Professional Documents
Culture Documents
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A91640 Measurements & Start EPC for Fume extraction system (IF 0 0 07-Sep-23 07-Oct-22
any )
A1065 As-Built Finished 0 0 06-Dec-23 06-Jan-23
A91560 End of Logistics for ISBL (EP CONTRACTOR SOW) Delivery 0 0 15-Mar-23 21-May-22
- Minor Parts
Material Supply 113 113 28-Feb-23 20-Jun-23 30-Apr-22 29-May-22
A91570 End of ISBL (EP CONTRACTOR SOW) Delivery - Minor Parts 0 0 28-Feb-23* 30-Apr-22
A1937 Utilities & Energizing are Available (Powrer Station By 0 0 07-May-23 07-Jun-22
Wotech)
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A7640 Finish of Chemical and Additive Warehouse (Commissioned) 0 0 07-Jun-23 07-Jul-22
A7650 Finish of Rice straw Storage with Firefighting Network 0 0 07-Jun-23 07-Jul-22
(Commissioned)
A7680 Fuel Station (Commissioned) 0 0 07-Jun-23 07-Jul-22
A7670 Main Fire Station and HSE Building (Control Room & DCS) & 0 0 07-Jun-23 07-Jul-22
Firefighting - (Commissioned)
A91610 End of Mechanical Installation for EP CONTRACTOR SOW 0 0 06-Jul-23 07-Aug-22
A1980 Ready for Commissioning for ISBL (with Feedstock) 0 0 07-Aug-23 07-Sep-22
A91580 Finish MC for ISBL- Production Line (EP CONTRACTOR 0 0 07-Sep-23 07-Oct-22
SOW)
A3440 Finish for Commissioning for ISBL (with Feedstock) 0 0 07-Oct-23 07-Nov-22
PROFESSIONAL SERVICES
SER 176 176 08-May-23 06-Dec-23 08-May-22 05-Jan-23
A13900 Piping Bulk Delivery ( CS & GALV) @ Site 246 16 15-May-22 A 15-Jan-23 14-Dec-21 27-Dec-21
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
Stainless Steel Piping 225 16 05-Jun-22 A 15-Jan-23
Piping Valves (Manual - Gate, Check & Globe) 338 35 29-May-22 A 03-Feb-23
A92095 Piping Valves (Gate, Check & Globe) - Delivery @ Site 214 21 05-Jul-22 A 03-Feb-23
A92080 Piping Valves - (Gate, Check & Globe) - Inspection 223 7 29-May-22 A 06-Jan-23
A92090 Piping Valves - (Gate, Check & Globe) - RFS 223 7 05-Jun-22 A 13-Jan-23
A93640 Piping Bulk Delivery - HDPE - Feed Line @ Site 70 33 24-Nov-22 A 01-Feb-23
A16800 Industrial Water Treatment PKG- Delivery @ Site 211 33 06-Jul-22 A 01-Feb-23 17-Feb-22 18-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A17250 FF Equipment - Inspection 260 54 15-Jun-22 A 01-Mar-23 06-Apr-22 06-Apr-22
A92940 Capacitor Banks (Power Factor) - Manufacturing 407 123 21-Mar-22 A 02-May-23
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A74420 AC UPS - Inspection 344 6 15-Feb-22 A 24-Jan-23 10-Jan-22 10-Jan-22
A14020 Cable Trays - Delivery @ Site 311 41 17-Apr-22 A 15-Feb-23 16-Feb-22 02-Mar-22
Instrumentation (Control
(Contro System) 344 67 15-Mar-22 A 07-Mar-23 17-Dec-21 14-Apr-22
A18320 Control System (DCS) - Manufacturing 329 38 15-Mar-22 A 06-Feb-23 24-Dec-21 28-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A18350 Control System (DCS) - Delivery @ Site 7 7 09-Feb-23 15-Feb-23 31-Mar-22 14-Apr-22
Control valve & On / Off Valves 314 39 11-Apr-22 A 07-Feb-23 17-Dec-21 07-Apr-22
A18400 Control & On / Off Valves - Manufacturing 265 1 11-Apr-22 A 31-Dec-22 17-Dec-21 06-Mar-22
A18410 Control & On / Off Valves - Inspection 129 7 01-Sep-22 A 07-Jan-23 07-Mar-22 07-Mar-22
A18420 Control & On / Off Valves - RFS 132 7 08-Sep-22 A 17-Jan-23 08-Mar-22 08-Mar-22
A18430 Control & On / Off Valves - Delivery @ Site 86 21 14-Nov-22 A 07-Feb-23 09-Mar-22 07-Apr-22
A18510 Instrument Cables & Glands - Delivery @ Site 151 67 08-Oct-22 A 07-Mar-23 17-Feb-22 03-Mar-22
A74510 Instrument JB's & Bulk Material - RFS 143 1 01-Sep-22 A 21-Jan-23 16-Feb-22 16-Feb-22
A74450 Instrument JB's & Bulk Material - Delivery @ Site 173 30 01-Sep-22 A 20-Feb-23 17-Feb-22 03-Mar-22
A74509 Instrument JB's & Bulk Material - LC Open (PO 45) 0 0 15-Jan-23*
A18640 Fire Alarm & Detection - Manufacturing 406 58 17-Jan-22 A 26-Feb-23 06-Dec-21 10-Feb-22
A18650 Fire Alarm & Detection - Inspection 157 58 24-Sep-22 A 27-Feb-23 11-Feb-22 11-Feb-22
A18660 Fire Alarm & Detection - RFS 153 58 29-Sep-22 A 28-Feb-23 12-Feb-22 12-Feb-22
A18670 Fire Alarm & Detection - Delivery @ Site 152 58 01-Oct-22 A 01-Mar-23 13-Feb-22 27-Feb-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A18970 IP Telephone - Inspection 195 1 06-Dec-22 A 18-Jun-23 12-Apr-22 12-Apr-22
A87610 Data Network - Manufacturing 397 105 14-Mar-22 A 14-Apr-23 10-Dec-21 14-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A93125 Fiber Optical Cables - Delivery @ Site 65 1 29-Nov-22 A 08-Mar-23
A89290 Grating & Chq. Plates - Manufacturing 88 58 01-Dec-22 A 26-Feb-23 31-Dec-21 12-Jan-22
A89300 Grating & Chq. Plates - Inspection 80 58 10-Dec-22 A 27-Feb-23 13-Jan-22 13-Jan-22
A89310 Grating & Chq. Plates - RFS 80 58 11-Dec-22 A 28-Feb-23 14-Jan-22 14-Jan-22
A89250 Grating & Chq. Plates - Delivery @ Site 80 58 12-Dec-22 A 01-Mar-23 15-Jan-22 29-Jan-22
A89330 Piping Supports - Delivery @ Site 212 52 01-Aug-22 A 02-Mar-23 16-Dec-21 30-Dec-21
A94420 Reject Water Tank (GRP) - RFQ / Delivery @ Site 7 7 21-Feb-23 01-Mar-23
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A16198 Truck Scale - Delivery @ Site 61 61 31-Dec-22 01-Mar-23 14-Feb-22 15-Mar-22
A87650 Mobile Fuel Station - Delivery @ Site 31 31 02-Jan-23 01-Feb-23 17-Jun-22 01-Jul-22
A88610 Mirrors Station with gear motor - Group 5445 - Delivery @ 33 33 31-Dec-22 01-Feb-23 17-Mar-22 31-Mar-22
Site
Sound Cabinet & Noise
Nois Protection System 152 152 01-Jan-23 01-Jun-23 19-Dec-21 07-Apr-22
A88780 Sound Cabinet & Noise Protection System - RFQ / Bidding 24 24 01-Jan-23 01-Feb-23 19-Dec-21 30-Dec-21
A88790 Sound Cabinet & Noise Protection System - Technical 18 18 02-Feb-23 27-Feb-23 02-Jan-22 23-Jan-22
Evaluation Approval
A88800 Sound Cabinet & Noise Protection System - Commercial 6 6 28-Feb-23 07-Mar-23 24-Jan-22 31-Jan-22
Evaluation Approval
A88760 Sound Cabinet & Noise Protection System - PO 6 6 08-Mar-23 15-Mar-23 01-Feb-22 07-Feb-22
A88810 Sound Cabinet & Noise Protection System - Manufacturing 61 61 16-Mar-23 15-May-23 08-Feb-22 21-Mar-22
A88820 Sound Cabinet & Noise Protection System - Inspection 1 1 16-May-23 16-May-23 22-Mar-22 22-Mar-22
A88830 Sound Cabinet & Noise Protection System - RFS 1 1 17-May-23 17-May-23 23-Mar-22 23-Mar-22
A88770 Sound Cabinet & Noise Protection System - Delivery @ Site 15 15 18-May-23 01-Jun-23 24-Mar-22 07-Apr-22
A88940 Safety Barriers & Fences - RFQ / Bidding 18 18 01-Jan-23 24-Jan-23 19-Dec-21 30-Dec-21
A88950 Safety Barriers & Fences - Technical Evaluation Approval 12 12 25-Jan-23 09-Feb-23 02-Jan-22 31-Jan-22
A88960 Safety Barriers & Fences - Commercial Evaluation Approval 6 6 12-Feb-23 19-Feb-23 01-Feb-22 07-Feb-22
A88970 Safety Barriers & Fences - Manufacturing 60 60 28-Feb-23 28-Apr-23 15-Feb-22 28-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A88980 Safety Barriers & Fences - Inspection 1 1 29-Apr-23 29-Apr-23 29-Mar-22 29-Mar-22
A88990 Safety Barriers & Fences - RFS 1 1 30-Apr-23 30-Apr-23 30-Mar-22 30-Mar-22
A88930 Safety Barriers & Fences - Delivery @ Site 15 15 01-May-23 15-May-23 31-Mar-22 14-Apr-22
A89020 Electrical Secured Accesses Door and Flaps - GR-4599 - 18 18 01-Jan-23 24-Jan-23 06-Feb-22 17-Feb-22
RFQ / Bidding
A89030 Electrical Secured Accesses Door and Flaps - GR-4599 - 12 12 25-Jan-23 09-Feb-23 20-Feb-22 17-Mar-22
Technical Evaluation Approval
A89040 Electrical Secured Accesses Door and Flaps - GR-4599 - 6 6 12-Feb-23 19-Feb-23 20-Mar-22 24-Mar-22
Commercial Evaluation Approval
A89000 Electrical Secured Accesses Door and Flaps - GR-4599 - PO 6 6 20-Feb-23 27-Feb-23 27-Mar-22 31-Mar-22
A89050 Electrical Secured Accesses Door and Flaps - GR-4599 - 60 60 28-Feb-23 28-Apr-23 01-Apr-22 12-May-22
Manufacturing
A89060 Electrical Secured Accesses Door and Flaps - GR-4599 - 1 1 29-Apr-23 29-Apr-23 13-May-22 13-May-22
Inspection
A89070 Electrical Secured Accesses Door and Flaps - GR-4599 - 1 1 30-Apr-23 30-Apr-23 14-May-22 14-May-22
RFS
A89010 Electrical Secured Accesses Door and Flaps - GR-4599 - 15 15 01-May-23 15-May-23 15-May-22 29-May-22
Delivery @ Site
Refractory 135 33 03-Sep-22 A 01-Feb-23 05-Jan-22 19-Jan-22
MANUFACTURING (Workshop
(W Activities) 396 52 02-Oct-21 A 02-Mar-23 01-Sep-21 06-Apr-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
WSD Approval 351 8 02-Nov-21 A 09-Jan-23 02-Nov-21 29-Jan-22
A86930 WSD Approval & Issuance for Others 364 8 02-Nov-21 A 09-Jan-23 02-Nov-21 29-Jan-22
A80520 St. Str. Fab. - Supporting Outlet Tube Above Fan 5910 152 14 01-Aug-22 A 26-Jan-23 01-Jan-22 20-Jan-22
A85040 St. Str. Fab. - Platform of Gripper Carriage 152 22 01-Aug-22 A 26-Jan-23 01-Jan-22 15-Jan-22
A85050 St. Str. Fab. - Platform 1 Inside Production Warehouse 152 22 01-Aug-22 A 26-Jan-23 01-Jan-22 23-Jan-22
A85060 St. Str. Fab. - Platform 2 Inside Production Warehouse 152 22 01-Aug-22 A 26-Jan-23 01-Jan-22 23-Jan-22
A85070 St. Str. Fab. - Platform 3 Inside Production Warehouse 152 22 01-Aug-22 A 26-Jan-23 01-Jan-22 23-Jan-22
A85080 St. Str. Fab. - Platform 4 Inside Production Warehouse 152 22 01-Aug-22 A 26-Jan-23 01-Jan-22 23-Jan-22
A85090 St. Str. Fab. - Platform 5 Inside Production Warehouse 152 22 01-Aug-22 A 26-Jan-23 01-Jan-22 23-Jan-22
A72980 St. Str. Fab. - Warehouse For Spare Parts (Plot-1) 160 22 23-Jul-22 A 26-Jan-23 17-Mar-22 06-Apr-22
A91650 St. Str. Fab. - Matformer - 02nd Part 385 22 25-Oct-21 A 26-Jan-23
A85390 St. Str. Fab. - Steel Housing For Supporting Belt 282 22 23-Feb-22 A 26-Jan-23 19-Dec-21 19-Jan-22
A85400 St. Str. Fab. - Platforms above Fans (Sifter Area) 280 22 26-Feb-22 A 26-Jan-23 30-Dec-21 26-Jan-22
A85520 St. Str. Fab. - Platform for cyclone 4910 250 22 02-Apr-22 A 26-Jan-23 30-Dec-21 02-Mar-22
A85480 St. Str. Fab. - Steel Str For Filter 4911 And 4947 220 22 12-May-22 A 26-Jan-23 31-Jan-22 26-Mar-22
A85490 St. Str. Fab. - Filter SFDT 0512-D-01 22 22 31-Dec-22 26-Jan-23 31-Jan-22 28-Feb-22
A85510 St. Str. Fab. - Pipe Rack For Crude Gas Duct SENA11 313 22 17-Jan-22 A 26-Jan-23 31-Jan-22 10-Mar-22
A85530 St. Str. Fab. - Platform for Pneumatic 4976 259 22 22-Mar-22 A 26-Jan-23 31-Jan-22 27-Feb-22
A91660 St. Str. Fab. - Sifting Tower 2051 (02nd. Part) 400 35 22-Oct-21 A 11-Feb-23
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A91670 St. Str. Fab. - Dryer 64m (02nd Part) 327 22 31-Dec-21 A 26-Jan-23
A91680 St. Str. Fab. - Str. Str. for Sifter Area (02nd. Part - Other Str.) 280 22 25-Feb-22 A 26-Jan-23
A85580 St. Str. Fab. - For Pneumatic 2785 389 22 20-Oct-21 A 26-Jan-23 20-Nov-21 27-Dec-21
A85670 St. Str. Fab. - Refinery Structure 297 22 06-Feb-22 A 26-Jan-23 09-Dec-21 15-Feb-22
A85600 St. Str. Fab. - Conveyor 1557 End Support Structure 350 22 05-Dec-21 A 26-Jan-23 30-Dec-21 07-Mar-22
A85630 St. Str. Fab. - Steel Structure For Conveyor 1555 350 22 05-Dec-21 A 26-Jan-23 13-Jan-22 26-Mar-22
A85780 St. Str. Fab. - Glue Storage Shed 219 22 14-May-22 A 26-Jan-23 15-Jan-22 17-Mar-22
A85800 St. Str. Fab. - Pump Room Warehouse 273 22 06-Mar-22 A 26-Jan-23 15-Jan-22 12-Feb-22
A85830 St. Str. Fab. - 1322-FILTER SFDW 05&09-D-03 168 30 23-Jul-22 A 05-Feb-23 30-Dec-21 03-Feb-22
A85840 St. Str. Fab. - 1332-FILTER SFDW 05&09-D-03 160 30 01-Aug-22 A 05-Feb-23 30-Dec-21 03-Feb-22
A85850 St. Str. Fab. - 1342-FILTER SFDW 05&09-D-03 168 30 23-Jul-22 A 05-Feb-23 30-Dec-21 03-Feb-22
A85870 St. Str. Fab. - 4911-FILTER SFDW 05&12-D-05 168 30 23-Jul-22 A 05-Feb-23 30-Dec-21 03-Feb-22
A85880 St. Str. Fab. - 5911-FILTER SFDW 05&12-D-07 160 30 01-Aug-22 A 05-Feb-23 30-Dec-21 03-Feb-22
A91790 St. Str. Fab. - Platforms for Silos 160 30 01-Aug-22 A 05-Feb-23
A93510 St. Str. Fab. - Sound Cabient for 4550 30 30 31-Dec-22 05-Feb-23
A93530 St. Str. Fab. - Loading Arm for PMDI Tanks 30 30 31-Dec-22 05-Feb-23
A75710 Fabrication - Vessel (Drain Box) - Group 2310 / 2332 101 29 08-Oct-22 A 04-Feb-23 01-Jan-22 12-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
Ducts Fabrication 396 29 02-Oct-21 A 04-Feb-23 01-Sep-21 16-Mar-22
A75340 Fab.- Drier Duct (From Drier to High Efficiency Cyclone) - 410 29 02-Oct-21 A 04-Feb-23 01-Sep-21 27-Feb-22
Group 2420
Energy Plant Ducts 237 29 23-Apr-22 A 04-Feb-23 26-Jan-22 14-Feb-22
A79100 Fab.- Transport pipes ducts for dust - Group 7370 239 29 23-Apr-22 A 04-Feb-23 26-Jan-22 14-Feb-22
A75320 Fab.- Chutes - Group 2300 239 29 23-Apr-22 A 04-Feb-23 30-Dec-21 30-Jan-22
A75490 Fab.- Chutes, Baffel Plates, Funnel at matformer backdoor - 239 29 23-Apr-22 A 04-Feb-23 30-Dec-21 30-Jan-22
Group 4200
A75390 Fab.- Chutes & Blow Out Channel - Group 2600 239 29 23-Apr-22 A 04-Feb-23 15-Feb-22 16-Mar-22
A5105 Paving (Interlock) - Interlock - Related to SK 380 26 06-Feb-22 A 08-May-23 12-Oct-21 13-Jan-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A91470 Paving (Plot-3) - Interlock 26 26 27-Mar-23 30-Apr-23 02-Mar-22 29-Mar-22
A83840 Control Room - Civil - Doors Fab. & Erection 6 6 23-Mar-23 29-Mar-23 02-Jul-22 07-Jul-22
A83850 Control Room - Civil - Raised Floor 6 6 08-May-23 14-May-23 25-Jul-22 31-Jul-22
SR01A ( LV12 - TR
TR12) 146 24 19-Nov-22 A 06-May-23 19-Mar-22 12-Apr-22
A80840 SR01A - Civil - Doors Fab. & Erection 140 6 19-Nov-22 A 06-May-23 19-Mar-22 24-Mar-22
SR01B ( LV13 - TR
TR13) 146 24 19-Nov-22 A 06-May-23 19-Mar-22 19-Apr-22
A80870 SR01B - Civil - Doors Fab. & Erection 140 6 19-Nov-22 A 06-May-23 19-Mar-22 24-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
SR03 ( LV32 - TR3
TR32) 146 24 19-Nov-22 A 06-May-23 03-Apr-22 27-Apr-22
A80900 SR03 - Civil - Doors Fab. & Erection 140 6 19-Nov-22 A 06-May-23 03-Apr-22 09-Apr-22
A80930 SR04 - Civil - Doors Fab. & Erection 140 6 19-Nov-22 A 06-May-23 03-Apr-22 09-Apr-22
SR02A ( LV22 - TR
TR22) 146 24 19-Nov-22 A 06-May-23 19-Mar-22 16-May-22
A80960 SR02A - Civil - Doors Fab. & Erection 140 6 19-Nov-22 A 06-May-23 19-Mar-22 24-Mar-22
SR02B ( LV21 - TR
TR21) & ( LV23 - TR23) 146 24 19-Nov-22 A 06-May-23 19-Mar-22 23-May-22
A80990 SR02B - Civil - Doors Fab. & Erection 140 6 19-Nov-22 A 06-May-23 19-Mar-22 24-Mar-22
SR02C ( LV24 - TR
TR24) 146 24 19-Nov-22 A 06-May-23 19-Mar-22 30-May-22
A81020 SR02C - Civil - Doors Fab. & Erection 140 6 19-Nov-22 A 06-May-23 19-Mar-22 24-Mar-22
A81050 SR22 - Civil - Doors Fab. & Erection 140 6 19-Nov-22 A 06-May-23 19-Mar-22 24-Mar-22
Steel Structure Erection Works 474 151 23-Oct-21 A 06-Jul-23 23-Oct-21 17-Jul-22
A86051 St. Str. Erec. - Matformer (02nd. Part) 293 31 19-Mar-22 A 04-Mar-23 10-Feb-22 19-May-22
A86020 St. Str. Erec.- Press Steel Support 12 12 31-Dec-22 14-Jan-23 12-Mar-22 24-Mar-22
A86720 St. Str. Erect. - Steel Stair for Mat Reject Tunnel 72 12 22-Oct-22 A 14-Jan-23 17-Mar-22 30-Mar-22
A86690 St. Str. Erection - Warehouse For Spare Parts (Plot-1) 177 11 16-Jul-22 A 08-Feb-23 07-Apr-22 07-Jun-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A85960 St. Str. Erec. - Platform of Gripper Carriage 148 16 15-Oct-22 A 06-Apr-23 19-Apr-22 29-May-22
A85930 St. Str. Erec. - Supporting Outlet Tube Above Fan 5910 54 18 10-Dec-22 A 16-Feb-23 02-May-22 08-Jun-22
A7581 St. Str. Erection - Final MDF Storage (02nd. Part) 293 6 07-May-22 A 15-Apr-23 07-May-22 19-May-22
A85970 St. Str. Erec. - Platform 1 Inside Production Warehouse 154 6 06-Aug-22 A 02-Feb-23 18-May-22 14-Jun-22
A85980 St. Str. Erec.- Platform 2 Inside Production Warehouse 158 10 06-Aug-22 A 07-Feb-23 18-May-22 14-Jun-22
A85990 St. Str. Erec.- Platform 3 Inside Production Warehouse 157 9 06-Aug-22 A 06-Feb-23 18-May-22 14-Jun-22
A86000 St. Str. Erec.- Platform 4 Inside Production Warehouse 155 7 06-Aug-22 A 04-Feb-23 18-May-22 14-Jun-22
A86010 St. Str. Erec.- Platform 5 Inside Production Warehouse 156 8 06-Aug-22 A 05-Feb-23 18-May-22 14-Jun-22
A86070 St. Str. Erec. - Steel Housing For Supporting Belt 320 28 12-Feb-22 A 28-Feb-23 20-Jan-22 07-Feb-22
A86200 St. Str. Erec. - Platform for cyclone 4910 219 16 01-Jun-22 A 14-Feb-23 03-Mar-22 28-Apr-22
A86120 St. Str. Erec. - Pipe Bridge Steam-Pipe Item 7021 255 6 04-Apr-22 A 04-Feb-23 19-Mar-22 07-May-22
A89760 St. Str. Erec. - Dryer 64m (02nd. Part) 280 19 25-Apr-22 A 23-Mar-23 26-Mar-22 21-Apr-22
A86130 St. Str. Erec. - Pipe Bridge Steel Structure 138 8 01-Aug-22 A 09-Jan-23 29-Mar-22 28-Apr-22
A86190 St. Str. Erec. - Pipe Rack For Crude Gas Duct SENA11 259 13 15-May-22 A 15-Mar-23 31-Mar-22 28-Apr-22
A86111 St. Str. Erec. - Sifting Tower 2051 (02nd. Part) 273 14 06-Apr-22 A 27-Feb-23 06-Apr-22 02-Jun-22
A86061 St. Str. Erec. - St. Str. for Sifter (02nd. part - Other Str.) 271 7 02-May-22 A 20-Mar-23 02-May-22 08-Jun-22
A86210 St. Str. Erec. - Platform for Pneumatic 4976 73 15 19-Nov-22 A 13-Feb-23 22-May-22 07-Jun-22
A86160 St. Str. Erec. - Steel Str For Filter 4911 And 4947 148 6 13-Aug-22 A 02-Feb-23 25-May-22 11-Jun-22
A86170 St. Str. Erec. - Filter SFDT 0512-D-01 15 15 28-Jan-23 13-Feb-23 02-Jun-22 19-Jun-22
A86080 St. Str. Erec. - Platforms above Fans (Sifter Area) 224 1 15-May-22 A 02-Feb-23 23-Jun-22 11-Jul-22
A86250 St. Str. Erec. - Pipe Bridge Steel Structure 2782 300 12 20-Jan-22 A 15-Jan-23 25-Dec-21 29-Jan-22
A86241 St. Str. Erec. - Thermal Oil Heating (02nd. Part) 280 13 15-Feb-22 A 16-Jan-23 03-Jan-22 16-Jan-22
A89820 St. Str. Erec. - Platforms & Walkways 218 2 16-Apr-22 A 01-Jan-23 06-Feb-22 12-Feb-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A86221 St. Str. Erec. - Fuel Gas Cleaning (02nd. Part) 245 4 17-Mar-22 A 04-Jan-23 17-Feb-22 21-Mar-22
A89840 St. Str. Erec. - Burner Housing 84 6 01-Oct-22 A 05-Jan-23 08-Mar-22 14-Mar-22
A86260 St. Str. Erec. - For Pneumatic 2785 236 2 20-Apr-22 A 29-Jan-23 26-Apr-22 04-Jun-22
A86331 St. Str. Erec. - Warehouse For Refinery Building (02nd. Part) 37 37 31-Dec-22 13-Feb-23 15-Feb-22 26-Apr-22
A86350 St. Str. Erec. - Refinery Structure 294 8 02-Mar-22 A 16-Feb-23 16-Feb-22 14-May-22
A86360 St. Str. Erec. - For Conveyor 1394 183 2 01-Jun-22 A 01-Jan-23 08-Mar-22 30-Mar-22
A86290 St. Str. Erec. - Steel Platforms For Filter Area 5091 132 2 01-Aug-22 A 01-Jan-23 15-Mar-22 13-Apr-22
A86320 St. Str. Erec. - Storage Bin 227 3 06-Apr-22 A 02-Jan-23 06-Apr-22 23-May-22
A86310 St. Str. Erec. - Steel Structure For Conveyor 1555 154 12 13-Aug-22 A 09-Feb-23 10-Apr-22 15-May-22
A86300 St. Str. Erec. - Steel Structure For Conveyor 1557 130 4 06-Aug-22 A 03-Jan-23 08-May-22 06-Jun-22
A86270 St. Str. Erec. - Pipe Rack For Pneumatic 4970 & 5920 138 12 06-Aug-22 A 14-Jan-23 22-May-22 07-Jun-22
A86280 St. Str. Erec. - Conveyor 1557 End Support Structure 145 2 11-Aug-22 A 29-Jan-23 28-May-22 13-Jun-22
A86390 St. Str. Erec. - Service Platform For TKF1398 118 3 18-Aug-22 A 02-Jan-23 18-Jun-22 23-Jun-22
A86490 St. Str. Erec. - Steel Supports For Pump Room Pipes 243 15 01-Apr-22 A 18-Jan-23 16-Feb-22 15-Mar-22
A86480 St. Str. Erec. - Pump Room Warehouse 176 12 01-Oct-22 A 18-Apr-23 09-Mar-22 22-Mar-22
A86500 St. Str. Erec. - Steel Structure For Pump Room 243 3 01-Apr-22 A 17-Jan-23 09-Mar-22 22-Mar-22
A86460 St. Str. Erec. - Glue Storage Shed 267 5 19-Mar-22 A 01-Feb-23 19-Mar-22 07-Apr-22
A86471 St. Str. Erec.- Dryer Mixing Chamber (02nd. Part) 239 1 21-Mar-22 A 01-Jan-23 21-Mar-22 30-Mar-22
A86510 St. Str. Erec. - 1322-FILTER SFDW 05&09-D-03 154 4 13-Aug-22 A 09-Feb-23 17-Apr-22 02-May-22
A86520 St. Str. Erec. - 1332-FILTER SFDW 05&09-D-03 120 12 01-Oct-22 A 19-Feb-23 17-Apr-22 02-May-22
A86530 St. Str. Erec. - 1342-FILTER SFDW 05&09-D-03 154 4 13-Aug-22 A 09-Feb-23 17-Apr-22 02-May-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A86550 St. Str. Erec. - 4911-FILTER SFDW 05&12-D-05 120 12 01-Oct-22 A 19-Feb-23 26-Apr-22 14-May-22
A86540 St. Str. Erec. - 1532-FILTER SFDW 05&09-C-01 78 12 15-Oct-22 A 14-Jan-23 07-May-22 19-May-22
A86560 St. Str. Erec. - 5911-FILTER SFDW 05&12-D-07 120 12 01-Oct-22 A 19-Feb-23 16-May-22 29-May-22
A91800 St. Str. Erection - Platforms for Silos 168 8 01-Aug-22 A 14-Feb-23
A93500 St. Str. Erection - Sound Cabient for 4550 32 32 06-Feb-23 14-Mar-23
A93520 St. Str. Erection - Loading Arm for PMDI Tanks 32 32 06-Feb-23 14-Mar-23
A94330 St. Str. Erection - Pits Covers (Chemical & Reject) 12 12 31-Dec-22 14-Jan-23
A73000 Cladding Works - Final MDF Warehouse (Plot-1) 368 3 23-Oct-21 A 02-Jan-23 23-Oct-21 07-Jan-22
A86620 Cladding Works - Pump Room Warehouse (Plot-7) 32 32 19-Apr-23 30-May-23 23-Mar-22 30-Apr-22
A86630 Cladding Works - Glue Storage Shed (Plot-7) 20 20 02-Feb-23 25-Feb-23 09-Apr-22 07-May-22
A86700 Cladding Works - Warehouse For Spare Parts (Plot-1) 30 30 09-Feb-23 15-Mar-23 08-Jun-22 16-Jul-22
A58271 Piping Fab. - Fuel Gas (FG) - CS 135 57 01-Oct-22 A 08-Mar-23 01-Jan-22 31-May-22
A58291 Piping Fab. - ONSPEC-Fire Water Above Ground - CS 156 77 08-Oct-22 A 01-Apr-23 01-Jan-22 31-May-22
A58101 Piping Fab. - Steam System (ST) - CS 162 77 01-Oct-22 A 01-Apr-23 10-Feb-22 31-May-22
A58141 Piping Fab. - Thermal Oil System (TOH) - CS - DIN - Include 175 77 15-Sep-22 A 01-Apr-23 10-Feb-22 31-May-22
Other System
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A93150 Piping Fab. - Boiling and Fresh Water (WH) - SD 78 57 06-Dec-22 A 08-Mar-23
A93770 Piping Fab. - Hydrulic Oil Unit - (Other Systems) 52 52 01-Feb-23 02-Apr-23
A58311 Piping Erection - Compressed Air (AI) - CS / GALV - Include 162 84 01-Oct-22 A 09-Apr-23 03-Mar-22 23-Jun-22
Other System
A58331 Piping Erection - Fuel Gas (FG) - CS 95 84 18-Dec-22 A 09-Apr-23 15-Mar-22 06-Jul-22
A58351 Piping Erection - ONSPEC-Fire Water Above Ground - CS 149 91 01-Nov-22 A 18-Apr-23 15-Mar-22 06-Jul-22
A58091 Piping Erection - Thermal Oil System (TOH) - CS - DIN 179 91 27-Sep-22 A 18-Apr-23 21-Apr-22 06-Jul-22
A76910 Piping Erection - Steam System (ST) - CS 149 91 01-Nov-22 A 18-Apr-23 21-Apr-22 06-Jul-22
A93240 Piping Erection - Boiling and Fresh Water (WH) - SD 88 26 11-Dec-22 A 25-Mar-23
A93670 Piping Erection - Chemical Dosing Skid (Other Systems) 26 26 08-Mar-23 06-Apr-23
A93780 Piping Erection - Hydrulic Oil Unit - (Other Systems) 38 38 06-Mar-23 19-Apr-23
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
Electrical Works 342 149 01-Mar-22 A 04-Jul-23 09-Oct-21 06-Aug-22
A80770 Lighting Fixtures Erection 200 105 01-Oct-22 A 29-May-23 27-Mar-22 19-Jul-22
A79430 Earthing - Bars & C-Clamps Installation 252 9 15-Mar-22 A 10-Jan-23 19-Dec-21 18-Jun-22
A80060 Cable Pulling (EMG42 & LV42/ SR04) 12 12 03-Jun-23 15-Jun-23 02-Mar-22 29-Mar-22
SR01A ( LV12 - TR
TR12) 103 103 31-Dec-22 07-May-23 16-Mar-22 19-Apr-22
SR01B ( LV13 - TR
TR13) 103 103 31-Dec-22 07-May-23 23-Mar-22 27-Apr-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A80020 SR01B - Termination 78 78 31-Jan-23 07-May-23 06-Apr-22 27-Apr-22
A79880 SR04 - LV42 / LV43 & TR42 / TR43 & UPS42 / UPS 43 & 161 12 13-Aug-22 A 27-Feb-23 13-Mar-22 02-Apr-22
Bus Duct Installation
A79890 SR04 Cable Pulling 78 78 31-Dec-22 02-Apr-23 06-Apr-22 19-Apr-22
SR02A ( LV22 - TR
TR22) 103 103 31-Dec-22 07-May-23 13-Apr-22 23-May-22
SR02B ( LV21 - TR
TR21) & ( LV23 - TR23) 103 103 31-Dec-22 07-May-23 20-Apr-22 30-May-22
SR02C ( LV24 - TR
TR24) 103 103 31-Dec-22 07-May-23 28-Apr-22 06-Jun-22
Local Panels & JB's Installation 103 103 31-Dec-22 07-May-23 15-Feb-22 12-Jun-22
A82920 Local Panels & JB's Supports Fab, & erection 70 70 31-Dec-22 23-Mar-23 15-Feb-22 04-Apr-22
A80090 Local Panels & JB's - Cable Pulling 70 70 28-Jan-23 19-Apr-23 02-Mar-22 19-Apr-22
A80080 Local Panels & JB's Installation 70 70 02-Feb-23 29-Apr-23 05-Apr-22 29-May-22
A80100 Local Panels & JB's - Termination 70 70 09-Feb-23 07-May-23 19-Apr-22 12-Jun-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
Instrumentation Works (ISBL)
( 254 103 16-Jul-22 A 07-May-23 06-Feb-22 04-Aug-22
A7486 ISBL - Inst. - Cable Trays 208 57 16-Jul-22 A 08-Mar-23 03-Mar-22 21-Jun-22
A79630 ISBL - Inst. - J.B's & Local Pannels 132 91 19-Nov-22 A 18-Apr-23 05-Mar-22 22-Jun-22
A82910 ISBL - Field Instrument Tubing Installation 60 60 15-Feb-23 30-Apr-23 29-Jun-22 03-Aug-22
Telecommunication Wor
Works 151 133 19-Nov-22 A 06-Jul-23 16-Jan-22 28-Jul-22
A83420 ISBL - Fire Alarm - JB's Installation 60 60 22-Jan-23 02-Apr-23 28-Feb-22 14-Apr-22
A83440 ISBL - Fire Alarm - Cable Pulling 102 60 19-Nov-22 A 02-Apr-23 14-Mar-22 22-May-22
A5190 Control Room - DCS Panels Installation (Marching) 30 30 16-Feb-23 22-Mar-23 15-May-22 29-Jun-22
A83860 Control Room - Desk Top Installation 12 12 23-Mar-23 05-Apr-23 16-Jun-22 29-Jun-22
A83870 Control Room - Cable laying & Termination 22 22 06-Apr-23 07-May-23 02-Jul-22 24-Jul-22
A83460 ISBL - Public Address - Cable Trays Supports Fab. & 34 34 05-Feb-23 15-Mar-23 16-Jan-22 03-Mar-22
Erection
A83470 ISBL - Public Address - Cable Trays Installation 34 34 16-Mar-23 29-Apr-23 05-Mar-22 19-Apr-22
A83480 ISBL - Public Address - JB's Installation 34 34 16-Mar-23 29-Apr-23 05-Mar-22 18-May-22
A83490 ISBL - Public Address - Speakers & Flashers Installation 34 34 16-Mar-23 29-Apr-23 05-Mar-22 18-May-22
A83500 ISBL - Public Address - Cable Pulling 34 34 30-Apr-23 08-Jun-23 16-Apr-22 29-Jun-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
CCTV System 88 76 19-Nov-22 A 25-May-23 24-Mar-22 21-Jul-22
A83520 ISBL - CCTV - Cable Trays Supports Fab. & Erection 82 13 19-Nov-22 A 07-Mar-23 24-Mar-22 15-May-22
A83530 ISBL - CCTV - Cable Trays Installation 13 13 08-Mar-23 22-Mar-23 07-Apr-22 29-May-22
A83580 ISBL - Data Network & IP Telephone - Cable Trays Supports 8 8 12-Jun-23 20-Jun-23 02-Apr-22 30-Apr-22
Fab. & Erection
A83590 ISBL - Data Network & IP Telephone - Cable Trays 8 8 12-Jun-23 20-Jun-23 16-Apr-22 06-Jun-22
Installation
A83600 ISBL - Data Network & IP Telephone - JB's Installation 8 8 21-Jun-23 04-Jul-23 30-Apr-22 19-Jun-22
A83610 ISBL - Data Network & IP Telephone - IP Telephone 8 8 21-Jun-23 04-Jul-23 30-Apr-22 19-Jun-22
Installation
A83620 ISBL - Data Network & IP Telephone - Cable Pulling 8 8 21-Jun-23 04-Jul-23 02-May-22 20-Jun-22
A83630 ISBL - Data Network & IP Telephone - Termination 8 8 24-Jun-23 06-Jul-23 19-May-22 05-Jul-22
A79730 ISBL - F&G - J.B's & Local Pannels 58 58 31-Dec-22 09-Mar-23 02-Jun-22 14-Jul-22
A78070 Fire Fighting Erection - Production Line 266 103 29-Jun-22 A 07-May-23 02-Apr-22 06-Aug-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A93850 HVAC - Switch Room SR02C 84 84 31-Dec-22 09-Apr-23
A80590 Thermal Insulation application for Group 4720 154 106 10-Dec-22 A 02-Jul-23 21-May-22 02-Jun-22
A80640 Thermal Insulation application for Group 4910 106 106 04-Feb-23 12-Jun-23 03-Jul-22 06-Aug-22
A80650 Thermal Insulation application for Group 4920 106 106 04-Feb-23 12-Jun-23 03-Jul-22 06-Aug-22
Prod. Line Installation ( PTJ scope of Supply) 359 151 10-Mar-22 A 06-Jul-23 01-Feb-22 15-Aug-22
A89780 Erection - High Efficiency Cyclone - Group 2420 29 6 08-Dec-22 A 10-Jan-23 02-Apr-22 16-May-22
Pneumatic Conveyor
Conve Ducts 359 111 01-Apr-22 A 17-May-23 26-Mar-22 15-Aug-22
A76580 Erection - Pipe ducts with bends and flanges - Group 3905 154 16 23-Jul-22 A 19-Jan-23 26-Mar-22 17-Apr-22
A79760 Erection - Duct Works & exhaust Pipes - Chipper Line (1) - 233 5 01-Apr-22 A 05-Jan-23 26-Apr-22 28-Jun-22
Group 1242 &1243
A79800 Erection - Duct Works & exhaust Pipes - Chipper Line (3) - 232 4 01-Apr-22 A 04-Jan-23 02-May-22 04-Jul-22
Group 1282 &1283
A89730 Erection - Duct Works & Pipes with bends and flanges - 136 6 01-Aug-22 A 05-Jan-23 02-May-22 27-Jun-22
Group 2615 / 2616
A79780 Erection - Duct Works & exhaust Pipes - Chipper Line (2) - 232 4 01-Apr-22 A 04-Jan-23 07-May-22 05-Jul-22
Group 1262 &1263
A89970 Erection - Pipe ducts with bends and flanges - Group 7112 / 212 32 06-Aug-22 A 09-Apr-23 25-May-22 09-Jul-22
7131
A89920 Erection - Duct Work, Pipes & Hoods - Group 4550 290 16 15-May-22 A 18-Apr-23 06-Jun-22 23-Jul-22
A89810 Erection - Duct Work & Pipes - Group 4975 187 17 01-Aug-22 A 08-Mar-23 19-Jun-22 04-Aug-22
A89750 Erection - Pipe ducts with bends and flanges - Group 5910 242 19 17-May-22 A 26-Feb-23 20-Jun-22 31-Jul-22
A89930 Erection - Duct Work & Pipes - Group 4910 156 26 01-Aug-22 A 31-Jan-23 21-Jun-22 01-Aug-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A89740 Erection - Duct Work & Pipes - Group 4920 154 24 01-Aug-22 A 29-Jan-23 23-Jun-22 06-Aug-22
A89800 Erection - Duct Work & Pipes - Group 4946 155 25 01-Aug-22 A 31-Jan-23 02-Jul-22 13-Aug-22
A89950 Erection - Pipe ducts with bends and flanges - Group 5917 186 12 06-Aug-22 A 12-Mar-23 02-Jul-22 24-Jul-22
A80320 Erection - Pipe ducts with bends and flanges - Group 2770 177 6 01-Aug-22 A 25-Feb-23 06-Jul-22 19-Jul-22
A80322 Erection - Pipe ducts with bends and flanges - Group 2780 12 12 31-Dec-22 14-Jan-23 10-Jul-22 23-Jul-22
A89940 Erection - Duct Work & Pipes - Group 4970 314 19 15-May-22 A 17-May-23 11-Jul-22 10-Aug-22
A89960 Erection - Pipe ducts with bends and flanges - Group 5920 217 20 25-May-22 A 05-Feb-23 11-Jul-22 15-Aug-22
A80510 Erection - Pipe ducts with bends and flanges - Group 1531 138 18 13-Aug-22 A 22-Jan-23 13-Jul-22 04-Aug-22
A89900 Erection - Pipe ducts with bends and flanges - Group 2782 198 10 13-Aug-22 A 30-Mar-23 19-Jul-22 01-Aug-22
A89910 Erection - Pipe ducts with bends and flanges - Group 2785 150 6 13-Aug-22 A 05-Feb-23 19-Jul-22 01-Aug-22
A89770 Erection - Dryer Duct (From Drier to High Efficiency Cyclone) - 309 9 10-Mar-22 A 12-Mar-23 13-Mar-22 21-May-22
Group 2420
Crude Gas Ducts 261 12 09-Jun-22 A 29-Apr-23 15-Jun-22 23-Jul-22
A89790 Erection - Crude gas duct - Group 7410 274 12 09-Jun-22 A 29-Apr-23 15-Jun-22 23-Jul-22
A90000 Erection - Connection for hot gas duct to quench chamber 3 3 18-Jan-23 22-Jan-23 01-Feb-22 03-Feb-22
and emergency stack - Group 7370
A90020 Erection - Duct work from ambient air fan to quench 1 1 09-Apr-23 10-Apr-23 05-Feb-22 05-Feb-22
chamber - Group 7385.060
A90050 Erection - Duct work from thermal oil heater to mixing 156 0 13-Aug-22 A 11-Feb-23 23-Feb-22 26-Feb-22
chamber - Group 3785.065
A90120 Erection - Duct work - outlet duct with vertical flanges to dust 3 3 07-Feb-23 11-Feb-23 23-Feb-22 26-Feb-22
collector - Group 7390
A90030 Erection - Duct work from ambient air fan to mixing chamber 128 0 13-Aug-22 A 09-Jan-23 15-Mar-22 16-Mar-22
- Group 7385.065
A90040 Erection - Duct work from mixing chamber to cyclones - 128 0 13-Aug-22 A 09-Jan-23 15-Mar-22 16-Mar-22
Group 7385.065
A89980 Erection - Duct work from combustion air fan to the burner - 251 1 09-Jun-22 A 30-Mar-23 29-Mar-22 31-Mar-22
Group 7370.061
A89990 Erection - Duct work from cooling air fan to the burner - 3 3 11-Apr-23 15-Apr-23 29-Mar-22 31-Mar-22
Group 7370.062
A90010 Erection - Transport pipes ducts for dust - Group 7370 3 3 27-Mar-23 30-Mar-23 29-Mar-22 31-Mar-22
A90100 Erection - Duct work from thermal oil heater to thermal oil 273 7 25-May-22 A 11-Apr-23 30-Mar-22 03-Apr-22
heater fan - Group 7390
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A90110 Erection - Duct work from thermal oil heater fan to mixing 271 7 25-May-22 A 09-Apr-23 30-Mar-22 03-Apr-22
chamber - Group 7390
A90070 Erection - Duct work from dust collector (Cyclones) to Main ID 202 6 13-Aug-22 A 04-Apr-23 06-Apr-22 14-Apr-22
fan - Group 7385.080
A90080 Erection - Duct work from the Main ID fan to Dryer Mixing 219 2 23-Apr-22 A 10-Jan-23 23-Apr-22 28-Apr-22
Chamber - Group 7385.090
A90090 Erection - Duct work from the Main ID fan to Start up Stack - 190 1 01-Jun-22 A 10-Jan-23 23-Apr-22 28-Apr-22
Group 7385.090
Safety Barriers & F
Fence 41 41 16-May-23 06-Jul-23 16-Apr-22 04-Jul-22
A76810 Erection - Fences for drive station 41 41 16-May-23 06-Jul-23 16-Apr-22 11-Jun-22
A76820 Erection - Fences for the Forming line 41 41 16-May-23 06-Jul-23 16-Apr-22 03-Jul-22
A76840 Erection - Fences for Trimming Saw 41 41 16-May-23 06-Jul-23 16-Apr-22 10-May-22
A80460 Erection - Fence for intermediate belt station 41 41 16-May-23 06-Jul-23 16-Apr-22 21-Jun-22
A80620 Erection- Electrical secured accesses door and flaps - 41 41 16-May-23 06-Jul-23 30-May-22 04-Jul-22
GR-4599
Utilities & Buildings 937 251 07-Jul-20 A 07-Sep-23 07-Jul-20 07-Dec-22
Buildings / Warehouses including all work ( Civil , Electrical ,Telecom ,etc.) 485 188 05-Apr-22 A 06-Jul-23 14-Dec-21 01-Nov-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A78080 Fire Fighting Erection - Substation 38 38 16-Mar-23 04-May-23 24-Mar-22 12-May-22
A74870 Data Network & IP Telephone - Substation Bldg. 12 12 14-Jun-23 02-Jul-23 30-Apr-22 14-May-22
A78870 Substation - UPS & Batteries Installation 95 12 12-Nov-22 A 14-Jan-23 01-Mar-22 07-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A78090 Fire Fighting Erection - Liquid Chemical Warehouse 30 30 16-Mar-23 20-Apr-23 08-May-22 11-Jun-22
A74910 Data Network & IP Telephone - Chemical WH 12 12 14-Jun-23 02-Jul-23 08-Jun-22 21-Jun-22
Internal Finishing W
Works (Civil) 76 30 26-Nov-22 A 05-Feb-23 10-Mar-22 27-Mar-22
A81120 Doors & Windows - Scale Room 60 12 26-Nov-22 A 05-Feb-23 21-Mar-22 27-Mar-22
Equipment Installation
Installat 24 24 02-Mar-23 29-Mar-23 11-Apr-22 07-May-22
A78040 Scale Room - Truck Scale Erection 24 24 02-Mar-23 29-Mar-23 11-Apr-22 07-May-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A74840 Fire Alarm - Scale Room 24 24 02-Mar-23 29-Mar-23 11-Apr-22 07-May-22
A7530 Data Network & IP Telephone - Scale Room 12 12 14-Jun-23 02-Jul-23 30-Apr-22 07-Jun-22
A5258 Fuel Station Erection & Commissioning 0 0 02-Feb-23 02-Feb-23 31-May-22 07-Jul-22
Main Fire Station and HSE Building 189 147 15-Oct-22 A 02-Jul-23 05-Feb-22 07-Jun-22
Internal Finishing W
Works (Civil) 137 15 29-Oct-22 A 17-Jan-23 14-Feb-22 03-Apr-22
A81320 Doors & Windows - HSE Building 89 6 26-Nov-22 A 17-Jan-23 07-Mar-22 20-Mar-22
A81360 External Plumbing Works (Sewage) - HSE Building 12 12 31-Dec-22 14-Jan-23 21-Mar-22 03-Apr-22
A81370 External Painting - HSE Building 114 12 15-Oct-22 A 29-Jan-23 04-Apr-22 07-May-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A74790 Fire Alarm - HSE Bldg. 30 30 02-Mar-23 05-Apr-23 04-Apr-22 07-May-22
A74780 Data Network & IP Telephone - HSE Bldg. 12 12 14-Jun-23 02-Jul-23 30-Apr-22 07-Jun-22
Equipment Installation
Installat 43 21 03-Dec-22 A 24-Jan-23 29-Mar-22 11-Apr-22
A72900 St. Str. Erection - Air Comp. Shed 81 6 22-Oct-22 A 24-Jan-23 12-Apr-22 18-Apr-22
A73070 Cladding Works - Air Comp. Shed 6 6 26-Jan-23 01-Feb-23 19-Apr-22 21-Apr-22
A74960 Fire Alarm - Air Compressor Shed 12 12 02-Mar-23 15-Mar-23 23-Apr-22 30-Apr-22
A74980 Public Address - Air Compressor Shed 11 11 16-Mar-23 28-Mar-23 23-Apr-22 30-Apr-22
A74990 Data Network & IP Telephone - Air Compressor Shed 10 10 21-Jun-23 06-Jul-23 30-Apr-22 09-May-22
A73030 Cladding Works - Industrial Water Pump Station 6 6 31-Dec-22 05-Jan-23 05-Apr-22 07-Apr-22
A74670 Elect - Industrial Water Pump Station 12 12 07-Jan-23 21-Jan-23 09-Apr-22 14-Apr-22
A73060 Cladding Works - Potable Water Pump Station 6 6 31-Dec-22 05-Jan-23 05-Apr-22 07-Apr-22
A74700 Elect - Potable Water Pump Station 12 12 07-Jan-23 21-Jan-23 09-Apr-22 14-Apr-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
Reject Water Pump Station
Sta 21 21 31-Dec-22 20-Jan-23 05-Apr-22 20-May-22
A73040 Cladding Works - Reject Water Pump Station 6 6 31-Dec-22 05-Jan-23 05-Apr-22 07-Apr-22
Equipment Installation
Installat 21 21 31-Dec-22 20-Jan-23 09-May-22 20-May-22
A74680 Elect - Reject Water Pump Station 12 12 03-Jan-23 17-Jan-23 09-Apr-22 14-Apr-22
A72880 Erection of Industrial Water Treatment PKG 84 20 12-Nov-22 A 18-Feb-23 23-Mar-22 02-May-22
A93460 Precom. & Commissioning for Industrial Water Treatment 35 35 18-Feb-23 29-Mar-23
PKG
Telecom. 94 94 09-Mar-23 06-Jul-23 05-Apr-22 09-May-22
A75000 Fire Alarm - Industrial Water Treatment PKG. 18 18 09-Mar-23 29-Mar-23 05-Apr-22 02-May-22
A75010 CCTV - Industrial Water Treatment PKG. 18 18 09-Mar-23 29-Mar-23 05-Apr-22 02-May-22
A75020 Public Address - Industrial Water Treatment PKG. 18 18 16-Mar-23 05-Apr-23 05-Apr-22 02-May-22
A75030 Data Network & IP Telephone - Industrial Water Treatment 10 10 21-Jun-23 06-Jul-23 30-Apr-22 09-May-22
PKG.
Fire Pump Shed 18 18 31-Dec-22 21-Jan-23 07-May-22 30-May-22
Equipment Installation
Installat 18 18 31-Dec-22 21-Jan-23 07-May-22 19-May-22
A73080 Cladding Works - Fire Pump Shed 6 6 31-Dec-22 05-Jan-23 28-May-22 30-May-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A87180 New Switch Room - Civil - Doors Fab. & Erection 139 6 26-Nov-22 A 06-May-23 19-Mar-22 24-Mar-22
A87190 New Switch Room - Civil - Raised Floor 12 12 18-Apr-23 06-May-23 31-May-22 13-Jun-22
A91760 St. Str. Erection - Transformer Shed beside New SR 127 4 18-Aug-22 A 14-Jan-23
A87210 New Switch Room - Cable Pulling 90 90 31-Dec-22 16-Apr-23 17-May-22 30-May-22
Internal Finishing W
Works (Civil) 76 30 26-Nov-22 A 05-Feb-23 28-Aug-22 01-Oct-22
A81750 Ceramics / Tiles - Main Security Room 18 18 31-Dec-22 21-Jan-23 28-Aug-22 17-Sep-22
A81760 Doors & Windows - Main Security Room 60 12 26-Nov-22 A 05-Feb-23 18-Sep-22 01-Oct-22
A74710 Fire Alarm - Main Security Bldg. 15 15 02-Mar-23 19-Mar-23 16-Oct-22 01-Nov-22
A74730 Public Address - Main Security Bldg. 15 15 16-Mar-23 02-Apr-23 16-Oct-22 01-Nov-22
A74740 Data Network & IP Telephone - Main Secuirty Bldg. 12 12 14-Jun-23 02-Jul-23 16-Oct-22 01-Nov-22
Internal Finishing W
Works (Civil) 76 30 26-Nov-22 A 05-Feb-23 28-Aug-22 01-Oct-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A81850 Ceramics / Tiles - Security Room 18 18 31-Dec-22 21-Jan-23 28-Aug-22 17-Sep-22
A81860 Doors & Windows - Security Room 60 12 26-Nov-22 A 05-Feb-23 18-Sep-22 01-Oct-22
A74820 Data Network & IP Telephone - Secuirty Bldg. 12 12 14-Jun-23 02-Jul-23 16-Oct-22 01-Nov-22
Internal Finishing W
Works (Civil) 40 18 26-Nov-22 A 21-Jan-23 25-Aug-22 28-Sep-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
HVAC 73 15 19-Nov-22 A 16-Mar-23 13-Oct-22 30-Oct-22
Finishing Works (C
(Civil) 62 62 07-Mar-23 24-May-23 25-Jul-22 01-Nov-22
A82280 Paving for OSBL - Tanks (Interlock) 89 53 03-Dec-22 A 18-Mar-23 20-Apr-22 05-Jul-22
A78480 Roads Activities - Interlock 239 203 03-Dec-22 A 07-Sep-23 18-May-22 07-Dec-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A78490 Roads Activities - Gravel Finish 239 203 03-Dec-22 A 07-Sep-23 18-May-22 07-Dec-22
A90970 Cut Works - Potable Water Network 174 30 16-Jul-22 A 05-Feb-23 15-Feb-22 28-Mar-22
A90980 Bedding Layer - Potable Water Network 114 114 31-Dec-22 20-May-23 22-Feb-22 04-Apr-22
A90990 Piping Laying (Poly-propylene) - Potable Water Network 50 50 25-Mar-23 27-May-23 01-Mar-22 11-Apr-22
A91000 Valve Bit - Potable Water Network 50 50 05-Apr-23 07-Jun-23 08-Mar-22 18-Apr-22
A91010 Pressure Test - Potable Water Network 15 15 08-Jun-23 25-Jun-23 19-Apr-22 26-Apr-22
A91030 Cut Works - Fire Fighting Network 283 56 03-Apr-22 A 07-Mar-23 01-Jan-22 27-Apr-22
A78050 HDPE - Piping Erection - Fire Fighting System (Rice Straw 279 76 05-May-22 A 30-Mar-23 15-Jan-22 16-May-22
Warehouse / Plant)
A91050 Valve Bit & Hydrant erection - Fire Fighting Network 60 60 19-Jan-23 30-Mar-23 22-Jan-22 23-May-22
A78060 Hydro-test - Fire Fighting System (Rice Straw Warehouse) 172 84 01-Oct-22 A 24-Apr-23 24-May-22 06-Jun-22
A91100 Laying P/L - Sewer Network 210 50 01-Aug-22 A 28-Feb-23 07-Mar-22 25-Jun-22
A78010 Backfilling & Insulation - Sewer Network 60 60 07-Jan-23 19-Mar-23 28-Mar-22 17-Jul-22
A5680 Covering & Accessories - Sewer Network 35 35 21-Feb-23 02-Apr-23 04-Apr-22 24-Jul-22
A91150 Cut Works - Storm Network 200 39 01-Jul-22 A 15-Feb-23 07-Feb-22 28-May-22
A91180 Manholes (Concrete) - Storm Network 200 39 02-Jul-22 A 15-Feb-23 28-Feb-22 18-Jun-22
A91190 Laying P/L - Storm Network 226 65 01-Aug-22 A 18-Apr-23 07-Mar-22 25-Jun-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A91210 Testing - Storm Network 35 35 15-Mar-23 29-Apr-23 21-Mar-22 10-Jul-22
A91220 Backfilling & Insulation - Storm Network 168 35 22-Oct-22 A 07-May-23 28-Mar-22 17-Jul-22
A91230 Covering & Accessories - Storm Network 35 35 22-Mar-23 07-May-23 04-Apr-22 24-Jul-22
A77970 Cut Works - Electrical Network 306 29 03-Feb-22 A 04-Feb-23 16-Dec-21 27-Jan-22
A78000 Insulation & Backfilling - Electrical Network 286 28 25-Feb-22 A 02-Feb-23 07-Jan-22 17-Feb-22
Instrumentation Network
Ne 179 35 23-Jul-22 A 11-Feb-23 30-Jan-22 12-Mar-22
A91290 Laying P/L - Instrument Network 181 35 23-Jul-22 A 11-Feb-23 30-Jan-22 12-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
Piping Fabrication & P
Painting 25 25 16-Jan-23 14-Feb-23 13-Jan-22 17-Apr-22
A79380 Control & Safety Valves Erection 6 6 19-Apr-23 29-Apr-23 16-Jun-22 27-Jun-22
A79470 Earthing - Bars & C-Clamps Installation 149 62 04-Oct-22 A 28-Mar-23 31-Jan-22 23-Apr-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A80740 Lightning Protection Works 98 41 24-Dec-22 A 19-Apr-23 24-Feb-22 14-Jun-22
A7345 Lighting Poles & Fixtures Installation 188 110 01-Oct-22 A 15-May-23 01-Mar-22 19-Jul-22
A79000 Lighting Fixtures & JB's Installation 210 110 01-Oct-22 A 10-Jun-23 27-Mar-22 14-Aug-22
A79530 OSBL - Inst. - Field Instrument Calibrations 31 31 31-Dec-22 06-Feb-23 01-Mar-22 04-Apr-22
A79520 OSBL - Inst. - J.B's & Local Pannels 30 30 21-Feb-23 27-Mar-23 05-Mar-22 07-Apr-22
A7485 OSBL- Inst. - Cable Trays Installation 31 31 31-Dec-22 06-Feb-23 22-Mar-22 12-May-22
A79560 OSBL - F&G - Cable Trays Installation 12 12 31-Dec-22 14-Jan-23 16-Apr-22 18-May-22
A79570 OSBL - F&G - J.B's & Local Pannels 59 59 15-Feb-23 29-Apr-23 16-Apr-22 18-May-22
Outdoor - Telecommunication
Telecommunic 151 151 01-Oct-22 A 06-Jul-23 29-Jan-22 07-Jun-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
A83160 OSBL - Fire Alarm - JB's Installation 40 40 22-Jan-23 09-Mar-23 28-Feb-22 05-Apr-22
A83180 OSBL - Fire Alarm - Cable Pulling 40 40 31-Dec-22 16-Feb-23 14-Mar-22 19-Apr-22
A83200 OSBL - Public Address - Cable Trays Supports Fab. & 52 52 16-Mar-23 21-May-23 29-Jan-22 03-Mar-22
Erection
A83210 OSBL - Public Address - Cable Trays Installation 52 52 23-Mar-23 28-May-23 05-Mar-22 07-Apr-22
A83220 OSBL - Public Address - JB's Installation 52 52 16-Mar-23 21-May-23 05-Mar-22 07-Apr-22
A83230 OSBL - Public Address - Speakers & Flashers Installation 52 52 16-Mar-23 21-May-23 05-Mar-22 07-Apr-22
A83240 OSBL - Public Address - Cable Pulling 52 52 28-Mar-23 01-Jun-23 16-Mar-22 19-Apr-22
A83260 OSBL - CCTV - Cable Trays Supports Fab. & Erection 119 16 01-Oct-22 A 01-Mar-23 08-Mar-22 23-Mar-22
A83270 OSBL - CCTV - Cable Trays Installation 122 16 01-Oct-22 A 05-Mar-23 24-Mar-22 09-Apr-22
A83360 OSBL - Data Network & IP Telephone - Cable Pulling 10 10 15-Jun-23 02-Jul-23 07-Apr-22 17-May-22
A83340 OSBL - Data Network & IP Telephone - JB's Installation 10 10 15-Jun-23 02-Jul-23 30-Apr-22 07-Jun-22
A83350 OSBL - Data Network & IP Telephone - IP Telephone 10 10 15-Jun-23 02-Jul-23 30-Apr-22 07-Jun-22
Installation
A83370 OSBL - Data Network & IP Telephone - Termination 10 10 21-Jun-23 06-Jul-23 30-Apr-22 07-Jun-22
Milestones Mechanical/Automation
Mechanical/A 0 0 06-Jul-23 06-Jul-23 07-Aug-22 07-Aug-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
Group -1000 - Rice Straw Preparation 187 55 10-Jul-22 A 11-Mar-23 15-Jan-22 10-Feb-22
000017 Installation receiving conveyor EQ No. 1110.1 181 3 23-Jul-22 A 04-Mar-23 15-Jan-22 20-Jan-22
000018 Installation receiving conveyor EQ No. 1120.1 184 3 23-Jul-22 A 07-Mar-23 18-Jan-22 24-Jan-22
000019 Installation receiving conveyor EQ No. 1130.1 187 3 23-Jul-22 A 11-Mar-23 22-Jan-22 27-Jan-22
000021 Installation receiving conveyor EQ No. 1150.1 145 3 10-Jul-22 A 09-Jan-23 29-Jan-22 03-Feb-22
000023 Installation receiving conveyor EQ No. 1151.1 137 3 23-Jul-22 A 12-Jan-23 05-Feb-22 10-Feb-22
000075 Positioning and assembly from filter unit EQ No. 1312 136 5 23-Jul-22 A 12-Jan-23 01-Jun-22 12-Jun-22
(1342?)
000078 Positioning and assembly from filter unit EQ No. 1322 165 5 23-Jul-22 A 16-Feb-23 08-Jun-22 19-Jun-22
000081 Positioning and assembly from filter unit EQ No. 1332 175 5 23-Jul-22 A 28-Feb-23 08-Jun-22 19-Jun-22
000082 Positioning and final assembly from trough chain conveyor 233 0 17-May-22 A 01-Mar-23 20-Jun-22 26-Jun-22
EQ No. 1398.05
000083 Install moisture analyzer EQ No. 1395.1 3 3 02-Mar-23 05-Mar-23 27-Jun-22 29-Jun-22
000089 Positioning and final assembly from belt conveyor EQ No. 174 1 04-Jun-22 A 07-Jan-23 01-Jun-22 07-Jun-22
1552.01
000102 Positioning and assembly from filter unit EQ No. 1532 119 5 18-Aug-22 A 19-Jan-23 21-Jun-22 02-Jul-22
000107 Refiner system 1 EQ No. 2310 377 107 10-Feb-22 A 10-May-23 22-Jan-22 16-May-22
000108 Refiner system 2 EQ No. 2332 377 107 10-Feb-22 A 10-May-23 05-Feb-22 30-May-22
000111 Dryer Area EQ No. 2420 351 72 31-Jan-22 A 30-Mar-23 05-Mar-22 02-Jun-22
000113 Positioning from troughed belt conveyor under the blenders 187 14 09-Jul-22 A 28-Feb-23 19-Feb-22 24-Mar-22
(Part 1) / After finishing Sifter system complete the install
Blender Line (1) 10 5 17-Dec-22 A 11-Jan-23 03-Mar-22 21-Mar-22
000117 Positioning and final assembly from blender (1) EQ No. 2551 8 3 17-Dec-22 A 09-Jan-23 03-Mar-22 06-Mar-22
000118 Positioning and connecting drive with blender EQ No. 10 2 17-Dec-22 A 11-Jan-23 07-Mar-22 08-Mar-22
2551.601
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000121 Install moisture analyzer EQ No. 2548.1 3 3 07-Jan-23 09-Jan-23 19-Mar-22 21-Mar-22
000125 Positioning and final assembly from blender (2) EQ No. 2552 11 3 17-Dec-22 A 12-Jan-23 06-Mar-22 08-Mar-22
000126 Positioning and connecting drive with blender EQ No. 13 2 17-Dec-22 A 15-Jan-23 09-Mar-22 10-Mar-22
2552.601
Blender Line (3) 20 8 17-Dec-22 A 15-Jan-23 08-Mar-22 26-Mar-22
000132 Positioning and final assembly from blender (3) EQ No. 2553 11 3 17-Dec-22 A 12-Jan-23 08-Mar-22 10-Mar-22
000133 Positioning and connecting drive with blender EQ No. 13 2 17-Dec-22 A 15-Jan-23 12-Mar-22 13-Mar-22
2553.601
000136 Install moisture analyzer EQ No. 2549.1 3 3 07-Jan-23 09-Jan-23 23-Mar-22 26-Mar-22
000140 Positioning and final assembly from blender (4) EQ No. 2554 11 3 17-Dec-22 A 12-Jan-23 10-Mar-22 13-Mar-22
000141 Positioning and connecting drive with blender EQ No. 13 2 17-Dec-22 A 15-Jan-23 14-Mar-22 15-Mar-22
2554.601
Group -2600 - Straw Fibre
Fibr Sifter System 182 24 09-Jul-22 A 04-Feb-23 25-Apr-22 27-Jun-22
000164 Connect pipes between sifter and cyclone above matformer 166 10 09-Jul-22 A 04-Feb-23 25-Apr-22 19-Jun-22
000169 Connect pipes between sifter and cyclone above matformer 153 10 09-Jul-22 A 18-Jan-23 03-May-22 27-Jun-22
Group -2700 - HP Blower unit with Filter 525 66 10-Apr-22 A 23-Mar-23 28-Jun-22 01-Aug-22
000172 Positioning and assembly from filter unit EQ No. 2771 64 4 19-Nov-22 A 18-Feb-23 28-Jun-22 02-Jul-22
000175 HP rotary airlock with drive EQ No. 2783 4 4 31-Dec-22 A 10-Jan-23 10-Jul-22 13-Jul-22
000177 Positioning from pulverizer EQ No. 2784 3 3 31-Dec-22 A 09-Jan-23 20-Jul-22 23-Jul-22
000179 Positioning and assembly from round filter for Silo (7140) EQ 286 2 10-Apr-22 A 23-Mar-23 27-Jul-22 01-Aug-22
No. 2786
Group -3200 - Glue Preparation
Prepa System 513 84 02-Mar-22 A 13-Apr-23 24-Apr-22 18-May-22
000195 Tanks/bins of emulsion. Installation level and align EQ No. 6 6 07-Jan-23 12-Jan-23 24-Apr-22 30-Apr-22
3226.102
000196 Tanks/bins - accessories EQ No. 3226.103 0 0 12-Jan-23 30-Apr-22
000186 PMDI-storage and transfer system. Installation of piping for 0 0 07-Jan-23 07-May-22
glueing system EQ No. 3211
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000187 Raw glue preparation system (PTJ's scope) EQ No. 3213 0 0 07-Jan-23 07-May-22
000189 Water-storage and transfer system consist of following 2 2 07-Jan-23 08-Jan-23 08-May-22 09-May-22
components EQ No. 3215
000190 Components transfer system. Installation level and align EQ 319 81 22-Mar-22 A 12-Apr-23 10-May-22 10-May-22
No. 3215.201
000191 Components transfer system. Installation level and align EQ 337 1 02-Mar-22 A 13-Apr-23 11-May-22 11-May-22
No. 3215.205
000192 Hardener preparation system (PTJ's scope) EQ No. 3216 0 0 13-Apr-23 11-May-22
000182 Danger and information signs EQ No. 3200.1 2 2 07-Jan-23 08-Jan-23 17-May-22 18-May-22
000200 Danger and information signs EQ No. 3300.1 2 2 09-Jan-23 10-Jan-23 19-May-22 21-May-22
000233 Dynamic mixer (PMDI & Polyol) EQ No. 3380 0 0 17-Jan-23 22-May-22
000234 Dynamic mixer. Installation level and align EQ No. 3380.211 6 6 11-Jan-23 17-Jan-23 22-May-22 28-May-22
000217 Components dosing system to dynamic mixer. Installation 43 2 05-Nov-22 A 08-Jan-23 24-May-22 25-May-22
level and align EQ No. 3315.211
000202 Components dosing system to dynamic mixer. Installation 143 2 23-Jul-22 A 19-Jan-23 25-May-22 26-May-22
level and align EQ No. 3311.211
000208 Dosing polyol EQ No. 3312 0 0 22-Jan-23 25-May-22
000209 Components dosing system to dynamic mixer. Installation 55 2 05-Nov-22 A 22-Jan-23 25-May-22 26-May-22
level and align EQ No. 3312.211
000235 Dynamic mixer. Installation level and align EQ No. 3380.212 6 6 18-Jan-23 24-Jan-23 25-May-22 31-May-22
000218 Components dosing system to dynamic mixer. Installation 45 2 05-Nov-22 A 10-Jan-23 26-May-22 28-May-22
level and align EQ No. 3315.212
000225 Dosing emulsion EQ No. 3326 0 0 07-Jan-23 26-May-22
000246 Pneumatic conveyor EQ No. 3905 134 1 20-Jul-22 A 07-Jan-23 26-May-22 26-May-22
000203 Components dosing system to dynamic mixer. Installation 145 2 23-Jul-22 A 22-Jan-23 28-May-22 29-May-22
level and align EQ No. 3311.212
000210 Components dosing system to dynamic mixer. Installation 2 2 23-Jan-23 24-Jan-23 28-May-22 29-May-22
level and align EQ No. 3312.212
000219 Components dosing system to dynamic mixer. Installation 47 2 05-Nov-22 A 12-Jan-23 29-May-22 30-May-22
level and align EQ No. 3315.213
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000236 Dynamic mixer. Installation level and align EQ No. 3380.213 6 6 25-Jan-23 31-Jan-23 29-May-22 04-Jun-22
000204 Components dosing system to dynamic mixer. Installation 147 2 23-Jul-22 A 24-Jan-23 30-May-22 31-May-22
level and align EQ No. 3311.213
000211 Components dosing system to dynamic mixer. Installation 59 2 05-Nov-22 A 26-Jan-23 30-May-22 31-May-22
level and align EQ No. 3312.213
000220 Components dosing system to dynamic mixer. Installation 49 2 05-Nov-22 A 15-Jan-23 31-May-22 01-Jun-22
level and align EQ No. 3315.214
000205 Components dosing system to dynamic mixer. Installation 149 2 23-Jul-22 A 26-Jan-23 01-Jun-22 02-Jun-22
level and align EQ No. 3311.214
000212 Components dosing system to dynamic mixer. Installation 61 2 05-Nov-22 A 29-Jan-23 01-Jun-22 02-Jun-22
level and align EQ No. 3312.214
000237 Dynamic mixer. Installation level and align EQ No. 3380.214 6 6 01-Feb-23 07-Feb-23 01-Jun-22 07-Jun-22
000221 Components dosing system to refiner system. Installation 51 2 05-Nov-22 A 17-Jan-23 02-Jun-22 04-Jun-22
level and align EQ No. 3315.215
000239 Glue injection EQ No. 3390 0 0 12-Jan-23 02-Jun-22
000241 Glue injection pipes (Connecting parts for refiner) EQ No. 0 0 12-Jan-23 02-Jun-22
3390.21
000242 PMDI injection pipes (Components glue distribution Refiner 1 0 0 12-Jan-23 02-Jun-22
& 2) EQ No. 3390.54
000243 Blowline Components (2 blowline, 2 nozzle) EQ No. 3390.55 0 0 12-Jan-23 02-Jun-22
000213 Raw glue dosing system (PTJ's scope) EQ No. 3313 0 0 29-Jan-23 02-Jun-22
000206 Components dosing system to refiner system. Installation 151 2 23-Jul-22 A 29-Jan-23 04-Jun-22 05-Jun-22
level and align EQ No. 3311.215
000222 Components dosing system to refiner system. Installation 53 2 05-Nov-22 A 19-Jan-23 05-Jun-22 06-Jun-22
level and align EQ No. 3315.216
000207 Components dosing system to refiner system. Installation 285 2 18-Feb-22 A 31-Jan-23 06-Jun-22 07-Jun-22
level and align EQ No. 3311.216
000223 Hardener dosing system (PTJ's scope) EQ No. 3316 0 0 19-Jan-23 06-Jun-22
000230 Components dosing system. Installation level and align EQ 2 2 01-Feb-23 02-Feb-23 08-Jun-22 09-Jun-22
No. 3330.21
000231 Protection agent EQ No. 3331 0 0 05-Feb-23 11-Jun-22
000232 Components dosing system. Installation level and align EQ 2 2 04-Feb-23 05-Feb-23 11-Jun-22 12-Jun-22
No. 3331.21
000247 Structural steelwork, cyclone separator, piping, bends, 0 0 05-Feb-23 12-Jun-22
flanges, chutes, burst disc, etc. PTJ's scope EQ No. 3905
Supplies and Services to be provided by the buyer 26 26 07-Jan-23 05-Feb-23 20-Apr-22 12-Jun-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000249 Appendix No.3 list of supplies and services to be provided by 0 0 07-Jan-23 20-Apr-22
the PTJ
000250 Installation of pipes and connection between all components 0 0 05-Feb-23 12-Jun-22
000259 Steel structure of forming line (PTJ´s scope of supply) has to 323 12 19-Mar-22 A 15-Apr-23 09-Feb-22 19-May-22
be installed parallel with Siempelkamp equipment
000260 Structure with stairs, hand rails, gratings for level of forming 251 12 19-Mar-22 A 19-Jan-23 09-Feb-22 19-May-22
head, equalising unit, matformer, distributor chute and
000279 Explosion protection system negative pressure flaps EQ No. 45 4 05-Nov-22 A 10-Jan-23 04-Apr-22 07-Apr-22
4210.13
000280 Explosion vents isolation sys. EQ No. 4210.781 4 4 11-Jan-23 15-Jan-23 09-Apr-22 12-Apr-22
000281 Explosion protection system EQ No. 4220.7 53 4 05-Nov-22 A 19-Jan-23 13-Apr-22 17-Apr-22
000282 Customer supply explosion protection EQ No. 4220.73 1 1 21-Jan-23 21-Jan-23 18-Apr-22 18-Apr-22
000290 Guide of pre- press (between lower and upper part) EQ No. 48 1 29-Oct-22 A 07-Jan-23 20-Apr-22 20-Apr-22
4330.14
000292 Main hydraulic cylinder (for lift up upper part of pre- press) 42 1 05-Nov-22 A 07-Jan-23 23-Apr-22 23-Apr-22
EQ No. 4330.21
000293 Gear boxes for pre- press (incl. accessories gear box) EQ 44 2 05-Nov-22 A 09-Jan-23 24-Apr-22 25-Apr-22
No. 4330.53
000295 Air evacuation area EQ No. 4330.4 132 1 23-Jul-22 A 07-Jan-23 27-Apr-22 30-Apr-22
000296 Side walls evacuation area EQ No. 4330.45 49 1 29-Oct-22 A 08-Jan-23 01-May-22 01-May-22
000297 Side walls of pre- press EQ No. 4330.16 52 3 29-Oct-22 A 11-Jan-23 02-May-22 04-May-22
000298 Limit switches, sensors EQ No. 4330.853 53 1 29-Oct-22 A 12-Jan-23 05-May-22 05-May-22
000301 Hydraulic connecting pipes EQ No. 4332.7 1 1 08-Jan-23 08-Jan-23 24-Apr-22 24-Apr-22
000303 Saw unit (consist of gantry across the forming line, 2 3 3 14-Jan-23 16-Jan-23 07-May-22 10-May-22
moveable carriage, 2 trimming units) level and align EQ No.
4336
000304 Collecting hogger for extraction system EQ No. 4336.2 1 1 01-Feb-23 01-Feb-23 11-May-22 11-May-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000305 Limit switch of saw unit EQ No. 4336.853 1 1 02-Feb-23 02-Feb-23 12-May-22 12-May-22
000308 Tables for ancillary equipment (pre-assemble level and align 147 3 02-Aug-22 A 06-Feb-23 14-May-22 22-May-22
according metering points) EQ No. 4310.411
000309 Metal detector EQ No. 4342 1 1 07-Feb-23 07-Feb-23 23-May-22 23-May-22
000310 Density gauge mat scanner NEO EQ No. 4341 2 2 08-Feb-23 09-Feb-23 24-May-22 25-May-22
000312 Disintegrating rollers with drives level and align EQ No. 2 2 08-Feb-23 09-Feb-23 26-May-22 28-May-22
4350.014
000313 Reject mat hopper with track for reject mat nose level and 4 4 09-Feb-23 13-Feb-23 29-May-22 01-Jun-22
align EQ No. 4350.01
Drive station 48 48 13-Feb-23 10-Apr-23 01-Jun-22 13-Jun-22
000316 Frame of drive station. Assembling level and align EQ No. 9 9 27-Mar-23 05-Apr-23 02-Jun-22 11-Jun-22
4310.52
000317 Gearbox for drive station level and align EQ No. 4310.511 2 2 06-Apr-23 08-Apr-23 12-Jun-22 13-Jun-22
000318 Servo drive (forming belt) EQ No. 4310.561 2 2 09-Apr-23 10-Apr-23 12-Jun-22 13-Jun-22
000320 Intermediate belt station EQ No. 4380.1 4 4 11-Apr-23 15-Apr-23 14-Jun-22 18-Jun-22
000323 Servo motor EQ No. 4380.161 135 1 29-Oct-22 A 18-Apr-23 21-Jun-22 21-Jun-22
000324 Limit switches, sensors EQ No. 4380.853 1 1 19-Apr-23 19-Apr-23 22-Jun-22 22-Jun-22
000325 Belt for intermediate station (installation after welding and 1 1 20-Apr-23 20-Apr-23 23-Jun-22 23-Jun-22
grinding works) EQ No. 4380.11
Forming line accessories
accessorie 0 0 20-Apr-23 20-Apr-23 23-Jun-22 23-Jun-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000330 Peak detector upstream metal detector between trimming 2 2 04-Feb-23 05-Feb-23 14-May-22 15-May-22
saw and metal detector EQ No. 4328.01
000331 Peak detector on intermediate belt EQ No. 4382.01 3 3 20-Apr-23 23-Apr-23 23-Jun-22 25-Jun-22
000332 Infrared moisture analyzer EQ No. 4322.1 1 1 24-Apr-23 24-Apr-23 26-Jun-22 26-Jun-22
000333 Belt spraying device EQ No. 4327.2 4 4 25-Apr-23 29-Apr-23 27-Jun-22 30-Jun-22
000334 Mat spraying device EQ No. 4344.2 4 4 30-Apr-23 03-May-23 02-Jul-22 05-Jul-22
000336 Measuring of the ContiRoll press and forming line 12 12 20-Apr-23 03-May-23 06-Jul-22 17-Jul-22
000338 Lay on and vulcanize forming line belt EQ No. 4310.6 6 6 27-Apr-23 03-May-23 18-Jul-22 23-Jul-22
000343 Safety equipment / fences for trimming saw EQ No. 0 0 02-Feb-23 12-May-22
4336.852
000345 Safety equipment / fences for drive station EQ No. 4310.852 0 0 10-Apr-23 13-Jun-22
000346 Safety equipment / fences for intermediate belt station EQ 0 0 20-Apr-23 23-Jun-22
No. 4380.852
000341 Safety equipment / fences for forming line EQ No. 4399.352 0 0 03-May-23 05-Jul-22
000342 Safety sensors for forming line EQ No. 4399.353 0 0 03-May-23 05-Jul-22
000340 Technical safety requirements for mat former EQ No. 0 0 03-May-23 23-Jul-22
4220.852
Group -4520 - ContiRoll® (8' x 48,7 m) 348 156 20-Mar-22 A 06-Jul-23 16-Jan-22 02-Aug-22
000353 Insolations tunnel bottom EQ No. 4520.334 221 14 23-Jul-22 A 20-Apr-23 26-Jan-22 13-Feb-22
000362 Installation of "Sandwich" pulling device EQ No. 4520.351 4 4 12-Jan-23 16-Jan-23 02-Mar-22 05-Mar-22
000366 Pulling of hot plates (As a Sandwich with press cylinders) EQ 4 4 17-Jan-23 21-Jan-23 13-Mar-22 16-Mar-22
No. 4520.117
000367 Press cylinder EQ No. 4520.113 4 4 22-Jan-23 25-Jan-23 13-Mar-22 16-Mar-22
000368 Press cylinder mounting parts EQ No. 4520.114 166 2 02-Jul-22 A 28-Jan-23 13-Mar-22 16-Mar-22
000383 Gearbox mounting parts for main drives and for chain drives 163 0 13-Aug-22 A 07-Mar-23 14-Mar-22 14-Mar-22
EQ No. 4520.335
000384 Mounting gearboxes with torque support on lower and upper 162 1 15-Aug-22 A 08-Mar-23 15-Mar-22 17-Mar-22
outfeed drum EQ No. 4520.36
000369 Installation of isolation for hot plates EQ No. 4520.137 4 4 29-Jan-23 01-Feb-23 17-Mar-22 20-Mar-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000385 Mounting gearboxes for chain drives EQ No. 4520.312 3 3 09-Mar-23 12-Mar-23 19-Mar-22 21-Mar-22
000386 Mounting main drives and chain drives EQ No. 4520.361 3 3 13-Mar-23 15-Mar-23 22-Mar-22 24-Mar-22
000371 Infeed head (Installation from bottom and upper part) EQ 5 5 02-Feb-23 07-Feb-23 24-Mar-22 28-Mar-22
No. 4520.21
000387 Infeed adjusting system EQ No. 4520.216 2 2 16-Mar-23 18-Mar-23 26-Mar-22 27-Mar-22
000373 Installation of Infeed frame left and right EQ No. 4520.319 4 4 08-Feb-23 12-Feb-23 30-Mar-22 03-Apr-22
000389 Infeed steel sheet covering EQ No. 4520.212 1 1 23-Mar-23 23-Mar-23 02-Apr-22 02-Apr-22
000390 Placement of pneumatic cabinets for Outfeed-Site EQ No. 1 1 25-Mar-23 25-Mar-23 03-Apr-22 03-Apr-22
4520.314
000374 Upper belt tracking unit (Installation with substructure) EQ 3 3 13-Feb-23 15-Feb-23 04-Apr-22 06-Apr-22
No. 4520.326
000391 Pneumatic piping for Roller-rod-chain (Chain -tensioning, 8 8 26-Mar-23 03-Apr-23 04-Apr-22 13-Apr-22
-greasing, -cleaning) EQ No. 4520.314
000375 Infeed drum (Installation from bottom and top drum) EQ No. 3 3 16-Feb-23 19-Feb-23 07-Apr-22 09-Apr-22
4520.321
000376 Installation of walk ways and handrails EQ No. 4520.325 193 2 25-Jun-22 A 21-Feb-23 10-Apr-22 19-Apr-22
000392 Pneumatic piping for steel belt tracking unit EQ No. 6 6 04-Apr-23 10-Apr-23 14-Apr-22 20-Apr-22
4520.314
000393 Pneumatic piping for brake of main drive EQ No. 4520.314 4 4 11-Apr-23 15-Apr-23 21-Apr-22 25-Apr-22
000394 Lubrication piping for Chain spanner (Bearings) EQ No. 9 9 16-Apr-23 25-Apr-23 26-Apr-22 05-May-22
4520.314
000380 Hydraulic pipes EQ No. 4520.118 12 12 22-Feb-23 07-Mar-23 05-May-22 17-May-22
000395 Placement of oil aggregate for Lubrication system EQ No. 1 1 26-Apr-23 26-Apr-23 07-May-22 07-May-22
4520.328
000396 Lubrication piping for Roller-rod and Roller-rod-chain EQ No. 9 9 27-Apr-23 07-May-23 08-May-22 17-May-22
4520.328
000398 Transfer roller conveyor EQ No. 4520.331 2 2 08-May-23 09-May-23 28-May-22 30-May-22
000408 Roller-rod chain install EQ No. 4520.317 5 5 11-Jun-23 15-Jun-23 28-May-22 02-Jun-22
000399 Remaining parts (Signboard) EQ No. 4520.125 1 1 10-May-23 10-May-23 31-May-22 31-May-22
000400 Automation (Sensors and encoder) EQ No. 4520.4 2 2 11-May-23 13-May-23 01-Jun-22 02-Jun-22
000401 Roller-rod control (Sensors for infeed and oufeed) EQ No. 2 2 14-May-23 15-May-23 04-Jun-22 06-Jun-22
4520.253
000409 Roller-rod install (10.350 Pieces delivered) EQ No. 4520.317 12 12 17-Jun-23 29-Jun-23 04-Jun-22 16-Jun-22
000402 Limit switches and position encoder (Bolt control, chain 2 2 16-May-23 17-May-23 07-Jun-22 09-Jun-22
guide tracking, steel belt tracking unit outfeed etc.) EQ No. 4
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000403 Temperature sensor (PT100) for hot plates and bearings of 2 2 18-May-23 20-May-23 11-Jun-22 12-Jun-22
infeed and outfeed drums EQ No. 4520.415
000404 Mounting parts position encoder (Steel belt tracking unit for 6 6 21-May-23 27-May-23 13-Jun-22 19-Jun-22
infeed drum and in the middle of the press, infeed head, c
000410 Steel belt pulling device EQ No. 4520.35 3 3 01-Jul-23 03-Jul-23 18-Jun-22 20-Jun-22
000405 Mounting parts position encoder (Press distance) EQ No. 6 6 28-May-23 03-Jun-23 20-Jun-22 26-Jun-22
4520.424
000411 Steel belt pulling EQ No. 4520.363 3 3 04-Jul-23 06-Jul-23 21-Jun-22 23-Jun-22
000412 Steel belt repair welding apparatus EQ No. 4579 0 0 01-Jul-23 25-Jun-22
000413 Steel belt welding EQ No. 4520.363 6 6 01-Jul-23 06-Jul-23 25-Jun-22 30-Jun-22
000406 Measuring frame for control system 6 6 04-Jun-23 10-Jun-23 27-Jun-22 03-Jul-22
000414 Isolation tunnel complement after Steel belt welding 5 5 02-Jul-23 06-Jul-23 02-Jul-22 07-Jul-22
000407 Steelbelt surface control system EQ No. 4520.33 5 5 02-Jul-23 06-Jul-23 04-Jul-22 09-Jul-22
000416 Safety fences along the ContiRoll-press EQ No. 4520.329 17 17 18-Jun-23 06-Jul-23 09-Jul-22 26-Jul-22
Hydraulic for ContiRoll® (8'x 48,7 m) 212 4 13-Aug-22 A 02-May-23 16-Jan-22 12-May-22
000418 Positioning of the hydraulic unit EQ No. 4540.01 1 1 27-Apr-23 29-Apr-23 16-Jan-22 16-Jan-22
000420 Connection hydraulic pipes between hydraulic unit and 212 3 13-Aug-22 A 02-May-23 09-May-22 12-May-22
ContiRoll-press EQ No. 4540.013
Steel belt cleaning device
devic (Bravo-Tech) 10 10 26-Jun-23 06-Jul-23 25-Jun-22 12-Jul-22
000422 Positioning and installation of steel belt cleaning device EQ 10 10 26-Jun-23 06-Jul-23 25-Jun-22 05-Jul-22
No. 4571
000423 Installation of release agent application device EQ No. 4572 6 6 01-Jul-23 06-Jul-23 06-Jul-22 12-Jul-22
000425 Positioning of the valve stations for fire extinguishing EQ No. 1 1 02-May-23 03-May-23 18-Jun-22 18-Jun-22
4592
000426 Fire extinguishing pipes and fire detection along the 1 1 03-May-23 04-May-23 19-Jun-22 30-Jun-22
ContiRoll-Press EQ No. 4592
000427 Fire extinguishing pipes and fire detection in the heating 9 9 04-May-23 15-May-23 02-Jul-22 13-Jul-22
pipe channel EQ No. 4592
000428 Fire extinguishing pipes and fire detection in the secondary 10 10 03-May-23 15-May-23 14-Jul-22 26-Jul-22
heating room EQ No. 4592
000429 Connection fire extinguishing pipes between vale stations 6 6 08-May-23 15-May-23 27-Jul-22 02-Aug-22
and ContiRoll-press EQ No. 4592
Secondary heating 276 37 20-Mar-22 A 19-Feb-23 16-Apr-22 02-Jun-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000434 Connecting heating pipes (Secondary site) EQ No. 4720.13 253 15 20-Mar-22 A 24-Jan-23 16-Apr-22 11-May-22
000435 Connecting heating pipes (Primary site) EQ No. 4720.11 267 21 21-Mar-22 A 11-Feb-23 11-May-22 18-May-22
000436 Connecting purging pipes and pneumatic pipe for 271 3 21-Mar-22 A 15-Feb-23 18-May-22 31-May-22
rapid-acting valve (Schematic plan) EQ No. 4720.002
000437 Pressure test of secondary heating circuit EQ No. 4720 3 3 15-Feb-23 19-Feb-23 31-May-22 02-Jun-22
000440 Installation of extraction system EQ No. 4550 278 17 15-Mar-22 A 19-Feb-23 10-Apr-22 28-May-22
000443 Noise protected cabin for radial fan EQ No. 4550.01 0 0 01-Jun-23 10-Apr-22
000450 Installation of modular component accessories EQ No. 197 17 26-May-22 A 25-Jan-23 14-Apr-22 25-Apr-22
4550.016
000453 Connecting of air pipes EQ No. 4550.006 139 2 16-Jul-22 A 08-Jan-23 14-Apr-22 04-May-22
000454 Connecting of water pipes EQ No. 4550.007 23 18 17-Dec-22 A 26-Jan-23 14-Apr-22 04-May-22
000458 Connecting pipes to WESP EQ No. 4550.097 65 24 05-Nov-22 A 02-Feb-23 14-Apr-22 11-May-22
000446 Container for discharge Sedimentation tank EQ No. 4550.01 0 0 07-Jan-23 17-Apr-22
000451 Installation screens EQ No. 4550.013 202 1 22-May-22 A 26-Jan-23 26-Apr-22 28-Apr-22
000452 Installation of chutes for screens EQ No. 4550.009 152 3 23-Jul-22 A 30-Jan-23 30-Apr-22 03-May-22
000456 Installation of water injection system (nozzle lances) EQ No. 4 4 07-Jan-23 10-Jan-23 16-May-22 19-May-22
4550.008
000457 Installation of sensors EQ No. 4550.014 4 4 11-Jan-23 15-Jan-23 21-May-22 24-May-22
Group -4900 - Extraction System for Forming Line, Trimming and DD-saw 525 114 11-Jun-22 A 20-May-23 05-Jul-22 15-Aug-22
000467 Positioning and assembly from round filter (DD- and trimming 206 39 11-Jun-22 A 21-Feb-23 05-Jul-22 10-Jul-22
saw) EQ No. 4971
000469 Positioning and assembly from round filter EQ No. 4976 157 3 01-Aug-22 A 16-Feb-23 13-Jul-22 18-Jul-22
000471 Radials fan with drive for press fume extraction EQ No. 4998 0 0 16-Feb-23 18-Jul-22
( Hold By EP Contractor )
000472 Radials fan with drive for cooling-turner fume extraction EQ 0 0 16-Feb-23 18-Jul-22
No. 4999 ( Hold By EP Contractor )
000470 Connection pipes and chutes (Steel structural, pipes, bends 24 14 01-Jul-22 A 20-May-23 19-Jul-22 15-Aug-22
and flanges, chutes etc.) PTJ's scope
Group -5200 - Cool- and Stacking Line 138 138 26-Nov-22 A 15-Jun-23 13-Apr-22 26-Jul-22
000486 Install Cooling-turner-arms (1) and align (Caution! - Pay close 16 16 07-Jan-23 24-Jan-23 13-Apr-22 01-May-22
attention to the instructions of the supervisor) EQ No.
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000496 Roller conveyor after ContiRoll-press outfeed EQ No. 5211 2 2 21-Jan-23 22-Jan-23 13-Apr-22 17-Apr-22
000497 Longitudinal trimming saw with individually adjustable 3 3 23-Jan-23 25-Jan-23 18-Apr-22 24-Apr-22
trimming units (assembling leveling and align EQ No. 5212
000498 Saw table for Multi-diagonal saw EQ No. 5216 2 2 26-Jan-23 28-Jan-23 25-Apr-22 28-Apr-22
000500 Noise protected cabinet EQ No. 5214.7 6 6 03-Jun-23 08-Jun-23 09-May-22 21-May-22
000501 Acceleration roller conveyor after Multi-diagonal saw EQ No. 2 2 10-Jun-23 11-Jun-23 22-May-22 25-May-22
5217
000502 Belt conveyor on raw board scale EQ No. 5221 2 2 12-Jun-23 13-Jun-23 26-May-22 30-May-22
000503 Raw board scale EQ No. 5222.1 2 2 14-Jun-23 15-Jun-23 31-May-22 04-Jun-22
000506 Roller conveyor for reject board station EQ No. 5227 2 2 07-Jan-23 08-Jan-23 21-Jun-22 25-Jun-22
000508 Installation support structure on Gripper carriage for catwalk 6 6 07-Jan-23 12-Jan-23 22-Jun-22 28-Jun-22
EQ No. 5271
000507 Limit switches equipment EQ No. 5200.04 5 5 09-Jan-23 14-Jan-23 26-Jun-22 05-Jul-22
000510 Safety fences for cool- and stacking line EQ No. 5200.042 6 6 09-Jan-23 15-Jan-23 06-Jul-22 19-Jul-22
000514 Rails for storage system including grouting EQ No. 5390 118 41 12-Nov-22 A 11-Apr-23 16-Mar-22 19-Apr-22
000516 Basic carriage SFG 1 EQ No. 5312 2 2 15-Apr-23 16-Apr-23 24-Apr-22 27-Apr-22
000517 Basic carriage SFG 2 EQ No. 5313 2 2 15-Apr-23 16-Apr-23 24-Apr-22 27-Apr-22
000518 Limit switches equipment EQ No. 5390.1 8 8 17-Apr-23 25-Apr-23 28-Apr-22 25-May-22
000520 Safety fences for storage EQ No. 5300.042 24 24 17-Apr-23 14-May-23 28-Apr-22 25-May-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000558 Noise protected cabin sanding machine EQ No. 5442.7 7 7 03-Jun-23 10-Jun-23 15-May-22 22-May-22
000560 Limit switches equipment EQ No. 5400.04 39 22 03-Dec-22 A 31-Jan-23 22-May-22 15-Jun-22
000561 Installation of Service platforms at sanding line 187 8 15-Jul-22 A 07-Mar-23 22-May-22 18-Jun-22
000559 Noise protected cabin Longitudinal saw EQ No. 5452.7 4 4 11-Jun-23 14-Jun-23 23-May-22 26-May-22
000563 Safety fences for sanding line EQ No. 5400.042 63 24 03-Dec-22 A 28-Feb-23 22-May-22 18-Jun-22
000574 Limit switches equipment EQ No. 5700.04 60 20 06-Nov-22 A 29-Jan-23 07-Jul-22 30-Jul-22
000576 Safety fences for packing line EQ No. 5700.042 80 20 06-Nov-22 A 21-Feb-23 07-Jul-22 30-Jul-22
000577 Safety sensors EQ No. 5700.043 100 20 06-Nov-22 A 16-Mar-23 07-Jul-22 30-Jul-22
Group -5900 - Extraction System for Finishing line, sanding maschine, trimmin 288 76 09-May-22 A 04-Apr-23 12-Jun-22 15-Aug-22
000579 Positioning radials fan with drive for sanding machine EQ 233 4 09-May-22 A 21-Feb-23 12-Jun-22 13-Jun-22
No. 5910
000580 Positioning and assembly from filter unit EQ No. 5911 165 4 01-Aug-22 A 26-Feb-23 14-Jun-22 19-Jun-22
000582 Positioning and assembly from round filter (sanding dust) EQ 47 6 05-Nov-22 A 12-Jan-23 25-Jun-22 30-Jun-22
No. 5918
000584 Positioning and assembly from round filter EQ No. 5921 134 3 23-Jul-22 A 10-Jan-23 04-Jul-22 10-Jul-22
000585 Connection pipes and chutes (Steel structural, pipes, bends 223 18 02-Jul-22 A 04-Apr-23 12-Jul-22 15-Aug-22
and flanges, chutes etc.) PTJ's scope
Group - 7100 - Silo Extra
Extraction Systems 185 80 16-Jul-22 A 09-Apr-23 12-May-22 11-Aug-22
000604 Connection pipes and chutes (Steel structural, pipes, bends 30 25 16-Jul-22 A 09-Apr-23 09-Jul-22 11-Aug-22
and flanges, chutes etc.) PTJ's scope
Sanding dust silo 107 66 03-Dec-22 A 23-Mar-23 12-May-22 24-May-22
000588 Discharge device under the silo EQ No. 7110.1 83 42 03-Dec-22 A 23-Mar-23 12-May-22 16-May-22
000590 HP rotary airlock with drive EQ No. 7112 9 4 17-Dec-22 A 10-Jan-23 21-May-22 24-May-22
000592 Discharge device under the silo EQ No. 7120.1 51 4 29-Oct-22 A 10-Jan-23 25-May-22 29-May-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
Saw dust silo 173 50 01-Aug-22 A 05-Mar-23 02-Jun-22 25-Jun-22
000595 Discharge device under the silo EQ No. 7130.1 173 2 01-Aug-22 A 05-Mar-23 02-Jun-22 06-Jun-22
000599 Positioning and assembly from round filter EQ No. 7136 5 5 07-Jan-23 11-Jan-23 20-Jun-22 25-Jun-22
000601 Discharge device under the silo EQ No. 7140.1 103 37 05-Nov-22 A 19-Mar-23 26-Jun-22 29-Jun-22
000603 HP rotary airlock with drive EQ No. 7141 4 4 31-Dec-22 A 10-Jan-23 04-Jul-22 07-Jul-22
000607 Thermal fluid system EQ No. 7390 367 70 25-Feb-22 A 12-Apr-23 03-Feb-22 07-May-22
000608 Steam system EQ No. 7390 318 82 25-Feb-22 A 11-Apr-23 27-Feb-22 20-Apr-22
000612 Positioning and assembly from Cooling unit EQ No. 7580 3 3 12-Apr-23 15-Apr-23 21-Apr-22 24-Apr-22
000613 Connecting pipes to refiner motor and blenders 20 20 16-Apr-23 08-May-23 25-Apr-22 17-May-22
000615 Installation of explosion protection system for sifter, blenders, 103 10 19-Nov-22 A 26-Apr-23 25-Apr-22 05-May-22
matformer, reject-mat etc. EQ No. 7601
000616 Installation of spark detection and extinguishing in the 10 10 07-Jan-23 17-Jan-23 01-May-22 11-May-22
production process EQ No. 7730
000617 Installation of anti-clogging device for the cyclone EQ No. 10 10 12-Jan-23 23-Jan-23 07-May-22 17-May-22
7750
Group -8110- Additional E
Equipment (options) 0 0 06-Jul-23 06-Jul-23 07-Aug-22 07-Aug-22
Activity ID Activity Name Original Rem. Start Finish BL1 Start BL1 Finish Month
Duration Dur.
0 31 32 33 34 35 36 37 38 39 40 41 42 43
000625 Kiln 0 0 06-Jul-23 07-Aug-22
1.00399 - Wotech - TR - Dryer Inst. Sch. - Rev 1 226 72 21-Feb-22 A 30-Mar-23 05-Mar-22 02-Jun-22
1.00399 - Wotech - EA - Energy Plant Inst. Sch. - Rev 1 265 98 15-Feb-22 A 30-Apr-23 15-Jan-22 04-Jun-22
A7620 Start-up, performance tuning & Test of EP CONTRACTOR 122 122 07-Sep-23 06-Jan-24 07-Oct-22 07-Feb-23
scope