A78350 Details of finishing items & Drawings 22 06-Nov-21 27-Nov-21 Details of finishing items & Drawings
Structure 10-Dec-21, Structure
91 11-Sep-21 10-Dec-21
A78360 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78370 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78380 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78390 Typical Floor (at Level +32' ~ 140' ) 32 21-Oct-21 21-Nov-21 Typical Floor (at Level +32' ~ 140' )
A78400 Roof Slab with Mumty (at Level +152' & 160') 19 22-Nov-21 10-Dec-21 Roof Slab with Mumty (at Level +152' & 160')
Actual Work Critical Remaining Work Summary Page 1 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
A78450 Roof Slab with Mumty (at Level +152' & 160') 19 22-Nov-21 10-Dec-21 Roof Slab with Mumty (at Level +152' & 160')
Revit / BIM Model (Arch /Str/ MEP) 15-Mar-22, Revit / BIM Model (Arch /Str/ MEP)
186 11-Sep-21 15-Mar-22
A78460 Basement Raft (at Level -10'-6") 81 11-Sep-21 30-Nov-21 Basement Raft (at Level -10'-6")
A78470 Basement Slab (at Level 0'-6") 30 01-Dec-21 30-Dec-21 Basement Slab (at Level 0'-6")
A78480 1st Floor (at Level +17'-00'') 21 31-Dec-21 20-Jan-22 1st Floor (at Level +17'-00'')
A78490 Typical Floor (at Level +32' ~ 140' ) 21 21-Jan-22 10-Feb-22 Typical Floor (at Level +32' ~ 140' )
A78500 Roof Slab with Mumty (at Level +152' & 160') 33 11-Feb-22 15-Mar-22 Roof Slab with Mumty (at Level +152' & 160')
IFC Drawings Of Building A & B 221 07-Aug-21 15-Mar-22 15-Mar-22, IFC Drawings Of Building A & B
Architecture 10-Dec-21, Architecture
126 07-Aug-21 10-Dec-21
A78510 Scehmatic Plans, building sections & 5 07-Aug-21 11-Aug-21 Scehmatic Plans, building sections & elevations, 3d views
elevations, 3d views
A78520 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78530 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78540 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78550 Typical Floor (at Level +32' ~ 140' ) 7 21-Oct-21 27-Oct-21 Typical Floor (at Level +32' ~ 140' )
A78560 Roof Slab with Mumty (at Level +152' & 160') 9 28-Oct-21 05-Nov-21 Roof Slab with Mumty (at Level +152' & 160')
A78570 Details of finishing items & Drawings 35 06-Nov-21 10-Dec-21 Details of finishing items & Drawings
Structure 10-Dec-21, Structure
91 11-Sep-21 10-Dec-21
A78580 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78590 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78600 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78610 Typical Floor (at Level +32' ~ 140' ) 32 21-Oct-21 21-Nov-21 Typical Floor (at Level +32' ~ 140' )
A78620 Roof Slab with Mumty (at Level +152' & 160') 19 22-Nov-21 10-Dec-21 Roof Slab with Mumty (at Level +152' & 160')
Revit / BIM Model (Arch /Str/ MEP) 15-Mar-22, Revit / BIM Model (Arch /Str/ MEP)
186 11-Sep-21 15-Mar-22
Actual Work Critical Remaining Work Summary Page 2 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
A78680 Basement Raft (at Level -10'-6") 81 11-Sep-21 30-Nov-21 Basement Raft (at Level -10'-6")
A78690 Basement Slab (at Level 0'-6") 30 01-Dec-21 30-Dec-21 Basement Slab (at Level 0'-6")
A78700 1st Floor (at Level +17'-00'') 21 31-Dec-21 20-Jan-22 1st Floor (at Level +17'-00'')
A78710 Typical Floor (at Level +32' ~ 140' ) 21 21-Jan-22 10-Feb-22 Typical Floor (at Level +32' ~ 140' )
A78720 Roof Slab with Mumty (at Level +152' & 160') 33 11-Feb-22 15-Mar-22 Roof Slab with Mumty (at Level +152' & 160')
Site Setting-up/ Mobilization 108 23-Jun-21 08-Oct-21 08-Oct-21, Site Setting-up/ Mobilization
A22455 Site Office and facilities establishment 70 23-Jun-21 31-Aug-21 Site Office and facilities establishment
Tube Well Works 06-Sep-21, Tube Well Works
41 28-Jul-21 06-Sep-21
A1220 Temporary Water Supply Bore 7 28-Jul-21 03-Aug-21 Temporary Water Supply Bore
A1230 Tubewell No.1 9 11-Aug-21 19-Aug-21 Tubewell No.1
A1240 Tubewell No.2 9 20-Aug-21 28-Aug-21 Tubewell No.2
A1250 Tubewell No.3 9 29-Aug-21 06-Sep-21 Tubewell No.3
Site Barrication & Fencing 05-Sep-21, Site Barrication & Fencing
6 31-Aug-21 05-Sep-21
A1465 Site barrication & cordoning off 6 31-Aug-21 05-Sep-21 Site barrication & cordoning off
Batching Plant Establishment 08-Oct-21, Batching Plant Establishment
38 01-Sep-21 08-Oct-21
A1550 Installation, Testing & Commissioning of 38 01-Sep-21 08-Oct-21 Installation, Testing & Commissioning of Batching Plant
Batching Plant
Labour and Staff Camp Area 07-Sep-21, Labour and Staff Camp Area
7 01-Sep-21 07-Sep-21
A2035 Establishment of Labor & staff camp 7 01-Sep-21 07-Sep-21 Establishment of Labor & staff camp facilities
facilities
Steel Yard Facility 12-Sep-21, Steel Yard Facility
6 07-Sep-21 12-Sep-21
A1970 Layout of Steel Yard 6 07-Sep-21 12-Sep-21 Layout of Steel Yard
Fabrication of Formwork 15-Sep-21, Fabrication of Formwork
15 01-Sep-21 15-Sep-21
A2010 Fabrication of Columns Formwork 7 01-Sep-21 07-Sep-21 Fabrication of Columns Formwork
A2020 Fabrication of Retaining wall Formwork 8 08-Sep-21 15-Sep-21 Fabrication of Retaining wall Formwork
Site Execution 551 06-Sep-21 10-Mar-23 10-Mar-23, Site Execution
Block-C 30-Dec-22, Block-C
481 06-Sep-21 30-Dec-22
Grey Structure 30-Dec-22, Grey Structure
481 06-Sep-21 30-Dec-22
Sub Structure 26-Dec-21, Sub Structure
112 06-Sep-21 26-Dec-21
Earth Works 24-Oct-21, Earth Works
49 06-Sep-21 24-Oct-21
A2130 Cleaning and Grubbing 9 06-Sep-21 14-Sep-21 Cleaning and Grubbing
A2140 Excavation Work 23 16-Sep-21 08-Oct-21 Excavation Work
A55270 Surface leveling and Compaction 29 25-Sep-21 23-Oct-21 Surface leveling and Compaction
A55280 Anti Termite Treatment 30 25-Sep-21 24-Oct-21 Anti Termite Treatment
A55290 Lean Concrete 30 25-Sep-21 24-Oct-21 Lean Concrete
Raft Pouring at Level -(9'-7'') 09-Nov-21, Raft Pouring at Level -(9'-7'')
31 10-Oct-21 09-Nov-21
Actual Work Critical Remaining Work Summary Page 3 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 4 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 8 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 9 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 10 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 11 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 12 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 13 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 14 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
A78945 Delivery & Installation of Power Cable 120 10-Dec-22 08-Apr-23 Delivery & Installation of
A78950 Delivery & Installation of HT/LT Panels 180 22-Aug-22 17-Feb-23 Delivery & Installation of HT/
A78960 Delivery & Installation of Genset 210 21-Sep-22 18-Apr-23 Delivery & Installation o
A78970 Delivery & Installation of Lift 210 06-Oct-22 03-May-23 Delivery & Installation
A78980 ELV System (PA+CCTV+FA+DT) 90 03-Jun-23 31-Aug-23 ELV System
A78985 Delivery & Installation of Energy Meters 120 18-Feb-23 17-Jun-23 Delivery & Installa
A78990 Installation of Terminal Fixtures 90 03-Jun-23 31-Aug-23 Installation
A79190 Testing & Commissioning 10 01-Sep-23 10-Sep-23 Testing & C
Plumbing Works 20-Sep-23
440 08-Jul-22 20-Sep-23
A79000 Installation of Piping Network (WS+SS) 265 08-Jul-22 29-Mar-23 Installation of Piping Netw
A79005 Delivery & Installation of Filteration Plant 45 28-Jun-23 11-Aug-23 Delivery & Ins
A79010 Delivery & Installation of Pumps 150 30-Mar-23 26-Aug-23 Delivery & In
A79020 Installation of Terminal Fixtures (Faucets, 165 30-Mar-23 10-Sep-23 Installation
WBs, WCs)
A79210 Testing & Commissioning 10 11-Sep-23 20-Sep-23 Testing &
Fire Fighting Works 23-Jun-23, Fire Fig
365 24-Jun-22 23-Jun-23
A79030 Installation of Piping Network 265 24-Jun-22 15-Mar-23 Installation of Piping Netw
A79035 Delivery & Installation of FF Sprinklers 150 16-Nov-22 14-Apr-23 Delivery & Installation o
A79040 Delivery & Installation of Pumps 180 16-Nov-22 14-May-23 Delivery & Installation
A79050 Delivery & Installation of FH Cabinets 75 31-Mar-23 13-Jun-23 Delivery & Installat
A79060 Delivery & Installation of Fire Hydrants 75 31-Mar-23 13-Jun-23 Delivery & Installat
A79070 Delivery & Installation of Extingishing 75 31-Mar-23 13-Jun-23 Delivery & Installat
Supplies
A79080 Testing & Commissioning 10 14-Jun-23 23-Jun-23 Testing & Commis
Air Conditioning Works 15-Mar-23, Air Conditioning
265 24-Jun-22 15-Mar-23
A79090 Installation of Ducts & Copper pipes 265 24-Jun-22 15-Mar-23 Installation of Ducts & Cop
Finishing Works 400 18-Aug-22 21-Sep-23 21-Sep-23
A79100 Internal Plaster 240 18-Aug-22 14-Apr-23 Internal Plaster
A79101 Flooring Works 270 18-Aug-22 14-May-23 Flooring Works
A79105 False Ceiling Works 270 06-Sep-22 02-Jun-23 False Ceiling Works
A79115 Floor & Wall Tiling 265 22-Sep-22 13-Jun-23 Floor & Wall Tiling
A79116 Paint Works 310 16-Nov-22 21-Sep-23 Paint Wor
A79117 Installation of Aluminium Windows 120 14-Feb-23 13-Jun-23 Installation of Alum
A79120 Carpentry & Joinery 105 15-May-23 27-Aug-23 Carpentry &
Actual Work Critical Remaining Work Summary Page 15 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Actual Work Critical Remaining Work Summary Page 16 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation