You are on page 1of 16

 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O
Construction of Union Luxury Apartments 1020 15-Dec-20 30-Sep-23 30-Sep-2
Design & Drawings 225 15-Dec-20 27-Jul-21 27-Jul-21, Design & Drawings
A78230 Design and Modeling 225 15-Dec-20 27-Jul-21 Design and Modeling
Contract Signing with Consultants 22 20-Oct-21 10-Nov-21 10-Nov-21, Contract Signing with Consultants
A78240 Designereast 22 20-Oct-21 10-Nov-21 Designereast
A78250 Ahad Associates 22 20-Oct-21 10-Nov-21 Ahad Associates
A78260 Studio 360 22 20-Oct-21 10-Nov-21 Studio 360
LDA approval 0 27-Jul-21 27-Jul-21 27-Jul-21, LDA approval
A78270 LDA approval 0 27-Jul-21 LDA approval
Demarcation Plan 0 22-Oct-21 22-Oct-21 22-Oct-21, Demarcation Plan
A78280 Demarcation Plan 0 22-Oct-21 Demarcation Plan
IFC Drawings Of Building C 221 07-Aug-21 15-Mar-22 15-Mar-22, IFC Drawings Of Building C
Architecture 27-Nov-21, Architecture
113 07-Aug-21 27-Nov-21
A78290 Scehmatic Plans, building sections & 5 07-Aug-21 11-Aug-21 Scehmatic Plans, building sections & elevations, 3d views
elevations, 3d views
A78300 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78310 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78320 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78330 Typical Floor (at Level +32' ~ 140' ) 7 21-Oct-21 27-Oct-21 Typical Floor (at Level +32' ~ 140' )
A78340 Roof Slab with Mumty (at Level +152' & 160') 9 28-Oct-21 05-Nov-21 Roof Slab with Mumty (at Level +152' & 160')

A78350 Details of finishing items & Drawings 22 06-Nov-21 27-Nov-21 Details of finishing items & Drawings
Structure 10-Dec-21, Structure
91 11-Sep-21 10-Dec-21
A78360 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78370 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78380 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78390 Typical Floor (at Level +32' ~ 140' ) 32 21-Oct-21 21-Nov-21 Typical Floor (at Level +32' ~ 140' )
A78400 Roof Slab with Mumty (at Level +152' & 160') 19 22-Nov-21 10-Dec-21 Roof Slab with Mumty (at Level +152' & 160')

MEP 10-Dec-21, MEP


91 11-Sep-21 10-Dec-21
A78410 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78420 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78430 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78440 Typical Floor (at Level +32' ~ 140' ) 32 21-Oct-21 21-Nov-21 Typical Floor (at Level +32' ~ 140' )

Actual Work Critical Remaining Work Summary Page 1 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A78450 Roof Slab with Mumty (at Level +152' & 160') 19 22-Nov-21 10-Dec-21 Roof Slab with Mumty (at Level +152' & 160')

Revit / BIM Model (Arch /Str/ MEP) 15-Mar-22, Revit / BIM Model (Arch /Str/ MEP)
186 11-Sep-21 15-Mar-22
A78460 Basement Raft (at Level -10'-6") 81 11-Sep-21 30-Nov-21 Basement Raft (at Level -10'-6")
A78470 Basement Slab (at Level 0'-6") 30 01-Dec-21 30-Dec-21 Basement Slab (at Level 0'-6")
A78480 1st Floor (at Level +17'-00'') 21 31-Dec-21 20-Jan-22 1st Floor (at Level +17'-00'')
A78490 Typical Floor (at Level +32' ~ 140' ) 21 21-Jan-22 10-Feb-22 Typical Floor (at Level +32' ~ 140' )
A78500 Roof Slab with Mumty (at Level +152' & 160') 33 11-Feb-22 15-Mar-22 Roof Slab with Mumty (at Level +152' & 160')

IFC Drawings Of Building A & B 221 07-Aug-21 15-Mar-22 15-Mar-22, IFC Drawings Of Building A & B
Architecture 10-Dec-21, Architecture
126 07-Aug-21 10-Dec-21
A78510 Scehmatic Plans, building sections & 5 07-Aug-21 11-Aug-21 Scehmatic Plans, building sections & elevations, 3d views
elevations, 3d views
A78520 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78530 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78540 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78550 Typical Floor (at Level +32' ~ 140' ) 7 21-Oct-21 27-Oct-21 Typical Floor (at Level +32' ~ 140' )
A78560 Roof Slab with Mumty (at Level +152' & 160') 9 28-Oct-21 05-Nov-21 Roof Slab with Mumty (at Level +152' & 160')

A78570 Details of finishing items & Drawings 35 06-Nov-21 10-Dec-21 Details of finishing items & Drawings
Structure 10-Dec-21, Structure
91 11-Sep-21 10-Dec-21
A78580 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78590 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78600 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78610 Typical Floor (at Level +32' ~ 140' ) 32 21-Oct-21 21-Nov-21 Typical Floor (at Level +32' ~ 140' )
A78620 Roof Slab with Mumty (at Level +152' & 160') 19 22-Nov-21 10-Dec-21 Roof Slab with Mumty (at Level +152' & 160')

MEP 10-Dec-21, MEP


91 11-Sep-21 10-Dec-21
A78630 Basement Raft (at Level -10'-6") 18 11-Sep-21 28-Sep-21 Basement Raft (at Level -10'-6")
A78640 Basement Slab (at Level 0'-6") 15 29-Sep-21 13-Oct-21 Basement Slab (at Level 0'-6")
A78650 1st Floor (at Level +17'-00'') 7 14-Oct-21 20-Oct-21 1st Floor (at Level +17'-00'')
A78660 Typical Floor (at Level +32' ~ 140' ) 32 21-Oct-21 21-Nov-21 Typical Floor (at Level +32' ~ 140' )
A78670 Roof Slab with Mumty (at Level +152' & 160') 19 22-Nov-21 10-Dec-21 Roof Slab with Mumty (at Level +152' & 160')

Revit / BIM Model (Arch /Str/ MEP) 15-Mar-22, Revit / BIM Model (Arch /Str/ MEP)
186 11-Sep-21 15-Mar-22
Actual Work Critical Remaining Work Summary Page 2 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A78680 Basement Raft (at Level -10'-6") 81 11-Sep-21 30-Nov-21 Basement Raft (at Level -10'-6")
A78690 Basement Slab (at Level 0'-6") 30 01-Dec-21 30-Dec-21 Basement Slab (at Level 0'-6")
A78700 1st Floor (at Level +17'-00'') 21 31-Dec-21 20-Jan-22 1st Floor (at Level +17'-00'')
A78710 Typical Floor (at Level +32' ~ 140' ) 21 21-Jan-22 10-Feb-22 Typical Floor (at Level +32' ~ 140' )
A78720 Roof Slab with Mumty (at Level +152' & 160') 33 11-Feb-22 15-Mar-22 Roof Slab with Mumty (at Level +152' & 160')

Site Setting-up/ Mobilization 108 23-Jun-21 08-Oct-21 08-Oct-21, Site Setting-up/ Mobilization
A22455 Site Office and facilities establishment 70 23-Jun-21 31-Aug-21 Site Office and facilities establishment
Tube Well Works 06-Sep-21, Tube Well Works
41 28-Jul-21 06-Sep-21
A1220 Temporary Water Supply Bore 7 28-Jul-21 03-Aug-21 Temporary Water Supply Bore
A1230 Tubewell No.1 9 11-Aug-21 19-Aug-21 Tubewell No.1
A1240 Tubewell No.2 9 20-Aug-21 28-Aug-21 Tubewell No.2
A1250 Tubewell No.3 9 29-Aug-21 06-Sep-21 Tubewell No.3
Site Barrication & Fencing 05-Sep-21, Site Barrication & Fencing
6 31-Aug-21 05-Sep-21
A1465 Site barrication & cordoning off 6 31-Aug-21 05-Sep-21 Site barrication & cordoning off
Batching Plant Establishment 08-Oct-21, Batching Plant Establishment
38 01-Sep-21 08-Oct-21
A1550 Installation, Testing & Commissioning of 38 01-Sep-21 08-Oct-21 Installation, Testing & Commissioning of Batching Plant
Batching Plant
Labour and Staff Camp Area 07-Sep-21, Labour and Staff Camp Area
7 01-Sep-21 07-Sep-21
A2035 Establishment of Labor & staff camp 7 01-Sep-21 07-Sep-21 Establishment of Labor & staff camp facilities
facilities
Steel Yard Facility 12-Sep-21, Steel Yard Facility
6 07-Sep-21 12-Sep-21
A1970 Layout of Steel Yard 6 07-Sep-21 12-Sep-21 Layout of Steel Yard
Fabrication of Formwork 15-Sep-21, Fabrication of Formwork
15 01-Sep-21 15-Sep-21
A2010 Fabrication of Columns Formwork 7 01-Sep-21 07-Sep-21 Fabrication of Columns Formwork
A2020 Fabrication of Retaining wall Formwork 8 08-Sep-21 15-Sep-21 Fabrication of Retaining wall Formwork
Site Execution 551 06-Sep-21 10-Mar-23 10-Mar-23, Site Execution
Block-C 30-Dec-22, Block-C
481 06-Sep-21 30-Dec-22
Grey Structure 30-Dec-22, Grey Structure
481 06-Sep-21 30-Dec-22
Sub Structure 26-Dec-21, Sub Structure
112 06-Sep-21 26-Dec-21
Earth Works 24-Oct-21, Earth Works
49 06-Sep-21 24-Oct-21
A2130 Cleaning and Grubbing 9 06-Sep-21 14-Sep-21 Cleaning and Grubbing
A2140 Excavation Work 23 16-Sep-21 08-Oct-21 Excavation Work
A55270 Surface leveling and Compaction 29 25-Sep-21 23-Oct-21 Surface leveling and Compaction
A55280 Anti Termite Treatment 30 25-Sep-21 24-Oct-21 Anti Termite Treatment
A55290 Lean Concrete 30 25-Sep-21 24-Oct-21 Lean Concrete
Raft Pouring at Level -(9'-7'') 09-Nov-21, Raft Pouring at Level -(9'-7'')
31 10-Oct-21 09-Nov-21
Actual Work Critical Remaining Work Summary Page 3 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O
Pour 1 15-Oct-21, Pour 1
6 10-Oct-21 15-Oct-21
A55300 Steel Fixing of Raft 4 10-Oct-21 13-Oct-21 Steel Fixing of Raft
A55310 Formwork of Raft 1 14-Oct-21 14-Oct-21 Formwork of Raft
A55320 Concrete Pouring of Raft 1 15-Oct-21 15-Oct-21 Concrete Pouring of Raft
Pour 2 19-Oct-21, Pour 2
6 14-Oct-21 19-Oct-21
A55360 Steel Fixing of Raft 4 14-Oct-21 17-Oct-21 Steel Fixing of Raft
A55370 Formwork of Raft 1 18-Oct-21 18-Oct-21 Formwork of Raft
A55380 Concrete Pouring of Raft 1 19-Oct-21 19-Oct-21 Concrete Pouring of Raft
Pour 3 21-Oct-21, Pour 3
6 16-Oct-21 21-Oct-21
A55420 Steel Fixing of Raft 3 16-Oct-21 18-Oct-21 Steel Fixing of Raft
A55430 Formwork of Raft 2 19-Oct-21 20-Oct-21 Formwork of Raft
A55440 Concrete Pouring of Raft 1 21-Oct-21 21-Oct-21 Concrete Pouring of Raft
Pour 4 27-Oct-21, Pour 4
8 20-Oct-21 27-Oct-21
A55480 Steel Fixing of Raft 4 20-Oct-21 23-Oct-21 Steel Fixing of Raft
A55490 Formwork of Raft 2 24-Oct-21 25-Oct-21 Formwork of Raft
A55500 Concrete Pouring of Raft 1 27-Oct-21 27-Oct-21 Concrete Pouring of Raft
Pour 5 29-Oct-21, Pour 5
6 24-Oct-21 29-Oct-21
A55540 Steel Fixing of Raft 3 24-Oct-21 26-Oct-21 Steel Fixing of Raft
A55550 Formwork of Raft 2 27-Oct-21 28-Oct-21 Formwork of Raft
A55560 Concrete Pouring of Raft 1 29-Oct-21 29-Oct-21 Concrete Pouring of Raft
Pour 6 02-Nov-21, Pour 6
7 27-Oct-21 02-Nov-21
A78770 Steel Fixing of Raft 4 27-Oct-21 30-Oct-21 Steel Fixing of Raft
A78780 Formwork of Raft 2 31-Oct-21 01-Nov-21 Formwork of Raft
A78790 Concrete Pouring of Raft 1 02-Nov-21 02-Nov-21 Concrete Pouring of Raft
Pour 7 06-Nov-21, Pour 7
7 31-Oct-21 06-Nov-21
A78830 Steel Fixing of Raft 4 31-Oct-21 03-Nov-21 Steel Fixing of Raft
A78840 Formwork of Raft 2 04-Nov-21 05-Nov-21 Formwork of Raft
A78850 Concrete Pouring of Raft 1 06-Nov-21 06-Nov-21 Concrete Pouring of Raft
Pour 8 09-Nov-21, Pour 8
7 03-Nov-21 09-Nov-21
A78890 Steel Fixing of Raft 4 03-Nov-21 06-Nov-21 Steel Fixing of Raft
A78900 Formwork of Raft 2 07-Nov-21 08-Nov-21 Formwork of Raft
A78910 Concrete Pouring of Raft 1 09-Nov-21 09-Nov-21 Concrete Pouring of Raft
Basement Floor at Level +2'-00 26-Dec-21, Basement Floor at Level +2'-00
47 10-Nov-21 26-Dec-21
Vertical Members 02-Dec-21, Vertical Members
23 10-Nov-21 02-Dec-21
A79220 Rebar Works 17 10-Nov-21 26-Nov-21 Rebar Works

Actual Work Critical Remaining Work Summary Page 4 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A79230 Formwork 18 13-Nov-21 30-Nov-21 Formwork


A79240 Concrete 17 16-Nov-21 02-Dec-21 Concrete
Horizontal Members 26-Dec-21, Horizontal Members
34 23-Nov-21 26-Dec-21
A79250 Formwork 26 23-Nov-21 18-Dec-21 Formwork
A79260 Rebar Works 21 05-Dec-21 25-Dec-21 Rebar Works
A79270 Concrete 15 12-Dec-21 26-Dec-21 Concrete
Super Structure 30-Dec-22, Super Structure
383 13-Dec-21 30-Dec-22
Ground Floor at Level +17'-00'' 26-Jan-22, Ground Floor at Level +17'-00''
45 13-Dec-21 26-Jan-22
Vertical Members 07-Jan-22, Vertical Members
26 13-Dec-21 07-Jan-22
A79280 Rebar Works 20 13-Dec-21 01-Jan-22 Rebar Works
A79290 Formwork 18 19-Dec-21 05-Jan-22 Formwork
A79300 Concrete 15 24-Dec-21 07-Jan-22 Concrete
Horizontal Members 26-Jan-22, Horizontal Members
31 27-Dec-21 26-Jan-22
A79310 Formwork 24 27-Dec-21 19-Jan-22 Formwork
A79320 Rebar Works 20 07-Jan-22 26-Jan-22 Rebar Works
A79330 Concrete 8 16-Jan-22 23-Jan-22 Concrete
First Floor at Level +32'-0'' 02-Mar-22, First Floor at Level +32'-0''
45 17-Jan-22 02-Mar-22
Vertical Members 07-Feb-22, Vertical Members
22 17-Jan-22 07-Feb-22
A79340 Rebar Works 14 17-Jan-22 30-Jan-22 Rebar Works
A79350 Formwork 13 24-Jan-22 05-Feb-22 Formwork
A79360 Concrete 9 30-Jan-22 07-Feb-22 Concrete
Horizontal Members 02-Mar-22, Horizontal Members
29 02-Feb-22 02-Mar-22
A79370 Formwork 20 02-Feb-22 21-Feb-22 Formwork
A79380 Rebar Works 14 16-Feb-22 01-Mar-22 Rebar Works
A79390 Concrete 9 22-Feb-22 02-Mar-22 Concrete
Second Floor at Level +44'-0'' 31-Mar-22, Second Floor at Level +44'-0''
35 25-Feb-22 31-Mar-22
Vertical Members 14-Mar-22, Vertical Members
18 25-Feb-22 14-Mar-22
A79400 Rebar Works 11 25-Feb-22 07-Mar-22 Rebar Works
A79410 Formwork 12 01-Mar-22 12-Mar-22 Formwork
A79420 Concrete 9 06-Mar-22 14-Mar-22 Concrete

Horizontal Members 31-Mar-22, Horizontal Members


24 08-Mar-22 31-Mar-22
A79430 Formwork 17 08-Mar-22 24-Mar-22 Formwork
A79440 Rebar Works 13 18-Mar-22 30-Mar-22 Rebar Works
A79450 Concrete 8 24-Mar-22 31-Mar-22 Concrete
Third Floor at Level +56'-0'' 28-Apr-22, Third Floor at Level +56'-0''
35 25-Mar-22 28-Apr-22
Vertical Members 11-Apr-22, Vertical Members
18 25-Mar-22 11-Apr-22
Actual Work Critical Remaining Work Summary Page 5 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A79460 Rebar Works 14 25-Mar-22 07-Apr-22 Rebar Works


A79470 Formwork 11 30-Mar-22 09-Apr-22 Formwork
A79480 Concrete 9 03-Apr-22 11-Apr-22 Concrete
Horizontal Members 28-Apr-22, Horizontal Members
24 05-Apr-22 28-Apr-22
A79490 Formwork 17 05-Apr-22 21-Apr-22 Formwork
A79500 Rebar Works 13 15-Apr-22 27-Apr-22 Rebar Works
A79510 Concrete 8 21-Apr-22 28-Apr-22 Concrete
Forth Floor at Level +68'-0'' 26-May-22, Forth Floor at Level +68'-0''
35 22-Apr-22 26-May-22
Vertical Members 09-May-22, Vertical Members
18 22-Apr-22 09-May-22
A79520 Rebar Works 11 22-Apr-22 02-May-22 Rebar Works
A79530 Formwork 12 26-Apr-22 07-May-22 Formwork
A79540 Concrete 9 01-May-22 09-May-22 Concrete
Horizontal Members 26-May-22, Horizontal Members
24 03-May-22 26-May-22
A79550 Formwork 17 03-May-22 19-May-22 Formwork
A79560 Rebar Works 13 13-May-22 25-May-22 Rebar Works
A79570 Concrete 8 19-May-22 26-May-22 Concrete

Fifth Floor at Level +80'-0'' 23-Jun-22, Fifth Floor at Level +80'-0''


35 20-May-22 23-Jun-22
Vertical Members 06-Jun-22, Vertical Members
18 20-May-22 06-Jun-22
A79580 Rebar Works 11 20-May-22 30-May-22 Rebar Works
A79590 Formwork 12 24-May-22 04-Jun-22 Formwork
A79600 Concrete 9 29-May-22 06-Jun-22 Concrete
Horizontal Members 23-Jun-22, Horizontal Members
24 31-May-22 23-Jun-22
A79610 Formwork 17 31-May-22 16-Jun-22 Formwork
A79620 Rebar Works 13 10-Jun-22 22-Jun-22 Rebar Works
A79630 Concrete 8 16-Jun-22 23-Jun-22 Concrete
Sixth Floor at Level +92'-0'' 21-Jul-22, Sixth Floor at Level +92'-0''
35 17-Jun-22 21-Jul-22
Vertical Members 04-Jul-22, Vertical Members
18 17-Jun-22 04-Jul-22
A79640 Rebar Works 12 17-Jun-22 28-Jun-22 Rebar Works
A79650 Formwork 11 22-Jun-22 02-Jul-22 Formwork
A79660 Concrete 9 26-Jun-22 04-Jul-22 Concrete
Horizontal Members 21-Jul-22, Horizontal Members
24 28-Jun-22 21-Jul-22
A79670 Formwork 17 28-Jun-22 14-Jul-22 Formwork
A79680 Rebar Works 13 08-Jul-22 20-Jul-22 Rebar Works
A79690 Concrete 8 14-Jul-22 21-Jul-22 Concrete
Seveth Floor at Level +104'-0'' 19-Aug-22, Seveth Floor at Level +104'-0''
35 16-Jul-22 19-Aug-22
Actual Work Critical Remaining Work Summary Page 6 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O
Vertical Members 01-Aug-22, Vertical Members
17 16-Jul-22 01-Aug-22
A79700 Rebar Works 11 16-Jul-22 26-Jul-22 Rebar Works
A79710 Formwork 11 20-Jul-22 30-Jul-22 Formwork
A79720 Concrete 9 24-Jul-22 01-Aug-22 Concrete
Horizontal Members 19-Aug-22, Horizontal Members
25 26-Jul-22 19-Aug-22
A79730 Formwork 17 26-Jul-22 11-Aug-22 Formwork
A79740 Rebar Works 14 05-Aug-22 18-Aug-22 Rebar Works
A79750 Concrete 8 12-Aug-22 19-Aug-22 Concrete
Eight Floor at Level +116'-0'' 17-Sep-22, Eight Floor at Level +116'-0''
35 14-Aug-22 17-Sep-22
Vertical Members 30-Aug-22, Vertical Members
17 14-Aug-22 30-Aug-22
A79760 Rebar Works 11 14-Aug-22 24-Aug-22 Rebar Works
A79770 Formwork 10 19-Aug-22 28-Aug-22 Formwork
A79780 Concrete 8 23-Aug-22 30-Aug-22 Concrete
Horizontal Members 17-Sep-22, Horizontal Members
24 25-Aug-22 17-Sep-22
A79790 Formwork 16 25-Aug-22 09-Sep-22 Formwork
A79800 Rebar Works 14 03-Sep-22 16-Sep-22 Rebar Works
A79810 Concrete 9 09-Sep-22 17-Sep-22 Concrete
Ninth Floor at Level +128'-0'' 15-Oct-22, Ninth Floor at Level +128'-0''
35 11-Sep-22 15-Oct-22
Vertical Members 28-Sep-22, Vertical Members
18 11-Sep-22 28-Sep-22
A79820 Rebar Works 12 11-Sep-22 22-Sep-22 Rebar Works
A79830 Formwork 11 16-Sep-22 26-Sep-22 Formwork
A79840 Concrete 9 20-Sep-22 28-Sep-22 Concrete
Horizontal Members 15-Oct-22, Horizontal Members
24 22-Sep-22 15-Oct-22
A79850 Formwork 17 22-Sep-22 08-Oct-22 Formwork
A79860 Rebar Works 15 30-Sep-22 14-Oct-22 Rebar Works
A79870 Concrete 9 07-Oct-22 15-Oct-22 Concrete
Tenth Floor at Level +140'-0'' 12-Nov-22, Tenth Floor at Level +140'
35 09-Oct-22 12-Nov-22
Vertical Members 26-Oct-22, Vertical Members
18 09-Oct-22 26-Oct-22
A79880 Rebar Works 12 09-Oct-22 20-Oct-22 Rebar Works
A79890 Formwork 11 14-Oct-22 24-Oct-22 Formwork
A79900 Concrete 9 18-Oct-22 26-Oct-22 Concrete
Horizontal Members 12-Nov-22, Horizontal Members
24 20-Oct-22 12-Nov-22
A79910 Formwork 17 20-Oct-22 05-Nov-22 Formwork
A79920 Rebar Works 15 28-Oct-22 11-Nov-22 Rebar Works
A79930 Concrete 9 04-Nov-22 12-Nov-22 Concrete
Eleventh Floor at Level +152'-0'' 10-Dec-22, Eleventh Floor at Leve
35 06-Nov-22 10-Dec-22
Actual Work Critical Remaining Work Summary Page 7 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O
Vertical Members 23-Nov-22, Vertical Members
18 06-Nov-22 23-Nov-22
A79940 Rebar Works 12 06-Nov-22 17-Nov-22 Rebar Works
A79950 Formwork 11 11-Nov-22 21-Nov-22 Formwork
A79960 Concrete 9 15-Nov-22 23-Nov-22 Concrete
Horizontal Members 10-Dec-22, Horizontal Members
24 17-Nov-22 10-Dec-22
A79970 Formwork 17 17-Nov-22 03-Dec-22 Formwork
A79980 Rebar Works 15 25-Nov-22 09-Dec-22 Rebar Works
A79990 Concrete 9 02-Dec-22 10-Dec-22 Concrete
Roof Slab at Level +160'-0'' 30-Dec-22, Roof Slab at Level +1
20 11-Dec-22 30-Dec-22
Vertical Members 24-Dec-22, Vertical Members
14 11-Dec-22 24-Dec-22
A80000 Rebar Works 9 11-Dec-22 19-Dec-22 Rebar Works
A80010 Formwork 10 14-Dec-22 23-Dec-22 Formwork
A80020 Concrete 8 17-Dec-22 24-Dec-22 Concrete
Horizontal Members 30-Dec-22, Horizontal Members
9 22-Dec-22 30-Dec-22
A80030 Formwork 5 22-Dec-22 26-Dec-22 Formwork
A80040 Rebar Works 4 26-Dec-22 29-Dec-22 Rebar Works
A80050 Concrete 3 28-Dec-22 30-Dec-22 Concrete
Block-A & B 10-Mar-23, Block-A & B
551 06-Sep-21 10-Mar-23
Grey Structure 10-Mar-23, Grey Structure
551 06-Sep-21 10-Mar-23
Sub Structure-1 04-Feb-22, Sub Structure-1
152 06-Sep-21 04-Feb-22
Earth Works 22-Dec-21, Earth Works
108 06-Sep-21 22-Dec-21
A46740 Cleaning and Grubbing 5 06-Sep-21 10-Sep-21 Cleaning and Grubbing
A46750 Excavation Work 64 08-Sep-21 10-Nov-21 Excavation Work
A46755 Levelling & Comapction 46 05-Nov-21 20-Dec-21 Levelling & Comapction
A52201 Anti Termite 44 08-Nov-21 21-Dec-21 Anti Termite
A78920 Lean Concrete 45 08-Nov-21 22-Dec-21 Lean Concrete
UGWT 03-Jan-22, UGWT
27 08-Dec-21 03-Jan-22
Raft Pouring 14-Dec-21, Raft Pouring
7 08-Dec-21 14-Dec-21
A52210 Steel Fixing of Bed 3 08-Dec-21 10-Dec-21 Steel Fixing of Bed
A52220 Formwork of Raft 3 11-Dec-21 13-Dec-21 Formwork of Raft
A52230 Concrete Pouring of Raft 1 14-Dec-21 14-Dec-21 Concrete Pouring of Raft
Retaining Walls 24-Dec-21, Retaining Walls
10 15-Dec-21 24-Dec-21
A52240 Steel fixing of walls 5 15-Dec-21 19-Dec-21 Steel fixing of walls
A52250 Formwork of walls 4 20-Dec-21 23-Dec-21 Formwork of walls
A52260 Cocrete Pouring of Walls 1 24-Dec-21 24-Dec-21 Cocrete Pouring of Walls
Slab 03-Jan-22, Slab
10 25-Dec-21 03-Jan-22

Actual Work Critical Remaining Work Summary Page 8 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A52270 Formwork of Slab 5 25-Dec-21 29-Dec-21 Formwork of Slab


A52280 Steel Fixing of Slab 4 30-Dec-21 02-Jan-22 Steel Fixing of Slab
A52290 Concrete Pouring of Slab 1 03-Jan-22 03-Jan-22 Concrete Pouring of Slab
Raft Pouring at Level -(9'-7'') 07-Jan-22, Raft Pouring at Level -(9'-7'')
57 12-Nov-21 07-Jan-22
Pour 1 15-Nov-21, Pour 1
4 12-Nov-21 15-Nov-21
A57190 Steel Fixing of Raft 2 12-Nov-21 13-Nov-21 Steel Fixing of Raft
A57200 Formwork of Raft 1 14-Nov-21 14-Nov-21 Formwork of Raft
A57210 Concrete Pouring of Raft 1 15-Nov-21 15-Nov-21 Concrete Pouring of Raft
Pour 2 20-Nov-21, Pour 2
7 14-Nov-21 20-Nov-21
A57250 Steel Fixing of Raft 4 14-Nov-21 17-Nov-21 Steel Fixing of Raft
A57260 Formwork of Raft 2 18-Nov-21 19-Nov-21 Formwork of Raft
A57270 Concrete Pouring of Raft 1 20-Nov-21 20-Nov-21 Concrete Pouring of Raft
Pour 3 23-Nov-21, Pour 3
6 18-Nov-21 23-Nov-21
A57310 Steel Fixing of Raft 3 18-Nov-21 20-Nov-21 Steel Fixing of Raft
A57320 Formwork of Raft 2 21-Nov-21 22-Nov-21 Formwork of Raft
A57330 Concrete Pouring of Raft 1 23-Nov-21 23-Nov-21 Concrete Pouring of Raft
Pour 4 26-Nov-21, Pour 4
6 21-Nov-21 26-Nov-21
A57370 Steel Fixing of Raft 4 21-Nov-21 24-Nov-21 Steel Fixing of Raft
A57380 Formwork of Raft 1 25-Nov-21 25-Nov-21 Formwork of Raft
A57390 Concrete Pouring of Raft 1 26-Nov-21 26-Nov-21 Concrete Pouring of Raft
Pour 5 29-Nov-21, Pour 5
5 25-Nov-21 29-Nov-21
A57430 Steel Fixing of Raft 3 25-Nov-21 27-Nov-21 Steel Fixing of Raft
A57440 Formwork of Raft 1 28-Nov-21 28-Nov-21 Formwork of Raft
A57450 Concrete Pouring of Raft 1 29-Nov-21 29-Nov-21 Concrete Pouring of Raft
Pour 6 02-Dec-21, Pour 6
5 28-Nov-21 02-Dec-21
A58150 Steel Fixing of Raft 3 28-Nov-21 30-Nov-21 Steel Fixing of Raft
A58160 Formwork of Raft 1 01-Dec-21 01-Dec-21 Formwork of Raft
A58170 Concrete Pouring of Raft 1 02-Dec-21 02-Dec-21 Concrete Pouring of Raft
Pour 7 05-Dec-21, Pour 7
5 01-Dec-21 05-Dec-21
A58210 Steel Fixing of Raft 3 01-Dec-21 03-Dec-21 Steel Fixing of Raft
A58220 Formwork of Raft 1 04-Dec-21 04-Dec-21 Formwork of Raft
A58230 Concrete Pouring of Raft 1 05-Dec-21 05-Dec-21 Concrete Pouring of Raft
Pour 8 08-Dec-21, Pour 8
5 04-Dec-21 08-Dec-21
A57490 Steel Fixing of Raft 3 04-Dec-21 06-Dec-21 Steel Fixing of Raft
A57500 Formwork of Raft 1 07-Dec-21 07-Dec-21 Formwork of Raft

Actual Work Critical Remaining Work Summary Page 9 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A57510 Concrete Pouring of Raft 1 08-Dec-21 08-Dec-21 Concrete Pouring of Raft


Pour 9 11-Dec-21, Pour 9
5 07-Dec-21 11-Dec-21
A57550 Steel Fixing of Raft 3 07-Dec-21 09-Dec-21 Steel Fixing of Raft
A57560 Formwork of Raft 1 10-Dec-21 10-Dec-21 Formwork of Raft
A57570 Concrete Pouring of Raft 1 11-Dec-21 11-Dec-21 Concrete Pouring of Raft
Pour 10 14-Dec-21, Pour 10
5 10-Dec-21 14-Dec-21
A57610 Steel Fixing of Raft 3 10-Dec-21 12-Dec-21 Steel Fixing of Raft
A57620 Formwork of Raft 1 13-Dec-21 13-Dec-21 Formwork of Raft
A57630 Concrete Pouring of Raft 1 14-Dec-21 14-Dec-21 Concrete Pouring of Raft
Pour 11 17-Dec-21, Pour 11
5 13-Dec-21 17-Dec-21
A57670 Steel Fixing of Raft 3 13-Dec-21 15-Dec-21 Steel Fixing of Raft
A57680 Formwork of Raft 1 16-Dec-21 16-Dec-21 Formwork of Raft
A57690 Concrete Pouring of Raft 1 17-Dec-21 17-Dec-21 Concrete Pouring of Raft
Pour 12 20-Dec-21, Pour 12
5 16-Dec-21 20-Dec-21
A57730 Steel Fixing of Raft 3 16-Dec-21 18-Dec-21 Steel Fixing of Raft
A57740 Formwork of Raft 1 19-Dec-21 19-Dec-21 Formwork of Raft
A57750 Concrete Pouring of Raft 1 20-Dec-21 20-Dec-21 Concrete Pouring of Raft
Pour 13 22-Dec-21, Pour 13
5 18-Dec-21 22-Dec-21
A58270 Steel Fixing of Raft 3 18-Dec-21 20-Dec-21 Steel Fixing of Raft
A58280 Formwork of Raft 1 21-Dec-21 21-Dec-21 Formwork of Raft
A58290 Concrete Pouring of Raft 1 22-Dec-21 22-Dec-21 Concrete Pouring of Raft
Pour 14 24-Dec-21, Pour 14
4 21-Dec-21 24-Dec-21
A57790 Steel Fixing of Raft 2 21-Dec-21 22-Dec-21 Steel Fixing of Raft
A57800 Formwork of Raft 1 23-Dec-21 23-Dec-21 Formwork of Raft
A57810 Concrete Pouring of Raft 1 24-Dec-21 24-Dec-21 Concrete Pouring of Raft
Pour 15 26-Dec-21, Pour 15
4 23-Dec-21 26-Dec-21
A57850 Steel Fixing of Raft 2 23-Dec-21 24-Dec-21 Steel Fixing of Raft
A57860 Formwork of Raft 1 25-Dec-21 25-Dec-21 Formwork of Raft
A57870 Concrete Pouring of Raft 1 26-Dec-21 26-Dec-21 Concrete Pouring of Raft
Pour 16 30-Dec-21, Pour 16
6 25-Dec-21 30-Dec-21
A57910 Steel Fixing of Raft 3 25-Dec-21 27-Dec-21 Steel Fixing of Raft
A57920 Formwork of Raft 2 28-Dec-21 29-Dec-21 Formwork of Raft
A57930 Concrete Pouring of Raft 1 30-Dec-21 30-Dec-21 Concrete Pouring of Raft
Pour 17 02-Jan-22, Pour 17
6 28-Dec-21 02-Jan-22
A57970 Steel Fixing of Raft 3 28-Dec-21 30-Dec-21 Steel Fixing of Raft

Actual Work Critical Remaining Work Summary Page 10 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A57980 Formwork of Raft 2 31-Dec-21 01-Jan-22 Formwork of Raft


A57990 Concrete Pouring of Raft 1 02-Jan-22 02-Jan-22 Concrete Pouring of Raft
Pour 18 04-Jan-22, Pour 18
5 31-Dec-21 04-Jan-22
A58030 Steel Fixing of Raft 3 31-Dec-21 02-Jan-22 Steel Fixing of Raft
A58040 Formwork of Raft 1 03-Jan-22 03-Jan-22 Formwork of Raft
A58050 Concrete Pouring of Raft 1 04-Jan-22 04-Jan-22 Concrete Pouring of Raft
Pour 19 07-Jan-22, Pour 19
5 03-Jan-22 07-Jan-22
A58090 Steel Fixing of Raft 3 03-Jan-22 05-Jan-22 Steel Fixing of Raft
A58100 Formwork of Raft 1 06-Jan-22 06-Jan-22 Formwork of Raft
A58110 Concrete Pouring of Raft 1 07-Jan-22 07-Jan-22 Concrete Pouring of Raft
Basement Floor at Level +2'-00 04-Feb-22, Basement Floor at Level +2'-00
64 03-Dec-21 04-Feb-22
Vertical Members 19-Jan-22, Vertical Members
48 03-Dec-21 19-Jan-22
A80060 Rebar Works 45 03-Dec-21 16-Jan-22 Rebar Works
A80070 Formwork 43 07-Dec-21 18-Jan-22 Formwork
A80080 Concrete 41 10-Dec-21 19-Jan-22 Concrete
Horizontal Members 04-Feb-22, Horizontal Members
50 17-Dec-21 04-Feb-22
A80090 Formwork 43 17-Dec-21 28-Jan-22 Formwork
A80100 Rebar Works 42 24-Dec-21 03-Feb-22 Rebar Works
A80110 Concrete 39 28-Dec-21 04-Feb-22 Concrete
Super Structure 10-Mar-23, Super Structure
417 18-Jan-22 10-Mar-23
Ground Floor at Level +17'-00'' 11-Mar-22, Ground Floor at Level +17'-00''
53 18-Jan-22 11-Mar-22
Vertical Members 17-Feb-22, Vertical Members
31 18-Jan-22 17-Feb-22
A80120 Rebar Works 23 18-Jan-22 09-Feb-22 Rebar Works
A80130 Formwork 22 25-Jan-22 15-Feb-22 Formwork
A80140 Concrete 19 30-Jan-22 17-Feb-22 Concrete
Horizontal Members 11-Mar-22, Horizontal Members
38 02-Feb-22 11-Mar-22
A80150 Formwork 29 02-Feb-22 02-Mar-22 Formwork
A80160 Rebar Works 26 13-Feb-22 10-Mar-22 Rebar Works
A80170 Concrete 20 20-Feb-22 11-Mar-22 Concrete
First Floor at Level +32'-00'''' 10-Apr-22, First Floor at Level +32'-00''''
48 22-Feb-22 10-Apr-22
Vertical Members 24-Mar-22, Vertical Members
31 22-Feb-22 24-Mar-22
A80180 Rebar Works 23 22-Feb-22 16-Mar-22 Rebar Works
A80190 Formwork 25 26-Feb-22 22-Mar-22 Formwork
A80200 Concrete 22 03-Mar-22 24-Mar-22 Concrete
Horizontal Members 10-Apr-22, Horizontal Members
37 05-Mar-22 10-Apr-22
A80210 Formwork 30 05-Mar-22 03-Apr-22 Formwork

Actual Work Critical Remaining Work Summary Page 11 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A80220 Rebar Works 26 15-Mar-22 09-Apr-22 Rebar Works


A80230 Concrete 21 21-Mar-22 10-Apr-22 Concrete
Second Floor at Level +44'-00'' 25-May-22, Second Floor at Level +44'-00''
65 22-Mar-22 25-May-22
Vertical Members 08-May-22, Vertical Members
48 22-Mar-22 08-May-22
A80240 Rebar Works 41 22-Mar-22 01-May-22 Rebar Works
A80250 Formwork 40 28-Mar-22 06-May-22 Formwork
A80260 Concrete 38 01-Apr-22 08-May-22 Concrete
Horizontal Members 25-May-22, Horizontal Members
53 03-Apr-22 25-May-22
A80270 Formwork 46 03-Apr-22 18-May-22 Formwork
A80280 Rebar Works 42 13-Apr-22 24-May-22 Rebar Works
A80290 Concrete 37 19-Apr-22 25-May-22 Concrete
Third Floor at Level +56'-00'' 23-Jun-22, Third Floor at Level +56'-00''
65 20-Apr-22 23-Jun-22
Vertical Members 07-Jun-22, Vertical Members
49 20-Apr-22 07-Jun-22
A80300 Rebar Works 42 20-Apr-22 31-May-22 Rebar Works
A80310 Formwork 41 26-Apr-22 05-Jun-22 Formwork
A80320 Concrete 40 29-Apr-22 07-Jun-22 Concrete
Horizontal Members 23-Jun-22, Horizontal Members
54 01-May-22 23-Jun-22
A80330 Formwork 47 01-May-22 16-Jun-22 Formwork
A80340 Rebar Works 42 12-May-22 22-Jun-22 Rebar Works
A80350 Concrete 38 17-May-22 23-Jun-22 Concrete
Forth Floor at Level +68'-00'' 23-Jul-22, Forth Floor at Level +68'-00''
67 18-May-22 23-Jul-22
Vertical Members 06-Jul-22, Vertical Members
50 18-May-22 06-Jul-22
A80360 Rebar Works 43 18-May-22 29-Jun-22 Rebar Works
A80370 Formwork 43 23-May-22 04-Jul-22 Formwork
A80380 Concrete 40 28-May-22 06-Jul-22 Concrete
Horizontal Members 23-Jul-22, Horizontal Members
56 29-May-22 23-Jul-22
A80390 Formwork 49 29-May-22 16-Jul-22 Formwork
A80400 Rebar Works 46 07-Jun-22 22-Jul-22 Rebar Works
A80410 Concrete 41 13-Jun-22 23-Jul-22 Concrete
Fifth Floor at Level +80'-00'' 22-Aug-22, Fifth Floor at Level +80'-00''
70 14-Jun-22 22-Aug-22
Vertical Members 05-Aug-22, Vertical Members
53 14-Jun-22 05-Aug-22
A80420 Rebar Works 46 14-Jun-22 29-Jul-22 Rebar Works
A80430 Formwork 47 18-Jun-22 03-Aug-22 Formwork
A80440 Concrete 45 22-Jun-22 05-Aug-22 Concrete
Horizontal Members 22-Aug-22, Horizontal Members
60 24-Jun-22 22-Aug-22
A80450 Formwork 53 24-Jun-22 15-Aug-22 Formwork

Actual Work Critical Remaining Work Summary Page 12 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A80460 Rebar Works 49 04-Jul-22 21-Aug-22 Rebar Works


A80470 Concrete 44 10-Jul-22 22-Aug-22 Concrete
Sixth Floor at Level +92'-00'' 22-Sep-22, Sixth Floor at Level +92'-00''
74 11-Jul-22 22-Sep-22
Vertical Members 04-Sep-22, Vertical Members
56 11-Jul-22 04-Sep-22
A80480 Rebar Works 49 11-Jul-22 28-Aug-22 Rebar Works
A80490 Formwork 49 16-Jul-22 02-Sep-22 Formwork
A80500 Concrete 46 21-Jul-22 04-Sep-22 Concrete
Horizontal Members 22-Sep-22, Horizontal Members
62 23-Jul-22 22-Sep-22
A80510 Formwork 53 23-Jul-22 13-Sep-22 Formwork
A80520 Rebar Works 52 01-Aug-22 21-Sep-22 Rebar Works
A80530 Concrete 47 07-Aug-22 22-Sep-22 Concrete
Seveth Floor at Level +104'-00'' 23-Oct-22, Seveth Floor at Level +104'-
75 10-Aug-22 23-Oct-22
Vertical Members 04-Oct-22, Vertical Members
56 10-Aug-22 04-Oct-22
A80540 Rebar Works 50 10-Aug-22 28-Sep-22 Rebar Works
A80550 Formwork 48 16-Aug-22 02-Oct-22 Formwork
A80560 Concrete 46 20-Aug-22 04-Oct-22 Concrete
Horizontal Members 23-Oct-22, Horizontal Members
63 22-Aug-22 23-Oct-22
A80570 Formwork 53 22-Aug-22 13-Oct-22 Formwork
A80580 Rebar Works 52 31-Aug-22 21-Oct-22 Rebar Works
A80590 Concrete 46 08-Sep-22 23-Oct-22 Concrete
Eight Floor at Level +116'-00'' 20-Nov-22, Eight Floor at Level +116
72 10-Sep-22 20-Nov-22
Vertical Members 04-Nov-22, Vertical Members
56 10-Sep-22 04-Nov-22
A80600 Rebar Works 50 10-Sep-22 29-Oct-22 Rebar Works
A80610 Formwork 48 16-Sep-22 02-Nov-22 Formwork
A80620 Concrete 46 20-Sep-22 04-Nov-22 Concrete
Horizontal Members 20-Nov-22, Horizontal Members
60 22-Sep-22 20-Nov-22
A80630 Formwork 53 22-Sep-22 13-Nov-22 Formwork
A80640 Rebar Works 50 01-Oct-22 19-Nov-22 Rebar Works
A80650 Concrete 45 07-Oct-22 20-Nov-22 Concrete
Ninth Floor at Level +128'-00'' 17-Dec-22, Ninth Floor at Level +1
69 10-Oct-22 17-Dec-22
Vertical Members 30-Nov-22, Vertical Members
52 10-Oct-22 30-Nov-22
A80660 Rebar Works 46 10-Oct-22 24-Nov-22 Rebar Works
A80670 Formwork 44 16-Oct-22 28-Nov-22 Formwork
A80680 Concrete 42 20-Oct-22 30-Nov-22 Concrete
Horizontal Members 17-Dec-22, Horizontal Members
60 19-Oct-22 17-Dec-22
A80690 Formwork 53 19-Oct-22 10-Dec-22 Formwork

Actual Work Critical Remaining Work Summary Page 13 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A80700 Rebar Works 50 28-Oct-22 16-Dec-22 Rebar Works


A80710 Concrete 45 03-Nov-22 17-Dec-22 Concrete
Tenth Floor at Level +140'-00'' 15-Jan-23, Tenth Floor at Level
71 06-Nov-22 15-Jan-23
Vertical Members 27-Dec-22, Vertical Members
52 06-Nov-22 27-Dec-22
A80720 Rebar Works 46 06-Nov-22 21-Dec-22 Rebar Works
A80730 Formwork 44 12-Nov-22 25-Dec-22 Formwork
A80740 Concrete 42 16-Nov-22 27-Dec-22 Concrete
Horizontal Members 15-Jan-23, Horizontal Members
60 17-Nov-22 15-Jan-23
A80750 Formwork 53 17-Nov-22 08-Jan-23 Formwork
A80760 Rebar Works 48 28-Nov-22 14-Jan-23 Rebar Works
A80770 Concrete 41 06-Dec-22 15-Jan-23 Concrete
Eleventh Floor at Level +152'-00'' 12-Feb-23, Eleventh Floor at
66 09-Dec-22 12-Feb-23
Vertical Members 25-Jan-23, Vertical Members
48 09-Dec-22 25-Jan-23
A80780 Rebar Works 44 09-Dec-22 21-Jan-23 Rebar Works
A80790 Formwork 42 13-Dec-22 23-Jan-23 Formwork
A80800 Concrete 40 17-Dec-22 25-Jan-23 Concrete
Horizontal Members 12-Feb-23, Horizontal Membe
57 18-Dec-22 12-Feb-23
A80810 Formwork 50 18-Dec-22 05-Feb-23 Formwork
A80820 Rebar Works 45 28-Dec-22 10-Feb-23 Rebar Works
A80830 Concrete 41 03-Jan-23 12-Feb-23 Concrete
Roof Slab at Level +160'-0'' 10-Mar-23, Roof Slab at Le
26 13-Feb-23 10-Mar-23
Vertical Members 21-Feb-23, Vertical Members
9 13-Feb-23 21-Feb-23
A80840 Rebar Works 4 13-Feb-23 16-Feb-23 Rebar Works
A80850 Formwork 4 17-Feb-23 20-Feb-23 Formwork
A80860 Concrete 1 21-Feb-23 21-Feb-23 Concrete
Horizontal Members 10-Mar-23, Horizontal Mem
17 22-Feb-23 10-Mar-23
A80870 Formwork 9 22-Feb-23 02-Mar-23 Formwork
A80880 Rebar Works 7 03-Mar-23 09-Mar-23 Rebar Works
A80890 Concrete 1 10-Mar-23 10-Mar-23 Concrete
Block Masonry/EPS Works 265 24-Jun-22 15-Mar-23 15-Mar-23, Block Masonry/
A22410 Block Masonry/EPS 265 24-Jun-22 15-Mar-23 Block Masonry/EPS
MEP Works 454 24-Jun-22 20-Sep-23 20-Sep-23
Electrical Works 10-Sep-23,
430 08-Jul-22 10-Sep-23
A78930 Layout & Installation of Conduits, Cables & 270 08-Jul-22 03-Apr-23 Layout & Installation of C
Backboxes (General+ELV)
A78940 Layout & Installation of Cable Trays 240 28-Jul-22 24-Mar-23 Layout & Installation of C

Actual Work Critical Remaining Work Summary Page 14 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A78945 Delivery & Installation of Power Cable 120 10-Dec-22 08-Apr-23 Delivery & Installation of
A78950 Delivery & Installation of HT/LT Panels 180 22-Aug-22 17-Feb-23 Delivery & Installation of HT/
A78960 Delivery & Installation of Genset 210 21-Sep-22 18-Apr-23 Delivery & Installation o
A78970 Delivery & Installation of Lift 210 06-Oct-22 03-May-23 Delivery & Installation
A78980 ELV System (PA+CCTV+FA+DT) 90 03-Jun-23 31-Aug-23 ELV System
A78985 Delivery & Installation of Energy Meters 120 18-Feb-23 17-Jun-23 Delivery & Installa
A78990 Installation of Terminal Fixtures 90 03-Jun-23 31-Aug-23 Installation
A79190 Testing & Commissioning 10 01-Sep-23 10-Sep-23 Testing & C
Plumbing Works 20-Sep-23
440 08-Jul-22 20-Sep-23
A79000 Installation of Piping Network (WS+SS) 265 08-Jul-22 29-Mar-23 Installation of Piping Netw
A79005 Delivery & Installation of Filteration Plant 45 28-Jun-23 11-Aug-23 Delivery & Ins
A79010 Delivery & Installation of Pumps 150 30-Mar-23 26-Aug-23 Delivery & In
A79020 Installation of Terminal Fixtures (Faucets, 165 30-Mar-23 10-Sep-23 Installation
WBs, WCs)
A79210 Testing & Commissioning 10 11-Sep-23 20-Sep-23 Testing &
Fire Fighting Works 23-Jun-23, Fire Fig
365 24-Jun-22 23-Jun-23
A79030 Installation of Piping Network 265 24-Jun-22 15-Mar-23 Installation of Piping Netw
A79035 Delivery & Installation of FF Sprinklers 150 16-Nov-22 14-Apr-23 Delivery & Installation o
A79040 Delivery & Installation of Pumps 180 16-Nov-22 14-May-23 Delivery & Installation
A79050 Delivery & Installation of FH Cabinets 75 31-Mar-23 13-Jun-23 Delivery & Installat
A79060 Delivery & Installation of Fire Hydrants 75 31-Mar-23 13-Jun-23 Delivery & Installat
A79070 Delivery & Installation of Extingishing 75 31-Mar-23 13-Jun-23 Delivery & Installat
Supplies
A79080 Testing & Commissioning 10 14-Jun-23 23-Jun-23 Testing & Commis
Air Conditioning Works 15-Mar-23, Air Conditioning
265 24-Jun-22 15-Mar-23
A79090 Installation of Ducts & Copper pipes 265 24-Jun-22 15-Mar-23 Installation of Ducts & Cop
Finishing Works 400 18-Aug-22 21-Sep-23 21-Sep-23
A79100 Internal Plaster 240 18-Aug-22 14-Apr-23 Internal Plaster
A79101 Flooring Works 270 18-Aug-22 14-May-23 Flooring Works
A79105 False Ceiling Works 270 06-Sep-22 02-Jun-23 False Ceiling Works
A79115 Floor & Wall Tiling 265 22-Sep-22 13-Jun-23 Floor & Wall Tiling
A79116 Paint Works 310 16-Nov-22 21-Sep-23 Paint Wor
A79117 Installation of Aluminium Windows 120 14-Feb-23 13-Jun-23 Installation of Alum
A79120 Carpentry & Joinery 105 15-May-23 27-Aug-23 Carpentry &

Actual Work Critical Remaining Work Summary Page 15 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
 

Union Luxury Apartments


Project Schedule
Activity ID Activity Name Original Start Finish 2021 2022 2023
Duration
J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O

A79130 Glass Partitioning Works 60 14-Jun-23 12-Aug-23 Glass Partition


A79150 Marble & Granite Works 120 15-Apr-23 12-Aug-23 Marble & Gra
A79160 Water Proofing Works on Roof 60 11-Mar-23 09-May-23 Water Proofing Works
A79170 Railing Works 60 29-Jun-23 27-Aug-23 Railing Work
A79195 Facade Works 150 16-Mar-23 12-Aug-23 Facade Work
A79198 Exterior Services 150 16-Mar-23 12-Aug-23 Exterior Servi
Snagging & De-Snagging 9 22-Sep-23 30-Sep-23 30-Sep-2
A79199 Punch List Items 9 22-Sep-23 30-Sep-23 Punch Li
A79200 Project Finish 0 30-Sep-23 Project F

Actual Work Critical Remaining Work Summary Page 16 of 16 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation

You might also like