Appendix III-04(1) TANAHU HYDROPOWER PROJECT

TOTAL SCHEDULE
N01(REV7)_Aug_31 REV-7
with tabular listing
Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
N01-1(Rev7) Tanahu-Package 1 Total Schedule1733 31-Aug-21 31-May-26 31-Aug-21 31-May-26 08-Feb-22 31-May-26 0 0 31-May-26, N01-1(Rev7) Tan

N01-1(Rev7).1 MILSTONE 1733 31-Aug-21 31-May-26 31-Aug-21 31-May-26 08-Feb-22 31-May-26 0 0 31-May-26, N01-1(Rev7).1 M

N01-1(Rev7).1.1 COMMENCEMENT DATE 0 31-Aug-21 31-Aug-21 31-Aug-21 31-Aug-21 08-Feb-22 08-Feb-22 0 159 31-Aug-21, N01-1(Rev7).1.1 COMMENCEMENT DATE
COM-1000 Commencement Date (expected) 0 31-Aug-21 31-Aug-21 08-Feb-22 0 159

N01-1(Rev7).1.2 SECTION OF THE WORKS 1733 31-Aug-21 31-May-26 31-Aug-21 31-May-26 08-Feb-22 31-May-26 0 0 31-May-26, N01-1(Rev7).1.2
SEC-1000 Section 1.1: Completion of all works for the 119 31-Aug-21 28-Dec-21 31-Aug-21 28-Dec-21 08-Feb-22 31-May-26 0 1614 31-Aug-21 28-Dec-21
Employer's and Engineer's Sub-Office (119d)

SEC-1010 Section 1.2: Completion of construction and 154 31-Aug-21 02-Feb-22 31-Aug-21 02-Feb-22 08-Feb-22 31-May-26 0 1579 31-Aug-21 02-Feb-22
installation of Crushing & Batching Plant (154d)

SEC-1020 Section 1.3: Completion of the Contractor's 242 31-Aug-21 01-May-22 31-Aug-21 01-May-22 08-Feb-22 31-May-26 0 1491 31-Aug-21 01-May-22
auxiliary works (Site office, Catering, ..., 182d)

SEC-1030 Section 2.1: Completion of all analyses and other 98 31-Aug-21 07-Dec-21 31-Aug-21 07-Dec-21 08-Feb-22 31-May-26 0 1635 31-Aug-21 07-Dec-21
design activities for the detailed design of the river
diversion (98d)
SEC-1040 Section 2.2: Completion of all analyses&other 364 31-Aug-21 31-Aug-22 31-Aug-21 31-Aug-22 08-Feb-22 31-May-26 0 1369 31-Aug-21 31-Aug-22
design activities for the detailed design of the
M.&D.stream Au.Dam (364d)
SEC-1050 Section 3: Completion of the construction of the 336 31-Aug-21 03-Aug-22 31-Aug-21 03-Aug-22 08-Feb-22 31-May-26 0 1397 31-Aug-21 03-Aug-22
Diversion Tunnels (406d)

SEC-1060 Section 4.1: Completion of the construction of the 587 31-Aug-21 11-Apr-23 31-Aug-21 11-Apr-23 08-Feb-22 31-May-26 0 1146 31-Aug-21 11-Apr-23
main River Cofferdams (532d)

SEC-1070 Section 4.2: Completion of excavation for the 772 31-Aug-21 13-Oct-23 31-Aug-21 13-Oct-23 08-Feb-22 13-Oct-23 0 0 31-Aug-21 13-Oct-23
M.Dam foundation (including contact concrete,...,
714d)
SEC-1080 Section 5.1: Completion of concrete of M.Dam to 1109 31-Aug-21 14-Sep-24 31-Aug-21 14-Sep-24 08-Feb-22 14-Sep-24 0 0 31-Aug-21 14-Sep-24
permit installation of hydro.equipment of Sediment
Flushing (1050d)
SEC-1090 Section 5.2: Completion of concrete of M.Dam to 1237 31-Aug-21 20-Jan-25 31-Aug-21 20-Jan-25 08-Feb-22 20-Jan-25 0 0 31-Aug-21 20-Jan-25
permit installation of hydro.equipent of Water Level
Lowering (1176d)
SEC-1100 Section 5.3: Completion of concrete of M.Dam to 1265 31-Aug-21 17-Feb-25 31-Aug-21 17-Feb-25 08-Feb-22 17-Feb-25 0 0 31-Aug-21 17-Feb-25
permit installation of hydro.equipment of
Environmental flow (1204d)
SEC-1110 Section 5.4: Completion of all concrete&other civil 1551 31-Aug-21 30-Nov-25 31-Aug-21 30-Nov-25 08-Feb-22 30-Nov-25 0 0 31-Aug-21 30-Nov-25
works to the M.Dam ready for erection of the
Spillway Gates (1295d)
SEC-1120 Section 6.1: Completion of all excavation for the 989 31-Aug-21 17-May-24 31-Aug-21 17-May-24 08-Feb-22 31-May-26 0 744 31-Aug-21 17-May-24
Down.Auxiliary Dam foundation (928d)

SEC-1130 Section 6.2: Completion of all concrete and other 1276 31-Aug-21 28-Feb-25 31-Aug-21 28-Feb-25 08-Feb-22 01-Apr-26 0 397 31-Aug-21 28-Feb-25
civil works to the Downstream Auxiliary Dam
(1215d)
SEC-1140 Section 7: Completion of removal of cofferdams, 1613 31-Aug-21 31-Jan-26 31-Aug-21 31-Jan-26 08-Feb-22 31-Jan-26 0 0 31-Aug-21 31-Jan-26
plugging of diversion tunnels&the approach tunnel,
Impounding (1533d)
SEC-1150 Section 8: Overall completion of the whole of the 1733 31-Aug-21 31-May-26 31-Aug-21 31-May-26 08-Feb-22 31-May-26 0 0 31-Aug-21 31-May-26
Works (1733d)

N01-1(Rev7).1.3 INTERFACE SCHEDULE 1687 31-Aug-21 15-Apr-26 31-Aug-21 15-Apr-26 08-Feb-22 31-May-26 0 46 15-Apr-26, N01-1(Rev7).1.3 INT
N01-1(Rev7).1.3.1 GENERAL 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 29-Nov-21, N01-1(Rev7).1.3.1 GENERAL
A16740 ID No. 0.1-The PKG2 confirm loads & 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
dimensions of hyromechanical gates&other
components to PKG1 (90d)

Remaining Work Start Constraint Current Bar Labels Page 1 of 9


Critical Remaining Work Finish Constraint Milestone
TANAHU HYDROPOWER PROJECT
TOTAL SCHEDULE
REV-7

Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
1642EQUIPMENTS
N01-1(Rev7).1.3.2 RADIAL GATES, STOPLOGS AND OPERATING 31-Aug-21 01-Mar-26 31-Aug-21
FOR MAIN DAM SPILLWAY01-Mar-26 08-Feb-22 31-May-26 0 91 01-Mar-26, N01-1(Rev7).1.3.2 RADI
ITF-1010 ID 1.1-Section 5.4-Completion of M.Dam concrete 1437 31-Aug-21 08-Aug-25 31-Aug-21 08-Aug-25 08-Feb-22 31-Oct-25 0 84 31-Aug-21 08-Aug-25
to allow PKG2 to start erection of Spillway gates
(PKG1: 1295d)
ITF-1020 ID 1.2-Spillway Bay No1 gate installation 1528 31-Aug-21 07-Nov-25 31-Aug-21 07-Nov-25 08-Feb-22 30-Jan-26 0 84 31-Aug-21 07-Nov-25
completed and released to PKG1 (PKG2: 1386d)

ITF-1030 ID 1.3-Spillway Bay No2 gate released to PKG2 1494 31-Aug-21 04-Oct-25 31-Aug-21 04-Oct-25 08-Feb-22 31-Oct-25 0 27 31-Aug-21 04-Oct-25
(PKG1: 1414d)

ITF-1040 ID 1.4-Spillway Bay No2 gate installation 1585 31-Aug-21 03-Jan-26 31-Aug-21 03-Jan-26 08-Feb-22 30-Jan-26 0 27 31-Aug-21 03-Jan-26
completed and released to PKG1 (PKG2: 1505d)

ITF-1050 ID 1.5-Spillway Bay No3 released to PKG2 for 1502 31-Aug-21 12-Oct-25 31-Aug-21 12-Oct-25 08-Feb-22 31-Oct-25 0 19 31-Aug-21 12-Oct-25
gate installation (PKG1: 1449d)

ITF-1060 ID 1.6-Spillway Bay No3 gate installation 1593 31-Aug-21 11-Jan-26 31-Aug-21 11-Jan-26 08-Feb-22 30-Jan-26 0 19 31-Aug-21 11-Jan-26
completed and released to PKG1 (PKG2: 1540d)

ITF-1070 ID 1.7-Spillway Bay No4 released to PKG2 for 1551 31-Aug-21 30-Nov-25 31-Aug-21 30-Nov-25 08-Feb-22 30-Nov-25 0 0 31-Aug-21 30-Nov-25
gate installation (PKG1: 1449d)

ITF-1080 ID 1.8-Spillway Bay No4 gate installation 1642 31-Aug-21 01-Mar-26 31-Aug-21 01-Mar-26 08-Feb-22 01-Mar-26 0 0 31-Aug-21 01-Mar-26
completed and released to PKG1 (PKG2: 1540d)

ITF-1090 ID 1.9-Block C released to PKG2 for Spillway 1494 31-Aug-21 04-Oct-25 31-Aug-21 04-Oct-25 08-Feb-22 22-Feb-26 0 141 31-Aug-21 04-Oct-25
stoplogs storage works (PK1:1453d)

ITF-1100 ID 1.10-Stoplog spillway storage bay works 1592 31-Aug-21 10-Jan-26 31-Aug-21 10-Jan-26 08-Feb-22 31-May-26 0 141 31-Aug-21 10-Jan-26
completed and released to PKG1 (PKG2: 1533d)

ITF-1120 ID 1.11-Spillway gates and stoplogs detailed layout 224 31-Aug-21 13-Apr-22 31-Aug-21 13-Apr-22 08-Feb-22 11-Jan-26 0 1369 31-Aug-21 13-Apr-22
and shape design by PKG2 (PKG2: 224d)

ITF-1130 ID 1.12-Detailed design of all spillway and dam 1357 31-Aug-21 20-May-25 31-Aug-21 20-May-25 08-Feb-22 20-May-25 0 0 31-Aug-21 20-May-25
crest hydromechanical components by PKG2
(PKG2: 630d)
ITF-1140 ID 1.13-Provision of drawing&supply of first stage 1357 31-Aug-21 20-May-25 31-Aug-21 20-May-25 08-Feb-22 20-May-25 0 0 31-Aug-21 20-May-25
embeded steel parts to PKG1 (PKG2: 945d)

ITF-1150 ID 1.14-Provision of requirments for grounding 642 31-Aug-21 05-Jun-23 31-Aug-21 05-Jun-23 08-Feb-22 31-Jan-26 0 971 31-Aug-21 05-Jun-23
system to the PKG1 (PKG2:120)

ITF-1160 ID 1.15-Design, supply and installation of 762 31-Aug-21 03-Oct-23 31-Aug-21 03-Oct-23 08-Feb-22 31-May-26 0 971 31-Aug-21 03-Oct-23
grounding system (PKG1: 700d)

N01-1(Rev7).1.3.3 GATES ANS OPERATING EQUIPMENT AND1559 31-Aug-21


STEEL 08-Dec-25
LINERS FOR 31-Aug-21
WATER LEVEL 08-Dec-25
LOWERING 08-Feb-22 31-May-26 0 174 08-Dec-25, N01-1(Rev7).1.3.3 GATES ANS
ITF-1180 ID 2.1-(Section 5.2)-Completion to allow PKG2 to 1237 31-Aug-21 20-Jan-25 31-Aug-21 20-Jan-25 08-Feb-22 20-Jan-25 0 0 31-Aug-21 20-Jan-25
commence installation of hydromechanical
equipment (PKG1: 1176d)
ITF-1190 ID 2.2-Left water level lowering gates area handed 1300 31-Aug-21 24-Mar-25 31-Aug-21 24-Mar-25 08-Feb-22 31-May-26 0 433 31-Aug-21 24-Mar-25
over to PKG1 (PKG2: 1239d)

ITF-1200 ID 2.3-Right water lever lowering gates area handed 1300 31-Aug-21 24-Mar-25 31-Aug-21 24-Mar-25 08-Feb-22 31-May-26 0 433 31-Aug-21 24-Mar-25
over to PKG1 (PKG2: 1239d)

ITF-1210 ID 2.4-Completion of installation and dry testing of 1559 31-Aug-21 08-Dec-25 31-Aug-21 08-Dec-25 08-Feb-22 08-Dec-25 0 0 31-Aug-21 08-Dec-25
all hydromechanical equipment ready for
impoundment (PKG2: 1498d)

Remaining Work Start Constraint Current Bar Labels Page 2 of 9


Critical Remaining Work Finish Constraint Milestone
TANAHU HYDROPOWER PROJECT
TOTAL SCHEDULE
REV-7

Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
ITF-1220 ID 2.5-Provision of preliminary design information 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
to the PKG1 (PKG2: 90d)

ITF-1230 ID 2.6-Provision of final design information to the 270 31-Aug-21 29-May-22 31-Aug-21 29-May-22 08-Feb-22 26-Feb-26 0 1369 31-Aug-21 29-May-22
PKG1 (PKG2: 270d)

ITF-1240 ID 2.7-Design of the structures including block-outs 364 31-Aug-21 31-Aug-22 31-Aug-21 31-Aug-22 08-Feb-22 31-May-26 0 1369 31-Aug-21 31-Aug-22
for gate installation and access ladders or steps
(PKG1: 364d)
ITF-1250 ID 2.8-Provision of drawings and supply of first 1199 31-Aug-21 13-Dec-24 31-Aug-21 13-Dec-24 08-Feb-22 13-Dec-24 0 0 31-Aug-21 13-Dec-24
stage embedded steel parts to PKG1 (PKG2: 896d)

ITF-1260 ID 2.9-Provision of requirements of operation 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
rooms of water level lowering equipment to PKG1
(PKG2: 90d)

N01-1(Rev7).1.3.4 GATES AND OPERATING EQUIPMENT AND1578 31-Aug-21


STEEL 27-Dec-25
LINERS FOR SEDIMENT31-Aug-21
FLUSHING 27-Dec-25 08-Feb-22 31-May-26 0 155 27-Dec-25, N01-1(Rev7).1.3.4 GATES AN
ITF-1280 ID No 3.1-(Section 5.1)-Complete concrete to allow 1109 31-Aug-21 14-Sep-24 31-Aug-21 14-Sep-24 08-Feb-22 14-Sep-24 0 0 31-Aug-21 14-Sep-24
PKG2 installation of the hydromechanical
equipment (PKG1: 1050d)
ITF-1290 ID No 3.2-Sediment sluice area handed over to 1274 31-Aug-21 26-Feb-25 31-Aug-21 26-Feb-25 08-Feb-22 31-May-26 0 459 31-Aug-21 26-Feb-25
PKG1 (PKG2: 1215d)

ITF-1300 ID No 3.3-Completion of Intallation and Dry testing 1410 31-Aug-21 12-Jul-25 31-Aug-21 12-Jul-25 08-Feb-22 12-Jul-25 0 0 31-Aug-21 12-Jul-25
of all hydromechanical equipment ready for
impoundment (PKG2: 1351d)
ITF-1310 ID No 3.4-Sediment flushing maintenance 1578 31-Aug-21 27-Dec-25 31-Aug-21 27-Dec-25 08-Feb-22 27-Dec-25 0 0 31-Aug-21 27-Dec-25
gate&hoisting equipment erection&dry testing
completed by the PKG2 (PKG2: 1519d)
ITF-1320 ID No 3.5-Provision of preliminary design 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
information to the PKG1 (PKG2: 90d)

ITF-1330 ID No 3.6-Provision of final design information to 270 31-Aug-21 29-May-22 31-Aug-21 29-May-22 08-Feb-22 26-Feb-26 0 1369 31-Aug-21 29-May-22
the PKG1 (PKG2: 270d)

ITF-1340 ID No 3.7-Design of the concrete structures (PKG1: 364 31-Aug-21 31-Aug-22 31-Aug-21 31-Aug-22 08-Feb-22 31-May-26 0 1369 31-Aug-21 31-Aug-22
364d).

ITF-1350 ID No 3.8-Provision of drawings and supply of 623 31-Aug-21 17-May-23 31-Aug-21 17-May-23 08-Feb-22 17-May-23 0 0 31-Aug-21 17-May-23
first stage embedded steel parts to the PKG1
(PKG2: 770d)
ITF-1360 ID No 3.9-Provision of drawings of operation 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
rooms to PKG1 (PKG2: 90d)

1417 31-Aug-21
N01-1(Rev7).1.3.5 GATES, STOPLOGS AND OPERATING EQUIMENT 19-Jul-25
FOR ENVIRONMENTAL 31-Aug-21
FLOW 19-Jul-25
OUTLET 08-Feb-22
AND POWER PLANT 31-May-26 0 316 19-Jul-25, N01-1(Rev7).1.3.5 GATES, STOPLOGS AND
ITF-1380 ID No. 4.1-Provision of requirements for concrete 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
foundations/structures to PKG1 (PKG2: 90d)

ITF-1390 ID No. 4.2-Provision of preliminary design 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
information of the hydromechanical equipment to
PKG1 (PKG2: 90d)
ITF-1400 ID No. 4.3-Provision of final design information of 270 31-Aug-21 29-May-22 31-Aug-21 29-May-22 08-Feb-22 26-Feb-26 0 1369 31-Aug-21 29-May-22
the hydromechanical to PKG1 (PKG2: 270d)

ITF-1410 ID No. 4.4-Design&construction of concrete 1417 31-Aug-21 19-Jul-25 31-Aug-21 19-Jul-25 08-Feb-22 19-Jul-25 0 0 31-Aug-21 19-Jul-25
foundations/structures, ...in the m.dam intake and
pressure pipe (PKG1: 364d)
ITF-1420 ID No. 4.5-Provision of drawings&supply of 1st 1109 31-Aug-21 14-Sep-24 31-Aug-21 14-Sep-24 08-Feb-22 14-Sep-24 0 0 31-Aug-21 14-Sep-24
stage embedded steel plates to PKG1 (PKG2:
971d)

Remaining Work Start Constraint Current Bar Labels Page 3 of 9


Critical Remaining Work Finish Constraint Milestone
TANAHU HYDROPOWER PROJECT
TOTAL SCHEDULE
REV-7

Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
ITF-1430 ID No. 4.6-Section 5.3-Completion of concrete of 1265 31-Aug-21 17-Feb-25 31-Aug-21 17-Feb-25 08-Feb-22 17-Feb-25 0 0 31-Aug-21 17-Feb-25
m.dam to permit installation of hydromechanical
equipment (PKG1: 1204d)
ITF-1440 ID No. 4.7-Environmental flow intake pipe encased 1300 31-Aug-21 24-Mar-25 31-Aug-21 24-Mar-25 08-Feb-22 31-May-26 0 433 31-Aug-21 24-Mar-25
and released to PKG1 (PKG2: 1239d)

N01-1(Rev7).1.3.6 DAM OPERATION AND SERVICE BUILDING 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 29-Nov-21, N01-1(Rev7).1.3.6 DAM OPERATIONAND SERVICE BUILDING
ITF-1460 Provision of requirements of the Dam Operation 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
and Service Building to PKG1 (PKG2: 90d)

N01-1(Rev7).1.3.7 DISTRIBUTION LINES IN THE DAM AREA 1687 31-Aug-21 15-Apr-26 31-Aug-21 15-Apr-26 08-Feb-22 31-May-26 0 46 15-Apr-26, N01-1(Rev7).1.3.7 DI
ITF-1480 ID No. 6.1-Provision of requirements for 11kV 25 31-Aug-21 25-Sep-21 31-Aug-21 25-Sep-21 07-May-26 31-May-26 1708 1708 31-Aug-21 25-Sep-21
distribution line from THL's distribution to the Dam
Operation (PKG2: 25d)
ITF-1490 ID No. 6.2-Design, supply and installation of the 399 31-Aug-21 05-Oct-22 31-Aug-21 05-Oct-22 28-Apr-25 31-May-26 1334 1334 31-Aug-21 05-Oct-22
said 11kVdistribution line (PKG1: 399d)

ITF-1500 ID No. 6.3-11kVdistribution line completed and 1687 31-Aug-21 15-Apr-26 31-Aug-21 15-Apr-26 08-Feb-22 31-May-26 0 46 31-Aug-21 15-Apr-26
released to the PKG2 (PKG1: 1379d)

N01-1(Rev7).1.3.8 WATER LEVEL GAUGES AT THE DAM 562 31-Aug-21 17-Mar-23 31-Aug-21 17-Mar-23 08-Feb-22 30-Aug-25 0 897 17-Mar-23, N01-1(Rev7).1.3.8 WATER LEVEL GAUGES AT THE DAM
ITF-1520 Provision of requirements for PVC pipes for two 90 31-Aug-21 29-Nov-21 31-Aug-21 29-Nov-21 08-Feb-22 30-Aug-25 0 1369 31-Aug-21 29-Nov-21
water level gauges to PKG1 (PKG2: 90d)

ITF-1530 Provision of drawings and supply and installation 562 31-Aug-21 17-Mar-23 31-Aug-21 17-Mar-23 08-Feb-22 17-Mar-23 0 0 31-Aug-21 17-Mar-23
of PVC pipe for water level gauges (PKG2: 270d)

N01-1(Rev7).1.3.11 PKG2 MAIN POWER INTAKE STRUCTURE1053


STRUCTURE 31-Aug-21 20-Jul-24 31-Aug-21 20-Jul-24 08-Feb-22 31-May-26 0 680 20-Jul-24, N01-1(Rev7).1.3.11 PKG2 MAIN POWER INTAKE STRUCTURE
ITF-1610 Completion of all works for the construction of the 1053 31-Aug-21 20-Jul-24 31-Aug-21 20-Jul-24 08-Feb-22 31-May-26 0 680 31-Aug-21 20-Jul-24
intake, ready for reservoir impoundment (PKG2:
429d)

N01-1(Rev7).2 DESIGN 702 31-Aug-21 05-Aug-23 31-Aug-21 05-Aug-23 02-Jun-25 31-May-26 0 1031 05-Aug-23, N01-1(Rev7).2 DESIGN

DES-1000 Section 2.1-Completion of all analyses and Design 98 31-Aug-21 07-Dec-21 31-Aug-21 07-Dec-21 23-Feb-26 31-May-26 1635 1635 31-Aug-21 07-Dec-21
of the river diversion works.

DES-1010 Section 2.2-Completion of all analyses and Design 364 31-Aug-21 31-Aug-22 31-Aug-21 31-Aug-22 02-Jun-25 31-May-26 1369 1369 31-Aug-21 31-Aug-22
of the Main Dam and the Downstream Auxiliary
Dam
DES-1020 Design of grouding system of Spillway 60 06-Jun-23 05-Aug-23 06-Jun-23 05-Aug-23 01-Feb-26 01-Apr-26 971 971 06-Jun-23 05-Aug-23

242 31-Aug-21
N01-1(Rev7).3 MOBILIZATION AND SITE PREPARATION 01-May-22 31-Aug-21 01-May-22 02-Oct-25 31-May-26 0 1491 01-May-22, N01-1(Rev7).3 MOBILIZATIONAND SITE PREPARATION
A1800 Section 1.1-Completion of all works required for 119 31-Aug-21 28-Dec-21 31-Aug-21 28-Dec-21 02-Feb-26 31-May-26 1614 1614 31-Aug-21 28-Dec-21
the Empoyer' and Engineer's Sub-Office

A1810 Section 1.2-Completion of all works required for 154 31-Aug-21 02-Feb-22 31-Aug-21 02-Feb-22 29-Dec-25 31-May-26 1579 1579 31-Aug-21 02-Feb-22
the Crushing plant(s) and Bathching plant(s).

A1830 Section 1.3-Completion of all works required for 242 31-Aug-21 01-May-22 31-Aug-21 01-May-22 02-Oct-25 31-May-26 1491 1491 31-Aug-21 01-May-22
the Contractor's Site establishment

260 31-Aug-21
N01-1(Rev7).4 CONSTRUCTION OF ACCESS ROAD 19-May-22 31-Aug-21 19-May-22 10-Nov-24 27-Jul-25 0 1165 19-May-22, N01-1(Rev7).4 CONSTRUCTION OFACCESS ROAD
A1840 Construction of access road 260 31-Aug-21 19-May-22 31-Aug-21 19-May-22 10-Nov-24 27-Jul-25 63 1165 31-Aug-21 19-May-22
N01-1(Rev7).5 RIVER DIVERSIONS 587 31-Aug-21 11-Apr-23 31-Aug-21 11-Apr-23 08-Feb-22 31-May-26 0 1146 11-Apr-23, N01-1(Rev7).5 RIVER DIVERSIONS

N01-1(Rev7).5.1 DIVERSION TUNNEL 336 31-Aug-21 03-Aug-22 31-Aug-21 03-Aug-22 08-Feb-22 31-May-26 0 1397 03-Aug-22, N01-1(Rev7).5.1 DIVERSION TUNNEL
N01-1(Rev7).5.1.1 No.01 (EL320.00) 336 31-Aug-21 03-Aug-22 31-Aug-21 03-Aug-22 08-Feb-22 31-May-26 0 1397 03-Aug-22, N01-1(Rev7).5.1.1 No.01 (EL320.00)
A16760 Inlet portal (access road, excavation, slope 30 20-Oct-21 19-Nov-21 20-Oct-21 19-Nov-21 01-Jun-22 30-Jun-22 55 223 20-Oct-21 19-Nov-21
protection)
A16761 Adit tunnel (70m) 30 31-Aug-21 30-Sep-21 31-Aug-21 30-Sep-21 08-Feb-22 09-Mar-22 0 159 31-Aug-21 30-Sep-21

Remaining Work Start Constraint Current Bar Labels Page 4 of 9


Critical Remaining Work Finish Constraint Milestone
TANAHU HYDROPOWER PROJECT
TOTAL SCHEDULE
REV-7

Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
A16762 Excavation from Adit to downstream, L=189.4m 55 14-Jan-22 09-Mar-22 14-Jan-22 09-Mar-22 22-Jun-22 15-Aug-22 0 159 14-Jan-22 09-Mar-22

A16790 Outlet portal (access road, excavation, slope 60 15-Oct-21 13-Dec-21 15-Oct-21 13-Dec-21 22-Jan-26 22-Mar-26 162 1559 15-Oct-21 13-Dec-21
protection, concrete)

A16800 Excavation from Outlet to upstream (Heading, and 85 14-Dec-21 09-Mar-22 14-Dec-21 09-Mar-22 23-May-22 15-Aug-22 0 159 14-Dec-21 09-Mar-22
then Benching 30m after), L=301m

A16801 Excavation from Adit to upstream (Heading, and 30 14-Dec-21 13-Jan-22 14-Dec-21 13-Jan-22 23-May-22 21-Jun-22 0 159 14-Dec-21 13-Jan-22
then Benching 30m after), L=66.14m

A16802 Construction, hydromechanical installation of Inlet 90 14-Jan-22 13-Apr-22 14-Jan-22 13-Apr-22 01-Jul-22 28-Sep-22 0 168 14-Jan-22 13-Apr-22
concrete structure

A16860 Formwork re-assembly (At Outlet) 15 29-Mar-22 12-Apr-22 29-Mar-22 12-Apr-22 24-Jan-26 07-Feb-26 0 1397 29-Mar-22 12-Apr-22

A16880 Stoplog fabrication, assembly, installation, and 185 09-Nov-21 13-May-22 09-Nov-21 13-May-22 27-Apr-22 28-Oct-22 0 168 09-Nov-21 13-May-22
electric winch

A16920 Concrete lining (From Inlet to Outlet) 93 13-Apr-22 14-Jul-22 13-Apr-22 14-Jul-22 08-Feb-26 11-May-26 0 1397 13-Apr-22 14-Jul-22

A16930 Grouting 70 26-May-22 03-Aug-22 26-May-22 03-Aug-22 23-Mar-26 31-May-26 1397 1397 26-May-22 03-Aug-22
N01-1(Rev7).5.1.2 No.02 (EL315.00) 266 31-Aug-21 25-May-22 31-Aug-21 25-May-22 08-Feb-22 31-Oct-22 0 159 25-May-22, N01-1(Rev7).5.1.2 No.02 (EL315.00)
A16770 Inlet portal (access road, excavation, slope 30 04-Nov-21 04-Dec-21 04-Nov-21 04-Dec-21 16-Jun-22 15-Jul-22 0 223 04-Nov-21 04-Dec-21
protection)
A16771 Excavation from Adit to upstream (54.35m) 20 01-Oct-21 20-Oct-21 01-Oct-21 20-Oct-21 01-Jun-22 20-Jun-22 44 242 01-Oct-21 20-Oct-21

A16772 Excavation from Adit to downstream (Heading, and 74 01-Oct-21 13-Dec-21 01-Oct-21 13-Dec-21 10-Mar-22 22-May-22 0 159 01-Oct-21 13-Dec-21
then Benching 30m after), L=254m

A16780 Outlet portal (access road, excavation, slope 60 31-Aug-21 30-Oct-21 31-Aug-21 30-Oct-21 08-Feb-22 08-Apr-22 0 159 31-Aug-21 30-Oct-21
protection, concrete)

A16811 Excavation from Outlet to upstream, L=314m 89 16-Sep-21 13-Dec-21 16-Sep-21 13-Dec-21 23-Feb-22 22-May-22 0 159 16-Sep-21 13-Dec-21

A16820 Construction, hydromechanical installation of Inlet 90 14-Dec-21 14-Mar-22 14-Dec-21 14-Mar-22 01-Jul-22 28-Sep-22 0 198 14-Dec-21 14-Mar-22
concrete structure

A16840 Formwork assembly (At Intlet) 10 04-Dec-21 14-Dec-21 04-Dec-21 14-Dec-21 21-Jun-22 30-Jun-22 0 198 04-Dec-21 14-Dec-21

A16850 Concrete lining (Starting from Inlet), L=622m 104 14-Dec-21 28-Mar-22 14-Dec-21 28-Mar-22 30-Jun-22 12-Oct-22 0 198 14-Dec-21 28-Mar-22

A16870 Grouting 77 10-Mar-22 25-May-22 10-Mar-22 25-May-22 16-Aug-22 31-Oct-22 159 159 10-Mar-22 25-May-22
A16900 Stoplog fabrication, assembly, installation, and 186 09-Oct-21 13-Apr-22 09-Oct-21 13-Apr-22 26-Apr-22 28-Oct-22 30 198 09-Oct-21 13-Apr-22
electric winch

A16910 Dry test and hanging stoplog (Two tunnels) 3 14-May-22 16-May-22 14-May-22 16-May-22 29-Oct-22 31-Oct-22 168 168 14-May-22 16-May-22

N01-1(Rev7).5.2 COFFER DAM 162 01-Nov-22 11-Apr-23 01-Nov-22 11-Apr-23 01-Nov-22 31-May-26 0 1146 11-Apr-23, N01-1(Rev7).5.2 COFFER DAM
N01-1(Rev7).5.2.1 UP STREAM COFFER DAM 162 01-Nov-22 11-Apr-23 01-Nov-22 11-Apr-23 01-Nov-22 31-May-26 0 1146 11-Apr-23, N01-1(Rev7).5.2.1 UP STREAM COFFER DAM
A1020 Foundation excavation and Construction of Rock 35 01-Nov-22 05-Dec-22 01-Nov-22 05-Dec-22 01-Nov-22 05-Dec-22 0 0 01-Nov-22* 05-Dec-22
block (1) up to EL320.00 and Block (1A) up to EL
323.00
A1030 Construction of the rock layer to reinforce the 35 01-Nov-22 05-Dec-22 01-Nov-22 05-Dec-22 26-Feb-26 01-Apr-26 0 1213 01-Nov-22 05-Dec-22
upstream slope (7A)

A1040 Construction of transition block (2C) & (2D) at the 20 26-Nov-22 15-Dec-22 26-Nov-22 15-Dec-22 23-Mar-26 11-Apr-26 67 1213 26-Nov-22 15-Dec-22
same time with Block (6B)-earth fill

Remaining Work Start Constraint Current Bar Labels Page 5 of 9


Critical Remaining Work Finish Constraint Milestone
TANAHU HYDROPOWER PROJECT
TOTAL SCHEDULE
REV-7

Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
A1050 Construction of jet-grouting 77 06-Dec-22 20-Feb-23 06-Dec-22 20-Feb-23 06-Dec-22 20-Feb-23 0 0 06-Dec-22 20-Feb-23
A1060 Construction of earthfill block (6A) 35 21-Feb-23 27-Mar-23 21-Feb-23 27-Mar-23 12-Apr-26 16-May-26 0 1146 21-Feb-23 27-Mar-23

A1070 Construction of rock Block (4) at the same time 35 21-Feb-23 27-Mar-23 21-Feb-23 27-Mar-23 12-Apr-26 16-May-26 0 1146 21-Feb-23 27-Mar-23
with transition Block (5) and slope protection (7B)

A1080 Section 4.1-Construction of slope protection block 15 28-Mar-23 11-Apr-23 28-Mar-23 11-Apr-23 17-May-26 31-May-26 1146 1146 28-Mar-23 11-Apr-23
(7C) and defect

N01-1(Rev7).5.2.2 DOWN STREAM COFFER DAM 78 01-Nov-22 17-Jan-23 01-Nov-22 17-Jan-23 12-Dec-22 31-May-26 0 1230 17-Jan-23, N01-1(Rev7).5.2.2 DOWN STREAM COFFER DAM
A1090 Construction of Block 1 (Rock) up to EL305.00 21 01-Nov-22 21-Nov-22 01-Nov-22 21-Nov-22 12-Dec-22 01-Jan-23 0 41 01-Nov-22 21-Nov-22

A1100 Construction Block 3 (Transition Layer) - 2 (earth 20 22-Nov-22 11-Dec-22 22-Nov-22 11-Dec-22 02-Jan-23 21-Jan-23 0 41 22-Nov-22 11-Dec-22
fill) and Block 4 (slope protection)

A1110 Construction of Block 2 (earth fill) - 3 (transition) - 1 20 12-Dec-22 31-Dec-22 12-Dec-22 31-Dec-22 22-Jan-23 10-Feb-23 0 41 12-Dec-22 31-Dec-22
(mix rock) - 4 (slope protection) up to EL311.00

A1120 Construction of jet-grouting 50 22-Nov-22 10-Jan-23 22-Nov-22 10-Jan-23 02-Jan-23 20-Feb-23 0 41 22-Nov-22 10-Jan-23
A1130 Section 4.1-Construction of remaining section 7 11-Jan-23 17-Jan-23 11-Jan-23 17-Jan-23 25-May-26 31-May-26 1230 1230 11-Jan-23 17-Jan-23

N01-1(Rev7).6 MAIN DAM 1598 15-Jan-22 31-May-26 15-Jan-22 31-May-26 21-Feb-23 31-May-26 0 0 31-May-26, N01-1(Rev7).6 M
517 15-Jan-22
N01-1(Rev7).6.1 EXCAVATION OF THE MAIN DAM FOUDATION 15-Jun-23 15-Jan-22 15-Jun-23 21-Feb-23 26-Feb-26 0 987 15-Jun-23, N01-1(Rev7).6.1 EXCAVATION OF THE MAIN DAM FOUDATION
A1140 Excavation of the L&R bank of M.Dam foundation 188 15-Jan-22 22-Jul-22 15-Jan-22 22-Jul-22 25-Jun-25 29-Dec-25 0 1257 15-Jan-22 22-Jul-22
down to EL420.0-about 860,000m3 (including
rock support&slope protection)
A1150 Excavation of M.Dam foundation from 214 22-Jul-22 21-Feb-23 22-Jul-22 21-Feb-23 28-Jul-25 26-Feb-26 0 1102 22-Jul-22 21-Feb-23
EL420-310, about 570,000m3 (including period of
grouting tunnel construction)
A1160 Excavation of the River bed of the Main Dam, from 115 21-Feb-23 15-Jun-23 21-Feb-23 15-Jun-23 21-Feb-23 15-Jun-23 0 0 21-Feb-23 15-Jun-23
EL310.00-EL283.00 (about 386,000m3)

N01-1(Rev7).6.2 GROUTING TUNNEL 441 22-Jul-22 05-Oct-23 22-Jul-22 05-Oct-23 16-Oct-25 31-May-26 0 969 05-Oct-23, N01-1(Rev7).6.2 GROUTING TUNNEL
N01-1(Rev7).6.2.1 LEFT BANK 405 22-Jul-22 30-Aug-23 22-Jul-22 30-Aug-23 07-Nov-25 31-May-26 0 1005 30-Aug-23, N01-1(Rev7).6.2.1 LEFT BANK
N01-1(Rev7).6.2.1.1 GROUTING TUNNELAT EL420 (185M) 122 22-Jul-22 20-Nov-22 22-Jul-22 20-Nov-22 30-Jan-26 31-May-26 0 1288 20-Nov-22, N01-1(Rev7).6.2.1.1 GROUTING TUNNELATEL420 (185M)
A1170 Excavation and provisional support (14.07m2) 60 22-Jul-22 19-Sep-22 22-Jul-22 19-Sep-22 30-Jan-26 30-Mar-26 0 1288 22-Jul-22 19-Sep-22

A1180 Concrete lining. 62 20-Sep-22 20-Nov-22 20-Sep-22 20-Nov-22 31-Mar-26 31-May-26 1288 1288 20-Sep-22 20-Nov-22
N01-1(Rev7).6.2.1.2 GROUTING TUNNELAT EL346 (240M) 249 10-Oct-22 15-Jun-23 10-Oct-22 15-Jun-23 28-Dec-25 31-May-26 0 1081 15-Jun-23, N01-1(Rev7).6.2.1.2 GROUTING TUNNELATEL346 (240M)
A1190 Excavation and provisional support (18.65m2) 75 10-Oct-22 23-Dec-22 10-Oct-22 23-Dec-22 28-Dec-25 12-Mar-26 94 1175 10-Oct-22 23-Dec-22

A1200 Concrete lining. 80 28-Mar-23 15-Jun-23 28-Mar-23 15-Jun-23 13-Mar-26 31-May-26 1081 1081 28-Mar-23 15-Jun-23
N01-1(Rev7).6.2.1.3 GROUTING TUNNELAT EL283 (229) 206 06-Feb-23 30-Aug-23 06-Feb-23 30-Aug-23 07-Nov-25 31-May-26 0 1005 30-Aug-23, N01-1(Rev7).6.2.1.3 GROUTING TUNNELATEL283 (229)
A1210 Excavation and provision support (23.88m2) 130 06-Feb-23 15-Jun-23 06-Feb-23 15-Jun-23 07-Nov-25 16-Mar-26 0 1005 06-Feb-23 15-Jun-23

A1220 Concrete lining. 76 16-Jun-23 30-Aug-23 16-Jun-23 30-Aug-23 17-Mar-26 31-May-26 1005 1005 16-Jun-23 30-Aug-23
N01-1(Rev7).6.2.2 RIGHT BANK 441 22-Jul-22 05-Oct-23 22-Jul-22 05-Oct-23 16-Oct-25 31-May-26 0 969 05-Oct-23, N01-1(Rev7).6.2.2 RIGHT BANK
N01-1(Rev7).6.2.2.1 GROUTING TUNNELAT EL420 (235M) 153 22-Jul-22 21-Dec-22 22-Jul-22 21-Dec-22 30-Dec-25 31-May-26 0 1257 21-Dec-22, N01-1(Rev7).6.2.2.1 GROUTING TUNNELATEL420 (235M)
A1230 Excavation and provisional support (14.07m2) 75 22-Jul-22 04-Oct-22 22-Jul-22 04-Oct-22 30-Dec-25 14-Mar-26 0 1257 22-Jul-22 04-Oct-22

A1240 Concrete lining. 78 05-Oct-22 21-Dec-22 05-Oct-22 21-Dec-22 15-Mar-26 31-May-26 1257 1257 05-Oct-22 21-Dec-22
N01-1(Rev7).6.2.2.3 GROUTING TUNNELAT EL346 (370M) 249 10-Oct-22 15-Jun-23 10-Oct-22 15-Jun-23 16-Oct-25 31-May-26 0 1081 15-Jun-23, N01-1(Rev7).6.2.2.3 GROUTING TUNNELATEL 346 (370M)
A1250 Excavation and provisional support (18.65m2) 105 10-Oct-22 22-Jan-23 10-Oct-22 22-Jan-23 16-Oct-25 28-Jan-26 21 1102 10-Oct-22 22-Jan-23

A1260 Concrete lining. 123 13-Feb-23 15-Jun-23 13-Feb-23 15-Jun-23 29-Jan-26 31-May-26 1081 1081 13-Feb-23 15-Jun-23
N01-1(Rev7).6.2.2.2 GROUTING TUNNELAT EL283 (336) 212 08-Mar-23 05-Oct-23 08-Mar-23 05-Oct-23 01-Nov-25 31-May-26 0 969 05-Oct-23, N01-1(Rev7).6.2.2.2 GROUTING TUNNELATEL 283 (336)

Remaining Work Start Constraint Current Bar Labels Page 6 of 9


Critical Remaining Work Finish Constraint Milestone
TANAHU HYDROPOWER PROJECT
TOTAL SCHEDULE
REV-7

Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
A1270 Excavation and provisional support, including adit 100 08-Mar-23 15-Jun-23 08-Mar-23 15-Jun-23 01-Nov-25 08-Feb-26 0 969 08-Mar-23 15-Jun-23
tunnel (23.88m2)

A1280 Concrete lining. 112 16-Jun-23 05-Oct-23 16-Jun-23 05-Oct-23 09-Feb-26 31-May-26 969 969 16-Jun-23 05-Oct-23
831 21-Nov-22
N01-1(Rev7).6.3 DRILLING AND GROUTING, DRAINAGE DRILLING 28-Feb-25 21-Nov-22 28-Feb-25 04-Oct-23 31-Dec-25 0 306 28-Feb-25, N01-1(Rev7).6.3 DRILLINGAND GROUTING, DRAINA
A1290 Drilling and grouting of grout curtain (about: 0 04-Oct-23 04-Oct-23 04-Oct-23 04-Oct-23 04-Oct-23 31-Dec-25 0 820 04-Oct-23 04-Oct-23
32,660md)
A1320 Drainage drilling (about 16,570 md) 484 03-Nov-23 28-Feb-25 03-Nov-23 28-Feb-25 31-Dec-25 31-Dec-25 0 306 03-Nov-23 28-Feb-25

A1330 Consolidation grouting for grout tunnels (about: 831 21-Nov-22 28-Feb-25 21-Nov-22 28-Feb-25 31-Dec-25 31-Dec-25 0 306 21-Nov-22 28-Feb-25
5.860md)
N01-1(Rev7).6.4 POURING CONCRETE 1035 16-Jun-23 15-Apr-26 16-Jun-23 15-Apr-26 16-Jun-23 31-May-26 0 46 15-Apr-26, N01-1(Rev7).6.4 POU
120 16-Jun-23
N01-1(Rev7).6.4.1 CONTACT CONCRETE & GROUTING CONSOLIDATION 13-Oct-23 16-Jun-23 13-Oct-23 16-Jun-23 31-May-26 0 961 13-Oct-23, N01-1(Rev7).6.4.1 CONTACT CONCRETE & GROUTING CONSOLIDATION
A1300 Contact concrete up to EL 283.00 (about 110 16-Jun-23 03-Oct-23 16-Jun-23 03-Oct-23 16-Jun-23 03-Oct-23 0 0 16-Jun-23 03-Oct-23
20,000m3)
A1301 ID No. 1.15-Supply and Instalation of grouding 60 05-Aug-23 03-Oct-23 05-Aug-23 03-Oct-23 01-Apr-26 31-May-26 0 971 05-Aug-23 03-Oct-23
system
A1310 Section 4.2-Drilling and grouting consolidation of 90 16-Jul-23 13-Oct-23 16-Jul-23 13-Oct-23 16-Jul-23 13-Oct-23 0 0 16-Jul-23 13-Oct-23
Dam riverbed (1,840md).

N01-1(Rev7).6.4.2 STAGE 1 561 16-Aug-23 26-Feb-25 16-Aug-23 26-Feb-25 16-Aug-23 31-May-26 0 459 26-Feb-25, N01-1(Rev7).6.4.2 STAGE 1
A1340 Section 5.1-Concrete up to EL338.50, about 396 16-Aug-23 14-Sep-24 16-Aug-23 14-Sep-24 16-Aug-23 14-Sep-24 0 0 16-Aug-23 14-Sep-24
384,292 m3.

A1341 Interface ID No. 3.2.1-Completion of installation of 0 09-Nov-24 09-Nov-24 19-Dec-24 0 40


Steel lining of Sediment equipment (56days)

A1361 Interface ID No. 3.2-Completion of installation 0 26-Feb-25 26-Feb-25 31-May-26 459 459
Sediment equipment (165days)

N01-1(Rev7).6.4.3 STAGE 2 191 15-Sep-24 24-Mar-25 15-Sep-24 24-Mar-25 15-Sep-24 31-May-26 0 433 24-Mar-25, N01-1(Rev7).6.4.3 STAGE 2
A1720 Concrete from BR2-:-BL2, about 131,334m3 128 15-Sep-24 20-Jan-25 15-Sep-24 20-Jan-25 15-Sep-24 20-Jan-25 0 0 15-Sep-24 20-Jan-25

A1721 Concrete Block BS3 above of the Sediment Flush 60 10-Nov-24 08-Jan-25 10-Nov-24 08-Jan-25 20-Dec-24 17-Feb-25 40 40 10-Nov-24 08-Jan-25

A1722 Section 5.2-Completion of concrete placement to 0 20-Jan-25 20-Jan-25 20-Jan-25 0 0


permit installation of Water level lowering

A1723 Interface ID 2.2.1-Completion of Steel 0 14-Feb-25 14-Feb-25 14-Feb-25 0 0


lining&second stage concrete of Water Level
Lowering up to EL342.8
A1850 ID 2.2&2.3-Completion of installation of Water 0 24-Mar-25 24-Mar-25 31-May-26 433 433
Level Lowering (Operation room and other
activities, up to EL356.8)

N01-1(Rev7).6.4.4 STAGE 3 63 21-Jan-25 24-Mar-25 21-Jan-25 24-Mar-25 21-Jan-25 31-May-26 0 433 24-Mar-25, N01-1(Rev7).6.4.4 STAGE 3
A1360 Section 5.3-Concrete (BL1&2, BS1-:-5; BR1&2, 28 21-Jan-25 17-Feb-25 21-Jan-25 17-Feb-25 21-Jan-25 17-Feb-25 0 0 21-Jan-25 17-Feb-25
about 32,274 m3) upto EL374.50 (Evironmental
intake pipe)
A1410 Interface ID4.7-Environmental flow intake pipe 0 24-Mar-25 24-Mar-25 31-May-26 433 433
encased and released to Package 1 Contractor

N01-1(Rev7).6.4.5 STAGE 4 92 18-Feb-25 20-May-25 18-Feb-25 20-May-25 18-Feb-25 20-May-25 0 0 20-May-25, N01-1(Rev7).6.4.5 STAGE 4
A1370 Concrete (BS1-:-5; BR1&2, about 106,565 m3) 92 18-Feb-25 20-May-25 18-Feb-25 20-May-25 18-Feb-25 20-May-25 0 0 18-Feb-25 20-May-25
upto EL392.50 (Ready for Spillway overflow
concrete Gate 1&2)

N01-1(Rev7).6.4.6 STAGE 5 65 21-May-25 24-Jul-25 21-May-25 24-Jul-25 21-May-25 24-Jul-25 0 0 24-Jul-25, N01-1(Rev7).6.4.6 STAGE 5
A1390 Concrete (BS3-:-5; BR1&2, about 60,790 m3) 65 21-May-25 24-Jul-25 21-May-25 24-Jul-25 21-May-25 24-Jul-25 0 0 21-May-25 24-Jul-25
upto EL392.50 (Ready for Spillway overflow
concrete Gate 3)

Remaining Work Start Constraint Current Bar Labels Page 7 of 9


Critical Remaining Work Finish Constraint Milestone
TANAHU HYDROPOWER PROJECT
TOTAL SCHEDULE
REV-7

Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
N01-1(Rev7).6.4.7 STAGE 6 50 25-Jul-25 12-Sep-25 25-Jul-25 12-Sep-25 25-Jul-25 12-Sep-25 0 0 12-Sep-25, N01-1(Rev7).6.4.7 STAGE 6
A1430 Concrete (BL1, BL2; BR1, BL2, about 35,776 50 25-Jul-25 12-Sep-25 25-Jul-25 12-Sep-25 25-Jul-25 12-Sep-25 0 0 25-Jul-25 12-Sep-25
m3) upto EL392.50 (Ready for Spillway overflow
concrete Gate 4)

N01-1(Rev7).6.4.8 STAGE 7 170 25-Jul-25 10-Jan-26 25-Jul-25 10-Jan-26 21-Aug-25 31-May-26 0 141 10-Jan-26, N01-1(Rev7).6.4.8 STAGE 7
A1450 Concrete (BS3, about 6,588 m3) up to EL420.00. 72 25-Jul-25 04-Oct-25 25-Jul-25 04-Oct-25 21-Aug-25 31-Oct-25 0 27 25-Jul-25 04-Oct-25

A1460 Interface ID No. 1.9-Block C released to P2 for 0 04-Oct-25 04-Oct-25 22-Feb-26 0 141
spillway stoplogs storage works

A1650 Interface ID No. 1.10-Stoplog spillway storage bay 0 10-Jan-26 10-Jan-26 31-May-26 141 141
works completed and release to P1

N01-1(Rev7).6.4.13 STAGE 8 104 13-Sep-25 25-Dec-25 13-Sep-25 25-Dec-25 03-Jan-26 16-Apr-26 0 112 25-Dec-25, N01-1(Rev7).6.4.13 STAGE 8
A16940 Concrete (BL1&2; BS1&2, about 49,726m3), up 104 13-Sep-25 25-Dec-25 13-Sep-25 25-Dec-25 03-Jan-26 16-Apr-26 66 112 13-Sep-25 25-Dec-25
to EL420.00
N01-1(Rev7).6.4.9 BUCKETS, CHUTES AND OGEES 298 21-May-25 14-Mar-26 21-May-25 14-Mar-26 13-Aug-25 01-Apr-26 0 18 14-Mar-26, N01-1(Rev7).6.4.9 BUC
N01-1(Rev7).6.4.9.1 BS1 183 21-May-25 19-Nov-25 21-May-25 19-Nov-25 13-Aug-25 01-Apr-26 0 133 19-Nov-25, N01-1(Rev7).6.4.9.1 BS1
A1470 Concrete up to EL372.26. 138 05-Jul-25 19-Nov-25 05-Jul-25 19-Nov-25 15-Nov-25 01-Apr-26 133 133 05-Jul-25 19-Nov-25
A1480 Concrete from EL372.26-:-398.10. 45 21-May-25 04-Jul-25 21-May-25 04-Jul-25 13-Aug-25 26-Sep-25 0 84 21-May-25 04-Jul-25

N01-1(Rev7).6.4.9.3 BS2 183 21-May-25 19-Nov-25 21-May-25 19-Nov-25 13-Aug-25 01-Apr-26 0 133 19-Nov-25, N01-1(Rev7).6.4.9.3 BS2
A1490 Concrete up to EL372.26. 138 05-Jul-25 19-Nov-25 05-Jul-25 19-Nov-25 15-Nov-25 01-Apr-26 133 133 05-Jul-25 19-Nov-25
A1500 Concrete from EL372.26-:-398.10. 45 21-May-25 04-Jul-25 21-May-25 04-Jul-25 13-Aug-25 26-Sep-25 0 84 21-May-25 04-Jul-25

N01-1(Rev7).6.4.9.2 BS3 138 05-Oct-25 19-Feb-26 05-Oct-25 19-Feb-26 15-Nov-25 01-Apr-26 0 41 19-Feb-26, N01-1(Rev7).6.4.9.2 BS3
A16950 Concrete up to EL372.26. 138 05-Oct-25 19-Feb-26 05-Oct-25 19-Feb-26 15-Nov-25 01-Apr-26 41 41 05-Oct-25 19-Feb-26
N01-1(Rev7).6.4.9.4 BS4 183 25-Jul-25 23-Jan-26 25-Jul-25 23-Jan-26 13-Aug-25 01-Apr-26 0 68 23-Jan-26, N01-1(Rev7).6.4.9.4 BS4
A1530 Concrete up to EL372.26. 138 08-Sep-25 23-Jan-26 08-Sep-25 23-Jan-26 15-Nov-25 01-Apr-26 68 68 08-Sep-25 23-Jan-26
A1540 Concrete from EL372.26-:-398.10. 45 25-Jul-25 07-Sep-25 25-Jul-25 07-Sep-25 13-Aug-25 26-Sep-25 0 19 25-Jul-25 07-Sep-25

N01-1(Rev7).6.4.9.5 BS5 183 13-Sep-25 14-Mar-26 13-Sep-25 14-Mar-26 13-Sep-25 01-Apr-26 0 18 14-Mar-26, N01-1(Rev7).6.4.9.5 BS
A1550 Concrete up to EL372.26. 138 28-Oct-25 14-Mar-26 28-Oct-25 14-Mar-26 15-Nov-25 01-Apr-26 18 18 28-Oct-25 14-Mar-26
A1560 Concrete from EL372.26-:-398.10. 45 13-Sep-25 27-Oct-25 13-Sep-25 27-Oct-25 13-Sep-25 27-Oct-25 0 0 13-Sep-25 27-Oct-25

N01-1(Rev7).6.4.10 LEFT AND RIGHT WALS 236 09-Aug-25 01-Apr-26 09-Aug-25 01-Apr-26 01-Nov-25 01-Apr-26 0 0 01-Apr-26, N01-1(Rev7).6.4.10 LE
A1570 Concrete of Left wall up to EL382.39 (about 6,031 236 09-Aug-25 01-Apr-26 09-Aug-25 01-Apr-26 01-Nov-25 01-Apr-26 0 0 09-Aug-25 01-Apr-26
m3)
A1580 Concrete of Right wall up to EL382.39 (about 122 01-Dec-25 01-Apr-26 01-Dec-25 01-Apr-26 01-Dec-25 01-Apr-26 0 0 01-Dec-25 01-Apr-26
6,031 m3)
N01-1(Rev7).6.4.11 PIERS 285 21-May-25 01-Mar-26 21-May-25 01-Mar-26 13-Aug-25 01-Mar-26 0 0 01-Mar-26, N01-1(Rev7).6.4.11 PIER
A1590 ID No. 1.1-Section 5.4-Pier No.1 (Counting from 80 21-May-25 08-Aug-25 21-May-25 08-Aug-25 13-Aug-25 31-Oct-25 0 84 21-May-25 08-Aug-25
Left to Right, about 9,034m3)

A1591 ID No. 1.2-Spillway Bay No1 gate installation 0 07-Nov-25 07-Nov-25 30-Jan-26 84 84
completion
A1600 ID No. 1.1-Section 5.4-Pier No.2 (about 5,982m3) 80 21-May-25 08-Aug-25 21-May-25 08-Aug-25 13-Aug-25 31-Oct-25 0 84 21-May-25 08-Aug-25

A1601 ID No 1.4-Spillway Bay No.2 gate installation 0 03-Jan-26 03-Jan-26 30-Jan-26 27 27


completion
A1620 ID No. 1.5-Pier No.4 (about 5,982m3) 80 25-Jul-25 12-Oct-25 25-Jul-25 12-Oct-25 13-Aug-25 31-Oct-25 0 19 25-Jul-25 12-Oct-25

A1621 ID No. 1.6-Spillway Bay No.3 gate installation 0 11-Jan-26 11-Jan-26 30-Jan-26 19 19
completion
A1630 ID No. 1.7-Pier No.5 (about 9,034m3) 79 13-Sep-25 30-Nov-25 13-Sep-25 30-Nov-25 13-Sep-25 30-Nov-25 0 0 13-Sep-25 30-Nov-25

Remaining Work Start Constraint Current Bar Labels Page 8 of 9


Critical Remaining Work Finish Constraint Milestone
TANAHU HYDROPOWER PROJECT
TOTAL SCHEDULE
REV-7

Activity ID Activity Name Original BL Project BL Project Early Start Early Finish Late Start Late Finish Free Total Float
Duration Start Finish Float 2021 2022 2023 2024 2025 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
A1731 ID No. 1.8-Spillway Bay No.4 gate installation 0 01-Mar-26 01-Mar-26 01-Mar-26 0 0
completion
N01-1(Rev7).6.4.12 DAM CREST COMPLETION 45 02-Mar-26 15-Apr-26 02-Mar-26 15-Apr-26 17-Apr-26 31-May-26 0 46 15-Apr-26, N01-1(Rev7).6.4.12 D
A1640 Completion of Dam crest 45 02-Mar-26 15-Apr-26 02-Mar-26 15-Apr-26 17-Apr-26 31-May-26 46 46 02-Mar-26 15-Apr-26
N01-1(Rev7).6.13 DOWN STREAM AUXILIARY DAM 407 19-Jan-24 01-Mar-25 19-Jan-24 01-Mar-25 06-Dec-25 31-May-26 0 457 01-Mar-25, N01-1(Rev7).6.13 DOWN STREAMAUXILIARY DAM
A1690 Section 6.1-Excavation for the Downstream 120 19-Jan-24 18-May-24 19-Jan-24 18-May-24 01-Feb-26 31-May-26 744 744 19-Jan-24 18-May-24
Auxiliary Dam and Plunge Pool, and all foundation
treatment (about 344,000m3)
A1700 Drilling of bore hole and Structural concrete as 140 18-May-24 05-Oct-24 18-May-24 05-Oct-24 12-Jan-26 31-May-26 0 604 18-May-24 05-Oct-24
specified in primary secant pile (about 1,935md,
9,980m3)
A1710 Drilling of bore hole and Structural concrete as 140 17-Jun-24 04-Nov-24 17-Jun-24 04-Nov-24 12-Jan-26 31-May-26 0 574 17-Jun-24 04-Nov-24
specified in secondary secant pile (about 1,935md,
9,980m3)
A1740 Section 6.2-Reinforced abrasion resistant concrete 117 04-Nov-24 01-Mar-25 04-Nov-24 01-Mar-25 06-Dec-25 01-Apr-26 0 397 04-Nov-24 01-Mar-25
to Downstream Auxiliary Dam crest (21,399m3)

120 24-Oct-22
N01-1(Rev7).6.8 DISTRIBUTION LINES 11KV IN THE DAM AREA 21-Feb-23 24-Oct-22 21-Feb-23 03-Dec-25 01-Apr-26 0 1136 21-Feb-23, N01-1(Rev7).6.8 DISTRIBUTION LINES 11KVIN THE DAM AREA
A16720 Design, supply and installation of 11kVdistribution 120 24-Oct-22 21-Feb-23 24-Oct-22 21-Feb-23 03-Dec-25 01-Apr-26 1136 1136 24-Oct-22 21-Feb-23
line up to Dam Operation and Service Building

N01-1(Rev7).6.5 RESERVOIR SLOPE PROTECTION 730 02-Sep-22 31-Aug-24 02-Sep-22 31-Aug-24 02-Apr-24 01-Apr-26 0 578 31-Aug-24, N01-1(Rev7).6.5 RESERVOIR SLOPE PROTECTION
A1760 Reservoir slope protection works 730 02-Sep-22 31-Aug-24 02-Sep-22 31-Aug-24 02-Apr-24 01-Apr-26 578 578 02-Sep-22 31-Aug-24

N01-1(Rev7).6.6 DIVERSION TUNNEL PLUG 397 01-Mar-25 01-Apr-26 01-Mar-25 01-Apr-26 01-Jan-26 01-Apr-26 0 0 01-Apr-26, N01-1(Rev7).6.6 DIVE
A1770 Removing of upstream cofferdam (through Access 31 01-Mar-25 31-Mar-25 01-Mar-25 31-Mar-25 01-Jan-26 31-Jan-26 0 306 01-Mar-25 31-Mar-25
Tunnel)

A1771 Sealing Access Tunnel and Diversion Tunnel No.1 60 25-Nov-25 24-Jan-26 25-Nov-25 24-Jan-26 01-Feb-26 01-Apr-26 68 68 25-Nov-25 24-Jan-26

A1772 Section 7-Close the stoplog of Diversion Tunnels 1 31-Jan-26 31-Jan-26 31-Jan-26 31-Jan-26 31-Jan-26 31-Jan-26 0 0 31-Jan-26 31-Jan-26
(preparation works, checking hydromechanical
completed prior execution)

A1773 Sealing the Diversion Tunnels (3,925m3-No.2, 25 60 01-Feb-26 01-Apr-26 01-Feb-26 01-Apr-26 01-Feb-26 01-Apr-26 0 0 01-Feb-26 01-Apr-26
blocks for each tunnel)

60THE
N01-1(Rev7).6.7 OVERAL COMPLETION OF THE WHOLE OF 02-Apr-26
WORKS31-May-26 02-Apr-26 31-May-26 02-Apr-26 31-May-26 0 0 31-May-26, N01-1(Rev7).6.7
A1790 Section 8-Overall completion of the whole of the 60 02-Apr-26 31-May-26 02-Apr-26 31-May-26 02-Apr-26 31-May-26 0 0 02-Apr-26 31-May-26
works