GUGGENHEIM MUSEUM ABU DHABI

Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
650 04-Mar-22 10-Jun-24 04-Mar-22 A 10-Jun-24 0 0
GALLERY 105 -Rev. 01_UPDT_17_04_23
GENERAL 0 04-Mar-22 04-Mar-22 04-Mar-22 A 04-Mar-22 A 0
G105-G-1000 Project Commencement 0 04-Mar-22 04-Mar-22 A 100% 0
SCAFFOLDING 420 31-Oct-22 19-Apr-24 31-Oct-22 A 19-Apr-24 25 -1

Internal Scaffolding 420 31-Oct-22 19-Apr-24 31-Oct-22 A 19-Apr-24 0 -1


Scaffold for Structural Steel works 95 31-Oct-22 21-Feb-23 31-Oct-22 A 21-Feb-23 A 0
G105-C-SC-200 Internal Scaffolding Installation G105 - Level 01 - 03 5 31-Oct-22 04-Nov-22 31-Oct-22 A 04-Nov-22 A 100% 0
G105-C-SC-210 Internal Scaffolding Installation Level 04 - 06 2 15-Dec-22 16-Dec-22 15-Dec-22 A 16-Dec-22 A 100% 0
G105-C-SC-220 Internal Scaffolding Installation Level 07 - 08 2 20-Feb-23 21-Feb-23 20-Feb-23 A 21-Feb-23 A 100% 0
Dismantling of Scaffold 296 01-Apr-23 19-Apr-24 01-Apr-23 A 19-Apr-24 0 -1
G105-C-SC-240 Lowering of Scaffold for MEP works {up to 1.8 m Ht} 7 01-Apr-23 14-Apr-23 01-Apr-23 A 10-Apr-23 A 100% 3
G105-C-SC-250 Dismantling of Internal Scaffold for Floor finishes 22 08-Mar-24 19-Apr-24 09-Mar-24 19-Apr-24 0% 0 -1
External Scaffolding 16 18-Mar-23 01-May-23 07-Mar-23 A 25-Mar-23 A 19
G105-C-SC-113 External Scaffolding Erection [for GFRC Package] Elev 4 14 04-Apr-23 01-May-23 10-Mar-23 A 18-Mar-23 A 100% 24
G105-C-SC-111 External Scaffolding Erection [for GFRC Package] Elev 2 14 23-Mar-23 19-Apr-23 09-Mar-23 A 18-Mar-23 A 100% 18
G105-C-SC-112 External Scaffolding Erection [for GFRC Package] Elev 3 14 29-Mar-23 27-Apr-23 10-Mar-23 A 18-Mar-23 A 100% 21
G105-C-SC-110 External Scaffolding Erection [for GFRC Package] Elev 1 14 18-Mar-23 11-Apr-23 07-Mar-23 A 25-Mar-23 A 100% 9
Scaffolding for Works on Roof 11 27-Mar-23 17-Apr-23 29-Apr-23 12-May-23 15 -17
G105-C-SC-230 Scaffolding Erection on roof [for MEP / Extrnal Facade & Glazing Packages] 11 27-Mar-23 17-Apr-23 29-Apr-23 12-May-23 0% 15 -17 Scaffolding Erection on roof [for MEP / Extrnal Facade & G
Dismantling of Scaffold 26 01-Aug-23 31-Aug-23 27-Jul-23 25-Aug-23 210 5
G105-C-SC-120 External Scaffolding Dismantling 26 01-Aug-23 31-Aug-23 27-Jul-23 25-Aug-23 0% 210 5 External Scaffolding Dismantling
STRUCTURAL STEEL (EVS) 237 31-Oct-22 28-Aug-23 31-Oct-22 A 28-Aug-23 0 -1

Steructural Steel Erection (EVS) 83 31-Oct-22 07-Feb-23 31-Oct-22 A 20-Feb-23 A -10


G105-SS-CON-1420 Assembly and Erection of Temporary Structure 6 31-Oct-22 05-Nov-22 31-Oct-22 A 05-Nov-22 A 100% 0
G105-SS-CON-1430 Alignment, Fitup, Welding & Bolting of Temporary Structure 6 07-Nov-22 12-Nov-22 07-Nov-22 A 12-Nov-22 A 100% 0
G105-SS-CON-1440 Ground Assembly, Alig nment, Fitup, Welding & NDT of Steel Structure incl Cat Walk and Staircases 7 29-Nov-22 09-Dec-22 29-Nov-22 A 09-Dec-22 A 100% 0
G105-SS-CON-1450 Erection of Steel Structure Level 01 4 10-Dec-22 14-Dec-22 10-Dec-22 A 14-Dec-22 A 100% 0
G105-SS-CON-1510 Erection of Steel Structure Level 02 8 15-Dec-22 23-Dec-22 15-Dec-22 A 23-Dec-22 A 100% 0
G105-SS-CON-1480 Erection of Steel Structure Level 03 3 24-Dec-22 27-Dec-22 24-Dec-22 A 27-Dec-22 A 100% 0
G105-SS-CON-1460 Erection of Steel Structure Level 04 4 28-Dec-22 31-Dec-22 28-Dec-22 A 31-Dec-22 A 100% 0
G105-SS-CON-1560 Erection of Steel Structure Level 05 3 02-Jan-23 04-Jan-23 02-Jan-23 A 04-Jan-23 A 100% 1
G105-SS-CON-1470 Erection of Steel Structure Level 06 4 05-Jan-23 09-Jan-23 05-Jan-23 A 09-Jan-23 A 100% 0
G105-SS-CON-1530 Erection of Steel Structure Level 07 2 10-Jan-23 11-Jan-23 10-Jan-23 A 15-Jan-23 A 100% -3
G105-SS-CON-1580 Erection of Steel Structure Level 08 20 16-Jan-23 07-Feb-23 16-Jan-23 A 20-Feb-23 A 100% -10
Metal Decking & Casting 46 20-Feb-23 27-Mar-23 04-Jan-23 A 29-Apr-23 15 -17
Metal Deck 9 20-Feb-23 01-Mar-23 20-Feb-23 A 01-Mar-23 A 0
G105-SS-CON-1590 Remove Scaffold to allow Metal Decking 2 20-Feb-23 21-Feb-23 20-Feb-23 A 21-Feb-23 A 100% 0
G105-SS-CON-1610 Metal deck including shear stud welding and inspection 7 22-Feb-23 01-Mar-23 22-Feb-23 A 01-Mar-23 A 100% 0
Concrete Works 28 09-Mar-23 27-Mar-23 04-Jan-23 A 29-Apr-23 15 -17
G105-SS-E-1880 Approval of Shop Drawings for Composite Slab 12 06-Mar-23 A 16-Mar-23 A 100%
Deck Slab 14 09-Mar-23 15-Mar-23 04-Jan-23 A 01-Apr-23 A -11
G105-SS-E-1890 Approval of Shop Drawings for Composite Slab - Decking detail 12 04-Jan-23 A 27-Mar-23 A 100%
G105-SS-CON-1600 Composite Slab casting by STJV 12 09-Mar-23 15-Mar-23 07-Mar-23 A 01-Apr-23 A 100% -11
Upstands & Eqpt Plinth 13 16-Mar-23 27-Mar-23 03-Apr-23 A 29-Apr-23 15 -17
G105-SS-CON-1850 Upstand casting by STJV 6 16-Mar-23 22-Mar-23 03-Apr-23 A 19-Apr-23 70% 18 -14 Upstand casting by STJV
G105-SS-CON-1630 Equipment plinth casting by STJV 6 18-Mar-23 27-Mar-23 17-Apr-23 29-Apr-23 0% 15 -17 Equipment plinth casting by STJV
SECONDARY STEEL FOR CATWALKS 105 25-Mar-23 28-Aug-23 17-Apr-23 28-Aug-23 0 -1
Design 37 25-Mar-23 03-Jun-23 17-Apr-23 05-Jun-23 0 -1
G105-SS-CON-1760 Submission of Design-Secondary Steel Structure for Architectural Lighting Catwalks 9 25-Mar-23 29-Apr-23 17-Apr-23 03-May-23 0% 0 -2
G105-SS-CON-1770 Approval of Design-Secondary Steel Structure for Architectural Lighting Catwalks 12 29-Apr-23 13-May-23 03-May-23 17-May-23 0% 0 -2
G105-SS-CON-1780 Re-Submission of Design-Secondary Steel Structure for Architectural Lighting Catwalks 6 13-May-23 20-May-23 17-May-23 24-May-23 0% 0 -2
G105-SS-CON-1790 Approval of Design-Secondary Steel Structure for Architectural Lighting Catwalks 10 20-May-23 03-Jun-23 24-May-23 05-Jun-23 0% 0 -1
Shop Drawings 42 05-Jun-23 29-Jul-23 06-Jun-23 29-Jul-23 0 -1
G105-SS-CON-1800 Submission of Shop Drawings -Secondary Steel Structure for Architectural Lighting Catwalks 12 05-Jun-23 19-Jun-23 06-Jun-23 19-Jun-23 0% 0 -1
G105-SS-CON-1810 Approval of Shop Drawings -Secondary Steel Structure for Architectural Lighting Catwalks 12 19-Jun-23 07-Jul-23 20-Jun-23 07-Jul-23 0% 0 -1

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 1 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
G105-SS-CON-1820 Re-Submission of Shop Drawings -Secondary Steel Structure for Architectural Lighting Catwalks 6 07-Jul-23 14-Jul-23 08-Jul-23 14-Jul-23 0% 0 -1
G105-SS-CON-1830 Approval of Shop Drawings -Secondary Steel Structure for Architectural Lighting Catwalks 12 14-Jul-23 29-Jul-23 15-Jul-23 29-Jul-23 0% 0 -1
Procurement 12 31-Jul-23 14-Aug-23 01-Aug-23 14-Aug-23 0 -1
G105-SS-CON-1840 Fabrication & Delivery -Secondary Steel Structure for Architectural Lighting Catwalks 12 31-Jul-23 14-Aug-23 01-Aug-23 14-Aug-23 0% 0 -1
Secondary Steel Erection Works 12 14-Aug-23 28-Aug-23 15-Aug-23 28-Aug-23 0 -1
G105-SS-CON-1740 Erection of Secondary Steel Structure for Architectural Lighting Catwalks- Below Deck slab 12 14-Aug-23 28-Aug-23 15-Aug-23 28-Aug-23 0% 0 -1
GFRC PACKAGE (FIBREX) 240 23-Sep-22 01-Aug-23 15-Sep-22 A 26-Jul-23 204 5

Design and Engineering Works 190 23-Sep-22 19-May-23 15-Sep-22 A 23-May-23 84 -3


System Drawings 39 23-Sep-22 08-Nov-22 25-Sep-22 A 04-Nov-22 A 4
ES1 (GFRC Works) 36 23-Sep-22 04-Nov-22 25-Sep-22 A 31-Oct-22 A 5
G105-GRC-ENG-05 Preparation and Submission of System Drawings 7 23-Sep-22 30-Sep-22 25-Sep-22 A 01-Oct-22 A 100% 0
G105-GRC-ENG-06 Review and Approval of System Drawings 10 03-Oct-22 14-Oct-22 01-Oct-22 A 04-Oct-22 A 100% 8
G105-GRC-ENG-07 Resubmission of System Drawings 6 14-Oct-22 21-Oct-22 04-Oct-22 A 06-Oct-22 A 100% 13
G105-GRC-ENG-08 Approval of System Drawings 10 24-Oct-22 04-Nov-22 06-Oct-22 A 31-Oct-22 A 100% 5
IS1 36 27-Sep-22 08-Nov-22 25-Sep-22 A 04-Nov-22 A 4
G105-GRC-ENG-10 Review and Approval of System Drawings 10 05-Oct-22 18-Oct-22 04-Oct-22 A 04-Oct-22 A 100% 11
G105-GRC-ENG-09 Preparation and Submission of System Drawings 7 27-Sep-22 04-Oct-22 25-Sep-22 A 04-Oct-22 A 100% 0
G105-GRC-ENG-11 Resubmission of System Drawings 6 18-Oct-22 25-Oct-22 04-Oct-22 A 06-Oct-22 A 100% 16
G105-GRC-ENG-12 Approval of System Drawings 10 26-Oct-22 08-Nov-22 06-Oct-22 A 04-Nov-22 A 100% 3
Materials 30 03-Jan-23 06-Feb-23 15-Sep-22 A 22-Feb-23 A -13
G105-GRC-MAT-03 Preparation and Submission of Material Submittals 30 03-Jan-23 06-Feb-23 15-Sep-22 A 20-Feb-23 A 100% -11
G105-GRC-MAT-04 Review and Approval of Material Submittals 10 05-Jan-23 18-Jan-23 17-Sep-22 A 22-Feb-23 A 100% -24
Structural / Design Calculations 62 03-Jan-23 17-Apr-23 30-Sep-22 A 01-May-23 83 -7
ES1, IS1 36 03-Jan-23 13-Feb-23 30-Sep-22 A 29-Oct-22 A 89
G105-GRC-ENG-73 Preparation and Submission of Structural Calculation 24 03-Jan-23 30-Jan-23 30-Sep-22 A 13-Oct-22 A 100% 91
G105-GRC-ENG-74 Review and Approval of Structural Calculation 10 31-Jan-23 13-Feb-23 14-Oct-22 A 29-Oct-22 A 100% 74
LOD300 7 13-Feb-23 20-Feb-23 06-Feb-23 A 23-Feb-23 A -3
Gallery 105 7 13-Feb-23 20-Feb-23 06-Feb-23 A 23-Feb-23 A -3
G105-GRC-ENG-91 Preparation and Submission of LOD300 7 13-Feb-23 20-Feb-23 06-Feb-23 A 23-Feb-23 A 100% -3
LOD350 27 23-Feb-23 17-Apr-23 13-Feb-23 A 01-May-23 83 -7
Gallery 105 27 23-Feb-23 17-Apr-23 13-Feb-23 A 01-May-23 83 -7
G105-GRC-ENG-114 Providing of Coordinated Interface Trade Models 12 23-Feb-23 09-Mar-23 13-Feb-23 A 18-Apr-23 90% 85 -34 Providing of Coordinated Interface Trade Models
G105-GRC-ENG-115 Preparation and Submission of LOD350 21 09-Mar-23 03-Apr-23 20-Feb-23 A 24-Apr-23 90% 86 -15 Preparation and Submission of LOD350
G105-GRC-ENG-118 Approval of LOD350/400 10 03-Apr-23 17-Apr-23 27-Feb-23 A 01-May-23 50% 70 -7 Approval of LOD350/400
Shop Drawings 66 20-Feb-23 19-May-23 20-Feb-23 A 23-May-23 84 -3
Peliminary Shop Drawings(For Infill System) 25 20-Feb-23 20-Mar-23 20-Feb-23 A 23-Mar-23 A -2
G105-GRC-ENG-168 Preparation and Submission of Shop Drawings (For Infill System) 10 20-Feb-23 02-Mar-23 20-Feb-23 A 10-Mar-23 A 100% -6
G105-GRC-ENG-178 Approval of Shop Drawings (For Infill System) 12 03-Mar-23 20-Mar-23 03-Mar-23 A 23-Mar-23 A 100% -2
Coordinated Shop Drawings 28 17-Apr-23 19-May-23 05-Apr-23 A 23-May-23 84 -3
G105-GRC-ENG-155 Preparation and Submission of Shop Drawings 14 17-Apr-23 07-May-23 05-Apr-23 A 09-May-23 50% 85 -2 Preparation and Submission of Shop Drawings
G105-GRC-ENG-158 Approval of Shop Drawings 10 08-May-23 19-May-23 09-May-23 23-May-23 0% 69 -2 Approval of Shop Drawings
Method Statement 30 11-Jan-23 14-Feb-23 10-Dec-22 A 09-Jan-23 A 32
G105-GRC-MS-01 Preparation and Submission of Installation MS 18 11-Jan-23 31-Jan-23 10-Dec-22 A 26-Dec-22 A 100% 31
G105-GRC-MS-02 Review and Approval of Installation MS 10 01-Feb-23 14-Feb-23 27-Dec-22 A 09-Jan-23 A 100% 27
Procurement 57 20-Mar-23 01-Jul-23 07-Mar-23 A 10-Jun-23 221 15
G105-GRC-PROC-02 Procurement of Material 12 20-Mar-23 31-Mar-23 07-Mar-23 A 22-Apr-23 80% 45 -20 Procurement of Material
Production and Delivery Works 65 27-Mar-23 01-Jul-23 07-Mar-23 A 10-Jun-23 222 15
Gallery 105 65 27-Mar-23 01-Jul-23 07-Mar-23 A 10-Jun-23 222 15
Elevation 01 64 27-Mar-23 14-Jun-23 07-Mar-23 A 09-Jun-23 205 5
ES1- Material Fabrication & Delivery (GFRC Works) 64 27-Mar-23 14-Jun-23 07-Mar-23 A 09-Jun-23 205 5
G105-GRC-FAB-40 Fabrication of Secondary Steel 8 27-Mar-23 04-Apr-23 07-Mar-23 A 17-Apr-23 90% 35 -11 Fabrication of Secondary Steel
G105-GRC-FAB-60 Delivery of Secondary Steel 6 05-Apr-23 11-Apr-23 15-Mar-23 A 19-Apr-23 75% 35 -7 Delivery of Secondary Steel
G105-GRC-FAB-50 Fabrication of GRC Material 18 20-May-23 09-Jun-23 08-Mar-23 A 05-Jun-23 42% 84 5 Fabrication of GRC Material
G105-GRC-FAB-70 Delivery of GRC Material 10 03-Jun-23 14-Jun-23 29-May-23 09-Jun-23 0% 205 5 Delivery of GRC Material
Elevation 02 56 31-Mar-23 17-Jun-23 07-Mar-23 A 08-Jun-23 211 9
ES1- Material Fabrication & Delivery (GFRC Works) 56 31-Mar-23 17-Jun-23 07-Mar-23 A 08-Jun-23 211 9
G105-GRC-FAB-90 Fabrication of Secondary Steel 8 31-Mar-23 10-Apr-23 07-Mar-23 A 24-Apr-23 90% 35 -9 Fabrication of Secondary Steel
G105-GRC-FAB-110 Delivery of Secondary Steel 6 10-Apr-23 17-Apr-23 21-Mar-23 A 26-Apr-23 75% 38 -5 Delivery of Secondary Steel
G105-GRC-FAB-100 Fabrication of GRC Material 18 24-May-23 13-Jun-23 08-Mar-23 A 03-Jun-23 45% 84 9 Fabrication of GRC Material
G105-GRC-FAB-120 Delivery of GRC Material 10 07-Jun-23 17-Jun-23 27-May-23 08-Jun-23 0% 211 9 Delivery of GRC Material

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 2 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
Elevation 03 50 10-Apr-23 22-Jun-23 10-Mar-23 A 10-Jun-23 216 11
ES1- Material Fabrication & Delivery (GFRC Works) 50 10-Apr-23 22-Jun-23 10-Mar-23 A 10-Jun-23 216 11
G105-GRC-FAB-140 Fabrication of Secondary Steel 8 10-Apr-23 19-Apr-23 10-Mar-23 A 25-Apr-23 90% 35 -2 Fabrication of Secondary Steel
G105-GRC-FAB-160 Delivery of Secondary Steel 6 19-Apr-23 29-Apr-23 21-Mar-23 A 27-Apr-23 75% 37 3 Delivery of Secondary Steel
G105-GRC-FAB-150 Fabrication of GRC Material 18 29-May-23 17-Jun-23 15-Mar-23 A 06-Jun-23 35% 84 11 Fabrication of GRC Material
G105-GRC-FAB-170 Delivery of GRC Material 10 12-Jun-23 22-Jun-23 30-May-23 10-Jun-23 0% 216 11 Delivery of GRC Material
Elevation 04 47 13-Apr-23 01-Jul-23 08-Mar-23 A 10-Jun-23 222 15
ES1- Material Fabrication & Delivery (GFRC Works) 47 13-Apr-23 01-Jul-23 08-Mar-23 A 10-Jun-23 222 15
G105-GRC-FAB-190 Fabrication of Secondary Steel 8 13-Apr-23 26-Apr-23 08-Mar-23 A 25-Apr-23 90% 35 1 Fabrication of Secondary Steel
G105-GRC-FAB-210 Delivery of Secondary Steel 6 26-Apr-23 03-May-23 21-Mar-23 A 27-Apr-23 75% 35 6 Delivery of Secondary Steel
G105-GRC-FAB-200 Fabrication of GRC Material 18 02-Jun-23 22-Jun-23 09-Mar-23 A 06-Jun-23 35% 84 15 Fabrication of GRC Material
G105-GRC-FAB-220 Delivery of GRC Material 10 16-Jun-23 01-Jul-23 30-May-23 10-Jun-23 0% 222 15 Delivery of GRC Material
IS1- Material Fabrication & Delivery 39 26-Apr-23 14-Jun-23 10-Mar-23 A 02-Jun-23 91 10
G105-GRC-FAB-230 Fabrication of Secondary Steel 7 26-Apr-23 04-May-23 16-Mar-23 A 26-Apr-23 80% 105 7 Fabrication of Secondary Steel
G105-GRC-FAB-260 Delivery of Secondary Steel 7 04-May-23 12-May-23 14-Apr-23 A 03-May-23 20% 105 8 Delivery of Secondary Steel
G105-GRC-FAB-240 Fabrication of GRC Material 7 02-Jun-23 09-Jun-23 10-Mar-23 A 29-May-23 25% 84 10 Fabrication of GRC Material
G105-GRC-FAB-250 Delivery of GRC Material 7 07-Jun-23 14-Jun-23 25-May-23 02-Jun-23 0% 91 10 Delivery of GRC Material
Installation Works 92 12-Apr-23 01-Aug-23 15-Mar-23 A 26-Jul-23 204 5
Main Scope 92 12-Apr-23 01-Aug-23 15-Mar-23 A 26-Jul-23 204 5
ES1 - GFRC Facade System 92 12-Apr-23 01-Aug-23 15-Mar-23 A 26-Jul-23 204 5
Elevation 01 (Near Entrance / Opposite Core Wall) 63 12-Apr-23 10-Jul-23 04-Apr-23 A 04-Jul-23 204 5
ES1 63 12-Apr-23 10-Jul-23 04-Apr-23 A 04-Jul-23 204 5
G105-ES-1090 Providing of Access, Clearance and Equipment -Elevation -01 0 12-Apr-23 07-Apr-23 A 100% 2 Providing of Access, Clearance and Equipment -Elevation -01
G105-ES-1060 Installation of Steel (Including Drilling holes & Fireproof coat) -Elevation -01 10 12-Apr-23 01-May-23 07-Apr-23 A 01-May-23 40% 34 0 Installation of Steel (Including Drilling holes & Fireproof coat)
G105-ES-1070 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - From 6m to 20m -Elevation -01 8 01-May-23 10-May-23 01-May-23 10-May-23 0% 34 0 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - F
G105-ES-1110 Application of Cementitious Fireproofing and paint touchup works at site up to 6m -Elevation -01 5 10-May-23 16-May-23 04-Apr-23 A 11-May-23 80% 34 4 Application of Cementitious Fireproofing and paint touchup
G105-ES-1100 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - up to 6m Ht from Bottom -Elevation -01 3 16-May-23 19-May-23 11-May-23 15-May-23 0% 34 4 Installation of Unitized Panel ( Vapour Barrier, Insulation ) -
G105-ES-1080 Installation of GFRC Panel- ES1/ES1.1 -Elevation -01 18 14-Jun-23 10-Jul-23 09-Jun-23 04-Jul-23 0% 204 5 Installation of GFRC Panel- ES1/ES1.1 -Elevation
Elevation 02 (Towards Cone-07) 80 19-Apr-23 17-Jul-23 15-Mar-23 A 11-Jul-23 204 5
ES1 80 19-Apr-23 17-Jul-23 15-Mar-23 A 11-Jul-23 204 5
G105-ES-1030 Providing of Access, Clearance and Equipment -Elevation -02 0 19-Apr-23 15-Mar-23 A 100% 21 Providing of Access, Clearance and Equipment -Elevation -02
G105-ES-1050 Application of Cementitious Fireproofing and paint touchup works at site up to 6m -Elevation -02 5 15-May-23 20-May-23 20-Mar-23 A 31-Mar-23 A 100% 33
G105-ES-1000 Installation of Steel (Including Drilling holes & Fireproof coat) -Elevation -02 10 19-Apr-23 05-May-23 16-Mar-23 A 27-Apr-23 85% 38 7 Installation of Steel (Including Drilling holes & Fireproof coat)
G105-ES-1010 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - From 6m to 20m -Elevation -02 8 05-May-23 15-May-23 27-Apr-23 06-May-23 0% 38 7 Installation of Unitized Panel ( Vapour Barrier, Insulation ) -
G105-ES-1040 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - up to 6m Ht from Bottom -Elevation -02 3 20-May-23 24-May-23 06-May-23 10-May-23 0% 38 12 Installation of Unitized Panel ( Vapour Barrier, Insulation )
G105-ES-1020 Installation of GFRC Panel- ES1/ES1.1 -Elevation -02 18 21-Jun-23 17-Jul-23 16-Jun-23 11-Jul-23 0% 204 5 Installation of GFRC Panel- ES1/ES1.1 -Elevation
Elevation 03(Towards Sea) 86 27-Apr-23 25-Jul-23 15-Mar-23 A 18-Jul-23 204 5
ES1 86 27-Apr-23 25-Jul-23 15-Mar-23 A 18-Jul-23 204 5
G105-ES-1150 Providing of Access, Clearance and Equipment -Elevation -03 0 27-Apr-23 15-Mar-23 A 100% 24 Providing of Access, Clearance and Equipment -Elevation -03
G105-ES-1170 Application of Cementitious Fireproofing and paint touchup works at site up to 6m -Elevation -03 5 20-May-23 26-May-23 24-Mar-23 A 07-Apr-23 A 100% 34
G105-ES-1120 Installation of Steel (Including Drilling holes & Fireproof coat) -Elevation -03 10 29-Apr-23 11-May-23 16-Mar-23 A 28-Apr-23 80% 37 11 Installation of Steel (Including Drilling holes & Fireproof coat
G105-ES-1130 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - From 6m to 20m -Elevation -03 8 11-May-23 20-May-23 29-Apr-23 08-May-23 0% 37 11 Installation of Unitized Panel ( Vapour Barrier, Insulation ) -
G105-ES-1160 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - up to 6m Ht from Bottom -Elevation -03 3 26-May-23 30-May-23 09-May-23 11-May-23 0% 37 16 Installation of Unitized Panel ( Vapour Barrier, Insulation
G105-ES-1140 Installation of GFRC Panel- ES1/ES1.1 -Elevation -03 (Without Leavouts for Shards) 18 03-Jul-23 25-Jul-23 23-Jun-23 18-Jul-23 0% 204 5 Installation of GFRC Panel- ES1/ES1.1 -Elevatio
Elevation 04 (Near Shard 09) 85 01-May-23 01-Aug-23 29-Mar-23 A 26-Jul-23 204 5
ES1 85 01-May-23 01-Aug-23 29-Mar-23 A 26-Jul-23 204 5
G105-ES-1210 Providing of Access, Clearance and Equipment -Elevation -04 0 01-May-23 29-Mar-23 A 100% 17 Providing of Access, Clearance and Equipment -Elevation -04
G105-ES-1230 Application of Cementitious Fireproofing and paint touchup works at site up to 6m -Elevation -04 5 24-May-23 30-May-23 04-Apr-23 A 08-Apr-23 A 100% 37
G105-ES-1180 Installation of Steel (Including Drilling holes & Fireproof coat) -Elevation -04 10 03-May-23 15-May-23 30-Mar-23 A 29-Apr-23 70% 35 13 Installation of Steel (Including Drilling holes & Fireproof coa
G105-ES-1190 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - From 6m to 20m -Elevation -04 8 15-May-23 24-May-23 01-May-23 09-May-23 0% 35 13 Installation of Unitized Panel ( Vapour Barrier, Insulation )
G105-ES-1220 Installation of Unitized Panel ( Vapour Barrier, Insulation ) - up to 6m Ht from Bottom -Elevation -04 3 30-May-23 02-Jun-23 10-May-23 12-May-23 0% 35 18 Installation of Unitized Panel ( Vapour Barrier, Insulation
G105-ES-1200 Installation of GFRC Panel- ES1/ES1.1 -Elevation -04 18 10-Jul-23 01-Aug-23 05-Jul-23 26-Jul-23 0% 204 5 Installation of GFRC Panel- ES1/ES1.1 -Elevat
IS1 (Precast Panels @ Door Entrance) 25 02-Jun-23 05-Jul-23 23-May-23 21-Jun-23 84 8
G105-GRC-INST-158 Providing of Access, Clearance and Equipment 0 02-Jun-23 02-Jun-23 23-May-23 23-May-23 0% 84 8 Providing of Access, Clearance and Equipment
G105-GRC-INST-238 Drilling of Holes for Brackets 6 02-Jun-23 08-Jun-23 23-May-23 30-May-23 0% 84 8 Drilling of Holes for Brackets
G105-GRC-INST-168 Installation of Steel 6 07-Jun-23 13-Jun-23 27-May-23 03-Jun-23 0% 84 8 Installation of Steel
G105-GRC-INST-178 Installation of Build Up with Waterproofing 6 14-Jun-23 20-Jun-23 03-Jun-23 10-Jun-23 0% 84 8 Installation of Build Up with Waterproofing
G105-GRC-INST-188 Installation of GRC Panel 9 21-Jun-23 05-Jul-23 10-Jun-23 21-Jun-23 0% 84 8 Installation of GRC Panel
MEP WORKS 355 07-Sep-22 15-Nov-23 01-Apr-22 A 22-Nov-23 92 -5

Engineering 277 07-Sep-22 02-Aug-23 01-Apr-22 A 03-Aug-23 103 -1


BIM Model Finalization (MEP) 138 07-Sep-22 18-Mar-23 07-Sep-22 A 18-Feb-23 A 24

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 3 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
G105-E-GP-440 BIM model for Gallery 105 - Preparation and Submission 6 07-Sep-22 13-Sep-22 07-Sep-22 A 23-Nov-22 A 100% -59
G105-E-GP-450 BIM model for Gallery 105 - Collaborations and Clash Detection 18 20-Feb-23 11-Mar-23 20-Jan-23 A 09-Feb-23 A 100% 26
G105-E-GP-460 BIM model for Gallery 105 - Clash Resolutions and Resubmission 6 13-Mar-23 18-Mar-23 13-Feb-23 A 18-Feb-23 A 100% 24
Shop Drawings 156 10-Oct-22 28-Apr-23 18-Aug-22 A 26-Apr-23 94 2
Submissions 144 10-Oct-22 03-Apr-23 18-Aug-22 A 07-Apr-23 A -2
G105-MEP-SD-1600 Preparation and Submission of Shop Drawings - Level 01 24 13-Feb-23 11-Mar-23 18-Aug-22 A 17-Mar-23 A 100% -4
G105-MEP-SD-1620 Preparation and Submission of Shop Drawings - Level 01M 24 16-Feb-23 15-Mar-23 23-Sep-22 A 22-Mar-23 A 100% -5
G105-MEP-SD-1660 Preparation and Submission of Shop Drawings - Level 02M 24 02-Mar-23 03-Apr-23 21-Oct-22 A 25-Mar-23 A 100% 5
G105-MEP-SD-1640 Preparation and Submission of Shop Drawings - Level 02 24 27-Feb-23 28-Mar-23 10-Oct-22 A 06-Apr-23 A 100% -5
G105-MEP-SD-1680 Preparation and Submission of Shop Drawings - Level 03 24 10-Oct-22 05-Nov-22 15-Nov-22 A 07-Apr-23 A 100% -122
Approvals 50 14-Feb-23 28-Apr-23 25-Aug-22 A 26-Apr-23 94 2
G105-MEP-SD-1630 Review & Approval of Shop Drawings - Level 01M 24 27-Feb-23 28-Mar-23 30-Sep-22 A 25-Mar-23 A 100% 1
G105-MEP-SD-1670 Review & Approval of Shop Drawings - Level 02M 24 06-Mar-23 08-Apr-23 28-Oct-22 A 17-Apr-23 98% 33 -4 Review & Approval of Shop Drawings - Level 02M
G105-MEP-SD-1610 Review & Approval of Shop Drawings - Level 01 24 14-Feb-23 14-Mar-23 25-Aug-22 A 19-Apr-23 94% 54 -22 Review & Approval of Shop Drawings - Level 01
G105-MEP-SD-1650 Review & Approval of Shop Drawings - Level 02 24 02-Mar-23 03-Apr-23 17-Oct-22 A 26-Apr-23 88% 94 -9 Review & Approval of Shop Drawings - Level 02
G105-MEP-SD-1690 Review & Approval of Shop Drawings - Level 03 24 16-Mar-23 28-Apr-23 22-Nov-22 A 26-Apr-23 87% 30 2 Review & Approval of Shop Drawings - Level 03
Procurement 243 18-Oct-22 02-Aug-23 01-Apr-22 A 03-Aug-23 103 -1
Material Submittals & Procurement 243 18-Oct-22 02-Aug-23 01-Apr-22 A 03-Aug-23 103 -1
MEP 1st & 2nd Fix 162 18-Oct-22 13-May-23 01-Apr-22 A 06-May-23 33 6
G105-MEP-PR-1760 Preparation and Submission of Material Submittals 48 18-Oct-22 15-Dec-22 01-Apr-22 A 22-Mar-23 A 100% -82
G105-MEP-PR-1770 Review & Approvals 48 18-Oct-22 15-Dec-22 08-Apr-22 A 24-Mar-23 A 100% -84
G105-MEP-PR-1800 Place Orders 36 04-Feb-23 17-Mar-23 04-Feb-23 A 26-Apr-23 90% 33 -20 Place Orders
G105-MEP-PR-1810 Manufacturing & Delivery to Site 48 03-Mar-23 13-May-23 11-Feb-23 A 06-May-23 75% 33 6 Manufacturing & Delivery to Site
MEP Final Fix 145 13-Feb-23 02-Aug-23 01-Jun-22 A 03-Aug-23 103 -1
G105-MEP-PR-1820 Preparation and Submission of Material Submittals / Calculations 36 13-Feb-23 28-Mar-23 01-Jun-22 A 05-Apr-23 A 100% -4
G105-MEP-PR-1830 Review & Approvals 48 13-Feb-23 25-Apr-23 03-Jun-22 A 29-Apr-23 88% 103 -4 Review & Approvals
G105-MEP-PR-1860 Place Orders 21 27-Mar-23 04-May-23 06-Apr-23 A 18-May-23 25% 103 -12 Place Orders
G105-MEP-PR-1870 Manufacturing & Delivery to Site (Equipments / Final Fixes) 72 04-May-23 02-Aug-23 07-Apr-23 A 03-Aug-23 15% 103 -1 Manufacturing & Delivery to Site (Equipments /
Construction 181 15-Apr-23 15-Nov-23 24-Mar-23 A 22-Nov-23 92 -5
MEP works below Decking Slab 73 15-Apr-23 02-Aug-23 24-Mar-23 A 07-Jul-23 65 21
G105-SS-CON-1640 Access for MEP 1st Fix 1 15-Apr-23 17-Apr-23 10-Apr-23 A 11-Apr-23 A 100% 3
G105-SS-CON-1650 Installation of MEP 1st Fix 36 17-Apr-23 03-Jun-23 24-Mar-23 A 03-Jun-23 15% 50 0 Installation of MEP 1st Fix
G105-SS-CON-1860 Installation of MEP 2nd Fix 48 13-May-23 13-Jul-23 06-May-23 06-Jul-23 0% 50 6 Installation of MEP 2nd Fix
G105-SS-CON-1660 Installation of MEP (Risers) 35 16-Jun-23 02-Aug-23 12-Apr-23 A 07-Jul-23 15% 65 21 Installation of MEP (Risers)
MEP works above Decking Slab 160 17-Apr-23 15-Nov-23 12-May-23 22-Nov-23 92 -5
G105-SS-CON-1680 Access for MEP 1st Fix 1 17-Apr-23 19-Apr-23 12-May-23 13-May-23 0% 15 -17 Access for MEP 1st Fix
G105-SS-CON-1690 Installation of MEP 1st Fix 48 19-Apr-23 19-Jun-23 13-May-23 13-Jul-23 0% 15 -17 Installation of MEP 1st Fix
G105-SS-CON-1700 Installation of MEP 2nd Fix 56 10-May-23 20-Jul-23 01-Jun-23 11-Aug-23 0% 11 -19 Installation of MEP 2nd Fix
G105-SS-CON-1720 Instalation of MEP Equipments 24 02-Aug-23 30-Aug-23 03-Aug-23 31-Aug-23 0% 139 -1 Instalation of MEP Equipments
G105-SS-CON-1870 Installation of MEP Final Fix 56 11-Sep-23 15-Nov-23 16-Sep-23 22-Nov-23 0% 92 -5 Installation of MEP Final Fix
BMU WORKS (COX) 452 01-Sep-22 14-Mar-24 01-Sep-22 A 15-Mar-24 43 -1

Engineering 211 01-Sep-22 01-Jun-23 01-Sep-22 A 25-May-23 182 6


Structural Design 196 01-Sep-22 08-Apr-23 01-Sep-22 A 28-Apr-23 90 -9
Design Reports 31 01-Sep-22 06-Oct-22 01-Sep-22 A 06-Oct-22 A 1
G105-BMU-ENG-1450 Structural Design Report Submission 6 01-Sep-22 07-Sep-22 01-Sep-22 A 07-Sep-22 A 100% 1
G105-BMU-ENG-1490 Structural Design Review and Comment 26 07-Sep-22 06-Oct-22 07-Sep-22 A 06-Oct-22 A 100% 1
Design Calculations 157 18-Oct-22 08-Apr-23 16-Jan-23 A 28-Apr-23 90 -9
Submissions 145 18-Oct-22 18-Mar-23 16-Jan-23 A 25-Apr-23 93 -18
G105-BMU-ENG-1500 Resubmission of Design Calculation for Typical Deviation Brackets 18 18-Oct-22 07-Nov-22 16-Jan-23 A 20-Feb-23 A 100% -86
G105-BMU-ENG-1520 Resubmission of Design Calculation for Typical Landing platform & Architectural Lightning Platform. 18 20-Feb-23 11-Mar-23 03-Mar-23 A 13-Mar-23 A 100% 0
G105-BMU-ENG-2100 Resubmission of Design Calculation for Typical Guard Rails 12 04-Mar-23 17-Mar-23 03-Mar-23 A 13-Mar-23 A 100% 5
G105-BMU-ENG-2080 Resubmission of Design Calculation for Typical Skylight Platform 12 03-Mar-23 16-Mar-23 03-Mar-23 A 14-Mar-23 A 100% 3
G105-BMU-ENG-2120 Resubmission of Design Calculation for Typical Roof Access Ladders 12 06-Mar-23 18-Mar-23 03-Mar-23 A 14-Mar-23 A 100% 5
G105-BMU-ENG-2040 Resubmission of Design Calculation for Typical Abseiling points 12 18-Jan-23 31-Jan-23 18-Jan-23 A 25-Apr-23 80% 90 -58 Resubmission of Design Calculation for Typical Abseiling poin
G105-BMU-ENG-2060 Resubmission of Design Calculation for Typical Combined Cableline & Abseiling Systems 12 02-Mar-23 15-Mar-23 28-Mar-23 A 25-Apr-23 80% 90 -21 Resubmission of Design Calculation for Typical Combined Ca
Approvals 32 02-Mar-23 08-Apr-23 07-Mar-23 A 28-Apr-23 90 -9
G105-BMU-ENG-1510 Design Calculation Approval - Typical Deviation Brackets 10 02-Mar-23 13-Mar-23 07-Mar-23 A 11-Mar-23 A 100% 2
G105-BMU-ENG-2130 Approval of Design Calculation for Typical Roof Access Ladders 12 20-Mar-23 08-Apr-23 08-Mar-23 A 17-Mar-23 A 100% 14
G105-BMU-ENG-1530 Approval of Design Calculation for Typical Landing platform & Architectural Lightning Platform 10 13-Mar-23 24-Mar-23 08-Mar-23 A 18-Mar-23 A 100% 5
G105-BMU-ENG-2090 Approval of Design Calculation for Typical Skylight Platform 12 17-Mar-23 05-Apr-23 07-Mar-23 A 18-Mar-23 A 100% 11
G105-BMU-ENG-2110 Approval of Design Calculation for Typical Guard Rails 12 18-Mar-23 07-Apr-23 07-Mar-23 A 18-Mar-23 A 100% 12

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 4 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
G105-BMU-ENG-2050 Approval of Design Calculation for Typical Abseiling points 12 09-Mar-23 22-Mar-23 30-Mar-23 A 28-Apr-23 75% 90 -18 Approval of Design Calculation for Typical Abseiling points
G105-BMU-ENG-2070 Approval of Design Calculation for Typical Combined Cableline & Abseiling Systems 12 16-Mar-23 03-Apr-23 30-Mar-23 A 28-Apr-23 75% 90 -12 Approval of Design Calculation for Typical Combined Cablelin
Shop Drawings 211 01-Sep-22 01-Jun-23 01-Sep-22 A 25-May-23 182 6
Submissions 199 01-Sep-22 18-May-23 01-Sep-22 A 11-May-23 182 6
G105-BMU-ENG-1430 Shop Drawing Submission 8 01-Sep-22 09-Sep-22 01-Sep-22 A 09-Sep-22 A 100% 1
G105-BMU-ENG-1420 BIM Model Preparation & Submission ( 3D ) 20 09-Sep-22 01-Oct-22 09-Sep-22 A 01-Oct-22 A 100% 1
G105-BMU-ENG-1480 Resubmission of Shop Drawing -Rev-01 7 18-Oct-22 25-Oct-22 18-Oct-22 A 29-Mar-23 A 100% -127
G105-BMU-ENG-2020 Resubmission of Shop Drawing -Rev-02 7 10-May-23 18-May-23 03-May-23 11-May-23 0% 182 6 Resubmission of Shop Drawing -Rev-02
Approvals 204 09-Sep-22 01-Jun-23 09-Sep-22 A 25-May-23 182 6
G105-BMU-ENG-1470 Shop Drawing Review and Comment 26 09-Sep-22 10-Oct-22 09-Sep-22 A 10-Oct-22 A 100% 1
G105-BMU-ENG-1440 Approval of Shop Drawings -Rev-01 12 26-Apr-23 10-May-23 01-Apr-23 A 03-May-23 67% 182 6 Approval of Shop Drawings -Rev-01
G105-BMU-ENG-2030 Approval of Shop Drawings -Rev-02 12 18-May-23 01-Jun-23 11-May-23 25-May-23 0% 182 6 Approval of Shop Drawings -Rev-02
Procurement 177 30-Dec-22 16-Aug-23 23-Dec-22 A 09-Aug-23 192 6
Material Submittals & Approvals 98 30-Dec-22 17-May-23 23-Dec-22 A 06-May-23 209 10
Submissions 93 30-Dec-22 03-May-23 23-Dec-22 A 29-Apr-23 215 4
G105-BMU-PROC-2040 Material & Sample Submission for Hatch 24 30-Dec-22 26-Jan-23 23-Dec-22 A 14-Jan-23 A 100% 11
G105-BMU-PROC-2020 Material Submission for Paint 24 16-Jan-23 11-Feb-23 10-Jan-23 A 14-Feb-23 A 100% -1
G105-BMU-PROC-2000 Material Submission for Combined Cableline & Abseiling Systems 24 16-Jan-23 11-Feb-23 30-Dec-22 A 04-Mar-23 A 100% -17
G105-BMU-PROC-2150 Material Submission for Combined Cableline & Abseiling Systems-Rev-01 12 12-Apr-23 03-May-23 10-Mar-23 A 10-Mar-23 A 100% 33
G105-BMU-PROC-2170 Material & Sample Submission for Hatch-Rev-01 12 12-Apr-23 03-May-23 17-Feb-23 A 29-Apr-23 50% 201 4 Material & Sample Submission for Hatch-Rev-01
Approvals 91 14-Mar-23 17-May-23 24-Dec-22 A 06-May-23 209 10
G105-BMU-PROC-2050 Material & Sample Approval / Comments for Hatch 18 14-Mar-23 11-Apr-23 24-Dec-22 A 25-Jan-23 A 100% 59
G105-BMU-PROC-2010 Material Approval / Comments for Combined Cableline & Abseiling Systems 18 14-Mar-23 11-Apr-23 02-Jan-23 A 26-Jan-23 A 100% 58
G105-BMU-PROC-2030 Material Approval for Paint 18 14-Mar-23 11-Apr-23 07-Feb-23 A 13-Feb-23 A 100% 43
G105-BMU-PROC-2160 Material Approval for Combined Cableline & Abseiling Systems-Rev-01 12 03-May-23 17-May-23 14-Mar-23 A 29-Mar-23 A 100% 31
G105-BMU-PROC-2180 Material & Sample Approval for Hatch-Rev-01 12 03-May-23 17-May-23 23-Mar-23 A 06-May-23 50% 201 10 Material & Sample Approval for Hatch-Rev-01
Material Fabrication & Deliveries 128 20-Feb-23 16-Aug-23 20-Feb-23 A 09-Aug-23 192 6
G105-BMU-PROC-2140 Place Order & Material Delivery-Paints 22 20-Mar-23 29-Apr-23 20-Mar-23 A 29-Apr-23 71% 197 0 Place Order & Material Delivery-Paints
G105-BMU-PROC-2060 Raw Material Procurement 45 14-Mar-23 20-May-23 16-Mar-23 A 23-May-23 41% 69 -2 Raw Material Procurement
Platforms, Walkways & Ladders 85 30-Mar-23 26-Jul-23 30-Mar-23 A 28-Jul-23 202 -2
G105-BMU-PROC-3070 Fabrication & Delivery - Platforms @ Lvl 30.458 24 30-Mar-23 10-May-23 30-Mar-23 A 10-May-23 38% 87 1 Fabrication & Delivery - Platforms @ Lvl 30.458
G105-BMU-PROC-2070 Fabrication & Delivery - Platforms @ Lvl 37.646 24 11-Apr-23 17-May-23 13-Apr-23 A 17-May-23 13% 183 1 Fabrication & Delivery - Platforms @ Lvl 37.646
G105-BMU-PROC-3080 Fabrication & Delivery - Platforms @ Lvl 30.107 24 11-Apr-23 17-May-23 17-Apr-23 20-May-23 0% 87 -3 Fabrication & Delivery - Platforms @ Lvl 30.107
G105-BMU-PROC-3090 Fabrication & Delivery - Platforms @ Lvl 27.669 (Catwalk) 24 28-Apr-23 26-May-23 01-May-23 29-May-23 0% 69 -2 Fabrication & Delivery - Platforms @ Lvl 27.669 (Catwal
G105-BMU-PROC-3100 Fabrication & Delivery - Platforms @ Lvl 41.025 24 09-May-23 06-Jun-23 11-May-23 08-Jun-23 0% 170 -2 Fabrication & Delivery - Platforms @ Lvl 41.025
G105-BMU-PROC3100 Fabrication & Delivery - Platforms @ Lvl 27.569 24 18-May-23 15-Jun-23 20-May-23 17-Jun-23 0% 69 -2 Fabrication & Delivery - Platforms @ Lvl 27.569
G105-BMU-PROC3110 Fabrication & Delivery - Peripheral Walkway @ Lvl 26.185 24 18-May-23 15-Jun-23 20-May-23 17-Jun-23 0% 69 -2 Fabrication & Delivery - Peripheral Walkway @ Lvl 26
G105-BMU-PROC3120 Fabrication & Delivery - Platform @ Lvl 20.031 24 15-Jun-23 18-Jul-23 17-Jun-23 21-Jul-23 0% 202 -2 Fabrication & Delivery - Platform @ Lvl 20.031
G105-BMU-PROC3130 Fabrication & Delivery - Platform @ Lvl 14.031 24 22-Jun-23 26-Jul-23 24-Jun-23 28-Jul-23 0% 202 -2 Fabrication & Delivery - Platform @ Lvl 14.031
Other Materials 128 20-Feb-23 16-Aug-23 20-Feb-23 A 09-Aug-23 192 6
G105-BMU-PROC-2080 Fabrication & Delivery - Stub Brackets for Combined Fall Restraint & Abseiling Post 12 20-Feb-23 04-Mar-23 20-Feb-23 A 04-Mar-23 A 100% 0
G105-BMU-PROC-2090 Fabrication & Delivery - Support Brackets for Combined Fall Restraint & Abseiling Post 30 01-Jun-23 11-Jul-23 25-May-23 04-Jul-23 0% 186 6 Fabrication & Delivery - Support Brackets for Com
G105-BMU-PROC-2110 Fabrication & Delivery - Abseil Brackets 30 01-Jun-23 11-Jul-23 25-May-23 04-Jul-23 0% 182 6 Fabrication & Delivery - Abseil Brackets
G105-BMU-PROC-2130 Place Order & Delivery - Hatch 30 01-Jun-23 11-Jul-23 25-May-23 04-Jul-23 0% 184 6 Place Order & Delivery - Hatch
G105-BMU-PROC-2120 Place Order & Delivery - Fall Arrest/Cable Line 60 01-Jun-23 16-Aug-23 25-May-23 09-Aug-23 0% 192 6 Place Order & Delivery - Fall Arrest/Cable Line
Installation 271 06-Mar-23 12-Feb-24 06-Mar-23 A 12-Feb-24 43 -1
Works below Decking Slab 101 12-Jun-23 25-Sep-23 24-May-23 25-Sep-23 158 -1
G105-BMU-CON-2100 Installation of Platforms @ Lvl 30.458 7 12-Jun-23 20-Jun-23 24-May-23 01-Jun-23 0% 77 16 Installation of Platforms @ Lvl 30.458
G105-BMU-CON-2110 Installation of Platforms @ Lvl 30.107 6 20-Jun-23 27-Jun-23 01-Jun-23 08-Jun-23 0% 77 16 Installation of Platforms @ Lvl 30.107
G105-BMU-CON-2140 Installation of Platforms @ Lvl 26.185 (Peripheral Walkway) 12 27-Jun-23 15-Jul-23 17-Jun-23 06-Jul-23 0% 69 8 Installation of Platforms @ Lvl 26.185 (Peripheral
G105-BMU-CON-2120 Installation of Platforms @ Lvl 27.669 - (Architectural lighting Catwalk) - Posts 6 28-Aug-23 04-Sep-23 29-Aug-23 04-Sep-23 0% 0 -1
G105-BMU-CON-2180 Installation of Platforms @ Lvl 27.669 - (Architectural lighting Catwalk) - Modules with Handrails 6 28-Aug-23 04-Sep-23 29-Aug-23 04-Sep-23 0% 158 -1 Installation of Platforms @ Lvl 27.669 - (Ar
G105-BMU-CON-2130 Installation of Platforms @ Lvl 27.569 6 04-Sep-23 11-Sep-23 05-Sep-23 11-Sep-23 0% 158 -1 Installation of Platforms @ Lvl 27.569
G105-BMU-CON-2150 Installation of Platforms @ Lvl 20.031 6 11-Sep-23 18-Sep-23 12-Sep-23 18-Sep-23 0% 158 -1 Installation of Platforms @ Lvl 20.031
G105-BMU-CON-2160 Installation of Platforms @ Lvl 14.031 6 18-Sep-23 25-Sep-23 19-Sep-23 25-Sep-23 0% 158 -1 Installation of Platforms @ Lvl 14.031
Works above Decking Slab 271 06-Mar-23 12-Feb-24 06-Mar-23 A 12-Feb-24 43 -1
G105-BMU-CON-2000 Installation of Stub Brackets for Combined Cableline & Abseiling Systems at Level +34.15 3 06-Mar-23 08-Mar-23 06-Mar-23 A 08-Mar-23 A 100% 1
G105-BMU-CON-2060 Installation of Support Brackets for Combined Cableline & Abseiling Systems at Level +34.15 2 11-Jul-23 13-Jul-23 04-Jul-23 06-Jul-23 0% 186 6 Installation of Support Brackets for Combined Cab
G105-BMU-CON-2070 Hatch Installation 4 11-Jul-23 15-Jul-23 04-Jul-23 08-Jul-23 0% 184 6 Hatch Installation
G105-BMU-CON-2090 Installation of Platforms @ Lvl 37.646 7 20-Jul-23 28-Jul-23 11-Aug-23 19-Aug-23 0% 114 -19 Installation of Platforms @ Lvl 37.646
G105-BMU-CON-2030 Installation of Roof Walkway@ Lvl 41.025 24 28-Jul-23 25-Aug-23 19-Aug-23 16-Sep-23 0% 114 -19 Installation of Roof Walkway@ Lvl 41.02
G105-BMU-CON-2040 Installation of Abseiling Brackets at Roof 6 25-Aug-23 01-Sep-23 16-Sep-23 23-Sep-23 0% 120 -19 Installation of Abseiling Brackets at Roo

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 5 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
G105-BMU-CON-2020 Installation of Ladders & Platforms Above Decking Slab 12 25-Aug-23 08-Sep-23 16-Sep-23 02-Oct-23 0% 114 -19 Installation of Ladders & Platforms Abo
G105-BMU-CON-2080 Installation of Fall Arrest/Cable Line 6 05-Feb-24 12-Feb-24 06-Feb-24 12-Feb-24 0% 43 -1 Installation of Fall Ar
Commissioning 26 12-Feb-24 14-Mar-24 13-Feb-24 15-Mar-24 43 -1
G105-BMU-PROC-1560 Testing & Commissioning (Load tests / 3rd Party Inspections / Visual tests) 26 12-Feb-24 14-Mar-24 13-Feb-24 15-Mar-24 0% 43 -1 Testing & Com
GYPSUM AND PARTITION WORKS (MAIS & OTHERS) 313 20-Feb-23 08-Mar-24 10-Feb-23 A 08-Mar-24 47 -1

Engineering 91 20-Feb-23 07-Jun-23 10-Feb-23 A 12-Jun-23 18 -4


Calcluations 60 20-Feb-23 11-May-23 20-Feb-23 A 16-May-23 19 -4
G105-E-GP-100 Calculation for Gallery 105 - Preparation and Submission 24 20-Feb-23 18-Mar-23 20-Feb-23 A 25-Mar-23 A 100% -5
G105-E-GP-110 Calculation for Gallery 105 - Review & Comments 14 20-Mar-23 08-Apr-23 25-Mar-23 A 17-Apr-23 95% 16 -5 Calculation for Gallery 105 - Review & Comments
G105-E-GP-120 Calculation for Gallery 105 - Revise & Resubmission 6 08-Apr-23 25-Apr-23 17-Apr-23 29-Apr-23 0% 19 -4 Calculation for Gallery 105 - Revise & Resubmission
G105-E-GP-130 Calculation for Gallery 105 - Review & Approval 12 25-Apr-23 11-May-23 01-May-23 16-May-23 0% 16 -4 Calculation for Gallery 105 - Review & Approval
Wall Section & 3D Isometric 63 06-Mar-23 05-Jun-23 07-Mar-23 A 08-Jun-23 21 -3
G105-E-GP-240 3D Isometric and Wall sections for Gallery 105 - Preparation and Submission 12 06-Mar-23 18-Mar-23 07-Mar-23 A 17-Apr-23 95% 25 -16 3D Isometric and Wall sections for Gallery 105 - Preparation an
G105-E-GP-250 3D Isometric and Wall sections for Gallery 105 - Review & Comments 14 20-Mar-23 08-Apr-23 18-Apr-23 11-May-23 0% 21 -20 3D Isometric and Wall sections for Gallery 105 - Review &
G105-E-GP-260 3D Isometric and Wall sections for Gallery 105 - Revise & Resubmission 6 11-May-23 18-May-23 16-May-23 23-May-23 0% 21 -4 3D Isometric and Wall sections for Gallery 105 - Revise &
G105-E-GP-270 3D Isometric and Wall sections for Gallery 105 - Review & Approval 12 18-May-23 05-Jun-23 24-May-23 08-Jun-23 0% 18 -4 3D Isometric and Wall sections for Gallery 105 - Review
Shop Drawings 59 06-Mar-23 07-Jun-23 20-Mar-23 A 12-Jun-23 18 -4
G105-E-GP-280 Shop Drawings for Gallery 105 - Preparation and Submission 18 06-Mar-23 28-Mar-23 20-Mar-23 A 18-Apr-23 95% 28 -11 Shop Drawings for Gallery 105 - Preparation and Submission
G105-E-GP-290 Shop Drawings for G Gallery 105 - Review & Comments 9 29-Mar-23 11-Apr-23 18-Apr-23 04-May-23 0% 24 -13 Shop Drawings for G Gallery 105 - Review & Comments
G105-E-GP-300 Shop Drawings for Gallery 105 - Re Submission 6 11-May-23 18-May-23 16-May-23 23-May-23 0% 19 -4 Shop Drawings for Gallery 105 - Re Submission
G105-E-GP-310 Shop Drawings for G Gallery 105 - Approval 14 18-May-23 07-Jun-23 24-May-23 12-Jun-23 0% 16 -4 Shop Drawings for G Gallery 105 - Approval
Material Submittals &Approvals 55 20-Feb-23 04-May-23 10-Feb-23 A 17-Apr-23 55 10
G105-E-GP-500 Material Submittals for Gallery 105 - Preparation and Submission 18 20-Feb-23 11-Mar-23 10-Feb-23 A 02-Mar-23 A 100% 8
G105-E-GP-510 Material Submittals for G Gallery 105 - Review & Comments 12 13-Mar-23 29-Mar-23 07-Mar-23 A 10-Mar-23 A 100% 13
G105-E-GP-520 Material Submittals for Gallery 105 - Re Submission 6 29-Mar-23 10-Apr-23 24-Mar-23 A 30-Mar-23 A 100% 6
G105-E-GP-530 Material Submittals for G Gallery 105 - Approval 14 10-Apr-23 04-May-23 30-Mar-23 A 17-Apr-23 95% 46 9 Material Submittals for G Gallery 105 - Approval
Procurement 135 14-Apr-23 07-Sep-23 01-Mar-23 A 26-Aug-23 104 10
Purchase Orders 68 14-Apr-23 15-Jun-23 01-Mar-23 A 03-Jun-23 102 10
G105-P-GP-100 Purchase Order for Gypsum Gallery Walls 18 14-Apr-23 12-May-23 01-Mar-23 A 21-Mar-23 A 100% 31
G105-P-GP-120 Purchase Order for Acoustic Plaster 36 04-May-23 15-Jun-23 17-Apr-23 03-Jun-23 0% 102 10 Purchase Order for Acoustic Plaster
Production & Deliveries 117 12-May-23 07-Sep-23 01-May-23 26-Aug-23 126 12
G105-P-GP-110 Manufacturing & Delivery for Gypsum Gallery Walls 20 12-May-23 01-Jun-23 01-May-23 21-May-23 0% 67 11 Manufacturing & Delivery for Gypsum Gallery Walls
G105-P-GP-130 Manufacturing & Delivery for Acoustic Plaster 84 15-Jun-23 07-Sep-23 03-Jun-23 26-Aug-23 0% 126 12 Manufacturing & Delivery for Acoustic Plas
Construction 222 13-Jun-23 08-Mar-24 12-Jun-23 08-Mar-24 47 -1
Skylight Well wall 114 13-Jun-23 24-Oct-23 12-Jun-23 31-Oct-23 155 -5
Gypsum works 110 13-Jun-23 19-Oct-23 12-Jun-23 26-Oct-23 159 -5
G105-C-GP-100 Erection of Steel Scaffolding (H:25m) 6 13-Jun-23 20-Jun-23 12-Jun-23 19-Jun-23 0% 18 1 Erection of Steel Scaffolding (H:25m)
G105-C-GP-110 Setting out points/Marking and Inspection (H:25m) 3 20-Jun-23 23-Jun-23 19-Jun-23 22-Jun-23 0% 18 1 Setting out points/Marking and Inspection (H:25m)
G105-C-GP-120 Approval of Setting out points/Marking (H:25m) 2 23-Jun-23 26-Jun-23 22-Jun-23 24-Jun-23 0% 18 1 Approval of Setting out points/Marking (H:25m)
G105-C-GP-130 Framing (H:25m) 12 03-Jul-23 15-Jul-23 08-Jul-23 24-Jul-23 0% 10 -5 Framing (H:25m)
G105-C-GP-140 Fixing of Gypsum Board for Closure 1st Layer (H:25m) 12 08-Jul-23 22-Jul-23 14-Jul-23 29-Jul-23 0% 10 -5 Fixing of Gypsum Board for Closure 1st Layer (H
G105-C-GP-160 Clearance from Main-contractor for Closure (H:25m) 12 24-Jul-23 05-Aug-23 29-Jul-23 12-Aug-23 0% 10 -5 Clearance from Main-contractor for Closure (H
G105-C-GP-170 Approval From Consultant for Closure (H:25m) 6 07-Aug-23 12-Aug-23 12-Aug-23 19-Aug-23 0% 10 -5 Approval From Consultant for Closure (H:25m
G105-C-GP-180 Fixing of Gypsum Board for Closure (H:25m) 9 14-Aug-23 23-Aug-23 19-Aug-23 30-Aug-23 0% 10 -5 Fixing of Gypsum Board for Closure (H:25m
G105-C-GP-190 Acoustical Plaster Insulation (H:25m) 7 24-Aug-23 31-Aug-23 30-Aug-23 07-Sep-23 0% 65 -5 Acoustical Plaster Insulation (H:25m)
G105-C-GP-200 Marking of MEP Final Fixes from Main-Contractor (H:25m) 4 01-Sep-23 05-Sep-23 07-Sep-23 12-Sep-23 0% 65 -5 Marking of MEP Final Fixes from Main-C
G105-C-GP-210 Cutting for MEP Final Fixes and Fixation of Access Panel (H:25m) 4 06-Sep-23 09-Sep-23 12-Sep-23 16-Sep-23 0% 65 -5 Cutting for MEP Final Fixes and Fixation
G105-C-GP-620 MEP Final Fixes (Covelights, Fire alarm, Grills & Diffussers PV/AV, etc.) 9 11-Sep-23 20-Sep-23 16-Sep-23 28-Sep-23 0% 65 -5 MEP Final Fixes (Covelights, Fire alarm
G105-C-GP-220 Skim Coating Finish (H:25m) 12 21-Sep-23 05-Oct-23 28-Sep-23 12-Oct-23 0% 65 -5 Skim Coating Finish (H:25m)
G105-C-GP-650 Final Finish (Paint etc.) (H:25m) 12 06-Oct-23 19-Oct-23 12-Oct-23 26-Oct-23 0% 159 -5 Final Finish (Paint etc.) (H:25m)
Acoustic Plaster 16 06-Oct-23 24-Oct-23 12-Oct-23 31-Oct-23 65 -5
G105-C-GP-230 Acoustical Plaster Finish (H:25m) 16 06-Oct-23 24-Oct-23 12-Oct-23 31-Oct-23 0% 65 -5 Acoustical Plaster Finish (H:25m)
Gallery Ceiling 94 04-Sep-23 27-Dec-23 05-Sep-23 27-Dec-23 61 -1
Gypsum works 94 04-Sep-23 27-Dec-23 05-Sep-23 27-Dec-23 61 -1
G105-C-GP-500 Setting out points/Marking and Inspection (H:20m) 4 04-Sep-23 08-Sep-23 05-Sep-23 08-Sep-23 0% 0 -1
G105-C-GP-510 Approval of Setting out points/Marking (H:20m) 2 08-Sep-23 11-Sep-23 09-Sep-23 11-Sep-23 0% 0 -1
G105-C-GP-520 Fixing Hangers (H:20m) 12 11-Sep-23 25-Sep-23 12-Sep-23 25-Sep-23 0% 0 -1
G105-C-GP-530 Location of access Panel by Main-Contractor (H:20m) 4 21-Sep-23 26-Sep-23 22-Sep-23 26-Sep-23 0% 0 -1
G105-C-GP-540 Install Framing (H:20m) 12 26-Sep-23 11-Oct-23 28-Sep-23 11-Oct-23 0% 0 -1
G105-C-GP-550 Closure Clearance from Main-Contractor (H:20m) 12 11-Oct-23 25-Oct-23 12-Oct-23 25-Oct-23 0% 31 -1 Closure Clearance from Main-Contr
G105-C-GP-560 Approval From Consultant for Closure (H:20m) 6 25-Oct-23 01-Nov-23 26-Oct-23 01-Nov-23 0% 31 -1 Approval From Consultant for Clos

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 6 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
G105-C-GP-570 Fixing of Gypsum board (H:20m) 6 01-Nov-23 08-Nov-23 02-Nov-23 08-Nov-23 0% 31 -1 Fixing of Gypsum board (H:20m)
G105-C-GP-580 Acoustical Plaster Insulation (H:20m) 4 08-Nov-23 13-Nov-23 09-Nov-23 13-Nov-23 0% 31 -1 Acoustical Plaster Insulation (H:2
G105-C-GP-590 Marking of MEP Final Fixes from Main-Contractor (H:20m) 4 13-Nov-23 17-Nov-23 14-Nov-23 17-Nov-23 0% 31 -1 Marking of MEP Final Fixes from
G105-C-GP-600 Cutting for MEP Final Fixes and Fixation of Access Panel (H:20m) 4 17-Nov-23 22-Nov-23 18-Nov-23 22-Nov-23 0% 31 -1 Cutting for MEP Final Fixes and
G105-C-GP-630 MEP Final Fixes (Lights, Fire alarm, Grills & Diffussers PV/AV, etc.) 15 22-Nov-23 13-Dec-23 23-Nov-23 13-Dec-23 0% 31 -1 MEP Final Fixes (Lights, Fire
G105-C-GP-660 Final Finish (Paint etc.) (H:20m) 12 13-Dec-23 27-Dec-23 14-Dec-23 27-Dec-23 0% 61 -1 Final Finish (Paint etc.) (H:
Acoustic Plaster 12 13-Dec-23 27-Dec-23 14-Dec-23 27-Dec-23 31 -1
G105-C-GP-610 Acoustical Plaster Finish (H:20m) 12 13-Dec-23 27-Dec-23 14-Dec-23 27-Dec-23 0% 31 -1 Acoustical Plaster Finish (
Gallery Walls 136 26-Sep-23 08-Mar-24 28-Sep-23 08-Mar-24 0 -1
G105-C-GP-300 Setting out points/Marking and Inspection (H:20m) 4 26-Sep-23 02-Oct-23 28-Sep-23 02-Oct-23 0% 0 -1
G105-C-GP-310 Approval of Setting out points/Marking (H:20m) 2 02-Oct-23 04-Oct-23 03-Oct-23 04-Oct-23 0% 0 -1
G105-C-GP-330 Steel Protection Spray by Main Contractor (H:20m) 6 14-Oct-23 21-Oct-23 16-Oct-23 21-Oct-23 0% 16 -1 Steel Protection Spray by Main Con
G105-C-GP-320 Installation of Steel Bracing (H:20m) 22 04-Oct-23 30-Oct-23 05-Oct-23 30-Oct-23 0% 0 -1
G105-C-GP-340 Framing (H:20m) 22 18-Oct-23 13-Nov-23 19-Oct-23 13-Nov-23 0% 0 -1
G105-C-GP-350 Clearance from Main-contractor for Closure (H:20m) 12 13-Nov-23 27-Nov-23 14-Nov-23 27-Nov-23 0% 0 -1
G105-C-GP-360 Approval From Consultant for Closure (H:20m) 6 27-Nov-23 07-Dec-23 28-Nov-23 07-Dec-23 0% 0 -1
G105-C-GP-370 Fixing of Gypsum Board for Closure 1st Layer (H:20m) 22 07-Dec-23 03-Jan-24 08-Dec-23 03-Jan-24 0% 0 -1
G105-C-GP-390 Fixing of Gypsum Board for Closure 2nd Layer (H:20m) 22 11-Dec-23 06-Jan-24 12-Dec-23 06-Jan-24 0% 0 -1
G105-C-GP-400 Marking of MEP Final Fixes from Main-Contractor (H:20m) 10 28-Dec-23 10-Jan-24 29-Dec-23 10-Jan-24 0% 0 -1
G105-C-GP-410 Cutting for MEP Final Fixes and Fixation of Access Panel (H:20m) 10 30-Dec-23 12-Jan-24 02-Jan-24 12-Jan-24 0% 0 -1
G105-C-GP-640 MEP Final Fixtures 18 12-Jan-24 02-Feb-24 13-Jan-24 02-Feb-24 0% 0 -1
G105-C-GP-420 Skim Coating (H:20m) 12 02-Feb-24 16-Feb-24 03-Feb-24 16-Feb-24 0% 0 -1
G105-C-GP-670 Final Finish (Paint etc.) (H:20m) 18 16-Feb-24 08-Mar-24 17-Feb-24 08-Mar-24 0% 0 -1
EXTERNAL GLAZING (ALICO) 382 01-Oct-22 22-Jan-24 01-Oct-22 A 22-Jan-24 105 -1

Engineering 183 01-Oct-22 06-May-23 01-Oct-22 A 29-May-23 11 -19


BIM Model Finalization (ALICO) 138 14-Nov-22 02-Mar-23 14-Nov-22 A 15-May-23 11 -49
G105-E-GP-360 BIM model for Gallery 105 - Preparation and Submission 18 14-Nov-22 07-Dec-22 14-Nov-22 A 01-May-23 60% 11 -110 BIM model for Gallery 105 - Preparation and Submission
G105-E-GP-370 BIM model for Gallery 105 - Collaborations and Clash Detection 9 06-Dec-22 26-Dec-22 24-Mar-23 A 06-May-23 40% 11 -99 BIM model for Gallery 105 - Collaborations and Clash Detec
G105-E-GP-380 BIM model for Gallery 105 - Clash Resolutions and Resubmission 8 21-Feb-23 02-Mar-23 31-Mar-23 A 15-May-23 20% 11 -49 BIM model for Gallery 105 - Clash Resolutions and Resub
System Design 124 01-Oct-22 27-Feb-23 01-Oct-22 A 05-Feb-23 A 19
EG2.2 (Skylight) 23 01-Oct-22 28-Oct-22 01-Oct-22 A 26-Oct-22 A 3
G105-EG-ENG-1000 System Design Submission EG2.2 6 01-Oct-22 07-Oct-22 01-Oct-22 A 07-Oct-22 A 100% 1
G105-EG-ENG-1010 System Design Approval EG2.2 17 10-Oct-22 28-Oct-22 08-Oct-22 A 26-Oct-22 A 100% 3
ES9 (External Metal Cladding) 118 10-Oct-22 27-Feb-23 08-Oct-22 A 05-Feb-23 A 19
G105-EG-ENG-1040 System Design Submission ES9 13 10-Oct-22 24-Oct-22 08-Oct-22 A 21-Dec-22 A 100% -46
G105-EG-ENG-1050 System Design Approval ES9 48 03-Jan-23 27-Feb-23 03-Nov-22 A 05-Feb-23 A 100% 19
Shop Drawings 145 16-Nov-22 06-May-23 12-Oct-22 A 29-May-23 11 -19
EG2.2 (Skylight) 16 16-Nov-22 07-Dec-22 16-Nov-22 A 20-May-23 16 -127
G105-EG-ENG-1060 Preparation and Submission of Shop Drawing EG2.2 6 16-Nov-22 22-Nov-22 16-Nov-22 A 26-Apr-23 50% 32 -116 Preparation and Submission of Shop Drawing EG2.2
G105-EG-ENG-1070 Approval of Shop Drawing EG2.2 10 23-Nov-22 07-Dec-22 23-Nov-22 A 20-May-23 50% 16 -127 Approval of Shop Drawing EG2.2
ES9 (External Metal Cladding) 30 16-Mar-23 06-May-23 12-Oct-22 A 29-May-23 11 -19
G105-EG-ENG-1100 Preparation and Submission of Shop Drawing ES9 18 16-Mar-23 17-Apr-23 12-Oct-22 A 15-May-23 10% 11 -19 Preparation and Submission of Shop Drawing ES9
G105-EG-ENG-1110 Approval of Shop Drawing ES9 18 05-Apr-23 06-May-23 02-Nov-22 A 29-May-23 10% 11 -19 Approval of Shop Drawing ES9
Procurement 57 10-Oct-22 06-Jun-23 17-Apr-23 03-Jul-23 274 -19
EG2.2 (Skylight) 30 10-Oct-22 04-Mar-23 17-Apr-23 27-May-23 10 -58
G105-EG-PRO-1120 Material Procurment EG2.2 - Extrusion 30 10-Oct-22 16-Nov-22 17-Apr-23 27-May-23 0% 10 -148 Material Procurment EG2.2 - Extrusion
G105-EG-PRO-1130 Material Procurement - EG2.2 - Brackets, Frames & Glass 30 23-Jan-23 04-Mar-23 17-Apr-23 27-May-23 0% 10 -58 Material Procurement - EG2.2 - Brackets, Frames & Gla
G105-EG-PRO-1140 Material Procurement - EG2.2 - Hardware & Accessories 30 23-Jan-23 25-Feb-23 17-Apr-23 27-May-23 0% 10 -64 Material Procurement - EG2.2 - Hardware & Accessories
ES9 (External Metal Cladding) 38 17-Apr-23 06-Jun-23 15-May-23 03-Jul-23 274 -19
G105-EG-PRO-1250 Material Procurement - ES9 - Secondary Steel / Brackets etc. 18 17-Apr-23 13-May-23 15-May-23 05-Jun-23 0% 13 -19 Material Procurement - ES9 - Secondary Steel / Bracke
G105-EG-PRO-1190 Material Procurement - ES9 - Metal Panels 26 06-May-23 06-Jun-23 29-May-23 03-Jul-23 0% 11 -19 Material Procurement - ES9 - Metal Panels
G105-EG-PRO-1200 Material Procurement - ES9 - Runners, Hardware & Accessories 26 06-May-23 06-Jun-23 29-May-23 03-Jul-23 0% 274 -19 Material Procurement - ES9 - Runners, Hardware &
Material Fabrication & Deliveries 47 28-Apr-23 04-Jul-23 27-May-23 27-Jul-23 254 -19
G105-EG-PRO-1240 Fabrication & Delivery of Brackets, Frames & Metal Panels Assembly - ES9 12 13-May-23 27-May-23 05-Jun-23 19-Jun-23 0% 13 -19 Fabrication & Delivery of Brackets, Frames & Metal P
G105-EG-PRO-1210 Fabrication & Delivery of Brackets, Frames & Glass - EG2.2 20 28-Apr-23 24-May-23 27-May-23 20-Jun-23 0% 10 -23 Fabrication & Delivery of Brackets, Frames & Glass -
G105-EG-PRO-1260 Fabrication & Delivery of Metal Panels Assembly - ES9 20 06-Jun-23 04-Jul-23 03-Jul-23 27-Jul-23 0% 254 -19 Fabrication & Delivery of Metal Panels Assembl
Installation 189 13-May-23 22-Jan-24 05-Jun-23 22-Jan-24 55 -1
EG2.2 (Skylight) 176 24-May-23 22-Jan-24 20-Jun-23 22-Jan-24 43 -1
G105-EG-CON-1260 Survey and Setting out 6 24-May-23 31-May-23 20-Jun-23 27-Jun-23 0% 10 -23 Survey and Setting out
G105-EG-CON-1270 Installation of Main Steel with Alignment 12 27-May-23 10-Jun-23 23-Jun-23 12-Jul-23 0% 10 -23 Installation of Main Steel with Alignment
G105-EG-CON-1280 Installation of Brackets & Frames (EG2.2) 15 03-Jun-23 21-Jun-23 05-Jul-23 24-Jul-23 0% 10 -23 Installation of Brackets & Frames (EG2.2)

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 7 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
G105-EG-CON-1290 Installation of Glass 15 27-Dec-23 15-Jan-24 28-Dec-23 15-Jan-24 0% 43 -1 Installation of Glass
G105-EG-CON-1300 Finishing Work 15 04-Jan-24 22-Jan-24 05-Jan-24 22-Jan-24 0% 43 -1 Finishing Work
ES9 (External Metal Cladding) 64 13-May-23 02-Aug-23 05-Jun-23 24-Aug-23 180 -19
G105-EG-CON-1360 Survey and Setting out 6 13-May-23 20-May-23 05-Jun-23 12-Jun-23 0% 13 -19 Survey and Setting out
G105-EG-CON-1370 Installation of Main Steel with Alignment 6 20-May-23 27-May-23 12-Jun-23 19-Jun-23 0% 13 -19 Installation of Main Steel with Alignment
G105-EG-CON-1380 Installation of Brackets & Frames (ES9) 20 27-May-23 20-Jun-23 19-Jun-23 17-Jul-23 0% 13 -19 Installation of Brackets & Frames (ES9)
G105-EG-CON-1390 Installation of Cladding 26 06-Jun-23 11-Jul-23 03-Jul-23 03-Aug-23 0% 11 -19 Installation of Cladding
G105-EG-CON-1400 Finishing Work 18 11-Jul-23 02-Aug-23 03-Aug-23 24-Aug-23 0% 180 -19 Finishing Work
ROOFING ASSEMBLY (WP3+EP5) 277 20-Feb-23 05-Feb-24 20-Feb-23 A 05-Feb-24 43 -1

WP 3 SYSTEM (PROTECT MIDDLE EAST) 195 20-Feb-23 05-Oct-23 20-Feb-23 A 27-Oct-23 114 -19
BIM Model Finalization (PROTECT ME) 61 20-Feb-23 27-Apr-23 20-Feb-23 A 18-May-23 150 -18
G105-E-GP-470 BIM model for Gallery 105 - Preparation and Submission 18 20-Feb-23 11-Mar-23 20-Feb-23 A 03-May-23 50% 150 -31 BIM model for Gallery 105 - Preparation and Submission
G105-E-GP-480 BIM model for Gallery 105 - Collaborations and Clash Detection 18 13-Mar-23 08-Apr-23 01-Mar-23 A 13-May-23 50% 150 -22 BIM model for Gallery 105 - Collaborations and Clash Dete
G105-E-GP-490 BIM model for Gallery 105 - Clash Resolutions and Resubmission 8 10-Apr-23 27-Apr-23 20-Mar-23 A 18-May-23 50% 150 -18 BIM model for Gallery 105 - Clash Resolutions and Resub
Engineering 85 27-Apr-23 27-Jun-23 20-Mar-23 A 10-Jul-23 184 -7
G105-RW-CON-1000 Submission of Shop Drawings 22 27-Apr-23 23-May-23 20-Mar-23 A 31-May-23 50% 150 -7 Submission of Shop Drawings
G105-RW-CON-1010 Shop Drawing Review & Comments 12 23-May-23 06-Jun-23 31-May-23 14-Jun-23 0% 150 -7 Shop Drawing Review & Comments
G105-RW-CON-1050 Submission of Shop Drawings- Rev-01 6 06-Jun-23 13-Jun-23 14-Jun-23 21-Jun-23 0% 184 -7 Submission of Shop Drawings- Rev-01
G105-RW-CON-1060 Approval of Shop Drawings- Rev-01 12 13-Jun-23 27-Jun-23 21-Jun-23 10-Jul-23 0% 184 -7 Approval of Shop Drawings- Rev-01
Procurement 52 06-Jun-23 11-Aug-23 14-Jun-23 19-Aug-23 150 -7
G105-RW-CON-1020 Delivery of Materials 52 06-Jun-23 11-Aug-23 14-Jun-23 19-Aug-23 0% 150 -7 Delivery of Materials
Construction 22 08-Sep-23 05-Oct-23 02-Oct-23 27-Oct-23 114 -19
G105-RW-CON-1040 Application of Waterproofing System on the Roof surface 22 08-Sep-23 05-Oct-23 02-Oct-23 27-Oct-23 0% 114 -19 Application of Waterproofing System
EP5 ROOFING ASSEMBLY 238 13-Apr-23 05-Feb-24 17-Apr-23 05-Feb-24 43 -1
Engineering 40 13-Apr-23 06-Jun-23 17-Apr-23 08-Jun-23 229 -2
G105-RW-CON-1070 Submission of Shop Drawings 10 13-Apr-23 02-May-23 17-Apr-23* 04-May-23 0% 187 -2 Submission of Shop Drawings
G105-RW-CON-1080 Shop Drawing Review & Comments 12 02-May-23 16-May-23 04-May-23 18-May-23 0% 187 -2 Shop Drawing Review & Comments
G105-RW-CON-1120 Submission of Shop Drawings- Rev-01 6 16-May-23 23-May-23 18-May-23 25-May-23 0% 229 -2 Submission of Shop Drawings- Rev-01
G105-RW-CON-1130 Approval of Shop Drawings- Rev-01 12 23-May-23 06-Jun-23 25-May-23 08-Jun-23 0% 229 -2 Approval of Shop Drawings- Rev-01
Procurement 60 16-May-23 31-Jul-23 18-May-23 02-Aug-23 187 -2
G105-RW-CON-1090 Delivery of Materials 60 16-May-23 31-Jul-23 18-May-23 02-Aug-23 0% 187 -2 Delivery of Materials
Construction 154 12-Jul-23 05-Feb-24 04-Aug-23 05-Feb-24 43 -1
G105-RW-CON-1140 Installation of Roof drain / Overflow drain 6 12-Jul-23 20-Jul-23 04-Aug-23 11-Aug-23 0% 157 -19 Installation of Roof drain / Overflow drain
G105-RW-CON-1110 Installation of Concrete paver Ballast 12 22-Jan-24 05-Feb-24 23-Jan-24 05-Feb-24 0% 43 -1 Installation of Concre
SHADES PACKAGE (MIMA) 395 18-Oct-22 21-Feb-24 18-Oct-22 A 21-Feb-24 61 -1

General 119 18-Oct-22 08-Mar-23 18-Oct-22 A 13-Mar-23 A -3


G105-G-SHD-100 Tendering & Package Awarding 12 18-Oct-22 28-Dec-22 18-Oct-22 A 27-Feb-23 A 100% -51
G105-G-SHD-110 Subcontractor Mobilization 12 22-Feb-23 08-Mar-23 12-Feb-23 A 13-Mar-23 A 100% -3
Engineering 97 01-Mar-23 17-Jun-23 15-Feb-23 A 23-Jun-23 142 -5
Design 47 01-Mar-23 09-May-23 18-Feb-23 A 29-May-23 26 -17
G105-E-SHD-100 Submission of Design - Shades Pkg. 12 01-Mar-23 15-Mar-23 18-Feb-23 A 10-Mar-23 A 100% 5
G105-E-SHD-110 Review and Comments on Design - Shades Pkg. 12 15-Mar-23 03-Apr-23 11-Mar-23 A 04-May-23 10% 20 -17 Review and Comments on Design - Shades Pkg.
G105-E-SHD-120 Resubmission of Design (Post Comments) - Shades Pkg. 9 03-Apr-23 25-Apr-23 05-May-23 15-May-23 0% 26 -17 Resubmission of Design (Post Comments) - Shades Pkg.
G105-E-SHD-130 Final Approval of Design - Shades Pkg 12 25-Apr-23 09-May-23 16-May-23 29-May-23 0% 26 -17 Final Approval of Design - Shades Pkg
Shop Drawings 47 03-Apr-23 29-May-23 17-Apr-23 15-Jun-23 26 -15
G105-E-SHD-140 Submission of Shop Drawings 6 03-Apr-23 14-Apr-23 17-Apr-23 29-Apr-23 0% 20 -7 Submission of Shop Drawings
G105-E-SHD-150 Review and Comments on Shop Drawings 14 14-Apr-23 08-May-23 29-Apr-23 16-May-23 0% 34 -7 Review and Comments on Shop Drawings
G105-E-SHD-160 Re-submission of Shop Drawings 6 08-May-23 15-May-23 26-May-23 01-Jun-23 0% 26 -15 Re-submission of Shop Drawings
G105-E-SHD-170 Approval of Shop Drawings 12 15-May-23 29-May-23 02-Jun-23 15-Jun-23 0% 26 -15 Approval of Shop Drawings
Method Statement 63 22-Mar-23 17-Jun-23 18-Feb-23 A 23-Jun-23 20 -5
G105-E-SHD-180 Submission of Method Statement 14 22-Mar-23 19-Apr-23 18-Feb-23 A 10-Mar-23 A 100% 25
G105-E-SHD-190 Review and Comments on Method Statement 21 19-Apr-23 18-May-23 11-Mar-23 A 24-May-23 10% 20 -5 Review and Comments on Method Statement
G105-E-SHD-200 Re-submission of Method Statement 14 18-May-23 03-Jun-23 24-May-23 09-Jun-23 0% 20 -5 Re-submission of Method Statement
G105-E-SHD-210 Approval of Method Statement 12 03-Jun-23 17-Jun-23 09-Jun-23 23-Jun-23 0% 20 -5 Approval of Method Statement
Material Submittals 89 01-Mar-23 10-Jun-23 15-Feb-23 A 14-Apr-23 A 44
Motors 60 01-Mar-23 06-May-23 18-Feb-23 A 14-Apr-23 A 14
G105-E-SHD-220 Submission of Material Submittal 12 01-Mar-23 15-Mar-23 18-Feb-23 A 17-Mar-23 A 100% -1
G105-E-SHD-240 Re-submission of Material Submittal 7 03-Apr-23 17-Apr-23 18-Feb-23 A 17-Mar-23 A 100% 18
G105-E-SHD-230 Review and Comments on Material Submittal 12 15-Mar-23 03-Apr-23 17-Mar-23 A 14-Apr-23 A 100% -5
G105-E-SHD-250 Approval of Material Submittal 12 17-Apr-23 06-May-23 17-Mar-23 A 14-Apr-23 A 100% 14
Blinds 89 15-Mar-23 10-Jun-23 15-Feb-23 A 13-Apr-23 A 44

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 8 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23
Activity ID Activity Name Original BL Project Start BL Project Finish Actual / Actual / Expected % Comp Total Var - BL Project 2023 2024
Duration Expected Start Finish Float Finish M A M J Jul A S Oct N D J F M Apr M JJul
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1516
G105-E-SHD-260 Submission of Material Submittal 14 15-Mar-23 07-Apr-23 15-Feb-23 A 17-Mar-23 A 100% 13
G105-E-SHD-280 Re-submission of Material Submittal 14 01-May-23 17-May-23 15-Feb-23 A 17-Mar-23 A 100% 39
G105-E-SHD-270 Review and Comments on Material Submittal 12 07-Apr-23 01-May-23 17-Mar-23 A 13-Apr-23 A 100% 9
G105-E-SHD-290 Approval of Material Submittal 21 17-May-23 10-Jun-23 17-Mar-23 A 13-Apr-23 A 100% 44
Procurement 112 06-May-23 30-Sep-23 17-Apr-23 06-Aug-23 243 55
G105-P-SHD-100 Procurement Works - Motors 56 06-May-23 01-Jul-23 17-Apr-23 11-Jun-23 0% 40 20 Procurement Works - Motors
G105-P-SHD-110 Procurement Works- Blind (Fabric) 112 10-Jun-23 30-Sep-23 17-Apr-23 06-Aug-23 0% 243 55 Procurement Works- Blind (Fabric)
Construction 190 03-Jul-23 21-Feb-24 08-Jul-23 21-Feb-24 61 -1
G105-C-SHD-210 Installation Works -Shades (Motors / Rollers etc.) 12 03-Jul-23 15-Jul-23 08-Jul-23 24-Jul-23 0% 10 -5 Installation Works -Shades (Motors / Rollers etc.
G105-C-SHD-100 Installation Works-Shades (Fabric/ Accessories etc.) 26 15-Jan-24 14-Feb-24 16-Jan-24 14-Feb-24 0% 61 -1 Installation Works-S
G105-C-SHD-200 T&C Works 6 14-Feb-24 21-Feb-24 15-Feb-24 21-Feb-24 0% 61 -1 T&C Works
GALLERY FLOOR FINISHES 317 01-May-23 20-May-24 24-Aug-22 A 20-May-24 18 0

Engineering 62 01-May-23 31-Jul-23 24-Aug-22 A 03-Jun-23 294 44


Shop Drawings 52 01-May-23 04-Jul-23 24-Aug-22 A 01-Sep-22 A 241
G105-FF-CON-1150 Submission of Shop Drawings 22 01-May-23 25-May-23 24-Aug-22 A 31-Aug-22 A 100% 212
G105-FF-CON-1170 Submission of Shop Drawings- Rev-01 6 09-Jun-23 15-Jun-23 24-Aug-22 A 31-Aug-22 A 100% 230
G105-FF-CON-1160 Shop Drawing Review & Comments 12 26-May-23 08-Jun-23 31-Aug-22 A 01-Sep-22 A 100% 223
G105-FF-CON-1180 Approval of Shop Drawings- Rev-01 12 16-Jun-23 04-Jul-23 31-Aug-22 A 01-Sep-22 A 100% 241
Material Submittals 40 26-May-23 31-Jul-23 05-Mar-23 A 03-Jun-23 154 44
G105-FF-CON-1200 Submission of Material Submittals 22 26-May-23 20-Jun-23 05-Mar-23 A 13-Mar-23 A 100% 72
G105-FF-CON-1210 Material Submittals- Review & Comments 12 21-Jun-23 08-Jul-23 13-Mar-23 A 04-May-23 10% 154 52 Material Submittals- Review & Comments
G105-FF-CON-1220 Submission of Material Submittals- Rev-01 6 10-Jul-23 15-Jul-23 05-May-23 11-May-23 0% 154 52 Submission of Material Submittals- Rev-01
G105-FF-CON-1230 Approval of Material Submittals- Rev-01 20 17-Jul-23 31-Jul-23 12-May-23 03-Jun-23 0% 154 44 Approval of Material Submittals- Rev-01
Procurement 177 09-Jun-23 16-Jan-24 17-Apr-23 21-Nov-23 154 44
G105-FF-CON-1190 Delivery of Materials 52 09-Jun-23 14-Aug-23 17-Apr-23 22-Jun-23 0% 279 41 Delivery of Materials
G105-FF-CON-1240 Award of Contract to Applicator 48 01-Aug-23 25-Sep-23 05-Jun-23 04-Aug-23 0% 154 44 Award of Contract to Applicator
G105-FF-CON-1250 Mobilization of Applicator 12 03-Jan-24 16-Jan-24 08-Nov-23 21-Nov-23 0% 154 44 Mobilization of Applicato
Construction 25 19-Apr-24 20-May-24 20-Apr-24 20-May-24 0 0
G105-FF-CON-1260 Application of Floor Finishes (SE- Silane, Penetrating Water Repellent) 25 19-Apr-24 20-May-24 20-Apr-24 20-May-24 0% 0 0
COMPLETION OF THE WORKS 18 20-May-24 10-Jun-24 20-May-24 10-Jun-24 0 0

G105-G-200 Snagging works / Inspections 18 20-May-24 10-Jun-24 20-May-24 10-Jun-24* 0% 0 0

Remaining Level of Effort Remaini... Date Revision Checked Approved


Page 9 of 9 Start Date: 04-Mar-22
Primary Baseline Critical R... Finish Date: 10-Jun-24
GALLERY 105 -Rev. 01_UPDT_17_04_23
Actual Work Milestone Data Date: 17-Apr-23