PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4...

Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
272 10-May-22 31-Mar-23 31-Mar-23, GDH- BUILDING 3- 3MW- DH1 +ID
GDH- BUILDING 3-
3 3MW- DH1 +IDFs 1- 4
GENERAL 272 10-May-22 31-Mar-23 31-Mar-23, GENERAL

GEN1030 CONTRACT SIGNED BETWEEN GDH & SDK 5 10-May-22 16-May-22 CONTRACT SIGNED BETWEEN GDH & SDK
GEN1010 PROJECT START 0 10-May-22 PROJECT START
GEN1020 PROJECT DURATION 325 10-May-22 30-Mar-23 PROJECT DURATION
GEN1050 MOBILIZATION & SITE PREPARATION 30 11-May-22 14-Jun-22 MOBILIZATION & SITE PREPARATION
GEN1040 APPOINTENT OF SUBCONTRACTORS 30 17-May-22 27-Jun-22 APPOINTENT OF SUBCONTRACTORS
GEN1060 PROJECT FINISH 0 31-Mar-23 PROJECT FINISH
PROJECT KEY MILESTONES
MILE 1 17-May-22 17-May-22 17-May-22, PROJECT KEY MILESTONES

BLG31000 RECEIVING DESIGN NOC BY CONSULTANT 1 17-May-22 17-May-22 RECEIVING DESIGN NOC BY CONSULTANT
AUTHORITIES-NOC 61 17-May-22 15-Aug-22 15-Aug-22, AUTHORITIES-NOC

AUT1040 DEWA SUBMISSION & APPROVAL FOR LV 40 17-May-22 15-Jul-22 DEWA SUBMISSION & APPROVAL FOR LV
AUT1030 DEWA SUBMISSION AND APPROVAL FOR HV 21 18-May-22 15-Jun-22 DEWA SUBMISSION AND APPROVAL FOR HV
AUT1020 DCD APPROVAL 26 18-May-22 22-Jun-22 DCD APPROVAL
AUT1010 DM/DSO APPROVAL 21 31-May-22 28-Jun-22 DM/DSO APPROVAL
DEWMV110 SHOP DRAWINGS & LOAD SCHEDULE SUBMISSION & APPROVAL 21 16-Jun-22 19-Jul-22 SHOP DRAWINGS & LOAD SCHEDULE SUBMISSION & APPROVAL
DEWMV120 NOC SUBMISSION & APPROVAL 12 20-Jul-22 04-Aug-22 NOC SUBMISSION & APPROVAL
DEWMV130 NOMINATION OF MV CABLES INSTALLER ( BY OTHERS) 7 05-Aug-22 15-Aug-22 NOMINATION OF MV CABLES INSTALLER ( BY OTHERS)
ENGINEEING 102 18-May-22 16-Sep-22 16-Sep-22, ENGINEEING

SHOP DRAWINGS
DRAWINGS/ RAMS/MATERIAL SUBMISSION & APPROVAL 102 18-May-22 16-Sep-22 16-Sep-22, SHOP DRAWINGS/ RAMS/MATERIAL SUBMISSION & APPROVAL

ENGMSS100 METHOD STATEMENTS SUBMISSIONS 60 18-May-22 29-Jul-22 METHOD STATEMENTS SUBMISSIONS


ENGMTS100 MATERIALS SUBMISSIONS 60 18-May-22 29-Jul-22 MATERIALS SUBMISSIONS
ENGMSA110 METHOD STATEMENTS APPROVALS 60 25-May-22 05-Aug-22 METHOD STATEMENTS APPROVALS
ENGMTS110 MATERIALS APPROVALS 60 25-May-22 05-Aug-22 MATERIALS APPROVALS
ENGSDS100 SHOP DRAWINGS SUBMISSIONS 60 29-Jun-22 09-Sep-22 SHOP DRAWINGS SUBMISSIONS
ENGSDA100 SHOP DRAWINGS APPROVALS 60 06-Jul-22 16-Sep-22 SHOP DRAWINGS APPROVALS
LONGLEAD MATE
MATERIAL SUBMISISON & APPROVAL 60 18-May-22 29-Jul-22 29-Jul-22, LONGLEAD MATERIAL SUBMISISON & APPROVAL

ELECTRICAL 46 03-Jun-22 29-Jul-22 29-Jul-22, ELECTRICAL


ENGMTSELE120 MV SWITCHBOARDS - MATERIAL SUBMISSION & APPROVAL 12 03-Jun-22 16-Jun-22 MV SWITCHBOARDS - MATERIAL SUBMISSION & APPROVAL
ENGMTSELE140 LV SWITCHBOARDS - MATERIAL SUBMISSION & APPROVAL 12 15-Jun-22 29-Jun-22 LV SWITCHBOARDS - MATERIAL SUBMISSION & APPROVAL
ENGMTSELE130 TRANSFORMERS - MATERIAL SUBMISSION & APPROVAL 12 16-Jun-22 29-Jun-22 TRANSFORMERS - MATERIAL SUBMISSION & APPROVAL
ENGMTSELE150 BUSBAR - MATERIAL SUBMISSION & APPROVAL 12 15-Jul-22 29-Jul-22 BUSBAR - MATERIAL SUBMISSION & APPROVAL
MECHANICAL 26 18-May-22 16-Jun-22 16-Jun-22, MECHANICAL
ENGMTSMEC100 CHILLERS - MATERIAL SUBMISSION & APPROVAL 12 18-May-22 31-May-22 CHILLERS - MATERIAL SUBMISSION & APPROVAL
ENGMTSMEC110 CCU - MATERIAL SUBMISSION & APPROVAL 12 18-May-22 31-May-22 CCU - MATERIAL SUBMISSION & APPROVAL
ENGMTSMEC120 FAN WALL UNITS ( FWU) - MATERIAL SUBMISSION & APPROVAL 12 18-May-22 31-May-22 FAN WALL UNITS ( FWU) - MATERIAL SUBMISSION & APPROVAL

ENGMTSMEC130 ELEVATORS - MATERIAL SUBMISSION & APPROVAL 12 03-Jun-22 16-Jun-22 ELEVATORS - MATERIAL SUBMISSION & APPROVAL
PROCUREMENT & DELIVERY 217 10-May-22 25-Jan-23 25-Jan-23, PROCUREMENT & DELIVERY

GENERAL 120 17-Jun-22 14-Oct-22 14-Oct-22, GENERAL

ENGPRD210 ELEVATORS - Procurement & Delivery 120 17-Jun-22 14-Oct-22 ELEVATORS - Procurement & Delivery
ELECTRICAL 210 10-May-22 17-Jan-23 17-Jan-23, ELECTRICAL

PRDELE210 GENERATORS - Procurement & Delivery - (12 MW) 120 10-May-22 06-Sep-22 GENERATORS - Procurement & Delivery - (12 MW)
PRDELE140 UPS - Procurement & Delivery - (12 MW) 120 25-May-22 21-Sep-22 UPS - Procurement & Delivery - (12 MW)
PRDELE160 BATTERIES- Procurement & Delivery - (12 MW) 165 25-May-22 05-Nov-22 BATTERIES- Procurement & Delivery - (12 MW)
PRDELE180 CABLE TRAYS- Procurement & Delivery 30 10-Jun-22 09-Jul-22 CABLE TRAYS- Procurement & Delivery
PRDELE130 TRANSFORMERS (TRX) - Procurement & Delivery - (12 MW) 110 16-Jun-22 03-Oct-22 TRANSFORMERS (TRX) - Procurement & Delivery - (12 MW)
PRDELE110 MV SWITCHGEARS - Procurement & Delivery - (12 MW) 150 17-Jun-22 13-Nov-22 MV SWITCHGEARS - Procurement & Delivery - (12 MW)
PRDELE240 BMS SYSTEM - Procurement & Delivery 126 24-Jun-22 27-Oct-22 BMS SYSTEM - Procurement & Delivery
PRDELE250 CPM SYSTEM- Procurement & Delivery 120 24-Jun-22 21-Oct-22 CPM SYSTEM- Procurement & Delivery

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 1 of 9
Remaining Work
Critical Remaining Work
Milestone
Summary
PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4... Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
PRDELE120 LV PANELS - Procurement & Delivery - (12 MW) 112 29-Jun-22 19-Oct-22 LV PANELS - Procurement & Delivery - (12 MW)
PRDELE260 ACTIVE NETWORK - Procurement & Delivery 157 14-Jul-22 17-Jan-23 ACTIVE NETWORK - Procurement & Delivery
PRDELE170 POWER CABLES- Procurement & Delivery 60 15-Jul-22 13-Sep-22 POWER CABLES- Procurement & Delivery
PRDELE190 POWER BUSBAR - Procurement & Delivery 90 29-Jul-22 27-Oct-22 POWER BUSBAR - Procurement & Delivery
PRDELE200 BUSBAR OVERHEAD TAPOFF - Procurement & Delivery 120 29-Jul-22 26-Nov-22 BUSBAR OVERHEAD TAPOFF - Procurement & Delivery
PRDELE150 CCTV & ACCESS CONTROL- Procurement & Delivery 120 06-Aug-22 03-Dec-22 CCTV & ACCESS CONTROL- Procurement & Delivery
PRDELE230 TAMPER PROOF TRUNKING - Procurement & Delivery 120 06-Aug-22 03-Dec-22 TAMPER PROOF TRUNKING - Procurement & Delivery
PRDELE220 GENERATORS CANOPY PREPARATION 60 07-Sep-22 16-Nov-22 GENERATORS CANOPY PREPARATION
MECHANICAL 252 19-May-22 25-Jan-23 25-Jan-23, MECHANICAL

PRDMEC110 FAN WALL UNITS (FWU) - Procurement & Delivery - (11 UNITS) 252 19-May-22 25-Jan-23 FAN WALL UNITS (FWU) - Procurement & Delivery - (11 UNITS)
PRDMEC120 CHILLERS - Procurement & Delivery - (12 MW) 231 26-May-22 11-Jan-23 CHILLERS - Procurement & Delivery - (12 MW)
PRDMEC100 CUU UNITS - Procurement & Delivery - (20 UNITS) 175 01-Jun-22 22-Nov-22 CUU UNITS - Procurement & Delivery - (20 UNITS)
PRDMEC150 CHW PIPES- Procurement & Delivery 60 18-Jun-22 16-Aug-22 CHW PIPES- Procurement & Delivery
PRDMEC190 FIRE FIGHTING - NOVEC SYSTEM- Procurement & Delivery 150 28-Jun-22 24-Nov-22 FIRE FIGHTING - NOVEC SYSTEM- Procurement & Delivery
PRDMEC210 FIRE FIGHTING - VESDA SYSTEM - Procurement & Delivery 120 29-Jun-22 26-Oct-22 FIRE FIGHTING - VESDA SYSTEM - Procurement & Delivery
PRDMEC180 FIRE FIGHTING PUMP - Procurement & Delivery 120 06-Aug-22 03-Dec-22 FIRE FIGHTING PUMP - Procurement & Delivery
PRDMEC130 AHU & FAHUs - Procurement & Delivery 120 06-Aug-22 03-Dec-22 AHU & FAHUs - Procurement & Delivery
PRDMEC170 GRP WATER TANK- Procurement & Delivery 90 06-Aug-22 03-Nov-22 GRP WATER TANK- Procurement & Delivery
PRDMEC140 DX VRF - Procurement & Delivery 90 06-Aug-22 03-Nov-22 DX VRF - Procurement & Delivery
PRDMEC160 THERMAL STORAGE TANKS - Procurement & Delivery 120 06-Aug-22 03-Dec-22 THERMAL STORAGE TANKS - Procurement & Delivery
INSTALLATION 216 15-Jun-22 01-Mar-23 01-Mar-23, INSTALLATION

CIVIL WORKS 179 15-Jun-22 17-Jan-23 17-Jan-23, CIVIL WORKS

EXTERNAL WORKS 81 15-Jun-22 20-Sep-22 20-Sep-22, EXTERNAL WORKS


EXTGENCVL120 EXTERNAL WORKS- TRENCHES LV & MV - SLEEVES 33 15-Jun-22 26-Jul-22 EXTERNAL WORKS- TRENCHES LV & MV - SLEEVES
EXTGENCVL130 EXTERNAL MEP NETWORK & SERVICES 36 15-Jun-22 29-Jul-22 EXTERNAL MEP NETWORK & SERVICES
EXTGENMEC200 EXTERNAL GENERATORS FOUNDATION 40 22-Jul-22 06-Sep-22 EXTERNAL GENERATORS FOUNDATION
EXTGENCVL150 EXTERNAL ROAD NETWORK 45 30-Jul-22 20-Sep-22 EXTERNAL ROAD NETWORK
EXTGENCVL140 EXTERNAL WORKS - GENERATORS FOUNDATIONS 21 13-Aug-22 06-Sep-22 EXTERNAL WORKS - GENERATORS FOUNDATIONS
DEWA INTAKE ROOM/
ROO RMU 107 15-Jun-22 21-Oct-22 21-Oct-22, DEWA INTAKE ROOM/ RMU
RMUCVL100 STRUCTURAL WORKS 43 15-Jun-22 06-Aug-22 STRUCTURAL WORKS
RMUCVL110 BLOCK WORKS & PLASTERING 15 08-Aug-22 24-Aug-22 BLOCK WORKS & PLASTERING
RMUCVL120 INTERNAL FINISHING WORKS 22 25-Aug-22 19-Sep-22 INTERNAL FINISHING WORKS
RMUCVL130 DOORS & WINDOWS FIXING 15 20-Sep-22 06-Oct-22 DOORS & WINDOWS FIXING
RMUCVL140 EXTERNAL FINISHING WORKS 12 07-Oct-22 21-Oct-22 EXTERNAL FINISHING WORKS
MV SWITCHGEAR R
ROOMS 94 15-Jun-22 05-Oct-22 05-Oct-22, MV SWITCHGEAR ROOMS
MVRGENCVL100 STRUCTURAL WORKS 30 15-Jun-22 22-Jul-22 STRUCTURAL WORKS
MVRGENCVL120 BLOCK WORKS & PLASTERING 15 23-Jul-22 09-Aug-22 BLOCK WORKS & PLASTERING
MVRGENCVL130 INTERNAL FINISHING WORKS 22 10-Aug-22 03-Sep-22 INTERNAL FINISHING WORKS
MVRGENCVL140 DOORS & WINDOWS FIXING 15 05-Sep-22 21-Sep-22 DOORS & WINDOWS FIXING
MVRGENCVL150 EXTERNAL FINISHING WORKS 12 22-Sep-22 05-Oct-22 EXTERNAL FINISHING WORKS
FIRE PUMP Room 31 11-Aug-22 15-Sep-22 15-Sep-22, FIRE PUMP Room
PMRGENCVL100 PLASTERING WORKS 5 11-Aug-22 16-Aug-22 PLASTERING WORKS
PMRGENCVL110 INTERNAL FINISHING WORKS 15 17-Aug-22 02-Sep-22 INTERNAL FINISHING WORKS
PMRGENCVL140 DOORS & WINDOWS FIXING 6 03-Sep-22 09-Sep-22 DOORS & WINDOWS FIXING
PMRGENCVL150 EXTERNAL FINISHING WORKS 5 10-Sep-22 15-Sep-22 EXTERNAL FINISHING WORKS
INTERNAL FINISHES 179 15-Jun-22 17-Jan-23 17-Jan-23, INTERNAL FINISHES
GROUND FLOOR 108 15-Jun-22 24-Oct-22 24-Oct-22, GROUND FLOOR
GFLGENINF100 INTERNAL WALL PARTITIONS- GF 25 15-Jun-22 16-Jul-22 INTERNAL WALL PARTITIONS- GF
GFLGENINF110 FINISHING WORKS - PLASTER - GF 20 19-Jul-22 10-Aug-22 FINISHING WORKS - PLASTER - GF
GFLGENINF120 FINISHING WORKS - PAINTING - GF 25 26-Jul-22 23-Aug-22 FINISHING WORKS - PAINTING - GF
GFLGENINF150 WINDOWS FIXING -GF 15 24-Aug-22 09-Sep-22 WINDOWS FIXING -GF
GFLGENINF160 DOORS FIXING- GF 10 10-Sep-22 21-Sep-22 DOORS FIXING- GF
GFLGENINF130 CEILING WORKS - GF 20 12-Sep-22 05-Oct-22 CEILING WORKS - GF

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 2 of 9
Remaining Work
Critical Remaining Work
Milestone
Summary
PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4... Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
GFLGENINF140 SCREED AND EPOXY -GF 15 05-Oct-22 24-Oct-22 SCREED AND EPOXY -GF
FIRST FLOOR 128 18-Jul-22 17-Dec-22 17-Dec-22, FIRST FLOOR
COMMON AREAS/
AREAS GENERAL 128 18-Jul-22 17-Dec-22 17-Dec-22, COMMON AREAS/ GENERAL
F01GENINF-10 INTERNAL WALL PARTITIONS - F1 26 18-Jul-22 16-Aug-22 INTERNAL WALL PARTITIONS - F1
F01GENINF-110 FINISHING WORKS - PLASTER - F1 26 29-Aug-22 27-Sep-22 FINISHING WORKS - PLASTER - F1
F01GENINF-12 FINISHING WORKS - PAINTING - F1 26 28-Sep-22 28-Oct-22 FINISHING WORKS - PAINTING - F1
F01GENINF-14 WINDOWS FIXING- F1 20 29-Oct-22 21-Nov-22 WINDOWS FIXING- F1
F01GENINF-13 SCREED AND EPOXY -F1 15 22-Nov-22 12-Dec-22 SCREED AND EPOXY -F1
F01GENINF-15 DOORS FIXING -F1 20 22-Nov-22 17-Dec-22 DOORS FIXING -F1
DATA HALL 1 -1F 52 28-Sep-22 28-Nov-22 28-Nov-22, DATA HALL 1 -1F
F01DH1INF-110 CEILING WORKS - DH1 -1F 40 28-Sep-22 14-Nov-22 CEILING WORKS - DH1 -1F
F01DH1INF-100 PAINT & EPOXY - DH1 -1F 12 15-Nov-22 28-Nov-22 PAINT & EPOXY - DH1 -1F
SECOND FLOOR 128 17-Aug-22 17-Jan-23 17-Jan-23, SECOND FLOOR
COMMON AREAS/
AREAS GENERAL 127 17-Aug-22 16-Jan-23 16-Jan-23, COMMON AREAS/ GENERAL
F02GENINF-10 INTERNAL WALL PARTITIONS - 2F 21 17-Aug-22 09-Sep-22 INTERNAL WALL PARTITIONS - 2F
F02GENINF-110 FINISHING WORKS - PLASTER - 2F 14 12-Oct-22 27-Oct-22 FINISHING WORKS - PLASTER - 2F
F02GENINF-12 FINISHING WORKS - PAINTING - 2F 21 27-Oct-22 19-Nov-22 FINISHING WORKS - PAINTING - 2F
F02GENINF-14 WINDOWS FIXING - 2F 15 22-Nov-22 12-Dec-22 WINDOWS FIXING - 2F
F02GENINF-15 DOORS FIXING - 2F 10 19-Dec-22 29-Dec-22 DOORS FIXING - 2F
F02GENINF-13 SCREED AND EPOXY - 2F 15 30-Dec-22 16-Jan-23 SCREED AND EPOXY - 2F
DATA HALL 1 -2F 52 15-Nov-22 17-Jan-23 17-Jan-23, DATA HALL 1 -2F
F02DH1INF-110 CEILING WORKS - DH1 -1F 40 15-Nov-22 03-Jan-23 CEILING WORKS - DH1 -1F
F02DH1INF-100 PAINT & EPOXY - DH1 -1F 12 04-Jan-23 17-Jan-23 PAINT & EPOXY - DH1 -1F
ROOF FLOOR 64 28-Jun-22 13-Sep-22 13-Sep-22, ROOF FLOOR
ROFGENCVL100 CHILLER PLATFORM 24 28-Jun-22 28-Jul-22 CHILLER PLATFORM
ROFGENCVL110 MACHINE ROOMS 7 29-Jul-22 05-Aug-22 MACHINE ROOMS
ROFGENCVL120 MEP EQUIPMENT FOUNDATION 20 29-Jul-22 20-Aug-22 MEP EQUIPMENT FOUNDATION
ROFGENCVL130 UPPER ROOF WATERPROOFING 20 22-Aug-22 13-Sep-22 UPPER ROOF WATERPROOFING
GENERALL 43 15-Oct-22 07-Dec-22 07-Dec-22, GENERALL
INFGEN-130 ELEVATORS INSTALLATION 35 15-Oct-22 24-Nov-22 ELEVATORS INSTALLATION
INFGEN-140 MANTRAP INSTALLATION 35 25-Oct-22 07-Dec-22 MANTRAP INSTALLATION
ELECTRICAL WO
WORKS 190 18-Jul-22 28-Feb-23 28-Feb-23, ELECTRICAL WORKS

EXTERNAL WORKS 139 16-Aug-22 28-Jan-23 28-Jan-23, EXTERNAL WORKS


MV SWITCHGEAR ROOMS
RO 41 24-Nov-22 13-Jan-23 13-Jan-23, MV SWITCHGEAR ROOMS
B3GFMVRELE101 MV SWITCHGEARS INSTALLATION 21 24-Nov-22 21-Dec-22 MV SWITCHGEARS INSTALLATION
B3GFMVRELE112 MV SWITCHGEARS TERMINATIONS 32 08-Dec-22 13-Jan-23 MV SWITCHGEARS TERMINATIONS
GENERATORS 120 07-Sep-22 28-Jan-23 28-Jan-23, GENERATORS
EXTGENELE160 EARTHING 30 07-Sep-22 12-Oct-22 EARTHING
EXTGENELE100 POWER CABLES PULLING - GENERATORS 34 13-Sep-22 24-Oct-22 POWER CABLES PULLING - GENERATORS
EXTGENELEPA1 PA1 GENERATOR POSITIONING & CABLES TERMINATION 10 17-Nov-22 28-Nov-22 PA1 GENERATOR POSITIONING & CABLES TERMINATION
EXTGENELEPB1 PB1 GENERATOR POSITIONING & CABLES TERMINATION 10 29-Nov-22 13-Dec-22 PB1 GENERATOR POSITIONING & CABLES TERMINATION
EXTGENELEPC1 PC1 GENERATOR POSITIONING & CABLES TERMINATION 10 14-Dec-22 24-Dec-22 PC1 GENERATOR POSITIONING & CABLES TERMINATION
EXTGENELEPD1 PD1 GENERATOR POSITIONING & CABLES TERMINATION 10 26-Dec-22 05-Jan-23 PD1 GENERATOR POSITIONING & CABLES TERMINATION
EXTGENELEPE1 PE1 GENERATOR POSITIONING & CABLES TERMINATION 10 06-Jan-23 17-Jan-23 PE1 GENERATOR POSITIONING & CABLES TERMINATION
EXTGENELEPHL PHL GENERATOR POSITIONING & CABLES TERMINATION 10 18-Jan-23 28-Jan-23 PHL GENERATOR POSITIONING & CABLES TERMINATION
DEWA INTAKE ROOM/
ROOM RMU 125 16-Aug-22 12-Jan-23 12-Jan-23, DEWA INTAKE ROOM/ RMU
EXTGENELE120 DEWA MV CABLES LAYING 45 16-Aug-22 17-Oct-22 DEWA MV CABLES LAYING
EXTGENELE190 MV CABLESTERMINATION - MAIN INTAKE ROOM 60 18-Oct-22 12-Jan-23 MV CABLESTERMINATION - MAIN INTAKE ROOM
EXTGENELE170 MV POSITIONING - MAIN INTAKE ROOM 18 24-Nov-22 17-Dec-22 MV POSITIONING - MAIN INTAKE ROOM
GROUND FLOOR 167 18-Jul-22 01-Feb-23 01-Feb-23, GROUND FLOOR
COMMON AREAS 118 18-Jul-22 06-Dec-22 06-Dec-22, COMMON AREAS
B3GFCOMELE100 INSTALLATION OF CONDUITS & BOXES IN BLOCK WORKS 26 18-Jul-22 16-Aug-22 INSTALLATION OF CONDUITS & BOXES IN BLOCK WORKS
B3GFCOMELE113 SMALL POWER CONDUITING & CABLES PULLING 21 04-Aug-22 27-Aug-22 SMALL POWER CONDUITING & CABLES PULLING

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 3 of 9
Remaining Work
Critical Remaining Work
Milestone
Summary
PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4... Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
B3GFCOMELE103 CABLE TRAYS INSTALLATION 40 17-Aug-22 01-Oct-22 CABLE TRAYS INSTALLATION
B3GFCOMELE1050 GI PIPES INSTALLATION AND CABLES PULLING FOR FIRE 40 29-Aug-22 14-Oct-22 GI PIPES INSTALLATION AND CABLES PULLING FOR FIRE ALARM/EMERGENCY LIGHT
ALARM/EMERGENCY LIGHT
B3GFCOMELE106 POWER CABLES PULLING & TERMINATION 45 03-Oct-22 24-Nov-22 POWER CABLES PULLING & TERMINATION
B3GFCOMELE112 EMERGENCY LIGHT FIXTURES INSTALLATION 36 15-Oct-22 26-Nov-22 EMERGENCY LIGHT FIXTURES INSTALLATION
B3GFCOMELE1140 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES 40 15-Oct-22 03-Dec-22 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES

B3GFCOMELE104 PANELS POSITIONING- ELV ROOMS 6 19-Oct-22 26-Oct-22 PANELS POSITIONING- ELV ROOMS
B3GFCOMELE109 LIGHT FIXTURES INSTALLATION 32 26-Oct-22 06-Dec-22 LIGHT FIXTURES INSTALLATION
LV ROOM - A1 115 18-Jul-22 03-Dec-22 03-Dec-22, LV ROOM - A1
GFPA1ELE1000 CABLE TRAYS INSTALLATION 12 18-Jul-22 30-Jul-22 CABLE TRAYS INSTALLATION
GFPA1ELE1010 POWER CABLES LAYING 12 13-Sep-22 27-Sep-22 POWER CABLES LAYING
GFPA1ELE1020 UPS POSITIONING 2 04-Oct-22 05-Oct-22 UPS POSITIONING
GFPA1ELE1040 PANELS POSITIONING 6 19-Oct-22 26-Oct-22 PANELS POSITIONING
GFPA1ELE1050 TRAYS & POWER CABLES TERMINATION 12 25-Oct-22 08-Nov-22 TRAYS & POWER CABLES TERMINATION
GFPA1ELE1080 BUSBAR - (UPS to MDB) 8 27-Oct-22 05-Nov-22 BUSBAR - (UPS to MDB)
GFPA1ELE1030 BUSBAR - PATHWAY A1 7 08-Nov-22 16-Nov-22 BUSBAR - PATHWAY A1
GFPA1ELE1090 BUSBAR - TRX A1 6 16-Nov-22 23-Nov-22 BUSBAR - TRX A1
GFPA1ELE1070 BATTERY RACKS & BATTERIES INSTALLATION 10 18-Nov-22 03-Dec-22 BATTERY RACKS & BATTERIES INSTALLATION
LV ROOM - B1 114 01-Aug-22 15-Dec-22 15-Dec-22, LV ROOM - B1
GFPB1ELE1000 CABLE TRAYS INSTALLATION 12 01-Aug-22 13-Aug-22 CABLE TRAYS INSTALLATION
GFPB1ELE1010 POWER CABLES LAYING 12 13-Sep-22 27-Sep-22 POWER CABLES LAYING
GFPB1ELE1020 UPS POSITIONING 2 04-Oct-22 05-Oct-22 UPS POSITIONING
GFPB1ELE1040 PANELS POSITIONING 6 26-Oct-22 02-Nov-22 PANELS POSITIONING
GFPB1ELE1050 TRAYS & POWER CABLES TERMINATION 12 31-Oct-22 14-Nov-22 TRAYS & POWER CABLES TERMINATION
GFPB1ELE1080 BUSBAR - (UPS to MDB) 8 02-Nov-22 11-Nov-22 BUSBAR - (UPS to MDB)
GFPB1ELE1030 BUSBAR - PATHWAY B1 7 16-Nov-22 24-Nov-22 BUSBAR - PATHWAY B1
GFPB1ELE1090 BUSBAR - TRX B1 6 23-Nov-22 03-Dec-22 BUSBAR - TRX B1
GFPB1ELE1070 BATTERY RACKS & BATTERIES INSTALLATION 10 03-Dec-22 15-Dec-22 BATTERY RACKS & BATTERIES INSTALLATION
LV ROOM - C1 112 15-Aug-22 27-Dec-22 27-Dec-22, LV ROOM - C1
GFPC1ELE1000 CABLE TRAYS INSTALLATION 12 15-Aug-22 27-Aug-22 CABLE TRAYS INSTALLATION
GFPC1ELE1010 POWER CABLES LAYING 12 13-Sep-22 27-Sep-22 POWER CABLES LAYING
GFPC1ELE1020 UPS POSITIONING 2 04-Oct-22 05-Oct-22 UPS POSITIONING
GFPC1ELE1040 PANELS POSITIONING 6 02-Nov-22 09-Nov-22 PANELS POSITIONING
GFPC1ELE1050 TRAYS & POWER CABLES TERMINATION 12 07-Nov-22 21-Nov-22 TRAYS & POWER CABLES TERMINATION
GFPC1ELE1080 BUSBAR - (UPS to MDB) 8 09-Nov-22 18-Nov-22 BUSBAR - (UPS to MDB)
GFPC1ELE1030 BUSBAR - PATHWAY C1 7 24-Nov-22 06-Dec-22 BUSBAR - PATHWAY C1
GFPC1ELE1090 BUSBAR - TRX C1 6 03-Dec-22 10-Dec-22 BUSBAR - TRX C1
GFPC1ELE1070 BATTERY RACKS & BATTERIES INSTALLATION 10 15-Dec-22 27-Dec-22 BATTERY RACKS & BATTERIES INSTALLATION
LV ROOM - D1 110 29-Aug-22 07-Jan-23 07-Jan-23, LV ROOM - D1
GFPD1ELE1000 CABLE TRAYS INSTALLATION 12 29-Aug-22 10-Sep-22 CABLE TRAYS INSTALLATION
GFPD1ELE1010 POWER CABLES LAYING 12 13-Sep-22 27-Sep-22 POWER CABLES LAYING
GFPD1ELE1020 UPS POSITIONING 2 04-Oct-22 05-Oct-22 UPS POSITIONING
GFPD1ELE1040 PANELS POSITIONING 6 09-Nov-22 16-Nov-22 PANELS POSITIONING
GFPD1ELE1050 TRAYS & POWER CABLES TERMINATION 12 14-Nov-22 28-Nov-22 TRAYS & POWER CABLES TERMINATION
GFPD1ELE1080 BUSBAR - (UPS to MDB) 8 16-Nov-22 25-Nov-22 BUSBAR - (UPS to MDB)
GFPD1ELE1030 BUSBAR - PATHWAY D1 7 06-Dec-22 14-Dec-22 BUSBAR - PATHWAY D1
GFPD1ELE1090 BUSBAR - TRX D1 6 10-Dec-22 17-Dec-22 BUSBAR - TRX D1
GFPD1ELE1070 BATTERY RACKS & BATTERIES INSTALLATION 10 27-Dec-22 07-Jan-23 BATTERY RACKS & BATTERIES INSTALLATION
LV ROOM - E1 108 12-Sep-22 20-Jan-23 20-Jan-23, LV ROOM - E1
GFPE1ELE1000 CABLE TRAYS INSTALLATION 12 12-Sep-22 24-Sep-22 CABLE TRAYS INSTALLATION
GFPE1ELE1010 POWER CABLES LAYING 12 26-Sep-22 10-Oct-22 POWER CABLES LAYING
GFPE1ELE1020 UPS POSITIONING 2 04-Oct-22 05-Oct-22 UPS POSITIONING
GFPE1ELE1040 PANELS POSITIONING 6 16-Nov-22 23-Nov-22 PANELS POSITIONING
GFPE1ELE1050 TRAYS & POWER CABLES TERMINATION 12 21-Nov-22 08-Dec-22 TRAYS & POWER CABLES TERMINATION

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 4 of 9
Remaining Work
Critical Remaining Work
Milestone
Summary
PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4... Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
GFPE1ELE1080 BUSBAR - (UPS to MDB) 8 23-Nov-22 06-Dec-22 BUSBAR - (UPS to MDB)
GFPE1ELE1030 BUSBAR - PATHWAY E1 7 14-Dec-22 22-Dec-22 BUSBAR - PATHWAY E1
GFPE1ELE1090 BUSBAR - TRX E1 6 17-Dec-22 24-Dec-22 BUSBAR - TRX E1
GFPE1ELE1070 BATTERY RACKS & BATTERIES INSTALLATION 10 09-Jan-23 20-Jan-23 BATTERY RACKS & BATTERIES INSTALLATION
LV ROOM HL 107 26-Sep-22 01-Feb-23 01-Feb-23, LV ROOM HL
GFPHLELE1000 CABLE TRAYS INSTALLATION 12 26-Sep-22 10-Oct-22 CABLE TRAYS INSTALLATION
GFPHLELE1020 UPS POSITIONING 2 04-Oct-22 05-Oct-22 UPS POSITIONING
GFPHLELE1010 POWER CABLES LAYING 12 11-Oct-22 24-Oct-22 POWER CABLES LAYING
GFPHLELE1050 TRAYS & POWER CABLES TERMINATION 12 25-Oct-22 07-Nov-22 TRAYS & POWER CABLES TERMINATION
GFPHLELE1040 PANELS POSITIONING 6 23-Nov-22 03-Dec-22 PANELS POSITIONING
GFPHLELE1090 BUSBAR - TRX HL 6 24-Dec-22 31-Dec-22 BUSBAR - TRX HL
GFPHLELE1070 BATTERY RACKS & BATTERIES INSTALLATION 10 20-Jan-23 01-Feb-23 BATTERY RACKS & BATTERIES INSTALLATION
TRANSFORMER ROOMS
ROO 12 04-Oct-22 18-Oct-22 18-Oct-22, TRANSFORMER ROOMS
GFPA1ELETRX TRANSFORMERS INSTALLATION- TRX A1 2 04-Oct-22 05-Oct-22 TRANSFORMERS INSTALLATION- TRX A1
GFTRXELE1030 INSTALLATION OF EARTHING & LIGHTNING PROTECTION 12 04-Oct-22 18-Oct-22 INSTALLATION OF EARTHING & LIGHTNING PROTECTION
GFPB1ELETRX TRANSFORMERS INSTALLATION- TRX B1 2 06-Oct-22 07-Oct-22 TRANSFORMERS INSTALLATION- TRX B1
GFPC1ELETRX TRANSFORMERS INSTALLATION- TRX C1 2 10-Oct-22 11-Oct-22 TRANSFORMERS INSTALLATION- TRX C1
GFPD1ELETRX TRANSFORMERS INSTALLATION- TRX D1 2 12-Oct-22 13-Oct-22 TRANSFORMERS INSTALLATION- TRX D1
GFPE1ELETRX TRANSFORMERS INSTALLATION- TRX E1 2 14-Oct-22 15-Oct-22 TRANSFORMERS INSTALLATION- TRX E1
GFPHLELETRX TRANSFORMERS INSTALLATION- TRX HL 2 17-Oct-22 18-Oct-22 TRANSFORMERS INSTALLATION- TRX HL
FIRST FLOOR 163 17-Aug-22 27-Feb-23 27-Feb-23, FIRST FLOOR
COMMON AREAS/ G
GENERAL 123 17-Aug-22 11-Jan-23 11-Jan-23, COMMON AREAS/ GENERAL
F01GENELE110 INSTALLATION OF CONDUITS & BOXES IN BLOCK WORKS 26 17-Aug-22 15-Sep-22 INSTALLATION OF CONDUITS & BOXES IN BLOCK WORKS
F01GENELE120 CABLE TRAYS INSTALLATION 28 16-Sep-22 19-Oct-22 CABLE TRAYS INSTALLATION
F01GENELE100 SMALL POWER CONDUITING & CABLES PULLING 36 28-Sep-22 09-Nov-22 SMALL POWER CONDUITING & CABLES PULLING
F01GENELE200 GI PIPES INSTALLATION AND CABLES PULLING FOR FIRE 36 15-Oct-22 25-Nov-22 GI PIPES INSTALLATION AND CABLES PULLING FOR FIRE ALARM/EMERGENCY L
ALARM/EMERGENCY LIGHT
F01GENELE140 POWER CABLES PULLING 26 20-Oct-22 18-Nov-22 POWER CABLES PULLING
F01GENELE170 LIGHT FIXTURES INSTALLATION 21 10-Nov-22 07-Dec-22 LIGHT FIXTURES INSTALLATION
F01GENELE180 EMERGENCY LIGHT FIXTURES INSTALLATION 18 10-Nov-22 03-Dec-22 EMERGENCY LIGHT FIXTURES INSTALLATION
F01GENELE210 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES 12 26-Nov-22 13-Dec-22 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES

F01GENELE130 PANELS POSITIONING- ELV ROOMS 6 03-Dec-22 10-Dec-22 PANELS POSITIONING- ELV ROOMS
F01GENELE150 POWER CABLES TERMINATION 20 14-Dec-22 06-Jan-23 POWER CABLES TERMINATION
F01GENELE160 BUSBAR & OVERHEAD TAPOFF INSTALLATION 24 14-Dec-22 11-Jan-23 BUSBAR & OVERHEAD TAPOFF INSTALLATION
DATA HALL 1 - 1F 101 29-Oct-22 27-Feb-23 27-Feb-23, DATA HALL 1 - 1F
F01DH1ELE110 EARTHING & GROUNDING INSTALLATION 11 29-Oct-22 10-Nov-22 EARTHING & GROUNDING INSTALLATION
F01DH1ELE120 LIGHT FIXTURES INSTALLATION 17 15-Nov-22 07-Dec-22 LIGHT FIXTURES INSTALLATION
F01DH1ELE160 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES 26 26-Nov-22 29-Dec-22 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES

F01DH1ELE140 TAMPERPROOF TRUNKING 15 05-Dec-22 21-Dec-22 TAMPERPROOF TRUNKING


F01DH1ELE100 BUSBAR OVERHEAD TAPOFF INSTALLATION 18 11-Jan-23 01-Feb-23 BUSBAR OVERHEAD TAPOFF INSTALLATION
F01DH1ELE130 FWU TERMINATION 24 31-Jan-23 27-Feb-23 FWU TERMINATION
SECOND FLOOR 143 10-Sep-22 28-Feb-23 28-Feb-23, SECOND FLOOR
COMMON AREAS/ G
GENERAL 122 10-Sep-22 03-Feb-23 03-Feb-23, COMMON AREAS/ GENERAL
F02GENELE110 INSTALLATION OF CONDUITS & BOXES IN BLOCK WORKS 26 10-Sep-22 11-Oct-22 INSTALLATION OF CONDUITS & BOXES IN BLOCK WORKS
F02GENELE120 CABLE TRAYS INSTALLATION 29 12-Oct-22 14-Nov-22 CABLE TRAYS INSTALLATION
F02GENELE100 SMALL POWER CONDUITING & CABLES PULLING 30 10-Nov-22 17-Dec-22 SMALL POWER CONDUITING & CABLES PULLING
F02GENELE140 POWER CABLES PULLING 20 15-Nov-22 10-Dec-22 POWER CABLES PULLING
F02DH3ELE150 GI PIPES INSTALLATION AND CABLES PULLING FOR FIRE 32 26-Nov-22 05-Jan-23 GI PIPES INSTALLATION AND CABLES PULLING FOR FIRE ALARM/EM
ALARM/EMERGENCY LIGHT
F02GENELE130 PANELS POSITIONING- ELV ROOMS 6 10-Dec-22 17-Dec-22 PANELS POSITIONING- ELV ROOMS
F02GENELE160 BUSBAR & OVERHEAD TAPOFF INSTALLATION 18 14-Dec-22 04-Jan-23 BUSBAR & OVERHEAD TAPOFF INSTALLATION
F02GENELE150 POWER CABLES TERMINATION 24 17-Dec-22 14-Jan-23 POWER CABLES TERMINATION
F02GENELE170 LIGHT FIXTURES INSTALLATION 34 19-Dec-22 26-Jan-23 LIGHT FIXTURES INSTALLATION

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 5 of 9
Remaining Work
Critical Remaining Work
Milestone
Summary
PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4... Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
F02DH3ELE160 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES 18 06-Jan-23 26-Jan-23 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSOR

F02GENELE180 EMERGENCY LIGHT FIXTURES INSTALLATION 17 14-Jan-23 03-Feb-23 EMERGENCY LIGHT FIXTURES INSTALLATION
DATA HALL 1 - 2F 91 11-Nov-22 28-Feb-23 28-Feb-23, DATA HALL 1 - 2F
F02DH1ELE110 EARTHING & GROUNDING INSTALLATION 11 11-Nov-22 23-Nov-22 EARTHING & GROUNDING INSTALLATION
F02DH1ELE160 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES 26 21-Nov-22 23-Dec-22 INSTALLATION OF FIRE ALAM DEVICES/ PANELS & ACCESSORIES

F02DH1ELE100 BUSBAR OVERHEAD TAPOFF INSTALLATION 18 26-Nov-22 21-Dec-22 BUSBAR OVERHEAD TAPOFF INSTALLATION
F02DH1ELE140 TAMPERPROOF TRUNKING 15 21-Dec-22 06-Jan-23 TAMPERPROOF TRUNKING
F02DH1ELE120 LIGHT FIXTURES INSTALLATION 17 04-Jan-23 23-Jan-23 LIGHT FIXTURES INSTALLATION
F02DH1ELE130 FWUs TERMINATION - 2 Units 8 20-Feb-23 28-Feb-23 FWUs TERMINATION - 2 Units
ROOF FLOOR 127 14-Sep-22 13-Feb-23 13-Feb-23, ROOF FLOOR
ROFGENELE120 CABLE TRAYS INSTALLATION 21 14-Sep-22 07-Oct-22 CABLE TRAYS INSTALLATION
ROFGENELE170 CPM CONTAINMENT INSTALLATION 26 01-Oct-22 01-Nov-22 CPM CONTAINMENT INSTALLATION
ROFGENELE130 CHILLERS CABLES PULLING 20 10-Oct-22 01-Nov-22 CHILLERS CABLES PULLING
ROFGENELE100 LIGHTING PROTECTION 33 10-Oct-22 16-Nov-22 LIGHTING PROTECTION
ROFGENELE110 CHILLERS ISOLATORS POSITIONING 10 19-Oct-22 31-Oct-22 CHILLERS ISOLATORS POSITIONING
ROFGENELE180 CPM CABLES PULLING & TERMINATION 26 02-Nov-22 05-Dec-22 CPM CABLES PULLING & TERMINATION
ROFGENELE190 CPM FIELD DEVICES INSTALLATION 21 06-Dec-22 29-Dec-22 CPM FIELD DEVICES INSTALLATION
ROFGENELE150 CHILLERS CABLES TERMINATION 20 21-Jan-23 13-Feb-23 CHILLERS CABLES TERMINATION
MECHANICAL WORKS
WO 191 18-Jul-22 01-Mar-23 01-Mar-23, MECHANICAL WORKS

GROUND FLOOR 153 18-Jul-22 16-Jan-23 16-Jan-23, GROUND FLOOR


GFLGENMEC100 PLUMBING WORKS 13 18-Jul-22 01-Aug-22 PLUMBING WORKS
GFLGENMEC200 COPPPER PIPES FOR VRF 24 26-Jul-22 22-Aug-22 COPPPER PIPES FOR VRF
GFLGENMEC120 DUCT WORKS 30 24-Aug-22 28-Sep-22 DUCT WORKS
GFLGENMEC220 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION 39 24-Aug-22 07-Oct-22 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION
GFLGENMEC110 CHW PIPES INSTALLATION 36 05-Sep-22 17-Oct-22 CHW PIPES INSTALLATION
GFLGENMEC150 CHW PIPE WORK INSULATION 21 18-Oct-22 10-Nov-22 CHW PIPE WORK INSULATION
GFLGENMEC170 EQUIPMENT INSTALLATION (DX Unit) 18 04-Nov-22 24-Nov-22 EQUIPMENT INSTALLATION (DX Unit)
GFLGENMEC210 CONDENSATE DRAIN PIPING & RELATED CONNECTIONS TO 28 25-Nov-22 30-Dec-22 CONDENSATE DRAIN PIPING & RELATED CONNECTIONS TO EQUIPMEN
EQUIPMENTS
GFLGENMEC190 CUU UNITS INSTALLATION 16 05-Dec-22 22-Dec-22 CUU UNITS INSTALLATION
GFLGENMEC230 FIRE FIGHTING NOVEC CYLINDERS & FINAL FIXES 37 05-Dec-22 16-Jan-23 FIRE FIGHTING NOVEC CYLINDERS & FINAL FIXES
GFLGENMEC240 FIRE FIGHTING PUMP INSTALLATION & RELATED CONNECTIONS 21 14-Dec-22 06-Jan-23 FIRE FIGHTING PUMP INSTALLATION & RELATED CONNECTIONS

FIRST FLOOR 163 17-Aug-22 27-Feb-23 27-Feb-23, FIRST FLOOR


COMMON AREAS/ G
GENERAL 139 17-Aug-22 30-Jan-23 30-Jan-23, COMMON AREAS/ GENERAL
F01GENMEC110 PLUMBING WORKS 21 17-Aug-22 09-Sep-22 PLUMBING WORKS
F01GENMEC100 DUCT WORKS 41 28-Sep-22 15-Nov-22 DUCT WORKS
F01GENMEC160 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION 40 13-Oct-22 28-Nov-22 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION
F01GENMEC120 CHW PIPE WORK INSTALLATION 32 18-Oct-22 23-Nov-22 CHW PIPE WORK INSTALLATION
F01GENMEC130 EQUIPMENT INSTALLATION (FCU) 14 04-Nov-22 21-Nov-22 EQUIPMENT INSTALLATION (FCU)
F01GENMEC180 COPPPER PIPES FOR VRF 25 21-Nov-22 23-Dec-22 COPPPER PIPES FOR VRF
F01GENMEC140 CHW PIPE WORK INSULATION 25 23-Nov-22 26-Dec-22 CHW PIPE WORK INSULATION
F01GENMEC190 FIREFIGHTING PREACTION SYSTEM INSTALLATION 30 29-Nov-22 05-Jan-23 FIREFIGHTING PREACTION SYSTEM INSTALLATION
F01GENMEC200 CONDENSATE DRAIN PIPING & RELATED CONNECTIONS TO 26 31-Dec-22 30-Jan-23 CONDENSATE DRAIN PIPING & RELATED CONNECTIONS TO E
EQUIPMENTS
DATA HALL 1 -1F 75 29-Nov-22 27-Feb-23 27-Feb-23, DATA HALL 1 -1F
F01DH1MEC150 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION 24 29-Nov-22 29-Dec-22 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION
F01DH1MEC140 GRILLS & DIFFUSERS 10 19-Dec-22 30-Dec-22 GRILLS & DIFFUSERS
F01DH1MEC110 FWUs INSTALLATION -9 Units 10 07-Feb-23 17-Feb-23 FWUs INSTALLATION -9 Units
F01DH1MEC160 CONNECTION To FWUs -9 Units 18 07-Feb-23 27-Feb-23 CONNECTION To FWUs -9 Units
SECOND FLOOR 144 10-Sep-22 01-Mar-23 01-Mar-23, SECOND FLOOR
COMMON AREAS/ G
GENERAL 144 10-Sep-22 01-Mar-23 01-Mar-23, COMMON AREAS/ GENERAL

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 6 of 9
Remaining Work
Critical Remaining Work
Milestone
Summary
PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4... Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
F02GENMEC110 PLUMBING WORKS 32 10-Sep-22 18-Oct-22 PLUMBING WORKS
F02GENMEC190 FIREFIGHTING PREACTION SYSTEM INSTALLATION 30 14-Nov-22 21-Dec-22 FIREFIGHTING PREACTION SYSTEM INSTALLATION
F02GENMEC100 DUCT WORKS 28 16-Nov-22 21-Dec-22 DUCT WORKS
F02GENMEC180 COPPPER PIPES FOR VRF 19 21-Nov-22 15-Dec-22 COPPPER PIPES FOR VRF
F02GENMEC130 EQUIPMENT INSTALLATION (FCU) 15 21-Nov-22 12-Dec-22 EQUIPMENT INSTALLATION (FCU)
F02GENMEC120 CHW PIPE WORK INSTALLATION 28 23-Nov-22 29-Dec-22 CHW PIPE WORK INSTALLATION
F02GENMEC160 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION 30 22-Dec-22 25-Jan-23 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION
F02GENMEC140 CHW PIPE WORK INSULATION 22 29-Dec-22 24-Jan-23 CHW PIPE WORK INSULATION
F02DH1MEC130 CONDENSATE DRAIN PIPING & RELATED CONNECTIONS TO 26 31-Jan-23 01-Mar-23 CONDENSATE DRAIN PIPING & RELATED CONNECTIO
EQUIPMENTS
DATA HALL 1-2F 143 10-Sep-22 28-Feb-23 28-Feb-23, DATA HALL 1-2F
F02DH1MEC150 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION 18 10-Sep-22 30-Sep-22 FIRE FIGHTING PIPES/ SPRINKLERS INSTALLATION
F02DH1MEC140 GRILLS & DIFFUSERS 10 04-Jan-23 16-Jan-23 GRILLS & DIFFUSERS
F02DH1MEC110 FWUs INSTALLATION - 2units 4 18-Feb-23 22-Feb-23 FWUs INSTALLATION - 2units
F02DH1MEC160 CONNECTION To FWUs - 2units 8 20-Feb-23 28-Feb-23 CONNECTION To FWUs - 2units
ROOF FLOOR 129 14-Sep-22 15-Feb-23 15-Feb-23, ROOF FLOOR
ROFGENMEC100 CHW PIPES INSTALLATION 45 14-Sep-22 05-Nov-22 CHW PIPES INSTALLATION
ROFGENMEC110 EQUIPMENT INSTALLATION (VRF Outdoor Unit) 21 04-Nov-22 28-Nov-22 EQUIPMENT INSTALLATION (VRF Outdoor Unit)
ROFGENMEC150 CHW PIPES INSULATION 29 07-Nov-22 13-Dec-22 CHW PIPES INSULATION
ROFGENMEC140 EQUIPMENT INSTALLATION ( FAHU) 14 05-Dec-22 20-Dec-22 EQUIPMENT INSTALLATION ( FAHU)
ROFGENMEC190 THERMAL STORAGE TANKS INSTALLATION & CONNECTIONS 12 05-Dec-22 17-Dec-22 THERMAL STORAGE TANKS INSTALLATION & CONNECTIONS
ROFGENMEC170 CHW FLUSHING 45 26-Dec-22 15-Feb-23 CHW FLUSHING
ROFGENMEC180 CHW PIPES CLADDING 25 11-Jan-23 09-Feb-23 CHW PIPES CLADDING
ROFGENMEC120 CHILLERS POSITIONING & CHW PIPES CONNECTIONS 12 24-Jan-23 06-Feb-23 CHILLERS POSITIONING & CHW PIPES CONNECTIONS
EXTERNAL WORKS 85 07-Sep-22 19-Dec-22 19-Dec-22, EXTERNAL WORKS
EXTGENMEC100 PLUMBING WORKS 40 07-Sep-22 24-Oct-22 PLUMBING WORKS
EXTGENMEC130 GRP WATER TANK INSTALLATION 36 04-Nov-22 19-Dec-22 GRP WATER TANK INSTALLATION
ELV SYSTEMS INSTALLATION
INS 125 16-Sep-22 13-Feb-23 13-Feb-23, ELV SYSTEMS INSTALLATION

ELVCNT1000 ELV CONTAINMENT INSTALLATION 45 16-Sep-22 08-Nov-22 ELV CONTAINMENT INSTALLATION


ELVWIR1000 ELV WIRING & CABLING 60 12-Oct-22 23-Dec-22 ELV WIRING & CABLING
ELVSTC1000 STRUCTURED CABLING PULLING & RACK/ CABINET INSTALLATION 45 09-Nov-22 03-Jan-23 STRUCTURED CABLING PULLING & RACK/ CABINET INSTALLATION

ELVGTB1000 GATE BARRIER & INTERCOM SYSTEM INSTALLATION 21 24-Dec-22 17-Jan-23 GATE BARRIER & INTERCOM SYSTEM INSTALLATION
ELVCCT1000 CCTV /ACCESS CONTROL INSTALLATION 44 24-Dec-22 13-Feb-23 CCTV /ACCESS CONTROL INSTALLATION
ELVACN1000 ACTIVE NETWORK EQUIPMENT INSTALLATION - IDF & MDF 18 18-Jan-23 07-Feb-23 ACTIVE NETWORK EQUIPMENT INSTALLATION - IDF & MDF
BMS SYSTEM 157 18-Jul-22 20-Jan-23 20-Jan-23, BMS SYSTEM

ELVBMS1000 BMS CONTAINMENT INSTALLATION 40 18-Jul-22 01-Sep-22 BMS CONTAINMENT INSTALLATION


ELVBMS1010 BMS CABLES PULLING 60 02-Sep-22 11-Nov-22 BMS CABLES PULLING
ELVBMS1020 DDC PANELS INSTALLATION 26 12-Nov-22 15-Dec-22 DDC PANELS INSTALLATION
ELVBMS1030 FIELD DEVICES INSTALLATION & TERMINATION 36 12-Nov-22 27-Dec-22 FIELD DEVICES INSTALLATION & TERMINATION
ELVBMS1040 DDC PANEL TERMINATION & PRE-COMMISSIONING 36 10-Dec-22 20-Jan-23 DDC PANEL TERMINATION & PRE-COMMISSIONING
AUTHORITIES 28 16-Jan-23 22-Feb-23 22-Feb-23, AUTHORITIES

DEWA 25 16-Jan-23 17-Feb-23 17-Feb-23, DEWA

AUT1080 DEWA INSPECTION 24 16-Jan-23 16-Feb-23 DEWA INSPECTION


AUT1100 DEWA APPROVAL & POWER ON 1 17-Feb-23 17-Feb-23* DEWA APPROVAL & POWER ON
DCD, SIRA 19 27-Jan-23 22-Feb-23 22-Feb-23, DCD, SIRA

AUT1110 DCD INSPECTION & APPROVAL 12 27-Jan-23 13-Feb-23 DCD INSPECTION & APPROVAL
AUT1120 SIRA INSPECTION & APPROVAL 7 14-Feb-23 22-Feb-23 SIRA INSPECTION & APPROVAL
TESTING & COMMISSIONING
COMMIS 55 26-Jan-23 30-Mar-23 30-Mar-23, TESTING & COMMISSIONING

LEVEL 2- PRECOMMISSIONING
PRECO 12 10-Feb-23 23-Feb-23 23-Feb-23, LEVEL 2- PRECOMMISSIONING

L2-PA1-1000 L2 Test LV ROOM A1 2 10-Feb-23 11-Feb-23 L2 Test LV ROOM A1


L2-PB1-1000 L2 Test LV ROOM B1 2 13-Feb-23 14-Feb-23 L2 Test LV ROOM B1

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 7 of 9
Remaining Work
Critical Remaining Work
Milestone
Summary
PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4... Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
L2-PC1-1000 L2 Test LV ROOM C1 2 15-Feb-23 16-Feb-23 L2 Test LV ROOM C1
L2-PD1-1000 L2 Test LV ROOM D1 2 17-Feb-23 18-Feb-23 L2 Test LV ROOM D1
L2-PE1-1000 L2 Test LV ROOM E1 2 20-Feb-23 21-Feb-23 L2 Test LV ROOM E1
L2-PHL-1000 L2 Test LV ROOM HL 2 22-Feb-23 23-Feb-23 L2 Test LV ROOM HL
LEVEL 2 - ENERGIZATION
ENERG 12 13-Feb-23 27-Feb-23 27-Feb-23, LEVEL 2 - ENERGIZATION

L2-PA1-1010 PATHWAY A1 2 13-Feb-23 15-Feb-23 PATHWAY A1


L2-PB1-1010 PATHWAY B1 2 15-Feb-23 17-Feb-23 PATHWAY B1
L2-PC1-1010 PATHWAY C1 2 17-Feb-23 20-Feb-23 PATHWAY C1
L2-PD1-1010 PATHWAY D1 2 20-Feb-23 22-Feb-23 PATHWAY D1
L2-PE1-1010 PATHWAY E1 2 22-Feb-23 24-Feb-23 PATHWAY E1
L2-PHL-1010 PATHWAY HL 2 24-Feb-23 27-Feb-23 PATHWAY HL
LEVEL 3 - COMMISSIONING
COMMI 20 18-Feb-23 13-Mar-23 13-Mar-23, LEVEL 3 - COMMISSIONING

Pathway A1 10 18-Feb-23 01-Mar-23 01-Mar-23, Pathway A1


L3-PA1-TRX TRANSFORMER & MV 2 18-Feb-23 20-Feb-23 TRANSFORMER & MV
L3-PA1-CHL CHILLER 1 18-Feb-23 18-Feb-23 CHILLER
L3-PA1-UPS UPS 2 18-Feb-23 20-Feb-23 UPS
L3-PA1-MDB MDB 3 21-Feb-23 23-Feb-23 MDB
L3-PA1-GEN GENERATOR 1 24-Feb-23 24-Feb-23 GENERATOR
L3-PA1-CRC FWU/CCU 1 01-Mar-23 01-Mar-23 FWU/CCU
Pathway B1 10 20-Feb-23 02-Mar-23 02-Mar-23, Pathway B1
L3-PB1-CHL CHILLER 1 20-Feb-23 20-Feb-23 CHILLER
L3-PB1-TRX TRANSFORMER & MV 2 21-Feb-23 22-Feb-23 TRANSFORMER & MV
L3-PB1-UPS UPS 2 21-Feb-23 22-Feb-23 UPS
L3-PB1-MDB MDB 3 24-Feb-23 27-Feb-23 MDB
L3-PB1-GEN GENERATOR 1 25-Feb-23 25-Feb-23 GENERATOR
L3-PB1-CRC FWU/CCU 1 02-Mar-23 02-Mar-23 FWU/CCU
Pathway C1 10 21-Feb-23 03-Mar-23 03-Mar-23, Pathway C1
L3-PC1-CHL CHILLER 1 21-Feb-23 21-Feb-23 CHILLER
L3-PC1-TRX TRANSFORMER & MV 2 23-Feb-23 24-Feb-23 TRANSFORMER & MV
L3-PC1-UPS UPS 2 23-Feb-23 24-Feb-23 UPS
L3-PC1-GEN GENERATOR 1 27-Feb-23 27-Feb-23 GENERATOR
L3-PC1-MDB MDB 3 28-Feb-23 02-Mar-23 MDB
L3-PC1-CRC FWU/CCU 1 03-Mar-23 03-Mar-23 FWU/CCU
Pathway D1 11 22-Feb-23 06-Mar-23 06-Mar-23, Pathway D1
L3-PD1-CHL CHILLER 1 22-Feb-23 23-Feb-23 CHILLER
L3-PD1-TRX TRANSFORMER & MV 2 25-Feb-23 27-Feb-23 TRANSFORMER & MV
L3-PD1-UPS UPS 2 25-Feb-23 27-Feb-23 UPS
L3-PD1-GEN GENERATOR 1 28-Feb-23 28-Feb-23 GENERATOR
L3-PD1-MDB MDB 3 03-Mar-23 06-Mar-23 MDB
L3-PD1-CRC FWU/CCU 1 04-Mar-23 04-Mar-23 FWU/CCU
Pathway E1 12 24-Feb-23 09-Mar-23 09-Mar-23, Pathway E1
L3-PE1-CHL CHILLER 1 24-Feb-23 25-Feb-23 CHILLER
L3-PE1-TRX TRANSFORMER & MV 2 28-Feb-23 01-Mar-23 TRANSFORMER & MV
L3-PE1-UPS UPS 2 28-Feb-23 01-Mar-23 UPS
L3-PE1-GEN GENERATOR 1 01-Mar-23 01-Mar-23 GENERATOR
L3-PE1-CRC FWU/CCU 1 06-Mar-23 06-Mar-23 FWU/CCU
L3-PE1-MDB MDB 3 07-Mar-23 09-Mar-23 MDB
Pathway HL 13 27-Feb-23 13-Mar-23 13-Mar-23, Pathway HL
L3-PHL-CHL CHILLER 1 27-Feb-23 28-Feb-23 CHILLER
L3-PHL-UPS UPS 2 28-Feb-23 01-Mar-23 UPS
L3-PHL-TRX TRANSFORMER & MV 2 02-Mar-23 03-Mar-23 TRANSFORMER & MV
L3-PHL-GEN GENERATOR 1 02-Mar-23 02-Mar-23 GENERATOR
L3-PHL-CRC FWU/CCU 1 07-Mar-23 07-Mar-23 FWU/CCU

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 8 of 9
Remaining Work
Critical Remaining Work
Milestone
Summary
PR13644-R7... : GDH- BUILDING 3- 3MW- DH1 +IDFs 1- 4... Date : 20-May-22
POW
Start :10-May-22 Finish :31-Jul-23
Activity ID Activity Name Remaining Start Finish 2022 2023
Duration
pr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
L3-PHL-MDB MDB 3 10-Mar-23 13-Mar-23 MDB
LEVEL 4 - PERFORMANCE
PERFO /LOAD TESTING 45 26-Jan-23 18-Mar-23 18-Mar-23, LEVEL 4 - PERFORMANCE /LOAD TE

UPS LOAD TESTING + CCU PERFORMANCE TEST 11 02-Mar-23 14-Mar-23 14-Mar-23, UPS LOAD TESTING + CCU PERFORM
IT UPS L4 8 02-Mar-23 10-Mar-23 10-Mar-23, IT UPS L4
L4-UPSA1-BC PA1 - UPS BATTERY CHARGING 2 02-Mar-23 03-Mar-23 PA1 - UPS BATTERY CHARGING
L4-UPSB1-BC PB1 - UPS BATTERY CHARGING 2 03-Mar-23 04-Mar-23 PB1 - UPS BATTERY CHARGING
L4-UPSA1-IT PA1 - UPS IT 1 04-Mar-23 04-Mar-23 PA1 - UPS IT
L4-UPSB1-IT PB1 - UPS IT 1 04-Mar-23 06-Mar-23 PB1 - UPS IT
L4-UPSC1-BC PC1 - UPS BATTERY CHARGING 2 04-Mar-23 07-Mar-23 PC1 - UPS BATTERY CHARGING
L4-UPSC1-IT PC1 - UPS IT 1 07-Mar-23 09-Mar-23 PC1 - UPS IT
L4-UPSD1-BC PD1 - UPS BATTERY CHARGING 2 07-Mar-23 09-Mar-23 PD1 - UPS BATTERY CHARGING
L4-UPSE1-BC PE1 - UPS BATTERY CHARGING 2 07-Mar-23 09-Mar-23 PE1 - UPS BATTERY CHARGING
L4-UPSHL-BC PHL - UPS BATTERY CHARGING 2 08-Mar-23 09-Mar-23 PHL - UPS BATTERY CHARGING
L4-UPSE1-IT PE1 - UPS IT 1 09-Mar-23 10-Mar-23 PE1 - UPS IT
L4-UPSD1-IT PD1 - UPS IT 1 09-Mar-23 10-Mar-23 PD1 - UPS IT
L4-UPSHL-IT PHL - UPS IT 1 10-Mar-23 10-Mar-23 PHL - UPS IT
ME UPS L4 8 06-Mar-23 14-Mar-23 14-Mar-23, ME UPS L4
L4-UPSPA1-ME PA1 - UPS ME 1 06-Mar-23 07-Mar-23 PA1 - UPS ME
L4-UPSPB1-ME PB1 - UPS ME 1 07-Mar-23 08-Mar-23 PB1 - UPS ME
L4-UPSPC1-ME PC1 - UPS ME 1 09-Mar-23 10-Mar-23 PC1 - UPS ME
L4-UPSPD1-ME PD1 - UPS ME 1 10-Mar-23 11-Mar-23 PD1 - UPS ME
L4-UPSPE1-ME PE1 - UPS ME 1 11-Mar-23 13-Mar-23 PE1 - UPS ME
L4-UPSPHL-ME PHL - UPS ME 1 13-Mar-23 14-Mar-23 PHL - UPS ME
GENERATOR LOAD TESTING 8 25-Feb-23 06-Mar-23 06-Mar-23, GENERATOR LOAD TESTING
L4-GENPA1 GENERATOR A1- Load Testing 3 25-Feb-23 28-Feb-23 GENERATOR A1- Load Testing
L4-GENPB1 GENERATOR B1- Load Testing 3 27-Feb-23 01-Mar-23 GENERATOR B1- Load Testing
L4-GENPC1 GENERATOR C1- Load Testing 3 28-Feb-23 02-Mar-23 GENERATOR C1- Load Testing
L4-GENPD1 GENERATOR D1- Load Testing 3 01-Mar-23 03-Mar-23 GENERATOR D1- Load Testing
L4-GENPE1 GENERATOR E1- Load Testing 3 02-Mar-23 04-Mar-23 GENERATOR E1- Load Testing
L4-GENPHL GENERATOR HL- Load Testing 3 03-Mar-23 06-Mar-23 GENERATOR HL- Load Testing
DATA HALLS LOAD TESTING 10 02-Mar-23 13-Mar-23 13-Mar-23, DATA HALLS LOAD TESTING
TCL4-HL-IDF2 IDF 2- HEAT LOAD TESTING 4 02-Mar-23 06-Mar-23 IDF 2- HEAT LOAD TESTING
TCL4-HL-IDF3 IDF 3- HEAT LOAD TESTING 4 04-Mar-23 08-Mar-23 IDF 3- HEAT LOAD TESTING
TCL4-HL-IDF4 IDF 4- HEAT LOAD TESTING 4 07-Mar-23 10-Mar-23 IDF 4- HEAT LOAD TESTING
TCL4-HL-DH1 DATA HALL 1-HEAT LOAD TESTING 5 08-Mar-23 13-Mar-23 DATA HALL 1-HEAT LOAD TESTING
GENERAL 45 26-Jan-23 18-Mar-23 18-Mar-23, GENERAL
L4GGENFAL-100 FIRE FIGHTING SYSTEM TESTING 21 26-Jan-23 18-Feb-23 FIRE FIGHTING SYSTEM TESTING
L4GENFAL-100 FIRE ALARM SYSTEM TESTING 21 27-Jan-23 20-Feb-23 FIRE ALARM SYSTEM TESTING
L4GENAHU-100 AHU TESTING & SYSTEM BALANCING 18 20-Feb-23 11-Mar-23 AHU TESTING & SYSTEM BALANCING
L4GENBMS-100 BMS SAT 12 02-Mar-23 15-Mar-23 BMS SAT
L4GENCPM-100 CPM SAT 12 02-Mar-23 15-Mar-23 CPM SAT
L4GENSAT-100 COOLING SYSTEM SAT 5 14-Mar-23 18-Mar-23 COOLING SYSTEM SAT
LEVEL 5 10 20-Mar-23 30-Mar-23 30-Mar-23, LEVEL 5

TCL5-GEN-ITS INTEGRATED SYSTEM TESTNG 5 20-Mar-23 24-Mar-23 INTEGRATED SYSTEM TESTNG


TCL5-GEN-ITS10 UPTIME TESTING 5 25-Mar-23 30-Mar-23 UPTIME TESTING
SNAGGING & HANDING
HAND OVER 47 25-Jan-23 31-Mar-23 31-Mar-23, SNAGGING & HANDING OVER

BLG31120 EARLY ACCESS to DH 1 0 25-Jan-23* EARLY ACCESS to DH 1


BLG31110 SNAGGING & HANDING OVER 40 02-Feb-23 30-Mar-23 SNAGGING & HANDING OVER
BLG31090 READY FOR SERVICE - DH 1 0 31-Mar-23 READY FOR SERVICE - DH 1
314 18-Jul-22 31-Jul-23 31-Jul-
DAY 2 - 9 MW

Actual Work DOC-01-BLN-01 ; TASK filter: All Activities Date Revision Checked Approved
Page 9 of 9