AIN TSILA DEVELOPMENT PROJECT

OVERALL SCHEDULE
A-PLN-SCH-730-38926-REV00
Activity ID Activity Name Original Start Finish 2021 2022
Duration October November December January February March April May June
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24 01 08 15 22 29 05
OVERALL SPHERE SCHEDULE 169d 25-Oct-21 23-May-22

MILESTONES 169d 25-Oct-21 23-May-22

A2070 Project Start Date 0d 25-Oct-21

A2080 Site mobilisation and installation 0d 25-Nov-21


A2090 Handover Sphere A 0d 29-Apr-22
A2100 Handover Sphere B 0d 19-Apr-22
A2110 Handover Sphere C 0d 14-May-22
A2120 Project Finish Date 0d 23-May-22
PRE-CONSTRUCTION 169d 25-Oct-21 23-May-22

SITE MOBILIZATION 169d 25-Oct-21 23-May-22


A1000 Temporary facilities / offices 2d 25-Oct-21 26-Oct-21
A1010 Equipments / cranes / tools 2d 25-Oct-21 26-Oct-21
A1020 Personnel / Staff 25d 26-Oct-21 25-Nov-21
A1025 PQR 2d 01-Nov-21 03-Nov-21
A1030 Consumable / Welding materials 15d 29-Oct-21 17-Nov-21
A1040 Progressive demobilization as per construction progress 55d 15-Mar-22 23-May-22
PRE-CONSTRUCTION CHECK 15d 01-Nov-21 19-Nov-21
A1050 Foundation check (alignment & elevation) 8d 01-Nov-21 10-Nov-21
A1060 Shell plates check (marking, damage, corrosion) 8d 01-Nov-21 10-Nov-21
A1070 Preparation of construction documents as per planned construction schedule 15d 01-Nov-21 19-Nov-21
A1080 Safely arrangements & preparations 15d 01-Nov-21 19-Nov-21
CONSTRUCTION 149d 10-Nov-21 14-May-22

SPHERE A 137d 10-Nov-21 29-Apr-22


SPHERE A - MAIN VESSEL 67d 10-Nov-21 02-Feb-22
A1090 Lower columns & scaffolding 11d 10-Nov-21 24-Nov-21
A1100 Scaffolding supports on equatorial plates 9d 10-Nov-21 22-Nov-21
A1110 Equatorial plates (main and secondary) + column bracings 18d 22-Nov-21 14-Dec-21
A1120 Bottom Crown 10d 01-Dec-21 14-Dec-21
A1130 Top Crown 10d 14-Dec-21 27-Dec-21
A1140 Welding 30d 27-Dec-21 02-Feb-22
SPHERE A - ACCESSORIES 29d 02-Feb-22 10-Mar-22
A1160 Nozzles 8d 02-Feb-22 11-Feb-22
A1170 Firefighting network 10d 11-Feb-22 24-Feb-22
A1180 Stair & Platforms 15d 02-Feb-22 21-Feb-22
A1190 Internal Ladders, supports & accessories 8d 02-Feb-22 11-Feb-22
A1200 Pipings 21d 11-Feb-22 10-Mar-22
SPHERE A - TESTING & HAND OVER 93d 22-Nov-21 17-Mar-22
A1620 Fit-up check (Dimentional & visual) 35d 22-Nov-21 04-Jan-22
A1630 NDE on welding joints 20d 02-Feb-22 26-Feb-22
A1640 Construction & Welding tracking / traceability 20d 02-Feb-22 26-Feb-22
A1650 Test-package handover and hydrotest 15d 26-Feb-22 17-Mar-22
SPHERE A - PAINTING & INSULATION 35d 17-Mar-22 29-Apr-22
A1210 Tank painting & touch up 16d 17-Mar-22 06-Apr-22
A1220 Touch up on temporary attachment's removal 3d 06-Apr-22 09-Apr-22
A1230 Painting & Insulation inspection 16d 11-Apr-22 29-Apr-22
SPHERE B 112d 30-Nov-21 19-Apr-22
SPHERE B - MAIN VESSEL 63d 30-Nov-21 16-Feb-22
A1670 Lower columns & scaffolding 11d 30-Nov-21 14-Dec-21
A1680 Scaffolding supports on equatorial plates 9d 30-Nov-21 11-Dec-21
A1690 Equatorial plates (main and secondary) + column bracings 18d 11-Dec-21 03-Jan-22
A1700 Bottom Crown 2d 31-Dec-21 03-Jan-22
A1710 Top Crown 3d 03-Jan-22 06-Jan-22
A1720 Welding 36d 03-Jan-22 16-Feb-22
SPHERE B - ACCESSORIES 29d 03-Jan-22 08-Feb-22
A1740 Nozzles 8d 03-Jan-22 13-Jan-22
A1750 Firefighting network 10d 13-Jan-22 25-Jan-22
A1760 Stair & Platforms 15d 03-Jan-22 21-Jan-22
A1770 Internal Ladders, supports & accessories 8d 03-Jan-22 13-Jan-22
A1780 Pipings 21d 13-Jan-22 08-Feb-22
SPHERE B - TESTING & HAND OVER 78d 11-Dec-21 18-Mar-22
A1820 Fit-up check (Dimentional & visual) 35d 11-Dec-21 24-Jan-22
A1830 NDE on welding joints 25d 10-Jan-22 09-Feb-22
A1840 Construction & Welding tracking / traceability 25d 15-Jan-22 15-Feb-22
A1850 Test-package handover and hydrotest 15d 16-Feb-22 07-Mar-22
A1860 Painting & Insulation inspection 10d 07-Mar-22 18-Mar-22
SPHERE B - PAINTING & INSULATION 35d 07-Mar-22 19-Apr-22
A1790 Tank painting & touch up 16d 07-Mar-22 25-Mar-22
A1800 Touch up on temporary attachment's removal 3d 25-Mar-22 30-Mar-22
A1810 Insulation 16d 30-Mar-22 19-Apr-22
SPHERE C 112d 27-Dec-21 14-May-22
SPHERE C - MAIN VESSEL 63d 27-Dec-21 15-Mar-22
A1870 Lower columns & scaffolding 11d 27-Dec-21 10-Jan-22
A1880 Scaffolding supports on equatorial plates 9d 27-Dec-21 06-Jan-22
A1890 Equatorial plates (main and secondary) + column bracings 18d 06-Jan-22 28-Jan-22
A1900 Bottom Crown 2d 26-Jan-22 28-Jan-22
A1910 Top Crown 3d 28-Jan-22 02-Feb-22
A1920 Welding 36d 28-Jan-22 15-Mar-22
SPHERE C - ACCESSORIES 29d 28-Jan-22 07-Mar-22
A1940 Nozzles 8d 28-Jan-22 08-Feb-22
A1950 Firefighting network 10d 08-Feb-22 21-Feb-22
A1960 Stair & Platforms 15d 28-Jan-22 16-Feb-22
A1970 Internal Ladders, supports & accessories 8d 28-Jan-22 08-Feb-22
A1980 Pipings 21d 08-Feb-22 07-Mar-22
SPHERE C - TESTING & HAND OVER 78d 06-Jan-22 13-Apr-22
A2020 Fit-up check (Dimentional & visual) 35d 06-Jan-22 18-Feb-22
A2030 NDE on welding joints 25d 04-Feb-22 08-Mar-22
A2040 Construction & Welding tracking / traceability 25d 10-Feb-22 14-Mar-22
A2050 Test-package handover and hydrotest 15d 14-Mar-22 01-Apr-22
A2060 Painting & Insulation inspection 10d 01-Apr-22 13-Apr-22
SPHERE C - PAINTING & INSULATION 35d 01-Apr-22 14-May-22
A1990 Tank painting & touch up 16d 01-Apr-22 21-Apr-22
A2000 Touch up on temporary attachment's removal 3d 21-Apr-22 25-Apr-22
A2010 Insulation 16d 25-Apr-22 14-May-22
AT THE END OF CONSTRUCTION 50d 17-Mar-22 18-May-22
A1290 Punch removal 30d 17-Mar-22 23-Apr-22
A1300 Mechanical Completion 20d 12-Apr-22 06-May-22
A1310 As-Built documents and final Dossier handover 25d 18-Apr-22 18-May-22

Remaining Level of Effort Actual Work Critical Remaining W... Date Revision Checked Approved
Page 1 of 1
Actual Level of Effort Remaining Work Milestone