Summary Schedule - Remedial Measures against Flooding in

Al Jouf Province

Activity ID Activity Name Original Start Finish D J F M A M J J A S O N D J F M A M J J A S O N


Duration 22012 01123 12201 20112 01230 22011 00122 11201 23012 01120 12301 20122 11200 22011 01123 12201 20012 012
355 30-Mar-21 22-Jun-22 22-Jun-22, Remedial Measures against Flooding in Al J
Remedial Measures against Flooding in Al Jouf Province (15 M)-Contractual -Time Schedule - Rev-0.5
Milestones 355 30-Mar-21 22-Jun-22 Contract
Project Start
Agreement 22-Jun-22,
Project Finish
Milestones

Mobilization 56 31-Mar-21 19-Jun-21 19-Jun-21, Mobilization

Project Pre-Construction Deliverables 56 31-Mar-21 19-Jun-21 19-Jun-21, Project Pre-Construction Deliverables

Project Management Plan Submittal 35 31-Mar-21 25-May-21 25-May-21, Project Management Plan Submittal
Project Management Plan Approval 35 02-May-21 19-Jun-21 19-Jun-21, Project Management Plan Approval

Surveying Work 28 20-May-21 21-Jun-21 21-Jun-21, Surveying Work

Design, Engineering & Submittals 316 22-May-21 14-Jun-22 14-Jun-22, Design, Engineering & Submittals

Design Drawings 42 22-May-21 08-Jul-21 08-Jul-21, Design Drawings


Shop Drawings 73 12-Jun-21 08-Sep-21 08-Sep-21, Shop Drawings
Method of Statment 119 14-Jun-21 04-Nov-21 04-Nov-21, Method of Statment
As Built Drawings 208 30-Sep-21 14-Jun-22 14-Jun-22,As Built Drawings

Procurement 207 12-Jun-21 13-Feb-22 13-Feb-22, Procurement

Slope Protection 181 12-Jun-21 13-Jan-22 13-Jan-22, Slope Protection


Remedial of # BC 187 05-Jul-21 13-Feb-22 13-Feb-22, Remedial of # BC

Construction 276 23-Jun-21 31-May-22 31-May-22, Construction

ZONE 08 86 23-Jun-21 06-Oct-21 06-Oct-21, ZONE 08


ZONE 07 70 11-Sep-21 01-Dec-21 01-Dec-21, ZONE 07
ZONE 06 65 28-Oct-21 11-Jan-22 11-Jan-22, ZONE 06
ZONE 05 130 29-Nov-21 14-May-22 14-May-22, ZONE 05
ZONE 04 39 23-Jan-22 08-Mar-22 08-Mar-22, ZONE 04
ZONE 03 36 06-Mar-22 26-Apr-22 26-Apr-22, ZONE 03
ZONE 02 34 11-Apr-22 31-May-22 31-May-22, ZONE 02
ZONE 01 31 11-Apr-22 28-May-22 28-May-22, ZONE 01

Project Handover 21 30-May-22 22-Jun-22 22-Jun-22, Project Handover

Actual Work Critical Remaining Work Page 1 of 1 TASK filter: All Activities