 Demolition (Asphalt.Paving,etc.....) 03-Mar-24 10-Mar-24 6 77
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1650 Excavation And Disposal 10-Mar-24 21-Mar-24 8 77


GR-CON-Z10-1651 Prepretion And Compaction 21-Mar-24 04-Apr-24 9 198
GR-CON-Z10-1652 Backfilling 04-Apr-24 21-Apr-24 9 198
Curbstone and Paving 21-Mar-24 26-Jun-24 71 145
GR-CON-Z10-1653 Excavation Curbstone 21-Mar-24 02-Apr-24 8 97
GR-CON-Z10-1654 Plain Concrete 03-Apr-24 20-Apr-24 9 145
GR-CON-Z10-1655 Installation Curbstone 21-Apr-24 06-May-24 14 145
GR-CON-Z10-1656 Casting Concrete (Mortar haunch) 07-May-24 13-May-24 6 145
GR-CON-Z10-1657 Backfilling (sand / Sub base) 14-May-24 29-May-24 14 145
GR-CON-Z10-1658 Installation of Paving 30-May-24 26-Jun-24 20 145
Landscape Works 03-Apr-24 06-Nov-24 176 0
GR-CON-Z10-1659 Excavation (Tree Pit ) 03-Apr-24 18-Apr-24 8 97
GR-CON-Z10-1660 Aggregate Drainage layer 20-Apr-24 29-Apr-24 9 97
GR-CON-Z10-1661 Installation Geotextile 30-Apr-24 06-May-24 6 97
GR-CON-Z10-1662 Backfilling (Soil max for tree) 07-May-24 16-May-24 9 97
GR-CON-Z10-1663 Installation of Trees 11-Sep-24 16-Sep-24 4 0
GR-CON-Z10-11736 Installation of Shrubs 16-Sep-24 19-Sep-24 3 0
GR-CON-Z10-11746 Installation of Succulents 19-Sep-24 24-Sep-24 3 0
GR-CON-Z10-11756 Installation of Ground Covers 24-Sep-24 28-Sep-24 3 0
GR-CON-Z10-11766 Installation of Grass 28-Sep-24 01-Oct-24 3 0
GR-CON-Z10-1664 Backfilling (Mulch) 01-Oct-24 07-Oct-24 5 0
GR-CON-Z10-1665 Natural Boulders Installation 07-Oct-24 14-Oct-24 6 0
GR-CON-Z10-1666 Retaining walls . Steps, forming risers, treads and edges with finishes
14-Oct-24 06-Nov-24 20 0
Site Furnishing 06-Nov-24 14-Dec-24 32 0
GR-CON-Z10-1675 Garden planter box 06-Nov-24 16-Nov-24 8 0
GR-CON-Z10-1676 Wheel stoppers 16-Nov-24 25-Nov-24 8 0
GR-CON-Z10-1677 Steel Lattice 25-Nov-24 04-Dec-24 8 0
GR-CON-Z10-1678 Handrail 04-Dec-24 14-Dec-24 8 0
Storm Piping Works 03-Dec-24 14-Dec-24 9 0
GR-CON-Z10-1679 Installation of DI grating covers 03-Dec-24 14-Dec-24 9 0
Irrigation Works 21-Mar-24 08-Jul-24 81 126
GR-CON-Z10-1667 Excavation Pipe Irrigation 21-Mar-24 02-Apr-24 8 77
GR-CON-Z10-1668 Sand Bedding 03-Apr-24 11-Apr-24 6 77
GR-CON-Z10-1669 HDPE Pipe Installations and fittings and conduit for cable 17-Apr-24 13-May-24 23 77
GR-CON-Z10-1671 Test pressure 14-May-24 22-May-24 8 77
GR-CON-Z10-1670 Installation of Valves and Accessories 23-May-24 29-May-24 6 77
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1672 Back filling (sand / Subbase ) 30-May-24 09-Jun-24 9 77


GR-CON-Z10-1673 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Jun-24 24-Jun-24 9 126
GR-CON-Z10-1674 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jun-24
system 08-Jul-24 12 126
Electrical Works 03-Apr-24 14-Dec-24 208 0
GR-CON-Z10-1680 Excavation And Disposal 03-Apr-24 18-Apr-24 8 166
GR-CON-Z10-1681 Sand Bedding 20-Apr-24 25-Apr-24 6 166
GR-CON-Z10-1682 laying cables 27-Apr-24 02-May-24 6 166
GR-CON-Z10-1683 Backfilling (sand / Sub base) 04-May-24 12-May-24 8 166
GR-CON-Z10-1684 Control Panel / Distribution Panel Installation 13-May-24 19-May-24 6 166
GR-CON-Z10-1685 Road Crossing Ducts 04-Dec-24 14-Dec-24 8 0
Street SS-39 16-Mar-24 16-Nov-24 196 24
Site Preparation 16-Mar-24 20-Apr-24 21 199
GR-CON-Z10-1353 Demolition (Asphalt.Paving,etc.....) 16-Mar-24 21-Mar-24 4 0
GR-CON-Z10-1354 Excavation And Disposal 21-Mar-24 28-Mar-24 5 93
GR-CON-Z10-1355 Prepretion And Compaction 30-Mar-24 07-Apr-24 6 199
GR-CON-Z10-1356 Backfilling 08-Apr-24 20-Apr-24 6 199
Curbstone and Paving 30-Mar-24 29-May-24 46 165
GR-CON-Z10-1357 Excavation Curbstone 30-Mar-24 06-Apr-24 5 130
GR-CON-Z10-1358 Plain Concrete 06-Apr-24 18-Apr-24 6 165
GR-CON-Z10-1359 Installation Curbstone 20-Apr-24 29-Apr-24 9 165
GR-CON-Z10-1360 Casting Concrete (Mortar haunch) 30-Apr-24 04-May-24 4 165
GR-CON-Z10-1361 Backfilling (sand / Sub base) 05-May-24 14-May-24 9 165
GR-CON-Z10-1362 Installation of Paving 15-May-24 29-May-24 13 165
Landscape Works 06-Apr-24 23-Oct-24 162 24
GR-CON-Z10-1363 Excavation (Tree Pit ) 06-Apr-24 17-Apr-24 5 130
GR-CON-Z10-1364 Aggregate Drainage layer 18-Apr-24 24-Apr-24 6 130
GR-CON-Z10-1365 Installation Geotextile 25-Apr-24 29-Apr-24 4 130
GR-CON-Z10-1366 Backfilling (Soil max for tree) 30-Apr-24 06-May-24 6 130
GR-CON-Z10-1367 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11416 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
GR-CON-Z10-11426 Installation of Succulents 18-Sep-24 22-Sep-24 3 24
GR-CON-Z10-11436 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11446 Installation of Grass 26-Sep-24 30-Sep-24 3 24
GR-CON-Z10-1368 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 24
GR-CON-Z10-1369 Natural Boulders Installation 03-Oct-24 08-Oct-24 4 24
GR-CON-Z10-1370 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Oct-24 23-Oct-24 13 24
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Furnishing 23-Oct-24 16-Nov-24 20 24


GR-CON-Z10-1379 Garden planter box 23-Oct-24 29-Oct-24 5 24
GR-CON-Z10-1380 Wheel stoppers 29-Oct-24 04-Nov-24 5 24
GR-CON-Z10-1381 Steel Lattice 04-Nov-24 10-Nov-24 5 24
GR-CON-Z10-1382 Handrail 10-Nov-24 16-Nov-24 5 24
Storm Piping Works 09-Nov-24 16-Nov-24 6 24
GR-CON-Z10-1383 Installation of DI grating covers 09-Nov-24 16-Nov-24 6 24
Irrigation Works 30-Mar-24 06-Jun-24 53 152
GR-CON-Z10-1371 Excavation Pipe Irrigation 30-Mar-24 06-Apr-24 5 93
GR-CON-Z10-1372 Sand Bedding 06-Apr-24 11-Apr-24 4 93
GR-CON-Z10-1373 HDPE Pipe Installations and fittings and conduit for cable 17-Apr-24 04-May-24 15 93
GR-CON-Z10-1375 Test pressure 05-May-24 09-May-24 5 93
GR-CON-Z10-1374 Installation of Valves and Accessories 11-May-24 14-May-24 4 93
GR-CON-Z10-1376 Back filling (sand / Subbase ) 15-May-24 21-May-24 6 93
GR-CON-Z10-1377 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 22-May-24 28-May-24 6 152
GR-CON-Z10-1378 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
29-May-24
system 06-Jun-24 8 152
Electrical Works 06-Apr-24 16-Nov-24 182 24
GR-CON-Z10-1384 Excavation And Disposal 06-Apr-24 17-Apr-24 5 179
GR-CON-Z10-1385 Sand Bedding 18-Apr-24 22-Apr-24 4 179
GR-CON-Z10-1386 laying cables 23-Apr-24 27-Apr-24 4 179
GR-CON-Z10-1387 Backfilling (sand / Sub base) 28-Apr-24 02-May-24 5 179
GR-CON-Z10-1388 Control Panel / Distribution Panel Installation 04-May-24 07-May-24 4 179
GR-CON-Z10-1389 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Street SS-68 21-Mar-24 16-Nov-24 192 24
Site Preparation 21-Mar-24 24-Apr-24 21 195
GR-CON-Z10-1390 Demolition (Asphalt.Paving,etc.....) 21-Mar-24 27-Mar-24 4 0
GR-CON-Z10-1391 Excavation And Disposal 27-Mar-24 04-Apr-24 5 89
GR-CON-Z10-1392 Prepretion And Compaction 04-Apr-24 17-Apr-24 6 195
GR-CON-Z10-1393 Backfilling 18-Apr-24 24-Apr-24 6 195
Curbstone and Paving 04-Apr-24 03-Jun-24 46 161
GR-CON-Z10-1394 Excavation Curbstone 04-Apr-24 11-Apr-24 5 126
GR-CON-Z10-1395 Plain Concrete 17-Apr-24 23-Apr-24 6 161
GR-CON-Z10-1396 Installation Curbstone 24-Apr-24 04-May-24 9 161
GR-CON-Z10-1397 Casting Concrete (Mortar haunch) 05-May-24 08-May-24 4 161
GR-CON-Z10-1398 Backfilling (sand / Sub base) 09-May-24 19-May-24 9 161
GR-CON-Z10-1399 Installation of Paving 20-May-24 03-Jun-24 13 161
Activity ID Activity Name Start Finish Original Total Float
Duration

Landscape Works 17-Apr-24 23-Oct-24 158 24


GR-CON-Z10-1400 Excavation (Tree Pit ) 17-Apr-24 22-Apr-24 5 126
GR-CON-Z10-1401 Aggregate Drainage layer 23-Apr-24 29-Apr-24 6 126
GR-CON-Z10-1402 Installation Geotextile 30-Apr-24 04-May-24 4 126
GR-CON-Z10-1403 Backfilling (Soil max for tree) 05-May-24 11-May-24 6 126
GR-CON-Z10-1404 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11456 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
GR-CON-Z10-11466 Installation of Succulents 18-Sep-24 22-Sep-24 3 24
GR-CON-Z10-11476 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11486 Installation of Grass 26-Sep-24 30-Sep-24 3 24
GR-CON-Z10-1405 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 24
GR-CON-Z10-1406 Natural Boulders Installation 03-Oct-24 08-Oct-24 4 24
GR-CON-Z10-1407 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Oct-24 23-Oct-24 13 24
Site Furnishing 23-Oct-24 16-Nov-24 20 24
GR-CON-Z10-1416 Garden planter box 23-Oct-24 29-Oct-24 5 24
GR-CON-Z10-1417 Wheel stoppers 29-Oct-24 04-Nov-24 5 24
GR-CON-Z10-1418 Steel Lattice 04-Nov-24 10-Nov-24 5 24
GR-CON-Z10-1419 Handrail 10-Nov-24 16-Nov-24 5 24
Storm Piping Works 09-Nov-24 16-Nov-24 6 24
GR-CON-Z10-1420 Installation of DI grating covers 09-Nov-24 16-Nov-24 6 24
Irrigation Works 04-Apr-24 11-Jun-24 53 148
GR-CON-Z10-1408 Excavation Pipe Irrigation 04-Apr-24 11-Apr-24 5 89
GR-CON-Z10-1409 Sand Bedding 17-Apr-24 21-Apr-24 4 89
GR-CON-Z10-1410 HDPE Pipe Installations and fittings and conduit for cable 22-Apr-24 08-May-24 15 89
GR-CON-Z10-1412 Test pressure 09-May-24 14-May-24 5 89
GR-CON-Z10-1411 Installation of Valves and Accessories 15-May-24 19-May-24 4 89
GR-CON-Z10-1413 Back filling (sand / Subbase ) 20-May-24 26-May-24 6 89
GR-CON-Z10-1414 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-May-24 02-Jun-24 6 148
GR-CON-Z10-1415 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jun-24
system 11-Jun-24 8 148
Electrical Works 17-Apr-24 16-Nov-24 178 24
GR-CON-Z10-1421 Excavation And Disposal 17-Apr-24 22-Apr-24 5 175
GR-CON-Z10-1422 Sand Bedding 23-Apr-24 27-Apr-24 4 175
GR-CON-Z10-1423 laying cables 28-Apr-24 01-May-24 4 175
GR-CON-Z10-1424 Backfilling (sand / Sub base) 02-May-24 07-May-24 5 175
GR-CON-Z10-1425 Control Panel / Distribution Panel Installation 08-May-24 12-May-24 4 175
GR-CON-Z10-1426 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Activity ID Activity Name Start Finish Original Total Float
Duration

Street SS-72 27-Mar-24 16-Nov-24 188 24


Site Preparation 27-Mar-24 29-Apr-24 21 191
GR-CON-Z10-1427 Demolition (Asphalt.Paving,etc.....) 27-Mar-24 02-Apr-24 4 0
GR-CON-Z10-1428 Excavation And Disposal 03-Apr-24 10-Apr-24 5 85
GR-CON-Z10-1429 Prepretion And Compaction 10-Apr-24 22-Apr-24 6 191
GR-CON-Z10-1430 Backfilling 23-Apr-24 29-Apr-24 6 191
Curbstone and Paving 10-Apr-24 08-Jun-24 46 157
GR-CON-Z10-1431 Excavation Curbstone 10-Apr-24 21-Apr-24 5 122
GR-CON-Z10-1432 Plain Concrete 22-Apr-24 28-Apr-24 6 157
GR-CON-Z10-1433 Installation Curbstone 29-Apr-24 08-May-24 9 157
GR-CON-Z10-1434 Casting Concrete (Mortar haunch) 09-May-24 13-May-24 4 157
GR-CON-Z10-1435 Backfilling (sand / Sub base) 14-May-24 23-May-24 9 157
GR-CON-Z10-1436 Installation of Paving 25-May-24 08-Jun-24 13 157
Landscape Works 22-Apr-24 23-Oct-24 154 24
GR-CON-Z10-1437 Excavation (Tree Pit ) 22-Apr-24 27-Apr-24 5 122
GR-CON-Z10-1438 Aggregate Drainage layer 28-Apr-24 04-May-24 6 122
GR-CON-Z10-1439 Installation Geotextile 05-May-24 08-May-24 4 122
GR-CON-Z10-1440 Backfilling (Soil max for tree) 09-May-24 15-May-24 6 122
GR-CON-Z10-1441 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11496 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
GR-CON-Z10-11506 Installation of Succulents 18-Sep-24 22-Sep-24 3 24
GR-CON-Z10-11516 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11526 Installation of Grass 26-Sep-24 30-Sep-24 3 24
GR-CON-Z10-1442 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 24
GR-CON-Z10-1443 Natural Boulders Installation 03-Oct-24 08-Oct-24 4 24
GR-CON-Z10-1444 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Oct-24 23-Oct-24 13 24
Site Furnishing 23-Oct-24 16-Nov-24 20 24
GR-CON-Z10-1453 Garden planter box 23-Oct-24 29-Oct-24 5 24
GR-CON-Z10-1454 Wheel stoppers 29-Oct-24 04-Nov-24 5 24
GR-CON-Z10-1455 Steel Lattice 04-Nov-24 10-Nov-24 5 24
GR-CON-Z10-1456 Handrail 10-Nov-24 16-Nov-24 5 24
Storm Piping Works 09-Nov-24 16-Nov-24 6 24
GR-CON-Z10-1457 Installation of DI grating covers 09-Nov-24 16-Nov-24 6 24
Irrigation Works 10-Apr-24 16-Jun-24 53 144
GR-CON-Z10-1445 Excavation Pipe Irrigation 10-Apr-24 21-Apr-24 5 85
GR-CON-Z10-1446 Sand Bedding 22-Apr-24 25-Apr-24 4 85
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1447 HDPE Pipe Installations and fittings and conduit for cable 27-Apr-24 13-May-24 15 85
GR-CON-Z10-1449 Test pressure 14-May-24 19-May-24 5 85
GR-CON-Z10-1448 Installation of Valves and Accessories 20-May-24 23-May-24 4 85
GR-CON-Z10-1450 Back filling (sand / Subbase ) 25-May-24 30-May-24 6 85
GR-CON-Z10-1451 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Jun-24 06-Jun-24 6 144
GR-CON-Z10-1452 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Jun-24
system 16-Jun-24 8 144
Electrical Works 22-Apr-24 16-Nov-24 174 24
GR-CON-Z10-1458 Excavation And Disposal 22-Apr-24 27-Apr-24 5 171
GR-CON-Z10-1459 Sand Bedding 28-Apr-24 01-May-24 4 171
GR-CON-Z10-1460 laying cables 02-May-24 06-May-24 4 171
GR-CON-Z10-1461 Backfilling (sand / Sub base) 07-May-24 12-May-24 5 171
GR-CON-Z10-1462 Control Panel / Distribution Panel Installation 13-May-24 16-May-24 4 171
GR-CON-Z10-1463 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Street SS-73 03-Apr-24 16-Nov-24 184 24
Site Preparation 03-Apr-24 04-May-24 21 187
GR-CON-Z10-1464 Demolition (Asphalt.Paving,etc.....) 03-Apr-24 09-Apr-24 4 0
GR-CON-Z10-1465 Excavation And Disposal 09-Apr-24 20-Apr-24 5 81
GR-CON-Z10-1466 Prepretion And Compaction 21-Apr-24 27-Apr-24 6 187
GR-CON-Z10-1467 Backfilling 28-Apr-24 04-May-24 6 187
Curbstone and Paving 21-Apr-24 12-Jun-24 46 153
GR-CON-Z10-1468 Excavation Curbstone 21-Apr-24 25-Apr-24 5 118
GR-CON-Z10-1469 Plain Concrete 27-Apr-24 02-May-24 6 153
GR-CON-Z10-1470 Installation Curbstone 04-May-24 13-May-24 9 153
GR-CON-Z10-1471 Casting Concrete (Mortar haunch) 14-May-24 18-May-24 4 153
GR-CON-Z10-1472 Backfilling (sand / Sub base) 19-May-24 28-May-24 9 153
GR-CON-Z10-1473 Installation of Paving 29-May-24 12-Jun-24 13 153
Landscape Works 27-Apr-24 23-Oct-24 150 24
GR-CON-Z10-1474 Excavation (Tree Pit ) 27-Apr-24 01-May-24 5 118
GR-CON-Z10-1475 Aggregate Drainage layer 02-May-24 08-May-24 6 118
GR-CON-Z10-1476 Installation Geotextile 09-May-24 13-May-24 4 118
GR-CON-Z10-1477 Backfilling (Soil max for tree) 14-May-24 20-May-24 6 118
GR-CON-Z10-1478 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11536 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
GR-CON-Z10-11546 Installation of Succulents 18-Sep-24 22-Sep-24 3 24
GR-CON-Z10-11556 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11566 Installation of Grass 26-Sep-24 30-Sep-24 3 24
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1479 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 24


GR-CON-Z10-1480 Natural Boulders Installation 03-Oct-24 08-Oct-24 4 24
GR-CON-Z10-1481 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Oct-24 23-Oct-24 13 24
Site Furnishing 23-Oct-24 16-Nov-24 20 24
GR-CON-Z10-1490 Garden planter box 23-Oct-24 29-Oct-24 5 24
GR-CON-Z10-1491 Wheel stoppers 29-Oct-24 04-Nov-24 5 24
GR-CON-Z10-1492 Steel Lattice 04-Nov-24 10-Nov-24 5 24
GR-CON-Z10-1493 Handrail 10-Nov-24 16-Nov-24 5 24
Storm Piping Works 09-Nov-24 16-Nov-24 6 24
GR-CON-Z10-1494 Installation of DI grating covers 09-Nov-24 16-Nov-24 6 24
Irrigation Works 21-Apr-24 25-Jun-24 53 140
GR-CON-Z10-1482 Excavation Pipe Irrigation 21-Apr-24 25-Apr-24 5 81
GR-CON-Z10-1483 Sand Bedding 27-Apr-24 30-Apr-24 4 81
GR-CON-Z10-1484 HDPE Pipe Installations and fittings and conduit for cable 01-May-24 18-May-24 15 81
GR-CON-Z10-1486 Test pressure 19-May-24 23-May-24 5 81
GR-CON-Z10-1485 Installation of Valves and Accessories 25-May-24 28-May-24 4 81
GR-CON-Z10-1487 Back filling (sand / Subbase ) 29-May-24 04-Jun-24 6 81
GR-CON-Z10-1488 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-Jun-24 11-Jun-24 6 140
GR-CON-Z10-1489 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-Jun-24
system 25-Jun-24 8 140
Electrical Works 27-Apr-24 16-Nov-24 170 24
GR-CON-Z10-1495 Excavation And Disposal 27-Apr-24 01-May-24 5 167
GR-CON-Z10-1496 Sand Bedding 02-May-24 06-May-24 4 167
GR-CON-Z10-1497 laying cables 07-May-24 11-May-24 4 167
GR-CON-Z10-1498 Backfilling (sand / Sub base) 12-May-24 16-May-24 5 167
GR-CON-Z10-1499 Control Panel / Distribution Panel Installation 18-May-24 21-May-24 4 167
GR-CON-Z10-1500 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Street SS-75 09-Apr-24 16-Nov-24 180 24
Site Preparation 09-Apr-24 08-May-24 21 183
GR-CON-Z10-1501 Demolition (Asphalt.Paving,etc.....) 09-Apr-24 18-Apr-24 4 0
GR-CON-Z10-1502 Excavation And Disposal 20-Apr-24 24-Apr-24 5 77
GR-CON-Z10-1503 Prepretion And Compaction 25-Apr-24 01-May-24 6 183
GR-CON-Z10-1504 Backfilling 02-May-24 08-May-24 6 183
Curbstone and Paving 25-Apr-24 17-Jun-24 46 149
GR-CON-Z10-1505 Excavation Curbstone 25-Apr-24 30-Apr-24 5 114
GR-CON-Z10-1506 Plain Concrete 01-May-24 07-May-24 6 149
GR-CON-Z10-1507 Installation Curbstone 08-May-24 18-May-24 9 149
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1508 Casting Concrete (Mortar haunch) 19-May-24 22-May-24 4 149


GR-CON-Z10-1509 Backfilling (sand / Sub base) 23-May-24 02-Jun-24 9 149
GR-CON-Z10-1510 Installation of Paving 03-Jun-24 17-Jun-24 13 149
Landscape Works 01-May-24 23-Oct-24 146 24
GR-CON-Z10-1511 Excavation (Tree Pit ) 01-May-24 06-May-24 5 114
GR-CON-Z10-1512 Aggregate Drainage layer 07-May-24 13-May-24 6 114
GR-CON-Z10-1513 Installation Geotextile 14-May-24 18-May-24 4 114
GR-CON-Z10-1514 Backfilling (Soil max for tree) 19-May-24 25-May-24 6 114
GR-CON-Z10-1515 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11576 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
GR-CON-Z10-11586 Installation of Succulents 18-Sep-24 22-Sep-24 3 24
GR-CON-Z10-11596 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11606 Installation of Grass 26-Sep-24 30-Sep-24 3 24
GR-CON-Z10-1516 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 24
GR-CON-Z10-1517 Natural Boulders Installation 03-Oct-24 08-Oct-24 4 24
GR-CON-Z10-1518 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Oct-24 23-Oct-24 13 24
Site Furnishing 23-Oct-24 16-Nov-24 20 24
GR-CON-Z10-1527 Garden planter box 23-Oct-24 29-Oct-24 5 24
GR-CON-Z10-1528 Wheel stoppers 29-Oct-24 04-Nov-24 5 24
GR-CON-Z10-1529 Steel Lattice 04-Nov-24 10-Nov-24 5 24
GR-CON-Z10-1530 Handrail 10-Nov-24 16-Nov-24 5 24
Storm Piping Works 09-Nov-24 16-Nov-24 6 24
GR-CON-Z10-1531 Installation of DI grating covers 09-Nov-24 16-Nov-24 6 24
Irrigation Works 25-Apr-24 30-Jun-24 53 136
GR-CON-Z10-1519 Excavation Pipe Irrigation 25-Apr-24 30-Apr-24 5 77
GR-CON-Z10-1520 Sand Bedding 01-May-24 05-May-24 4 77
GR-CON-Z10-1521 HDPE Pipe Installations and fittings and conduit for cable 06-May-24 22-May-24 15 77
GR-CON-Z10-1523 Test pressure 23-May-24 28-May-24 5 77
GR-CON-Z10-1522 Installation of Valves and Accessories 29-May-24 02-Jun-24 4 77
GR-CON-Z10-1524 Back filling (sand / Subbase ) 03-Jun-24 09-Jun-24 6 77
GR-CON-Z10-1525 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Jun-24 16-Jun-24 6 136
GR-CON-Z10-1526 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Jun-24
system 30-Jun-24 8 136
Electrical Works 01-May-24 16-Nov-24 166 24
GR-CON-Z10-1532 Excavation And Disposal 01-May-24 06-May-24 5 163
GR-CON-Z10-1533 Sand Bedding 07-May-24 11-May-24 4 163
GR-CON-Z10-1534 laying cables 12-May-24 15-May-24 4 163
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1535 Backfilling (sand / Sub base) 16-May-24 21-May-24 5 163


GR-CON-Z10-1536 Control Panel / Distribution Panel Installation 22-May-24 26-May-24 4 163
GR-CON-Z10-1537 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Street SS-76 20-Apr-24 16-Nov-24 176 24
Site Preparation 20-Apr-24 13-May-24 21 179
GR-CON-Z10-1538 Demolition (Asphalt.Paving,etc.....) 20-Apr-24 23-Apr-24 4 0
GR-CON-Z10-1539 Excavation And Disposal 24-Apr-24 29-Apr-24 5 73
GR-CON-Z10-1540 Prepretion And Compaction 30-Apr-24 06-May-24 6 179
GR-CON-Z10-1541 Backfilling 07-May-24 13-May-24 6 179
Curbstone and Paving 30-Apr-24 26-Jun-24 46 145
GR-CON-Z10-1542 Excavation Curbstone 30-Apr-24 05-May-24 5 110
GR-CON-Z10-1543 Plain Concrete 06-May-24 12-May-24 6 145
GR-CON-Z10-1544 Installation Curbstone 13-May-24 22-May-24 9 145
GR-CON-Z10-1545 Casting Concrete (Mortar haunch) 23-May-24 27-May-24 4 145
GR-CON-Z10-1546 Backfilling (sand / Sub base) 28-May-24 06-Jun-24 9 145
GR-CON-Z10-1547 Installation of Paving 08-Jun-24 26-Jun-24 13 145
Landscape Works 06-May-24 23-Oct-24 142 24
GR-CON-Z10-1548 Excavation (Tree Pit ) 06-May-24 11-May-24 5 110
GR-CON-Z10-1549 Aggregate Drainage layer 12-May-24 18-May-24 6 110
GR-CON-Z10-1550 Installation Geotextile 19-May-24 22-May-24 4 110
GR-CON-Z10-1551 Backfilling (Soil max for tree) 23-May-24 29-May-24 6 110
GR-CON-Z10-1552 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11616 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
GR-CON-Z10-11626 Installation of Succulents 18-Sep-24 22-Sep-24 3 24
GR-CON-Z10-11636 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11646 Installation of Grass 26-Sep-24 30-Sep-24 3 24
GR-CON-Z10-1553 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 24
GR-CON-Z10-1554 Natural Boulders Installation 03-Oct-24 08-Oct-24 4 24
GR-CON-Z10-1555 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Oct-24 23-Oct-24 13 24
Site Furnishing 23-Oct-24 16-Nov-24 20 24
GR-CON-Z10-1564 Garden planter box 23-Oct-24 29-Oct-24 5 24
GR-CON-Z10-1565 Wheel stoppers 29-Oct-24 04-Nov-24 5 24
GR-CON-Z10-1566 Steel Lattice 04-Nov-24 10-Nov-24 5 24
GR-CON-Z10-1567 Handrail 10-Nov-24 16-Nov-24 5 24
Storm Piping Works 09-Nov-24 16-Nov-24 6 24
GR-CON-Z10-1568 Installation of DI grating covers 09-Nov-24 16-Nov-24 6 24
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 30-Apr-24 04-Jul-24 53 132


GR-CON-Z10-1556 Excavation Pipe Irrigation 30-Apr-24 05-May-24 5 73
GR-CON-Z10-1557 Sand Bedding 06-May-24 09-May-24 4 73
GR-CON-Z10-1558 HDPE Pipe Installations and fittings and conduit for cable 11-May-24 27-May-24 15 73
GR-CON-Z10-1560 Test pressure 28-May-24 02-Jun-24 5 73
GR-CON-Z10-1559 Installation of Valves and Accessories 03-Jun-24 06-Jun-24 4 73
GR-CON-Z10-1561 Back filling (sand / Subbase ) 08-Jun-24 13-Jun-24 6 73
GR-CON-Z10-1562 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Jun-24 25-Jun-24 6 132
GR-CON-Z10-1563 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-Jun-24
system 04-Jul-24 8 132
Electrical Works 06-May-24 16-Nov-24 162 24
GR-CON-Z10-1569 Excavation And Disposal 06-May-24 11-May-24 5 159
GR-CON-Z10-1570 Sand Bedding 12-May-24 15-May-24 4 159
GR-CON-Z10-1571 laying cables 16-May-24 20-May-24 4 159
GR-CON-Z10-1572 Backfilling (sand / Sub base) 21-May-24 26-May-24 5 159
GR-CON-Z10-1573 Control Panel / Distribution Panel Installation 27-May-24 30-May-24 4 159
GR-CON-Z10-1574 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Street SS-77 24-Apr-24 16-Nov-24 172 24
Site Preparation 24-Apr-24 18-May-24 21 175
GR-CON-Z10-1575 Demolition (Asphalt.Paving,etc.....) 24-Apr-24 28-Apr-24 4 0
GR-CON-Z10-1576 Excavation And Disposal 29-Apr-24 04-May-24 5 69
GR-CON-Z10-1577 Prepretion And Compaction 05-May-24 11-May-24 6 175
GR-CON-Z10-1578 Backfilling 12-May-24 18-May-24 6 175
Curbstone and Paving 05-May-24 01-Jul-24 46 141
GR-CON-Z10-1579 Excavation Curbstone 05-May-24 09-May-24 5 106
GR-CON-Z10-1580 Plain Concrete 11-May-24 16-May-24 6 141
GR-CON-Z10-1581 Installation Curbstone 18-May-24 27-May-24 9 141
GR-CON-Z10-1582 Casting Concrete (Mortar haunch) 28-May-24 01-Jun-24 4 141
GR-CON-Z10-1583 Backfilling (sand / Sub base) 02-Jun-24 11-Jun-24 9 141
GR-CON-Z10-1584 Installation of Paving 12-Jun-24 01-Jul-24 13 141
Landscape Works 11-May-24 23-Oct-24 138 24
GR-CON-Z10-1585 Excavation (Tree Pit ) 11-May-24 15-May-24 5 106
GR-CON-Z10-1586 Aggregate Drainage layer 16-May-24 22-May-24 6 106
GR-CON-Z10-1587 Installation Geotextile 23-May-24 27-May-24 4 106
GR-CON-Z10-1588 Backfilling (Soil max for tree) 28-May-24 03-Jun-24 6 106
GR-CON-Z10-1589 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11656 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-11666 Installation of Succulents 18-Sep-24 22-Sep-24 3 24


GR-CON-Z10-11676 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11686 Installation of Grass 26-Sep-24 30-Sep-24 3 24
GR-CON-Z10-1590 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 24
GR-CON-Z10-1591 Natural Boulders Installation 03-Oct-24 08-Oct-24 4 24
GR-CON-Z10-1592 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Oct-24 23-Oct-24 13 24
Site Furnishing 23-Oct-24 16-Nov-24 20 24
GR-CON-Z10-1601 Garden planter box 23-Oct-24 29-Oct-24 5 24
GR-CON-Z10-1602 Wheel stoppers 29-Oct-24 04-Nov-24 5 24
GR-CON-Z10-1603 Steel Lattice 04-Nov-24 10-Nov-24 5 24
GR-CON-Z10-1604 Handrail 10-Nov-24 16-Nov-24 5 24
Storm Piping Works 09-Nov-24 16-Nov-24 6 24
GR-CON-Z10-1605 Installation of DI grating covers 09-Nov-24 16-Nov-24 6 24
Irrigation Works 05-May-24 09-Jul-24 53 128
GR-CON-Z10-1593 Excavation Pipe Irrigation 05-May-24 09-May-24 5 69
GR-CON-Z10-1594 Sand Bedding 11-May-24 14-May-24 4 69
GR-CON-Z10-1595 HDPE Pipe Installations and fittings and conduit for cable 15-May-24 01-Jun-24 15 69
GR-CON-Z10-1597 Test pressure 02-Jun-24 06-Jun-24 5 69
GR-CON-Z10-1596 Installation of Valves and Accessories 08-Jun-24 11-Jun-24 4 69
GR-CON-Z10-1598 Back filling (sand / Subbase ) 12-Jun-24 18-Jun-24 6 69
GR-CON-Z10-1599 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Jun-24 30-Jun-24 6 128
GR-CON-Z10-1600 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
01-Jul-24
system 09-Jul-24 8 128
Electrical Works 11-May-24 16-Nov-24 158 24
GR-CON-Z10-1606 Excavation And Disposal 11-May-24 15-May-24 5 155
GR-CON-Z10-1607 Sand Bedding 16-May-24 20-May-24 4 155
GR-CON-Z10-1608 laying cables 21-May-24 25-May-24 4 155
GR-CON-Z10-1609 Backfilling (sand / Sub base) 26-May-24 30-May-24 5 155
GR-CON-Z10-1610 Control Panel / Distribution Panel Installation 01-Jun-24 04-Jun-24 4 155
GR-CON-Z10-1611 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Street SS-87 29-Apr-24 16-Nov-24 168 24
Site Preparation 29-Apr-24 22-May-24 21 171
GR-CON-Z10-1612 Demolition (Asphalt.Paving,etc.....) 29-Apr-24 02-May-24 4 65
GR-CON-Z10-1613 Excavation And Disposal 04-May-24 08-May-24 5 65
GR-CON-Z10-1614 Prepretion And Compaction 09-May-24 15-May-24 6 171
GR-CON-Z10-1615 Backfilling 16-May-24 22-May-24 6 171
Curbstone and Paving 09-May-24 06-Jul-24 46 137
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1616 Excavation Curbstone 09-May-24 14-May-24 5 102


GR-CON-Z10-1617 Plain Concrete 15-May-24 21-May-24 6 137
GR-CON-Z10-1618 Installation Curbstone 22-May-24 01-Jun-24 9 137
GR-CON-Z10-1619 Casting Concrete (Mortar haunch) 02-Jun-24 05-Jun-24 4 137
GR-CON-Z10-1620 Backfilling (sand / Sub base) 06-Jun-24 16-Jun-24 9 137
GR-CON-Z10-1621 Installation of Paving 17-Jun-24 06-Jul-24 13 137
Landscape Works 15-May-24 23-Oct-24 134 24
GR-CON-Z10-1622 Excavation (Tree Pit ) 15-May-24 20-May-24 5 102
GR-CON-Z10-1623 Aggregate Drainage layer 21-May-24 27-May-24 6 102
GR-CON-Z10-1624 Installation Geotextile 28-May-24 01-Jun-24 4 102
GR-CON-Z10-1625 Backfilling (Soil max for tree) 02-Jun-24 08-Jun-24 6 102
GR-CON-Z10-1626 Installation of Trees 11-Sep-24 15-Sep-24 3 24
GR-CON-Z10-11696 Installation of Shrubs 15-Sep-24 18-Sep-24 3 24
GR-CON-Z10-11706 Installation of Succulents 18-Sep-24 22-Sep-24 3 24
GR-CON-Z10-11716 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 24
GR-CON-Z10-11726 Installation of Grass 26-Sep-24 30-Sep-24 3 24
GR-CON-Z10-1627 Backfilling (Mulch) 30-Sep-24 03-Oct-24 3 24
GR-CON-Z10-1628 Natural Boulders Installation 03-Oct-24 08-Oct-24 4 24
GR-CON-Z10-1629 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Oct-24 23-Oct-24 13 24
Site Furnishing 23-Oct-24 16-Nov-24 20 24
GR-CON-Z10-1638 Garden planter box 23-Oct-24 29-Oct-24 5 24
GR-CON-Z10-1639 Wheel stoppers 29-Oct-24 04-Nov-24 5 24
GR-CON-Z10-1640 Steel Lattice 04-Nov-24 10-Nov-24 5 24
GR-CON-Z10-1641 Handrail 10-Nov-24 16-Nov-24 5 24
Storm Piping Works 09-Nov-24 16-Nov-24 6 24
GR-CON-Z10-1642 Installation of DI grating covers 09-Nov-24 16-Nov-24 6 24
Irrigation Works 09-May-24 14-Jul-24 53 124
GR-CON-Z10-1630 Excavation Pipe Irrigation 09-May-24 14-May-24 5 65
GR-CON-Z10-1631 Sand Bedding 15-May-24 19-May-24 4 65
GR-CON-Z10-1632 HDPE Pipe Installations and fittings and conduit for cable 20-May-24 05-Jun-24 15 65
GR-CON-Z10-1634 Test pressure 06-Jun-24 11-Jun-24 5 65
GR-CON-Z10-1633 Installation of Valves and Accessories 12-Jun-24 16-Jun-24 4 65
GR-CON-Z10-1635 Back filling (sand / Subbase ) 17-Jun-24 27-Jun-24 6 65
GR-CON-Z10-1636 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Jun-24 04-Jul-24 6 124
GR-CON-Z10-1637 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Jul-24
system 14-Jul-24 8 124
Electrical Works 15-May-24 16-Nov-24 154 24
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z10-1643 Excavation And Disposal 15-May-24 20-May-24 5 151


GR-CON-Z10-1644 Sand Bedding 21-May-24 25-May-24 4 151
GR-CON-Z10-1645 laying cables 26-May-24 29-May-24 4 151
GR-CON-Z10-1646 Backfilling (sand / Sub base) 30-May-24 04-Jun-24 5 151
GR-CON-Z10-1647 Control Panel / Distribution Panel Installation 05-Jun-24 09-Jun-24 4 151
GR-CON-Z10-1648 Road Crossing Ducts 10-Nov-24 16-Nov-24 5 24
Existing Neighborhood Park ENP-01 29-Apr-24 10-Oct-24 137 55
Site Preparation 29-Apr-24 26-May-24 24 168
GR-CON-Z10-1039 Demolition (Asphalt.Paving,etc.....) 29-Apr-24 04-May-24 5 0
GR-CON-Z10-1040 Excavation And Disposal 05-May-24 11-May-24 6 0
GR-CON-Z10-1041 Prepretion And Compaction 12-May-24 16-May-24 5 168
GR-CON-Z10-1042 Backfilling 18-May-24 26-May-24 8 168
Landscape Works 12-May-24 10-Oct-24 126 55
GR-CON-Z10-1043 Excavation (Tree Pit ) 12-May-24 18-May-24 6 130
GR-CON-Z10-1044 Aggregate Drainage layer 19-May-24 27-May-24 8 130
GR-CON-Z10-1045 Installation Geotextile 28-May-24 02-Jun-24 5 130
GR-CON-Z10-1046 Backfilling (Soil max for tree) 03-Jun-24 11-Jun-24 8 130
GR-CON-Z10-1047 Installation of Trees 11-Sep-24 15-Sep-24 3 55
GR-CON-Z10-11448 Installation of Climbers 15-Sep-24 18-Sep-24 3 55
GR-CON-Z10-14116 Installation of Succulents 18-Sep-24 22-Sep-24 3 55
GR-CON-Z10-14126 Installation of Ground Covers 22-Sep-24 26-Sep-24 3 55
GR-CON-Z10-11458 Installation of Shrubs 26-Sep-24 30-Sep-24 3 55
GR-CON-Z10-11468 Installation of Grass 30-Sep-24 03-Oct-24 3 55
GR-CON-Z10-11478 Installation of Lawns 03-Oct-24 07-Oct-24 3 55
GR-CON-Z10-1048 Backfilling (Mulch) 07-Oct-24 10-Oct-24 3 55
Irrigation Works 12-May-24 10-Oct-24 126 55
GR-CON-Z10-1049 Excavation Pipe Irrigation 12-May-24 18-May-24 6 0
GR-CON-Z10-1050 Sand Bedding 19-May-24 21-May-24 3 0
GR-CON-Z10-1051 HDPE Pipe Installations and fittings and conduit for cable 22-May-24 11-Jun-24 18 0
GR-CON-Z10-1053 Test pressure 12-Jun-24 18-Jun-24 6 0
GR-CON-Z10-1052 Installation of Valves and Accessories 24-Jun-24 29-Jun-24 5 0
GR-CON-Z10-1054 Back filling (sand / Subbase ) 30-Jun-24 08-Jul-24 8 0
GR-CON-Z10-1055 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Jul-24 17-Jul-24 8 118
GR-CON-Z10-1056 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
30-Sep-24
system 10-Oct-24 9 55
Zone 14 29-Jul-23 20-Nov-24 396 14
Future Neighborhood Park FNP-04 29-Jul-23 27-Jul-24 297 113
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 29-Jul-23 31-Aug-23 30 381


GR-CON-Z14-1073 Demolition (Asphalt.Paving,etc.....) 29-Jul-23 03-Aug-23 6 1
GR-CON-Z14-1074 Excavation And Disposal 05-Aug-23 13-Aug-23 8 259
GR-CON-Z14-1075 Prepretion And Compaction 14-Aug-23 20-Aug-23 6 381
GR-CON-Z14-1076 Backfilling 21-Aug-23 31-Aug-23 10 381
Curbstone and Paving 14-Aug-23 05-Nov-23 71 326
GR-CON-Z14-1077 Excavation Curbstone 14-Aug-23 22-Aug-23 8 263
GR-CON-Z14-1078 Plain Concrete 23-Aug-23 03-Sep-23 10 326
GR-CON-Z14-1079 Installation Curbstone 04-Sep-23 19-Sep-23 14 326
GR-CON-Z14-1080 Casting Concrete (Mortar haunch) 20-Sep-23 27-Sep-23 6 326
GR-CON-Z14-1081 Backfilling (sand / Sub base) 28-Sep-23 14-Oct-23 14 326
GR-CON-Z14-1082 Installation of Paving 15-Oct-23 05-Nov-23 19 326
Landscape Works 23-Aug-23 27-Jul-24 275 113
GR-CON-Z14-1083 Excavation (Tree Pit ) 23-Aug-23 31-Aug-23 8 263
GR-CON-Z14-1084 Aggregate Drainage layer 02-Sep-23 12-Sep-23 10 305
GR-CON-Z14-1085 Installation Geotextile 13-Sep-23 19-Sep-23 6 305
GR-CON-Z14-1086 Backfilling (Soil max for tree) 20-Sep-23 02-Oct-23 10 305
GR-CON-Z14-1087 Installation of Trees 10-Jan-24 14-Jan-24 3 219
GR-CON-Z14-2586 Installation of Shrubs 14-Jan-24 17-Jan-24 3 219
GR-CON-Z14-2596 Installation of Succulents 17-Jan-24 21-Jan-24 3 219
GR-CON-Z14-2606 Installation of Ground Covers 21-Jan-24 24-Jan-24 3 219
GR-CON-Z14-2616 Installation of Climbers 24-Jan-24 28-Jan-24 3 219
GR-CON-Z14-2626 Installation of Grass 28-Jan-24 31-Jan-24 3 219
GR-CON-Z14-2636 Installation of Lawns 31-Jan-24 04-Feb-24 3 219
GR-CON-Z14-1088 Backfilling (Mulch) 04-Feb-24 08-Feb-24 4 219
GR-CON-Z14-1089 Natural Boulders Installation 08-Feb-24 15-Feb-24 6 219
GR-CON-Z14-1090 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jul-24 27-Jul-24 19 113
MUGA 02-Sep-23 27-Jul-24 267 113
GR-CON-Z14-1091 Excavation And Disposal 02-Sep-23 10-Sep-23 8 263
GR-CON-Z14-1092 Prepretion And Compaction 11-Sep-23 21-Sep-23 10 263
GR-CON-Z14-1093 polyethylene under footings ( fence and gates) 24-Sep-23 02-Oct-23 8 263
GR-CON-Z14-1094 Blinding concrete (flooring) 03-Oct-23 11-Oct-23 8 263
GR-CON-Z14-1095 Concrete Footings ( fence and gates) 12-Oct-23 02-Nov-23 19 263
GR-CON-Z14-1096 Tools Play Installation ( basketball / football ..) 02-Jan-24 29-Jan-24 23 211
GR-CON-Z14-1097 PaintAcrylic Play Surface 29-Jan-24 20-Feb-24 19 211
GR-CON-Z14-1098 Fence (high / low) / gates Installation 30-Jun-24 27-Jul-24 23 113
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 14-Aug-23 27-Jul-24 283 113


GR-CON-Z14-1099 Excavation Pipe Irrigation 14-Aug-23 22-Aug-23 8 259
GR-CON-Z14-1100 Sand Bedding 23-Aug-23 27-Aug-23 4 259
GR-CON-Z14-1101 HDPE Pipe Installations and fittings and conduit for cable 02-Sep-23 30-Sep-23 23 254
GR-CON-Z14-1103 Test pressure 30-Sep-23 09-Oct-23 8 254
GR-CON-Z14-1102 Installation of Valves and Accessories 09-Oct-23 16-Oct-23 6 254
GR-CON-Z14-1104 Back filling (sand / Subbase ) 16-Oct-23 28-Oct-23 10 254
GR-CON-Z14-1105 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-Oct-23 08-Nov-23 10 311
GR-CON-Z14-1106 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jul-24
system 27-Jul-24 12 113
Future Neighborhood Park FNP-11 05-Aug-23 03-Mar-24 180 205
Site Preparation 05-Aug-23 30-Aug-23 23 354
GR-CON-Z14-1039 Demolition (Asphalt.Paving,etc.....) 05-Aug-23 09-Aug-23 5 40
GR-CON-Z14-1040 Excavation And Disposal 10-Aug-23 16-Aug-23 6 271
GR-CON-Z14-1041 Prepretion And Compaction 17-Aug-23 22-Aug-23 5 354
GR-CON-Z14-1042 Backfilling 23-Aug-23 30-Aug-23 7 354
Curbstone and Paving 17-Aug-23 15-Oct-23 50 316
GR-CON-Z14-1043 Excavation Curbstone 17-Aug-23 23-Aug-23 6 276
GR-CON-Z14-1044 Plain Concrete 24-Aug-23 31-Aug-23 7 316
GR-CON-Z14-1045 Installation Curbstone 02-Sep-23 10-Sep-23 8 316
GR-CON-Z14-1046 Casting Concrete (Mortar haunch) 11-Sep-23 16-Sep-23 5 316
GR-CON-Z14-1047 Backfilling (sand / Sub base) 17-Sep-23 28-Sep-23 10 316
GR-CON-Z14-1048 Installation of Paving 30-Sep-23 15-Oct-23 14 316
Landscape Works 24-Aug-23 21-Feb-24 154 205
GR-CON-Z14-1049 Excavation (Tree Pit ) 24-Aug-23 30-Aug-23 6 276
GR-CON-Z14-1050 Aggregate Drainage layer 31-Aug-23 07-Sep-23 7 299
GR-CON-Z14-1051 Installation Geotextile 09-Sep-23 13-Sep-23 5 299
GR-CON-Z14-1052 Backfilling (Soil max for tree) 14-Sep-23 21-Sep-23 7 299
GR-CON-Z14-1053 Installation of Trees 10-Jan-24 13-Jan-24 2 205
GR-CON-Z14-2526 Installation of Shrubs 13-Jan-24 15-Jan-24 2 205
GR-CON-Z14-2536 Installation of Succulents 15-Jan-24 17-Jan-24 2 205
GR-CON-Z14-2546 Installation of Ground Covers 17-Jan-24 20-Jan-24 2 205
GR-CON-Z14-2556 Installation of Climbers 20-Jan-24 22-Jan-24 2 205
GR-CON-Z14-2566 Installation of Grass 22-Jan-24 24-Jan-24 2 205
GR-CON-Z14-2576 Installation of Lawns 24-Jan-24 27-Jan-24 2 205
GR-CON-Z14-1054 Backfilling (Mulch) 27-Jan-24 30-Jan-24 3 205
GR-CON-Z14-1055 Natural Boulders Installation 30-Jan-24 05-Feb-24 5 205
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1056 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Feb-24 21-Feb-24 14 205
MUGA 31-Aug-23 27-Feb-24 153 209
GR-CON-Z14-1057 Excavation And Disposal 31-Aug-23 06-Sep-23 6 276
GR-CON-Z14-1058 Prepretion And Compaction 07-Sep-23 14-Sep-23 7 276
GR-CON-Z14-1059 polyethylene under footings ( fence and gates) 16-Sep-23 21-Sep-23 6 276
GR-CON-Z14-1060 Blinding concrete (flooring) 24-Sep-23 30-Sep-23 6 276
GR-CON-Z14-1061 Concrete Footings ( fence and gates) 01-Oct-23 16-Oct-23 14 276
GR-CON-Z14-1062 Tools Play Installation ( basketball / football ..) 02-Jan-24 22-Jan-24 17 209
GR-CON-Z14-1063 PaintAcrylic Play Surface 22-Jan-24 07-Feb-24 14 209
GR-CON-Z14-1064 Fence (high / low) / gates Installation 07-Feb-24 27-Feb-24 17 209
Irrigation Works 17-Aug-23 03-Mar-24 169 205
GR-CON-Z14-1065 Excavation Pipe Irrigation 17-Aug-23 23-Aug-23 6 271
GR-CON-Z14-1066 Sand Bedding 24-Aug-23 27-Aug-23 3 271
GR-CON-Z14-1067 HDPE Pipe Installations and fittings and conduit for cable 02-Sep-23 21-Sep-23 17 266
GR-CON-Z14-1069 Test pressure 21-Sep-23 30-Sep-23 6 266
GR-CON-Z14-1068 Installation of Valves and Accessories 30-Sep-23 05-Oct-23 5 266
GR-CON-Z14-1070 Back filling (sand / Subbase ) 05-Oct-23 14-Oct-23 7 266
GR-CON-Z14-1071 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Oct-23 22-Oct-23 7 310
GR-CON-Z14-1072 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-Feb-24
system 03-Mar-24 9 205
Mosque M-23 10-Aug-23 27-Mar-24 193 206
Site Preparation 10-Aug-23 31-Aug-23 19 359
GR-CON-Z14-1107 Demolition (Asphalt.Paving,etc.....) 10-Aug-23 14-Aug-23 4 40
GR-CON-Z14-1108 Excavation And Disposal 15-Aug-23 20-Aug-23 5 274
GR-CON-Z14-1109 Prepretion And Compaction 21-Aug-23 24-Aug-23 4 359
GR-CON-Z14-1110 Backfilling 26-Aug-23 31-Aug-23 6 359
Curbstone and Paving 02-Sep-23 27-Sep-23 22 359
GR-CON-Z14-1115 Backfilling (sand / Sub base) 02-Sep-23 11-Sep-23 9 359
GR-CON-Z14-1116 Installation of Paving 12-Sep-23 27-Sep-23 13 359
Landscape Works 21-Aug-23 27-Mar-24 184 206
GR-CON-Z14-1117 Excavation (Tree Pit ) 21-Aug-23 26-Aug-23 5 307
GR-CON-Z14-1118 Aggregate Drainage layer 27-Aug-23 02-Sep-23 6 307
GR-CON-Z14-1119 Installation Geotextile 03-Sep-23 07-Sep-23 5 307
GR-CON-Z14-1120 Backfilling (Soil max for tree) 09-Sep-23 13-Sep-23 5 307
GR-CON-Z14-1121 Installation of Trees 10-Jan-24 15-Jan-24 4 206
GR-CON-Z14-4346 Installation of Climbers 15-Jan-24 20-Jan-24 4 206
GR-CON-Z14-4356 Installation of Shrubs 20-Jan-24 24-Jan-24 4 206
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-4366 Installation of Succulents 24-Jan-24 29-Jan-24 4 206


GR-CON-Z14-4376 Installation of Ground Covers 29-Jan-24 03-Feb-24 4 206
GR-CON-Z14-1122 Backfilling (Mulch) 03-Feb-24 20-Feb-24 15 206
GR-CON-Z14-1123 Natural Boulders Installation 20-Feb-24 06-Mar-24 13 206
GR-CON-Z14-1124 Retaining walls . Steps, forming risers, treads and edges with finishes
06-Mar-24 27-Mar-24 15 206
Irrigation Works 21-Aug-23 27-Mar-24 184 206
GR-CON-Z14-1125 Excavation Pipe Irrigation 21-Aug-23 26-Aug-23 5 274
GR-CON-Z14-1126 Sand Bedding 27-Aug-23 29-Aug-23 3 274
GR-CON-Z14-1127 HDPE Pipe Installations and fittings and conduit for cable 02-Sep-23 19-Sep-23 15 271
GR-CON-Z14-1129 Test pressure 19-Sep-23 26-Sep-23 5 271
GR-CON-Z14-1128 Installation of Valves and Accessories 26-Sep-23 01-Oct-23 4 271
GR-CON-Z14-1130 Back filling (sand / Subbase ) 01-Oct-23 08-Oct-23 6 271
GR-CON-Z14-1131 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-Oct-23 15-Oct-23 6 338
GR-CON-Z14-1132 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Mar-24
system 27-Mar-24 6 206
Mosque M-24 15-Aug-23 27-Mar-24 189 206
Site Preparation 15-Aug-23 05-Sep-23 19 355
GR-CON-Z14-1133 Demolition (Asphalt.Paving,etc.....) 15-Aug-23 19-Aug-23 4 40
GR-CON-Z14-1134 Excavation And Disposal 20-Aug-23 24-Aug-23 5 270
GR-CON-Z14-1135 Prepretion And Compaction 26-Aug-23 29-Aug-23 4 355
GR-CON-Z14-1136 Backfilling 30-Aug-23 05-Sep-23 6 355
Curbstone and Paving 06-Sep-23 02-Oct-23 22 355
GR-CON-Z14-1141 Backfilling (sand / Sub base) 06-Sep-23 16-Sep-23 9 355
GR-CON-Z14-1142 Installation of Paving 17-Sep-23 02-Oct-23 13 355
Landscape Works 26-Aug-23 27-Mar-24 180 206
GR-CON-Z14-1143 Excavation (Tree Pit ) 26-Aug-23 30-Aug-23 5 303
GR-CON-Z14-1144 Aggregate Drainage layer 31-Aug-23 06-Sep-23 6 303
GR-CON-Z14-1145 Installation Geotextile 07-Sep-23 12-Sep-23 5 303
GR-CON-Z14-1146 Backfilling (Soil max for tree) 13-Sep-23 18-Sep-23 5 303
GR-CON-Z14-1147 Installation of Trees 10-Jan-24 15-Jan-24 4 206
GR-CON-Z14-4386 Installation of Climbers 15-Jan-24 20-Jan-24 4 206
GR-CON-Z14-4396 Installation of Shrubs 20-Jan-24 24-Jan-24 4 206
GR-CON-Z14-4406 Installation of Succulents 24-Jan-24 29-Jan-24 4 206
GR-CON-Z14-4416 Installation of Ground Covers 29-Jan-24 03-Feb-24 4 206
GR-CON-Z14-1148 Backfilling (Mulch) 03-Feb-24 20-Feb-24 15 206
GR-CON-Z14-1149 Natural Boulders Installation 20-Feb-24 06-Mar-24 13 206
GR-CON-Z14-1150 Retaining walls . Steps, forming risers, treads and edges with finishes
06-Mar-24 27-Mar-24 15 206
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 26-Aug-23 27-Mar-24 180 206


GR-CON-Z14-1151 Excavation Pipe Irrigation 26-Aug-23 30-Aug-23 5 270
GR-CON-Z14-1152 Sand Bedding 31-Aug-23 03-Sep-23 3 270
GR-CON-Z14-1153 HDPE Pipe Installations and fittings and conduit for cable 04-Sep-23 20-Sep-23 15 270
GR-CON-Z14-1155 Test pressure 21-Sep-23 27-Sep-23 5 270
GR-CON-Z14-1154 Installation of Valves and Accessories 28-Sep-23 02-Oct-23 4 270
GR-CON-Z14-1156 Back filling (sand / Subbase ) 03-Oct-23 09-Oct-23 6 270
GR-CON-Z14-1157 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Oct-23 16-Oct-23 6 337
GR-CON-Z14-1158 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Mar-24
system 27-Mar-24 6 206
Mosque M-08 20-Aug-23 27-Mar-24 185 206
Site Preparation 20-Aug-23 10-Sep-23 19 351
GR-CON-Z14-1159 Demolition (Asphalt.Paving,etc.....) 20-Aug-23 23-Aug-23 4 40
GR-CON-Z14-1160 Excavation And Disposal 24-Aug-23 29-Aug-23 5 266
GR-CON-Z14-1161 Prepretion And Compaction 30-Aug-23 03-Sep-23 4 351
GR-CON-Z14-1162 Backfilling 04-Sep-23 10-Sep-23 6 351
Curbstone and Paving 11-Sep-23 07-Oct-23 22 351
GR-CON-Z14-1167 Backfilling (sand / Sub base) 11-Sep-23 20-Sep-23 9 351
GR-CON-Z14-1168 Installation of Paving 21-Sep-23 07-Oct-23 13 351
Landscape Works 30-Aug-23 27-Mar-24 176 206
GR-CON-Z14-1169 Excavation (Tree Pit ) 30-Aug-23 04-Sep-23 5 299
GR-CON-Z14-1170 Aggregate Drainage layer 05-Sep-23 11-Sep-23 6 299
GR-CON-Z14-1171 Installation Geotextile 12-Sep-23 17-Sep-23 5 299
GR-CON-Z14-1172 Backfilling (Soil max for tree) 18-Sep-23 24-Sep-23 5 299
GR-CON-Z14-1173 Installation of Trees 10-Jan-24 15-Jan-24 4 206
GR-CON-Z14-4426 Installation of Climbers 15-Jan-24 20-Jan-24 4 206
GR-CON-Z14-4436 Installation of Shrubs 20-Jan-24 24-Jan-24 4 206
GR-CON-Z14-4446 Installation of Succulents 24-Jan-24 29-Jan-24 4 206
GR-CON-Z14-4456 Installation of Ground Covers 29-Jan-24 03-Feb-24 4 206
GR-CON-Z14-1174 Backfilling (Mulch) 03-Feb-24 20-Feb-24 15 206
GR-CON-Z14-1175 Natural Boulders Installation 20-Feb-24 06-Mar-24 13 206
GR-CON-Z14-1176 Retaining walls . Steps, forming risers, treads and edges with finishes
06-Mar-24 27-Mar-24 15 206
Irrigation Works 30-Aug-23 27-Mar-24 176 206
GR-CON-Z14-1177 Excavation Pipe Irrigation 30-Aug-23 04-Sep-23 5 266
GR-CON-Z14-1178 Sand Bedding 05-Sep-23 07-Sep-23 3 266
GR-CON-Z14-1179 HDPE Pipe Installations and fittings and conduit for cable 09-Sep-23 26-Sep-23 15 266
GR-CON-Z14-1181 Test pressure 27-Sep-23 02-Oct-23 5 266
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1180 Installation of Valves and Accessories 03-Oct-23 07-Oct-23 4 266


GR-CON-Z14-1182 Back filling (sand / Subbase ) 08-Oct-23 14-Oct-23 6 266
GR-CON-Z14-1183 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Oct-23 21-Oct-23 6 333
GR-CON-Z14-1184 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Mar-24
system 27-Mar-24 6 206
Parking P-24 22-Aug-23 12-Feb-24 148 241
Site Preparation 22-Aug-23 28-Aug-23 6 371
GR-CON-Z14-1188 Backfilling 22-Aug-23 28-Aug-23 6 371
GR-CON-Z14-1186 Excavation And Disposal 23-Aug-23 28-Aug-23 5 267
GR-CON-Z14-1185 Demolition (Asphalt.Paving,etc.....) 24-Aug-23 28-Aug-23 4 40
GR-CON-Z14-1187 Prepretion And Compaction 24-Aug-23 28-Aug-23 4 371
Curbstone and Paving 29-Aug-23 22-Oct-23 46 338
GR-CON-Z14-1189 Excavation Curbstone 29-Aug-23 03-Sep-23 5 330
GR-CON-Z14-1190 Plain Concrete 04-Sep-23 10-Sep-23 6 338
GR-CON-Z14-1191 Installation Curbstone 11-Sep-23 20-Sep-23 9 338
GR-CON-Z14-1192 Casting Concrete (Mortar haunch) 21-Sep-23 26-Sep-23 4 338
GR-CON-Z14-1193 Backfilling (sand / Sub base) 27-Sep-23 07-Oct-23 9 338
GR-CON-Z14-1194 Installation of Paving 08-Oct-23 22-Oct-23 13 338
Landscape Works 04-Sep-23 31-Jan-24 127 241
GR-CON-Z14-1195 Excavation (Tree Pit ) 04-Sep-23 09-Sep-23 5 330
GR-CON-Z14-1196 Aggregate Drainage layer 10-Sep-23 16-Sep-23 6 330
GR-CON-Z14-1197 Installation Geotextile 17-Sep-23 20-Sep-23 4 330
GR-CON-Z14-1198 Backfilling (Soil max for tree) 21-Sep-23 28-Sep-23 6 330
GR-CON-Z14-1199 Installation of Trees 10-Jan-24 14-Jan-24 3 241
GR-CON-Z14-8096 Installation of Shrubs 14-Jan-24 17-Jan-24 3 241
GR-CON-Z14-8106 Installation of Ground Covers 17-Jan-24 21-Jan-24 3 241
GR-CON-Z14-8116 Installation of Succulents 21-Jan-24 24-Jan-24 3 241
GR-CON-Z14-8126 Installation of Grass 24-Jan-24 28-Jan-24 3 241
GR-CON-Z14-1200 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 241
Site Furnishing 31-Jan-24 12-Feb-24 10 241
GR-CON-Z14-1211 Tree Grate 31-Jan-24 06-Feb-24 5 241
GR-CON-Z14-1212 Wheel stoppers 06-Feb-24 12-Feb-24 5 241
Irrigation Works 29-Aug-23 12-Feb-24 142 241
GR-CON-Z14-1203 Excavation Pipe Irrigation 29-Aug-23 03-Sep-23 5 267
GR-CON-Z14-1204 Sand Bedding 04-Sep-23 06-Sep-23 3 267
GR-CON-Z14-1205 HDPE Pipe Installations and fittings and conduit for cable 07-Sep-23 25-Sep-23 15 267
GR-CON-Z14-1207 Test pressure 26-Sep-23 01-Oct-23 5 267
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1206 Installation of Valves and Accessories 02-Oct-23 05-Oct-23 4 267


GR-CON-Z14-1208 Back filling (sand / Subbase ) 07-Oct-23 12-Oct-23 6 267
GR-CON-Z14-1209 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Oct-23 19-Oct-23 6 332
GR-CON-Z14-1210 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Feb-24
system 12-Feb-24 8 241
Parking P-05 27-Aug-23 12-Feb-24 144 241
Site Preparation 27-Aug-23 02-Sep-23 6 367
GR-CON-Z14-1300 Backfilling 27-Aug-23 02-Sep-23 6 367
GR-CON-Z14-1298 Excavation And Disposal 28-Aug-23 02-Sep-23 5 263
GR-CON-Z14-1297 Demolition (Asphalt.Paving,etc.....) 29-Aug-23 02-Sep-23 4 40
GR-CON-Z14-1299 Prepretion And Compaction 29-Aug-23 02-Sep-23 4 367
Curbstone and Paving 03-Sep-23 26-Oct-23 46 334
GR-CON-Z14-1301 Excavation Curbstone 03-Sep-23 07-Sep-23 5 326
GR-CON-Z14-1302 Plain Concrete 09-Sep-23 14-Sep-23 6 334
GR-CON-Z14-1303 Installation Curbstone 16-Sep-23 26-Sep-23 9 334
GR-CON-Z14-1304 Casting Concrete (Mortar haunch) 27-Sep-23 01-Oct-23 4 334
GR-CON-Z14-1305 Backfilling (sand / Sub base) 02-Oct-23 11-Oct-23 9 334
GR-CON-Z14-1306 Installation of Paving 12-Oct-23 26-Oct-23 13 334
Landscape Works 09-Sep-23 31-Jan-24 123 241
GR-CON-Z14-1307 Excavation (Tree Pit ) 09-Sep-23 13-Sep-23 5 326
GR-CON-Z14-1308 Aggregate Drainage layer 14-Sep-23 20-Sep-23 6 326
GR-CON-Z14-1309 Installation Geotextile 21-Sep-23 26-Sep-23 4 326
GR-CON-Z14-1310 Backfilling (Soil max for tree) 27-Sep-23 03-Oct-23 6 326
GR-CON-Z14-1311 Installation of Trees 10-Jan-24 14-Jan-24 3 241
GR-CON-Z14-8256 Installation of Shrubs 14-Jan-24 17-Jan-24 3 241
GR-CON-Z14-8266 Installation of Ground Covers 17-Jan-24 21-Jan-24 3 241
GR-CON-Z14-8276 Installation of Succulents 21-Jan-24 24-Jan-24 3 241
GR-CON-Z14-8286 Installation of Grass 24-Jan-24 28-Jan-24 3 241
GR-CON-Z14-1312 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 241
Site Furnishing 31-Jan-24 12-Feb-24 10 241
GR-CON-Z14-1323 Tree Grate 31-Jan-24 06-Feb-24 5 241
GR-CON-Z14-1324 Wheel stoppers 06-Feb-24 12-Feb-24 5 241
Irrigation Works 03-Sep-23 12-Feb-24 138 241
GR-CON-Z14-1315 Excavation Pipe Irrigation 03-Sep-23 07-Sep-23 5 263
GR-CON-Z14-1316 Sand Bedding 09-Sep-23 11-Sep-23 3 263
GR-CON-Z14-1317 HDPE Pipe Installations and fittings and conduit for cable 12-Sep-23 30-Sep-23 15 263
GR-CON-Z14-1319 Test pressure 01-Oct-23 05-Oct-23 5 263
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1318 Installation of Valves and Accessories 07-Oct-23 10-Oct-23 4 263


GR-CON-Z14-1320 Back filling (sand / Subbase ) 11-Oct-23 17-Oct-23 6 263
GR-CON-Z14-1321 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Oct-23 24-Oct-23 6 328
GR-CON-Z14-1322 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Feb-24
system 12-Feb-24 8 241
Parking P-36 31-Aug-23 12-Feb-24 140 241
Site Preparation 31-Aug-23 06-Sep-23 6 363
GR-CON-Z14-1216 Backfilling 31-Aug-23 06-Sep-23 6 363
GR-CON-Z14-1214 Excavation And Disposal 02-Sep-23 06-Sep-23 5 259
GR-CON-Z14-1213 Demolition (Asphalt.Paving,etc.....) 03-Sep-23 06-Sep-23 4 40
GR-CON-Z14-1215 Prepretion And Compaction 03-Sep-23 06-Sep-23 4 363
Curbstone and Paving 07-Sep-23 31-Oct-23 46 330
GR-CON-Z14-1217 Excavation Curbstone 07-Sep-23 12-Sep-23 5 322
GR-CON-Z14-1218 Plain Concrete 13-Sep-23 19-Sep-23 6 330
GR-CON-Z14-1219 Installation Curbstone 20-Sep-23 01-Oct-23 9 330
GR-CON-Z14-1220 Casting Concrete (Mortar haunch) 02-Oct-23 05-Oct-23 4 330
GR-CON-Z14-1221 Backfilling (sand / Sub base) 07-Oct-23 16-Oct-23 9 330
GR-CON-Z14-1222 Installation of Paving 17-Oct-23 31-Oct-23 13 330
Landscape Works 13-Sep-23 31-Jan-24 119 241
GR-CON-Z14-1223 Excavation (Tree Pit ) 13-Sep-23 18-Sep-23 5 322
GR-CON-Z14-1224 Aggregate Drainage layer 19-Sep-23 26-Sep-23 6 322
GR-CON-Z14-1225 Installation Geotextile 27-Sep-23 01-Oct-23 4 322
GR-CON-Z14-1226 Backfilling (Soil max for tree) 02-Oct-23 08-Oct-23 6 322
GR-CON-Z14-1227 Installation of Trees 10-Jan-24 14-Jan-24 3 241
GR-CON-Z14-8136 Installation of Shrubs 14-Jan-24 17-Jan-24 3 241
GR-CON-Z14-8146 Installation of Ground Covers 17-Jan-24 21-Jan-24 3 241
GR-CON-Z14-8156 Installation of Succulents 21-Jan-24 24-Jan-24 3 241
GR-CON-Z14-8166 Installation of Grass 24-Jan-24 28-Jan-24 3 241
GR-CON-Z14-1228 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 241
Site Furnishing 31-Jan-24 12-Feb-24 10 241
GR-CON-Z14-1239 Tree Grate 31-Jan-24 06-Feb-24 5 241
GR-CON-Z14-1240 Wheel stoppers 06-Feb-24 12-Feb-24 5 241
Irrigation Works 07-Sep-23 12-Feb-24 134 241
GR-CON-Z14-1231 Excavation Pipe Irrigation 07-Sep-23 12-Sep-23 5 259
GR-CON-Z14-1232 Sand Bedding 13-Sep-23 16-Sep-23 3 259
GR-CON-Z14-1233 HDPE Pipe Installations and fittings and conduit for cable 17-Sep-23 04-Oct-23 15 259
GR-CON-Z14-1235 Test pressure 05-Oct-23 10-Oct-23 5 259
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1234 Installation of Valves and Accessories 11-Oct-23 15-Oct-23 4 259


GR-CON-Z14-1236 Back filling (sand / Subbase ) 16-Oct-23 22-Oct-23 6 259
GR-CON-Z14-1237 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-Oct-23 29-Oct-23 6 324
GR-CON-Z14-1238 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Feb-24
system 12-Feb-24 8 241
Parking P-42 05-Sep-23 12-Feb-24 136 241
Site Preparation 05-Sep-23 11-Sep-23 6 359
GR-CON-Z14-1244 Backfilling 05-Sep-23 11-Sep-23 6 359
GR-CON-Z14-1242 Excavation And Disposal 06-Sep-23 11-Sep-23 5 255
GR-CON-Z14-1241 Demolition (Asphalt.Paving,etc.....) 07-Sep-23 11-Sep-23 4 40
GR-CON-Z14-1243 Prepretion And Compaction 07-Sep-23 11-Sep-23 4 359
Curbstone and Paving 12-Sep-23 05-Nov-23 46 326
GR-CON-Z14-1245 Excavation Curbstone 12-Sep-23 17-Sep-23 5 318
GR-CON-Z14-1246 Plain Concrete 18-Sep-23 25-Sep-23 6 326
GR-CON-Z14-1247 Installation Curbstone 26-Sep-23 05-Oct-23 9 326
GR-CON-Z14-1248 Casting Concrete (Mortar haunch) 07-Oct-23 10-Oct-23 4 326
GR-CON-Z14-1249 Backfilling (sand / Sub base) 11-Oct-23 21-Oct-23 9 326
GR-CON-Z14-1250 Installation of Paving 22-Oct-23 05-Nov-23 13 326
Landscape Works 18-Sep-23 31-Jan-24 115 241
GR-CON-Z14-1251 Excavation (Tree Pit ) 18-Sep-23 24-Sep-23 5 318
GR-CON-Z14-1252 Aggregate Drainage layer 25-Sep-23 01-Oct-23 6 318
GR-CON-Z14-1253 Installation Geotextile 02-Oct-23 05-Oct-23 4 318
GR-CON-Z14-1254 Backfilling (Soil max for tree) 07-Oct-23 12-Oct-23 6 318
GR-CON-Z14-1255 Installation of Trees 10-Jan-24 14-Jan-24 3 241
GR-CON-Z14-8176 Installation of Shrubs 14-Jan-24 17-Jan-24 3 241
GR-CON-Z14-8186 Installation of Ground Covers 17-Jan-24 21-Jan-24 3 241
GR-CON-Z14-8196 Installation of Succulents 21-Jan-24 24-Jan-24 3 241
GR-CON-Z14-8206 Installation of Grass 24-Jan-24 28-Jan-24 3 241
GR-CON-Z14-1256 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 241
Site Furnishing 31-Jan-24 12-Feb-24 10 241
GR-CON-Z14-1267 Tree Grate 31-Jan-24 06-Feb-24 5 241
GR-CON-Z14-1268 Wheel stoppers 06-Feb-24 12-Feb-24 5 241
Irrigation Works 12-Sep-23 12-Feb-24 130 241
GR-CON-Z14-1259 Excavation Pipe Irrigation 12-Sep-23 17-Sep-23 5 255
GR-CON-Z14-1260 Sand Bedding 18-Sep-23 20-Sep-23 3 255
GR-CON-Z14-1261 HDPE Pipe Installations and fittings and conduit for cable 21-Sep-23 09-Oct-23 15 255
GR-CON-Z14-1263 Test pressure 10-Oct-23 15-Oct-23 5 255
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1262 Installation of Valves and Accessories 16-Oct-23 19-Oct-23 4 255


GR-CON-Z14-1264 Back filling (sand / Subbase ) 21-Oct-23 26-Oct-23 6 255
GR-CON-Z14-1265 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-Oct-23 02-Nov-23 6 320
GR-CON-Z14-1266 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Feb-24
system 12-Feb-24 8 241
Parking P-43 10-Sep-23 12-Feb-24 132 241
Site Preparation 10-Sep-23 16-Sep-23 6 355
GR-CON-Z14-1272 Backfilling 10-Sep-23 16-Sep-23 6 355
GR-CON-Z14-1270 Excavation And Disposal 11-Sep-23 16-Sep-23 5 251
GR-CON-Z14-1269 Demolition (Asphalt.Paving,etc.....) 12-Sep-23 16-Sep-23 4 40
GR-CON-Z14-1271 Prepretion And Compaction 12-Sep-23 16-Sep-23 4 355
Curbstone and Paving 17-Sep-23 09-Nov-23 46 322
GR-CON-Z14-1273 Excavation Curbstone 17-Sep-23 21-Sep-23 5 314
GR-CON-Z14-1274 Plain Concrete 24-Sep-23 30-Sep-23 6 322
GR-CON-Z14-1275 Installation Curbstone 01-Oct-23 10-Oct-23 9 322
GR-CON-Z14-1276 Casting Concrete (Mortar haunch) 11-Oct-23 15-Oct-23 4 322
GR-CON-Z14-1277 Backfilling (sand / Sub base) 16-Oct-23 25-Oct-23 9 322
GR-CON-Z14-1278 Installation of Paving 26-Oct-23 09-Nov-23 13 322
Landscape Works 24-Sep-23 31-Jan-24 111 241
GR-CON-Z14-1279 Excavation (Tree Pit ) 24-Sep-23 28-Sep-23 5 314
GR-CON-Z14-1280 Aggregate Drainage layer 30-Sep-23 05-Oct-23 6 314
GR-CON-Z14-1281 Installation Geotextile 07-Oct-23 10-Oct-23 4 314
GR-CON-Z14-1282 Backfilling (Soil max for tree) 11-Oct-23 17-Oct-23 6 314
GR-CON-Z14-1283 Installation of Trees 10-Jan-24 14-Jan-24 3 241
GR-CON-Z14-8216 Installation of Shrubs 14-Jan-24 17-Jan-24 3 241
GR-CON-Z14-8226 Installation of Ground Covers 17-Jan-24 21-Jan-24 3 241
GR-CON-Z14-8236 Installation of Succulents 21-Jan-24 24-Jan-24 3 241
GR-CON-Z14-8246 Installation of Grass 24-Jan-24 28-Jan-24 3 241
GR-CON-Z14-1284 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 241
Site Furnishing 31-Jan-24 12-Feb-24 10 241
GR-CON-Z14-1295 Tree Grate 31-Jan-24 06-Feb-24 5 241
GR-CON-Z14-1296 Wheel stoppers 06-Feb-24 12-Feb-24 5 241
Irrigation Works 17-Sep-23 12-Feb-24 126 241
GR-CON-Z14-1287 Excavation Pipe Irrigation 17-Sep-23 21-Sep-23 5 251
GR-CON-Z14-1288 Sand Bedding 24-Sep-23 26-Sep-23 3 251
GR-CON-Z14-1289 HDPE Pipe Installations and fittings and conduit for cable 27-Sep-23 14-Oct-23 15 251
GR-CON-Z14-1291 Test pressure 15-Oct-23 19-Oct-23 5 251
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1290 Installation of Valves and Accessories 21-Oct-23 24-Oct-23 4 251


GR-CON-Z14-1292 Back filling (sand / Subbase ) 25-Oct-23 31-Oct-23 6 251
GR-CON-Z14-1293 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Nov-23 07-Nov-23 6 316
GR-CON-Z14-1294 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Feb-24
system 12-Feb-24 8 241
Street SS-19.1 17-Sep-23 23-Apr-24 177 190
Site Preparation 17-Sep-23 24-Oct-23 32 336
GR-CON-Z14-1353 Demolition (Asphalt.Paving,etc.....) 17-Sep-23 24-Sep-23 6 40
GR-CON-Z14-1354 Excavation And Disposal 25-Sep-23 03-Oct-23 8 215
GR-CON-Z14-1355 Prepretion And Compaction 04-Oct-23 14-Oct-23 9 336
GR-CON-Z14-1356 Backfilling 15-Oct-23 24-Oct-23 9 336
Curbstone and Paving 04-Oct-23 25-Dec-23 71 283
GR-CON-Z14-1357 Excavation Curbstone 04-Oct-23 12-Oct-23 8 235
GR-CON-Z14-1358 Plain Concrete 14-Oct-23 23-Oct-23 9 283
GR-CON-Z14-1359 Installation Curbstone 24-Oct-23 08-Nov-23 14 283
GR-CON-Z14-1360 Casting Concrete (Mortar haunch) 09-Nov-23 15-Nov-23 6 283
GR-CON-Z14-1361 Backfilling (sand / Sub base) 16-Nov-23 02-Dec-23 14 283
GR-CON-Z14-1362 Installation of Paving 03-Dec-23 25-Dec-23 20 283
Landscape Works 14-Oct-23 05-Mar-24 123 190
GR-CON-Z14-1363 Excavation (Tree Pit ) 14-Oct-23 22-Oct-23 8 235
GR-CON-Z14-1364 Aggregate Drainage layer 23-Oct-23 01-Nov-23 9 235
GR-CON-Z14-1365 Installation Geotextile 02-Nov-23 08-Nov-23 6 235
GR-CON-Z14-1366 Backfilling (Soil max for tree) 09-Nov-23 19-Nov-23 9 235
GR-CON-Z14-1367 Installation of Trees 10-Jan-24 15-Jan-24 4 190
GR-CON-Z14-12296 Installation of Shrubs 15-Jan-24 18-Jan-24 3 190
GR-CON-Z14-12306 Installation of Succulents 18-Jan-24 22-Jan-24 3 190
GR-CON-Z14-12316 Installation of Ground Covers 22-Jan-24 25-Jan-24 3 190
GR-CON-Z14-12326 Installation of Grass 25-Jan-24 29-Jan-24 3 190
GR-CON-Z14-1368 Backfilling (Mulch) 29-Jan-24 04-Feb-24 5 190
GR-CON-Z14-1369 Natural Boulders Installation 04-Feb-24 11-Feb-24 6 190
GR-CON-Z14-1370 Retaining walls . Steps, forming risers, treads and edges with finishes
11-Feb-24 05-Mar-24 20 190
Site Furnishing 05-Mar-24 23-Apr-24 32 190
GR-CON-Z14-1379 Garden planter box 05-Mar-24 14-Mar-24 8 190
GR-CON-Z14-1380 Wheel stoppers 14-Mar-24 27-Mar-24 8 190
GR-CON-Z14-1381 Steel Lattice 27-Mar-24 08-Apr-24 8 190
GR-CON-Z14-1382 Handrail 09-Apr-24 23-Apr-24 8 190
Storm Piping Works 07-Apr-24 23-Apr-24 9 190
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1383 Installation of DI grating covers 07-Apr-24 23-Apr-24 9 190


Irrigation Works 04-Oct-23 06-Jan-24 81 264
GR-CON-Z14-1371 Excavation Pipe Irrigation 04-Oct-23 12-Oct-23 8 215
GR-CON-Z14-1372 Sand Bedding 14-Oct-23 19-Oct-23 6 215
GR-CON-Z14-1373 HDPE Pipe Installations and fittings and conduit for cable 21-Oct-23 15-Nov-23 23 215
GR-CON-Z14-1375 Test pressure 16-Nov-23 25-Nov-23 8 215
GR-CON-Z14-1374 Installation of Valves and Accessories 26-Nov-23 02-Dec-23 6 215
GR-CON-Z14-1376 Back filling (sand / Subbase ) 03-Dec-23 12-Dec-23 9 215
GR-CON-Z14-1377 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Dec-23 23-Dec-23 9 264
GR-CON-Z14-1378 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Dec-23
system 06-Jan-24 12 264
Electrical Works 14-Oct-23 23-Apr-24 155 190
GR-CON-Z14-1384 Excavation And Disposal 14-Oct-23 22-Oct-23 8 304
GR-CON-Z14-1385 Sand Bedding 23-Oct-23 29-Oct-23 6 304
GR-CON-Z14-1386 laying cables 30-Oct-23 05-Nov-23 6 304
GR-CON-Z14-1387 Backfilling (sand / Sub base) 06-Nov-23 14-Nov-23 8 304
GR-CON-Z14-1388 Control Panel / Distribution Panel Installation 15-Nov-23 21-Nov-23 6 304
GR-CON-Z14-1389 Road Crossing Ducts 09-Apr-24 23-Apr-24 8 190
Street SS-32 25-Sep-23 14-Mar-24 147 214
Site Preparation 25-Sep-23 18-Oct-23 21 341
GR-CON-Z14-1390 Demolition (Asphalt.Paving,etc.....) 25-Sep-23 28-Sep-23 4 40
GR-CON-Z14-1391 Excavation And Disposal 30-Sep-23 04-Oct-23 5 235
GR-CON-Z14-1392 Prepretion And Compaction 05-Oct-23 11-Oct-23 6 341
GR-CON-Z14-1393 Backfilling 12-Oct-23 18-Oct-23 6 341
Curbstone and Paving 05-Oct-23 27-Nov-23 46 307
GR-CON-Z14-1394 Excavation Curbstone 05-Oct-23 10-Oct-23 5 272
GR-CON-Z14-1395 Plain Concrete 11-Oct-23 17-Oct-23 6 307
GR-CON-Z14-1396 Installation Curbstone 18-Oct-23 28-Oct-23 9 307
GR-CON-Z14-1397 Casting Concrete (Mortar haunch) 29-Oct-23 01-Nov-23 4 307
GR-CON-Z14-1398 Backfilling (sand / Sub base) 02-Nov-23 12-Nov-23 9 307
GR-CON-Z14-1399 Installation of Paving 13-Nov-23 27-Nov-23 13 307
Landscape Works 11-Oct-23 20-Feb-24 113 214
GR-CON-Z14-1400 Excavation (Tree Pit ) 11-Oct-23 16-Oct-23 5 272
GR-CON-Z14-1401 Aggregate Drainage layer 17-Oct-23 23-Oct-23 6 272
GR-CON-Z14-1402 Installation Geotextile 24-Oct-23 28-Oct-23 4 272
GR-CON-Z14-1403 Backfilling (Soil max for tree) 29-Oct-23 04-Nov-23 6 272
GR-CON-Z14-1404 Installation of Trees 10-Jan-24 14-Jan-24 3 214
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-12336 Installation of Shrubs 14-Jan-24 17-Jan-24 3 214


GR-CON-Z14-12346 Installation of Succulents 17-Jan-24 21-Jan-24 3 214
GR-CON-Z14-12356 Installation of Ground Covers 21-Jan-24 24-Jan-24 3 214
GR-CON-Z14-12366 Installation of Grass 24-Jan-24 28-Jan-24 3 214
GR-CON-Z14-1405 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 214
GR-CON-Z14-1406 Natural Boulders Installation 31-Jan-24 05-Feb-24 4 214
GR-CON-Z14-1407 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Feb-24 20-Feb-24 13 214
Site Furnishing 20-Feb-24 14-Mar-24 20 214
GR-CON-Z14-1416 Garden planter box 20-Feb-24 26-Feb-24 5 214
GR-CON-Z14-1417 Wheel stoppers 26-Feb-24 03-Mar-24 5 214
GR-CON-Z14-1418 Steel Lattice 03-Mar-24 09-Mar-24 5 214
GR-CON-Z14-1419 Handrail 09-Mar-24 14-Mar-24 5 214
Storm Piping Works 07-Mar-24 14-Mar-24 6 214
GR-CON-Z14-1420 Installation of DI grating covers 07-Mar-24 14-Mar-24 6 214
Irrigation Works 05-Oct-23 05-Dec-23 53 294
GR-CON-Z14-1408 Excavation Pipe Irrigation 05-Oct-23 10-Oct-23 5 235
GR-CON-Z14-1409 Sand Bedding 11-Oct-23 15-Oct-23 4 235
GR-CON-Z14-1410 HDPE Pipe Installations and fittings and conduit for cable 16-Oct-23 01-Nov-23 15 235
GR-CON-Z14-1412 Test pressure 02-Nov-23 07-Nov-23 5 235
GR-CON-Z14-1411 Installation of Valves and Accessories 08-Nov-23 12-Nov-23 4 235
GR-CON-Z14-1413 Back filling (sand / Subbase ) 13-Nov-23 19-Nov-23 6 235
GR-CON-Z14-1414 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Nov-23 26-Nov-23 6 294
GR-CON-Z14-1415 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
27-Nov-23
system 05-Dec-23 8 294
Electrical Works 11-Oct-23 14-Mar-24 133 214
GR-CON-Z14-1421 Excavation And Disposal 11-Oct-23 16-Oct-23 5 321
GR-CON-Z14-1422 Sand Bedding 17-Oct-23 21-Oct-23 4 321
GR-CON-Z14-1423 laying cables 22-Oct-23 25-Oct-23 4 321
GR-CON-Z14-1424 Backfilling (sand / Sub base) 26-Oct-23 31-Oct-23 5 321
GR-CON-Z14-1425 Control Panel / Distribution Panel Installation 01-Nov-23 05-Nov-23 4 321
GR-CON-Z14-1426 Road Crossing Ducts 09-Mar-24 14-Mar-24 5 214
Street SS-33 30-Sep-23 14-Mar-24 143 214
Site Preparation 30-Sep-23 23-Oct-23 21 337
GR-CON-Z14-1427 Demolition (Asphalt.Paving,etc.....) 30-Sep-23 03-Oct-23 4 40
GR-CON-Z14-1428 Excavation And Disposal 04-Oct-23 09-Oct-23 5 231
GR-CON-Z14-1429 Prepretion And Compaction 10-Oct-23 16-Oct-23 6 337
GR-CON-Z14-1430 Backfilling 17-Oct-23 23-Oct-23 6 337
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 10-Oct-23 02-Dec-23 46 303


GR-CON-Z14-1431 Excavation Curbstone 10-Oct-23 15-Oct-23 5 268
GR-CON-Z14-1432 Plain Concrete 16-Oct-23 22-Oct-23 6 303
GR-CON-Z14-1433 Installation Curbstone 23-Oct-23 01-Nov-23 9 303
GR-CON-Z14-1434 Casting Concrete (Mortar haunch) 02-Nov-23 06-Nov-23 4 303
GR-CON-Z14-1435 Backfilling (sand / Sub base) 07-Nov-23 16-Nov-23 9 303
GR-CON-Z14-1436 Installation of Paving 18-Nov-23 02-Dec-23 13 303
Landscape Works 16-Oct-23 20-Feb-24 109 214
GR-CON-Z14-1437 Excavation (Tree Pit ) 16-Oct-23 21-Oct-23 5 268
GR-CON-Z14-1438 Aggregate Drainage layer 22-Oct-23 28-Oct-23 6 268
GR-CON-Z14-1439 Installation Geotextile 29-Oct-23 01-Nov-23 4 268
GR-CON-Z14-1440 Backfilling (Soil max for tree) 02-Nov-23 08-Nov-23 6 268
GR-CON-Z14-1441 Installation of Trees 10-Jan-24 14-Jan-24 3 214
GR-CON-Z14-12376 Installation of Shrubs 14-Jan-24 17-Jan-24 3 214
GR-CON-Z14-12386 Installation of Succulents 17-Jan-24 21-Jan-24 3 214
GR-CON-Z14-12396 Installation of Ground Covers 21-Jan-24 24-Jan-24 3 214
GR-CON-Z14-12406 Installation of Grass 24-Jan-24 28-Jan-24 3 214
GR-CON-Z14-1442 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 214
GR-CON-Z14-1443 Natural Boulders Installation 31-Jan-24 05-Feb-24 4 214
GR-CON-Z14-1444 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Feb-24 20-Feb-24 13 214
Site Furnishing 20-Feb-24 14-Mar-24 20 214
GR-CON-Z14-1453 Garden planter box 20-Feb-24 26-Feb-24 5 214
GR-CON-Z14-1454 Wheel stoppers 26-Feb-24 03-Mar-24 5 214
GR-CON-Z14-1455 Steel Lattice 03-Mar-24 09-Mar-24 5 214
GR-CON-Z14-1456 Handrail 09-Mar-24 14-Mar-24 5 214
Storm Piping Works 07-Mar-24 14-Mar-24 6 214
GR-CON-Z14-1457 Installation of DI grating covers 07-Mar-24 14-Mar-24 6 214
Irrigation Works 10-Oct-23 10-Dec-23 53 290
GR-CON-Z14-1445 Excavation Pipe Irrigation 10-Oct-23 15-Oct-23 5 231
GR-CON-Z14-1446 Sand Bedding 16-Oct-23 19-Oct-23 4 231
GR-CON-Z14-1447 HDPE Pipe Installations and fittings and conduit for cable 21-Oct-23 06-Nov-23 15 231
GR-CON-Z14-1449 Test pressure 07-Nov-23 12-Nov-23 5 231
GR-CON-Z14-1448 Installation of Valves and Accessories 13-Nov-23 16-Nov-23 4 231
GR-CON-Z14-1450 Back filling (sand / Subbase ) 18-Nov-23 23-Nov-23 6 231
GR-CON-Z14-1451 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-Nov-23 30-Nov-23 6 290
GR-CON-Z14-1452 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Dec-23
system 10-Dec-23 8 290
Activity ID Activity Name Start Finish Original Total Float
Duration

Electrical Works 16-Oct-23 14-Mar-24 129 214


GR-CON-Z14-1458 Excavation And Disposal 16-Oct-23 21-Oct-23 5 317
GR-CON-Z14-1459 Sand Bedding 22-Oct-23 25-Oct-23 4 317
GR-CON-Z14-1460 laying cables 26-Oct-23 30-Oct-23 4 317
GR-CON-Z14-1461 Backfilling (sand / Sub base) 31-Oct-23 05-Nov-23 5 317
GR-CON-Z14-1462 Control Panel / Distribution Panel Installation 06-Nov-23 09-Nov-23 4 317
GR-CON-Z14-1463 Road Crossing Ducts 09-Mar-24 14-Mar-24 5 214
Street SS-61 04-Oct-23 14-Mar-24 139 214
Site Preparation 04-Oct-23 28-Oct-23 21 333
GR-CON-Z14-1464 Demolition (Asphalt.Paving,etc.....) 04-Oct-23 08-Oct-23 4 40
GR-CON-Z14-1465 Excavation And Disposal 09-Oct-23 14-Oct-23 5 227
GR-CON-Z14-1466 Prepretion And Compaction 15-Oct-23 21-Oct-23 6 333
GR-CON-Z14-1467 Backfilling 22-Oct-23 28-Oct-23 6 333
Curbstone and Paving 15-Oct-23 06-Dec-23 46 299
GR-CON-Z14-1468 Excavation Curbstone 15-Oct-23 19-Oct-23 5 264
GR-CON-Z14-1469 Plain Concrete 21-Oct-23 26-Oct-23 6 299
GR-CON-Z14-1470 Installation Curbstone 28-Oct-23 06-Nov-23 9 299
GR-CON-Z14-1471 Casting Concrete (Mortar haunch) 07-Nov-23 11-Nov-23 4 299
GR-CON-Z14-1472 Backfilling (sand / Sub base) 12-Nov-23 21-Nov-23 9 299
GR-CON-Z14-1473 Installation of Paving 22-Nov-23 06-Dec-23 13 299
Landscape Works 21-Oct-23 20-Feb-24 105 214
GR-CON-Z14-1474 Excavation (Tree Pit ) 21-Oct-23 25-Oct-23 5 264
GR-CON-Z14-1475 Aggregate Drainage layer 26-Oct-23 01-Nov-23 6 264
GR-CON-Z14-1476 Installation Geotextile 02-Nov-23 06-Nov-23 4 264
GR-CON-Z14-1477 Backfilling (Soil max for tree) 07-Nov-23 13-Nov-23 6 264
GR-CON-Z14-1478 Installation of Trees 10-Jan-24 14-Jan-24 3 214
GR-CON-Z14-12416 Installation of Shrubs 14-Jan-24 17-Jan-24 3 214
GR-CON-Z14-12426 Installation of Succulents 17-Jan-24 21-Jan-24 3 214
GR-CON-Z14-12436 Installation of Ground Covers 21-Jan-24 24-Jan-24 3 214
GR-CON-Z14-12446 Installation of Grass 24-Jan-24 28-Jan-24 3 214
GR-CON-Z14-1479 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 214
GR-CON-Z14-1480 Natural Boulders Installation 31-Jan-24 05-Feb-24 4 214
GR-CON-Z14-1481 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Feb-24 20-Feb-24 13 214
Site Furnishing 20-Feb-24 14-Mar-24 20 214
GR-CON-Z14-1490 Garden planter box 20-Feb-24 26-Feb-24 5 214
GR-CON-Z14-1491 Wheel stoppers 26-Feb-24 03-Mar-24 5 214
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1492 Steel Lattice 03-Mar-24 09-Mar-24 5 214


GR-CON-Z14-1493 Handrail 09-Mar-24 14-Mar-24 5 214
Storm Piping Works 07-Mar-24 14-Mar-24 6 214
GR-CON-Z14-1494 Installation of DI grating covers 07-Mar-24 14-Mar-24 6 214
Irrigation Works 15-Oct-23 14-Dec-23 53 286
GR-CON-Z14-1482 Excavation Pipe Irrigation 15-Oct-23 19-Oct-23 5 227
GR-CON-Z14-1483 Sand Bedding 21-Oct-23 24-Oct-23 4 227
GR-CON-Z14-1484 HDPE Pipe Installations and fittings and conduit for cable 25-Oct-23 11-Nov-23 15 227
GR-CON-Z14-1486 Test pressure 12-Nov-23 16-Nov-23 5 227
GR-CON-Z14-1485 Installation of Valves and Accessories 18-Nov-23 21-Nov-23 4 227
GR-CON-Z14-1487 Back filling (sand / Subbase ) 22-Nov-23 28-Nov-23 6 227
GR-CON-Z14-1488 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Nov-23 05-Dec-23 6 286
GR-CON-Z14-1489 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Dec-23
system 14-Dec-23 8 286
Electrical Works 21-Oct-23 14-Mar-24 125 214
GR-CON-Z14-1495 Excavation And Disposal 21-Oct-23 25-Oct-23 5 313
GR-CON-Z14-1496 Sand Bedding 26-Oct-23 30-Oct-23 4 313
GR-CON-Z14-1497 laying cables 31-Oct-23 04-Nov-23 4 313
GR-CON-Z14-1498 Backfilling (sand / Sub base) 05-Nov-23 09-Nov-23 5 313
GR-CON-Z14-1499 Control Panel / Distribution Panel Installation 11-Nov-23 14-Nov-23 4 313
GR-CON-Z14-1500 Road Crossing Ducts 09-Mar-24 14-Mar-24 5 214
Street SS-62 09-Oct-23 14-Mar-24 135 214
Site Preparation 09-Oct-23 01-Nov-23 21 329
GR-CON-Z14-1501 Demolition (Asphalt.Paving,etc.....) 09-Oct-23 12-Oct-23 4 40
GR-CON-Z14-1502 Excavation And Disposal 14-Oct-23 18-Oct-23 5 223
GR-CON-Z14-1503 Prepretion And Compaction 19-Oct-23 25-Oct-23 6 329
GR-CON-Z14-1504 Backfilling 26-Oct-23 01-Nov-23 6 329
Curbstone and Paving 19-Oct-23 11-Dec-23 46 295
GR-CON-Z14-1505 Excavation Curbstone 19-Oct-23 24-Oct-23 5 260
GR-CON-Z14-1506 Plain Concrete 25-Oct-23 31-Oct-23 6 295
GR-CON-Z14-1507 Installation Curbstone 01-Nov-23 11-Nov-23 9 295
GR-CON-Z14-1508 Casting Concrete (Mortar haunch) 12-Nov-23 15-Nov-23 4 295
GR-CON-Z14-1509 Backfilling (sand / Sub base) 16-Nov-23 26-Nov-23 9 295
GR-CON-Z14-1510 Installation of Paving 27-Nov-23 11-Dec-23 13 295
Landscape Works 25-Oct-23 20-Feb-24 101 214
GR-CON-Z14-1511 Excavation (Tree Pit ) 25-Oct-23 30-Oct-23 5 260
GR-CON-Z14-1512 Aggregate Drainage layer 31-Oct-23 06-Nov-23 6 260
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1513 Installation Geotextile 07-Nov-23 11-Nov-23 4 260


GR-CON-Z14-1514 Backfilling (Soil max for tree) 12-Nov-23 18-Nov-23 6 260
GR-CON-Z14-1515 Installation of Trees 10-Jan-24 14-Jan-24 3 214
GR-CON-Z14-12456 Installation of Shrubs 14-Jan-24 17-Jan-24 3 214
GR-CON-Z14-12466 Installation of Succulents 17-Jan-24 21-Jan-24 3 214
GR-CON-Z14-12476 Installation of Ground Covers 21-Jan-24 24-Jan-24 3 214
GR-CON-Z14-12486 Installation of Grass 24-Jan-24 28-Jan-24 3 214
GR-CON-Z14-1516 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 214
GR-CON-Z14-1517 Natural Boulders Installation 31-Jan-24 05-Feb-24 4 214
GR-CON-Z14-1518 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Feb-24 20-Feb-24 13 214
Site Furnishing 20-Feb-24 14-Mar-24 20 214
GR-CON-Z14-1527 Garden planter box 20-Feb-24 26-Feb-24 5 214
GR-CON-Z14-1528 Wheel stoppers 26-Feb-24 03-Mar-24 5 214
GR-CON-Z14-1529 Steel Lattice 03-Mar-24 09-Mar-24 5 214
GR-CON-Z14-1530 Handrail 09-Mar-24 14-Mar-24 5 214
Storm Piping Works 07-Mar-24 14-Mar-24 6 214
GR-CON-Z14-1531 Installation of DI grating covers 07-Mar-24 14-Mar-24 6 214
Irrigation Works 19-Oct-23 19-Dec-23 53 282
GR-CON-Z14-1519 Excavation Pipe Irrigation 19-Oct-23 24-Oct-23 5 223
GR-CON-Z14-1520 Sand Bedding 25-Oct-23 29-Oct-23 4 223
GR-CON-Z14-1521 HDPE Pipe Installations and fittings and conduit for cable 30-Oct-23 15-Nov-23 15 223
GR-CON-Z14-1523 Test pressure 16-Nov-23 21-Nov-23 5 223
GR-CON-Z14-1522 Installation of Valves and Accessories 22-Nov-23 26-Nov-23 4 223
GR-CON-Z14-1524 Back filling (sand / Subbase ) 27-Nov-23 03-Dec-23 6 223
GR-CON-Z14-1525 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Dec-23 10-Dec-23 6 282
GR-CON-Z14-1526 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
11-Dec-23
system 19-Dec-23 8 282
Electrical Works 25-Oct-23 14-Mar-24 121 214
GR-CON-Z14-1532 Excavation And Disposal 25-Oct-23 30-Oct-23 5 309
GR-CON-Z14-1533 Sand Bedding 31-Oct-23 04-Nov-23 4 309
GR-CON-Z14-1534 laying cables 05-Nov-23 08-Nov-23 4 309
GR-CON-Z14-1535 Backfilling (sand / Sub base) 09-Nov-23 14-Nov-23 5 309
GR-CON-Z14-1536 Control Panel / Distribution Panel Installation 15-Nov-23 19-Nov-23 4 309
GR-CON-Z14-1537 Road Crossing Ducts 09-Mar-24 14-Mar-24 5 214
Street SS-89 14-Oct-23 14-Mar-24 131 214
Site Preparation 14-Oct-23 06-Nov-23 21 325
GR-CON-Z14-1538 Demolition (Asphalt.Paving,etc.....) 14-Oct-23 17-Oct-23 4 40
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1539 Excavation And Disposal 18-Oct-23 23-Oct-23 5 219


GR-CON-Z14-1540 Prepretion And Compaction 24-Oct-23 30-Oct-23 6 325
GR-CON-Z14-1541 Backfilling 31-Oct-23 06-Nov-23 6 325
Curbstone and Paving 24-Oct-23 16-Dec-23 46 291
GR-CON-Z14-1542 Excavation Curbstone 24-Oct-23 29-Oct-23 5 256
GR-CON-Z14-1543 Plain Concrete 30-Oct-23 05-Nov-23 6 291
GR-CON-Z14-1544 Installation Curbstone 06-Nov-23 15-Nov-23 9 291
GR-CON-Z14-1545 Casting Concrete (Mortar haunch) 16-Nov-23 20-Nov-23 4 291
GR-CON-Z14-1546 Backfilling (sand / Sub base) 21-Nov-23 30-Nov-23 9 291
GR-CON-Z14-1547 Installation of Paving 02-Dec-23 16-Dec-23 13 291
Landscape Works 30-Oct-23 20-Feb-24 97 214
GR-CON-Z14-1548 Excavation (Tree Pit ) 30-Oct-23 04-Nov-23 5 256
GR-CON-Z14-1549 Aggregate Drainage layer 05-Nov-23 11-Nov-23 6 256
GR-CON-Z14-1550 Installation Geotextile 12-Nov-23 15-Nov-23 4 256
GR-CON-Z14-1551 Backfilling (Soil max for tree) 16-Nov-23 22-Nov-23 6 256
GR-CON-Z14-1552 Installation of Trees 10-Jan-24 14-Jan-24 3 214
GR-CON-Z14-12496 Installation of Shrubs 14-Jan-24 17-Jan-24 3 214
GR-CON-Z14-12506 Installation of Succulents 17-Jan-24 21-Jan-24 3 214
GR-CON-Z14-12516 Installation of Ground Covers 21-Jan-24 24-Jan-24 3 214
GR-CON-Z14-12526 Installation of Grass 24-Jan-24 28-Jan-24 3 214
GR-CON-Z14-1553 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 214
GR-CON-Z14-1554 Natural Boulders Installation 31-Jan-24 05-Feb-24 4 214
GR-CON-Z14-1555 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Feb-24 20-Feb-24 13 214
Site Furnishing 20-Feb-24 14-Mar-24 20 214
GR-CON-Z14-1564 Garden planter box 20-Feb-24 26-Feb-24 5 214
GR-CON-Z14-1565 Wheel stoppers 26-Feb-24 03-Mar-24 5 214
GR-CON-Z14-1566 Steel Lattice 03-Mar-24 09-Mar-24 5 214
GR-CON-Z14-1567 Handrail 09-Mar-24 14-Mar-24 5 214
Storm Piping Works 07-Mar-24 14-Mar-24 6 214
GR-CON-Z14-1568 Installation of DI grating covers 07-Mar-24 14-Mar-24 6 214
Irrigation Works 24-Oct-23 24-Dec-23 53 278
GR-CON-Z14-1556 Excavation Pipe Irrigation 24-Oct-23 29-Oct-23 5 219
GR-CON-Z14-1557 Sand Bedding 30-Oct-23 02-Nov-23 4 219
GR-CON-Z14-1558 HDPE Pipe Installations and fittings and conduit for cable 04-Nov-23 20-Nov-23 15 219
GR-CON-Z14-1560 Test pressure 21-Nov-23 26-Nov-23 5 219
GR-CON-Z14-1559 Installation of Valves and Accessories 27-Nov-23 30-Nov-23 4 219
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1561 Back filling (sand / Subbase ) 02-Dec-23 07-Dec-23 6 219


GR-CON-Z14-1562 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Dec-23 14-Dec-23 6 278
GR-CON-Z14-1563 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
16-Dec-23
system 24-Dec-23 8 278
Electrical Works 30-Oct-23 14-Mar-24 117 214
GR-CON-Z14-1569 Excavation And Disposal 30-Oct-23 04-Nov-23 5 305
GR-CON-Z14-1570 Sand Bedding 05-Nov-23 08-Nov-23 4 305
GR-CON-Z14-1571 laying cables 09-Nov-23 13-Nov-23 4 305
GR-CON-Z14-1572 Backfilling (sand / Sub base) 14-Nov-23 19-Nov-23 5 305
GR-CON-Z14-1573 Control Panel / Distribution Panel Installation 20-Nov-23 23-Nov-23 4 305
GR-CON-Z14-1574 Road Crossing Ducts 09-Mar-24 14-Mar-24 5 214
Street SS-93 24-Oct-23 14-Mar-24 122 214
Site Preparation 24-Oct-23 18-Nov-23 21 315
GR-CON-Z14-1575 Demolition (Asphalt.Paving,etc.....) 24-Oct-23 29-Oct-23 4 34
GR-CON-Z14-1576 Excavation And Disposal 29-Oct-23 04-Nov-23 5 209
GR-CON-Z14-1577 Prepretion And Compaction 04-Nov-23 11-Nov-23 6 315
GR-CON-Z14-1578 Backfilling 11-Nov-23 18-Nov-23 6 315
Curbstone and Paving 04-Nov-23 27-Dec-23 46 281
GR-CON-Z14-1579 Excavation Curbstone 04-Nov-23 09-Nov-23 5 246
GR-CON-Z14-1580 Plain Concrete 09-Nov-23 16-Nov-23 6 281
GR-CON-Z14-1581 Installation Curbstone 16-Nov-23 27-Nov-23 9 281
GR-CON-Z14-1582 Casting Concrete (Mortar haunch) 27-Nov-23 02-Dec-23 4 281
GR-CON-Z14-1583 Backfilling (sand / Sub base) 02-Dec-23 12-Dec-23 9 281
GR-CON-Z14-1584 Installation of Paving 12-Dec-23 27-Dec-23 13 281
Landscape Works 09-Nov-23 20-Feb-24 88 214
GR-CON-Z14-1585 Excavation (Tree Pit ) 09-Nov-23 15-Nov-23 5 246
GR-CON-Z14-1586 Aggregate Drainage layer 15-Nov-23 22-Nov-23 6 246
GR-CON-Z14-1587 Installation Geotextile 22-Nov-23 27-Nov-23 4 246
GR-CON-Z14-1588 Backfilling (Soil max for tree) 27-Nov-23 04-Dec-23 6 246
GR-CON-Z14-1589 Installation of Trees 10-Jan-24 14-Jan-24 3 214
GR-CON-Z14-12536 Installation of Shrubs 14-Jan-24 17-Jan-24 3 214
GR-CON-Z14-12546 Installation of Succulents 17-Jan-24 21-Jan-24 3 214
GR-CON-Z14-12556 Installation of Ground Covers 21-Jan-24 24-Jan-24 3 214
GR-CON-Z14-12566 Installation of Grass 24-Jan-24 28-Jan-24 3 214
GR-CON-Z14-1590 Backfilling (Mulch) 28-Jan-24 31-Jan-24 3 214
GR-CON-Z14-1591 Natural Boulders Installation 31-Jan-24 05-Feb-24 4 214
GR-CON-Z14-1592 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Feb-24 20-Feb-24 13 214
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Furnishing 20-Feb-24 14-Mar-24 20 214


GR-CON-Z14-1601 Garden planter box 20-Feb-24 26-Feb-24 5 214
GR-CON-Z14-1602 Wheel stoppers 26-Feb-24 03-Mar-24 5 214
GR-CON-Z14-1603 Steel Lattice 03-Mar-24 09-Mar-24 5 214
GR-CON-Z14-1604 Handrail 09-Mar-24 14-Mar-24 5 214
Storm Piping Works 07-Mar-24 14-Mar-24 6 214
GR-CON-Z14-1605 Installation of DI grating covers 07-Mar-24 14-Mar-24 6 214
Irrigation Works 04-Nov-23 04-Jan-24 53 268
GR-CON-Z14-1593 Excavation Pipe Irrigation 04-Nov-23 09-Nov-23 5 209
GR-CON-Z14-1594 Sand Bedding 09-Nov-23 14-Nov-23 4 209
GR-CON-Z14-1595 HDPE Pipe Installations and fittings and conduit for cable 14-Nov-23 02-Dec-23 15 209
GR-CON-Z14-1597 Test pressure 02-Dec-23 07-Dec-23 5 209
GR-CON-Z14-1596 Installation of Valves and Accessories 07-Dec-23 12-Dec-23 4 209
GR-CON-Z14-1598 Back filling (sand / Subbase ) 12-Dec-23 19-Dec-23 6 209
GR-CON-Z14-1599 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-Dec-23 26-Dec-23 6 268
GR-CON-Z14-1600 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-Dec-23
system 04-Jan-24 8 268
Electrical Works 09-Nov-23 14-Mar-24 108 214
GR-CON-Z14-1606 Excavation And Disposal 09-Nov-23 15-Nov-23 5 295
GR-CON-Z14-1607 Sand Bedding 15-Nov-23 20-Nov-23 4 295
GR-CON-Z14-1608 laying cables 20-Nov-23 25-Nov-23 4 295
GR-CON-Z14-1609 Backfilling (sand / Sub base) 25-Nov-23 30-Nov-23 5 295
GR-CON-Z14-1610 Control Panel / Distribution Panel Installation 30-Nov-23 05-Dec-23 4 295
GR-CON-Z14-1611 Road Crossing Ducts 09-Mar-24 14-Mar-24 5 214
School S-12 21-Nov-23 10-Mar-24 94 218
Site Preparation 21-Nov-23 02-Dec-23 9 303
GR-CON-Z14-1326 Excavation And Disposal 21-Nov-23 27-Nov-23 5 14
GR-CON-Z14-1327 Prepretion And Compaction 27-Nov-23 02-Dec-23 4 303
Curbstone and Paving 27-Nov-23 20-Jan-24 46 261
GR-CON-Z14-1329 Excavation Curbstone 27-Nov-23 03-Dec-23 5 230
GR-CON-Z14-1330 Plain Concrete 03-Dec-23 10-Dec-23 6 261
GR-CON-Z14-1331 Installation Curbstone 10-Dec-23 20-Dec-23 9 261
GR-CON-Z14-1332 Casting Concrete (Mortar haunch) 20-Dec-23 25-Dec-23 4 261
GR-CON-Z14-1333 Backfilling (sand / Sub base) 25-Dec-23 04-Jan-24 9 261
GR-CON-Z14-1334 Installation of Paving 04-Jan-24 20-Jan-24 13 261
Landscape Works 03-Dec-23 27-Feb-24 74 218
GR-CON-Z14-1335 Excavation (Tree Pit ) 03-Dec-23 09-Dec-23 5 230
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1336 Aggregate Drainage layer 09-Dec-23 16-Dec-23 6 230


GR-CON-Z14-1337 Installation Geotextile 16-Dec-23 20-Dec-23 4 230
GR-CON-Z14-1338 Backfilling (Soil max for tree) 20-Dec-23 27-Dec-23 6 230
GR-CON-Z14-1339 Installation of Trees 10-Jan-24 14-Jan-24 3 218
GR-CON-Z14-5776 Installation of Shrubs 14-Jan-24 17-Jan-24 3 218
GR-CON-Z14-5786 Installation of Succulents 17-Jan-24 21-Jan-24 3 218
GR-CON-Z14-5796 Installation of Ground Covers 21-Jan-24 24-Jan-24 3 218
GR-CON-Z14-5806 Installation of Climbers 24-Jan-24 28-Jan-24 3 218
GR-CON-Z14-5816 Installation of Grass 28-Jan-24 31-Jan-24 3 218
GR-CON-Z14-5826 Installation of Lawns 31-Jan-24 04-Feb-24 3 218
GR-CON-Z14-1340 Backfilling (Mulch) 04-Feb-24 07-Feb-24 3 218
GR-CON-Z14-1341 Natural Boulders Installation 07-Feb-24 12-Feb-24 4 218
GR-CON-Z14-1342 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Feb-24 27-Feb-24 13 218
Site Furnishing 27-Feb-24 10-Mar-24 10 218
GR-CON-Z14-1351 Garden planter box 27-Feb-24 04-Mar-24 5 218
GR-CON-Z14-1352 Wheel stoppers 04-Mar-24 10-Mar-24 5 218
Irrigation Works 27-Nov-23 10-Mar-24 89 218
GR-CON-Z14-1343 Excavation Pipe Irrigation 27-Nov-23 03-Dec-23 5 190
GR-CON-Z14-1344 Sand Bedding 03-Dec-23 06-Dec-23 3 190
GR-CON-Z14-1345 HDPE Pipe Installations and fittings and conduit for cable 06-Dec-23 24-Dec-23 15 190
GR-CON-Z14-1347 Test pressure 24-Dec-23 30-Dec-23 5 190
GR-CON-Z14-1346 Installation of Valves and Accessories 30-Dec-23 03-Jan-24 4 190
GR-CON-Z14-1348 Back filling (sand / Subbase ) 03-Jan-24 10-Jan-24 6 190
GR-CON-Z14-1349 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Jan-24 17-Jan-24 6 255
GR-CON-Z14-1350 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
29-Feb-24
system 10-Mar-24 8 218
Toilet - 02 27-Nov-23 20-Nov-24 293 14
Site Preparation 27-Nov-23 09-Dec-23 10 14
GR-CON-Z14-1000 Excavation And Disposal 27-Nov-23 03-Dec-23 5 14
GR-CON-Z14-1001 Backfilling (one layer) 03-Dec-23 09-Dec-23 5 14
Civil Works 09-Dec-23 04-May-24 116 24
GR-CON-Z14-1002 Polyethylene Under Footings, Grade Slab and Beams 09-Dec-23 12-Dec-23 3 14
GR-CON-Z14-1003 Blinding concrete 12-Dec-23 18-Dec-23 5 14
GR-CON-Z14-1004 Footings 18-Dec-23 27-Dec-23 8 14
GR-CON-Z14-1005 Waterproofing Under Footing 27-Dec-23 02-Jan-24 5 14
GR-CON-Z14-1006 Column Necks 02-Jan-24 09-Jan-24 6 14
GR-CON-Z14-1007 Waterproofing (Toilet) 09-Jan-24 20-Jan-24 9 14
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z14-1008 Backfilling 20-Jan-24 27-Jan-24 6 14


GR-CON-Z14-1009 Ground beams 27-Jan-24 11-Feb-24 13 14
GR-CON-Z14-1010 Slab on grade 11-Feb-24 03-Mar-24 18 14
GR-CON-Z14-1011 Columns 03-Mar-24 19-Mar-24 13 14
GR-CON-Z14-1012 Concrete, slabs Ground floor 19-Mar-24 23-Apr-24 21 14
GR-CON-Z14-1013 Roof Thermal And Moisture Protection Work 23-Apr-24 04-May-24 9 24
Architectural Works 15-May-24 20-Nov-24 157 14
GR-CON-Z14-1014 Blockwork 15-May-24 06-Jun-24 19 14
GR-CON-Z14-1015 Waterproofing 16-Jun-24 01-Jul-24 9 14
GR-CON-Z14-1016 Back Filling (sand) 01-Jul-24 07-Jul-24 5 14
GR-CON-Z14-1017 Floor finish 07-Jul-24 22-Jul-24 13 14
GR-CON-Z14-1018 Wall Finish 22-Jul-24 20-Aug-24 25 14
GR-CON-Z14-1019 Door Installation 20-Aug-24 25-Aug-24 4 14
GR-CON-Z14-1021 Celling finish 25-Aug-24 09-Sep-24 13 14
GR-CON-Z14-1022 ToiletAccessories 09-Sep-24 14-Sep-24 4 14
GR-CON-Z14-1023 Facade Finishing Works 14-Sep-24 07-Oct-24 19 14
GR-CON-Z14-1024 Metal Work 07-Oct-24 29-Oct-24 19 14
GR-CON-Z14-1025 Wood Work 29-Oct-24 20-Nov-24 19 14
Mechanical Works 06-Jun-24 20-Nov-24 138 14
GR-CON-Z14-1026 Pipework Installations and fittings 06-Jun-24 16-Jun-24 8 14
GR-CON-Z14-1027 Installation of refrigerant supply/return pipework 06-Jun-24 11-Jun-24 4 74
GR-CON-Z14-1029 Water Meter With Meter Cabinet 06-Jun-24 10-Jun-24 3 139
GR-CON-Z14-1028 Installation of Sanitary Fixtures 22-Jul-24 31-Jul-24 8 35
GR-CON-Z14-1031 Installation of Exhaust Equipmets and Air outlets 09-Nov-24 20-Nov-24 10 14
Electrical Works 06-Jun-24 20-Nov-24 138 14
GR-CON-Z14-1032 Conduits Installation 06-Jun-24 12-Jun-24 5 44
GR-CON-Z14-1034 Earthing and lightning protection system 12-Jun-24 17-Jun-24 4 118
GR-CON-Z14-1033 Install of power cables 20-Aug-24 24-Aug-24 3 15
GR-CON-Z14-1035 Installation of wiring devices and lighting fixtures 20-Aug-24 26-Aug-24 5 67
GR-CON-Z14-1036 Installation of Alarm with park BMS system 26-Aug-24 01-Sep-24 5 67
GR-CON-Z14-1030 Installation of Fire Detection System 01-Sep-24 10-Sep-24 8 67
GR-CON-Z14-1037 Installation of Panel Board 10-Sep-24 15-Sep-24 4 67
GR-CON-Z14-1038 Connecting to nearest feeder pillar 17-Nov-24 20-Nov-24 3 14
Zone 09 05-Aug-23 21-Oct-24 365 34
Future Neighborhood Park FNP-11 05-Aug-23 31-Aug-24 322 77
Site Preparation 05-Aug-23 30-Aug-23 23 376
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1000 Demolition (Asphalt.Paving,etc.....) 05-Aug-23 09-Aug-23 5 1


GR-CON-Z09-1001 Excavation And Disposal 10-Aug-23 16-Aug-23 6 265
GR-CON-Z09-1002 Prepretion And Compaction 17-Aug-23 22-Aug-23 5 376
GR-CON-Z09-1003 Backfilling 23-Aug-23 30-Aug-23 7 376
Curbstone and Paving 17-Aug-23 28-Oct-23 61 327
GR-CON-Z09-1004 Excavation Curbstone 17-Aug-23 23-Aug-23 6 321
GR-CON-Z09-1005 Plain Concrete 24-Aug-23 31-Aug-23 7 327
GR-CON-Z09-1006 Installation Curbstone 02-Sep-23 12-Sep-23 10 327
GR-CON-Z09-1007 Casting Concrete (Mortar haunch) 13-Sep-23 21-Sep-23 8 327
GR-CON-Z09-1008 Backfilling (sand / Sub base) 24-Sep-23 07-Oct-23 12 327
GR-CON-Z09-1009 Installation of Paving 08-Oct-23 28-Oct-23 18 327
Landscape Works 24-Aug-23 31-Aug-24 305 77
GR-CON-Z09-1010 Excavation (Tree Pit ) 24-Aug-23 30-Aug-23 6 321
GR-CON-Z09-1011 Aggregate Drainage layer 31-Aug-23 07-Sep-23 7 321
GR-CON-Z09-1012 Installation Geotextile 09-Sep-23 13-Sep-23 5 321
GR-CON-Z09-1013 Backfilling (Soil max for tree) 14-Sep-23 21-Sep-23 7 321
GR-CON-Z09-1014 Installation of Trees 21-Jul-24 22-Jul-24 2 77
GR-CON-Z09-2046 Installation of Shrubs 23-Jul-24 24-Jul-24 2 77
GR-CON-Z09-2056 Installation of Succulents 25-Jul-24 27-Jul-24 2 77
GR-CON-Z09-2066 Installation of Ground Covers 28-Jul-24 29-Jul-24 2 77
GR-CON-Z09-2076 Installation of Climbers 30-Jul-24 31-Jul-24 2 77
GR-CON-Z09-2086 Installation of Grass 01-Aug-24 03-Aug-24 2 77
GR-CON-Z09-2096 Installation of Lawns 04-Aug-24 05-Aug-24 2 77
GR-CON-Z09-1015 Backfilling (Mulch) 06-Aug-24 08-Aug-24 3 77
GR-CON-Z09-1016 Natural Boulders Installation 10-Aug-24 14-Aug-24 5 77
GR-CON-Z09-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 31-Aug-24 14 77
Irrigation Works 17-Aug-23 31-Aug-24 311 77
GR-CON-Z09-1018 Excavation Pipe Irrigation 17-Aug-23 23-Aug-23 6 265
GR-CON-Z09-1019 Sand Bedding 24-Aug-23 27-Aug-23 3 265
GR-CON-Z09-1020 HDPE Pipe Installations and fittings and conduit for cable 05-Sep-23 26-Sep-23 17 257
GR-CON-Z09-1022 Test pressure 26-Sep-23 03-Oct-23 6 257
GR-CON-Z09-1021 Installation of Valves and Accessories 03-Oct-23 09-Oct-23 5 257
GR-CON-Z09-1023 Back filling (sand / Subbase ) 09-Oct-23 17-Oct-23 7 257
GR-CON-Z09-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 17-Oct-23 25-Oct-23 7 320
GR-CON-Z09-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-Aug-24
system 31-Aug-24 9 77
Future Neighborhood Park FNP-23 02-Sep-23 31-Aug-24 298 77
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 02-Sep-23 28-Sep-23 23 352


GR-CON-Z09-1026 Demolition (Asphalt.Paving,etc.....) 02-Sep-23 06-Sep-23 5 200
GR-CON-Z09-1027 Excavation And Disposal 07-Sep-23 13-Sep-23 6 241
GR-CON-Z09-1028 Prepretion And Compaction 14-Sep-23 19-Sep-23 5 352
GR-CON-Z09-1029 Backfilling 20-Sep-23 28-Sep-23 7 352
Curbstone and Paving 14-Sep-23 14-Nov-23 52 312
GR-CON-Z09-1030 Excavation Curbstone 14-Sep-23 20-Sep-23 6 265
GR-CON-Z09-1031 Plain Concrete 21-Sep-23 30-Sep-23 7 312
GR-CON-Z09-1032 Installation Curbstone 01-Oct-23 11-Oct-23 10 312
GR-CON-Z09-1033 Casting Concrete (Mortar haunch) 12-Oct-23 17-Oct-23 5 312
GR-CON-Z09-1034 Backfilling (sand / Sub base) 18-Oct-23 29-Oct-23 10 312
GR-CON-Z09-1035 Installation of Paving 30-Oct-23 14-Nov-23 14 312
Landscape Works 21-Sep-23 31-Aug-24 281 77
GR-CON-Z09-1036 Excavation (Tree Pit ) 21-Sep-23 28-Sep-23 6 265
GR-CON-Z09-1037 Aggregate Drainage layer 30-Sep-23 07-Oct-23 7 297
GR-CON-Z09-1038 Installation Geotextile 08-Oct-23 12-Oct-23 5 297
GR-CON-Z09-1039 Backfilling (Soil max for tree) 14-Oct-23 21-Oct-23 7 297
GR-CON-Z09-1040 Installation of Trees 21-Jul-24 22-Jul-24 2 77
GR-CON-Z09-2106 Installation of Shrubs 23-Jul-24 24-Jul-24 2 77
GR-CON-Z09-2116 Installation of Succulents 25-Jul-24 27-Jul-24 2 77
GR-CON-Z09-2126 Installation of Ground Covers 28-Jul-24 29-Jul-24 2 77
GR-CON-Z09-2136 Installation of Climbers 30-Jul-24 31-Jul-24 2 77
GR-CON-Z09-2146 Installation of Grass 01-Aug-24 03-Aug-24 2 77
GR-CON-Z09-2156 Installation of Lawns 04-Aug-24 05-Aug-24 2 77
GR-CON-Z09-1041 Backfilling (Mulch) 06-Aug-24 08-Aug-24 3 77
GR-CON-Z09-1042 Natural Boulders Installation 10-Aug-24 14-Aug-24 5 77
GR-CON-Z09-1043 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 31-Aug-24 14 77
MUGA 30-Sep-23 31-Aug-24 275 77
GR-CON-Z09-1044 Excavation And Disposal 30-Sep-23 05-Oct-23 6 265
GR-CON-Z09-1045 Prepretion And Compaction 07-Oct-23 14-Oct-23 7 265
GR-CON-Z09-1046 polyethylene under footings ( fence and gates) 15-Oct-23 21-Oct-23 6 265
GR-CON-Z09-1047 Blinding concrete (flooring) 22-Oct-23 28-Oct-23 6 265
GR-CON-Z09-1048 Concrete Footings ( fence and gates) 29-Oct-23 13-Nov-23 14 265
GR-CON-Z09-1049 Tools Play Installation ( basketball / football ..) 02-Jan-24 22-Jan-24 17 222
GR-CON-Z09-1050 PaintAcrylic Play Surface 22-Jan-24 07-Feb-24 14 222
GR-CON-Z09-1051 Fence (high / low) / gates Installation 12-Aug-24 31-Aug-24 17 77
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 14-Sep-23 31-Aug-24 287 77


GR-CON-Z09-1052 Excavation Pipe Irrigation 14-Sep-23 20-Sep-23 6 241
GR-CON-Z09-1053 Sand Bedding 21-Sep-23 25-Sep-23 3 241
GR-CON-Z09-1054 HDPE Pipe Installations and fittings and conduit for cable 26-Sep-23 15-Oct-23 17 241
GR-CON-Z09-1056 Test pressure 16-Oct-23 22-Oct-23 6 241
GR-CON-Z09-1055 Installation of Valves and Accessories 23-Oct-23 28-Oct-23 5 241
GR-CON-Z09-1057 Back filling (sand / Subbase ) 29-Oct-23 05-Nov-23 7 241
GR-CON-Z09-1058 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Nov-23 13-Nov-23 7 304
GR-CON-Z09-1059 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-Aug-24
system 31-Aug-24 9 77
Mosque M-11 02-Oct-23 02-Oct-24 300 50
Site Preparation 02-Oct-23 23-Oct-23 19 309
GR-CON-Z09-1060 Demolition (Asphalt.Paving,etc.....) 02-Oct-23 05-Oct-23 4 200
GR-CON-Z09-1061 Excavation And Disposal 07-Oct-23 11-Oct-23 5 224
GR-CON-Z09-1062 Prepretion And Compaction 12-Oct-23 16-Oct-23 4 309
GR-CON-Z09-1063 Backfilling 17-Oct-23 23-Oct-23 6 309
Curbstone and Paving 24-Oct-23 18-Nov-23 22 309
GR-CON-Z09-1068 Backfilling (sand / Sub base) 24-Oct-23 02-Nov-23 9 309
GR-CON-Z09-1069 Installation of Paving 04-Nov-23 18-Nov-23 13 309
Landscape Works 12-Oct-23 02-Oct-24 291 50
GR-CON-Z09-1070 Excavation (Tree Pit ) 12-Oct-23 17-Oct-23 5 257
GR-CON-Z09-1071 Aggregate Drainage layer 18-Oct-23 24-Oct-23 6 257
GR-CON-Z09-1072 Installation Geotextile 25-Oct-23 30-Oct-23 5 257
GR-CON-Z09-1073 Backfilling (Soil max for tree) 31-Oct-23 05-Nov-23 5 257
GR-CON-Z09-1074 Installation of Trees 21-Jul-24 24-Jul-24 4 50
GR-CON-Z09-3866 Installation of Climbers 25-Jul-24 29-Jul-24 4 50
GR-CON-Z09-3876 Installation of Shrubs 30-Jul-24 03-Aug-24 4 50
GR-CON-Z09-3886 Installation of Succulents 04-Aug-24 07-Aug-24 4 50
GR-CON-Z09-3896 Installation of Ground Covers 08-Aug-24 12-Aug-24 4 50
GR-CON-Z09-1075 Backfilling (Mulch) 13-Aug-24 29-Aug-24 15 50
GR-CON-Z09-1076 Natural Boulders Installation 31-Aug-24 14-Sep-24 13 50
GR-CON-Z09-1077 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Sep-24 02-Oct-24 15 50
Irrigation Works 12-Oct-23 02-Oct-24 291 50
GR-CON-Z09-1078 Excavation Pipe Irrigation 12-Oct-23 17-Oct-23 5 224
GR-CON-Z09-1079 Sand Bedding 18-Oct-23 21-Oct-23 3 224
GR-CON-Z09-1080 HDPE Pipe Installations and fittings and conduit for cable 22-Oct-23 07-Nov-23 15 224
GR-CON-Z09-1082 Test pressure 08-Nov-23 13-Nov-23 5 224
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1081 Installation of Valves and Accessories 14-Nov-23 18-Nov-23 4 224


GR-CON-Z09-1083 Back filling (sand / Subbase ) 19-Nov-23 25-Nov-23 6 224
GR-CON-Z09-1084 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 26-Nov-23 02-Dec-23 6 291
GR-CON-Z09-1085 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-Sep-24
system 02-Oct-24 6 50
Mosque M-07 30-Oct-23 02-Oct-24 276 50
Site Preparation 30-Oct-23 20-Nov-23 19 285
GR-CON-Z09-1086 Demolition (Asphalt.Paving,etc.....) 30-Oct-23 02-Nov-23 4 200
GR-CON-Z09-1087 Excavation And Disposal 04-Nov-23 08-Nov-23 5 200
GR-CON-Z09-1088 Prepretion And Compaction 09-Nov-23 13-Nov-23 4 285
GR-CON-Z09-1089 Backfilling 14-Nov-23 20-Nov-23 6 285
Curbstone and Paving 21-Nov-23 16-Dec-23 22 285
GR-CON-Z09-1094 Backfilling (sand / Sub base) 21-Nov-23 30-Nov-23 9 285
GR-CON-Z09-1095 Installation of Paving 02-Dec-23 16-Dec-23 13 285
Landscape Works 09-Nov-23 02-Oct-24 267 50
GR-CON-Z09-1096 Excavation (Tree Pit ) 09-Nov-23 14-Nov-23 5 233
GR-CON-Z09-1097 Aggregate Drainage layer 15-Nov-23 21-Nov-23 6 233
GR-CON-Z09-1098 Installation Geotextile 22-Nov-23 27-Nov-23 5 233
GR-CON-Z09-1099 Backfilling (Soil max for tree) 28-Nov-23 03-Dec-23 5 233
GR-CON-Z09-1100 Installation of Trees 21-Jul-24 24-Jul-24 4 50
GR-CON-Z09-3906 Installation of Climbers 25-Jul-24 29-Jul-24 4 50
GR-CON-Z09-3916 Installation of Shrubs 30-Jul-24 03-Aug-24 4 50
GR-CON-Z09-3926 Installation of Succulents 04-Aug-24 07-Aug-24 4 50
GR-CON-Z09-3936 Installation of Ground Covers 08-Aug-24 12-Aug-24 4 50
GR-CON-Z09-1101 Backfilling (Mulch) 13-Aug-24 29-Aug-24 15 50
GR-CON-Z09-1102 Natural Boulders Installation 31-Aug-24 14-Sep-24 13 50
GR-CON-Z09-1103 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Sep-24 02-Oct-24 15 50
Irrigation Works 09-Nov-23 02-Oct-24 267 50
GR-CON-Z09-1104 Excavation Pipe Irrigation 09-Nov-23 14-Nov-23 5 200
GR-CON-Z09-1105 Sand Bedding 15-Nov-23 18-Nov-23 3 200
GR-CON-Z09-1106 HDPE Pipe Installations and fittings and conduit for cable 19-Nov-23 05-Dec-23 15 200
GR-CON-Z09-1108 Test pressure 06-Dec-23 11-Dec-23 5 200
GR-CON-Z09-1107 Installation of Valves and Accessories 12-Dec-23 16-Dec-23 4 200
GR-CON-Z09-1109 Back filling (sand / Subbase ) 17-Dec-23 23-Dec-23 6 200
GR-CON-Z09-1110 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Dec-23 30-Dec-23 6 267
GR-CON-Z09-1111 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-Sep-24
system 02-Oct-24 6 50
Parking P-23 03-Oct-23 21-Aug-24 263 85
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 03-Oct-23 10-Oct-23 6 329


GR-CON-Z09-1115 Backfilling 03-Oct-23 10-Oct-23 6 329
GR-CON-Z09-1113 Excavation And Disposal 04-Oct-23 10-Oct-23 5 225
GR-CON-Z09-1112 Demolition (Asphalt.Paving,etc.....) 05-Oct-23 10-Oct-23 4 225
GR-CON-Z09-1114 Prepretion And Compaction 05-Oct-23 10-Oct-23 4 329
Curbstone and Paving 10-Oct-23 03-Dec-23 46 296
GR-CON-Z09-1116 Excavation Curbstone 10-Oct-23 16-Oct-23 5 288
GR-CON-Z09-1117 Plain Concrete 16-Oct-23 23-Oct-23 6 296
GR-CON-Z09-1118 Installation Curbstone 23-Oct-23 02-Nov-23 9 296
GR-CON-Z09-1119 Casting Concrete (Mortar haunch) 02-Nov-23 07-Nov-23 4 296
GR-CON-Z09-1120 Backfilling (sand / Sub base) 07-Nov-23 18-Nov-23 9 296
GR-CON-Z09-1121 Installation of Paving 18-Nov-23 03-Dec-23 13 296
Landscape Works 16-Oct-23 10-Aug-24 242 85
GR-CON-Z09-1122 Excavation (Tree Pit ) 16-Oct-23 22-Oct-23 5 288
GR-CON-Z09-1123 Aggregate Drainage layer 22-Oct-23 29-Oct-23 6 288
GR-CON-Z09-1124 Installation Geotextile 29-Oct-23 02-Nov-23 4 288
GR-CON-Z09-1125 Backfilling (Soil max for tree) 02-Nov-23 09-Nov-23 6 288
GR-CON-Z09-1126 Installation of Trees 21-Jul-24 23-Jul-24 3 85
GR-CON-Z09-7296 Installation of Shrubs 24-Jul-24 27-Jul-24 3 85
GR-CON-Z09-7306 Installation of Ground Covers 28-Jul-24 30-Jul-24 3 85
GR-CON-Z09-7316 Installation of Succulents 31-Jul-24 03-Aug-24 3 85
GR-CON-Z09-7326 Installation of Grass 04-Aug-24 06-Aug-24 3 85
GR-CON-Z09-1127 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 85
Site Furnishing 11-Aug-24 21-Aug-24 10 85
GR-CON-Z09-1138 Tree Grate 11-Aug-24 15-Aug-24 5 85
GR-CON-Z09-1139 Wheel stoppers 17-Aug-24 21-Aug-24 5 85
Irrigation Works 10-Oct-23 21-Aug-24 257 85
GR-CON-Z09-1130 Excavation Pipe Irrigation 10-Oct-23 16-Oct-23 5 225
GR-CON-Z09-1131 Sand Bedding 16-Oct-23 19-Oct-23 3 225
GR-CON-Z09-1132 HDPE Pipe Installations and fittings and conduit for cable 19-Oct-23 06-Nov-23 15 225
GR-CON-Z09-1134 Test pressure 06-Nov-23 12-Nov-23 5 225
GR-CON-Z09-1133 Installation of Valves and Accessories 12-Nov-23 16-Nov-23 4 225
GR-CON-Z09-1135 Back filling (sand / Subbase ) 16-Nov-23 23-Nov-23 6 225
GR-CON-Z09-1136 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-Nov-23 30-Nov-23 6 290
GR-CON-Z09-1137 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Aug-24
system 21-Aug-24 8 85
Parking P-07 14-Oct-23 21-Aug-24 254 85
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 14-Oct-23 21-Oct-23 6 320


GR-CON-Z09-1143 Backfilling 14-Oct-23 21-Oct-23 6 320
GR-CON-Z09-1141 Excavation And Disposal 15-Oct-23 21-Oct-23 5 216
GR-CON-Z09-1140 Demolition (Asphalt.Paving,etc.....) 16-Oct-23 21-Oct-23 4 216
GR-CON-Z09-1142 Prepretion And Compaction 16-Oct-23 21-Oct-23 4 320
Curbstone and Paving 21-Oct-23 13-Dec-23 46 287
GR-CON-Z09-1144 Excavation Curbstone 21-Oct-23 26-Oct-23 5 279
GR-CON-Z09-1145 Plain Concrete 26-Oct-23 02-Nov-23 6 287
GR-CON-Z09-1146 Installation Curbstone 02-Nov-23 13-Nov-23 9 287
GR-CON-Z09-1147 Casting Concrete (Mortar haunch) 13-Nov-23 18-Nov-23 4 287
GR-CON-Z09-1148 Backfilling (sand / Sub base) 18-Nov-23 28-Nov-23 9 287
GR-CON-Z09-1149 Installation of Paving 28-Nov-23 13-Dec-23 13 287
Landscape Works 26-Oct-23 10-Aug-24 233 85
GR-CON-Z09-1150 Excavation (Tree Pit ) 26-Oct-23 01-Nov-23 5 279
GR-CON-Z09-1151 Aggregate Drainage layer 01-Nov-23 08-Nov-23 6 279
GR-CON-Z09-1152 Installation Geotextile 08-Nov-23 13-Nov-23 4 279
GR-CON-Z09-1153 Backfilling (Soil max for tree) 13-Nov-23 20-Nov-23 6 279
GR-CON-Z09-1154 Installation of Trees 21-Jul-24 23-Jul-24 3 85
GR-CON-Z09-7336 Installation of Shrubs 24-Jul-24 27-Jul-24 3 85
GR-CON-Z09-7346 Installation of Ground Covers 28-Jul-24 30-Jul-24 3 85
GR-CON-Z09-7356 Installation of Succulents 31-Jul-24 03-Aug-24 3 85
GR-CON-Z09-7366 Installation of Grass 04-Aug-24 06-Aug-24 3 85
GR-CON-Z09-1155 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 85
Site Furnishing 11-Aug-24 21-Aug-24 10 85
GR-CON-Z09-1166 Tree Grate 11-Aug-24 15-Aug-24 5 85
GR-CON-Z09-1167 Wheel stoppers 17-Aug-24 21-Aug-24 5 85
Irrigation Works 21-Oct-23 21-Aug-24 248 85
GR-CON-Z09-1158 Excavation Pipe Irrigation 21-Oct-23 26-Oct-23 5 216
GR-CON-Z09-1159 Sand Bedding 26-Oct-23 30-Oct-23 3 216
GR-CON-Z09-1160 HDPE Pipe Installations and fittings and conduit for cable 30-Oct-23 16-Nov-23 15 216
GR-CON-Z09-1162 Test pressure 16-Nov-23 22-Nov-23 5 216
GR-CON-Z09-1161 Installation of Valves and Accessories 22-Nov-23 27-Nov-23 4 216
GR-CON-Z09-1163 Back filling (sand / Subbase ) 27-Nov-23 04-Dec-23 6 216
GR-CON-Z09-1164 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Dec-23 11-Dec-23 6 281
GR-CON-Z09-1165 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Aug-24
system 21-Aug-24 8 85
Parking P-08 24-Oct-23 21-Aug-24 245 85
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 24-Oct-23 31-Oct-23 6 311


GR-CON-Z09-1171 Backfilling 24-Oct-23 31-Oct-23 6 311
GR-CON-Z09-1169 Excavation And Disposal 25-Oct-23 31-Oct-23 5 207
GR-CON-Z09-1168 Demolition (Asphalt.Paving,etc.....) 26-Oct-23 31-Oct-23 4 207
GR-CON-Z09-1170 Prepretion And Compaction 26-Oct-23 31-Oct-23 4 311
Curbstone and Paving 31-Oct-23 24-Dec-23 46 278
GR-CON-Z09-1172 Excavation Curbstone 31-Oct-23 06-Nov-23 5 270
GR-CON-Z09-1173 Plain Concrete 06-Nov-23 13-Nov-23 6 278
GR-CON-Z09-1174 Installation Curbstone 13-Nov-23 23-Nov-23 9 278
GR-CON-Z09-1175 Casting Concrete (Mortar haunch) 23-Nov-23 28-Nov-23 4 278
GR-CON-Z09-1176 Backfilling (sand / Sub base) 28-Nov-23 09-Dec-23 9 278
GR-CON-Z09-1177 Installation of Paving 09-Dec-23 24-Dec-23 13 278
Landscape Works 06-Nov-23 10-Aug-24 224 85
GR-CON-Z09-1178 Excavation (Tree Pit ) 06-Nov-23 12-Nov-23 5 270
GR-CON-Z09-1179 Aggregate Drainage layer 12-Nov-23 19-Nov-23 6 270
GR-CON-Z09-1180 Installation Geotextile 19-Nov-23 23-Nov-23 4 270
GR-CON-Z09-1181 Backfilling (Soil max for tree) 23-Nov-23 30-Nov-23 6 270
GR-CON-Z09-1182 Installation of Trees 21-Jul-24 23-Jul-24 3 85
GR-CON-Z09-7376 Installation of Shrubs 24-Jul-24 27-Jul-24 3 85
GR-CON-Z09-7386 Installation of Ground Covers 28-Jul-24 30-Jul-24 3 85
GR-CON-Z09-7396 Installation of Succulents 31-Jul-24 03-Aug-24 3 85
GR-CON-Z09-7406 Installation of Grass 04-Aug-24 06-Aug-24 3 85
GR-CON-Z09-1183 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 85
Site Furnishing 11-Aug-24 21-Aug-24 10 85
GR-CON-Z09-1194 Tree Grate 11-Aug-24 15-Aug-24 5 85
GR-CON-Z09-1195 Wheel stoppers 17-Aug-24 21-Aug-24 5 85
Irrigation Works 31-Oct-23 21-Aug-24 239 85
GR-CON-Z09-1186 Excavation Pipe Irrigation 31-Oct-23 06-Nov-23 5 207
GR-CON-Z09-1187 Sand Bedding 06-Nov-23 09-Nov-23 3 207
GR-CON-Z09-1188 HDPE Pipe Installations and fittings and conduit for cable 09-Nov-23 27-Nov-23 15 207
GR-CON-Z09-1190 Test pressure 27-Nov-23 03-Dec-23 5 207
GR-CON-Z09-1189 Installation of Valves and Accessories 03-Dec-23 07-Dec-23 4 207
GR-CON-Z09-1191 Back filling (sand / Subbase ) 07-Dec-23 14-Dec-23 6 207
GR-CON-Z09-1192 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Dec-23 21-Dec-23 6 272
GR-CON-Z09-1193 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Aug-24
system 21-Aug-24 8 85
Street SS-41 23-Nov-23 22-Sep-24 246 58
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 23-Nov-23 18-Dec-23 21 283


GR-CON-Z09-1261 Demolition (Asphalt.Paving,etc.....) 23-Nov-23 28-Nov-23 4 177
GR-CON-Z09-1262 Excavation And Disposal 28-Nov-23 04-Dec-23 5 177
GR-CON-Z09-1263 Prepretion And Compaction 04-Dec-23 11-Dec-23 6 283
GR-CON-Z09-1264 Backfilling 11-Dec-23 18-Dec-23 6 283
Curbstone and Paving 04-Dec-23 27-Jan-24 46 249
GR-CON-Z09-1265 Excavation Curbstone 04-Dec-23 10-Dec-23 5 214
GR-CON-Z09-1266 Plain Concrete 10-Dec-23 17-Dec-23 6 249
GR-CON-Z09-1267 Installation Curbstone 17-Dec-23 27-Dec-23 9 249
GR-CON-Z09-1268 Casting Concrete (Mortar haunch) 27-Dec-23 01-Jan-24 4 249
GR-CON-Z09-1269 Backfilling (sand / Sub base) 01-Jan-24 11-Jan-24 9 249
GR-CON-Z09-1270 Installation of Paving 11-Jan-24 27-Jan-24 13 249
Landscape Works 10-Dec-23 29-Aug-24 212 58
GR-CON-Z09-1271 Excavation (Tree Pit ) 10-Dec-23 16-Dec-23 5 214
GR-CON-Z09-1272 Aggregate Drainage layer 16-Dec-23 23-Dec-23 6 214
GR-CON-Z09-1273 Installation Geotextile 23-Dec-23 27-Dec-23 4 214
GR-CON-Z09-1274 Backfilling (Soil max for tree) 27-Dec-23 03-Jan-24 6 214
GR-CON-Z09-1275 Installation of Trees 21-Jul-24 23-Jul-24 3 58
GR-CON-Z09-11056 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11066 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
GR-CON-Z09-11076 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58
GR-CON-Z09-11086 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1276 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
GR-CON-Z09-1277 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58
GR-CON-Z09-1278 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1287 Garden planter box 31-Aug-24 04-Sep-24 5 58
GR-CON-Z09-1288 Wheel stoppers 05-Sep-24 10-Sep-24 5 58
GR-CON-Z09-1289 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1290 Handrail 17-Sep-24 22-Sep-24 5 58
Storm Piping Works 16-Sep-24 22-Sep-24 6 58
GR-CON-Z09-1291 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 04-Dec-23 04-Feb-24 53 236
GR-CON-Z09-1279 Excavation Pipe Irrigation 04-Dec-23 10-Dec-23 5 177
GR-CON-Z09-1280 Sand Bedding 10-Dec-23 14-Dec-23 4 177
GR-CON-Z09-1281 HDPE Pipe Installations and fittings and conduit for cable 14-Dec-23 01-Jan-24 15 177
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1283 Test pressure 01-Jan-24 07-Jan-24 5 177


GR-CON-Z09-1282 Installation of Valves and Accessories 07-Jan-24 11-Jan-24 4 177
GR-CON-Z09-1284 Back filling (sand / Subbase ) 11-Jan-24 18-Jan-24 6 177
GR-CON-Z09-1285 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Jan-24 25-Jan-24 6 236
GR-CON-Z09-1286 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jan-24
system 04-Feb-24 8 236
Electrical Works 10-Dec-23 22-Sep-24 232 58
GR-CON-Z09-1292 Excavation And Disposal 10-Dec-23 16-Dec-23 5 263
GR-CON-Z09-1293 Sand Bedding 16-Dec-23 20-Dec-23 4 263
GR-CON-Z09-1294 laying cables 20-Dec-23 25-Dec-23 4 263
GR-CON-Z09-1295 Backfilling (sand / Sub base) 25-Dec-23 31-Dec-23 5 263
GR-CON-Z09-1296 Control Panel / Distribution Panel Installation 31-Dec-23 04-Jan-24 4 263
GR-CON-Z09-1297 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
Street SS-46 21-Dec-23 22-Sep-24 222 58
Site Preparation 21-Dec-23 15-Jan-24 21 259
GR-CON-Z09-1372 Demolition (Asphalt.Paving,etc.....) 21-Dec-23 26-Dec-23 4 153
GR-CON-Z09-1373 Excavation And Disposal 26-Dec-23 01-Jan-24 5 153
GR-CON-Z09-1374 Prepretion And Compaction 01-Jan-24 08-Jan-24 6 259
GR-CON-Z09-1375 Backfilling 08-Jan-24 15-Jan-24 6 259
Curbstone and Paving 01-Jan-24 24-Feb-24 46 225
GR-CON-Z09-1376 Excavation Curbstone 01-Jan-24 07-Jan-24 5 190
GR-CON-Z09-1377 Plain Concrete 07-Jan-24 14-Jan-24 6 225
GR-CON-Z09-1378 Installation Curbstone 14-Jan-24 24-Jan-24 9 225
GR-CON-Z09-1379 Casting Concrete (Mortar haunch) 24-Jan-24 29-Jan-24 4 225
GR-CON-Z09-1380 Backfilling (sand / Sub base) 29-Jan-24 08-Feb-24 9 225
GR-CON-Z09-1381 Installation of Paving 08-Feb-24 24-Feb-24 13 225
Landscape Works 07-Jan-24 29-Aug-24 188 58
GR-CON-Z09-1382 Excavation (Tree Pit ) 07-Jan-24 13-Jan-24 5 190
GR-CON-Z09-1383 Aggregate Drainage layer 13-Jan-24 20-Jan-24 6 190
GR-CON-Z09-1384 Installation Geotextile 20-Jan-24 24-Jan-24 4 190
GR-CON-Z09-1385 Backfilling (Soil max for tree) 24-Jan-24 31-Jan-24 6 190
GR-CON-Z09-1386 Installation of Trees 21-Jul-24 23-Jul-24 3 58
GR-CON-Z09-11176 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11186 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
GR-CON-Z09-11196 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58
GR-CON-Z09-11206 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1387 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1388 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58


GR-CON-Z09-1389 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1398 Garden planter box 31-Aug-24 04-Sep-24 5 58
GR-CON-Z09-1399 Wheel stoppers 05-Sep-24 10-Sep-24 5 58
GR-CON-Z09-1400 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1401 Handrail 17-Sep-24 22-Sep-24 5 58
Storm Piping Works 16-Sep-24 22-Sep-24 6 58
GR-CON-Z09-1402 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 01-Jan-24 03-Mar-24 53 212
GR-CON-Z09-1390 Excavation Pipe Irrigation 01-Jan-24 07-Jan-24 5 153
GR-CON-Z09-1391 Sand Bedding 07-Jan-24 11-Jan-24 4 153
GR-CON-Z09-1392 HDPE Pipe Installations and fittings and conduit for cable 11-Jan-24 29-Jan-24 15 153
GR-CON-Z09-1394 Test pressure 29-Jan-24 04-Feb-24 5 153
GR-CON-Z09-1393 Installation of Valves and Accessories 04-Feb-24 08-Feb-24 4 153
GR-CON-Z09-1395 Back filling (sand / Subbase ) 08-Feb-24 15-Feb-24 6 153
GR-CON-Z09-1396 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Feb-24 22-Feb-24 6 212
GR-CON-Z09-1397 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-Feb-24
system 03-Mar-24 8 212
Electrical Works 07-Jan-24 22-Sep-24 208 58
GR-CON-Z09-1403 Excavation And Disposal 07-Jan-24 13-Jan-24 5 239
GR-CON-Z09-1404 Sand Bedding 13-Jan-24 17-Jan-24 4 239
GR-CON-Z09-1405 laying cables 17-Jan-24 22-Jan-24 4 239
GR-CON-Z09-1406 Backfilling (sand / Sub base) 22-Jan-24 28-Jan-24 5 239
GR-CON-Z09-1407 Control Panel / Distribution Panel Installation 28-Jan-24 01-Feb-24 4 239
GR-CON-Z09-1408 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
Street SS-74 18-Jan-24 22-Sep-24 198 58
Site Preparation 18-Jan-24 12-Feb-24 21 235
GR-CON-Z09-1483 Demolition (Asphalt.Paving,etc.....) 18-Jan-24 23-Jan-24 4 129
GR-CON-Z09-1484 Excavation And Disposal 23-Jan-24 29-Jan-24 5 129
GR-CON-Z09-1485 Prepretion And Compaction 29-Jan-24 05-Feb-24 6 235
GR-CON-Z09-1486 Backfilling 05-Feb-24 12-Feb-24 6 235
Curbstone and Paving 29-Jan-24 25-Mar-24 46 201
GR-CON-Z09-1487 Excavation Curbstone 29-Jan-24 04-Feb-24 5 166
GR-CON-Z09-1488 Plain Concrete 04-Feb-24 11-Feb-24 6 201
GR-CON-Z09-1489 Installation Curbstone 11-Feb-24 21-Feb-24 9 201
GR-CON-Z09-1490 Casting Concrete (Mortar haunch) 21-Feb-24 26-Feb-24 4 201
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1491 Backfilling (sand / Sub base) 26-Feb-24 07-Mar-24 9 201


GR-CON-Z09-1492 Installation of Paving 07-Mar-24 25-Mar-24 13 201
Landscape Works 04-Feb-24 29-Aug-24 164 58
GR-CON-Z09-1493 Excavation (Tree Pit ) 04-Feb-24 10-Feb-24 5 166
GR-CON-Z09-1494 Aggregate Drainage layer 10-Feb-24 17-Feb-24 6 166
GR-CON-Z09-1495 Installation Geotextile 17-Feb-24 21-Feb-24 4 166
GR-CON-Z09-1496 Backfilling (Soil max for tree) 21-Feb-24 28-Feb-24 6 166
GR-CON-Z09-1497 Installation of Trees 21-Jul-24 23-Jul-24 3 58
GR-CON-Z09-11296 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11306 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
GR-CON-Z09-11316 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58
GR-CON-Z09-11326 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1498 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
GR-CON-Z09-1499 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58
GR-CON-Z09-1500 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1509 Garden planter box 31-Aug-24 04-Sep-24 5 58
GR-CON-Z09-1510 Wheel stoppers 05-Sep-24 10-Sep-24 5 58
GR-CON-Z09-1511 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1512 Handrail 17-Sep-24 22-Sep-24 5 58
Storm Piping Works 16-Sep-24 22-Sep-24 6 58
GR-CON-Z09-1513 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 29-Jan-24 06-Apr-24 53 188
GR-CON-Z09-1501 Excavation Pipe Irrigation 29-Jan-24 04-Feb-24 5 129
GR-CON-Z09-1502 Sand Bedding 04-Feb-24 08-Feb-24 4 129
GR-CON-Z09-1503 HDPE Pipe Installations and fittings and conduit for cable 08-Feb-24 26-Feb-24 15 129
GR-CON-Z09-1505 Test pressure 26-Feb-24 03-Mar-24 5 129
GR-CON-Z09-1504 Installation of Valves and Accessories 03-Mar-24 07-Mar-24 4 129
GR-CON-Z09-1506 Back filling (sand / Subbase ) 07-Mar-24 14-Mar-24 6 129
GR-CON-Z09-1507 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Mar-24 24-Mar-24 6 188
GR-CON-Z09-1508 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Mar-24
system 06-Apr-24 8 188
Electrical Works 04-Feb-24 22-Sep-24 184 58
GR-CON-Z09-1514 Excavation And Disposal 04-Feb-24 10-Feb-24 5 215
GR-CON-Z09-1515 Sand Bedding 10-Feb-24 14-Feb-24 4 215
GR-CON-Z09-1516 laying cables 14-Feb-24 19-Feb-24 4 215
GR-CON-Z09-1517 Backfilling (sand / Sub base) 19-Feb-24 25-Feb-24 5 215
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1518 Control Panel / Distribution Panel Installation 25-Feb-24 29-Feb-24 4 215


GR-CON-Z09-1519 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
Street SS-04.1 23-Jan-24 21-Oct-24 218 34
Site Preparation 23-Jan-24 29-Feb-24 32 220
GR-CON-Z09-1224 Demolition (Asphalt.Paving,etc.....) 23-Jan-24 30-Jan-24 6 99
GR-CON-Z09-1225 Excavation And Disposal 30-Jan-24 08-Feb-24 8 99
GR-CON-Z09-1226 Prepretion And Compaction 08-Feb-24 19-Feb-24 9 220
GR-CON-Z09-1227 Backfilling 19-Feb-24 29-Feb-24 9 220
Curbstone and Paving 08-Feb-24 13-May-24 71 167
GR-CON-Z09-1228 Excavation Curbstone 08-Feb-24 18-Feb-24 8 119
GR-CON-Z09-1229 Plain Concrete 18-Feb-24 28-Feb-24 9 167
GR-CON-Z09-1230 Installation Curbstone 28-Feb-24 17-Mar-24 14 167
GR-CON-Z09-1231 Casting Concrete (Mortar haunch) 17-Mar-24 26-Mar-24 6 167
GR-CON-Z09-1232 Backfilling (sand / Sub base) 26-Mar-24 20-Apr-24 14 167
GR-CON-Z09-1233 Installation of Paving 21-Apr-24 13-May-24 20 167
Landscape Works 18-Feb-24 12-Sep-24 164 34
GR-CON-Z09-1234 Excavation (Tree Pit ) 18-Feb-24 27-Feb-24 8 119
GR-CON-Z09-1235 Aggregate Drainage layer 27-Feb-24 09-Mar-24 9 119
GR-CON-Z09-1236 Installation Geotextile 09-Mar-24 17-Mar-24 6 119
GR-CON-Z09-1237 Backfilling (Soil max for tree) 17-Mar-24 31-Mar-24 9 119
GR-CON-Z09-1238 Installation of Trees 21-Jul-24 24-Jul-24 4 34
GR-CON-Z09-11016 Installation of Shrubs 25-Jul-24 28-Jul-24 3 34
GR-CON-Z09-11026 Installation of Succulents 29-Jul-24 31-Jul-24 3 34
GR-CON-Z09-11036 Installation of Ground Covers 01-Aug-24 04-Aug-24 3 34
GR-CON-Z09-11046 Installation of Grass 05-Aug-24 07-Aug-24 3 34
GR-CON-Z09-1239 Backfilling (Mulch) 08-Aug-24 13-Aug-24 5 34
GR-CON-Z09-1240 Natural Boulders Installation 14-Aug-24 20-Aug-24 6 34
GR-CON-Z09-1241 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Aug-24 12-Sep-24 20 34
Site Furnishing 14-Sep-24 21-Oct-24 32 34
GR-CON-Z09-1250 Garden planter box 14-Sep-24 22-Sep-24 8 34
GR-CON-Z09-1251 Wheel stoppers 24-Sep-24 02-Oct-24 8 34
GR-CON-Z09-1252 Steel Lattice 03-Oct-24 12-Oct-24 8 34
GR-CON-Z09-1253 Handrail 13-Oct-24 21-Oct-24 8 34
Storm Piping Works 12-Oct-24 21-Oct-24 9 34
GR-CON-Z09-1254 Installation of DI grating covers 12-Oct-24 21-Oct-24 9 34
Irrigation Works 08-Feb-24 25-May-24 81 148
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1242 Excavation Pipe Irrigation 08-Feb-24 18-Feb-24 8 99


GR-CON-Z09-1243 Sand Bedding 18-Feb-24 25-Feb-24 6 99
GR-CON-Z09-1244 HDPE Pipe Installations and fittings and conduit for cable 25-Feb-24 26-Mar-24 23 99
GR-CON-Z09-1246 Test pressure 26-Mar-24 07-Apr-24 8 99
GR-CON-Z09-1245 Installation of Valves and Accessories 08-Apr-24 20-Apr-24 6 99
GR-CON-Z09-1247 Back filling (sand / Subbase ) 21-Apr-24 30-Apr-24 9 99
GR-CON-Z09-1248 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-May-24 11-May-24 9 148
GR-CON-Z09-1249 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-May-24
system 25-May-24 12 148
Electrical Works 18-Feb-24 21-Oct-24 196 34
GR-CON-Z09-1255 Excavation And Disposal 18-Feb-24 27-Feb-24 8 188
GR-CON-Z09-1256 Sand Bedding 27-Feb-24 05-Mar-24 6 188
GR-CON-Z09-1257 laying cables 05-Mar-24 12-Mar-24 6 188
GR-CON-Z09-1258 Backfilling (sand / Sub base) 12-Mar-24 24-Mar-24 8 188
GR-CON-Z09-1259 Control Panel / Distribution Panel Installation 25-Mar-24 02-Apr-24 6 188
GR-CON-Z09-1260 Road Crossing Ducts 13-Oct-24 21-Oct-24 8 34
Street SS-43.1 28-Jan-24 22-Sep-24 190 58
Site Preparation 28-Jan-24 21-Feb-24 21 227
GR-CON-Z09-1298 Demolition (Asphalt.Paving,etc.....) 28-Jan-24 01-Feb-24 4 121
GR-CON-Z09-1299 Excavation And Disposal 01-Feb-24 07-Feb-24 5 121
GR-CON-Z09-1300 Prepretion And Compaction 07-Feb-24 14-Feb-24 6 227
GR-CON-Z09-1301 Backfilling 14-Feb-24 21-Feb-24 6 227
Curbstone and Paving 07-Feb-24 07-Apr-24 46 193
GR-CON-Z09-1302 Excavation Curbstone 07-Feb-24 13-Feb-24 5 158
GR-CON-Z09-1303 Plain Concrete 13-Feb-24 20-Feb-24 6 193
GR-CON-Z09-1304 Installation Curbstone 20-Feb-24 02-Mar-24 9 193
GR-CON-Z09-1305 Casting Concrete (Mortar haunch) 02-Mar-24 06-Mar-24 4 193
GR-CON-Z09-1306 Backfilling (sand / Sub base) 06-Mar-24 18-Mar-24 9 193
GR-CON-Z09-1307 Installation of Paving 18-Mar-24 07-Apr-24 13 193
Landscape Works 13-Feb-24 29-Aug-24 156 58
GR-CON-Z09-1308 Excavation (Tree Pit ) 13-Feb-24 19-Feb-24 5 158
GR-CON-Z09-1309 Aggregate Drainage layer 19-Feb-24 26-Feb-24 6 158
GR-CON-Z09-1310 Installation Geotextile 26-Feb-24 02-Mar-24 4 158
GR-CON-Z09-1311 Backfilling (Soil max for tree) 02-Mar-24 09-Mar-24 6 158
GR-CON-Z09-1312 Installation of Trees 21-Jul-24 23-Jul-24 3 58
GR-CON-Z09-11096 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11106 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-11116 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58


GR-CON-Z09-11126 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1313 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
GR-CON-Z09-1314 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58
GR-CON-Z09-1315 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1324 Garden planter box 31-Aug-24 04-Sep-24 5 58
GR-CON-Z09-1325 Wheel stoppers 05-Sep-24 10-Sep-24 5 58
GR-CON-Z09-1326 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1327 Handrail 17-Sep-24 22-Sep-24 5 58
Storm Piping Works 16-Sep-24 22-Sep-24 6 58
GR-CON-Z09-1328 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 07-Feb-24 21-Apr-24 53 180
GR-CON-Z09-1316 Excavation Pipe Irrigation 07-Feb-24 13-Feb-24 5 121
GR-CON-Z09-1317 Sand Bedding 13-Feb-24 18-Feb-24 4 121
GR-CON-Z09-1318 HDPE Pipe Installations and fittings and conduit for cable 18-Feb-24 06-Mar-24 15 121
GR-CON-Z09-1320 Test pressure 06-Mar-24 12-Mar-24 5 121
GR-CON-Z09-1319 Installation of Valves and Accessories 12-Mar-24 18-Mar-24 4 121
GR-CON-Z09-1321 Back filling (sand / Subbase ) 18-Mar-24 27-Mar-24 6 121
GR-CON-Z09-1322 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-Mar-24 06-Apr-24 6 180
GR-CON-Z09-1323 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Apr-24
system 21-Apr-24 8 180
Electrical Works 13-Feb-24 22-Sep-24 176 58
GR-CON-Z09-1329 Excavation And Disposal 13-Feb-24 19-Feb-24 5 207
GR-CON-Z09-1330 Sand Bedding 19-Feb-24 24-Feb-24 4 207
GR-CON-Z09-1331 laying cables 24-Feb-24 28-Feb-24 4 207
GR-CON-Z09-1332 Backfilling (sand / Sub base) 28-Feb-24 05-Mar-24 5 207
GR-CON-Z09-1333 Control Panel / Distribution Panel Installation 05-Mar-24 10-Mar-24 4 207
GR-CON-Z09-1334 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
Street SS-45 20-Feb-24 22-Sep-24 170 58
Site Preparation 20-Feb-24 17-Mar-24 21 207
GR-CON-Z09-1335 Demolition (Asphalt.Paving,etc.....) 20-Feb-24 25-Feb-24 4 101
GR-CON-Z09-1336 Excavation And Disposal 25-Feb-24 02-Mar-24 5 101
GR-CON-Z09-1337 Prepretion And Compaction 02-Mar-24 09-Mar-24 6 207
GR-CON-Z09-1338 Backfilling 09-Mar-24 17-Mar-24 6 207
Curbstone and Paving 02-Mar-24 06-May-24 46 173
GR-CON-Z09-1339 Excavation Curbstone 02-Mar-24 07-Mar-24 5 138
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1340 Plain Concrete 07-Mar-24 14-Mar-24 6 173


GR-CON-Z09-1341 Installation Curbstone 16-Mar-24 28-Mar-24 9 173
GR-CON-Z09-1342 Casting Concrete (Mortar haunch) 30-Mar-24 04-Apr-24 4 173
GR-CON-Z09-1343 Backfilling (sand / Sub base) 04-Apr-24 21-Apr-24 9 173
GR-CON-Z09-1344 Installation of Paving 22-Apr-24 06-May-24 13 173
Landscape Works 07-Mar-24 29-Aug-24 136 58
GR-CON-Z09-1345 Excavation (Tree Pit ) 07-Mar-24 13-Mar-24 5 138
GR-CON-Z09-1346 Aggregate Drainage layer 13-Mar-24 23-Mar-24 6 138
GR-CON-Z09-1347 Installation Geotextile 23-Mar-24 28-Mar-24 4 138
GR-CON-Z09-1348 Backfilling (Soil max for tree) 30-Mar-24 07-Apr-24 6 138
GR-CON-Z09-1349 Installation of Trees 21-Jul-24 23-Jul-24 3 58
GR-CON-Z09-11136 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11146 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
GR-CON-Z09-11156 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58
GR-CON-Z09-11166 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1350 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
GR-CON-Z09-1351 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58
GR-CON-Z09-1352 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1361 Garden planter box 31-Aug-24 04-Sep-24 5 58
GR-CON-Z09-1362 Wheel stoppers 05-Sep-24 10-Sep-24 5 58
GR-CON-Z09-1363 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1364 Handrail 17-Sep-24 22-Sep-24 5 58
Storm Piping Works 16-Sep-24 22-Sep-24 6 58
GR-CON-Z09-1365 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 02-Mar-24 14-May-24 53 160
GR-CON-Z09-1353 Excavation Pipe Irrigation 02-Mar-24 07-Mar-24 5 101
GR-CON-Z09-1354 Sand Bedding 07-Mar-24 12-Mar-24 4 101
GR-CON-Z09-1355 HDPE Pipe Installations and fittings and conduit for cable 12-Mar-24 04-Apr-24 15 101
GR-CON-Z09-1357 Test pressure 04-Apr-24 11-Apr-24 5 101
GR-CON-Z09-1356 Installation of Valves and Accessories 17-Apr-24 21-Apr-24 4 101
GR-CON-Z09-1358 Back filling (sand / Subbase ) 22-Apr-24 28-Apr-24 6 101
GR-CON-Z09-1359 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Apr-24 05-May-24 6 160
GR-CON-Z09-1360 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-May-24
system 14-May-24 8 160
Electrical Works 07-Mar-24 22-Sep-24 156 58
GR-CON-Z09-1366 Excavation And Disposal 07-Mar-24 13-Mar-24 5 187
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1367 Sand Bedding 13-Mar-24 19-Mar-24 4 187


GR-CON-Z09-1368 laying cables 20-Mar-24 26-Mar-24 4 187
GR-CON-Z09-1369 Backfilling (sand / Sub base) 26-Mar-24 02-Apr-24 5 187
GR-CON-Z09-1370 Control Panel / Distribution Panel Installation 03-Apr-24 09-Apr-24 4 187
GR-CON-Z09-1371 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
Street SS-50 25-Feb-24 22-Sep-24 166 58
Site Preparation 25-Feb-24 23-Mar-24 21 203
GR-CON-Z09-1409 Demolition (Asphalt.Paving,etc.....) 25-Feb-24 29-Feb-24 4 97
GR-CON-Z09-1410 Excavation And Disposal 29-Feb-24 06-Mar-24 5 97
GR-CON-Z09-1411 Prepretion And Compaction 06-Mar-24 13-Mar-24 6 203
GR-CON-Z09-1412 Backfilling 13-Mar-24 23-Mar-24 6 203
Curbstone and Paving 06-Mar-24 11-May-24 46 169
GR-CON-Z09-1413 Excavation Curbstone 06-Mar-24 12-Mar-24 5 134
GR-CON-Z09-1414 Plain Concrete 12-Mar-24 21-Mar-24 6 169
GR-CON-Z09-1415 Installation Curbstone 21-Mar-24 04-Apr-24 9 169
GR-CON-Z09-1416 Casting Concrete (Mortar haunch) 04-Apr-24 10-Apr-24 4 169
GR-CON-Z09-1417 Backfilling (sand / Sub base) 10-Apr-24 25-Apr-24 9 169
GR-CON-Z09-1418 Installation of Paving 27-Apr-24 11-May-24 13 169
Landscape Works 12-Mar-24 29-Aug-24 132 58
GR-CON-Z09-1419 Excavation (Tree Pit ) 12-Mar-24 19-Mar-24 5 134
GR-CON-Z09-1420 Aggregate Drainage layer 20-Mar-24 28-Mar-24 6 134
GR-CON-Z09-1421 Installation Geotextile 30-Mar-24 04-Apr-24 4 134
GR-CON-Z09-1422 Backfilling (Soil max for tree) 04-Apr-24 17-Apr-24 6 134
GR-CON-Z09-1423 Installation of Trees 21-Jul-24 23-Jul-24 3 58
GR-CON-Z09-11216 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11226 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
GR-CON-Z09-11236 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58
GR-CON-Z09-11246 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1424 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
GR-CON-Z09-1425 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58
GR-CON-Z09-1426 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1435 Garden planter box 31-Aug-24 04-Sep-24 5 58
GR-CON-Z09-1436 Wheel stoppers 05-Sep-24 10-Sep-24 5 58
GR-CON-Z09-1437 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1438 Handrail 17-Sep-24 22-Sep-24 5 58
Activity ID Activity Name Start Finish Original Total Float
Duration

Storm Piping Works 16-Sep-24 22-Sep-24 6 58


GR-CON-Z09-1439 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 06-Mar-24 19-May-24 53 156
GR-CON-Z09-1427 Excavation Pipe Irrigation 06-Mar-24 12-Mar-24 5 97
GR-CON-Z09-1428 Sand Bedding 12-Mar-24 18-Mar-24 4 97
GR-CON-Z09-1429 HDPE Pipe Installations and fittings and conduit for cable 18-Mar-24 10-Apr-24 15 97
GR-CON-Z09-1431 Test pressure 10-Apr-24 21-Apr-24 5 97
GR-CON-Z09-1430 Installation of Valves and Accessories 22-Apr-24 25-Apr-24 4 97
GR-CON-Z09-1432 Back filling (sand / Subbase ) 27-Apr-24 02-May-24 6 97
GR-CON-Z09-1433 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-May-24 09-May-24 6 156
GR-CON-Z09-1434 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
11-May-24
system 19-May-24 8 156
Electrical Works 12-Mar-24 22-Sep-24 152 58
GR-CON-Z09-1440 Excavation And Disposal 12-Mar-24 19-Mar-24 5 183
GR-CON-Z09-1441 Sand Bedding 20-Mar-24 26-Mar-24 4 183
GR-CON-Z09-1442 laying cables 26-Mar-24 01-Apr-24 4 183
GR-CON-Z09-1443 Backfilling (sand / Sub base) 01-Apr-24 09-Apr-24 5 183
GR-CON-Z09-1444 Control Panel / Distribution Panel Installation 09-Apr-24 18-Apr-24 4 183
GR-CON-Z09-1445 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
Street SS-07 21-Mar-24 22-Sep-24 146 58
Site Preparation 21-Mar-24 24-Apr-24 21 183
GR-CON-Z09-1446 Demolition (Asphalt.Paving,etc.....) 21-Mar-24 27-Mar-24 4 77
GR-CON-Z09-1447 Excavation And Disposal 27-Mar-24 04-Apr-24 5 77
GR-CON-Z09-1448 Prepretion And Compaction 04-Apr-24 17-Apr-24 6 183
GR-CON-Z09-1449 Backfilling 18-Apr-24 24-Apr-24 6 183
Curbstone and Paving 04-Apr-24 03-Jun-24 46 149
GR-CON-Z09-1450 Excavation Curbstone 04-Apr-24 11-Apr-24 5 114
GR-CON-Z09-1451 Plain Concrete 17-Apr-24 23-Apr-24 6 149
GR-CON-Z09-1452 Installation Curbstone 24-Apr-24 04-May-24 9 149
GR-CON-Z09-1453 Casting Concrete (Mortar haunch) 05-May-24 08-May-24 4 149
GR-CON-Z09-1454 Backfilling (sand / Sub base) 09-May-24 19-May-24 9 149
GR-CON-Z09-1455 Installation of Paving 20-May-24 03-Jun-24 13 149
Landscape Works 17-Apr-24 29-Aug-24 112 58
GR-CON-Z09-1456 Excavation (Tree Pit ) 17-Apr-24 22-Apr-24 5 114
GR-CON-Z09-1457 Aggregate Drainage layer 23-Apr-24 29-Apr-24 6 114
GR-CON-Z09-1458 Installation Geotextile 30-Apr-24 04-May-24 4 114
GR-CON-Z09-1459 Backfilling (Soil max for tree) 05-May-24 11-May-24 6 114
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1460 Installation of Trees 21-Jul-24 23-Jul-24 3 58


GR-CON-Z09-11256 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11266 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
GR-CON-Z09-11276 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58
GR-CON-Z09-11286 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1461 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
GR-CON-Z09-1462 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58
GR-CON-Z09-1463 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1472 Garden planter box 31-Aug-24 04-Sep-24 5 58
GR-CON-Z09-1473 Wheel stoppers 05-Sep-24 10-Sep-24 5 58
GR-CON-Z09-1474 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1475 Handrail 17-Sep-24 22-Sep-24 5 58
Storm Piping Works 16-Sep-24 22-Sep-24 6 58
GR-CON-Z09-1476 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 04-Apr-24 11-Jun-24 53 136
GR-CON-Z09-1464 Excavation Pipe Irrigation 04-Apr-24 11-Apr-24 5 77
GR-CON-Z09-1465 Sand Bedding 17-Apr-24 21-Apr-24 4 77
GR-CON-Z09-1466 HDPE Pipe Installations and fittings and conduit for cable 22-Apr-24 08-May-24 15 77
GR-CON-Z09-1468 Test pressure 09-May-24 14-May-24 5 77
GR-CON-Z09-1467 Installation of Valves and Accessories 15-May-24 19-May-24 4 77
GR-CON-Z09-1469 Back filling (sand / Subbase ) 20-May-24 26-May-24 6 77
GR-CON-Z09-1470 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-May-24 02-Jun-24 6 136
GR-CON-Z09-1471 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jun-24
system 11-Jun-24 8 136
Electrical Works 17-Apr-24 22-Sep-24 132 58
GR-CON-Z09-1477 Excavation And Disposal 17-Apr-24 22-Apr-24 5 163
GR-CON-Z09-1478 Sand Bedding 23-Apr-24 27-Apr-24 4 163
GR-CON-Z09-1479 laying cables 28-Apr-24 01-May-24 4 163
GR-CON-Z09-1480 Backfilling (sand / Sub base) 02-May-24 07-May-24 5 163
GR-CON-Z09-1481 Control Panel / Distribution Panel Installation 08-May-24 12-May-24 4 163
GR-CON-Z09-1482 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
Street SS-78 27-Mar-24 22-Sep-24 142 58
Site Preparation 27-Mar-24 29-Apr-24 21 179
GR-CON-Z09-1520 Demolition (Asphalt.Paving,etc.....) 27-Mar-24 02-Apr-24 4 73
GR-CON-Z09-1521 Excavation And Disposal 03-Apr-24 10-Apr-24 5 73
GR-CON-Z09-1522 Prepretion And Compaction 10-Apr-24 22-Apr-24 6 179
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1523 Backfilling 23-Apr-24 29-Apr-24 6 179


Curbstone and Paving 10-Apr-24 08-Jun-24 46 145
GR-CON-Z09-1524 Excavation Curbstone 10-Apr-24 21-Apr-24 5 110
GR-CON-Z09-1525 Plain Concrete 22-Apr-24 28-Apr-24 6 145
GR-CON-Z09-1526 Installation Curbstone 29-Apr-24 08-May-24 9 145
GR-CON-Z09-1527 Casting Concrete (Mortar haunch) 09-May-24 13-May-24 4 145
GR-CON-Z09-1528 Backfilling (sand / Sub base) 14-May-24 23-May-24 9 145
GR-CON-Z09-1529 Installation of Paving 25-May-24 08-Jun-24 13 145
Landscape Works 22-Apr-24 29-Aug-24 108 58
GR-CON-Z09-1530 Excavation (Tree Pit ) 22-Apr-24 27-Apr-24 5 110
GR-CON-Z09-1531 Aggregate Drainage layer 28-Apr-24 04-May-24 6 110
GR-CON-Z09-1532 Installation Geotextile 05-May-24 08-May-24 4 110
GR-CON-Z09-1533 Backfilling (Soil max for tree) 09-May-24 15-May-24 6 110
GR-CON-Z09-1534 Installation of Trees 21-Jul-24 23-Jul-24 3 58
GR-CON-Z09-11336 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11346 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
GR-CON-Z09-11356 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58
GR-CON-Z09-11366 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1535 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
GR-CON-Z09-1536 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58
GR-CON-Z09-1537 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1546 Garden planter box 31-Aug-24 04-Sep-24 5 58
GR-CON-Z09-1547 Wheel stoppers 05-Sep-24 10-Sep-24 5 58
GR-CON-Z09-1548 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1549 Handrail 17-Sep-24 22-Sep-24 5 58
Storm Piping Works 16-Sep-24 22-Sep-24 6 58
GR-CON-Z09-1550 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 10-Apr-24 16-Jun-24 53 132
GR-CON-Z09-1538 Excavation Pipe Irrigation 10-Apr-24 21-Apr-24 5 73
GR-CON-Z09-1539 Sand Bedding 22-Apr-24 25-Apr-24 4 73
GR-CON-Z09-1540 HDPE Pipe Installations and fittings and conduit for cable 27-Apr-24 13-May-24 15 73
GR-CON-Z09-1542 Test pressure 14-May-24 19-May-24 5 73
GR-CON-Z09-1541 Installation of Valves and Accessories 20-May-24 23-May-24 4 73
GR-CON-Z09-1543 Back filling (sand / Subbase ) 25-May-24 30-May-24 6 73
GR-CON-Z09-1544 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Jun-24 06-Jun-24 6 132
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1545 Pull box , Decoders , Connecting to plots /Connection to infra irrigation


08-Jun-24
system 16-Jun-24 8 132
Electrical Works 22-Apr-24 22-Sep-24 128 58
GR-CON-Z09-1551 Excavation And Disposal 22-Apr-24 27-Apr-24 5 159
GR-CON-Z09-1552 Sand Bedding 28-Apr-24 01-May-24 4 159
GR-CON-Z09-1553 laying cables 02-May-24 06-May-24 4 159
GR-CON-Z09-1554 Backfilling (sand / Sub base) 07-May-24 12-May-24 5 159
GR-CON-Z09-1555 Control Panel / Distribution Panel Installation 13-May-24 16-May-24 4 159
GR-CON-Z09-1556 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
Street SS-79 29-Apr-24 22-Sep-24 122 58
Site Preparation 29-Apr-24 22-May-24 21 159
GR-CON-Z09-1557 Demolition (Asphalt.Paving,etc.....) 29-Apr-24 02-May-24 4 53
GR-CON-Z09-1558 Excavation And Disposal 04-May-24 08-May-24 5 53
GR-CON-Z09-1559 Prepretion And Compaction 09-May-24 15-May-24 6 159
GR-CON-Z09-1560 Backfilling 16-May-24 22-May-24 6 159
Curbstone and Paving 09-May-24 06-Jul-24 46 125
GR-CON-Z09-1561 Excavation Curbstone 09-May-24 14-May-24 5 90
GR-CON-Z09-1562 Plain Concrete 15-May-24 21-May-24 6 125
GR-CON-Z09-1563 Installation Curbstone 22-May-24 01-Jun-24 9 125
GR-CON-Z09-1564 Casting Concrete (Mortar haunch) 02-Jun-24 05-Jun-24 4 125
GR-CON-Z09-1565 Backfilling (sand / Sub base) 06-Jun-24 16-Jun-24 9 125
GR-CON-Z09-1566 Installation of Paving 17-Jun-24 06-Jul-24 13 125
Landscape Works 15-May-24 29-Aug-24 88 58
GR-CON-Z09-1567 Excavation (Tree Pit ) 15-May-24 20-May-24 5 90
GR-CON-Z09-1568 Aggregate Drainage layer 21-May-24 27-May-24 6 90
GR-CON-Z09-1569 Installation Geotextile 28-May-24 01-Jun-24 4 90
GR-CON-Z09-1570 Backfilling (Soil max for tree) 02-Jun-24 08-Jun-24 6 90
GR-CON-Z09-1571 Installation of Trees 21-Jul-24 23-Jul-24 3 58
GR-CON-Z09-11376 Installation of Shrubs 24-Jul-24 27-Jul-24 3 58
GR-CON-Z09-11386 Installation of Succulents 28-Jul-24 30-Jul-24 3 58
GR-CON-Z09-11396 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 58
GR-CON-Z09-11406 Installation of Grass 04-Aug-24 06-Aug-24 3 58
GR-CON-Z09-1572 Backfilling (Mulch) 07-Aug-24 10-Aug-24 3 58
GR-CON-Z09-1573 Natural Boulders Installation 11-Aug-24 14-Aug-24 4 58
GR-CON-Z09-1574 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Aug-24 29-Aug-24 13 58
Site Furnishing 31-Aug-24 22-Sep-24 20 58
GR-CON-Z09-1583 Garden planter box 31-Aug-24 04-Sep-24 5 58
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1584 Wheel stoppers 05-Sep-24 10-Sep-24 5 58


GR-CON-Z09-1585 Steel Lattice 11-Sep-24 16-Sep-24 5 58
GR-CON-Z09-1586 Handrail 17-Sep-24 22-Sep-24 5 58
Storm Piping Works 16-Sep-24 22-Sep-24 6 58
GR-CON-Z09-1587 Installation of DI grating covers 16-Sep-24 22-Sep-24 6 58
Irrigation Works 09-May-24 14-Jul-24 53 112
GR-CON-Z09-1575 Excavation Pipe Irrigation 09-May-24 14-May-24 5 53
GR-CON-Z09-1576 Sand Bedding 15-May-24 19-May-24 4 53
GR-CON-Z09-1577 HDPE Pipe Installations and fittings and conduit for cable 20-May-24 05-Jun-24 15 53
GR-CON-Z09-1579 Test pressure 06-Jun-24 11-Jun-24 5 53
GR-CON-Z09-1578 Installation of Valves and Accessories 12-Jun-24 16-Jun-24 4 53
GR-CON-Z09-1580 Back filling (sand / Subbase ) 17-Jun-24 27-Jun-24 6 53
GR-CON-Z09-1581 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Jun-24 04-Jul-24 6 112
GR-CON-Z09-1582 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Jul-24
system 14-Jul-24 8 112
Electrical Works 15-May-24 22-Sep-24 108 58
GR-CON-Z09-1588 Excavation And Disposal 15-May-24 20-May-24 5 139
GR-CON-Z09-1589 Sand Bedding 21-May-24 25-May-24 4 139
GR-CON-Z09-1590 laying cables 26-May-24 29-May-24 4 139
GR-CON-Z09-1591 Backfilling (sand / Sub base) 30-May-24 04-Jun-24 5 139
GR-CON-Z09-1592 Control Panel / Distribution Panel Installation 05-Jun-24 09-Jun-24 4 139
GR-CON-Z09-1593 Road Crossing Ducts 17-Sep-24 22-Sep-24 5 58
School S-05 27-May-24 17-Sep-24 94 62
Site Preparation 27-May-24 05-Jun-24 9 147
GR-CON-Z09-1197 Excavation And Disposal 27-May-24 01-Jun-24 5 34
GR-CON-Z09-1198 Prepretion And Compaction 02-Jun-24 05-Jun-24 4 147
Curbstone and Paving 02-Jun-24 21-Jul-24 39 112
GR-CON-Z09-1200 Excavation Curbstone 02-Jun-24 05-Jun-24 4 75
GR-CON-Z09-1201 Plain Concrete 06-Jun-24 11-Jun-24 5 112
GR-CON-Z09-1202 Installation Curbstone 12-Jun-24 25-Jun-24 8 112
GR-CON-Z09-1203 Casting Concrete (Mortar haunch) 26-Jun-24 29-Jun-24 3 112
GR-CON-Z09-1204 Backfilling (sand / Sub base) 30-Jun-24 06-Jul-24 6 112
GR-CON-Z09-1205 Installation of Paving 07-Jul-24 21-Jul-24 13 112
Landscape Works 06-Jun-24 05-Sep-24 75 62
GR-CON-Z09-1206 Excavation (Tree Pit ) 06-Jun-24 11-Jun-24 5 75
GR-CON-Z09-1207 Aggregate Drainage layer 12-Jun-24 18-Jun-24 6 75
GR-CON-Z09-1208 Installation Geotextile 24-Jun-24 27-Jun-24 4 75
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z09-1209 Backfilling (Soil max for tree) 29-Jun-24 04-Jul-24 6 75


GR-CON-Z09-1210 Installation of Trees 21-Jul-24 23-Jul-24 3 62
GR-CON-Z09-5536 Installation of Shrubs 24-Jul-24 27-Jul-24 3 62
GR-CON-Z09-5546 Installation of Succulents 28-Jul-24 30-Jul-24 3 62
GR-CON-Z09-5556 Installation of Ground Covers 31-Jul-24 03-Aug-24 3 62
GR-CON-Z09-5566 Installation of Climbers 04-Aug-24 06-Aug-24 3 62
GR-CON-Z09-5576 Installation of Grass 07-Aug-24 10-Aug-24 3 62
GR-CON-Z09-5586 Installation of Lawns 11-Aug-24 13-Aug-24 3 62
GR-CON-Z09-1211 Backfilling (Mulch) 14-Aug-24 17-Aug-24 3 62
GR-CON-Z09-1212 Natural Boulders Installation 18-Aug-24 21-Aug-24 4 62
GR-CON-Z09-1213 Retaining walls . Steps, forming risers, treads and edges with finishes
22-Aug-24 05-Sep-24 13 62
Site Furnishing 07-Sep-24 17-Sep-24 10 62
GR-CON-Z09-1222 Garden planter box 07-Sep-24 11-Sep-24 5 62
GR-CON-Z09-1223 Wheel stoppers 12-Sep-24 17-Sep-24 5 62
Irrigation Works 02-Jun-24 17-Sep-24 89 62
GR-CON-Z09-1214 Excavation Pipe Irrigation 02-Jun-24 06-Jun-24 5 34
GR-CON-Z09-1215 Sand Bedding 08-Jun-24 10-Jun-24 3 34
GR-CON-Z09-1216 HDPE Pipe Installations and fittings and conduit for cable 11-Jun-24 02-Jul-24 15 34
GR-CON-Z09-1218 Test pressure 03-Jul-24 08-Jul-24 5 34
GR-CON-Z09-1217 Installation of Valves and Accessories 09-Jul-24 13-Jul-24 4 34
GR-CON-Z09-1219 Back filling (sand / Subbase ) 14-Jul-24 20-Jul-24 6 34
GR-CON-Z09-1220 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Jul-24 27-Jul-24 6 99
GR-CON-Z09-1221 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
09-Sep-24
system 17-Sep-24 8 62
Zone 12 24-Oct-23 18-Nov-24 321 16
Future Neighborhood Park FNP-10 24-Oct-23 26-Sep-24 276 61
Site Preparation 24-Oct-23 15-Nov-23 20 317
GR-CON-Z12-1000 Demolition (Asphalt.Paving,etc.....) 24-Oct-23 28-Oct-23 4 22
GR-CON-Z12-1001 Excavation And Disposal 29-Oct-23 04-Nov-23 6 210
GR-CON-Z12-1002 Prepretion And Compaction 05-Nov-23 08-Nov-23 4 317
GR-CON-Z12-1003 Backfilling 09-Nov-23 15-Nov-23 6 317
Curbstone and Paving 05-Nov-23 04-Jan-24 53 274
GR-CON-Z12-1004 Excavation Curbstone 05-Nov-23 09-Nov-23 5 240
GR-CON-Z12-1005 Plain Concrete 11-Nov-23 16-Nov-23 6 274
GR-CON-Z12-1006 Installation Curbstone 18-Nov-23 27-Nov-23 9 274
GR-CON-Z12-1007 Casting Concrete (Mortar haunch) 28-Nov-23 04-Dec-23 6 274
GR-CON-Z12-1008 Backfilling (sand / Sub base) 05-Dec-23 18-Dec-23 12 274
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1009 Installation of Paving 19-Dec-23 04-Jan-24 15 274


Landscape Works 11-Nov-23 26-Sep-24 261 61
GR-CON-Z12-1010 Excavation (Tree Pit ) 11-Nov-23 15-Nov-23 5 240
GR-CON-Z12-1011 Aggregate Drainage layer 16-Nov-23 22-Nov-23 6 267
GR-CON-Z12-1012 Installation Geotextile 23-Nov-23 27-Nov-23 4 267
GR-CON-Z12-1013 Backfilling (Soil max for tree) 28-Nov-23 04-Dec-23 6 267
GR-CON-Z12-1014 Installation of Trees 18-Aug-24 19-Aug-24 2 61
GR-CON-Z12-2406 Installation of Shrubs 20-Aug-24 21-Aug-24 2 61
GR-CON-Z12-2416 Installation of Succulents 22-Aug-24 24-Aug-24 2 61
GR-CON-Z12-2426 Installation of Ground Covers 25-Aug-24 26-Aug-24 2 61
GR-CON-Z12-2436 Installation of Climbers 27-Aug-24 28-Aug-24 2 61
GR-CON-Z12-2446 Installation of Grass 29-Aug-24 31-Aug-24 2 61
GR-CON-Z12-2456 Installation of Lawns 01-Sep-24 02-Sep-24 2 61
GR-CON-Z12-1015 Backfilling (Mulch) 03-Sep-24 05-Sep-24 3 61
GR-CON-Z12-1016 Natural Boulders Installation 07-Sep-24 10-Sep-24 4 61
GR-CON-Z12-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
11-Sep-24 26-Sep-24 13 61
MUGA 16-Nov-23 26-Sep-24 256 61
GR-CON-Z12-1018 Excavation And Disposal 16-Nov-23 21-Nov-23 5 240
GR-CON-Z12-1019 Prepretion And Compaction 22-Nov-23 28-Nov-23 6 240
GR-CON-Z12-1020 polyethylene under footings ( fence and gates) 29-Nov-23 04-Dec-23 5 240
GR-CON-Z12-1021 Blinding concrete (flooring) 05-Dec-23 10-Dec-23 5 240
GR-CON-Z12-1022 Concrete Footings ( fence and gates) 11-Dec-23 25-Dec-23 13 240
GR-CON-Z12-1023 Tools Play Installation ( basketball / football ..) 02-Jan-24 20-Jan-24 15 233
GR-CON-Z12-1024 PaintAcrylic Play Surface 20-Jan-24 04-Feb-24 13 233
GR-CON-Z12-1025 Fence (high / low) / gates Installation 09-Sep-24 26-Sep-24 15 61
Irrigation Works 05-Nov-23 26-Sep-24 266 61
GR-CON-Z12-1026 Excavation Pipe Irrigation 05-Nov-23 09-Nov-23 5 210
GR-CON-Z12-1027 Sand Bedding 11-Nov-23 13-Nov-23 3 210
GR-CON-Z12-1028 HDPE Pipe Installations and fittings and conduit for cable 14-Nov-23 30-Nov-23 15 210
GR-CON-Z12-1030 Test pressure 02-Dec-23 06-Dec-23 5 210
GR-CON-Z12-1029 Installation of Valves and Accessories 07-Dec-23 11-Dec-23 4 210
GR-CON-Z12-1031 Back filling (sand / Subbase ) 12-Dec-23 18-Dec-23 6 210
GR-CON-Z12-1032 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-Dec-23 25-Dec-23 6 275
GR-CON-Z12-1033 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Sep-24
system 26-Sep-24 8 61
Future Neighborhood Park FNP-20 29-Oct-23 26-Sep-24 272 61
Site Preparation 29-Oct-23 20-Nov-23 20 313
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1034 Demolition (Asphalt.Paving,etc.....) 29-Oct-23 01-Nov-23 4 22


GR-CON-Z12-1035 Excavation And Disposal 02-Nov-23 08-Nov-23 6 206
GR-CON-Z12-1036 Prepretion And Compaction 09-Nov-23 13-Nov-23 4 313
GR-CON-Z12-1037 Backfilling 14-Nov-23 20-Nov-23 6 313
Curbstone and Paving 09-Nov-23 06-Jan-24 50 273
GR-CON-Z12-1038 Excavation Curbstone 09-Nov-23 14-Nov-23 5 263
GR-CON-Z12-1039 Plain Concrete 15-Nov-23 21-Nov-23 6 273
GR-CON-Z12-1040 Installation Curbstone 22-Nov-23 05-Dec-23 12 273
GR-CON-Z12-1041 Casting Concrete (Mortar haunch) 06-Dec-23 11-Dec-23 5 273
GR-CON-Z12-1042 Backfilling (sand / Sub base) 12-Dec-23 21-Dec-23 9 273
GR-CON-Z12-1043 Installation of Paving 23-Dec-23 06-Jan-24 13 273
Landscape Works 15-Nov-23 26-Sep-24 257 61
GR-CON-Z12-1044 Excavation (Tree Pit ) 15-Nov-23 20-Nov-23 5 263
GR-CON-Z12-1045 Aggregate Drainage layer 21-Nov-23 27-Nov-23 6 263
GR-CON-Z12-1046 Installation Geotextile 28-Nov-23 02-Dec-23 4 263
GR-CON-Z12-1047 Backfilling (Soil max for tree) 03-Dec-23 09-Dec-23 6 263
GR-CON-Z12-1048 Installation of Trees 18-Aug-24 19-Aug-24 2 61
GR-CON-Z12-2466 Installation of Shrubs 20-Aug-24 21-Aug-24 2 61
GR-CON-Z12-2476 Installation of Succulents 22-Aug-24 24-Aug-24 2 61
GR-CON-Z12-2486 Installation of Ground Covers 25-Aug-24 26-Aug-24 2 61
GR-CON-Z12-2496 Installation of Climbers 27-Aug-24 28-Aug-24 2 61
GR-CON-Z12-2506 Installation of Grass 29-Aug-24 31-Aug-24 2 61
GR-CON-Z12-2516 Installation of Lawns 01-Sep-24 02-Sep-24 2 61
GR-CON-Z12-1049 Backfilling (Mulch) 03-Sep-24 05-Sep-24 3 61
GR-CON-Z12-1050 Natural Boulders Installation 07-Sep-24 10-Sep-24 4 61
GR-CON-Z12-1051 Retaining walls . Steps, forming risers, treads and edges with finishes
11-Sep-24 26-Sep-24 13 61
Irrigation Works 09-Nov-23 26-Sep-24 262 61
GR-CON-Z12-1052 Excavation Pipe Irrigation 09-Nov-23 14-Nov-23 5 206
GR-CON-Z12-1053 Sand Bedding 15-Nov-23 18-Nov-23 3 206
GR-CON-Z12-1054 HDPE Pipe Installations and fittings and conduit for cable 19-Nov-23 05-Dec-23 15 206
GR-CON-Z12-1056 Test pressure 06-Dec-23 11-Dec-23 5 206
GR-CON-Z12-1055 Installation of Valves and Accessories 12-Dec-23 16-Dec-23 4 206
GR-CON-Z12-1057 Back filling (sand / Subbase ) 17-Dec-23 23-Dec-23 6 206
GR-CON-Z12-1058 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Dec-23 30-Dec-23 6 271
GR-CON-Z12-1059 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Sep-24
system 26-Sep-24 8 61
Mosque M-18 02-Nov-23 30-Oct-24 297 32
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 02-Nov-23 23-Nov-23 19 288


GR-CON-Z12-1060 Demolition (Asphalt.Paving,etc.....) 02-Nov-23 06-Nov-23 4 22
GR-CON-Z12-1061 Excavation And Disposal 07-Nov-23 12-Nov-23 5 203
GR-CON-Z12-1062 Prepretion And Compaction 13-Nov-23 16-Nov-23 4 288
GR-CON-Z12-1063 Backfilling 18-Nov-23 23-Nov-23 6 288
Curbstone and Paving 25-Nov-23 19-Dec-23 22 288
GR-CON-Z12-1068 Backfilling (sand / Sub base) 25-Nov-23 04-Dec-23 9 288
GR-CON-Z12-1069 Installation of Paving 05-Dec-23 19-Dec-23 13 288
Landscape Works 13-Nov-23 30-Oct-24 288 32
GR-CON-Z12-1070 Excavation (Tree Pit ) 13-Nov-23 18-Nov-23 5 236
GR-CON-Z12-1071 Aggregate Drainage layer 19-Nov-23 25-Nov-23 6 236
GR-CON-Z12-1072 Installation Geotextile 26-Nov-23 30-Nov-23 5 236
GR-CON-Z12-1073 Backfilling (Soil max for tree) 02-Dec-23 06-Dec-23 5 236
GR-CON-Z12-1074 Installation of Trees 18-Aug-24 21-Aug-24 4 32
GR-CON-Z12-4146 Installation of Climbers 22-Aug-24 26-Aug-24 4 32
GR-CON-Z12-4156 Installation of Shrubs 27-Aug-24 31-Aug-24 4 32
GR-CON-Z12-4166 Installation of Succulents 01-Sep-24 04-Sep-24 4 32
GR-CON-Z12-4176 Installation of Ground Covers 05-Sep-24 09-Sep-24 4 32
GR-CON-Z12-1075 Backfilling (Mulch) 10-Sep-24 28-Sep-24 15 32
GR-CON-Z12-1076 Natural Boulders Installation 29-Sep-24 13-Oct-24 13 32
GR-CON-Z12-1077 Retaining walls . Steps, forming risers, treads and edges with finishes
14-Oct-24 30-Oct-24 15 32
Irrigation Works 13-Nov-23 30-Oct-24 288 32
GR-CON-Z12-1078 Excavation Pipe Irrigation 13-Nov-23 18-Nov-23 5 203
GR-CON-Z12-1079 Sand Bedding 19-Nov-23 21-Nov-23 3 203
GR-CON-Z12-1080 HDPE Pipe Installations and fittings and conduit for cable 22-Nov-23 09-Dec-23 15 203
GR-CON-Z12-1082 Test pressure 10-Dec-23 14-Dec-23 5 203
GR-CON-Z12-1081 Installation of Valves and Accessories 16-Dec-23 19-Dec-23 4 203
GR-CON-Z12-1083 Back filling (sand / Subbase ) 20-Dec-23 26-Dec-23 6 203
GR-CON-Z12-1084 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-Dec-23 02-Jan-24 6 270
GR-CON-Z12-1085 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Oct-24
system 30-Oct-24 6 32
Mosque M-19 07-Nov-23 30-Oct-24 293 32
Site Preparation 07-Nov-23 28-Nov-23 19 284
GR-CON-Z12-1086 Demolition (Asphalt.Paving,etc.....) 07-Nov-23 11-Nov-23 4 124
GR-CON-Z12-1087 Excavation And Disposal 12-Nov-23 16-Nov-23 5 199
GR-CON-Z12-1088 Prepretion And Compaction 18-Nov-23 21-Nov-23 4 284
GR-CON-Z12-1089 Backfilling 22-Nov-23 28-Nov-23 6 284
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 29-Nov-23 24-Dec-23 22 284


GR-CON-Z12-1094 Backfilling (sand / Sub base) 29-Nov-23 09-Dec-23 9 284
GR-CON-Z12-1095 Installation of Paving 10-Dec-23 24-Dec-23 13 284
Landscape Works 18-Nov-23 30-Oct-24 284 32
GR-CON-Z12-1096 Excavation (Tree Pit ) 18-Nov-23 22-Nov-23 5 232
GR-CON-Z12-1097 Aggregate Drainage layer 23-Nov-23 29-Nov-23 6 232
GR-CON-Z12-1098 Installation Geotextile 30-Nov-23 05-Dec-23 5 232
GR-CON-Z12-1099 Backfilling (Soil max for tree) 06-Dec-23 11-Dec-23 5 232
GR-CON-Z12-1100 Installation of Trees 18-Aug-24 21-Aug-24 4 32
GR-CON-Z12-4186 Installation of Climbers 22-Aug-24 26-Aug-24 4 32
GR-CON-Z12-4196 Installation of Shrubs 27-Aug-24 31-Aug-24 4 32
GR-CON-Z12-4206 Installation of Succulents 01-Sep-24 04-Sep-24 4 32
GR-CON-Z12-4216 Installation of Ground Covers 05-Sep-24 09-Sep-24 4 32
GR-CON-Z12-1101 Backfilling (Mulch) 10-Sep-24 28-Sep-24 15 32
GR-CON-Z12-1102 Natural Boulders Installation 29-Sep-24 13-Oct-24 13 32
GR-CON-Z12-1103 Retaining walls . Steps, forming risers, treads and edges with finishes
14-Oct-24 30-Oct-24 15 32
Irrigation Works 18-Nov-23 30-Oct-24 284 32
GR-CON-Z12-1104 Excavation Pipe Irrigation 18-Nov-23 22-Nov-23 5 199
GR-CON-Z12-1105 Sand Bedding 23-Nov-23 26-Nov-23 3 199
GR-CON-Z12-1106 HDPE Pipe Installations and fittings and conduit for cable 27-Nov-23 13-Dec-23 15 199
GR-CON-Z12-1108 Test pressure 14-Dec-23 19-Dec-23 5 199
GR-CON-Z12-1107 Installation of Valves and Accessories 20-Dec-23 24-Dec-23 4 199
GR-CON-Z12-1109 Back filling (sand / Subbase ) 25-Dec-23 31-Dec-23 6 199
GR-CON-Z12-1110 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Jan-24 07-Jan-24 6 266
GR-CON-Z12-1111 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Oct-24
system 30-Oct-24 6 32
Mosque M-06 12-Nov-23 30-Oct-24 289 32
Site Preparation 12-Nov-23 03-Dec-23 19 280
GR-CON-Z12-1138 Demolition (Asphalt.Paving,etc.....) 12-Nov-23 15-Nov-23 4 124
GR-CON-Z12-1139 Excavation And Disposal 16-Nov-23 21-Nov-23 5 195
GR-CON-Z12-1140 Prepretion And Compaction 22-Nov-23 26-Nov-23 4 280
GR-CON-Z12-1141 Backfilling 27-Nov-23 03-Dec-23 6 280
Curbstone and Paving 04-Dec-23 28-Dec-23 22 280
GR-CON-Z12-1146 Backfilling (sand / Sub base) 04-Dec-23 13-Dec-23 9 280
GR-CON-Z12-1147 Installation of Paving 14-Dec-23 28-Dec-23 13 280
Landscape Works 22-Nov-23 30-Oct-24 280 32
GR-CON-Z12-1148 Excavation (Tree Pit ) 22-Nov-23 27-Nov-23 5 228
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1149 Aggregate Drainage layer 28-Nov-23 04-Dec-23 6 228


GR-CON-Z12-1150 Installation Geotextile 05-Dec-23 10-Dec-23 5 228
GR-CON-Z12-1151 Backfilling (Soil max for tree) 11-Dec-23 16-Dec-23 5 228
GR-CON-Z12-1152 Installation of Trees 18-Aug-24 21-Aug-24 4 32
GR-CON-Z12-4266 Installation of Climbers 22-Aug-24 26-Aug-24 4 32
GR-CON-Z12-4276 Installation of Shrubs 27-Aug-24 31-Aug-24 4 32
GR-CON-Z12-4286 Installation of Succulents 01-Sep-24 04-Sep-24 4 32
GR-CON-Z12-4296 Installation of Ground Covers 05-Sep-24 09-Sep-24 4 32
GR-CON-Z12-1153 Backfilling (Mulch) 10-Sep-24 28-Sep-24 15 32
GR-CON-Z12-1154 Natural Boulders Installation 29-Sep-24 13-Oct-24 13 32
GR-CON-Z12-1155 Retaining walls . Steps, forming risers, treads and edges with finishes
14-Oct-24 30-Oct-24 15 32
Irrigation Works 22-Nov-23 30-Oct-24 280 32
GR-CON-Z12-1156 Excavation Pipe Irrigation 22-Nov-23 27-Nov-23 5 195
GR-CON-Z12-1157 Sand Bedding 28-Nov-23 30-Nov-23 3 195
GR-CON-Z12-1158 HDPE Pipe Installations and fittings and conduit for cable 02-Dec-23 18-Dec-23 15 195
GR-CON-Z12-1160 Test pressure 19-Dec-23 24-Dec-23 5 195
GR-CON-Z12-1159 Installation of Valves and Accessories 25-Dec-23 28-Dec-23 4 195
GR-CON-Z12-1161 Back filling (sand / Subbase ) 30-Dec-23 04-Jan-24 6 195
GR-CON-Z12-1162 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Jan-24 11-Jan-24 6 262
GR-CON-Z12-1163 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Oct-24
system 30-Oct-24 6 32
Mosque M-20 16-Nov-23 30-Oct-24 285 32
Site Preparation 16-Nov-23 07-Dec-23 19 276
GR-CON-Z12-1112 Demolition (Asphalt.Paving,etc.....) 16-Nov-23 20-Nov-23 4 124
GR-CON-Z12-1113 Excavation And Disposal 21-Nov-23 26-Nov-23 5 191
GR-CON-Z12-1114 Prepretion And Compaction 27-Nov-23 30-Nov-23 4 276
GR-CON-Z12-1115 Backfilling 02-Dec-23 07-Dec-23 6 276
Curbstone and Paving 09-Dec-23 02-Jan-24 22 276
GR-CON-Z12-1120 Backfilling (sand / Sub base) 09-Dec-23 18-Dec-23 9 276
GR-CON-Z12-1121 Installation of Paving 19-Dec-23 02-Jan-24 13 276
Landscape Works 27-Nov-23 30-Oct-24 276 32
GR-CON-Z12-1122 Excavation (Tree Pit ) 27-Nov-23 02-Dec-23 5 224
GR-CON-Z12-1123 Aggregate Drainage layer 03-Dec-23 09-Dec-23 6 224
GR-CON-Z12-1124 Installation Geotextile 10-Dec-23 14-Dec-23 5 224
GR-CON-Z12-1125 Backfilling (Soil max for tree) 16-Dec-23 20-Dec-23 5 224
GR-CON-Z12-1126 Installation of Trees 18-Aug-24 21-Aug-24 4 32
GR-CON-Z12-4226 Installation of Climbers 22-Aug-24 26-Aug-24 4 32
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-4236 Installation of Shrubs 27-Aug-24 31-Aug-24 4 32


GR-CON-Z12-4246 Installation of Succulents 01-Sep-24 04-Sep-24 4 32
GR-CON-Z12-4256 Installation of Ground Covers 05-Sep-24 09-Sep-24 4 32
GR-CON-Z12-1127 Backfilling (Mulch) 10-Sep-24 28-Sep-24 15 32
GR-CON-Z12-1128 Natural Boulders Installation 29-Sep-24 13-Oct-24 13 32
GR-CON-Z12-1129 Retaining walls . Steps, forming risers, treads and edges with finishes
14-Oct-24 30-Oct-24 15 32
Irrigation Works 27-Nov-23 30-Oct-24 276 32
GR-CON-Z12-1130 Excavation Pipe Irrigation 27-Nov-23 02-Dec-23 5 191
GR-CON-Z12-1131 Sand Bedding 03-Dec-23 05-Dec-23 3 191
GR-CON-Z12-1132 HDPE Pipe Installations and fittings and conduit for cable 06-Dec-23 23-Dec-23 15 191
GR-CON-Z12-1134 Test pressure 24-Dec-23 28-Dec-23 5 191
GR-CON-Z12-1133 Installation of Valves and Accessories 30-Dec-23 02-Jan-24 4 191
GR-CON-Z12-1135 Back filling (sand / Subbase ) 03-Jan-24 09-Jan-24 6 191
GR-CON-Z12-1136 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Jan-24 16-Jan-24 6 258
GR-CON-Z12-1137 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Oct-24
system 30-Oct-24 6 32
Parking P-04 19-Nov-23 18-Sep-24 248 67
Site Preparation 19-Nov-23 25-Nov-23 6 296
GR-CON-Z12-1167 Backfilling 19-Nov-23 25-Nov-23 6 296
GR-CON-Z12-1165 Excavation And Disposal 20-Nov-23 25-Nov-23 5 192
GR-CON-Z12-1164 Demolition (Asphalt.Paving,etc.....) 21-Nov-23 25-Nov-23 4 124
GR-CON-Z12-1166 Prepretion And Compaction 21-Nov-23 25-Nov-23 4 296
Curbstone and Paving 26-Nov-23 17-Jan-24 46 263
GR-CON-Z12-1168 Excavation Curbstone 26-Nov-23 30-Nov-23 5 255
GR-CON-Z12-1169 Plain Concrete 02-Dec-23 07-Dec-23 6 263
GR-CON-Z12-1170 Installation Curbstone 09-Dec-23 18-Dec-23 9 263
GR-CON-Z12-1171 Casting Concrete (Mortar haunch) 19-Dec-23 23-Dec-23 4 263
GR-CON-Z12-1172 Backfilling (sand / Sub base) 24-Dec-23 02-Jan-24 9 263
GR-CON-Z12-1173 Installation of Paving 03-Jan-24 17-Jan-24 13 263
Landscape Works 02-Dec-23 07-Sep-24 227 67
GR-CON-Z12-1174 Excavation (Tree Pit ) 02-Dec-23 06-Dec-23 5 255
GR-CON-Z12-1175 Aggregate Drainage layer 07-Dec-23 13-Dec-23 6 255
GR-CON-Z12-1176 Installation Geotextile 14-Dec-23 18-Dec-23 4 255
GR-CON-Z12-1177 Backfilling (Soil max for tree) 19-Dec-23 25-Dec-23 6 255
GR-CON-Z12-1178 Installation of Trees 18-Aug-24 20-Aug-24 3 67
GR-CON-Z12-7856 Installation of Shrubs 21-Aug-24 24-Aug-24 3 67
GR-CON-Z12-7866 Installation of Ground Covers 25-Aug-24 27-Aug-24 3 67
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-7876 Installation of Succulents 28-Aug-24 31-Aug-24 3 67


GR-CON-Z12-7886 Installation of Grass 01-Sep-24 03-Sep-24 3 67
GR-CON-Z12-1179 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 67
Site Furnishing 08-Sep-24 18-Sep-24 10 67
GR-CON-Z12-1190 Tree Grate 08-Sep-24 12-Sep-24 5 67
GR-CON-Z12-1191 Wheel stoppers 14-Sep-24 18-Sep-24 5 67
Irrigation Works 26-Nov-23 18-Sep-24 242 67
GR-CON-Z12-1182 Excavation Pipe Irrigation 26-Nov-23 30-Nov-23 5 192
GR-CON-Z12-1183 Sand Bedding 02-Dec-23 04-Dec-23 3 192
GR-CON-Z12-1184 HDPE Pipe Installations and fittings and conduit for cable 05-Dec-23 21-Dec-23 15 192
GR-CON-Z12-1186 Test pressure 23-Dec-23 27-Dec-23 5 192
GR-CON-Z12-1185 Installation of Valves and Accessories 28-Dec-23 01-Jan-24 4 192
GR-CON-Z12-1187 Back filling (sand / Subbase ) 02-Jan-24 08-Jan-24 6 192
GR-CON-Z12-1188 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Jan-24 15-Jan-24 6 257
GR-CON-Z12-1189 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Sep-24
system 18-Sep-24 8 67
Parking P-44 23-Nov-23 18-Sep-24 244 67
Site Preparation 23-Nov-23 29-Nov-23 6 292
GR-CON-Z12-1195 Backfilling 23-Nov-23 29-Nov-23 6 292
GR-CON-Z12-1193 Excavation And Disposal 25-Nov-23 29-Nov-23 5 188
GR-CON-Z12-1192 Demolition (Asphalt.Paving,etc.....) 26-Nov-23 29-Nov-23 4 124
GR-CON-Z12-1194 Prepretion And Compaction 26-Nov-23 29-Nov-23 4 292
Curbstone and Paving 30-Nov-23 22-Jan-24 46 259
GR-CON-Z12-1196 Excavation Curbstone 30-Nov-23 05-Dec-23 5 251
GR-CON-Z12-1197 Plain Concrete 06-Dec-23 12-Dec-23 6 259
GR-CON-Z12-1198 Installation Curbstone 13-Dec-23 23-Dec-23 9 259
GR-CON-Z12-1199 Casting Concrete (Mortar haunch) 24-Dec-23 27-Dec-23 4 259
GR-CON-Z12-1200 Backfilling (sand / Sub base) 28-Dec-23 07-Jan-24 9 259
GR-CON-Z12-1201 Installation of Paving 08-Jan-24 22-Jan-24 13 259
Landscape Works 06-Dec-23 07-Sep-24 223 67
GR-CON-Z12-1202 Excavation (Tree Pit ) 06-Dec-23 11-Dec-23 5 251
GR-CON-Z12-1203 Aggregate Drainage layer 12-Dec-23 18-Dec-23 6 251
GR-CON-Z12-1204 Installation Geotextile 19-Dec-23 23-Dec-23 4 251
GR-CON-Z12-1205 Backfilling (Soil max for tree) 24-Dec-23 30-Dec-23 6 251
GR-CON-Z12-1206 Installation of Trees 18-Aug-24 20-Aug-24 3 67
GR-CON-Z12-7896 Installation of Shrubs 21-Aug-24 24-Aug-24 3 67
GR-CON-Z12-7906 Installation of Ground Covers 25-Aug-24 27-Aug-24 3 67
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-7916 Installation of Succulents 28-Aug-24 31-Aug-24 3 67


GR-CON-Z12-7926 Installation of Grass 01-Sep-24 03-Sep-24 3 67
GR-CON-Z12-1207 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 67
Site Furnishing 08-Sep-24 18-Sep-24 10 67
GR-CON-Z12-1218 Tree Grate 08-Sep-24 12-Sep-24 5 67
GR-CON-Z12-1219 Wheel stoppers 14-Sep-24 18-Sep-24 5 67
Irrigation Works 30-Nov-23 18-Sep-24 238 67
GR-CON-Z12-1210 Excavation Pipe Irrigation 30-Nov-23 05-Dec-23 5 188
GR-CON-Z12-1211 Sand Bedding 06-Dec-23 09-Dec-23 3 188
GR-CON-Z12-1212 HDPE Pipe Installations and fittings and conduit for cable 10-Dec-23 26-Dec-23 15 188
GR-CON-Z12-1214 Test pressure 27-Dec-23 01-Jan-24 5 188
GR-CON-Z12-1213 Installation of Valves and Accessories 02-Jan-24 06-Jan-24 4 188
GR-CON-Z12-1215 Back filling (sand / Subbase ) 07-Jan-24 13-Jan-24 6 188
GR-CON-Z12-1216 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Jan-24 20-Jan-24 6 253
GR-CON-Z12-1217 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Sep-24
system 18-Sep-24 8 67
Parking P-50 28-Nov-23 18-Sep-24 240 67
Site Preparation 28-Nov-23 04-Dec-23 6 288
GR-CON-Z12-1223 Backfilling 28-Nov-23 04-Dec-23 6 288
GR-CON-Z12-1221 Excavation And Disposal 29-Nov-23 04-Dec-23 5 184
GR-CON-Z12-1220 Demolition (Asphalt.Paving,etc.....) 30-Nov-23 04-Dec-23 4 124
GR-CON-Z12-1222 Prepretion And Compaction 30-Nov-23 04-Dec-23 4 288
Curbstone and Paving 05-Dec-23 27-Jan-24 46 255
GR-CON-Z12-1224 Excavation Curbstone 05-Dec-23 10-Dec-23 5 247
GR-CON-Z12-1225 Plain Concrete 11-Dec-23 17-Dec-23 6 255
GR-CON-Z12-1226 Installation Curbstone 18-Dec-23 27-Dec-23 9 255
GR-CON-Z12-1227 Casting Concrete (Mortar haunch) 28-Dec-23 01-Jan-24 4 255
GR-CON-Z12-1228 Backfilling (sand / Sub base) 02-Jan-24 11-Jan-24 9 255
GR-CON-Z12-1229 Installation of Paving 13-Jan-24 27-Jan-24 13 255
Landscape Works 11-Dec-23 07-Sep-24 219 67
GR-CON-Z12-1230 Excavation (Tree Pit ) 11-Dec-23 16-Dec-23 5 247
GR-CON-Z12-1231 Aggregate Drainage layer 17-Dec-23 23-Dec-23 6 247
GR-CON-Z12-1232 Installation Geotextile 24-Dec-23 27-Dec-23 4 247
GR-CON-Z12-1233 Backfilling (Soil max for tree) 28-Dec-23 03-Jan-24 6 247
GR-CON-Z12-1234 Installation of Trees 18-Aug-24 20-Aug-24 3 67
GR-CON-Z12-7936 Installation of Shrubs 21-Aug-24 24-Aug-24 3 67
GR-CON-Z12-7946 Installation of Ground Covers 25-Aug-24 27-Aug-24 3 67
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-7956 Installation of Succulents 28-Aug-24 31-Aug-24 3 67


GR-CON-Z12-7966 Installation of Grass 01-Sep-24 03-Sep-24 3 67
GR-CON-Z12-1235 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 67
Site Furnishing 08-Sep-24 18-Sep-24 10 67
GR-CON-Z12-1246 Tree Grate 08-Sep-24 12-Sep-24 5 67
GR-CON-Z12-1247 Wheel stoppers 14-Sep-24 18-Sep-24 5 67
Irrigation Works 05-Dec-23 18-Sep-24 234 67
GR-CON-Z12-1238 Excavation Pipe Irrigation 05-Dec-23 10-Dec-23 5 184
GR-CON-Z12-1239 Sand Bedding 11-Dec-23 13-Dec-23 3 184
GR-CON-Z12-1240 HDPE Pipe Installations and fittings and conduit for cable 14-Dec-23 31-Dec-23 15 184
GR-CON-Z12-1242 Test pressure 01-Jan-24 06-Jan-24 5 184
GR-CON-Z12-1241 Installation of Valves and Accessories 07-Jan-24 10-Jan-24 4 184
GR-CON-Z12-1243 Back filling (sand / Subbase ) 11-Jan-24 17-Jan-24 6 184
GR-CON-Z12-1244 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Jan-24 24-Jan-24 6 249
GR-CON-Z12-1245 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Sep-24
system 18-Sep-24 8 67
Street SS-18 21-Dec-23 21-Oct-24 246 40
Site Preparation 21-Dec-23 15-Jan-24 21 265
GR-CON-Z12-1276 Demolition (Asphalt.Paving,etc.....) 21-Dec-23 26-Dec-23 4 109
GR-CON-Z12-1277 Excavation And Disposal 26-Dec-23 01-Jan-24 5 159
GR-CON-Z12-1278 Prepretion And Compaction 01-Jan-24 08-Jan-24 6 265
GR-CON-Z12-1279 Backfilling 08-Jan-24 15-Jan-24 6 265
Curbstone and Paving 01-Jan-24 24-Feb-24 46 231
GR-CON-Z12-1280 Excavation Curbstone 01-Jan-24 07-Jan-24 5 196
GR-CON-Z12-1281 Plain Concrete 07-Jan-24 14-Jan-24 6 231
GR-CON-Z12-1282 Installation Curbstone 14-Jan-24 24-Jan-24 9 231
GR-CON-Z12-1283 Casting Concrete (Mortar haunch) 24-Jan-24 29-Jan-24 4 231
GR-CON-Z12-1284 Backfilling (sand / Sub base) 29-Jan-24 08-Feb-24 9 231
GR-CON-Z12-1285 Installation of Paving 08-Feb-24 24-Feb-24 13 231
Landscape Works 07-Jan-24 28-Sep-24 212 40
GR-CON-Z12-1286 Excavation (Tree Pit ) 07-Jan-24 13-Jan-24 5 196
GR-CON-Z12-1287 Aggregate Drainage layer 13-Jan-24 20-Jan-24 6 196
GR-CON-Z12-1288 Installation Geotextile 20-Jan-24 24-Jan-24 4 196
GR-CON-Z12-1289 Backfilling (Soil max for tree) 24-Jan-24 31-Jan-24 6 196
GR-CON-Z12-1290 Installation of Trees 18-Aug-24 20-Aug-24 3 40
GR-CON-Z12-11856 Installation of Shrubs 21-Aug-24 24-Aug-24 3 40
GR-CON-Z12-11866 Installation of Succulents 25-Aug-24 27-Aug-24 3 40
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-11876 Installation of Ground Covers 28-Aug-24 31-Aug-24 3 40


GR-CON-Z12-11886 Installation of Grass 01-Sep-24 03-Sep-24 3 40
GR-CON-Z12-1291 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 40
GR-CON-Z12-1292 Natural Boulders Installation 08-Sep-24 11-Sep-24 4 40
GR-CON-Z12-1293 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Sep-24 28-Sep-24 13 40
Site Furnishing 29-Sep-24 21-Oct-24 20 40
GR-CON-Z12-1302 Garden planter box 29-Sep-24 03-Oct-24 5 40
GR-CON-Z12-1303 Wheel stoppers 05-Oct-24 09-Oct-24 5 40
GR-CON-Z12-1304 Steel Lattice 10-Oct-24 15-Oct-24 5 40
GR-CON-Z12-1305 Handrail 16-Oct-24 21-Oct-24 5 40
Storm Piping Works 15-Oct-24 21-Oct-24 6 40
GR-CON-Z12-1306 Installation of DI grating covers 15-Oct-24 21-Oct-24 6 40
Irrigation Works 01-Jan-24 03-Mar-24 53 218
GR-CON-Z12-1294 Excavation Pipe Irrigation 01-Jan-24 07-Jan-24 5 159
GR-CON-Z12-1295 Sand Bedding 07-Jan-24 11-Jan-24 4 159
GR-CON-Z12-1296 HDPE Pipe Installations and fittings and conduit for cable 11-Jan-24 29-Jan-24 15 159
GR-CON-Z12-1298 Test pressure 29-Jan-24 04-Feb-24 5 159
GR-CON-Z12-1297 Installation of Valves and Accessories 04-Feb-24 08-Feb-24 4 159
GR-CON-Z12-1299 Back filling (sand / Subbase ) 08-Feb-24 15-Feb-24 6 159
GR-CON-Z12-1300 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Feb-24 22-Feb-24 6 218
GR-CON-Z12-1301 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-Feb-24
system 03-Mar-24 8 218
Electrical Works 07-Jan-24 21-Oct-24 232 40
GR-CON-Z12-1307 Excavation And Disposal 07-Jan-24 13-Jan-24 5 245
GR-CON-Z12-1308 Sand Bedding 13-Jan-24 17-Jan-24 4 245
GR-CON-Z12-1309 laying cables 17-Jan-24 22-Jan-24 4 245
GR-CON-Z12-1310 Backfilling (sand / Sub base) 22-Jan-24 28-Jan-24 5 245
GR-CON-Z12-1311 Control Panel / Distribution Panel Installation 28-Jan-24 01-Feb-24 4 245
GR-CON-Z12-1312 Road Crossing Ducts 16-Oct-24 21-Oct-24 5 40
Street SS-34 01-Jan-24 21-Oct-24 237 40
Site Preparation 01-Jan-24 25-Jan-24 21 256
GR-CON-Z12-1313 Demolition (Asphalt.Paving,etc.....) 01-Jan-24 06-Jan-24 4 104
GR-CON-Z12-1314 Excavation And Disposal 06-Jan-24 11-Jan-24 5 150
GR-CON-Z12-1315 Prepretion And Compaction 11-Jan-24 18-Jan-24 6 256
GR-CON-Z12-1316 Backfilling 18-Jan-24 25-Jan-24 6 256
Curbstone and Paving 11-Jan-24 05-Mar-24 46 222
GR-CON-Z12-1317 Excavation Curbstone 11-Jan-24 17-Jan-24 5 187
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1318 Plain Concrete 17-Jan-24 24-Jan-24 6 222


GR-CON-Z12-1319 Installation Curbstone 24-Jan-24 04-Feb-24 9 222
GR-CON-Z12-1320 Casting Concrete (Mortar haunch) 04-Feb-24 08-Feb-24 4 222
GR-CON-Z12-1321 Backfilling (sand / Sub base) 08-Feb-24 19-Feb-24 9 222
GR-CON-Z12-1322 Installation of Paving 19-Feb-24 05-Mar-24 13 222
Landscape Works 17-Jan-24 28-Sep-24 203 40
GR-CON-Z12-1323 Excavation (Tree Pit ) 17-Jan-24 23-Jan-24 5 187
GR-CON-Z12-1324 Aggregate Drainage layer 23-Jan-24 30-Jan-24 6 187
GR-CON-Z12-1325 Installation Geotextile 30-Jan-24 04-Feb-24 4 187
GR-CON-Z12-1326 Backfilling (Soil max for tree) 04-Feb-24 11-Feb-24 6 187
GR-CON-Z12-1327 Installation of Trees 18-Aug-24 20-Aug-24 3 40
GR-CON-Z12-11896 Installation of Shrubs 21-Aug-24 24-Aug-24 3 40
GR-CON-Z12-11906 Installation of Succulents 25-Aug-24 27-Aug-24 3 40
GR-CON-Z12-11916 Installation of Ground Covers 28-Aug-24 31-Aug-24 3 40
GR-CON-Z12-11926 Installation of Grass 01-Sep-24 03-Sep-24 3 40
GR-CON-Z12-1328 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 40
GR-CON-Z12-1329 Natural Boulders Installation 08-Sep-24 11-Sep-24 4 40
GR-CON-Z12-1330 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Sep-24 28-Sep-24 13 40
Site Furnishing 29-Sep-24 21-Oct-24 20 40
GR-CON-Z12-1339 Garden planter box 29-Sep-24 03-Oct-24 5 40
GR-CON-Z12-1340 Wheel stoppers 05-Oct-24 09-Oct-24 5 40
GR-CON-Z12-1341 Steel Lattice 10-Oct-24 15-Oct-24 5 40
GR-CON-Z12-1342 Handrail 16-Oct-24 21-Oct-24 5 40
Storm Piping Works 15-Oct-24 21-Oct-24 6 40
GR-CON-Z12-1343 Installation of DI grating covers 15-Oct-24 21-Oct-24 6 40
Irrigation Works 11-Jan-24 13-Mar-24 53 209
GR-CON-Z12-1331 Excavation Pipe Irrigation 11-Jan-24 17-Jan-24 5 150
GR-CON-Z12-1332 Sand Bedding 17-Jan-24 22-Jan-24 4 150
GR-CON-Z12-1333 HDPE Pipe Installations and fittings and conduit for cable 22-Jan-24 08-Feb-24 15 150
GR-CON-Z12-1335 Test pressure 08-Feb-24 14-Feb-24 5 150
GR-CON-Z12-1334 Installation of Valves and Accessories 14-Feb-24 19-Feb-24 4 150
GR-CON-Z12-1336 Back filling (sand / Subbase ) 19-Feb-24 26-Feb-24 6 150
GR-CON-Z12-1337 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 26-Feb-24 04-Mar-24 6 209
GR-CON-Z12-1338 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
04-Mar-24
system 13-Mar-24 8 209
Electrical Works 17-Jan-24 21-Oct-24 223 40
GR-CON-Z12-1344 Excavation And Disposal 17-Jan-24 23-Jan-24 5 236
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1345 Sand Bedding 23-Jan-24 28-Jan-24 4 236


GR-CON-Z12-1346 laying cables 28-Jan-24 01-Feb-24 4 236
GR-CON-Z12-1347 Backfilling (sand / Sub base) 01-Feb-24 07-Feb-24 5 236
GR-CON-Z12-1348 Control Panel / Distribution Panel Installation 07-Feb-24 12-Feb-24 4 236
GR-CON-Z12-1349 Road Crossing Ducts 16-Oct-24 21-Oct-24 5 40
Street SS-55 07-Jan-24 21-Oct-24 232 40
Site Preparation 07-Jan-24 31-Jan-24 21 251
GR-CON-Z12-1350 Demolition (Asphalt.Paving,etc.....) 07-Jan-24 11-Jan-24 4 103
GR-CON-Z12-1351 Excavation And Disposal 11-Jan-24 17-Jan-24 5 145
GR-CON-Z12-1352 Prepretion And Compaction 17-Jan-24 24-Jan-24 6 251
GR-CON-Z12-1353 Backfilling 24-Jan-24 31-Jan-24 6 251
Curbstone and Paving 17-Jan-24 11-Mar-24 46 217
GR-CON-Z12-1354 Excavation Curbstone 17-Jan-24 23-Jan-24 5 182
GR-CON-Z12-1355 Plain Concrete 23-Jan-24 30-Jan-24 6 217
GR-CON-Z12-1356 Installation Curbstone 30-Jan-24 10-Feb-24 9 217
GR-CON-Z12-1357 Casting Concrete (Mortar haunch) 10-Feb-24 14-Feb-24 4 217
GR-CON-Z12-1358 Backfilling (sand / Sub base) 14-Feb-24 25-Feb-24 9 217
GR-CON-Z12-1359 Installation of Paving 25-Feb-24 11-Mar-24 13 217
Landscape Works 23-Jan-24 28-Sep-24 198 40
GR-CON-Z12-1360 Excavation (Tree Pit ) 23-Jan-24 29-Jan-24 5 182
GR-CON-Z12-1361 Aggregate Drainage layer 29-Jan-24 05-Feb-24 6 182
GR-CON-Z12-1362 Installation Geotextile 05-Feb-24 10-Feb-24 4 182
GR-CON-Z12-1363 Backfilling (Soil max for tree) 10-Feb-24 17-Feb-24 6 182
GR-CON-Z12-1364 Installation of Trees 18-Aug-24 20-Aug-24 3 40
GR-CON-Z12-11936 Installation of Shrubs 21-Aug-24 24-Aug-24 3 40
GR-CON-Z12-11946 Installation of Succulents 25-Aug-24 27-Aug-24 3 40
GR-CON-Z12-11956 Installation of Ground Covers 28-Aug-24 31-Aug-24 3 40
GR-CON-Z12-11966 Installation of Grass 01-Sep-24 03-Sep-24 3 40
GR-CON-Z12-1365 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 40
GR-CON-Z12-1366 Natural Boulders Installation 08-Sep-24 11-Sep-24 4 40
GR-CON-Z12-1367 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Sep-24 28-Sep-24 13 40
Site Furnishing 29-Sep-24 21-Oct-24 20 40
GR-CON-Z12-1376 Garden planter box 29-Sep-24 03-Oct-24 5 40
GR-CON-Z12-1377 Wheel stoppers 05-Oct-24 09-Oct-24 5 40
GR-CON-Z12-1378 Steel Lattice 10-Oct-24 15-Oct-24 5 40
GR-CON-Z12-1379 Handrail 16-Oct-24 21-Oct-24 5 40
Activity ID Activity Name Start Finish Original Total Float
Duration

Storm Piping Works 15-Oct-24 21-Oct-24 6 40


GR-CON-Z12-1380 Installation of DI grating covers 15-Oct-24 21-Oct-24 6 40
Irrigation Works 17-Jan-24 20-Mar-24 53 204
GR-CON-Z12-1368 Excavation Pipe Irrigation 17-Jan-24 23-Jan-24 5 145
GR-CON-Z12-1369 Sand Bedding 23-Jan-24 28-Jan-24 4 145
GR-CON-Z12-1370 HDPE Pipe Installations and fittings and conduit for cable 28-Jan-24 14-Feb-24 15 145
GR-CON-Z12-1372 Test pressure 14-Feb-24 20-Feb-24 5 145
GR-CON-Z12-1371 Installation of Valves and Accessories 20-Feb-24 25-Feb-24 4 145
GR-CON-Z12-1373 Back filling (sand / Subbase ) 25-Feb-24 03-Mar-24 6 145
GR-CON-Z12-1374 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Mar-24 10-Mar-24 6 204
GR-CON-Z12-1375 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Mar-24
system 20-Mar-24 8 204
Electrical Works 23-Jan-24 21-Oct-24 218 40
GR-CON-Z12-1381 Excavation And Disposal 23-Jan-24 29-Jan-24 5 231
GR-CON-Z12-1382 Sand Bedding 29-Jan-24 03-Feb-24 4 231
GR-CON-Z12-1383 laying cables 03-Feb-24 07-Feb-24 4 231
GR-CON-Z12-1384 Backfilling (sand / Sub base) 07-Feb-24 13-Feb-24 5 231
GR-CON-Z12-1385 Control Panel / Distribution Panel Installation 13-Feb-24 18-Feb-24 4 231
GR-CON-Z12-1386 Road Crossing Ducts 16-Oct-24 21-Oct-24 5 40
Street SS-56 17-Jan-24 21-Oct-24 223 40
Site Preparation 17-Jan-24 11-Feb-24 21 242
GR-CON-Z12-1387 Demolition (Asphalt.Paving,etc.....) 17-Jan-24 22-Jan-24 4 98
GR-CON-Z12-1388 Excavation And Disposal 22-Jan-24 28-Jan-24 5 136
GR-CON-Z12-1389 Prepretion And Compaction 28-Jan-24 04-Feb-24 6 242
GR-CON-Z12-1390 Backfilling 04-Feb-24 11-Feb-24 6 242
Curbstone and Paving 28-Jan-24 24-Mar-24 46 208
GR-CON-Z12-1391 Excavation Curbstone 28-Jan-24 03-Feb-24 5 173
GR-CON-Z12-1392 Plain Concrete 03-Feb-24 10-Feb-24 6 208
GR-CON-Z12-1393 Installation Curbstone 10-Feb-24 20-Feb-24 9 208
GR-CON-Z12-1394 Casting Concrete (Mortar haunch) 20-Feb-24 25-Feb-24 4 208
GR-CON-Z12-1395 Backfilling (sand / Sub base) 25-Feb-24 06-Mar-24 9 208
GR-CON-Z12-1396 Installation of Paving 06-Mar-24 24-Mar-24 13 208
Landscape Works 03-Feb-24 28-Sep-24 189 40
GR-CON-Z12-1397 Excavation (Tree Pit ) 03-Feb-24 08-Feb-24 5 173
GR-CON-Z12-1398 Aggregate Drainage layer 08-Feb-24 15-Feb-24 6 173
GR-CON-Z12-1399 Installation Geotextile 15-Feb-24 20-Feb-24 4 173
GR-CON-Z12-1400 Backfilling (Soil max for tree) 20-Feb-24 27-Feb-24 6 173
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1401 Installation of Trees 18-Aug-24 20-Aug-24 3 40


GR-CON-Z12-11976 Installation of Shrubs 21-Aug-24 24-Aug-24 3 40
GR-CON-Z12-11986 Installation of Succulents 25-Aug-24 27-Aug-24 3 40
GR-CON-Z12-11996 Installation of Ground Covers 28-Aug-24 31-Aug-24 3 40
GR-CON-Z12-12006 Installation of Grass 01-Sep-24 03-Sep-24 3 40
GR-CON-Z12-1402 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 40
GR-CON-Z12-1403 Natural Boulders Installation 08-Sep-24 11-Sep-24 4 40
GR-CON-Z12-1404 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Sep-24 28-Sep-24 13 40
Site Furnishing 29-Sep-24 21-Oct-24 20 40
GR-CON-Z12-1413 Garden planter box 29-Sep-24 03-Oct-24 5 40
GR-CON-Z12-1414 Wheel stoppers 05-Oct-24 09-Oct-24 5 40
GR-CON-Z12-1415 Steel Lattice 10-Oct-24 15-Oct-24 5 40
GR-CON-Z12-1416 Handrail 16-Oct-24 21-Oct-24 5 40
Storm Piping Works 15-Oct-24 21-Oct-24 6 40
GR-CON-Z12-1417 Installation of DI grating covers 15-Oct-24 21-Oct-24 6 40
Irrigation Works 28-Jan-24 03-Apr-24 53 195
GR-CON-Z12-1405 Excavation Pipe Irrigation 28-Jan-24 03-Feb-24 5 136
GR-CON-Z12-1406 Sand Bedding 03-Feb-24 07-Feb-24 4 136
GR-CON-Z12-1407 HDPE Pipe Installations and fittings and conduit for cable 07-Feb-24 25-Feb-24 15 136
GR-CON-Z12-1409 Test pressure 25-Feb-24 02-Mar-24 5 136
GR-CON-Z12-1408 Installation of Valves and Accessories 02-Mar-24 06-Mar-24 4 136
GR-CON-Z12-1410 Back filling (sand / Subbase ) 06-Mar-24 13-Mar-24 6 136
GR-CON-Z12-1411 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Mar-24 23-Mar-24 6 195
GR-CON-Z12-1412 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-Mar-24
system 03-Apr-24 8 195
Electrical Works 03-Feb-24 21-Oct-24 209 40
GR-CON-Z12-1418 Excavation And Disposal 03-Feb-24 08-Feb-24 5 222
GR-CON-Z12-1419 Sand Bedding 08-Feb-24 13-Feb-24 4 222
GR-CON-Z12-1420 laying cables 13-Feb-24 18-Feb-24 4 222
GR-CON-Z12-1421 Backfilling (sand / Sub base) 18-Feb-24 24-Feb-24 5 222
GR-CON-Z12-1422 Control Panel / Distribution Panel Installation 24-Feb-24 28-Feb-24 4 222
GR-CON-Z12-1423 Road Crossing Ducts 16-Oct-24 21-Oct-24 5 40
Street SS-58 22-Jan-24 21-Oct-24 219 40
Site Preparation 22-Jan-24 15-Feb-24 21 238
GR-CON-Z12-1424 Demolition (Asphalt.Paving,etc.....) 22-Jan-24 27-Jan-24 4 98
GR-CON-Z12-1425 Excavation And Disposal 27-Jan-24 01-Feb-24 5 132
GR-CON-Z12-1426 Prepretion And Compaction 01-Feb-24 08-Feb-24 6 238
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1427 Backfilling 08-Feb-24 15-Feb-24 6 238


Curbstone and Paving 01-Feb-24 30-Mar-24 46 204
GR-CON-Z12-1428 Excavation Curbstone 01-Feb-24 07-Feb-24 5 169
GR-CON-Z12-1429 Plain Concrete 07-Feb-24 14-Feb-24 6 204
GR-CON-Z12-1430 Installation Curbstone 14-Feb-24 25-Feb-24 9 204
GR-CON-Z12-1431 Casting Concrete (Mortar haunch) 25-Feb-24 29-Feb-24 4 204
GR-CON-Z12-1432 Backfilling (sand / Sub base) 29-Feb-24 11-Mar-24 9 204
GR-CON-Z12-1433 Installation of Paving 11-Mar-24 30-Mar-24 13 204
Landscape Works 07-Feb-24 28-Sep-24 185 40
GR-CON-Z12-1434 Excavation (Tree Pit ) 07-Feb-24 13-Feb-24 5 169
GR-CON-Z12-1435 Aggregate Drainage layer 13-Feb-24 20-Feb-24 6 169
GR-CON-Z12-1436 Installation Geotextile 20-Feb-24 25-Feb-24 4 169
GR-CON-Z12-1437 Backfilling (Soil max for tree) 25-Feb-24 03-Mar-24 6 169
GR-CON-Z12-1438 Installation of Trees 18-Aug-24 20-Aug-24 3 40
GR-CON-Z12-12016 Installation of Shrubs 21-Aug-24 24-Aug-24 3 40
GR-CON-Z12-12026 Installation of Succulents 25-Aug-24 27-Aug-24 3 40
GR-CON-Z12-12036 Installation of Ground Covers 28-Aug-24 31-Aug-24 3 40
GR-CON-Z12-12046 Installation of Grass 01-Sep-24 03-Sep-24 3 40
GR-CON-Z12-1439 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 40
GR-CON-Z12-1440 Natural Boulders Installation 08-Sep-24 11-Sep-24 4 40
GR-CON-Z12-1441 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Sep-24 28-Sep-24 13 40
Site Furnishing 29-Sep-24 21-Oct-24 20 40
GR-CON-Z12-1450 Garden planter box 29-Sep-24 03-Oct-24 5 40
GR-CON-Z12-1451 Wheel stoppers 05-Oct-24 09-Oct-24 5 40
GR-CON-Z12-1452 Steel Lattice 10-Oct-24 15-Oct-24 5 40
GR-CON-Z12-1453 Handrail 16-Oct-24 21-Oct-24 5 40
Storm Piping Works 15-Oct-24 21-Oct-24 6 40
GR-CON-Z12-1454 Installation of DI grating covers 15-Oct-24 21-Oct-24 6 40
Irrigation Works 01-Feb-24 10-Apr-24 53 191
GR-CON-Z12-1442 Excavation Pipe Irrigation 01-Feb-24 07-Feb-24 5 132
GR-CON-Z12-1443 Sand Bedding 07-Feb-24 12-Feb-24 4 132
GR-CON-Z12-1444 HDPE Pipe Installations and fittings and conduit for cable 12-Feb-24 29-Feb-24 15 132
GR-CON-Z12-1446 Test pressure 29-Feb-24 06-Mar-24 5 132
GR-CON-Z12-1445 Installation of Valves and Accessories 06-Mar-24 11-Mar-24 4 132
GR-CON-Z12-1447 Back filling (sand / Subbase ) 11-Mar-24 19-Mar-24 6 132
GR-CON-Z12-1448 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-Mar-24 28-Mar-24 6 191
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1449 Pull box , Decoders , Connecting to plots /Connection to infra irrigation


28-Mar-24
system 10-Apr-24 8 191
Electrical Works 07-Feb-24 21-Oct-24 205 40
GR-CON-Z12-1455 Excavation And Disposal 07-Feb-24 13-Feb-24 5 218
GR-CON-Z12-1456 Sand Bedding 13-Feb-24 18-Feb-24 4 218
GR-CON-Z12-1457 laying cables 18-Feb-24 22-Feb-24 4 218
GR-CON-Z12-1458 Backfilling (sand / Sub base) 22-Feb-24 28-Feb-24 5 218
GR-CON-Z12-1459 Control Panel / Distribution Panel Installation 28-Feb-24 04-Mar-24 4 218
GR-CON-Z12-1460 Road Crossing Ducts 16-Oct-24 21-Oct-24 5 40
Street SS-07 27-Jan-24 21-Oct-24 215 40
Site Preparation 27-Jan-24 20-Feb-24 21 234
GR-CON-Z12-1461 Demolition (Asphalt.Paving,etc.....) 27-Jan-24 31-Jan-24 4 98
GR-CON-Z12-1462 Excavation And Disposal 31-Jan-24 06-Feb-24 5 128
GR-CON-Z12-1463 Prepretion And Compaction 06-Feb-24 13-Feb-24 6 234
GR-CON-Z12-1464 Backfilling 13-Feb-24 20-Feb-24 6 234
Curbstone and Paving 06-Feb-24 06-Apr-24 46 200
GR-CON-Z12-1465 Excavation Curbstone 06-Feb-24 12-Feb-24 5 165
GR-CON-Z12-1466 Plain Concrete 12-Feb-24 19-Feb-24 6 200
GR-CON-Z12-1467 Installation Curbstone 19-Feb-24 29-Feb-24 9 200
GR-CON-Z12-1468 Casting Concrete (Mortar haunch) 29-Feb-24 05-Mar-24 4 200
GR-CON-Z12-1469 Backfilling (sand / Sub base) 05-Mar-24 16-Mar-24 9 200
GR-CON-Z12-1470 Installation of Paving 17-Mar-24 06-Apr-24 13 200
Landscape Works 12-Feb-24 28-Sep-24 181 40
GR-CON-Z12-1471 Excavation (Tree Pit ) 12-Feb-24 18-Feb-24 5 165
GR-CON-Z12-1472 Aggregate Drainage layer 18-Feb-24 25-Feb-24 6 165
GR-CON-Z12-1473 Installation Geotextile 25-Feb-24 29-Feb-24 4 165
GR-CON-Z12-1474 Backfilling (Soil max for tree) 29-Feb-24 07-Mar-24 6 165
GR-CON-Z12-1475 Installation of Trees 18-Aug-24 20-Aug-24 3 40
GR-CON-Z12-12056 Installation of Shrubs 21-Aug-24 24-Aug-24 3 40
GR-CON-Z12-12066 Installation of Succulents 25-Aug-24 27-Aug-24 3 40
GR-CON-Z12-12076 Installation of Ground Covers 28-Aug-24 31-Aug-24 3 40
GR-CON-Z12-12086 Installation of Grass 01-Sep-24 03-Sep-24 3 40
GR-CON-Z12-1476 Backfilling (Mulch) 04-Sep-24 07-Sep-24 3 40
GR-CON-Z12-1477 Natural Boulders Installation 08-Sep-24 11-Sep-24 4 40
GR-CON-Z12-1478 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Sep-24 28-Sep-24 13 40
Site Furnishing 29-Sep-24 21-Oct-24 20 40
GR-CON-Z12-1487 Garden planter box 29-Sep-24 03-Oct-24 5 40
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1488 Wheel stoppers 05-Oct-24 09-Oct-24 5 40


GR-CON-Z12-1489 Steel Lattice 10-Oct-24 15-Oct-24 5 40
GR-CON-Z12-1490 Handrail 16-Oct-24 21-Oct-24 5 40
Storm Piping Works 15-Oct-24 21-Oct-24 6 40
GR-CON-Z12-1491 Installation of DI grating covers 15-Oct-24 21-Oct-24 6 40
Irrigation Works 06-Feb-24 20-Apr-24 53 187
GR-CON-Z12-1479 Excavation Pipe Irrigation 06-Feb-24 12-Feb-24 5 128
GR-CON-Z12-1480 Sand Bedding 12-Feb-24 17-Feb-24 4 128
GR-CON-Z12-1481 HDPE Pipe Installations and fittings and conduit for cable 17-Feb-24 05-Mar-24 15 128
GR-CON-Z12-1483 Test pressure 05-Mar-24 11-Mar-24 5 128
GR-CON-Z12-1482 Installation of Valves and Accessories 11-Mar-24 16-Mar-24 4 128
GR-CON-Z12-1484 Back filling (sand / Subbase ) 17-Mar-24 25-Mar-24 6 128
GR-CON-Z12-1485 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 26-Mar-24 03-Apr-24 6 187
GR-CON-Z12-1486 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
04-Apr-24
system 20-Apr-24 8 187
Electrical Works 12-Feb-24 21-Oct-24 201 40
GR-CON-Z12-1492 Excavation And Disposal 12-Feb-24 18-Feb-24 5 214
GR-CON-Z12-1493 Sand Bedding 18-Feb-24 22-Feb-24 4 214
GR-CON-Z12-1494 laying cables 22-Feb-24 27-Feb-24 4 214
GR-CON-Z12-1495 Backfilling (sand / Sub base) 27-Feb-24 04-Mar-24 5 214
GR-CON-Z12-1496 Control Panel / Distribution Panel Installation 04-Mar-24 09-Mar-24 4 214
GR-CON-Z12-1497 Road Crossing Ducts 16-Oct-24 21-Oct-24 5 40
Street SS-07.1 31-Jan-24 18-Nov-24 235 16
Site Preparation 31-Jan-24 09-Mar-24 32 219
GR-CON-Z12-1498 Demolition (Asphalt.Paving,etc.....) 31-Jan-24 07-Feb-24 6 98
GR-CON-Z12-1499 Excavation And Disposal 07-Feb-24 17-Feb-24 8 98
GR-CON-Z12-1500 Prepretion And Compaction 17-Feb-24 27-Feb-24 9 219
GR-CON-Z12-1501 Backfilling 27-Feb-24 09-Mar-24 9 219
Curbstone and Paving 17-Feb-24 21-May-24 71 166
GR-CON-Z12-1502 Excavation Curbstone 17-Feb-24 26-Feb-24 8 118
GR-CON-Z12-1503 Plain Concrete 26-Feb-24 07-Mar-24 9 166
GR-CON-Z12-1504 Installation Curbstone 07-Mar-24 27-Mar-24 14 166
GR-CON-Z12-1505 Casting Concrete (Mortar haunch) 27-Mar-24 06-Apr-24 6 166
GR-CON-Z12-1506 Backfilling (sand / Sub base) 06-Apr-24 28-Apr-24 14 166
GR-CON-Z12-1507 Installation of Paving 28-Apr-24 21-May-24 20 166
Landscape Works 26-Feb-24 12-Oct-24 181 16
GR-CON-Z12-1508 Excavation (Tree Pit ) 26-Feb-24 06-Mar-24 8 118
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1509 Aggregate Drainage layer 06-Mar-24 18-Mar-24 9 118


GR-CON-Z12-1510 Installation Geotextile 18-Mar-24 27-Mar-24 6 118
GR-CON-Z12-1511 Backfilling (Soil max for tree) 27-Mar-24 10-Apr-24 9 118
GR-CON-Z12-1512 Installation of Trees 18-Aug-24 21-Aug-24 4 16
GR-CON-Z12-12096 Installation of Shrubs 22-Aug-24 25-Aug-24 3 16
GR-CON-Z12-12106 Installation of Succulents 26-Aug-24 28-Aug-24 3 16
GR-CON-Z12-12116 Installation of Ground Covers 29-Aug-24 01-Sep-24 3 16
GR-CON-Z12-12126 Installation of Grass 02-Sep-24 04-Sep-24 3 16
GR-CON-Z12-1513 Backfilling (Mulch) 05-Sep-24 10-Sep-24 5 16
GR-CON-Z12-1514 Natural Boulders Installation 11-Sep-24 17-Sep-24 6 16
GR-CON-Z12-1515 Retaining walls . Steps, forming risers, treads and edges with finishes
18-Sep-24 12-Oct-24 20 16
Site Furnishing 13-Oct-24 18-Nov-24 32 16
GR-CON-Z12-1524 Garden planter box 13-Oct-24 21-Oct-24 8 16
GR-CON-Z12-1525 Wheel stoppers 22-Oct-24 30-Oct-24 8 16
GR-CON-Z12-1526 Steel Lattice 31-Oct-24 09-Nov-24 8 16
GR-CON-Z12-1527 Handrail 10-Nov-24 18-Nov-24 8 16
Storm Piping Works 09-Nov-24 18-Nov-24 9 16
GR-CON-Z12-1528 Installation of DI grating covers 09-Nov-24 18-Nov-24 9 16
Irrigation Works 17-Feb-24 02-Jun-24 81 147
GR-CON-Z12-1516 Excavation Pipe Irrigation 17-Feb-24 26-Feb-24 8 98
GR-CON-Z12-1517 Sand Bedding 26-Feb-24 04-Mar-24 6 98
GR-CON-Z12-1518 HDPE Pipe Installations and fittings and conduit for cable 04-Mar-24 06-Apr-24 23 98
GR-CON-Z12-1520 Test pressure 06-Apr-24 21-Apr-24 8 98
GR-CON-Z12-1519 Installation of Valves and Accessories 21-Apr-24 28-Apr-24 6 98
GR-CON-Z12-1521 Back filling (sand / Subbase ) 28-Apr-24 08-May-24 9 98
GR-CON-Z12-1522 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-May-24 19-May-24 9 147
GR-CON-Z12-1523 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
19-May-24
system 02-Jun-24 12 147
Electrical Works 26-Feb-24 18-Nov-24 213 16
GR-CON-Z12-1529 Excavation And Disposal 26-Feb-24 06-Mar-24 8 187
GR-CON-Z12-1530 Sand Bedding 06-Mar-24 13-Mar-24 6 187
GR-CON-Z12-1531 laying cables 13-Mar-24 23-Mar-24 6 187
GR-CON-Z12-1532 Backfilling (sand / Sub base) 23-Mar-24 03-Apr-24 8 187
GR-CON-Z12-1533 Control Panel / Distribution Panel Installation 04-Apr-24 17-Apr-24 6 187
GR-CON-Z12-1534 Road Crossing Ducts 10-Nov-24 18-Nov-24 8 16
School S-08 29-Jun-24 16-Oct-24 94 44
Site Preparation 29-Jun-24 08-Jul-24 9 129
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z12-1249 Excavation And Disposal 29-Jun-24 03-Jul-24 5 16


GR-CON-Z12-1250 Prepretion And Compaction 04-Jul-24 08-Jul-24 4 129
Curbstone and Paving 04-Jul-24 26-Aug-24 46 87
GR-CON-Z12-1252 Excavation Curbstone 04-Jul-24 09-Jul-24 5 56
GR-CON-Z12-1253 Plain Concrete 10-Jul-24 16-Jul-24 6 87
GR-CON-Z12-1254 Installation Curbstone 17-Jul-24 27-Jul-24 9 87
GR-CON-Z12-1255 Casting Concrete (Mortar haunch) 28-Jul-24 31-Jul-24 4 87
GR-CON-Z12-1256 Backfilling (sand / Sub base) 01-Aug-24 11-Aug-24 9 87
GR-CON-Z12-1257 Installation of Paving 12-Aug-24 26-Aug-24 13 87
Landscape Works 10-Jul-24 05-Oct-24 74 44
GR-CON-Z12-1258 Excavation (Tree Pit ) 10-Jul-24 15-Jul-24 5 56
GR-CON-Z12-1259 Aggregate Drainage layer 16-Jul-24 22-Jul-24 6 56
GR-CON-Z12-1260 Installation Geotextile 23-Jul-24 27-Jul-24 4 56
GR-CON-Z12-1261 Backfilling (Soil max for tree) 28-Jul-24 03-Aug-24 6 56
GR-CON-Z12-1262 Installation of Trees 18-Aug-24 20-Aug-24 3 44
GR-CON-Z12-5596 Installation of Shrubs 21-Aug-24 24-Aug-24 3 44
GR-CON-Z12-5606 Installation of Succulents 25-Aug-24 27-Aug-24 3 44
GR-CON-Z12-5616 Installation of Ground Covers 28-Aug-24 31-Aug-24 3 44
GR-CON-Z12-5626 Installation of Climbers 01-Sep-24 03-Sep-24 3 44
GR-CON-Z12-5636 Installation of Grass 04-Sep-24 07-Sep-24 3 44
GR-CON-Z12-5646 Installation of Lawns 08-Sep-24 10-Sep-24 3 44
GR-CON-Z12-1263 Backfilling (Mulch) 11-Sep-24 14-Sep-24 3 44
GR-CON-Z12-1264 Natural Boulders Installation 15-Sep-24 18-Sep-24 4 44
GR-CON-Z12-1265 Retaining walls . Steps, forming risers, treads and edges with finishes
19-Sep-24 05-Oct-24 13 44
Site Furnishing 06-Oct-24 16-Oct-24 10 44
GR-CON-Z12-1274 Garden planter box 06-Oct-24 10-Oct-24 5 44
GR-CON-Z12-1275 Wheel stoppers 12-Oct-24 16-Oct-24 5 44
Irrigation Works 04-Jul-24 16-Oct-24 89 44
GR-CON-Z12-1266 Excavation Pipe Irrigation 04-Jul-24 09-Jul-24 5 16
GR-CON-Z12-1267 Sand Bedding 10-Jul-24 13-Jul-24 3 16
GR-CON-Z12-1268 HDPE Pipe Installations and fittings and conduit for cable 14-Jul-24 30-Jul-24 15 16
GR-CON-Z12-1270 Test pressure 31-Jul-24 05-Aug-24 5 16
GR-CON-Z12-1269 Installation of Valves and Accessories 06-Aug-24 10-Aug-24 4 16
GR-CON-Z12-1271 Back filling (sand / Subbase ) 11-Aug-24 17-Aug-24 6 16
GR-CON-Z12-1272 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Aug-24 24-Aug-24 6 81
GR-CON-Z12-1273 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Oct-24
system 16-Oct-24 8 44
Activity ID Activity Name Start Finish Original Total Float
Duration

Zone 13 07-Nov-23 19-Sep-24 258 54


Mosque M-21 07-Nov-23 01-Sep-24 242 70
Site Preparation 07-Nov-23 28-Nov-23 19 271
GR-CON-Z13-1000 Demolition (Asphalt.Paving,etc.....) 07-Nov-23 11-Nov-23 4 22
GR-CON-Z13-1001 Excavation And Disposal 12-Nov-23 16-Nov-23 5 186
GR-CON-Z13-1002 Prepretion And Compaction 18-Nov-23 21-Nov-23 4 271
GR-CON-Z13-1003 Backfilling 22-Nov-23 28-Nov-23 6 271
Curbstone and Paving 29-Nov-23 24-Dec-23 22 271
GR-CON-Z13-1008 Backfilling (sand / Sub base) 29-Nov-23 09-Dec-23 9 271
GR-CON-Z13-1009 Installation of Paving 10-Dec-23 24-Dec-23 13 271
Landscape Works 18-Nov-23 01-Sep-24 233 70
GR-CON-Z13-1010 Excavation (Tree Pit ) 18-Nov-23 22-Nov-23 5 219
GR-CON-Z13-1011 Aggregate Drainage layer 23-Nov-23 29-Nov-23 6 219
GR-CON-Z13-1012 Installation Geotextile 30-Nov-23 05-Dec-23 5 219
GR-CON-Z13-1013 Backfilling (Soil max for tree) 06-Dec-23 11-Dec-23 5 219
GR-CON-Z13-1014 Installation of Trees 15-Jun-24 24-Jun-24 4 70
GR-CON-Z13-4306 Installation of Climbers 24-Jun-24 29-Jun-24 4 70
GR-CON-Z13-4316 Installation of Shrubs 29-Jun-24 03-Jul-24 4 70
GR-CON-Z13-4326 Installation of Succulents 03-Jul-24 08-Jul-24 4 70
GR-CON-Z13-4336 Installation of Ground Covers 08-Jul-24 13-Jul-24 4 70
GR-CON-Z13-1015 Backfilling (Mulch) 13-Jul-24 30-Jul-24 15 70
GR-CON-Z13-1016 Natural Boulders Installation 30-Jul-24 14-Aug-24 13 70
GR-CON-Z13-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
14-Aug-24 01-Sep-24 15 70
Irrigation Works 18-Nov-23 01-Sep-24 233 70
GR-CON-Z13-1018 Excavation Pipe Irrigation 18-Nov-23 22-Nov-23 5 186
GR-CON-Z13-1019 Sand Bedding 23-Nov-23 26-Nov-23 3 186
GR-CON-Z13-1020 HDPE Pipe Installations and fittings and conduit for cable 27-Nov-23 13-Dec-23 15 186
GR-CON-Z13-1022 Test pressure 14-Dec-23 19-Dec-23 5 186
GR-CON-Z13-1021 Installation of Valves and Accessories 20-Dec-23 24-Dec-23 4 186
GR-CON-Z13-1023 Back filling (sand / Subbase ) 25-Dec-23 31-Dec-23 6 186
GR-CON-Z13-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Jan-24 07-Jan-24 6 253
GR-CON-Z13-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Aug-24
system 01-Sep-24 6 70
Parking P-21 12-Nov-23 22-Jul-24 203 105
Site Preparation 12-Nov-23 03-Dec-23 19 276
GR-CON-Z13-1026 Demolition (Asphalt.Paving,etc.....) 12-Nov-23 15-Nov-23 4 127
GR-CON-Z13-1027 Excavation And Disposal 16-Nov-23 21-Nov-23 5 182
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1028 Prepretion And Compaction 22-Nov-23 26-Nov-23 4 276


GR-CON-Z13-1029 Backfilling 27-Nov-23 03-Dec-23 6 276
Curbstone and Paving 22-Nov-23 14-Jan-24 46 253
GR-CON-Z13-1030 Excavation Curbstone 22-Nov-23 27-Nov-23 5 245
GR-CON-Z13-1031 Plain Concrete 28-Nov-23 04-Dec-23 6 253
GR-CON-Z13-1032 Installation Curbstone 05-Dec-23 14-Dec-23 9 253
GR-CON-Z13-1033 Casting Concrete (Mortar haunch) 16-Dec-23 19-Dec-23 4 253
GR-CON-Z13-1034 Backfilling (sand / Sub base) 20-Dec-23 30-Dec-23 9 253
GR-CON-Z13-1035 Installation of Paving 31-Dec-23 14-Jan-24 13 253
Landscape Works 28-Nov-23 10-Jul-24 179 105
GR-CON-Z13-1036 Excavation (Tree Pit ) 28-Nov-23 03-Dec-23 5 245
GR-CON-Z13-1037 Aggregate Drainage layer 04-Dec-23 10-Dec-23 6 245
GR-CON-Z13-1038 Installation Geotextile 11-Dec-23 14-Dec-23 4 245
GR-CON-Z13-1039 Backfilling (Soil max for tree) 16-Dec-23 21-Dec-23 6 245
GR-CON-Z13-1040 Installation of Trees 15-Jun-24 18-Jun-24 3 105
GR-CON-Z13-7976 Installation of Shrubs 18-Jun-24 26-Jun-24 3 105
GR-CON-Z13-7986 Installation of Ground Covers 26-Jun-24 30-Jun-24 3 105
GR-CON-Z13-7996 Installation of Succulents 30-Jun-24 03-Jul-24 3 105
GR-CON-Z13-8006 Installation of Grass 03-Jul-24 07-Jul-24 3 105
GR-CON-Z13-1041 Backfilling (Mulch) 07-Jul-24 10-Jul-24 3 105
Site Furnishing 10-Jul-24 22-Jul-24 10 105
GR-CON-Z13-1052 Tree Grate 10-Jul-24 16-Jul-24 5 105
GR-CON-Z13-1053 Wheel stoppers 16-Jul-24 22-Jul-24 5 105
Irrigation Works 22-Nov-23 22-Jul-24 194 105
GR-CON-Z13-1044 Excavation Pipe Irrigation 22-Nov-23 27-Nov-23 5 182
GR-CON-Z13-1045 Sand Bedding 28-Nov-23 30-Nov-23 3 182
GR-CON-Z13-1046 HDPE Pipe Installations and fittings and conduit for cable 02-Dec-23 18-Dec-23 15 182
GR-CON-Z13-1048 Test pressure 19-Dec-23 24-Dec-23 5 182
GR-CON-Z13-1047 Installation of Valves and Accessories 25-Dec-23 28-Dec-23 4 182
GR-CON-Z13-1049 Back filling (sand / Subbase ) 30-Dec-23 04-Jan-24 6 182
GR-CON-Z13-1050 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Jan-24 11-Jan-24 6 247
GR-CON-Z13-1051 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jul-24
system 22-Jul-24 8 105
Parking P-25 24-Dec-23 22-Jul-24 167 105
Site Preparation 24-Dec-23 15-Jan-24 19 240
GR-CON-Z13-1054 Demolition (Asphalt.Paving,etc.....) 24-Dec-23 28-Dec-23 4 95
GR-CON-Z13-1055 Excavation And Disposal 28-Dec-23 03-Jan-24 5 146
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1056 Prepretion And Compaction 03-Jan-24 08-Jan-24 4 240


GR-CON-Z13-1057 Backfilling 08-Jan-24 15-Jan-24 6 240
Curbstone and Paving 03-Jan-24 26-Feb-24 46 217
GR-CON-Z13-1058 Excavation Curbstone 03-Jan-24 09-Jan-24 5 209
GR-CON-Z13-1059 Plain Concrete 09-Jan-24 16-Jan-24 6 217
GR-CON-Z13-1060 Installation Curbstone 16-Jan-24 27-Jan-24 9 217
GR-CON-Z13-1061 Casting Concrete (Mortar haunch) 27-Jan-24 31-Jan-24 4 217
GR-CON-Z13-1062 Backfilling (sand / Sub base) 31-Jan-24 11-Feb-24 9 217
GR-CON-Z13-1063 Installation of Paving 11-Feb-24 26-Feb-24 13 217
Landscape Works 09-Jan-24 10-Jul-24 143 105
GR-CON-Z13-1064 Excavation (Tree Pit ) 09-Jan-24 15-Jan-24 5 209
GR-CON-Z13-1065 Aggregate Drainage layer 15-Jan-24 22-Jan-24 6 209
GR-CON-Z13-1066 Installation Geotextile 22-Jan-24 27-Jan-24 4 209
GR-CON-Z13-1067 Backfilling (Soil max for tree) 27-Jan-24 03-Feb-24 6 209
GR-CON-Z13-1068 Installation of Trees 15-Jun-24 18-Jun-24 3 105
GR-CON-Z13-8016 Installation of Shrubs 18-Jun-24 26-Jun-24 3 105
GR-CON-Z13-8026 Installation of Ground Covers 26-Jun-24 30-Jun-24 3 105
GR-CON-Z13-8036 Installation of Succulents 30-Jun-24 03-Jul-24 3 105
GR-CON-Z13-8046 Installation of Grass 03-Jul-24 07-Jul-24 3 105
GR-CON-Z13-1069 Backfilling (Mulch) 07-Jul-24 10-Jul-24 3 105
Site Furnishing 10-Jul-24 22-Jul-24 10 105
GR-CON-Z13-1080 Tree Grate 10-Jul-24 16-Jul-24 5 105
GR-CON-Z13-1081 Wheel stoppers 16-Jul-24 22-Jul-24 5 105
Irrigation Works 03-Jan-24 22-Jul-24 158 105
GR-CON-Z13-1072 Excavation Pipe Irrigation 03-Jan-24 09-Jan-24 5 146
GR-CON-Z13-1073 Sand Bedding 09-Jan-24 13-Jan-24 3 146
GR-CON-Z13-1074 HDPE Pipe Installations and fittings and conduit for cable 13-Jan-24 30-Jan-24 15 146
GR-CON-Z13-1076 Test pressure 30-Jan-24 05-Feb-24 5 146
GR-CON-Z13-1075 Installation of Valves and Accessories 05-Feb-24 10-Feb-24 4 146
GR-CON-Z13-1077 Back filling (sand / Subbase ) 10-Feb-24 17-Feb-24 6 146
GR-CON-Z13-1078 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 17-Feb-24 24-Feb-24 6 211
GR-CON-Z13-1079 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jul-24
system 22-Jul-24 8 105
Parking P-35 18-Jan-24 22-Jul-24 145 105
Site Preparation 18-Jan-24 25-Jan-24 6 231
GR-CON-Z13-1085 Backfilling 18-Jan-24 25-Jan-24 6 231
GR-CON-Z13-1083 Excavation And Disposal 20-Jan-24 25-Jan-24 5 127
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1082 Demolition (Asphalt.Paving,etc.....) 21-Jan-24 25-Jan-24 4 75


GR-CON-Z13-1084 Prepretion And Compaction 21-Jan-24 25-Jan-24 4 231
Curbstone and Paving 25-Jan-24 20-Mar-24 46 198
GR-CON-Z13-1086 Excavation Curbstone 25-Jan-24 31-Jan-24 5 190
GR-CON-Z13-1087 Plain Concrete 31-Jan-24 07-Feb-24 6 198
GR-CON-Z13-1088 Installation Curbstone 07-Feb-24 18-Feb-24 9 198
GR-CON-Z13-1089 Casting Concrete (Mortar haunch) 18-Feb-24 22-Feb-24 4 198
GR-CON-Z13-1090 Backfilling (sand / Sub base) 22-Feb-24 04-Mar-24 9 198
GR-CON-Z13-1091 Installation of Paving 04-Mar-24 20-Mar-24 13 198
Landscape Works 31-Jan-24 10-Jul-24 124 105
GR-CON-Z13-1092 Excavation (Tree Pit ) 31-Jan-24 06-Feb-24 5 190
GR-CON-Z13-1093 Aggregate Drainage layer 06-Feb-24 13-Feb-24 6 190
GR-CON-Z13-1094 Installation Geotextile 13-Feb-24 18-Feb-24 4 190
GR-CON-Z13-1095 Backfilling (Soil max for tree) 18-Feb-24 25-Feb-24 6 190
GR-CON-Z13-1096 Installation of Trees 15-Jun-24 18-Jun-24 3 105
GR-CON-Z13-8056 Installation of Shrubs 18-Jun-24 26-Jun-24 3 105
GR-CON-Z13-8066 Installation of Ground Covers 26-Jun-24 30-Jun-24 3 105
GR-CON-Z13-8076 Installation of Succulents 30-Jun-24 03-Jul-24 3 105
GR-CON-Z13-8086 Installation of Grass 03-Jul-24 07-Jul-24 3 105
GR-CON-Z13-1097 Backfilling (Mulch) 07-Jul-24 10-Jul-24 3 105
Site Furnishing 10-Jul-24 22-Jul-24 10 105
GR-CON-Z13-1108 Tree Grate 10-Jul-24 16-Jul-24 5 105
GR-CON-Z13-1109 Wheel stoppers 16-Jul-24 22-Jul-24 5 105
Irrigation Works 25-Jan-24 22-Jul-24 139 105
GR-CON-Z13-1100 Excavation Pipe Irrigation 25-Jan-24 31-Jan-24 5 127
GR-CON-Z13-1101 Sand Bedding 31-Jan-24 04-Feb-24 3 127
GR-CON-Z13-1102 HDPE Pipe Installations and fittings and conduit for cable 04-Feb-24 21-Feb-24 15 127
GR-CON-Z13-1104 Test pressure 21-Feb-24 27-Feb-24 5 127
GR-CON-Z13-1103 Installation of Valves and Accessories 27-Feb-24 03-Mar-24 4 127
GR-CON-Z13-1105 Back filling (sand / Subbase ) 03-Mar-24 10-Mar-24 6 127
GR-CON-Z13-1106 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Mar-24 18-Mar-24 6 192
GR-CON-Z13-1107 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jul-24
system 22-Jul-24 8 105
Street SS-18.1 18-Feb-24 22-Aug-24 146 78
Site Preparation 18-Feb-24 13-Mar-24 21 203
GR-CON-Z13-1166 Demolition (Asphalt.Paving,etc.....) 18-Feb-24 22-Feb-24 4 55
GR-CON-Z13-1167 Excavation And Disposal 22-Feb-24 28-Feb-24 5 97
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1168 Prepretion And Compaction 28-Feb-24 06-Mar-24 6 203


GR-CON-Z13-1169 Backfilling 06-Mar-24 13-Mar-24 6 203
Curbstone and Paving 28-Feb-24 04-May-24 46 169
GR-CON-Z13-1170 Excavation Curbstone 28-Feb-24 05-Mar-24 5 134
GR-CON-Z13-1171 Plain Concrete 05-Mar-24 12-Mar-24 6 169
GR-CON-Z13-1172 Installation Curbstone 12-Mar-24 25-Mar-24 9 169
GR-CON-Z13-1173 Casting Concrete (Mortar haunch) 26-Mar-24 01-Apr-24 4 169
GR-CON-Z13-1174 Backfilling (sand / Sub base) 01-Apr-24 18-Apr-24 9 169
GR-CON-Z13-1175 Installation of Paving 18-Apr-24 04-May-24 13 169
Landscape Works 05-Mar-24 30-Jul-24 112 78
GR-CON-Z13-1176 Excavation (Tree Pit ) 05-Mar-24 11-Mar-24 5 134
GR-CON-Z13-1177 Aggregate Drainage layer 11-Mar-24 19-Mar-24 6 134
GR-CON-Z13-1178 Installation Geotextile 19-Mar-24 25-Mar-24 4 134
GR-CON-Z13-1179 Backfilling (Soil max for tree) 26-Mar-24 03-Apr-24 6 134
GR-CON-Z13-1180 Installation of Trees 15-Jun-24 18-Jun-24 3 78
GR-CON-Z13-12136 Installation of Shrubs 18-Jun-24 26-Jun-24 3 78
GR-CON-Z13-12146 Installation of Succulents 26-Jun-24 30-Jun-24 3 78
GR-CON-Z13-12156 Installation of Ground Covers 30-Jun-24 03-Jul-24 3 78
GR-CON-Z13-12166 Installation of Grass 03-Jul-24 07-Jul-24 3 78
GR-CON-Z13-1181 Backfilling (Mulch) 07-Jul-24 10-Jul-24 3 78
GR-CON-Z13-1182 Natural Boulders Installation 10-Jul-24 15-Jul-24 4 78
GR-CON-Z13-1183 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Jul-24 30-Jul-24 13 78
Site Furnishing 30-Jul-24 22-Aug-24 20 78
GR-CON-Z13-1192 Garden planter box 30-Jul-24 05-Aug-24 5 78
GR-CON-Z13-1193 Wheel stoppers 05-Aug-24 11-Aug-24 5 78
GR-CON-Z13-1194 Steel Lattice 11-Aug-24 17-Aug-24 5 78
GR-CON-Z13-1195 Handrail 17-Aug-24 22-Aug-24 5 78
Storm Piping Works 15-Aug-24 22-Aug-24 6 78
GR-CON-Z13-1196 Installation of DI grating covers 15-Aug-24 22-Aug-24 6 78
Irrigation Works 28-Feb-24 12-May-24 53 156
GR-CON-Z13-1184 Excavation Pipe Irrigation 28-Feb-24 05-Mar-24 5 97
GR-CON-Z13-1185 Sand Bedding 05-Mar-24 10-Mar-24 4 97
GR-CON-Z13-1186 HDPE Pipe Installations and fittings and conduit for cable 10-Mar-24 01-Apr-24 15 97
GR-CON-Z13-1188 Test pressure 01-Apr-24 08-Apr-24 5 97
GR-CON-Z13-1187 Installation of Valves and Accessories 09-Apr-24 18-Apr-24 4 97
GR-CON-Z13-1189 Back filling (sand / Subbase ) 18-Apr-24 25-Apr-24 6 97
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1190 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-Apr-24 02-May-24 6 156
GR-CON-Z13-1191 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-May-24
system 12-May-24 8 156
Electrical Works 05-Mar-24 22-Aug-24 132 78
GR-CON-Z13-1197 Excavation And Disposal 05-Mar-24 11-Mar-24 5 183
GR-CON-Z13-1198 Sand Bedding 11-Mar-24 16-Mar-24 4 183
GR-CON-Z13-1199 laying cables 17-Mar-24 23-Mar-24 4 183
GR-CON-Z13-1200 Backfilling (sand / Sub base) 23-Mar-24 30-Mar-24 5 183
GR-CON-Z13-1201 Control Panel / Distribution Panel Installation 31-Mar-24 06-Apr-24 4 183
GR-CON-Z13-1202 Road Crossing Ducts 17-Aug-24 22-Aug-24 5 78
Street SS-19 24-Feb-24 19-Sep-24 165 54
Site Preparation 24-Feb-24 07-Apr-24 32 187
GR-CON-Z13-1203 Demolition (Asphalt.Paving,etc.....) 24-Feb-24 02-Mar-24 6 54
GR-CON-Z13-1204 Excavation And Disposal 02-Mar-24 11-Mar-24 8 66
GR-CON-Z13-1205 Prepretion And Compaction 11-Mar-24 24-Mar-24 9 187
GR-CON-Z13-1206 Backfilling 24-Mar-24 07-Apr-24 9 187
Curbstone and Paving 11-Mar-24 13-Jun-24 71 134
GR-CON-Z13-1207 Excavation Curbstone 11-Mar-24 23-Mar-24 8 86
GR-CON-Z13-1208 Plain Concrete 23-Mar-24 06-Apr-24 9 134
GR-CON-Z13-1209 Installation Curbstone 06-Apr-24 28-Apr-24 14 134
GR-CON-Z13-1210 Casting Concrete (Mortar haunch) 28-Apr-24 05-May-24 6 134
GR-CON-Z13-1211 Backfilling (sand / Sub base) 05-May-24 21-May-24 14 134
GR-CON-Z13-1212 Installation of Paving 21-May-24 13-Jun-24 20 134
Landscape Works 23-Mar-24 13-Aug-24 111 54
GR-CON-Z13-1213 Excavation (Tree Pit ) 23-Mar-24 03-Apr-24 8 86
GR-CON-Z13-1214 Aggregate Drainage layer 04-Apr-24 21-Apr-24 9 86
GR-CON-Z13-1215 Installation Geotextile 21-Apr-24 28-Apr-24 6 86
GR-CON-Z13-1216 Backfilling (Soil max for tree) 28-Apr-24 08-May-24 9 86
GR-CON-Z13-1217 Installation of Trees 15-Jun-24 24-Jun-24 4 54
GR-CON-Z13-12176 Installation of Shrubs 24-Jun-24 27-Jun-24 3 54
GR-CON-Z13-12186 Installation of Succulents 27-Jun-24 01-Jul-24 3 54
GR-CON-Z13-12196 Installation of Ground Covers 01-Jul-24 04-Jul-24 3 54
GR-CON-Z13-12206 Installation of Grass 04-Jul-24 08-Jul-24 3 54
GR-CON-Z13-1218 Backfilling (Mulch) 08-Jul-24 14-Jul-24 5 54
GR-CON-Z13-1219 Natural Boulders Installation 14-Jul-24 21-Jul-24 6 54
GR-CON-Z13-1220 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Jul-24 13-Aug-24 20 54
Site Furnishing 13-Aug-24 19-Sep-24 32 54
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1229 Garden planter box 13-Aug-24 22-Aug-24 8 54


GR-CON-Z13-1230 Wheel stoppers 22-Aug-24 01-Sep-24 8 54
GR-CON-Z13-1231 Steel Lattice 01-Sep-24 10-Sep-24 8 54
GR-CON-Z13-1232 Handrail 10-Sep-24 19-Sep-24 8 54
Storm Piping Works 09-Sep-24 19-Sep-24 9 54
GR-CON-Z13-1233 Installation of DI grating covers 09-Sep-24 19-Sep-24 9 54
Irrigation Works 11-Mar-24 30-Jun-24 81 115
GR-CON-Z13-1221 Excavation Pipe Irrigation 11-Mar-24 23-Mar-24 8 66
GR-CON-Z13-1222 Sand Bedding 23-Mar-24 01-Apr-24 6 66
GR-CON-Z13-1223 HDPE Pipe Installations and fittings and conduit for cable 01-Apr-24 05-May-24 23 66
GR-CON-Z13-1225 Test pressure 05-May-24 14-May-24 8 66
GR-CON-Z13-1224 Installation of Valves and Accessories 14-May-24 21-May-24 6 66
GR-CON-Z13-1226 Back filling (sand / Subbase ) 21-May-24 01-Jun-24 9 66
GR-CON-Z13-1227 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Jun-24 11-Jun-24 9 115
GR-CON-Z13-1228 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
11-Jun-24
system 30-Jun-24 12 115
Electrical Works 23-Mar-24 19-Sep-24 143 54
GR-CON-Z13-1234 Excavation And Disposal 23-Mar-24 03-Apr-24 8 155
GR-CON-Z13-1235 Sand Bedding 04-Apr-24 17-Apr-24 6 155
GR-CON-Z13-1236 laying cables 17-Apr-24 24-Apr-24 6 155
GR-CON-Z13-1237 Backfilling (sand / Sub base) 24-Apr-24 04-May-24 8 155
GR-CON-Z13-1238 Control Panel / Distribution Panel Installation 04-May-24 11-May-24 6 155
GR-CON-Z13-1239 Road Crossing Ducts 10-Sep-24 19-Sep-24 8 54
Street SS-08 02-Mar-24 19-Sep-24 159 54
Site Preparation 02-Mar-24 20-Apr-24 32 181
GR-CON-Z13-1240 Demolition (Asphalt.Paving,etc.....) 02-Mar-24 09-Mar-24 6 54
GR-CON-Z13-1241 Excavation And Disposal 09-Mar-24 19-Mar-24 8 60
GR-CON-Z13-1242 Prepretion And Compaction 19-Mar-24 02-Apr-24 9 181
GR-CON-Z13-1243 Backfilling 02-Apr-24 20-Apr-24 9 181
Curbstone and Paving 19-Mar-24 25-Jun-24 71 128
GR-CON-Z13-1244 Excavation Curbstone 19-Mar-24 01-Apr-24 8 80
GR-CON-Z13-1245 Plain Concrete 01-Apr-24 18-Apr-24 9 128
GR-CON-Z13-1246 Installation Curbstone 18-Apr-24 05-May-24 14 128
GR-CON-Z13-1247 Casting Concrete (Mortar haunch) 05-May-24 12-May-24 6 128
GR-CON-Z13-1248 Backfilling (sand / Sub base) 12-May-24 28-May-24 14 128
GR-CON-Z13-1249 Installation of Paving 28-May-24 25-Jun-24 20 128
Landscape Works 01-Apr-24 13-Aug-24 105 54
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1250 Excavation (Tree Pit ) 01-Apr-24 17-Apr-24 8 80


GR-CON-Z13-1251 Aggregate Drainage layer 17-Apr-24 28-Apr-24 9 80
GR-CON-Z13-1252 Installation Geotextile 28-Apr-24 05-May-24 6 80
GR-CON-Z13-1253 Backfilling (Soil max for tree) 05-May-24 15-May-24 9 80
GR-CON-Z13-1254 Installation of Trees 15-Jun-24 24-Jun-24 4 54
GR-CON-Z13-12216 Installation of Shrubs 24-Jun-24 27-Jun-24 3 54
GR-CON-Z13-12226 Installation of Succulents 27-Jun-24 01-Jul-24 3 54
GR-CON-Z13-12236 Installation of Ground Covers 01-Jul-24 04-Jul-24 3 54
GR-CON-Z13-12246 Installation of Grass 04-Jul-24 08-Jul-24 3 54
GR-CON-Z13-1255 Backfilling (Mulch) 08-Jul-24 14-Jul-24 5 54
GR-CON-Z13-1256 Natural Boulders Installation 14-Jul-24 21-Jul-24 6 54
GR-CON-Z13-1257 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Jul-24 13-Aug-24 20 54
Site Furnishing 13-Aug-24 19-Sep-24 32 54
GR-CON-Z13-1266 Garden planter box 13-Aug-24 22-Aug-24 8 54
GR-CON-Z13-1267 Wheel stoppers 22-Aug-24 01-Sep-24 8 54
GR-CON-Z13-1268 Steel Lattice 01-Sep-24 10-Sep-24 8 54
GR-CON-Z13-1269 Handrail 10-Sep-24 19-Sep-24 8 54
Storm Piping Works 09-Sep-24 19-Sep-24 9 54
GR-CON-Z13-1270 Installation of DI grating covers 09-Sep-24 19-Sep-24 9 54
Irrigation Works 19-Mar-24 07-Jul-24 81 109
GR-CON-Z13-1258 Excavation Pipe Irrigation 19-Mar-24 01-Apr-24 8 60
GR-CON-Z13-1259 Sand Bedding 01-Apr-24 10-Apr-24 6 60
GR-CON-Z13-1260 HDPE Pipe Installations and fittings and conduit for cable 10-Apr-24 12-May-24 23 60
GR-CON-Z13-1262 Test pressure 12-May-24 21-May-24 8 60
GR-CON-Z13-1261 Installation of Valves and Accessories 21-May-24 28-May-24 6 60
GR-CON-Z13-1263 Back filling (sand / Subbase ) 28-May-24 08-Jun-24 9 60
GR-CON-Z13-1264 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-Jun-24 18-Jun-24 9 109
GR-CON-Z13-1265 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Jun-24
system 07-Jul-24 12 109
Electrical Works 01-Apr-24 19-Sep-24 137 54
GR-CON-Z13-1271 Excavation And Disposal 01-Apr-24 17-Apr-24 8 149
GR-CON-Z13-1272 Sand Bedding 17-Apr-24 24-Apr-24 6 149
GR-CON-Z13-1273 laying cables 24-Apr-24 01-May-24 6 149
GR-CON-Z13-1274 Backfilling (sand / Sub base) 01-May-24 11-May-24 8 149
GR-CON-Z13-1275 Control Panel / Distribution Panel Installation 11-May-24 18-May-24 6 149
GR-CON-Z13-1276 Road Crossing Ducts 10-Sep-24 19-Sep-24 8 54
Street SS-08.1 09-Mar-24 19-Sep-24 153 54
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 09-Mar-24 27-Apr-24 32 175


GR-CON-Z13-1277 Demolition (Asphalt.Paving,etc.....) 09-Mar-24 16-Mar-24 6 54
GR-CON-Z13-1278 Excavation And Disposal 17-Mar-24 28-Mar-24 8 54
GR-CON-Z13-1279 Prepretion And Compaction 28-Mar-24 11-Apr-24 9 175
GR-CON-Z13-1280 Backfilling 11-Apr-24 27-Apr-24 9 175
Curbstone and Paving 28-Mar-24 02-Jul-24 71 122
GR-CON-Z13-1281 Excavation Curbstone 28-Mar-24 10-Apr-24 8 74
GR-CON-Z13-1282 Plain Concrete 10-Apr-24 25-Apr-24 9 122
GR-CON-Z13-1283 Installation Curbstone 25-Apr-24 12-May-24 14 122
GR-CON-Z13-1284 Casting Concrete (Mortar haunch) 12-May-24 19-May-24 6 122
GR-CON-Z13-1285 Backfilling (sand / Sub base) 19-May-24 04-Jun-24 14 122
GR-CON-Z13-1286 Installation of Paving 04-Jun-24 02-Jul-24 20 122
Landscape Works 10-Apr-24 13-Aug-24 99 54
GR-CON-Z13-1287 Excavation (Tree Pit ) 10-Apr-24 24-Apr-24 8 74
GR-CON-Z13-1288 Aggregate Drainage layer 24-Apr-24 05-May-24 9 74
GR-CON-Z13-1289 Installation Geotextile 05-May-24 12-May-24 6 74
GR-CON-Z13-1290 Backfilling (Soil max for tree) 12-May-24 22-May-24 9 74
GR-CON-Z13-1291 Installation of Trees 15-Jun-24 24-Jun-24 4 54
GR-CON-Z13-12256 Installation of Shrubs 24-Jun-24 27-Jun-24 3 54
GR-CON-Z13-12266 Installation of Succulents 27-Jun-24 01-Jul-24 3 54
GR-CON-Z13-12276 Installation of Ground Covers 01-Jul-24 04-Jul-24 3 54
GR-CON-Z13-12286 Installation of Grass 04-Jul-24 08-Jul-24 3 54
GR-CON-Z13-1292 Backfilling (Mulch) 08-Jul-24 14-Jul-24 5 54
GR-CON-Z13-1293 Natural Boulders Installation 14-Jul-24 21-Jul-24 6 54
GR-CON-Z13-1294 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Jul-24 13-Aug-24 20 54
Site Furnishing 13-Aug-24 19-Sep-24 32 54
GR-CON-Z13-1303 Garden planter box 13-Aug-24 22-Aug-24 8 54
GR-CON-Z13-1304 Wheel stoppers 22-Aug-24 01-Sep-24 8 54
GR-CON-Z13-1305 Steel Lattice 01-Sep-24 10-Sep-24 8 54
GR-CON-Z13-1306 Handrail 10-Sep-24 19-Sep-24 8 54
Storm Piping Works 09-Sep-24 19-Sep-24 9 54
GR-CON-Z13-1307 Installation of DI grating covers 09-Sep-24 19-Sep-24 9 54
Irrigation Works 28-Mar-24 14-Jul-24 81 103
GR-CON-Z13-1295 Excavation Pipe Irrigation 28-Mar-24 10-Apr-24 8 54
GR-CON-Z13-1296 Sand Bedding 10-Apr-24 22-Apr-24 6 54
GR-CON-Z13-1297 HDPE Pipe Installations and fittings and conduit for cable 22-Apr-24 19-May-24 23 54
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1299 Test pressure 19-May-24 28-May-24 8 54


GR-CON-Z13-1298 Installation of Valves and Accessories 28-May-24 04-Jun-24 6 54
GR-CON-Z13-1300 Back filling (sand / Subbase ) 04-Jun-24 15-Jun-24 9 54
GR-CON-Z13-1301 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Jun-24 30-Jun-24 9 103
GR-CON-Z13-1302 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
30-Jun-24
system 14-Jul-24 12 103
Electrical Works 10-Apr-24 19-Sep-24 131 54
GR-CON-Z13-1308 Excavation And Disposal 10-Apr-24 24-Apr-24 8 143
GR-CON-Z13-1309 Sand Bedding 24-Apr-24 01-May-24 6 143
GR-CON-Z13-1310 laying cables 01-May-24 08-May-24 6 143
GR-CON-Z13-1311 Backfilling (sand / Sub base) 08-May-24 18-May-24 8 143
GR-CON-Z13-1312 Control Panel / Distribution Panel Installation 18-May-24 25-May-24 6 143
GR-CON-Z13-1313 Road Crossing Ducts 10-Sep-24 19-Sep-24 8 54
School S-10 17-Mar-24 18-Aug-24 119 82
Site Preparation 17-Mar-24 30-Mar-24 9 192
GR-CON-Z13-1111 Excavation And Disposal 17-Mar-24 24-Mar-24 5 74
GR-CON-Z13-1112 Prepretion And Compaction 24-Mar-24 30-Mar-24 4 192
Curbstone and Paving 24-Mar-24 26-May-24 46 150
GR-CON-Z13-1114 Excavation Curbstone 24-Mar-24 01-Apr-24 5 119
GR-CON-Z13-1115 Plain Concrete 01-Apr-24 10-Apr-24 6 150
GR-CON-Z13-1116 Installation Curbstone 10-Apr-24 25-Apr-24 9 150
GR-CON-Z13-1117 Casting Concrete (Mortar haunch) 25-Apr-24 30-Apr-24 4 150
GR-CON-Z13-1118 Backfilling (sand / Sub base) 30-Apr-24 11-May-24 9 150
GR-CON-Z13-1119 Installation of Paving 11-May-24 26-May-24 13 150
Landscape Works 01-Apr-24 06-Aug-24 99 82
GR-CON-Z13-1120 Excavation (Tree Pit ) 01-Apr-24 08-Apr-24 5 119
GR-CON-Z13-1121 Aggregate Drainage layer 09-Apr-24 21-Apr-24 6 119
GR-CON-Z13-1122 Installation Geotextile 21-Apr-24 25-Apr-24 4 119
GR-CON-Z13-1123 Backfilling (Soil max for tree) 25-Apr-24 02-May-24 6 119
GR-CON-Z13-1124 Installation of Trees 15-Jun-24 18-Jun-24 3 82
GR-CON-Z13-5656 Installation of Shrubs 18-Jun-24 26-Jun-24 3 82
GR-CON-Z13-5666 Installation of Succulents 26-Jun-24 30-Jun-24 3 82
GR-CON-Z13-5676 Installation of Ground Covers 30-Jun-24 03-Jul-24 3 82
GR-CON-Z13-5686 Installation of Climbers 03-Jul-24 07-Jul-24 3 82
GR-CON-Z13-5696 Installation of Grass 07-Jul-24 10-Jul-24 3 82
GR-CON-Z13-5706 Installation of Lawns 10-Jul-24 14-Jul-24 3 82
GR-CON-Z13-1125 Backfilling (Mulch) 14-Jul-24 17-Jul-24 3 82
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-1126 Natural Boulders Installation 17-Jul-24 22-Jul-24 4 82


GR-CON-Z13-1127 Retaining walls . Steps, forming risers, treads and edges with finishes
22-Jul-24 06-Aug-24 13 82
Site Furnishing 06-Aug-24 18-Aug-24 10 82
GR-CON-Z13-1136 Garden planter box 06-Aug-24 12-Aug-24 5 82
GR-CON-Z13-1137 Wheel stoppers 12-Aug-24 18-Aug-24 5 82
Irrigation Works 24-Mar-24 18-Aug-24 114 82
GR-CON-Z13-1128 Excavation Pipe Irrigation 24-Mar-24 01-Apr-24 5 79
GR-CON-Z13-1129 Sand Bedding 01-Apr-24 06-Apr-24 3 79
GR-CON-Z13-1130 HDPE Pipe Installations and fittings and conduit for cable 06-Apr-24 29-Apr-24 15 79
GR-CON-Z13-1132 Test pressure 29-Apr-24 05-May-24 5 79
GR-CON-Z13-1131 Installation of Valves and Accessories 05-May-24 09-May-24 4 79
GR-CON-Z13-1133 Back filling (sand / Subbase ) 09-May-24 16-May-24 6 79
GR-CON-Z13-1134 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-May-24 23-May-24 6 144
GR-CON-Z13-1135 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Aug-24
system 18-Aug-24 8 82
School S-09 26-Mar-24 18-Aug-24 113 82
Site Preparation 26-Mar-24 08-Apr-24 9 186
GR-CON-Z13-1139 Excavation And Disposal 26-Mar-24 02-Apr-24 5 73
GR-CON-Z13-1140 Prepretion And Compaction 02-Apr-24 08-Apr-24 4 186
Curbstone and Paving 02-Apr-24 02-Jun-24 46 144
GR-CON-Z13-1142 Excavation Curbstone 02-Apr-24 10-Apr-24 5 113
GR-CON-Z13-1143 Plain Concrete 10-Apr-24 22-Apr-24 6 144
GR-CON-Z13-1144 Installation Curbstone 22-Apr-24 02-May-24 9 144
GR-CON-Z13-1145 Casting Concrete (Mortar haunch) 02-May-24 07-May-24 4 144
GR-CON-Z13-1146 Backfilling (sand / Sub base) 07-May-24 18-May-24 9 144
GR-CON-Z13-1147 Installation of Paving 18-May-24 02-Jun-24 13 144
Landscape Works 10-Apr-24 06-Aug-24 93 82
GR-CON-Z13-1148 Excavation (Tree Pit ) 10-Apr-24 21-Apr-24 5 113
GR-CON-Z13-1149 Aggregate Drainage layer 21-Apr-24 28-Apr-24 6 113
GR-CON-Z13-1150 Installation Geotextile 28-Apr-24 02-May-24 4 113
GR-CON-Z13-1151 Backfilling (Soil max for tree) 02-May-24 09-May-24 6 113
GR-CON-Z13-1152 Installation of Trees 15-Jun-24 18-Jun-24 3 82
GR-CON-Z13-5716 Installation of Shrubs 18-Jun-24 26-Jun-24 3 82
GR-CON-Z13-5726 Installation of Succulents 26-Jun-24 30-Jun-24 3 82
GR-CON-Z13-5736 Installation of Ground Covers 30-Jun-24 03-Jul-24 3 82
GR-CON-Z13-5746 Installation of Climbers 03-Jul-24 07-Jul-24 3 82
GR-CON-Z13-5756 Installation of Grass 07-Jul-24 10-Jul-24 3 82
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z13-5766 Installation of Lawns 10-Jul-24 14-Jul-24 3 82


GR-CON-Z13-1153 Backfilling (Mulch) 14-Jul-24 17-Jul-24 3 82
GR-CON-Z13-1154 Natural Boulders Installation 17-Jul-24 22-Jul-24 4 82
GR-CON-Z13-1155 Retaining walls . Steps, forming risers, treads and edges with finishes
22-Jul-24 06-Aug-24 13 82
Site Furnishing 06-Aug-24 18-Aug-24 10 82
GR-CON-Z13-1164 Garden planter box 06-Aug-24 12-Aug-24 5 82
GR-CON-Z13-1165 Wheel stoppers 12-Aug-24 18-Aug-24 5 82
Irrigation Works 02-Apr-24 18-Aug-24 108 82
GR-CON-Z13-1156 Excavation Pipe Irrigation 02-Apr-24 10-Apr-24 5 73
GR-CON-Z13-1157 Sand Bedding 10-Apr-24 18-Apr-24 3 73
GR-CON-Z13-1158 HDPE Pipe Installations and fittings and conduit for cable 18-Apr-24 06-May-24 15 73
GR-CON-Z13-1160 Test pressure 06-May-24 12-May-24 5 73
GR-CON-Z13-1159 Installation of Valves and Accessories 12-May-24 16-May-24 4 73
GR-CON-Z13-1161 Back filling (sand / Subbase ) 16-May-24 23-May-24 6 73
GR-CON-Z13-1162 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-May-24 30-May-24 6 138
GR-CON-Z13-1163 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Aug-24
system 18-Aug-24 8 82
Zone 11 07-Dec-23 25-Nov-24 288 16
Future Neighborhood Park FNP-21 07-Dec-23 20-Aug-24 206 98
Site Preparation 07-Dec-23 11-Jan-24 30 274
GR-CON-Z11-1131 Demolition (Asphalt.Paving,etc.....) 07-Dec-23 14-Dec-23 6 16
GR-CON-Z11-1132 Excavation And Disposal 14-Dec-23 24-Dec-23 8 136
GR-CON-Z11-1133 Prepretion And Compaction 24-Dec-23 31-Dec-23 6 274
GR-CON-Z11-1134 Backfilling 31-Dec-23 11-Jan-24 10 274
Curbstone and Paving 24-Dec-23 04-Mar-24 61 229
GR-CON-Z11-1135 Excavation Curbstone 24-Dec-23 02-Jan-24 8 152
GR-CON-Z11-1136 Plain Concrete 02-Jan-24 14-Jan-24 10 229
GR-CON-Z11-1137 Installation Curbstone 14-Jan-24 25-Jan-24 10 229
GR-CON-Z11-1138 Casting Concrete (Mortar haunch) 25-Jan-24 31-Jan-24 5 229
GR-CON-Z11-1139 Backfilling (sand / Sub base) 31-Jan-24 10-Feb-24 8 229
GR-CON-Z11-1140 Installation of Paving 10-Feb-24 04-Mar-24 20 229
Landscape Works 02-Jan-24 20-Aug-24 184 98
GR-CON-Z11-1141 Excavation (Tree Pit ) 02-Jan-24 11-Jan-24 8 152
GR-CON-Z11-1142 Aggregate Drainage layer 11-Jan-24 23-Jan-24 10 183
GR-CON-Z11-1143 Installation Geotextile 23-Jan-24 30-Jan-24 6 183
GR-CON-Z11-1144 Backfilling (Soil max for tree) 30-Jan-24 11-Feb-24 10 183
GR-CON-Z11-1145 Installation of Trees 21-May-24 25-May-24 3 107
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-2346 Installation of Shrubs 25-May-24 28-May-24 3 107


GR-CON-Z11-2356 Installation of Succulents 28-May-24 01-Jun-24 3 107
GR-CON-Z11-2366 Installation of Ground Covers 01-Jun-24 04-Jun-24 3 107
GR-CON-Z11-2376 Installation of Climbers 04-Jun-24 08-Jun-24 3 107
GR-CON-Z11-2386 Installation of Grass 08-Jun-24 11-Jun-24 3 107
GR-CON-Z11-2396 Installation of Lawns 11-Jun-24 15-Jun-24 3 107
GR-CON-Z11-1146 Backfilling (Mulch) 15-Jun-24 24-Jun-24 4 107
GR-CON-Z11-1147 Natural Boulders Installation 24-Jun-24 01-Jul-24 6 107
GR-CON-Z11-1148 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Jul-24 20-Aug-24 26 98
MUGA 11-Jan-24 20-Aug-24 176 98
GR-CON-Z11-1149 Excavation And Disposal 11-Jan-24 21-Jan-24 8 152
GR-CON-Z11-1150 Prepretion And Compaction 21-Jan-24 01-Feb-24 10 152
GR-CON-Z11-1151 polyethylene under footings ( fence and gates) 01-Feb-24 11-Feb-24 8 152
GR-CON-Z11-1152 Blinding concrete (flooring) 11-Feb-24 20-Feb-24 8 152
GR-CON-Z11-1153 Concrete Footings ( fence and gates) 20-Feb-24 14-Mar-24 20 152
GR-CON-Z11-1154 Tools Play Installation ( basketball / football ..) 14-Mar-24 23-Apr-24 24 152
GR-CON-Z11-1155 PaintAcrylic Play Surface 23-Apr-24 16-May-24 20 152
GR-CON-Z11-1156 Fence (high / low) / gates Installation 23-Jul-24 20-Aug-24 24 98
Irrigation Works 24-Dec-23 20-Aug-24 192 98
GR-CON-Z11-1157 Excavation Pipe Irrigation 24-Dec-23 02-Jan-24 8 136
GR-CON-Z11-1158 Sand Bedding 02-Jan-24 07-Jan-24 4 136
GR-CON-Z11-1159 HDPE Pipe Installations and fittings and conduit for cable 07-Jan-24 30-Jan-24 20 136
GR-CON-Z11-1161 Test pressure 30-Jan-24 08-Feb-24 8 136
GR-CON-Z11-1160 Installation of Valves and Accessories 08-Feb-24 15-Feb-24 6 136
GR-CON-Z11-1162 Back filling (sand / Subbase ) 15-Feb-24 27-Feb-24 10 136
GR-CON-Z11-1163 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-Feb-24 10-Mar-24 10 212
GR-CON-Z11-1164 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Aug-24
system 20-Aug-24 12 98
Mosque M-35 14-Dec-23 07-Aug-24 189 109
Site Preparation 14-Dec-23 06-Jan-24 19 246
GR-CON-Z11-1191 Demolition (Asphalt.Paving,etc.....) 14-Dec-23 19-Dec-23 4 74
GR-CON-Z11-1192 Excavation And Disposal 19-Dec-23 25-Dec-23 5 153
GR-CON-Z11-1193 Prepretion And Compaction 25-Dec-23 30-Dec-23 4 246
GR-CON-Z11-1194 Backfilling 30-Dec-23 06-Jan-24 6 246
Curbstone and Paving 06-Jan-24 31-Jan-24 22 246
GR-CON-Z11-1199 Backfilling (sand / Sub base) 06-Jan-24 16-Jan-24 9 246
GR-CON-Z11-1200 Installation of Paving 16-Jan-24 31-Jan-24 13 246
Activity ID Activity Name Start Finish Original Total Float
Duration

Landscape Works 25-Dec-23 07-Aug-24 180 98


GR-CON-Z11-1201 Excavation (Tree Pit ) 25-Dec-23 31-Dec-23 5 194
GR-CON-Z11-1202 Aggregate Drainage layer 31-Dec-23 07-Jan-24 6 194
GR-CON-Z11-1203 Installation Geotextile 07-Jan-24 13-Jan-24 5 194
GR-CON-Z11-1204 Backfilling (Soil max for tree) 13-Jan-24 18-Jan-24 5 194
GR-CON-Z11-1205 Installation of Trees 21-May-24 26-May-24 4 98
GR-CON-Z11-4106 Installation of Climbers 26-May-24 30-May-24 4 98
GR-CON-Z11-4116 Installation of Shrubs 30-May-24 04-Jun-24 4 98
GR-CON-Z11-4126 Installation of Succulents 04-Jun-24 09-Jun-24 4 98
GR-CON-Z11-4136 Installation of Ground Covers 09-Jun-24 13-Jun-24 4 98
GR-CON-Z11-1206 Backfilling (Mulch) 13-Jun-24 06-Jul-24 15 98
GR-CON-Z11-1207 Natural Boulders Installation 06-Jul-24 21-Jul-24 13 98
GR-CON-Z11-1208 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Jul-24 07-Aug-24 15 98
Irrigation Works 25-Dec-23 07-Aug-24 180 109
GR-CON-Z11-1209 Excavation Pipe Irrigation 25-Dec-23 31-Dec-23 5 153
GR-CON-Z11-1210 Sand Bedding 31-Dec-23 03-Jan-24 3 153
GR-CON-Z11-1211 HDPE Pipe Installations and fittings and conduit for cable 03-Jan-24 21-Jan-24 15 153
GR-CON-Z11-1213 Test pressure 21-Jan-24 27-Jan-24 5 153
GR-CON-Z11-1212 Installation of Valves and Accessories 27-Jan-24 31-Jan-24 4 153
GR-CON-Z11-1214 Back filling (sand / Subbase ) 31-Jan-24 07-Feb-24 6 153
GR-CON-Z11-1215 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 07-Feb-24 14-Feb-24 6 239
GR-CON-Z11-1216 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
31-Jul-24
system 07-Aug-24 6 109
Mosque M-17 19-Dec-23 07-Aug-24 185 109
Site Preparation 19-Dec-23 10-Jan-24 19 253
GR-CON-Z11-1165 Demolition (Asphalt.Paving,etc.....) 19-Dec-23 24-Dec-23 4 74
GR-CON-Z11-1166 Excavation And Disposal 24-Dec-23 30-Dec-23 5 149
GR-CON-Z11-1167 Prepretion And Compaction 30-Dec-23 03-Jan-24 4 253
GR-CON-Z11-1168 Backfilling 03-Jan-24 10-Jan-24 6 253
Curbstone and Paving 10-Jan-24 05-Feb-24 22 253
GR-CON-Z11-1173 Backfilling (sand / Sub base) 10-Jan-24 21-Jan-24 9 253
GR-CON-Z11-1174 Installation of Paving 21-Jan-24 05-Feb-24 13 253
Landscape Works 30-Dec-23 07-Aug-24 176 109
GR-CON-Z11-1175 Excavation (Tree Pit ) 30-Dec-23 04-Jan-24 5 201
GR-CON-Z11-1176 Aggregate Drainage layer 04-Jan-24 11-Jan-24 6 201
GR-CON-Z11-1177 Installation Geotextile 11-Jan-24 17-Jan-24 5 201
GR-CON-Z11-1178 Backfilling (Soil max for tree) 17-Jan-24 23-Jan-24 5 201
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-1179 Installation of Trees 21-May-24 26-May-24 4 109


GR-CON-Z11-4066 Installation of Climbers 26-May-24 30-May-24 4 109
GR-CON-Z11-4076 Installation of Shrubs 30-May-24 04-Jun-24 4 109
GR-CON-Z11-4086 Installation of Succulents 04-Jun-24 09-Jun-24 4 109
GR-CON-Z11-4096 Installation of Ground Covers 09-Jun-24 13-Jun-24 4 109
GR-CON-Z11-1180 Backfilling (Mulch) 13-Jun-24 06-Jul-24 15 109
GR-CON-Z11-1181 Natural Boulders Installation 06-Jul-24 21-Jul-24 13 109
GR-CON-Z11-1182 Retaining walls . Steps, forming risers, treads and edges with finishes
21-Jul-24 07-Aug-24 15 109
Irrigation Works 30-Dec-23 07-Aug-24 176 109
GR-CON-Z11-1183 Excavation Pipe Irrigation 30-Dec-23 04-Jan-24 5 149
GR-CON-Z11-1184 Sand Bedding 04-Jan-24 08-Jan-24 3 149
GR-CON-Z11-1185 HDPE Pipe Installations and fittings and conduit for cable 08-Jan-24 25-Jan-24 15 149
GR-CON-Z11-1187 Test pressure 25-Jan-24 31-Jan-24 5 149
GR-CON-Z11-1186 Installation of Valves and Accessories 31-Jan-24 05-Feb-24 4 149
GR-CON-Z11-1188 Back filling (sand / Subbase ) 05-Feb-24 12-Feb-24 6 149
GR-CON-Z11-1189 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 12-Feb-24 19-Feb-24 6 235
GR-CON-Z11-1190 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
31-Jul-24
system 07-Aug-24 6 109
Parking P-38 21-Dec-23 27-Jun-24 148 144
Site Preparation 21-Dec-23 28-Dec-23 6 273
GR-CON-Z11-1248 Backfilling 21-Dec-23 28-Dec-23 6 273
GR-CON-Z11-1246 Excavation And Disposal 23-Dec-23 28-Dec-23 5 150
GR-CON-Z11-1245 Demolition (Asphalt.Paving,etc.....) 24-Dec-23 28-Dec-23 4 74
GR-CON-Z11-1247 Prepretion And Compaction 24-Dec-23 28-Dec-23 4 273
Curbstone and Paving 28-Dec-23 20-Feb-24 46 240
GR-CON-Z11-1249 Excavation Curbstone 28-Dec-23 03-Jan-24 5 232
GR-CON-Z11-1250 Plain Concrete 03-Jan-24 10-Jan-24 6 240
GR-CON-Z11-1251 Installation Curbstone 10-Jan-24 21-Jan-24 9 240
GR-CON-Z11-1252 Casting Concrete (Mortar haunch) 21-Jan-24 25-Jan-24 4 240
GR-CON-Z11-1253 Backfilling (sand / Sub base) 25-Jan-24 05-Feb-24 9 240
GR-CON-Z11-1254 Installation of Paving 05-Feb-24 20-Feb-24 13 240
Landscape Works 03-Jan-24 11-Jun-24 127 144
GR-CON-Z11-1255 Excavation (Tree Pit ) 03-Jan-24 09-Jan-24 5 232
GR-CON-Z11-1256 Aggregate Drainage layer 09-Jan-24 16-Jan-24 6 232
GR-CON-Z11-1257 Installation Geotextile 16-Jan-24 21-Jan-24 4 232
GR-CON-Z11-1258 Backfilling (Soil max for tree) 21-Jan-24 28-Jan-24 6 232
GR-CON-Z11-1259 Installation of Trees 21-May-24 25-May-24 3 144
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-7816 Installation of Shrubs 25-May-24 28-May-24 3 144


GR-CON-Z11-7826 Installation of Ground Covers 28-May-24 01-Jun-24 3 144
GR-CON-Z11-7836 Installation of Succulents 01-Jun-24 04-Jun-24 3 144
GR-CON-Z11-7846 Installation of Grass 04-Jun-24 08-Jun-24 3 144
GR-CON-Z11-1260 Backfilling (Mulch) 08-Jun-24 11-Jun-24 3 144
Site Furnishing 11-Jun-24 27-Jun-24 10 144
GR-CON-Z11-1271 Tree Grate 11-Jun-24 17-Jun-24 5 144
GR-CON-Z11-1272 Wheel stoppers 17-Jun-24 27-Jun-24 5 144
Irrigation Works 28-Dec-23 27-Jun-24 142 144
GR-CON-Z11-1263 Excavation Pipe Irrigation 28-Dec-23 03-Jan-24 5 150
GR-CON-Z11-1264 Sand Bedding 03-Jan-24 07-Jan-24 3 150
GR-CON-Z11-1265 HDPE Pipe Installations and fittings and conduit for cable 07-Jan-24 24-Jan-24 15 150
GR-CON-Z11-1267 Test pressure 24-Jan-24 30-Jan-24 5 150
GR-CON-Z11-1266 Installation of Valves and Accessories 30-Jan-24 04-Feb-24 4 150
GR-CON-Z11-1268 Back filling (sand / Subbase ) 04-Feb-24 11-Feb-24 6 150
GR-CON-Z11-1269 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Feb-24 18-Feb-24 6 234
GR-CON-Z11-1270 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jun-24
system 27-Jun-24 8 144
Parking P-03 26-Dec-23 27-Jun-24 144 144
Site Preparation 26-Dec-23 02-Jan-24 6 269
GR-CON-Z11-1332 Backfilling 26-Dec-23 02-Jan-24 6 269
GR-CON-Z11-1330 Excavation And Disposal 27-Dec-23 02-Jan-24 5 146
GR-CON-Z11-1329 Demolition (Asphalt.Paving,etc.....) 28-Dec-23 02-Jan-24 4 74
GR-CON-Z11-1331 Prepretion And Compaction 28-Dec-23 02-Jan-24 4 269
Curbstone and Paving 02-Jan-24 25-Feb-24 46 236
GR-CON-Z11-1333 Excavation Curbstone 02-Jan-24 08-Jan-24 5 228
GR-CON-Z11-1334 Plain Concrete 08-Jan-24 15-Jan-24 6 236
GR-CON-Z11-1335 Installation Curbstone 15-Jan-24 25-Jan-24 9 236
GR-CON-Z11-1336 Casting Concrete (Mortar haunch) 25-Jan-24 30-Jan-24 4 236
GR-CON-Z11-1337 Backfilling (sand / Sub base) 30-Jan-24 10-Feb-24 9 236
GR-CON-Z11-1338 Installation of Paving 10-Feb-24 25-Feb-24 13 236
Landscape Works 08-Jan-24 11-Jun-24 123 144
GR-CON-Z11-1339 Excavation (Tree Pit ) 08-Jan-24 14-Jan-24 5 228
GR-CON-Z11-1340 Aggregate Drainage layer 14-Jan-24 21-Jan-24 6 228
GR-CON-Z11-1341 Installation Geotextile 21-Jan-24 25-Jan-24 4 228
GR-CON-Z11-1342 Backfilling (Soil max for tree) 25-Jan-24 01-Feb-24 6 228
GR-CON-Z11-1343 Installation of Trees 21-May-24 25-May-24 3 144
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-7696 Installation of Shrubs 25-May-24 28-May-24 3 144


GR-CON-Z11-7706 Installation of Ground Covers 28-May-24 01-Jun-24 3 144
GR-CON-Z11-7716 Installation of Succulents 01-Jun-24 04-Jun-24 3 144
GR-CON-Z11-7726 Installation of Grass 04-Jun-24 08-Jun-24 3 144
GR-CON-Z11-1344 Backfilling (Mulch) 08-Jun-24 11-Jun-24 3 144
Site Furnishing 11-Jun-24 27-Jun-24 10 144
GR-CON-Z11-1355 Tree Grate 11-Jun-24 17-Jun-24 5 144
GR-CON-Z11-1356 Wheel stoppers 17-Jun-24 27-Jun-24 5 144
Irrigation Works 02-Jan-24 27-Jun-24 138 144
GR-CON-Z11-1347 Excavation Pipe Irrigation 02-Jan-24 08-Jan-24 5 146
GR-CON-Z11-1348 Sand Bedding 08-Jan-24 11-Jan-24 3 146
GR-CON-Z11-1349 HDPE Pipe Installations and fittings and conduit for cable 11-Jan-24 29-Jan-24 15 146
GR-CON-Z11-1351 Test pressure 29-Jan-24 04-Feb-24 5 146
GR-CON-Z11-1350 Installation of Valves and Accessories 04-Feb-24 08-Feb-24 4 146
GR-CON-Z11-1352 Back filling (sand / Subbase ) 08-Feb-24 15-Feb-24 6 146
GR-CON-Z11-1353 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Feb-24 22-Feb-24 6 230
GR-CON-Z11-1354 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jun-24
system 27-Jun-24 8 144
Parking P-33 31-Dec-23 27-Jun-24 140 144
Site Preparation 31-Dec-23 07-Jan-24 6 265
GR-CON-Z11-1276 Backfilling 31-Dec-23 07-Jan-24 6 265
GR-CON-Z11-1274 Excavation And Disposal 01-Jan-24 07-Jan-24 5 142
GR-CON-Z11-1273 Demolition (Asphalt.Paving,etc.....) 02-Jan-24 07-Jan-24 4 74
GR-CON-Z11-1275 Prepretion And Compaction 02-Jan-24 07-Jan-24 4 265
Curbstone and Paving 07-Jan-24 29-Feb-24 46 232
GR-CON-Z11-1277 Excavation Curbstone 07-Jan-24 13-Jan-24 5 224
GR-CON-Z11-1278 Plain Concrete 13-Jan-24 20-Jan-24 6 232
GR-CON-Z11-1279 Installation Curbstone 20-Jan-24 30-Jan-24 9 232
GR-CON-Z11-1280 Casting Concrete (Mortar haunch) 30-Jan-24 04-Feb-24 4 232
GR-CON-Z11-1281 Backfilling (sand / Sub base) 04-Feb-24 14-Feb-24 9 232
GR-CON-Z11-1282 Installation of Paving 14-Feb-24 29-Feb-24 13 232
Landscape Works 13-Jan-24 11-Jun-24 119 144
GR-CON-Z11-1283 Excavation (Tree Pit ) 13-Jan-24 18-Jan-24 5 224
GR-CON-Z11-1284 Aggregate Drainage layer 18-Jan-24 25-Jan-24 6 224
GR-CON-Z11-1285 Installation Geotextile 25-Jan-24 30-Jan-24 4 224
GR-CON-Z11-1286 Backfilling (Soil max for tree) 30-Jan-24 06-Feb-24 6 224
GR-CON-Z11-1287 Installation of Trees 21-May-24 25-May-24 3 144
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-7776 Installation of Shrubs 25-May-24 28-May-24 3 144


GR-CON-Z11-7786 Installation of Ground Covers 28-May-24 01-Jun-24 3 144
GR-CON-Z11-7796 Installation of Succulents 01-Jun-24 04-Jun-24 3 144
GR-CON-Z11-7806 Installation of Grass 04-Jun-24 08-Jun-24 3 144
GR-CON-Z11-1288 Backfilling (Mulch) 08-Jun-24 11-Jun-24 3 144
Site Furnishing 11-Jun-24 27-Jun-24 10 144
GR-CON-Z11-1299 Tree Grate 11-Jun-24 17-Jun-24 5 144
GR-CON-Z11-1300 Wheel stoppers 17-Jun-24 27-Jun-24 5 144
Irrigation Works 07-Jan-24 27-Jun-24 134 144
GR-CON-Z11-1291 Excavation Pipe Irrigation 07-Jan-24 13-Jan-24 5 142
GR-CON-Z11-1292 Sand Bedding 13-Jan-24 16-Jan-24 3 142
GR-CON-Z11-1293 HDPE Pipe Installations and fittings and conduit for cable 16-Jan-24 03-Feb-24 15 142
GR-CON-Z11-1295 Test pressure 03-Feb-24 08-Feb-24 5 142
GR-CON-Z11-1294 Installation of Valves and Accessories 08-Feb-24 13-Feb-24 4 142
GR-CON-Z11-1296 Back filling (sand / Subbase ) 13-Feb-24 20-Feb-24 6 142
GR-CON-Z11-1297 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Feb-24 27-Feb-24 6 226
GR-CON-Z11-1298 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jun-24
system 27-Jun-24 8 144
Parking P-17 04-Jan-24 27-Jun-24 136 144
Site Preparation 04-Jan-24 11-Jan-24 6 261
GR-CON-Z11-1220 Backfilling 04-Jan-24 11-Jan-24 6 261
GR-CON-Z11-1218 Excavation And Disposal 06-Jan-24 11-Jan-24 5 143
GR-CON-Z11-1217 Demolition (Asphalt.Paving,etc.....) 07-Jan-24 11-Jan-24 4 74
GR-CON-Z11-1219 Prepretion And Compaction 07-Jan-24 11-Jan-24 4 261
Curbstone and Paving 11-Jan-24 05-Mar-24 46 228
GR-CON-Z11-1221 Excavation Curbstone 11-Jan-24 17-Jan-24 5 220
GR-CON-Z11-1222 Plain Concrete 17-Jan-24 24-Jan-24 6 228
GR-CON-Z11-1223 Installation Curbstone 24-Jan-24 04-Feb-24 9 228
GR-CON-Z11-1224 Casting Concrete (Mortar haunch) 04-Feb-24 08-Feb-24 4 228
GR-CON-Z11-1225 Backfilling (sand / Sub base) 08-Feb-24 19-Feb-24 9 228
GR-CON-Z11-1226 Installation of Paving 19-Feb-24 05-Mar-24 13 228
Landscape Works 17-Jan-24 11-Jun-24 115 144
GR-CON-Z11-1227 Excavation (Tree Pit ) 17-Jan-24 23-Jan-24 5 220
GR-CON-Z11-1228 Aggregate Drainage layer 23-Jan-24 30-Jan-24 6 220
GR-CON-Z11-1229 Installation Geotextile 30-Jan-24 04-Feb-24 4 220
GR-CON-Z11-1230 Backfilling (Soil max for tree) 04-Feb-24 11-Feb-24 6 220
GR-CON-Z11-1231 Installation of Trees 21-May-24 25-May-24 3 144
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-7616 Installation of Shrubs 25-May-24 28-May-24 3 144


GR-CON-Z11-7626 Installation of Ground Covers 28-May-24 01-Jun-24 3 144
GR-CON-Z11-7636 Installation of Succulents 01-Jun-24 04-Jun-24 3 144
GR-CON-Z11-7646 Installation of Grass 04-Jun-24 08-Jun-24 3 144
GR-CON-Z11-1232 Backfilling (Mulch) 08-Jun-24 11-Jun-24 3 144
Site Furnishing 11-Jun-24 27-Jun-24 10 144
GR-CON-Z11-1243 Tree Grate 11-Jun-24 17-Jun-24 5 144
GR-CON-Z11-1244 Wheel stoppers 17-Jun-24 27-Jun-24 5 144
Irrigation Works 11-Jan-24 27-Jun-24 130 144
GR-CON-Z11-1235 Excavation Pipe Irrigation 11-Jan-24 17-Jan-24 5 143
GR-CON-Z11-1236 Sand Bedding 17-Jan-24 21-Jan-24 3 143
GR-CON-Z11-1237 HDPE Pipe Installations and fittings and conduit for cable 21-Jan-24 01-Feb-24 10 143
GR-CON-Z11-1239 Test pressure 01-Feb-24 07-Feb-24 5 143
GR-CON-Z11-1238 Installation of Valves and Accessories 07-Feb-24 12-Feb-24 4 143
GR-CON-Z11-1240 Back filling (sand / Subbase ) 12-Feb-24 19-Feb-24 6 143
GR-CON-Z11-1241 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-Feb-24 26-Feb-24 6 227
GR-CON-Z11-1242 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jun-24
system 27-Jun-24 8 144
Parking P-19 09-Jan-24 27-Jun-24 132 144
Site Preparation 09-Jan-24 16-Jan-24 6 257
GR-CON-Z11-1360 Backfilling 09-Jan-24 16-Jan-24 6 257
GR-CON-Z11-1358 Excavation And Disposal 10-Jan-24 16-Jan-24 5 134
GR-CON-Z11-1357 Demolition (Asphalt.Paving,etc.....) 11-Jan-24 16-Jan-24 4 74
GR-CON-Z11-1359 Prepretion And Compaction 11-Jan-24 16-Jan-24 4 257
Curbstone and Paving 16-Jan-24 10-Mar-24 46 224
GR-CON-Z11-1361 Excavation Curbstone 16-Jan-24 22-Jan-24 5 216
GR-CON-Z11-1362 Plain Concrete 22-Jan-24 29-Jan-24 6 224
GR-CON-Z11-1363 Installation Curbstone 29-Jan-24 08-Feb-24 9 224
GR-CON-Z11-1364 Casting Concrete (Mortar haunch) 08-Feb-24 13-Feb-24 4 224
GR-CON-Z11-1365 Backfilling (sand / Sub base) 13-Feb-24 24-Feb-24 9 224
GR-CON-Z11-1366 Installation of Paving 24-Feb-24 10-Mar-24 13 224
Landscape Works 22-Jan-24 11-Jun-24 111 144
GR-CON-Z11-1367 Excavation (Tree Pit ) 22-Jan-24 28-Jan-24 5 216
GR-CON-Z11-1368 Aggregate Drainage layer 28-Jan-24 04-Feb-24 6 216
GR-CON-Z11-1369 Installation Geotextile 04-Feb-24 08-Feb-24 4 216
GR-CON-Z11-1370 Backfilling (Soil max for tree) 08-Feb-24 15-Feb-24 6 216
GR-CON-Z11-1371 Installation of Trees 21-May-24 25-May-24 3 144
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-7656 Installation of Shrubs 25-May-24 28-May-24 3 144


GR-CON-Z11-7666 Installation of Ground Covers 28-May-24 01-Jun-24 3 144
GR-CON-Z11-7676 Installation of Succulents 01-Jun-24 04-Jun-24 3 144
GR-CON-Z11-7686 Installation of Grass 04-Jun-24 08-Jun-24 3 144
GR-CON-Z11-1372 Backfilling (Mulch) 08-Jun-24 11-Jun-24 3 144
Site Furnishing 11-Jun-24 27-Jun-24 10 144
GR-CON-Z11-1383 Tree Grate 11-Jun-24 17-Jun-24 5 144
GR-CON-Z11-1384 Wheel stoppers 17-Jun-24 27-Jun-24 5 144
Irrigation Works 16-Jan-24 27-Jun-24 126 144
GR-CON-Z11-1375 Excavation Pipe Irrigation 16-Jan-24 22-Jan-24 5 134
GR-CON-Z11-1376 Sand Bedding 22-Jan-24 25-Jan-24 3 134
GR-CON-Z11-1377 HDPE Pipe Installations and fittings and conduit for cable 25-Jan-24 12-Feb-24 15 134
GR-CON-Z11-1379 Test pressure 12-Feb-24 18-Feb-24 5 134
GR-CON-Z11-1378 Installation of Valves and Accessories 18-Feb-24 22-Feb-24 4 134
GR-CON-Z11-1380 Back filling (sand / Subbase ) 22-Feb-24 29-Feb-24 6 134
GR-CON-Z11-1381 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Feb-24 07-Mar-24 6 218
GR-CON-Z11-1382 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jun-24
system 27-Jun-24 8 144
Parking P-32 14-Jan-24 27-Jun-24 128 144
Site Preparation 14-Jan-24 21-Jan-24 6 253
GR-CON-Z11-1304 Backfilling 14-Jan-24 21-Jan-24 6 253
GR-CON-Z11-1302 Excavation And Disposal 15-Jan-24 21-Jan-24 5 130
GR-CON-Z11-1301 Demolition (Asphalt.Paving,etc.....) 16-Jan-24 21-Jan-24 4 74
GR-CON-Z11-1303 Prepretion And Compaction 16-Jan-24 21-Jan-24 4 253
Curbstone and Paving 21-Jan-24 14-Mar-24 46 220
GR-CON-Z11-1305 Excavation Curbstone 21-Jan-24 27-Jan-24 5 212
GR-CON-Z11-1306 Plain Concrete 27-Jan-24 03-Feb-24 6 220
GR-CON-Z11-1307 Installation Curbstone 03-Feb-24 13-Feb-24 9 220
GR-CON-Z11-1308 Casting Concrete (Mortar haunch) 13-Feb-24 18-Feb-24 4 220
GR-CON-Z11-1309 Backfilling (sand / Sub base) 18-Feb-24 28-Feb-24 9 220
GR-CON-Z11-1310 Installation of Paving 28-Feb-24 14-Mar-24 13 220
Landscape Works 27-Jan-24 11-Jun-24 107 144
GR-CON-Z11-1311 Excavation (Tree Pit ) 27-Jan-24 01-Feb-24 5 212
GR-CON-Z11-1312 Aggregate Drainage layer 01-Feb-24 08-Feb-24 6 212
GR-CON-Z11-1313 Installation Geotextile 08-Feb-24 13-Feb-24 4 212
GR-CON-Z11-1314 Backfilling (Soil max for tree) 13-Feb-24 20-Feb-24 6 212
GR-CON-Z11-1315 Installation of Trees 21-May-24 25-May-24 3 144
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-7736 Installation of Shrubs 25-May-24 28-May-24 3 144


GR-CON-Z11-7746 Installation of Ground Covers 28-May-24 01-Jun-24 3 144
GR-CON-Z11-7756 Installation of Succulents 01-Jun-24 04-Jun-24 3 144
GR-CON-Z11-7766 Installation of Grass 04-Jun-24 08-Jun-24 3 144
GR-CON-Z11-1316 Backfilling (Mulch) 08-Jun-24 11-Jun-24 3 144
Site Furnishing 11-Jun-24 27-Jun-24 10 144
GR-CON-Z11-1327 Tree Grate 11-Jun-24 17-Jun-24 5 144
GR-CON-Z11-1328 Wheel stoppers 17-Jun-24 27-Jun-24 5 144
Irrigation Works 21-Jan-24 27-Jun-24 122 144
GR-CON-Z11-1319 Excavation Pipe Irrigation 21-Jan-24 27-Jan-24 5 130
GR-CON-Z11-1320 Sand Bedding 27-Jan-24 30-Jan-24 3 130
GR-CON-Z11-1321 HDPE Pipe Installations and fittings and conduit for cable 30-Jan-24 17-Feb-24 15 130
GR-CON-Z11-1323 Test pressure 17-Feb-24 22-Feb-24 5 130
GR-CON-Z11-1322 Installation of Valves and Accessories 22-Feb-24 27-Feb-24 4 130
GR-CON-Z11-1324 Back filling (sand / Subbase ) 27-Feb-24 05-Mar-24 6 130
GR-CON-Z11-1325 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-Mar-24 12-Mar-24 6 214
GR-CON-Z11-1326 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jun-24
system 27-Jun-24 8 144
Street SS-17 21-Jan-24 29-Jul-24 149 117
Site Preparation 21-Jan-24 14-Feb-24 21 245
GR-CON-Z11-1385 Demolition (Asphalt.Paving,etc.....) 21-Jan-24 25-Jan-24 4 74
GR-CON-Z11-1386 Excavation And Disposal 25-Jan-24 31-Jan-24 5 120
GR-CON-Z11-1387 Prepretion And Compaction 31-Jan-24 07-Feb-24 6 245
GR-CON-Z11-1388 Backfilling 07-Feb-24 14-Feb-24 6 245
Curbstone and Paving 31-Jan-24 28-Mar-24 46 211
GR-CON-Z11-1389 Excavation Curbstone 31-Jan-24 06-Feb-24 5 176
GR-CON-Z11-1390 Plain Concrete 06-Feb-24 13-Feb-24 6 211
GR-CON-Z11-1391 Installation Curbstone 13-Feb-24 24-Feb-24 9 211
GR-CON-Z11-1392 Casting Concrete (Mortar haunch) 24-Feb-24 28-Feb-24 4 211
GR-CON-Z11-1393 Backfilling (sand / Sub base) 28-Feb-24 10-Mar-24 9 211
GR-CON-Z11-1394 Installation of Paving 10-Mar-24 28-Mar-24 13 211
Landscape Works 06-Feb-24 08-Jul-24 117 117
GR-CON-Z11-1395 Excavation (Tree Pit ) 06-Feb-24 12-Feb-24 5 176
GR-CON-Z11-1396 Aggregate Drainage layer 12-Feb-24 19-Feb-24 6 176
GR-CON-Z11-1397 Installation Geotextile 19-Feb-24 24-Feb-24 4 176
GR-CON-Z11-1398 Backfilling (Soil max for tree) 24-Feb-24 02-Mar-24 6 176
GR-CON-Z11-1399 Installation of Trees 21-May-24 25-May-24 3 117
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-11776 Installation of Shrubs 25-May-24 28-May-24 3 117


GR-CON-Z11-11786 Installation of Succulents 28-May-24 01-Jun-24 3 117
GR-CON-Z11-11796 Installation of Ground Covers 01-Jun-24 04-Jun-24 3 117
GR-CON-Z11-11806 Installation of Grass 04-Jun-24 08-Jun-24 3 117
GR-CON-Z11-1400 Backfilling (Mulch) 08-Jun-24 13-Jun-24 5 117
GR-CON-Z11-1401 Natural Boulders Installation 13-Jun-24 18-Jun-24 4 117
GR-CON-Z11-1402 Retaining walls . Steps, forming risers, treads and edges with finishes
18-Jun-24 08-Jul-24 13 117
Site Furnishing 08-Jul-24 29-Jul-24 18 117
GR-CON-Z11-1411 Garden planter box 08-Jul-24 14-Jul-24 5 117
GR-CON-Z11-1412 Wheel stoppers 14-Jul-24 20-Jul-24 5 117
GR-CON-Z11-1413 Steel Lattice 20-Jul-24 23-Jul-24 3 117
GR-CON-Z11-1414 Handrail 23-Jul-24 29-Jul-24 5 117
Storm Piping Works 22-Jul-24 29-Jul-24 6 117
GR-CON-Z11-1415 Installation of DI grating covers 22-Jul-24 29-Jul-24 6 117
Irrigation Works 31-Jan-24 08-Apr-24 53 198
GR-CON-Z11-1403 Excavation Pipe Irrigation 31-Jan-24 06-Feb-24 5 120
GR-CON-Z11-1404 Sand Bedding 06-Feb-24 11-Feb-24 4 120
GR-CON-Z11-1405 HDPE Pipe Installations and fittings and conduit for cable 11-Feb-24 28-Feb-24 15 120
GR-CON-Z11-1407 Test pressure 28-Feb-24 05-Mar-24 5 120
GR-CON-Z11-1406 Installation of Valves and Accessories 05-Mar-24 10-Mar-24 4 120
GR-CON-Z11-1408 Back filling (sand / Subbase ) 10-Mar-24 18-Mar-24 6 120
GR-CON-Z11-1409 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Mar-24 27-Mar-24 6 198
GR-CON-Z11-1410 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
27-Mar-24
system 08-Apr-24 8 198
Electrical Works 06-Feb-24 29-Jul-24 135 117
GR-CON-Z11-1416 Excavation And Disposal 06-Feb-24 12-Feb-24 5 225
GR-CON-Z11-1417 Sand Bedding 12-Feb-24 17-Feb-24 4 225
GR-CON-Z11-1418 laying cables 17-Feb-24 21-Feb-24 4 225
GR-CON-Z11-1419 Backfilling (sand / Sub base) 21-Feb-24 27-Feb-24 5 225
GR-CON-Z11-1420 Control Panel / Distribution Panel Installation 27-Feb-24 03-Mar-24 4 225
GR-CON-Z11-1421 Road Crossing Ducts 23-Jul-24 29-Jul-24 5 117
Street SS-26 25-Jan-24 17-Sep-24 188 74
Site Preparation 25-Jan-24 14-Mar-24 42 220
GR-CON-Z11-1422 Demolition (Asphalt.Paving,etc.....) 25-Jan-24 04-Feb-24 8 74
GR-CON-Z11-1423 Excavation And Disposal 04-Feb-24 15-Feb-24 10 74
GR-CON-Z11-1424 Prepretion And Compaction 15-Feb-24 29-Feb-24 12 220
GR-CON-Z11-1425 Backfilling 29-Feb-24 14-Mar-24 12 220
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 15-Feb-24 11-Jun-24 90 154


GR-CON-Z11-1426 Excavation Curbstone 15-Feb-24 27-Feb-24 10 94
GR-CON-Z11-1427 Plain Concrete 27-Feb-24 12-Mar-24 12 154
GR-CON-Z11-1428 Installation Curbstone 12-Mar-24 08-Apr-24 18 154
GR-CON-Z11-1429 Casting Concrete (Mortar haunch) 09-Apr-24 23-Apr-24 8 154
GR-CON-Z11-1430 Backfilling (sand / Sub base) 23-Apr-24 14-May-24 18 154
GR-CON-Z11-1431 Installation of Paving 14-May-24 11-Jun-24 24 154
Landscape Works 27-Feb-24 01-Aug-24 120 74
GR-CON-Z11-1432 Excavation (Tree Pit ) 27-Feb-24 10-Mar-24 10 94
GR-CON-Z11-1433 Aggregate Drainage layer 10-Mar-24 27-Mar-24 12 94
GR-CON-Z11-1434 Installation Geotextile 27-Mar-24 08-Apr-24 8 94
GR-CON-Z11-1435 Backfilling (Soil max for tree) 09-Apr-24 28-Apr-24 12 94
GR-CON-Z11-1436 Installation of Trees 21-May-24 26-May-24 4 74
GR-CON-Z11-11816 Installation of Shrubs 26-May-24 30-May-24 4 74
GR-CON-Z11-11826 Installation of Succulents 30-May-24 04-Jun-24 4 74
GR-CON-Z11-11836 Installation of Ground Covers 04-Jun-24 09-Jun-24 4 74
GR-CON-Z11-11846 Installation of Grass 09-Jun-24 13-Jun-24 4 74
GR-CON-Z11-1437 Backfilling (Mulch) 13-Jun-24 25-Jun-24 6 74
GR-CON-Z11-1438 Natural Boulders Installation 25-Jun-24 04-Jul-24 8 74
GR-CON-Z11-1439 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jul-24 01-Aug-24 24 74
Site Furnishing 01-Aug-24 17-Sep-24 40 74
GR-CON-Z11-1448 Garden planter box 01-Aug-24 13-Aug-24 10 74
GR-CON-Z11-1449 Wheel stoppers 13-Aug-24 25-Aug-24 10 74
GR-CON-Z11-1450 Steel Lattice 25-Aug-24 05-Sep-24 10 74
GR-CON-Z11-1451 Handrail 05-Sep-24 17-Sep-24 10 74
Storm Piping Works 03-Sep-24 17-Sep-24 12 74
GR-CON-Z11-1452 Installation of DI grating covers 03-Sep-24 17-Sep-24 12 74
Irrigation Works 15-Feb-24 27-Jun-24 100 132
GR-CON-Z11-1440 Excavation Pipe Irrigation 15-Feb-24 27-Feb-24 10 74
GR-CON-Z11-1441 Sand Bedding 27-Feb-24 07-Mar-24 8 74
GR-CON-Z11-1442 HDPE Pipe Installations and fittings and conduit for cable 07-Mar-24 11-Apr-24 24 74
GR-CON-Z11-1444 Test pressure 11-Apr-24 28-Apr-24 10 74
GR-CON-Z11-1443 Installation of Valves and Accessories 28-Apr-24 07-May-24 8 74
GR-CON-Z11-1445 Back filling (sand / Subbase ) 07-May-24 21-May-24 12 74
GR-CON-Z11-1446 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-May-24 04-Jun-24 12 132
GR-CON-Z11-1447 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
04-Jun-24
system 27-Jun-24 16 132
Activity ID Activity Name Start Finish Original Total Float
Duration

Electrical Works 27-Feb-24 17-Sep-24 160 74


GR-CON-Z11-1453 Excavation And Disposal 27-Feb-24 10-Mar-24 10 180
GR-CON-Z11-1454 Sand Bedding 10-Mar-24 20-Mar-24 8 180
GR-CON-Z11-1455 laying cables 21-Mar-24 02-Apr-24 8 180
GR-CON-Z11-1456 Backfilling (sand / Sub base) 02-Apr-24 21-Apr-24 10 180
GR-CON-Z11-1457 Control Panel / Distribution Panel Installation 21-Apr-24 30-Apr-24 8 180
GR-CON-Z11-1458 Road Crossing Ducts 05-Sep-24 17-Sep-24 10 74
Toilet - 04 14-Dec-23 25-Nov-24 282 16
Site Preparation 14-Dec-23 26-Dec-23 10 16
GR-CON-Z11-1022 Excavation And Disposal 14-Dec-23 20-Dec-23 5 16
GR-CON-Z11-1023 Backfilling (one layer) 20-Dec-23 26-Dec-23 5 16
Civil Works 26-Dec-23 21-May-24 116 16
GR-CON-Z11-1024 Polyethylene Under Footings, Grade Slab and Beams 26-Dec-23 30-Dec-23 3 16
GR-CON-Z11-1025 Blinding concrete 30-Dec-23 04-Jan-24 5 16
GR-CON-Z11-1026 Footings 04-Jan-24 14-Jan-24 8 16
GR-CON-Z11-1027 Waterproofing Under Footing 14-Jan-24 20-Jan-24 5 16
GR-CON-Z11-1028 Column Necks 20-Jan-24 27-Jan-24 6 16
GR-CON-Z11-1029 Waterproofing (Toilet) 27-Jan-24 06-Feb-24 9 16
GR-CON-Z11-1030 Backfilling 06-Feb-24 13-Feb-24 6 16
GR-CON-Z11-1031 Ground beams 13-Feb-24 28-Feb-24 13 16
GR-CON-Z11-1032 Slab on grade 28-Feb-24 23-Mar-24 18 16
GR-CON-Z11-1033 Columns 23-Mar-24 11-Apr-24 13 16
GR-CON-Z11-1034 Concrete, slabs Ground floor 11-Apr-24 11-May-24 21 16
GR-CON-Z11-1035 Roof Thermal And Moisture Protection Work 11-May-24 21-May-24 9 16
Architectural Works 21-May-24 25-Nov-24 156 16
GR-CON-Z11-1036 Blockwork 21-May-24 12-Jun-24 19 16
GR-CON-Z11-1037 Waterproofing 26-Jun-24 07-Jul-24 9 16
GR-CON-Z11-1038 Back Filling (sand) 07-Jul-24 13-Jul-24 5 16
GR-CON-Z11-1039 Floor finish 13-Jul-24 28-Jul-24 13 16
GR-CON-Z11-1040 Wall Finish 28-Jul-24 26-Aug-24 25 16
GR-CON-Z11-1041 Door Installation 26-Aug-24 31-Aug-24 4 16
GR-CON-Z11-1043 Celling finish 31-Aug-24 15-Sep-24 13 16
GR-CON-Z11-1044 ToiletAccessories 15-Sep-24 19-Sep-24 4 16
GR-CON-Z11-1045 Facade Finishing Works 19-Sep-24 13-Oct-24 19 16
GR-CON-Z11-1046 Metal Work 12-Oct-24 03-Nov-24 19 16
GR-CON-Z11-1047 Wood Work 03-Nov-24 25-Nov-24 19 16
Activity ID Activity Name Start Finish Original Total Float
Duration

Mechanical Works 12-Jun-24 25-Nov-24 137 16


GR-CON-Z11-1048 Pipework Installations and fittings 12-Jun-24 26-Jun-24 8 16
GR-CON-Z11-1049 Installation of refrigerant supply/return pipework 12-Jun-24 17-Jun-24 4 76
GR-CON-Z11-1051 Water Meter With Meter Cabinet 12-Jun-24 16-Jun-24 3 140
GR-CON-Z11-1050 Installation of Sanitary Fixtures 28-Jul-24 06-Aug-24 8 37
GR-CON-Z11-1053 Installation of Exhaust Equipmets and Air outlets 13-Nov-24 25-Nov-24 10 16
Electrical Works 12-Jun-24 25-Nov-24 137 16
GR-CON-Z11-1054 Conduits Installation 12-Jun-24 18-Jun-24 5 46
GR-CON-Z11-1056 Earthing and lightning protection system 12-Jun-24 17-Jun-24 4 124
GR-CON-Z11-1055 Install of power cables 26-Aug-24 29-Aug-24 3 17
GR-CON-Z11-1057 Installation of wiring devices and lighting fixtures 26-Aug-24 01-Sep-24 5 68
GR-CON-Z11-1058 Installation of Alarm with park BMS system 01-Sep-24 07-Sep-24 5 68
GR-CON-Z11-1052 Installation of Fire Detection System 07-Sep-24 16-Sep-24 8 68
GR-CON-Z11-1059 Installation of Panel Board 16-Sep-24 21-Sep-24 4 68
GR-CON-Z11-1060 Connecting to nearest feeder pillar 21-Nov-24 25-Nov-24 3 16
Government G-01 04-Feb-24 13-Jul-24 123 131
Site Preparation 04-Feb-24 26-Feb-24 19 235
GR-CON-Z11-1459 Demolition (Asphalt.Paving,etc.....) 04-Feb-24 08-Feb-24 4 101
GR-CON-Z11-1460 Excavation And Disposal 08-Feb-24 14-Feb-24 5 109
GR-CON-Z11-1461 Prepretion And Compaction 14-Feb-24 19-Feb-24 4 235
GR-CON-Z11-1462 Backfilling 19-Feb-24 26-Feb-24 6 235
Curbstone and Paving 14-Feb-24 20-Apr-24 46 199
GR-CON-Z11-1463 Excavation Curbstone 14-Feb-24 20-Feb-24 5 178
GR-CON-Z11-1464 Plain Concrete 20-Feb-24 27-Feb-24 6 199
GR-CON-Z11-1465 Installation Curbstone 27-Feb-24 09-Mar-24 9 199
GR-CON-Z11-1466 Casting Concrete (Mortar haunch) 09-Mar-24 13-Mar-24 4 199
GR-CON-Z11-1467 Backfilling (sand / Sub base) 13-Mar-24 27-Mar-24 9 199
GR-CON-Z11-1468 Installation of Paving 27-Mar-24 20-Apr-24 13 199
Landscape Works 20-Feb-24 13-Jul-24 109 131
GR-CON-Z11-1469 Excavation (Tree Pit ) 20-Feb-24 26-Feb-24 5 178
GR-CON-Z11-1470 Aggregate Drainage layer 26-Feb-24 04-Mar-24 6 178
GR-CON-Z11-1471 Installation Geotextile 04-Mar-24 09-Mar-24 4 178
GR-CON-Z11-1472 Backfilling (Soil max for tree) 09-Mar-24 16-Mar-24 6 178
GR-CON-Z11-1473 Installation of Trees 21-May-24 25-May-24 3 131
GR-CON-Z11-6376 Installation of Shrubs 25-May-24 28-May-24 3 131
GR-CON-Z11-6386 Installation of Succulents 28-May-24 01-Jun-24 3 131
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-6396 Installation of Ground Covers 01-Jun-24 04-Jun-24 3 131


GR-CON-Z11-6406 Installation of Climbers 04-Jun-24 08-Jun-24 3 131
GR-CON-Z11-6416 Installation of Grass 08-Jun-24 11-Jun-24 3 131
GR-CON-Z11-6426 Installation of Lawns 11-Jun-24 15-Jun-24 3 131
GR-CON-Z11-1474 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 131
GR-CON-Z11-1475 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 131
GR-CON-Z11-1476 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 131
Irrigation Works 14-Feb-24 13-Jul-24 114 131
GR-CON-Z11-1477 Excavation Pipe Irrigation 14-Feb-24 20-Feb-24 5 109
GR-CON-Z11-1478 Sand Bedding 20-Feb-24 24-Feb-24 3 109
GR-CON-Z11-1479 HDPE Pipe Installations and fittings and conduit for cable 24-Feb-24 12-Mar-24 15 109
GR-CON-Z11-1481 Test pressure 12-Mar-24 19-Mar-24 5 109
GR-CON-Z11-1480 Installation of Valves and Accessories 19-Mar-24 25-Mar-24 4 109
GR-CON-Z11-1482 Back filling (sand / Subbase ) 26-Mar-24 03-Apr-24 6 109
GR-CON-Z11-1483 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Apr-24 17-Apr-24 6 193
GR-CON-Z11-1484 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jul-24
system 13-Jul-24 8 131
Government G-02 08-Feb-24 13-Jul-24 119 131
Site Preparation 08-Feb-24 02-Mar-24 19 231
GR-CON-Z11-1079 Demolition (Asphalt.Paving,etc.....) 08-Feb-24 13-Feb-24 4 101
GR-CON-Z11-1080 Excavation And Disposal 13-Feb-24 19-Feb-24 5 105
GR-CON-Z11-1081 Prepretion And Compaction 19-Feb-24 24-Feb-24 4 231
GR-CON-Z11-1082 Backfilling 24-Feb-24 02-Mar-24 6 231
Curbstone and Paving 19-Feb-24 24-Apr-24 46 195
GR-CON-Z11-1083 Excavation Curbstone 19-Feb-24 25-Feb-24 5 174
GR-CON-Z11-1084 Plain Concrete 25-Feb-24 03-Mar-24 6 195
GR-CON-Z11-1085 Installation Curbstone 03-Mar-24 13-Mar-24 9 195
GR-CON-Z11-1086 Casting Concrete (Mortar haunch) 13-Mar-24 19-Mar-24 4 195
GR-CON-Z11-1087 Backfilling (sand / Sub base) 19-Mar-24 02-Apr-24 9 195
GR-CON-Z11-1088 Installation of Paving 02-Apr-24 24-Apr-24 13 195
Landscape Works 25-Feb-24 13-Jul-24 105 131
GR-CON-Z11-1089 Excavation (Tree Pit ) 25-Feb-24 02-Mar-24 5 174
GR-CON-Z11-1090 Aggregate Drainage layer 02-Mar-24 09-Mar-24 6 174
GR-CON-Z11-1091 Installation Geotextile 09-Mar-24 13-Mar-24 4 174
GR-CON-Z11-1092 Backfilling (Soil max for tree) 13-Mar-24 23-Mar-24 6 174
GR-CON-Z11-1093 Installation of Trees 21-May-24 25-May-24 3 131
GR-CON-Z11-6496 Installation of Shrubs 25-May-24 28-May-24 3 131
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-6506 Installation of Succulents 28-May-24 01-Jun-24 3 131


GR-CON-Z11-6516 Installation of Ground Covers 01-Jun-24 04-Jun-24 3 131
GR-CON-Z11-6526 Installation of Climbers 04-Jun-24 08-Jun-24 3 131
GR-CON-Z11-6536 Installation of Grass 08-Jun-24 11-Jun-24 3 131
GR-CON-Z11-6546 Installation of Lawns 11-Jun-24 15-Jun-24 3 131
GR-CON-Z11-1094 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 131
GR-CON-Z11-1095 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 131
GR-CON-Z11-1096 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 131
Irrigation Works 19-Feb-24 13-Jul-24 110 131
GR-CON-Z11-1097 Excavation Pipe Irrigation 19-Feb-24 25-Feb-24 5 105
GR-CON-Z11-1098 Sand Bedding 25-Feb-24 28-Feb-24 3 105
GR-CON-Z11-1099 HDPE Pipe Installations and fittings and conduit for cable 28-Feb-24 18-Mar-24 15 105
GR-CON-Z11-1101 Test pressure 18-Mar-24 25-Mar-24 5 105
GR-CON-Z11-1100 Installation of Valves and Accessories 26-Mar-24 01-Apr-24 4 105
GR-CON-Z11-1102 Back filling (sand / Subbase ) 01-Apr-24 10-Apr-24 6 105
GR-CON-Z11-1103 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Apr-24 22-Apr-24 6 189
GR-CON-Z11-1104 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jul-24
system 13-Jul-24 8 131
Government G-05 13-Feb-24 13-Jul-24 115 131
Site Preparation 13-Feb-24 06-Mar-24 19 227
GR-CON-Z11-1105 Demolition (Asphalt.Paving,etc.....) 13-Feb-24 18-Feb-24 4 101
GR-CON-Z11-1106 Excavation And Disposal 18-Feb-24 24-Feb-24 5 101
GR-CON-Z11-1107 Prepretion And Compaction 24-Feb-24 28-Feb-24 4 227
GR-CON-Z11-1108 Backfilling 28-Feb-24 06-Mar-24 6 227
Curbstone and Paving 24-Feb-24 29-Apr-24 46 191
GR-CON-Z11-1109 Excavation Curbstone 24-Feb-24 29-Feb-24 5 170
GR-CON-Z11-1110 Plain Concrete 29-Feb-24 07-Mar-24 6 191
GR-CON-Z11-1111 Installation Curbstone 07-Mar-24 19-Mar-24 9 191
GR-CON-Z11-1112 Casting Concrete (Mortar haunch) 19-Mar-24 25-Mar-24 4 191
GR-CON-Z11-1113 Backfilling (sand / Sub base) 26-Mar-24 08-Apr-24 9 191
GR-CON-Z11-1114 Installation of Paving 09-Apr-24 29-Apr-24 13 191
Landscape Works 29-Feb-24 13-Jul-24 101 131
GR-CON-Z11-1115 Excavation (Tree Pit ) 29-Feb-24 06-Mar-24 5 170
GR-CON-Z11-1116 Aggregate Drainage layer 06-Mar-24 13-Mar-24 6 170
GR-CON-Z11-1117 Installation Geotextile 13-Mar-24 19-Mar-24 4 170
GR-CON-Z11-1118 Backfilling (Soil max for tree) 19-Mar-24 28-Mar-24 6 170
GR-CON-Z11-1119 Installation of Trees 21-May-24 25-May-24 3 131
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-6556 Installation of Shrubs 25-May-24 28-May-24 3 131


GR-CON-Z11-6566 Installation of Succulents 28-May-24 01-Jun-24 3 131
GR-CON-Z11-6576 Installation of Ground Covers 01-Jun-24 04-Jun-24 3 131
GR-CON-Z11-6586 Installation of Climbers 04-Jun-24 08-Jun-24 3 131
GR-CON-Z11-6596 Installation of Grass 08-Jun-24 11-Jun-24 3 131
GR-CON-Z11-6606 Installation of Lawns 11-Jun-24 15-Jun-24 3 131
GR-CON-Z11-1120 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 131
GR-CON-Z11-1121 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 131
GR-CON-Z11-1122 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 131
Irrigation Works 24-Feb-24 13-Jul-24 106 131
GR-CON-Z11-1123 Excavation Pipe Irrigation 24-Feb-24 29-Feb-24 5 101
GR-CON-Z11-1124 Sand Bedding 29-Feb-24 04-Mar-24 3 101
GR-CON-Z11-1125 HDPE Pipe Installations and fittings and conduit for cable 04-Mar-24 24-Mar-24 15 101
GR-CON-Z11-1127 Test pressure 24-Mar-24 01-Apr-24 5 101
GR-CON-Z11-1126 Installation of Valves and Accessories 01-Apr-24 07-Apr-24 4 101
GR-CON-Z11-1128 Back filling (sand / Subbase ) 07-Apr-24 20-Apr-24 6 101
GR-CON-Z11-1129 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Apr-24 27-Apr-24 6 185
GR-CON-Z11-1130 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jul-24
system 13-Jul-24 8 131
Health H-01 13-Jan-24 27-Jun-24 129 144
Site Preparation 13-Jan-24 30-Jan-24 15 258
GR-CON-Z11-1486 Excavation And Disposal 13-Jan-24 18-Jan-24 5 132
GR-CON-Z11-1487 Prepretion And Compaction 18-Jan-24 23-Jan-24 4 258
GR-CON-Z11-1488 Backfilling 23-Jan-24 30-Jan-24 6 258
Curbstone and Paving 18-Jan-24 12-Mar-24 46 222
GR-CON-Z11-1000 Excavation Curbstone 18-Jan-24 24-Jan-24 5 214
GR-CON-Z11-1001 Plain Concrete 24-Jan-24 31-Jan-24 6 222
GR-CON-Z11-1002 Installation Curbstone 31-Jan-24 11-Feb-24 9 222
GR-CON-Z11-1003 Casting Concrete (Mortar haunch) 11-Feb-24 15-Feb-24 4 222
GR-CON-Z11-1004 Backfilling (sand / Sub base) 15-Feb-24 26-Feb-24 9 222
GR-CON-Z11-1005 Installation of Paving 26-Feb-24 12-Mar-24 13 222
Landscape Works 24-Jan-24 27-Jun-24 119 144
GR-CON-Z11-1006 Excavation (Tree Pit ) 24-Jan-24 30-Jan-24 5 214
GR-CON-Z11-1007 Aggregate Drainage layer 30-Jan-24 06-Feb-24 6 214
GR-CON-Z11-1008 Installation Geotextile 06-Feb-24 11-Feb-24 4 214
GR-CON-Z11-1009 Backfilling (Soil max for tree) 11-Feb-24 18-Feb-24 6 214
GR-CON-Z11-1010 Installation of Trees 21-May-24 25-May-24 3 144
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z11-6316 Installation of Shrubs 25-May-24 28-May-24 3 144


GR-CON-Z11-6326 Installation of Succulents 28-May-24 01-Jun-24 3 144
GR-CON-Z11-6336 Installation of Ground Covers 01-Jun-24 04-Jun-24 3 144
GR-CON-Z11-6346 Installation of Climbers 04-Jun-24 08-Jun-24 3 144
GR-CON-Z11-6356 Installation of Grass 08-Jun-24 11-Jun-24 3 144
GR-CON-Z11-6366 Installation of Lawns 11-Jun-24 15-Jun-24 3 144
GR-CON-Z11-1011 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 144
GR-CON-Z11-1012 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 144
Irrigation Works 18-Jan-24 27-Jun-24 124 144
GR-CON-Z11-1014 Excavation Pipe Irrigation 18-Jan-24 24-Jan-24 5 132
GR-CON-Z11-1015 Sand Bedding 24-Jan-24 28-Jan-24 3 132
GR-CON-Z11-1016 HDPE Pipe Installations and fittings and conduit for cable 28-Jan-24 14-Feb-24 15 132
GR-CON-Z11-1018 Test pressure 14-Feb-24 20-Feb-24 5 132
GR-CON-Z11-1017 Installation of Valves and Accessories 20-Feb-24 25-Feb-24 4 132
GR-CON-Z11-1019 Back filling (sand / Subbase ) 25-Feb-24 03-Mar-24 6 132
GR-CON-Z11-1020 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Mar-24 10-Mar-24 6 216
GR-CON-Z11-1021 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jun-24
system 27-Jun-24 8 144
Existing Neighborhood Park ENP-02 18-Jan-24 13-Jun-24 116 152
Site Preparation 18-Jan-24 05-Feb-24 15 253
GR-CON-Z11-1061 Demolition (Asphalt.Paving,etc.....) 18-Jan-24 22-Jan-24 3 133
GR-CON-Z11-1062 Excavation And Disposal 22-Jan-24 27-Jan-24 4 133
GR-CON-Z11-1063 Prepretion And Compaction 27-Jan-24 30-Jan-24 3 253
GR-CON-Z11-1064 Backfilling 30-Jan-24 05-Feb-24 5 253
Landscape Works 27-Jan-24 13-Jun-24 109 152
GR-CON-Z11-1065 Excavation (Tree Pit ) 27-Jan-24 31-Jan-24 4 224
GR-CON-Z11-1066 Aggregate Drainage layer 31-Jan-24 06-Feb-24 5 224
GR-CON-Z11-1067 Installation Geotextile 06-Feb-24 10-Feb-24 3 224
GR-CON-Z11-1068 Backfilling (Soil max for tree) 10-Feb-24 15-Feb-24 5 224
GR-CON-Z11-1069 Installation of Trees 21-May-24 28-May-24 6 152
GR-CON-Z11-11488 Installation of Climbers 28-May-24 30-May-24 2 152
GR-CON-Z11-14136 Installation of Succulents 30-May-24 02-Jun-24 2 152
GR-CON-Z11-14146 Installation of Ground Covers 02-Jun-24 04-Jun-24 2 152
GR-CON-Z11-11498 Installation of Shrubs 04-Jun-24 06-Jun-24 2 152
GR-CON-Z11-11508 Installation of Grass 06-Jun-24 09-Jun-24 2 152
GR-CON-Z11-11518 Installation of Lawns 09-Jun-24 11-Jun-24 2 152
GR-CON-Z11-1070 Backfilling (Mulch) 11-Jun-24 13-Jun-24 2 152
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 27-Jan-24 13-Jun-24 109 152


GR-CON-Z11-1071 Excavation Pipe Irrigation 27-Jan-24 31-Jan-24 4 133
GR-CON-Z11-1072 Sand Bedding 31-Jan-24 03-Feb-24 2 133
GR-CON-Z11-1073 HDPE Pipe Installations and fittings and conduit for cable 03-Feb-24 17-Feb-24 12 133
GR-CON-Z11-1075 Test pressure 17-Feb-24 21-Feb-24 4 133
GR-CON-Z11-1074 Installation of Valves and Accessories 21-Feb-24 25-Feb-24 3 133
GR-CON-Z11-1076 Back filling (sand / Subbase ) 25-Feb-24 02-Mar-24 5 133
GR-CON-Z11-1077 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 02-Mar-24 07-Mar-24 5 220
GR-CON-Z11-1078 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Jun-24
system 13-Jun-24 6 152
Sector 3 07-Sep-23 07-Dec-24 376 6
Zone 19 07-Sep-23 06-Nov-24 349 1
Future Neighborhood Park FNP-17 07-Sep-23 27-Aug-24 289 61
Site Preparation 07-Sep-23 01-Oct-23 20 37
GR-CON-Z19-1202 Demolition (Asphalt.Paving,etc.....) 07-Sep-23 11-Sep-23 4 1
GR-CON-Z19-1203 Excavation And Disposal 12-Sep-23 18-Sep-23 6 1
GR-CON-Z19-1204 Prepretion And Compaction 19-Sep-23 24-Sep-23 4 37
GR-CON-Z19-1205 Backfilling 25-Sep-23 01-Oct-23 6 37
Curbstone and Paving 19-Sep-23 12-Nov-23 46 1
GR-CON-Z19-1206 Excavation Curbstone 19-Sep-23 25-Sep-23 5 1
GR-CON-Z19-1207 Plain Concrete 26-Sep-23 02-Oct-23 6 1
GR-CON-Z19-1208 Installation Curbstone 03-Oct-23 12-Oct-23 9 1
GR-CON-Z19-1209 Casting Concrete (Mortar haunch) 14-Oct-23 17-Oct-23 4 1
GR-CON-Z19-1210 Backfilling (sand / Sub base) 18-Oct-23 28-Oct-23 9 1
GR-CON-Z19-1211 Installation of Paving 29-Oct-23 12-Nov-23 13 1
Landscape Works 26-Sep-23 27-Aug-24 274 28
GR-CON-Z19-1212 Excavation (Tree Pit ) 26-Sep-23 01-Oct-23 5 248
GR-CON-Z19-1213 Aggregate Drainage layer 02-Oct-23 08-Oct-23 6 248
GR-CON-Z19-1214 Installation Geotextile 09-Oct-23 12-Oct-23 4 248
GR-CON-Z19-1215 Backfilling (Soil max for tree) 14-Oct-23 19-Oct-23 6 248
GR-CON-Z19-1216 Installation of Trees 18-Jul-24 21-Jul-24 2 28
GR-CON-Z19-2946 Installation of Shrubs 21-Jul-24 23-Jul-24 2 28
GR-CON-Z19-2956 Installation of Succulents 23-Jul-24 25-Jul-24 2 28
GR-CON-Z19-2966 Installation of Ground Covers 25-Jul-24 28-Jul-24 2 28
GR-CON-Z19-2976 Installation of Climbers 28-Jul-24 30-Jul-24 2 28
GR-CON-Z19-2986 Installation of Grass 30-Jul-24 01-Aug-24 2 28
GR-CON-Z19-2996 Installation of Lawns 01-Aug-24 04-Aug-24 2 28
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1217 Backfilling (Mulch) 04-Aug-24 07-Aug-24 3 28


GR-CON-Z19-1218 Natural Boulders Installation 07-Aug-24 12-Aug-24 4 28
GR-CON-Z19-1219 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Aug-24 27-Aug-24 13 28
Irrigation Works 19-Sep-23 27-Aug-24 279 61
GR-CON-Z19-1220 Excavation Pipe Irrigation 19-Sep-23 25-Sep-23 5 209
GR-CON-Z19-1221 Sand Bedding 26-Sep-23 28-Sep-23 3 209
GR-CON-Z19-1222 HDPE Pipe Installations and fittings and conduit for cable 30-Sep-23 16-Oct-23 15 209
GR-CON-Z19-1224 Test pressure 17-Oct-23 22-Oct-23 5 209
GR-CON-Z19-1223 Installation of Valves and Accessories 23-Oct-23 26-Oct-23 4 209
GR-CON-Z19-1225 Back filling (sand / Subbase ) 28-Oct-23 02-Nov-23 6 209
GR-CON-Z19-1226 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Nov-23 09-Nov-23 6 289
GR-CON-Z19-1227 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
18-Aug-24
system 27-Aug-24 8 61
Future Neighborhood Park FNP-18 13-Nov-23 19-Sep-24 253 41
Site Preparation 13-Nov-23 05-Dec-23 20 37
GR-CON-Z19-1228 Demolition (Asphalt.Paving,etc.....) 13-Nov-23 16-Nov-23 4 1
GR-CON-Z19-1229 Excavation And Disposal 18-Nov-23 22-Nov-23 5 1
GR-CON-Z19-1230 Prepretion And Compaction 23-Nov-23 27-Nov-23 4 37
GR-CON-Z19-1231 Backfilling 28-Nov-23 05-Dec-23 7 37
Curbstone and Paving 23-Nov-23 16-Jan-24 47 1
GR-CON-Z19-1232 Excavation Curbstone 23-Nov-23 28-Nov-23 5 1
GR-CON-Z19-1233 Plain Concrete 29-Nov-23 06-Dec-23 7 1
GR-CON-Z19-1234 Installation Curbstone 07-Dec-23 17-Dec-23 9 1
GR-CON-Z19-1235 Casting Concrete (Mortar haunch) 18-Dec-23 21-Dec-23 4 1
GR-CON-Z19-1236 Backfilling (sand / Sub base) 23-Dec-23 01-Jan-24 9 1
GR-CON-Z19-1237 Installation of Paving 02-Jan-24 16-Jan-24 13 1
Landscape Works 29-Nov-23 19-Sep-24 239 28
GR-CON-Z19-1238 Excavation (Tree Pit ) 29-Nov-23 04-Dec-23 5 198
GR-CON-Z19-1239 Aggregate Drainage layer 05-Dec-23 12-Dec-23 7 204
GR-CON-Z19-1240 Installation Geotextile 13-Dec-23 17-Dec-23 4 204
GR-CON-Z19-1241 Backfilling (Soil max for tree) 18-Dec-23 25-Dec-23 7 204
GR-CON-Z19-1242 Installation of Trees 18-Jul-24 21-Jul-24 2 41
GR-CON-Z19-3006 Installation of Shrubs 21-Jul-24 23-Jul-24 2 41
GR-CON-Z19-3016 Installation of Succulents 23-Jul-24 25-Jul-24 2 41
GR-CON-Z19-3026 Installation of Ground Covers 25-Jul-24 28-Jul-24 2 41
GR-CON-Z19-3036 Installation of Climbers 28-Jul-24 30-Jul-24 2 41
GR-CON-Z19-3046 Installation of Grass 30-Jul-24 01-Aug-24 2 41
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-3056 Installation of Lawns 01-Aug-24 04-Aug-24 2 41


GR-CON-Z19-1243 Backfilling (Mulch) 04-Aug-24 07-Aug-24 3 41
GR-CON-Z19-1244 Natural Boulders Installation 07-Aug-24 12-Aug-24 4 41
GR-CON-Z19-1245 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Aug-24 19-Sep-24 20 28
MUGA 05-Dec-23 19-Sep-24 234 41
GR-CON-Z19-1246 Excavation And Disposal 05-Dec-23 10-Dec-23 5 198
GR-CON-Z19-1247 Prepretion And Compaction 11-Dec-23 18-Dec-23 7 198
GR-CON-Z19-1248 polyethylene under footings ( fence and gates) 19-Dec-23 24-Dec-23 5 198
GR-CON-Z19-1249 Blinding concrete (flooring) 25-Dec-23 30-Dec-23 5 198
GR-CON-Z19-1250 Concrete Footings ( fence and gates) 31-Dec-23 14-Jan-24 13 198
GR-CON-Z19-1251 Tools Play Installation ( basketball / football ..) 15-Jan-24 31-Jan-24 15 198
GR-CON-Z19-1252 PaintAcrylic Play Surface 01-Feb-24 15-Feb-24 13 198
GR-CON-Z19-1253 Fence (high / low) / gates Installation 02-Sep-24 19-Sep-24 15 41
Irrigation Works 23-Nov-23 19-Sep-24 244 41
GR-CON-Z19-1254 Excavation Pipe Irrigation 23-Nov-23 28-Nov-23 5 153
GR-CON-Z19-1255 Sand Bedding 29-Nov-23 02-Dec-23 3 153
GR-CON-Z19-1256 HDPE Pipe Installations and fittings and conduit for cable 03-Dec-23 19-Dec-23 15 153
GR-CON-Z19-1258 Test pressure 20-Dec-23 25-Dec-23 5 153
GR-CON-Z19-1257 Installation of Valves and Accessories 26-Dec-23 30-Dec-23 4 153
GR-CON-Z19-1259 Back filling (sand / Subbase ) 31-Dec-23 07-Jan-24 7 153
GR-CON-Z19-1260 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-Jan-24 15-Jan-24 7 232
GR-CON-Z19-1261 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Sep-24
system 19-Sep-24 8 41
Future Neighborhood Park FNP-19 17-Jan-24 06-Oct-24 210 28
Site Preparation 17-Jan-24 08-Feb-24 20 1
GR-CON-Z19-1262 Demolition (Asphalt.Paving,etc.....) 17-Jan-24 21-Jan-24 4 1
GR-CON-Z19-1263 Excavation And Disposal 22-Jan-24 28-Jan-24 6 1
GR-CON-Z19-1264 Prepretion And Compaction 29-Jan-24 01-Feb-24 4 1
GR-CON-Z19-1265 Backfilling 03-Feb-24 08-Feb-24 6 1
Curbstone and Paving 29-Jan-24 25-Mar-24 46 183
GR-CON-Z19-1266 Excavation Curbstone 29-Jan-24 03-Feb-24 5 169
GR-CON-Z19-1267 Plain Concrete 04-Feb-24 10-Feb-24 6 183
GR-CON-Z19-1268 Installation Curbstone 11-Feb-24 20-Feb-24 9 183
GR-CON-Z19-1269 Casting Concrete (Mortar haunch) 21-Feb-24 25-Feb-24 4 183
GR-CON-Z19-1270 Backfilling (sand / Sub base) 26-Feb-24 06-Mar-24 9 183
GR-CON-Z19-1271 Installation of Paving 07-Mar-24 25-Mar-24 13 183
Landscape Works 04-Feb-24 06-Oct-24 195 28
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1272 Excavation (Tree Pit ) 04-Feb-24 08-Feb-24 5 169


GR-CON-Z19-1273 Aggregate Drainage layer 10-Feb-24 15-Feb-24 6 169
GR-CON-Z19-1274 Installation Geotextile 17-Feb-24 20-Feb-24 4 169
GR-CON-Z19-1275 Backfilling (Soil max for tree) 21-Feb-24 27-Feb-24 6 169
GR-CON-Z19-1276 Installation of Trees 18-Jul-24 21-Jul-24 2 61
GR-CON-Z19-3066 Installation of Shrubs 21-Jul-24 23-Jul-24 2 61
GR-CON-Z19-3076 Installation of Succulents 23-Jul-24 25-Jul-24 2 61
GR-CON-Z19-3086 Installation of Ground Covers 25-Jul-24 28-Jul-24 2 61
GR-CON-Z19-3096 Installation of Climbers 28-Jul-24 30-Jul-24 2 61
GR-CON-Z19-3106 Installation of Grass 30-Jul-24 01-Aug-24 2 61
GR-CON-Z19-3116 Installation of Lawns 01-Aug-24 04-Aug-24 2 61
GR-CON-Z19-1277 Backfilling (Mulch) 04-Aug-24 07-Aug-24 3 61
GR-CON-Z19-1278 Natural Boulders Installation 07-Aug-24 12-Aug-24 4 61
GR-CON-Z19-1279 Retaining walls . Steps, forming risers, treads and edges with finishes
19-Sep-24 06-Oct-24 13 28
Irrigation Works 29-Jan-24 06-Oct-24 200 28
GR-CON-Z19-1280 Excavation Pipe Irrigation 29-Jan-24 03-Feb-24 5 97
GR-CON-Z19-1281 Sand Bedding 04-Feb-24 06-Feb-24 3 97
GR-CON-Z19-1282 HDPE Pipe Installations and fittings and conduit for cable 07-Feb-24 24-Feb-24 15 97
GR-CON-Z19-1284 Test pressure 25-Feb-24 29-Feb-24 5 97
GR-CON-Z19-1283 Installation of Valves and Accessories 02-Mar-24 05-Mar-24 4 97
GR-CON-Z19-1285 Back filling (sand / Subbase ) 06-Mar-24 12-Mar-24 6 97
GR-CON-Z19-1286 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Mar-24 21-Mar-24 6 177
GR-CON-Z19-1287 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-Sep-24
system 06-Oct-24 8 28
Mosque M-31 10-Feb-24 01-Oct-24 186 32
Site Preparation 10-Feb-24 02-Mar-24 19 178
GR-CON-Z19-1288 Demolition (Asphalt.Paving,etc.....) 10-Feb-24 13-Feb-24 4 1
GR-CON-Z19-1289 Excavation And Disposal 14-Feb-24 19-Feb-24 5 78
GR-CON-Z19-1290 Prepretion And Compaction 20-Feb-24 24-Feb-24 4 178
GR-CON-Z19-1291 Backfilling 25-Feb-24 02-Mar-24 6 178
Curbstone and Paving 03-Mar-24 02-Apr-24 22 178
GR-CON-Z19-1296 Backfilling (sand / Sub base) 03-Mar-24 12-Mar-24 9 178
GR-CON-Z19-1297 Installation of Paving 13-Mar-24 02-Apr-24 13 178
Landscape Works 20-Feb-24 01-Oct-24 177 32
GR-CON-Z19-1298 Excavation (Tree Pit ) 20-Feb-24 25-Feb-24 5 126
GR-CON-Z19-1299 Aggregate Drainage layer 26-Feb-24 03-Mar-24 6 126
GR-CON-Z19-1300 Installation Geotextile 04-Mar-24 09-Mar-24 5 126
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1301 Backfilling (Soil max for tree) 10-Mar-24 16-Mar-24 5 126


GR-CON-Z19-1302 Installation of Trees 18-Jul-24 23-Jul-24 4 32
GR-CON-Z19-4826 Installation of Climbers 23-Jul-24 28-Jul-24 4 32
GR-CON-Z19-4836 Installation of Shrubs 28-Jul-24 01-Aug-24 4 32
GR-CON-Z19-4846 Installation of Succulents 01-Aug-24 06-Aug-24 4 32
GR-CON-Z19-4856 Installation of Ground Covers 06-Aug-24 11-Aug-24 4 32
GR-CON-Z19-1303 Backfilling (Mulch) 11-Aug-24 28-Aug-24 15 32
GR-CON-Z19-1304 Natural Boulders Installation 28-Aug-24 12-Sep-24 13 32
GR-CON-Z19-1305 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Sep-24 01-Oct-24 15 32
Irrigation Works 20-Feb-24 01-Oct-24 177 32
GR-CON-Z19-1306 Excavation Pipe Irrigation 20-Feb-24 25-Feb-24 5 78
GR-CON-Z19-1307 Sand Bedding 26-Feb-24 28-Feb-24 3 78
GR-CON-Z19-1308 HDPE Pipe Installations and fittings and conduit for cable 29-Feb-24 19-Mar-24 15 78
GR-CON-Z19-1310 Test pressure 19-Mar-24 26-Mar-24 5 78
GR-CON-Z19-1309 Installation of Valves and Accessories 27-Mar-24 02-Apr-24 4 78
GR-CON-Z19-1311 Back filling (sand / Subbase ) 02-Apr-24 11-Apr-24 6 78
GR-CON-Z19-1312 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Apr-24 23-Apr-24 6 160
GR-CON-Z19-1313 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
24-Sep-24
system 01-Oct-24 6 32
Parking P-20 12-Feb-24 20-Aug-24 149 67
Site Preparation 12-Feb-24 18-Feb-24 6 198
GR-CON-Z19-1317 Backfilling 12-Feb-24 18-Feb-24 6 198
GR-CON-Z19-1315 Excavation And Disposal 13-Feb-24 18-Feb-24 5 79
GR-CON-Z19-1314 Demolition (Asphalt.Paving,etc.....) 14-Feb-24 18-Feb-24 4 1
GR-CON-Z19-1316 Prepretion And Compaction 14-Feb-24 18-Feb-24 4 198
Curbstone and Paving 19-Feb-24 24-Apr-24 46 165
GR-CON-Z19-1318 Excavation Curbstone 19-Feb-24 24-Feb-24 5 157
GR-CON-Z19-1319 Plain Concrete 25-Feb-24 02-Mar-24 6 165
GR-CON-Z19-1320 Installation Curbstone 03-Mar-24 12-Mar-24 9 165
GR-CON-Z19-1321 Casting Concrete (Mortar haunch) 13-Mar-24 19-Mar-24 4 165
GR-CON-Z19-1322 Backfilling (sand / Sub base) 19-Mar-24 02-Apr-24 9 165
GR-CON-Z19-1323 Installation of Paving 02-Apr-24 24-Apr-24 13 165
Landscape Works 25-Feb-24 08-Aug-24 128 67
GR-CON-Z19-1324 Excavation (Tree Pit ) 25-Feb-24 29-Feb-24 5 157
GR-CON-Z19-1325 Aggregate Drainage layer 02-Mar-24 07-Mar-24 6 157
GR-CON-Z19-1326 Installation Geotextile 09-Mar-24 12-Mar-24 4 157
GR-CON-Z19-1327 Backfilling (Soil max for tree) 13-Mar-24 21-Mar-24 6 157
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1328 Installation of Trees 18-Jul-24 22-Jul-24 3 67


GR-CON-Z19-8936 Installation of Shrubs 22-Jul-24 25-Jul-24 3 67
GR-CON-Z19-8946 Installation of Ground Covers 25-Jul-24 29-Jul-24 3 67
GR-CON-Z19-8956 Installation of Succulents 29-Jul-24 01-Aug-24 3 67
GR-CON-Z19-8966 Installation of Grass 01-Aug-24 05-Aug-24 3 67
GR-CON-Z19-1329 Backfilling (Mulch) 05-Aug-24 08-Aug-24 3 67
Site Furnishing 08-Aug-24 20-Aug-24 10 67
GR-CON-Z19-1340 Tree Grate 08-Aug-24 14-Aug-24 5 67
GR-CON-Z19-1341 Wheel stoppers 14-Aug-24 20-Aug-24 5 67
Irrigation Works 19-Feb-24 20-Aug-24 143 67
GR-CON-Z19-1332 Excavation Pipe Irrigation 19-Feb-24 24-Feb-24 5 79
GR-CON-Z19-1333 Sand Bedding 25-Feb-24 27-Feb-24 3 79
GR-CON-Z19-1334 HDPE Pipe Installations and fittings and conduit for cable 28-Feb-24 17-Mar-24 15 79
GR-CON-Z19-1336 Test pressure 18-Mar-24 25-Mar-24 5 79
GR-CON-Z19-1335 Installation of Valves and Accessories 25-Mar-24 31-Mar-24 4 79
GR-CON-Z19-1337 Back filling (sand / Subbase ) 01-Apr-24 09-Apr-24 6 79
GR-CON-Z19-1338 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Apr-24 22-Apr-24 6 159
GR-CON-Z19-1339 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
11-Aug-24
system 20-Aug-24 8 67
Parking P-37 17-Feb-24 20-Aug-24 145 67
Site Preparation 17-Feb-24 22-Feb-24 6 194
GR-CON-Z19-1345 Backfilling 17-Feb-24 22-Feb-24 6 194
GR-CON-Z19-1343 Excavation And Disposal 18-Feb-24 22-Feb-24 5 75
GR-CON-Z19-1342 Demolition (Asphalt.Paving,etc.....) 19-Feb-24 22-Feb-24 4 1
GR-CON-Z19-1344 Prepretion And Compaction 19-Feb-24 22-Feb-24 4 194
Curbstone and Paving 24-Feb-24 29-Apr-24 46 161
GR-CON-Z19-1346 Excavation Curbstone 24-Feb-24 28-Feb-24 5 153
GR-CON-Z19-1347 Plain Concrete 29-Feb-24 06-Mar-24 6 161
GR-CON-Z19-1348 Installation Curbstone 07-Mar-24 19-Mar-24 9 161
GR-CON-Z19-1349 Casting Concrete (Mortar haunch) 19-Mar-24 25-Mar-24 4 161
GR-CON-Z19-1350 Backfilling (sand / Sub base) 25-Mar-24 08-Apr-24 9 161
GR-CON-Z19-1351 Installation of Paving 08-Apr-24 29-Apr-24 13 161
Landscape Works 29-Feb-24 08-Aug-24 124 67
GR-CON-Z19-1352 Excavation (Tree Pit ) 29-Feb-24 05-Mar-24 5 153
GR-CON-Z19-1353 Aggregate Drainage layer 06-Mar-24 12-Mar-24 6 153
GR-CON-Z19-1354 Installation Geotextile 13-Mar-24 19-Mar-24 4 153
GR-CON-Z19-1355 Backfilling (Soil max for tree) 19-Mar-24 28-Mar-24 6 153
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1356 Installation of Trees 18-Jul-24 22-Jul-24 3 67


GR-CON-Z19-8976 Installation of Shrubs 22-Jul-24 25-Jul-24 3 67
GR-CON-Z19-8986 Installation of Ground Covers 25-Jul-24 29-Jul-24 3 67
GR-CON-Z19-8996 Installation of Succulents 29-Jul-24 01-Aug-24 3 67
GR-CON-Z19-9006 Installation of Grass 01-Aug-24 05-Aug-24 3 67
GR-CON-Z19-1357 Backfilling (Mulch) 05-Aug-24 08-Aug-24 3 67
Site Furnishing 08-Aug-24 20-Aug-24 10 67
GR-CON-Z19-1368 Tree Grate 08-Aug-24 14-Aug-24 5 67
GR-CON-Z19-1369 Wheel stoppers 14-Aug-24 20-Aug-24 5 67
Irrigation Works 24-Feb-24 20-Aug-24 139 67
GR-CON-Z19-1360 Excavation Pipe Irrigation 24-Feb-24 28-Feb-24 5 75
GR-CON-Z19-1361 Sand Bedding 29-Feb-24 03-Mar-24 3 75
GR-CON-Z19-1362 HDPE Pipe Installations and fittings and conduit for cable 04-Mar-24 24-Mar-24 15 75
GR-CON-Z19-1364 Test pressure 24-Mar-24 31-Mar-24 5 75
GR-CON-Z19-1363 Installation of Valves and Accessories 01-Apr-24 07-Apr-24 4 75
GR-CON-Z19-1365 Back filling (sand / Subbase ) 07-Apr-24 20-Apr-24 6 75
GR-CON-Z19-1366 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Apr-24 27-Apr-24 6 155
GR-CON-Z19-1367 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
11-Aug-24
system 20-Aug-24 8 67
Street SS-20.2 24-Feb-24 21-Sep-24 166 40
Site Preparation 24-Feb-24 20-Mar-24 21 186
GR-CON-Z19-1000 Demolition (Asphalt.Paving,etc.....) 24-Feb-24 27-Feb-24 4 1
GR-CON-Z19-1001 Excavation And Disposal 28-Feb-24 04-Mar-24 5 65
GR-CON-Z19-1002 Prepretion And Compaction 05-Mar-24 11-Mar-24 6 186
GR-CON-Z19-1003 Backfilling 12-Mar-24 20-Mar-24 6 186
Curbstone and Paving 05-Mar-24 09-May-24 46 152
GR-CON-Z19-1004 Excavation Curbstone 05-Mar-24 10-Mar-24 5 117
GR-CON-Z19-1005 Plain Concrete 11-Mar-24 19-Mar-24 6 152
GR-CON-Z19-1006 Installation Curbstone 19-Mar-24 02-Apr-24 9 152
GR-CON-Z19-1007 Casting Concrete (Mortar haunch) 02-Apr-24 08-Apr-24 4 152
GR-CON-Z19-1008 Backfilling (sand / Sub base) 08-Apr-24 24-Apr-24 9 152
GR-CON-Z19-1009 Installation of Paving 24-Apr-24 09-May-24 13 152
Landscape Works 11-Mar-24 28-Aug-24 132 40
GR-CON-Z19-1010 Excavation (Tree Pit ) 11-Mar-24 17-Mar-24 5 117
GR-CON-Z19-1011 Aggregate Drainage layer 18-Mar-24 26-Mar-24 6 117
GR-CON-Z19-1012 Installation Geotextile 27-Mar-24 02-Apr-24 4 117
GR-CON-Z19-1013 Backfilling (Soil max for tree) 02-Apr-24 11-Apr-24 6 117
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1014 Installation of Trees 18-Jul-24 22-Jul-24 3 40


GR-CON-Z19-13856 Installation of Shrubs 22-Jul-24 25-Jul-24 3 40
GR-CON-Z19-13866 Installation of Succulents 25-Jul-24 29-Jul-24 3 40
GR-CON-Z19-13876 Installation of Ground Covers 29-Jul-24 01-Aug-24 3 40
GR-CON-Z19-13886 Installation of Grass 01-Aug-24 05-Aug-24 3 40
GR-CON-Z19-1015 Backfilling (Mulch) 05-Aug-24 08-Aug-24 3 40
GR-CON-Z19-1016 Natural Boulders Installation 08-Aug-24 13-Aug-24 4 40
GR-CON-Z19-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
13-Aug-24 28-Aug-24 13 40
Site Furnishing 28-Aug-24 21-Sep-24 20 40
GR-CON-Z19-1026 Garden planter box 28-Aug-24 03-Sep-24 5 40
GR-CON-Z19-1027 Wheel stoppers 03-Sep-24 09-Sep-24 5 40
GR-CON-Z19-1028 Steel Lattice 09-Sep-24 15-Sep-24 5 40
GR-CON-Z19-1029 Handrail 15-Sep-24 21-Sep-24 5 40
Storm Piping Works 14-Sep-24 21-Sep-24 6 40
GR-CON-Z19-1030 Installation of DI grating covers 14-Sep-24 21-Sep-24 6 40
Irrigation Works 05-Mar-24 18-May-24 53 139
GR-CON-Z19-1018 Excavation Pipe Irrigation 05-Mar-24 10-Mar-24 5 65
GR-CON-Z19-1019 Sand Bedding 11-Mar-24 16-Mar-24 4 65
GR-CON-Z19-1020 HDPE Pipe Installations and fittings and conduit for cable 16-Mar-24 08-Apr-24 15 65
GR-CON-Z19-1022 Test pressure 08-Apr-24 20-Apr-24 5 65
GR-CON-Z19-1021 Installation of Valves and Accessories 20-Apr-24 24-Apr-24 4 65
GR-CON-Z19-1023 Back filling (sand / Subbase ) 24-Apr-24 01-May-24 6 65
GR-CON-Z19-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-May-24 08-May-24 6 139
GR-CON-Z19-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-May-24
system 18-May-24 8 139
Electrical Works 11-Mar-24 21-Sep-24 152 40
GR-CON-Z19-1031 Excavation And Disposal 11-Mar-24 17-Mar-24 5 166
GR-CON-Z19-1032 Sand Bedding 18-Mar-24 24-Mar-24 4 166
GR-CON-Z19-1033 laying cables 24-Mar-24 30-Mar-24 4 166
GR-CON-Z19-1034 Backfilling (sand / Sub base) 30-Mar-24 07-Apr-24 5 166
GR-CON-Z19-1035 Control Panel / Distribution Panel Installation 07-Apr-24 17-Apr-24 4 166
GR-CON-Z19-1036 Road Crossing Ducts 15-Sep-24 21-Sep-24 5 40
Street SS-27 28-Feb-24 06-Nov-24 201 1
Site Preparation 28-Feb-24 29-Apr-24 42 161
GR-CON-Z19-1037 Demolition (Asphalt.Paving,etc.....) 28-Feb-24 07-Mar-24 8 1
GR-CON-Z19-1038 Excavation And Disposal 09-Mar-24 21-Mar-24 10 1
GR-CON-Z19-1039 Prepretion And Compaction 23-Mar-24 09-Apr-24 12 161
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1040 Backfilling 10-Apr-24 29-Apr-24 12 161


Curbstone and Paving 23-Mar-24 13-Jul-24 84 101
GR-CON-Z19-1041 Excavation Curbstone 23-Mar-24 07-Apr-24 10 39
GR-CON-Z19-1042 Plain Concrete 07-Apr-24 27-Apr-24 12 101
GR-CON-Z19-1043 Installation Curbstone 27-Apr-24 11-May-24 12 101
GR-CON-Z19-1044 Casting Concrete (Mortar haunch) 11-May-24 20-May-24 8 101
GR-CON-Z19-1045 Backfilling (sand / Sub base) 20-May-24 10-Jun-24 18 101
GR-CON-Z19-1046 Installation of Paving 10-Jun-24 13-Jul-24 24 101
Landscape Works 07-Apr-24 19-Sep-24 133 1
GR-CON-Z19-1047 Excavation (Tree Pit ) 07-Apr-24 24-Apr-24 10 39
GR-CON-Z19-1048 Aggregate Drainage layer 24-Apr-24 08-May-24 12 39
GR-CON-Z19-1049 Installation Geotextile 08-May-24 18-May-24 8 39
GR-CON-Z19-1050 Backfilling (Soil max for tree) 18-May-24 01-Jun-24 12 39
GR-CON-Z19-1051 Installation of Trees 18-Jul-24 23-Jul-24 4 1
GR-CON-Z19-13896 Installation of Shrubs 23-Jul-24 27-Jul-24 3 1
GR-CON-Z19-13906 Installation of Succulents 27-Jul-24 30-Jul-24 3 1
GR-CON-Z19-13916 Installation of Ground Covers 30-Jul-24 03-Aug-24 3 1
GR-CON-Z19-13926 Installation of Grass 03-Aug-24 06-Aug-24 3 1
GR-CON-Z19-1052 Backfilling (Mulch) 06-Aug-24 13-Aug-24 6 1
GR-CON-Z19-1053 Natural Boulders Installation 13-Aug-24 22-Aug-24 8 1
GR-CON-Z19-1054 Retaining walls . Steps, forming risers, treads and edges with finishes
22-Aug-24 19-Sep-24 24 1
Site Furnishing 19-Sep-24 06-Nov-24 40 1
GR-CON-Z19-1063 Garden planter box 19-Sep-24 02-Oct-24 10 1
GR-CON-Z19-1064 Wheel stoppers 02-Oct-24 14-Oct-24 10 1
GR-CON-Z19-1065 Steel Lattice 14-Oct-24 26-Oct-24 10 1
GR-CON-Z19-1066 Handrail 26-Oct-24 06-Nov-24 10 1
Storm Piping Works 23-Oct-24 06-Nov-24 12 1
GR-CON-Z19-1067 Installation of DI grating covers 23-Oct-24 06-Nov-24 12 1
Irrigation Works 23-Mar-24 23-Jul-24 93 79
GR-CON-Z19-1055 Excavation Pipe Irrigation 23-Mar-24 07-Apr-24 10 1
GR-CON-Z19-1056 Sand Bedding 07-Apr-24 22-Apr-24 8 1
GR-CON-Z19-1057 HDPE Pipe Installations and fittings and conduit for cable 22-Apr-24 20-May-24 24 1
GR-CON-Z19-1059 Test pressure 20-May-24 01-Jun-24 10 1
GR-CON-Z19-1058 Installation of Valves and Accessories 01-Jun-24 10-Jun-24 8 1
GR-CON-Z19-1060 Back filling (sand / Subbase ) 05-Jun-24 16-Jun-24 9 1
GR-CON-Z19-1061 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Jun-24 04-Jul-24 12 79
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1062 Pull box , Decoders , Connecting to plots /Connection to infra irrigation


04-Jul-24
system 23-Jul-24 16 79
Electrical Works 07-Apr-24 06-Nov-24 173 1
GR-CON-Z19-1068 Excavation And Disposal 07-Apr-24 24-Apr-24 10 121
GR-CON-Z19-1069 Sand Bedding 24-Apr-24 04-May-24 8 121
GR-CON-Z19-1070 laying cables 04-May-24 13-May-24 8 121
GR-CON-Z19-1071 Backfilling (sand / Sub base) 13-May-24 25-May-24 10 121
GR-CON-Z19-1072 Control Panel / Distribution Panel Installation 25-May-24 03-Jun-24 8 121
GR-CON-Z19-1073 Road Crossing Ducts 26-Oct-24 06-Nov-24 10 1
Street SS-74 09-Mar-24 21-Sep-24 154 40
Site Preparation 09-Mar-24 08-Apr-24 21 174
GR-CON-Z19-1074 Demolition (Asphalt.Paving,etc.....) 09-Mar-24 12-Mar-24 4 15
GR-CON-Z19-1075 Excavation And Disposal 13-Mar-24 20-Mar-24 5 53
GR-CON-Z19-1076 Prepretion And Compaction 20-Mar-24 30-Mar-24 6 174
GR-CON-Z19-1077 Backfilling 30-Mar-24 08-Apr-24 6 174
Curbstone and Paving 20-Mar-24 23-May-24 46 140
GR-CON-Z19-1078 Excavation Curbstone 20-Mar-24 28-Mar-24 5 105
GR-CON-Z19-1079 Plain Concrete 28-Mar-24 07-Apr-24 6 140
GR-CON-Z19-1080 Installation Curbstone 07-Apr-24 23-Apr-24 9 140
GR-CON-Z19-1081 Casting Concrete (Mortar haunch) 23-Apr-24 28-Apr-24 4 140
GR-CON-Z19-1082 Backfilling (sand / Sub base) 28-Apr-24 08-May-24 9 140
GR-CON-Z19-1083 Installation of Paving 08-May-24 23-May-24 13 140
Landscape Works 28-Mar-24 28-Aug-24 120 40
GR-CON-Z19-1084 Excavation (Tree Pit ) 28-Mar-24 04-Apr-24 5 105
GR-CON-Z19-1085 Aggregate Drainage layer 06-Apr-24 18-Apr-24 6 105
GR-CON-Z19-1086 Installation Geotextile 18-Apr-24 23-Apr-24 4 105
GR-CON-Z19-1087 Backfilling (Soil max for tree) 23-Apr-24 30-Apr-24 6 105
GR-CON-Z19-1088 Installation of Trees 18-Jul-24 22-Jul-24 3 40
GR-CON-Z19-13936 Installation of Shrubs 22-Jul-24 25-Jul-24 3 40
GR-CON-Z19-13946 Installation of Succulents 25-Jul-24 29-Jul-24 3 40
GR-CON-Z19-13956 Installation of Ground Covers 29-Jul-24 01-Aug-24 3 40
GR-CON-Z19-13966 Installation of Grass 01-Aug-24 05-Aug-24 3 40
GR-CON-Z19-1089 Backfilling (Mulch) 05-Aug-24 08-Aug-24 3 40
GR-CON-Z19-1090 Natural Boulders Installation 08-Aug-24 13-Aug-24 4 40
GR-CON-Z19-1091 Retaining walls . Steps, forming risers, treads and edges with finishes
13-Aug-24 28-Aug-24 13 40
Site Furnishing 28-Aug-24 21-Sep-24 20 40
GR-CON-Z19-1100 Garden planter box 28-Aug-24 03-Sep-24 5 40
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1101 Wheel stoppers 03-Sep-24 09-Sep-24 5 40


GR-CON-Z19-1102 Steel Lattice 09-Sep-24 15-Sep-24 5 40
GR-CON-Z19-1103 Handrail 15-Sep-24 21-Sep-24 5 40
Storm Piping Works 14-Sep-24 21-Sep-24 6 40
GR-CON-Z19-1104 Installation of DI grating covers 14-Sep-24 21-Sep-24 6 40
Irrigation Works 20-Mar-24 01-Jun-24 53 127
GR-CON-Z19-1092 Excavation Pipe Irrigation 20-Mar-24 28-Mar-24 5 53
GR-CON-Z19-1093 Sand Bedding 28-Mar-24 03-Apr-24 4 53
GR-CON-Z19-1094 HDPE Pipe Installations and fittings and conduit for cable 03-Apr-24 28-Apr-24 15 53
GR-CON-Z19-1096 Test pressure 28-Apr-24 04-May-24 5 53
GR-CON-Z19-1095 Installation of Valves and Accessories 04-May-24 08-May-24 4 53
GR-CON-Z19-1097 Back filling (sand / Subbase ) 08-May-24 15-May-24 6 53
GR-CON-Z19-1098 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-May-24 22-May-24 6 127
GR-CON-Z19-1099 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-May-24
system 01-Jun-24 8 127
Electrical Works 28-Mar-24 21-Sep-24 140 40
GR-CON-Z19-1105 Excavation And Disposal 28-Mar-24 04-Apr-24 5 154
GR-CON-Z19-1106 Sand Bedding 06-Apr-24 11-Apr-24 4 154
GR-CON-Z19-1107 laying cables 11-Apr-24 21-Apr-24 4 154
GR-CON-Z19-1108 Backfilling (sand / Sub base) 21-Apr-24 27-Apr-24 5 154
GR-CON-Z19-1109 Control Panel / Distribution Panel Installation 27-Apr-24 01-May-24 4 154
GR-CON-Z19-1110 Road Crossing Ducts 15-Sep-24 21-Sep-24 5 40
Street SS-75 13-Mar-24 21-Sep-24 150 40
Site Preparation 13-Mar-24 18-Apr-24 21 170
GR-CON-Z19-1111 Demolition (Asphalt.Paving,etc.....) 13-Mar-24 19-Mar-24 4 15
GR-CON-Z19-1112 Excavation And Disposal 19-Mar-24 26-Mar-24 5 49
GR-CON-Z19-1113 Prepretion And Compaction 27-Mar-24 04-Apr-24 6 170
GR-CON-Z19-1114 Backfilling 06-Apr-24 18-Apr-24 6 170
Curbstone and Paving 27-Mar-24 28-May-24 46 136
GR-CON-Z19-1115 Excavation Curbstone 27-Mar-24 03-Apr-24 5 101
GR-CON-Z19-1116 Plain Concrete 03-Apr-24 17-Apr-24 6 136
GR-CON-Z19-1117 Installation Curbstone 17-Apr-24 28-Apr-24 9 136
GR-CON-Z19-1118 Casting Concrete (Mortar haunch) 28-Apr-24 02-May-24 4 136
GR-CON-Z19-1119 Backfilling (sand / Sub base) 02-May-24 13-May-24 9 136
GR-CON-Z19-1120 Installation of Paving 13-May-24 28-May-24 13 136
Landscape Works 03-Apr-24 28-Aug-24 116 40
GR-CON-Z19-1121 Excavation (Tree Pit ) 03-Apr-24 11-Apr-24 5 101
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1122 Aggregate Drainage layer 11-Apr-24 23-Apr-24 6 101


GR-CON-Z19-1123 Installation Geotextile 23-Apr-24 28-Apr-24 4 101
GR-CON-Z19-1124 Backfilling (Soil max for tree) 28-Apr-24 05-May-24 6 101
GR-CON-Z19-1125 Installation of Trees 18-Jul-24 22-Jul-24 3 40
GR-CON-Z19-13976 Installation of Shrubs 22-Jul-24 25-Jul-24 3 40
GR-CON-Z19-13986 Installation of Succulents 25-Jul-24 29-Jul-24 3 40
GR-CON-Z19-13996 Installation of Ground Covers 29-Jul-24 01-Aug-24 3 40
GR-CON-Z19-14006 Installation of Grass 01-Aug-24 05-Aug-24 3 40
GR-CON-Z19-1126 Backfilling (Mulch) 05-Aug-24 08-Aug-24 3 40
GR-CON-Z19-1127 Natural Boulders Installation 08-Aug-24 13-Aug-24 4 40
GR-CON-Z19-1128 Retaining walls . Steps, forming risers, treads and edges with finishes
13-Aug-24 28-Aug-24 13 40
Site Furnishing 28-Aug-24 21-Sep-24 20 40
GR-CON-Z19-1137 Garden planter box 28-Aug-24 03-Sep-24 5 40
GR-CON-Z19-1138 Wheel stoppers 03-Sep-24 09-Sep-24 5 40
GR-CON-Z19-1139 Steel Lattice 09-Sep-24 15-Sep-24 5 40
GR-CON-Z19-1140 Handrail 15-Sep-24 21-Sep-24 5 40
Storm Piping Works 14-Sep-24 21-Sep-24 6 40
GR-CON-Z19-1141 Installation of DI grating covers 14-Sep-24 21-Sep-24 6 40
Irrigation Works 27-Mar-24 05-Jun-24 53 123
GR-CON-Z19-1129 Excavation Pipe Irrigation 27-Mar-24 03-Apr-24 5 49
GR-CON-Z19-1130 Sand Bedding 03-Apr-24 09-Apr-24 4 49
GR-CON-Z19-1131 HDPE Pipe Installations and fittings and conduit for cable 10-Apr-24 02-May-24 15 49
GR-CON-Z19-1133 Test pressure 02-May-24 08-May-24 5 49
GR-CON-Z19-1132 Installation of Valves and Accessories 08-May-24 13-May-24 4 49
GR-CON-Z19-1134 Back filling (sand / Subbase ) 13-May-24 20-May-24 6 49
GR-CON-Z19-1135 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-May-24 27-May-24 6 123
GR-CON-Z19-1136 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
27-May-24
system 05-Jun-24 8 123
Electrical Works 03-Apr-24 21-Sep-24 136 40
GR-CON-Z19-1142 Excavation And Disposal 03-Apr-24 11-Apr-24 5 150
GR-CON-Z19-1143 Sand Bedding 11-Apr-24 21-Apr-24 4 150
GR-CON-Z19-1144 laying cables 21-Apr-24 25-Apr-24 4 150
GR-CON-Z19-1145 Backfilling (sand / Sub base) 25-Apr-24 01-May-24 5 150
GR-CON-Z19-1146 Control Panel / Distribution Panel Installation 01-May-24 06-May-24 4 150
GR-CON-Z19-1147 Road Crossing Ducts 15-Sep-24 21-Sep-24 5 40
Street SS-76 19-Mar-24 21-Sep-24 146 40
Site Preparation 19-Mar-24 23-Apr-24 21 166
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1148 Demolition (Asphalt.Paving,etc.....) 19-Mar-24 25-Mar-24 4 15


GR-CON-Z19-1149 Excavation And Disposal 25-Mar-24 02-Apr-24 5 45
GR-CON-Z19-1150 Prepretion And Compaction 02-Apr-24 11-Apr-24 6 166
GR-CON-Z19-1151 Backfilling 11-Apr-24 23-Apr-24 6 166
Curbstone and Paving 02-Apr-24 02-Jun-24 46 132
GR-CON-Z19-1152 Excavation Curbstone 02-Apr-24 09-Apr-24 5 97
GR-CON-Z19-1153 Plain Concrete 10-Apr-24 22-Apr-24 6 132
GR-CON-Z19-1154 Installation Curbstone 22-Apr-24 02-May-24 9 132
GR-CON-Z19-1155 Casting Concrete (Mortar haunch) 02-May-24 07-May-24 4 132
GR-CON-Z19-1156 Backfilling (sand / Sub base) 07-May-24 18-May-24 9 132
GR-CON-Z19-1157 Installation of Paving 18-May-24 02-Jun-24 13 132
Landscape Works 10-Apr-24 28-Aug-24 112 40
GR-CON-Z19-1158 Excavation (Tree Pit ) 10-Apr-24 21-Apr-24 5 97
GR-CON-Z19-1159 Aggregate Drainage layer 21-Apr-24 28-Apr-24 6 97
GR-CON-Z19-1160 Installation Geotextile 28-Apr-24 02-May-24 4 97
GR-CON-Z19-1161 Backfilling (Soil max for tree) 02-May-24 09-May-24 6 97
GR-CON-Z19-1162 Installation of Trees 18-Jul-24 22-Jul-24 3 40
GR-CON-Z19-14016 Installation of Shrubs 22-Jul-24 25-Jul-24 3 40
GR-CON-Z19-14026 Installation of Succulents 25-Jul-24 29-Jul-24 3 40
GR-CON-Z19-14036 Installation of Ground Covers 29-Jul-24 01-Aug-24 3 40
GR-CON-Z19-14046 Installation of Grass 01-Aug-24 05-Aug-24 3 40
GR-CON-Z19-1163 Backfilling (Mulch) 05-Aug-24 08-Aug-24 3 40
GR-CON-Z19-1164 Natural Boulders Installation 08-Aug-24 13-Aug-24 4 40
GR-CON-Z19-1165 Retaining walls . Steps, forming risers, treads and edges with finishes
13-Aug-24 28-Aug-24 13 40
Site Furnishing 28-Aug-24 21-Sep-24 20 40
GR-CON-Z19-1174 Garden planter box 28-Aug-24 03-Sep-24 5 40
GR-CON-Z19-1175 Wheel stoppers 03-Sep-24 09-Sep-24 5 40
GR-CON-Z19-1176 Steel Lattice 09-Sep-24 15-Sep-24 5 40
GR-CON-Z19-1177 Handrail 15-Sep-24 21-Sep-24 5 40
Storm Piping Works 14-Sep-24 21-Sep-24 6 40
GR-CON-Z19-1178 Installation of DI grating covers 14-Sep-24 21-Sep-24 6 40
Irrigation Works 02-Apr-24 10-Jun-24 53 119
GR-CON-Z19-1166 Excavation Pipe Irrigation 02-Apr-24 09-Apr-24 5 45
GR-CON-Z19-1167 Sand Bedding 10-Apr-24 20-Apr-24 4 45
GR-CON-Z19-1168 HDPE Pipe Installations and fittings and conduit for cable 20-Apr-24 07-May-24 15 45
GR-CON-Z19-1170 Test pressure 07-May-24 13-May-24 5 45
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1169 Installation of Valves and Accessories 13-May-24 18-May-24 4 45


GR-CON-Z19-1171 Back filling (sand / Subbase ) 18-May-24 25-May-24 6 45
GR-CON-Z19-1172 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-May-24 01-Jun-24 6 119
GR-CON-Z19-1173 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
01-Jun-24
system 10-Jun-24 8 119
Electrical Works 10-Apr-24 21-Sep-24 132 40
GR-CON-Z19-1179 Excavation And Disposal 10-Apr-24 21-Apr-24 5 146
GR-CON-Z19-1180 Sand Bedding 21-Apr-24 25-Apr-24 4 146
GR-CON-Z19-1181 laying cables 25-Apr-24 30-Apr-24 4 146
GR-CON-Z19-1182 Backfilling (sand / Sub base) 30-Apr-24 06-May-24 5 146
GR-CON-Z19-1183 Control Panel / Distribution Panel Installation 06-May-24 11-May-24 4 146
GR-CON-Z19-1370 Road Crossing Ducts 15-Sep-24 21-Sep-24 5 40
Existing Neighborhood Park ENP-04 25-Mar-24 15-Aug-24 111 71
Site Preparation 25-Mar-24 08-May-24 30 153
GR-CON-Z19-1184 Demolition (Asphalt.Paving,etc.....) 25-Mar-24 03-Apr-24 6 15
GR-CON-Z19-1185 Excavation And Disposal 03-Apr-24 20-Apr-24 8 15
GR-CON-Z19-1186 Prepretion And Compaction 20-Apr-24 27-Apr-24 6 153
GR-CON-Z19-1187 Backfilling 27-Apr-24 08-May-24 10 153
Landscape Works 20-Apr-24 15-Aug-24 97 71
GR-CON-Z19-1188 Excavation (Tree Pit ) 20-Apr-24 29-Apr-24 8 111
GR-CON-Z19-1189 Aggregate Drainage layer 29-Apr-24 11-May-24 10 111
GR-CON-Z19-1190 Installation Geotextile 11-May-24 18-May-24 6 111
GR-CON-Z19-1191 Backfilling (Soil max for tree) 18-May-24 29-May-24 10 111
GR-CON-Z19-1192 Installation of Trees 18-Jul-24 23-Jul-24 4 71
GR-CON-Z19-11648 Installation of Climbers 23-Jul-24 28-Jul-24 4 71
GR-CON-Z19-11658 Installation of Shrubs 28-Jul-24 01-Aug-24 4 71
GR-CON-Z19-14216 Installation of Succulents 28-Jul-24 01-Aug-24 4 71
GR-CON-Z19-11668 Installation of Grass 01-Aug-24 06-Aug-24 4 71
GR-CON-Z19-14226 Installation of Ground Covers 01-Aug-24 06-Aug-24 4 71
GR-CON-Z19-11678 Installation of Lawns 06-Aug-24 11-Aug-24 4 71
GR-CON-Z19-1193 Backfilling (Mulch) 11-Aug-24 15-Aug-24 4 71
Irrigation Works 20-Apr-24 15-Aug-24 97 71
GR-CON-Z19-1194 Excavation Pipe Irrigation 20-Apr-24 29-Apr-24 8 15
GR-CON-Z19-1195 Sand Bedding 29-Apr-24 04-May-24 4 15
GR-CON-Z19-1196 HDPE Pipe Installations and fittings and conduit for cable 04-May-24 01-Jun-24 24 15
GR-CON-Z19-1198 Test pressure 01-Jun-24 10-Jun-24 8 15
GR-CON-Z19-1197 Installation of Valves and Accessories 10-Jun-24 17-Jun-24 6 15
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z19-1199 Back filling (sand / Subbase ) 17-Jun-24 03-Jul-24 10 15


GR-CON-Z19-1200 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Jul-24 15-Jul-24 10 87
GR-CON-Z19-1201 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
01-Aug-24
system 15-Aug-24 12 71
Zone 17 12-Nov-23 15-Jul-24 197 123
Future Neighborhood Park FNP-15 12-Nov-23 19-May-24 152 168
Site Preparation 12-Nov-23 04-Dec-23 20 301
GR-CON-Z17-1148 Demolition (Asphalt.Paving,etc.....) 12-Nov-23 15-Nov-23 4 22
GR-CON-Z17-1149 Excavation And Disposal 16-Nov-23 22-Nov-23 6 194
GR-CON-Z17-1150 Prepretion And Compaction 23-Nov-23 27-Nov-23 4 301
GR-CON-Z17-1151 Backfilling 28-Nov-23 04-Dec-23 6 301
Curbstone and Paving 23-Nov-23 15-Jan-24 46 265
GR-CON-Z17-1152 Excavation Curbstone 23-Nov-23 28-Nov-23 5 224
GR-CON-Z17-1153 Plain Concrete 29-Nov-23 05-Dec-23 6 265
GR-CON-Z17-1154 Installation Curbstone 06-Dec-23 16-Dec-23 9 265
GR-CON-Z17-1155 Casting Concrete (Mortar haunch) 17-Dec-23 20-Dec-23 4 265
GR-CON-Z17-1156 Backfilling (sand / Sub base) 21-Dec-23 31-Dec-23 9 265
GR-CON-Z17-1157 Installation of Paving 01-Jan-24 15-Jan-24 13 265
Landscape Works 29-Nov-23 19-May-24 137 168
GR-CON-Z17-1158 Excavation (Tree Pit ) 29-Nov-23 04-Dec-23 5 224
GR-CON-Z17-1159 Aggregate Drainage layer 05-Dec-23 11-Dec-23 6 251
GR-CON-Z17-1160 Installation Geotextile 12-Dec-23 16-Dec-23 4 251
GR-CON-Z17-1161 Backfilling (Soil max for tree) 17-Dec-23 23-Dec-23 6 251
GR-CON-Z17-1162 Installation of Trees 02-Apr-24 06-Apr-24 2 168
GR-CON-Z17-2766 Installation of Shrubs 06-Apr-24 08-Apr-24 2 168
GR-CON-Z17-2776 Installation of Succulents 09-Apr-24 11-Apr-24 2 168
GR-CON-Z17-2786 Installation of Ground Covers 11-Apr-24 18-Apr-24 2 168
GR-CON-Z17-2796 Installation of Climbers 18-Apr-24 21-Apr-24 2 168
GR-CON-Z17-2806 Installation of Grass 21-Apr-24 23-Apr-24 2 168
GR-CON-Z17-2816 Installation of Lawns 23-Apr-24 25-Apr-24 2 168
GR-CON-Z17-1163 Backfilling (Mulch) 25-Apr-24 29-Apr-24 3 168
GR-CON-Z17-1164 Natural Boulders Installation 29-Apr-24 04-May-24 4 168
GR-CON-Z17-1165 Retaining walls . Steps, forming risers, treads and edges with finishes
04-May-24 19-May-24 13 168
MUGA 05-Dec-23 19-May-24 132 168
GR-CON-Z17-1166 Excavation And Disposal 05-Dec-23 10-Dec-23 5 224
GR-CON-Z17-1167 Prepretion And Compaction 11-Dec-23 17-Dec-23 6 224
GR-CON-Z17-1168 polyethylene under footings ( fence and gates) 18-Dec-23 23-Dec-23 5 224
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z17-1169 Blinding concrete (flooring) 24-Dec-23 28-Dec-23 5 224


GR-CON-Z17-1170 Concrete Footings ( fence and gates) 30-Dec-23 13-Jan-24 13 224
GR-CON-Z17-1171 Tools Play Installation ( basketball / football ..) 14-Jan-24 30-Jan-24 15 224
GR-CON-Z17-1172 PaintAcrylic Play Surface 31-Jan-24 14-Feb-24 13 224
GR-CON-Z17-1173 Fence (high / low) / gates Installation 01-May-24 19-May-24 15 168
Irrigation Works 23-Nov-23 19-May-24 142 168
GR-CON-Z17-1174 Excavation Pipe Irrigation 23-Nov-23 28-Nov-23 5 194
GR-CON-Z17-1175 Sand Bedding 29-Nov-23 02-Dec-23 3 194
GR-CON-Z17-1176 HDPE Pipe Installations and fittings and conduit for cable 03-Dec-23 19-Dec-23 15 194
GR-CON-Z17-1178 Test pressure 20-Dec-23 25-Dec-23 5 194
GR-CON-Z17-1177 Installation of Valves and Accessories 26-Dec-23 30-Dec-23 4 194
GR-CON-Z17-1179 Back filling (sand / Subbase ) 31-Dec-23 06-Jan-24 6 194
GR-CON-Z17-1180 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 07-Jan-24 13-Jan-24 6 259
GR-CON-Z17-1181 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
09-May-24
system 19-May-24 8 168
Mosque M-27 16-Nov-23 26-Jun-24 177 139
Site Preparation 16-Nov-23 07-Dec-23 19 276
GR-CON-Z17-1182 Demolition (Asphalt.Paving,etc.....) 16-Nov-23 20-Nov-23 4 148
GR-CON-Z17-1183 Excavation And Disposal 21-Nov-23 26-Nov-23 5 191
GR-CON-Z17-1184 Prepretion And Compaction 27-Nov-23 30-Nov-23 4 276
GR-CON-Z17-1185 Backfilling 02-Dec-23 07-Dec-23 6 276
Curbstone and Paving 09-Dec-23 02-Jan-24 22 276
GR-CON-Z17-1190 Backfilling (sand / Sub base) 09-Dec-23 18-Dec-23 9 276
GR-CON-Z17-1191 Installation of Paving 19-Dec-23 02-Jan-24 13 276
Landscape Works 27-Nov-23 26-Jun-24 168 139
GR-CON-Z17-1192 Excavation (Tree Pit ) 27-Nov-23 02-Dec-23 5 224
GR-CON-Z17-1193 Aggregate Drainage layer 03-Dec-23 09-Dec-23 6 224
GR-CON-Z17-1194 Installation Geotextile 10-Dec-23 14-Dec-23 5 224
GR-CON-Z17-1195 Backfilling (Soil max for tree) 16-Dec-23 20-Dec-23 5 224
GR-CON-Z17-1196 Installation of Trees 02-Apr-24 08-Apr-24 4 139
GR-CON-Z17-4746 Installation of Climbers 09-Apr-24 18-Apr-24 4 139
GR-CON-Z17-4756 Installation of Shrubs 18-Apr-24 23-Apr-24 4 139
GR-CON-Z17-4766 Installation of Succulents 23-Apr-24 28-Apr-24 4 139
GR-CON-Z17-4776 Installation of Ground Covers 28-Apr-24 02-May-24 4 139
GR-CON-Z17-1197 Backfilling (Mulch) 02-May-24 20-May-24 15 139
GR-CON-Z17-1198 Natural Boulders Installation 20-May-24 04-Jun-24 13 139
GR-CON-Z17-1199 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jun-24 26-Jun-24 15 139
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 27-Nov-23 26-Jun-24 168 139


GR-CON-Z17-1200 Excavation Pipe Irrigation 27-Nov-23 02-Dec-23 5 191
GR-CON-Z17-1201 Sand Bedding 03-Dec-23 05-Dec-23 3 191
GR-CON-Z17-1202 HDPE Pipe Installations and fittings and conduit for cable 06-Dec-23 23-Dec-23 15 191
GR-CON-Z17-1204 Test pressure 24-Dec-23 28-Dec-23 5 191
GR-CON-Z17-1203 Installation of Valves and Accessories 30-Dec-23 02-Jan-24 4 191
GR-CON-Z17-1205 Back filling (sand / Subbase ) 03-Jan-24 09-Jan-24 6 191
GR-CON-Z17-1206 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Jan-24 16-Jan-24 6 258
GR-CON-Z17-1207 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
15-Jun-24
system 26-Jun-24 6 139
Parking P-11 19-Nov-23 12-May-24 140 174
Site Preparation 19-Nov-23 25-Nov-23 6 296
GR-CON-Z17-1211 Backfilling 19-Nov-23 25-Nov-23 6 296
GR-CON-Z17-1209 Excavation And Disposal 20-Nov-23 25-Nov-23 5 192
GR-CON-Z17-1208 Demolition (Asphalt.Paving,etc.....) 21-Nov-23 25-Nov-23 4 148
GR-CON-Z17-1210 Prepretion And Compaction 21-Nov-23 25-Nov-23 4 296
Curbstone and Paving 26-Nov-23 17-Jan-24 46 263
GR-CON-Z17-1212 Excavation Curbstone 26-Nov-23 30-Nov-23 5 255
GR-CON-Z17-1213 Plain Concrete 02-Dec-23 07-Dec-23 6 263
GR-CON-Z17-1214 Installation Curbstone 09-Dec-23 18-Dec-23 9 263
GR-CON-Z17-1215 Casting Concrete (Mortar haunch) 19-Dec-23 23-Dec-23 4 263
GR-CON-Z17-1216 Backfilling (sand / Sub base) 24-Dec-23 02-Jan-24 9 263
GR-CON-Z17-1217 Installation of Paving 03-Jan-24 17-Jan-24 13 263
Landscape Works 02-Dec-23 30-Apr-24 119 174
GR-CON-Z17-1218 Excavation (Tree Pit ) 02-Dec-23 06-Dec-23 5 255
GR-CON-Z17-1219 Aggregate Drainage layer 07-Dec-23 13-Dec-23 6 255
GR-CON-Z17-1220 Installation Geotextile 14-Dec-23 18-Dec-23 4 255
GR-CON-Z17-1221 Backfilling (Soil max for tree) 19-Dec-23 25-Dec-23 6 255
GR-CON-Z17-1222 Installation of Trees 02-Apr-24 07-Apr-24 3 174
GR-CON-Z17-8696 Installation of Shrubs 07-Apr-24 11-Apr-24 3 174
GR-CON-Z17-8706 Installation of Ground Covers 11-Apr-24 20-Apr-24 3 174
GR-CON-Z17-8716 Installation of Succulents 20-Apr-24 23-Apr-24 3 174
GR-CON-Z17-8726 Installation of Grass 23-Apr-24 27-Apr-24 3 174
GR-CON-Z17-1223 Backfilling (Mulch) 27-Apr-24 30-Apr-24 3 174
Site Furnishing 30-Apr-24 12-May-24 10 174
GR-CON-Z17-1234 Tree Grate 30-Apr-24 06-May-24 5 174
GR-CON-Z17-1235 Wheel stoppers 06-May-24 12-May-24 5 174
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 26-Nov-23 12-May-24 134 174


GR-CON-Z17-1226 Excavation Pipe Irrigation 26-Nov-23 30-Nov-23 5 192
GR-CON-Z17-1227 Sand Bedding 02-Dec-23 04-Dec-23 3 192
GR-CON-Z17-1228 HDPE Pipe Installations and fittings and conduit for cable 05-Dec-23 21-Dec-23 15 192
GR-CON-Z17-1230 Test pressure 23-Dec-23 27-Dec-23 5 192
GR-CON-Z17-1229 Installation of Valves and Accessories 28-Dec-23 01-Jan-24 4 192
GR-CON-Z17-1231 Back filling (sand / Subbase ) 02-Jan-24 08-Jan-24 6 192
GR-CON-Z17-1232 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Jan-24 15-Jan-24 6 257
GR-CON-Z17-1233 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-May-24
system 12-May-24 8 174
Parking P-40 27-Nov-23 12-May-24 133 174
Site Preparation 27-Nov-23 04-Dec-23 6 288
GR-CON-Z17-1239 Backfilling 27-Nov-23 04-Dec-23 6 288
GR-CON-Z17-1237 Excavation And Disposal 28-Nov-23 04-Dec-23 5 184
GR-CON-Z17-1236 Demolition (Asphalt.Paving,etc.....) 29-Nov-23 04-Dec-23 4 144
GR-CON-Z17-1238 Prepretion And Compaction 29-Nov-23 04-Dec-23 4 288
Curbstone and Paving 04-Dec-23 27-Jan-24 46 255
GR-CON-Z17-1240 Excavation Curbstone 04-Dec-23 10-Dec-23 5 247
GR-CON-Z17-1241 Plain Concrete 10-Dec-23 17-Dec-23 6 255
GR-CON-Z17-1242 Installation Curbstone 17-Dec-23 27-Dec-23 9 255
GR-CON-Z17-1243 Casting Concrete (Mortar haunch) 27-Dec-23 01-Jan-24 4 255
GR-CON-Z17-1244 Backfilling (sand / Sub base) 01-Jan-24 11-Jan-24 9 255
GR-CON-Z17-1245 Installation of Paving 11-Jan-24 27-Jan-24 13 255
Landscape Works 10-Dec-23 30-Apr-24 112 174
GR-CON-Z17-1246 Excavation (Tree Pit ) 10-Dec-23 16-Dec-23 5 247
GR-CON-Z17-1247 Aggregate Drainage layer 16-Dec-23 23-Dec-23 6 247
GR-CON-Z17-1248 Installation Geotextile 23-Dec-23 27-Dec-23 4 247
GR-CON-Z17-1249 Backfilling (Soil max for tree) 27-Dec-23 03-Jan-24 6 247
GR-CON-Z17-1250 Installation of Trees 02-Apr-24 07-Apr-24 3 174
GR-CON-Z17-8736 Installation of Shrubs 07-Apr-24 11-Apr-24 3 174
GR-CON-Z17-8746 Installation of Ground Covers 11-Apr-24 20-Apr-24 3 174
GR-CON-Z17-8756 Installation of Succulents 20-Apr-24 23-Apr-24 3 174
GR-CON-Z17-8766 Installation of Grass 23-Apr-24 27-Apr-24 3 174
GR-CON-Z17-1251 Backfilling (Mulch) 27-Apr-24 30-Apr-24 3 174
Site Furnishing 30-Apr-24 12-May-24 10 174
GR-CON-Z17-1262 Tree Grate 30-Apr-24 06-May-24 5 174
GR-CON-Z17-1263 Wheel stoppers 06-May-24 12-May-24 5 174
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 04-Dec-23 12-May-24 127 174


GR-CON-Z17-1254 Excavation Pipe Irrigation 04-Dec-23 10-Dec-23 5 184
GR-CON-Z17-1255 Sand Bedding 10-Dec-23 13-Dec-23 3 184
GR-CON-Z17-1256 HDPE Pipe Installations and fittings and conduit for cable 13-Dec-23 31-Dec-23 15 184
GR-CON-Z17-1258 Test pressure 31-Dec-23 06-Jan-24 5 184
GR-CON-Z17-1257 Installation of Valves and Accessories 06-Jan-24 10-Jan-24 4 184
GR-CON-Z17-1259 Back filling (sand / Subbase ) 10-Jan-24 17-Jan-24 6 184
GR-CON-Z17-1260 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 17-Jan-24 24-Jan-24 6 249
GR-CON-Z17-1261 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-May-24
system 12-May-24 8 174
Parking P-9 25-Dec-23 12-May-24 109 174
Site Preparation 25-Dec-23 01-Jan-24 6 264
GR-CON-Z17-1267 Backfilling 25-Dec-23 01-Jan-24 6 264
GR-CON-Z17-1265 Excavation And Disposal 26-Dec-23 01-Jan-24 5 160
GR-CON-Z17-1264 Demolition (Asphalt.Paving,etc.....) 27-Dec-23 01-Jan-24 4 124
GR-CON-Z17-1266 Prepretion And Compaction 27-Dec-23 01-Jan-24 4 264
Curbstone and Paving 01-Jan-24 24-Feb-24 46 231
GR-CON-Z17-1268 Excavation Curbstone 01-Jan-24 07-Jan-24 5 223
GR-CON-Z17-1269 Plain Concrete 07-Jan-24 14-Jan-24 6 231
GR-CON-Z17-1270 Installation Curbstone 14-Jan-24 24-Jan-24 9 231
GR-CON-Z17-1271 Casting Concrete (Mortar haunch) 24-Jan-24 29-Jan-24 4 231
GR-CON-Z17-1272 Backfilling (sand / Sub base) 29-Jan-24 08-Feb-24 9 231
GR-CON-Z17-1273 Installation of Paving 08-Feb-24 24-Feb-24 13 231
Landscape Works 07-Jan-24 30-Apr-24 88 174
GR-CON-Z17-1274 Excavation (Tree Pit ) 07-Jan-24 13-Jan-24 5 223
GR-CON-Z17-1275 Aggregate Drainage layer 13-Jan-24 20-Jan-24 6 223
GR-CON-Z17-1276 Installation Geotextile 20-Jan-24 24-Jan-24 4 223
GR-CON-Z17-1277 Backfilling (Soil max for tree) 24-Jan-24 31-Jan-24 6 223
GR-CON-Z17-1278 Installation of Trees 02-Apr-24 07-Apr-24 3 174
GR-CON-Z17-8776 Installation of Shrubs 07-Apr-24 11-Apr-24 3 174
GR-CON-Z17-8786 Installation of Ground Covers 11-Apr-24 20-Apr-24 3 174
GR-CON-Z17-8796 Installation of Succulents 20-Apr-24 23-Apr-24 3 174
GR-CON-Z17-8806 Installation of Grass 23-Apr-24 27-Apr-24 3 174
GR-CON-Z17-1279 Backfilling (Mulch) 27-Apr-24 30-Apr-24 3 174
Site Furnishing 30-Apr-24 12-May-24 10 174
GR-CON-Z17-1290 Tree Grate 30-Apr-24 06-May-24 5 174
GR-CON-Z17-1291 Wheel stoppers 06-May-24 12-May-24 5 174
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 01-Jan-24 12-May-24 103 174


GR-CON-Z17-1282 Excavation Pipe Irrigation 01-Jan-24 07-Jan-24 5 160
GR-CON-Z17-1283 Sand Bedding 07-Jan-24 10-Jan-24 3 160
GR-CON-Z17-1284 HDPE Pipe Installations and fittings and conduit for cable 10-Jan-24 28-Jan-24 15 160
GR-CON-Z17-1286 Test pressure 28-Jan-24 03-Feb-24 5 160
GR-CON-Z17-1285 Installation of Valves and Accessories 03-Feb-24 07-Feb-24 4 160
GR-CON-Z17-1287 Back filling (sand / Subbase ) 07-Feb-24 14-Feb-24 6 160
GR-CON-Z17-1288 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Feb-24 21-Feb-24 6 225
GR-CON-Z17-1289 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-May-24
system 12-May-24 8 174
Street SS-11.1 02-Jan-24 15-Jul-24 153 123
Site Preparation 02-Jan-24 08-Feb-24 32 244
GR-CON-Z17-1000 Demolition (Asphalt.Paving,etc.....) 02-Jan-24 09-Jan-24 6 123
GR-CON-Z17-1001 Excavation And Disposal 09-Jan-24 18-Jan-24 8 123
GR-CON-Z17-1002 Prepretion And Compaction 18-Jan-24 29-Jan-24 9 244
GR-CON-Z17-1003 Backfilling 29-Jan-24 08-Feb-24 9 244
Curbstone and Paving 18-Jan-24 22-Apr-24 71 191
GR-CON-Z17-1004 Excavation Curbstone 18-Jan-24 28-Jan-24 8 143
GR-CON-Z17-1005 Plain Concrete 28-Jan-24 07-Feb-24 9 191
GR-CON-Z17-1006 Installation Curbstone 07-Feb-24 24-Feb-24 14 191
GR-CON-Z17-1007 Casting Concrete (Mortar haunch) 24-Feb-24 02-Mar-24 6 191
GR-CON-Z17-1008 Backfilling (sand / Sub base) 02-Mar-24 19-Mar-24 14 191
GR-CON-Z17-1009 Installation of Paving 19-Mar-24 22-Apr-24 20 191
Landscape Works 28-Jan-24 03-Jun-24 99 123
GR-CON-Z17-1010 Excavation (Tree Pit ) 28-Jan-24 06-Feb-24 8 143
GR-CON-Z17-1011 Aggregate Drainage layer 06-Feb-24 17-Feb-24 9 143
GR-CON-Z17-1012 Installation Geotextile 17-Feb-24 24-Feb-24 6 143
GR-CON-Z17-1013 Backfilling (Soil max for tree) 24-Feb-24 05-Mar-24 9 143
GR-CON-Z17-1014 Installation of Trees 02-Apr-24 08-Apr-24 4 123
GR-CON-Z17-13456 Installation of Shrubs 09-Apr-24 17-Apr-24 3 123
GR-CON-Z17-13466 Installation of Succulents 17-Apr-24 21-Apr-24 3 123
GR-CON-Z17-13476 Installation of Ground Covers 21-Apr-24 24-Apr-24 3 123
GR-CON-Z17-13486 Installation of Grass 24-Apr-24 28-Apr-24 3 123
GR-CON-Z17-1015 Backfilling (Mulch) 28-Apr-24 04-May-24 5 123
GR-CON-Z17-1016 Natural Boulders Installation 04-May-24 11-May-24 6 123
GR-CON-Z17-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
11-May-24 03-Jun-24 20 123
Site Furnishing 03-Jun-24 15-Jul-24 32 123
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z17-1026 Garden planter box 03-Jun-24 12-Jun-24 8 123


GR-CON-Z17-1027 Wheel stoppers 12-Jun-24 26-Jun-24 8 123
GR-CON-Z17-1028 Steel Lattice 26-Jun-24 06-Jul-24 8 123
GR-CON-Z17-1029 Handrail 06-Jul-24 15-Jul-24 8 123
Storm Piping Works 04-Jul-24 15-Jul-24 9 123
GR-CON-Z17-1030 Installation of DI grating covers 04-Jul-24 15-Jul-24 9 123
Irrigation Works 18-Jan-24 04-May-24 81 172
GR-CON-Z17-1018 Excavation Pipe Irrigation 18-Jan-24 28-Jan-24 8 123
GR-CON-Z17-1019 Sand Bedding 28-Jan-24 04-Feb-24 6 123
GR-CON-Z17-1020 HDPE Pipe Installations and fittings and conduit for cable 04-Feb-24 02-Mar-24 23 123
GR-CON-Z17-1022 Test pressure 02-Mar-24 11-Mar-24 8 123
GR-CON-Z17-1021 Installation of Valves and Accessories 11-Mar-24 19-Mar-24 6 123
GR-CON-Z17-1023 Back filling (sand / Subbase ) 19-Mar-24 02-Apr-24 9 123
GR-CON-Z17-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 02-Apr-24 20-Apr-24 9 172
GR-CON-Z17-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
20-Apr-24
system 04-May-24 12 172
Electrical Works 28-Jan-24 15-Jul-24 131 123
GR-CON-Z17-1031 Excavation And Disposal 28-Jan-24 06-Feb-24 8 212
GR-CON-Z17-1032 Sand Bedding 06-Feb-24 13-Feb-24 6 212
GR-CON-Z17-1033 laying cables 13-Feb-24 20-Feb-24 6 212
GR-CON-Z17-1034 Backfilling (sand / Sub base) 20-Feb-24 29-Feb-24 8 212
GR-CON-Z17-1035 Control Panel / Distribution Panel Installation 29-Feb-24 07-Mar-24 6 212
GR-CON-Z17-1036 Road Crossing Ducts 06-Jul-24 15-Jul-24 8 123
Street SS-19.3 09-Jan-24 12-Jun-24 123 147
Site Preparation 09-Jan-24 03-Feb-24 21 249
GR-CON-Z17-1037 Demolition (Asphalt.Paving,etc.....) 09-Jan-24 14-Jan-24 4 131
GR-CON-Z17-1038 Excavation And Disposal 14-Jan-24 20-Jan-24 5 143
GR-CON-Z17-1039 Prepretion And Compaction 20-Jan-24 27-Jan-24 6 249
GR-CON-Z17-1040 Backfilling 27-Jan-24 03-Feb-24 6 249
Curbstone and Paving 20-Jan-24 13-Mar-24 46 215
GR-CON-Z17-1041 Excavation Curbstone 20-Jan-24 25-Jan-24 5 180
GR-CON-Z17-1042 Plain Concrete 25-Jan-24 01-Feb-24 6 215
GR-CON-Z17-1043 Installation Curbstone 01-Feb-24 12-Feb-24 9 215
GR-CON-Z17-1044 Casting Concrete (Mortar haunch) 12-Feb-24 17-Feb-24 4 215
GR-CON-Z17-1045 Backfilling (sand / Sub base) 17-Feb-24 27-Feb-24 9 215
GR-CON-Z17-1046 Installation of Paving 27-Feb-24 13-Mar-24 13 215
Landscape Works 25-Jan-24 20-May-24 89 147
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z17-1047 Excavation (Tree Pit ) 25-Jan-24 31-Jan-24 5 180


GR-CON-Z17-1048 Aggregate Drainage layer 31-Jan-24 07-Feb-24 6 180
GR-CON-Z17-1049 Installation Geotextile 07-Feb-24 12-Feb-24 4 180
GR-CON-Z17-1050 Backfilling (Soil max for tree) 12-Feb-24 19-Feb-24 6 180
GR-CON-Z17-1051 Installation of Trees 02-Apr-24 07-Apr-24 3 147
GR-CON-Z17-13496 Installation of Shrubs 07-Apr-24 11-Apr-24 3 147
GR-CON-Z17-13506 Installation of Succulents 11-Apr-24 20-Apr-24 3 147
GR-CON-Z17-13516 Installation of Ground Covers 20-Apr-24 23-Apr-24 3 147
GR-CON-Z17-13526 Installation of Grass 23-Apr-24 27-Apr-24 3 147
GR-CON-Z17-1052 Backfilling (Mulch) 27-Apr-24 30-Apr-24 3 147
GR-CON-Z17-1053 Natural Boulders Installation 30-Apr-24 05-May-24 4 147
GR-CON-Z17-1054 Retaining walls . Steps, forming risers, treads and edges with finishes
05-May-24 20-May-24 13 147
Site Furnishing 20-May-24 12-Jun-24 20 147
GR-CON-Z17-1063 Garden planter box 20-May-24 26-May-24 5 147
GR-CON-Z17-1064 Wheel stoppers 26-May-24 01-Jun-24 5 147
GR-CON-Z17-1065 Steel Lattice 01-Jun-24 06-Jun-24 5 147
GR-CON-Z17-1066 Handrail 06-Jun-24 12-Jun-24 5 147
Storm Piping Works 05-Jun-24 12-Jun-24 6 147
GR-CON-Z17-1067 Installation of DI grating covers 05-Jun-24 12-Jun-24 6 147
Irrigation Works 20-Jan-24 24-Mar-24 53 202
GR-CON-Z17-1055 Excavation Pipe Irrigation 20-Jan-24 25-Jan-24 5 143
GR-CON-Z17-1056 Sand Bedding 25-Jan-24 30-Jan-24 4 143
GR-CON-Z17-1057 HDPE Pipe Installations and fittings and conduit for cable 30-Jan-24 17-Feb-24 15 143
GR-CON-Z17-1059 Test pressure 17-Feb-24 22-Feb-24 5 143
GR-CON-Z17-1058 Installation of Valves and Accessories 22-Feb-24 27-Feb-24 4 143
GR-CON-Z17-1060 Back filling (sand / Subbase ) 27-Feb-24 05-Mar-24 6 143
GR-CON-Z17-1061 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-Mar-24 12-Mar-24 6 202
GR-CON-Z17-1062 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-Mar-24
system 24-Mar-24 8 202
Electrical Works 25-Jan-24 12-Jun-24 109 147
GR-CON-Z17-1068 Excavation And Disposal 25-Jan-24 31-Jan-24 5 229
GR-CON-Z17-1069 Sand Bedding 31-Jan-24 05-Feb-24 4 229
GR-CON-Z17-1070 laying cables 05-Feb-24 10-Feb-24 4 229
GR-CON-Z17-1071 Backfilling (sand / Sub base) 10-Feb-24 15-Feb-24 5 229
GR-CON-Z17-1072 Control Panel / Distribution Panel Installation 15-Feb-24 20-Feb-24 4 229
GR-CON-Z17-1073 Road Crossing Ducts 06-Jun-24 12-Jun-24 5 147
Street SS-20 20-Jan-24 12-Jun-24 114 147
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 20-Jan-24 13-Feb-24 21 240


GR-CON-Z17-1074 Demolition (Asphalt.Paving,etc.....) 20-Jan-24 24-Jan-24 4 126
GR-CON-Z17-1075 Excavation And Disposal 24-Jan-24 30-Jan-24 5 134
GR-CON-Z17-1076 Prepretion And Compaction 30-Jan-24 06-Feb-24 6 240
GR-CON-Z17-1077 Backfilling 06-Feb-24 13-Feb-24 6 240
Curbstone and Paving 30-Jan-24 27-Mar-24 46 206
GR-CON-Z17-1078 Excavation Curbstone 30-Jan-24 05-Feb-24 5 171
GR-CON-Z17-1079 Plain Concrete 05-Feb-24 12-Feb-24 6 206
GR-CON-Z17-1080 Installation Curbstone 12-Feb-24 22-Feb-24 9 206
GR-CON-Z17-1081 Casting Concrete (Mortar haunch) 22-Feb-24 27-Feb-24 4 206
GR-CON-Z17-1082 Backfilling (sand / Sub base) 27-Feb-24 09-Mar-24 9 206
GR-CON-Z17-1083 Installation of Paving 09-Mar-24 27-Mar-24 13 206
Landscape Works 05-Feb-24 20-May-24 80 147
GR-CON-Z17-1084 Excavation (Tree Pit ) 05-Feb-24 11-Feb-24 5 171
GR-CON-Z17-1085 Aggregate Drainage layer 11-Feb-24 18-Feb-24 6 171
GR-CON-Z17-1086 Installation Geotextile 18-Feb-24 22-Feb-24 4 171
GR-CON-Z17-1087 Backfilling (Soil max for tree) 22-Feb-24 29-Feb-24 6 171
GR-CON-Z17-1088 Installation of Trees 02-Apr-24 07-Apr-24 3 147
GR-CON-Z17-13536 Installation of Shrubs 07-Apr-24 11-Apr-24 3 147
GR-CON-Z17-13546 Installation of Succulents 11-Apr-24 20-Apr-24 3 147
GR-CON-Z17-13556 Installation of Ground Covers 20-Apr-24 23-Apr-24 3 147
GR-CON-Z17-13566 Installation of Grass 23-Apr-24 27-Apr-24 3 147
GR-CON-Z17-1089 Backfilling (Mulch) 27-Apr-24 30-Apr-24 3 147
GR-CON-Z17-1090 Natural Boulders Installation 30-Apr-24 05-May-24 4 147
GR-CON-Z17-1091 Retaining walls . Steps, forming risers, treads and edges with finishes
05-May-24 20-May-24 13 147
Site Furnishing 20-May-24 12-Jun-24 20 147
GR-CON-Z17-1100 Garden planter box 20-May-24 26-May-24 5 147
GR-CON-Z17-1101 Wheel stoppers 26-May-24 01-Jun-24 5 147
GR-CON-Z17-1102 Steel Lattice 01-Jun-24 06-Jun-24 5 147
GR-CON-Z17-1103 Handrail 06-Jun-24 12-Jun-24 5 147
Storm Piping Works 05-Jun-24 12-Jun-24 6 147
GR-CON-Z17-1104 Installation of DI grating covers 05-Jun-24 12-Jun-24 6 147
Irrigation Works 30-Jan-24 07-Apr-24 53 193
GR-CON-Z17-1092 Excavation Pipe Irrigation 30-Jan-24 05-Feb-24 5 134
GR-CON-Z17-1093 Sand Bedding 05-Feb-24 10-Feb-24 4 134
GR-CON-Z17-1094 HDPE Pipe Installations and fittings and conduit for cable 10-Feb-24 27-Feb-24 15 134
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z17-1096 Test pressure 27-Feb-24 04-Mar-24 5 134


GR-CON-Z17-1095 Installation of Valves and Accessories 04-Mar-24 09-Mar-24 4 134
GR-CON-Z17-1097 Back filling (sand / Subbase ) 09-Mar-24 16-Mar-24 6 134
GR-CON-Z17-1098 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 17-Mar-24 25-Mar-24 6 193
GR-CON-Z17-1099 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-Mar-24
system 07-Apr-24 8 193
Electrical Works 05-Feb-24 12-Jun-24 100 147
GR-CON-Z17-1105 Excavation And Disposal 05-Feb-24 11-Feb-24 5 220
GR-CON-Z17-1106 Sand Bedding 11-Feb-24 15-Feb-24 4 220
GR-CON-Z17-1107 laying cables 15-Feb-24 20-Feb-24 4 220
GR-CON-Z17-1108 Backfilling (sand / Sub base) 20-Feb-24 26-Feb-24 5 220
GR-CON-Z17-1109 Control Panel / Distribution Panel Installation 26-Feb-24 02-Mar-24 4 220
GR-CON-Z17-1110 Road Crossing Ducts 06-Jun-24 12-Jun-24 5 147
Street SS-21 25-Jan-24 12-Jun-24 109 147
Site Preparation 25-Jan-24 19-Feb-24 21 235
GR-CON-Z17-1111 Demolition (Asphalt.Paving,etc.....) 25-Jan-24 30-Jan-24 4 125
GR-CON-Z17-1112 Excavation And Disposal 30-Jan-24 05-Feb-24 5 129
GR-CON-Z17-1113 Prepretion And Compaction 05-Feb-24 12-Feb-24 6 235
GR-CON-Z17-1114 Backfilling 12-Feb-24 19-Feb-24 6 235
Curbstone and Paving 05-Feb-24 03-Apr-24 46 201
GR-CON-Z17-1115 Excavation Curbstone 05-Feb-24 11-Feb-24 5 166
GR-CON-Z17-1116 Plain Concrete 11-Feb-24 18-Feb-24 6 201
GR-CON-Z17-1117 Installation Curbstone 18-Feb-24 28-Feb-24 9 201
GR-CON-Z17-1118 Casting Concrete (Mortar haunch) 28-Feb-24 04-Mar-24 4 201
GR-CON-Z17-1119 Backfilling (sand / Sub base) 04-Mar-24 14-Mar-24 9 201
GR-CON-Z17-1120 Installation of Paving 14-Mar-24 03-Apr-24 13 201
Landscape Works 11-Feb-24 20-May-24 75 147
GR-CON-Z17-1121 Excavation (Tree Pit ) 11-Feb-24 17-Feb-24 5 166
GR-CON-Z17-1122 Aggregate Drainage layer 17-Feb-24 24-Feb-24 6 166
GR-CON-Z17-1123 Installation Geotextile 24-Feb-24 28-Feb-24 4 166
GR-CON-Z17-1124 Backfilling (Soil max for tree) 28-Feb-24 06-Mar-24 6 166
GR-CON-Z17-1125 Installation of Trees 02-Apr-24 07-Apr-24 3 147
GR-CON-Z17-13576 Installation of Shrubs 07-Apr-24 11-Apr-24 3 147
GR-CON-Z17-13586 Installation of Succulents 11-Apr-24 20-Apr-24 3 147
GR-CON-Z17-13596 Installation of Ground Covers 20-Apr-24 23-Apr-24 3 147
GR-CON-Z17-13606 Installation of Grass 23-Apr-24 27-Apr-24 3 147
GR-CON-Z17-1126 Backfilling (Mulch) 27-Apr-24 30-Apr-24 3 147
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z17-1127 Natural Boulders Installation 30-Apr-24 05-May-24 4 147


GR-CON-Z17-1128 Retaining walls . Steps, forming risers, treads and edges with finishes
05-May-24 20-May-24 13 147
Site Furnishing 20-May-24 12-Jun-24 20 147
GR-CON-Z17-1137 Garden planter box 20-May-24 26-May-24 5 147
GR-CON-Z17-1138 Wheel stoppers 26-May-24 01-Jun-24 5 147
GR-CON-Z17-1139 Steel Lattice 01-Jun-24 06-Jun-24 5 147
GR-CON-Z17-1140 Handrail 06-Jun-24 12-Jun-24 5 147
Storm Piping Works 05-Jun-24 12-Jun-24 6 147
GR-CON-Z17-1141 Installation of DI grating covers 05-Jun-24 12-Jun-24 6 147
Irrigation Works 05-Feb-24 18-Apr-24 53 188
GR-CON-Z17-1129 Excavation Pipe Irrigation 05-Feb-24 11-Feb-24 5 129
GR-CON-Z17-1130 Sand Bedding 11-Feb-24 15-Feb-24 4 129
GR-CON-Z17-1131 HDPE Pipe Installations and fittings and conduit for cable 15-Feb-24 04-Mar-24 15 129
GR-CON-Z17-1133 Test pressure 04-Mar-24 10-Mar-24 5 129
GR-CON-Z17-1132 Installation of Valves and Accessories 10-Mar-24 14-Mar-24 4 129
GR-CON-Z17-1134 Back filling (sand / Subbase ) 14-Mar-24 24-Mar-24 6 129
GR-CON-Z17-1135 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Mar-24 02-Apr-24 6 188
GR-CON-Z17-1136 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Apr-24
system 18-Apr-24 8 188
Electrical Works 11-Feb-24 12-Jun-24 95 147
GR-CON-Z17-1142 Excavation And Disposal 11-Feb-24 17-Feb-24 5 215
GR-CON-Z17-1143 Sand Bedding 17-Feb-24 21-Feb-24 4 215
GR-CON-Z17-1144 laying cables 21-Feb-24 26-Feb-24 4 215
GR-CON-Z17-1145 Backfilling (sand / Sub base) 26-Feb-24 03-Mar-24 5 215
GR-CON-Z17-1146 Control Panel / Distribution Panel Installation 03-Mar-24 07-Mar-24 4 215
GR-CON-Z17-1147 Road Crossing Ducts 06-Jun-24 12-Jun-24 5 147
School S-15 31-Jan-24 08-Jun-24 100 151
Site Preparation 31-Jan-24 11-Feb-24 9 242
GR-CON-Z17-1293 Excavation And Disposal 31-Jan-24 06-Feb-24 5 124
GR-CON-Z17-1294 Prepretion And Compaction 06-Feb-24 11-Feb-24 4 242
Curbstone and Paving 06-Feb-24 06-Apr-24 46 200
GR-CON-Z17-1296 Excavation Curbstone 06-Feb-24 12-Feb-24 5 169
GR-CON-Z17-1297 Plain Concrete 12-Feb-24 19-Feb-24 6 200
GR-CON-Z17-1298 Installation Curbstone 19-Feb-24 29-Feb-24 9 200
GR-CON-Z17-1299 Casting Concrete (Mortar haunch) 29-Feb-24 05-Mar-24 4 200
GR-CON-Z17-1300 Backfilling (sand / Sub base) 05-Mar-24 16-Mar-24 9 200
GR-CON-Z17-1301 Installation of Paving 17-Mar-24 06-Apr-24 13 200
Activity ID Activity Name Start Finish Original Total Float
Duration

Landscape Works 12-Feb-24 27-May-24 80 151


GR-CON-Z17-1302 Excavation (Tree Pit ) 12-Feb-24 18-Feb-24 5 169
GR-CON-Z17-1303 Aggregate Drainage layer 18-Feb-24 25-Feb-24 6 169
GR-CON-Z17-1304 Installation Geotextile 25-Feb-24 29-Feb-24 4 169
GR-CON-Z17-1305 Backfilling (Soil max for tree) 29-Feb-24 07-Mar-24 6 169
GR-CON-Z17-1306 Installation of Trees 02-Apr-24 07-Apr-24 3 151
GR-CON-Z17-5956 Installation of Shrubs 07-Apr-24 11-Apr-24 3 151
GR-CON-Z17-5966 Installation of Succulents 11-Apr-24 20-Apr-24 3 151
GR-CON-Z17-5976 Installation of Ground Covers 20-Apr-24 23-Apr-24 3 151
GR-CON-Z17-5986 Installation of Climbers 23-Apr-24 27-Apr-24 3 151
GR-CON-Z17-5996 Installation of Grass 27-Apr-24 30-Apr-24 3 151
GR-CON-Z17-6006 Installation of Lawns 30-Apr-24 04-May-24 3 151
GR-CON-Z17-1307 Backfilling (Mulch) 04-May-24 07-May-24 3 151
GR-CON-Z17-1308 Natural Boulders Installation 07-May-24 12-May-24 4 151
GR-CON-Z17-1309 Retaining walls . Steps, forming risers, treads and edges with finishes
12-May-24 27-May-24 13 151
Site Furnishing 27-May-24 08-Jun-24 10 151
GR-CON-Z17-1318 Garden planter box 27-May-24 02-Jun-24 5 151
GR-CON-Z17-1319 Wheel stoppers 02-Jun-24 08-Jun-24 5 151
Irrigation Works 06-Feb-24 08-Jun-24 95 151
GR-CON-Z17-1310 Excavation Pipe Irrigation 06-Feb-24 12-Feb-24 5 129
GR-CON-Z17-1311 Sand Bedding 12-Feb-24 15-Feb-24 3 129
GR-CON-Z17-1312 HDPE Pipe Installations and fittings and conduit for cable 15-Feb-24 04-Mar-24 15 129
GR-CON-Z17-1314 Test pressure 04-Mar-24 10-Mar-24 5 129
GR-CON-Z17-1313 Installation of Valves and Accessories 10-Mar-24 14-Mar-24 4 129
GR-CON-Z17-1315 Back filling (sand / Subbase ) 14-Mar-24 24-Mar-24 6 129
GR-CON-Z17-1316 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Mar-24 02-Apr-24 6 194
GR-CON-Z17-1317 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
29-May-24
system 08-Jun-24 8 151
School S-16 06-Feb-24 08-Jun-24 95 151
Site Preparation 06-Feb-24 17-Feb-24 9 237
GR-CON-Z17-1321 Excavation And Disposal 06-Feb-24 12-Feb-24 5 124
GR-CON-Z17-1322 Prepretion And Compaction 12-Feb-24 17-Feb-24 4 237
Curbstone and Paving 12-Feb-24 17-Apr-24 46 195
GR-CON-Z17-1324 Excavation Curbstone 12-Feb-24 18-Feb-24 5 164
GR-CON-Z17-1325 Plain Concrete 18-Feb-24 25-Feb-24 6 195
GR-CON-Z17-1326 Installation Curbstone 25-Feb-24 06-Mar-24 9 195
GR-CON-Z17-1327 Casting Concrete (Mortar haunch) 06-Mar-24 11-Mar-24 4 195
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z17-1328 Backfilling (sand / Sub base) 11-Mar-24 24-Mar-24 9 195


GR-CON-Z17-1329 Installation of Paving 24-Mar-24 17-Apr-24 13 195
Landscape Works 18-Feb-24 27-May-24 75 151
GR-CON-Z17-1330 Excavation (Tree Pit ) 18-Feb-24 24-Feb-24 5 164
GR-CON-Z17-1331 Aggregate Drainage layer 24-Feb-24 02-Mar-24 6 164
GR-CON-Z17-1332 Installation Geotextile 02-Mar-24 06-Mar-24 4 164
GR-CON-Z17-1333 Backfilling (Soil max for tree) 06-Mar-24 13-Mar-24 6 164
GR-CON-Z17-1334 Installation of Trees 02-Apr-24 07-Apr-24 3 151
GR-CON-Z17-6016 Installation of Shrubs 07-Apr-24 11-Apr-24 3 151
GR-CON-Z17-6026 Installation of Succulents 11-Apr-24 20-Apr-24 3 151
GR-CON-Z17-6036 Installation of Ground Covers 20-Apr-24 23-Apr-24 3 151
GR-CON-Z17-6046 Installation of Climbers 23-Apr-24 27-Apr-24 3 151
GR-CON-Z17-6056 Installation of Grass 27-Apr-24 30-Apr-24 3 151
GR-CON-Z17-6066 Installation of Lawns 30-Apr-24 04-May-24 3 151
GR-CON-Z17-1335 Backfilling (Mulch) 04-May-24 07-May-24 3 151
GR-CON-Z17-1336 Natural Boulders Installation 07-May-24 12-May-24 4 151
GR-CON-Z17-1337 Retaining walls . Steps, forming risers, treads and edges with finishes
12-May-24 27-May-24 13 151
Site Furnishing 27-May-24 08-Jun-24 10 151
GR-CON-Z17-1346 Garden planter box 27-May-24 02-Jun-24 5 151
GR-CON-Z17-1347 Wheel stoppers 02-Jun-24 08-Jun-24 5 151
Irrigation Works 12-Feb-24 08-Jun-24 90 151
GR-CON-Z17-1338 Excavation Pipe Irrigation 12-Feb-24 18-Feb-24 5 124
GR-CON-Z17-1339 Sand Bedding 18-Feb-24 21-Feb-24 3 124
GR-CON-Z17-1340 HDPE Pipe Installations and fittings and conduit for cable 21-Feb-24 10-Mar-24 15 124
GR-CON-Z17-1342 Test pressure 10-Mar-24 16-Mar-24 5 124
GR-CON-Z17-1341 Installation of Valves and Accessories 17-Mar-24 23-Mar-24 4 124
GR-CON-Z17-1343 Back filling (sand / Subbase ) 23-Mar-24 01-Apr-24 6 124
GR-CON-Z17-1344 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 01-Apr-24 10-Apr-24 6 189
GR-CON-Z17-1345 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
29-May-24
system 08-Jun-24 8 151
Zone 18 16-Nov-23 27-Jul-24 203 101
Future Neighborhood Park FNP-16 16-Nov-23 18-Jun-24 174 130
Site Preparation 16-Nov-23 09-Dec-23 20 284
GR-CON-Z18-1222 Demolition (Asphalt.Paving,etc.....) 16-Nov-23 20-Nov-23 4 22
GR-CON-Z18-1223 Excavation And Disposal 21-Nov-23 27-Nov-23 6 193
GR-CON-Z18-1224 Prepretion And Compaction 28-Nov-23 02-Dec-23 4 284
GR-CON-Z18-1225 Backfilling 03-Dec-23 09-Dec-23 6 284
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 28-Nov-23 20-Jan-24 46 248


GR-CON-Z18-1226 Excavation Curbstone 28-Nov-23 03-Dec-23 5 234
GR-CON-Z18-1227 Plain Concrete 04-Dec-23 10-Dec-23 6 248
GR-CON-Z18-1228 Installation Curbstone 11-Dec-23 20-Dec-23 9 248
GR-CON-Z18-1229 Casting Concrete (Mortar haunch) 21-Dec-23 25-Dec-23 4 248
GR-CON-Z18-1230 Backfilling (sand / Sub base) 26-Dec-23 04-Jan-24 9 248
GR-CON-Z18-1231 Installation of Paving 06-Jan-24 20-Jan-24 13 248
Landscape Works 04-Dec-23 18-Jun-24 159 130
GR-CON-Z18-1232 Excavation (Tree Pit ) 04-Dec-23 09-Dec-23 5 234
GR-CON-Z18-1233 Aggregate Drainage layer 10-Dec-23 16-Dec-23 6 234
GR-CON-Z18-1234 Installation Geotextile 17-Dec-23 20-Dec-23 4 234
GR-CON-Z18-1235 Backfilling (Soil max for tree) 21-Dec-23 27-Dec-23 6 234
GR-CON-Z18-1236 Installation of Trees 09-May-24 12-May-24 2 130
GR-CON-Z18-2826 Installation of Shrubs 12-May-24 14-May-24 2 130
GR-CON-Z18-2836 Installation of Succulents 14-May-24 16-May-24 2 130
GR-CON-Z18-2846 Installation of Ground Covers 16-May-24 19-May-24 2 130
GR-CON-Z18-2856 Installation of Climbers 19-May-24 21-May-24 2 130
GR-CON-Z18-2866 Installation of Grass 21-May-24 23-May-24 2 130
GR-CON-Z18-2876 Installation of Lawns 23-May-24 26-May-24 2 130
GR-CON-Z18-1237 Backfilling (Mulch) 26-May-24 29-May-24 3 130
GR-CON-Z18-1238 Natural Boulders Installation 29-May-24 03-Jun-24 4 130
GR-CON-Z18-1239 Retaining walls . Steps, forming risers, treads and edges with finishes
03-Jun-24 18-Jun-24 13 130
Irrigation Works 28-Nov-23 18-Jun-24 164 130
GR-CON-Z18-1240 Excavation Pipe Irrigation 28-Nov-23 03-Dec-23 5 193
GR-CON-Z18-1241 Sand Bedding 04-Dec-23 06-Dec-23 3 193
GR-CON-Z18-1242 HDPE Pipe Installations and fittings and conduit for cable 07-Dec-23 24-Dec-23 15 193
GR-CON-Z18-1244 Test pressure 25-Dec-23 30-Dec-23 5 193
GR-CON-Z18-1243 Installation of Valves and Accessories 31-Dec-23 03-Jan-24 4 193
GR-CON-Z18-1245 Back filling (sand / Subbase ) 04-Jan-24 10-Jan-24 6 193
GR-CON-Z18-1246 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Jan-24 17-Jan-24 6 242
GR-CON-Z18-1247 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
09-Jun-24
system 18-Jun-24 8 130
Future Neighborhood Park FNP-23 21-Nov-23 18-Jun-24 170 130
Site Preparation 21-Nov-23 13-Dec-23 20 280
GR-CON-Z18-1248 Demolition (Asphalt.Paving,etc.....) 21-Nov-23 25-Nov-23 4 149
GR-CON-Z18-1249 Excavation And Disposal 26-Nov-23 02-Dec-23 6 189
GR-CON-Z18-1250 Prepretion And Compaction 03-Dec-23 06-Dec-23 4 280
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1251 Backfilling 07-Dec-23 13-Dec-23 6 280


Curbstone and Paving 03-Dec-23 24-Jan-24 46 244
GR-CON-Z18-1252 Excavation Curbstone 03-Dec-23 07-Dec-23 5 230
GR-CON-Z18-1253 Plain Concrete 09-Dec-23 14-Dec-23 6 244
GR-CON-Z18-1254 Installation Curbstone 16-Dec-23 25-Dec-23 9 244
GR-CON-Z18-1255 Casting Concrete (Mortar haunch) 26-Dec-23 30-Dec-23 4 244
GR-CON-Z18-1256 Backfilling (sand / Sub base) 31-Dec-23 09-Jan-24 9 244
GR-CON-Z18-1257 Installation of Paving 10-Jan-24 24-Jan-24 13 244
Landscape Works 09-Dec-23 18-Jun-24 155 130
GR-CON-Z18-1258 Excavation (Tree Pit ) 09-Dec-23 13-Dec-23 5 230
GR-CON-Z18-1259 Aggregate Drainage layer 14-Dec-23 20-Dec-23 6 230
GR-CON-Z18-1260 Installation Geotextile 21-Dec-23 25-Dec-23 4 230
GR-CON-Z18-1261 Backfilling (Soil max for tree) 26-Dec-23 01-Jan-24 6 230
GR-CON-Z18-1262 Installation of Trees 09-May-24 12-May-24 2 130
GR-CON-Z18-2886 Installation of Shrubs 12-May-24 14-May-24 2 130
GR-CON-Z18-2896 Installation of Succulents 14-May-24 16-May-24 2 130
GR-CON-Z18-2906 Installation of Ground Covers 16-May-24 19-May-24 2 130
GR-CON-Z18-2916 Installation of Climbers 19-May-24 21-May-24 2 130
GR-CON-Z18-2926 Installation of Grass 21-May-24 23-May-24 2 130
GR-CON-Z18-2936 Installation of Lawns 23-May-24 26-May-24 2 130
GR-CON-Z18-1263 Backfilling (Mulch) 26-May-24 29-May-24 3 130
GR-CON-Z18-1264 Natural Boulders Installation 29-May-24 03-Jun-24 4 130
GR-CON-Z18-1265 Retaining walls . Steps, forming risers, treads and edges with finishes
03-Jun-24 18-Jun-24 13 130
Irrigation Works 03-Dec-23 18-Jun-24 160 130
GR-CON-Z18-1266 Excavation Pipe Irrigation 03-Dec-23 07-Dec-23 5 189
GR-CON-Z18-1267 Sand Bedding 09-Dec-23 11-Dec-23 3 189
GR-CON-Z18-1268 HDPE Pipe Installations and fittings and conduit for cable 12-Dec-23 28-Dec-23 15 189
GR-CON-Z18-1270 Test pressure 30-Dec-23 03-Jan-24 5 189
GR-CON-Z18-1269 Installation of Valves and Accessories 04-Jan-24 08-Jan-24 4 189
GR-CON-Z18-1271 Back filling (sand / Subbase ) 09-Jan-24 15-Jan-24 6 189
GR-CON-Z18-1272 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Jan-24 22-Jan-24 6 238
GR-CON-Z18-1273 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
09-Jun-24
system 18-Jun-24 8 130
Mosque M-30 26-Nov-23 27-Jul-24 195 101
Site Preparation 26-Nov-23 17-Dec-23 19 255
GR-CON-Z18-1274 Demolition (Asphalt.Paving,etc.....) 26-Nov-23 29-Nov-23 4 149
GR-CON-Z18-1275 Excavation And Disposal 30-Nov-23 05-Dec-23 5 186
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1276 Prepretion And Compaction 06-Dec-23 10-Dec-23 4 255


GR-CON-Z18-1277 Backfilling 11-Dec-23 17-Dec-23 6 255
Curbstone and Paving 18-Dec-23 11-Jan-24 22 255
GR-CON-Z18-1282 Backfilling (sand / Sub base) 18-Dec-23 27-Dec-23 9 255
GR-CON-Z18-1283 Installation of Paving 28-Dec-23 11-Jan-24 13 255
Landscape Works 06-Dec-23 27-Jul-24 186 101
GR-CON-Z18-1284 Excavation (Tree Pit ) 06-Dec-23 11-Dec-23 5 203
GR-CON-Z18-1285 Aggregate Drainage layer 12-Dec-23 18-Dec-23 6 203
GR-CON-Z18-1286 Installation Geotextile 19-Dec-23 24-Dec-23 5 203
GR-CON-Z18-1287 Backfilling (Soil max for tree) 25-Dec-23 30-Dec-23 5 203
GR-CON-Z18-1288 Installation of Trees 09-May-24 14-May-24 4 101
GR-CON-Z18-4786 Installation of Climbers 14-May-24 19-May-24 4 101
GR-CON-Z18-4796 Installation of Shrubs 19-May-24 23-May-24 4 101
GR-CON-Z18-4806 Installation of Succulents 23-May-24 28-May-24 4 101
GR-CON-Z18-4816 Installation of Ground Covers 28-May-24 02-Jun-24 4 101
GR-CON-Z18-1289 Backfilling (Mulch) 02-Jun-24 24-Jun-24 15 101
GR-CON-Z18-1290 Natural Boulders Installation 24-Jun-24 09-Jul-24 13 101
GR-CON-Z18-1291 Retaining walls . Steps, forming risers, treads and edges with finishes
09-Jul-24 27-Jul-24 15 101
Irrigation Works 06-Dec-23 27-Jul-24 186 101
GR-CON-Z18-1292 Excavation Pipe Irrigation 06-Dec-23 11-Dec-23 5 186
GR-CON-Z18-1293 Sand Bedding 12-Dec-23 14-Dec-23 3 186
GR-CON-Z18-1294 HDPE Pipe Installations and fittings and conduit for cable 16-Dec-23 01-Jan-24 15 186
GR-CON-Z18-1296 Test pressure 02-Jan-24 07-Jan-24 5 186
GR-CON-Z18-1295 Installation of Valves and Accessories 08-Jan-24 11-Jan-24 4 186
GR-CON-Z18-1297 Back filling (sand / Subbase ) 13-Jan-24 18-Jan-24 6 186
GR-CON-Z18-1298 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Jan-24 25-Jan-24 6 237
GR-CON-Z18-1299 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
20-Jul-24
system 27-Jul-24 6 101
Parking P-12 28-Nov-23 11-Jun-24 158 136
Site Preparation 28-Nov-23 04-Dec-23 6 275
GR-CON-Z18-1303 Backfilling 28-Nov-23 04-Dec-23 6 275
GR-CON-Z18-1301 Excavation And Disposal 29-Nov-23 04-Dec-23 5 187
GR-CON-Z18-1300 Demolition (Asphalt.Paving,etc.....) 30-Nov-23 04-Dec-23 4 149
GR-CON-Z18-1302 Prepretion And Compaction 30-Nov-23 04-Dec-23 4 275
Curbstone and Paving 05-Dec-23 27-Jan-24 46 242
GR-CON-Z18-1304 Excavation Curbstone 05-Dec-23 10-Dec-23 5 234
GR-CON-Z18-1305 Plain Concrete 11-Dec-23 17-Dec-23 6 242
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1306 Installation Curbstone 18-Dec-23 27-Dec-23 9 242


GR-CON-Z18-1307 Casting Concrete (Mortar haunch) 28-Dec-23 01-Jan-24 4 242
GR-CON-Z18-1308 Backfilling (sand / Sub base) 02-Jan-24 11-Jan-24 9 242
GR-CON-Z18-1309 Installation of Paving 13-Jan-24 27-Jan-24 13 242
Landscape Works 11-Dec-23 30-May-24 137 136
GR-CON-Z18-1310 Excavation (Tree Pit ) 11-Dec-23 16-Dec-23 5 234
GR-CON-Z18-1311 Aggregate Drainage layer 17-Dec-23 23-Dec-23 6 234
GR-CON-Z18-1312 Installation Geotextile 24-Dec-23 27-Dec-23 4 234
GR-CON-Z18-1313 Backfilling (Soil max for tree) 28-Dec-23 03-Jan-24 6 234
GR-CON-Z18-1314 Installation of Trees 09-May-24 13-May-24 3 136
GR-CON-Z18-8816 Installation of Shrubs 13-May-24 16-May-24 3 136
GR-CON-Z18-8826 Installation of Ground Covers 16-May-24 20-May-24 3 136
GR-CON-Z18-8836 Installation of Succulents 20-May-24 23-May-24 3 136
GR-CON-Z18-8846 Installation of Grass 23-May-24 27-May-24 3 136
GR-CON-Z18-1315 Backfilling (Mulch) 27-May-24 30-May-24 3 136
Site Furnishing 30-May-24 11-Jun-24 10 136
GR-CON-Z18-1326 Tree Grate 30-May-24 05-Jun-24 5 136
GR-CON-Z18-1327 Wheel stoppers 05-Jun-24 11-Jun-24 5 136
Irrigation Works 05-Dec-23 11-Jun-24 152 136
GR-CON-Z18-1318 Excavation Pipe Irrigation 05-Dec-23 10-Dec-23 5 187
GR-CON-Z18-1319 Sand Bedding 11-Dec-23 13-Dec-23 3 187
GR-CON-Z18-1320 HDPE Pipe Installations and fittings and conduit for cable 14-Dec-23 31-Dec-23 15 187
GR-CON-Z18-1322 Test pressure 01-Jan-24 06-Jan-24 5 187
GR-CON-Z18-1321 Installation of Valves and Accessories 07-Jan-24 10-Jan-24 4 187
GR-CON-Z18-1323 Back filling (sand / Subbase ) 11-Jan-24 17-Jan-24 6 187
GR-CON-Z18-1324 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Jan-24 24-Jan-24 6 236
GR-CON-Z18-1325 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Jun-24
system 11-Jun-24 8 136
Parking P-13 25-Dec-23 11-Jun-24 135 136
Site Preparation 25-Dec-23 01-Jan-24 6 252
GR-CON-Z18-1331 Backfilling 25-Dec-23 01-Jan-24 6 252
GR-CON-Z18-1329 Excavation And Disposal 26-Dec-23 01-Jan-24 5 164
GR-CON-Z18-1328 Demolition (Asphalt.Paving,etc.....) 27-Dec-23 01-Jan-24 4 130
GR-CON-Z18-1330 Prepretion And Compaction 27-Dec-23 01-Jan-24 4 252
Curbstone and Paving 01-Jan-24 24-Feb-24 46 219
GR-CON-Z18-1332 Excavation Curbstone 01-Jan-24 07-Jan-24 5 211
GR-CON-Z18-1333 Plain Concrete 07-Jan-24 14-Jan-24 6 219
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1334 Installation Curbstone 14-Jan-24 24-Jan-24 9 219


GR-CON-Z18-1335 Casting Concrete (Mortar haunch) 24-Jan-24 29-Jan-24 4 219
GR-CON-Z18-1336 Backfilling (sand / Sub base) 29-Jan-24 08-Feb-24 9 219
GR-CON-Z18-1337 Installation of Paving 08-Feb-24 24-Feb-24 13 219
Landscape Works 07-Jan-24 30-May-24 114 136
GR-CON-Z18-1338 Excavation (Tree Pit ) 07-Jan-24 13-Jan-24 5 211
GR-CON-Z18-1339 Aggregate Drainage layer 13-Jan-24 20-Jan-24 6 211
GR-CON-Z18-1340 Installation Geotextile 20-Jan-24 24-Jan-24 4 211
GR-CON-Z18-1341 Backfilling (Soil max for tree) 24-Jan-24 31-Jan-24 6 211
GR-CON-Z18-1342 Installation of Trees 09-May-24 13-May-24 3 136
GR-CON-Z18-8856 Installation of Shrubs 13-May-24 16-May-24 3 136
GR-CON-Z18-8866 Installation of Ground Covers 16-May-24 20-May-24 3 136
GR-CON-Z18-8876 Installation of Succulents 20-May-24 23-May-24 3 136
GR-CON-Z18-8886 Installation of Grass 23-May-24 27-May-24 3 136
GR-CON-Z18-1343 Backfilling (Mulch) 27-May-24 30-May-24 3 136
Site Furnishing 30-May-24 11-Jun-24 10 136
GR-CON-Z18-1354 Tree Grate 30-May-24 05-Jun-24 5 136
GR-CON-Z18-1355 Wheel stoppers 05-Jun-24 11-Jun-24 5 136
Irrigation Works 01-Jan-24 11-Jun-24 129 136
GR-CON-Z18-1346 Excavation Pipe Irrigation 01-Jan-24 07-Jan-24 5 164
GR-CON-Z18-1347 Sand Bedding 07-Jan-24 10-Jan-24 3 164
GR-CON-Z18-1348 HDPE Pipe Installations and fittings and conduit for cable 10-Jan-24 28-Jan-24 15 164
GR-CON-Z18-1350 Test pressure 28-Jan-24 03-Feb-24 5 164
GR-CON-Z18-1349 Installation of Valves and Accessories 03-Feb-24 07-Feb-24 4 164
GR-CON-Z18-1351 Back filling (sand / Subbase ) 07-Feb-24 14-Feb-24 6 164
GR-CON-Z18-1352 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Feb-24 21-Feb-24 6 213
GR-CON-Z18-1353 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Jun-24
system 11-Jun-24 8 136
Parking P-14 22-Jan-24 11-Jun-24 111 136
Site Preparation 22-Jan-24 29-Jan-24 6 228
GR-CON-Z18-1359 Backfilling 22-Jan-24 29-Jan-24 6 228
GR-CON-Z18-1357 Excavation And Disposal 23-Jan-24 29-Jan-24 5 140
GR-CON-Z18-1356 Demolition (Asphalt.Paving,etc.....) 24-Jan-24 29-Jan-24 4 110
GR-CON-Z18-1358 Prepretion And Compaction 24-Jan-24 29-Jan-24 4 228
Curbstone and Paving 29-Jan-24 25-Mar-24 46 195
GR-CON-Z18-1360 Excavation Curbstone 29-Jan-24 04-Feb-24 5 187
GR-CON-Z18-1361 Plain Concrete 04-Feb-24 11-Feb-24 6 195
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1362 Installation Curbstone 11-Feb-24 21-Feb-24 9 195


GR-CON-Z18-1363 Casting Concrete (Mortar haunch) 21-Feb-24 26-Feb-24 4 195
GR-CON-Z18-1364 Backfilling (sand / Sub base) 26-Feb-24 07-Mar-24 9 195
GR-CON-Z18-1365 Installation of Paving 07-Mar-24 25-Mar-24 13 195
Landscape Works 04-Feb-24 30-May-24 90 136
GR-CON-Z18-1366 Excavation (Tree Pit ) 04-Feb-24 10-Feb-24 5 187
GR-CON-Z18-1367 Aggregate Drainage layer 10-Feb-24 17-Feb-24 6 187
GR-CON-Z18-1368 Installation Geotextile 17-Feb-24 21-Feb-24 4 187
GR-CON-Z18-1369 Backfilling (Soil max for tree) 21-Feb-24 28-Feb-24 6 187
GR-CON-Z18-1370 Installation of Trees 09-May-24 13-May-24 3 136
GR-CON-Z18-8896 Installation of Shrubs 13-May-24 16-May-24 3 136
GR-CON-Z18-8906 Installation of Ground Covers 16-May-24 20-May-24 3 136
GR-CON-Z18-8916 Installation of Succulents 20-May-24 23-May-24 3 136
GR-CON-Z18-8926 Installation of Grass 23-May-24 27-May-24 3 136
GR-CON-Z18-1371 Backfilling (Mulch) 27-May-24 30-May-24 3 136
Site Furnishing 30-May-24 11-Jun-24 10 136
GR-CON-Z18-1382 Tree Grate 30-May-24 05-Jun-24 5 136
GR-CON-Z18-1383 Wheel stoppers 05-Jun-24 11-Jun-24 5 136
Irrigation Works 29-Jan-24 11-Jun-24 105 136
GR-CON-Z18-1374 Excavation Pipe Irrigation 29-Jan-24 04-Feb-24 5 140
GR-CON-Z18-1375 Sand Bedding 04-Feb-24 07-Feb-24 3 140
GR-CON-Z18-1376 HDPE Pipe Installations and fittings and conduit for cable 07-Feb-24 25-Feb-24 15 140
GR-CON-Z18-1378 Test pressure 25-Feb-24 02-Mar-24 5 140
GR-CON-Z18-1377 Installation of Valves and Accessories 02-Mar-24 06-Mar-24 4 140
GR-CON-Z18-1379 Back filling (sand / Subbase ) 06-Mar-24 13-Mar-24 6 140
GR-CON-Z18-1380 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Mar-24 23-Mar-24 6 189
GR-CON-Z18-1381 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Jun-24
system 11-Jun-24 8 136
Street SS-20.1 30-Jan-24 17-Jul-24 131 109
Site Preparation 30-Jan-24 24-Feb-24 21 219
GR-CON-Z18-1000 Demolition (Asphalt.Paving,etc.....) 30-Jan-24 04-Feb-24 4 109
GR-CON-Z18-1001 Excavation And Disposal 04-Feb-24 10-Feb-24 5 129
GR-CON-Z18-1002 Prepretion And Compaction 10-Feb-24 17-Feb-24 6 219
GR-CON-Z18-1003 Backfilling 17-Feb-24 24-Feb-24 6 219
Curbstone and Paving 10-Feb-24 10-Apr-24 46 185
GR-CON-Z18-1004 Excavation Curbstone 10-Feb-24 15-Feb-24 5 150
GR-CON-Z18-1005 Plain Concrete 15-Feb-24 22-Feb-24 6 185
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1006 Installation Curbstone 22-Feb-24 04-Mar-24 9 185


GR-CON-Z18-1007 Casting Concrete (Mortar haunch) 04-Mar-24 09-Mar-24 4 185
GR-CON-Z18-1008 Backfilling (sand / Sub base) 09-Mar-24 20-Mar-24 9 185
GR-CON-Z18-1009 Installation of Paving 21-Mar-24 10-Apr-24 13 185
Landscape Works 15-Feb-24 24-Jun-24 97 109
GR-CON-Z18-1010 Excavation (Tree Pit ) 15-Feb-24 21-Feb-24 5 150
GR-CON-Z18-1011 Aggregate Drainage layer 21-Feb-24 28-Feb-24 6 150
GR-CON-Z18-1012 Installation Geotextile 28-Feb-24 04-Mar-24 4 150
GR-CON-Z18-1013 Backfilling (Soil max for tree) 04-Mar-24 11-Mar-24 6 150
GR-CON-Z18-1014 Installation of Trees 09-May-24 13-May-24 3 109
GR-CON-Z18-13616 Installation of Shrubs 13-May-24 16-May-24 3 109
GR-CON-Z18-13626 Installation of Succulents 16-May-24 20-May-24 3 109
GR-CON-Z18-13636 Installation of Ground Covers 20-May-24 23-May-24 3 109
GR-CON-Z18-13646 Installation of Grass 23-May-24 27-May-24 3 109
GR-CON-Z18-1015 Backfilling (Mulch) 27-May-24 30-May-24 3 109
GR-CON-Z18-1016 Natural Boulders Installation 30-May-24 04-Jun-24 4 109
GR-CON-Z18-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jun-24 24-Jun-24 13 109
Site Furnishing 24-Jun-24 17-Jul-24 20 109
GR-CON-Z18-1026 Garden planter box 24-Jun-24 30-Jun-24 5 109
GR-CON-Z18-1027 Wheel stoppers 30-Jun-24 06-Jul-24 5 109
GR-CON-Z18-1028 Steel Lattice 06-Jul-24 11-Jul-24 5 109
GR-CON-Z18-1029 Handrail 11-Jul-24 17-Jul-24 5 109
Storm Piping Works 10-Jul-24 17-Jul-24 6 109
GR-CON-Z18-1030 Installation of DI grating covers 10-Jul-24 17-Jul-24 6 109
Irrigation Works 10-Feb-24 23-Apr-24 53 172
GR-CON-Z18-1018 Excavation Pipe Irrigation 10-Feb-24 15-Feb-24 5 129
GR-CON-Z18-1019 Sand Bedding 15-Feb-24 20-Feb-24 4 129
GR-CON-Z18-1020 HDPE Pipe Installations and fittings and conduit for cable 20-Feb-24 09-Mar-24 15 129
GR-CON-Z18-1022 Test pressure 09-Mar-24 14-Mar-24 5 129
GR-CON-Z18-1021 Installation of Valves and Accessories 14-Mar-24 20-Mar-24 4 129
GR-CON-Z18-1023 Back filling (sand / Subbase ) 21-Mar-24 30-Mar-24 6 129
GR-CON-Z18-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 31-Mar-24 08-Apr-24 6 172
GR-CON-Z18-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
09-Apr-24
system 23-Apr-24 8 172
Electrical Works 15-Feb-24 17-Jul-24 117 109
GR-CON-Z18-1031 Excavation And Disposal 15-Feb-24 21-Feb-24 5 199
GR-CON-Z18-1032 Sand Bedding 21-Feb-24 26-Feb-24 4 199
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1033 laying cables 26-Feb-24 02-Mar-24 4 199


GR-CON-Z18-1034 Backfilling (sand / Sub base) 02-Mar-24 07-Mar-24 5 199
GR-CON-Z18-1035 Control Panel / Distribution Panel Installation 07-Mar-24 12-Mar-24 4 199
GR-CON-Z18-1036 Road Crossing Ducts 11-Jul-24 17-Jul-24 5 109
Street SS-69 05-Feb-24 17-Jul-24 126 109
Site Preparation 05-Feb-24 29-Feb-24 21 214
GR-CON-Z18-1037 Demolition (Asphalt.Paving,etc.....) 05-Feb-24 10-Feb-24 4 108
GR-CON-Z18-1038 Excavation And Disposal 10-Feb-24 15-Feb-24 5 124
GR-CON-Z18-1039 Prepretion And Compaction 15-Feb-24 22-Feb-24 6 214
GR-CON-Z18-1040 Backfilling 22-Feb-24 29-Feb-24 6 214
Curbstone and Paving 15-Feb-24 21-Apr-24 46 180
GR-CON-Z18-1041 Excavation Curbstone 15-Feb-24 21-Feb-24 5 145
GR-CON-Z18-1042 Plain Concrete 21-Feb-24 28-Feb-24 6 180
GR-CON-Z18-1043 Installation Curbstone 28-Feb-24 10-Mar-24 9 180
GR-CON-Z18-1044 Casting Concrete (Mortar haunch) 10-Mar-24 14-Mar-24 4 180
GR-CON-Z18-1045 Backfilling (sand / Sub base) 14-Mar-24 28-Mar-24 9 180
GR-CON-Z18-1046 Installation of Paving 28-Mar-24 21-Apr-24 13 180
Landscape Works 21-Feb-24 24-Jun-24 92 109
GR-CON-Z18-1047 Excavation (Tree Pit ) 21-Feb-24 27-Feb-24 5 145
GR-CON-Z18-1048 Aggregate Drainage layer 27-Feb-24 05-Mar-24 6 145
GR-CON-Z18-1049 Installation Geotextile 05-Mar-24 10-Mar-24 4 145
GR-CON-Z18-1050 Backfilling (Soil max for tree) 10-Mar-24 18-Mar-24 6 145
GR-CON-Z18-1051 Installation of Trees 09-May-24 13-May-24 3 109
GR-CON-Z18-13656 Installation of Shrubs 13-May-24 16-May-24 3 109
GR-CON-Z18-13666 Installation of Succulents 16-May-24 20-May-24 3 109
GR-CON-Z18-13676 Installation of Ground Covers 20-May-24 23-May-24 3 109
GR-CON-Z18-13686 Installation of Grass 23-May-24 27-May-24 3 109
GR-CON-Z18-1052 Backfilling (Mulch) 27-May-24 30-May-24 3 109
GR-CON-Z18-1053 Natural Boulders Installation 30-May-24 04-Jun-24 4 109
GR-CON-Z18-1054 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jun-24 24-Jun-24 13 109
Site Furnishing 24-Jun-24 17-Jul-24 20 109
GR-CON-Z18-1063 Garden planter box 24-Jun-24 30-Jun-24 5 109
GR-CON-Z18-1064 Wheel stoppers 30-Jun-24 06-Jul-24 5 109
GR-CON-Z18-1065 Steel Lattice 06-Jul-24 11-Jul-24 5 109
GR-CON-Z18-1066 Handrail 11-Jul-24 17-Jul-24 5 109
Storm Piping Works 10-Jul-24 17-Jul-24 6 109
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1067 Installation of DI grating covers 10-Jul-24 17-Jul-24 6 109


Irrigation Works 15-Feb-24 29-Apr-24 53 167
GR-CON-Z18-1055 Excavation Pipe Irrigation 15-Feb-24 21-Feb-24 5 124
GR-CON-Z18-1056 Sand Bedding 21-Feb-24 26-Feb-24 4 124
GR-CON-Z18-1057 HDPE Pipe Installations and fittings and conduit for cable 26-Feb-24 14-Mar-24 15 124
GR-CON-Z18-1059 Test pressure 14-Mar-24 23-Mar-24 5 124
GR-CON-Z18-1058 Installation of Valves and Accessories 23-Mar-24 28-Mar-24 4 124
GR-CON-Z18-1060 Back filling (sand / Subbase ) 28-Mar-24 07-Apr-24 6 124
GR-CON-Z18-1061 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 07-Apr-24 20-Apr-24 6 167
GR-CON-Z18-1062 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
20-Apr-24
system 29-Apr-24 8 167
Electrical Works 21-Feb-24 17-Jul-24 112 109
GR-CON-Z18-1068 Excavation And Disposal 21-Feb-24 27-Feb-24 5 194
GR-CON-Z18-1069 Sand Bedding 27-Feb-24 03-Mar-24 4 194
GR-CON-Z18-1070 laying cables 03-Mar-24 07-Mar-24 4 194
GR-CON-Z18-1071 Backfilling (sand / Sub base) 07-Mar-24 13-Mar-24 5 194
GR-CON-Z18-1072 Control Panel / Distribution Panel Installation 13-Mar-24 19-Mar-24 4 194
GR-CON-Z18-1073 Road Crossing Ducts 11-Jul-24 17-Jul-24 5 109
Street SS-71 17-Feb-24 17-Jul-24 116 109
Site Preparation 17-Feb-24 12-Mar-24 21 204
GR-CON-Z18-1074 Demolition (Asphalt.Paving,etc.....) 17-Feb-24 21-Feb-24 4 102
GR-CON-Z18-1075 Excavation And Disposal 21-Feb-24 27-Feb-24 5 114
GR-CON-Z18-1076 Prepretion And Compaction 27-Feb-24 05-Mar-24 6 204
GR-CON-Z18-1077 Backfilling 05-Mar-24 12-Mar-24 6 204
Curbstone and Paving 27-Feb-24 02-May-24 46 170
GR-CON-Z18-1078 Excavation Curbstone 27-Feb-24 04-Mar-24 5 135
GR-CON-Z18-1079 Plain Concrete 04-Mar-24 11-Mar-24 6 170
GR-CON-Z18-1080 Installation Curbstone 11-Mar-24 24-Mar-24 9 170
GR-CON-Z18-1081 Casting Concrete (Mortar haunch) 24-Mar-24 30-Mar-24 4 170
GR-CON-Z18-1082 Backfilling (sand / Sub base) 31-Mar-24 17-Apr-24 9 170
GR-CON-Z18-1083 Installation of Paving 17-Apr-24 02-May-24 13 170
Landscape Works 04-Mar-24 24-Jun-24 82 109
GR-CON-Z18-1084 Excavation (Tree Pit ) 04-Mar-24 10-Mar-24 5 135
GR-CON-Z18-1085 Aggregate Drainage layer 10-Mar-24 18-Mar-24 6 135
GR-CON-Z18-1086 Installation Geotextile 18-Mar-24 24-Mar-24 4 135
GR-CON-Z18-1087 Backfilling (Soil max for tree) 24-Mar-24 02-Apr-24 6 135
GR-CON-Z18-1088 Installation of Trees 09-May-24 13-May-24 3 109
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-13696 Installation of Shrubs 13-May-24 16-May-24 3 109


GR-CON-Z18-13706 Installation of Succulents 16-May-24 20-May-24 3 109
GR-CON-Z18-13716 Installation of Ground Covers 20-May-24 23-May-24 3 109
GR-CON-Z18-13726 Installation of Grass 23-May-24 27-May-24 3 109
GR-CON-Z18-1089 Backfilling (Mulch) 27-May-24 30-May-24 3 109
GR-CON-Z18-1090 Natural Boulders Installation 30-May-24 04-Jun-24 4 109
GR-CON-Z18-1091 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jun-24 24-Jun-24 13 109
Site Furnishing 24-Jun-24 17-Jul-24 20 109
GR-CON-Z18-1100 Garden planter box 24-Jun-24 30-Jun-24 5 109
GR-CON-Z18-1101 Wheel stoppers 30-Jun-24 06-Jul-24 5 109
GR-CON-Z18-1102 Steel Lattice 06-Jul-24 11-Jul-24 5 109
GR-CON-Z18-1103 Handrail 11-Jul-24 17-Jul-24 5 109
Storm Piping Works 10-Jul-24 17-Jul-24 6 109
GR-CON-Z18-1104 Installation of DI grating covers 10-Jul-24 17-Jul-24 6 109
Irrigation Works 27-Feb-24 11-May-24 53 157
GR-CON-Z18-1092 Excavation Pipe Irrigation 27-Feb-24 04-Mar-24 5 114
GR-CON-Z18-1093 Sand Bedding 04-Mar-24 09-Mar-24 4 114
GR-CON-Z18-1094 HDPE Pipe Installations and fittings and conduit for cable 09-Mar-24 30-Mar-24 15 114
GR-CON-Z18-1096 Test pressure 31-Mar-24 07-Apr-24 5 114
GR-CON-Z18-1095 Installation of Valves and Accessories 07-Apr-24 17-Apr-24 4 114
GR-CON-Z18-1097 Back filling (sand / Subbase ) 17-Apr-24 24-Apr-24 6 114
GR-CON-Z18-1098 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Apr-24 01-May-24 6 157
GR-CON-Z18-1099 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
01-May-24
system 11-May-24 8 157
Electrical Works 04-Mar-24 17-Jul-24 102 109
GR-CON-Z18-1105 Excavation And Disposal 04-Mar-24 10-Mar-24 5 184
GR-CON-Z18-1106 Sand Bedding 10-Mar-24 14-Mar-24 4 184
GR-CON-Z18-1107 laying cables 14-Mar-24 20-Mar-24 4 184
GR-CON-Z18-1108 Backfilling (sand / Sub base) 21-Mar-24 28-Mar-24 5 184
GR-CON-Z18-1109 Control Panel / Distribution Panel Installation 28-Mar-24 03-Apr-24 4 184
GR-CON-Z18-1110 Road Crossing Ducts 11-Jul-24 17-Jul-24 5 109
Street SS-97 22-Feb-24 17-Jul-24 111 109
Site Preparation 22-Feb-24 19-Mar-24 21 199
GR-CON-Z18-1111 Demolition (Asphalt.Paving,etc.....) 22-Feb-24 27-Feb-24 4 101
GR-CON-Z18-1112 Excavation And Disposal 27-Feb-24 04-Mar-24 5 109
GR-CON-Z18-1113 Prepretion And Compaction 04-Mar-24 11-Mar-24 6 199
GR-CON-Z18-1114 Backfilling 11-Mar-24 19-Mar-24 6 199
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 04-Mar-24 08-May-24 46 165


GR-CON-Z18-1115 Excavation Curbstone 04-Mar-24 10-Mar-24 5 130
GR-CON-Z18-1116 Plain Concrete 10-Mar-24 18-Mar-24 6 165
GR-CON-Z18-1117 Installation Curbstone 18-Mar-24 01-Apr-24 9 165
GR-CON-Z18-1118 Casting Concrete (Mortar haunch) 01-Apr-24 07-Apr-24 4 165
GR-CON-Z18-1119 Backfilling (sand / Sub base) 07-Apr-24 23-Apr-24 9 165
GR-CON-Z18-1120 Installation of Paving 23-Apr-24 08-May-24 13 165
Landscape Works 10-Mar-24 24-Jun-24 77 109
GR-CON-Z18-1121 Excavation (Tree Pit ) 10-Mar-24 16-Mar-24 5 130
GR-CON-Z18-1122 Aggregate Drainage layer 17-Mar-24 25-Mar-24 6 130
GR-CON-Z18-1123 Installation Geotextile 26-Mar-24 01-Apr-24 4 130
GR-CON-Z18-1124 Backfilling (Soil max for tree) 01-Apr-24 10-Apr-24 6 130
GR-CON-Z18-1125 Installation of Trees 09-May-24 13-May-24 3 109
GR-CON-Z18-13736 Installation of Shrubs 13-May-24 16-May-24 3 109
GR-CON-Z18-13746 Installation of Succulents 16-May-24 20-May-24 3 109
GR-CON-Z18-13756 Installation of Ground Covers 20-May-24 23-May-24 3 109
GR-CON-Z18-13766 Installation of Grass 23-May-24 27-May-24 3 109
GR-CON-Z18-1126 Backfilling (Mulch) 27-May-24 30-May-24 3 109
GR-CON-Z18-1127 Natural Boulders Installation 30-May-24 04-Jun-24 4 109
GR-CON-Z18-1128 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jun-24 24-Jun-24 13 109
Site Furnishing 24-Jun-24 17-Jul-24 20 109
GR-CON-Z18-1137 Garden planter box 24-Jun-24 30-Jun-24 5 109
GR-CON-Z18-1138 Wheel stoppers 30-Jun-24 06-Jul-24 5 109
GR-CON-Z18-1139 Steel Lattice 06-Jul-24 11-Jul-24 5 109
GR-CON-Z18-1140 Handrail 11-Jul-24 17-Jul-24 5 109
Storm Piping Works 10-Jul-24 17-Jul-24 6 109
GR-CON-Z18-1141 Installation of DI grating covers 10-Jul-24 17-Jul-24 6 109
Irrigation Works 04-Mar-24 16-May-24 53 152
GR-CON-Z18-1129 Excavation Pipe Irrigation 04-Mar-24 10-Mar-24 5 109
GR-CON-Z18-1130 Sand Bedding 10-Mar-24 14-Mar-24 4 109
GR-CON-Z18-1131 HDPE Pipe Installations and fittings and conduit for cable 14-Mar-24 07-Apr-24 15 109
GR-CON-Z18-1133 Test pressure 07-Apr-24 18-Apr-24 5 109
GR-CON-Z18-1132 Installation of Valves and Accessories 18-Apr-24 23-Apr-24 4 109
GR-CON-Z18-1134 Back filling (sand / Subbase ) 23-Apr-24 30-Apr-24 6 109
GR-CON-Z18-1135 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Apr-24 07-May-24 6 152
GR-CON-Z18-1136 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-May-24
system 16-May-24 8 152
Activity ID Activity Name Start Finish Original Total Float
Duration

Electrical Works 10-Mar-24 17-Jul-24 97 109


GR-CON-Z18-1142 Excavation And Disposal 10-Mar-24 16-Mar-24 5 179
GR-CON-Z18-1143 Sand Bedding 17-Mar-24 23-Mar-24 4 179
GR-CON-Z18-1144 laying cables 23-Mar-24 28-Mar-24 4 179
GR-CON-Z18-1145 Backfilling (sand / Sub base) 28-Mar-24 06-Apr-24 5 179
GR-CON-Z18-1146 Control Panel / Distribution Panel Installation 06-Apr-24 11-Apr-24 4 179
GR-CON-Z18-1147 Road Crossing Ducts 11-Jul-24 17-Jul-24 5 109
Street SS-98 27-Feb-24 17-Jul-24 107 109
Site Preparation 27-Feb-24 25-Mar-24 21 195
GR-CON-Z18-1148 Demolition (Asphalt.Paving,etc.....) 27-Feb-24 03-Mar-24 4 101
GR-CON-Z18-1149 Excavation And Disposal 03-Mar-24 09-Mar-24 5 105
GR-CON-Z18-1150 Prepretion And Compaction 09-Mar-24 16-Mar-24 6 195
GR-CON-Z18-1151 Backfilling 17-Mar-24 25-Mar-24 6 195
Curbstone and Paving 09-Mar-24 13-May-24 46 161
GR-CON-Z18-1152 Excavation Curbstone 09-Mar-24 14-Mar-24 5 126
GR-CON-Z18-1153 Plain Concrete 14-Mar-24 24-Mar-24 6 161
GR-CON-Z18-1154 Installation Curbstone 24-Mar-24 07-Apr-24 9 161
GR-CON-Z18-1155 Casting Concrete (Mortar haunch) 07-Apr-24 17-Apr-24 4 161
GR-CON-Z18-1156 Backfilling (sand / Sub base) 17-Apr-24 28-Apr-24 9 161
GR-CON-Z18-1157 Installation of Paving 28-Apr-24 13-May-24 13 161
Landscape Works 14-Mar-24 24-Jun-24 73 109
GR-CON-Z18-1158 Excavation (Tree Pit ) 14-Mar-24 23-Mar-24 5 126
GR-CON-Z18-1159 Aggregate Drainage layer 23-Mar-24 01-Apr-24 6 126
GR-CON-Z18-1160 Installation Geotextile 01-Apr-24 07-Apr-24 4 126
GR-CON-Z18-1161 Backfilling (Soil max for tree) 07-Apr-24 20-Apr-24 6 126
GR-CON-Z18-1162 Installation of Trees 09-May-24 13-May-24 3 109
GR-CON-Z18-13776 Installation of Shrubs 13-May-24 16-May-24 3 109
GR-CON-Z18-13786 Installation of Succulents 16-May-24 20-May-24 3 109
GR-CON-Z18-13796 Installation of Ground Covers 20-May-24 23-May-24 3 109
GR-CON-Z18-13806 Installation of Grass 23-May-24 27-May-24 3 109
GR-CON-Z18-1163 Backfilling (Mulch) 27-May-24 30-May-24 3 109
GR-CON-Z18-1164 Natural Boulders Installation 30-May-24 04-Jun-24 4 109
GR-CON-Z18-1165 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jun-24 24-Jun-24 13 109
Site Furnishing 24-Jun-24 17-Jul-24 20 109
GR-CON-Z18-1174 Garden planter box 24-Jun-24 30-Jun-24 5 109
GR-CON-Z18-1175 Wheel stoppers 30-Jun-24 06-Jul-24 5 109
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1176 Steel Lattice 06-Jul-24 11-Jul-24 5 109


GR-CON-Z18-1177 Handrail 11-Jul-24 17-Jul-24 5 109
Storm Piping Works 10-Jul-24 17-Jul-24 6 109
GR-CON-Z18-1178 Installation of DI grating covers 10-Jul-24 17-Jul-24 6 109
Irrigation Works 09-Mar-24 21-May-24 53 148
GR-CON-Z18-1166 Excavation Pipe Irrigation 09-Mar-24 14-Mar-24 5 105
GR-CON-Z18-1167 Sand Bedding 14-Mar-24 20-Mar-24 4 105
GR-CON-Z18-1168 HDPE Pipe Installations and fittings and conduit for cable 21-Mar-24 17-Apr-24 15 105
GR-CON-Z18-1170 Test pressure 17-Apr-24 23-Apr-24 5 105
GR-CON-Z18-1169 Installation of Valves and Accessories 23-Apr-24 28-Apr-24 4 105
GR-CON-Z18-1171 Back filling (sand / Subbase ) 28-Apr-24 05-May-24 6 105
GR-CON-Z18-1172 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-May-24 12-May-24 6 148
GR-CON-Z18-1173 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-May-24
system 21-May-24 8 148
Electrical Works 14-Mar-24 17-Jul-24 93 109
GR-CON-Z18-1179 Excavation And Disposal 14-Mar-24 23-Mar-24 5 175
GR-CON-Z18-1180 Sand Bedding 23-Mar-24 28-Mar-24 4 175
GR-CON-Z18-1181 laying cables 28-Mar-24 03-Apr-24 4 175
GR-CON-Z18-1182 Backfilling (sand / Sub base) 04-Apr-24 11-Apr-24 5 175
GR-CON-Z18-1183 Control Panel / Distribution Panel Installation 11-Apr-24 21-Apr-24 4 175
GR-CON-Z18-1184 Road Crossing Ducts 11-Jul-24 17-Jul-24 5 109
Street SS-99 03-Mar-24 17-Jul-24 103 109
Site Preparation 03-Mar-24 01-Apr-24 21 191
GR-CON-Z18-1185 Demolition (Asphalt.Paving,etc.....) 03-Mar-24 07-Mar-24 4 101
GR-CON-Z18-1186 Excavation And Disposal 07-Mar-24 13-Mar-24 5 101
GR-CON-Z18-1187 Prepretion And Compaction 13-Mar-24 23-Mar-24 6 191
GR-CON-Z18-1188 Backfilling 23-Mar-24 01-Apr-24 6 191
Curbstone and Paving 13-Mar-24 18-May-24 46 157
GR-CON-Z18-1189 Excavation Curbstone 13-Mar-24 20-Mar-24 5 122
GR-CON-Z18-1190 Plain Concrete 21-Mar-24 30-Mar-24 6 157
GR-CON-Z18-1191 Installation Curbstone 31-Mar-24 17-Apr-24 9 157
GR-CON-Z18-1192 Casting Concrete (Mortar haunch) 17-Apr-24 22-Apr-24 4 157
GR-CON-Z18-1193 Backfilling (sand / Sub base) 22-Apr-24 02-May-24 9 157
GR-CON-Z18-1194 Installation of Paving 02-May-24 18-May-24 13 157
Landscape Works 21-Mar-24 24-Jun-24 69 109
GR-CON-Z18-1195 Excavation (Tree Pit ) 21-Mar-24 28-Mar-24 5 122
GR-CON-Z18-1196 Aggregate Drainage layer 28-Mar-24 07-Apr-24 6 122
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1197 Installation Geotextile 07-Apr-24 17-Apr-24 4 122


GR-CON-Z18-1198 Backfilling (Soil max for tree) 17-Apr-24 24-Apr-24 6 122
GR-CON-Z18-1199 Installation of Trees 09-May-24 13-May-24 3 109
GR-CON-Z18-13816 Installation of Shrubs 13-May-24 16-May-24 3 109
GR-CON-Z18-13826 Installation of Succulents 16-May-24 20-May-24 3 109
GR-CON-Z18-13836 Installation of Ground Covers 20-May-24 23-May-24 3 109
GR-CON-Z18-13846 Installation of Grass 23-May-24 27-May-24 3 109
GR-CON-Z18-1200 Backfilling (Mulch) 27-May-24 30-May-24 3 109
GR-CON-Z18-1201 Natural Boulders Installation 30-May-24 04-Jun-24 4 109
GR-CON-Z18-1202 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jun-24 24-Jun-24 13 109
Site Furnishing 24-Jun-24 17-Jul-24 20 109
GR-CON-Z18-1211 Garden planter box 24-Jun-24 30-Jun-24 5 109
GR-CON-Z18-1212 Wheel stoppers 30-Jun-24 06-Jul-24 5 109
GR-CON-Z18-1213 Steel Lattice 06-Jul-24 11-Jul-24 5 109
GR-CON-Z18-1214 Handrail 11-Jul-24 17-Jul-24 5 109
Storm Piping Works 10-Jul-24 17-Jul-24 6 109
GR-CON-Z18-1215 Installation of DI grating covers 10-Jul-24 17-Jul-24 6 109
Irrigation Works 13-Mar-24 26-May-24 53 144
GR-CON-Z18-1203 Excavation Pipe Irrigation 13-Mar-24 20-Mar-24 5 101
GR-CON-Z18-1204 Sand Bedding 21-Mar-24 27-Mar-24 4 101
GR-CON-Z18-1205 HDPE Pipe Installations and fittings and conduit for cable 27-Mar-24 22-Apr-24 15 101
GR-CON-Z18-1207 Test pressure 22-Apr-24 28-Apr-24 5 101
GR-CON-Z18-1206 Installation of Valves and Accessories 28-Apr-24 02-May-24 4 101
GR-CON-Z18-1208 Back filling (sand / Subbase ) 02-May-24 09-May-24 6 101
GR-CON-Z18-1209 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-May-24 16-May-24 6 144
GR-CON-Z18-1210 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
16-May-24
system 26-May-24 8 144
Electrical Works 21-Mar-24 17-Jul-24 89 109
GR-CON-Z18-1216 Excavation And Disposal 21-Mar-24 28-Mar-24 5 171
GR-CON-Z18-1217 Sand Bedding 28-Mar-24 03-Apr-24 4 171
GR-CON-Z18-1218 laying cables 04-Apr-24 10-Apr-24 4 171
GR-CON-Z18-1219 Backfilling (sand / Sub base) 10-Apr-24 21-Apr-24 5 171
GR-CON-Z18-1220 Control Panel / Distribution Panel Installation 21-Apr-24 25-Apr-24 4 171
GR-CON-Z18-1221 Road Crossing Ducts 11-Jul-24 17-Jul-24 5 109
School S-17 07-Mar-24 13-Jul-24 95 113
Site Preparation 07-Mar-24 19-Mar-24 9 199
GR-CON-Z18-1385 Excavation And Disposal 07-Mar-24 13-Mar-24 5 102
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z18-1386 Prepretion And Compaction 13-Mar-24 19-Mar-24 4 199


Curbstone and Paving 13-Mar-24 18-May-24 46 157
GR-CON-Z18-1388 Excavation Curbstone 13-Mar-24 20-Mar-24 5 126
GR-CON-Z18-1389 Plain Concrete 21-Mar-24 30-Mar-24 6 157
GR-CON-Z18-1390 Installation Curbstone 31-Mar-24 17-Apr-24 9 157
GR-CON-Z18-1391 Casting Concrete (Mortar haunch) 17-Apr-24 22-Apr-24 4 157
GR-CON-Z18-1392 Backfilling (sand / Sub base) 22-Apr-24 02-May-24 9 157
GR-CON-Z18-1393 Installation of Paving 02-May-24 18-May-24 13 157
Landscape Works 21-Mar-24 01-Jul-24 75 113
GR-CON-Z18-1394 Excavation (Tree Pit ) 21-Mar-24 28-Mar-24 5 126
GR-CON-Z18-1395 Aggregate Drainage layer 28-Mar-24 07-Apr-24 6 126
GR-CON-Z18-1396 Installation Geotextile 07-Apr-24 17-Apr-24 4 126
GR-CON-Z18-1397 Backfilling (Soil max for tree) 17-Apr-24 24-Apr-24 6 126
GR-CON-Z18-1398 Installation of Trees 09-May-24 13-May-24 3 113
GR-CON-Z18-6076 Installation of Shrubs 13-May-24 16-May-24 3 113
GR-CON-Z18-6086 Installation of Succulents 16-May-24 20-May-24 3 113
GR-CON-Z18-6096 Installation of Ground Covers 20-May-24 23-May-24 3 113
GR-CON-Z18-6106 Installation of Climbers 23-May-24 27-May-24 3 113
GR-CON-Z18-6116 Installation of Grass 27-May-24 30-May-24 3 113
GR-CON-Z18-6126 Installation of Lawns 30-May-24 03-Jun-24 3 113
GR-CON-Z18-1399 Backfilling (Mulch) 03-Jun-24 06-Jun-24 3 113
GR-CON-Z18-1400 Natural Boulders Installation 06-Jun-24 11-Jun-24 4 113
GR-CON-Z18-1401 Retaining walls . Steps, forming risers, treads and edges with finishes
11-Jun-24 01-Jul-24 13 113
Site Furnishing 01-Jul-24 13-Jul-24 10 113
GR-CON-Z18-1410 Garden planter box 01-Jul-24 07-Jul-24 5 113
GR-CON-Z18-1411 Wheel stoppers 07-Jul-24 13-Jul-24 5 113
Irrigation Works 13-Mar-24 13-Jul-24 90 113
GR-CON-Z18-1402 Excavation Pipe Irrigation 13-Mar-24 20-Mar-24 5 102
GR-CON-Z18-1403 Sand Bedding 21-Mar-24 25-Mar-24 3 102
GR-CON-Z18-1404 HDPE Pipe Installations and fittings and conduit for cable 26-Mar-24 21-Apr-24 15 102
GR-CON-Z18-1406 Test pressure 21-Apr-24 27-Apr-24 5 102
GR-CON-Z18-1405 Installation of Valves and Accessories 27-Apr-24 01-May-24 4 102
GR-CON-Z18-1407 Back filling (sand / Subbase ) 01-May-24 08-May-24 6 102
GR-CON-Z18-1408 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-May-24 15-May-24 6 151
GR-CON-Z18-1409 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jul-24
system 13-Jul-24 8 113
Zone 20 21-Nov-23 07-Dec-24 313 0
Activity ID Activity Name Start Finish Original Total Float
Duration

Future Neighborhood Park FNP-31 21-Nov-23 18-Sep-24 246 67


Site Preparation 21-Nov-23 13-Dec-23 20 280
GR-CON-Z20-1367 Demolition (Asphalt.Paving,etc.....) 21-Nov-23 25-Nov-23 4 22
GR-CON-Z20-1368 Excavation And Disposal 26-Nov-23 02-Dec-23 6 164
GR-CON-Z20-1369 Prepretion And Compaction 03-Dec-23 06-Dec-23 4 280
GR-CON-Z20-1370 Backfilling 07-Dec-23 13-Dec-23 6 280
Curbstone and Paving 03-Dec-23 24-Jan-24 46 244
GR-CON-Z20-1371 Excavation Curbstone 03-Dec-23 07-Dec-23 5 216
GR-CON-Z20-1372 Plain Concrete 09-Dec-23 14-Dec-23 6 244
GR-CON-Z20-1373 Installation Curbstone 16-Dec-23 25-Dec-23 9 244
GR-CON-Z20-1374 Casting Concrete (Mortar haunch) 26-Dec-23 30-Dec-23 4 244
GR-CON-Z20-1375 Backfilling (sand / Sub base) 31-Dec-23 09-Jan-24 9 244
GR-CON-Z20-1376 Installation of Paving 10-Jan-24 24-Jan-24 13 244
Landscape Works 09-Dec-23 18-Sep-24 231 54
GR-CON-Z20-1377 Excavation (Tree Pit ) 09-Dec-23 13-Dec-23 5 216
GR-CON-Z20-1378 Aggregate Drainage layer 14-Dec-23 20-Dec-23 6 230
GR-CON-Z20-1379 Installation Geotextile 21-Dec-23 25-Dec-23 4 230
GR-CON-Z20-1380 Backfilling (Soil max for tree) 26-Dec-23 01-Jan-24 6 230
GR-CON-Z20-1381 Installation of Trees 11-Aug-24 12-Aug-24 2 54
GR-CON-Z20-3186 Installation of Shrubs 13-Aug-24 14-Aug-24 2 54
GR-CON-Z20-3196 Installation of Succulents 15-Aug-24 17-Aug-24 2 54
GR-CON-Z20-3206 Installation of Ground Covers 18-Aug-24 19-Aug-24 2 54
GR-CON-Z20-3216 Installation of Climbers 20-Aug-24 21-Aug-24 2 54
GR-CON-Z20-3226 Installation of Grass 22-Aug-24 24-Aug-24 2 54
GR-CON-Z20-3236 Installation of Lawns 25-Aug-24 26-Aug-24 2 54
GR-CON-Z20-1382 Backfilling (Mulch) 27-Aug-24 29-Aug-24 3 54
GR-CON-Z20-1383 Natural Boulders Installation 31-Aug-24 03-Sep-24 4 54
GR-CON-Z20-1384 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Sep-24 18-Sep-24 13 54
MUGA 14-Dec-23 18-Sep-24 226 67
GR-CON-Z20-1385 Excavation And Disposal 14-Dec-23 19-Dec-23 5 216
GR-CON-Z20-1386 Prepretion And Compaction 20-Dec-23 26-Dec-23 6 216
GR-CON-Z20-1387 polyethylene under footings ( fence and gates) 27-Dec-23 01-Jan-24 5 216
GR-CON-Z20-1388 Blinding concrete (flooring) 02-Jan-24 07-Jan-24 5 216
GR-CON-Z20-1389 Concrete Footings ( fence and gates) 08-Jan-24 22-Jan-24 13 216
GR-CON-Z20-1390 Tools Play Installation ( basketball / football ..) 23-Jan-24 08-Feb-24 15 216
GR-CON-Z20-1391 PaintAcrylic Play Surface 10-Feb-24 24-Feb-24 13 216
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1392 Fence (high / low) / gates Installation 02-Sep-24 18-Sep-24 15 67


Irrigation Works 03-Dec-23 18-Sep-24 236 67
GR-CON-Z20-1393 Excavation Pipe Irrigation 03-Dec-23 07-Dec-23 5 164
GR-CON-Z20-1394 Sand Bedding 09-Dec-23 11-Dec-23 3 164
GR-CON-Z20-1395 HDPE Pipe Installations and fittings and conduit for cable 12-Dec-23 28-Dec-23 15 164
GR-CON-Z20-1397 Test pressure 30-Dec-23 03-Jan-24 5 164
GR-CON-Z20-1396 Installation of Valves and Accessories 04-Jan-24 08-Jan-24 4 164
GR-CON-Z20-1398 Back filling (sand / Subbase ) 09-Jan-24 15-Jan-24 6 164
GR-CON-Z20-1399 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 16-Jan-24 22-Jan-24 6 251
GR-CON-Z20-1400 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Sep-24
system 18-Sep-24 8 67
Future Neighborhood Park FNP-26 26-Nov-23 18-Sep-24 242 67
Site Preparation 26-Nov-23 18-Dec-23 20 289
GR-CON-Z20-1333 Demolition (Asphalt.Paving,etc.....) 26-Nov-23 29-Nov-23 4 137
GR-CON-Z20-1334 Excavation And Disposal 30-Nov-23 06-Dec-23 6 160
GR-CON-Z20-1335 Prepretion And Compaction 07-Dec-23 11-Dec-23 4 289
GR-CON-Z20-1336 Backfilling 12-Dec-23 18-Dec-23 6 289
Curbstone and Paving 07-Dec-23 29-Jan-24 46 253
GR-CON-Z20-1337 Excavation Curbstone 07-Dec-23 12-Dec-23 5 212
GR-CON-Z20-1338 Plain Concrete 13-Dec-23 19-Dec-23 6 253
GR-CON-Z20-1339 Installation Curbstone 20-Dec-23 30-Dec-23 9 253
GR-CON-Z20-1340 Casting Concrete (Mortar haunch) 31-Dec-23 03-Jan-24 4 253
GR-CON-Z20-1341 Backfilling (sand / Sub base) 04-Jan-24 14-Jan-24 9 253
GR-CON-Z20-1342 Installation of Paving 15-Jan-24 29-Jan-24 13 253
Landscape Works 13-Dec-23 18-Sep-24 227 67
GR-CON-Z20-1343 Excavation (Tree Pit ) 13-Dec-23 18-Dec-23 5 212
GR-CON-Z20-1344 Aggregate Drainage layer 19-Dec-23 25-Dec-23 6 239
GR-CON-Z20-1345 Installation Geotextile 26-Dec-23 30-Dec-23 4 239
GR-CON-Z20-1346 Backfilling (Soil max for tree) 31-Dec-23 06-Jan-24 6 239
GR-CON-Z20-1347 Installation of Trees 11-Aug-24 12-Aug-24 2 67
GR-CON-Z20-3126 Installation of Shrubs 13-Aug-24 14-Aug-24 2 67
GR-CON-Z20-3136 Installation of Succulents 15-Aug-24 17-Aug-24 2 67
GR-CON-Z20-3146 Installation of Ground Covers 18-Aug-24 19-Aug-24 2 67
GR-CON-Z20-3156 Installation of Climbers 20-Aug-24 21-Aug-24 2 67
GR-CON-Z20-3166 Installation of Grass 22-Aug-24 24-Aug-24 2 67
GR-CON-Z20-3176 Installation of Lawns 25-Aug-24 26-Aug-24 2 67
GR-CON-Z20-1348 Backfilling (Mulch) 27-Aug-24 29-Aug-24 3 67
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1349 Natural Boulders Installation 31-Aug-24 03-Sep-24 4 67


GR-CON-Z20-1350 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Sep-24 18-Sep-24 13 67
MUGA 19-Dec-23 18-Sep-24 222 67
GR-CON-Z20-1351 Excavation And Disposal 19-Dec-23 24-Dec-23 5 212
GR-CON-Z20-1352 Prepretion And Compaction 25-Dec-23 31-Dec-23 6 212
GR-CON-Z20-1353 polyethylene under footings ( fence and gates) 01-Jan-24 06-Jan-24 5 212
GR-CON-Z20-1354 Blinding concrete (flooring) 07-Jan-24 11-Jan-24 5 212
GR-CON-Z20-1355 Concrete Footings ( fence and gates) 13-Jan-24 27-Jan-24 13 212
GR-CON-Z20-1356 Tools Play Installation ( basketball / football ..) 28-Jan-24 13-Feb-24 15 212
GR-CON-Z20-1357 PaintAcrylic Play Surface 14-Feb-24 28-Feb-24 13 212
GR-CON-Z20-1358 Fence (high / low) / gates Installation 02-Sep-24 18-Sep-24 15 67
Irrigation Works 07-Dec-23 18-Sep-24 232 67
GR-CON-Z20-1359 Excavation Pipe Irrigation 07-Dec-23 12-Dec-23 5 160
GR-CON-Z20-1360 Sand Bedding 13-Dec-23 16-Dec-23 3 160
GR-CON-Z20-1361 HDPE Pipe Installations and fittings and conduit for cable 17-Dec-23 02-Jan-24 15 160
GR-CON-Z20-1363 Test pressure 03-Jan-24 08-Jan-24 5 160
GR-CON-Z20-1362 Installation of Valves and Accessories 09-Jan-24 13-Jan-24 4 160
GR-CON-Z20-1364 Back filling (sand / Subbase ) 14-Jan-24 20-Jan-24 6 160
GR-CON-Z20-1365 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Jan-24 27-Jan-24 6 247
GR-CON-Z20-1366 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Sep-24
system 18-Sep-24 8 67
Future Neighborhood Park FNP-32 30-Nov-23 05-Oct-24 251 54
Site Preparation 30-Nov-23 23-Dec-23 20 285
GR-CON-Z20-1401 Demolition (Asphalt.Paving,etc.....) 30-Nov-23 04-Dec-23 4 137
GR-CON-Z20-1402 Excavation And Disposal 05-Dec-23 11-Dec-23 6 156
GR-CON-Z20-1403 Prepretion And Compaction 12-Dec-23 16-Dec-23 4 285
GR-CON-Z20-1404 Backfilling 17-Dec-23 23-Dec-23 6 285
Curbstone and Paving 12-Dec-23 03-Feb-24 46 249
GR-CON-Z20-1405 Excavation Curbstone 12-Dec-23 17-Dec-23 5 208
GR-CON-Z20-1406 Plain Concrete 18-Dec-23 24-Dec-23 6 249
GR-CON-Z20-1407 Installation Curbstone 25-Dec-23 03-Jan-24 9 249
GR-CON-Z20-1408 Casting Concrete (Mortar haunch) 04-Jan-24 08-Jan-24 4 249
GR-CON-Z20-1409 Backfilling (sand / Sub base) 09-Jan-24 18-Jan-24 9 249
GR-CON-Z20-1410 Installation of Paving 20-Jan-24 03-Feb-24 13 249
Landscape Works 18-Dec-23 05-Oct-24 236 54
GR-CON-Z20-1411 Excavation (Tree Pit ) 18-Dec-23 23-Dec-23 5 208
GR-CON-Z20-1412 Aggregate Drainage layer 24-Dec-23 30-Dec-23 6 235
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1413 Installation Geotextile 31-Dec-23 03-Jan-24 4 235


GR-CON-Z20-1414 Backfilling (Soil max for tree) 04-Jan-24 10-Jan-24 6 235
GR-CON-Z20-1415 Installation of Trees 11-Aug-24 12-Aug-24 2 67
GR-CON-Z20-3246 Installation of Shrubs 13-Aug-24 14-Aug-24 2 67
GR-CON-Z20-3256 Installation of Succulents 15-Aug-24 17-Aug-24 2 67
GR-CON-Z20-3266 Installation of Ground Covers 18-Aug-24 19-Aug-24 2 67
GR-CON-Z20-3276 Installation of Climbers 20-Aug-24 21-Aug-24 2 67
GR-CON-Z20-3286 Installation of Grass 22-Aug-24 24-Aug-24 2 67
GR-CON-Z20-3296 Installation of Lawns 25-Aug-24 26-Aug-24 2 67
GR-CON-Z20-1416 Backfilling (Mulch) 27-Aug-24 29-Aug-24 3 67
GR-CON-Z20-1417 Natural Boulders Installation 31-Aug-24 03-Sep-24 4 67
GR-CON-Z20-1418 Retaining walls . Steps, forming risers, treads and edges with finishes
19-Sep-24 05-Oct-24 13 54
MUGA 24-Dec-23 05-Oct-24 231 54
GR-CON-Z20-1419 Excavation And Disposal 24-Dec-23 28-Dec-23 5 208
GR-CON-Z20-1420 Prepretion And Compaction 30-Dec-23 04-Jan-24 6 208
GR-CON-Z20-1421 polyethylene under footings ( fence and gates) 06-Jan-24 10-Jan-24 5 208
GR-CON-Z20-1422 Blinding concrete (flooring) 11-Jan-24 16-Jan-24 5 208
GR-CON-Z20-1423 Concrete Footings ( fence and gates) 17-Jan-24 31-Jan-24 13 208
GR-CON-Z20-1424 Tools Play Installation ( basketball / football ..) 01-Feb-24 18-Feb-24 15 208
GR-CON-Z20-1425 PaintAcrylic Play Surface 19-Feb-24 04-Mar-24 13 208
GR-CON-Z20-1426 Fence (high / low) / gates Installation 17-Sep-24 05-Oct-24 15 54
Irrigation Works 12-Dec-23 05-Oct-24 241 54
GR-CON-Z20-1427 Excavation Pipe Irrigation 12-Dec-23 17-Dec-23 5 156
GR-CON-Z20-1428 Sand Bedding 18-Dec-23 20-Dec-23 3 156
GR-CON-Z20-1429 HDPE Pipe Installations and fittings and conduit for cable 21-Dec-23 07-Jan-24 15 156
GR-CON-Z20-1431 Test pressure 08-Jan-24 13-Jan-24 5 156
GR-CON-Z20-1430 Installation of Valves and Accessories 14-Jan-24 17-Jan-24 4 156
GR-CON-Z20-1432 Back filling (sand / Subbase ) 18-Jan-24 24-Jan-24 6 156
GR-CON-Z20-1433 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-Jan-24 31-Jan-24 6 243
GR-CON-Z20-1434 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-Sep-24
system 05-Oct-24 8 54
Mosque M-22 05-Dec-23 23-Oct-24 263 38
Site Preparation 05-Dec-23 26-Dec-23 19 260
GR-CON-Z20-1435 Demolition (Asphalt.Paving,etc.....) 05-Dec-23 09-Dec-23 4 137
GR-CON-Z20-1436 Excavation And Disposal 10-Dec-23 14-Dec-23 5 153
GR-CON-Z20-1437 Prepretion And Compaction 16-Dec-23 19-Dec-23 4 260
GR-CON-Z20-1438 Backfilling 20-Dec-23 26-Dec-23 6 260
Activity ID Activity Name Start Finish Original Total Float
Duration

Curbstone and Paving 27-Dec-23 21-Jan-24 22 260


GR-CON-Z20-1443 Backfilling (sand / Sub base) 27-Dec-23 06-Jan-24 9 260
GR-CON-Z20-1444 Installation of Paving 07-Jan-24 21-Jan-24 13 260
Landscape Works 16-Dec-23 23-Oct-24 254 38
GR-CON-Z20-1445 Excavation (Tree Pit ) 16-Dec-23 20-Dec-23 5 208
GR-CON-Z20-1446 Aggregate Drainage layer 21-Dec-23 27-Dec-23 6 208
GR-CON-Z20-1447 Installation Geotextile 28-Dec-23 02-Jan-24 5 208
GR-CON-Z20-1448 Backfilling (Soil max for tree) 03-Jan-24 08-Jan-24 5 208
GR-CON-Z20-1449 Installation of Trees 11-Aug-24 14-Aug-24 4 38
GR-CON-Z20-4866 Installation of Climbers 15-Aug-24 19-Aug-24 4 38
GR-CON-Z20-4876 Installation of Shrubs 20-Aug-24 24-Aug-24 4 38
GR-CON-Z20-4886 Installation of Succulents 25-Aug-24 28-Aug-24 4 38
GR-CON-Z20-4896 Installation of Ground Covers 29-Aug-24 02-Sep-24 4 38
GR-CON-Z20-1450 Backfilling (Mulch) 03-Sep-24 19-Sep-24 15 38
GR-CON-Z20-1451 Natural Boulders Installation 21-Sep-24 06-Oct-24 13 38
GR-CON-Z20-1452 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 23-Oct-24 15 38
Irrigation Works 16-Dec-23 23-Oct-24 254 38
GR-CON-Z20-1453 Excavation Pipe Irrigation 16-Dec-23 20-Dec-23 5 153
GR-CON-Z20-1454 Sand Bedding 21-Dec-23 24-Dec-23 3 153
GR-CON-Z20-1455 HDPE Pipe Installations and fittings and conduit for cable 25-Dec-23 10-Jan-24 15 153
GR-CON-Z20-1457 Test pressure 11-Jan-24 16-Jan-24 5 153
GR-CON-Z20-1456 Installation of Valves and Accessories 17-Jan-24 21-Jan-24 4 153
GR-CON-Z20-1458 Back filling (sand / Subbase ) 22-Jan-24 28-Jan-24 6 153
GR-CON-Z20-1459 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 29-Jan-24 04-Feb-24 6 242
GR-CON-Z20-1460 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Oct-24
system 23-Oct-24 6 38
Mosque M-24 10-Dec-23 23-Oct-24 259 38
Site Preparation 10-Dec-23 31-Dec-23 19 256
GR-CON-Z20-1461 Demolition (Asphalt.Paving,etc.....) 10-Dec-23 13-Dec-23 4 137
GR-CON-Z20-1462 Excavation And Disposal 14-Dec-23 19-Dec-23 5 149
GR-CON-Z20-1463 Prepretion And Compaction 20-Dec-23 24-Dec-23 4 256
GR-CON-Z20-1464 Backfilling 25-Dec-23 31-Dec-23 6 256
Curbstone and Paving 01-Jan-24 25-Jan-24 22 256
GR-CON-Z20-1469 Backfilling (sand / Sub base) 01-Jan-24 10-Jan-24 9 256
GR-CON-Z20-1470 Installation of Paving 11-Jan-24 25-Jan-24 13 256
Landscape Works 20-Dec-23 23-Oct-24 250 38
GR-CON-Z20-1471 Excavation (Tree Pit ) 20-Dec-23 25-Dec-23 5 204
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1472 Aggregate Drainage layer 26-Dec-23 01-Jan-24 6 204


GR-CON-Z20-1473 Installation Geotextile 02-Jan-24 07-Jan-24 5 204
GR-CON-Z20-1474 Backfilling (Soil max for tree) 08-Jan-24 13-Jan-24 5 204
GR-CON-Z20-1475 Installation of Trees 11-Aug-24 14-Aug-24 4 38
GR-CON-Z20-4906 Installation of Climbers 15-Aug-24 19-Aug-24 4 38
GR-CON-Z20-4916 Installation of Shrubs 20-Aug-24 24-Aug-24 4 38
GR-CON-Z20-4926 Installation of Succulents 25-Aug-24 28-Aug-24 4 38
GR-CON-Z20-4936 Installation of Ground Covers 29-Aug-24 02-Sep-24 4 38
GR-CON-Z20-1476 Backfilling (Mulch) 03-Sep-24 19-Sep-24 15 38
GR-CON-Z20-1477 Natural Boulders Installation 21-Sep-24 06-Oct-24 13 38
GR-CON-Z20-1478 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 23-Oct-24 15 38
Irrigation Works 20-Dec-23 23-Oct-24 250 38
GR-CON-Z20-1479 Excavation Pipe Irrigation 20-Dec-23 25-Dec-23 5 149
GR-CON-Z20-1480 Sand Bedding 26-Dec-23 28-Dec-23 3 149
GR-CON-Z20-1481 HDPE Pipe Installations and fittings and conduit for cable 30-Dec-23 15-Jan-24 15 149
GR-CON-Z20-1483 Test pressure 16-Jan-24 21-Jan-24 5 149
GR-CON-Z20-1482 Installation of Valves and Accessories 22-Jan-24 25-Jan-24 4 149
GR-CON-Z20-1484 Back filling (sand / Subbase ) 27-Jan-24 01-Feb-24 6 149
GR-CON-Z20-1485 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Feb-24 08-Feb-24 6 238
GR-CON-Z20-1486 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Oct-24
system 23-Oct-24 6 38
Mosque M-25 14-Dec-23 23-Oct-24 255 38
Site Preparation 14-Dec-23 04-Jan-24 19 252
GR-CON-Z20-1487 Demolition (Asphalt.Paving,etc.....) 14-Dec-23 18-Dec-23 4 137
GR-CON-Z20-1488 Excavation And Disposal 19-Dec-23 24-Dec-23 5 145
GR-CON-Z20-1489 Prepretion And Compaction 25-Dec-23 28-Dec-23 4 252
GR-CON-Z20-1490 Backfilling 30-Dec-23 04-Jan-24 6 252
Curbstone and Paving 06-Jan-24 30-Jan-24 22 252
GR-CON-Z20-1495 Backfilling (sand / Sub base) 06-Jan-24 15-Jan-24 9 252
GR-CON-Z20-1496 Installation of Paving 16-Jan-24 30-Jan-24 13 252
Landscape Works 25-Dec-23 23-Oct-24 246 38
GR-CON-Z20-1497 Excavation (Tree Pit ) 25-Dec-23 30-Dec-23 5 200
GR-CON-Z20-1498 Aggregate Drainage layer 31-Dec-23 06-Jan-24 6 200
GR-CON-Z20-1499 Installation Geotextile 07-Jan-24 11-Jan-24 5 200
GR-CON-Z20-1500 Backfilling (Soil max for tree) 13-Jan-24 17-Jan-24 5 200
GR-CON-Z20-1501 Installation of Trees 11-Aug-24 14-Aug-24 4 38
GR-CON-Z20-4946 Installation of Climbers 15-Aug-24 19-Aug-24 4 38
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-4956 Installation of Shrubs 20-Aug-24 24-Aug-24 4 38


GR-CON-Z20-4966 Installation of Succulents 25-Aug-24 28-Aug-24 4 38
GR-CON-Z20-4976 Installation of Ground Covers 29-Aug-24 02-Sep-24 4 38
GR-CON-Z20-1502 Backfilling (Mulch) 03-Sep-24 19-Sep-24 15 38
GR-CON-Z20-1503 Natural Boulders Installation 21-Sep-24 06-Oct-24 13 38
GR-CON-Z20-1504 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 23-Oct-24 15 38
Irrigation Works 25-Dec-23 23-Oct-24 246 38
GR-CON-Z20-1505 Excavation Pipe Irrigation 25-Dec-23 30-Dec-23 5 145
GR-CON-Z20-1506 Sand Bedding 31-Dec-23 02-Jan-24 3 145
GR-CON-Z20-1507 HDPE Pipe Installations and fittings and conduit for cable 03-Jan-24 20-Jan-24 15 145
GR-CON-Z20-1509 Test pressure 21-Jan-24 25-Jan-24 5 145
GR-CON-Z20-1508 Installation of Valves and Accessories 27-Jan-24 30-Jan-24 4 145
GR-CON-Z20-1510 Back filling (sand / Subbase ) 31-Jan-24 06-Feb-24 6 145
GR-CON-Z20-1511 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 07-Feb-24 13-Feb-24 6 234
GR-CON-Z20-1512 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Oct-24
system 23-Oct-24 6 38
Mosque M-26 19-Dec-23 23-Oct-24 251 38
Site Preparation 19-Dec-23 09-Jan-24 19 248
GR-CON-Z20-1513 Demolition (Asphalt.Paving,etc.....) 19-Dec-23 23-Dec-23 4 137
GR-CON-Z20-1514 Excavation And Disposal 24-Dec-23 28-Dec-23 5 141
GR-CON-Z20-1515 Prepretion And Compaction 30-Dec-23 02-Jan-24 4 248
GR-CON-Z20-1516 Backfilling 03-Jan-24 09-Jan-24 6 248
Curbstone and Paving 10-Jan-24 04-Feb-24 22 248
GR-CON-Z20-1521 Backfilling (sand / Sub base) 10-Jan-24 20-Jan-24 9 248
GR-CON-Z20-1522 Installation of Paving 21-Jan-24 04-Feb-24 13 248
Landscape Works 30-Dec-23 23-Oct-24 242 38
GR-CON-Z20-1523 Excavation (Tree Pit ) 30-Dec-23 03-Jan-24 5 196
GR-CON-Z20-1524 Aggregate Drainage layer 04-Jan-24 10-Jan-24 6 196
GR-CON-Z20-1525 Installation Geotextile 11-Jan-24 16-Jan-24 5 196
GR-CON-Z20-1526 Backfilling (Soil max for tree) 17-Jan-24 22-Jan-24 5 196
GR-CON-Z20-1527 Installation of Trees 11-Aug-24 14-Aug-24 4 38
GR-CON-Z20-4986 Installation of Climbers 15-Aug-24 19-Aug-24 4 38
GR-CON-Z20-4996 Installation of Shrubs 20-Aug-24 24-Aug-24 4 38
GR-CON-Z20-5006 Installation of Succulents 25-Aug-24 28-Aug-24 4 38
GR-CON-Z20-5016 Installation of Ground Covers 29-Aug-24 02-Sep-24 4 38
GR-CON-Z20-1528 Backfilling (Mulch) 03-Sep-24 19-Sep-24 15 38
GR-CON-Z20-1529 Natural Boulders Installation 21-Sep-24 06-Oct-24 13 38
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1530 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 23-Oct-24 15 38
Irrigation Works 30-Dec-23 23-Oct-24 242 38
GR-CON-Z20-1531 Excavation Pipe Irrigation 30-Dec-23 03-Jan-24 5 141
GR-CON-Z20-1532 Sand Bedding 04-Jan-24 07-Jan-24 3 141
GR-CON-Z20-1533 HDPE Pipe Installations and fittings and conduit for cable 08-Jan-24 24-Jan-24 15 141
GR-CON-Z20-1535 Test pressure 25-Jan-24 30-Jan-24 5 141
GR-CON-Z20-1534 Installation of Valves and Accessories 31-Jan-24 04-Feb-24 4 141
GR-CON-Z20-1536 Back filling (sand / Subbase ) 05-Feb-24 11-Feb-24 6 141
GR-CON-Z20-1537 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 12-Feb-24 18-Feb-24 6 230
GR-CON-Z20-1538 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Oct-24
system 23-Oct-24 6 38
Mosque M-28 24-Dec-23 23-Oct-24 247 38
Site Preparation 24-Dec-23 14-Jan-24 19 244
GR-CON-Z20-1539 Demolition (Asphalt.Paving,etc.....) 24-Dec-23 27-Dec-23 4 137
GR-CON-Z20-1540 Excavation And Disposal 28-Dec-23 02-Jan-24 5 137
GR-CON-Z20-1541 Prepretion And Compaction 03-Jan-24 07-Jan-24 4 244
GR-CON-Z20-1542 Backfilling 08-Jan-24 14-Jan-24 6 244
Curbstone and Paving 15-Jan-24 08-Feb-24 22 244
GR-CON-Z20-1547 Backfilling (sand / Sub base) 15-Jan-24 24-Jan-24 9 244
GR-CON-Z20-1548 Installation of Paving 25-Jan-24 08-Feb-24 13 244
Landscape Works 03-Jan-24 23-Oct-24 238 38
GR-CON-Z20-1549 Excavation (Tree Pit ) 03-Jan-24 08-Jan-24 5 192
GR-CON-Z20-1550 Aggregate Drainage layer 09-Jan-24 15-Jan-24 6 192
GR-CON-Z20-1551 Installation Geotextile 16-Jan-24 21-Jan-24 5 192
GR-CON-Z20-1552 Backfilling (Soil max for tree) 22-Jan-24 27-Jan-24 5 192
GR-CON-Z20-1553 Installation of Trees 11-Aug-24 14-Aug-24 4 38
GR-CON-Z20-5026 Installation of Climbers 15-Aug-24 19-Aug-24 4 38
GR-CON-Z20-5036 Installation of Shrubs 20-Aug-24 24-Aug-24 4 38
GR-CON-Z20-5046 Installation of Succulents 25-Aug-24 28-Aug-24 4 38
GR-CON-Z20-5056 Installation of Ground Covers 29-Aug-24 02-Sep-24 4 38
GR-CON-Z20-1554 Backfilling (Mulch) 03-Sep-24 19-Sep-24 15 38
GR-CON-Z20-1555 Natural Boulders Installation 21-Sep-24 06-Oct-24 13 38
GR-CON-Z20-1556 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 23-Oct-24 15 38
Irrigation Works 03-Jan-24 23-Oct-24 238 38
GR-CON-Z20-1557 Excavation Pipe Irrigation 03-Jan-24 08-Jan-24 5 137
GR-CON-Z20-1558 Sand Bedding 09-Jan-24 11-Jan-24 3 137
GR-CON-Z20-1559 HDPE Pipe Installations and fittings and conduit for cable 13-Jan-24 29-Jan-24 15 137
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1561 Test pressure 30-Jan-24 04-Feb-24 5 137


GR-CON-Z20-1560 Installation of Valves and Accessories 05-Feb-24 08-Feb-24 4 137
GR-CON-Z20-1562 Back filling (sand / Subbase ) 10-Feb-24 15-Feb-24 6 137
GR-CON-Z20-1563 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 17-Feb-24 22-Feb-24 6 226
GR-CON-Z20-1564 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Oct-24
system 23-Oct-24 6 38
Mosque M-29 04-Dec-23 23-Oct-24 263 38
Site Preparation 04-Dec-23 26-Dec-23 19 260
GR-CON-Z20-1565 Demolition (Asphalt.Paving,etc.....) 04-Dec-23 09-Dec-23 4 153
GR-CON-Z20-1566 Excavation And Disposal 09-Dec-23 14-Dec-23 5 153
GR-CON-Z20-1567 Prepretion And Compaction 14-Dec-23 19-Dec-23 4 260
GR-CON-Z20-1568 Backfilling 19-Dec-23 26-Dec-23 6 260
Curbstone and Paving 26-Dec-23 21-Jan-24 22 260
GR-CON-Z20-1573 Backfilling (sand / Sub base) 26-Dec-23 06-Jan-24 9 260
GR-CON-Z20-1574 Installation of Paving 06-Jan-24 21-Jan-24 13 260
Landscape Works 14-Dec-23 23-Oct-24 254 38
GR-CON-Z20-1575 Excavation (Tree Pit ) 14-Dec-23 20-Dec-23 5 208
GR-CON-Z20-1576 Aggregate Drainage layer 20-Dec-23 27-Dec-23 6 208
GR-CON-Z20-1577 Installation Geotextile 27-Dec-23 02-Jan-24 5 208
GR-CON-Z20-1578 Backfilling (Soil max for tree) 02-Jan-24 08-Jan-24 5 208
GR-CON-Z20-1579 Installation of Trees 11-Aug-24 14-Aug-24 4 38
GR-CON-Z20-5066 Installation of Climbers 15-Aug-24 19-Aug-24 4 38
GR-CON-Z20-5076 Installation of Shrubs 20-Aug-24 24-Aug-24 4 38
GR-CON-Z20-5086 Installation of Succulents 25-Aug-24 28-Aug-24 4 38
GR-CON-Z20-5096 Installation of Ground Covers 29-Aug-24 02-Sep-24 4 38
GR-CON-Z20-1580 Backfilling (Mulch) 03-Sep-24 19-Sep-24 15 38
GR-CON-Z20-1581 Natural Boulders Installation 21-Sep-24 06-Oct-24 13 38
GR-CON-Z20-1582 Retaining walls . Steps, forming risers, treads and edges with finishes
07-Oct-24 23-Oct-24 15 38
Irrigation Works 14-Dec-23 23-Oct-24 254 38
GR-CON-Z20-1583 Excavation Pipe Irrigation 14-Dec-23 20-Dec-23 5 153
GR-CON-Z20-1584 Sand Bedding 20-Dec-23 24-Dec-23 3 153
GR-CON-Z20-1585 HDPE Pipe Installations and fittings and conduit for cable 24-Dec-23 10-Jan-24 15 153
GR-CON-Z20-1587 Test pressure 10-Jan-24 16-Jan-24 5 153
GR-CON-Z20-1586 Installation of Valves and Accessories 16-Jan-24 21-Jan-24 4 153
GR-CON-Z20-1588 Back filling (sand / Subbase ) 21-Jan-24 28-Jan-24 6 153
GR-CON-Z20-1589 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-Jan-24 04-Feb-24 6 242
GR-CON-Z20-1590 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Oct-24
system 23-Oct-24 6 38
Activity ID Activity Name Start Finish Original Total Float
Duration

Parking P-16 21-Dec-23 11-Sep-24 213 73


Site Preparation 21-Dec-23 28-Dec-23 6 267
GR-CON-Z20-1594 Backfilling 21-Dec-23 28-Dec-23 6 267
GR-CON-Z20-1592 Excavation And Disposal 23-Dec-23 28-Dec-23 5 141
GR-CON-Z20-1591 Demolition (Asphalt.Paving,etc.....) 24-Dec-23 28-Dec-23 4 137
GR-CON-Z20-1593 Prepretion And Compaction 24-Dec-23 28-Dec-23 4 267
Curbstone and Paving 28-Dec-23 20-Feb-24 46 234
GR-CON-Z20-1595 Excavation Curbstone 28-Dec-23 03-Jan-24 5 226
GR-CON-Z20-1596 Plain Concrete 03-Jan-24 10-Jan-24 6 234
GR-CON-Z20-1597 Installation Curbstone 10-Jan-24 21-Jan-24 9 234
GR-CON-Z20-1598 Casting Concrete (Mortar haunch) 21-Jan-24 25-Jan-24 4 234
GR-CON-Z20-1599 Backfilling (sand / Sub base) 25-Jan-24 05-Feb-24 9 234
GR-CON-Z20-1600 Installation of Paving 05-Feb-24 20-Feb-24 13 234
Landscape Works 03-Jan-24 31-Aug-24 192 73
GR-CON-Z20-1601 Excavation (Tree Pit ) 03-Jan-24 09-Jan-24 5 226
GR-CON-Z20-1602 Aggregate Drainage layer 09-Jan-24 16-Jan-24 6 226
GR-CON-Z20-1603 Installation Geotextile 16-Jan-24 21-Jan-24 4 226
GR-CON-Z20-1604 Backfilling (Soil max for tree) 21-Jan-24 28-Jan-24 6 226
GR-CON-Z20-1605 Installation of Trees 11-Aug-24 13-Aug-24 3 73
GR-CON-Z20-9016 Installation of Shrubs 14-Aug-24 17-Aug-24 3 73
GR-CON-Z20-9026 Installation of Ground Covers 18-Aug-24 20-Aug-24 3 73
GR-CON-Z20-9036 Installation of Succulents 21-Aug-24 24-Aug-24 3 73
GR-CON-Z20-9046 Installation of Grass 25-Aug-24 27-Aug-24 3 73
GR-CON-Z20-1606 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 73
Site Furnishing 01-Sep-24 11-Sep-24 10 73
GR-CON-Z20-1617 Tree Grate 01-Sep-24 05-Sep-24 5 73
GR-CON-Z20-1618 Wheel stoppers 07-Sep-24 11-Sep-24 5 73
Irrigation Works 28-Dec-23 11-Sep-24 207 73
GR-CON-Z20-1609 Excavation Pipe Irrigation 28-Dec-23 03-Jan-24 5 141
GR-CON-Z20-1610 Sand Bedding 03-Jan-24 07-Jan-24 3 141
GR-CON-Z20-1611 HDPE Pipe Installations and fittings and conduit for cable 07-Jan-24 24-Jan-24 15 141
GR-CON-Z20-1613 Test pressure 24-Jan-24 30-Jan-24 5 141
GR-CON-Z20-1612 Installation of Valves and Accessories 30-Jan-24 04-Feb-24 4 141
GR-CON-Z20-1614 Back filling (sand / Subbase ) 04-Feb-24 11-Feb-24 6 141
GR-CON-Z20-1615 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Feb-24 18-Feb-24 6 228
GR-CON-Z20-1616 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Sep-24
system 11-Sep-24 8 73
Activity ID Activity Name Start Finish Original Total Float
Duration

Parking P-21 28-Dec-23 11-Sep-24 207 73


Site Preparation 28-Dec-23 04-Jan-24 6 261
GR-CON-Z20-1622 Backfilling 28-Dec-23 04-Jan-24 6 261
GR-CON-Z20-1620 Excavation And Disposal 30-Dec-23 04-Jan-24 5 135
GR-CON-Z20-1619 Demolition (Asphalt.Paving,etc.....) 31-Dec-23 04-Jan-24 4 135
GR-CON-Z20-1621 Prepretion And Compaction 31-Dec-23 04-Jan-24 4 261
Curbstone and Paving 04-Jan-24 27-Feb-24 46 228
GR-CON-Z20-1623 Excavation Curbstone 04-Jan-24 10-Jan-24 5 220
GR-CON-Z20-1624 Plain Concrete 10-Jan-24 17-Jan-24 6 228
GR-CON-Z20-1625 Installation Curbstone 17-Jan-24 28-Jan-24 9 228
GR-CON-Z20-1626 Casting Concrete (Mortar haunch) 28-Jan-24 01-Feb-24 4 228
GR-CON-Z20-1627 Backfilling (sand / Sub base) 01-Feb-24 12-Feb-24 9 228
GR-CON-Z20-1628 Installation of Paving 12-Feb-24 27-Feb-24 13 228
Landscape Works 10-Jan-24 31-Aug-24 186 73
GR-CON-Z20-1629 Excavation (Tree Pit ) 10-Jan-24 16-Jan-24 5 220
GR-CON-Z20-1630 Aggregate Drainage layer 16-Jan-24 23-Jan-24 6 220
GR-CON-Z20-1631 Installation Geotextile 23-Jan-24 28-Jan-24 4 220
GR-CON-Z20-1632 Backfilling (Soil max for tree) 28-Jan-24 04-Feb-24 6 220
GR-CON-Z20-1633 Installation of Trees 11-Aug-24 13-Aug-24 3 73
GR-CON-Z20-9056 Installation of Shrubs 14-Aug-24 17-Aug-24 3 73
GR-CON-Z20-9066 Installation of Ground Covers 18-Aug-24 20-Aug-24 3 73
GR-CON-Z20-9076 Installation of Succulents 21-Aug-24 24-Aug-24 3 73
GR-CON-Z20-9086 Installation of Grass 25-Aug-24 27-Aug-24 3 73
GR-CON-Z20-1634 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 73
Site Furnishing 01-Sep-24 11-Sep-24 10 73
GR-CON-Z20-1645 Tree Grate 01-Sep-24 05-Sep-24 5 73
GR-CON-Z20-1646 Wheel stoppers 07-Sep-24 11-Sep-24 5 73
Irrigation Works 04-Jan-24 11-Sep-24 201 73
GR-CON-Z20-1637 Excavation Pipe Irrigation 04-Jan-24 10-Jan-24 5 135
GR-CON-Z20-1638 Sand Bedding 10-Jan-24 14-Jan-24 3 135
GR-CON-Z20-1639 HDPE Pipe Installations and fittings and conduit for cable 14-Jan-24 31-Jan-24 15 135
GR-CON-Z20-1641 Test pressure 31-Jan-24 06-Feb-24 5 135
GR-CON-Z20-1640 Installation of Valves and Accessories 06-Feb-24 11-Feb-24 4 135
GR-CON-Z20-1642 Back filling (sand / Subbase ) 11-Feb-24 18-Feb-24 6 135
GR-CON-Z20-1643 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Feb-24 25-Feb-24 6 222
GR-CON-Z20-1644 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Sep-24
system 11-Sep-24 8 73
Activity ID Activity Name Start Finish Original Total Float
Duration

Parking P-29 14-Dec-23 11-Sep-24 219 73


Site Preparation 14-Dec-23 21-Dec-23 6 273
GR-CON-Z20-1650 Backfilling 14-Dec-23 21-Dec-23 6 273
GR-CON-Z20-1648 Excavation And Disposal 16-Dec-23 21-Dec-23 5 147
GR-CON-Z20-1647 Demolition (Asphalt.Paving,etc.....) 17-Dec-23 21-Dec-23 4 111
GR-CON-Z20-1649 Prepretion And Compaction 17-Dec-23 21-Dec-23 4 273
Curbstone and Paving 21-Dec-23 13-Feb-24 46 240
GR-CON-Z20-1651 Excavation Curbstone 21-Dec-23 27-Dec-23 5 232
GR-CON-Z20-1652 Plain Concrete 27-Dec-23 03-Jan-24 6 240
GR-CON-Z20-1653 Installation Curbstone 03-Jan-24 14-Jan-24 9 240
GR-CON-Z20-1654 Casting Concrete (Mortar haunch) 14-Jan-24 18-Jan-24 4 240
GR-CON-Z20-1655 Backfilling (sand / Sub base) 18-Jan-24 29-Jan-24 9 240
GR-CON-Z20-1656 Installation of Paving 29-Jan-24 13-Feb-24 13 240
Landscape Works 27-Dec-23 31-Aug-24 198 73
GR-CON-Z20-1657 Excavation (Tree Pit ) 27-Dec-23 02-Jan-24 5 232
GR-CON-Z20-1658 Aggregate Drainage layer 02-Jan-24 09-Jan-24 6 232
GR-CON-Z20-1659 Installation Geotextile 09-Jan-24 14-Jan-24 4 232
GR-CON-Z20-1660 Backfilling (Soil max for tree) 14-Jan-24 21-Jan-24 6 232
GR-CON-Z20-1661 Installation of Trees 11-Aug-24 13-Aug-24 3 73
GR-CON-Z20-9096 Installation of Shrubs 14-Aug-24 17-Aug-24 3 73
GR-CON-Z20-9106 Installation of Ground Covers 18-Aug-24 20-Aug-24 3 73
GR-CON-Z20-9116 Installation of Succulents 21-Aug-24 24-Aug-24 3 73
GR-CON-Z20-9126 Installation of Grass 25-Aug-24 27-Aug-24 3 73
GR-CON-Z20-1662 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 73
Site Furnishing 01-Sep-24 11-Sep-24 10 73
GR-CON-Z20-1673 Tree Grate 01-Sep-24 05-Sep-24 5 73
GR-CON-Z20-1674 Wheel stoppers 07-Sep-24 11-Sep-24 5 73
Irrigation Works 21-Dec-23 11-Sep-24 213 73
GR-CON-Z20-1665 Excavation Pipe Irrigation 21-Dec-23 27-Dec-23 5 147
GR-CON-Z20-1666 Sand Bedding 27-Dec-23 31-Dec-23 3 147
GR-CON-Z20-1667 HDPE Pipe Installations and fittings and conduit for cable 31-Dec-23 17-Jan-24 15 147
GR-CON-Z20-1669 Test pressure 17-Jan-24 23-Jan-24 5 147
GR-CON-Z20-1668 Installation of Valves and Accessories 23-Jan-24 28-Jan-24 4 147
GR-CON-Z20-1670 Back filling (sand / Subbase ) 28-Jan-24 04-Feb-24 6 147
GR-CON-Z20-1671 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Feb-24 11-Feb-24 6 234
GR-CON-Z20-1672 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Sep-24
system 11-Sep-24 8 73
Activity ID Activity Name Start Finish Original Total Float
Duration

Street SS-18 07-Jan-24 14-Oct-24 226 46


Site Preparation 07-Jan-24 31-Jan-24 21 251
GR-CON-Z20-1037 Demolition (Asphalt.Paving,etc.....) 07-Jan-24 11-Jan-24 4 119
GR-CON-Z20-1038 Excavation And Disposal 11-Jan-24 17-Jan-24 5 123
GR-CON-Z20-1039 Prepretion And Compaction 17-Jan-24 24-Jan-24 6 251
GR-CON-Z20-1040 Backfilling 24-Jan-24 31-Jan-24 6 251
Curbstone and Paving 17-Jan-24 29-Feb-24 37 226
GR-CON-Z20-1041 Excavation Curbstone 17-Jan-24 23-Jan-24 5 182
GR-CON-Z20-1042 Plain Concrete 23-Jan-24 30-Jan-24 6 226
GR-CON-Z20-1043 Installation Curbstone 30-Jan-24 10-Feb-24 9 226
GR-CON-Z20-1044 Casting Concrete (Mortar haunch) 10-Feb-24 14-Feb-24 4 226
GR-CON-Z20-1045 Backfilling (sand / Sub base) 14-Feb-24 20-Feb-24 5 226
GR-CON-Z20-1046 Installation of Paving 14-Feb-24 29-Feb-24 13 226
Landscape Works 23-Jan-24 19-Sep-24 192 46
GR-CON-Z20-1047 Excavation (Tree Pit ) 23-Jan-24 29-Jan-24 5 182
GR-CON-Z20-1048 Aggregate Drainage layer 29-Jan-24 05-Feb-24 6 182
GR-CON-Z20-1049 Installation Geotextile 05-Feb-24 10-Feb-24 4 182
GR-CON-Z20-1050 Backfilling (Soil max for tree) 10-Feb-24 17-Feb-24 6 182
GR-CON-Z20-1051 Installation of Trees 11-Aug-24 13-Aug-24 3 46
GR-CON-Z20-14096 Installation of Shrubs 14-Aug-24 17-Aug-24 3 46
GR-CON-Z20-14106 Installation of Succulents 18-Aug-24 20-Aug-24 3 46
GR-CON-Z20-14116 Installation of Ground Covers 21-Aug-24 24-Aug-24 3 46
GR-CON-Z20-14126 Installation of Grass 25-Aug-24 27-Aug-24 3 46
GR-CON-Z20-1052 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 46
GR-CON-Z20-1053 Natural Boulders Installation 01-Sep-24 04-Sep-24 4 46
GR-CON-Z20-1054 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Sep-24 19-Sep-24 13 46
Site Furnishing 21-Sep-24 14-Oct-24 20 46
GR-CON-Z20-1063 Garden planter box 21-Sep-24 26-Sep-24 5 46
GR-CON-Z20-1064 Wheel stoppers 28-Sep-24 02-Oct-24 5 46
GR-CON-Z20-1065 Steel Lattice 03-Oct-24 08-Oct-24 5 46
GR-CON-Z20-1066 Handrail 09-Oct-24 14-Oct-24 5 46
Storm Piping Works 08-Oct-24 14-Oct-24 6 46
GR-CON-Z20-1067 Installation of DI grating covers 08-Oct-24 14-Oct-24 6 46
Irrigation Works 17-Jan-24 20-Mar-24 53 204
GR-CON-Z20-1055 Excavation Pipe Irrigation 17-Jan-24 23-Jan-24 5 123
GR-CON-Z20-1056 Sand Bedding 23-Jan-24 28-Jan-24 4 123
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1057 HDPE Pipe Installations and fittings and conduit for cable 28-Jan-24 14-Feb-24 15 123
GR-CON-Z20-1059 Test pressure 14-Feb-24 20-Feb-24 5 123
GR-CON-Z20-1058 Installation of Valves and Accessories 20-Feb-24 25-Feb-24 4 123
GR-CON-Z20-1060 Back filling (sand / Subbase ) 25-Feb-24 03-Mar-24 6 123
GR-CON-Z20-1061 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Mar-24 10-Mar-24 6 204
GR-CON-Z20-1062 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
10-Mar-24
system 20-Mar-24 8 204
Electrical Works 23-Jan-24 14-Oct-24 212 46
GR-CON-Z20-1068 Excavation And Disposal 23-Jan-24 29-Jan-24 5 231
GR-CON-Z20-1069 Sand Bedding 29-Jan-24 03-Feb-24 4 231
GR-CON-Z20-1070 laying cables 03-Feb-24 07-Feb-24 4 231
GR-CON-Z20-1071 Backfilling (sand / Sub base) 07-Feb-24 13-Feb-24 5 231
GR-CON-Z20-1072 Control Panel / Distribution Panel Installation 13-Feb-24 18-Feb-24 4 231
GR-CON-Z20-1073 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Street SS-19 13-Jan-24 14-Oct-24 221 46
Site Preparation 13-Jan-24 06-Feb-24 21 246
GR-CON-Z20-1074 Demolition (Asphalt.Paving,etc.....) 13-Jan-24 17-Jan-24 4 118
GR-CON-Z20-1075 Excavation And Disposal 17-Jan-24 23-Jan-24 5 118
GR-CON-Z20-1076 Prepretion And Compaction 23-Jan-24 30-Jan-24 6 246
GR-CON-Z20-1077 Backfilling 30-Jan-24 06-Feb-24 6 246
Curbstone and Paving 23-Jan-24 18-Mar-24 46 212
GR-CON-Z20-1078 Excavation Curbstone 23-Jan-24 29-Jan-24 5 177
GR-CON-Z20-1079 Plain Concrete 29-Jan-24 05-Feb-24 6 212
GR-CON-Z20-1080 Installation Curbstone 05-Feb-24 15-Feb-24 9 212
GR-CON-Z20-1081 Casting Concrete (Mortar haunch) 15-Feb-24 20-Feb-24 4 212
GR-CON-Z20-1082 Backfilling (sand / Sub base) 20-Feb-24 02-Mar-24 9 212
GR-CON-Z20-1083 Installation of Paving 02-Mar-24 18-Mar-24 13 212
Landscape Works 29-Jan-24 19-Sep-24 187 46
GR-CON-Z20-1084 Excavation (Tree Pit ) 29-Jan-24 04-Feb-24 5 177
GR-CON-Z20-1085 Aggregate Drainage layer 04-Feb-24 11-Feb-24 6 177
GR-CON-Z20-1086 Installation Geotextile 11-Feb-24 15-Feb-24 4 177
GR-CON-Z20-1087 Backfilling (Soil max for tree) 15-Feb-24 22-Feb-24 6 177
GR-CON-Z20-1088 Installation of Trees 11-Aug-24 13-Aug-24 3 46
GR-CON-Z20-14136 Installation of Shrubs 14-Aug-24 17-Aug-24 3 46
GR-CON-Z20-14146 Installation of Succulents 18-Aug-24 20-Aug-24 3 46
GR-CON-Z20-14156 Installation of Ground Covers 21-Aug-24 24-Aug-24 3 46
GR-CON-Z20-14166 Installation of Grass 25-Aug-24 27-Aug-24 3 46
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1089 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 46


GR-CON-Z20-1090 Natural Boulders Installation 01-Sep-24 04-Sep-24 4 46
GR-CON-Z20-1091 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Sep-24 19-Sep-24 13 46
Site Furnishing 21-Sep-24 14-Oct-24 20 46
GR-CON-Z20-1100 Garden planter box 21-Sep-24 26-Sep-24 5 46
GR-CON-Z20-1101 Wheel stoppers 28-Sep-24 02-Oct-24 5 46
GR-CON-Z20-1102 Steel Lattice 03-Oct-24 08-Oct-24 5 46
GR-CON-Z20-1103 Handrail 09-Oct-24 14-Oct-24 5 46
Storm Piping Works 08-Oct-24 14-Oct-24 6 46
GR-CON-Z20-1104 Installation of DI grating covers 08-Oct-24 14-Oct-24 6 46
Irrigation Works 23-Jan-24 28-Mar-24 53 199
GR-CON-Z20-1092 Excavation Pipe Irrigation 23-Jan-24 29-Jan-24 5 118
GR-CON-Z20-1093 Sand Bedding 29-Jan-24 03-Feb-24 4 118
GR-CON-Z20-1094 HDPE Pipe Installations and fittings and conduit for cable 03-Feb-24 20-Feb-24 15 118
GR-CON-Z20-1096 Test pressure 20-Feb-24 26-Feb-24 5 118
GR-CON-Z20-1095 Installation of Valves and Accessories 26-Feb-24 02-Mar-24 4 118
GR-CON-Z20-1097 Back filling (sand / Subbase ) 02-Mar-24 09-Mar-24 6 118
GR-CON-Z20-1098 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Mar-24 16-Mar-24 6 199
GR-CON-Z20-1099 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Mar-24
system 28-Mar-24 8 199
Electrical Works 29-Jan-24 14-Oct-24 207 46
GR-CON-Z20-1105 Excavation And Disposal 29-Jan-24 04-Feb-24 5 226
GR-CON-Z20-1106 Sand Bedding 04-Feb-24 08-Feb-24 4 226
GR-CON-Z20-1107 laying cables 08-Feb-24 13-Feb-24 4 226
GR-CON-Z20-1108 Backfilling (sand / Sub base) 13-Feb-24 19-Feb-24 5 226
GR-CON-Z20-1109 Control Panel / Distribution Panel Installation 19-Feb-24 24-Feb-24 4 226
GR-CON-Z20-1110 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Street SS-26 10-Feb-24 30-Nov-24 237 6
Site Preparation 10-Feb-24 03-Apr-24 42 201
GR-CON-Z20-1111 Demolition (Asphalt.Paving,etc.....) 10-Feb-24 19-Feb-24 8 40
GR-CON-Z20-1112 Excavation And Disposal 19-Feb-24 02-Mar-24 10 40
GR-CON-Z20-1113 Prepretion And Compaction 02-Mar-24 16-Mar-24 12 201
GR-CON-Z20-1114 Backfilling 17-Mar-24 03-Apr-24 12 201
Curbstone and Paving 02-Mar-24 17-Jun-24 82 143
GR-CON-Z20-1115 Excavation Curbstone 02-Mar-24 13-Mar-24 10 78
GR-CON-Z20-1116 Plain Concrete 13-Mar-24 01-Apr-24 12 143
GR-CON-Z20-1117 Installation Curbstone 01-Apr-24 29-Apr-24 18 143
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1118 Casting Concrete (Mortar haunch) 29-Apr-24 08-May-24 8 143


GR-CON-Z20-1119 Backfilling (sand / Sub base) 08-May-24 29-May-24 18 143
GR-CON-Z20-1120 Installation of Paving 29-May-24 17-Jun-24 16 143
Landscape Works 13-Mar-24 14-Oct-24 169 6
GR-CON-Z20-1121 Excavation (Tree Pit ) 13-Mar-24 28-Mar-24 10 78
GR-CON-Z20-1122 Aggregate Drainage layer 28-Mar-24 20-Apr-24 12 78
GR-CON-Z20-1123 Installation Geotextile 20-Apr-24 29-Apr-24 8 78
GR-CON-Z20-1124 Backfilling (Soil max for tree) 29-Apr-24 13-May-24 12 78
GR-CON-Z20-1125 Installation of Trees 11-Aug-24 15-Aug-24 5 6
GR-CON-Z20-14176 Installation of Shrubs 17-Aug-24 19-Aug-24 3 6
GR-CON-Z20-14186 Installation of Succulents 20-Aug-24 22-Aug-24 3 6
GR-CON-Z20-14196 Installation of Ground Covers 24-Aug-24 26-Aug-24 3 6
GR-CON-Z20-14206 Installation of Grass 27-Aug-24 29-Aug-24 3 6
GR-CON-Z20-1126 Backfilling (Mulch) 31-Aug-24 05-Sep-24 6 6
GR-CON-Z20-1127 Natural Boulders Installation 07-Sep-24 15-Sep-24 8 6
GR-CON-Z20-1128 Retaining walls . Steps, forming risers, treads and edges with finishes
16-Sep-24 14-Oct-24 24 6
Site Furnishing 15-Oct-24 30-Nov-24 40 6
GR-CON-Z20-1137 Garden planter box 15-Oct-24 26-Oct-24 10 6
GR-CON-Z20-1138 Wheel stoppers 27-Oct-24 06-Nov-24 10 6
GR-CON-Z20-1139 Steel Lattice 07-Nov-24 18-Nov-24 10 6
GR-CON-Z20-1140 Handrail 19-Nov-24 30-Nov-24 10 6
Storm Piping Works 17-Nov-24 30-Nov-24 12 6
GR-CON-Z20-1141 Installation of DI grating covers 17-Nov-24 30-Nov-24 12 6
Irrigation Works 02-Mar-24 08-Jul-24 96 117
GR-CON-Z20-1129 Excavation Pipe Irrigation 02-Mar-24 13-Mar-24 10 40
GR-CON-Z20-1130 Sand Bedding 13-Mar-24 25-Mar-24 8 40
GR-CON-Z20-1131 HDPE Pipe Installations and fittings and conduit for cable 26-Mar-24 01-May-24 24 40
GR-CON-Z20-1133 Test pressure 01-May-24 13-May-24 10 40
GR-CON-Z20-1132 Installation of Valves and Accessories 13-May-24 22-May-24 8 40
GR-CON-Z20-1134 Back filling (sand / Subbase ) 22-May-24 01-Jun-24 8 40
GR-CON-Z20-1135 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 02-Jun-24 15-Jun-24 12 117
GR-CON-Z20-1136 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
16-Jun-24
system 08-Jul-24 16 117
Electrical Works 13-Mar-24 30-Nov-24 209 6
GR-CON-Z20-1142 Excavation And Disposal 13-Mar-24 28-Mar-24 10 161
GR-CON-Z20-1143 Sand Bedding 28-Mar-24 10-Apr-24 8 161
GR-CON-Z20-1144 laying cables 10-Apr-24 24-Apr-24 8 161
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1145 Backfilling (sand / Sub base) 24-Apr-24 06-May-24 10 161


GR-CON-Z20-1146 Control Panel / Distribution Panel Installation 06-May-24 15-May-24 8 161
GR-CON-Z20-1147 Road Crossing Ducts 19-Nov-24 30-Nov-24 10 6
Street SS-63 23-Apr-24 14-Oct-24 145 46
Site Preparation 23-Apr-24 16-May-24 21 170
GR-CON-Z20-1148 Demolition (Asphalt.Paving,etc.....) 23-Apr-24 27-Apr-24 4 26
GR-CON-Z20-1149 Excavation And Disposal 28-Apr-24 02-May-24 5 42
GR-CON-Z20-1150 Prepretion And Compaction 04-May-24 09-May-24 6 170
GR-CON-Z20-1151 Backfilling 11-May-24 16-May-24 6 170
Curbstone and Paving 04-May-24 30-Jun-24 46 136
GR-CON-Z20-1152 Excavation Curbstone 04-May-24 08-May-24 5 101
GR-CON-Z20-1153 Plain Concrete 09-May-24 15-May-24 6 136
GR-CON-Z20-1154 Installation Curbstone 16-May-24 26-May-24 9 136
GR-CON-Z20-1155 Casting Concrete (Mortar haunch) 27-May-24 30-May-24 4 136
GR-CON-Z20-1156 Backfilling (sand / Sub base) 01-Jun-24 10-Jun-24 9 136
GR-CON-Z20-1157 Installation of Paving 11-Jun-24 30-Jun-24 13 136
Landscape Works 09-May-24 19-Sep-24 111 46
GR-CON-Z20-1158 Excavation (Tree Pit ) 09-May-24 14-May-24 5 101
GR-CON-Z20-1159 Aggregate Drainage layer 15-May-24 21-May-24 6 101
GR-CON-Z20-1160 Installation Geotextile 22-May-24 26-May-24 4 101
GR-CON-Z20-1161 Backfilling (Soil max for tree) 27-May-24 02-Jun-24 6 101
GR-CON-Z20-1162 Installation of Trees 11-Aug-24 13-Aug-24 3 46
GR-CON-Z20-14216 Installation of Shrubs 14-Aug-24 17-Aug-24 3 46
GR-CON-Z20-14226 Installation of Succulents 18-Aug-24 20-Aug-24 3 46
GR-CON-Z20-14236 Installation of Ground Covers 21-Aug-24 24-Aug-24 3 46
GR-CON-Z20-14246 Installation of Grass 25-Aug-24 27-Aug-24 3 46
GR-CON-Z20-1163 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 46
GR-CON-Z20-1164 Natural Boulders Installation 01-Sep-24 04-Sep-24 4 46
GR-CON-Z20-1165 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Sep-24 19-Sep-24 13 46
Site Furnishing 21-Sep-24 14-Oct-24 20 46
GR-CON-Z20-1174 Garden planter box 21-Sep-24 26-Sep-24 5 46
GR-CON-Z20-1175 Wheel stoppers 28-Sep-24 02-Oct-24 5 46
GR-CON-Z20-1176 Steel Lattice 03-Oct-24 08-Oct-24 5 46
GR-CON-Z20-1177 Handrail 09-Oct-24 14-Oct-24 5 46
Storm Piping Works 08-Oct-24 14-Oct-24 6 46
GR-CON-Z20-1178 Installation of DI grating covers 08-Oct-24 14-Oct-24 6 46
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 04-May-24 08-Jul-24 53 123


GR-CON-Z20-1166 Excavation Pipe Irrigation 04-May-24 08-May-24 5 42
GR-CON-Z20-1167 Sand Bedding 09-May-24 13-May-24 4 42
GR-CON-Z20-1168 HDPE Pipe Installations and fittings and conduit for cable 14-May-24 30-May-24 15 42
GR-CON-Z20-1170 Test pressure 01-Jun-24 05-Jun-24 5 42
GR-CON-Z20-1169 Installation of Valves and Accessories 06-Jun-24 10-Jun-24 4 42
GR-CON-Z20-1171 Back filling (sand / Subbase ) 11-Jun-24 17-Jun-24 6 42
GR-CON-Z20-1172 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Jun-24 29-Jun-24 6 123
GR-CON-Z20-1173 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
30-Jun-24
system 08-Jul-24 8 123
Electrical Works 09-May-24 14-Oct-24 131 46
GR-CON-Z20-1179 Excavation And Disposal 09-May-24 14-May-24 5 150
GR-CON-Z20-1180 Sand Bedding 15-May-24 19-May-24 4 150
GR-CON-Z20-1181 laying cables 20-May-24 23-May-24 4 150
GR-CON-Z20-1182 Backfilling (sand / Sub base) 25-May-24 29-May-24 5 150
GR-CON-Z20-1183 Control Panel / Distribution Panel Installation 30-May-24 03-Jun-24 4 150
GR-CON-Z20-1184 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Street SS-65 06-May-24 14-Oct-24 134 46
Site Preparation 06-May-24 29-May-24 21 159
GR-CON-Z20-1185 Demolition (Asphalt.Paving,etc.....) 06-May-24 09-May-24 4 19
GR-CON-Z20-1186 Excavation And Disposal 11-May-24 15-May-24 5 31
GR-CON-Z20-1187 Prepretion And Compaction 16-May-24 22-May-24 6 159
GR-CON-Z20-1188 Backfilling 23-May-24 29-May-24 6 159
Curbstone and Paving 16-May-24 13-Jul-24 46 125
GR-CON-Z20-1189 Excavation Curbstone 16-May-24 21-May-24 5 90
GR-CON-Z20-1190 Plain Concrete 22-May-24 28-May-24 6 125
GR-CON-Z20-1191 Installation Curbstone 29-May-24 08-Jun-24 9 125
GR-CON-Z20-1192 Casting Concrete (Mortar haunch) 09-Jun-24 12-Jun-24 4 125
GR-CON-Z20-1193 Backfilling (sand / Sub base) 13-Jun-24 27-Jun-24 9 125
GR-CON-Z20-1194 Installation of Paving 29-Jun-24 13-Jul-24 13 125
Landscape Works 22-May-24 19-Sep-24 100 46
GR-CON-Z20-1195 Excavation (Tree Pit ) 22-May-24 27-May-24 5 90
GR-CON-Z20-1196 Aggregate Drainage layer 28-May-24 03-Jun-24 6 90
GR-CON-Z20-1197 Installation Geotextile 04-Jun-24 08-Jun-24 4 90
GR-CON-Z20-1198 Backfilling (Soil max for tree) 09-Jun-24 15-Jun-24 6 90
GR-CON-Z20-1199 Installation of Trees 11-Aug-24 13-Aug-24 3 46
GR-CON-Z20-14256 Installation of Shrubs 14-Aug-24 17-Aug-24 3 46
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-14266 Installation of Succulents 18-Aug-24 20-Aug-24 3 46


GR-CON-Z20-14276 Installation of Ground Covers 21-Aug-24 24-Aug-24 3 46
GR-CON-Z20-14286 Installation of Grass 25-Aug-24 27-Aug-24 3 46
GR-CON-Z20-1200 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 46
GR-CON-Z20-1201 Natural Boulders Installation 01-Sep-24 04-Sep-24 4 46
GR-CON-Z20-1202 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Sep-24 19-Sep-24 13 46
Site Furnishing 21-Sep-24 14-Oct-24 20 46
GR-CON-Z20-1211 Garden planter box 21-Sep-24 26-Sep-24 5 46
GR-CON-Z20-1212 Wheel stoppers 28-Sep-24 02-Oct-24 5 46
GR-CON-Z20-1213 Steel Lattice 03-Oct-24 08-Oct-24 5 46
GR-CON-Z20-1214 Handrail 09-Oct-24 14-Oct-24 5 46
Storm Piping Works 08-Oct-24 14-Oct-24 6 46
GR-CON-Z20-1215 Installation of DI grating covers 08-Oct-24 14-Oct-24 6 46
Irrigation Works 16-May-24 21-Jul-24 53 112
GR-CON-Z20-1203 Excavation Pipe Irrigation 16-May-24 21-May-24 5 31
GR-CON-Z20-1204 Sand Bedding 22-May-24 26-May-24 4 31
GR-CON-Z20-1205 HDPE Pipe Installations and fittings and conduit for cable 27-May-24 12-Jun-24 15 31
GR-CON-Z20-1207 Test pressure 13-Jun-24 18-Jun-24 5 31
GR-CON-Z20-1206 Installation of Valves and Accessories 24-Jun-24 27-Jun-24 4 31
GR-CON-Z20-1208 Back filling (sand / Subbase ) 29-Jun-24 04-Jul-24 6 31
GR-CON-Z20-1209 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Jul-24 11-Jul-24 6 112
GR-CON-Z20-1210 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
13-Jul-24
system 21-Jul-24 8 112
Electrical Works 22-May-24 14-Oct-24 120 46
GR-CON-Z20-1216 Excavation And Disposal 22-May-24 27-May-24 5 139
GR-CON-Z20-1217 Sand Bedding 28-May-24 01-Jun-24 4 139
GR-CON-Z20-1218 laying cables 02-Jun-24 05-Jun-24 4 139
GR-CON-Z20-1219 Backfilling (sand / Sub base) 06-Jun-24 11-Jun-24 5 139
GR-CON-Z20-1220 Control Panel / Distribution Panel Installation 12-Jun-24 16-Jun-24 4 139
GR-CON-Z20-1221 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Street SS-16 12-May-24 07-Dec-24 175 0
Site Preparation 12-May-24 17-Jun-24 32 143
GR-CON-Z20-1000 Demolition (Asphalt.Paving,etc.....) 12-May-24 18-May-24 6 0
GR-CON-Z20-1001 Excavation And Disposal 19-May-24 27-May-24 8 0
GR-CON-Z20-1002 Prepretion And Compaction 28-May-24 06-Jun-24 9 143
GR-CON-Z20-1003 Backfilling 08-Jun-24 17-Jun-24 9 143
Curbstone and Paving 28-May-24 22-Aug-24 71 90
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1004 Excavation Curbstone 28-May-24 05-Jun-24 8 20


GR-CON-Z20-1005 Plain Concrete 06-Jun-24 16-Jun-24 9 90
GR-CON-Z20-1006 Installation Curbstone 17-Jun-24 07-Jul-24 14 90
GR-CON-Z20-1007 Casting Concrete (Mortar haunch) 08-Jul-24 14-Jul-24 6 90
GR-CON-Z20-1008 Backfilling (sand / Sub base) 15-Jul-24 30-Jul-24 14 90
GR-CON-Z20-1009 Installation of Paving 31-Jul-24 22-Aug-24 20 90
Landscape Works 06-Jun-24 21-Oct-24 113 0
GR-CON-Z20-1010 Excavation (Tree Pit ) 06-Jun-24 15-Jun-24 8 20
GR-CON-Z20-1011 Aggregate Drainage layer 16-Jun-24 30-Jun-24 9 20
GR-CON-Z20-1012 Installation Geotextile 01-Jul-24 07-Jul-24 6 20
GR-CON-Z20-1013 Backfilling (Soil max for tree) 08-Jul-24 17-Jul-24 9 20
GR-CON-Z20-1014 Installation of Trees 11-Aug-24 19-Aug-24 8 0
GR-CON-Z20-14056 Installation of Shrubs 20-Aug-24 25-Aug-24 5 0
GR-CON-Z20-14066 Installation of Succulents 26-Aug-24 31-Aug-24 5 0
GR-CON-Z20-14076 Installation of Ground Covers 01-Sep-24 05-Sep-24 5 0
GR-CON-Z20-14086 Installation of Grass 07-Sep-24 11-Sep-24 5 0
GR-CON-Z20-1015 Backfilling (Mulch) 12-Sep-24 18-Sep-24 6 0
GR-CON-Z20-1016 Natural Boulders Installation 19-Sep-24 28-Sep-24 7 0
GR-CON-Z20-1017 Retaining walls . Steps, forming risers, treads and edges with finishes
29-Sep-24 21-Oct-24 20 0
Site Furnishing 22-Oct-24 07-Dec-24 40 0
GR-CON-Z20-1026 Garden planter box 22-Oct-24 02-Nov-24 10 0
GR-CON-Z20-1027 Wheel stoppers 03-Nov-24 13-Nov-24 10 0
GR-CON-Z20-1028 Steel Lattice 14-Nov-24 25-Nov-24 10 0
GR-CON-Z20-1029 Handrail 26-Nov-24 07-Dec-24 10 0
Storm Piping Works 26-Nov-24 07-Dec-24 10 0
GR-CON-Z20-1030 Installation of DI grating covers 26-Nov-24 07-Dec-24 10 0
Irrigation Works 28-May-24 03-Sep-24 81 70
GR-CON-Z20-1018 Excavation Pipe Irrigation 28-May-24 05-Jun-24 8 0
GR-CON-Z20-1019 Sand Bedding 06-Jun-24 12-Jun-24 6 0
GR-CON-Z20-1020 HDPE Pipe Installations and fittings and conduit for cable 13-Jun-24 14-Jul-24 23 0
GR-CON-Z20-1022 Test pressure 15-Jul-24 23-Jul-24 8 0
GR-CON-Z20-1021 Installation of Valves and Accessories 24-Jul-24 30-Jul-24 6 0
GR-CON-Z20-1023 Back filling (sand / Subbase ) 31-Jul-24 10-Aug-24 9 0
GR-CON-Z20-1024 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Aug-24 20-Aug-24 9 70
GR-CON-Z20-1025 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-Aug-24
system 03-Sep-24 12 70
Electrical Works 06-Jun-24 07-Dec-24 153 0
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1031 Excavation And Disposal 06-Jun-24 15-Jun-24 8 111


GR-CON-Z20-1032 Sand Bedding 16-Jun-24 26-Jun-24 6 111
GR-CON-Z20-1033 laying cables 27-Jun-24 03-Jul-24 6 111
GR-CON-Z20-1034 Backfilling (sand / Sub base) 04-Jul-24 13-Jul-24 8 111
GR-CON-Z20-1035 Control Panel / Distribution Panel Installation 14-Jul-24 20-Jul-24 6 111
GR-CON-Z20-1036 Road Crossing Ducts 28-Nov-24 07-Dec-24 8 0
Street SS-67 11-May-24 14-Oct-24 130 46
Site Preparation 11-May-24 03-Jun-24 21 155
GR-CON-Z20-1222 Demolition (Asphalt.Paving,etc.....) 11-May-24 14-May-24 4 19
GR-CON-Z20-1223 Excavation And Disposal 15-May-24 20-May-24 5 27
GR-CON-Z20-1224 Prepretion And Compaction 21-May-24 27-May-24 6 155
GR-CON-Z20-1225 Backfilling 28-May-24 03-Jun-24 6 155
Curbstone and Paving 21-May-24 17-Jul-24 46 121
GR-CON-Z20-1226 Excavation Curbstone 21-May-24 26-May-24 5 86
GR-CON-Z20-1227 Plain Concrete 27-May-24 02-Jun-24 6 121
GR-CON-Z20-1228 Installation Curbstone 03-Jun-24 12-Jun-24 9 121
GR-CON-Z20-1229 Casting Concrete (Mortar haunch) 13-Jun-24 17-Jun-24 4 121
GR-CON-Z20-1230 Backfilling (sand / Sub base) 18-Jun-24 02-Jul-24 9 121
GR-CON-Z20-1231 Installation of Paving 03-Jul-24 17-Jul-24 13 121
Landscape Works 27-May-24 19-Sep-24 96 46
GR-CON-Z20-1232 Excavation (Tree Pit ) 27-May-24 01-Jun-24 5 86
GR-CON-Z20-1233 Aggregate Drainage layer 02-Jun-24 08-Jun-24 6 86
GR-CON-Z20-1234 Installation Geotextile 09-Jun-24 12-Jun-24 4 86
GR-CON-Z20-1235 Backfilling (Soil max for tree) 13-Jun-24 24-Jun-24 6 86
GR-CON-Z20-1236 Installation of Trees 11-Aug-24 13-Aug-24 3 46
GR-CON-Z20-14296 Installation of Shrubs 14-Aug-24 17-Aug-24 3 46
GR-CON-Z20-14306 Installation of Succulents 18-Aug-24 20-Aug-24 3 46
GR-CON-Z20-14316 Installation of Ground Covers 21-Aug-24 24-Aug-24 3 46
GR-CON-Z20-14326 Installation of Grass 25-Aug-24 27-Aug-24 3 46
GR-CON-Z20-1237 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 46
GR-CON-Z20-1238 Natural Boulders Installation 01-Sep-24 04-Sep-24 4 46
GR-CON-Z20-1239 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Sep-24 19-Sep-24 13 46
Site Furnishing 21-Sep-24 14-Oct-24 20 46
GR-CON-Z20-1248 Garden planter box 21-Sep-24 26-Sep-24 5 46
GR-CON-Z20-1249 Wheel stoppers 28-Sep-24 02-Oct-24 5 46
GR-CON-Z20-1250 Steel Lattice 03-Oct-24 08-Oct-24 5 46
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1251 Handrail 09-Oct-24 14-Oct-24 5 46


Storm Piping Works 08-Oct-24 14-Oct-24 6 46
GR-CON-Z20-1252 Installation of DI grating covers 08-Oct-24 14-Oct-24 6 46
Irrigation Works 21-May-24 25-Jul-24 53 108
GR-CON-Z20-1240 Excavation Pipe Irrigation 21-May-24 26-May-24 5 27
GR-CON-Z20-1241 Sand Bedding 27-May-24 30-May-24 4 27
GR-CON-Z20-1242 HDPE Pipe Installations and fittings and conduit for cable 01-Jun-24 17-Jun-24 15 27
GR-CON-Z20-1244 Test pressure 18-Jun-24 27-Jun-24 5 27
GR-CON-Z20-1243 Installation of Valves and Accessories 29-Jun-24 02-Jul-24 4 27
GR-CON-Z20-1245 Back filling (sand / Subbase ) 03-Jul-24 09-Jul-24 6 27
GR-CON-Z20-1246 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Jul-24 16-Jul-24 6 108
GR-CON-Z20-1247 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
17-Jul-24
system 25-Jul-24 8 108
Electrical Works 27-May-24 14-Oct-24 116 46
GR-CON-Z20-1253 Excavation And Disposal 27-May-24 01-Jun-24 5 135
GR-CON-Z20-1254 Sand Bedding 02-Jun-24 05-Jun-24 4 135
GR-CON-Z20-1255 laying cables 06-Jun-24 10-Jun-24 4 135
GR-CON-Z20-1256 Backfilling (sand / Sub base) 11-Jun-24 16-Jun-24 5 135
GR-CON-Z20-1257 Control Panel / Distribution Panel Installation 17-Jun-24 25-Jun-24 4 135
GR-CON-Z20-1258 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Street SS-84 15-May-24 14-Oct-24 126 46
Site Preparation 15-May-24 08-Jun-24 21 151
GR-CON-Z20-1259 Demolition (Asphalt.Paving,etc.....) 15-May-24 19-May-24 4 19
GR-CON-Z20-1260 Excavation And Disposal 20-May-24 25-May-24 5 23
GR-CON-Z20-1261 Prepretion And Compaction 26-May-24 01-Jun-24 6 151
GR-CON-Z20-1262 Backfilling 02-Jun-24 08-Jun-24 6 151
Curbstone and Paving 26-May-24 22-Jul-24 46 117
GR-CON-Z20-1263 Excavation Curbstone 26-May-24 30-May-24 5 82
GR-CON-Z20-1264 Plain Concrete 01-Jun-24 06-Jun-24 6 117
GR-CON-Z20-1265 Installation Curbstone 08-Jun-24 17-Jun-24 9 117
GR-CON-Z20-1266 Casting Concrete (Mortar haunch) 18-Jun-24 26-Jun-24 4 117
GR-CON-Z20-1267 Backfilling (sand / Sub base) 27-Jun-24 07-Jul-24 9 117
GR-CON-Z20-1268 Installation of Paving 08-Jul-24 22-Jul-24 13 117
Landscape Works 01-Jun-24 19-Sep-24 92 46
GR-CON-Z20-1269 Excavation (Tree Pit ) 01-Jun-24 05-Jun-24 5 82
GR-CON-Z20-1270 Aggregate Drainage layer 06-Jun-24 12-Jun-24 6 82
GR-CON-Z20-1271 Installation Geotextile 13-Jun-24 17-Jun-24 4 82
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1272 Backfilling (Soil max for tree) 18-Jun-24 29-Jun-24 6 82


GR-CON-Z20-1273 Installation of Trees 11-Aug-24 13-Aug-24 3 46
GR-CON-Z20-14336 Installation of Shrubs 14-Aug-24 17-Aug-24 3 46
GR-CON-Z20-14346 Installation of Succulents 18-Aug-24 20-Aug-24 3 46
GR-CON-Z20-14356 Installation of Ground Covers 21-Aug-24 24-Aug-24 3 46
GR-CON-Z20-14366 Installation of Grass 25-Aug-24 27-Aug-24 3 46
GR-CON-Z20-1274 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 46
GR-CON-Z20-1275 Natural Boulders Installation 01-Sep-24 04-Sep-24 4 46
GR-CON-Z20-1276 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Sep-24 19-Sep-24 13 46
Site Furnishing 21-Sep-24 14-Oct-24 20 46
GR-CON-Z20-1285 Garden planter box 21-Sep-24 26-Sep-24 5 46
GR-CON-Z20-1286 Wheel stoppers 28-Sep-24 02-Oct-24 5 46
GR-CON-Z20-1287 Steel Lattice 03-Oct-24 08-Oct-24 5 46
GR-CON-Z20-1288 Handrail 09-Oct-24 14-Oct-24 5 46
Storm Piping Works 08-Oct-24 14-Oct-24 6 46
GR-CON-Z20-1289 Installation of DI grating covers 08-Oct-24 14-Oct-24 6 46
Irrigation Works 26-May-24 30-Jul-24 53 104
GR-CON-Z20-1277 Excavation Pipe Irrigation 26-May-24 30-May-24 5 23
GR-CON-Z20-1278 Sand Bedding 01-Jun-24 04-Jun-24 4 23
GR-CON-Z20-1279 HDPE Pipe Installations and fittings and conduit for cable 05-Jun-24 26-Jun-24 15 23
GR-CON-Z20-1281 Test pressure 27-Jun-24 02-Jul-24 5 23
GR-CON-Z20-1280 Installation of Valves and Accessories 03-Jul-24 07-Jul-24 4 23
GR-CON-Z20-1282 Back filling (sand / Subbase ) 08-Jul-24 14-Jul-24 6 23
GR-CON-Z20-1283 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Jul-24 21-Jul-24 6 104
GR-CON-Z20-1284 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-Jul-24
system 30-Jul-24 8 104
Electrical Works 01-Jun-24 14-Oct-24 112 46
GR-CON-Z20-1290 Excavation And Disposal 01-Jun-24 05-Jun-24 5 131
GR-CON-Z20-1291 Sand Bedding 06-Jun-24 10-Jun-24 4 131
GR-CON-Z20-1292 laying cables 11-Jun-24 15-Jun-24 4 131
GR-CON-Z20-1293 Backfilling (sand / Sub base) 16-Jun-24 25-Jun-24 5 131
GR-CON-Z20-1294 Control Panel / Distribution Panel Installation 26-Jun-24 30-Jun-24 4 131
GR-CON-Z20-1295 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Street SS-85 20-May-24 14-Oct-24 122 46
Site Preparation 20-May-24 12-Jun-24 21 147
GR-CON-Z20-1296 Demolition (Asphalt.Paving,etc.....) 20-May-24 23-May-24 4 19
GR-CON-Z20-1297 Excavation And Disposal 25-May-24 29-May-24 5 19
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1298 Prepretion And Compaction 30-May-24 05-Jun-24 6 147


GR-CON-Z20-1299 Backfilling 06-Jun-24 12-Jun-24 6 147
Curbstone and Paving 30-May-24 27-Jul-24 46 113
GR-CON-Z20-1300 Excavation Curbstone 30-May-24 04-Jun-24 5 78
GR-CON-Z20-1301 Plain Concrete 05-Jun-24 11-Jun-24 6 113
GR-CON-Z20-1302 Installation Curbstone 12-Jun-24 26-Jun-24 9 113
GR-CON-Z20-1303 Casting Concrete (Mortar haunch) 27-Jun-24 01-Jul-24 4 113
GR-CON-Z20-1304 Backfilling (sand / Sub base) 02-Jul-24 11-Jul-24 9 113
GR-CON-Z20-1305 Installation of Paving 13-Jul-24 27-Jul-24 13 113
Landscape Works 05-Jun-24 19-Sep-24 88 46
GR-CON-Z20-1306 Excavation (Tree Pit ) 05-Jun-24 10-Jun-24 5 78
GR-CON-Z20-1307 Aggregate Drainage layer 11-Jun-24 17-Jun-24 6 78
GR-CON-Z20-1308 Installation Geotextile 18-Jun-24 26-Jun-24 4 78
GR-CON-Z20-1309 Backfilling (Soil max for tree) 27-Jun-24 03-Jul-24 6 78
GR-CON-Z20-1310 Installation of Trees 11-Aug-24 13-Aug-24 3 46
GR-CON-Z20-14376 Installation of Shrubs 14-Aug-24 17-Aug-24 3 46
GR-CON-Z20-14386 Installation of Succulents 18-Aug-24 20-Aug-24 3 46
GR-CON-Z20-14396 Installation of Ground Covers 21-Aug-24 24-Aug-24 3 46
GR-CON-Z20-14406 Installation of Grass 25-Aug-24 27-Aug-24 3 46
GR-CON-Z20-1311 Backfilling (Mulch) 28-Aug-24 31-Aug-24 3 46
GR-CON-Z20-1312 Natural Boulders Installation 01-Sep-24 04-Sep-24 4 46
GR-CON-Z20-1313 Retaining walls . Steps, forming risers, treads and edges with finishes
05-Sep-24 19-Sep-24 13 46
Site Furnishing 21-Sep-24 14-Oct-24 20 46
GR-CON-Z20-1322 Garden planter box 21-Sep-24 26-Sep-24 5 46
GR-CON-Z20-1323 Wheel stoppers 28-Sep-24 02-Oct-24 5 46
GR-CON-Z20-1324 Steel Lattice 03-Oct-24 08-Oct-24 5 46
GR-CON-Z20-1325 Handrail 09-Oct-24 14-Oct-24 5 46
Storm Piping Works 08-Oct-24 14-Oct-24 6 46
GR-CON-Z20-1326 Installation of DI grating covers 08-Oct-24 14-Oct-24 6 46
Irrigation Works 30-May-24 04-Aug-24 53 100
GR-CON-Z20-1314 Excavation Pipe Irrigation 30-May-24 04-Jun-24 5 19
GR-CON-Z20-1315 Sand Bedding 05-Jun-24 09-Jun-24 4 19
GR-CON-Z20-1316 HDPE Pipe Installations and fittings and conduit for cable 10-Jun-24 01-Jul-24 15 19
GR-CON-Z20-1318 Test pressure 02-Jul-24 07-Jul-24 5 19
GR-CON-Z20-1317 Installation of Valves and Accessories 08-Jul-24 11-Jul-24 4 19
GR-CON-Z20-1319 Back filling (sand / Subbase ) 13-Jul-24 18-Jul-24 6 19
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z20-1320 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Jul-24 25-Jul-24 6 100
GR-CON-Z20-1321 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
27-Jul-24
system 04-Aug-24 8 100
Electrical Works 05-Jun-24 14-Oct-24 108 46
GR-CON-Z20-1327 Excavation And Disposal 05-Jun-24 10-Jun-24 5 127
GR-CON-Z20-1328 Sand Bedding 11-Jun-24 15-Jun-24 4 127
GR-CON-Z20-1329 laying cables 16-Jun-24 24-Jun-24 4 127
GR-CON-Z20-1330 Backfilling (sand / Sub base) 25-Jun-24 30-Jun-24 5 127
GR-CON-Z20-1331 Control Panel / Distribution Panel Installation 01-Jul-24 04-Jul-24 4 127
GR-CON-Z20-1332 Road Crossing Ducts 09-Oct-24 14-Oct-24 5 46
Zone 16 03-Dec-23 17-Nov-24 285 11
Future Neighborhood Park FNP-24 03-Dec-23 25-Sep-24 240 56
Site Preparation 03-Dec-23 26-Dec-23 20 276
GR-CON-Z16-1157 Demolition (Asphalt.Paving,etc.....) 03-Dec-23 07-Dec-23 4 16
GR-CON-Z16-1158 Excavation And Disposal 07-Dec-23 14-Dec-23 6 169
GR-CON-Z16-1159 Prepretion And Compaction 14-Dec-23 19-Dec-23 4 276
GR-CON-Z16-1160 Backfilling 19-Dec-23 26-Dec-23 6 276
Curbstone and Paving 14-Dec-23 06-Feb-24 46 240
GR-CON-Z16-1161 Excavation Curbstone 14-Dec-23 20-Dec-23 5 226
GR-CON-Z16-1162 Plain Concrete 20-Dec-23 27-Dec-23 6 240
GR-CON-Z16-1163 Installation Curbstone 27-Dec-23 07-Jan-24 9 240
GR-CON-Z16-1164 Casting Concrete (Mortar haunch) 07-Jan-24 11-Jan-24 4 240
GR-CON-Z16-1165 Backfilling (sand / Sub base) 11-Jan-24 22-Jan-24 9 240
GR-CON-Z16-1166 Installation of Paving 22-Jan-24 06-Feb-24 13 240
Landscape Works 20-Dec-23 25-Sep-24 225 56
GR-CON-Z16-1167 Excavation (Tree Pit ) 20-Dec-23 26-Dec-23 5 226
GR-CON-Z16-1168 Aggregate Drainage layer 26-Dec-23 02-Jan-24 6 226
GR-CON-Z16-1169 Installation Geotextile 02-Jan-24 07-Jan-24 4 226
GR-CON-Z16-1170 Backfilling (Soil max for tree) 07-Jan-24 14-Jan-24 6 226
GR-CON-Z16-1171 Installation of Trees 15-Aug-24 18-Aug-24 2 56
GR-CON-Z16-2706 Installation of Shrubs 18-Aug-24 20-Aug-24 2 56
GR-CON-Z16-2716 Installation of Succulents 20-Aug-24 22-Aug-24 2 56
GR-CON-Z16-2726 Installation of Ground Covers 22-Aug-24 25-Aug-24 2 56
GR-CON-Z16-2736 Installation of Climbers 25-Aug-24 27-Aug-24 2 56
GR-CON-Z16-2746 Installation of Grass 27-Aug-24 29-Aug-24 2 56
GR-CON-Z16-2756 Installation of Lawns 29-Aug-24 01-Sep-24 2 56
GR-CON-Z16-1172 Backfilling (Mulch) 01-Sep-24 04-Sep-24 3 56
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1173 Natural Boulders Installation 04-Sep-24 09-Sep-24 4 56


GR-CON-Z16-1174 Retaining walls . Steps, forming risers, treads and edges with finishes
09-Sep-24 25-Sep-24 13 56
Irrigation Works 14-Dec-23 25-Sep-24 230 56
GR-CON-Z16-1175 Excavation Pipe Irrigation 14-Dec-23 20-Dec-23 5 169
GR-CON-Z16-1176 Sand Bedding 20-Dec-23 24-Dec-23 3 169
GR-CON-Z16-1177 HDPE Pipe Installations and fittings and conduit for cable 24-Dec-23 10-Jan-24 15 169
GR-CON-Z16-1179 Test pressure 10-Jan-24 16-Jan-24 5 169
GR-CON-Z16-1178 Installation of Valves and Accessories 16-Jan-24 21-Jan-24 4 169
GR-CON-Z16-1180 Back filling (sand / Subbase ) 21-Jan-24 28-Jan-24 6 169
GR-CON-Z16-1181 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-Jan-24 04-Feb-24 6 234
GR-CON-Z16-1182 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
15-Sep-24
system 25-Sep-24 8 56
Mosque M-25 07-Dec-23 29-Oct-24 265 27
Site Preparation 07-Dec-23 30-Dec-23 19 251
GR-CON-Z16-1183 Demolition (Asphalt.Paving,etc.....) 07-Dec-23 12-Dec-23 4 63
GR-CON-Z16-1184 Excavation And Disposal 12-Dec-23 18-Dec-23 5 166
GR-CON-Z16-1185 Prepretion And Compaction 18-Dec-23 23-Dec-23 4 251
GR-CON-Z16-1186 Backfilling 23-Dec-23 30-Dec-23 6 251
Curbstone and Paving 30-Dec-23 24-Jan-24 22 251
GR-CON-Z16-1191 Backfilling (sand / Sub base) 30-Dec-23 09-Jan-24 9 251
GR-CON-Z16-1192 Installation of Paving 09-Jan-24 24-Jan-24 13 251
Landscape Works 18-Dec-23 29-Oct-24 256 27
GR-CON-Z16-1193 Excavation (Tree Pit ) 18-Dec-23 24-Dec-23 5 199
GR-CON-Z16-1194 Aggregate Drainage layer 24-Dec-23 31-Dec-23 6 199
GR-CON-Z16-1195 Installation Geotextile 31-Dec-23 06-Jan-24 5 199
GR-CON-Z16-1196 Backfilling (Soil max for tree) 06-Jan-24 11-Jan-24 5 199
GR-CON-Z16-1197 Installation of Trees 15-Aug-24 20-Aug-24 4 27
GR-CON-Z16-4626 Installation of Climbers 20-Aug-24 25-Aug-24 4 27
GR-CON-Z16-4636 Installation of Shrubs 25-Aug-24 29-Aug-24 4 27
GR-CON-Z16-4646 Installation of Succulents 29-Aug-24 03-Sep-24 4 27
GR-CON-Z16-4656 Installation of Ground Covers 03-Sep-24 08-Sep-24 4 27
GR-CON-Z16-1198 Backfilling (Mulch) 08-Sep-24 26-Sep-24 15 27
GR-CON-Z16-1199 Natural Boulders Installation 26-Sep-24 12-Oct-24 13 27
GR-CON-Z16-1200 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Oct-24 29-Oct-24 15 27
Irrigation Works 18-Dec-23 29-Oct-24 256 27
GR-CON-Z16-1201 Excavation Pipe Irrigation 18-Dec-23 24-Dec-23 5 166
GR-CON-Z16-1202 Sand Bedding 24-Dec-23 27-Dec-23 3 166
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1203 HDPE Pipe Installations and fittings and conduit for cable 27-Dec-23 14-Jan-24 15 166
GR-CON-Z16-1205 Test pressure 14-Jan-24 20-Jan-24 5 166
GR-CON-Z16-1204 Installation of Valves and Accessories 20-Jan-24 24-Jan-24 4 166
GR-CON-Z16-1206 Back filling (sand / Subbase ) 24-Jan-24 31-Jan-24 6 166
GR-CON-Z16-1207 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 31-Jan-24 07-Feb-24 6 233
GR-CON-Z16-1208 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-Oct-24
system 29-Oct-24 6 27
Mosque M-26 12-Dec-23 29-Oct-24 261 27
Site Preparation 12-Dec-23 03-Jan-24 19 247
GR-CON-Z16-1209 Demolition (Asphalt.Paving,etc.....) 12-Dec-23 17-Dec-23 4 63
GR-CON-Z16-1210 Excavation And Disposal 17-Dec-23 23-Dec-23 5 162
GR-CON-Z16-1211 Prepretion And Compaction 23-Dec-23 27-Dec-23 4 247
GR-CON-Z16-1212 Backfilling 27-Dec-23 03-Jan-24 6 247
Curbstone and Paving 03-Jan-24 29-Jan-24 22 247
GR-CON-Z16-1217 Backfilling (sand / Sub base) 03-Jan-24 14-Jan-24 9 247
GR-CON-Z16-1218 Installation of Paving 14-Jan-24 29-Jan-24 13 247
Landscape Works 23-Dec-23 29-Oct-24 252 27
GR-CON-Z16-1219 Excavation (Tree Pit ) 23-Dec-23 28-Dec-23 5 195
GR-CON-Z16-1220 Aggregate Drainage layer 28-Dec-23 04-Jan-24 6 195
GR-CON-Z16-1221 Installation Geotextile 04-Jan-24 10-Jan-24 5 195
GR-CON-Z16-1222 Backfilling (Soil max for tree) 10-Jan-24 16-Jan-24 5 195
GR-CON-Z16-1223 Installation of Trees 15-Aug-24 20-Aug-24 4 27
GR-CON-Z16-4666 Installation of Climbers 20-Aug-24 25-Aug-24 4 27
GR-CON-Z16-4676 Installation of Shrubs 25-Aug-24 29-Aug-24 4 27
GR-CON-Z16-4686 Installation of Succulents 29-Aug-24 03-Sep-24 4 27
GR-CON-Z16-4696 Installation of Ground Covers 03-Sep-24 08-Sep-24 4 27
GR-CON-Z16-1224 Backfilling (Mulch) 08-Sep-24 26-Sep-24 15 27
GR-CON-Z16-1225 Natural Boulders Installation 26-Sep-24 12-Oct-24 13 27
GR-CON-Z16-1226 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Oct-24 29-Oct-24 15 27
Irrigation Works 23-Dec-23 29-Oct-24 252 27
GR-CON-Z16-1227 Excavation Pipe Irrigation 23-Dec-23 28-Dec-23 5 162
GR-CON-Z16-1228 Sand Bedding 28-Dec-23 01-Jan-24 3 162
GR-CON-Z16-1229 HDPE Pipe Installations and fittings and conduit for cable 01-Jan-24 18-Jan-24 15 162
GR-CON-Z16-1231 Test pressure 18-Jan-24 24-Jan-24 5 162
GR-CON-Z16-1230 Installation of Valves and Accessories 24-Jan-24 29-Jan-24 4 162
GR-CON-Z16-1232 Back filling (sand / Subbase ) 29-Jan-24 05-Feb-24 6 162
GR-CON-Z16-1233 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-Feb-24 12-Feb-24 6 229
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1234 Pull box , Decoders , Connecting to plots /Connection to infra irrigation


22-Oct-24
system 29-Oct-24 6 27
Mosque M-37 17-Dec-23 29-Oct-24 257 27
Site Preparation 17-Dec-23 08-Jan-24 19 243
GR-CON-Z16-1235 Demolition (Asphalt.Paving,etc.....) 17-Dec-23 21-Dec-23 4 63
GR-CON-Z16-1236 Excavation And Disposal 21-Dec-23 27-Dec-23 5 158
GR-CON-Z16-1237 Prepretion And Compaction 27-Dec-23 01-Jan-24 4 243
GR-CON-Z16-1238 Backfilling 01-Jan-24 08-Jan-24 6 243
Curbstone and Paving 08-Jan-24 03-Feb-24 22 243
GR-CON-Z16-1243 Backfilling (sand / Sub base) 08-Jan-24 18-Jan-24 9 243
GR-CON-Z16-1244 Installation of Paving 18-Jan-24 03-Feb-24 13 243
Landscape Works 27-Dec-23 29-Oct-24 248 27
GR-CON-Z16-1245 Excavation (Tree Pit ) 27-Dec-23 02-Jan-24 5 191
GR-CON-Z16-1246 Aggregate Drainage layer 02-Jan-24 09-Jan-24 6 191
GR-CON-Z16-1247 Installation Geotextile 09-Jan-24 15-Jan-24 5 191
GR-CON-Z16-1248 Backfilling (Soil max for tree) 15-Jan-24 21-Jan-24 5 191
GR-CON-Z16-1249 Installation of Trees 15-Aug-24 20-Aug-24 4 27
GR-CON-Z16-4706 Installation of Climbers 20-Aug-24 25-Aug-24 4 27
GR-CON-Z16-4716 Installation of Shrubs 25-Aug-24 29-Aug-24 4 27
GR-CON-Z16-4726 Installation of Succulents 29-Aug-24 03-Sep-24 4 27
GR-CON-Z16-4736 Installation of Ground Covers 03-Sep-24 08-Sep-24 4 27
GR-CON-Z16-1250 Backfilling (Mulch) 08-Sep-24 26-Sep-24 15 27
GR-CON-Z16-1251 Natural Boulders Installation 26-Sep-24 12-Oct-24 13 27
GR-CON-Z16-1252 Retaining walls . Steps, forming risers, treads and edges with finishes
12-Oct-24 29-Oct-24 15 27
Irrigation Works 27-Dec-23 29-Oct-24 248 27
GR-CON-Z16-1253 Excavation Pipe Irrigation 27-Dec-23 02-Jan-24 5 158
GR-CON-Z16-1254 Sand Bedding 02-Jan-24 06-Jan-24 3 158
GR-CON-Z16-1255 HDPE Pipe Installations and fittings and conduit for cable 06-Jan-24 23-Jan-24 15 158
GR-CON-Z16-1257 Test pressure 23-Jan-24 29-Jan-24 5 158
GR-CON-Z16-1256 Installation of Valves and Accessories 29-Jan-24 03-Feb-24 4 158
GR-CON-Z16-1258 Back filling (sand / Subbase ) 03-Feb-24 10-Feb-24 6 158
GR-CON-Z16-1259 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 10-Feb-24 17-Feb-24 6 225
GR-CON-Z16-1260 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-Oct-24
system 29-Oct-24 6 27
Parking P-22 19-Dec-23 17-Sep-24 220 62
Site Preparation 19-Dec-23 26-Dec-23 6 263
GR-CON-Z16-1264 Backfilling 19-Dec-23 26-Dec-23 6 263
GR-CON-Z16-1262 Excavation And Disposal 20-Dec-23 26-Dec-23 5 159
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1261 Demolition (Asphalt.Paving,etc.....) 21-Dec-23 26-Dec-23 4 63


GR-CON-Z16-1263 Prepretion And Compaction 21-Dec-23 26-Dec-23 4 263
Curbstone and Paving 26-Dec-23 18-Feb-24 46 230
GR-CON-Z16-1265 Excavation Curbstone 26-Dec-23 01-Jan-24 5 222
GR-CON-Z16-1266 Plain Concrete 01-Jan-24 08-Jan-24 6 230
GR-CON-Z16-1267 Installation Curbstone 08-Jan-24 18-Jan-24 9 230
GR-CON-Z16-1268 Casting Concrete (Mortar haunch) 18-Jan-24 23-Jan-24 4 230
GR-CON-Z16-1269 Backfilling (sand / Sub base) 23-Jan-24 03-Feb-24 9 230
GR-CON-Z16-1270 Installation of Paving 03-Feb-24 18-Feb-24 13 230
Landscape Works 01-Jan-24 05-Sep-24 199 62
GR-CON-Z16-1271 Excavation (Tree Pit ) 01-Jan-24 07-Jan-24 5 222
GR-CON-Z16-1272 Aggregate Drainage layer 07-Jan-24 14-Jan-24 6 222
GR-CON-Z16-1273 Installation Geotextile 14-Jan-24 18-Jan-24 4 222
GR-CON-Z16-1274 Backfilling (Soil max for tree) 18-Jan-24 25-Jan-24 6 222
GR-CON-Z16-1275 Installation of Trees 15-Aug-24 19-Aug-24 3 62
GR-CON-Z16-8456 Installation of Shrubs 19-Aug-24 22-Aug-24 3 62
GR-CON-Z16-8466 Installation of Ground Covers 22-Aug-24 26-Aug-24 3 62
GR-CON-Z16-8476 Installation of Succulents 26-Aug-24 29-Aug-24 3 62
GR-CON-Z16-8486 Installation of Grass 29-Aug-24 02-Sep-24 3 62
GR-CON-Z16-1276 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 62
Site Furnishing 05-Sep-24 17-Sep-24 10 62
GR-CON-Z16-1287 Tree Grate 05-Sep-24 11-Sep-24 5 62
GR-CON-Z16-1288 Wheel stoppers 11-Sep-24 17-Sep-24 5 62
Irrigation Works 26-Dec-23 17-Sep-24 214 62
GR-CON-Z16-1279 Excavation Pipe Irrigation 26-Dec-23 01-Jan-24 5 159
GR-CON-Z16-1280 Sand Bedding 01-Jan-24 04-Jan-24 3 159
GR-CON-Z16-1281 HDPE Pipe Installations and fittings and conduit for cable 04-Jan-24 22-Jan-24 15 159
GR-CON-Z16-1283 Test pressure 22-Jan-24 28-Jan-24 5 159
GR-CON-Z16-1282 Installation of Valves and Accessories 28-Jan-24 01-Feb-24 4 159
GR-CON-Z16-1284 Back filling (sand / Subbase ) 01-Feb-24 08-Feb-24 6 159
GR-CON-Z16-1285 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 08-Feb-24 15-Feb-24 6 224
GR-CON-Z16-1286 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Sep-24
system 17-Sep-24 8 62
Parking P-23 24-Dec-23 17-Sep-24 216 62
Site Preparation 24-Dec-23 31-Dec-23 6 259
GR-CON-Z16-1292 Backfilling 24-Dec-23 31-Dec-23 6 259
GR-CON-Z16-1290 Excavation And Disposal 25-Dec-23 31-Dec-23 5 155
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1289 Demolition (Asphalt.Paving,etc.....) 26-Dec-23 31-Dec-23 4 63


GR-CON-Z16-1291 Prepretion And Compaction 26-Dec-23 31-Dec-23 4 259
Curbstone and Paving 31-Dec-23 22-Feb-24 46 226
GR-CON-Z16-1293 Excavation Curbstone 31-Dec-23 06-Jan-24 5 218
GR-CON-Z16-1294 Plain Concrete 06-Jan-24 13-Jan-24 6 226
GR-CON-Z16-1295 Installation Curbstone 13-Jan-24 23-Jan-24 9 226
GR-CON-Z16-1296 Casting Concrete (Mortar haunch) 23-Jan-24 28-Jan-24 4 226
GR-CON-Z16-1297 Backfilling (sand / Sub base) 28-Jan-24 07-Feb-24 9 226
GR-CON-Z16-1298 Installation of Paving 07-Feb-24 22-Feb-24 13 226
Landscape Works 06-Jan-24 05-Sep-24 195 62
GR-CON-Z16-1299 Excavation (Tree Pit ) 06-Jan-24 11-Jan-24 5 218
GR-CON-Z16-1300 Aggregate Drainage layer 11-Jan-24 18-Jan-24 6 218
GR-CON-Z16-1301 Installation Geotextile 18-Jan-24 23-Jan-24 4 218
GR-CON-Z16-1302 Backfilling (Soil max for tree) 23-Jan-24 30-Jan-24 6 218
GR-CON-Z16-1303 Installation of Trees 15-Aug-24 19-Aug-24 3 62
GR-CON-Z16-8496 Installation of Shrubs 19-Aug-24 22-Aug-24 3 62
GR-CON-Z16-8506 Installation of Ground Covers 22-Aug-24 26-Aug-24 3 62
GR-CON-Z16-8516 Installation of Succulents 26-Aug-24 29-Aug-24 3 62
GR-CON-Z16-8526 Installation of Grass 29-Aug-24 02-Sep-24 3 62
GR-CON-Z16-1304 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 62
Site Furnishing 05-Sep-24 17-Sep-24 10 62
GR-CON-Z16-1315 Tree Grate 05-Sep-24 11-Sep-24 5 62
GR-CON-Z16-1316 Wheel stoppers 11-Sep-24 17-Sep-24 5 62
Irrigation Works 31-Dec-23 17-Sep-24 210 62
GR-CON-Z16-1307 Excavation Pipe Irrigation 31-Dec-23 06-Jan-24 5 155
GR-CON-Z16-1308 Sand Bedding 06-Jan-24 09-Jan-24 3 155
GR-CON-Z16-1309 HDPE Pipe Installations and fittings and conduit for cable 09-Jan-24 27-Jan-24 15 155
GR-CON-Z16-1311 Test pressure 27-Jan-24 01-Feb-24 5 155
GR-CON-Z16-1310 Installation of Valves and Accessories 01-Feb-24 06-Feb-24 4 155
GR-CON-Z16-1312 Back filling (sand / Subbase ) 06-Feb-24 13-Feb-24 6 155
GR-CON-Z16-1313 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Feb-24 20-Feb-24 6 220
GR-CON-Z16-1314 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Sep-24
system 17-Sep-24 8 62
Parking P-39 28-Dec-23 17-Sep-24 212 62
Site Preparation 28-Dec-23 04-Jan-24 6 255
GR-CON-Z16-1320 Backfilling 28-Dec-23 04-Jan-24 6 255
GR-CON-Z16-1318 Excavation And Disposal 30-Dec-23 04-Jan-24 5 151
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1317 Demolition (Asphalt.Paving,etc.....) 31-Dec-23 04-Jan-24 4 63


GR-CON-Z16-1319 Prepretion And Compaction 31-Dec-23 04-Jan-24 4 255
Curbstone and Paving 04-Jan-24 27-Feb-24 46 222
GR-CON-Z16-1321 Excavation Curbstone 04-Jan-24 10-Jan-24 5 214
GR-CON-Z16-1322 Plain Concrete 10-Jan-24 17-Jan-24 6 222
GR-CON-Z16-1323 Installation Curbstone 17-Jan-24 28-Jan-24 9 222
GR-CON-Z16-1324 Casting Concrete (Mortar haunch) 28-Jan-24 01-Feb-24 4 222
GR-CON-Z16-1325 Backfilling (sand / Sub base) 01-Feb-24 12-Feb-24 9 222
GR-CON-Z16-1326 Installation of Paving 12-Feb-24 27-Feb-24 13 222
Landscape Works 10-Jan-24 05-Sep-24 191 62
GR-CON-Z16-1327 Excavation (Tree Pit ) 10-Jan-24 16-Jan-24 5 214
GR-CON-Z16-1328 Aggregate Drainage layer 16-Jan-24 23-Jan-24 6 214
GR-CON-Z16-1329 Installation Geotextile 23-Jan-24 28-Jan-24 4 214
GR-CON-Z16-1330 Backfilling (Soil max for tree) 28-Jan-24 04-Feb-24 6 214
GR-CON-Z16-1331 Installation of Trees 15-Aug-24 19-Aug-24 3 62
GR-CON-Z16-8536 Installation of Shrubs 19-Aug-24 22-Aug-24 3 62
GR-CON-Z16-8546 Installation of Ground Covers 22-Aug-24 26-Aug-24 3 62
GR-CON-Z16-8556 Installation of Succulents 26-Aug-24 29-Aug-24 3 62
GR-CON-Z16-8566 Installation of Grass 29-Aug-24 02-Sep-24 3 62
GR-CON-Z16-1332 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 62
Site Furnishing 05-Sep-24 17-Sep-24 10 62
GR-CON-Z16-1343 Tree Grate 05-Sep-24 11-Sep-24 5 62
GR-CON-Z16-1344 Wheel stoppers 11-Sep-24 17-Sep-24 5 62
Irrigation Works 04-Jan-24 17-Sep-24 206 62
GR-CON-Z16-1335 Excavation Pipe Irrigation 04-Jan-24 10-Jan-24 5 151
GR-CON-Z16-1336 Sand Bedding 10-Jan-24 14-Jan-24 3 151
GR-CON-Z16-1337 HDPE Pipe Installations and fittings and conduit for cable 14-Jan-24 31-Jan-24 15 151
GR-CON-Z16-1339 Test pressure 31-Jan-24 06-Feb-24 5 151
GR-CON-Z16-1338 Installation of Valves and Accessories 06-Feb-24 11-Feb-24 4 151
GR-CON-Z16-1340 Back filling (sand / Subbase ) 11-Feb-24 18-Feb-24 6 151
GR-CON-Z16-1341 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Feb-24 25-Feb-24 6 216
GR-CON-Z16-1342 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Sep-24
system 17-Sep-24 8 62
Parking P-41 02-Jan-24 17-Sep-24 208 62
Site Preparation 02-Jan-24 09-Jan-24 6 251
GR-CON-Z16-1348 Backfilling 02-Jan-24 09-Jan-24 6 251
GR-CON-Z16-1346 Excavation And Disposal 03-Jan-24 09-Jan-24 5 147
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1345 Demolition (Asphalt.Paving,etc.....) 04-Jan-24 09-Jan-24 4 63


GR-CON-Z16-1347 Prepretion And Compaction 04-Jan-24 09-Jan-24 4 251
Curbstone and Paving 09-Jan-24 03-Mar-24 46 218
GR-CON-Z16-1349 Excavation Curbstone 09-Jan-24 15-Jan-24 5 210
GR-CON-Z16-1350 Plain Concrete 15-Jan-24 22-Jan-24 6 218
GR-CON-Z16-1351 Installation Curbstone 22-Jan-24 01-Feb-24 9 218
GR-CON-Z16-1352 Casting Concrete (Mortar haunch) 01-Feb-24 06-Feb-24 4 218
GR-CON-Z16-1353 Backfilling (sand / Sub base) 06-Feb-24 17-Feb-24 9 218
GR-CON-Z16-1354 Installation of Paving 17-Feb-24 03-Mar-24 13 218
Landscape Works 15-Jan-24 05-Sep-24 187 62
GR-CON-Z16-1355 Excavation (Tree Pit ) 15-Jan-24 21-Jan-24 5 210
GR-CON-Z16-1356 Aggregate Drainage layer 21-Jan-24 28-Jan-24 6 210
GR-CON-Z16-1357 Installation Geotextile 28-Jan-24 01-Feb-24 4 210
GR-CON-Z16-1358 Backfilling (Soil max for tree) 01-Feb-24 08-Feb-24 6 210
GR-CON-Z16-1359 Installation of Trees 15-Aug-24 19-Aug-24 3 62
GR-CON-Z16-8576 Installation of Shrubs 19-Aug-24 22-Aug-24 3 62
GR-CON-Z16-8586 Installation of Ground Covers 22-Aug-24 26-Aug-24 3 62
GR-CON-Z16-8596 Installation of Succulents 26-Aug-24 29-Aug-24 3 62
GR-CON-Z16-8606 Installation of Grass 29-Aug-24 02-Sep-24 3 62
GR-CON-Z16-1360 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 62
Site Furnishing 05-Sep-24 17-Sep-24 10 62
GR-CON-Z16-1371 Tree Grate 05-Sep-24 11-Sep-24 5 62
GR-CON-Z16-1372 Wheel stoppers 11-Sep-24 17-Sep-24 5 62
Irrigation Works 09-Jan-24 17-Sep-24 202 62
GR-CON-Z16-1363 Excavation Pipe Irrigation 09-Jan-24 15-Jan-24 5 147
GR-CON-Z16-1364 Sand Bedding 15-Jan-24 18-Jan-24 3 147
GR-CON-Z16-1365 HDPE Pipe Installations and fittings and conduit for cable 18-Jan-24 05-Feb-24 15 147
GR-CON-Z16-1367 Test pressure 05-Feb-24 11-Feb-24 5 147
GR-CON-Z16-1366 Installation of Valves and Accessories 11-Feb-24 15-Feb-24 4 147
GR-CON-Z16-1368 Back filling (sand / Subbase ) 15-Feb-24 22-Feb-24 6 147
GR-CON-Z16-1369 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 22-Feb-24 29-Feb-24 6 212
GR-CON-Z16-1370 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Sep-24
system 17-Sep-24 8 62
Parking P-06 11-Jan-24 17-Sep-24 200 62
Site Preparation 11-Jan-24 18-Jan-24 6 243
GR-CON-Z16-1376 Backfilling 11-Jan-24 18-Jan-24 6 243
GR-CON-Z16-1374 Excavation And Disposal 13-Jan-24 18-Jan-24 5 139
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1373 Demolition (Asphalt.Paving,etc.....) 14-Jan-24 18-Jan-24 4 59


GR-CON-Z16-1375 Prepretion And Compaction 14-Jan-24 18-Jan-24 4 243
Curbstone and Paving 18-Jan-24 12-Mar-24 46 210
GR-CON-Z16-1377 Excavation Curbstone 18-Jan-24 24-Jan-24 5 202
GR-CON-Z16-1378 Plain Concrete 24-Jan-24 31-Jan-24 6 210
GR-CON-Z16-1379 Installation Curbstone 31-Jan-24 11-Feb-24 9 210
GR-CON-Z16-1380 Casting Concrete (Mortar haunch) 11-Feb-24 15-Feb-24 4 210
GR-CON-Z16-1381 Backfilling (sand / Sub base) 15-Feb-24 26-Feb-24 9 210
GR-CON-Z16-1382 Installation of Paving 26-Feb-24 12-Mar-24 13 210
Landscape Works 24-Jan-24 05-Sep-24 179 62
GR-CON-Z16-1383 Excavation (Tree Pit ) 24-Jan-24 30-Jan-24 5 202
GR-CON-Z16-1384 Aggregate Drainage layer 30-Jan-24 06-Feb-24 6 202
GR-CON-Z16-1385 Installation Geotextile 06-Feb-24 11-Feb-24 4 202
GR-CON-Z16-1386 Backfilling (Soil max for tree) 11-Feb-24 18-Feb-24 6 202
GR-CON-Z16-1387 Installation of Trees 15-Aug-24 19-Aug-24 3 62
GR-CON-Z16-8616 Installation of Shrubs 19-Aug-24 22-Aug-24 3 62
GR-CON-Z16-8626 Installation of Ground Covers 22-Aug-24 26-Aug-24 3 62
GR-CON-Z16-8636 Installation of Succulents 26-Aug-24 29-Aug-24 3 62
GR-CON-Z16-8646 Installation of Grass 29-Aug-24 02-Sep-24 3 62
GR-CON-Z16-1388 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 62
Site Furnishing 05-Sep-24 17-Sep-24 10 62
GR-CON-Z16-1399 Tree Grate 05-Sep-24 11-Sep-24 5 62
GR-CON-Z16-1400 Wheel stoppers 11-Sep-24 17-Sep-24 5 62
Irrigation Works 18-Jan-24 17-Sep-24 194 62
GR-CON-Z16-1391 Excavation Pipe Irrigation 18-Jan-24 24-Jan-24 5 139
GR-CON-Z16-1392 Sand Bedding 24-Jan-24 28-Jan-24 3 139
GR-CON-Z16-1393 HDPE Pipe Installations and fittings and conduit for cable 28-Jan-24 14-Feb-24 15 139
GR-CON-Z16-1395 Test pressure 14-Feb-24 20-Feb-24 5 139
GR-CON-Z16-1394 Installation of Valves and Accessories 20-Feb-24 25-Feb-24 4 139
GR-CON-Z16-1396 Back filling (sand / Subbase ) 25-Feb-24 03-Mar-24 6 139
GR-CON-Z16-1397 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 03-Mar-24 10-Mar-24 6 204
GR-CON-Z16-1398 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Sep-24
system 17-Sep-24 8 62
Parking P-08 08-Feb-24 17-Sep-24 176 62
Site Preparation 08-Feb-24 15-Feb-24 6 219
GR-CON-Z16-1404 Backfilling 08-Feb-24 15-Feb-24 6 219
GR-CON-Z16-1402 Excavation And Disposal 10-Feb-24 15-Feb-24 5 115
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1401 Demolition (Asphalt.Paving,etc.....) 11-Feb-24 15-Feb-24 4 39


GR-CON-Z16-1403 Prepretion And Compaction 11-Feb-24 15-Feb-24 4 219
Curbstone and Paving 15-Feb-24 21-Apr-24 46 186
GR-CON-Z16-1405 Excavation Curbstone 15-Feb-24 21-Feb-24 5 178
GR-CON-Z16-1406 Plain Concrete 21-Feb-24 28-Feb-24 6 186
GR-CON-Z16-1407 Installation Curbstone 28-Feb-24 10-Mar-24 9 186
GR-CON-Z16-1408 Casting Concrete (Mortar haunch) 10-Mar-24 14-Mar-24 4 186
GR-CON-Z16-1409 Backfilling (sand / Sub base) 14-Mar-24 28-Mar-24 9 186
GR-CON-Z16-1410 Installation of Paving 28-Mar-24 21-Apr-24 13 186
Landscape Works 21-Feb-24 05-Sep-24 155 62
GR-CON-Z16-1411 Excavation (Tree Pit ) 21-Feb-24 27-Feb-24 5 178
GR-CON-Z16-1412 Aggregate Drainage layer 27-Feb-24 05-Mar-24 6 178
GR-CON-Z16-1413 Installation Geotextile 05-Mar-24 10-Mar-24 4 178
GR-CON-Z16-1414 Backfilling (Soil max for tree) 10-Mar-24 18-Mar-24 6 178
GR-CON-Z16-1415 Installation of Trees 15-Aug-24 19-Aug-24 3 62
GR-CON-Z16-8656 Installation of Shrubs 19-Aug-24 22-Aug-24 3 62
GR-CON-Z16-8666 Installation of Ground Covers 22-Aug-24 26-Aug-24 3 62
GR-CON-Z16-8676 Installation of Succulents 26-Aug-24 29-Aug-24 3 62
GR-CON-Z16-8686 Installation of Grass 29-Aug-24 02-Sep-24 3 62
GR-CON-Z16-1416 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 62
Site Furnishing 05-Sep-24 17-Sep-24 10 62
GR-CON-Z16-1427 Tree Grate 05-Sep-24 11-Sep-24 5 62
GR-CON-Z16-1428 Wheel stoppers 11-Sep-24 17-Sep-24 5 62
Irrigation Works 15-Feb-24 17-Sep-24 170 62
GR-CON-Z16-1419 Excavation Pipe Irrigation 15-Feb-24 21-Feb-24 5 115
GR-CON-Z16-1420 Sand Bedding 21-Feb-24 25-Feb-24 3 115
GR-CON-Z16-1421 HDPE Pipe Installations and fittings and conduit for cable 25-Feb-24 13-Mar-24 15 115
GR-CON-Z16-1423 Test pressure 13-Mar-24 20-Mar-24 5 115
GR-CON-Z16-1422 Installation of Valves and Accessories 21-Mar-24 27-Mar-24 4 115
GR-CON-Z16-1424 Back filling (sand / Subbase ) 27-Mar-24 06-Apr-24 6 115
GR-CON-Z16-1425 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 06-Apr-24 18-Apr-24 6 180
GR-CON-Z16-1426 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
08-Sep-24
system 17-Sep-24 8 62
Street SS-19.2 15-Feb-24 17-Nov-24 221 11
Site Preparation 15-Feb-24 27-Mar-24 32 200
GR-CON-Z16-1457 Demolition (Asphalt.Paving,etc.....) 15-Feb-24 22-Feb-24 6 39
GR-CON-Z16-1458 Excavation And Disposal 22-Feb-24 03-Mar-24 8 79
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1459 Prepretion And Compaction 03-Mar-24 13-Mar-24 9 200


GR-CON-Z16-1460 Backfilling 13-Mar-24 27-Mar-24 9 200
Curbstone and Paving 03-Mar-24 05-Jun-24 71 147
GR-CON-Z16-1461 Excavation Curbstone 03-Mar-24 12-Mar-24 8 99
GR-CON-Z16-1462 Plain Concrete 12-Mar-24 25-Mar-24 9 147
GR-CON-Z16-1463 Installation Curbstone 26-Mar-24 20-Apr-24 14 147
GR-CON-Z16-1464 Casting Concrete (Mortar haunch) 20-Apr-24 27-Apr-24 6 147
GR-CON-Z16-1465 Backfilling (sand / Sub base) 27-Apr-24 13-May-24 14 147
GR-CON-Z16-1466 Installation of Paving 13-May-24 05-Jun-24 20 147
Landscape Works 12-Mar-24 10-Oct-24 167 11
GR-CON-Z16-1467 Excavation (Tree Pit ) 12-Mar-24 24-Mar-24 8 99
GR-CON-Z16-1468 Aggregate Drainage layer 24-Mar-24 07-Apr-24 9 99
GR-CON-Z16-1469 Installation Geotextile 07-Apr-24 20-Apr-24 6 99
GR-CON-Z16-1470 Backfilling (Soil max for tree) 20-Apr-24 30-Apr-24 9 99
GR-CON-Z16-1471 Installation of Trees 15-Aug-24 20-Aug-24 4 11
GR-CON-Z16-13056 Installation of Shrubs 20-Aug-24 24-Aug-24 3 11
GR-CON-Z16-13066 Installation of Succulents 24-Aug-24 27-Aug-24 3 11
GR-CON-Z16-13076 Installation of Ground Covers 27-Aug-24 31-Aug-24 3 11
GR-CON-Z16-13086 Installation of Grass 31-Aug-24 03-Sep-24 3 11
GR-CON-Z16-1472 Backfilling (Mulch) 03-Sep-24 09-Sep-24 5 11
GR-CON-Z16-1473 Natural Boulders Installation 09-Sep-24 16-Sep-24 6 11
GR-CON-Z16-1474 Retaining walls . Steps, forming risers, treads and edges with finishes
16-Sep-24 10-Oct-24 20 11
Site Furnishing 10-Oct-24 17-Nov-24 32 11
GR-CON-Z16-1483 Garden planter box 10-Oct-24 20-Oct-24 8 11
GR-CON-Z16-1484 Wheel stoppers 20-Oct-24 29-Oct-24 8 11
GR-CON-Z16-1485 Steel Lattice 29-Oct-24 07-Nov-24 8 11
GR-CON-Z16-1486 Handrail 07-Nov-24 17-Nov-24 8 11
Storm Piping Works 06-Nov-24 17-Nov-24 9 11
GR-CON-Z16-1487 Installation of DI grating covers 06-Nov-24 17-Nov-24 9 11
Irrigation Works 03-Mar-24 17-Jun-24 81 128
GR-CON-Z16-1475 Excavation Pipe Irrigation 03-Mar-24 12-Mar-24 8 79
GR-CON-Z16-1476 Sand Bedding 12-Mar-24 20-Mar-24 6 79
GR-CON-Z16-1477 HDPE Pipe Installations and fittings and conduit for cable 21-Mar-24 27-Apr-24 23 79
GR-CON-Z16-1479 Test pressure 27-Apr-24 06-May-24 8 79
GR-CON-Z16-1478 Installation of Valves and Accessories 06-May-24 13-May-24 6 79
GR-CON-Z16-1480 Back filling (sand / Subbase ) 13-May-24 23-May-24 9 79
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1481 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-May-24 03-Jun-24 9 128
GR-CON-Z16-1482 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
03-Jun-24
system 17-Jun-24 12 128
Electrical Works 12-Mar-24 17-Nov-24 199 11
GR-CON-Z16-1488 Excavation And Disposal 12-Mar-24 24-Mar-24 8 168
GR-CON-Z16-1489 Sand Bedding 24-Mar-24 02-Apr-24 6 168
GR-CON-Z16-1490 laying cables 02-Apr-24 11-Apr-24 6 168
GR-CON-Z16-1491 Backfilling (sand / Sub base) 11-Apr-24 25-Apr-24 8 168
GR-CON-Z16-1492 Control Panel / Distribution Panel Installation 25-Apr-24 02-May-24 6 168
GR-CON-Z16-1493 Road Crossing Ducts 07-Nov-24 17-Nov-24 8 11
Street SS-28 22-Feb-24 20-Oct-24 191 35
Site Preparation 22-Feb-24 19-Mar-24 21 205
GR-CON-Z16-1494 Demolition (Asphalt.Paving,etc.....) 22-Feb-24 27-Feb-24 4 39
GR-CON-Z16-1495 Excavation And Disposal 27-Feb-24 04-Mar-24 5 99
GR-CON-Z16-1496 Prepretion And Compaction 04-Mar-24 11-Mar-24 6 205
GR-CON-Z16-1497 Backfilling 11-Mar-24 19-Mar-24 6 205
Curbstone and Paving 04-Mar-24 08-May-24 46 171
GR-CON-Z16-1498 Excavation Curbstone 04-Mar-24 10-Mar-24 5 136
GR-CON-Z16-1499 Plain Concrete 10-Mar-24 18-Mar-24 6 171
GR-CON-Z16-1500 Installation Curbstone 18-Mar-24 01-Apr-24 9 171
GR-CON-Z16-1501 Casting Concrete (Mortar haunch) 01-Apr-24 07-Apr-24 4 171
GR-CON-Z16-1502 Backfilling (sand / Sub base) 07-Apr-24 23-Apr-24 9 171
GR-CON-Z16-1503 Installation of Paving 23-Apr-24 08-May-24 13 171
Landscape Works 10-Mar-24 26-Sep-24 157 35
GR-CON-Z16-1504 Excavation (Tree Pit ) 10-Mar-24 16-Mar-24 5 136
GR-CON-Z16-1505 Aggregate Drainage layer 17-Mar-24 25-Mar-24 6 136
GR-CON-Z16-1506 Installation Geotextile 26-Mar-24 01-Apr-24 4 136
GR-CON-Z16-1507 Backfilling (Soil max for tree) 01-Apr-24 10-Apr-24 6 136
GR-CON-Z16-1508 Installation of Trees 15-Aug-24 19-Aug-24 3 35
GR-CON-Z16-13096 Installation of Shrubs 19-Aug-24 22-Aug-24 3 35
GR-CON-Z16-13106 Installation of Succulents 22-Aug-24 26-Aug-24 3 35
GR-CON-Z16-13116 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 35
GR-CON-Z16-13126 Installation of Grass 29-Aug-24 02-Sep-24 3 35
GR-CON-Z16-1509 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 35
GR-CON-Z16-1510 Natural Boulders Installation 05-Sep-24 10-Sep-24 4 35
GR-CON-Z16-1511 Retaining walls . Steps, forming risers, treads and edges with finishes
10-Sep-24 26-Sep-24 13 35
Site Furnishing 26-Sep-24 20-Oct-24 20 35
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1520 Garden planter box 26-Sep-24 02-Oct-24 5 35


GR-CON-Z16-1521 Wheel stoppers 02-Oct-24 08-Oct-24 5 35
GR-CON-Z16-1522 Steel Lattice 08-Oct-24 14-Oct-24 5 35
GR-CON-Z16-1523 Handrail 14-Oct-24 20-Oct-24 5 35
Storm Piping Works 13-Oct-24 20-Oct-24 6 35
GR-CON-Z16-1524 Installation of DI grating covers 13-Oct-24 20-Oct-24 6 35
Irrigation Works 04-Mar-24 16-May-24 53 158
GR-CON-Z16-1512 Excavation Pipe Irrigation 04-Mar-24 10-Mar-24 5 99
GR-CON-Z16-1513 Sand Bedding 10-Mar-24 14-Mar-24 4 99
GR-CON-Z16-1514 HDPE Pipe Installations and fittings and conduit for cable 14-Mar-24 07-Apr-24 15 99
GR-CON-Z16-1516 Test pressure 07-Apr-24 18-Apr-24 5 99
GR-CON-Z16-1515 Installation of Valves and Accessories 18-Apr-24 23-Apr-24 4 99
GR-CON-Z16-1517 Back filling (sand / Subbase ) 23-Apr-24 30-Apr-24 6 99
GR-CON-Z16-1518 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Apr-24 07-May-24 6 158
GR-CON-Z16-1519 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-May-24
system 16-May-24 8 158
Electrical Works 10-Mar-24 20-Oct-24 177 35
GR-CON-Z16-1525 Excavation And Disposal 10-Mar-24 16-Mar-24 5 185
GR-CON-Z16-1526 Sand Bedding 17-Mar-24 23-Mar-24 4 185
GR-CON-Z16-1527 laying cables 23-Mar-24 28-Mar-24 4 185
GR-CON-Z16-1528 Backfilling (sand / Sub base) 28-Mar-24 06-Apr-24 5 185
GR-CON-Z16-1529 Control Panel / Distribution Panel Installation 06-Apr-24 11-Apr-24 4 185
GR-CON-Z16-1530 Road Crossing Ducts 14-Oct-24 20-Oct-24 5 35
Street SS-30 27-Feb-24 20-Oct-24 187 35
Site Preparation 27-Feb-24 25-Mar-24 21 201
GR-CON-Z16-1531 Demolition (Asphalt.Paving,etc.....) 27-Feb-24 03-Mar-24 4 39
GR-CON-Z16-1532 Excavation And Disposal 03-Mar-24 09-Mar-24 5 95
GR-CON-Z16-1533 Prepretion And Compaction 09-Mar-24 16-Mar-24 6 201
GR-CON-Z16-1534 Backfilling 17-Mar-24 25-Mar-24 6 201
Curbstone and Paving 09-Mar-24 13-May-24 46 167
GR-CON-Z16-1535 Excavation Curbstone 09-Mar-24 14-Mar-24 5 132
GR-CON-Z16-1536 Plain Concrete 14-Mar-24 24-Mar-24 6 167
GR-CON-Z16-1537 Installation Curbstone 24-Mar-24 07-Apr-24 9 167
GR-CON-Z16-1538 Casting Concrete (Mortar haunch) 07-Apr-24 17-Apr-24 4 167
GR-CON-Z16-1539 Backfilling (sand / Sub base) 17-Apr-24 28-Apr-24 9 167
GR-CON-Z16-1540 Installation of Paving 28-Apr-24 13-May-24 13 167
Landscape Works 14-Mar-24 26-Sep-24 153 35
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1541 Excavation (Tree Pit ) 14-Mar-24 23-Mar-24 5 132


GR-CON-Z16-1542 Aggregate Drainage layer 23-Mar-24 01-Apr-24 6 132
GR-CON-Z16-1543 Installation Geotextile 01-Apr-24 07-Apr-24 4 132
GR-CON-Z16-1544 Backfilling (Soil max for tree) 07-Apr-24 20-Apr-24 6 132
GR-CON-Z16-1545 Installation of Trees 15-Aug-24 19-Aug-24 3 35
GR-CON-Z16-13136 Installation of Shrubs 19-Aug-24 22-Aug-24 3 35
GR-CON-Z16-13146 Installation of Succulents 22-Aug-24 26-Aug-24 3 35
GR-CON-Z16-13156 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 35
GR-CON-Z16-13166 Installation of Grass 29-Aug-24 02-Sep-24 3 35
GR-CON-Z16-1546 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 35
GR-CON-Z16-1547 Natural Boulders Installation 05-Sep-24 10-Sep-24 4 35
GR-CON-Z16-1548 Retaining walls . Steps, forming risers, treads and edges with finishes
10-Sep-24 26-Sep-24 13 35
Site Furnishing 26-Sep-24 20-Oct-24 20 35
GR-CON-Z16-1557 Garden planter box 26-Sep-24 02-Oct-24 5 35
GR-CON-Z16-1558 Wheel stoppers 02-Oct-24 08-Oct-24 5 35
GR-CON-Z16-1559 Steel Lattice 08-Oct-24 14-Oct-24 5 35
GR-CON-Z16-1560 Handrail 14-Oct-24 20-Oct-24 5 35
Storm Piping Works 13-Oct-24 20-Oct-24 6 35
GR-CON-Z16-1561 Installation of DI grating covers 13-Oct-24 20-Oct-24 6 35
Irrigation Works 09-Mar-24 21-May-24 53 154
GR-CON-Z16-1549 Excavation Pipe Irrigation 09-Mar-24 14-Mar-24 5 95
GR-CON-Z16-1550 Sand Bedding 14-Mar-24 20-Mar-24 4 95
GR-CON-Z16-1551 HDPE Pipe Installations and fittings and conduit for cable 21-Mar-24 17-Apr-24 15 95
GR-CON-Z16-1553 Test pressure 17-Apr-24 23-Apr-24 5 95
GR-CON-Z16-1552 Installation of Valves and Accessories 23-Apr-24 28-Apr-24 4 95
GR-CON-Z16-1554 Back filling (sand / Subbase ) 28-Apr-24 05-May-24 6 95
GR-CON-Z16-1555 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-May-24 12-May-24 6 154
GR-CON-Z16-1556 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-May-24
system 21-May-24 8 154
Electrical Works 14-Mar-24 20-Oct-24 173 35
GR-CON-Z16-1562 Excavation And Disposal 14-Mar-24 23-Mar-24 5 181
GR-CON-Z16-1563 Sand Bedding 23-Mar-24 28-Mar-24 4 181
GR-CON-Z16-1564 laying cables 28-Mar-24 03-Apr-24 4 181
GR-CON-Z16-1565 Backfilling (sand / Sub base) 04-Apr-24 11-Apr-24 5 181
GR-CON-Z16-1566 Control Panel / Distribution Panel Installation 11-Apr-24 21-Apr-24 4 181
GR-CON-Z16-1567 Road Crossing Ducts 14-Oct-24 20-Oct-24 5 35
Street SS-63 03-Mar-24 20-Oct-24 183 35
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 03-Mar-24 01-Apr-24 21 197


GR-CON-Z16-1568 Demolition (Asphalt.Paving,etc.....) 03-Mar-24 07-Mar-24 4 39
GR-CON-Z16-1569 Excavation And Disposal 07-Mar-24 13-Mar-24 5 91
GR-CON-Z16-1570 Prepretion And Compaction 13-Mar-24 23-Mar-24 6 197
GR-CON-Z16-1571 Backfilling 23-Mar-24 01-Apr-24 6 197
Curbstone and Paving 13-Mar-24 18-May-24 46 163
GR-CON-Z16-1572 Excavation Curbstone 13-Mar-24 20-Mar-24 5 128
GR-CON-Z16-1573 Plain Concrete 21-Mar-24 30-Mar-24 6 163
GR-CON-Z16-1574 Installation Curbstone 31-Mar-24 17-Apr-24 9 163
GR-CON-Z16-1575 Casting Concrete (Mortar haunch) 17-Apr-24 22-Apr-24 4 163
GR-CON-Z16-1576 Backfilling (sand / Sub base) 22-Apr-24 02-May-24 9 163
GR-CON-Z16-1577 Installation of Paving 02-May-24 18-May-24 13 163
Landscape Works 21-Mar-24 26-Sep-24 149 35
GR-CON-Z16-1578 Excavation (Tree Pit ) 21-Mar-24 28-Mar-24 5 128
GR-CON-Z16-1579 Aggregate Drainage layer 28-Mar-24 07-Apr-24 6 128
GR-CON-Z16-1580 Installation Geotextile 07-Apr-24 17-Apr-24 4 128
GR-CON-Z16-1581 Backfilling (Soil max for tree) 17-Apr-24 24-Apr-24 6 128
GR-CON-Z16-1582 Installation of Trees 15-Aug-24 19-Aug-24 3 35
GR-CON-Z16-13176 Installation of Shrubs 19-Aug-24 22-Aug-24 3 35
GR-CON-Z16-13186 Installation of Succulents 22-Aug-24 26-Aug-24 3 35
GR-CON-Z16-13196 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 35
GR-CON-Z16-13206 Installation of Grass 29-Aug-24 02-Sep-24 3 35
GR-CON-Z16-1583 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 35
GR-CON-Z16-1584 Natural Boulders Installation 05-Sep-24 10-Sep-24 4 35
GR-CON-Z16-1585 Retaining walls . Steps, forming risers, treads and edges with finishes
10-Sep-24 26-Sep-24 13 35
Site Furnishing 26-Sep-24 20-Oct-24 20 35
GR-CON-Z16-1594 Garden planter box 26-Sep-24 02-Oct-24 5 35
GR-CON-Z16-1595 Wheel stoppers 02-Oct-24 08-Oct-24 5 35
GR-CON-Z16-1596 Steel Lattice 08-Oct-24 14-Oct-24 5 35
GR-CON-Z16-1597 Handrail 14-Oct-24 20-Oct-24 5 35
Storm Piping Works 13-Oct-24 20-Oct-24 6 35
GR-CON-Z16-1598 Installation of DI grating covers 13-Oct-24 20-Oct-24 6 35
Irrigation Works 13-Mar-24 26-May-24 53 150
GR-CON-Z16-1586 Excavation Pipe Irrigation 13-Mar-24 20-Mar-24 5 91
GR-CON-Z16-1587 Sand Bedding 21-Mar-24 27-Mar-24 4 91
GR-CON-Z16-1588 HDPE Pipe Installations and fittings and conduit for cable 27-Mar-24 22-Apr-24 15 91
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1590 Test pressure 22-Apr-24 28-Apr-24 5 91


GR-CON-Z16-1589 Installation of Valves and Accessories 28-Apr-24 02-May-24 4 91
GR-CON-Z16-1591 Back filling (sand / Subbase ) 02-May-24 09-May-24 6 91
GR-CON-Z16-1592 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-May-24 16-May-24 6 150
GR-CON-Z16-1593 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
16-May-24
system 26-May-24 8 150
Electrical Works 21-Mar-24 20-Oct-24 169 35
GR-CON-Z16-1599 Excavation And Disposal 21-Mar-24 28-Mar-24 5 177
GR-CON-Z16-1600 Sand Bedding 28-Mar-24 03-Apr-24 4 177
GR-CON-Z16-1601 laying cables 04-Apr-24 10-Apr-24 4 177
GR-CON-Z16-1602 Backfilling (sand / Sub base) 10-Apr-24 21-Apr-24 5 177
GR-CON-Z16-1603 Control Panel / Distribution Panel Installation 21-Apr-24 25-Apr-24 4 177
GR-CON-Z16-1604 Road Crossing Ducts 14-Oct-24 20-Oct-24 5 35
Street SS-65 02-Apr-24 20-Oct-24 161 35
Site Preparation 02-Apr-24 04-May-24 21 175
GR-CON-Z16-1605 Demolition (Asphalt.Paving,etc.....) 02-Apr-24 08-Apr-24 4 21
GR-CON-Z16-1606 Excavation And Disposal 09-Apr-24 20-Apr-24 5 69
GR-CON-Z16-1607 Prepretion And Compaction 20-Apr-24 27-Apr-24 6 175
GR-CON-Z16-1608 Backfilling 27-Apr-24 04-May-24 6 175
Curbstone and Paving 20-Apr-24 12-Jun-24 46 141
GR-CON-Z16-1609 Excavation Curbstone 20-Apr-24 25-Apr-24 5 106
GR-CON-Z16-1610 Plain Concrete 25-Apr-24 02-May-24 6 141
GR-CON-Z16-1611 Installation Curbstone 02-May-24 13-May-24 9 141
GR-CON-Z16-1612 Casting Concrete (Mortar haunch) 13-May-24 18-May-24 4 141
GR-CON-Z16-1613 Backfilling (sand / Sub base) 18-May-24 28-May-24 9 141
GR-CON-Z16-1614 Installation of Paving 28-May-24 12-Jun-24 13 141
Landscape Works 25-Apr-24 26-Sep-24 127 35
GR-CON-Z16-1615 Excavation (Tree Pit ) 25-Apr-24 01-May-24 5 106
GR-CON-Z16-1616 Aggregate Drainage layer 01-May-24 08-May-24 6 106
GR-CON-Z16-1617 Installation Geotextile 08-May-24 13-May-24 4 106
GR-CON-Z16-1618 Backfilling (Soil max for tree) 13-May-24 20-May-24 6 106
GR-CON-Z16-1619 Installation of Trees 15-Aug-24 19-Aug-24 3 35
GR-CON-Z16-13216 Installation of Shrubs 19-Aug-24 22-Aug-24 3 35
GR-CON-Z16-13226 Installation of Succulents 22-Aug-24 26-Aug-24 3 35
GR-CON-Z16-13236 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 35
GR-CON-Z16-13246 Installation of Grass 29-Aug-24 02-Sep-24 3 35
GR-CON-Z16-1620 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 35
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1621 Natural Boulders Installation 05-Sep-24 10-Sep-24 4 35


GR-CON-Z16-1622 Retaining walls . Steps, forming risers, treads and edges with finishes
10-Sep-24 26-Sep-24 13 35
Site Furnishing 26-Sep-24 20-Oct-24 20 35
GR-CON-Z16-1631 Garden planter box 26-Sep-24 02-Oct-24 5 35
GR-CON-Z16-1632 Wheel stoppers 02-Oct-24 08-Oct-24 5 35
GR-CON-Z16-1633 Steel Lattice 08-Oct-24 14-Oct-24 5 35
GR-CON-Z16-1634 Handrail 14-Oct-24 20-Oct-24 5 35
Storm Piping Works 13-Oct-24 20-Oct-24 6 35
GR-CON-Z16-1635 Installation of DI grating covers 13-Oct-24 20-Oct-24 6 35
Irrigation Works 20-Apr-24 25-Jun-24 53 128
GR-CON-Z16-1623 Excavation Pipe Irrigation 20-Apr-24 25-Apr-24 5 69
GR-CON-Z16-1624 Sand Bedding 25-Apr-24 30-Apr-24 4 69
GR-CON-Z16-1625 HDPE Pipe Installations and fittings and conduit for cable 30-Apr-24 18-May-24 15 69
GR-CON-Z16-1627 Test pressure 18-May-24 23-May-24 5 69
GR-CON-Z16-1626 Installation of Valves and Accessories 23-May-24 28-May-24 4 69
GR-CON-Z16-1628 Back filling (sand / Subbase ) 28-May-24 04-Jun-24 6 69
GR-CON-Z16-1629 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Jun-24 11-Jun-24 6 128
GR-CON-Z16-1630 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
11-Jun-24
system 25-Jun-24 8 128
Electrical Works 25-Apr-24 20-Oct-24 147 35
GR-CON-Z16-1636 Excavation And Disposal 25-Apr-24 01-May-24 5 155
GR-CON-Z16-1637 Sand Bedding 01-May-24 06-May-24 4 155
GR-CON-Z16-1638 laying cables 06-May-24 11-May-24 4 155
GR-CON-Z16-1639 Backfilling (sand / Sub base) 11-May-24 16-May-24 5 155
GR-CON-Z16-1640 Control Panel / Distribution Panel Installation 16-May-24 21-May-24 4 155
GR-CON-Z16-1641 Road Crossing Ducts 14-Oct-24 20-Oct-24 5 35
Street SS-66 09-Apr-24 20-Oct-24 157 35
Site Preparation 09-Apr-24 08-May-24 21 171
GR-CON-Z16-1642 Demolition (Asphalt.Paving,etc.....) 09-Apr-24 18-Apr-24 4 21
GR-CON-Z16-1643 Excavation And Disposal 18-Apr-24 24-Apr-24 5 65
GR-CON-Z16-1644 Prepretion And Compaction 24-Apr-24 01-May-24 6 171
GR-CON-Z16-1645 Backfilling 01-May-24 08-May-24 6 171
Curbstone and Paving 24-Apr-24 17-Jun-24 46 137
GR-CON-Z16-1646 Excavation Curbstone 24-Apr-24 30-Apr-24 5 102
GR-CON-Z16-1647 Plain Concrete 30-Apr-24 07-May-24 6 137
GR-CON-Z16-1648 Installation Curbstone 07-May-24 18-May-24 9 137
GR-CON-Z16-1649 Casting Concrete (Mortar haunch) 18-May-24 22-May-24 4 137
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1650 Backfilling (sand / Sub base) 22-May-24 02-Jun-24 9 137


GR-CON-Z16-1651 Installation of Paving 02-Jun-24 17-Jun-24 13 137
Landscape Works 30-Apr-24 26-Sep-24 123 35
GR-CON-Z16-1652 Excavation (Tree Pit ) 30-Apr-24 06-May-24 5 102
GR-CON-Z16-1653 Aggregate Drainage layer 06-May-24 13-May-24 6 102
GR-CON-Z16-1654 Installation Geotextile 13-May-24 18-May-24 4 102
GR-CON-Z16-1655 Backfilling (Soil max for tree) 18-May-24 25-May-24 6 102
GR-CON-Z16-1656 Installation of Trees 15-Aug-24 19-Aug-24 3 35
GR-CON-Z16-13256 Installation of Shrubs 19-Aug-24 22-Aug-24 3 35
GR-CON-Z16-13266 Installation of Succulents 22-Aug-24 26-Aug-24 3 35
GR-CON-Z16-13276 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 35
GR-CON-Z16-13286 Installation of Grass 29-Aug-24 02-Sep-24 3 35
GR-CON-Z16-1657 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 35
GR-CON-Z16-1658 Natural Boulders Installation 05-Sep-24 10-Sep-24 4 35
GR-CON-Z16-1659 Retaining walls . Steps, forming risers, treads and edges with finishes
10-Sep-24 26-Sep-24 13 35
Site Furnishing 26-Sep-24 20-Oct-24 20 35
GR-CON-Z16-1668 Garden planter box 26-Sep-24 02-Oct-24 5 35
GR-CON-Z16-1669 Wheel stoppers 02-Oct-24 08-Oct-24 5 35
GR-CON-Z16-1670 Steel Lattice 08-Oct-24 14-Oct-24 5 35
GR-CON-Z16-1671 Handrail 14-Oct-24 20-Oct-24 5 35
Storm Piping Works 13-Oct-24 20-Oct-24 6 35
GR-CON-Z16-1672 Installation of DI grating covers 13-Oct-24 20-Oct-24 6 35
Irrigation Works 24-Apr-24 30-Jun-24 53 124
GR-CON-Z16-1660 Excavation Pipe Irrigation 24-Apr-24 30-Apr-24 5 65
GR-CON-Z16-1661 Sand Bedding 30-Apr-24 05-May-24 4 65
GR-CON-Z16-1662 HDPE Pipe Installations and fittings and conduit for cable 05-May-24 22-May-24 15 65
GR-CON-Z16-1664 Test pressure 22-May-24 28-May-24 5 65
GR-CON-Z16-1663 Installation of Valves and Accessories 28-May-24 02-Jun-24 4 65
GR-CON-Z16-1665 Back filling (sand / Subbase ) 02-Jun-24 09-Jun-24 6 65
GR-CON-Z16-1666 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Jun-24 16-Jun-24 6 124
GR-CON-Z16-1667 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
16-Jun-24
system 30-Jun-24 8 124
Electrical Works 30-Apr-24 20-Oct-24 143 35
GR-CON-Z16-1673 Excavation And Disposal 30-Apr-24 06-May-24 5 151
GR-CON-Z16-1674 Sand Bedding 06-May-24 11-May-24 4 151
GR-CON-Z16-1675 laying cables 11-May-24 15-May-24 4 151
GR-CON-Z16-1676 Backfilling (sand / Sub base) 15-May-24 21-May-24 5 151
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1677 Control Panel / Distribution Panel Installation 21-May-24 26-May-24 4 151


GR-CON-Z16-1678 Road Crossing Ducts 14-Oct-24 20-Oct-24 5 35
Street SS-67 18-Apr-24 20-Oct-24 153 35
Site Preparation 18-Apr-24 13-May-24 21 167
GR-CON-Z16-1679 Demolition (Asphalt.Paving,etc.....) 18-Apr-24 23-Apr-24 4 21
GR-CON-Z16-1680 Excavation And Disposal 23-Apr-24 29-Apr-24 5 61
GR-CON-Z16-1681 Prepretion And Compaction 29-Apr-24 06-May-24 6 167
GR-CON-Z16-1682 Backfilling 06-May-24 13-May-24 6 167
Curbstone and Paving 29-Apr-24 26-Jun-24 46 133
GR-CON-Z16-1683 Excavation Curbstone 29-Apr-24 05-May-24 5 98
GR-CON-Z16-1684 Plain Concrete 05-May-24 12-May-24 6 133
GR-CON-Z16-1685 Installation Curbstone 12-May-24 22-May-24 9 133
GR-CON-Z16-1686 Casting Concrete (Mortar haunch) 22-May-24 27-May-24 4 133
GR-CON-Z16-1687 Backfilling (sand / Sub base) 27-May-24 06-Jun-24 9 133
GR-CON-Z16-1000 Installation of Paving 06-Jun-24 26-Jun-24 13 133
Landscape Works 05-May-24 26-Sep-24 119 35
GR-CON-Z16-1001 Excavation (Tree Pit ) 05-May-24 11-May-24 5 98
GR-CON-Z16-1002 Aggregate Drainage layer 11-May-24 18-May-24 6 98
GR-CON-Z16-1003 Installation Geotextile 18-May-24 22-May-24 4 98
GR-CON-Z16-1004 Backfilling (Soil max for tree) 22-May-24 29-May-24 6 98
GR-CON-Z16-1005 Installation of Trees 15-Aug-24 19-Aug-24 3 35
GR-CON-Z16-13296 Installation of Shrubs 19-Aug-24 22-Aug-24 3 35
GR-CON-Z16-13306 Installation of Succulents 22-Aug-24 26-Aug-24 3 35
GR-CON-Z16-13316 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 35
GR-CON-Z16-13326 Installation of Grass 29-Aug-24 02-Sep-24 3 35
GR-CON-Z16-1006 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 35
GR-CON-Z16-1007 Natural Boulders Installation 05-Sep-24 10-Sep-24 4 35
GR-CON-Z16-1008 Retaining walls . Steps, forming risers, treads and edges with finishes
10-Sep-24 26-Sep-24 13 35
Site Furnishing 26-Sep-24 20-Oct-24 20 35
GR-CON-Z16-1017 Garden planter box 26-Sep-24 02-Oct-24 5 35
GR-CON-Z16-1018 Wheel stoppers 02-Oct-24 08-Oct-24 5 35
GR-CON-Z16-1019 Steel Lattice 08-Oct-24 14-Oct-24 5 35
GR-CON-Z16-1020 Handrail 14-Oct-24 20-Oct-24 5 35
Storm Piping Works 13-Oct-24 20-Oct-24 6 35
GR-CON-Z16-1021 Installation of DI grating covers 13-Oct-24 20-Oct-24 6 35
Irrigation Works 29-Apr-24 04-Jul-24 53 120
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1009 Excavation Pipe Irrigation 29-Apr-24 05-May-24 5 61


GR-CON-Z16-1010 Sand Bedding 05-May-24 09-May-24 4 61
GR-CON-Z16-1011 HDPE Pipe Installations and fittings and conduit for cable 09-May-24 27-May-24 15 61
GR-CON-Z16-1013 Test pressure 27-May-24 02-Jun-24 5 61
GR-CON-Z16-1012 Installation of Valves and Accessories 02-Jun-24 06-Jun-24 4 61
GR-CON-Z16-1014 Back filling (sand / Subbase ) 06-Jun-24 13-Jun-24 6 61
GR-CON-Z16-1015 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Jun-24 25-Jun-24 6 120
GR-CON-Z16-1016 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jun-24
system 04-Jul-24 8 120
Electrical Works 05-May-24 20-Oct-24 139 35
GR-CON-Z16-1022 Excavation And Disposal 05-May-24 11-May-24 5 147
GR-CON-Z16-1023 Sand Bedding 11-May-24 15-May-24 4 147
GR-CON-Z16-1024 laying cables 15-May-24 20-May-24 4 147
GR-CON-Z16-1025 Backfilling (sand / Sub base) 20-May-24 26-May-24 5 147
GR-CON-Z16-1026 Control Panel / Distribution Panel Installation 26-May-24 30-May-24 4 147
GR-CON-Z16-1027 Road Crossing Ducts 14-Oct-24 20-Oct-24 5 35
Street SS-68 23-Apr-24 20-Oct-24 149 35
Site Preparation 23-Apr-24 18-May-24 21 163
GR-CON-Z16-1028 Demolition (Asphalt.Paving,etc.....) 23-Apr-24 28-Apr-24 4 21
GR-CON-Z16-1029 Excavation And Disposal 28-Apr-24 04-May-24 5 57
GR-CON-Z16-1030 Prepretion And Compaction 04-May-24 11-May-24 6 163
GR-CON-Z16-1031 Backfilling 11-May-24 18-May-24 6 163
Curbstone and Paving 04-May-24 01-Jul-24 46 129
GR-CON-Z16-1032 Excavation Curbstone 04-May-24 09-May-24 5 94
GR-CON-Z16-1033 Plain Concrete 09-May-24 16-May-24 6 129
GR-CON-Z16-1034 Installation Curbstone 16-May-24 27-May-24 9 129
GR-CON-Z16-1035 Casting Concrete (Mortar haunch) 27-May-24 01-Jun-24 4 129
GR-CON-Z16-1036 Backfilling (sand / Sub base) 01-Jun-24 11-Jun-24 9 129
GR-CON-Z16-1037 Installation of Paving 11-Jun-24 01-Jul-24 13 129
Landscape Works 09-May-24 26-Sep-24 115 35
GR-CON-Z16-1038 Excavation (Tree Pit ) 09-May-24 15-May-24 5 94
GR-CON-Z16-1039 Aggregate Drainage layer 15-May-24 22-May-24 6 94
GR-CON-Z16-1040 Installation Geotextile 22-May-24 27-May-24 4 94
GR-CON-Z16-1041 Backfilling (Soil max for tree) 27-May-24 03-Jun-24 6 94
GR-CON-Z16-1042 Installation of Trees 15-Aug-24 19-Aug-24 3 35
GR-CON-Z16-13336 Installation of Shrubs 19-Aug-24 22-Aug-24 3 35
GR-CON-Z16-13346 Installation of Succulents 22-Aug-24 26-Aug-24 3 35
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-13356 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 35


GR-CON-Z16-13366 Installation of Grass 29-Aug-24 02-Sep-24 3 35
GR-CON-Z16-1043 Backfilling (Mulch) 02-Sep-24 05-Sep-24 3 35
GR-CON-Z16-1044 Natural Boulders Installation 05-Sep-24 10-Sep-24 4 35
GR-CON-Z16-1045 Retaining walls . Steps, forming risers, treads and edges with finishes
10-Sep-24 26-Sep-24 13 35
Site Furnishing 26-Sep-24 20-Oct-24 20 35
GR-CON-Z16-1054 Garden planter box 26-Sep-24 02-Oct-24 5 35
GR-CON-Z16-1055 Wheel stoppers 02-Oct-24 08-Oct-24 5 35
GR-CON-Z16-1056 Steel Lattice 08-Oct-24 14-Oct-24 5 35
GR-CON-Z16-1057 Handrail 14-Oct-24 20-Oct-24 5 35
Storm Piping Works 13-Oct-24 20-Oct-24 6 35
GR-CON-Z16-1058 Installation of DI grating covers 13-Oct-24 20-Oct-24 6 35
Irrigation Works 04-May-24 09-Jul-24 53 116
GR-CON-Z16-1046 Excavation Pipe Irrigation 04-May-24 09-May-24 5 57
GR-CON-Z16-1047 Sand Bedding 09-May-24 14-May-24 4 57
GR-CON-Z16-1048 HDPE Pipe Installations and fittings and conduit for cable 14-May-24 01-Jun-24 15 57
GR-CON-Z16-1050 Test pressure 01-Jun-24 06-Jun-24 5 57
GR-CON-Z16-1049 Installation of Valves and Accessories 06-Jun-24 11-Jun-24 4 57
GR-CON-Z16-1051 Back filling (sand / Subbase ) 11-Jun-24 18-Jun-24 6 57
GR-CON-Z16-1052 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 18-Jun-24 30-Jun-24 6 116
GR-CON-Z16-1053 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
30-Jun-24
system 09-Jul-24 8 116
Electrical Works 09-May-24 20-Oct-24 135 35
GR-CON-Z16-1059 Excavation And Disposal 09-May-24 15-May-24 5 143
GR-CON-Z16-1060 Sand Bedding 15-May-24 20-May-24 4 143
GR-CON-Z16-1061 laying cables 20-May-24 25-May-24 4 143
GR-CON-Z16-1062 Backfilling (sand / Sub base) 25-May-24 30-May-24 5 143
GR-CON-Z16-1063 Control Panel / Distribution Panel Installation 30-May-24 04-Jun-24 4 143
GR-CON-Z16-1064 Road Crossing Ducts 14-Oct-24 20-Oct-24 5 35
Street SS-09 28-Apr-24 17-Nov-24 169 11
Site Preparation 28-Apr-24 04-Jun-24 32 148
GR-CON-Z16-1065 Demolition (Asphalt.Paving,etc.....) 28-Apr-24 05-May-24 6 21
GR-CON-Z16-1066 Excavation And Disposal 05-May-24 14-May-24 8 27
GR-CON-Z16-1067 Prepretion And Compaction 14-May-24 25-May-24 9 148
GR-CON-Z16-1068 Backfilling 25-May-24 04-Jun-24 9 148
Curbstone and Paving 14-May-24 10-Aug-24 71 95
GR-CON-Z16-1069 Excavation Curbstone 14-May-24 23-May-24 8 47
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1070 Plain Concrete 23-May-24 03-Jun-24 9 95


GR-CON-Z16-1071 Installation Curbstone 03-Jun-24 24-Jun-24 14 95
GR-CON-Z16-1072 Casting Concrete (Mortar haunch) 24-Jun-24 01-Jul-24 6 95
GR-CON-Z16-1073 Backfilling (sand / Sub base) 01-Jul-24 17-Jul-24 14 95
GR-CON-Z16-1074 Installation of Paving 17-Jul-24 10-Aug-24 20 95
Landscape Works 23-May-24 10-Oct-24 115 11
GR-CON-Z16-1075 Excavation (Tree Pit ) 23-May-24 02-Jun-24 8 47
GR-CON-Z16-1076 Aggregate Drainage layer 02-Jun-24 12-Jun-24 9 47
GR-CON-Z16-1077 Installation Geotextile 12-Jun-24 24-Jun-24 6 47
GR-CON-Z16-1078 Backfilling (Soil max for tree) 24-Jun-24 04-Jul-24 9 47
GR-CON-Z16-1079 Installation of Trees 15-Aug-24 20-Aug-24 4 11
GR-CON-Z16-13376 Installation of Shrubs 20-Aug-24 24-Aug-24 3 11
GR-CON-Z16-13386 Installation of Succulents 24-Aug-24 27-Aug-24 3 11
GR-CON-Z16-13396 Installation of Ground Covers 27-Aug-24 31-Aug-24 3 11
GR-CON-Z16-13406 Installation of Grass 31-Aug-24 03-Sep-24 3 11
GR-CON-Z16-1080 Backfilling (Mulch) 03-Sep-24 09-Sep-24 5 11
GR-CON-Z16-1081 Natural Boulders Installation 09-Sep-24 16-Sep-24 6 11
GR-CON-Z16-1082 Retaining walls . Steps, forming risers, treads and edges with finishes
16-Sep-24 10-Oct-24 20 11
Site Furnishing 10-Oct-24 17-Nov-24 32 11
GR-CON-Z16-1091 Garden planter box 10-Oct-24 20-Oct-24 8 11
GR-CON-Z16-1092 Wheel stoppers 20-Oct-24 29-Oct-24 8 11
GR-CON-Z16-1093 Steel Lattice 29-Oct-24 07-Nov-24 8 11
GR-CON-Z16-1094 Handrail 07-Nov-24 17-Nov-24 8 11
Storm Piping Works 06-Nov-24 17-Nov-24 9 11
GR-CON-Z16-1095 Installation of DI grating covers 06-Nov-24 17-Nov-24 9 11
Irrigation Works 14-May-24 21-Aug-24 81 76
GR-CON-Z16-1083 Excavation Pipe Irrigation 14-May-24 23-May-24 8 27
GR-CON-Z16-1084 Sand Bedding 23-May-24 30-May-24 6 27
GR-CON-Z16-1085 HDPE Pipe Installations and fittings and conduit for cable 30-May-24 01-Jul-24 23 27
GR-CON-Z16-1087 Test pressure 01-Jul-24 10-Jul-24 8 27
GR-CON-Z16-1086 Installation of Valves and Accessories 10-Jul-24 17-Jul-24 6 27
GR-CON-Z16-1088 Back filling (sand / Subbase ) 17-Jul-24 28-Jul-24 9 27
GR-CON-Z16-1089 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-Jul-24 07-Aug-24 9 76
GR-CON-Z16-1090 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-Aug-24
system 21-Aug-24 12 76
Electrical Works 23-May-24 17-Nov-24 147 11
GR-CON-Z16-1096 Excavation And Disposal 23-May-24 02-Jun-24 8 116
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-1097 Sand Bedding 02-Jun-24 09-Jun-24 6 116


GR-CON-Z16-1098 laying cables 09-Jun-24 16-Jun-24 6 116
GR-CON-Z16-1099 Backfilling (sand / Sub base) 16-Jun-24 30-Jun-24 8 116
GR-CON-Z16-1100 Control Panel / Distribution Panel Installation 30-Jun-24 07-Jul-24 6 116
GR-CON-Z16-1101 Road Crossing Ducts 07-Nov-24 17-Nov-24 8 11
Street SS-09.1 05-May-24 17-Nov-24 163 11
Site Preparation 05-May-24 11-Jun-24 32 142
GR-CON-Z16-1102 Demolition (Asphalt.Paving,etc.....) 05-May-24 12-May-24 6 21
GR-CON-Z16-1103 Excavation And Disposal 12-May-24 21-May-24 8 21
GR-CON-Z16-1104 Prepretion And Compaction 21-May-24 01-Jun-24 9 142
GR-CON-Z16-1105 Backfilling 01-Jun-24 11-Jun-24 9 142
Curbstone and Paving 21-May-24 17-Aug-24 71 89
GR-CON-Z16-1106 Excavation Curbstone 21-May-24 30-May-24 8 41
GR-CON-Z16-1107 Plain Concrete 30-May-24 10-Jun-24 9 89
GR-CON-Z16-1108 Installation Curbstone 10-Jun-24 01-Jul-24 14 89
GR-CON-Z16-1109 Casting Concrete (Mortar haunch) 01-Jul-24 08-Jul-24 6 89
GR-CON-Z16-1110 Backfilling (sand / Sub base) 08-Jul-24 24-Jul-24 14 89
GR-CON-Z16-1111 Installation of Paving 24-Jul-24 17-Aug-24 20 89
Landscape Works 30-May-24 10-Oct-24 109 11
GR-CON-Z16-1112 Excavation (Tree Pit ) 30-May-24 09-Jun-24 8 41
GR-CON-Z16-1113 Aggregate Drainage layer 09-Jun-24 24-Jun-24 9 41
GR-CON-Z16-1114 Installation Geotextile 24-Jun-24 01-Jul-24 6 41
GR-CON-Z16-1115 Backfilling (Soil max for tree) 01-Jul-24 11-Jul-24 9 41
GR-CON-Z16-1116 Installation of Trees 15-Aug-24 20-Aug-24 4 11
GR-CON-Z16-13416 Installation of Shrubs 20-Aug-24 24-Aug-24 3 11
GR-CON-Z16-13426 Installation of Succulents 24-Aug-24 27-Aug-24 3 11
GR-CON-Z16-13436 Installation of Ground Covers 27-Aug-24 31-Aug-24 3 11
GR-CON-Z16-13446 Installation of Grass 31-Aug-24 03-Sep-24 3 11
GR-CON-Z16-1117 Backfilling (Mulch) 03-Sep-24 09-Sep-24 5 11
GR-CON-Z16-1118 Natural Boulders Installation 09-Sep-24 16-Sep-24 6 11
GR-CON-Z16-1119 Retaining walls . Steps, forming risers, treads and edges with finishes
16-Sep-24 10-Oct-24 20 11
Site Furnishing 10-Oct-24 17-Nov-24 32 11
GR-CON-Z16-1128 Garden planter box 10-Oct-24 20-Oct-24 8 11
GR-CON-Z16-1129 Wheel stoppers 20-Oct-24 29-Oct-24 8 11
GR-CON-Z16-1130 Steel Lattice 29-Oct-24 07-Nov-24 8 11
GR-CON-Z16-1131 Handrail 07-Nov-24 17-Nov-24 8 11
Activity ID Activity Name Start Finish Original Total Float
Duration

Storm Piping Works 06-Nov-24 17-Nov-24 9 11


GR-CON-Z16-1132 Installation of DI grating covers 06-Nov-24 17-Nov-24 9 11
Irrigation Works 21-May-24 28-Aug-24 81 70
GR-CON-Z16-1120 Excavation Pipe Irrigation 21-May-24 30-May-24 8 21
GR-CON-Z16-1121 Sand Bedding 30-May-24 06-Jun-24 6 21
GR-CON-Z16-1122 HDPE Pipe Installations and fittings and conduit for cable 06-Jun-24 08-Jul-24 23 21
GR-CON-Z16-1124 Test pressure 08-Jul-24 17-Jul-24 8 21
GR-CON-Z16-1123 Installation of Valves and Accessories 17-Jul-24 24-Jul-24 6 21
GR-CON-Z16-1125 Back filling (sand / Subbase ) 24-Jul-24 04-Aug-24 9 21
GR-CON-Z16-1126 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Aug-24 14-Aug-24 9 70
GR-CON-Z16-1127 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
14-Aug-24
system 28-Aug-24 12 70
Electrical Works 30-May-24 17-Nov-24 141 11
GR-CON-Z16-1133 Excavation And Disposal 30-May-24 09-Jun-24 8 110
GR-CON-Z16-1134 Sand Bedding 09-Jun-24 16-Jun-24 6 110
GR-CON-Z16-1135 laying cables 16-Jun-24 27-Jun-24 6 110
GR-CON-Z16-1136 Backfilling (sand / Sub base) 27-Jun-24 07-Jul-24 8 110
GR-CON-Z16-1137 Control Panel / Distribution Panel Installation 07-Jul-24 14-Jul-24 6 110
GR-CON-Z16-1138 Road Crossing Ducts 07-Nov-24 17-Nov-24 8 11
School S-14 30-May-24 15-Oct-24 113 39
Site Preparation 30-May-24 10-Jun-24 9 143
GR-CON-Z16-1430 Excavation And Disposal 30-May-24 05-Jun-24 5 11
GR-CON-Z16-1431 Prepretion And Compaction 05-Jun-24 10-Jun-24 4 143
Curbstone and Paving 05-Jun-24 03-Aug-24 46 101
GR-CON-Z16-1433 Excavation Curbstone 05-Jun-24 11-Jun-24 5 70
GR-CON-Z16-1434 Plain Concrete 11-Jun-24 18-Jun-24 6 101
GR-CON-Z16-1435 Installation Curbstone 18-Jun-24 03-Jul-24 9 101
GR-CON-Z16-1436 Casting Concrete (Mortar haunch) 03-Jul-24 08-Jul-24 4 101
GR-CON-Z16-1437 Backfilling (sand / Sub base) 08-Jul-24 18-Jul-24 9 101
GR-CON-Z16-1438 Installation of Paving 18-Jul-24 03-Aug-24 13 101
Landscape Works 11-Jun-24 03-Oct-24 93 39
GR-CON-Z16-1439 Excavation (Tree Pit ) 11-Jun-24 17-Jun-24 5 70
GR-CON-Z16-1440 Aggregate Drainage layer 17-Jun-24 29-Jun-24 6 70
GR-CON-Z16-1441 Installation Geotextile 29-Jun-24 03-Jul-24 4 70
GR-CON-Z16-1442 Backfilling (Soil max for tree) 03-Jul-24 10-Jul-24 6 70
GR-CON-Z16-1443 Installation of Trees 15-Aug-24 19-Aug-24 3 39
GR-CON-Z16-5896 Installation of Shrubs 19-Aug-24 22-Aug-24 3 39
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-5906 Installation of Succulents 22-Aug-24 26-Aug-24 3 39


GR-CON-Z16-5916 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 39
GR-CON-Z16-5926 Installation of Climbers 29-Aug-24 02-Sep-24 3 39
GR-CON-Z16-5936 Installation of Grass 02-Sep-24 05-Sep-24 3 39
GR-CON-Z16-5946 Installation of Lawns 05-Sep-24 09-Sep-24 3 39
GR-CON-Z16-1444 Backfilling (Mulch) 09-Sep-24 12-Sep-24 3 39
GR-CON-Z16-1445 Natural Boulders Installation 12-Sep-24 17-Sep-24 4 39
GR-CON-Z16-1446 Retaining walls . Steps, forming risers, treads and edges with finishes
17-Sep-24 03-Oct-24 13 39
Site Furnishing 03-Oct-24 15-Oct-24 10 39
GR-CON-Z16-1455 Garden planter box 03-Oct-24 09-Oct-24 5 39
GR-CON-Z16-1456 Wheel stoppers 09-Oct-24 15-Oct-24 5 39
Irrigation Works 05-Jun-24 15-Oct-24 108 39
GR-CON-Z16-1447 Excavation Pipe Irrigation 05-Jun-24 11-Jun-24 5 30
GR-CON-Z16-1448 Sand Bedding 11-Jun-24 15-Jun-24 3 30
GR-CON-Z16-1449 HDPE Pipe Installations and fittings and conduit for cable 15-Jun-24 07-Jul-24 15 30
GR-CON-Z16-1451 Test pressure 07-Jul-24 13-Jul-24 5 30
GR-CON-Z16-1450 Installation of Valves and Accessories 13-Jul-24 17-Jul-24 4 30
GR-CON-Z16-1452 Back filling (sand / Subbase ) 17-Jul-24 24-Jul-24 6 30
GR-CON-Z16-1453 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Jul-24 31-Jul-24 6 95
GR-CON-Z16-1454 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Oct-24
system 15-Oct-24 8 39
Existing Neighborhood Park ENP-03 05-Jun-24 12-Sep-24 81 66
Site Preparation 05-Jun-24 08-Jul-24 24 123
GR-CON-Z16-1139 Demolition (Asphalt.Paving,etc.....) 05-Jun-24 11-Jun-24 5 11
GR-CON-Z16-1140 Excavation And Disposal 11-Jun-24 18-Jun-24 6 11
GR-CON-Z16-1141 Prepretion And Compaction 18-Jun-24 29-Jun-24 5 123
GR-CON-Z16-1142 Backfilling 29-Jun-24 08-Jul-24 8 123
Landscape Works 18-Jun-24 12-Sep-24 70 66
GR-CON-Z16-1143 Excavation (Tree Pit ) 18-Jun-24 30-Jun-24 6 85
GR-CON-Z16-1144 Aggregate Drainage layer 30-Jun-24 09-Jul-24 8 85
GR-CON-Z16-1145 Installation Geotextile 09-Jul-24 15-Jul-24 5 85
GR-CON-Z16-1146 Backfilling (Soil max for tree) 15-Jul-24 24-Jul-24 8 85
GR-CON-Z16-1147 Installation of Trees 15-Aug-24 19-Aug-24 3 66
GR-CON-Z16-11608 Installation of Climbers 19-Aug-24 22-Aug-24 3 66
GR-CON-Z16-14196 Installation of Succulents 22-Aug-24 26-Aug-24 3 66
GR-CON-Z16-14206 Installation of Ground Covers 26-Aug-24 29-Aug-24 3 66
GR-CON-Z16-11618 Installation of Shrubs 29-Aug-24 02-Sep-24 3 66
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z16-11628 Installation of Grass 02-Sep-24 05-Sep-24 3 66


GR-CON-Z16-11638 Installation of Lawns 05-Sep-24 09-Sep-24 3 66
GR-CON-Z16-1148 Backfilling (Mulch) 09-Sep-24 12-Sep-24 3 66
Irrigation Works 18-Jun-24 12-Sep-24 70 66
GR-CON-Z16-1149 Excavation Pipe Irrigation 18-Jun-24 30-Jun-24 6 11
GR-CON-Z16-1150 Sand Bedding 30-Jun-24 03-Jul-24 3 11
GR-CON-Z16-1151 HDPE Pipe Installations and fittings and conduit for cable 03-Jul-24 24-Jul-24 18 11
GR-CON-Z16-1153 Test pressure 24-Jul-24 31-Jul-24 6 11
GR-CON-Z16-1152 Installation of Valves and Accessories 31-Jul-24 06-Aug-24 5 11
GR-CON-Z16-1154 Back filling (sand / Subbase ) 06-Aug-24 15-Aug-24 8 11
GR-CON-Z16-1155 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 15-Aug-24 25-Aug-24 8 73
GR-CON-Z16-1156 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-Sep-24
system 12-Sep-24 9 66
Zone 15 14-Dec-23 26-Nov-24 283 15
Future Neighborhood Park FNP-25 14-Dec-23 29-Jul-24 181 117
Site Preparation 14-Dec-23 16-Jan-24 28 270
GR-CON-Z15-1101 Demolition (Asphalt.Paving,etc.....) 14-Dec-23 21-Dec-23 6 38
GR-CON-Z15-1102 Excavation And Disposal 21-Dec-23 30-Dec-23 7 140
GR-CON-Z15-1103 Prepretion And Compaction 30-Dec-23 06-Jan-24 6 270
GR-CON-Z15-1104 Backfilling 06-Jan-24 16-Jan-24 9 270
Curbstone and Paving 30-Dec-23 16-Mar-24 66 219
GR-CON-Z15-1105 Excavation Curbstone 30-Dec-23 07-Jan-24 7 163
GR-CON-Z15-1106 Plain Concrete 07-Jan-24 17-Jan-24 9 219
GR-CON-Z15-1107 Installation Curbstone 17-Jan-24 01-Feb-24 13 219
GR-CON-Z15-1108 Casting Concrete (Mortar haunch) 01-Feb-24 08-Feb-24 6 219
GR-CON-Z15-1109 Backfilling (sand / Sub base) 08-Feb-24 24-Feb-24 13 219
GR-CON-Z15-1110 Installation of Paving 24-Feb-24 16-Mar-24 18 219
Landscape Works 07-Jan-24 29-Jul-24 161 117
GR-CON-Z15-1111 Excavation (Tree Pit ) 07-Jan-24 15-Jan-24 7 163
GR-CON-Z15-1112 Aggregate Drainage layer 15-Jan-24 25-Jan-24 9 198
GR-CON-Z15-1113 Installation Geotextile 25-Jan-24 01-Feb-24 6 198
GR-CON-Z15-1114 Backfilling (Soil max for tree) 01-Feb-24 12-Feb-24 9 198
GR-CON-Z15-1115 Installation of Trees 28-May-24 01-Jun-24 3 117
GR-CON-Z15-2646 Installation of Shrubs 01-Jun-24 04-Jun-24 3 117
GR-CON-Z15-2656 Installation of Succulents 04-Jun-24 08-Jun-24 3 117
GR-CON-Z15-2666 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 117
GR-CON-Z15-2676 Installation of Climbers 11-Jun-24 15-Jun-24 3 117
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-2686 Installation of Grass 15-Jun-24 18-Jun-24 3 117


GR-CON-Z15-2696 Installation of Lawns 18-Jun-24 26-Jun-24 3 117
GR-CON-Z15-1116 Backfilling (Mulch) 26-Jun-24 01-Jul-24 4 117
GR-CON-Z15-1117 Natural Boulders Installation 01-Jul-24 08-Jul-24 6 117
GR-CON-Z15-1118 Retaining walls . Steps, forming risers, treads and edges with finishes
08-Jul-24 29-Jul-24 18 117
MUGA 15-Jan-24 29-Jul-24 154 117
GR-CON-Z15-1119 Excavation And Disposal 15-Jan-24 23-Jan-24 7 163
GR-CON-Z15-1120 Prepretion And Compaction 23-Jan-24 03-Feb-24 9 163
GR-CON-Z15-1121 polyethylene under footings ( fence and gates) 03-Feb-24 11-Feb-24 7 163
GR-CON-Z15-1122 Blinding concrete (flooring) 11-Feb-24 19-Feb-24 7 163
GR-CON-Z15-1123 Concrete Footings ( fence and gates) 19-Feb-24 11-Mar-24 18 163
GR-CON-Z15-1124 Tools Play Installation ( basketball / football ..) 11-Mar-24 11-Apr-24 21 163
GR-CON-Z15-1125 PaintAcrylic Play Surface 11-Apr-24 07-May-24 18 163
GR-CON-Z15-1126 Fence (high / low) / gates Installation 04-Jul-24 29-Jul-24 21 117
Irrigation Works 30-Dec-23 29-Jul-24 168 117
GR-CON-Z15-1127 Excavation Pipe Irrigation 30-Dec-23 07-Jan-24 7 140
GR-CON-Z15-1128 Sand Bedding 07-Jan-24 11-Jan-24 4 140
GR-CON-Z15-1129 HDPE Pipe Installations and fittings and conduit for cable 11-Jan-24 05-Feb-24 21 140
GR-CON-Z15-1131 Test pressure 05-Feb-24 13-Feb-24 7 140
GR-CON-Z15-1130 Installation of Valves and Accessories 13-Feb-24 20-Feb-24 6 140
GR-CON-Z15-1132 Back filling (sand / Subbase ) 20-Feb-24 02-Mar-24 9 140
GR-CON-Z15-1133 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 02-Mar-24 12-Mar-24 9 211
GR-CON-Z15-1134 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
16-Jul-24
system 29-Jul-24 11 117
Mosque M-13 21-Dec-23 14-Aug-24 189 103
Site Preparation 21-Dec-23 13-Jan-24 19 251
GR-CON-Z15-1135 Demolition (Asphalt.Paving,etc.....) 21-Dec-23 26-Dec-23 4 38
GR-CON-Z15-1136 Excavation And Disposal 26-Dec-23 01-Jan-24 5 154
GR-CON-Z15-1137 Prepretion And Compaction 01-Jan-24 06-Jan-24 4 251
GR-CON-Z15-1138 Backfilling 06-Jan-24 13-Jan-24 6 251
Curbstone and Paving 13-Jan-24 07-Feb-24 22 251
GR-CON-Z15-1143 Backfilling (sand / Sub base) 13-Jan-24 23-Jan-24 9 251
GR-CON-Z15-1144 Installation of Paving 23-Jan-24 07-Feb-24 13 251
Landscape Works 01-Jan-24 14-Aug-24 180 103
GR-CON-Z15-1145 Excavation (Tree Pit ) 01-Jan-24 07-Jan-24 5 199
GR-CON-Z15-1146 Aggregate Drainage layer 07-Jan-24 14-Jan-24 6 199
GR-CON-Z15-1147 Installation Geotextile 14-Jan-24 20-Jan-24 5 199
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1148 Backfilling (Soil max for tree) 20-Jan-24 25-Jan-24 5 199


GR-CON-Z15-1149 Installation of Trees 28-May-24 02-Jun-24 4 103
GR-CON-Z15-4466 Installation of Climbers 02-Jun-24 06-Jun-24 4 103
GR-CON-Z15-4476 Installation of Shrubs 06-Jun-24 11-Jun-24 4 103
GR-CON-Z15-4486 Installation of Succulents 11-Jun-24 16-Jun-24 4 103
GR-CON-Z15-4496 Installation of Ground Covers 16-Jun-24 25-Jun-24 4 103
GR-CON-Z15-1150 Backfilling (Mulch) 25-Jun-24 13-Jul-24 15 103
GR-CON-Z15-1151 Natural Boulders Installation 13-Jul-24 28-Jul-24 13 103
GR-CON-Z15-1152 Retaining walls . Steps, forming risers, treads and edges with finishes
28-Jul-24 14-Aug-24 15 103
Irrigation Works 01-Jan-24 14-Aug-24 180 103
GR-CON-Z15-1153 Excavation Pipe Irrigation 01-Jan-24 07-Jan-24 5 154
GR-CON-Z15-1154 Sand Bedding 07-Jan-24 10-Jan-24 3 154
GR-CON-Z15-1155 HDPE Pipe Installations and fittings and conduit for cable 10-Jan-24 28-Jan-24 15 154
GR-CON-Z15-1157 Test pressure 28-Jan-24 03-Feb-24 5 154
GR-CON-Z15-1156 Installation of Valves and Accessories 03-Feb-24 07-Feb-24 4 154
GR-CON-Z15-1158 Back filling (sand / Subbase ) 07-Feb-24 14-Feb-24 6 154
GR-CON-Z15-1159 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-Feb-24 21-Feb-24 6 233
GR-CON-Z15-1160 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-Aug-24
system 14-Aug-24 6 103
Mosque M-18 26-Dec-23 14-Aug-24 185 103
Site Preparation 26-Dec-23 17-Jan-24 19 247
GR-CON-Z15-1161 Demolition (Asphalt.Paving,etc.....) 26-Dec-23 31-Dec-23 4 75
GR-CON-Z15-1162 Excavation And Disposal 31-Dec-23 06-Jan-24 5 150
GR-CON-Z15-1163 Prepretion And Compaction 06-Jan-24 10-Jan-24 4 247
GR-CON-Z15-1164 Backfilling 10-Jan-24 17-Jan-24 6 247
Curbstone and Paving 17-Jan-24 12-Feb-24 22 247
GR-CON-Z15-1169 Backfilling (sand / Sub base) 17-Jan-24 28-Jan-24 9 247
GR-CON-Z15-1170 Installation of Paving 28-Jan-24 12-Feb-24 13 247
Landscape Works 06-Jan-24 14-Aug-24 176 103
GR-CON-Z15-1171 Excavation (Tree Pit ) 06-Jan-24 11-Jan-24 5 195
GR-CON-Z15-1172 Aggregate Drainage layer 11-Jan-24 18-Jan-24 6 195
GR-CON-Z15-1173 Installation Geotextile 18-Jan-24 24-Jan-24 5 195
GR-CON-Z15-1174 Backfilling (Soil max for tree) 24-Jan-24 30-Jan-24 5 195
GR-CON-Z15-1175 Installation of Trees 28-May-24 02-Jun-24 4 103
GR-CON-Z15-4506 Installation of Climbers 02-Jun-24 06-Jun-24 4 103
GR-CON-Z15-4516 Installation of Shrubs 06-Jun-24 11-Jun-24 4 103
GR-CON-Z15-4526 Installation of Succulents 11-Jun-24 16-Jun-24 4 103
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-4536 Installation of Ground Covers 16-Jun-24 25-Jun-24 4 103


GR-CON-Z15-1176 Backfilling (Mulch) 25-Jun-24 13-Jul-24 15 103
GR-CON-Z15-1177 Natural Boulders Installation 13-Jul-24 28-Jul-24 13 103
GR-CON-Z15-1178 Retaining walls . Steps, forming risers, treads and edges with finishes
28-Jul-24 14-Aug-24 15 103
Irrigation Works 06-Jan-24 14-Aug-24 176 103
GR-CON-Z15-1179 Excavation Pipe Irrigation 06-Jan-24 11-Jan-24 5 150
GR-CON-Z15-1180 Sand Bedding 11-Jan-24 15-Jan-24 3 150
GR-CON-Z15-1181 HDPE Pipe Installations and fittings and conduit for cable 15-Jan-24 01-Feb-24 15 150
GR-CON-Z15-1183 Test pressure 01-Feb-24 07-Feb-24 5 150
GR-CON-Z15-1182 Installation of Valves and Accessories 07-Feb-24 12-Feb-24 4 150
GR-CON-Z15-1184 Back filling (sand / Subbase ) 12-Feb-24 19-Feb-24 6 150
GR-CON-Z15-1185 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-Feb-24 26-Feb-24 6 229
GR-CON-Z15-1186 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-Aug-24
system 14-Aug-24 6 103
Mosque M-20 31-Dec-23 14-Aug-24 181 103
Site Preparation 31-Dec-23 22-Jan-24 19 243
GR-CON-Z15-1187 Demolition (Asphalt.Paving,etc.....) 31-Dec-23 04-Jan-24 4 75
GR-CON-Z15-1188 Excavation And Disposal 04-Jan-24 10-Jan-24 5 146
GR-CON-Z15-1189 Prepretion And Compaction 10-Jan-24 15-Jan-24 4 243
GR-CON-Z15-1190 Backfilling 15-Jan-24 22-Jan-24 6 243
Curbstone and Paving 22-Jan-24 17-Feb-24 22 243
GR-CON-Z15-1195 Backfilling (sand / Sub base) 22-Jan-24 01-Feb-24 9 243
GR-CON-Z15-1196 Installation of Paving 01-Feb-24 17-Feb-24 13 243
Landscape Works 10-Jan-24 14-Aug-24 172 103
GR-CON-Z15-1197 Excavation (Tree Pit ) 10-Jan-24 16-Jan-24 5 191
GR-CON-Z15-1198 Aggregate Drainage layer 16-Jan-24 23-Jan-24 6 191
GR-CON-Z15-1199 Installation Geotextile 23-Jan-24 29-Jan-24 5 191
GR-CON-Z15-1200 Backfilling (Soil max for tree) 29-Jan-24 04-Feb-24 5 191
GR-CON-Z15-1201 Installation of Trees 28-May-24 02-Jun-24 4 103
GR-CON-Z15-4546 Installation of Climbers 02-Jun-24 06-Jun-24 4 103
GR-CON-Z15-4556 Installation of Shrubs 06-Jun-24 11-Jun-24 4 103
GR-CON-Z15-4566 Installation of Succulents 11-Jun-24 16-Jun-24 4 103
GR-CON-Z15-4576 Installation of Ground Covers 16-Jun-24 25-Jun-24 4 103
GR-CON-Z15-1202 Backfilling (Mulch) 25-Jun-24 13-Jul-24 15 103
GR-CON-Z15-1203 Natural Boulders Installation 13-Jul-24 28-Jul-24 13 103
GR-CON-Z15-1204 Retaining walls . Steps, forming risers, treads and edges with finishes
28-Jul-24 14-Aug-24 15 103
Irrigation Works 10-Jan-24 14-Aug-24 172 103
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1205 Excavation Pipe Irrigation 10-Jan-24 16-Jan-24 5 146


GR-CON-Z15-1206 Sand Bedding 16-Jan-24 20-Jan-24 3 146
GR-CON-Z15-1207 HDPE Pipe Installations and fittings and conduit for cable 20-Jan-24 06-Feb-24 15 146
GR-CON-Z15-1209 Test pressure 06-Feb-24 12-Feb-24 5 146
GR-CON-Z15-1208 Installation of Valves and Accessories 12-Feb-24 17-Feb-24 4 146
GR-CON-Z15-1210 Back filling (sand / Subbase ) 17-Feb-24 24-Feb-24 6 146
GR-CON-Z15-1211 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 24-Feb-24 02-Mar-24 6 225
GR-CON-Z15-1212 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-Aug-24
system 14-Aug-24 6 103
Mosque M-21 04-Jan-24 14-Aug-24 177 103
Site Preparation 04-Jan-24 27-Jan-24 19 239
GR-CON-Z15-1213 Demolition (Asphalt.Paving,etc.....) 04-Jan-24 09-Jan-24 4 75
GR-CON-Z15-1214 Excavation And Disposal 09-Jan-24 15-Jan-24 5 142
GR-CON-Z15-1215 Prepretion And Compaction 15-Jan-24 20-Jan-24 4 239
GR-CON-Z15-1216 Backfilling 20-Jan-24 27-Jan-24 6 239
Curbstone and Paving 27-Jan-24 21-Feb-24 22 239
GR-CON-Z15-1221 Backfilling (sand / Sub base) 27-Jan-24 06-Feb-24 9 239
GR-CON-Z15-1222 Installation of Paving 06-Feb-24 21-Feb-24 13 239
Landscape Works 15-Jan-24 14-Aug-24 168 103
GR-CON-Z15-1223 Excavation (Tree Pit ) 15-Jan-24 21-Jan-24 5 187
GR-CON-Z15-1224 Aggregate Drainage layer 21-Jan-24 28-Jan-24 6 187
GR-CON-Z15-1225 Installation Geotextile 28-Jan-24 03-Feb-24 5 187
GR-CON-Z15-1226 Backfilling (Soil max for tree) 03-Feb-24 08-Feb-24 5 187
GR-CON-Z15-1227 Installation of Trees 28-May-24 02-Jun-24 4 103
GR-CON-Z15-4586 Installation of Climbers 02-Jun-24 06-Jun-24 4 103
GR-CON-Z15-4596 Installation of Shrubs 06-Jun-24 11-Jun-24 4 103
GR-CON-Z15-4606 Installation of Succulents 11-Jun-24 16-Jun-24 4 103
GR-CON-Z15-4616 Installation of Ground Covers 16-Jun-24 25-Jun-24 4 103
GR-CON-Z15-1228 Backfilling (Mulch) 25-Jun-24 13-Jul-24 15 103
GR-CON-Z15-1229 Natural Boulders Installation 13-Jul-24 28-Jul-24 13 103
GR-CON-Z15-1230 Retaining walls . Steps, forming risers, treads and edges with finishes
28-Jul-24 14-Aug-24 15 103
Irrigation Works 15-Jan-24 14-Aug-24 168 103
GR-CON-Z15-1231 Excavation Pipe Irrigation 15-Jan-24 21-Jan-24 5 142
GR-CON-Z15-1232 Sand Bedding 21-Jan-24 24-Jan-24 3 142
GR-CON-Z15-1233 HDPE Pipe Installations and fittings and conduit for cable 24-Jan-24 11-Feb-24 15 142
GR-CON-Z15-1235 Test pressure 11-Feb-24 17-Feb-24 5 142
GR-CON-Z15-1234 Installation of Valves and Accessories 17-Feb-24 21-Feb-24 4 142
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1236 Back filling (sand / Subbase ) 21-Feb-24 28-Feb-24 6 142


GR-CON-Z15-1237 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-Feb-24 06-Mar-24 6 221
GR-CON-Z15-1238 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-Aug-24
system 14-Aug-24 6 103
Parking P-30 09-Jan-24 04-Jul-24 138 138
Site Preparation 09-Jan-24 31-Jan-24 19 244
GR-CON-Z15-1239 Demolition (Asphalt.Paving,etc.....) 09-Jan-24 14-Jan-24 4 75
GR-CON-Z15-1240 Excavation And Disposal 14-Jan-24 20-Jan-24 5 138
GR-CON-Z15-1241 Prepretion And Compaction 20-Jan-24 24-Jan-24 4 244
GR-CON-Z15-1242 Backfilling 24-Jan-24 31-Jan-24 6 244
Curbstone and Paving 20-Jan-24 13-Mar-24 46 221
GR-CON-Z15-1243 Excavation Curbstone 20-Jan-24 25-Jan-24 5 213
GR-CON-Z15-1244 Plain Concrete 25-Jan-24 01-Feb-24 6 221
GR-CON-Z15-1245 Installation Curbstone 01-Feb-24 12-Feb-24 9 221
GR-CON-Z15-1246 Casting Concrete (Mortar haunch) 12-Feb-24 17-Feb-24 4 221
GR-CON-Z15-1247 Backfilling (sand / Sub base) 17-Feb-24 27-Feb-24 9 221
GR-CON-Z15-1248 Installation of Paving 27-Feb-24 13-Mar-24 13 221
Landscape Works 25-Jan-24 18-Jun-24 114 138
GR-CON-Z15-1249 Excavation (Tree Pit ) 25-Jan-24 31-Jan-24 5 213
GR-CON-Z15-1250 Aggregate Drainage layer 31-Jan-24 07-Feb-24 6 213
GR-CON-Z15-1251 Installation Geotextile 07-Feb-24 12-Feb-24 4 213
GR-CON-Z15-1252 Backfilling (Soil max for tree) 12-Feb-24 19-Feb-24 6 213
GR-CON-Z15-1253 Installation of Trees 28-May-24 01-Jun-24 3 138
GR-CON-Z15-8296 Installation of Shrubs 01-Jun-24 04-Jun-24 3 138
GR-CON-Z15-8306 Installation of Ground Covers 04-Jun-24 08-Jun-24 3 138
GR-CON-Z15-8316 Installation of Succulents 08-Jun-24 11-Jun-24 3 138
GR-CON-Z15-8326 Installation of Grass 11-Jun-24 15-Jun-24 3 138
GR-CON-Z15-1254 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 138
Site Furnishing 18-Jun-24 04-Jul-24 10 138
GR-CON-Z15-1265 Tree Grate 18-Jun-24 29-Jun-24 5 138
GR-CON-Z15-1266 Wheel stoppers 29-Jun-24 04-Jul-24 5 138
Irrigation Works 20-Jan-24 04-Jul-24 129 138
GR-CON-Z15-1257 Excavation Pipe Irrigation 20-Jan-24 25-Jan-24 5 138
GR-CON-Z15-1258 Sand Bedding 25-Jan-24 29-Jan-24 3 138
GR-CON-Z15-1259 HDPE Pipe Installations and fittings and conduit for cable 29-Jan-24 15-Feb-24 15 138
GR-CON-Z15-1261 Test pressure 15-Feb-24 21-Feb-24 5 138
GR-CON-Z15-1260 Installation of Valves and Accessories 21-Feb-24 26-Feb-24 4 138
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1262 Back filling (sand / Subbase ) 26-Feb-24 04-Mar-24 6 138


GR-CON-Z15-1263 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 04-Mar-24 11-Mar-24 6 215
GR-CON-Z15-1264 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jun-24
system 04-Jul-24 8 138
Parking P-17 14-Jan-24 04-Jul-24 134 138
Site Preparation 14-Jan-24 05-Feb-24 19 240
GR-CON-Z15-1267 Demolition (Asphalt.Paving,etc.....) 14-Jan-24 18-Jan-24 4 75
GR-CON-Z15-1268 Excavation And Disposal 18-Jan-24 24-Jan-24 5 134
GR-CON-Z15-1269 Prepretion And Compaction 24-Jan-24 29-Jan-24 4 240
GR-CON-Z15-1270 Backfilling 29-Jan-24 05-Feb-24 6 240
Curbstone and Paving 24-Jan-24 19-Mar-24 46 217
GR-CON-Z15-1271 Excavation Curbstone 24-Jan-24 30-Jan-24 5 209
GR-CON-Z15-1272 Plain Concrete 30-Jan-24 06-Feb-24 6 217
GR-CON-Z15-1273 Installation Curbstone 06-Feb-24 17-Feb-24 9 217
GR-CON-Z15-1274 Casting Concrete (Mortar haunch) 17-Feb-24 21-Feb-24 4 217
GR-CON-Z15-1275 Backfilling (sand / Sub base) 21-Feb-24 03-Mar-24 9 217
GR-CON-Z15-1276 Installation of Paving 03-Mar-24 19-Mar-24 13 217
Landscape Works 30-Jan-24 18-Jun-24 110 138
GR-CON-Z15-1277 Excavation (Tree Pit ) 30-Jan-24 05-Feb-24 5 209
GR-CON-Z15-1278 Aggregate Drainage layer 05-Feb-24 12-Feb-24 6 209
GR-CON-Z15-1279 Installation Geotextile 12-Feb-24 17-Feb-24 4 209
GR-CON-Z15-1280 Backfilling (Soil max for tree) 17-Feb-24 24-Feb-24 6 209
GR-CON-Z15-1281 Installation of Trees 28-May-24 01-Jun-24 3 138
GR-CON-Z15-8336 Installation of Shrubs 01-Jun-24 04-Jun-24 3 138
GR-CON-Z15-8346 Installation of Ground Covers 04-Jun-24 08-Jun-24 3 138
GR-CON-Z15-8356 Installation of Succulents 08-Jun-24 11-Jun-24 3 138
GR-CON-Z15-8366 Installation of Grass 11-Jun-24 15-Jun-24 3 138
GR-CON-Z15-1282 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 138
Site Furnishing 18-Jun-24 04-Jul-24 10 138
GR-CON-Z15-1293 Tree Grate 18-Jun-24 29-Jun-24 5 138
GR-CON-Z15-1294 Wheel stoppers 29-Jun-24 04-Jul-24 5 138
Irrigation Works 24-Jan-24 04-Jul-24 125 138
GR-CON-Z15-1285 Excavation Pipe Irrigation 24-Jan-24 30-Jan-24 5 134
GR-CON-Z15-1286 Sand Bedding 30-Jan-24 03-Feb-24 3 134
GR-CON-Z15-1287 HDPE Pipe Installations and fittings and conduit for cable 03-Feb-24 20-Feb-24 15 134
GR-CON-Z15-1289 Test pressure 20-Feb-24 26-Feb-24 5 134
GR-CON-Z15-1288 Installation of Valves and Accessories 26-Feb-24 02-Mar-24 4 134
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1290 Back filling (sand / Subbase ) 02-Mar-24 09-Mar-24 6 134


GR-CON-Z15-1291 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Mar-24 16-Mar-24 6 211
GR-CON-Z15-1292 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jun-24
system 04-Jul-24 8 138
Parking P-20 18-Jan-24 04-Jul-24 130 138
Site Preparation 18-Jan-24 10-Feb-24 19 236
GR-CON-Z15-1295 Demolition (Asphalt.Paving,etc.....) 18-Jan-24 23-Jan-24 4 75
GR-CON-Z15-1296 Excavation And Disposal 23-Jan-24 29-Jan-24 5 130
GR-CON-Z15-1297 Prepretion And Compaction 29-Jan-24 03-Feb-24 4 236
GR-CON-Z15-1298 Backfilling 03-Feb-24 10-Feb-24 6 236
Curbstone and Paving 29-Jan-24 25-Mar-24 46 213
GR-CON-Z15-1299 Excavation Curbstone 29-Jan-24 04-Feb-24 5 205
GR-CON-Z15-1300 Plain Concrete 04-Feb-24 11-Feb-24 6 213
GR-CON-Z15-1301 Installation Curbstone 11-Feb-24 21-Feb-24 9 213
GR-CON-Z15-1302 Casting Concrete (Mortar haunch) 21-Feb-24 26-Feb-24 4 213
GR-CON-Z15-1303 Backfilling (sand / Sub base) 26-Feb-24 07-Mar-24 9 213
GR-CON-Z15-1304 Installation of Paving 07-Mar-24 25-Mar-24 13 213
Landscape Works 04-Feb-24 18-Jun-24 106 138
GR-CON-Z15-1305 Excavation (Tree Pit ) 04-Feb-24 10-Feb-24 5 205
GR-CON-Z15-1306 Aggregate Drainage layer 10-Feb-24 17-Feb-24 6 205
GR-CON-Z15-1307 Installation Geotextile 17-Feb-24 21-Feb-24 4 205
GR-CON-Z15-1308 Backfilling (Soil max for tree) 21-Feb-24 28-Feb-24 6 205
GR-CON-Z15-1309 Installation of Trees 28-May-24 01-Jun-24 3 138
GR-CON-Z15-8376 Installation of Shrubs 01-Jun-24 04-Jun-24 3 138
GR-CON-Z15-8386 Installation of Ground Covers 04-Jun-24 08-Jun-24 3 138
GR-CON-Z15-8396 Installation of Succulents 08-Jun-24 11-Jun-24 3 138
GR-CON-Z15-8406 Installation of Grass 11-Jun-24 15-Jun-24 3 138
GR-CON-Z15-1310 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 138
Site Furnishing 18-Jun-24 04-Jul-24 10 138
GR-CON-Z15-1321 Tree Grate 18-Jun-24 29-Jun-24 5 138
GR-CON-Z15-1322 Wheel stoppers 29-Jun-24 04-Jul-24 5 138
Irrigation Works 29-Jan-24 04-Jul-24 121 138
GR-CON-Z15-1313 Excavation Pipe Irrigation 29-Jan-24 04-Feb-24 5 130
GR-CON-Z15-1314 Sand Bedding 04-Feb-24 07-Feb-24 3 130
GR-CON-Z15-1315 HDPE Pipe Installations and fittings and conduit for cable 07-Feb-24 25-Feb-24 15 130
GR-CON-Z15-1317 Test pressure 25-Feb-24 02-Mar-24 5 130
GR-CON-Z15-1316 Installation of Valves and Accessories 02-Mar-24 06-Mar-24 4 130
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1318 Back filling (sand / Subbase ) 06-Mar-24 13-Mar-24 6 130


GR-CON-Z15-1319 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Mar-24 23-Mar-24 6 207
GR-CON-Z15-1320 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jun-24
system 04-Jul-24 8 138
Parking P-09 23-Jan-24 04-Jul-24 126 138
Site Preparation 23-Jan-24 14-Feb-24 19 232
GR-CON-Z15-1323 Demolition (Asphalt.Paving,etc.....) 23-Jan-24 28-Jan-24 4 75
GR-CON-Z15-1324 Excavation And Disposal 28-Jan-24 03-Feb-24 5 126
GR-CON-Z15-1325 Prepretion And Compaction 03-Feb-24 07-Feb-24 4 232
GR-CON-Z15-1326 Backfilling 07-Feb-24 14-Feb-24 6 232
Curbstone and Paving 03-Feb-24 01-Apr-24 46 209
GR-CON-Z15-1327 Excavation Curbstone 03-Feb-24 08-Feb-24 5 201
GR-CON-Z15-1328 Plain Concrete 08-Feb-24 15-Feb-24 6 209
GR-CON-Z15-1329 Installation Curbstone 15-Feb-24 26-Feb-24 9 209
GR-CON-Z15-1330 Casting Concrete (Mortar haunch) 26-Feb-24 02-Mar-24 4 209
GR-CON-Z15-1331 Backfilling (sand / Sub base) 02-Mar-24 12-Mar-24 9 209
GR-CON-Z15-1332 Installation of Paving 12-Mar-24 01-Apr-24 13 209
Landscape Works 08-Feb-24 18-Jun-24 102 138
GR-CON-Z15-1333 Excavation (Tree Pit ) 08-Feb-24 14-Feb-24 5 201
GR-CON-Z15-1334 Aggregate Drainage layer 14-Feb-24 21-Feb-24 6 201
GR-CON-Z15-1335 Installation Geotextile 21-Feb-24 26-Feb-24 4 201
GR-CON-Z15-1336 Backfilling (Soil max for tree) 26-Feb-24 04-Mar-24 6 201
GR-CON-Z15-1337 Installation of Trees 28-May-24 01-Jun-24 3 138
GR-CON-Z15-8416 Installation of Shrubs 01-Jun-24 04-Jun-24 3 138
GR-CON-Z15-8426 Installation of Ground Covers 04-Jun-24 08-Jun-24 3 138
GR-CON-Z15-8436 Installation of Succulents 08-Jun-24 11-Jun-24 3 138
GR-CON-Z15-8446 Installation of Grass 11-Jun-24 15-Jun-24 3 138
GR-CON-Z15-1338 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 138
Site Furnishing 18-Jun-24 04-Jul-24 10 138
GR-CON-Z15-1349 Tree Grate 18-Jun-24 29-Jun-24 5 138
GR-CON-Z15-1350 Wheel stoppers 29-Jun-24 04-Jul-24 5 138
Irrigation Works 03-Feb-24 04-Jul-24 117 138
GR-CON-Z15-1341 Excavation Pipe Irrigation 03-Feb-24 08-Feb-24 5 126
GR-CON-Z15-1342 Sand Bedding 08-Feb-24 12-Feb-24 3 126
GR-CON-Z15-1343 HDPE Pipe Installations and fittings and conduit for cable 12-Feb-24 29-Feb-24 15 126
GR-CON-Z15-1345 Test pressure 29-Feb-24 06-Mar-24 5 126
GR-CON-Z15-1344 Installation of Valves and Accessories 06-Mar-24 11-Mar-24 4 126
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1346 Back filling (sand / Subbase ) 11-Mar-24 19-Mar-24 6 126


GR-CON-Z15-1347 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-Mar-24 28-Mar-24 6 203
GR-CON-Z15-1348 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jun-24
system 04-Jul-24 8 138
Street SS-11 28-Jan-24 05-Aug-24 149 111
Site Preparation 28-Jan-24 21-Feb-24 21 239
GR-CON-Z15-1379 Demolition (Asphalt.Paving,etc.....) 28-Jan-24 01-Feb-24 4 75
GR-CON-Z15-1380 Excavation And Disposal 01-Feb-24 07-Feb-24 5 121
GR-CON-Z15-1381 Prepretion And Compaction 07-Feb-24 14-Feb-24 6 239
GR-CON-Z15-1382 Backfilling 14-Feb-24 21-Feb-24 6 239
Curbstone and Paving 07-Feb-24 07-Apr-24 46 205
GR-CON-Z15-1383 Excavation Curbstone 07-Feb-24 13-Feb-24 5 170
GR-CON-Z15-1384 Plain Concrete 13-Feb-24 20-Feb-24 6 205
GR-CON-Z15-1385 Installation Curbstone 20-Feb-24 02-Mar-24 9 205
GR-CON-Z15-1386 Casting Concrete (Mortar haunch) 02-Mar-24 06-Mar-24 4 205
GR-CON-Z15-1387 Backfilling (sand / Sub base) 06-Mar-24 18-Mar-24 9 205
GR-CON-Z15-1388 Installation of Paving 18-Mar-24 07-Apr-24 13 205
Landscape Works 13-Feb-24 13-Jul-24 115 111
GR-CON-Z15-1389 Excavation (Tree Pit ) 13-Feb-24 19-Feb-24 5 170
GR-CON-Z15-1390 Aggregate Drainage layer 19-Feb-24 26-Feb-24 6 170
GR-CON-Z15-1391 Installation Geotextile 26-Feb-24 02-Mar-24 4 170
GR-CON-Z15-1392 Backfilling (Soil max for tree) 02-Mar-24 09-Mar-24 6 170
GR-CON-Z15-1393 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12576 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12586 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12596 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12606 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1394 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1395 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1396 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1405 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1406 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1407 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1408 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1409 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Activity ID Activity Name Start Finish Original Total Float
Duration

Irrigation Works 07-Feb-24 21-Apr-24 53 192


GR-CON-Z15-1397 Excavation Pipe Irrigation 07-Feb-24 13-Feb-24 5 121
GR-CON-Z15-1398 Sand Bedding 13-Feb-24 18-Feb-24 4 121
GR-CON-Z15-1399 HDPE Pipe Installations and fittings and conduit for cable 18-Feb-24 06-Mar-24 15 121
GR-CON-Z15-1401 Test pressure 06-Mar-24 12-Mar-24 5 121
GR-CON-Z15-1400 Installation of Valves and Accessories 12-Mar-24 18-Mar-24 4 121
GR-CON-Z15-1402 Back filling (sand / Subbase ) 18-Mar-24 27-Mar-24 6 121
GR-CON-Z15-1403 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-Mar-24 06-Apr-24 6 192
GR-CON-Z15-1404 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
06-Apr-24
system 21-Apr-24 8 192
Electrical Works 13-Feb-24 05-Aug-24 135 111
GR-CON-Z15-1410 Excavation And Disposal 13-Feb-24 19-Feb-24 5 219
GR-CON-Z15-1411 Sand Bedding 19-Feb-24 24-Feb-24 4 219
GR-CON-Z15-1412 laying cables 24-Feb-24 28-Feb-24 4 219
GR-CON-Z15-1413 Backfilling (sand / Sub base) 28-Feb-24 05-Mar-24 5 219
GR-CON-Z15-1414 Control Panel / Distribution Panel Installation 05-Mar-24 10-Mar-24 4 219
GR-CON-Z15-1415 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-15 01-Feb-24 26-Nov-24 241 15
Site Preparation 01-Feb-24 10-Mar-24 32 224
GR-CON-Z15-1416 Demolition (Asphalt.Paving,etc.....) 01-Feb-24 08-Feb-24 6 75
GR-CON-Z15-1417 Excavation And Disposal 08-Feb-24 18-Feb-24 8 88
GR-CON-Z15-1418 Prepretion And Compaction 18-Feb-24 28-Feb-24 9 224
GR-CON-Z15-1419 Backfilling 28-Feb-24 10-Mar-24 9 224
Curbstone and Paving 18-Feb-24 05-Jun-24 83 159
GR-CON-Z15-1420 Excavation Curbstone 18-Feb-24 29-Feb-24 10 107
GR-CON-Z15-1421 Plain Concrete 29-Feb-24 14-Mar-24 12 159
GR-CON-Z15-1422 Installation Curbstone 14-Mar-24 25-Apr-24 26 159
GR-CON-Z15-1423 Casting Concrete (Mortar haunch) 25-Apr-24 06-May-24 9 159
GR-CON-Z15-1424 Backfilling (sand / Sub base) 06-May-24 22-May-24 14 159
GR-CON-Z15-1425 Installation of Paving 06-May-24 05-Jun-24 26 159
Landscape Works 29-Feb-24 01-Aug-24 118 82
GR-CON-Z15-1426 Excavation (Tree Pit ) 29-Feb-24 12-Mar-24 10 107
GR-CON-Z15-1427 Aggregate Drainage layer 12-Mar-24 30-Mar-24 12 107
GR-CON-Z15-1428 Installation Geotextile 31-Mar-24 17-Apr-24 9 107
GR-CON-Z15-1429 Backfilling (Soil max for tree) 17-Apr-24 29-Apr-24 10 107
GR-CON-Z15-1430 Installation of Trees 28-May-24 08-Jun-24 9 82
GR-CON-Z15-12616 Installation of Shrubs 08-Jun-24 13-Jun-24 5 82
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-12626 Installation of Succulents 13-Jun-24 24-Jun-24 5 82


GR-CON-Z15-12636 Installation of Ground Covers 24-Jun-24 30-Jun-24 5 82
GR-CON-Z15-12646 Installation of Grass 30-Jun-24 06-Jul-24 5 82
GR-CON-Z15-1431 Backfilling (Mulch) 06-Jul-24 15-Jul-24 8 82
GR-CON-Z15-1432 Natural Boulders Installation 15-Jul-24 22-Jul-24 6 82
GR-CON-Z15-1433 Retaining walls . Steps, forming risers, treads and edges with finishes
15-Jul-24 01-Aug-24 15 82
Site Furnishing 01-Aug-24 26-Nov-24 99 15
GR-CON-Z15-1442 Garden planter box 01-Aug-24 11-Aug-24 8 82
GR-CON-Z15-1443 Wheel stoppers 29-Oct-24 07-Nov-24 8 15
GR-CON-Z15-1444 Steel Lattice 07-Nov-24 17-Nov-24 8 15
GR-CON-Z15-1445 Handrail 17-Nov-24 26-Nov-24 8 15
Storm Piping Works 16-Nov-24 26-Nov-24 9 15
GR-CON-Z15-1446 Installation of DI grating covers 16-Nov-24 26-Nov-24 9 15
Irrigation Works 18-Feb-24 06-Jun-24 84 149
GR-CON-Z15-1434 Excavation Pipe Irrigation 18-Feb-24 27-Feb-24 8 88
GR-CON-Z15-1435 Sand Bedding 27-Feb-24 05-Mar-24 6 88
GR-CON-Z15-1436 HDPE Pipe Installations and fittings and conduit for cable 05-Mar-24 11-Apr-24 26 88
GR-CON-Z15-1438 Test pressure 11-Apr-24 25-Apr-24 8 88
GR-CON-Z15-1437 Installation of Valves and Accessories 25-Apr-24 02-May-24 6 88
GR-CON-Z15-1439 Back filling (sand / Subbase ) 02-May-24 13-May-24 9 88
GR-CON-Z15-1440 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-May-24 23-May-24 9 149
GR-CON-Z15-1441 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-May-24
system 06-Jun-24 12 149
Electrical Works 27-Feb-24 26-Nov-24 219 15
GR-CON-Z15-1447 Excavation And Disposal 27-Feb-24 07-Mar-24 8 192
GR-CON-Z15-1448 Sand Bedding 07-Mar-24 14-Mar-24 6 192
GR-CON-Z15-1449 laying cables 14-Mar-24 24-Mar-24 6 192
GR-CON-Z15-1450 Backfilling (sand / Sub base) 24-Mar-24 06-Apr-24 8 192
GR-CON-Z15-1451 Control Panel / Distribution Panel Installation 06-Apr-24 18-Apr-24 6 192
GR-CON-Z15-1452 Road Crossing Ducts 17-Nov-24 26-Nov-24 8 15
Street SS-50.1 08-Feb-24 05-Aug-24 139 111
Site Preparation 08-Feb-24 04-Mar-24 21 229
GR-CON-Z15-1453 Demolition (Asphalt.Paving,etc.....) 08-Feb-24 13-Feb-24 4 75
GR-CON-Z15-1454 Excavation And Disposal 13-Feb-24 19-Feb-24 5 111
GR-CON-Z15-1455 Prepretion And Compaction 19-Feb-24 26-Feb-24 6 229
GR-CON-Z15-1456 Backfilling 26-Feb-24 04-Mar-24 6 229
Curbstone and Paving 19-Feb-24 24-Apr-24 46 195
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1457 Excavation Curbstone 19-Feb-24 25-Feb-24 5 160


GR-CON-Z15-1458 Plain Concrete 25-Feb-24 03-Mar-24 6 195
GR-CON-Z15-1459 Installation Curbstone 03-Mar-24 13-Mar-24 9 195
GR-CON-Z15-1460 Casting Concrete (Mortar haunch) 13-Mar-24 19-Mar-24 4 195
GR-CON-Z15-1461 Backfilling (sand / Sub base) 19-Mar-24 02-Apr-24 9 195
GR-CON-Z15-1462 Installation of Paving 02-Apr-24 24-Apr-24 13 195
Landscape Works 25-Feb-24 13-Jul-24 105 111
GR-CON-Z15-1463 Excavation (Tree Pit ) 25-Feb-24 02-Mar-24 5 160
GR-CON-Z15-1464 Aggregate Drainage layer 02-Mar-24 09-Mar-24 6 160
GR-CON-Z15-1465 Installation Geotextile 09-Mar-24 13-Mar-24 4 160
GR-CON-Z15-1466 Backfilling (Soil max for tree) 13-Mar-24 23-Mar-24 6 160
GR-CON-Z15-1467 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12656 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12666 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12676 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12686 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1468 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1469 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1470 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1479 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1480 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1481 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1482 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1483 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 19-Feb-24 02-May-24 53 182
GR-CON-Z15-1471 Excavation Pipe Irrigation 19-Feb-24 25-Feb-24 5 111
GR-CON-Z15-1472 Sand Bedding 25-Feb-24 29-Feb-24 4 111
GR-CON-Z15-1473 HDPE Pipe Installations and fittings and conduit for cable 29-Feb-24 19-Mar-24 15 111
GR-CON-Z15-1475 Test pressure 19-Mar-24 27-Mar-24 5 111
GR-CON-Z15-1474 Installation of Valves and Accessories 27-Mar-24 02-Apr-24 4 111
GR-CON-Z15-1476 Back filling (sand / Subbase ) 02-Apr-24 11-Apr-24 6 111
GR-CON-Z15-1477 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 11-Apr-24 23-Apr-24 6 182
GR-CON-Z15-1478 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
23-Apr-24
system 02-May-24 8 182
Electrical Works 25-Feb-24 05-Aug-24 125 111
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1484 Excavation And Disposal 25-Feb-24 02-Mar-24 5 209


GR-CON-Z15-1485 Sand Bedding 02-Mar-24 06-Mar-24 4 209
GR-CON-Z15-1486 laying cables 06-Mar-24 11-Mar-24 4 209
GR-CON-Z15-1487 Backfilling (sand / Sub base) 11-Mar-24 18-Mar-24 5 209
GR-CON-Z15-1488 Control Panel / Distribution Panel Installation 18-Mar-24 24-Mar-24 4 209
GR-CON-Z15-1489 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-54 13-Feb-24 05-Aug-24 135 111
Site Preparation 13-Feb-24 09-Mar-24 21 225
GR-CON-Z15-1490 Demolition (Asphalt.Paving,etc.....) 13-Feb-24 18-Feb-24 4 75
GR-CON-Z15-1491 Excavation And Disposal 18-Feb-24 24-Feb-24 5 107
GR-CON-Z15-1492 Prepretion And Compaction 24-Feb-24 02-Mar-24 6 225
GR-CON-Z15-1493 Backfilling 02-Mar-24 09-Mar-24 6 225
Curbstone and Paving 24-Feb-24 29-Apr-24 46 191
GR-CON-Z15-1494 Excavation Curbstone 24-Feb-24 29-Feb-24 5 156
GR-CON-Z15-1495 Plain Concrete 29-Feb-24 07-Mar-24 6 191
GR-CON-Z15-1496 Installation Curbstone 07-Mar-24 19-Mar-24 9 191
GR-CON-Z15-1497 Casting Concrete (Mortar haunch) 19-Mar-24 25-Mar-24 4 191
GR-CON-Z15-1498 Backfilling (sand / Sub base) 26-Mar-24 08-Apr-24 9 191
GR-CON-Z15-1499 Installation of Paving 09-Apr-24 29-Apr-24 13 191
Landscape Works 29-Feb-24 13-Jul-24 101 111
GR-CON-Z15-1500 Excavation (Tree Pit ) 29-Feb-24 06-Mar-24 5 156
GR-CON-Z15-1501 Aggregate Drainage layer 06-Mar-24 13-Mar-24 6 156
GR-CON-Z15-1502 Installation Geotextile 13-Mar-24 19-Mar-24 4 156
GR-CON-Z15-1503 Backfilling (Soil max for tree) 19-Mar-24 28-Mar-24 6 156
GR-CON-Z15-1504 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12696 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12706 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12716 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12726 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1505 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1506 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1507 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1516 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1517 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1518 Steel Lattice 24-Jul-24 30-Jul-24 5 111
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1519 Handrail 30-Jul-24 05-Aug-24 5 111


Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1520 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 24-Feb-24 07-May-24 53 178
GR-CON-Z15-1508 Excavation Pipe Irrigation 24-Feb-24 29-Feb-24 5 107
GR-CON-Z15-1509 Sand Bedding 29-Feb-24 05-Mar-24 4 107
GR-CON-Z15-1510 HDPE Pipe Installations and fittings and conduit for cable 05-Mar-24 25-Mar-24 15 107
GR-CON-Z15-1512 Test pressure 26-Mar-24 02-Apr-24 5 107
GR-CON-Z15-1511 Installation of Valves and Accessories 02-Apr-24 08-Apr-24 4 107
GR-CON-Z15-1513 Back filling (sand / Subbase ) 09-Apr-24 21-Apr-24 6 107
GR-CON-Z15-1514 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 21-Apr-24 28-Apr-24 6 178
GR-CON-Z15-1515 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
28-Apr-24
system 07-May-24 8 178
Electrical Works 29-Feb-24 05-Aug-24 121 111
GR-CON-Z15-1521 Excavation And Disposal 29-Feb-24 06-Mar-24 5 205
GR-CON-Z15-1522 Sand Bedding 06-Mar-24 11-Mar-24 4 205
GR-CON-Z15-1523 laying cables 11-Mar-24 16-Mar-24 4 205
GR-CON-Z15-1524 Backfilling (sand / Sub base) 17-Mar-24 24-Mar-24 5 205
GR-CON-Z15-1525 Control Panel / Distribution Panel Installation 24-Mar-24 30-Mar-24 4 205
GR-CON-Z15-1526 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-55 18-Feb-24 05-Aug-24 131 111
Site Preparation 18-Feb-24 13-Mar-24 21 221
GR-CON-Z15-1527 Demolition (Asphalt.Paving,etc.....) 18-Feb-24 22-Feb-24 4 75
GR-CON-Z15-1528 Excavation And Disposal 22-Feb-24 28-Feb-24 5 103
GR-CON-Z15-1529 Prepretion And Compaction 28-Feb-24 06-Mar-24 6 221
GR-CON-Z15-1530 Backfilling 06-Mar-24 13-Mar-24 6 221
Curbstone and Paving 28-Feb-24 04-May-24 46 187
GR-CON-Z15-1531 Excavation Curbstone 28-Feb-24 05-Mar-24 5 152
GR-CON-Z15-1532 Plain Concrete 05-Mar-24 12-Mar-24 6 187
GR-CON-Z15-1533 Installation Curbstone 12-Mar-24 25-Mar-24 9 187
GR-CON-Z15-1534 Casting Concrete (Mortar haunch) 26-Mar-24 01-Apr-24 4 187
GR-CON-Z15-1535 Backfilling (sand / Sub base) 01-Apr-24 18-Apr-24 9 187
GR-CON-Z15-1536 Installation of Paving 18-Apr-24 04-May-24 13 187
Landscape Works 05-Mar-24 13-Jul-24 97 111
GR-CON-Z15-1537 Excavation (Tree Pit ) 05-Mar-24 11-Mar-24 5 152
GR-CON-Z15-1538 Aggregate Drainage layer 11-Mar-24 19-Mar-24 6 152
GR-CON-Z15-1539 Installation Geotextile 19-Mar-24 25-Mar-24 4 152
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1540 Backfilling (Soil max for tree) 26-Mar-24 03-Apr-24 6 152


GR-CON-Z15-1541 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12736 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12746 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12756 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12766 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1542 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1543 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1544 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1553 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1554 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1555 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1556 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1557 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 28-Feb-24 12-May-24 53 174
GR-CON-Z15-1545 Excavation Pipe Irrigation 28-Feb-24 05-Mar-24 5 103
GR-CON-Z15-1546 Sand Bedding 05-Mar-24 10-Mar-24 4 103
GR-CON-Z15-1547 HDPE Pipe Installations and fittings and conduit for cable 10-Mar-24 01-Apr-24 15 103
GR-CON-Z15-1549 Test pressure 01-Apr-24 08-Apr-24 5 103
GR-CON-Z15-1548 Installation of Valves and Accessories 09-Apr-24 18-Apr-24 4 103
GR-CON-Z15-1550 Back filling (sand / Subbase ) 18-Apr-24 25-Apr-24 6 103
GR-CON-Z15-1551 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 25-Apr-24 02-May-24 6 174
GR-CON-Z15-1552 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
02-May-24
system 12-May-24 8 174
Electrical Works 05-Mar-24 05-Aug-24 117 111
GR-CON-Z15-1558 Excavation And Disposal 05-Mar-24 11-Mar-24 5 201
GR-CON-Z15-1559 Sand Bedding 11-Mar-24 16-Mar-24 4 201
GR-CON-Z15-1560 laying cables 17-Mar-24 23-Mar-24 4 201
GR-CON-Z15-1561 Backfilling (sand / Sub base) 23-Mar-24 30-Mar-24 5 201
GR-CON-Z15-1562 Control Panel / Distribution Panel Installation 31-Mar-24 06-Apr-24 4 201
GR-CON-Z15-1563 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-56 22-Feb-24 05-Aug-24 127 111
Site Preparation 22-Feb-24 19-Mar-24 21 217
GR-CON-Z15-1564 Demolition (Asphalt.Paving,etc.....) 22-Feb-24 27-Feb-24 4 75
GR-CON-Z15-1565 Excavation And Disposal 27-Feb-24 04-Mar-24 5 99
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1566 Prepretion And Compaction 04-Mar-24 11-Mar-24 6 217


GR-CON-Z15-1567 Backfilling 11-Mar-24 19-Mar-24 6 217
Curbstone and Paving 04-Mar-24 08-May-24 46 183
GR-CON-Z15-1568 Excavation Curbstone 04-Mar-24 10-Mar-24 5 148
GR-CON-Z15-1569 Plain Concrete 10-Mar-24 18-Mar-24 6 183
GR-CON-Z15-1570 Installation Curbstone 18-Mar-24 01-Apr-24 9 183
GR-CON-Z15-1571 Casting Concrete (Mortar haunch) 01-Apr-24 07-Apr-24 4 183
GR-CON-Z15-1572 Backfilling (sand / Sub base) 07-Apr-24 23-Apr-24 9 183
GR-CON-Z15-1573 Installation of Paving 23-Apr-24 08-May-24 13 183
Landscape Works 10-Mar-24 13-Jul-24 93 111
GR-CON-Z15-1574 Excavation (Tree Pit ) 10-Mar-24 16-Mar-24 5 148
GR-CON-Z15-1575 Aggregate Drainage layer 17-Mar-24 25-Mar-24 6 148
GR-CON-Z15-1576 Installation Geotextile 26-Mar-24 01-Apr-24 4 148
GR-CON-Z15-1577 Backfilling (Soil max for tree) 01-Apr-24 10-Apr-24 6 148
GR-CON-Z15-1578 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12776 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12786 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12796 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12806 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1579 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1580 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1581 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1590 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1591 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1592 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1593 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1594 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 04-Mar-24 16-May-24 53 170
GR-CON-Z15-1582 Excavation Pipe Irrigation 04-Mar-24 10-Mar-24 5 99
GR-CON-Z15-1583 Sand Bedding 10-Mar-24 14-Mar-24 4 99
GR-CON-Z15-1584 HDPE Pipe Installations and fittings and conduit for cable 14-Mar-24 07-Apr-24 15 99
GR-CON-Z15-1586 Test pressure 07-Apr-24 18-Apr-24 5 99
GR-CON-Z15-1585 Installation of Valves and Accessories 18-Apr-24 23-Apr-24 4 99
GR-CON-Z15-1587 Back filling (sand / Subbase ) 23-Apr-24 30-Apr-24 6 99
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1588 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 30-Apr-24 07-May-24 6 170
GR-CON-Z15-1589 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
07-May-24
system 16-May-24 8 170
Electrical Works 10-Mar-24 05-Aug-24 113 111
GR-CON-Z15-1595 Excavation And Disposal 10-Mar-24 16-Mar-24 5 197
GR-CON-Z15-1596 Sand Bedding 17-Mar-24 23-Mar-24 4 197
GR-CON-Z15-1597 laying cables 23-Mar-24 28-Mar-24 4 197
GR-CON-Z15-1598 Backfilling (sand / Sub base) 28-Mar-24 06-Apr-24 5 197
GR-CON-Z15-1599 Control Panel / Distribution Panel Installation 06-Apr-24 11-Apr-24 4 197
GR-CON-Z15-1600 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-57 27-Feb-24 05-Aug-24 123 111
Site Preparation 27-Feb-24 25-Mar-24 21 213
GR-CON-Z15-1601 Demolition (Asphalt.Paving,etc.....) 27-Feb-24 03-Mar-24 4 75
GR-CON-Z15-1602 Excavation And Disposal 03-Mar-24 09-Mar-24 5 95
GR-CON-Z15-1603 Prepretion And Compaction 09-Mar-24 16-Mar-24 6 213
GR-CON-Z15-1604 Backfilling 17-Mar-24 25-Mar-24 6 213
Curbstone and Paving 09-Mar-24 13-May-24 46 179
GR-CON-Z15-1605 Excavation Curbstone 09-Mar-24 14-Mar-24 5 144
GR-CON-Z15-1606 Plain Concrete 14-Mar-24 24-Mar-24 6 179
GR-CON-Z15-1607 Installation Curbstone 24-Mar-24 07-Apr-24 9 179
GR-CON-Z15-1608 Casting Concrete (Mortar haunch) 07-Apr-24 17-Apr-24 4 179
GR-CON-Z15-1609 Backfilling (sand / Sub base) 17-Apr-24 28-Apr-24 9 179
GR-CON-Z15-1610 Installation of Paving 28-Apr-24 13-May-24 13 179
Landscape Works 14-Mar-24 13-Jul-24 89 111
GR-CON-Z15-1611 Excavation (Tree Pit ) 14-Mar-24 23-Mar-24 5 144
GR-CON-Z15-1612 Aggregate Drainage layer 23-Mar-24 01-Apr-24 6 144
GR-CON-Z15-1613 Installation Geotextile 01-Apr-24 07-Apr-24 4 144
GR-CON-Z15-1614 Backfilling (Soil max for tree) 07-Apr-24 20-Apr-24 6 144
GR-CON-Z15-1615 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12816 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12826 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12836 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12846 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1616 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1617 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1618 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1627 Garden planter box 13-Jul-24 18-Jul-24 5 111


GR-CON-Z15-1628 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1629 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1630 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1631 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 09-Mar-24 21-May-24 53 166
GR-CON-Z15-1619 Excavation Pipe Irrigation 09-Mar-24 14-Mar-24 5 95
GR-CON-Z15-1620 Sand Bedding 14-Mar-24 20-Mar-24 4 95
GR-CON-Z15-1621 HDPE Pipe Installations and fittings and conduit for cable 21-Mar-24 17-Apr-24 15 95
GR-CON-Z15-1623 Test pressure 17-Apr-24 23-Apr-24 5 95
GR-CON-Z15-1622 Installation of Valves and Accessories 23-Apr-24 28-Apr-24 4 95
GR-CON-Z15-1624 Back filling (sand / Subbase ) 28-Apr-24 05-May-24 6 95
GR-CON-Z15-1625 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 05-May-24 12-May-24 6 166
GR-CON-Z15-1626 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
12-May-24
system 21-May-24 8 166
Electrical Works 14-Mar-24 05-Aug-24 109 111
GR-CON-Z15-1632 Excavation And Disposal 14-Mar-24 23-Mar-24 5 193
GR-CON-Z15-1633 Sand Bedding 23-Mar-24 28-Mar-24 4 193
GR-CON-Z15-1634 laying cables 28-Mar-24 03-Apr-24 4 193
GR-CON-Z15-1635 Backfilling (sand / Sub base) 04-Apr-24 11-Apr-24 5 193
GR-CON-Z15-1636 Control Panel / Distribution Panel Installation 11-Apr-24 21-Apr-24 4 193
GR-CON-Z15-1637 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-58 03-Mar-24 05-Aug-24 119 111
Site Preparation 03-Mar-24 01-Apr-24 21 209
GR-CON-Z15-1638 Demolition (Asphalt.Paving,etc.....) 03-Mar-24 07-Mar-24 4 75
GR-CON-Z15-1639 Excavation And Disposal 07-Mar-24 13-Mar-24 5 91
GR-CON-Z15-1640 Prepretion And Compaction 13-Mar-24 23-Mar-24 6 209
GR-CON-Z15-1641 Backfilling 23-Mar-24 01-Apr-24 6 209
Curbstone and Paving 13-Mar-24 18-May-24 46 175
GR-CON-Z15-1642 Excavation Curbstone 13-Mar-24 20-Mar-24 5 140
GR-CON-Z15-1643 Plain Concrete 21-Mar-24 30-Mar-24 6 175
GR-CON-Z15-1644 Installation Curbstone 31-Mar-24 17-Apr-24 9 175
GR-CON-Z15-1645 Casting Concrete (Mortar haunch) 17-Apr-24 22-Apr-24 4 175
GR-CON-Z15-1646 Backfilling (sand / Sub base) 22-Apr-24 02-May-24 9 175
GR-CON-Z15-1647 Installation of Paving 02-May-24 18-May-24 13 175
Landscape Works 21-Mar-24 13-Jul-24 85 111
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1648 Excavation (Tree Pit ) 21-Mar-24 28-Mar-24 5 140


GR-CON-Z15-1649 Aggregate Drainage layer 28-Mar-24 07-Apr-24 6 140
GR-CON-Z15-1650 Installation Geotextile 07-Apr-24 17-Apr-24 4 140
GR-CON-Z15-1651 Backfilling (Soil max for tree) 17-Apr-24 24-Apr-24 6 140
GR-CON-Z15-1652 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12856 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12866 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12876 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12886 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1653 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1654 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1655 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1664 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1665 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1666 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1667 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1668 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 13-Mar-24 26-May-24 53 162
GR-CON-Z15-1656 Excavation Pipe Irrigation 13-Mar-24 20-Mar-24 5 91
GR-CON-Z15-1657 Sand Bedding 21-Mar-24 27-Mar-24 4 91
GR-CON-Z15-1658 HDPE Pipe Installations and fittings and conduit for cable 27-Mar-24 22-Apr-24 15 91
GR-CON-Z15-1660 Test pressure 22-Apr-24 28-Apr-24 5 91
GR-CON-Z15-1659 Installation of Valves and Accessories 28-Apr-24 02-May-24 4 91
GR-CON-Z15-1661 Back filling (sand / Subbase ) 02-May-24 09-May-24 6 91
GR-CON-Z15-1662 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-May-24 16-May-24 6 162
GR-CON-Z15-1663 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
16-May-24
system 26-May-24 8 162
Electrical Works 21-Mar-24 05-Aug-24 105 111
GR-CON-Z15-1669 Excavation And Disposal 21-Mar-24 28-Mar-24 5 189
GR-CON-Z15-1670 Sand Bedding 28-Mar-24 03-Apr-24 4 189
GR-CON-Z15-1671 laying cables 04-Apr-24 10-Apr-24 4 189
GR-CON-Z15-1672 Backfilling (sand / Sub base) 10-Apr-24 21-Apr-24 5 189
GR-CON-Z15-1673 Control Panel / Distribution Panel Installation 21-Apr-24 25-Apr-24 4 189
GR-CON-Z15-1674 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-80 07-Mar-24 05-Aug-24 115 111
Activity ID Activity Name Start Finish Original Total Float
Duration

Site Preparation 07-Mar-24 07-Apr-24 21 205


GR-CON-Z15-1675 Demolition (Asphalt.Paving,etc.....) 07-Mar-24 12-Mar-24 4 75
GR-CON-Z15-1676 Excavation And Disposal 12-Mar-24 19-Mar-24 5 87
GR-CON-Z15-1677 Prepretion And Compaction 19-Mar-24 28-Mar-24 6 205
GR-CON-Z15-1678 Backfilling 28-Mar-24 07-Apr-24 6 205
Curbstone and Paving 19-Mar-24 22-May-24 46 171
GR-CON-Z15-1679 Excavation Curbstone 19-Mar-24 27-Mar-24 5 136
GR-CON-Z15-1680 Plain Concrete 27-Mar-24 06-Apr-24 6 171
GR-CON-Z15-1681 Installation Curbstone 06-Apr-24 22-Apr-24 9 171
GR-CON-Z15-1682 Casting Concrete (Mortar haunch) 22-Apr-24 27-Apr-24 4 171
GR-CON-Z15-1683 Backfilling (sand / Sub base) 27-Apr-24 07-May-24 9 171
GR-CON-Z15-1684 Installation of Paving 07-May-24 22-May-24 13 171
Landscape Works 27-Mar-24 13-Jul-24 81 111
GR-CON-Z15-1685 Excavation (Tree Pit ) 27-Mar-24 03-Apr-24 5 136
GR-CON-Z15-1686 Aggregate Drainage layer 04-Apr-24 17-Apr-24 6 136
GR-CON-Z15-1687 Installation Geotextile 17-Apr-24 22-Apr-24 4 136
GR-CON-Z15-1688 Backfilling (Soil max for tree) 22-Apr-24 29-Apr-24 6 136
GR-CON-Z15-1689 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12896 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12906 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12916 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12926 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1690 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1691 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1692 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1701 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1702 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1703 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1704 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1705 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 19-Mar-24 30-May-24 53 158
GR-CON-Z15-1693 Excavation Pipe Irrigation 19-Mar-24 27-Mar-24 5 87
GR-CON-Z15-1694 Sand Bedding 27-Mar-24 02-Apr-24 4 87
GR-CON-Z15-1695 HDPE Pipe Installations and fittings and conduit for cable 02-Apr-24 27-Apr-24 15 87
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1697 Test pressure 27-Apr-24 02-May-24 5 87


GR-CON-Z15-1696 Installation of Valves and Accessories 02-May-24 07-May-24 4 87
GR-CON-Z15-1698 Back filling (sand / Subbase ) 07-May-24 14-May-24 6 87
GR-CON-Z15-1699 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 14-May-24 21-May-24 6 158
GR-CON-Z15-1700 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
21-May-24
system 30-May-24 8 158
Electrical Works 27-Mar-24 05-Aug-24 101 111
GR-CON-Z15-1706 Excavation And Disposal 27-Mar-24 03-Apr-24 5 185
GR-CON-Z15-1707 Sand Bedding 04-Apr-24 10-Apr-24 4 185
GR-CON-Z15-1708 laying cables 10-Apr-24 20-Apr-24 4 185
GR-CON-Z15-1709 Backfilling (sand / Sub base) 20-Apr-24 25-Apr-24 5 185
GR-CON-Z15-1710 Control Panel / Distribution Panel Installation 25-Apr-24 30-Apr-24 4 185
GR-CON-Z15-1711 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-81 12-Mar-24 05-Aug-24 111 111
Site Preparation 12-Mar-24 17-Apr-24 21 201
GR-CON-Z15-1712 Demolition (Asphalt.Paving,etc.....) 12-Mar-24 18-Mar-24 4 75
GR-CON-Z15-1713 Excavation And Disposal 18-Mar-24 25-Mar-24 5 83
GR-CON-Z15-1714 Prepretion And Compaction 26-Mar-24 03-Apr-24 6 201
GR-CON-Z15-1715 Backfilling 04-Apr-24 17-Apr-24 6 201
Curbstone and Paving 26-Mar-24 27-May-24 46 167
GR-CON-Z15-1716 Excavation Curbstone 26-Mar-24 02-Apr-24 5 132
GR-CON-Z15-1717 Plain Concrete 02-Apr-24 11-Apr-24 6 167
GR-CON-Z15-1718 Installation Curbstone 11-Apr-24 27-Apr-24 9 167
GR-CON-Z15-1719 Casting Concrete (Mortar haunch) 27-Apr-24 01-May-24 4 167
GR-CON-Z15-1720 Backfilling (sand / Sub base) 01-May-24 12-May-24 9 167
GR-CON-Z15-1721 Installation of Paving 12-May-24 27-May-24 13 167
Landscape Works 02-Apr-24 13-Jul-24 77 111
GR-CON-Z15-1722 Excavation (Tree Pit ) 02-Apr-24 10-Apr-24 5 132
GR-CON-Z15-1723 Aggregate Drainage layer 10-Apr-24 22-Apr-24 6 132
GR-CON-Z15-1724 Installation Geotextile 22-Apr-24 27-Apr-24 4 132
GR-CON-Z15-1725 Backfilling (Soil max for tree) 27-Apr-24 04-May-24 6 132
GR-CON-Z15-1726 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12936 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12946 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12956 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-12966 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1727 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1728 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111


GR-CON-Z15-1729 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1738 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1739 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1740 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1741 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1742 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 26-Mar-24 04-Jun-24 53 154
GR-CON-Z15-1730 Excavation Pipe Irrigation 26-Mar-24 02-Apr-24 5 83
GR-CON-Z15-1731 Sand Bedding 02-Apr-24 08-Apr-24 4 83
GR-CON-Z15-1732 HDPE Pipe Installations and fittings and conduit for cable 09-Apr-24 01-May-24 15 83
GR-CON-Z15-1734 Test pressure 01-May-24 07-May-24 5 83
GR-CON-Z15-1733 Installation of Valves and Accessories 07-May-24 12-May-24 4 83
GR-CON-Z15-1735 Back filling (sand / Subbase ) 12-May-24 19-May-24 6 83
GR-CON-Z15-1736 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 19-May-24 26-May-24 6 154
GR-CON-Z15-1737 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
26-May-24
system 04-Jun-24 8 154
Electrical Works 02-Apr-24 05-Aug-24 97 111
GR-CON-Z15-1743 Excavation And Disposal 02-Apr-24 10-Apr-24 5 181
GR-CON-Z15-1744 Sand Bedding 10-Apr-24 20-Apr-24 4 181
GR-CON-Z15-1745 laying cables 20-Apr-24 24-Apr-24 4 181
GR-CON-Z15-1746 Backfilling (sand / Sub base) 24-Apr-24 30-Apr-24 5 181
GR-CON-Z15-1747 Control Panel / Distribution Panel Installation 30-Apr-24 05-May-24 4 181
GR-CON-Z15-1748 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-82 18-Mar-24 05-Aug-24 107 111
Site Preparation 18-Mar-24 22-Apr-24 21 197
GR-CON-Z15-1749 Demolition (Asphalt.Paving,etc.....) 18-Mar-24 24-Mar-24 4 75
GR-CON-Z15-1750 Excavation And Disposal 24-Mar-24 01-Apr-24 5 79
GR-CON-Z15-1751 Prepretion And Compaction 01-Apr-24 10-Apr-24 6 197
GR-CON-Z15-1752 Backfilling 10-Apr-24 22-Apr-24 6 197
Curbstone and Paving 01-Apr-24 01-Jun-24 46 163
GR-CON-Z15-1753 Excavation Curbstone 01-Apr-24 08-Apr-24 5 128
GR-CON-Z15-1754 Plain Concrete 09-Apr-24 21-Apr-24 6 163
GR-CON-Z15-1755 Installation Curbstone 21-Apr-24 01-May-24 9 163
GR-CON-Z15-1756 Casting Concrete (Mortar haunch) 01-May-24 06-May-24 4 163
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1757 Backfilling (sand / Sub base) 06-May-24 16-May-24 9 163


GR-CON-Z15-1758 Installation of Paving 16-May-24 01-Jun-24 13 163
Landscape Works 09-Apr-24 13-Jul-24 73 111
GR-CON-Z15-1759 Excavation (Tree Pit ) 09-Apr-24 20-Apr-24 5 128
GR-CON-Z15-1760 Aggregate Drainage layer 20-Apr-24 27-Apr-24 6 128
GR-CON-Z15-1761 Installation Geotextile 27-Apr-24 01-May-24 4 128
GR-CON-Z15-1762 Backfilling (Soil max for tree) 01-May-24 08-May-24 6 128
GR-CON-Z15-1763 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-12976 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-12986 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-12996 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-13006 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1764 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1765 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1766 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1775 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1776 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1777 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1778 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1779 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 01-Apr-24 09-Jun-24 53 150
GR-CON-Z15-1767 Excavation Pipe Irrigation 01-Apr-24 08-Apr-24 5 79
GR-CON-Z15-1768 Sand Bedding 09-Apr-24 18-Apr-24 4 79
GR-CON-Z15-1769 HDPE Pipe Installations and fittings and conduit for cable 18-Apr-24 06-May-24 15 79
GR-CON-Z15-1771 Test pressure 06-May-24 12-May-24 5 79
GR-CON-Z15-1770 Installation of Valves and Accessories 12-May-24 16-May-24 4 79
GR-CON-Z15-1772 Back filling (sand / Subbase ) 16-May-24 23-May-24 6 79
GR-CON-Z15-1773 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 23-May-24 30-May-24 6 150
GR-CON-Z15-1774 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
30-May-24
system 09-Jun-24 8 150
Electrical Works 09-Apr-24 05-Aug-24 93 111
GR-CON-Z15-1780 Excavation And Disposal 09-Apr-24 20-Apr-24 5 177
GR-CON-Z15-1781 Sand Bedding 20-Apr-24 24-Apr-24 4 177
GR-CON-Z15-1782 laying cables 24-Apr-24 29-Apr-24 4 177
GR-CON-Z15-1783 Backfilling (sand / Sub base) 29-Apr-24 05-May-24 5 177
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1784 Control Panel / Distribution Panel Installation 05-May-24 09-May-24 4 177


GR-CON-Z15-1785 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
Street SS-83 24-Mar-24 05-Aug-24 103 111
Site Preparation 24-Mar-24 27-Apr-24 21 193
GR-CON-Z15-1786 Demolition (Asphalt.Paving,etc.....) 24-Mar-24 30-Mar-24 4 75
GR-CON-Z15-1787 Excavation And Disposal 31-Mar-24 07-Apr-24 5 75
GR-CON-Z15-1788 Prepretion And Compaction 07-Apr-24 20-Apr-24 6 193
GR-CON-Z15-1789 Backfilling 20-Apr-24 27-Apr-24 6 193
Curbstone and Paving 07-Apr-24 05-Jun-24 46 159
GR-CON-Z15-1790 Excavation Curbstone 07-Apr-24 18-Apr-24 5 124
GR-CON-Z15-1791 Plain Concrete 18-Apr-24 25-Apr-24 6 159
GR-CON-Z15-1792 Installation Curbstone 25-Apr-24 06-May-24 9 159
GR-CON-Z15-1793 Casting Concrete (Mortar haunch) 06-May-24 11-May-24 4 159
GR-CON-Z15-1794 Backfilling (sand / Sub base) 11-May-24 21-May-24 9 159
GR-CON-Z15-1795 Installation of Paving 21-May-24 05-Jun-24 13 159
Landscape Works 18-Apr-24 13-Jul-24 69 111
GR-CON-Z15-1796 Excavation (Tree Pit ) 18-Apr-24 24-Apr-24 5 124
GR-CON-Z15-1797 Aggregate Drainage layer 24-Apr-24 01-May-24 6 124
GR-CON-Z15-1798 Installation Geotextile 01-May-24 06-May-24 4 124
GR-CON-Z15-1799 Backfilling (Soil max for tree) 06-May-24 13-May-24 6 124
GR-CON-Z15-1800 Installation of Trees 28-May-24 01-Jun-24 3 111
GR-CON-Z15-13016 Installation of Shrubs 01-Jun-24 04-Jun-24 3 111
GR-CON-Z15-13026 Installation of Succulents 04-Jun-24 08-Jun-24 3 111
GR-CON-Z15-13036 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 111
GR-CON-Z15-13046 Installation of Grass 11-Jun-24 15-Jun-24 3 111
GR-CON-Z15-1801 Backfilling (Mulch) 15-Jun-24 18-Jun-24 3 111
GR-CON-Z15-1802 Natural Boulders Installation 18-Jun-24 27-Jun-24 4 111
GR-CON-Z15-1803 Retaining walls . Steps, forming risers, treads and edges with finishes
27-Jun-24 13-Jul-24 13 111
Site Furnishing 13-Jul-24 05-Aug-24 20 111
GR-CON-Z15-1812 Garden planter box 13-Jul-24 18-Jul-24 5 111
GR-CON-Z15-1813 Wheel stoppers 18-Jul-24 24-Jul-24 5 111
GR-CON-Z15-1814 Steel Lattice 24-Jul-24 30-Jul-24 5 111
GR-CON-Z15-1815 Handrail 30-Jul-24 05-Aug-24 5 111
Storm Piping Works 29-Jul-24 05-Aug-24 6 111
GR-CON-Z15-1816 Installation of DI grating covers 29-Jul-24 05-Aug-24 6 111
Irrigation Works 07-Apr-24 13-Jun-24 53 146
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1804 Excavation Pipe Irrigation 07-Apr-24 18-Apr-24 5 75


GR-CON-Z15-1805 Sand Bedding 18-Apr-24 23-Apr-24 4 75
GR-CON-Z15-1806 HDPE Pipe Installations and fittings and conduit for cable 23-Apr-24 11-May-24 15 75
GR-CON-Z15-1808 Test pressure 11-May-24 16-May-24 5 75
GR-CON-Z15-1807 Installation of Valves and Accessories 16-May-24 21-May-24 4 75
GR-CON-Z15-1809 Back filling (sand / Subbase ) 21-May-24 28-May-24 6 75
GR-CON-Z15-1810 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 28-May-24 04-Jun-24 6 146
GR-CON-Z15-1811 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
04-Jun-24
system 13-Jun-24 8 146
Electrical Works 18-Apr-24 05-Aug-24 89 111
GR-CON-Z15-1817 Excavation And Disposal 18-Apr-24 24-Apr-24 5 173
GR-CON-Z15-1818 Sand Bedding 24-Apr-24 29-Apr-24 4 173
GR-CON-Z15-1819 laying cables 29-Apr-24 04-May-24 4 173
GR-CON-Z15-1820 Backfilling (sand / Sub base) 04-May-24 09-May-24 5 173
GR-CON-Z15-1821 Control Panel / Distribution Panel Installation 09-May-24 14-May-24 4 173
GR-CON-Z15-1822 Road Crossing Ducts 30-Jul-24 05-Aug-24 5 111
School S-06 31-Mar-24 31-Jul-24 95 115
Site Preparation 31-Mar-24 17-Apr-24 9 201
GR-CON-Z15-1352 Excavation And Disposal 31-Mar-24 07-Apr-24 5 76
GR-CON-Z15-1353 Prepretion And Compaction 07-Apr-24 17-Apr-24 4 201
Curbstone and Paving 07-Apr-24 05-Jun-24 46 159
GR-CON-Z15-1355 Excavation Curbstone 07-Apr-24 18-Apr-24 5 128
GR-CON-Z15-1356 Plain Concrete 18-Apr-24 25-Apr-24 6 159
GR-CON-Z15-1357 Installation Curbstone 25-Apr-24 06-May-24 9 159
GR-CON-Z15-1358 Casting Concrete (Mortar haunch) 06-May-24 11-May-24 4 159
GR-CON-Z15-1359 Backfilling (sand / Sub base) 11-May-24 21-May-24 9 159
GR-CON-Z15-1360 Installation of Paving 21-May-24 05-Jun-24 13 159
Landscape Works 18-Apr-24 20-Jul-24 75 115
GR-CON-Z15-1361 Excavation (Tree Pit ) 18-Apr-24 24-Apr-24 5 128
GR-CON-Z15-1362 Aggregate Drainage layer 24-Apr-24 01-May-24 6 128
GR-CON-Z15-1363 Installation Geotextile 01-May-24 06-May-24 4 128
GR-CON-Z15-1364 Backfilling (Soil max for tree) 06-May-24 13-May-24 6 128
GR-CON-Z15-1365 Installation of Trees 28-May-24 01-Jun-24 3 115
GR-CON-Z15-5836 Installation of Shrubs 01-Jun-24 04-Jun-24 3 115
GR-CON-Z15-5846 Installation of Succulents 04-Jun-24 08-Jun-24 3 115
GR-CON-Z15-5856 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 115
GR-CON-Z15-5866 Installation of Climbers 11-Jun-24 15-Jun-24 3 115
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-5876 Installation of Grass 15-Jun-24 18-Jun-24 3 115


GR-CON-Z15-5886 Installation of Lawns 18-Jun-24 26-Jun-24 3 115
GR-CON-Z15-1366 Backfilling (Mulch) 26-Jun-24 30-Jun-24 3 115
GR-CON-Z15-1367 Natural Boulders Installation 30-Jun-24 04-Jul-24 4 115
GR-CON-Z15-1368 Retaining walls . Steps, forming risers, treads and edges with finishes
04-Jul-24 20-Jul-24 13 115
Site Furnishing 20-Jul-24 31-Jul-24 10 115
GR-CON-Z15-1377 Garden planter box 20-Jul-24 25-Jul-24 5 115
GR-CON-Z15-1378 Wheel stoppers 25-Jul-24 31-Jul-24 5 115
Irrigation Works 07-Apr-24 31-Jul-24 90 115
GR-CON-Z15-1369 Excavation Pipe Irrigation 07-Apr-24 18-Apr-24 5 76
GR-CON-Z15-1370 Sand Bedding 18-Apr-24 22-Apr-24 3 76
GR-CON-Z15-1371 HDPE Pipe Installations and fittings and conduit for cable 22-Apr-24 09-May-24 15 76
GR-CON-Z15-1373 Test pressure 09-May-24 15-May-24 5 76
GR-CON-Z15-1372 Installation of Valves and Accessories 15-May-24 20-May-24 4 76
GR-CON-Z15-1374 Back filling (sand / Subbase ) 20-May-24 27-May-24 6 76
GR-CON-Z15-1375 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 27-May-24 03-Jun-24 6 153
GR-CON-Z15-1376 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
22-Jul-24
system 31-Jul-24 8 115
Toilet - 05 26-Dec-23 30-Oct-24 250 38
Site Preparation 26-Dec-23 07-Jan-24 10 38
GR-CON-Z15-1000 Excavation And Disposal 26-Dec-23 01-Jan-24 5 38
GR-CON-Z15-1001 Backfilling (one layer) 01-Jan-24 07-Jan-24 5 38
Civil Works 07-Jan-24 02-Jun-24 116 38
GR-CON-Z15-1002 Polyethylene Under Footings, Grade Slab and Beams 07-Jan-24 10-Jan-24 3 38
GR-CON-Z15-1003 Blinding concrete 10-Jan-24 16-Jan-24 5 38
GR-CON-Z15-1004 Footings 16-Jan-24 25-Jan-24 8 38
GR-CON-Z15-1005 Waterproofing Under Footing 25-Jan-24 31-Jan-24 5 38
GR-CON-Z15-1006 Column Necks 31-Jan-24 07-Feb-24 6 38
GR-CON-Z15-1007 Waterproofing (Toilet) 07-Feb-24 18-Feb-24 9 38
GR-CON-Z15-1008 Backfilling 18-Feb-24 25-Feb-24 6 38
GR-CON-Z15-1009 Ground beams 25-Feb-24 11-Mar-24 13 38
GR-CON-Z15-1010 Slab on grade 11-Mar-24 07-Apr-24 18 38
GR-CON-Z15-1011 Columns 07-Apr-24 28-Apr-24 13 38
GR-CON-Z15-1012 Concrete, slabs Ground floor 28-Apr-24 22-May-24 21 38
GR-CON-Z15-1013 Roof Thermal And Moisture Protection Work 22-May-24 02-Jun-24 9 38
Architectural Works 02-Jun-24 30-Oct-24 124 38
GR-CON-Z15-1014 Blockwork 02-Jun-24 29-Jun-24 19 38
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1015 Waterproofing 08-Jul-24 18-Jul-24 9 38


GR-CON-Z15-1016 Back Filling (sand) 18-Jul-24 24-Jul-24 5 38
GR-CON-Z15-1017 Floor finish 24-Jul-24 08-Aug-24 13 38
GR-CON-Z15-1018 Wall Finish 29-Jul-24 27-Aug-24 25 38
GR-CON-Z15-1019 Door Installation 27-Aug-24 01-Sep-24 4 38
GR-CON-Z15-1021 Celling finish 01-Sep-24 16-Sep-24 13 38
GR-CON-Z15-1022 ToiletAccessories 16-Sep-24 21-Sep-24 4 38
GR-CON-Z15-1023 Facade Finishing Works 21-Sep-24 14-Oct-24 19 38
GR-CON-Z15-1024 Metal Work 30-Sep-24 22-Oct-24 19 38
GR-CON-Z15-1025 Wood Work 08-Oct-24 30-Oct-24 19 38
Mechanical Works 29-Jun-24 30-Oct-24 105 38
GR-CON-Z15-1026 Pipework Installations and fittings 29-Jun-24 08-Jul-24 8 38
GR-CON-Z15-1027 Installation of refrigerant supply/return pipework 29-Jun-24 03-Jul-24 4 89
GR-CON-Z15-1029 Water Meter With Meter Cabinet 29-Jun-24 02-Jul-24 3 130
GR-CON-Z15-1028 Installation of Sanitary Fixtures 08-Aug-24 18-Aug-24 8 50
GR-CON-Z15-1031 Installation of Exhaust Equipmets and Air outlets 19-Oct-24 30-Oct-24 10 38
Electrical Works 29-Jun-24 30-Oct-24 105 38
GR-CON-Z15-1032 Conduits Installation 29-Jun-24 04-Jul-24 5 59
GR-CON-Z15-1034 Earthing and lightning protection system 04-Jul-24 09-Jul-24 4 109
GR-CON-Z15-1033 Install of power cables 27-Aug-24 31-Aug-24 3 39
GR-CON-Z15-1035 Installation of wiring devices and lighting fixtures 27-Aug-24 02-Sep-24 5 67
GR-CON-Z15-1036 Installation of Alarm with park BMS system 02-Sep-24 08-Sep-24 5 67
GR-CON-Z15-1030 Installation of Fire Detection System 08-Sep-24 17-Sep-24 8 67
GR-CON-Z15-1037 Installation of Panel Board 17-Sep-24 22-Sep-24 4 67
GR-CON-Z15-1038 Connecting to nearest feeder pillar 27-Oct-24 30-Oct-24 3 38
Health H-02 01-Jan-24 04-Jul-24 145 138
Site Preparation 01-Jan-24 18-Jan-24 15 268
GR-CON-Z15-1076 Excavation And Disposal 01-Jan-24 07-Jan-24 5 109
GR-CON-Z15-1077 Prepretion And Compaction 07-Jan-24 11-Jan-24 4 268
GR-CON-Z15-1078 Backfilling 11-Jan-24 18-Jan-24 6 268
Curbstone and Paving 07-Jan-24 29-Feb-24 46 232
GR-CON-Z15-1079 Excavation Curbstone 07-Jan-24 13-Jan-24 5 224
GR-CON-Z15-1080 Plain Concrete 13-Jan-24 20-Jan-24 6 232
GR-CON-Z15-1081 Installation Curbstone 20-Jan-24 30-Jan-24 9 232
GR-CON-Z15-1082 Casting Concrete (Mortar haunch) 30-Jan-24 04-Feb-24 4 232
GR-CON-Z15-1083 Backfilling (sand / Sub base) 04-Feb-24 14-Feb-24 9 232
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1084 Installation of Paving 14-Feb-24 29-Feb-24 13 232


Landscape Works 13-Jan-24 04-Jul-24 135 138
GR-CON-Z15-1085 Excavation (Tree Pit ) 13-Jan-24 18-Jan-24 5 224
GR-CON-Z15-1086 Aggregate Drainage layer 18-Jan-24 25-Jan-24 6 224
GR-CON-Z15-1087 Installation Geotextile 25-Jan-24 30-Jan-24 4 224
GR-CON-Z15-1088 Backfilling (Soil max for tree) 30-Jan-24 06-Feb-24 6 224
GR-CON-Z15-1089 Installation of Trees 28-May-24 01-Jun-24 3 138
GR-CON-Z15-6436 Installation of Shrubs 01-Jun-24 04-Jun-24 3 138
GR-CON-Z15-6446 Installation of Succulents 04-Jun-24 08-Jun-24 3 138
GR-CON-Z15-6456 Installation of Ground Covers 08-Jun-24 11-Jun-24 3 138
GR-CON-Z15-6466 Installation of Climbers 11-Jun-24 15-Jun-24 3 138
GR-CON-Z15-6476 Installation of Grass 15-Jun-24 18-Jun-24 3 138
GR-CON-Z15-6486 Installation of Lawns 18-Jun-24 26-Jun-24 3 138
GR-CON-Z15-1090 Backfilling (Mulch) 26-Jun-24 30-Jun-24 3 138
GR-CON-Z15-1091 Natural Boulders Installation 30-Jun-24 04-Jul-24 4 138
Irrigation Works 07-Jan-24 04-Jul-24 140 138
GR-CON-Z15-1093 Excavation Pipe Irrigation 07-Jan-24 13-Jan-24 5 109
GR-CON-Z15-1094 Sand Bedding 13-Jan-24 16-Jan-24 3 109
GR-CON-Z15-1095 HDPE Pipe Installations and fittings and conduit for cable 16-Jan-24 03-Feb-24 15 109
GR-CON-Z15-1097 Test pressure 03-Feb-24 08-Feb-24 5 109
GR-CON-Z15-1096 Installation of Valves and Accessories 08-Feb-24 13-Feb-24 4 109
GR-CON-Z15-1098 Back filling (sand / Subbase ) 13-Feb-24 20-Feb-24 6 109
GR-CON-Z15-1099 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 20-Feb-24 27-Feb-24 6 226
GR-CON-Z15-1100 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jun-24
system 04-Jul-24 8 138
Existing Neighborhood Park ENP-04 07-Jan-24 09-Jul-24 144 134
Site Preparation 07-Jan-24 11-Feb-24 30 248
GR-CON-Z15-1039 Demolition (Asphalt.Paving,etc.....) 07-Jan-24 14-Jan-24 6 113
GR-CON-Z15-1040 Excavation And Disposal 14-Jan-24 23-Jan-24 8 113
GR-CON-Z15-1041 Prepretion And Compaction 23-Jan-24 30-Jan-24 6 248
GR-CON-Z15-1042 Backfilling 30-Jan-24 11-Feb-24 10 248
Landscape Works 23-Jan-24 09-Jul-24 130 134
GR-CON-Z15-1043 Excavation (Tree Pit ) 23-Jan-24 01-Feb-24 8 198
GR-CON-Z15-1044 Aggregate Drainage layer 01-Feb-24 13-Feb-24 10 198
GR-CON-Z15-1045 Installation Geotextile 13-Feb-24 20-Feb-24 6 198
GR-CON-Z15-1046 Backfilling (Soil max for tree) 20-Feb-24 03-Mar-24 10 198
GR-CON-Z15-1047 Installation of Trees 28-May-24 02-Jun-24 4 134
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-11528 Installation of Climbers 02-Jun-24 06-Jun-24 4 134


GR-CON-Z15-14156 Installation of Succulents 06-Jun-24 11-Jun-24 4 134
GR-CON-Z15-14166 Installation of Ground Covers 11-Jun-24 16-Jun-24 4 134
GR-CON-Z15-11538 Installation of Shrubs 16-Jun-24 25-Jun-24 4 134
GR-CON-Z15-11548 Installation of Grass 25-Jun-24 30-Jun-24 4 134
GR-CON-Z15-11558 Installation of Lawns 30-Jun-24 04-Jul-24 4 134
GR-CON-Z15-1048 Backfilling (Mulch) 04-Jul-24 09-Jul-24 4 134
Irrigation Works 23-Jan-24 09-Jul-24 130 134
GR-CON-Z15-1049 Excavation Pipe Irrigation 23-Jan-24 01-Feb-24 8 113
GR-CON-Z15-1050 Sand Bedding 01-Feb-24 06-Feb-24 4 113
GR-CON-Z15-1051 HDPE Pipe Installations and fittings and conduit for cable 06-Feb-24 05-Mar-24 24 113
GR-CON-Z15-1053 Test pressure 05-Mar-24 14-Mar-24 8 113
GR-CON-Z15-1052 Installation of Valves and Accessories 14-Mar-24 24-Mar-24 6 113
GR-CON-Z15-1054 Back filling (sand / Subbase ) 24-Mar-24 08-Apr-24 10 113
GR-CON-Z15-1055 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 09-Apr-24 25-Apr-24 10 182
GR-CON-Z15-1056 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
25-Jun-24
system 09-Jul-24 12 134
Existing Neighborhood Park ENP-05 30-Jan-24 16-Jun-24 108 150
Site Preparation 30-Jan-24 17-Feb-24 15 243
GR-CON-Z15-1057 Demolition (Asphalt.Paving,etc.....) 30-Jan-24 03-Feb-24 3 130
GR-CON-Z15-1058 Excavation And Disposal 03-Feb-24 07-Feb-24 4 130
GR-CON-Z15-1059 Prepretion And Compaction 07-Feb-24 11-Feb-24 3 243
GR-CON-Z15-1060 Backfilling 11-Feb-24 17-Feb-24 5 243
Landscape Works 07-Feb-24 16-Jun-24 101 150
GR-CON-Z15-1061 Excavation (Tree Pit ) 07-Feb-24 12-Feb-24 4 218
GR-CON-Z15-1062 Aggregate Drainage layer 12-Feb-24 18-Feb-24 5 218
GR-CON-Z15-1063 Installation Geotextile 18-Feb-24 21-Feb-24 3 218
GR-CON-Z15-1064 Backfilling (Soil max for tree) 21-Feb-24 27-Feb-24 5 218
GR-CON-Z15-1065 Installation of Trees 28-May-24 30-May-24 2 150
GR-CON-Z15-11568 Installation of Climbers 30-May-24 02-Jun-24 2 150
GR-CON-Z15-14176 Installation of Succulents 02-Jun-24 04-Jun-24 2 150
GR-CON-Z15-14186 Installation of Ground Covers 04-Jun-24 06-Jun-24 2 150
GR-CON-Z15-11578 Installation of Shrubs 06-Jun-24 09-Jun-24 2 150
GR-CON-Z15-11588 Installation of Grass 09-Jun-24 11-Jun-24 2 150
GR-CON-Z15-11598 Installation of Lawns 11-Jun-24 13-Jun-24 2 150
GR-CON-Z15-1066 Backfilling (Mulch) 13-Jun-24 16-Jun-24 2 150
Irrigation Works 07-Feb-24 16-Jun-24 101 150
Activity ID Activity Name Start Finish Original Total Float
Duration

GR-CON-Z15-1067 Excavation Pipe Irrigation 07-Feb-24 12-Feb-24 4 130


GR-CON-Z15-1068 Sand Bedding 12-Feb-24 14-Feb-24 2 130
GR-CON-Z15-1069 HDPE Pipe Installations and fittings and conduit for cable 14-Feb-24 28-Feb-24 12 130
GR-CON-Z15-1071 Test pressure 28-Feb-24 04-Mar-24 4 130
GR-CON-Z15-1070 Installation of Valves and Accessories 04-Mar-24 07-Mar-24 3 130
GR-CON-Z15-1072 Back filling (sand / Subbase ) 07-Mar-24 13-Mar-24 5 130
GR-CON-Z15-1073 Turf spray / Pipe transition point / Pop-up bubbler / Inline emitters 13-Mar-24 20-Mar-24 5 210
GR-CON-Z15-1074 Pull box , Decoders , Connecting to plots /Connection to infra irrigation
09-Jun-24
system 16-Jun-24 6 150